• SITUATED NEAR WITNEY TOWN IN OXFORDSHIRE

• DURATION: 01.02 – 25.04.2015

• 13 Mw POWER INSTALLED

• SADEF STRUCTURE, BYD SOLAR MODULES OF 255 Wp

• CENTRALIZED POWER CONNECTION: SMA INVERTERS

DUTIES: Coordination the works for following categories of operations:

1.Ramming and concreting of the foundation piles

2.Mounting the Sadef structure

3.Mounting the BYD solar panels

4.Mounting the AC, DC and MV cables

5.Foundations for the transformers

6.Mounting the transformers

WESTERFIELD SOLAR FARMUNITED KINGDOM

Page 3: Marius Soare Project  Portfolio Solar Farms

WESTERFIELD SOLAR FARMUNITED KINGDOM

Page 4: Marius Soare Project  Portfolio Solar Farms

SOLAR FARMS : POSITION ON GOOGLE EARTH (file Projects Google Earth.kmz attached)

ROMANIAN SOLAR FARMS

Page 5: Marius Soare Project  Portfolio Solar Farms

‘LUKOIL’ SOLAR FARM – 9 Mw

• SITUATED NEAR PLOIESTI TOWN IN PRAHOVA COUNTY

• DURATION: 01.2014 - 03.2015

• 9 Mw POWER INSTALLED

• ALUMIL STRUCTURE, REC SOLAR MODULES OF 255 Wp

• CENTRALIZED POWER CONNECTION: POWER ONE INVERTERS

DUTIES: Coordination the works for following categories of operations:

1.Ramming and concreting of the foundation piles

2.Mounting the Alumil structure

3.Mounting the REC solar panels

4.Mounting the AC, DC and MV cables

5.Foundations for the transformers

6.Mounting the transformers

7.Mounting the inverters

8.Supervising the testes and

connection to the grid

Page 6: Marius Soare Project  Portfolio Solar Farms

‘LUKOIL’ SOLAR FARM – 9 Mw

Page 7: Marius Soare Project  Portfolio Solar Farms

‘MAXINENI’ SOLAR FARM – 5.5 Mw

• SITUATED NEAR BRAILA TOWN IN BRAILA COUNTY

• DURATION: 08.2013 - 10.2013

• 5.5 Mw POWER INSTALLED

• ALUMIL STRUCTURE, PHONO SOLAR MODULES OF 240 Wp

• CENTRALIZED POWER CONNECTION: ABB INVERTERS

DUTIES: Coordination the works for following categories of operations:

1.Ramming the foundation piles

2.Mounting the Alumil structure

3.Mounting the PHONO SOLAR panels

4.Mounting the AC, DC and MV cables

5.Foundations for the transformers

6.Mounting the transformers

7.Mounting the inverters

8.Supervising the testes and

connection to the grid

Page 8: Marius Soare Project  Portfolio Solar Farms

‘MAXINENI’ SOLAR FARM – 5.5 Mw

Page 9: Marius Soare Project  Portfolio Solar Farms

‘VIDELE’ SOLAR FARM – 2.2 Mw

• SITUATED NEAR VIDELE TOWN IN GIURGIU COUNTY

• DURATION: 10.2013 - 11.2013

• 2.2 Mw POWER INSTALLED

• ALUMIL STRUCTURE, AXITEX SOLAR MODULES OF 245 Wp

• CENTRALIZED POWER CONNECTION: ABB INVERTERS

DUTIES: Coordination the works for following categories of operations:

1.Ramming the foundation piles

2.Mounting the Alumil structure

3.Mounting the AXITEX SOLAR panels

4.Mounting the AC, DC and MV cables

5.Foundations for the transformers

6.Mounting the transformers

7.Mounting the inverters

8.Supervising the testes and

connection to the grid

Page 10: Marius Soare Project  Portfolio Solar Farms

‘VIDELE’ SOLAR FARM – 2.2 Mw

Page 11: Marius Soare Project  Portfolio Solar Farms

‘SLOBOZIA’ SOLAR FARM – 1.9 Mw

• SITUATED NEAR SLOBOZIA TOWN IN IALOMITA COUNTY

• DURATION: 05.2013 - 07.2013

• 1.9 Mw POWER INSTALLED

• ALUMIL STRUCTURE, CONERGY SOLAR MODULES OF 250 Wp

• POWER CONNECTION: 65 pcs POWER ONE INVERTERS (27.6 Kv)

DUTIES: Coordination the works for following categories of operations:

1.Ramming the foundation piles

2.Mounting the Alumil structure

3.Mounting the CONERGY SOLAR panels

4.Mounting the AC, DC and MV cables

5.Foundations for the transformers

6.Mounting the transformers

7.Mounting the inverters

8.Supervising the testes and

connection to the grid

Page 12: Marius Soare Project  Portfolio Solar Farms

‘SLOBOZIA’ SOLAR FARM – 1.9 Mw

Page 13: Marius Soare Project  Portfolio Solar Farms

‘APRODEX’ SOLAR FARM – 0.50 Mw

• SITUATED IN BUCHAREST, ROOFTOP MOUNTING STRUCTURE

• DURATION: 08.2014 - 09.2014

• 0.50 Mw POWER INSTALLED

• ALUMIL STRUCTURE, CONERGY SOLAR MODULES OF 250 Wp

• POWER CONNECTION: 18 pcs POWER ONE INVERTERS (27.6 Kv)

DUTIES: Coordination the works for following categories of operations:

1.Preparing the foundation connections on roof structure

2.Mounting the Alumil structure

3.Mounting the CONERGY SOLAR panels

4.Mounting the AC, DC and MV cables

5.Mounting the inverters

6.Supervising the testes and

connection to the grid

Page 14: Marius Soare Project  Portfolio Solar Farms

‘APRODEX’ SOLAR FARM – 0.50 Mw

Page 15: Marius Soare Project  Portfolio Solar Farms

‘LECHINTA’ SOLAR FARM – 5 Mw

• SITUATED IN LECHINTA TOWN IN BISTRITA COUNTY

• DURATION: 07.2012 - 11.2012

• 5 Mw POWER INSTALLED

• ALUMIL STRUCTURE, SOLAR WORLD MODULES OF 235 Wp

• POWER CONNECTION: POWER ONE INVERTERS

DUTIES: Coordination the works for following categories of operations:

1.Ramming the foundation piles

2.Mounting the Alumil structure

3.Mounting the SOLAR WORLD panels

4.Mounting the AC, DC and MV cables

5.Foundations for the transformers

6.Mounting the transformers

7.Mounting the inverters

8.Supervising the testes and

connection to the grid

Page 16: Marius Soare Project  Portfolio Solar Farms