DPWES CAPITAL PROJECT SUMMARY REPORT Dec 2020 Providence 300-C30010 Fund GF-000023-001 0 Project Number/SubProject Number Massey Building Demolition Project Name Project Description Demolition of Massey Building, Massey Annex Demolition of Massey, Massey Annex, and Page Avenue House buildings, including hazardous materials abatement and site restoration. Total Project Estimate ($k) 20,000 Future Funding ($k) Current Status Post-Construction Construction Award 9/20/2018 (A) Project Complete 8/31/2020 (A) Remarks Project is 100% complete. (A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Upload: others

Post on 26-Sep-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: DPWES Capital Project Summary Report - Apr 2020 - Providence...DPWES CAPITAL PROJECT SUMMARY REPORT Apr 2020 Providence Fund 300-C30070 Project Number/SubProject Number OP-000008-001

DPWES CAPITAL PROJECT SUMMARY REPORT

Dec 2020

Providence

300-C30010 Fund

GF-000023-001 0Project Number/SubProject Number

Massey Building Demolition Project Name

Project Description Demolition of Massey Building, Massey Annex Demolition of Massey, Massey Annex, and Page Avenue House buildings, including hazardous materials abatement and site restoration.

Total Project Estimate ($k) 20,000

Future Funding ($k)

Current Status Post-Construction

Construction Award 9/20/2018 (A)

Project Complete 8/31/2020 (A)

Remarks Project is 100% complete.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 2: DPWES Capital Project Summary Report - Apr 2020 - Providence...DPWES CAPITAL PROJECT SUMMARY REPORT Apr 2020 Providence Fund 300-C30070 Project Number/SubProject Number OP-000008-001

DPWES CAPITAL PROJECT SUMMARY REPORT

Dec 2020

Providence

Fund 300-C30070

Project Number/SubProject Number 2G25-104-000 0

Project Name Judicial (Massey) Complex Master Plan

Project Description The Master Plan will include strategic planning of land use and development planning for the best use and integration within the surrounding area.

1,025 Total Project Estimate ($k) Future Funding ($k)

Pre-Design Current Status

NAConstruction Award

Project Complete NA

Remarks The selected Master Plan waas finalized and submitted for review and comment on November 10, 2020. All comments from stakeholders and the Land Use Redevelopment team were reconciled and included in the final report on December 21, 2020.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 3: DPWES Capital Project Summary Report - Apr 2020 - Providence...DPWES CAPITAL PROJECT SUMMARY REPORT Apr 2020 Providence Fund 300-C30070 Project Number/SubProject Number OP-000008-001

DPWES CAPITAL PROJECT SUMMARY REPORT

Dec 2020

Providence

Fund 300-C30070

Project Number/SubProject Number AD-000002-002 0

Project Name Adult Dentention Center-2018 Security

Project Description Upgrade of security systems at the Adult Detention Center. This is a sub-project to the Adult Detention Center - 2018 project. The project will be completed in phases.

26,600 Total Project Estimate ($k) 24,300 Future Funding ($k)

Design Current Status

Spring - 2021 Construction Award

Fall - 2023 Project Complete

Remarks Design work began on 3/13/2020, and is scheduled to be completed in early 2021. Construction documents are 70% complete. Construction start is scheduled for mid-2021.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 4: DPWES Capital Project Summary Report - Apr 2020 - Providence...DPWES CAPITAL PROJECT SUMMARY REPORT Apr 2020 Providence Fund 300-C30070 Project Number/SubProject Number OP-000008-001

DPWES CAPITAL PROJECT SUMMARY REPORT

Dec 2020

Providence

Fund 300-C30070

Project Number/SubProject Number AD-000002-003 0

Project Name Adult Detention Center - 2018 Capital Renewal

Project Description CAPITAL RENEWAL - Replacement of priority mechanical and electrical systems at the Adult Detention Center.

30,900 Total Project Estimate ($k) Future Funding ($k)

Pre-Design Current Status

TBD Construction Award

Project Complete TBD

Remarks The final revised fee proposal for the full scope of the Capital Renewal design by HOK was submitted 11/8/2020. The NIP package is being processed for approval. Design work is scheduled to start in February 2021.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 5: DPWES Capital Project Summary Report - Apr 2020 - Providence...DPWES CAPITAL PROJECT SUMMARY REPORT Apr 2020 Providence Fund 300-C30070 Project Number/SubProject Number OP-000008-001

DPWES CAPITAL PROJECT SUMMARY REPORT

Dec 2020

Providence

Fund 300-C30070

Project Number/SubProject Number AD-000002-004 0

Project Name Adult Detention Center - 2018 Capital Renewal West HW System

Project Description This sub-project is part of the Capital Renewal portion of the overall project and replaces the Domestic and Heating Water plant in the ADC West Building.

4,500 Total Project Estimate ($k) Future Funding ($k)

Design Current Status

Winter - 2021 Construction Award

Fall - 2022 Project Complete

Remarks The construction documents were issued for bid on 12/5/2020. Building Permit has been approved by all departments with exception of Wastewater. Construction bids are due 1/11/2021. Construction is scheduled to start in March 2021.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 6: DPWES Capital Project Summary Report - Apr 2020 - Providence...DPWES CAPITAL PROJECT SUMMARY REPORT Apr 2020 Providence Fund 300-C30070 Project Number/SubProject Number OP-000008-001

DPWES CAPITAL PROJECT SUMMARY REPORT

Dec 2020

Providence

300-C30070 Fund

CF-000003-002 0Project Number/SubProject Number

Courtroom Renovations Phase III Design Project Name

Project Description Interior Renovation of 22 Existing Courtrooms: Phase I - in Post-Construction, Phase II in Construction, Phase III & IV - in Design.

21,620 Total Project Estimate ($k) 4,180 Future Funding ($k)

Construction Current Status

12/29/2020 (A) Construction Award

Summer - 2022 Project Complete

Remarks The design of the six courtrooms of Phase III of the Courtroom Renovations project is complete. The building permit was obtained. Contractor

prequalifications are complete. The project was advertised for bid in late-August 2020.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 7: DPWES Capital Project Summary Report - Apr 2020 - Providence...DPWES CAPITAL PROJECT SUMMARY REPORT Apr 2020 Providence Fund 300-C30070 Project Number/SubProject Number OP-000008-001

DPWES CAPITAL PROJECT SUMMARY REPORT

Dec 2020

Providence

300-C30070 Fund

CF-000003-003 0Project Number/SubProject Number

Courtroom Renovations Phase IV Design Project Name

Project Description Interior Renovation of 22 Existing Courtrooms: Phase I - in Post-Construction, Phase II - in Construction, Phase III and IV in Design.

21,620 Total Project Estimate ($k) 4,180 Future Funding ($k)

Design Current Status

Summer - 2022 Construction Award

Fall - 2024 Project Complete

Remarks The design of the five courtrooms of Phase IV of the Courtroom Renovations project is complete. The building permit was obtained. The project

will go into construction in 2022 upon completion of the Phase III construction and technology integration.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 8: DPWES Capital Project Summary Report - Apr 2020 - Providence...DPWES CAPITAL PROJECT SUMMARY REPORT Apr 2020 Providence Fund 300-C30070 Project Number/SubProject Number OP-000008-001

DPWES CAPITAL PROJECT SUMMARY REPORT

Dec 2020

Providence

Fund 300-C30070

Project Number/SubProject Number FS-000013-001 0

Project Name Merrifield Fire Station

Project Description Renovation, minor addition and assiciated site improvments to the existing fire station located at 8739 Lee Highway, Fairfax.

9,000 Total Project Estimate ($k) Future Funding ($k)

Construction Current Status

11/7/2019 (A) Construction Award

Winter - 2022 Project Complete

Remarks Sumter Contracting has completed the Phase 1 work including the temporary modular building, the exercise and the locker rooms. Phase 2 work including

renovations to the apparatus bays and the living areas is ongoing. Moseley Architects continues to review shop drawings and respond to RFI's. The

project has been delayed by 73 calendar days due to Covid 19 related safety precautions.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 9: DPWES Capital Project Summary Report - Apr 2020 - Providence...DPWES CAPITAL PROJECT SUMMARY REPORT Apr 2020 Providence Fund 300-C30070 Project Number/SubProject Number OP-000008-001

DPWES CAPITAL PROJECT SUMMARY REPORT

Dec 2020

Providence

Fund 300-C30070

Project Number/SubProject Number FS-000042-001 0

Project Name Tysons Fire Station

Project Description Redevelopment of transit site located at 8300 Jones Branch Drive, McLean, VA to incorporate a permanent approximately 20,000 SF, five-bay fire station and seven-bay bus transit facility, associated buildings and roadway improvements.

20,000 Total Project Estimate ($k) 14,600 Future Funding ($k)

Pre-Design Current Status

Winter - 2023 Construction Award

Spring - 2024 Project Complete

Remarks The consultant Grimm + Parker Architects has been selected to provide design and construction administration services for the project. The project kicked off in December 2020. The Board of Supervisors approved the use of the Construction Management at Risk as a construction delivery method on 12/8/2020.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 10: DPWES Capital Project Summary Report - Apr 2020 - Providence...DPWES CAPITAL PROJECT SUMMARY REPORT Apr 2020 Providence Fund 300-C30070 Project Number/SubProject Number OP-000008-001

DPWES CAPITAL PROJECT SUMMARY REPORT

Dec 2020

Providence

Fund 300-C30070

Project Number/SubProject Number FS-000043-001 0

Project Name Tysons East Fire Station

Project Description New three-bay fire station located on Old Meadow Lane in Tysons provided by a Tysons proffer.

Total Project Estimate ($k) 800

Future Funding ($k)

Construction Current Status

9/30/2019 (A) Construction Award

Spring - 2021 Project Complete

Remarks Sprinkler installation and stormwater facilities began in 9/20. Interior and exterior finishes, and apparatus bay slab work began in 11/20. Trade

inspections continue and concealment inspections began early 12/20. Electrical, mechanical, site landscaping and bioretention work continues. Interior

finishes and HVAC equipment start-up began week of 12/14/20. Pre-occupancy meeting was held on 12/22/20. Fire alarm testing is scheduled for late

1/21.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 11: DPWES Capital Project Summary Report - Apr 2020 - Providence...DPWES CAPITAL PROJECT SUMMARY REPORT Apr 2020 Providence Fund 300-C30070 Project Number/SubProject Number OP-000008-001

DPWES CAPITAL PROJECT SUMMARY REPORT

Dec 2020

Providence

Fund 300-C30070

Project Number/SubProject Number OP-000008-001 0

Project Name Police Evidence Storage Annex

Project Description Replacement of the warrant desk and main evidence storage building located at 10600 Page Avenue, Fairfax with a new Evidence Storage

Building.

18,000 Total Project Estimate ($k) Future Funding ($k)

Pre-Design Current Status

TBD Construction Award

Project Complete TBD

Remarks The Architect provided a final program report on 12/2/2020. The Police Evidence Storage will be collocated with Building 1 as part of Phase I of

the Massey Complex Master Plan.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 12: DPWES Capital Project Summary Report - Apr 2020 - Providence...DPWES CAPITAL PROJECT SUMMARY REPORT Apr 2020 Providence Fund 300-C30070 Project Number/SubProject Number OP-000008-001

DPWES CAPITAL PROJECT SUMMARY REPORT

Dec 2020

Providence

Fund 400-C40101

Project Number/SubProject Number SD-000031-135 0

Project Name Stream & Water Quality Improvements

Crook Branch @ Mantua Elementary (AC9220/AC9221)

Project Description Restore ~3,900 linear feet of stream channel using natural channel des ign to improve water quality.

7,157 Total Project Estimate ($k) Future Funding ($k)

Construction Current Status

Winter - 2021 Construction Award

Fall - 2022 Project Complete

Remarks The construction pre-qualiification process is complete. Bid advertisement is scheduled for February 2021.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 13: DPWES Capital Project Summary Report - Apr 2020 - Providence...DPWES CAPITAL PROJECT SUMMARY REPORT Apr 2020 Providence Fund 300-C30070 Project Number/SubProject Number OP-000008-001

DPWES CAPITAL PROJECT SUMMARY REPORT

Dec 2020

Providence

Fund 400-C40101

Project Number/SubProject Number SD-000031-142-B 0

Project Name Stream & Water Quality Improvements

Nottoway Park BMP Retrofits - Phase II

Project Description Stormwater BMP retrofits for improved water quality.

1,420 Total Project Estimate ($k) Future Funding ($k)

Construction Current Status

4/15/2019 (A) Construction Award

6/2/2020 (A) Project Complete

Remarks Construction by Environmental Quality Resources, LLC began on 7/12/19, and reached substantial completion on 6/2/20. Final p lanting was installed in fall 2020 by Ashton Manor Environmental, LLC. The project is under warranty until 6/2/21.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 14: DPWES Capital Project Summary Report - Apr 2020 - Providence...DPWES CAPITAL PROJECT SUMMARY REPORT Apr 2020 Providence Fund 300-C30070 Project Number/SubProject Number OP-000008-001

DPWES CAPITAL PROJECT SUMMARY REPORT

Dec 2020

Providence

Fund 400-C40101

Project Number/SubProject Number SD-000031-184 0

Project Name Stream & Water Quality Improvements

Scotts Run@Old Meadow Rd(SC82-0002)

Project Description Restore ~2,350 linear feet of Scotts Run between Old Meadow Road and Colshire Meadow Drive and restore up to

~1,100 lf of concrete ditch above Old Meadow Road.

4,466 Total Project Estimate ($k) Future Funding ($k)

Construction Current Status

12/8/2020 (A) Construction Award

Fall - 2021 Project Complete

Remarks Construction contract with Avon Corporation was signed on 12/8/20. Notice-to-Proceed was issued for 12/28/20.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 15: DPWES Capital Project Summary Report - Apr 2020 - Providence...DPWES CAPITAL PROJECT SUMMARY REPORT Apr 2020 Providence Fund 300-C30070 Project Number/SubProject Number OP-000008-001

DPWES CAPITAL PROJECT SUMMARY REPORT

Dec 2020

Providence

400-C40101 Fund

SD-000031-219 0Project Number/SubProject Number

Stream & Water Quality Long BR N @ Arlington BLVD & Robin Rdg (Mult) Project Name Improvements

Project Description Restore ~4,500 linear feet of stream channel and enhance the riparian corridor to improve water quality.

7,572 Total Project Estimate ($k) 6,000 Future Funding ($k)

Design Current Status

TBD Construction Award

Project Complete TBD

Remarks Wetland Studies and Solutions, Inc. is scheduled to submit the 65% design by 2/28/21.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 16: DPWES Capital Project Summary Report - Apr 2020 - Providence...DPWES CAPITAL PROJECT SUMMARY REPORT Apr 2020 Providence Fund 300-C30070 Project Number/SubProject Number OP-000008-001

DPWES CAPITAL PROJECT SUMMARY REPORT

Dec 2020

Providence

400-C40101 Fund

SD-000031-226 0Project Number/SubProject Number

Pimmit Run Watershed Pimmit Run @ George C Marchall HS Project Name

Project Description Restore ~2,000 linear feet of stream channel and enhance the riparian corridor to improve water quality.

3,996 Total Project Estimate ($k) 2,750 Future Funding ($k)

Design Current Status

TBD Construction Award

Project Complete TBD

Remarks A concept design plan was received from Wetland Studies and Solutions, Inc. on 8/7/20. Easement plats were prepared and provided to Land Acquition Division for easement acquisition. Easement acquisition to be completed by 2/26/21.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 17: DPWES Capital Project Summary Report - Apr 2020 - Providence...DPWES CAPITAL PROJECT SUMMARY REPORT Apr 2020 Providence Fund 300-C30070 Project Number/SubProject Number OP-000008-001

DPWES CAPITAL PROJECT SUMMARY REPORT

Dec 2020

Providence

400-C40101 Fund

SD-000031-227 0Project Number/SubProject Number

Nutley Pond (WP0020) @ Virginia Project Name Center

Project Description Rehabilitation of existing pond to the original design and enhancment.

1,736 Total Project Estimate ($k) 1,576 Future Funding ($k)

Design Current Status

TBD Construction Award

Project Complete TBD

Remarks A 95% design plan from Gannett Fleming (Gannett) was received on 10/20/20. A design review meeting was conducted on 12/18/20. The comments were forwarded to Gannett 1/5/21.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 18: DPWES Capital Project Summary Report - Apr 2020 - Providence...DPWES CAPITAL PROJECT SUMMARY REPORT Apr 2020 Providence Fund 300-C30070 Project Number/SubProject Number OP-000008-001

DPWES CAPITAL PROJECT SUMMARY REPORT

Dec 2020

Providence

400-C40101 Fund

SD-000031-238 0Project Number/SubProject Number

Rocky Branch @ Hickory Hollow(DF82-Project Name 0021)

Project Description Restore - 3,430 lf of stream channel and enhance the riparian corridor to improve water quality.

6,002 Total Project Estimate ($k) 5,431 Future Funding ($k)

Design Current Status

TBD Construction Award

Project Complete TBD

Remarks Wetland Studies and Solutions, Inc. (WSSI) submitted a concept design plan on 12/10/20. Comments on concept design plan are due to WSSI by 1/29/21.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 19: DPWES Capital Project Summary Report - Apr 2020 - Providence...DPWES CAPITAL PROJECT SUMMARY REPORT Apr 2020 Providence Fund 300-C30070 Project Number/SubProject Number OP-000008-001

DPWES CAPITAL PROJECT SUMMARY REPORT

Dec 2020

Providence

400-C40101 Fund

SD-000031-239 0Project Number/SubProject Number

Rocky Br Trib @ Ashlawn Park (DF82-Project Name 0023)

Project Description Restore — 1,740 lf of stream channel and enhance the riparian corridor to improve water quality.

2,389 Total Project Estimate ($k) 2,174 Future Funding ($k)

Design Current Status

TBD Construction Award

Project Complete TBD

Remarks Wetland Studies and Solutions, Inc. (WSSI) submitted a concept design plan on 12/10/20. Comments on concept design plan are due to WSSI by 1/29/21.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 20: DPWES Capital Project Summary Report - Apr 2020 - Providence...DPWES CAPITAL PROJECT SUMMARY REPORT Apr 2020 Providence Fund 300-C30070 Project Number/SubProject Number OP-000008-001

DPWES CAPITAL PROJECT SUMMARY REPORT

Dec 2020

Providence

Fund 690-C69300

Project Number/SubProject Number WW-000001-007-A 0

Project Name Pumping Stations Four Smith & Loveless Pump Station Rehabilitation

Project Description Rehabilitation of four Smith and Loveless Pump Stations (PS): Lakevale PS (10209 Kenbrooke Ct, Vienna), High Ridge PS (3890 Fairfax Ridge Rd, Fairfax), Weid PS (8418A Holly Leaf Drive, McLean), and Langley Oaks PS (6526 Heather Brook Ct, McLean).

3,250 Total Project Estimate ($k) Future Funding ($k)

Construction Current Status

9/30/2019 (A) Construction Award

Winter - 2021 Project Complete

Remarks The Contractor is working on the Weid Pump Station (PS) where substantial completion will be in January 2021. The Contractor installed the

by-pass connection at Langely Oaks PS in December 2020.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 21: DPWES Capital Project Summary Report - Apr 2020 - Providence...DPWES CAPITAL PROJECT SUMMARY REPORT Apr 2020 Providence Fund 300-C30070 Project Number/SubProject Number OP-000008-001

DPWES CAPITAL PROJECT SUMMARY REPORT

Dec 2020

Providence

Fund 690-C69300

Project Number/SubProject Number WW-000001-017 0

Project Name Pumping Stations Oak Marr Pump Station Rehab

Project Description Provide Preliminary Engineering Report to rehabilitate Oak Marr Pump Station (PS) (located at 2913A Elmesmeade Court, Oakton, VA). Built in

1986, PS has capacity of 0.25 MGD. Project to assess major PS components & determine best upgrading approach.

2,700 Total Project Estimate ($k) 2,700 Future Funding ($k)

Pre-Design Current Status

TBD Construction Award

Project Complete TBD

Remarks Currently scoping the the design task order with A/E. Implementing the selected alternative from the study.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 22: DPWES Capital Project Summary Report - Apr 2020 - Providence...DPWES CAPITAL PROJECT SUMMARY REPORT Apr 2020 Providence Fund 300-C30070 Project Number/SubProject Number OP-000008-001

DPWES CAPITAL PROJECT SUMMARY REPORT

Dec 2020

Providence

Fund 690-C69300

Project Number/SubProject Number WW-000032-002 0

Project Name Gravity Sewer Capacity Improvements Tyson's West

Project Description The project (located in Tysons Corner) consists of a new 25 million gallons per day (MGD) wastewater pump station, five miles of 30" DIP forcemain, three miles of 48" gravity sewer, demolition of the existing pump station.

106,000 Total Project Estimate ($k) Future Funding ($k)

Pre-Design Current Status

TBD Construction Award

Project Complete TBD

Remarks Capital Facilities is currently successfully working with the property owner of the proposed pump station site. The Draft Preliminary Engineering

Report (PER) comment response meeting was 12/1/20. Forcemain routing discussion on was on 12/2/20. Executive Team Debriefing was on

12/2/20. Currently working on a contract amendment for the detailed design phase.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 23: DPWES Capital Project Summary Report - Apr 2020 - Providence...DPWES CAPITAL PROJECT SUMMARY REPORT Apr 2020 Providence Fund 300-C30070 Project Number/SubProject Number OP-000008-001

DPWES CAPITAL PROJECT SUMMARY REPORT

Dec 2020

Providence

Fund 690-C69300

Project Number/SubProject Number WW-000032-008 0

Project Name Gravity Sewer Capacity Improvements Lakevale Estates Discharge Realignment

Project Description The force main & gravity sewer system downstream of Lakevale Pump Station near Lakevale Estates is in need of capacity improvements & a discharge realignment. Need identified in 2019 in response to sewer backups when pump station operates.

1,970 Total Project Estimate ($k) Future Funding ($k)

Design Current Status

Fall - 2021 Construction Award

Fall - 2022 Project Complete

Remarks Completed a design kick-off meeting with Dewberry. Task Order (TO) has been signed, funds reserved, and site visit took place 12/30/20. SAM TO signed. Drawdown test scheduled for January 2021. Property owners to be notified of upcoming survey work in January 2021.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December

Page 24: DPWES Capital Project Summary Report - Apr 2020 - Providence...DPWES CAPITAL PROJECT SUMMARY REPORT Apr 2020 Providence Fund 300-C30070 Project Number/SubProject Number OP-000008-001

DPWES CAPITAL PROJECT SUMMARY REPORT

Dec 2020

Providence

690-C69300 Fund

WW-000032-009 0Project Number/SubProject Number

Gravity Sewer Capacity Improvements Merrifield Capacity Upgrade Project Name

Project Description As the Merrifield area grows in population due to its redevelopment, so does the gravity sewer that provides the community. This project

includes the upsizing of approximately 600 LF of 12-inch diameter gravity sewer.

1,500 Total Project Estimate ($k) Future Funding ($k)

Design Current Status

Spring - 2021 Construction Award

Summer - 2021 Project Complete

Remarks Wastewater Design & Construction Division completed a design kick-off meeting with Jacobs. Task Order has been signed, funds reserved, upcoming site visit is being coordinated. SAM contract has been designated and utility location coordination has started. Coordination with property owners for geotechnical survey has taken place. Coordination with the Land Acquisition Division for Letters of Permission has begun.

(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December