DPWES CAPITAL PROJECT SUMMARY REPORT April 2018 Mason Fund 300-C30010 Project Number/SubProject Number HS-000004-001 0 Project Name East County Human Services Center Project Description Planning and Pre-Design services for a new East County Human Services building to be located in the Baileys Crossroads area. Building size is approximately 180,000 gross SF with associated parking. 5,375 Total Project Estimate ($k) Future Funding ($k) Pre-Design Current Status TBD Construction Award Project Complete TBD Remarks County staff continues to finalize data, analyzing several locations for the East County Human Services Building including: continuing in a lease at the Heritage Center, building a new facility at Baily's Crossroads SE Quad site, or buying and renovating a building within the Skyline complex. Options and comparisons will be presented to the Board of Supervisiors Spring 2018. (A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Upload: vuminh

Post on 09-Apr-2018

222 views

Category:

Documents


7 download

TRANSCRIPT

Page 1: Mason - Capital Project Summary Report - Fairfax County · DPWES CAPITAL PROJECT SUMMARY REPORT Jan 2018 Mason Fund 300-C30010 ... Restore ~400 lf of Indian Run using natural channel

DPWES CAPITAL PROJECT SUMMARY REPORT April 2018

Mason

Fund 300-C30010

Project Number/SubProject Number HS-000004-001 0

Project Name East County Human Services Center

Project Description Planning and Pre-Design services for a new East County Human Services building to be located in the Baileys Crossroads area. Building size is approximately 180,000 gross SF with associated parking.

5,375 Total Project Estimate ($k)

Future Funding ($k)

Pre-Design Current Status

TBD Construction Award

Project Complete TBD

Remarks County staff continues to finalize data, analyzing several locations for the East County Human Services Building including: continuing in a lease at the Heritage Center, building a new facility at Baily's Crossroads SE Quad site, or buying and renovating a building within the Skyline complex. Options and comparisons will be presented to the Board of Supervisiors Spring 2018.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 2: Mason - Capital Project Summary Report - Fairfax County · DPWES CAPITAL PROJECT SUMMARY REPORT Jan 2018 Mason Fund 300-C30010 ... Restore ~400 lf of Indian Run using natural channel

DPWES CAPITAL PROJECT SUMMARY REPORT April 2018

Mason

Fund 300-C30010

Project Number/SubProject Number HS-000004-002 0

Project Name SE QUAD REDEVELOPMENT

Project Description Real Estate exchange, master planning, and rezoning to consolidate properties between Co. and private developer for the extension of Seminary Rd, county office site, and private residential development. The development site will provide an option to locate an approx. 180,000 SF county office facility with associated structured parking in the Bailey's Crossroads area.

1,761 Total Project Estimate ($k)

Future Funding ($k)

Construction Current Status

Fall - 2017 Construction Award

Summer - 2018 Project Complete

Remarks Closing for the real estate exchange with Columbia Crossroads, LP occurred on 12/21/17. Hazmat abatement and demolition activities

for the on-site structures are underway and will be complete in late August 2018. Coordination with the Fairfax County Park Authority on

the options for interim use of the site is in progress.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 3: Mason - Capital Project Summary Report - Fairfax County · DPWES CAPITAL PROJECT SUMMARY REPORT Jan 2018 Mason Fund 300-C30010 ... Restore ~400 lf of Indian Run using natural channel

DPWES CAPITAL PROJECT SUMMARY REPORT April 2018

Mason

Fund 300-C30010

Project Number/SubProject Number HS-000013-001 0

Project Name Bailey's Crossroads Community Shelter

Project Description An approximate 23,000 SF replacement facility for the existing Bailey's Shelter. The new facility will be located at 5914 Seminary Road in Bailey's Crossroads.

15,600 Total Project Estimate ($k)

Future Funding ($k)

Construction Current Status

3/12/2018 (A) Construction Award

Summer - 2019 Project Complete

Remarks The Site and Building permits were issued in 2/2018, and VDOT permit was approved on 3/2018. Construction bids were received in 1/2018 and the Notice-to-Proceed was issued on 3/12/18. A groundbreaking ceremony was held on 4/5/18 and construction is underway.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 4: Mason - Capital Project Summary Report - Fairfax County · DPWES CAPITAL PROJECT SUMMARY REPORT Jan 2018 Mason Fund 300-C30010 ... Restore ~400 lf of Indian Run using natural channel

DPWES CAPITAL PROJECT SUMMARY REPORT April 2018

Mason

Fund 300-C30010

Project Number/SubProject Number HS-000021-001 0

Project Name Patrick Henry Shelter

Project Description Demolition of the existing design and construction of a new facility to provide permanent supportive housing, located at 3080 Patrick Henry Drive, Falls Church.

12,000 Total Project Estimate ($k)

Future Funding ($k)

Pre-Design Current Status

TBD Construction Award

Project Complete TBD

Remarks Based on the condominium associations requirements of the existing shelter, options are being explored to renovate or build new on the current site. The

Building Design Branch met with Department of Planning and Zoning on 3/6/18, to discuss use determination and parking requirements. A meeting was

also held with Land Development Services on 4/12/18, to further discuss the site requirements.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 5: Mason - Capital Project Summary Report - Fairfax County · DPWES CAPITAL PROJECT SUMMARY REPORT Jan 2018 Mason Fund 300-C30010 ... Restore ~400 lf of Indian Run using natural channel

DPWES CAPITAL PROJECT SUMMARY REPORT April 2018

Mason

Fund 300-C30070

Project Number/SubProject Number FS-000010-001- 0

Project Name Jefferson Fire Station

Project Description A new, approximately 20,000 SF, five bay fire station and associated site improvements at 3101 Hodge Place, Falls Church, and an off-site temporary fire station.

13,700 Total Project Estimate ($k)

Future Funding ($k)

Construction Current Status

2/7/2018 (A) Construction Award

Winter - 2020 Project Complete

Remarks Notice to proceed was issued to Sorensen Gross (SG) on 2/7/18. SG completed asbestos abatement work on 4/13/18. An on-site meeting was held on 4/2/18 to review the contractor’s proposed location(s) for the Limit of Disturbance and Erosion & Sediment controls. Interior demolition work is in progress.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 6: Mason - Capital Project Summary Report - Fairfax County · DPWES CAPITAL PROJECT SUMMARY REPORT Jan 2018 Mason Fund 300-C30010 ... Restore ~400 lf of Indian Run using natural channel

DPWES CAPITAL PROJECT SUMMARY REPORT April 2018

Mason

Fund 300-C30070

Project Number/SubProject Number FS-000017-001 0

Project Name Edsall Road Fire Station

Project Description Renovation/Expansion of the fire station and associated site improvements and a temporary facility during construction.

12,100 Total Project Estimate ($k)

Future Funding ($k)

Design Current Status

Summer - 2019 Construction Award

Winter - 2021 Project Complete

Remarks The Design Development package for new station was received on 4/2/18. A community meeting was held on 3/19/18. The Value Engineering

workshop was completed on 4/13/18. The temporary facility lease was signed on 2/21/18. The 50% Construction Documents were submitted

on 4/6/18.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 7: Mason - Capital Project Summary Report - Fairfax County · DPWES CAPITAL PROJECT SUMMARY REPORT Jan 2018 Mason Fund 300-C30010 ... Restore ~400 lf of Indian Run using natural channel

DPWES CAPITAL PROJECT SUMMARY REPORT April 2018

Mason

Fund 300-C30070

Project Number/SubProject Number PS-000011-001 0

Project Name Operational Support Bureau

Project Description Renovation/expansion of the Police Operational Support Bureau located at 3911 Woodburn Road, Annandale and associated site improvements.

24,000 Total Project Estimate ($k)

Future Funding ($k)

Pre-Design Current Status

TBD Construction Award

Project Complete TBD

Remarks The Building Design Branch (BDB) approved the final space program and authorized AECOM to further develop the preferred concept. A meeting to review the massing and site layout was held on 3/16/18. AECOM incorporated comments from BDB and a meeting to review the updated massing and space layout was held with the using agency on 4/12/18. Comments from BDB and the using agency are due back to AECOM by 4/25/18.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 8: Mason - Capital Project Summary Report - Fairfax County · DPWES CAPITAL PROJECT SUMMARY REPORT Jan 2018 Mason Fund 300-C30010 ... Restore ~400 lf of Indian Run using natural channel

DPWES CAPITAL PROJECT SUMMARY REPORT April 2018

Mason

Fund 400-C40101

Project Number/SubProject Number SD-000031-146 0

Project Name Stream & Water Quality Improvements

Indian Run Court Stream Restoration

Project Description Restore ~1,500 lf of Indian Run using natural channel design for improved water quality.

2,460 Total Project Estimate ($k)

Future Funding ($k)

Construction Current Status

Spring - 2018 Construction Award

Fall - 2019 Project Complete

Remarks A pre-bid meeting for both Indian Run at Indian Run Court and Indian Run at Columbia Road was held 4/5/18. Bid opening was held on 4/26/18.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 9: Mason - Capital Project Summary Report - Fairfax County · DPWES CAPITAL PROJECT SUMMARY REPORT Jan 2018 Mason Fund 300-C30010 ... Restore ~400 lf of Indian Run using natural channel

DPWES CAPITAL PROJECT SUMMARY REPORT April 2018

Mason

Fund 400-C40101

Project Number/SubProject Number SD-000031-151 0

Project Name Stream & Water Quality Improvements

Turkeycock Run @ Mason District Park

Project Description Restore ~1,600 lf of Turkeycock Run using natural channel design for improved water quality.

1,870 Total Project Estimate ($k)

Future Funding ($k)

Construction Current Status

10/2/2017 (A) Construction Award

Spring - 2018 Project Complete

Remarks Construction by Environmental Quality Resources, LLC is 85% complete.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 10: Mason - Capital Project Summary Report - Fairfax County · DPWES CAPITAL PROJECT SUMMARY REPORT Jan 2018 Mason Fund 300-C30010 ... Restore ~400 lf of Indian Run using natural channel

DPWES CAPITAL PROJECT SUMMARY REPORT April 2018

Mason

Fund 400-C40101

Project Number/SubProject Number SD-000031-162 0

Project Name Stream & Water Quality Improvements

Indian Run @ Columbia Rd. Stream (CA9240)

Project Description Restore ~400 lf of Indian Run using natural channel design for improved water quality.

1,070 Total Project Estimate ($k)

Future Funding ($k)

Construction Current Status

Spring - 2018 Construction Award

Fall - 2019 Project Complete

Remarks A pre-bid meeting for both Indian Run at Indian Run Court and Indian Run at Columbia Road was held 4/5/18. Bid opening was held on 4/26/18.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 11: Mason - Capital Project Summary Report - Fairfax County · DPWES CAPITAL PROJECT SUMMARY REPORT Jan 2018 Mason Fund 300-C30010 ... Restore ~400 lf of Indian Run using natural channel

DPWES CAPITAL PROJECT SUMMARY REPORT April 2018

Mason

400-C40101 Fund

SD-000031-166 0Project Number/SubProject Number

Stream & Water Quality Coon Branch @ Annandale Park (AC82-0002) Project Name Improvements

Project Description Restore ~1,900 lf of Coon Branch using natural channel design for improved water quality.

4,360 Total Project Estimate ($k) 3,289 Future Funding ($k)

Design Current Status

TBD Construction Award

Project Complete TBD

Remarks Stantec Consulting Services, Inc. submitted the concept design on 3/2/18. A concept design charrette walk and a concept design review meeting were held in April.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 12: Mason - Capital Project Summary Report - Fairfax County · DPWES CAPITAL PROJECT SUMMARY REPORT Jan 2018 Mason Fund 300-C30010 ... Restore ~400 lf of Indian Run using natural channel

DPWES CAPITAL PROJECT SUMMARY REPORT April 2018

Mason

400-C40101 Fund

SD-000031-185 0Project Number/SubProject Number

Stream & Water Quality Backlick Run@Bren Mar Drive Seg2(CA9205A) Project Name Improvements

Project Description Stabilize ~1,775 lf of Backlick Run to halt channel lateral migration and improve water quality.

4,790 Total Project Estimate ($k) 4,590 Future Funding ($k)

Design Current Status

TBD Construction Award

Project Complete TBD

Remarks Wetland Studies and Solutions, Inc. delivered the concept design on 2/9/18. County comments were due by 4/25/18.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 13: Mason - Capital Project Summary Report - Fairfax County · DPWES CAPITAL PROJECT SUMMARY REPORT Jan 2018 Mason Fund 300-C30010 ... Restore ~400 lf of Indian Run using natural channel

DPWES CAPITAL PROJECT SUMMARY REPORT April 2018

Mason

Fund 690-C69300

Project Number/SubProject Number WW-000001-01 0

Project Name Pumping Stations Holmes Run Pump Station Rehab

Project Description Rehabilitation of the Holmes Run Pump Station located at 6623 Dearborn Drive in Falls Church. The existing building and equipment needs to be

evaluated for potential rehabilitation. The associated force main was recently lined.

9,000 Total Project Estimate ($k)

Future Funding ($k)

Pre-Design Current Status

TBD Construction Award

Project Complete TBD

Remarks The Wastewater Design and Construction Division and Wastewater Collection Division are currently determining the scope of work for this project. The Preliminary Engineering Study will begin in spring 2018.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 14: Mason - Capital Project Summary Report - Fairfax County · DPWES CAPITAL PROJECT SUMMARY REPORT Jan 2018 Mason Fund 300-C30010 ... Restore ~400 lf of Indian Run using natural channel

DPWES CAPITAL PROJECT SUMMARY REPORT April 2018

Mason

Fund 690-C69300

Project Number/SubProject Number WW-000007-01 0

Project Name Collection System Replacement and Rehabilitation

Colfax Emergency Sewer Rehabilitation

Project Description This is an emergency project to repair/replace approximately 1,250 feet of 10” cast iron wastewater sewer pipe from manhole 004 to manhole 168.

1,000 Total Project Estimate ($k) 1,000 Future Funding ($k)

Post-Construction Current Status

9/27/2017 (A) Construction Award

3/27/2018 (A) Project Complete

Remarks Phase II lining is complete as of 3/27/18. Site rehabilitation ongoing.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 15: Mason - Capital Project Summary Report - Fairfax County · DPWES CAPITAL PROJECT SUMMARY REPORT Jan 2018 Mason Fund 300-C30010 ... Restore ~400 lf of Indian Run using natural channel

DPWES CAPITAL PROJECT SUMMARY REPORT April 2018

Mason

690-C69300 Fund

WW-000008-00 0Project Number/SubProject Number

Force Main Rehabilitation Ravenwood PS & FM Replacement Project Name

Project Description Replacement of the Ravenwood Pump Station and 100 LF 6" diameter sanitary sewer force main.

Total Project Estimate ($k) 500

Future Funding ($k) 350

Design Current Status

Winter - 2019 Construction Award

Summer - 2019 Project Complete

Remarks Task Order #RK17-16 for design was authorized on 1/23/18. Thirty-five percent design plans due on 6/5/18.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 16: Mason - Capital Project Summary Report - Fairfax County · DPWES CAPITAL PROJECT SUMMARY REPORT Jan 2018 Mason Fund 300-C30010 ... Restore ~400 lf of Indian Run using natural channel

DPWES CAPITAL PROJECT SUMMARY REPORT

April 2018

Mason

Fund 690-C69300

Project Number/SubProject Number WW-000008-00 0

Project Name Force Main Rehabilitation Tyson's Dodge FM Rehab

Project Description Rehabilitation with Cured-In-Place Pipe lining of the Tysons Dodge sanitary sewer force main consisting of 2,217 LF of 6" diameter cast iron pipe.

1,800 Total Project Estimate ($k)

Future Funding ($k)

Design Current Status

Fall - 2018 Construction Award

Spring - 2019 Project Complete

Remarks Thirty-five percent design review meeting was held on 3/20/18. Design is progressing to 70%, plans due 4/30/18.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December