main stages in power station erection

Upload: sam

Post on 05-Apr-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Main Stages in Power Station Erection

    1/38

    TODAYS TOPIC

    MAIN STAGES IN POWER STATIONERECTION

    READINESS OF SITE FORERECTION ( RAILWAY SIDING ,STORAGE FACILITY , LABOUR

    COLONY,ERECTION TOOLS ANDTACKLES)

    METHODS / TECHNICS OF

    ERECTION

  • 7/31/2019 Main Stages in Power Station Erection

    2/38

    MAIN STAGES IN POWER

    STATION ERECTION

    PREPERATORY WORK

    CIVIL CONSTRUCTION

    STRUCTURAL ERECTION

    EQUIPMENT ERECTION ELECTRICAL ERECTION

    C&I ERECTION

    QUALITY CHECKS DURING ERECTION COMMISSIONING

    POST COMMISSIONING ACTIVITIES

  • 7/31/2019 Main Stages in Power Station Erection

    3/38

    PREPERATORY WORKS

    DE-VEGITATION OF SITE

    AREA LEVELLING

    AREA GRADING TO BRING IT TOPLANNED BLOCK LEVEL TO MAKE THESITE READY FOR START OF CIVILWORK

    EXCESS EARTH DISPOSAL

  • 7/31/2019 Main Stages in Power Station Erection

    4/38

    CIVIL WORKS

    PILING WORK

    PILING DESIGN AS PER LOAD DATA FROMEPC CONTRACTOR

    PILING

    PILE TESTING

    PILE CAP AND FOUNDATION FOR

    STRUCTURE( FDN CASTING AFTER JOINT CHECKINGWITH STRUCTURAL ERECTOR)

  • 7/31/2019 Main Stages in Power Station Erection

    5/38

    CIVIL WORKS- CONTD

    CASTING OF FLOORS ANDEQUIPMENT FDN

    SPECIAL FDNS LIKE T.G. DECK ANDOTHER FDN WITH V.I.Serecnphotos\Picture tg deck.jpg

    HANDING OVER OF FOUNDATION

    FINISHING WORKS AFTER ERECTIONCOMPLN

    http://erecn%20photos/Picture%20tg%20deck.jpghttp://erecn%20photos/Picture%20tg%20deck.jpghttp://erecn%20photos/Picture%20tg%20deck.jpghttp://erecn%20photos/Picture%20tg%20deck.jpghttp://erecn%20photos/Picture%20tg%20deck.jpghttp://erecn%20photos/Picture%20tg%20deck.jpg
  • 7/31/2019 Main Stages in Power Station Erection

    6/38

    STRUCTURAL ERECTION

    TAKING OVER OF FOUNDATION

    CHECK FOR LOCATION

    CHECK FOR LEVEL

    CHECK FOR BOLT/POCKET LOCATION

    PREFABRICATION

    SAND BLASTING AND PRIMER COAT

  • 7/31/2019 Main Stages in Power Station Erection

    7/38

    STRUCTURAL ERECTION-

    CONTD

    STRUCTURAL ERECTION BLUE MATCHING OF PACKER PLATES WITH

    FDNS

    FIRST STAGE COLUMN ERECTION & ROUGHALIGNMENT

    FURTHER STAGES COLUMNS , FRAME BEAMSAND BRACINGS ERECTIONerecn photos\chp str.jpg

    INTERMEDIATE AND FINAL ALIGNMENT

    FLOOR BEAMS AND RELEASE OF FRONT FORFLOOR CASTINGerecn photos\typical floor in str.jpg

    http://erecn%20photos/chp%20str.jpghttp://erecn%20photos/typical%20floor%20in%20str.jpghttp://erecn%20photos/typical%20floor%20in%20str.jpghttp://erecn%20photos/typical%20floor%20in%20str.jpghttp://erecn%20photos/typical%20floor%20in%20str.jpghttp://erecn%20photos/chp%20str.jpghttp://erecn%20photos/chp%20str.jpghttp://erecn%20photos/chp%20str.jpg
  • 7/31/2019 Main Stages in Power Station Erection

    8/38

    EQUIPMENT ERECTION

    TAKING OVER OF FOUNDATION

    CHECK FOR LOCATION

    CHECK FOR LEVEL

    CHECK FOR BOLT/POCKET LOCATION

    DEVISING HOISTING STRATAGY ANDSELECTION OF HOISTING T&P FORPLACEMENT OF EQUIPMENT

  • 7/31/2019 Main Stages in Power Station Erection

    9/38

    EQUIPMENT ERECTION

    EQUIPMENT PLACEMENT AND ROUGHLEVELLING WITH BOLT GROUTINGerecnphotos\Picture placemnt of id fan.jpg/erecnphotos\tg box up.jpg

    FINAL LEVELLING AND GROUTINGerecnphotos\mill erection.jpg

    ALIGNMENT OF ROTARY EQUIPMENTS ERECTION OF PIPING AND DUCTINGerecn

    photos\flue gas ducting.jpg PRESSURE /LEAKAGE TEST OF PIPING AND

    DUCTING

    http://erecn%20photos/Picture%20placemnt%20of%20id%20fan.jpghttp://erecn%20photos/Picture%20placemnt%20of%20id%20fan.jpghttp://erecn%20photos/tg%20box%20up.jpghttp://erecn%20photos/tg%20box%20up.jpghttp://erecn%20photos/mill%20%20erection.jpghttp://erecn%20photos/mill%20%20erection.jpghttp://erecn%20photos/flue%20gas%20ducting.jpghttp://erecn%20photos/flue%20gas%20ducting.jpghttp://erecn%20photos/flue%20gas%20ducting.jpghttp://erecn%20photos/flue%20gas%20ducting.jpghttp://erecn%20photos/flue%20gas%20ducting.jpghttp://erecn%20photos/flue%20gas%20ducting.jpghttp://erecn%20photos/mill%20%20erection.jpghttp://erecn%20photos/mill%20%20erection.jpghttp://erecn%20photos/mill%20%20erection.jpghttp://erecn%20photos/mill%20%20erection.jpghttp://erecn%20photos/tg%20box%20up.jpghttp://erecn%20photos/tg%20box%20up.jpghttp://erecn%20photos/tg%20box%20up.jpghttp://erecn%20photos/tg%20box%20up.jpghttp://erecn%20photos/Picture%20placemnt%20of%20id%20fan.jpghttp://erecn%20photos/Picture%20placemnt%20of%20id%20fan.jpghttp://erecn%20photos/Picture%20placemnt%20of%20id%20fan.jpghttp://erecn%20photos/Picture%20placemnt%20of%20id%20fan.jpg
  • 7/31/2019 Main Stages in Power Station Erection

    10/38

    ELECTRICAL ERECTION

    TAKING OVER OF FRONT FROMSTRUCTURAL ERECTOR / EQUIPMENTERECTOR

    ERECTION OF CABLE TRAY SUPPORTSTRUCTUREerecn photos\cross countrycable tray.jpg

    CABLE TRAY ERECTION FOR POWERAND CONTROL CABLEpipe rack.jpg

    CABLING AS PER CABLE SCHEDULE

    http://erecn%20photos/cross%20%20country%20cable%20tray.jpghttp://erecn%20photos/cross%20%20country%20cable%20tray.jpghttp://pipe%20%20rack.jpg/http://pipe%20%20rack.jpg/http://erecn%20photos/cross%20%20country%20cable%20tray.jpghttp://erecn%20photos/cross%20%20country%20cable%20tray.jpghttp://erecn%20photos/cross%20%20country%20cable%20tray.jpghttp://erecn%20photos/cross%20%20country%20cable%20tray.jpg
  • 7/31/2019 Main Stages in Power Station Erection

    11/38

    ELECTRICAL ERECTION- CONTD

    ERECTION OF LT& HT SW GRS

    ERECTION OF TRANSFORMERSerecnphotos\transf erecn.jpg

    CABLE TESTING AND TERMINATION

    EQUIPMENT EARTHING

    SWITCH YARD ERECTION

    http://erecn%20photos/transf%20erecn.jpghttp://erecn%20photos/transf%20erecn.jpghttp://erecn%20photos/transf%20erecn.jpghttp://erecn%20photos/transf%20erecn.jpghttp://erecn%20photos/transf%20erecn.jpghttp://erecn%20photos/transf%20erecn.jpg
  • 7/31/2019 Main Stages in Power Station Erection

    12/38

    C&I ERECTION

    ERECTION OF FIELD INSTRUMENTSAND J.BS

    PLC / CONTROL PANEL ERECTION

    CABLING BETWEEN INSTRUMENTS ,I/O PANELS & PLC / CONTROL PANELS

    CABLING BETWEEN MCC AND PLC/CONTROL PANELS

  • 7/31/2019 Main Stages in Power Station Erection

    13/38

    QUALITY CHECKS DURING

    ERECTION

    THREE TYPES OF QUALITY CHECKS

    A CLASS CHECK : - JOINTLY BYERECTION AND FQA DEPTT. THESE ARE

    CRITICAL CHECKS

    B CLASS CHECKS: - BY ERECTIONDEPTT

    C CLASS CHECKS :- BY THECONTRACTOR

  • 7/31/2019 Main Stages in Power Station Erection

    14/38

    COMMISSIONING PHASE

    RECHECKING OF ERECTION

    PRECOMMISSIONING CHECKS

    POWERING UP OF PANELS AND

    EQUIPMENTS NO LOAD RUN OF MOTORS

    COMMISSIONING OF FIELD INSTRUMENTSAND CONTROL SYSTEMS

    CHECKING OF LOGICS AND INTERLOCKS INITIAL RUN AND CHECK FOR HEALTHINESS

    OF THE SYSTEMS

  • 7/31/2019 Main Stages in Power Station Erection

    15/38

    POST COMMISSIONING

    ACTIVITIES

    LIQUIDATION OF MAJOR DEFECTS INTHE SYSTEM

    SYSTEM TRIAL OPERATION FORESTABLISHING SYSTEM RELIABILITY

    PERFORMANCE AND GUARANTEETEST- TO CHECK WHETHER THEPLANT ACHIEVES THE GUARANTEEDPARAMETERS

  • 7/31/2019 Main Stages in Power Station Erection

    16/38

    READINESS OF SITE FOR

    ERECTION

    PRE-REQUISITES

    APPROACH AND DRAINAGE SYSTEM

    CONTRACTORS LAYDOWN , STORAGEAND PRE FABRICATION AREA

    LABOUR COLONY

    RAILWAY SIDING:- Track connection from

    nearest rail head and unloading bay at site ERECTION TOOLS AND TACKLES

  • 7/31/2019 Main Stages in Power Station Erection

    17/38

    ERECTION TOOLS AND PLANTS

    TYPICAL TOOLS AND PLANTS REQUIRED FORTURNKEY CONTRACTS BATCHING PLANT FOR CONCRETING

    TRANSIT MIXERS AND CONCRETE PUMPS

    CRAWLER MOUNTED AND TYRE MOUNTED CRANES TRAILERS

    ELECTRICAL WINCHES AND CHAIN PULLEY BLOCKSWITH WIRE ROPES AND SLINGS

    WELDING AND GAS CUTTING SETS

    THEODOLITE, DIAL GUAGES AND OTHER INSTRUMNTS SPECIAL T&P AS REQD

  • 7/31/2019 Main Stages in Power Station Erection

    18/38

    METHODS AND TECHNICS OF

    ERECTION

    ADHERENCE TO ERECTION SEQUENCE ASPER ERECTION MANUAL :- VERYIMPORTANT FOR BOILER ERECTION

    ADHERENCE TO ACCEPTANCE CRITERIAFOR ERECTION TOLERANCES

    SPECIAL TECHNICS :- STRAND JACKMETHOD FOR BOILER DRUM LIFTING

  • 7/31/2019 Main Stages in Power Station Erection

    19/38

  • 7/31/2019 Main Stages in Power Station Erection

    20/38

    MAJOR MILESTONES IN

    ERECTION

  • 7/31/2019 Main Stages in Power Station Erection

    21/38

    ERECTION SCHEDULING

    TYPES OF PROJECT SCHEDULES

    MASTER NETWOR SCHEDULE OR L-1NETWORK

    PACKAGE SCHEDULE OR L-2 SCHEDULE

    L-3 SCHEDULE

    QUANTITATIVE SCHEDULE

  • 7/31/2019 Main Stages in Power Station Erection

    22/38

    MASTER NETWOR SCHEDULE

    OR L-1 NETWORK

    PERTAINS TO THE WHOLE PROJECT

    COVERS ALL ACTIVITIES FROM ENABLINGWORKS TO COMMERCIAL OPERATION OF

    THE UNITS IT ALSO SPECIFIES THE SCHEDULE OF PRE-

    AWARD AND POST AWARD ACTIVITIES OFALL MAJOR PACKAGES

    SAMPLENCTPP-II(1X490 MW).pdf

    http://nctpp-ii%281x490%20mw%29.pdf/http://nctpp-ii%281x490%20mw%29.pdf/http://nctpp-ii%281x490%20mw%29.pdf/http://nctpp-ii%281x490%20mw%29.pdf/
  • 7/31/2019 Main Stages in Power Station Erection

    23/38

    PACKAGE SCHEDULE OR L-2

    SCHEDULE

    SPECIFIC TO A PACKAGE

    IT IS IN PERT NETWORK FORM ANDSHOWS IN DETAIL ALL THEACTIVITIES INCLUDING VARIOUSSTAGES OF MANUF. & ERECTION

    IT IS A JOINTLY SIGNED DOCUMENTBETWEEN NTPC & CONTRACTOR

  • 7/31/2019 Main Stages in Power Station Erection

    24/38

    PACKAGE SCHEDULE OR L-2

    SCHEDULE CONTD-

    IT IS CONTRACTUALLY BINDINGDOCUMENT BETWEEN NTPC AND THECONTRACTOR

    IT ALSO SHOWS THE INTER-RELATION BETWEEN VARIOUSACTIVITIES AND DATE OF RELESE

    OF FRONTS TO THE CONTRACTOR

  • 7/31/2019 Main Stages in Power Station Erection

    25/38

    SAMPLE L-2 SCHEDULE SUPPLY

  • 7/31/2019 Main Stages in Power Station Erection

    26/38

    SAMPLE L-2 SCHEDULE

    ERECTIONtgfinal.pdf

    http://tgfinal.pdf/http://tgfinal.pdf/
  • 7/31/2019 Main Stages in Power Station Erection

    27/38

    L-3 SCHEDULE

    THIS SCHEDULE IS ACTIVITYSPECIFIC

    PREPARED AT PROJECT LEVEL

    FOR CLOSE MONITORING OFCRITICAL ACTIVITIES.

    SAMPLEL3_mech_1 CT.xls

    http://l3_mech_1%20ct.xls/http://l3_mech_1%20ct.xls/
  • 7/31/2019 Main Stages in Power Station Erection

    28/38

    QUANTITATIVE SCHEDULE

    MAINLY FOR THE ITEM RATECONTRACTS

    THIS SCHEDULE SHOWS QUANTITYFOR DIFFERENT ARES OF THEPACKAGE AND THEIR COMPLETIONSCHEDULE.

    QUANTITIES ARE SPREAD OUT IN THECOMPLETION SCHEDULE.

  • 7/31/2019 Main Stages in Power Station Erection

    29/38

    MEASUREMENT OF PROGRESS

    for TURNKEY CONTRACTS

    PROGRESS FOR SUPPLY

    PROGRESS OF SUPPLY MEASURED INFINANCIAL TERMS i.e. VALUE OF EQUIPMENTSRECEIVED

    VALUATION DONE WITH RESPECT TO THEBILLING BREAK-UP FOR REPORTING AS WELLAS FOR BILLING.

    FOR S.G. PACKAGE GENERALLYMEASUREMENT IS DONE ON TONNAGE BASIS

  • 7/31/2019 Main Stages in Power Station Erection

    30/38

    SAMPLE SUPPLY BILLING

    BREAK UPbbu supply chp.pdf

    http://bbu%20supply%20%20chp.pdf/http://bbu%20supply%20%20chp.pdf/
  • 7/31/2019 Main Stages in Power Station Erection

    31/38

    PROGRESS MEASUREMENT

    FOR ERECTION

    DONE ON SYSTEM COMPLETION WISE FORPHYSICAL MEASUREMENT

    FOR BILLING PURPOSE MEASUREMENT

    AND VALUATION OF ERECTION WORK ISDONE AS PER THE BILLING BREAK UP

    SAMPLE BBU

    FOR ITEM RATE CONTRACTSQUANTITATIVE PROGRESS CAN BE GIVEN

  • 7/31/2019 Main Stages in Power Station Erection

    32/38

    RECORDING OF OUTPUT

    RECORDING FOR THE PURPOSE OFBILLING IS DONE AS PER BILLINGBREAK UP FOR THE ERECTION OF

    EQUIPMENT COMPLETED

    FOR ITEM RATE CONTRACTS ,INSTEAD OF BBU THERE IS BOQ (

    BILL OF QUANTITIES)

  • 7/31/2019 Main Stages in Power Station Erection

    33/38

    REPORTING

    PROGRESS REPORTING

    MONTHLY PROGRESS REPORT

    WEEKLY PROGRESS REPORT

    DAILY PROGRESS REPORT

  • 7/31/2019 Main Stages in Power Station Erection

    34/38

    MONTHLY PROGRESS REPORT

    REPORTING OF ACTUAL PROGRESS VIS-A VIS SCHEDULE FOR THE MONTH

    REASONS OF SHORTFALL IS TO BERECORDED

    THE REPORT ALSO HIGHLIGHTS THEHOLD UPS WHERE SUPPORT FROMCOTPORATE CENTRE/HIGHER

    MANAGEMENT IS REQUIRED REPORT IS SENT TO THE CORPORATE

    MONITORING GROUP

  • 7/31/2019 Main Stages in Power Station Erection

    35/38

    WEEKLY PROGRESS REPORT

    MONTHLY TARGET BROKEN DOWN TOWEEKLY TARGET

    SHOWS PROGRESS VIS A VISTARGET

    REVIEWD BY PROJECT HEAD

    SITE CO-ORDINATION ISSUESRAISED IN THE REPORT

    SAMPLE.

  • 7/31/2019 Main Stages in Power Station Erection

    36/38

    DAILY PROGRESS REPORT

    FOR VERY CRITICAL AREASREQUIRING CLOSE ATTENTION

    DAILY MAN POWER AND RESOURCE

    DEPLOYMENT IS ALSO BROUGHTOUT

    ALSO BRINGS OUT THE

    REQUIREMENT OF ADDITIONALMANPOWER/RESOURCES

    SAMPLE.DPR pt plant.xls

    http://dpr%20pt%20plant.xls/http://dpr%20pt%20plant.xls/
  • 7/31/2019 Main Stages in Power Station Erection

    37/38

    REPORT FOR BUDGET

    UTILISATION

    REPORTING FOR ACTUAL BUDGETUTILISATION WITH RESPECT TOPROJECTED BUDGET

    GOOD INDICATOR OF OVERALLPROGRESS OF THE PACKAGE.

    SAMPLEbud uti.xls

    http://bud%20uti.xls/http://bud%20uti.xls/
  • 7/31/2019 Main Stages in Power Station Erection

    38/38

    THANK YOU

    .