minutes er 5th jcc finalwebapps.powergrid.in/ctu/docs/files/jcc meeting/er/10 5th... · 2016. 7....

15

Upload: others

Post on 08-Nov-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Minutes ER 5th JCC finalwebapps.powergrid.in/ctu/docs/files/JCC Meeting/ER/10 5th... · 2016. 7. 28. · Email : sbagrawal@adhunikgroup.co.in 10. Shri B.H.Ravindra Managing Director
Page 2: Minutes ER 5th JCC finalwebapps.powergrid.in/ctu/docs/files/JCC Meeting/ER/10 5th... · 2016. 7. 28. · Email : sbagrawal@adhunikgroup.co.in 10. Shri B.H.Ravindra Managing Director

Distribution List :

1. Shri R. K. Singh

Sr. Vice President

Sterlite Energy Ltd. 1

st Floor , City Mart Commercial Complex

Baramunda, Bhubansehwar – 751 003

Phone : 0674-6610300

Mobile : 09777451777

Email : [email protected]

2. Shri Amit Jain

Director

Jindal India Thermal Power Ltd. Plot-12, Sector B-1

Local Shopping Complex

Vasant Kunj, New Delhi – 110 070

Phone : 09810062441

Email : [email protected]

3. Shri S.K.Thatte

Managing Director – NPPL

Navabharat Power Private Limited 3

rd Floor, Fortune Towers,

Chandrasekharpur, Bhubaneshwar-751023

Phone : 06722-216031

Email : [email protected]

4. Shri R.V.Sheshan

Managing Director

GMR Kamalanga Energy Ltd. Plot No-29, Satyanagar

Bhubaneswar-751007

Mobile : 07894366221

Email : [email protected]

5. Shri S.K.Sekar

CEO & SBU Head-Thermal

Lanco Babandh Power Pvt. Ltd. Plot No. 397, Phase-III

Udyog Vihar, Gurgaon-122 016

Phone : 0124-4691101

Mobile : 9717782800

Email : [email protected]

6. Shri G. P. Choudhary

Vice President

Monnet Ispat & Energy Limited Mohta Building, 3

rd Floor

4, Bhikaji Cama Place, New Delhi – 110 066

Phone : 011-2617 6705

Mobile : 8826611844

Email : [email protected]

7. Shri J. Mohapatra

Director-Technical

Ind-Bharat Energy (Utkal) Limited Plot No. 30-A. Road No:1, Film Nagar

Jubilee Hills, Hyderabad-500 033

Phone : 040-23333459

Email : [email protected]

8. Shri T. Nagendra Rao

Director,

Shiga Energy Pvt. Ltd. 5

th Floor, DLF Building No. 8

Tower-C, DLF Cyber City, Phase-II

Gurgaon – 122002

Phone : 0124-4696300, 4100393,

Email : [email protected]

9. Shri S. B. Agrawal

CEO - Power

Adhunik Power & Natural Resources Ltd. Crescent Towers (3rd Floor)

229 A J C Bose Road, Kolkata-700 020

Phone : 033-30915300

Mobile : 09007098190

Email : [email protected]

10. Shri B.H.Ravindra

Managing Director

Essar Power (Jharkhand) Ltd. Essar Power Complex, Kanchan Nagri,

Chandwa, District- Latehar

Jharkhand – 829 203

Phone : 0651-2240679

Email : [email protected]

11. Shri Arun Gupta

Chief Executive Officer

Corporate Power Ltd. Maple Plaza, Opposite Road No. 2

Ashok Nagar, Ranchi, Jharkhand – 834002

Ph : 0651-3981900-908

Email : [email protected]

12. Shri M. S. Pal

Addl. Chief Engineer & In-charge of PTR

WBSEDCL Bidyut Bhawan, 7

th Floor,

B Block, DJ Block, Sector II,

Salt Lake City, Kolkata – 700 091

Email : [email protected]

Page 3: Minutes ER 5th JCC finalwebapps.powergrid.in/ctu/docs/files/JCC Meeting/ER/10 5th... · 2016. 7. 28. · Email : sbagrawal@adhunikgroup.co.in 10. Shri B.H.Ravindra Managing Director

13. Shri Harish Sharan

Executive Director

PTC India Limited, 2

nd Floor; NBCC Tower,

15 Bhikaji Cama Place

New Delhi – 110 066

Phone : 011-41659136,

Email : [email protected]

14. Shri S. R. Ganguly

Sr. VP

Lanco Teesta Pvt. Ltd. Plot No:397,Udyog Vihar

Phase-III,Gurgaon-122016

Phone : 01244741305

Mobile : 9810571433

Email : [email protected]

15. Shri M. K. Sharma

Chief Executive Officer

Jal Power Corporation Limited

A-102, Sector-65

Noida – 201 307

Phone : 0120-4397444

Email : [email protected]

16. Shri Sanjeev Upadhyay

President, Hydro

Gati Infrastructure Limited

268, Udyog Vihar, Ph-IV

Gurgaon – 122016, Haryana

Phone : 0124-2644284,

Email: [email protected]

17. Shri Y. Nagendra Rao

Director

Dans Energy Pvt. Ltd 5th Floor, DLF Building No. 8

Tower-C, DLF Cyber City, Phase-II

Gurgaon – 122002

Phone : 0124-4696300

Email : [email protected]

18. Dr. B. M. Goswami

Chief Executive Officer

Madhya Bharat Power Corporation Ltd. Daragaon, Tadong, Near Sikkim Computers

Gangtok – 737 102

Phone : 03592-231771, 320519

Mobile : 09891643501

Email : [email protected]

Page 4: Minutes ER 5th JCC finalwebapps.powergrid.in/ctu/docs/files/JCC Meeting/ER/10 5th... · 2016. 7. 28. · Email : sbagrawal@adhunikgroup.co.in 10. Shri B.H.Ravindra Managing Director

Minutes of 5th

JCC Meeting of IPPs granted LTA in ER

Page 1 of 12

Minutes of meeting of 5th Joint Co-ordination Meeting of IPPs granted LTA in ER held on 21.01.2015

1. The 5th meeting of the Joint Co-ordination Committee of IPPs in ER associated

with various high capacity power transmission corridors was held in MP Hall,

POWERGRID Township, Gurgaon on 21st January, 2015. The list of participants

is enclosed at Annexure-1.

2. POWERGRID welcomed the participants and it was informed that generation

developers should ensure completion of their dedicated lines to match with the

commissioning of transmission network in order to prevent bottling up of power.

POWERGRID stated that interim arrangements through LILO of existing lines

were provided only as a contingency measure and the IPPs need to focus on

implementing the final dedicated transmission system. Constraints shall be faced

in evacuation of power from the generation projects connected through LILO

arrangement, provided as an interim arrangement. In order to evacuate maximum

power from their power plant by utilizing the available transmission system, IPPs

should connect to pooling station from where High Capacity lines are being

commissioned. Therefore, all the IPPs should expedite the construction of their

dedicated line as well as the terminating bays at the Pooling Station. Wherever

POWERGRID is implementing the bays on consultancy basis, timely payment to

POWERGRID contractor for the same should be made. In case of non-payment,

the work of bays awarded to the contractor shall be cancelled and fresh tender of

the same shall delay the work by 6 months to 1 year. The responsibility of such

delay shall lies with the generation developer. Delay in completion of terminating

bays shall also delay connection to the pooling station and interim arrangement is

liable for removal for efficient grid operation and reliability and security of grid.

3. DGM (CTU), POWERGRID stated that the minutes of previous JCC minutes

were circulated vide letter dated 03.03.2014 and same were uploaded on

POWERGRID website also. As no comments/observations has been received,

the minutes are taken as confirmed.

4. It was said that since the construction of transmission line constitutes a very

small portion compared to the total investment made by the developers, it is

being put on a lesser priority by the generation developers and POWERGRID

emphasized the need to change this scenario as it could lead to a bottleneck for

transfer of power.

5. CTU informed that it has taken initiatives to prevent rejection of LTA/MTOA

applications on the basis of incompleteness/non-conformity with the regulations

Page 5: Minutes ER 5th JCC finalwebapps.powergrid.in/ctu/docs/files/JCC Meeting/ER/10 5th... · 2016. 7. 28. · Email : sbagrawal@adhunikgroup.co.in 10. Shri B.H.Ravindra Managing Director

Minutes of 5th

JCC Meeting of IPPs granted LTA in ER

Page 2 of 12

by making the necessary guidelines and information available on the

POWERGRID website.

6. POWERGRID mentioned that they are receiving requests from various IPP

generators for change of drawl region due to firming up of beneficiary through

signing of PPA in region(s) other than the target region(s). These requests

amount to relinquishment of LTA quantum in the earlier target regions.

7. The progress of generation projects and dedicated transmission systems of

various IPPs connected to High Capacity Power Transmission Corridors which

have been granted regulatory approval by CERC, was reviewed by

POWERGRID. The detailed list of IPPs is enclosed at Annexure- II.

The review of the progress made by each of the IPP is as under:

(i) Navabharat Power Pvt. Ltd :

Representative from M/s Navabharat Power Pvt. Ltd (NPPL) informed that there is no progress in the project due to unavoidable circumstances. He also informed that NPPL has applied for relinquishment of LTA and the case is pending in CERC. Upon query he informed that there is no feedback on the same from CERC. It was also informed that the construction phase Bank Guarantee is still alive. Additional GM (BDD) communicated that necessary actions and formalities shall be taken to close the project.

(ii) Essar Power (Jharkhand) Ltd. (2x600 MW):

Representative from M/s Essar Power (Jharkhand) Ltd (EPL) informed the status of project as follows:

43% work is completed till date. The project is on hold due to de-allocation of coal blocks. EPL will be participating in the soon to be held auctioning and work will be resumed after the coal allocation. All the required material for project is in place and new target date of completion is December’16 PPA: (450+300) MW with BSEB; 12% of power to JSEB; 240MW with Noida Power Company Ltd. (NPCL)

Further, it was mentioned by M/s EPL that they had already requested CTU in writing to consider the issue of coal blocks as Force Majeure to which CTU had already replied that their request could not be accepted. AGM (BDD) has asked M/s EPL about the payment due of Rs. 5 Crore and EPL assured that the payment issues will be sorted soon

Page 6: Minutes ER 5th JCC finalwebapps.powergrid.in/ctu/docs/files/JCC Meeting/ER/10 5th... · 2016. 7. 28. · Email : sbagrawal@adhunikgroup.co.in 10. Shri B.H.Ravindra Managing Director

Minutes of 5th

JCC Meeting of IPPs granted LTA in ER

Page 3 of 12

(iii) Jal Power Corporation (Rangit-IV) (3x40 MW):

Representative from M/s Jal Power Corporation (JPC) informed the status of project as follows:

All the clearances related to the generation plant are received and land had been acquired. 60% of the total work is already completed. COD of all three Units is expected by May-June’16. Dedicated line is expected to be completed by December’15. PPA: 60% of Power to WBSEDCL; 40% to TPTCL on merchant basis

AGM (BDD) informed that M/s JPC has produced Letter of Credit (LC) only for 20% and the balance 80% LC is pending because of which manufacturing of GIS equipment could not awarded. M/s JPC informed that the balance LC will be opened by March’15. POWERGRID requested to confirm the same in writing. Further, representative from M/s JPC informed about the change in LTA quantum which is as follows: ER- 72 MW (instead of 88); NR & WR: 24MW each (instead of 12 MW). POWERGRID stated that the request for change in Target Region cannot be entertained unless PPA in the region is firmed up..

(iv) Gati Infrastructure Ltd (Chuzachen) (2x49.5 MW)

Representative from M/s Gati Infrastructure Ltd (GIL) informed the status of project as follows:

Project Declared COD of both the units on 18th May, 2013 It was further informed by M/s GIL that the construction of bays falls under the scope of Govt. of Sikkim to which AGM (CTU) clarified that it is the responsibility of M/s GIL to ensure that bays are ready in time as the LTA Agreement was signed between M/s GIL and POWERGRID. Further, AGM (CTU) has reiterated that the above issue is a matter of serious concern and accordingly has asked M/s GIL to send monthly status on the same. Also, it was advised to M/s GIL to regularly take up the matter with Govt. of Sikkim.

(v) Gati Infrastructure Bhasmey Power Pvt. Ltd. (Bhasmey) (2x25.5 MW)

Representative from M/s Gati Infrastructure Bhasmey Power Pvt. Ltd (GIBPPLL) submitted the status of their project as follows:

Page 7: Minutes ER 5th JCC finalwebapps.powergrid.in/ctu/docs/files/JCC Meeting/ER/10 5th... · 2016. 7. 28. · Email : sbagrawal@adhunikgroup.co.in 10. Shri B.H.Ravindra Managing Director

Minutes of 5th

JCC Meeting of IPPs granted LTA in ER

Page 4 of 12

COD is postponed to December’17 due to issues with the dam It was also informed that interim connection through LILO arrangement will be provided by Govt. of Sikkim to which AGM (CTU) reiterated that it is the responsibility of M/s Gati Infrastructure Bhasmey Power Pvt. Ltd.

(vi) Lanco Babandh Power Pvt Ltd

Representative from M/s Lanco Babandh Power Pvt Ltd (LBPPL) submitted the status of their project as follows:

Revised COD of the project: the project is stalled therefore the revised COD cannot be confirmed with certainty, however the tentative COD may be taken as Unit 1- Dec’16 & Unit 2- Feb’17. PPAs have been signed for 330 MW with GRIDCO Odisha in 2006; 424 MW with UPPCL in 2013 and 350 MW with RVPN in 2013 Dedicated line: The consultancy contract for line bay work is to be signed between LBPL & PGCIL.

Representative from BDD has reminded M/s LBPPL about the agreement for bays which is yet to be signed. Accordingly, the representative from M/s LBPPL informed that the project work is stalled after completing 40% due to financial problems and agreement will be signed after the same is resumed.

(vii) Adhunik Power & Natural Resources Limited (2x270 MW)

Representative from M/s Adhunik Power & Natural Resources Ltd (APNRL) submitted the status of their project as follows:

The generation plant is already commissioned and dedicated line is operational

It has been clarified to M/s APNRL that their LTA application for transfer of 100 MW to Southern Region was received in January, 2014 and hence prioritized accordingly. Further, it was informed by the representative from M/s APNRL that though they wanted to transfer power through MTOA/ STOA till the start of LTA, they are unable to finalise applications for the same.

(viii) Ind Barath Energy (Utkal) Ltd

Representative from M/s Ind Barath Energy (Utkal) Ltd (IBEL) submitted the status of their project as follows:

Unit1: Synchronization in Mar’15 & COD in Apr’15; Unit 2: COD in July’15

Page 8: Minutes ER 5th JCC finalwebapps.powergrid.in/ctu/docs/files/JCC Meeting/ER/10 5th... · 2016. 7. 28. · Email : sbagrawal@adhunikgroup.co.in 10. Shri B.H.Ravindra Managing Director

Minutes of 5th

JCC Meeting of IPPs granted LTA in ER

Page 5 of 12

Dedicated line is expected to be commissioned before the synchronization of Unit 1 i.e.Mar’15

It was informed that Connection Agreement has been signed. AGM (BDD) enquired about the balance consultancy payments that are to be paid in the form of Letter of Credit (LC) and it was informed by M/s IBEL that a reply will be sent to POWERGRID.

(ix) GMR Kamalanga Energy Ltd

Representative from M/s GMR Kamalanga Energy Ltd (GMR) submitted the status of their project as follows

Units I, II & III have been commissioned in Apr’13, Nov’13 & Mar’14 respectively PPA of 260 MW is signed with Bihar. The dedicated line to Angul Pooling Station has been commissioned in Dec’14. The dedicated line to Meramundali S/s for delivery of power to the state govt. is under construction

AGM (CTU) stated that the machines should not be connected to the state as well as the ISTS system at the same time. Therefore if any machine is connected to the state system through a dedicated line, then the developer should make sure that the machine is isolated and not connected to the ISTS system. He further asked the project developer to convey the start date of LTA in writing at a later date and also suggested M/s GMR to ensure that all the formalities are completed by that time.

(x) Teesta Urja Ltd. / PTC (Teesta-III) (6x200 MW)

Representative from M/s Teesta Urja Ltd. (TUL) submitted the status of their project as follows:

Work is stalled since Sep’14 due to site problems and is expected to resume in the 1st week of Mar’15. 91% of the work is completed till date. Unit 1 is expected to be commissioned in Dec’15 and COD by Mar’16; The other Units (U#2 to U#6) will be followed with a gap of 20 days in between. Dedicated line: Construction of 79 km out of 216 km is completed till date. PPA for sale of 70% of total Power has already been signed with PTC India Ltd in 2006. The balance 30% Power shall be sold as merchant power on short term basis

Page 9: Minutes ER 5th JCC finalwebapps.powergrid.in/ctu/docs/files/JCC Meeting/ER/10 5th... · 2016. 7. 28. · Email : sbagrawal@adhunikgroup.co.in 10. Shri B.H.Ravindra Managing Director

Minutes of 5th

JCC Meeting of IPPs granted LTA in ER

Page 6 of 12

Representative from M/s TUL informed that they don’t have any issues with the project

(xi) Madhya Bharat Power Corporation Ltd. Representative from MBPCL did not attend the meeting but has submitted their status through a letter dated 16.1.2015, received on 20.01.2015. The detailed status is as given below:

COD of Unit 1 is expected by June-2018 followed by Unit 2 in July-2018 The PPAs will be signed 6 months prior to the commissioning of project EPC Contract for all the civil works was originally awarded to SEW and has been replaced by M/s Mosh Varaya Infrastructure Pvt Ltd in 2011 27 out of 30 towers for construction of dedicated line are falling under Forest Area for which 1st Stage Clearance order has already been received from GoI. The private land acquisition process for the remaining 3 tower footings is under progress.

8. POWERGRID informed about the status of transmission lines in the Corridors-I, II

& III and the associated other transmission lines which are under the scope of

POWERGRID. It was stated that Odisha & Jharkhand corridors are expected by

June’15. The detailed status of these lines is attached in Annexure-III.

POWERGRID has invited further comments/ suggestions if any from the

participants to which one of the participants has asked if there will be any surplus

corridor in Odisha to which CTU stated that the commitment for all the corridors is

already given to the applicants and any new application will be granted access

according to its priority.

The meeting ended with Vote of Thanks!

- - - - - x x x x - - - - - x x x x - - - - -

Page 10: Minutes ER 5th JCC finalwebapps.powergrid.in/ctu/docs/files/JCC Meeting/ER/10 5th... · 2016. 7. 28. · Email : sbagrawal@adhunikgroup.co.in 10. Shri B.H.Ravindra Managing Director

Minutes of 5th

JCC Meeting of IPPs granted LTA in ER

Page 7 of 12

Annexure-I

List of Participants of the meeting

Sl. No.

NAME DESIGNATION ORGANIZATION E-MAIL

1. Ashok Pal AGM (CTU-Plg) POWERGRID [email protected]

2 D N Rozekar DGM-CTU (Plg) POWERGRID [email protected]

3 Ms. Manju Gupta AGM-Reg. Cell POWERGRID [email protected]

4 D.V. Ramana AGM (BDD) POWERGRID [email protected]

5 Anil Kumar Meena Manager-CTU (Plg) POWERGRID [email protected]

7 Lakshmi Kant Manager-CTU (Plg) POWERGRID [email protected]

7 Ankita Singh Sr. Engineer (CTU-Plg) POWERGRID [email protected]

8 V.M.S. Prakash Y Sr. Engineer (BDD) POWERGRID [email protected]

9 Manish R Keshari Engineer-CTU (Plg) POWERGRID [email protected]

10 K Jyoth Kumar Officer- CTU (Plg) POWERGRID [email protected]

11 Rahul Banerjee GM GDF Suez Energy India Pvt. Ltd

[email protected]

12 Himanshu Mishra Manager MEPL [email protected]

13 Aman Engineer Teesta Urja Ltd [email protected]

14 M.N.Ravi Shankar CEO APNRL [email protected]

15 Vineet Sarawagi D.P. Manager APNRL [email protected]

16 Smarjit Sahoo Asst. Manager APNRL [email protected]

17 J. Mohapatra Director Ind Barath Energy (Utkal) Ltd

[email protected]

18 Ajaya Kumar Nathani

Head Transmission GMR [email protected]

19 Ravi Shankar Manager PTC India Ltd [email protected]

20 Mahavirsinh Jhala GM Lanco Babandh Power Ltd

[email protected]

21

Gaurav Prasad Asst. Manager Lanco Babandh Power Ltd

[email protected]

22 Devesh Gautam Manager Gati Infra Pvt. Ltd [email protected]

23 M.K Sharma M.D Jal Power Corp. Ltd [email protected]

24 R.S. Chadha Sr. Vice President (Transmission)

Jal Power Corp. Ltd [email protected]

25 Mohan Menon Advisor East Coast Energy Pvt. Ltd

[email protected]

26 R. Srinivasan V.P. (Corporate) East Coast Energy Pvt. Ltd

[email protected]

27 R.K. Kumara Swamy

Advisor Coast Energen Pvt. Ltd

[email protected]

28 Rajashekhar. M DGM TPCIL- Nellore [email protected]

29 K Raman Ramesh Plant Manager-VP NCC- Nellore [email protected]

30 Deepal Rodricks GM (Commercial & BD)

Essar Power/ Navabharat

[email protected]

31 V.L. Dua Vice Presindent IL & FS Tamil Nadu Power Co.Ltd

--

Page 11: Minutes ER 5th JCC finalwebapps.powergrid.in/ctu/docs/files/JCC Meeting/ER/10 5th... · 2016. 7. 28. · Email : sbagrawal@adhunikgroup.co.in 10. Shri B.H.Ravindra Managing Director

Minutes of 5th

JCC Meeting of IPPs granted LTA in ER

Page 8 of 12

Annexure-II

HIGH CAPACITY TRANSMISSION CORRIDOR - I (Phase-I IPPs in Odisha & associated Transmission System)

Sl. No.

Generation Developer/ Open Access Applicant

LTOA Quantum

(MW)

Target Beneficiaries Status

NR WR ER SR

1 Sterlite Energy Ltd 400 200 200 - -

2 GMR Kamalanga Energy Ltd 800 600 0 - 200 U-1/2 : Commissioned,

U-3 : Commissioning shortly

3 Navabharat Power Pvt. Ltd 720 465 255 - -

4 Monet Power Company Ltd 900 250 150 400 100 Dec, 2014

5 Jindal India Thermal Power Ltd 1044 834 210 - - U-1 : Mar, 2014

6 Lanco Babandh Power Pvt Ltd 800 774 26 - - Nov, 2015

7 Ind Barath Energy(Utkal) Ltd 616 166 200 250 - U-1 : May, 2014

Subtotal (Odisha) 5280 3289 1041 650 300

HIGH CAPACITY TRANSMISSION CORRIDOR - II (Phase-I IPPs in Jharkhand & associated Transmission System)

Sl. No.

Generation Developer/ Open Access Applicant

LTOA Quantum

(MW)

Target Beneficiaries Status

NR WR ER

1 Adhunik Power & Natural Resources Limited (2x270 MW)

450 200 50 200 Commissioned

2 Essar Power (Jharkhand) Ltd. (2x600 MW)

1100 400 400 300 Dec, 2016

3 Corporate Power Limited Ph-I (2x270 MW)

480 240 240 0 Uncertain

4 Corporate Power Limited Ph-II (2x270 MW)

480 240 240 0 Uncertain

5 WBSEDCL (1000 MW State surplus)

1000 600 400 0 Prog. By 2014-15

Total 3510 1680 1330 500

HIGH CAPACITY TRANSMISSION CORRIDOR - III

(Phase-I IPPs in Sikkim)

Sl. No.

Generation Developer/ Open Access Applicant

LTOA Quantum

(MW)

Target Beneficiaries Status

NR WR ER

1 Teesta Urja Ltd. / PTC (Teesta-III) (6x200 MW)

1200 840 - 144 Jan, 2015

Page 12: Minutes ER 5th JCC finalwebapps.powergrid.in/ctu/docs/files/JCC Meeting/ER/10 5th... · 2016. 7. 28. · Email : sbagrawal@adhunikgroup.co.in 10. Shri B.H.Ravindra Managing Director

Minutes of 5th

JCC Meeting of IPPs granted LTA in ER

Page 9 of 12

Sl. No.

Generation Developer/ Open Access Applicant

LTOA Quantum

(MW)

Target Beneficiaries Status

2 Lanco Energy Pvt. Ltd. (Teesta-VI) (4x125 MW)

500 - 500 - Apr, 2016

3 DANS Energy Pvt. Ltd. (Jorethang) (2x48)

96 48 48 - Oct, 2014

4 JAL Power Corporation (Rangit-IV) (3x40 MW)

120 16 16 88 Jun, 2016

5 Madhya Bharat Power Corpn Ltd. (Rongnichu) (2x48 MW)

96 56 40 0 Dec, 2017

6 Gati Infrastructure Ltd (Chuzachen) (2x49.5 MW)

99 99 - - Commissioned

7 Gati Infrastructure Bhasmey Power Pvt. Ltd. (Bhasmey) (2x25.5 MW)

51 36 15 - Mar, 2017

Total 2162 1095 619 232

Other Generation Project – Granted LTA

Sl. No.

Generation Developer/ Open Access Applicant

LTOA Quantum

(MW)

Target Beneficiaries Status

NR WR ER

1 Shiga Energy Pvt. Ltd. (Tashiding)

97 48.5 48.5

Page 13: Minutes ER 5th JCC finalwebapps.powergrid.in/ctu/docs/files/JCC Meeting/ER/10 5th... · 2016. 7. 28. · Email : sbagrawal@adhunikgroup.co.in 10. Shri B.H.Ravindra Managing Director

Minutes of 5th

JCC Meeting of IPPs granted LTA in ER

Page 10 of 12

Annexure-III

HIGH CAPACITY TRANSMISSION CORRIDOR - I

(Phase-I IPPs in Odisha & associated Transmission System)

Transmission System under the Scope of POWERGRID:

• Transmission System for Phase-1 generation projects in Odisha - Part-A

Sl. No.

Scope of Transmission System Status

1 Angul Pooling Station – Jharsuguda Pooling Station 765kV 2xS/c line Jan, 15 / Mar, 15

2 LILO of Rourkela – Raigarh 400kV D/c at Jharsuguda Pooling station Commissioned

3 LILO of Meramundali – Jeypore 400kV S/c line at Angul pooling station Commissioned

4 LILO of one ckt of Talcher - Meramundali 400kV D/c line at Angul pooling station

Commissioned

5 Establishment of 2x1500 MVA, 765/400kV Pooling Station at Jharsuguda Mar, 2015

6 Establishment of 4x1500MVA, 765/400kV Pooling Station at Angul Mar, 2015

• Transmission System for Phase-1 generation projects in Odisha - Part-B

Sl. No.

Scope of Transmission System Status

1 Establishment of 765kV switching station at Dharamjaygarh / near Korba Commissioned

2 LILO of Ranchi – WR Pooling near Sipat 765kV S/c line at Dharamjaygarh / near Korba

Commissioned

3 Jharsuguda Pooling Station – Dharamjaygarh / near Korba (WR) 765kV D/c Commissioned

4 Establishment of 765/400kV Pooling Station at Jabalpur Commissioned

5 Dharamjaygarh / near Korba – Jabalpur Pooling Station 765kV D/c line Jun, 2015

6 Jabalpur Pooling Station – Jabalpur 400 kV D/c (high capacity) line Commissioned

• Transmission System for Phase-1 generation projects in Odisha - Part-C

Sl. No.

Scope of Transmission System Status

1 Jabalpur Pooling Station – Bina 765kV D/c line Commissioned

2 Bina – Gwalior 765kV S/c (3rd circuit) Commissioned

3 Gwalior - Jaipur 765kV S/c line (2nd circuit) Jun, 2015

4 Jaipur - Bhiwani 765kV S/c line Feb, 2015

Transmission System under the Scope of Private Sector:

Sl. No.

Scope of Transmission System Status

1 Establishment of 2x1500MVA, 765/400kV Bhopal Pooling Station 2 Jabalpur Pool – Bhopal – Indore 765kV S/c 3 Bhopal New substation – Bhopal (M.P.) 400kV D/c (high capacity) 4 Establishment of 2x1500MVA, 765/400kV Bhopal Pooling Station

Page 14: Minutes ER 5th JCC finalwebapps.powergrid.in/ctu/docs/files/JCC Meeting/ER/10 5th... · 2016. 7. 28. · Email : sbagrawal@adhunikgroup.co.in 10. Shri B.H.Ravindra Managing Director

Minutes of 5th

JCC Meeting of IPPs granted LTA in ER

Page 11 of 12

HIGH CAPACITY TRANSMISSION CORRIDOR - II (Phase-I IPPs in Jharkhand & associated Transmission System)

Transmission System under the Scope of POWERGRID:

• Transmission System for Phase-I Generation Projects in Jharkhand & West Bengal : Part-A-1

Sl. No.

Scope of Transmission System Status

1 Establishment of 400kV GIS Pooling Station (Jharkhand Pool) near Essar and Corporate generation projects.

Mar, 2015

2 Ranchi - Gaya 400 kV D/c (Quad) line via pooling station proposed near Essar / Corporate generation projects

Mar, 2015

• Transmission System for Phase-I Generation Projects in Jharkhand & West Bengal : Part-A-2

Sl. No.

Scope of Transmission System Status

1 Ranchi New (765/400kV S/s) - Dharamjaygarh / near Korba 765kV S/c Mar, 2015

2 2x1500 MVA, 765/400 kV New GIS substation at Varanasi Jun, 2015

3 Gaya - Varanasi 765kV S/c Jun, 2015

4 Varanasi - Balia 765 kV S/c line Jun, 2015

• Transmission System for Phase-I Generation Projects in Jharkhand & West Bengal : Part-B

Sl. No.

Scope of Transmission System Status

1 New 2x1500 MVA, 765/400 kV substation at Kanpur Jun, 2015

2 Varanasi – Kanpur 765 kV D/c Jun, 2015

3 Kanpur – Jhatikra 765 kV S/c Jun, 2015

4 Kanpur (765/400kV) - Kanpur (Existing) 400kV D/C (Quad) Jun, 2015

5

400kV connectivity for new 765/400kV S/s at Varanasi

• Varanasi - Sarnath (UPPCL) 400kV D/c (quad)

• LILO of Sasaram - Allahabad 400kV line at Varanasi

• Opening of LILO of one ckt of Sasaram - Allahabad 400kV D/c line at Sarnath

Jun, 2015

Transmission System under the Scope of Private Sector:

Sl. No.

Scope of Transmission System Status

1 Dharamjaygarh – Jabalpur 765kV D/C line (2nd line)

• Sub-station bays under the scope of POWERGRID (associated with Private Sector lines)

Sl. No.

Scope of Transmission System Status

1 2 nos. 765kV line bays at Dharamjaygarh

2 2 nos. 765kV line bays at Jabalpur

Page 15: Minutes ER 5th JCC finalwebapps.powergrid.in/ctu/docs/files/JCC Meeting/ER/10 5th... · 2016. 7. 28. · Email : sbagrawal@adhunikgroup.co.in 10. Shri B.H.Ravindra Managing Director

Minutes of 5th

JCC Meeting of IPPs granted LTA in ER

Page 12 of 12

HIGH CAPACITY TRANSMISSION CORRIDOR - III (Phase-I IPPs in Sikkim)

Transmission System under the Scope of POWERGRID:

• Transfer of power from generation projects in Sikkim to NR/WR (Part-A)

Sl. No.

Scope of Transmission System Status

1 Establishment of New 2x315 MVA, 400kV sub-station at Kishanganj Jun, 2015

2 LILO of Siliguri (Existing) – Purnea 400kV D/c line(quad) at new pooling

station Kishanganj Jun, 2015

3 LILO of Siliguri (Existing) – Purnea 400kV D/c line (on which reconductoring

is being carried out) at Kishanganj with higher capacity (quad) conductor Jun, 2015

4 LILO of Siliguri – Dalkhola 220kV D/c line at new pooling station Kishanganj Jun, 2015

5 LILO of Gangtok-Melli 132kV S/c line upto Rangpo, where Chuzachen-

Rangpo 132kV D/c would be connected so as to form Chuzachen-Gangtok and Chuzachen-Melli 132kV S/c lines.

Commissioned

• Transfer of power from generation projects in Sikkim to NR/WR (Part-B)

Sl. No.

Scope of Transmission System Status

1 Establishment of 400/220/132kV (400/220kV, 16x105 MVA, Single Phase

transformers and 220/132kV, 3x100MVA) Gas Insulated Substation at Rangpo

Jan, 2015

2 Establishment of 220kV Gas Insulated switching station at New Melli Jan, 2015

3 LILO of Teesta III – Kishanganj 400kV D/c line (quad, Teesta III – Kishanganj

400kV D/c line to be constructed through JV route) at Rangpo Commissioned

4 Rangpo – New Melli 220kV D/c line (with twin Moose conductor) Feb, 2015

5

LILO of Gangtok-Rangit 132kV S/c line at Rangpo and termination of Gangtok-Rangpo/Chujachen and Melli – Rangpo/Chujachen 132kV lines

(constructed under part-A through LILO of Gangtok-Melli 132kV S/c line upto Rangpo) at Rangpo sub-station

Commissioned

6 LILO of Teesta V – Siliguri 400kV D/c line at Rangpo Commissioned

7 Kishanganj – Patna 400kV D/c (quad) line Jun’ 2015