    TODAYS TOPIC

    MAIN STAGES IN POWER STATIONERECTION

    READINESS OF SITE FORERECTION ( RAILWAY SIDING ,STORAGE FACILITY , LABOUR

    COLONY,ERECTION TOOLS ANDTACKLES)

    METHODS / TECHNICS OF

    ERECTION

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    2/38

    MAIN STAGES IN POWER

    STATION ERECTION

    PREPERATORY WORK

    CIVIL CONSTRUCTION

    STRUCTURAL ERECTION

    EQUIPMENT ERECTION ELECTRICAL ERECTION

    C&I ERECTION

    QUALITY CHECKS DURING ERECTION COMMISSIONING

    POST COMMISSIONING ACTIVITIES

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    3/38

    PREPERATORY WORKS

    DE-VEGITATION OF SITE

    AREA LEVELLING

    AREA GRADING TO BRING IT TOPLANNED BLOCK LEVEL TO MAKE THE

    SITE READY FOR START OF CIVIL

    WORK

    EXCESS EARTH DISPOSAL

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    4/38

    CIVIL WORKS

    PILING WORK

    PILING DESIGN AS PER LOAD DATA FROM

    EPC CONTRACTOR

    PILING

    PILE TESTING

    PILE CAP AND FOUNDATION FOR

    STRUCTURE( FDN CASTING AFTER JOINT CHECKING

    WITH STRUCTURAL ERECTOR)

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    5/38

    CIVIL WORKS- CONTD

    CASTING OF FLOORS ANDEQUIPMENT FDN

    SPECIAL FDNS LIKE T.G. DECK ANDOTHER FDN WITH V.I.Serecnphotos\Picture tg deck.jpg

    HANDING OVER OF FOUNDATION

    FINISHING WORKS AFTER ERECTIONCOMPLN

    http://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/Picture%20tg%20deck.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/Picture%20tg%20deck.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/Picture%20tg%20deck.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/Picture%20tg%20deck.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/Picture%20tg%20deck.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/Picture%20tg%20deck.jpg
  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    6/38

    STRUCTURAL ERECTION

    TAKING OVER OF FOUNDATION

    CHECK FOR LOCATION

    CHECK FOR LEVEL

    CHECK FOR BOLT/POCKET LOCATION

    PREFABRICATION

    SAND BLASTING AND PRIMER COAT

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    7/38

    STRUCTURAL ERECTION-

    CONTD

    STRUCTURAL ERECTION BLUE MATCHING OF PACKER PLATES WITH

    FDNS

    FIRST STAGE COLUMN ERECTION & ROUGHALIGNMENT

    FURTHER STAGES COLUMNS , FRAME BEAMSAND BRACINGS ERECTIONerecn photos\chp str.jpg

    INTERMEDIATE AND FINAL ALIGNMENT

    FLOOR BEAMS AND RELEASE OF FRONT FORFLOOR CASTINGerecn photos\typical floor in str.jpg

    http://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/chp%20str.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/typical%20floor%20in%20str.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/typical%20floor%20in%20str.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/typical%20floor%20in%20str.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/typical%20floor%20in%20str.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/chp%20str.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/chp%20str.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/chp%20str.jpg
  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    8/38

    EQUIPMENT ERECTION

    TAKING OVER OF FOUNDATION

    CHECK FOR LOCATION

    CHECK FOR LEVEL

    CHECK FOR BOLT/POCKET LOCATION

    DEVISING HOISTING STRATAGY AND

    SELECTION OF HOISTING T&P FOR

    PLACEMENT OF EQUIPMENT

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    9/38

    EQUIPMENT ERECTION

    EQUIPMENT PLACEMENT AND ROUGHLEVELLING WITH BOLT GROUTINGerecnphotos\Picture placemnt of id fan.jpg/erecnphotos\tg box up.jpg

    FINAL LEVELLING AND GROUTINGerecnphotos\mill erection.jpg

    ALIGNMENT OF ROTARY EQUIPMENTS ERECTION OF PIPING AND DUCTINGerecn

    photos\flue gas ducting.jpg PRESSURE /LEAKAGE TEST OF PIPING AND

    DUCTING

    http://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/Picture%20placemnt%20of%20id%20fan.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/Picture%20placemnt%20of%20id%20fan.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/tg%20box%20up.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/tg%20box%20up.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/mill%20%20erection.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/mill%20%20erection.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/flue%20gas%20ducting.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/flue%20gas%20ducting.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/flue%20gas%20ducting.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/flue%20gas%20ducting.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/flue%20gas%20ducting.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/flue%20gas%20ducting.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/mill%20%20erection.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/mill%20%20erection.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/mill%20%20erection.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/mill%20%20erection.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/tg%20box%20up.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/tg%20box%20up.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/tg%20box%20up.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/tg%20box%20up.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/Picture%20placemnt%20of%20id%20fan.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/Picture%20placemnt%20of%20id%20fan.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/Picture%20placemnt%20of%20id%20fan.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/Picture%20placemnt%20of%20id%20fan.jpg
  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    10/38

    ELECTRICAL ERECTION

    TAKING OVER OF FRONT FROMSTRUCTURAL ERECTOR / EQUIPMENTERECTOR

    ERECTION OF CABLE TRAY SUPPORTSTRUCTUREerecn photos\cross countrycable tray.jpg

    CABLE TRAY ERECTION FOR POWERAND CONTROL CABLEpipe rack.jpg

    CABLING AS PER CABLE SCHEDULE

    http://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/cross%20%20country%20cable%20tray.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/cross%20%20country%20cable%20tray.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/pipe%20%20rack.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/pipe%20%20rack.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/cross%20%20country%20cable%20tray.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/cross%20%20country%20cable%20tray.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/cross%20%20country%20cable%20tray.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/cross%20%20country%20cable%20tray.jpg
  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    11/38

    ELECTRICAL ERECTION- CONTD

    ERECTION OF LT& HT SW GRS

    ERECTION OF TRANSFORMERSerecn

    photos\transf erecn.jpg

    CABLE TESTING AND TERMINATION

    EQUIPMENT EARTHING

    SWITCH YARD ERECTION

    http://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/transf%20erecn.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/transf%20erecn.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/transf%20erecn.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/transf%20erecn.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/transf%20erecn.jpghttp://localhost/var/www/apps/conversion/tmp/scratch_6/erecn%20photos/transf%20erecn.jpg
  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    12/38

    C&I ERECTION

    ERECTION OF FIELD INSTRUMENTS

    AND JBS

    PLC / CONTROL PANEL ERECTION

    CABLING BETWEEN INSTRUMENTS ,

    I/O PANELS & PLC / CONTROL PANELS

    CABLING BETWEEN MCC AND PLC/CONTROL PANELS

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    13/38

    QUALITY CHECKS DURING

    ERECTION

    THREE TYPES OF QUALITY CHECKS

    A CLASS CHECK : - JOINTLY BY

    ERECTION AND FQA DEPTT. THESE ARE

    CRITICAL CHECKS

    B CLASS CHECKS: - BY ERECTION

    DEPTT

    C CLASS CHECKS :- BY THECONTRACTOR

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    14/38

    COMMISSIONING PHASE

    RECHECKING OF ERECTION

    PRECOMMISSIONING CHECKS

    POWERING UP OF PANELS AND

    EQUIPMENTS NO LOAD RUN OF MOTORS

    COMMISSIONING OF FIELD INSTRUMENTSAND CONTROL SYSTEMS

    CHECKING OF LOGICS AND INTERLOCKS

    INITIAL RUN AND CHECK FOR HEALTHINESSOF THE SYSTEMS

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    15/38

    POST COMMISSIONING

    ACTIVITIES

    LIQUIDATION OF MAJOR DEFECTS IN

    THE SYSTEM

    SYSTEM TRIAL OPERATION FOR

    ESTABLISHING SYSTEM RELIABILITY

    PERFORMANCE AND GUARANTEE

    TEST- TO CHECK WHETHER THE

    PLANT ACHIEVES THE GUARANTEED

    PARAMETERS

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    16/38

    READINESS OF SITE FOR

    ERECTION

    PRE-REQUISITES

    APPROACH AND DRAINAGE SYSTEM

    CONTRACTORS LAYDOWN , STORAGE

    AND PRE FABRICATION AREA

    LABOUR COLONY

    RAILWAY SIDING:- Track connection from

    nearest rail head and unloading bay at site ERECTION TOOLS AND TACKLES

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    17/38

    ERECTION TOOLS AND PLANTS

    TYPICAL TOOLS AND PLANTS REQUIRED FORTURNKEY CONTRACTS BATCHING PLANT FOR CONCRETING

    TRANSIT MIXERS AND CONCRETE PUMPS

    CRAWLER MOUNTED AND TYRE MOUNTED CRANES TRAILERS

    ELECTRICAL WINCHES AND CHAIN PULLEY BLOCKSWITH WIRE ROPES AND SLINGS

    WELDING AND GAS CUTTING SETS

    THEODOLITE, DIAL GUAGES AND OTHER INSTRUMNTS SPECIAL T&P AS REQD

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    18/38

    METHODS AND TECHNICS OF

    ERECTION

    ADHERENCE TO ERECTION SEQUENCE AS

    PER ERECTION MANUAL :- VERY

    IMPORTANT FOR BOILER ERECTION

    ADHERENCE TO ACCEPTANCE CRITERIAFOR ERECTION TOLERANCES

    SPECIAL TECHNICS :- STRAND JACK

    METHOD FOR BOILER DRUM LIFTING

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    19/38

    MAJOR MILESTONES

    Starting from Zero date( award of main plant pkg)

    Boiler erection start- 11 months

    Drum Lifting - 17 months

    Start of Cond erction 21 months

    Start of TG erect - 23 months

    Boiler hydro test - 29 months TG box up - 32 months

    BLU and AVO - 35 months

    Compln of TG oil flushing- 35 months

    Steam blowing Compln 37 months

    Synchronization - 39 months

    Coal firing - 39 months

    Trail operation - 42 months

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    20/38

    MAJOR MILESTONES IN

    ERECTION

    Daily review/coordination meeting

    Weekly progress review

    Monthly progress review (PRT) CRM Contract review meeting

    ECM- Engg Coordination meeting

    Review at various levels

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    21/38

    ERECTION SCHEDULING

    TYPES OF PROJECT SCHEDULES

    MASTER NETWOR SCHEDULE OR L-1

    NETWORK

    PACKAGE SCHEDULE OR L-2 SCHEDULE

    L-3 SCHEDULE

    QUANTITATIVE SCHEDULE

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    22/38

    MASTER NETWOR SCHEDULE

    OR L-1 NETWORK

    PERTAINS TO THE WHOLE PROJECT

    COVERS ALL ACTIVITIES FROM ENABLING

    WORKS TO COMMERCIAL OPERATION OF

    THE UNITS IT ALSO SPECIFIES THE SCHEDULE OF PRE-

    AWARD AND POST AWARD ACTIVITIES OF

    ALL MAJOR PACKAGES

    SAMPLENCTPP-II(1X490 MW).pdf

    http://localhost/var/www/apps/conversion/tmp/scratch_6/NCTPP-II(1X490%20MW).pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_6/NCTPP-II(1X490%20MW).pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_6/NCTPP-II(1X490%20MW).pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_6/NCTPP-II(1X490%20MW).pdf
  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    23/38

    PACKAGE SCHEDULE OR L-2

    SCHEDULE

    SPECIFIC TO A PACKAGE

    IT IS IN PERT NETWORK FORM AND

    SHOWS IN DETAIL ALL THE

    ACTIVITIES INCLUDING VARIOUS

    STAGES OF MANUF. & ERECTION

    IT IS A JOINTLY SIGNED DOCUMENT

    BETWEEN NTPC & CONTRACTOR

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    24/38

    PACKAGE SCHEDULE OR L-2

    SCHEDULE CONTD-

    IT IS CONTRACTUALLY BINDING

    DOCUMENT BETWEEN NTPC AND THE

    CONTRACTOR

    IT ALSO SHOWS THE INTER-

    RELATION BETWEEN VARIOUS

    ACTIVITIES AND DATE OF RELESE

    OF FRONTS TO THE CONTRACTOR

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    25/38

    SAMPLE L-2 SCHEDULE SUPPLY

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    26/38

    SAMPLE L-2 SCHEDULE

    ERECTIONtgfinal.pdf

    http://localhost/var/www/apps/conversion/tmp/scratch_6/tgfinal.pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_6/tgfinal.pdf
  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    27/38

    L-3 SCHEDULE

    THIS SCHEDULE IS ACTIVITY

    SPECIFIC

    PREPARED AT PROJECT LEVEL

    FOR CLOSE MONITORING OF

    CRITICAL ACTIVITIES.

    SAMPLEL3_mech_1 CT.xls

    http://localhost/var/www/apps/conversion/tmp/scratch_6/L3_mech_1%20CT.xlshttp://localhost/var/www/apps/conversion/tmp/scratch_6/L3_mech_1%20CT.xls
  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    28/38

    QUANTITATIVE SCHEDULE

    MAINLY FOR THE ITEM RATE

    CONTRACTS

    THIS SCHEDULE SHOWS QUANTITY

    FOR DIFFERENT ARES OF THE

    PACKAGE AND THEIR COMPLETION

    SCHEDULE.

    QUANTITIES ARE SPREAD OUT IN THE

    COMPLETION SCHEDULE.

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    29/38

    MEASUREMENT OF PROGRESS

    for TURNKEY CONTRACTS

    PROGRESS FOR SUPPLY

    PROGRESS OF SUPPLY MEASURED IN

    FINANCIAL TERMS i.e. VALUE OF EQUIPMENTS

    RECEIVED

    VALUATION DONE WITH RESPECT TO THE

    BILLING BREAK-UP FOR REPORTING AS WELL

    AS FOR BILLING.

    FOR S.G. PACKAGE GENERALLY

    MEASUREMENT IS DONE ON TONNAGE BASIS

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    30/38

    SAMPLE SUPPLY BILLING

    BREAK UPbbu supply chp.pdf

    http://localhost/var/www/apps/conversion/tmp/scratch_6/bbu%20supply%20%20chp.pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_6/bbu%20supply%20%20chp.pdf
  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    31/38

    PROGRESS MEASUREMENT

    FOR ERECTION

    DONE ON SYSTEM COMPLETION WISE FOR

    PHYSICAL MEASUREMENT

    FOR BILLING PURPOSE MEASUREMENT

    AND VALUATION OF ERECTION WORK ISDONE AS PER THE BILLING BREAK UP

    SAMPLE BBU

    FOR ITEM RATE CONTRACTSQUANTITATIVE PROGRESS CAN BE GIVEN

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    32/38

    RECORDING OF OUTPUT

    RECORDING FOR THE PURPOSE OF

    BILLING IS DONE AS PER BILLING

    BREAK UP FOR THE ERECTION OF

    EQUIPMENT COMPLETED

    FOR ITEM RATE CONTRACTS ,

    INSTEAD OF BBU THERE IS BOQ (

    BILL OF QUANTITIES)

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    33/38

    REPORTING

    PROGRESS REPORTING

    MONTHLY PROGRESS REPORT

    WEEKLY PROGRESS REPORT

    DAILY PROGRESS REPORT

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    34/38

    MONTHLY PROGRESS REPORT

    REPORTING OF ACTUAL PROGRESS VIS-A VIS SCHEDULE FOR THE MONTH

    REASONS OF SHORTFALL IS TO BERECORDED

    THE REPORT ALSO HIGHLIGHTS THEHOLD UPS WHERE SUPPORT FROMCOTPORATE CENTRE/HIGHER

    MANAGEMENT IS REQUIRED REPORT IS SENT TO THE CORPORATE

    MONITORING GROUP

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    35/38

    WEEKLY PROGRESS REPORT

    MONTHLY TARGET BROKEN DOWN TO

    WEEKLY TARGET

    SHOWS PROGRESS VIS A VIS

    TARGET

    REVIEWD BY PROJECT HEAD

    SITE CO-ORDINATION ISSUES

    RAISED IN THE REPORT

    SAMPLE.

  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    36/38

    DAILY PROGRESS REPORT

    FOR VERY CRITICAL AREASREQUIRING CLOSE ATTENTION

    DAILY MAN POWER AND RESOURCE

    DEPLOYMENT IS ALSO BROUGHTOUT

    ALSO BRINGS OUT THE

    REQUIREMENT OF ADDITIONALMANPOWER/RESOURCES

    SAMPLE.DPR pt plant.xls

    http://localhost/var/www/apps/conversion/tmp/scratch_6/DPR%20pt%20plant.xlshttp://localhost/var/www/apps/conversion/tmp/scratch_6/DPR%20pt%20plant.xls
  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    37/38

    REPORT FOR BUDGET

    UTILISATION

    REPORTING FOR ACTUAL BUDGET

    UTILISATION WITH RESPECT TO

    PROJECTED BUDGET

    GOOD INDICATOR OF OVERALL

    PROGRESS OF THE PACKAGE.

    SAMPLEbud uti.xls

    http://localhost/var/www/apps/conversion/tmp/scratch_6/bud%20uti.xlshttp://localhost/var/www/apps/conversion/tmp/scratch_6/bud%20uti.xls
  • 7/30/2019 94631852 Diff Erection Stages in Construction of Power Station

    38/38

    THANK YOU

    .