minutes of the 227th meeting

26
Page 1 of 26 MINUTES OF THE 227 th MEETING OF THE STATE LEVEL EXPERT APPRAISAL COMMITTEE HELD ON 10/2/2015 AT COMMITTEE ROOM, GUJARAT POLLUTION CONTROL BOARD, GANDHINAGAR. ------------------------------------------------------------------------------------------------ The 227 th meeting of the State Level Expert Appraisal Committee (SEAC) was held on 10 th February 2015 at Committee Room, Gujarat Pollution Control Board, Gandhinagar. Following members attended the meeting: 1. Shri T. P. Singh, Chairman, SEAC. 2. Dr. Nikhil Desai, Member, SEAC. 3. Shri V. C. Soni, Member, SEAC. 4. Shri R. J. Shah, Member, SEAC 5. Shri V.K. Jain, Member, SEAC 6. Shri V.N. Patel, Member, SEAC Following officers from the Geology and Mining Department attended the meeting: Shri A.K.Muley, Senior Geologist, CGM, Gandhinagar. Shri R.M. Gadhvi, Assistant Geologist, Dist: Patan. Shri P.J.Bhavsar, Geologist, Dist:Vadodara Shri D.S. Bariya, Geological Assistant, Dist:Porbandar. Shri K.N. Mahavadia, Asst. Geologist, Dist: Morbi. Shri J.K. Dave, Geologist, Dist: Junagadh. Shri M.D. Chaudhary, Geological Assistant, Kutch, Bhuj Of total 253 mining projects taken up in the meeting, 2 cases for appraisal on individual basis referred from MOEFCC, one table agenda, 7 cases for First Hearing and 244 cases of the applications received through the Office of the Geology and Mining Commissioner, Gandhinagar, along with the project information in Performa endorsed by the concerned district Geologist / Asst. Geologists were taken. APPRAISAL CASE : [1] TATA Chemicals Ltd.,S NO. 21/P, Village: Aniali, Ta: Ranavav, Porbander (15.99 Ha) It is a lime stone mine project having lease area of 15.99 Hectares. The application for TOR of "Lime Stone Mine" located in Village Aniali, Ta: Ranavav, Porbander was submitted on 12-07-2012 to MOEF, New Delhi as per the general condition of EIA notification 2006 considering project location within 10 Km from the boundary of Barda Wild life sanctuary. Barda wild life Sanctuary is located in NW direction at 7.63 Km from the proposed project. Naliyadhar Reserved Forest is located in NW direction at 2.10 Km from the lease area. Vide EIA Notification S.O. 1599(E) dated 25-06-2014, proposal is transferred from MOEF to State Level Environment Impact Assessment Authority vide letter no J-11015/305/2012-IA-II (M) dated 30-09-2014 considering project falls under category B as Barda Wild Life Sanctuary is beyond 5 Km from the proposed mine lease area, The project proponent made presentation regarding compliance of TOR before the committee in the meeting on 10-02- 2015. Mine is idle since 1986. Documents regarding approved scheme of mining, EIA report and public hearing are submitted for mine lease area of 15.99 Ha. Proposed Production is 0.05 Million MTPA, waste generation is Nil. Tata Chemical Ltd. has made the policy for safety, Health and Environment and Social accountability. The project proponent conforms to the standard operating procedures for legal and quality system as per ISO 9001, ISO 14001 and OHSAS 18001.The mining is proposed to be carried out by opencast mechanized method as per scheme of mining approved by Indian Bureau of Mines. There will be no overburden or

Upload: vandang

Post on 03-Jan-2017

224 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Minutes of the 227th meeting

 

Page 1 of 26  

MINUTES OF THE 227th MEETING OF THE STATE LEVEL EXPERT APPRAISAL COMMITTEE HELD ON 10/2/2015 AT COMMITTEE ROOM, GUJARAT POLLUTION CONTROL BOARD, GANDHINAGAR. ------------------------------------------------------------------------------------------------ The 227th meeting of the State Level Expert Appraisal Committee (SEAC) was held on 10th February 2015 at Committee Room, Gujarat Pollution Control Board, Gandhinagar. Following members attended the meeting: 1. Shri T. P. Singh, Chairman, SEAC. 2. Dr. Nikhil Desai, Member, SEAC. 3. Shri V. C. Soni, Member, SEAC. 4. Shri R. J. Shah, Member, SEAC 5. Shri V.K. Jain, Member, SEAC 6. Shri V.N. Patel, Member, SEAC

Following officers from the Geology and Mining Department attended the meeting:

Shri A.K.Muley, Senior Geologist, CGM, Gandhinagar. Shri R.M. Gadhvi, Assistant Geologist, Dist: Patan. Shri P.J.Bhavsar, Geologist, Dist:Vadodara Shri D.S. Bariya, Geological Assistant, Dist:Porbandar. Shri K.N. Mahavadia, Asst. Geologist, Dist: Morbi. Shri J.K. Dave, Geologist, Dist: Junagadh. Shri M.D. Chaudhary, Geological Assistant, Kutch, Bhuj Of total 253 mining projects taken up in the meeting, 2 cases for appraisal on individual basis referred from MOEFCC, one table agenda, 7 cases for First Hearing and 244 cases of the applications received through the Office of the Geology and Mining Commissioner, Gandhinagar, along with the project information in Performa endorsed by the concerned district Geologist / Asst. Geologists were taken. APPRAISAL CASE: [1] TATA Chemicals Ltd.,S NO. 21/P, Village: Aniali, Ta: Ranavav, Porbander (15.99 Ha) It is a lime stone mine project having lease area of 15.99 Hectares. The application for TOR of "Lime Stone Mine" located in Village Aniali, Ta: Ranavav, Porbander was submitted on 12-07-2012 to MOEF, New Delhi as per the general condition of EIA notification 2006 considering project location within 10 Km from the boundary of Barda Wild life sanctuary. Barda wild life Sanctuary is located in NW direction at 7.63 Km from the proposed project. Naliyadhar Reserved Forest is located in NW direction at 2.10 Km from the lease area. Vide EIA Notification S.O. 1599(E) dated 25-06-2014, proposal is transferred from MOEF to State Level Environment Impact Assessment Authority vide letter no J-11015/305/2012-IA-II (M) dated 30-09-2014 considering project falls under category B as Barda Wild Life Sanctuary is beyond 5 Km from the proposed mine lease area, The project proponent made presentation regarding compliance of TOR before the committee in the meeting on 10-02-2015. Mine is idle since 1986. Documents regarding approved scheme of mining, EIA report and public hearing are submitted for mine lease area of 15.99 Ha. Proposed Production is 0.05 Million MTPA, waste generation is Nil. Tata Chemical Ltd. has made the policy for safety, Health and Environment and Social accountability. The project proponent conforms to the standard operating procedures for legal and quality system as per ISO 9001, ISO 14001 and OHSAS 18001.The mining is proposed to be carried out by opencast mechanized method as per scheme of mining approved by Indian Bureau of Mines. There will be no overburden or

Page 2: Minutes of the 227th meeting

 

Page 2 of 26  

top soil overlying the deposit. The average bench height will be 3 m high. The EIA study area comprises of 10 Km zone around the proposed lease periphery. As per approved scheme of mining, the lease area is devoid of waste/ overburden and top soil. Land use category of 10 Km radius study area around the mine site comprises of agriculture land (65.13%), Forest Land (12.38%), Settlement (12.85%), Water Bodies (3.08%), Waste Land (4.91%) and Barda Wildlife Sanctuary (1.65%). Mine lease area does not include forest land. There is no habitation exist within core zone. Project proponents have proposed EMP includes creation of mining pits for rain water harvesting, water spray system to control fugitive dust emission, Machinery/ vehicle preventive maintenance and regular checkups, controlled blasting method, maintenance of road conditions, covering of loaded vehicles, visual display of sufficient traffic signs, Project proponents submits that there will be no impact on the wild life sanctuary due to proposed mining. During post mining stage, existing waste land will be converted to water harvesting bodies and green belt. Tata Chemicals Ltd. has applied for wild life clearance and presently it is under process. There is no Schedule I fauna found in core zone. Change of land use pattern for virgin area for mining reduces from 4.2074 Ha to 1.5694 Ha. Project Proponent has proposed CSR for natural resource management, Environmental Care and conservation, Empowerment to local residents, livelihood development, Health and education programmes, and infrastructure development support. Baseline environmental survey is considered for Land, Water, Air, Noise, Biological and Socio-economic quality status in the study area. Primary baseline data has been generated for the pre-monsoon season for three months(March 2013- May 2013).For ambient air quality, predicted incremental cumulative concentration of PM10 near Barda WLS is 58.218 microgram/Cubic meter (Baseline is 58.20 microgram/cubic meter, incremental 0.018 microgram/cubic meter), Predicted incremental cumulative concentration of PM10 near Naliyadhar R.F.is 49.16 microgram/Cubic meter (Baseline is 48.50 microgram/cubic meter, incremental 0.66 microgram/cubic meter),predicted incremental cumulative concentration of SO2 near Barda WLS is 11.1002 microgram/Cubic meter (Baseline is 11.10 microgram/cubic meter, incremental 0.0002 microgram/cubic meter), Predicted incremental cumulative concentration of SO2 near Naliyadhar R.F.is 48.5063 microgram/Cubic meter (Baseline is 48.50 microgram/cubic meter, incremental 0.0063 microgram/cubic meter),predicted incremental cumulative concentration of NO2 near Barda WLS is 58.2016 microgram/Cubic meter (Baseline is 58.20 microgram/cubic meter, incremental 0.0016 microgram/cubic meter),Predicted incremental cumulative concentration of NO2 near Naliyadhar R.F.is 48.5507 microgram/Cubic meter (Baseline is 48.50 microgram/cubic meter, incremental 0.0507 microgram/cubic meter), Study also includes predicted Noise incremental values. The proposed mining location and study area falls under Zone III which is classified as moderate risk zone as per GSDMA. Soil of study area is medium black soil. The general water table depth of study area falls between 17.5m to11.5 m BGL during pre-monsoon and post monsoon periods. During rainy season, the surface runoff follows the natural contour and flows in the same direction (i.e. NW to SE). Two seasonal rivers namely Minstar and Bileshwari are present in the study area. Surface water quality is in general poor (Brackish to saline).Water requirement of the project is 30 KLD and will be availed from ground water for which Project proponents have obtained approval from CGWA for abstraction. There will be no intersection of ground water table with mining. Project proponent have proposed rainwater harvesting and accordingly about 6,45,880 KL of water at the site will be used for green belt development and dust suppression. Plantation during pre operational phase is 0.15 Ha which is proposed to the1.15 Ha during operational phase and post mining at the end of mine life. The nearest habitation is more than 500 m away from the proposed project. During public hearing conducted on 04/12/2013, issues related to the CSR, air pollution due to proposed activities and vibrations due to blasting were raised which were answered satisfactorily by project proponents.

Page 3: Minutes of the 227th meeting

 

Page 3 of 26  

After detailed discussion on various aspects regarding project, it was decided to recommend the project to SEIAA, Gujarat for grant of Environmental Clearance only after submission of the following.

1. Based on contours, details of flow of rainwater runoff meeting to the nearby water bodies showing no resistance to the natural flow pattern due to proposed mining activities.

2. Details of existence of blue bull in study area and project activities impeding/endangering habitation of the said species and proposed action plan to protect its habitation.

3. Letter from department of Geology and mining regarding no other mine exists in the 500 m radial distance from the boundary of the mine lease area.

[2] TATA Chemicals Ltd.,S NO. 94/P, Village: Aniali, Ta: Ranavav, Porbander (6.07 Ha) It is a lime stone mine project having lease area of 6.07 Hectares. The application for TOR of "Lime Stone Mine" located in Village Aniali, Ta: Ranavav, Porbander was submitted on 12-07-2012 to MOEF, New Delhi as per the general condition of EIA notification 2006 considering project location within 10 Km from the boundary of Barda Wild life sanctuary. Barda wild life Sanctuary is located at 8.64 Km from the proposed project. Vide EIA Notification S.O. 1599(E) dated 25-06-2014, proposal is transferred from MOEF to State Level Environment Impact Assessment Authority vide letter no J-11015/305/2012-IA-II (M) dated 30-09-2014 considering project falls under category B as Barda Wild Life Sanctuary is beyond 5 Km from the proposed mine lease area, The project proponent made presentation regarding compliance of TOR before the committee in the meeting on 10-02-2015. Mine is idle since 1986. Documents regarding approved scheme of mining, EIA report and public hearing are submitted for mine lease area of 6.07 Ha. Proposed Production is 0.053 Million MTPA, waste generation is Nil. Tata Chemical Ltd. has made the policy for safety, Health and Environment and Social accountability. The project proponent conforms to the standard operating procedures for legal and quality system as per ISO 9001, ISO 14001 and OHSAS 18001.The mining is proposed to be carried out by opencast mechanized method as per scheme of mining approved by Indian Bureau of Mines. There will be no overburden or top soil overlying the deposit. The average bench height will be 3 m. The EIA study area comprises of 10 Km zone around the proposed lease periphery. As per approved scheme of mining, the lease area is devoid of waste/ overburden and top soil. Land use category of 10 Km radius study area around the mine site comprises of agriculture land (60.30%), Forest Land (18.23%), Settlement (11.84%), Water Bodies (2.89%), Waste Land (6.09%) and Barda Wildlife Sanctuary (0.65%). Mine lease area does not include forest land. There is no habitation exist within core zone. Project proponents have proposed EMP includes Plantation/ grass plot development to improve vegetation cover and biodiversity, creation of mining pits for rain water harvesting, water spray system to control fugitive dust emission, Machinery/ vehicle preventive maintenance and regular checkups, controlled blasting method, maintenance of road conditions, covering of loaded vehicles, visual display of sufficient traffic signs, Project proponents submits that there will be no impact on the wild life sanctuary due to proposed mining. During post mining stage, existing waste land will be converted to water harvesting bodies and green belt. Tata Chemicals Ltd. has applied for wild life clearance and presently it is under process. There is no Schedule I fauna found in core zone. Change of land use pattern is given and remaining virgin area reduces from 3.223 Ha to 0 Ha. Project Proponent has proposed CSR for natural resource management, Environmental Care and conservation, Empowerment to local residents, livelihood development, Health and education programmes, and infrastructure development support.

Page 4: Minutes of the 227th meeting

 

Page 4 of 26  

Baseline environmental survey is considered for Land, Water, Air, Noise, Biological and Socio-economic quality status in the study area. Primary baseline data has been generated for the pre-monsoon season for three months (March 2013- May 2013). Air modelling during study predicts concentration of total suspended Particulate Matter in SSE direction at 300 meter from mining site is 36.79 Microgram per Cubic meter, in South direction: at 150 meter from mining site is 35.22 Microgram per Cubic meter, in South direction: at 300 meter from mining site is 34.99 Microgram per Cubic meter, in north direction: at 150 meter from mining site is 34.74 Microgram per Cubic meter, in SSE direction: at 150 meter from mining site is 34.54 Microgram per Cubic meter and will be within norms as per National Ambient Air Quality Standards. Study also includes predicted Noise incremental values and it ranges from 49.1 (day) dB (A) to 66.3 (Day) dB (A). The proposed mining location and study area falls under Zone III which is classified as moderate risk zone as per GSDMA. The general water table depth of study area falls between 16m to 10m BGL during pre-monsoon to post monsoon periods and mining will not intersect the Ground water table. During rainy season, the runoff from the mine follows the natural slope. Surface water quality is in general poor (Brackish to saline).Water requirement of the project is 20 KLD and will be availed from ground water for which Project proponents have obtained approval from CGWA for abstraction. Project proponent have proposed rainwater harvesting and total estimated area of the pit will be 5.07 Ha with ultimate depth of 6.5 m. Shallow pit will cater water storage of about 3,29,550 KL at the site which will be used for green belt development and dust suppression. Plantation during pre operational phase is 0.0 Ha which is proposed to the1.00 Ha during prerational phase and post mining at the end of mine life. The nearest habitation is more than 500 m away from the proposed project. During public hearing on 06/12/2013, issues related to the CSR, wash out of land adjacent to the proposed mining activities were raised and replied by the representative of the project proponent satisfactorily. After detailed discussion on various aspects regarding project, it was decided to recommend the project to SEIAA, Gujarat for grant of Environmental Clearance only after submission of the following.

1. Based on contours, details of flow of rainwater runoff meeting to the nearby water bodies showing no resistance to the natural flow pattern due to proposed mining activities.

2. Details of existence of blue bull in study area and project activities impeding/endangering habitation of the said species and proposed action plan to protect its habitation.

3. Letter from department of Geology and mining regarding no other mine exists in the 500 m radial distance from the boundary of the mine lease area.

Table Agenda Jaldeep Minerals Company, S.NO: 182, Vill: Panvi, Ta: Vallabhipur, Dist: Bhavnagar. This is an existing Dolomite (White Chalk) mining lease running since 1977 and spread over an area of 8.0938 Ha at S NO: 182 of village Panvi in Vallabhipur.This case was appraised in 213th SEAC meeting held on 17-10-2014 and it was decided to recommend for grant of Environmental Clearance to SEIAA on satisfactory submission of the following documents.

1. Approved mining scheme and progressive mine closure plan for the lease area/project.

2. Supplementary report on flora and found in the study area and management plan for Schedule I species found in the study area.

3. Proposal to set up adequate sanitary facilitites at the site for employees working over there and to submit photographs.

Page 5: Minutes of the 227th meeting

 

Page 5 of 26  

4. Detailed storm water management plan. Project proponent submitted aforesaid details on 12 December 2014 which includes Mining scheme and mine closure plan for the lease area approved by Commissionerate of Geology and Mining, Supplementary report on flora and fauna in the study area which states that few Schedule I species were noted however all those species were of very common ocurrence. As per the ecological study, no schedule I species are found in the 1 Km area around the project site.Project proponents have proposed three toilets as part of sanitation facility for mine workers ( one for female workers and two for male workers). As part of storm water management plan, drains or berms will be provided along the periphery of the lease area to arrest inflow of surface run off in the quarry area and will be diverted to the nearby storm water drain.Garland drain is proposed for overburden/reject dumps (if any)to prevent its washout which can pollute nearby water bodies. In the meeting of SEAC held on 10 February 2015,after going through reply of the project proponents, committee found it satisfactory and decided to recommend grant of Environmental Clearance to SEIAA FIRST HEARING CASES : 3.Shri Janakkumar Kantilal Sadhu, S NO: 328/P, Taiyabpura, Kapadvsnj Kheda. 4.Imperial Minng Syndicate, S NO: 80 P, Navadra, Kalyanpur, Devbhumi Dwarka 5.Eklera China Clay Mine(Eklera Trading Co.),S NO:592/1, &4,593,594/1, &594/2,595, 598, 599 & 621,Eklera, Idar, Sabarkantha. 6.Eklera China Clay Works, S NO:10, 11(P), 12(P), 13(P), 591(P), 600- 601, 602(P), 603, 606, 608-20, 621(P),622,625,627,630 & part of river bed,Eklera Idar, Sabarkantha. Project proponents at serial no: 3,4,5,6 (As above) remained absent and committee decided to consider their proposal in one of the upcoming SEAC meeting. 7. Bhogat Bauxite Mines (Sandeep Abrasives Industries), (Lease area: 29.7749 Ha) S. NO: 360/P of Bhogat, Village:Kalyanpur, Devbhumi Dwarka. It is a bauxite mining project with(Lease area: 29.7749 Ha) and located at S. NO: 360/P of Bhogat, Village:Kalyanpur, Devbhumi Dwarka. Proposed production is 1,68,620 TPA of Bauxite. The proposal falls in project / activity no. 1(a) of the Schedule of the EIA Notification, 2006 and as the lease area is less than 50 Hectares, it falls under category B. The technical presentation of the project included introduction & background of the company, details of lease, location details and linkages, project description,photographs of site,Co-ordinates of mine, Coastal Zone Distance ,Environmental Sensitivity, Land use of study area, Land use break up,Surface geological plan,previous production details,yearwise development plan,details of reclamation, conceptual plan and section, equiment details, afforestation plan, proposed terms of referecne (TOR) etc. After deliberation on various aspects of the project, following additional TOR was prescribed for the EIA study to be done considering 10 Km radius from the periphery of the mine lease area.

Page 6: Minutes of the 227th meeting

 

Page 6 of 26  

1. Project site specific details such as distance of the project site from nearest (1) Village (2)Water Body : River / Creek / Nallah / Lake / Pond / Reservoir / Canal (3) National Highway (4) State Highway (5) Railway line (6) Heritage site (7) National Park / Wild Life Sanctuary /Reserve Forest / Protected Forest shall be included in the rapid EIA report to be prepared covering one season (other than monsoon) data. A map indicating the aerial distance of the lease area from these entities.

2. Distance of nearby mining lease areas from the periphery of the proposed project including a map covering distance of 1 Km from the periphery of the proposed project. In case of no mining lease areas existing in the 500 m periphery of the proposed project, certificate of the concerned geologist in this regard.

3. Copies of all requisite permissions including permissions from District Collector, Commissioner of Geology & Mining, Indian Bureau of Mines, GPCB etc. to be incorporated.

4. Land use plan of the mine lease area should be prepared to encompass pre-operational, operational and post operational phases.

5. Land use of the study area delineating forest area, agricultural area, waste land, grazing land,human settlements, water bodies etc. based on satellite imagery.

6. Approved mining plan including progressive mine closure plan shall be provided with EIA report. Letter of approval of IBM shall also be incorporated.

7. Details of peripheral drains to arrest the inflow of surface runoff in the quarry area and garland drains for arresting run off from the overburden / reject dumps. Specific measures to ensure that contaminated runoff from mine terrain will not lead to the rivers / natural drains / adjoining farms, in any case.

8. Air quality modeling should be carried out for prediction of impact of the project on the air quality of the area. It should also take in to account the impact of movement of vehicles for transportation of mineral. The details of the model used and the input parameters used for modeling should be provided. The air quality contours may be shown on the location map clearly indicating the location of site, location of sensitive receptors, if any, and habitation.

9. Impacts of blasting with respect to noise, vibration, fly rock and air pollution on the receptors including the habitation and measures to reduce impacts of blasting.

10. Significance of dust fall and details of mitigation measures for SPM control at mine site. 11. Impact due to fugitive emissions including that because of transportation activities and

the mitigation measures thereof need to be elaborated. 12. Impact on local transport infrastructure due to the project. Projected increase in truck

traffic as a result of the project in the present road network and whether it is capable of handling the increased load. Arrangement for improving the infrastructure like road etc. if any should be covered.

13. Dust suppression measures & control measures at worker level & proposed PPE to workers.

14. Detailed overburden and mine rejects management plan. 15. Detailed write up and drawing of mine closure plan. Water reservoirs to be constructed

after closure of mine should be in proper shape and having proper fencing. 16. Details on back filling system of the exhausted mine. Details on compaction of back

filling layer. 17. The reclamation plan, post mine land use and progressive green belt development plan

along with year wise financial outlay shall be included. 18. The water requirement for the project along with the source and availability as well as

necessary permissions from the competent authority for drawl of groundwater, if any. 19. Details of the water conservation measures proposed to be adopted in the project

should be highlighted. 20. Information on site elevation, working depth, ground water table should be provided.

Based on actual monitored data, it may clearly be shown whether working will intersect ground water. In case of intersection of ground water with working level, a detailed hydro geological study should be undertaken and report should be furnished.

Page 7: Minutes of the 227th meeting

 

Page 7 of 26  

21. Check list of flora and fauna in the study area and impacts of the project on the same along with mitigation measures.

22. Occupational health impact of the project especially during manual operations in the work area and the mitigation measures proposed along with the commitment of the project proponent for implementation of the mitigation measures.

23. Details of preventive measures to be taken for non occurrence of any fatal or non fatal accidents.

24. Plan for periodic medical examination of the mine workers. 25. Details of the basic amenities, infrastructure facilities, PPEs etc. to be provided to the

mine workers. 26. Detailed Mitigation Plan and the Environmental Management Plan with respect to all

likely impacts of the project activities. Total capital cost and recurring cost/annum earmarked for environment pollution control measures.

27. An action plan showing list of the activities along with the fund allocation shall be submitted based on the socio-economic profile of the surrounding villages and need base field assessment.

28. Details regarding existing green belt development activity carried out during past years. A detailed future greenbelt development plan including type of species, number of trees, budgetary allocation, etc.

29. Details of fencing, tree plantation done in the existing mined area. 30. The questionnaire for environmental appraisal of mining projects as devised earlier by

the Ministry of the Environment, Forest and Climate Change should be filled in and submitted.

31. Any litigation pending against the project and / or any direction / order passed by any Courtof Law against the project, if so, details thereof.

32. A tabular chart for the issues raised and addressed during public hearing/consultation should be provided.

33. (a) Does the company have a well laid down Environment Policy approved by its Board ofDirectors? If so, it may be detailed in the EIA report. (b) Does the Environment Policy prescribe for standard operating process / procedures tobring into focus any infringement / deviation / violation of the environmental or forest norms /conditions ? If so, it may be detailed in the EIA.

34. What is the hierarchical system or administrative order of the company to deal with the environmental issues and for ensuring compliance with the EC conditions. Details of this system may be given.

35. Does the company have a system of reporting of non compliances / violations of environmental norms to the Board of Directors of the company and / or shareholders or stakeholders at large? This reporting mechanism should be detailed in the EIA Report.

36. Certificate of accreditation issued by the NABET, QCI to the environmental consultant should be incorporated in the EIA Report.

The draft EIA report also covering the above TOR shall be prepared and submitted to the GPCB for conducting the public hearing / consultation process as per the provisions of the EIA Notification, 2006. The project shall be appraised on receipt of the final EIA report. 8. Mamuara China Clay Mines (Survey No: 483 (P), Mine lease Area: 13 Ha),Village: Mamuara, Ta: Bhuj, Dist: Kachchh, Gujarat. The project proponent has applied Environmental Clearance in Form 1 for their China Clay Mines located at Survey No: 483 (P),Village: Mamuara, Ta: Bhuj, Dist: Kachchh, Gujarat.The mine lease area is 13.00 Ha. Proposed rate of mining is 2,00,000 TPA of China Clay. The proposal falls in project / activity no. 1(a) of the Schedule of the EIA Notification, 2006 and as the lease area is less than 50 Hectares, it falls under category B.

Page 8: Minutes of the 227th meeting

 

Page 8 of 26  

The technical presentation of the project included introduction, location ( Latitude : N23 16 30.4 and Longitude : E 69 51 14.5), Ultimate depth of mine 82 MSL, cost of project : 70 Lacs, accessibility of project, google image of site & surrounding, Surface plan, Geological plan and sections, conceptual plan and sections, Geological setting, details of mining and its reserve, proposed terms of reference, site photographs.etc. After detailed deliberation, considering the scale of project and as mining is proposed to be carried out by semi mechanised means and does not include blasting,it was categorized as B2 and following additional information was sought for appraisal of the project.

1. Project site specific details such as distance of the project site from the nearest (1) Village (2) Water Body : River / Creek / Nallah / Lake / Pond / Reservoir / Canal (3) National Highway(4) State Highway (5) Railway line (6) Heritage site (7) National Park / Wild Life Sanctuary /Reserve Forest / Protected Forest.(8) Distance of other lease areas for mining from the periphery of proposed mine.A map indicating the aerial distance of the lease area from these entities.

2. Distance of nearby mining lease areas from the periphery of the proposed project including a map covering distance of 1 Km from the periphery of the proposed project. In case of no mining lease areas existing in the 500 m periphery of the proposed project, certificate of the concerned geologist in this regard.

3. Copies of all requisite permissions including permissions from District Collector, Commissioner of Geology & Mining, Indian Bureau of Mines, GPCB etc.

4. Land use plan of the mine lease area should be prepared to encompass pre-operational, operational and post operational phases.

5. Land use of the study area delineating forest area, agriculture area, waste land, grazing land, human settlement, water bodies etc. based on satellite imagery.

6. Approved mining plan including progressive mine closure plan and shall be incorporated with letter of approval of IBM.

7. Details of peripheral drains to arrest the inflow of surface runoff in the quarry area and garland drains for arresting run off from the overburden / reject dumps. Specific measures to ensure that contaminated runoff from mine terrain will not lead to the rivers / natural drains / adjoining farms, in any case.

8. Technical justification for no requirement of blasting. Notarized undertaking stating that no blasting shall be carried out.

9. Impact due to fugitive emissions including that because of transportation activities and the mitigation measures thereof need to be elaborated.

10. Dust suppression measures & control measures at worker level & proposed PPE to workers.

11. Detailed overburden and mine rejects management plan. 12. Detailed write up and drawing of mine closure plan. Water reservoirs to be

constructed after closure of mine should be in proper shape and having proper fencing.

13. Details on back filling system of the exhausted mine. Details on compaction of back filling layer.

14. The reclamation plan, post mine land use and progressive green belt development plan along with year wise financial outlay shall be included.

15. The water requirement for the project along with the source and availability as well as necessary permissions from the competent authority for drawl of groundwater, if any.

16. Details of the water conservation measures proposed to be adopted in the project should be highlighted.

17. Information on site elevation, working depth, ground water table should be provided. Based on actual monitored data, it may clearly be shown whether working will intersect ground water.

Page 9: Minutes of the 227th meeting

 

Page 9 of 26  

18. Check list of flora and fauna in the study area and impacts of the project on the same along with mitigation measures.

19. Occupational health impact of the project especially during manual operations in the work area and the mitigation measures proposed along with the commitment of the project proponent for implementation of the mitigation measures.

20. Plan for periodic medical examination of the mine workers. 21. Details of the basic amenities, infrastructure facilities, PPEs etc. to be provided to the

mine workers. 22. Detailed Mitigation Plan and the Environmental Management Plan with respect to all

likely impacts of the project activities. Total capital cost and recurring cost/annum earmarked for environment pollution control measures.

23. An action plan showing list of the activities along with the fund allocation shall be submitted based on the socio-economic profile of the surrounding villages and need base field assessment.

24. Details regarding existing green belt development activity carried out during past years. A detailed future greenbelt development plan including type of species, number of trees, budgetary allocation, etc.

25. Details of fencing, tree plantation done in the existing mined area. 26. Any litigation pending against the project and / or any direction / order passed by any

Court of Law against the project, if so, details thereof. 27. (a) Does the company have a well laid down Environment Policy approved by its

Board of Directors? If so, it may be detailed. (b). Does the Environment Policy prescribe for standard operating process / procedures to bring into focus any infringement / deviation / violation of the environmental or forest norms /conditions ? If so, it may be detailed.

28. What is the hierarchical system or administrative order of the company to deal with the environmental issues and for ensuring compliance with the EC conditions. Details of this system may be given.

29. Does the company have a system of reporting of non compliances / violations of environmental norms to the Board of Directors of the company and / or shareholders or stakeholders at large? This reporting mechanism should be detailed. The project shall be appraised after submission of above cited additional details.

[9] M/s.Mamuara China Clay Mines (Survey No: 483 (P), Mine lease Area: 13 Ha), Village: Mamuara, Ta: Bhuj, Dist: Kachchh, Gujarat. The project proponent has applied Environmental Clearance in Form 1 for their China Clay Mines located at Survey No: 483 (P),Village: Mamuara, Ta: Bhuj, Dist: Kachchh, Gujarat.The mine lease area is 13.00 Ha. Proposed rate of mining is 2,00,000 TPA of China Clay. The proposal falls in project / activity no. 1(a) of the Schedule of the EIA Notification, 2006 and as the lease area is less than 50 Hectares, it falls under category B. The technical presentation of the project included introduction, location ( Latitude : N23 15 12.02 and Longitude : E 69 51 18.75), Ultimate depth of mine 90 MSL, cost of project : 82 Lacs, accessibility of project, google image of site & surrounding, Surface plan, Geological plan and sections, conceptual plan and sections, Geological setting, details of mining and its reserve, proposed terms of reference, site photographs.etc. After detailed deliberation, considering the scale of project and as mining is proposed to be carried out by semi mechanised means and does not include blasting, it was categorized as B2 and following additional information was sought for appraisal of the project.

1. Project site specific details such as distance of the project site from the nearest (1) Village (2) Water Body : River / Creek / Nallah / Lake / Pond / Reservoir / Canal (3) National Highway(4) State Highway (5) Railway line (6) Heritage site (7) National

Page 10: Minutes of the 227th meeting

 

Page 10 of 26  

Park / Wild Life Sanctuary /Reserve Forest / Protected Forest. A map indicating the aerial distance of the lease area from these entities.

2. Distance of nearby mining lease areas from the periphery of the proposed project including a map covering distance of 1 Km from the periphery of the proposed project. In case of no mining lease areas existing in the 500 m periphery of the proposed project, certificate of the concerned geologist in this regard.

3. Copies of all requisite permissions including permissions from District Collector, Commissioner of Geology & Mining, Indian Bureau of Mines, GPCB etc

4. Land use plan of the mine lease area should be prepared to encompass pre-operational, operational and post operational phases.

5. Land use of the study area delineating forest area, agriculture area, waste land, grazing land, human settlement, water bodies etc. based on satellite imagery.

6. Approved mining plan including progressive mine closure plan and shall be incorporated with letter of approval of IBM.

7. Details of peripheral drains to arrest the inflow of surface runoff in the quarry area and garland drains for arresting run off from the overburden / reject dumps. Specific measures to ensure that contaminated runoff from mine terrain will not lead to the rivers / natural drains / adjoining farms, in any case.

8. Technical justification for no requirement of blasting. Notarized undertaking stating that no blasting shall be carried out.

9. Impact due to fugitive emissions including that because of transportation activities and the mitigation measures thereof need to be elaborated.

10. Dust suppression measures & control measures at worker level & proposed PPE to workers.

11. Detailed overburden and mine rejects management plan. 12. Detailed write up and drawing of mine closure plan. Water reservoirs to be

constructed after closure of mine should be in proper shape and having proper fencing.

13. Details on back filling system of the exhausted mine. Details on compaction of back filling layer.

14. The reclamation plan, post mine land use and progressive green belt development plan along with year wise financial outlay shall be included.

15. The water requirement for the project along with the source and availability as well as necessary permissions from the competent authority for drawl of groundwater, if any.

16. Details of the water conservation measures proposed to be adopted in the project should be highlighted.

17. Information on site elevation, working depth, ground water table should be provided. Based on actual monitored data, it may clearly be shown whether working will intersect ground water.

18. Check list of flora and fauna in the study area and impacts of the project on the same along with mitigation measures.

19. Occupational health impact of the project especially during manual operations in the work area and the mitigation measures proposed along with the commitment of the project proponent for implementation of the mitigation measures.

20. Plan for periodic medical examination of the mine workers. 21. Details of the basic amenities, infrastructure facilities, PPEs etc. to be provided to the

mine workers. 22. Detailed Mitigation Plan and the Environmental Management Plan with respect to all

likely impacts of the project activities. Total capital cost and recurring cost/annum earmarked for environment pollution control measures.

23. An action plan showing list of the activities along with the fund allocation shall be submitted based on the socio-economic profile of the surrounding villages and need base field assessment.

Page 11: Minutes of the 227th meeting

 

Page 11 of 26  

24. Details regarding existing green belt development activity carried out during past years. A detailed future greenbelt development plan including type of species, number of trees, budgetary allocation, etc.

25. Details of fencing, tree plantation done in the existing mined area. 26. Any litigation pending against the project and / or any direction / order passed by any

Court of Law against the project, if so, details thereof. 27. (a) Does the company have a well laid down Environment Policy approved by its

Board of Directors? If so, it may be detailed. (b). Does the Environment Policy prescribe for standard operating process / procedures to bring into focus any infringement / deviation / violation of the environmental or forest norms /conditions ? If so, it may be detailed.

28. What is the hierarchical system or administrative order of the company to deal with the environmental issues and for ensuring compliance with the EC conditions. Details of this system may be given.

29. Does the company have a system of reporting of non compliances / violations of environmental norms to the Board of Directors of the company and / or shareholders or stakeholders at large? This reporting mechanism should be detailed. The project shall be appraised after submission of above cited additional details.

PROPOSALS RECEIVED FROM THE OFFICE OF C.G.M., GANDHINAGAR: Total 244 proposals received from the Office of the Commissioner, Geology and Mining, Gandhinagar were considered in the meeting. Cases of minor mineral mining projects, which have been received by the Committee through the Office of the Mining Commissioner, Gandhinagar, along with the information in Performa endorsed by the district Geologist / Asst. Geologists, were taken up in the meeting as tabulated below.

PROPOSALS RECEIVED FROM THE OFFICE OF C.G.M., GANDHINAGAR

1. 8 Proposals Dahod District

2. 1 Proposal Devbhumi Dwarka District

3. 53 Proposals Gir Somnath District

4. 1 Proposal Jamnagar District

5. 40 Proposals Junagadh District

6. 31 Proposals Kutch District

7. 29 Proposals Morbi District

8. 35 Proposals Panchmahal District

9. 11 Proposals Patan District

10. 18 Proposals Porbandar District

11. 17 Proposals Vadodara District

Details of proposals received from the office of the Commissioner, Geology and mining, Gandhinagar are as under. SAND MINING PROJECTS DISTRICT DAHOD

Page 12: Minutes of the 227th meeting

 

Page 12 of 26  

Sr. No

Name of Applicant

Lease Area in Hactare

Opp. to: Name

of River

Village Taluka Rate of Mining

1 Savaya Batukbhai Fatesinhbhai

00-50-00 S.No.53p,86

Ujjal River

Ratadia Devgadh Baria

Not mentioned

2 Ravindrabhai Parvatbhai Savaya

10-1-00 S.No.52,53 Ujjal River

Ratadia Devgadh Baria

Not mentioned

3 Ravindrabhai Parvatbhai Savaya

01-50-00 S.No.45,47 Panam Nadi

Ratadia Devgadh Baria

Not mentioned

4 Rameshchandra Mithabhai Vankar

01-35-13 S.No.156,155/1

Ujjal River

Singor Devgadh Baria

Not mentioned

5 Nayak Parvatsingh Bhurabhai

03-00-00 S.No.15,16,17

Ujjal River

Virol Devgadh Baria

Not mentioned

6 Narvatbhai Bhudhabhai Pateliya

00-50-00 S.No.65 Ujjal River

Abhlod Devgadh Baria

Not mentioned

BLACKTRAP MINING PROJECTS - DISTRICT DAHOD

Sr. No

Name of Applicant Lease Area in Hactare

Address of site

Village Taluk

a Rate of Mining

1 Shree Vitthakesh Construction

01-00-00 S.No.127/4 P Borvani Dahod 25000 TPA

2 Alakhnanda Stone & Quarry

03-00-00 S.No.88 P Amba Zhalod 3750 MT/Month

BLACKTRAP MININGP ROJECT - DISTRICT DEVBHUMIDWARKA Sr .

No.

Name of Applicant Lease

Area in Hactare

Address of site

Village Taluka Rate of Mining

1 Nitaben Vajubhai Parmar

01-00-00

S. No. 41/1

Premsar

Kalyanpur

3333 MT/Month

BLACKTRAP MINING PROJECTS DISTRICT GIR SOMNATH

Sr. No

Name of Applicant Lease Area in Hactare

Address of site

Village Taluk

a Rate of Mining

1 Bambhaniya Mohanbhai Bhagvanbhai

00-77-00 S. No. 25/P

Jaragali Una 750 MT/Month

2 Shree Pravinchandr Maganlal Pandat

01-00-00 S.No.30 P

Sanvav Una 36000 TPA

BUILDING LIME STONE PROJECTS DISTRICT GIR SOMNATH

Sr. No

Name of Applicant Lease Area in Hactare

Address of site

Village Taluka Rate of Mining

1 Ajitbhai Kumbhabhai Jadav

01-16-35 S. No. 746 paiki 2

Amodra Una 24000 TPA

2 Devabhai Dayabhai Sarvaiya

01-00-00 S. No. 40/2 paiki 1/1

Bhuvavada

Sutrapada

18000 TPA

3 Bhikhabhai Naranbhai Barad

01-00-00 S. No. 334 paiki 1

Sindhaj Kodinar 500 MT/Month

4 Building Lime Stone 00-72-94 S. No. 475/1 p una Una 90

Page 13: Minutes of the 227th meeting

 

Page 13 of 26  

Sr. No

Name of Applicant Lease Area in Hactare

Address of site

Village Taluka Rate of Mining

of Himatgar Mohangar Others

MT/Month

5 Hasmukhbhai Ramshibhai Bhatiya

01-00-00 Moti Moli

Una 45 MT/Month

6 Ramjibhai Bhikhabhai Makwana

01-00-00 S. No. 127 paiki 2 & 4

Damasa Una 800 MT/Month

7 Bachubhai Naranbhai Bhaliya

01-00-00 S. No. 22 paiki Shiloj Una 800 MT/Month

8 Jayaben Mohanbhai Chauhan

01-00-00 S. No. 3/P4, 3/P4/P1

Nathal Una 500 MT/Month

9 Kesubhai Jivabhai Movaliya

01-00-00 S. No. 123/P-1 Dolasa Kodinar 500 MT/Month

10 Bhikhabhai Arjanbhai Bambhaniya

01-00-00

S. No. 31-P-1/ P-2, 31/P-2/P2, 31/P-3/P-2

Nathal Una 500 MT/Month

11 Lakhuben Nanji Sampat

01-00-00 S. No. 199 paiki

Garal Una 500 MT/Month

12 Ajitbhai Kumbhabhai Jadav

01-00-00 S. No. 746 /P 2

Amodra Una 500 MT/Month

13 Bhagvanbhai Varjangbhai Vaja

00-80-00 S. No. 28 Ankolali Una 400 MT/Month

14 Nanubhai Kanabhai Vaja

01-00-00 S. No. 31/1/P4 Faluka Una 500 MT/Month

15 Dipeshkumar Keshavbhai Solanki

01-00-00 S. No. 15 P-2/P-2

Bhebha Una 500 MT/Month

16 Sajanbhai Lilabhai Mer

01-00-00 S. No. 75 P Shiloj Una 500 MT/Month

17 Zeshingbhai Balubhai Zankar

01-00-00 S. No. 65/P-1 Khan Una 500 MT/Month

18 Rameshbhai Ukabhai Chauhan

01-00-00 S. No. 645/P1 Una Una 500 MT/Month

19 Sambhai Motigar Goswami

00-80-94 S. No. 9/P1 paiki

Ratad Una 400 MT/Month

20 HasmukhTulsidas Hariyani

00-80-94 S. No. 23 paiki 1

Undari Una 400 MT/Month

21 Rambhuben Bhikhabhai Makvana

00-52-46 S. No. 116/2 paiki

Khapat Una 300 MT/Month

22 Thummar Arjanbhai haribhai

00-86-00 S. No. 50/P1/P3

Kansari Una 400 MT/Month

23 Kalubhai Lakhmanbhai Damaniya

01-00-00 S. No. 26 paiki Shiloj Una 500 MT/Month

24 Palabhai Bhagvanbhai Chauhan

01-00-00 S. No. 102/2 Varsingpur

Una 500 MT/Month

25 Ashvinbhai Naranbhai Barad

01-05-00 S. No. 117/P3/P1/P3 &117/P3/P1/P4

Indroi Veraval 400 MT/Month

Page 14: Minutes of the 227th meeting

 

Page 14 of 26  

Sr. No

Name of Applicant Lease Area in Hactare

Address of site

Village Taluka Rate of Mining

26 Dharnantabhai Naranbhai Postariya

01-00-00 S. No. 340 paiki

Delvada Una 500 MT/Month

27 Arifbhai Usmanbhai Sorthiya

01-00-00 S. No. 648/P-4 P-2

Una Una 705 MT/Month

28 Subhanbhai Jamalbhai Kureshi

01-00-00 S. No. 192/P-1 Una Una 705 MT/Month

29 Ghanchi Yusuf mahamad

01-00-00 S. No. 100/P 10, 100/P-13

Una Una 705 MT/Month

30 Bhaveshkumar Hiralal Solanki

00-60-70 S. No. 93 paiki 2

Damasa Una 300 MT/Month

31 Yasinbhai Y Sorathiya & Shahidbhai G Vankot

01-00-00 S. No. 65/P3/P2, 64/P1/P2

Nathal Una 500 MT/Month

32 Bhaveshkumar Hiralal Solanki

00-60-70 S. No. 93 paiki 2

Damasa Una 300 MT/Month

33 Yasinbhai Y Sorathiya & Shahidbhai G Vankot

01-00-00 S. No. 65/P3/P2, 64/P1/P2

Nathal Una 500 MT/Month

34 Shree Bhagvanbhai Nondhanbhai Jadav

01-00-00 S.No.23/P 2 Bhebha Una 24000 TPA

35 Maheshbhai Rambhai Vala

01-00-00 S.No.118 P1 & 2

Bhiyal Una 800 MT/Month

36 Shree Chandubhai Naranbhai Barad

00-80-94 S.No.76 P2 Varshing-pur

Una 24000 TPA

37 Shree Vajshibhai Devashibhai Kothiya

01-00-00 S.No.106/1 P Umej Una 24000 TPA

38 Dineshbhai Bachubhai Vala

01-00-00 S.No.405 P Bodidar Una 800 MT/Month

39 Samatbhai K. Bambhaniya

01-00-00 S.No.13p 1/1 Nathad Una 90000 TPA

40 Rambhai Punjabhai Ram

01-00-00 S.No.200 p.1 Kanakbarda

Una 75000 TPA

41 Raiyabhai D. Kamaliya

01-00-00 S.No.93 P. Siloj Una 70000 TPA

42 Pravinbhai Varsingbhai Dodiya

01-00-00 S.No.54/2/1/2P &54/2/2p

Undari Una 35000 TPA

43 Shri Kalubhai Bambhaniya

01-00-00 S.No.191/p.1 Undari Una 35000 TPA

44 Shri Arashibhai Karashanbhai Pamak

01-00-00 S.No.98/p1/p2,99/2p

Mota-Desar

Una 50000 TPA

45 Dilipbhai Narsinhbhai Dobariya

01-00-00 S.No.832 P Amodra Una 24000 TPA

46 Veluben Rambhai Solanki

01-00-00 S.No.509 P Amodra Una 85000 TPA

47 Shri Babubhai Punabhai Pamak

01-00-00 S.No.47/1p1.p Una Una 500000 TPA

48 Shri Gordhanbhai Veljibhai Ramoliya

01-00-00 S.No.19/1p Jasadhar

Talala 35000 TPA

Page 15: Minutes of the 227th meeting

 

Page 15 of 26  

BUILDING LIME STONE MINING PROJECTS DISTRICT GIR SOMNATH

Sr No

Name of Applicant Lease

Area in Hactare

Address of site

Village Taluka Rate of Mining

1 Shri Laxmanbhai Jivabhai Mori

04-92-71 S.No.40/2 P3,41/P5,40/3P1

Lumbha Veraval 36000 TPA

2 Valjibhai Karshanbhai Makwana

01-00-00 S.No.122/P1,122/P2/P2/P2

Bhiyal Gir Gadhda

5000 TPA

3 Dhirajlal Panchhanbhai Vachhani

04-00-00 S.No.49 P Unadari Una 36000 TPA

SAND MINING PROJECTS DISTRICT JAMNAGAR Sr. No. Name of Applicant

Lease Area in Hactare

Name of River

Village Taluka Rate of Mining

1 Batukbhai Vejabhai Toyata

00-95-00 Aji Meghpar Jodiya 15000 MT/M

BLACKTRAP MINING PROJECTS DISTRICT JUNAGADH Sr. No

Name of Applicant Lease

Area in Hactare

Address of site

Village Taluka Rate of Mining

1 Baba Stone Crusher (Nebhabhai Surabhai Divranla)

01-00-00 S.No.202 P

Ravani Vanthali 36000 TPA

2 Sreeji Stone Crusher (Haresh kumar Bhimshibhai Solanki)

01-00-00 S.No.202 P

Ravani Vanthali 36000 TPA

3 Manthan Quarry Works 01-00-00 S.No.77 P 1

Ghantiya Vanthali 1500 MT/Month

4 Jagadhishbhai Devshibhai Solanki

01-00-00 S.No.227/p Pvt. Land

Kadaya Madiya Hatina

68000 TPA

5 Tusharbhai Karsanbhai Gor 01-00-00 S.No.77 P 1

Ghantiya Vanthali 1500 MT/Month

6 Manthan Quarry Works (Tushar K. Gor)

01-00-00 S.No.77 P 1

Ghantiya Vanthali 1500 MT/Month

7 Sutreja Stone Crusher (Desurbhai Nathubhai Sutreja)

00-80-94 S.No.38/2 Ishapur Junagadh

24000 TPA

8 Bharatkumar Jthabhai Ladani

01-21-41 S.No.44/1 &45/1P

Gelana Keshod 36000 TPA

9 Jitubhai Nathabhai Sutariya 00-80-94 S.No.97/1/P

Mendpara

Bhesan 12000 TPA

10 Hardasbhai Rambhai Solanki

01-00-00 S.No.6/P Kadaya Maliya Hatina

60000 TPA

11 Aebhabhai Chanabhai 01-00-00 S.No.202 Ravani Vanthali 500

Page 16: Minutes of the 227th meeting

 

Page 16 of 26  

Sr. No

Name of Applicant Lease

Area in Hactare

Address of site

Village Taluka Rate of Mining

Keshavala P Pvt. Land

MT/Month

12 Nebhabhai Sidibhai Antroliya

01-00-00 S.No.202 P

Ravani Vanthali 500 MT/Month

BUILDING LIME STONE MINING PROJECTS DISTRICT JUNAGADH Sr. No.

Name of Applicant Lease Area in Hactare

Address of site Village Taluka Rate of Mining

1 Lakhmanbhai Gangabhai Parmar

01-00-00 Kundhi Una 20000 TPA

2 Parbatbhai Rajshibhai Jadeja

01-00-00 Siloj Una 20000 TPA

3 Vejabhai Ranabhai jadeja 01-00-00 S. No. 595 P4/P2 & 596 P3 596/P1

Chorwad Maliya Hatina

500 MT/Month

4 Ranabhai B Dasa & Kanabhai N Parmar

00-93-70 S. No. 605/P2 Chorwad Maliya Hatina

500 MT/Month

5 Vejabhai R jadeja & Vikrambhai C Bhutiya

01-00-00 S. No. 321/1/P2 Arena Mangrol 500 MT/Month

6 Rambhai Bhojabhai Kuchadiya

01-00-00 S. No. 20/P1 Mangrol Mangrol 500 MT/Month

7 Hamirbhai R Muliyashiya & Nagajanbhai R jadeja

01-00-00 S. No. 378/1, 379/1/P-2

Mangrol Mangrol 500 MT/Month

8 Parvin Singh Ram Sinh Rathod & Prabatbhai Hardasbhai Modhvadiya

01-00-00 S.No.39 P2 Khan Una 10000 TPA

9 Shree Rajeshbhai Naranbhai & Bharatbhai Hirabhai Chudasma

02-00-00 S.No.426,617,618

Shil Mangrol 24000 TPA

10 Shree Manojbhai Ukabhai Keshwala

00-37-43 S.No.78/1p-2 Kukasavada

Maliya Hatina

3000 MT/Month

11 Merubhai Devabhai Kadachha

01-00-00 S.No.421/p-1 pvt. Land

Shil Mangrol 85000 TPA

12 Jayntibhai Ramjibhai Thakkar

01-00-00 S.No.607/p.1 pvt. Land

Chorwad Madiya Hatina

50000 TPA

13 Rajeshbhai Bhayabhai Ratiya

00-40-47 S.No.68 P1 Plasava Junagadh

12000 TPA

14 Dilipbhai Premjibhai Kodavala

01-00-00 S.No.59/P1/P2 & 59/P1/P3

Kukasavada

Maliya Hatina

36000 TPA

15 Jayntibhai Ramabhai Kamaliya

01-00-00 S.No.420/P1,420/P2

Shil Mangrol 24000 TPA

16 Jerambhai Bhurabhai Hirpara

01-61-88 S.No.191 P 1/26 Divasa Mangrol 1000 MT/Month

17 Keshubhai Arshibhai Vadar

01-00-00 S.No.422 P Shil Mangrol 24000 TPA

18 Rambhai J. Parmar 01-00-00 S.No.475/2,475/3,475/4,482 P

Chorwad Maliya 850 MT/M

19 Devendrakumar Bhikhabhai odedra

01-00-00 S.No.326 P Pvt. Land

Sheriyaj Mangrol 300 MT/Month

Page 17: Minutes of the 227th meeting

 

Page 17 of 26  

Sr. No.

Name of Applicant Lease Area in Hactare

Address of site Village Taluka Rate of Mining

20 Star Construction (Sabirbhai A. Duravesh)

01-00-00 S.No.174/2/p.1,174/1,174/2/p.1.p.1,158/2

Shapur Mangrol 350 MT/M

SAND MINING PROJECT DISTRICT JUNAGADH

Sr. No.

Name of Applicant Lease Area in Hactare

Opp. to: Name

of River

Village Taluka Rate of Mining

1 Devanandbhai Bhikhabhai Zala

01-00-00 Uben Vadhavi Junagadh

800 MT/Month

2 Pareshbhai Bhimjibhai Dobaria

01-50-00 S.No.304,335,336/2

Ojat Bagdu Junagadh

5000 TPA

3 Devrakhibhai Rukhadbhai Rabari

04-00-00 Ozat Shapur Vanthali 1000000 TPA

4 Shardulbhai Ravatbhai Chandrad

09-00-00 Ozat Prabhatpur

Junagadh

3000 MT/Month

5 Shardulbhai Ravatgbhai Chandrad

04-00-00 Ozat Rameshvar

Junagadh

1500 MT/Month

SANDSTONE MINING PROJECTS DISTRICT JUNAGADH

Sr. No.

Name of Applicant

Lease Area in Hactare

Address of site

Village Taluka Rate of Mining

1 Dilipbhai Premjibhai Kodavala

00-80-94 S. No. 86 paiki 1 paiki1

Dungarpur Junagadh 750 MT/Month

2 Dhanjibhai Bhikhabhai Makwana

00-80-94 S. No. 86 paiki 2

Dungarpur Junagadh 750 MT/Month

3 Rajeshkumar Natvarlal Bhojani

01-00-00 S. No. 142 paiki 1 paki 2

Vijapur Junagadh 750 MT/Month

BENTONITE MINING PROJECTS DISTRICT KUTCH

Sr. No.

Name of Applicant Lease

Area in Hactare

Address of site

Village Taluka Rate of Mining

1. Kesha Kheraj Harijan (Ashapura International Ltd.

03.00.00 S. No. 164 Miyani Abdasa 1500 MT/Month

2. Ashapura International Ltd.

00.83.00 Traverse Paiki Miyani Abdasa 400 MT/Month

3. Ashapura International Ltd.

08.71.30 S. No. 305/1 & 306/1

Chiyasar Abdasa 3300 MT/Month

4. Ashapura International Ltd.

01.00.00 S. No. 343 Vandh Mandvi 500 MT/Month

Page 18: Minutes of the 227th meeting

 

Page 18 of 26  

5. Ashapura International Ltd.

02.00.00 S. No. 95 Roha Sumri

Nakhtrana 2000 MT/Month

6. Rupsangji Samji Payar (AshaPura International Ltd.)

03.77.80 S. No. 163 Travers Paiki

Miyani Abdasa 1500 MT/Month

7. Ashapura Minechem Ind. 04.85.00 S. No. 65 Hamla Mandvi 1800 MT/Month

8. Manori Investement and Trading Company Pvt. Ltd.

02.85.30 S. No. 418/1 Paiki

Vandh Mandvi 1000 MT/Month

9. Ashapura Minechem Ind. 02.51.00 S. No. 418 Paiki

Vandh Mandvi 1000 MT/Month

10. Ashapura Minechem Ind. 02.64.08 Traverse Paiki Nundhatad

Abdasa 1000 MT/Month

11. Ashapura Minechem Ind. 01.23.42 70 Paiki Hamla Mandvi 600 MT/Month

12. Manali Mines 01.00.00 S. No. 170/2 Paiky

Sherdi Mandvi 1250 MT/Month

13. Manali Mines 01.00.00 S. No. 183 Paiki

Hamla Mandvi 1250 MT/Month

14. Ashapura International Ltd.

01.00.00 S. No.175 Paiki

Sherdi Mandvi 500 MT/Month

15. Ashapura International Ltd.

07.82.82 S. No.Traversh Paiki

Laxmipar Nakhtrana 1700 MT/Month

16. Ashapura Minechem Ind. 03.04.53 S. No. 343 Paiki

Vandh Mandvi 1250 MT/Month

17. Ashapura Minechem Ind. 01.94.25 S. No. 346 Vandh Mandvi 900 MT/Month

18. Ashapura Minechem Ind. 09.99.99 Traversh Paiki Laxmipar Nakhtrana 1700 MT/Month

19. Ashapura Minechem Ind. 04.17.84 S. No. 296 Pundi Mandvi 800 MT/Month

20. Ashapura Minechem Ind. 04.73.69 S. No.23 Traversh Paiki

Kandhay Abdasa 850 MT/Month

21. Ashapura Minechem Ind. 04.70.76 S. No. 23,24,36/1,37 Traversh Paiki

Kandhay Abdasa 850 MT/Month

22. Arlington Investment & Trading Company Pvt. Ltd.

01.75.00 S. No. 418 Khangi Paiki

Vandh Mandvi 1500 MT/Month

23. Kantilal R. Parmar (Ashapura International Ltd.)

01.00.00 S. No. 54 Paiki Denma Lakhpat 1000 MT/Month

24. Ashapura Minechem Ind. 05.07.14 Traverse Paiki Laxmipar Nakhtrana 1700 MT/Month

25. Kalubha Rupubha Jadeja 1.02.18 S. No. - 243/P2

Vandh Mandvi 70 Pr MT

26. Ashapura Minechem Ind. 01.33.29 S. No. 280 Vandh Mandvi 600 MT/Month

27. Ashapura Minechem Ind. 07.00.00 Traverse Paiki Laxmipar Nakhtrana 2500 MT/Month

28. Arlington Investment & 01.00.30 S. No. 183 Hamla Mandvi 1500

Page 19: Minutes of the 227th meeting

 

Page 19 of 26  

Trading Company Pvt. Ltd.

Khangi Paiki MT/Month

29. Ashapura Minechem Ind. 09.23.73 Traverse Paiki Laxmipar-2

Nakhtrana 3300 MT/Month

30. Riddhi Siddhi Minerals 02-00-00 S.No.175 Nani Tumbidi

Mundra 1500 MT/Month

31. Dhanji Narsi Harijan 10-00-00 S.No.128 P 47 Radhenjar Abdasa 6900 MT/M

BLACKTRAP MINING PTOJECTS DISTRICT MORBI

Sr. No

Name of Applicant Lease

Area in Hactare

Address of site Village Taluk

a Rate of Mining

1 Uma Stone Product (Sureshgiri Manhargiri Gosai)

01-25-00 Pvt. S. No. 163 Paiki 1

Sapakda

Halvad

2083 MT/Month

2 Khangarsinh Kathubha Zala

03-02-72 S. No. 158/1/1 paiki

Lilapur Morbi 9000 MT/Month

3 Hasmukhbhai Jamnadas Thakkar

04-29-85 S. No. 158/1 paiki

Lilapur Morbi 8000 MT/Month

4 Valjibhai Ravjibhai Vaghela

03-85-68 S. No. 158/1/1 paiki

Lilapur Morbi 8000 MT/Month

BUILDING LIME STONE MINING PTOJECTS DISTRICT MORBI

Sr. No

Name of Applicant Lease

Area in Hactare

Address of site Village Taluka Rate of Mining

1 Rajabhai Parbatbhai Parmar

01-67-95 S. No. 147 / P1 P1 Bhimguda Wankaner

18000 TPA

2 Parmar Rambhai Devabhai 01-78-06 S. No. 140 Paiky 2 Rajasthali Wankaner 10000 TPA3 Devjibhai Harjibhai 01-14-32 S. No. 139 Paiky 1 Rajasthali Wankaner 12000 TPASAND MINING PROJECTS DISTRICT MORBI Sr. No

Name of Applicant Lease

Area in Hactare

Name of River

VillageTaluk

a Rate of Mining

1 Bavarva Bhavesh Sureshbhai

01-37-00 Ghodadhroi Zinkiyali

Morbi 500 MT/Month

SANDSTONE MINING PROJECTS DISTRICT MORBI Sr. No

Name of Applicant Lease Area in Hactare

Address of site

Village Taluka Rate of Mining

1 Raydebhai Mulubhai Khistariya

02-00-00 Govt. S. No. 136/1 Paiki 1

Maktanpar

Wankaner

18000 TPA

2 Mrudulaben M. Dudharejiya

01-78-06 Private S. No. 126 Paiky 1

Vardusar Wankaner

15000 TPA

3 Kanubhai Keshavbhai Hirpara

01-98-30 Private S. No. 56 Paiky 1

Jamsar Wankaner

15000 TPA

4 Keshavbhai Ghelabhai 01-40-00 Govt. S. No. Nagalpur Wankan 1250

Page 20: Minutes of the 227th meeting

 

Page 20 of 26  

Sr. No

Name of Applicant Lease Area in Hactare

Address of site

Village Taluka Rate of Mining

Parmar 88 Paiki er MT/Month

5 Chanabhai Mandanbhai Odedara

01-46-62 Govt. S. No. 88/1 Paiki

Nagalpur Wankaner

1250 MT/Month

6 Raydebhai Mulubhai Khistariya

02-73-00 Govt. S. No. 133/1 Paiki

Anandpar

Wankaner

1916 MT/Month

7 Lilabhai Nagajanbhai Jadeja

03-35-00 Govt. S. No. 80/3 Paiki

Jamsar Wankaner

2500 MT/Month

8 Kanjiya Chaturbhai Karamshibhai & Dabhi Bharatbhai Nathabhai

02-37-24 Pvt. S. No. 82/1 Paiki

Anandpar

Wankaner

1666 MT/Month

9 Jignesh Kana Odedara 01-48-00 Govt. S. No. 88/1 Paiki

Nagalpur Wankaner

1250 MT/Month

10 Singarkhiya Parvatiben Bharatbhai

03-00-00 Govt. S. No. 133 Paiki 1

Anandpar

Wankaner

2083 MT/Month

11 Alkesha Navin Odedara 03-00-00 Govt. S. No. 86/4/1Paiki

Sultanpar

Wankaner

2083 MT/Month

12 Alkesha Navin Odedara 02-70-00 Govt. S. No. 87/1 Paiki

Paddhara

Wankaner

2083 MT/Month

13 Mayurbhai Virambhai Karavadra

04-83-00 Govt. S. No. 133/1 Paiki

Anandpar

Wankaner

3750 MT/Month

14 Chanabhai Mandanbhai Odedara

04-90-00 Govt. S. No. 80/3 Paiki

Jamsar Wankaner

3750 MT/Month

15 Rameshbhai Chanabhai Odedara

04-90-00 Govt. S. No. 80/3 Paiki

Jamsar Wankaner

3750 MT/Month

16 Tejas Dineshchandra Bhatt

03-00-00 Govt. S. No. 133 Paiki

Anandpar

Wankaner

2083 MT/Month

17 Hathiyabhai Parbatbhai parmar

01-77-60 Govt. S. No. 88 Paiki

Nagalpur Wankaner

1500 MT/Month

18 Navghan Lilabhai dasa 03-00-00 Govt. S. No. 86/4/1Paiki

Sultanpar

Wankaner

2083 MT/Month

19 Alkesha Navin Odedara 03-00-00 Govt. S. No. 86/4/1Paiki

Sultanpar

Wankaner

2083 MT/Month

20 Alkesha Navin Odedara 01-97-00 Govt. S. No. 87/1 Paiki

Paddhara

Wankaner

1500 MT/Month

21 Rameshbhai Chanabhai Odedara

04-90-00 Govt. S. No. 88/1 Paiki

Nagalpur Wankaner

3750 MT/Month

SAND MINING PROJECTS- DISTRICT PANCHMAHAL Sr. No

Name of Applicant

Lease Area in Hactare

Opp. to: Name

of River

Village Taluka Rate of Mining

1 Vinodbhai Bharatsinh Baria

01-00-00 Panam Chavad Godhara 1500 MT/Month

2 Sureshbhai Ranjansinh Patel

02-00-00 Panam Rampur Morwa Hadaf

1500 MT/Month

3 Sureahbhai Rajansinh Patel

00-45-00 Panam Rampur Morwa Hadaf

1500 MT/Month

4 Sureahbhai 01-75-00 Panam Rampur Morwa 1500

Page 21: Minutes of the 227th meeting

 

Page 21 of 26  

Sr. No

Name of Applicant

Lease Area in Hactare

Opp. to: Name

of River

Village Taluka Rate of Mining

Rajansinh Patel Hadaf MT/Month

5 Ranjitsinh Ratansinh Bariya

00-50-00 Panam Rampur Morwa Hadaf

1500 MT/Month

6 Ranjitsinh Ratansinh Bariya

01-00-00 Panam Rampur Morwa Hadaf

1500 MT/Month

7 Vinodbhai Bharatsinh Baria

00-70-00 Panam Chavad Godhara

833.33 MT/M

8 Jayesh Kanaiyalal Lalwani

02-50-00 Karad Varasada Halol 2500 MT/M

9 Dineshkumar T. Tanwani

02-25-00 Karad Varasada Halol 2500 MT/M

10 Rukhiben R Baria

00-64-00 S. No. 12 Panam Chavad Godhra 1500 MT/Month

11 Somabhai J Baria

02-00-00 S. No. 200/7

Panam Naglod Morwa Hadaf

2000 MT/Month

12 Bhupatsinh B Baria

01-00-00 S. No. 588 Panam Dhamnod Shahera 3000 MT/Month

13

Dhamnod Muwadi Majur Kamdar Sahkari Mandali

02-00-00 S. No. 589 Panam Dhamnod Shahera 3000 MT/Month

14 Somabhai J Baria

01-00-00 S. No. 158,159

Panam Naglod Morwa Hadaf

2000 MT/Month

15 Hardik S. Parikh 01-75-00 S. No. 136,139

Panam Rampur Morwa Hadaf

1000 MT/Month

16 Jalamsinh P Makwana

06-00-00

S. No. 349, 362, 382,383, 384,386,387,391,396,399

Panam Rasulpur Morwa Hadaf

5000 MT/Month

17 Arvindbhai S Baria

02-00-00 S. No. 125,152

Panam Saliya Morwa Hadaf

1500 MT/Month

18 Sankarbhai B Patel

01-68-00 S. No. 125 Panam Saliya Morwa Hadaf

3500 MT/Month

19 Anilkumar Manubhai Patel

00-60-00 S. No. 64 Panam Saliya Morwa Hadaf

800 MT/Month

20 Jasodaben Jalamsinh Makwana

03-00-00 S. No. 505 to 508,399 to 404

Panam Rasulpur Morwa Hadaf

5000 MT/Month

21

Nagai Reti Suppliers (Sandeepbhai K Patil)

03-50-00 S. No. 602,603

Goma Simaliya Ghoghmba

8000 MT/Month

22 Sandeepbhai K 03-00-00 S. No. Goma Simaliya Ghoghm 8000

Page 22: Minutes of the 227th meeting

 

Page 22 of 26  

Sr. No

Name of Applicant

Lease Area in Hactare

Opp. to: Name

of River

Village Taluka Rate of Mining

Patil 708,712 ba MT/Month

23 Somabhai J Baria

01-00-00 S. No. 200 Panam Naglod Morwa Hadaf

2000 MT/Month

24 Chandrikaben Somabhai Baria

01-00-00 S. No. 192,193,194

Panam Naglod Morwa Hadaf

2000 MT/Month

25 Somabhai J Baria

02-00-00 S. No. 135 Panam Rampur Morwa Hadaf

2000 MT/Month

26 Miteshkumar R Patel

01-25-00 S. No. 73,74

Panam Saliya Morwa Hadaf

1000 MT/Month

27 Mehbub Ishaq Bakkar

01-00-00 S. No. 155,156/3

Goma Sajora Ghoghmba

1000 MT/Month

28 Hitendrakumar Sanabhai Sangada

02-00-00 S. No. 248,249,250

Panam Chavad Godhra 1500 MT/Month

29 Vinodbhai Bharatsinh Baria

01-30-00 S. No. 19,20

Panam Chavad Godhra 833.33 MT/Month

30 Sureshkumar Ramansinh Baria

03-00-00 S. No. 505,509

Panam Rasulpur Morwa Hadaf

5000 MT/Month

31 Sokat Ismail Durvesh

02-00-00 S. No. 16,17,10

Goma Royan Kalol 833.33 MT/Month

32

Nagai Reti Suppliers (Sandeepbhai K Patil)

01-50-00 S. No. 383,497

Goma Alali Kalol 1000 MT/Month

33 Miteshkumar R Patel

01-00-00 S. No. 85,86

Panam Saliya Morwa Hadaf

1000 MT/Month

34 Kiransinh R makwana

01-00-00 S. No. 14,15

Kun Mithali Shahera 1000 MT/Month

35 Rukhiben R. Baria

00-64-00 Chavad Godhara 1500 MT/Month

SAND MINING PROJECTS DISTRICT PATAN

Sr. No.

Name of Applicant

Lease Area

in Hactar

e

Opp. to:Name of

River Village Taluka

Rate of Mining

1 Vanzara Bhikhaji Bheraji 9-3-22 Saraswati Dethali Siddhpur 10000 TPA

2 Rajput Bharatji Viramji 01-32-30

Saraswati Khali Siddhpur 5000 TPA

3 Khumanji Javanji Rajput 01-00-00

Saraswati Khali Siddhpur 5000 TPA

4 Harijan Bhagabhai Punjabhai

01-00-00

Saraswati Khakhali

Harij 5000 TPA

5 Rajput Prahladji Javanji 01-00-00

Saraswati Siddhpur

Siddhpur 5000 TPA

6 Meena Dineshbhai 03-51- Block Saraswati Runi Patan 15000

Page 23: Minutes of the 227th meeting

 

Page 23 of 26  

Sr. No.

Name of Applicant

Lease Area

in Hactar

e

Opp. to:Name of

River Village Taluka

Rate of Mining

Nathabhai 10 No.14 TPA

7 Padmaben Manojkumar Meena

03-49-68

Block No.15

Saraswati Runi Patan 15000 TPA

8 Thakor Bharatji Shankarji 04-50-00

Block No.5

Saraswati Nedra Siddhpur 15000 TPA

9 Thakor Viramji Shankarji 04-50-00

Block No.19

Saraswati Runi Patan 15000 TPA

10 Thakor Harpalji Shankarji 04-50-00

Block No.18

Saraswati Runi Patan 15000 TPA

11 Thakor Bharatji Maganji 04-05-07

Block No.25

Saraswati Dethali Siddhpur 15000 TPA

BLACKTRAP MINING PROJECTS - DISTRICT PORBANDAR

Sr. No

Name of Applicant Lease Area in Hactare

Address of site

Village Taluka Rate of Mining

1 Pioneer Builders (Jasuben Bhimabhai Modedarda)

02-00-00 S.No.174/1A-1P

Roghada

Kutiyana

40000 TPA

2 Krish Enterprise (Rambhai Sanganbhai Bapodara)

01-00-00 S.No.26/22 P Gokran Kutiyana

24000 TPA

BUILDING LIME STONE MINING PROJECTS DISTRICT PORBANDAR Sr. No.

Name of Applicant Lease Area in Hactare

Address of site

Village Taluka Rate of Mining

1 Arjanbhai Odedara 01-00-16 S.No.1/17 P 1

Miyani Porbandar 11700 TPA

2 Giga Vasta Modhvadiya 01-00-00 S.No.24/3 P 1

Miyani Porbandar 12000 TPA

3 Hiriben Jivabhai Keshvala 00-80-94 S.No.45 P 5 Ratdi Porbandar 1800 MT/M 4 Late Bhikhubhai A. Keshvala 01-00-00 S.No.45 P Ratdi Porbandar 2000 MT/M 5 Punjabhai Gangdasbhai Vala 00-32-98 S.No.25/3 P Ratdi Porbandar 1700 MT/M

6 Arjanbhai Lakhmanbhai Karavadra

00-39-00 S.No.25/3 P Ratdi Porbandar 1700 MT/M

7 Maldebhai Karshanbhai Karavadra

3-1-74 S.No.1/5P4,1/5P7

Miyani Porbandar 1800 MT/M

8 Sanjaybhai Savdasbhai Odedara & Chhaganbhai Vejabhai Kuchhadiya

01-00-00 S.No.1/5P6,1/5P3

Miyani Porbandar 7000 MT/Month

9 Deepakbhai Aatiyabhai Odedra

01-00-00 S.No.15/3 Odadar Porbandar 12000 TPA

10 Jethabhai Odedra 01-00-00 S.No.1/5/P1/P1

Miyani Porbandar 11700 TPA

11 Smt.Sumriben Parbatbhai & Sh.Menadbhai Chanabhai

01-00-00 S.No.176/2/1 P &176/2/2P

Mander Porbandar 10000 TPA

12 Meramanbhai Arjanbhai 01-00-00 S.No.128/3P,128/4P

Pata Porbandar 180000 TPA

13 Keshvbhai Rajabhai Odedra 01-00-00 S.No.15/2 Odadar Porbandar 12000 TPA

Page 24: Minutes of the 227th meeting

 

Page 24 of 26  

Sr. No.

Name of Applicant Lease Area in Hactare

Address of site

Village Taluka Rate of Mining

& Hiteshbhai Sanganbhai

14 Hajabhai Lakhmanbhai Antroliya

01-25-45 S.No.740,740/2

Madhavpur

Porbandar 12000 TPA

15 Karanbhai Virambhai 01-00-00 S.No.15/2 Odadar Porbandar 18000 TPA SAND MINING PROJECTS DISTRICT PORBANDAR

Sr. No.

Name of Applicant

Lease Area in Hactare

Opp . to: Name of River

Village Taluka Rate of Mining

1 Nileshkumar Charitable Trust

02-00-00 S.No.281,286,289 Block No.10

Vartu Nadi

Shingada

Porbandar 12000 TPA

BLACKTRAP MINING PROJECTS DISTRICT VADODARA Sr. No Name of Applicant

Lease Area in Hactare

Address of site Village Taluka Rate of Mining

1 Parshuram Quarry Works

01-00-00 S. No. 222/2 paiki

Jambugoral

Savli 2500 MT/Month

2 Khodiyar Stone Quarry

02-36-00 S. No. 218/47/1 paiki

Jambugoral

Savli 2500 MT/Month

SAND MINING PROJECTS DISTRICT VADODARA

Sr. No

Name of Applicant Lease

Area in Hactare

Opp. to: Name of

River Village Taluka

Rate of Mining

1 Pravinsinh Abhesinh Gohil

00-72-25 S No. 117/1/ 1 and 117/2

Mahi Kotna 4000 MT/M

2 Rameshbhai J Kanskiwala

02-00-00 S. No. 175 Orsang Navi Mangrol

Dabhoi 4000 MT/M

3 Ranjitji Rupaji Vanzara 02-00-00 S. No. 949,951, 952

Mahi Poicha (K)

Savli 4000 MT/M

4 Natubhai Somabhai Chauhan

03-00-00 S No. 767/ 78/ 786/ 947/948

Mahi Pipaliya Savli 4000 MT/M

5 Bhatiya Ritaben M 01-45-00 S No. 547 Orsang Karnet Dabhoi 4000 MT/M

6 Gulam Rasulbhai Malek 07-01-59 S. No. 130 Narmada

Somaj Karajan 4000 MT/M

7 Anilkumar Bhagubhai Patel

00-80-00 S. No. 10 to 14

Orsang Chanvada

Dabhoi 4000 MT/M

8 Thakorbhai Narsinhbhai Ode

09-00-00 S. No. 1428 paiki

Narmada

Oze Karjan 4000 MT/M

9 Kanubhai B Kanskiwala 01-00-00 S. No. 231,233

Orsang Akoti Dabhoi 4000 MT/M

10 Ishwarbhai Madhubhai Narola

02-32-07 S. No. 95,96 Orsang Guman-pura

Dabhoi 4000 MT/M

Page 25: Minutes of the 227th meeting

 

Page 25 of 26  

Sr. No

Name of Applicant Lease

Area in Hactare

Opp. to: Name of

River Village Taluka

Rate of Mining

11 Raghav Majur & Kamdar Sahkari Mandli Ltd.

08-34-00 S. No. 537,538

Narmada

Sayar Karajan 4000 MT/M

12 Falguniben Pankajkumar Vyas

01-20-00 S. No. 377/4 Orsang Bhimpura Dabhoi 4000 MT/M

13 Vijaybhai Natubhai Od 02-51-03 S. No. 538 & 562

Narmada

Sayar Karajan 4000 MT/M

14 Sureshbhai Ravjibhai Od 03-00-00 S. No. 562 Narmada

Sayar Karajan 4000 MT/M

15 Raghav Majur & Kamdar Sahkari Mandli Ltd.

03-09-86 S. No. 538 Narmada

Sayar Karajan 4000 MT/M

Hon’ble National Green Tribunal has passed an order dated 13th January 2015 and directed on the validity of the Notifications of 2013 and various OM issued by MOEF. Keeping this order in view, detailed deliberation was made between the members of SEAC and representatives of CGM.

Going through order of Honorable NGT, it has declared the Notification dated 9th September, 2013 as invalid and inoperative. Another directive is regarding the Office memorandums dated 24th June, and 24th December, 2013; wherein some part of them is declared invalid. According to NGT order in OM dated 24th June, 2013 clause 4 (b) (i) is declared invalid and under OM order dated 24th December, 2013 Clause 2 (I) (iii) is invalid. All the office memorandums and notifications issued by MoEF i.e. 1st December, 2009, 18th May, 2012 and 24th June, 2013 and 24th December, 2013 (except to the extent afore-stated) are operative and would apply to the lease mine holders irrespective of the fact whether the area involved is more or less than 5 hectares.

Accordingly under memorandums dated 24thJune 2013, clause no 4(b)(i) ‘no borrowing of earth/excavation of ‘brick earth’ or ‘ordinary earth shall be permitted in case the area of borrowing/excavation is within 1 km of boundary of national parks or wild life sanctuaries" – is held invalid.

Accordingly under memorandums dated 24th December, 2013, clause 2 (I) (iii), ‘No river sand mining project, with mine lease area less than 5 ha, may be considered for granting EC" is held invalid.

The NGT has also directed the MoEF to formulate a uniform cluster policy in consultation with the states for permitting minor mineral mining activity.

In view of the above, committee decided to bifurcate above mentioned proposals received from CGM (Commissioner, Geology and Mining) in below mentioned categories of mining leases as per the prevailing office memorandums of MoEF&CC, New Delhi

Page 26: Minutes of the 227th meeting

 

Page 26 of 26  

1. Lease area(s) which do not fall in any cluster situation.

2. Lease areas which fall under the cluster situation and cumulative total lease area becomes less than 25 Ha.

3. Lease areas which fall under the cluster situation and cumulative total lease area becomes equal or above 25 Ha but less than 50 Ha.

4. Lease areas which fall under the cluster situation and cumulative total lease becomes equals or above 50 Ha.

Once information regarding clusters pertaining to the proposals as mentioned above is furnished, it will taken in one of the next SEAC meeting for the hearing so as to comply with the order of Honorable National Green Tribunal dated 13 January 2015.

Minutes approved by: 1. Shri T. P. Singh, Chairman, SEAC. 

2. Dr. Nikhil Desai, Member, SEAC. 

3. Shri V. C. Soni, Member, SEAC. 

4. Shri R. J. Shah, Member, SEAC 

5.  Shri V.K. Jain, Member, SEAC 

6. Shri V.N. Patel, Member, SEAC