modern well design-presentation

Upload: raul-blanco

Post on 06-Jul-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/17/2019 Modern Well Design-Presentation

    1/70

    The Importance of Stresses inPetroleum Engineering

    Chapter 2.1 - Mud Weight Selection

    Approach

    This presentation:

    Approach

    Drilling problems

    Pressure Testing

    Stresses as Design Criterion

    Summary

    Drilling Problems

  • 8/17/2019 Modern Well Design-Presentation

    2/70

    Drilling Problems

    Mud loss: 2.5 days

    Tight hole: 0.3 days

    Squeeze cmt: 2.5 days

    Stuck csg.: 3.3 days

    Fishing: 0.3 days

    Lost time: 9 days

    Cost: +2 mill.$

    If problems get worse:

    Stuck + sidetrack 

    New well

    Drilling Problems

    Stress as Design Criterion

    EFFECTS OF HIGH MUD WEIGHT

    Element Advantage Debatable Disadvantage

    Reduce borehole collapse X

    Reduce fill X X

    Reduce pressure variations X

    Reduce washouts X X

    Reduce tight hole X X

    Reduce clay swelling X X

    Increase differential sticking X X

    Increase lost circulation X

    Reduced drilling rate X X

    Expensive mud X

    Poor pore pressure estimation X X

    Stress as Design Criterion

    From solid mechanics:

    Petroleum Rock Mechanics: Materialproperties

    Recent view: Stress dominated processes

    This leads to simplified design methods

     E   

  • 8/17/2019 Modern Well Design-Presentation

    3/70

    Stress as Design Criterion

    Horizontal stresses from Kirch eqn.:

      = ½(LOT+Pore Pressure)

      Mid-Line Principle

    Stress as Design Criterion

    Stress as Design Criterion

    Example from the North Sea

    Stress as Design Criterion

    Example of specific reaming time fromselected North Sea wells.

  • 8/17/2019 Modern Well Design-Presentation

    4/70

    Stress as Design Criterion Pressure Testing

    Stress as Design Criterion Summary

    In-situ stresses important for well problems

    LOT testing defines stress level

    Borehole collapse not fully understood

    Traditional approach: Rock mechanical data limited

    by data available

    Complementary approach: Stress analysis from

    Mid-Line Principle

    New principle demonstrated the past 8 years

  • 8/17/2019 Modern Well Design-Presentation

    5/70

    2.2-Design of Well Barriers toCombat Circulation Losses

    -

    Design of Well Barriers

    This presentation:

    Introduction

    Experimental work 

    Fracturing lab

    New fracture model

    Barrier stress model

    Design of fluid barriers

    Field case

    Summary

    Introduction

    Circulation losses and stuck pipe two unresolved

    issues in drilling

    Yearly losses Billions US$ worldwide

    Operational factors important

    Circulation losses:

    Geomechanics (stresses, lithology,….)

    Mud barrier (filtrate loss, bridging,…)

    Improvements depends on complementary processes

    Fundamental research Field application

    Experimental work 

    Fracturing lab built at U. of Stavanger in 1996

    Focus on basic mechanisms Fracturing of concrete cylinders

    Chemical effects(wettability,…)

    Hole geometry (circular, oval, square, trianguler

    holes,…)

    Controlled loading(confining, axial, borehole stress)

    Many types of barriers

  • 8/17/2019 Modern Well Design-Presentation

    6/70

    Experimental work, fracturing lab

    Test cell

    HollowConcrete

    Core

    Axial loadPump 1

    Pump 3

    Pump 2

    Confining

    Pressure

    PCControlSystem

    Well Pressure

    1 Pump   2 Pum

    Mud    ncirculatioMud  cell 

    1Valve

    2Valve

    3Valve  LabView

    Mudcake

    Mudcake

    1Cell    2Cell    3Cell 

    4Cell 5Cell 6Cell 

    Fracturing cell

    Mudcake strength

    Experimental work 

    Mudcake strength cell

    Experimental work, new fracmodel

    Example,

    3 drilling muds:

      

      

    a

    t  yo P w P  1ln

    3

    22

      

    0

    20

    40

    60

    A B C

    Drilling fluids

       F  r  a  c   t  u  r   i  n  g  p  r  e  s  s  u  r  e ,

       M   P  a . .

    Measured

    Kirsch equation

     New Kirsch eqn.

    Experimental work 

    Stone bridge principle

  • 8/17/2019 Modern Well Design-Presentation

    7/70

  • 8/17/2019 Modern Well Design-Presentation

    8/70

  • 8/17/2019 Modern Well Design-Presentation

    9/70

    2.3 Hole CleaningMethodology

    Based onAPI RP 13D: Rheology and Hydraulics of Oil-

    well Drilling Fluids.

    Based on BP research early 1990s

    Mainly based on experimental correlations

    Hole cleaning is a key issue, must control ROP to avoid

    overloading annulus with cuttings

    Mechanisms

    Variables Mud flow rate

    ROP Mud rheology/flow regime

    Mud weight (buoyancy)

    Hole size and angle

    Uncontrollable variables eccentricity

    cuttings size density

    Applications

    Transport index

    TI = RF (rheology factor) xMW (mud weight)x AF (angle factor)

    If hole is washed out:

    CFRwashout = CFR (flow rate)

  • 8/17/2019 Modern Well Design-Presentation

    10/70

    Example

    8.5” horizontal well

    MW = 1.45 sg, PV = 25 CP, YP= 18 lbf/100 ft2

    Questions:

    Maximum ROP if maximum flow is 480 gpm? (Correct book)

    If ROP = 20 m/hr, what is minimum flow?

    If hole is washed out 10 in, what flow rate is required?

    Solution

    From Fig. 2.16, RF = 0.91

    From Table 2.5, AF = 1

    From Eqn. 2.7, TI = 0.91x1.0x1.45 = 1.32

    Solution, cont.

    From Fig. 2.16b: at TI=1.32, Q=480 gpm, ROPmax=23

    m/hr

    If ROP = 20 m/hr, Qmin=470 gpm

    Solution, cont.

    If hole is washed out, correction factor:

    Minimum flow rate now:

    CFRwashout = 1.38 x 470 = 649 gpm

  • 8/17/2019 Modern Well Design-Presentation

    11/70

    Hydraulic OptimizationChapter 2.4

    Hydraulic System

    P 1 = pump pressureP 2 = nozzle pressure

    P 3 = system loss (parasitic)

    P 1 = P 2 + P 3

    Pressure drop

    Laminar flow

    Turbulent flow

    Empirical flow equation

     P Q 

    2

     P fQ  m P CQ

    Hydraulic System

  • 8/17/2019 Modern Well Design-Presentation

    12/70

    Hydraulic System

    P 3 = system lossP 3 = CQ

    m

    lnP 3 = lnC + mlnQ

    Hydraulic System

    Nozzle pressure drop from Bernoulli

    System losses

    2

    2 2 22 0.95

    Q P 

     gA

      

    3 2300bar  P P 

    Hydraulic Optimization

    Nozzle Horsepower

    Maximum

    2

    1 3

    1

    ( )

    (   m

     HP P Q

     P P 

     P CQ

    13

    1

    dHP P   P 

    dQ m

    Hydraulic Optimization

    Classical criteria

    Max. Hydraulic horsepower

    Max. Jet impact

    Limitations

    Physically correct?

    Adequate Q for hole cleaning?

  • 8/17/2019 Modern Well Design-Presentation

    13/70

    Hydraulic Optimization

    Performance indices

    Performanceindex

    Equation CriterionFraction parasitic

    pressure lossFlow rate

    1 Max. HP

    2 Max. Jetimpact

    3 New A

    4 New B

    5 New C5 2

    2q P 

    2

    2q P 

    3 2

    2q P 

    2q P 

    2qP 1

    1m

    2

    2m

    3

    3m

    4

    4m

    5

    5m

    1

    ( 1)

     P 

    C m

    12

    ( 2)

     P 

    C m

    13

    ( 3)

     P 

    C m

    14

    ( 4)

     P 

    C m

    15

    ( 5)

     P 

    C m

    Application

    1. Determine hole cleaning rate Q

    2. Select performance index3. Compute system loss (P 3) and bit loss

    (P 2)

    4. Compute nozzle area, A

    Proposed criteria

    Other data: Drill pipe: 675 m of 5 inch, rest 6-5/8 inch; Drill collars: 120 m 8-1/8 inch OD,

    2.81 inch ID; Mud density: 1.65 s.g., Yield point: 32 lbf/100 sq.ft.; Plastic viscosity: 42 cP.

    Proposed optimization criteria for typical 12-1/4 inch hole

    Hole length Vertical holes Deviated wellsdrilled with motor

    Deviated wellswithout motor

    Strongerrequirements

    Less than 2500 m Max. Hydr. Horsepower

    or max. Jet impact force

    Max. HHP or

    max. Jet impact

    Max. Jet impact New A

    2500-4000 m Max. HHP

    or max. Jet impact

    Max. Jet impact New A New B

    Deep(5000m) Max. HHP

    or max. Jet impact

    Max. Jet impact

    or New A

    New B New C

    Example

    Determination

    of flow ranges

    and optimisation

    criteria

  • 8/17/2019 Modern Well Design-Presentation

    14/70

    Drill Pipe Size Example

    Hydraulic parameters for the field case

    Criterion Percent parasitic press. loss Flow range (l/min)

    Max. Hydraulic power 54 2800-2220

    Max jet impact 52 2850-2280

    New A 63 3070-2450

    New B 69 3250-2580

    New C 73 3370-2800

    Optimal nozzle selection for New B criterion

    Depth (m) Nozzles (inch)

    1200 Five 13/32, one 16/32

    2200 Five 12/32, on 16/32

    3200 Five 11/32, on 16/32

    Example

    Summary of earlier bit runs

    Bit. No. Nozzles q (l/min) ROP (m/hr) Remarks

    1 5 x 16, 1 x 12 2960 1.5 Plugged center nozzle

    2 5 x 19, 1 x 12 2660 9.8

    3 5 x 16, 1 x 12 2600 13.64 5 x 19, 1 x 12 2300 18.2

    5 5 x 18, 1 x 12 2400 14.9 Plugged center nozzle

    6 6 x 12 2600 18.3

    7 5 x 14, 1 x 12 2400 15.4

    8 5 x 15, 1 x 12 2450 24

    9 5 x 14, 1 x 12 2400 4.8

    10 5 x 14, 1 x 12 2530 23.8

    11 5 x 19, 1 x 12 20 Plugged center nozzle

    12 5 x 19, 1 x 12 30

    13 5 x 18, 1 x 12 10

    14 5 x 18, 1 x 12 22 Plugged center nozzle

    15 5 x 19, 1 x 12 7 Plugged center nozzle

    16 5 x 18, 1 x 12 27 Plugged center nozzle

    17 5 x 19, 1 x 12 16 Plugged center nozzle

    18 5 x 19, 1 x 12 19 Plugged center nozzle

    Geomechanic EvaluationChapter 3.1 - Data Normalization

  • 8/17/2019 Modern Well Design-Presentation

    15/70

    Data Normalization

    Example, porepressure at 1000m:

    P(bar)= 0.098d(s.g)D(m)

    = 0.0981.03 1000

    = 100.9 bar

    Data Normalization

    Example, continued:New gradient from RKB

    1.03s.g.MSLd   

    100.91.0s.g.

    0.098 1025 RKB

    bar d 

    m

    Data Normalization

    From sea level

    From RKB

    MSL RKB

     Dd d 

     D h

     RKB MSL

     D hd d 

     D

    Data Normalization

    From floater

    From platform

     D

    h Dd d   RKB RKB

      12

    h D

     Dd d   RKB RKB

      21

    )( )(

  • 8/17/2019 Modern Well Design-Presentation

    16/70

    Data Normalization

    Normalize to seafloor

    1. Subtract water pressure

    2. Subtract water depth

    Data Normalization

    Well Csg (in) Depth (m) hw (m) hf  (m) LOT(s.g.) P0 (s.g.)   0 (s.g.)34/7-2 20 848 245 25 1.58 1.06 1.83

    13 3/8 1549 1.69 1.42 2.00

    9 5/8 2031 1.88 1.63 2.00

    34/7-8 20 848 286 25 1.62 1.04 1.72

    13 3/8 1859 1.83 1.42 1.93

    34/7-14 20 491 148 25 1.49 1.00 1.4913 3/8 1559 1.75 1.09 1.70

    9 5/8 1988 1.80 1.53 1.92

    )( sg o  )( sg o 

    Geomechanic EvaluationChapter 3.2 - Interpretation

    Interpretation

    Basic data

    Leak-Off-Pressure (LOT)

    Pore Pressure

    Overburden Stress

    Lithology

    Clays

    Sands, Chalks, …

  • 8/17/2019 Modern Well Design-Presentation

    17/70

    Interpretation

    Simple modelling

    Evaluate LOT data

    Effective stresses

    Horizontal stresses

    Effective horizontal stresses

    Depth normalize Effective depth normalized data

    Interpretation

    Example

    Well Dataset Depth(m) (s.g.) (s.g.) o(s.g.)

     A 1 899 1.46 1.04 1.63

    2 1821 1.74 1.28 1.81

    B 3 901 1.55 1.04 1.60

    4 1153 1.56 1.04 1.73

    5 1907 1.81 1.34 1.82

    6 2753 1.95 1.52 1.96

    Interpretation

    Example: LOT Pressure

    Interpretation

    Example

    LOT Gradient

  • 8/17/2019 Modern Well Design-Presentation

    18/70

    Interpretation

    Horizontal stresses,depth normalized

    Effective horizontalstresses, depth

    normalized

    2

    a o

    a o

    o o

     K 

     LOT P 

     

     

     

    '

    ' 2a o

    o o o

     LOT P 

     P 

     

     

    Interpretation

    Horizontal stresses

    Effective horizontalstresses

    2

    1

    2

    a o

    a o

     LOT P 

     LOT P 

     

     

    '

    1'

    2

    o

    a o

     P 

     LOT P 

     

     

    Interpretation

    Best fit

    Test of model

    Prognosis

    1' 0.23

    20.46

    a o

    o

     LOT P 

     LOT P 

       

    Geomechanical EvaluationChapter 3.2.4 - Advanced Modelling

  • 8/17/2019 Modern Well Design-Presentation

    19/70

    Advanced Modelling

    Principle: Normalize all data to same

    reference, example: Borehole inclination

    Compaction

    Inversion technique

    Advanced Modelling

    Borehole inclination

    Normalize all LOT’s tovertical for comparison

    * 2

    2

    2

    1(0 ) ( ) sin

    3

    1( ) sin

    2(0 )

    11 sin

    2

    wf wf o o

    wf o o

    wf 

     P P P P 

     P P 

     P 

     

     

     

    Advanced Modelling

    Compaction model

    Applications

    Normalization

    Structural geology Lost circulation

    1 2

    1

    1 3

    1

    a o

    wf o

     P 

     P P 

      

     

     

     

    Advanced Modelling

    Compaction model

    Example

    Depth(m) LOT (s.g.) P0 (s.g.)

    3885 2.10 1.79

    3821 2.13 1.84

    3818 1.98 1.44

    3914 2.06 1.58

  • 8/17/2019 Modern Well Design-Presentation

    20/70

    Advanced Modelling

    Inversion Technique

    Determines tectonic stress field that fits alldata sets

    Use this stress field to make prognosis for

    new well

    Determines also stress directions as applied

    to e.g. fracturing and stimulation

    Advanced Modelling

    Relaxed Depositional Basin   Tectonic Stress

    Advanced Modelling

    Inversion Technique, Example

    Dataset

      Well Casing  Depth

    (m)LOT(s.g.)

    P0(s.g.)

    o(s.g.)

     

    1 A 20 1101 1.53 1.03 1.71 0 0

    2 13 3/8 1888 1.84 1.39 1.82 27 923 9 5/8 2423 1.82 1.53 1.89 35 92

    4 B 20 1148 1.47 1.03 1.71 23 183

    5 13 3/8 1812 1.78 1.25 1.82 42 1836 9 5/8 2362 1.87 1.57 1.88 41 183

    7 C 20 1141 1.49 1.03 1.71 23 284

    8 13 3/8 1607 1.64 1.05 1.78 48 2849 9 5/8 2320 1.84 1.53 1.88 27 284

    10 New 20 1100 ? 1.03 1.71 15 13511 13 3/8 1700 ? 1.19 1.80 30 135

    12 9 5/8 2400 ? 1.55 1.89 45 135

    Depth interval(m) H /o   h /o   Direction Leak-off, new well1100-1148 0.754 0.750 44 1.53

    1607-1812 0.854 0.814 96 1.71

    2320-2423 0.927 0.906 90 1.86

    Advanced Modelling

    Inversion Technique, Example

  • 8/17/2019 Modern Well Design-Presentation

    21/70

    3.2.4 In-Situ Stress Modelling of the SnorreField

    Local Map

    This Presentation

    Applications

    Importance of in-situ stresses

    Experience from Snorre Modelling

    Regional stress field

    Earthquake focal mechanisms

    Local stress field

    Borehole elongation

    Leak-off inversion

    Conclusions

    Importance of fracture gradientprediction in well planning

    Casing seat selection using low frac. curve

    30”

    13 3/8”

    9 5/8”

    7”

    20”

    Gradients

    Frac

    Mud

    Pore

    Depth

    Casing seat selection using high frac. curve

    30”

    13 3/8”

    9 5/8”

    7”

    Gradients

    Frac

    Mud

    Pore

    Depth

  • 8/17/2019 Modern Well Design-Presentation

    22/70

  • 8/17/2019 Modern Well Design-Presentation

    23/70

    Horizontal stresses and directionsfrom borehole leak-off data Method: Inversion of leak-off and minifrac data

    Parameters: Fracture pressure

    Pore pressure

    Overburden stress

    Borehole inclination

    Borehole azimuth direction

    Horizontal stresses and directionsfrom borehole leak-off data

    Stress fields at reservoir level from leak-off inversion

    Horizontal stresses and directionsfrom borehole leak-off data Summary, leak-off inversion:

    For shallow depths (to 1500m), the horizontal stress

    state has relaxed, nearly hydrostatic state.

    In the deeper parts (1500 – 3000m), the horizontal

    stresses becomes anistropic with depth.

    The stress state varies both depthwise and areawise.

    In certain places the max. horizontal stress exceeds

    the overburden.

    The method gives realistic stress ratio. Also, the

    directions are consistent with the fault pattern of the

    area.

    Conclusions

    The stress field at Snorre is anisotropic due to tectonics of the area

    Focal mechanisms, borehole elongation and leak-off data have been

    used to assess the in-situ stress levels and direction at Snorre.

    The three methods shows consistency, but model various scales:

    Focal mechanism   regional scale

    Elongation data   local scale (one borehole)

    Leak-off inversion   local scale (several boreholes)

    Maximum horizontal stress is regionally in a North-West direction

    Stresses near faults dominated by faults

    The described approach has significantly improved fracture pressure

    prediction

  • 8/17/2019 Modern Well Design-Presentation

    24/70

     0   3   . 0   6   .2   0  1  1  1  

     G e om e c h  a ni   c  a l  E 

     v  a l   u a  t i   on

     G e om e c h  a ni   c  a l  E 

     v  a l   u a  t i   on

     Ch  a  p t  er  3  .4 -B  or  eh  ol   e

     C ol  l   a  p s  e

    B  or  eh  ol   e C ol  l   a  p s  e

    B  or  eh  ol   e C ol  l   a  p s  e

    B  or  eh  ol   e S  t r  e s  s  e s 

     C ol  l   a  p s  eM e c h  a ni   s m

    F i   el  d  c  or r  el   a  t i   on s 

    T i  m ed  e p end  en c  y 

    T i  m em od  el  

    B  or  eh  ol   e C ol  l   a  p s  e

    B  or  eh  ol   e C ol  l   a  p s  e

    B  or  eh  ol   e S  t r  e s  s  e s 

      

    R  a d i   a l   s  t r  e s  s  : 

     r =P 

     w

    = b  o

    r  eh  ol   e pr  e s  s  ur  e

      

    T  a n g  en t i   a l   s  t r  e s  s  : 

        

    =2   a -P 

     w

      

     V  er  t i   c  a l   s  t r  e s  s  : 

      v = o v  er  b  ur d  en= c  on s  t  a n t 

      

    P  or  e pr  e s  s  ur  e : 

    P  o

    B  or  eh  ol   e C ol  l   a  p s  e

    B  or  eh  ol   e C ol  l   a  p s  e

     C ol  l   a  p s  eM e c h  a ni   s m

    B  or  eh  ol   e C ol  l   a  p s  e

    B  or  eh  ol   e C ol  l   a  p s  e

     C ol  l   a  p s  eM e c h  a ni   s m

      

    M oh r - C o ul   om b f   a i  l   ur  em od  el  

    B  or  eh  ol   e C ol  l   a  p s  e

    B  or  eh  ol   e C ol  l   a  p s  e

    F i   el  d  c  or r  el   a  t i   on s 

     0   3   . 0   6   .2   0  1  1  2  

    B  or  eh  ol   e C ol  l   a  p s  e

    B  or  eh  ol   e C ol  l   a  p s  e

    F i   el  d  c  or r  el   a  t i   on s 

    B  or  eh  ol   e C ol  l   a  p s  e

    B  or  eh  ol   e C ol  l   a  p s  e

    B  or  eh  ol   e C ol  l   a  p s  e

    B  or  eh  ol   e C ol  l   a  p s  e

    T i  m em od  el  

    B  or  eh  ol   e C ol  l   a  p s  e

    B  or  eh  ol   e C ol  l   a  p s  e

    B  or  eh  ol   e C ol  l   a  p s  e

    B  or  eh  ol   e C ol  l   a  p s  e

    B  or  eh  ol   e c  ol  l   a  p s  e

    B  or  eh  ol   e c  ol  l   a  p s  e

     0   3   . 0   6   .2   0  1  1   3  

    B  or  eh  ol   e C ol  l   a  p s  e

    B  or  eh  ol   e C ol  l   a  p s  e

    3.5 Drillability Evaluation

  • 8/17/2019 Modern Well Design-Presentation

    25/70

    ROP models

    The simplest ROP model is:

    A more common model is the

    d- exponent:

    The d-exponent

    This model is used:

    Continuously in mudlogging units offshore

    Estimate pore pressure

    Assess bit wear with rollercone drillbits

    Various geological interpretation

    It is actually a normalised ROP model, but the linear model works as well

    The drillability is the only (?) measurement at the drillbit face. Other

    measurements are behind in depth.

    Drillability is always measured and provide a very important source of 

    information . Examples follows.

    Clay diaper example

    Tophole drilling found soft sediments

    that could not be detected on logs.

    Drillability analysis performed

    Found increase in drillability at a given depth

    interval

    Conclusion: Discovered an unidentified clay

    diaper characterized by:

    High water content

    High porosity

    Easy drillable

    Relief well example

    An underground blowout in a HPHT

    well was killed with a relief well.

    Difficult to detect distance between wells at 5000 m

    Breakthrough point critical as both wells could lose control

    Relief well finished one year after initial blowout.

    The blowing well had produced 18 000 bbls/day for one year leading

    to reduced pore pressure and changes in in-situ stress.

    Comparing the two drillabilities defined proximity and also extent of 

    damage caused by underground flow. This was the only information at

    that time.

  • 8/17/2019 Modern Well Design-Presentation

    26/70

    Relief well example

    .

    Drillability summary

    Examples shows the power of drillability information

    Drillability should be further explored as a formation evaluation

    tool and a well dignostic tool

    Fracture Model for GeneralOffshore Applications

    Chapter 3.6

    Fracture Model for General Offshore Applications

    Objectives

    Introduction

    The overburden stress

    Fracturing Empirical model

    Method to normalize data

    Field cases

    Summary and conclusions

  • 8/17/2019 Modern Well Design-Presentation

    27/70

    Introduction

    Problems increase with water depth

    Shallow water flow

    Hole collapse

    Circulation losses

    Fracture gradient decrease with increased

    water depth

    The overburden stress

    Overburden stress

    0

    w

    w

     D   D

     sw bulk ob

     D

    ob   g dD g dD gd D        

    Depth (m)

    Overburden

    stress grad. (s.g.)

    1.0 1.5 2.0

    1000

    2000

    3000

    1000 50015002000

    Water depth (m)

    0

    Eatons modelLinear approx.

    Linear approx.

    1

    2.015 000

    w

     D

    ob sw w bulk  

     D

    w f w f  w sw

    d D d D dD D

     D D D D D D Dd 

     D D

     

    Overburden stress gradient

    Fracturing

    Fracturing equation

    Horizontal stress

    Conclusion

    03v i j ywf    d d P P  d       

    0v y vwf    P P f d K   

    Depth (m)

    Stress grad. (s.g.)1.0 1.5 2.0

    1000

    2000

    3000

    LOT

    v,h H v  

    Fracture directions

    StressesEqual horizontal stresses Different horizontal stresses

     H h     H h  

     

      H  

  • 8/17/2019 Modern Well Design-Presentation

    28/70

    Fracturing – Flow barriers

    Pressure

    Radius

    Flow barrier 

    P0

    Pw

    Pressure

    Radius

    Flow barrier 

    P0

    Pw

    Non-penetrating fluids Penetrating fluids

    02   t wf    P P  P         01 2 1 t wf    P  P        

    Variation in break-down pressure: 02   wf  P P       

    Fracturing – LOT testing

    Pressure

    Volume

    Non-penetrating case

    Mud compressibility

    Penetrating case

    LOT

    Pressure

    Volume

    Water-based drilling fluid Oil-based drilling fluid

    Empirical fracture model

    Leak-off (LOT) data studied from 175-2071m waterdepth

    All data normalized by subtracting water pressureand depth

    Data correlates well with overburden andhorizontal stress curves

    Valid for all relaxed sedimentary depositional basins

    Fracture Model for General Offshore Applications

    Method to normalize data

    hf1

    hw1

    Dsb1

    Depth

    New depth

    New gradient

    1 1 1 1 f w sbh D D h  

    2 1   f w sbh D D D h

    12 1 2 22 1

    2 2 2 1 1

    wf w w b sbwf sw wf sw

    wf wf wf b sb

     Dh h d Dd d d d  

     D D D d D

    1 1 22 1

    2 2 1

     N N    N  fw ob   N N    ob

     fw fw N N    N 

     fw ob   ob

     P K P    P  P P 

     P K P    P 

    dwf1 dwf2

  • 8/17/2019 Modern Well Design-Presentation

    29/70

    Empirical correlation

    Five deep-water wellsselected for analysis

    Fracture prognosis of 98%of overburden stressgradient

    Standard deviation of 0.05

    Fracture Model for General Offshore Applications

    Ratio between le ak-off data and overburden

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    0.50 0.60 0.70 0.80 0.90 1.00 1.10 1.20 1.30

    d(LOT)/do

       D  e  p   t   h   (  m   )

    Ratio A ver age r atio

    Field case 1

    Well used for empirical

    correlation

    1274m water depth

    Variations in LOT influenced by:

    Rig procedures

    Interpretations of P-V-plots

    Mud density

    Quality of mud cake Assessment of bulk density and

    overburden stress

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    4500

    5000

    5500

    1,00 1,10 1,20 1,30 1,40 1,50 1,60 1,70 1,80 1,90 2,00

    Overburden Frac gradient LOT data

    Field case 2 - Prognosis

    Fracture prognosis used forplanning of shallow penetration

    gas well

    380m water depth

    Good agreement betweenprognosis and measured FIT

    Major contributor to thesuccess of the drilling operation

    Mud designed for strong mud

    cake

    350

    400

    450

    500

    550

    600

    1 1,05 1,1 1,15 1,2 1,25 1,3 1,35 1,4

       D  e  p   t   h   (  m   )

    s.g.

    Overburden Frac ture gradient Peon FIT

    Summary and conclusions

    Overburden gradient decreases with increasing water

    depth

    Fracture pressure governed by: Overburden stress

    Fluid barrier

    Field data fits general model

    Model presented to derive prognosis

    Normalization method derived to adjust data forarbitrary water depth

  • 8/17/2019 Modern Well Design-Presentation

    30/70

    3.6 General Fracturing ModelKey issues

    Important findings

    Overburden stress important Seabed penetration important as well

    A general fracturing model valid from land wellsto deepwater wells emerged from this

    Overburden stress

    In deepwater most overburden is water, leading to lowhorizontal stress

    This gives low fracture

    pressure

    Direct correlation betweenLOT and water depth

    Seabed penetration

    Using seabed reference by:

    Removing water pressure

    Removing water depth

    Led to a LOT correlation:

  • 8/17/2019 Modern Well Design-Presentation

    31/70

    Normalization

    Have data from Well 1. Prognose LOT for Well 2 by

    normalizing to new water depth

    Equations

    General equations:

    Different but constant bulk densities:

    Equal constant bulk densities:

    Example 1

    Well 1 is drilled in 400 m water, what is expected LOT if it drills

    inn 1100 m water depth, assuming equal conditions?

    LOT1 = 1.5 sg at 900 m (RKB)

    Solution, new depth: D2 = 900 + (1100-400)+(25-25) = 1600 m

    Expected LOT at 1600 m:

    Example 2

    Now we assume different bulk densities. Same data as in Example

    1, except bulk densities are 2.05 sg and 1. 85 sg

    Solution, new depth: D2 = 900 + (1100-400)+(25-25) = 1600 m

    Expected LOT at 1600 m

    Lower bulk density in well 2 leads to lower LOT

    Fi ld l

  • 8/17/2019 Modern Well Design-Presentation

    32/70

    Field example

    Well offshore Norway in water depth 1349 m:Well Design Premises

    Chapter 4

    4.1 Well Integrity

    Full well integrity Reduced integrity(Weak point below shoe)

    Reduced integrity(Weak point below wellhead)

    4.1 Well Integrity

    Full Well Integrity

    Required for Production Csg. Only

    Min. LOT to reach end open hole

    Reduced Well Integrity

    All other Csg. strings (exept 30”)

    Min. LOT to reach end open hole

    Max. LOT to ensure weak pt. below shoe

    Maximum kick size to ensure full integrity

    4 1 M i LOT 4 2 C i S i D h

  • 8/17/2019 Modern Well Design-Presentation

    33/70

    4.1 Maximum LOT

    Shut-in Gas Filled Well

    Wellhead Press. 200 bar =

    Burst Strength Csg.

    Shoe Pressure 200 bar (2.02s.g.)

    If LOT>2.02 s.g. Weak pointwellhead.

    UNACCEPTABLE

    4.2 Casing Setting Depth

    Pressure Conditions

    Frac. Pressure at Shoe

    Pore Pressure Open Hole

    Operational Conditions

    Borehole Stability, Collapse Mud Loss

    Completion Conditions

    Drilling conditions, No. Of Bits/Trips

    Example 1: Mud Weight

    Casing size

    (inch)

    Depth

    (m)

    Mud weight

    (s.g.)

    7 2700 1.60

    9 5/8 2400 1.60

    13 3/8 1300 1.30

    18 5/8 700 1.20

    30 400 Sea water  

    Example 2: Riser Margin

    E l 2 Ri M i E l 3 Ki k C it i

  • 8/17/2019 Modern Well Design-Presentation

    34/70

    Example 2: Riser Margin

    Casing size

    (inch)

    Depth

    (m)

    Mud weight

    (s.g.)

    7 2700 1.69

    9 5/8 2400 1.69

    13 3/8 1700 1.40

    18 5/8 900 1.20

    30 440 Sea water  

    Example 3: Kick Criteria

    Casing size

    (inch)

    Depth

    (m)

    Mud weight

    (s.g.)

    7 2700 1.69

    9 5/8 2400 1.69

    13 3/8 1700 1.40

    18 5/8 900 1.20

    30 440 Sea water  

    Summary, Csg. Seat Selection

    Determine depth requirements from Mud

    Weight (frac pressure and pore pressures)

    Determine operational factors based on

    experience

    Determine riser margins on floaters

    Only production csg. Need full integrity.

    Use kick margin for other strings.

    4.3 Completion and ProductionRequirements Wellhead design pressure (i.e. 5000 psi)

    Bullheading pressures

    Design alternatives

    Drilling only, or drilling and testing

    Other effects

    Temperature

    Time

    Perforation, stimulation,…

  • 8/17/2019 Modern Well Design-Presentation

    35/70

    Burst Design Burst Design

  • 8/17/2019 Modern Well Design-Presentation

    36/70

    Burst Design

    Leaking tubing

    Burst Design

    Gas Filled Casing

    For all csgs. except 30 in. and production csg.

    Leaking Tubing

    For production csg.

    Maximum gas kick 

    Max. vol. reservoir fluid without breakingdown shoe

    Burst Design

      

      

    t  D P 

     A F  i

    t t 

    21 

     

      

     

     D P 

     A

     F  i

    a

    aa

    4

    t=2a

    Burst Design

    Governed by tangential stress:

    P burst = 2 tensilet/D

    Parameters: tensile and t/D Use manufacturers data

    Use equation for wear assessment

    Burst Design Kick Scenario

  • 8/17/2019 Modern Well Design-Presentation

    37/70

    Burst Design

    Casing wear

    Proportionality, Example: Burst pressure: 419 bar

    Csg. wall worn from 8.92 to 5 mm

    Compute reduced burst strength

    Kick Scenario

    Gas filled casing Conservative criterion

    Leaking tubing For the production casing

    Maximum gas kick  For all casings except production casing

    Relates to csg. shoe strength

    Minimum LOT to reach next shoe

    Maximum LOT to ensure weak point at shoe Maximum influx volume

    Collapse Design

    More complicated than burst

    Yield collapse, plastic collapse,

    transitional collapse and elastic

    collapse depend on t/D ratio

    Elastic collapse:

    Collapse design

    Wear example: same as burst example

    Collapse reduction from 169bar to 80

    bar appears unrealistic

    Collapse criteria

    Mud losses to a thief zone

    Collapse during cementing

    Collapse criteria Tension design

  • 8/17/2019 Modern Well Design-Presentation

    38/70

    Collapse criteria

    Thief zone

    During cementation

    Tension design

    Major design criteria: Weight of casing including buoyancy

    Casing stretch caused by pressure testingwhile bumping cement plug

    Other criteria: Dynamic loads, difficult to assess

    Bending effects

    Temperature effects

    Example of B-annulus pressure in Chapter 4.3.4

    If temperature exceeds 80-100°C (200°F)

    Yield strength reduces

    Tensile strength

    Burst strength

    Bi-axial loading

    From von Mises yield criterion:

    Elliptic equation:

    Combination collapse and tension

    leads to reduced strength

    Other criteria Common design criteria

  • 8/17/2019 Modern Well Design-Presentation

    39/70

    Other criteria

    Sour service Weight loss corrosion

    Hydrogen embrittlement (H2S)

    Time scenario Exploration wells short life

    Production wells long life

    Casing wear

    Wear and damage reduces well integrity

    Common design criteria

    5.2 Casing test pressure

    Requirements, casing must:

    Be pressure tested for

    expected loading

    Not exceed 90% of yield strength (SF=1.11)

    Example surface casing and

    deeper casing

    Pressure tests critical wells

    Sometimes the casing is tested only in one end, e.g. at the

    wellhead

    Critical wells like HPHT wells may require testing of the

    entire casing from top to bottom Problem: Kick scenario assumes reservoir gas in annulus.

    During testing the annulus is filled with mud.

    Possible approaches:

    Bump plug during cementing - Assume pressure exceeding

    saltwater behind casing - Set packer in the middle of the casing

    and test both sides - Establish back pressure behind casing -

    Evacuate upper part to seawater, example to follow

    HPHT pressure test HPHT pressure test

  • 8/17/2019 Modern Well Design-Presentation

    40/70

    HPHT pressure test

    Design basis:

    HPHT pressure test

    Test load with 1.9 sg mud in

    well

    OK in top

    Overloaded at bottom

    Test is unacceptable

    HPHT pressure test

    Upper half displaced to

    seawater

    Test is OK throughout

    well

    HPHT pressure test

    When displacing upper half

    to seawater, always check for

    casing collapse

    Introduction

  • 8/17/2019 Modern Well Design-Presentation

    41/70

    5.3 Casing design example-

    t o uct o

    Summary Setting depth

    Design basis Casing design Summary

    Summary

    -

    Casing depths

    .

    Design basis 18-5/8” Casing design

  • 8/17/2019 Modern Well Design-Presentation

    42/70

    g

    Describe all assumptions for each casing string

    Collapse

    Burst

    tension,

    Cementation

    Wellbore stability

    Fluid densities

    Bullheading

    Wear and corrosion

    And so on…….

    g g

    .

    18-5/8” Casing design

    Collapse loading during

    cementation:

    18-5/8” Casing design

    .

    Summary

  • 8/17/2019 Modern Well Design-Presentation

    43/70

    y

    Results:

    Based on:

    Wateroutside

    Oil inside

    Chapter 6 will assume mud

    outside and gas inside

    5.4 Fully 3D Well Design ImprovesMargins in Critical Wells

    Overview

    Uniaxial, biaxial and triaxial well design

    Conventional triaxial design

    Fully three-dimensional well design

    Well examples

    Conclusions

    Background

    Evolution of long, deep and hot wells

    Design margins have become small

    A need for an accurate model to calculate

    burst and collapse

    Current technology Uniaxial well design

  • 8/17/2019 Modern Well Design-Presentation

    44/70

    gy

    Most well designs are based on one- and

    two-dimensional mechanics

    Recent design packages include a three-

    dimensional model

    Accurate only for certain conditions

    g

    Consider one of the three principal

    stresses

    Axial load design neglects pressure load

    effects

    Pressure load design neglects axial load

    effects

    Biaxial well design

    Consider two of the three principal

    stresses

    Hoop and axial stresses dominate

    Neglect radial stress

    Triaxial well design

    Consider all three principal stresses

    Combine these stresses to a single

    equivalent stress

    Classical von Mises distortion energy

    theory is used in the industry

    Conventional triaxial design Fully 3D well design

  • 8/17/2019 Modern Well Design-Presentation

    45/70

    Simplifications give practical design method

    For burst calculations, assume zero outside

    pressure

    For collapse calculations, assume zero inside

    pressure

    Use pressure differentials instead of actualinside and outside pressures

    New dimensionless solution that include

    all three principal stresses

    Use actual pressures inside and outside

    the pipe

    Dimensionless pipe analysis

    Group 1 ( x ) Inside pressure, axial stress, yield

    strength

    Group 2 ( y ) Inside pressure, outside pressure,

    yield strength, diameter

    Group 3 ( z) Equivalent von Mises stress, yield

    strength

    Group 4 (ß) Outside diameter, wall thickness

    3D yield surface

    ( ) /i o y y p p   

    ( ) /i a y x p    

    / y VME  z     

    2D design factors Example cases

  • 8/17/2019 Modern Well Design-Presentation

    46/70

    -1.5

    -1.0

    -0.5

    0.0

    0.5

    1.0

    1.5

    -1.5 -1.0 -0.5 0.0 0.5 1.0 1.5

    ( ) /i a y x p    

    ( ) /i o y y p p   

    Case 1

    Case 2

    Case 3 Case 4

    DF = 1.00

    DF = 1.10

    DF = 1.20

    DF = 1.30 HP/HT wells offshore Norway

    Well 1 Subsea wellhead

    - Pressure integrity of 10¾” x 9” production casing

    - Two burst cases and one collapse case

    Well 2 Platform

    - Collapse of snubbing pipe during live well intervention

    Pressure/load matrixCase #1 Burst below wellhead

    New 3D model

    DF = 1.37

    Conventional triaxialmodel

    DF = 1.36

    Biaxial model

    DF = 1.37

    Uniaxial model

    DF = 1.44

    Case #2 Burst on top of packer Case #3Thief zone

  • 8/17/2019 Modern Well Design-Presentation

    47/70

    New 3D model

    DF = 1.10

    Conventional triaxial model

    DF = 1.06

    Biaxial model

    DF = 1.04

    Uniaxial model

    DF = 1.17

    Thief zone

    New 3D model

    DF = 2.14

    Conventional triaxial model

    DF = 2.14

    Biaxial model

    DF = 2.04

    Case #4Snubbing

    New 3D model

    DF = 1.69

    Conventional triaxial model

    DF = 1.69

    Biaxial model

    DF = 1.64

    2D design factors

    -1.5

    -1.0

    -0.5

    0.0

    0.5

    1.0

    1.5

    -1.5 -1.0 -0.5 0.0 0.5 1.0 1.5

    ( ) /i a y x p    

    ( ) /i o y y p p   

    Case 1

    Case 2

    Case 3

    Case 4

    DF = 1.00

    DF = 1.10

    DF = 1.20

    DF = 1.30

    Conclusions6 6 C i d i

  • 8/17/2019 Modern Well Design-Presentation

    48/70

    Conventional triaxial design for burst and

    collapse is in error under certain

    conditions

    An accurate 3D model is developed

    Improvement in design margins is

    achieved using 3D model

    6.6 Casing design-

    24” Surface casing

    Collapse during cementation installation

    Burst, gas filled casing next section

    Post installation

    Integrity: Shoe weak, no kick margin, wellhead weak 

    point

    Production casing

    2 Types of tubing Temperature derating Tieback and liner designs

    Design summary

    Important issues

  • 8/17/2019 Modern Well Design-Presentation

    49/70

    .

    Assume gas inside

    and mud outside

    These factors are most important Reservoir pressure

    Reservoir fluid density Fracture pressure

    Density of fluid behind casing

    6. Design of HPHT wells-

    Content

    The following subjects are covered:

    HPHT definitions

    Design premises

    Geomechanical design

    Mud weight design

    Production casing considerations

    Design of shallow casing strings

    Intermediate casing design

    Design of the production casing

    HPHT Definitions Design premises

  • 8/17/2019 Modern Well Design-Presentation

    50/70

    A HPHT well is:

    Temperature higher than 150 °C (294°F)

    Pressure exceeding 10 000 psi

    1 of the above makes it HPHT

    Objectives:

    Flow test Jurassic reservoir

    Drill through reservoir

    Core or samle data

    Well depth 5000 m but due to geological uncertainty, design depth is 5100 m

    Consider sour service conditions

    Two designs due to uncertinty of flow testing

    Integrated design. Well can handle both drilling and well test phases

    Separate drilling and testing. In the unlikely event of flow testing, install a tie-back casing.

    This was chosen.

    Casing alternatives

    Alternatives

    1: No finds

    2: Run liner

    3. Flow test using tie-back 

    4: Use liner too early

    5: Use contingency to reach target

    6: Flow test using tie-back casing

    Prognosis

    Most important design input

    Key HPHT problem, narrowmargin at top reservoir

    Long openhole sections withwellbore stability issues

    Heavy production casingrequiring large drilling rig

    2011 cost: 150 M$

    Geomechanic design Geomechanic-Deep Fracturing

  • 8/17/2019 Modern Well Design-Presentation

    51/70

    Shallow gas require careful placement of upper casing strings

    Shall gas followed by losses below may give problems

    Riserless preferable from this point of view

    Detailed analysis of 70 HPHT wells

    Based modeling on Compaction Model,Modern Well Design page 62.

    Established frac model

    Problem is too much spread

    Must consider groups of data

    LOT

    Pore pressure

    Overburden

    Depth

    Lithology

    LOT vs Pore pressure

    Trend: High LOT – high Po

    Low LOT – low Po

    We will in the following

    normalize all LOTs to a

    pore pressure of 1.8 sg

    Resulting Frac Model

    Stress regimes Resulting frac prognosis

  • 8/17/2019 Modern Well Design-Presentation

    52/70

    Stress regimes in Central Graben

    Resulting frac model

    Process repeated

    for circulation

    loss data

    Frac from LOT data

    Lost circulation from dailydrilling reports during loss

    events

    Large uncertainty below 4700m, design must assume worstcase

    Tiny pressure window thelargest challenge

    Approximately 50% of totaltime spent in reservoir

    Mud weight design

    Drilling problems Well A

    Compare Drilling problems with

    median-line.

    Too low MW in top of well?

    MW design cont.

    Many drilling problems in

    Well B

    3 sidetracks in the 17-1/2”

    section MW gradually increased to

    above median-line

    MW design cont. MW selection

  • 8/17/2019 Modern Well Design-Presentation

    53/70

    Few drilling problems in Well C

    MW roughly around median-

    line

    Well was reasonably well

    MW criteria

    Top hole lower than median-line

    (ML) because of weak csg. shoes

    1000 – 3000 m, approx. ML

    Bottom lower than ML because:

    Need to ”tag” pore pressure to

    seaarch for production csg. Seat

    Accept som collapse in chalk 

    Increase MW gradually to

    minimize tight hole

    Production casing considerations

    Setting point critical

    Don´t know what is below

    If losses, must use contingency

    liners Operational strategy:

    Perform LOTs

    Kick simulation tools

    Drillability analysis

    Careful hydraulic monitoring

    Casing Setting Depths

    .

    Chapter 77.1 Wellheads

  • 8/17/2019 Modern Well Design-Presentation

    54/70

    Chapter 7Drilling Operations and Well Issues

    Operation: Hours used:

    Set anchors and pretension 24

    Ballast rig down.Make up BHA no. 1 and 1300 m drillpipe 20

    Stab into well 1,3

    Drill 50 m of 36 in hole 9

    Circulate hole clean 2

    Perform wiper trip 1

    Displace to hivis mud, pull back to mudline 2

    Position rig using thrusters

    Rig up for running 30 in conductor 0,5

    Make up 3,5 in cement stinger and run in hole 2

    Run in 30 in. conductor 6

    Circulate and cement 30 in., wait on cement 4

    Pull out cement tools and drillpipe 4

    Position rig using thrusters 0

    Total hours 32

    7.2 The 36 in. hole and the 30 in.

    conductor casing

    Operation: Hours used :

    Pull out and rack 36 in BHA 1

    Break down 36 in BHA 1Pull out and rack cement head in derrick 1

    Make up 26 in BHA and run to template 1,5

    Position rig w/thrusters, stab in and run to shoe 1

    Drill 150 m of 26 in hole 12

    Circulate hole clean 3

    Wiper trip, run to bottom and displace to hivis mud 4

    Pull out to seabed 2

    Pull to surface and rack pipes 4

    Position rig using thrusters

    Rig up and run 145 m 20 in casing 12

    Circulate and cement 20 in csg. 4

    Release running tool and pull out of hole 2

    Total hours: 49

    The 26 in. hole and the 20 in. surface

    casing

    The 17.5 in. hole and the 13-3/8 in.

  • 8/17/2019 Modern Well Design-Presentation

    55/70

    Operation: Hours used:

    Position rig using thrustersRig up for running BOP stack 4

    Run marine riser and BOP 16

    Land BOP 4

    Rig down riser handling equipment 4

    Prepare test plug for running in the hole 0,5

    Run in hole with test plug 3

    Test connector 1

    Test BOP 3

    Pull out BOP test tool 3

    Lay down test tool 0,5

    Total hours: 39

    Running BOPOperation: Hours used:

    Make up 17,5 in BHA 3

    Run in hole with BHA 3Drill 20 in cement, plugs and shoetrack 3

    Circulate contaminated mud and perform 2

    Pick up drillpipe 1

    Drill 700 m of directional 17,5 in hole. 24

    Circulate hole clean, wiper trip, pull out of hole 10

    Run log 8

    Rig up for running of 13-3/8 in. casing 3

    Set back cementing head, retrieve seat protector 6

    Run 500 m of 13-3/8 in casing 10

    Circulate and cement 13-3/8 in casing 3

    Set seal assembly and pressure test 1

    Perform BOP test and pull out 6

    Run and set 13-3/8 in wear bushing 6

    Lay down 17-1/2 in BHA 3

    Service cement head 1

    Total hours: 93

    intermediate casing

    Operation: Hours used:

    Make up 12,25 in. BHA 4

    Run in hole to 900 m 6Drill 1100 m of 12,25 in hole 86

    Circulate, wipertrip, circulate 8

    Pull out and rack 12,25 in. BHA 5

    Lay out 12,25 in BHA 2

    Retrieve wear bushing 6

    Rig up for running 9-5/8 in casing 3

    Run in 680 m of 9-5/8 in casing 14

    Circulate and cement casing, pressure test. 6

    Set and test seal assembly 1

    Pull out of well 3

    Run in wear bushing. Temporary P/A. Establish barrier 4

    Disconnect and secure BOP 8

    Total hours: 156

    The 12,25 in. hole and the 9-5/8 in.

    production casing

    Operation: Hours used:Pull marine riser and BOP 8

    Prepare for X-mas tree running 8

    Run and install X-mas tree 24

    Pull running tool 4

    Run marine riser and BOP 9

    Position and latch 2

    Total hours: 55

    Wellhead

    Install Lower Completion

  • 8/17/2019 Modern Well Design-Presentation

    56/70

    Operation: Hours used:

    Make up drillcollars and heavy weight drillpipe 4

    Pick up and make 8,5 in BHA 6

    Run in hole to 800 m 7

    Drill composite bridge plug 2

    Run in hole to 810 m 6

    Drill shoe, circulate, perform FIT 12

    Drill 1000 m horizontal section 160

    Total hours: 197

    The 8.5 in. hole through the reservoir 

    Operation: Hours used:

    Clear rig floor 0,8

    Make up scraper and magnet assy. 1,6

    Pick up heavy weight drill pipe 12

    Make scraper run 18,9

    Rig up tubing tongs 3,1Make up wirewrap screens, blanks and swellpackers 27,2

    Install screen packer/hanger and running tool 1,6

    Rig down tubing tongs 0,8

    Run screens on drill pipe 15,7

    Drop ball, pump down and set packer 3,1

    Test packer from above 1,6

    Release running tool and flowcheck 1,6

    Displace well above packer to brine 0

    Pull out and lay down running tool 7,9

    Make up anchor packer assy. 4,7

    Run in assembly on drill pipe 15,7

    Orient and set anchor packer 1,6

    Pull out and lay down running tool 7,9

    Total hours: 126

    Operation: Hours used:

    Pull bore protector 3,1

    Install lateral zone assemblies 7,9

    Splice and terminate el. cable 15,7

    Make up main completion assembly 6,3

    Run in 5,5 in. tubing 29,9Install TRSCSSV, splice cables 6,3

    Run in 5,5 in tubing 1,9

    Make up tubing hanger 6,3

    Make up THRT and STT?? 6,3

    Run in on WOR?? 18,9

    Install lifting frame, flow head 9,4

    Land and lock tubing hanger, test seals 1,6

    Drop ball, press. Tubing, set and test packer 3,1

    Close TRSCSSV, inflow test,equalize and open 1,6

    Rig up wirelin, pull packer setting plug 12,6

    Pull plug 3,1

    Press. Up annulus and test packer from above 1,6

    Total hours: 136

    Install Upper Completion

    Operation: Hours used:

    Prepare rig for well flow 3,1

    Displace WOR to nitrogen 9,4

    Flow out brine and mud and oil 12,6

    Bullhead tubing with diesel and wax inhibitor 3,1

    Displace WOR to brine 3,1Close TRSCSSV 0,8

    Install tubing head crown plug and test on wireline 12,6

    Close HXT valves and test 3,1

    Remove and lay-out WOR, SST etc. 12,6

    Install tree cap, test, pull and lay down running tool 9,4

    Pull BOP and marine riser 15,7

    Install corrosion cap 6

    Deballast and prepare to move rig 6,3

    Total hours: 98

    Start well for production

    7.3 Torque and Drag in 3D

    Dogleg

  • 8/17/2019 Modern Well Design-Presentation

    57/70

    Operation: Hours used: Percent time:

    36 in. hole 32 3.326 in. hole 49 5

    Running BOP 39 4

    17,5 in hole 93 9.5

    12,25 in. hole 156 15.9

    Wellhead 55 5.6

    8,5 in. hole 197 20

    Lower completion 126 12.8

    Upper completion 136 13.9

    Start well 98 10

    Total hours: 981

    40,9 days 100%

    Summary of well construction time

    Dogleg

    rad

    180)(DL

    coscoscossinsincos 212121

     

     X 

     Z 

    22

     

    1

     R

     R

     

    Friction vs. geometry

    Straight sections

    Curved sections

    sincosLwFF 12

         sin Lwr T   

     

    12

    1212

    sinsinLweFF 12

    121rFrNT  

    2D Example

    500

    1500

    0

    )(m Depth

     Horizontal 

    45335

    170

    kN 2861661

    500 1500

    45

    45

    455

    )(Re   mach

    1  3  0  8  

    1380

    1000

    170

    1000

    2D Results 2D Results

  • 8/17/2019 Modern Well Design-Presentation

    58/70

    Table 7.1: Forces in the drillstring during hoisting and lowering

    Position

    Static weight(kN) H oisting (kN) Lowering(kN)

    Well Bottom 0 0 0

    Bottom dropoff section 286 286 286

    Bottom sail section 286+0.237x120=

    286+28.4=314.4

    286x1.17+28.4=363 286x0.855+28.4=272.9

    Top sail section 314.4+0.237x925=

    =314.4+219.2=533.6

    363+0.237x1308(cos 45˚+0.20sin45˚)=626 272.9+0.237x1308(cos 45˚-0.20sin45˚)=448.3

    Top buildup section 533.6+0.237x120=

    533.6+28.4=562

    626x1.17+28.4=760.9 448.3x0.855+28.4=411.7

    Top well 562+0.237x335=

    562+79.4=641.4

    760.9+79.4=840.3 411.7+79.4=491.1

    500 1000

    500

    1000

    1500

    )( m Depth

    )( kN  Force

     Hoisting 

     Lowering 

    )( kNmTorque

    0 10 20

    0

    1661

    1380

    455

    335

    54.15 4.641 3.8401.491

    Static

    Torque

    Vertical

    Build-Up

    Straight

    Inclined

    Drop-Off 

    BHA

    Vertical

    500 1000

    500

    1000

    1500

    )(m Depth

    )(kN  Force

    )(kNmTorque

    0 10 20

    0

    1661

    1380

    455

    335

    kNmTOB 9WOB

    Without

     Bit Torque

    With

     Bit Torque

    90kN 

    Off  Bottom

    2254.1513 4.641

    Vertical

    Build-Up

    StraightInclined

    Drop-Off 

    BHAVertical

    Static Weight (Off-Bottom)

    Static Weight (On-Bottom)

    3D Example

     X 

     Z 

    500

    1052

    1512

    1752

    20632104

    40

    0

    25

    73

    3D Results

    500 1000

    1000

    2000

    3000

    )(mMD

    )(kN  Force

    )(kNmTorque

    0 10 20

    0

    500

    1100

    1700

    2075

    2865

     Hoisting  Lowering   Static

    768576463

    Build-up

    Straight Inclined

    Build-upwith

    RightSide Bend

    Build-up

    withLeftSide Bend

    Straight Inclined

    BHA

    Vertical

    5.13

    ueStaticTorq

    500 1000

    1000

    2000

    3000

    )(mMD

    )(kN  Force0

    500

    1100

    1700

    2075

    2865

    ht StaticWeig 

    768576463

    Build-up

    StraightInclined

    Build-up

    with

    RightSideBend

    Build-up

    with

    Left Side Bend

    StraightInclined

    BHA

    VerticalCombined 

     Hoisting 

    661513

     Pure Hoisting 

     Pure Lowering 

    Combined 

     Lowering 

    Friction Analysis for Long-Reach Wells

    This presentation

    I d

  • 8/17/2019 Modern Well Design-Presentation

    59/70

    Introduction

    Analytical models for torque and drag

    Field case

    Friction analysis for ultra-long wells

    Summary

    IntroductionSignificance of well friction

    Numerical simulators:

    Availability

    Limitations

    Closed form models:

    Increase availability

    Analytical approach

    Analytical models for torque and drag

    Basic model: Coulomb friction

    Linear hole sections

    Drag: F 2 = F 1 + w s(cos  sin  )

    Torque: T =  w srsin 

    Analytical models for torque and drag

    Drop-off section

    Analytical models for torque and drag

    Modified catenary profile

  • 8/17/2019 Modern Well Design-Presentation

    60/70

    pForces:

      Fx = 0

      Fz = 0

    Tension during hoisting:

    Tension during lowering:

    Torque:

    2 1

    2 1

    2 1

    2

    2 1( )

    2 1 2

    2 1

    (1 )(sin sin )

    1 2 (cos cos )

    ewR F F e

    e

     

     

     

         

         

     

     

     F F e wR e2 1 2 12 1 2 1    sin sin

    1 sin cos cos1 2 1 2 1T r F wR rwR  

    y pResults:

    Well path coordinates:

    Deviation from ”ideal”tension: F

    Drag:

    Torque:

    1 11 1 1 11 1

    sincosh sinh cot cosh sinh cot

    sin

     F    wx z 

    w F 

       

     

     s F 

    w

    wx

     F 

    11

    1 1

    11 1sin sinh sin

    sinh cot cos  

       

     F F 

    ws F 

     F cat  

     

     

     

     tan

    cos

    sin

    1 1 1

    1 1

    1 1 1

    1 1

    costan

    sincat 

    ws F T r F 

     F 

      

     

       

     Note: Entrance condition to modified catenary

    Analytical models for torque and drag

    Side bend

    Tension:

    Torque:

         

    2 1

    2 1

    2

    22

    2 1 122

    1 1

    1 1

    2 2

    wR e F F F wR e

     F F wR

     

     

    T r F wR  12 2 2 1

    Analytical models for torque and drag

    Combied rotation and axial movement

    a) Drag and torque for a pipe.

    b) Combined friction from rotationand axial movement.

    2

    22T   F w sr 

       

    Analytical models for torque and drag

    Downhole motor torque

    Analytical models for torque anddrag

  • 8/17/2019 Modern Well Design-Presentation

    61/70

    Downhole motor torque

    Bit power during rotary drilling:

    Bit power with downhole motor:

    Assuming equal power, the torque relation is:

    This is the ”gearbox” principle.

    Downhole motor may significantly reduce bit torque.

    motor motor motor 

    rotaryrotaryrotary

    n

    n

    CT  P 

    CT  P 

    rotary

    motor 

    rotarymotor    T 

    n

    nT   

    Application:

    - Split the well into geometries:

    e.g. straight section bottombuild-up section

    vertical section

    - Adding the equations for these geo metries gives total torque and drag

    Analytical models for torque anddrag

    Applications:

    3-Dimensional well path.

    Drag:

    Torque:

    Total solution:

    Drag:F=  F 2 from bottom to top

    Torque:T=    T from bottom to top

    2 2

    2 2 2 build_or_drop sidebend F F F 

    2 2

    2  build_or_drop sidebend F T T 

    Field case

    Long-reach well in the Yme field:Depth: 2950 mTVD top reservoir

    3100 mTVD total depth

    Horizontal reach: 7528 m

    Rig limitations:Hoist: 4540 kN (1.mill. lbs)

    Top drive: 35 kNm (25.800 lb-ft)

    Field case

    Well profile investigated

    Field case

    Results Top-drive:

  • 8/17/2019 Modern Well Design-Presentation

    62/70

    Hoist

    Conclutions:

    - Drill string tension not critical

    - Torque limiting element

    - Modified catenary profile best

    Top drive:

    WellProfile

    Static hookload (kN)

    Pick-upload (kN)

    Slack-offload (kNm)

    Modified

    catenary

    845 1360 593

    Minimum

    dog-leg

    843 1332 609

    Under-

    section

    842 1321 568

    Standard   858 1350 543

    WellProfile

    Surfacetorque (kNm)

    Torque build-upbnd (kNm)

     

    Torquehold

    Modified

    catenary

    28.57 7,11 21,46

    Minimum

    dog-leg

    30.91 11,04 19,87

    Under-

    section

    29.51 6,88 22,63

    Standard   30.42 9,05 21,37

    Friction analysis for ultra long wells

    Example: Prolong Yme well to a horizontal reach of 12 km

    Results

    Pulling Sta tic Lowering Build-up Hold

    section

    Total

    Steel   179 175 60 10,2 43.7 53.9

    Titanium   133 130 60 6,2 26,90 33.1

    Composite   102 101 60 3,7 16.0 19,70

    Drillpipe Hook load(kN) Torque(kNm)

    Conclusions:

    Well can be drilled if light drill pipe

    is used in the sail section Tension allowable for all cases

    Torque limiting factor

    Other elements within permissible

    limits, like hydraulics, hole cleaning,

    borehole stability, …

    Summary Analytical expression for torque and drag are derived in this paper.

    The models are valid for straight sections, build-up, drop-off and sidebends.

    Equations for geometry and torque and drag for a modified catenaryprofile is also given.

    Torque and drag analysis can be performed by adding equations for eachhole section.

    A field case from Yme demonstrates the application. A modified catenaryprofile was chosen to minimize torque.

    An ultra-long well was studied with the models. By using light-weight drillpipe in the sail section a 12 km(or longer) well can be drilled with existingrig equipment.

    Dominating limiting parameters:

    Friction

    Drill pipe weight

    Mud density

    Friction analysis for ultra-long wells

    Guidelines to obtain a low-friction well:

    7.4 Stuck pipe in deviatedwellbores

  • 8/17/2019 Modern Well Design-Presentation

    63/70

    High inclination in the sail section.

    Minimum weight BHA.

    Heaviest DP in top of string.

    Select modified catenary or another profile.

    Minimizing dog-leg and tortuosity.

    Downhole motor reduce torque.

    Reduce friction by:

    Low DP weight

    Small tool joint

    Self-lubricant matrix.

    -

    Content

    Introduction Industry practice Deviated wells and friction

    Depth to stuck point Field case Methods to free pipe Final comments

    Introduction

    Two most costly drilling problems: Circulation losses

    Stuck pipe

    Causes high economic risk for long wells Sidetrack often consequence

    Operational aspects important Often stuck after static period

    Industry practice

    If stuck drillstring, apply pull testAl l f d

    Deviated wells and friction

    This analysis valid for differential sticking

  • 8/17/2019 Modern Well Design-Presentation

    64/70

    Alternatively, run free point indicator

    Pull test estimate free pipe length fromelongation Current models neglects well friction

    Therefore strictly applicable for vertical wellsonly

    y g

    Differential pressure

    Area exposed

    Permeable formation

    Friction in curved bends and

    straight inclined sections

    Depth to stuck point

    Depth to stuck point,

    vertical well

    Depth to stuck point,

    deviated well(vertical, build, sail)

    Torsion test

    Field case

    DP stuck in long deviated well

    Friction coefficient causes uncertainty

    Results:

    Frictionless: 5097 m

    New model: 5693 m

    Torsion test: 5675 m

    Torsion is independent of friction as

    pipe is not pulled

    Torsion test should be included in rig

    procedures

    Methods to free pipe

    Maximum mechanical force

    Final comments

    This analysis is valid for cases with differential sticking. The

    diff i l llb /f i i h i i l l

  • 8/17/2019 Modern Well Design-Presentation

    65/70

    Pull/twist DP towards limit

    Minimum density method

    Displace well to minimum density mud to reduce

    bottomhole pressure. Also reduces buoyancy

    Maximum buoyancy method

    Displace DP to seawater. Buoyancy increases giveing higher pull margin

    Results:

    differential pressure wellbore/formation is the critical element.

    If the string is mechanically stuck, the differential pressure is no

    longer a factor. For this case reducing MW has no positive effect.

    We recommend that the Maximum Mechanical Force method, the

    Maximum Buoyancy method and theTorsion method to be used

    here.

    7.5 Well-Integrity Issues

    Offshore Norway

    Birgit Vignes, Petroleum Safety Authority Norway

    Bernt S. Aadnoy, Univ. of Stavanger

    Paper IADC/SPE 112535 presented at the 2008IADC/SPE Drilling Conference, Orlando

    1. Introduction of the pilot well integrity study

    2. Regulation and standards

    3. Results of the study

    4. Examples of well failures5. Continued work in 2008

    Summary

    This presentation

    1. Introduction - Background for the survey

    Several well integrity incidents

    Several shortfalls

    Scope:Scope: How comprehensive is theHow comprehensive is the

    well integrity problem on the NCS,well integrity problem on the NCS,

    and what are the main issues/ challenges?and what are the main issues/ challenges?

    S l i f ll f il i i

    1. Introduction - Well Categorization

  • 8/17/2019 Modern Well Design-Presentation

    66/70

    Several shortfalls

    Missing critical information Insufficient openness and access to well-data

    Competence issues

    Well conversions

    Varying management of changes

    Selection of wells for pilot examinationSelection of wells for pilot examination

    Well integrityWell integrity

    failure / issue ?failure / issue ?(or uncertainty)(or uncertainty)

    NoNoYesYesWhat kind of barrier/What kind of barrier/

    barrier elementbarrier element

    failure/ issue/ uncertainty ?failure/ issue/ uncertainty ?

    Well barrierWell barrierintactintact

    Impact?Impact?YesYes

    Cat. A:Well isshut In,

    E.g.: Leaks,over criteria,

    well contr .,

    Cat. B:Working

    under 

    conditions/exemptions

    E.g.: No gas lift 

    NoNo

    Cat. F:

    Shut in

    because of 

    topsides

    bottlenecks,planned

    testing and

    maintenance

    Incl.: SD&P 

    Cat.G:

    Shut in

    while

    awaiting

    P&A

    Cat. C:Insignificant

    deviation

    for currentoperation

    Determine injury/ damage/ Determine injury/ damage/ 

     production impact/  production impact/ 

    financial lossfinancial loss

    Shut in well ?Shut in well ?NoNoYesYes Well

    OK /

    active

    Cat. D:

    External

    conditionsE.g.:

    weatherconditions,

    other

    activities,

    union dispute,

    Cat. E:

    Shut in

    on the

    basis of 

    reservoar related

    issuesE.g.: high

    water cut 

    2. Regulation and standards

    Primary Well Barrier 

    Secondary Well Barrier 

    Ref. “Swiss cheesemodel” 

    The Primary Well Barrier is the first object to prevent

    unintentional flow from the source

    The Secondary Well Barrier prevents further

    unintentional flow if the primary well barrier should fail

    Common production well 

    with the 2 ”barrier envelopes” 

    Source

    Ref: Activities Regulation §76 w/ref. to NORSOK D010

    3. Results - Wells with integrity issues

    18% of 406 the assessed production- and injection wells were reported to have well

    integrity failures/ shortfalls or uncertainty.

    Well issues are related to 33% of the injectors, and 15% of the producers.

    Wells with integrity failure, issue or uncertanty

    48

    27

    75

    0

    10

    20

    30

    40

    5060

    70

    80

    Production Injection Total

    Production, injection and total

       N  u  m   b  e  r  o   f  w  e   l   l

    3. Results – Well integrity impact

    Well integrity impact

    20

    25

    3. Results - Well integrity issues by age

    Well integrity failure/issue distribution b y well age, per 1.3.2006

    25

    30

    s  s  u  e

  • 8/17/2019 Modern Well Design-Presentation

    67/70

    18

    22

    8

    10

    16

    1

    0

    5

    10

    15

    20

     A: Shut in B: Working under 

    conditions

    C: Insignificant deviattion

    for current operations

    Well integrity impact category A, B and C

       N  u  m   b  e  r  o   f

      w  e   l   l  s

    Producer 

    Injector 

    7% wells were shut in9% wells were working under conditions/exemptions

    2% wells had an insignificant deviation for current operations

    • The frequency of wells with integrity issues in age group 0-14 years is twice as

    high as for well group 15-29 years.• WAG wells and recently optimized well design have caused challenges

    • P&A wells are not included in this survey

    24

    26

    16

    6

    12

    0

    5

    10

    15

    20

    25

    0 to 4 5 to 9 10 to 14 15 to 19 20 to 24 25 to 29

    Age in years

       N  u  m   b  e  r  o   f  w  e   l   l  s  w   i   t   h   f  a   i   l  u  r  e   /   i  s

    Numbe r of w ells w ith we ll integrity problem

    29

    8

    4 2 1 1 1 2 12

    9 8

    12 4

      W e  l  l

      h e  a d

      D  H  S  V

      C o  n d

      u c  t o  r

      A  S  V  T  u

      b  i  n g   G  L

      V

      C  a  s  i  n

     g 

      C e  m e

      n  t

      P  a c  k

     e  r

      P  a c  k

     o  f  f

      C  h e  m

      i c  a  l i  n

      j  . l  i  n e

      T  R  S  V

      F  l  u  i d

     b  a  r  r  i

     e  r

      D e  s  i g 

      n

      F o  r  m

      a  t  i o  n

    C a t e r o r y b a r r i e r e l e m e n t f a i l ur e

       N  u  m   b  e  r

      o   f  w  e   l   l  s

    0

    5

    10

    15

    20

    25

    30

    35

    3. Results - Well barrier element 3. Results - Areas for improvement:

     Areas of high priority: Well documentation

    Handover documentation

    Regular monitoring

    Competence and training

    Event:

    18-5/8” csg. broke due to

    corrosion

    Reasons:

    Cement return port left

    open

    4. Example I: Surface Casing collapsed

    Event:

    Casing and tubing hangerand running tool failed

    Reasons:

    Hangers uprated 50%

    Manufacturers up-rating

    4. Example II: Production Casing Failure

  • 8/17/2019 Modern Well Design-Presentation

    68/70

    corrosion

    Wellhead dropped 44 cm Platform structure

    arrested further drop,

    reducing the damage

    potential

    open

    Fresh seawater and tide

    caused severe corrosion

    in splash zone

    Consequences:

    Platform production

    stopped

    High cost of event Initiated monitoring

    program

    and running tool failedduring operations

    Overloaded duringpressure testing

    Manufacturers up-rating

    failed

     Accepted uprating as OK

    Poor equipment design

    Consequences:

    Cost of well problems

    Many installations, cannot

    replace Reduce max. allowable

    loading

    Events:

    Severe lost circulation

    Plugged drill pipe

    Wellcontrol problem

    Open well in periods

    Reasons:

    Depleted reservoirs

    Gunk pill plugged off DP

    Less good operational

    decisions

    Consequences:

    Sidetracked well

    High cost

    Improved procedures

    4. Example III: Lost wellbore

    Events:

    Leaks in prod. tubings in

    14 wells

    Reasons:

    Leaks in PBR

    Corrosion

    Consequences: Increased monitoring

    Constraints for availability

    and flexibility

    4. Example IV: Gas Leaks in Tubings

    Events:

    Prod. csg. and tubing

    collapsed

    Reasons:

    Wrong csg. joint installed

    Leaks through PBR

    4. Example V: Production Casing Failure 5. Continued work in 2008Industry:

    Operators studies confirm PSA 2006 results

    OLF workshop initiative and founding of operators well integrity forum (WIF)

    Operators increased focus on well integrity issues and personnel competance

    Profile issue in Risk Level Project (KPIs & healthy wells)

  • 8/17/2019 Modern Well Design-Presentation

    69/70

    collapsed

    Well control incident

    during repair operation

    Leaks through PBR

    Uncertain pressureintegrity of well

    Consequences:

    High cost

    Clarify well integrity

    Improve workover

    procedures

    International Authorities:

    Information and documents requested in PSA 2006 study and auditing ofoperators

    Information to NOPSA (Australia) in meetings with PSA and Statoil

    Cooperation with SSM (Netherlands) 2007-2008 with similar approach as PSA2006

    PSA:

    Well integrity meeting and auditing of Marathon Norway in June 2007

    Well integrity challenges of CO2-injection to be studied by SINTEF

    Survey of temporary abandoned wells incl. well barrier schematic

    Well integrity issues related to GLV & ASV to be discussed with industry during2008

    The wells were a representative selection

     A high number of well-related failures and shortfalls

    18 % of the wells had well integrity issues or uncertainty

    7 % of the wells were shut in

    The barrier issues are within tubing, ASV, casing and cement The impairments represents a high potential for HSE

    improvement

    Examples of well failures presented

    Summary

    EXTRA VIEWGRAPHS 

    Initial Questionnaire for PSA’s survey

     A. Is the “well picture”/ outcome of the XLS- forms representing the typical situationon the facility ?

    B. Are key design premises, well history and current technical condition validatedand easy accessible for key personnel?

    C Does hand-over documents include sufficient well data with premises/ limits

  • 8/17/2019 Modern Well Design-Presentation

    70/70

    C. Does hand-over documents include sufficient well data with premises/ limits,including updated schematics, exposures, technical condition and changes/

    deviations/ precautions with regard to well integrity and well control issues?D. Are there established technical requirements to well barrier envelopes /elements,regular condition monitoring, and systematic management of well integrity issues?

    E. Are the company requirements for well barriers consistent with Norsok D-010 ?

    F. Is there a consistent practise within the company for managing well integrityissues?

    G. Are management of change and non-conformance handling consistently practised?

    H. Are requirements to competence and training defined and implemented forcommon understanding of the well barrier concept, barrier performancerequirements, records assurance, and actions required upon indications offailures ?

    I. How is openness and reporting of undesirable well incident encouraged, includingexchange of experience internally and externally ?

    J. Any specific performance indicators pertaining to well integrity ?

    K. Other issues relating to the subject