Thameslink Stabling and Train Presentation Facilities at Cambridge
MILL ROAD BRIDGE
Proposed Sequencing
The following sequencing drawings describe how we intend to carry out the works to Mill Road bridge.
To reduce risk to the programme, advance works are being carried out between February and June in preparation for the road closure planned
from Saturday 01st July to Sunday 25th August 2019.
We have carried out several studies to identify the best option for a temporary footbridge; although this may have an impact on our construction programme, we have tried to maximise public access.
Sequencing – Existing
Existing Layout
Existing Layout
Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 1
Road Closure from 01st July 2019…
Programme
Existing layout
The existing layout of Mill Road bridge showing from north of Mill Road Bridge looking towards the south.
February to end of June T-1
Footbridge Closed …Road Closure to Sunday 25th August 2019
Sequencing – Pre-works
Pre-works
Bridge Remains open to all traffic
Removal of brickwork to Archway 5
New temporary drivers walkway created
Excavation of ground below archway 6
Installation of new drainage pipework
Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 1
Programme
Programme
Pre-works
Creation of a new drivers walkway will be required through archway 5 to enable works to begin below archway 6
Road Closure
February to end of June T-1
Footbridge Closed Road Closure from 01st July 2019… Footbridge Closed …Road Closure to Sunday 25th August 2019
Sequencing – Pre-works
Pre-works
Bridge Remains open to all traffic
Installation of permanent stainless steel tie bars below
archway 4
Installation of temporary stainless steel tie bars
below archway 5
During tie bar works; drivers walkway will
divert through archway 6
Excavation under archway 5 to new
formation level
Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 1
Programme
Programme
Pre-works
Installation of Permanent tie-bars to arch 4 and temporary tie-bars to arch 5. All works complete between Feb and June.
Road Closure
February to end of June T-1
Footbridge Closed Road Closure from 01st July 2019… Footbridge Closed …Road Closure to Sunday 25th August 2019
Sequencing – Stage 0
Week t-1
Bridge Remains open to vehicle traffic
Parapet to pier 7 to be removed and temporary safety measures
put in place.
Existing access gate to drivers steps to be relocated
to top of stairway
Wall around steps landing to be removed
New temporary footbridge installed
Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 1
Programme
Programme
Week t-1
On the week leading up to the road closure, a new temporary footbridge will be installed to the south. We have not shown this on the following drawings.
Road Closure
February to end of June T-1
Footbridge Closed Road Closure from 01st July 2019… Footbridge Closed …Road Closure to Sunday 25th August 2019
Bridge width circa 2.1m. Pinch point likely to be at this point circa 1.3m
Example Bridges
At times it will be necessary to close the temporary footbridge for short periods, we will keep
the public informed of all closures in advance
It is our intention to close the temporary footbridge for a period of
5 days. This is subject to change dependant on detailed design
Technical Drawing
Public Information
It is our intention to keep the public fully informed of all closures, restrictions and also give updates on the progress of our work
Sequencing – Diversions
Day 1
Road Closed to vehicle traffic
Road Closed diversion signs erected
Fencing erected preventing all access apart from foot
traffic
Pedestrian access will be maintained
throughout
Cyclists must dismount to use temporary bridge
Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 1
Programme
Programme
Road Closed
Road diversions will commence on the 01st of July. Pedestrian and cycle access will still be available via temporary footbridge.
Road Closure
February to end of June T-1
Footbridge Closed Road Closure from 01st July 2019… Footbridge Closed …Road Closure to Sunday 25th August 2019
Bus Replacement Service
Sequencing – Stage 1
Stage 1 visual
Bridge Closed – pedestrian access via temporary footbridge
Removal of parapets and parapet support beams
Breakout roadway and pavements
Commence excavation of material in 100mm
layers to level
Temporary closure of pedestrian walkway
may be required
Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 1
Programme
Programme
Stage 1 – Road removal
01st July 2019: Removal or parapets, removal of parapet support beams, removal of footpaths and roadway, commence excavation.
Road Closure
February to end of June T-1
Footbridge Closed Road Closure from 01st July 2019… Footbridge Closed …Road Closure to Sunday 25th August 2019
Sequencing – Stage 2
Stage 2 visual
Completion of Excavation of material above arches
Existing services under the roadway supported
Removal of temp support props under arch 6
Commence breakout of bridge structure to
impost beam level
Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 1
Programme
Programme
Stage 2 – Bridge demolition
Completion of excavation works; removal of temporary support props to archway 6; commence removal of bridge structure
Road Closure
February to end of June T-1
Footbridge Closed Road Closure from 01st July 2019… Footbridge Closed …Road Closure to Sunday 25th August 2019
Sequencing – Stage 3
Stage 3 visual
Installation of impost beams Impost beams secured in to
place by securing to brickwork New tie bars installed through Impost beam
Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 1
Programme
Programme
Stage 3 - Install Impost beams
Continue removal of brickwork to impost beam level. Place impost beams. Secure beams in place. Install permanent tie bars under archway 5.
Road Closure
February to end of June T-1
Footbridge Closed Road Closure from 01st July 2019… Footbridge Closed …Road Closure to Sunday 25th August 2019
Sequencing – Stage 4
Stage 4 visual
Mobilise crane to site on prepared footprint
Once crane work complete - open temporary bridge to
pedestrians again
Precast concrete Units lifted in to place and secured in
place
Week 2 Week 3 Week 5 Week 6 Week 7 Week 8 Week 1 Week 4
Programme
Programme
Stage 4 – Install new structure pre-cast units
Once impost beams are in place, the main bridge structure pre-cast units will be lifted into place and secured
Temporary Footbridge Closed to pedestrians during daytime crane
works for a duration of 5 days
Road Closure
February to end of June T-1
Footbridge Closed Road Closure from 01st July 2019… Footbridge Closed …Road Closure to Sunday 25th August 2019
Sequencing – Stage 5
Stage 5 visual
Infill of below roadway back to formation level
Grouting and waterproofing of concrete structure
Week 2 Week 3 Week 4 Week 6 Week 7 Week 8 Week 1 Week 5
Programme
Programme
Stage 5 – Reinstate infill under carriageway
Installation of infill material above arch 5, grouting and waterproofing of new concrete structure, infilling between structure and rail bridge.
Road Closure
February to end of June T-1
Footbridge Closed Road Closure from 01st July 2019… Footbridge Closed …Road Closure to Sunday 25th August 2019
Sequencing
– Stage 6
Stage 6 visual
Build up external bridgework with reclaimed bricks to match existing
Week 2 Week 3 Week 4 Week 7 Week 8 Week 1 Week 5
Installation of parapet beams and modified parapets
Week 6
Programme
Programme
Stage 6 – Reinstate brickwork and parapets
Replacement of brickwork and completion of infill to road surface level. Replacement of modified parapets and support beams.
Road Closure
February to end of June T-1
Footbridge Closed Road Closure from 01st July 2019… Footbridge Closed …Road Closure to Sunday 25th August 2019
Sequencing – Stage 7
Stage 7 visual
New brick parapet construction
Reinstatement of carriageway and footpaths
Installation of new fencing to drivers walkway
Construction of drivers walkway in permanent
location
Week 2 Week 3 Week 4 Week 7 Week 8 Week 1 Week 6 Week 5 Week 7
Closure of temporary footbridge; pedestrians able to
use fenced route over bridge
Programme
Programme
Stage 7 – New brickwork parapet construction
New brick parapet constructed around precast parapet. Excavation of drivers walkway.
Road Closure
February to end of June T-1
Footbridge Closed Road Closure from 01st July 2019… Footbridge Closed …Road Closure to Sunday 25th August 2019
Sequencing – Stage 8
Stage 8 visual
New brick parapet construction
Reinstatement of carriageway and footpaths
Installation of new fencing to drivers walkway
Construction of drivers walkway in permanent
location
Week 2 Week 3 Week 4 Week 7 Week 8 Week 1 Week 6 Week 5 Week 7
Closure of temporary footbridge; pedestrians able to
use fenced route over bridge
Programme
Programme
Stage 8 – New brickwork parapet construction
New brick parapet constructed around precast parapet. Installation of drivers walkway to final position. Installation of driver walkway fencing.
Road Closure
February to end of June T-1
Footbridge Closed Road Closure from 01st July 2019… Footbridge Closed …Road Closure to Sunday 25th August 2019
Sequencing – Stage 9
Stage 9 visual
Removal of temporary bridge and replacement of parapets, walls and access gate.
Bridge fully open to all traffic following Highway’s inspection
on Sunday 25th August 2019
Week 2 Week 3 Week 4 Week 7 Week 8 Week 1 Week 6 Week 5 Week 7 Week 8
Programme
Programme
Stage 9 – Final works
Reconstruction of parapets to piers 5 & 7; including wall around drivers steps landing. Reinstatement of drivers access gate. Open bridge to road traffic 25th August.
Future Works
Road Closure
February to end of June T-1
Footbridge Closed Road Closure from 01st July 2019… Footbridge Closed …Road Closure to Sunday 25th August 2019
Artwork
Following consultation with the local councillors we will be providing 4 rendered
panels (2 on each side of the bridge) suitable for future artwork