Page 1: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION

INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

MEP Offsite Manufacturing Kaizen

October 2017

Kevin Labrecque, HarperJustin Brockenbrough, HarperStephen Gibson, I.C. Thomasson

Page 2: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

Agenda

Harper Offsite Manufacturing History

3D Rack Deep Dive

Next Steps - Manufacturing Kaizen

Who We Are

Closing Thoughts

Page 3: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

Agenda

Harper Offsite Manufacturing History

3D Rack Deep Dive

Next Steps - Manufacturing Kaizen

Who We Are

Closing Thoughts

Page 4: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

Who We Are

Kevin LabrecqueSenior Vice President

Justin

BrockenbroughFabrication Manager

Stephen Gibson, P.E. CSCP, PMP

Continuous Improvement Project

Manager

Page 5: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

Who We AreLimbach - 116 years, DB MEP Firm operating from 14 offices in New England, the Mid-Atlantic,

the Southeast, the Midwest and California.

ICT - 75 years, employee-owned, multidisciplinary engineering consulting firm providing designs

for healthcare, commercial, hospitality, recreation, education, institutional clients.

Page 6: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

Agenda

Harper Offsite Manufacturing History

3D Rack Deep Dive

Next Steps - Manufacturing Kaizen

Who We Are

Closing Thoughts

Page 7: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

Who We Are

7 7

“Virtually every other major

industry has been automated in

the last 100 years, except

construction. Imagine ordering a

car, and having thousands of parts

delivered to your driveway, from

hundreds of suppliers, for on site

assembly. This happens in

construction everyday.”

Tim McDonaldPresident & CEO of Onion Flatsgb&d, volume 1, issue 1 July/August 2010

Page 8: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

Gathering the Facts

MEP Solutions

Lang O’Rourke

NG Bailey

Ormandy

M-Tech

Armstrong Balfour Beatty

Skanska

Heron Tower

Converging Themes

North American Growth

in Prefabricated

Elements

Global Movement Towards

Manufactured

Enabling

Tools

Page 9: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

“What’s New is Old”, or is it “What’s Old is New”?

Page 10: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

What is Offsite?

Level 1

Sub Assemblies

Level 2

Non-Volumetric

Level 3

Volumetric

Level 4

Modular Building

Page 11: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

Agenda

Harper Offsite Manufacturing History

3D Rack Deep Dive

Next Steps - Manufacturing Kaizen

Who We Are

Closing Thoughts

Page 12: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

Offsite Manufacturing Experience

Phase 1

Tradition Medical Center

Phase I - 2013

● 190k sf, 82 bed Acute Care Facility

in Port St. Lucie, FL

● Patient floors (3, 4 & 5) corridors

racked

● Fabrication facility 140 miles away

in Sanford

● 80’ of corridor per delivery

● Each floor took < two weeks to

install on site

Page 13: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

Offsite Manufacturing Experience

Tradition Medical Center

Phase II – 2016

● Expansion (Floors 6, 7 & 8)

● 50% of overall mechanical systems

prefabricated

● New fabrication facility in Lake Mary

Phase 2

Page 14: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

Offsite Manufacturing Process

Step One: Engineering Design

Identify Rack Systems &

Locations

Coordinate Systems then

Fit with Racks

Generate Module

Fabrication Drawings

Step Two: Factory

Assembly

Page 15: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

Offsite Manufacturing Process

Step Three: System Install

All Testing: Pressure

Tests

Insulating, Labeling &

Final Inspections

Step Four: Receive at Job

Site

Page 16: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

Offsite Manufacturing Process

Step Five: Install at Job Site

● Raised into Place

● Connected to

Hanger Rods

● Connections

Made Between

Racks

Final Product

Page 17: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

Lessons Learned - Outcomes

Phase 1

Phase 2

● Optimize systems, then fit the racks

● Intra-module dimensions key, inter-

module over done

● Local inspections brought on board

early - get parties on board early

● Fewer personnel on site, less waste,

safer, faster install

● Ergonomic strike zone in shop

● Quality - 360 degree view of install

● Learning curve – after first few racks,

team was asking “should we

continue”, by the third floor, time

savings were significant

● Schedule Time Savings - with

Optimized Shop Crew

Page 18: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

Offsite Innovations & Tools

In Wall Specialty Tools 2D Racks

Multi-Trade 2D Racks

2D Racks Installed

Best Practice

Page 19: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

Agenda

Harper Offsite Manufacturing History

3D Rack Deep Dive

Next Steps - Manufacturing Kaizen

Who We Are

Closing Thoughts

Page 20: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

The Concept: Production to Mass Customization

20

1903to

Today

Page 21: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

The Start: Limbach SoCal Shop Reviews

1200 Sq. Ft.

Opportunities:

• Changed Rack layout – More storage in less floor space

• Opportunities to use AGV’s to move goods to person

• Use vacuum lift system to improve safety and reduce manpower

Page 22: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

The Plan: During The Kaizen Event

Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of

the current process is developed to determine the path of parts or raw materials.

Day 2 Training continues. Then team members collect data. Team goals are written

on Day 2 and an opportunity chart is compiled.

Day 3 The opportunity chart is completed, and solutions are developed to key issues.

A floor plan is created. Equipment is moved where necessary to create a better flow.

Day 4 Improvements are finished, and operators are trained on new processes.

Production using the new methods begins. Measurements are again taken.

Day 5 A 5S/visual workplace activity makes sure the workplace is well organized and

tools, cabinets and storage areas are labeled. Standard operating procedures are

updated. A summary report is prepared for upper management. It includes team goals,

floor plan before and after, key results and savings.

Page 23: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

The Future: Flexible Manufacturing Near/ On-Site

23

Page 24: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

Agenda

Harper Offsite Manufacturing History

3D Rack Deep Dive

Next Steps - Manufacturing Kaizen

Who We Are

Closing Thoughts

Page 25: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

Changing The Question

How you phrase the question is important:

• What parts of this project can we prefabricate?

Versus – Starting with the Assumption of 100% Prefabrication and Asking

• What parts of this project won’t we be able to prefabricate?

“What if the dashboard was the duct?”

Page 26: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

Rhythm, Meter & Measure

Page 27: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

The Tyranny of Common Sense

“Innovation is hard, because it means challenging what we take for granted,

things we think are obvious. The great problem for transformation is the tyranny of

common sense.”

Sir Ken Robinson: Bring on the learning revolution! TED, February 2010

Page 28: MEP Offsite Manufacturing Kaizen Panel 12-Labrecque.pdf · Day 1 The first day is spent on a quick review of lean concepts and strategy. A map of A map of the current process is developed

© LEAN CONSTRUCTION INSTITUTE

CAPTURE AND LEVERAGE THE LEAN ADVANTAGE

Thank You!