Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen, Ethel Sheffer,
Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26933
RESOLVED That the Design Commission, having considered designs for the installation of
rooftop mechanical equipment, Queens District 7 Garage, 120-15 31st Avenue, Flushing,
Queens, submitted by the Department of Design and Construction and the Department of
Sanitation, represented by exhibits 5990-N, O, P & Q of record in this matter, hereby gives to
the same unanimous preliminary and final approval. Commissioner Hawkinson recused herself.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26960
RESOLVED That the Design Commission, having considered designs for the construction of a
parking lot adjacent to Building 280, Flushing Avenue, North Oxford Street, Ordinance Avenue,
and Fifth Street, Brooklyn Navy Yard Industrial Park, Brooklyn, submitted by the Brooklyn Navy
Yard Development Corporation, represented by exhibits 6063-OZ, PA, PB & PC of record in
this matter, hereby gives to the same unanimous preliminary and final approval.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26961
RESOLVED That the Design Commission, having considered designs for the reconstruction of
a parking lot adjacent to Building 5, Market Street, Eighth Avenue, Paulding Street, and Sixth
Street, Brooklyn Navy Yard Industrial Park, Brooklyn, submitted by the Brooklyn Navy Yard
Development Corporation, represented by exhibits 6063-PD, PE, PF & PG of record in this
matter, hereby gives to the same unanimous preliminary and final approval with the
understanding that (1) all existing catch basins will be fully cleaned after the reconstruction
work is complete and (2) should additional funds be obtained, the drainage and grading in the
parking lot will be re-studied.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26962
RESOLVED That the Design Commission, having considered designs for the installation of a
prototypical newsstand, 1396 Second Avenue, northeast corner of Second Avenue and East
72nd Street, Manhattan, submitted by the Department of Consumer Affairs and the
Department of Transportation, represented by exhibits 7447-A, B & C of record in this matter,
hereby gives to the same unanimous preliminary and final approval.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26963
RESOLVED That the Design Commission, having considered designs for the installation of a
prototypical newsstand, 3100 47th Avenue, southeast corner of 47th Avenue and 31st Street,
Long Island City, Queens, submitted by the Department of Consumer Affairs and the
Department of Transportation, represented by exhibits 7448-A, B & C of record in this matter,
hereby gives to the same unanimous preliminary and final approval.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26964
RESOLVED That the Design Commission, having considered designs for the installation of a
prototypical newsstand, 660 Columbus Avenue, northwest corner of Columbus Avenue and
West 92nd Street, Manhattan, submitted by the Department of Consumer Affairs and the
Department of Transportation, represented by exhibits 7236-D, E & F of record in this matter,
hereby gives to the same unanimous preliminary and final approval. Commissioner Sheffer
recused herself.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26965
RESOLVED That the Design Commission, having considered a proposal for the installation of
the Rebecca Salome Foster Memorial by Karl Bitter, 60 Centre Street, Manhattan, submitted by
the Department of Citywide Administrative Services, represented by exhibits 739-FS, FT, FU &
FV of record in this matter, hereby gives to the same unanimous preliminary approval with the
understanding that (1) the plywood joints will be adjusted so that the front piece covers the
ends of the side pieces; (2) samples of the paint color will be submitted for review before the
pedestal is painted; (3) the visible steel tubes will be brushed to a non-shiny surface; and (4)
the artwork identification and ownership information will be discretely and permanently
inscribed on the back of the pedestal.
Preliminary approval is conditioned upon commencement of work before March 18, 2021 and
submission of this project for final review and approval.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26966
RESOLVED That the Design Commission, having considered a proposal for the installation of
Urban Poet by Alexandre Arrechea, Atlantic Avenue median between Conduit Boulevard and
Fountain Avenue, Brooklyn, submitted by the Department of Cultural Affairs’ Percent for Art
Program, the Department of Design and Construction, and the Department of Transportation,
represented by exhibits 7441-A, B, C & D of record in this matter, hereby gives to the same
unanimous conceptual approval.
Conceptual approval is conditioned upon submission of this project for preliminary review and
approval before March 18, 2021.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26967
RESOLVED That the Design Commission, having considered a proposal for the installation of
un(Common) Threads by Borinquen Gallo, 40th Police Precinct, East 149th Street and St.
Ann's Avenue, Bronx, submitted by the Department of Cultural Affairs’ Percent for Art Program,
the Department of Design and Construction, and the New York City Police Department,
represented by exhibits 2169-EC, ED, EE & EF of record in this matter, hereby gives to the
same unanimous conceptual approval with the understanding that, for preliminary review, the
artist will break down the larger installation into several smaller-scaled interventions.
Conceptual approval is conditioned upon submission of this project for preliminary review and
approval before March 18, 2021.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26968
RESOLVED That the Design Commission, having considered designs for the installation of
interpretive signage for an educational compost facility, Queens Botanical Garden, 43-50 Main
Street, Flushing, Queens, submitted by the Department of Cultural Affairs, the Department of
Parks & Recreation, and the Department of Sanitation, represented by exhibits 2440-JM, JN,
JO & JP of record in this matter, hereby gives to the same unanimous preliminary and final
approval.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26969
RESOLVED That the Design Commission, having considered designs for the construction of
Myrtle Wyckoff Plaza, Wyckoff Avenue between Gates Avenue and Myrtle Avenue, Brooklyn
and Queens, submitted by the Department of Design and Construction and the Department of
Transportation, represented by exhibits 6391-AC, AD, AE & AF of record in this matter, hereby
gives to the same unanimous preliminary and final approval with the understanding that
designs for the prototypical citywide kiosk will be submitted for final review in May 2019.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26970
RESOLVED That the Design Commission, having considered designs for the construction of
the 116th Police Precinct, North Conduit Avenue and 244th Street, Rosedale, Queens,
submitted by the Department of Design and Construction and the New York City Police
Department, represented by exhibits 7353-P, Q, R & S of record in this matter, hereby gives to
the same unanimous final approval with the understanding that the team will study a simplified
paving pattern and any revisions to the paving pattern will be submitted for review per
standard procedure.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26971
RESOLVED That the Design Commission, having considered designs for the installation of
flood protection measures as part of the DEP Wastewater Resiliency Program, Bowery Bay
Wastewater Treatment Plant, 43-01 Berrain Boulevard, Queens, submitted by the Department
of Environmental Protection, represented by exhibits 2229-EK, EL, EM & EN of record in this
matter, hereby gives to the same unanimous preliminary and final approval with the
understanding that, if there are any revisions to the design resulting from review by the State
Historic Preservation Office, the project will be resubmitted, per standard procedure.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26972
RESOLVED That the Design Commission, having considered designs for the reconstruction of
sludge docks and installation of a prefabricated storage shed, Owls Head Wastewater
Treatment Plant, 6700 Shore Road, Brooklyn, submitted by the Department of Environmental
Protection, represented by exhibits 2429-CW, CX, CY & CZ of record in this matter, hereby
gives to the same unanimous preliminary and final approval.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26973
RESOLVED That the Design Commission, having considered designs for the reconstruction of
the landscape and adjacent site work, Tallman Island Water Pollution Control Plant, 127th
Street and Powell's Cove Boulevard, College Point, Queens, submitted by the Department of
Environmental Protection, represented by exhibits 2116-BS, BT, BU & BV of record in this
matter, hereby gives to the same unanimous final approval with the understanding that the
project will be submitted for amended review if any revisions to the plantings at the staging
area are required by the Department of Parks & Recreation, per standard procedure.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26974
RESOLVED That the Design Commission, having considered designs for the rehabilitation of
the Eltingville Pumping Station (formerly Brookfield Landfill), Arthur Kill Road and Brookfield
Avenue, Staten Island, submitted by the Department of Environmental Protection and the
Department of Parks & Recreation, represented by exhibits 2977-KS, KT, KU & KV of record in
this matter, hereby gives to the same unanimous preliminary approval with the understanding
that color samples for the blue emergency generator and orange crane will be submitted for
review.
Preliminary approval is conditioned upon submission of this project for final review and
approval before March 18, 2021.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26975
RESOLVED That the Design Commission, having considered designs for the installation of
rooftop guardrails, Eric M. Taylor Center, 10-10 Hazen Street, Rikers Island, Bronx, submitted
by the Department of Correction, represented by exhibits 1554-SR, SS, ST & SU of record in
this matter, hereby gives to the same unanimous preliminary and final approval.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26976
RESOLVED That the Design Commission, having considered designs for the installation of
rooftop guardrails, George Motchan Detention Center, 15-15 Hazen Street, Rikers Island,
Bronx, submitted by the Department of Correction, represented by exhibits 1554-SV, SW, SX &
SY of record in this matter, hereby gives to the same unanimous preliminary and final approval.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26977
RESOLVED That the Design Commission, having considered designs for the installation of
rooftop guardrails, North Infirmary Command Annex, 15-00 Hazen Street, Rikers Island, Bronx,
submitted by the Department of Correction, represented by exhibits 1554-SZ, TA, TB, TC & TD
of record in this matter, hereby gives to the same unanimous preliminary and final approval.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26978
RESOLVED That the Design Commission, having considered designs for the installation of two
prefabricated trailers and adjacent site work, Rodman’s Neck, Pelham Bay Park, Bronx,
submitted by the Department of Correction, represented by exhibits 1842-IB, IC, ID & IE of
record in this matter, hereby gives to the same unanimous preliminary and final approval.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26979
RESOLVED That the Design Commission, having considered designs for the installation of a
soccer sealcoat field, P.S. 142, Amalia Castro School and Manhattan Charter School, 100
Attorney Street, Manhattan, submitted by the Department of Education, represented by
exhibits 7449-A, B, C & D of record in this matter, hereby gives to the same unanimous
preliminary and final approval.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26980
RESOLVED That the Design Commission, having considered designs for the installation of
signage, Brooklyn Science and Engineering Academy, 5404 Tilden Avenue, Brooklyn,
submitted by the Department of Education, represented by exhibits 2162-J & K of record in
this matter, hereby gives to the same unanimous preliminary and final approval.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26981
RESOLVED That the Design Commission, having considered designs for the installation of
signage, P.S. 152, 725 East 23rd Street, Brooklyn, submitted by the Department of Education,
represented by exhibits 7450-A & B of record in this matter, hereby gives to the same
unanimous preliminary and final approval.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26982
RESOLVED That the Design Commission, having considered designs for the installation of a
prototypical neighborhood wayfinding (WalkNYC) sign, Riverside Park, Riverside Drive between
West 94th Street and West 95th Street, Manhattan, submitted by the Department of
Transportation, represented by exhibits 2287-KH, KI & KJ of record in this matter, hereby gives
to the same unanimous preliminary and final approval. Commissioner Sheffer recused herself.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26983
RESOLVED That the Design Commission, having considered designs for the installation of a
prototypical neighborhood wayfinding (WalkNYC) sign, Riverside Park, West 97th Street, and
Riverside Drive, Manhattan, submitted by the Department of Transportation, represented by
exhibits 2287-KK, KL & KM of record in this matter, hereby gives to the same unanimous
preliminary and final approval. Commissioner Sheffer recused herself.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26984
RESOLVED That the Design Commission, having considered designs for the installation of an
ADA lift, 2416 Lorillard Place, Bronx, submitted by the Department of Transportation,
represented by exhibits 7451-A, B & C of record in this matter, hereby gives to the same
unanimous preliminary and final approval.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26985
RESOLVED That the Design Commission, having considered designs for the construction of
streetscape improvements, Parsons Boulevard between Jamaica Avenue and Archer Avenue,
Jamaica Queens, submitted by the Department of Design and Construction and the
Department of Transportation, represented by exhibits 5121-CJ, CK, CL & CM of record in this
matter, hereby gives to the same unanimous preliminary and final approval.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26986
RESOLVED That the Design Commission, having considered designs for the construction of
the northern portion of Success Garden, Livonia Avenue between Alabama Street and Williams
Street, Brooklyn, submitted by the Department of Parks & Recreation, represented by exhibits
5936-F, G, H & I of record in this matter, hereby gives to the same unanimous preliminary
approval.
Preliminary approval is conditioned upon submission of this project for final review and
approval before March 18, 2021.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26987
RESOLVED That the Design Commission, having considered designs for the reconstruction of
a ballfield (Ballfield 3) and related site work, McCarren Park, Bedford Avenue, Lorimer Avenue,
Driggs Avenue, and North 12th Street, Brooklyn, submitted by the Department of Parks &
Recreation, represented by exhibits 580-BZ, CA & CB of record in this matter, hereby gives to
the same unanimous preliminary approval.
Preliminary approval is conditioned upon submission of this project for final review and
approval before March 18, 2021.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26988
RESOLVED That the Design Commission, having considered designs for the reconstruction of
a portion of Anne Loftus Playground, Fort Tryon Park, Dyckman Street and Broadway,
Manhattan, submitted by the Department of Parks & Recreation, represented by exhibits 2026-
CD, CE & CF of record in this matter, hereby gives to the same unanimous preliminary
approval.
Preliminary approval is conditioned upon submission of this project for final review and
approval before March 18, 2021.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26989
RESOLVED That the Design Commission, having considered designs for the reconstruction of
a portion of Lincoln Terrace Park, East New York Avenue between Rochester Avenue and
Buffalo Avenue, Brooklyn, submitted by the Department of Parks & Recreation, represented by
exhibits 2043-AE, AF & AG of record in this matter, hereby gives to the same unanimous
preliminary approval.
Preliminary approval is conditioned upon submission of this project for final review and
approval before March 18, 2021.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26990
RESOLVED That the Design Commission, having considered designs for the rehabilitation of a
comfort station, Captain George H. Tilly Memorial Park Playground, 85th Avenue between
165th Street and Chapin Parkway, Jamaica, Queens, submitted by the Department of Parks &
Recreation, represented by exhibits 2313-J, K & L of record in this matter, hereby gives to the
same unanimous preliminary approval with the understanding that the wing walls with
balusters and the precast stone panels beneath the windows will be reconstructed to match
the original 1934 condition.
Preliminary approval is conditioned upon submission of this project for final review and
approval before March 18, 2021.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26991
RESOLVED That the Design Commission, having considered designs for the rehabilitation of a
comfort station, Cooper Park, Maspeth Avenue, Morgan Avenue, Sharon Street and Olive
Street, Brooklyn, submitted by the Department of Parks & Recreation, represented by exhibits
143-AE, AF, AG, AH & AI of record in this matter, hereby gives to the same unanimous
preliminary and final approval.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26992
RESOLVED That the Design Commission, having considered designs for the rehabilitation of a
comfort station, Lower Highland East Playground, Highland Park, Jamaica Avenue between
Elton Street and Linwood Street, Brooklyn, submitted by the Department of Parks &
Recreation, represented by exhibits 729-AM, AN, AO & AP of record in this matter, hereby
gives to the same unanimous preliminary and final approval.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26993
RESOLVED That the Design Commission, having considered designs for the reconstruction of
Lower Highland East Playground and a performance space, Highland Park, Jamaica Avenue
between Elton Street and Linwood Street, Brooklyn, submitted by the Department of Parks &
Recreation, represented by exhibits 729-AQ, AR, AS & AT of record in this matter, hereby gives
to the same unanimous final approval.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26994
RESOLVED That the Design Commission, having considered designs for the construction of an
adult fitness area, St. John's Park, Troy Avenue, Prospect Place, Schenectady Avenue and
Bergen Street, Brooklyn, submitted by the Department of Parks & Recreation, represented by
exhibits 2749-AN, AO & AP of record in this matter, hereby gives to the same unanimous final
approval.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26995
RESOLVED That the Design Commission, having considered designs for the installation of
windows, a door, and mechanical equipment, Owen F. Dolen Golden Age Recreation Center,
Owen F. Dolen Park, 2551 Westchester Avenue, Bronx, submitted by the Department of Parks
& Recreation, represented by exhibits 1396-AP & AQ of record in this matter, hereby gives to
the same unanimous final approval.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26996
RESOLVED That the Design Commission, having considered designs for the reconstruction of
a memorial, Olde Towne of Flushing Burial Ground (formerly Martins Field), 45th Avenue, 46th
Avenue, 164th Street and 166th Street, Queens., submitted by the Department of Parks &
Recreation, represented by exhibits 6573-T, U & V of record in this matter, hereby gives to the
same unanimous final approval.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26997
RESOLVED That the Design Commission, having considered designs for the reconstruction of
Bridge Playground, Undercliff Avenue, Boscobel Place, and University Avenue, Bronx,
submitted by the Department of Parks & Recreation, represented by exhibits 2826-H, I, J & K
of record in this matter, hereby gives to the same unanimous final approval.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26998
RESOLVED That the Design Commission, having considered designs for the installation of an
artwork by Stacy Levy, East Midtown Greenway, East River between East 53rd Street and East
61st Street, Manhattan, submitted by Economic Development Corporation, the Department of
Parks & Recreation, and the Department of Transportation, represented by exhibits 7369-M, N,
O & P of record in this matter, hereby gives to the same unanimous conceptual approval.
Conceptual approval is conditioned upon submission of this project for preliminary review and
approval before March 18, 2021.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 26999
RESOLVED That the Design Commission, having considered designs for the installation of
rooftop mechanical equipment and windows, Engine Company 82, 1215 Intervale Avenue,
Bronx, submitted by the Fire Department, represented by exhibits 7452-A, B, C & D of record
in this matter, hereby gives to the same unanimous preliminary and final approval.
Final approval is conditioned upon commencement of work before March 18, 2021 and
submission of comprehensive photographic documentation of the completed project
consisting of 8” x 10” archival-quality color photographs.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director
Laurie Hawkinson, Manuel Miranda, Richard Moore, Susan Morgenthau, Signe Nielsen,
Ethel Sheffer, Hank Willis Thomas, Shin-pei Tsay, Mary Valverde, Commissioners
March 18, 2019
CERTIFICATE 27000
RESOLVED That the Design Commission, having considered a proposal for the installation of
the Elizabeth Cady Stanton and Susan B. Anthony Monument by Meredith Bergmann, Literary
Walk, The Mall, Central Park, Manhattan, submitted by the Department of Parks & Recreation,
represented by exhibits 7422-A, B & D of record in this matter, hereby gives to the same
unanimous conceptual approval with the understanding that (1) the artist will (a) work on
refining the anatomy and proportions of each of the two figures, (b) restudy the gaze of the two
women, (c) simplify the pedestal design so that the surface is flush, (d) eliminate the
rectangular base or revise it to an oval to match the pedestal, and (e) integrate the bronze into
the top of the base and (2) the team will submit revised pedestal text, including the birth and
death dates for the two women and alternative quotes.
The Commission appreciates that this monument will commemorate two women who were
pioneering activists of the Woman Suffrage Movement. The Commission also acknowledges
Elizabeth Cady Stanton and Susan B. Anthony's complicated history, and that the
contributions and struggles of the many women of color who played a role in this Movement
remain overlooked.
With this in mind, the Commission gives approval conditioned upon the understanding that,
separate from the statue of Elizabeth Cady Stanton and Susan B. Anthony, the applicant will
work to identify meaningful ways to acknowledge and commemorate women of color who
played an active role in the Woman Suffrage Movement.
Conceptual approval is conditioned upon submission of this project for preliminary review and
approval before March 18, 2021.
A true copy of resolution adopted by
the Design Commission at its meeting
on March 18, 2019.
Justin Garrett Moore
Executive Director