lss.fnal.gov · 1.0 scope the gem collaboration will be submitting to the superconducting super...

158
©@®U Approved by: Ron Barber, LANL Dave Etherton, SSCL Tony Chargin, LLNL Frank Nimblett, CSDL Gary Deis, LLNL Mark Rennich, ORNL Dan Marlow, Princeton University Prepared by: Rick Sawicki, LLNL

Upload: others

Post on 12-Jun-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

@~[MJ

©@®U ~®UD[]l])@UDITll~ [l2l~®ITll

~®[plUa ~ ®~ ~ ®®~

Approved by:

Ron Barber, LANL Dave Etherton, SSCL

Tony Chargin, LLNL Frank Nimblett, CSDL

Gary Deis, LLNL Mark Rennich, ORNL

Dan Marlow, Princeton University

Prepared by:

Rick Sawicki, LLNL

Page 2: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

1.a Scope 2.a Objectives 3.a Basis

Table of Contents

4.a Work Breakdown Structure s.a Cost matrix s.a Labor rates 7.a Material costs s.a Risk Analysis/Contingency 9.a Escalation 1 a.a Supporting Documentation 11 .a Responsibilities 12.a Review process 13.a Schedule

Page 3: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a large high PT detector at the SSC site. In support of this document a detailed cost estimate of this detector shall be provided to identify all expenses required to complete the construction of all equipment defined in the LOI. This Cost Estimating Plan (CEP) delineates the method, personnel, and schedule that will be used in the development of the cost.

Since GEM is truly an international collaboration of many participants spanning a broad spectrum of resources from numerous universities and laboratories around the world, clear and decisive guidance is required from the beginning of the cost estimating process to assure that the final product is complete and consistent. All participants shall perform their work in full compliance with the CEP. Any changes required shall be amended to this plan only after approval from the signatories of this document.

2.0 Objectives

2.1 The primary objective is to develop a comprehensive cost estimate of the total GEM project. This includes costs for the necessary research and development activities as well as for the engineering, design, analysis, procurement, fabrication, assembly,. installation and management of the construction project itself. Contributions of all collaborating institutions shall be included and implemented in consistent content and format. Costs shall be accumulated starting from the beginning of the project, defined to be the time when the LOI is accepted, to the completion of the project, defined to be the commencement of experimental activities.

2.2 During the cost estimating process it is desired to develop the detailed backup information that will substantiate the estimate and make it easily defensible. The intent is to provide SSCL with sufficient information that the project may be started with high confidence that the GEM costs are well understood. Therefore, this necessarily will include an appropriate risk/contingency analysis that accounts for unavoidable uncertainties and inevitable

Page 4: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

unexpected factors that usually emerge during projects of the size and complexity of the GEM detector.

2.3 Subsequent to the acceptance of the GEM LOI a comprehensive cost control and monitoring effort will be established. An important objective of this present cost planning exercise is to provide a sound basis on which this future effort can be built. The two dimensional system/task hierarchy used in the CEP establishes costs in a format that can be easily translated to a computerized planning system. That system could then be quickly implemented to track the the actual cost against the projected costs determined by the exercise. It is thus vital that the guidelines established by this CEP be strictly followed so that subsequent project monitoring activities may be facilitated.

3.0 Basis

3.1 The basis for the cost estimate developed according to this CEP will be a detailed bottoms up estimate for each subsystem. These estimates shall be based on FY 91 dollars. Escalation factors will be applied at the top level by the CEP coordinator using the standard factors shown below and the temporal cost distributions defined by the subsystem estimators.

3.2 Cost estimates will be developed according to a preapproved two dimensional cost matrix, shown in Table 1, that will be based on a system wide Work Breakdown Structure (WBS). The vertical dimensional of the matrix will be the WBS hierarchy which delineates all subsystems and divides each of those into multiple levels of component parts. The second dimension of the matrix defines the labor and material required in each of four functional activities for each WBS element. These activities are engineering/design, inspection/administration, procurement/fabrication and assembly/installation.

3.3 In addition to providing cost matrix information each estimator shall develop his/her own cost book. This document shall contain supporting information which substantiates each cost data item. This information will be used during both the internal and external defense of the system costs.

4.0 Work Breakdown Structure

Page 5: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

The WBS is a hierarchy of elements which identifies all components of a system and their mother/daughter relationships. Costs for all systems and activities will be accumulated in a single WBS list. Cost estimators will develop the subsystem WBS hierarchies which will be collected via e-mail and collated into the GEM detector WBS.

4.1 Level 1 and 2 The guideline WBS hierarchy is listed in Table 2. The top level elements are listed below:

5.2 Detectors 5.2.2 GEM

5.2.2.1 5.2.2.2 5.2.2.3

Research and Development (R&D) Conceptual/Preliminary Design Construction

level 1 level 2

4.1.1 Research and development tasks are those engineering and scientific tasks that are performed to advance the design of a particular subsystem or demonstrate the feasibility of a new concept. They can be analytical or experimental in nature. After a particular design concept is baselined and approved by SSCL at the Engineering Design Report (EDR) all future development activities are considered part of the construction project unless they advance the state of the art of that design. Costs for R&D will clearly be heaviest in the early phase of the project and declining rapidly after the EDR process is complete.

4.1.2 Conceptual/ preliminary design activities include all engineering design tasks from the Expression of Interest (EOI) to the EDR. Analysis, tradeoffs studies, design engineering, planning, and costing activities that are exercised to establish a baseline design are part of this WBS element.

4.1 .3 The construction WBS element consumes the bulk of the GEM project costs. It includes all engineering activities between the EDR and project completion. All engineering, analysis, design, procurement, fabrication, assembly and installation costs are accumulated under this element. Facility, utility and subsystem project management costs that are unique to a particular subsystem are included under that subsystem's WBS element.

4.2 Level 3

Page 6: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

4.2.1 Each of the three level 2 items will have six subelements corresponding to the six major subsystems of the GEM project. These are

x.1 Magnet subsystem level 3 x.2 Muon subsystem x.3 Hadron calorimeter subsystem x.4 Electromagnetic calorimeter subsystem x.5 Central tracker subsystem x.6 Trigger and data acquisition subsystem

The LOI may submit for consideration to SSCL options for each subsystem. As they are identified they will be appended after subelement 6.

4.2.1.1 Subsystems 1 through 5 shall include all hardware within the detector itself, all utilities and facilities specific to that subsystem and electronic channel costs. Electronic channel costs begin in the detector and end where data signals enter the main data storage system.

4.2.1.2 The trigger and data acquisition system includes the main control computer, data storage devices, and on-line data processing equipment. SSCL shall provide tape storage equipment and off-line computing facilities.

4.2.1 .3 The magnet subsystem shall include all structural support systems required for the magnet and the detectors such as the central membrane, detector cradle, and end supports.

4.2.2 Project management will be included in each of the the three level 2 entries as follows:

5.2.2 GEM 5.2.2.1 Research and Development (R&D)

5.2.2.1.9 R&D Project Management 5.2.2.2 Conceptual/Preliminary Design

5.2.2.2.9 C/P Design Project Mgmt 5.2.2.3 Construction

5.2.2.3.9 GEM Constr. Project Mgmt

level 1 level 2 level 3

level 3

level 3

4.2.2.1 Project management encompasses all administrative and management efforts required to direct the GEM project through

Page 7: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

completion. This includes management personnel and technical staff, resource management, safety, and QA personnel, ancillary support contracts, travel, and supplies and expenses. Costs that are required to manage the detector project as a whole are included here. Subsystem management costs are defined at the subsystem level.

4.2.3 Interface Systems will be included within the level 2 Construction element (5.2.2.3) as follows:

5.2.2.3 Construction 5.2.2.3.8 Interface Systems 5.2.2.3.9 GEM Constr. Project Mgmt

level 2 level 3 level 3

4.2.3.1 Interface systems are facilities, installation equipment and non-standard utilities that are not provided by SSCL. They are not subsystem specific and are used by the collaboration as a whole. Items that are required for a single subsystem are listed under that subsystem WBS element. Examples of interface systems are compressed air systems, scaffolding, installation fixturing, transport systems, non-conventional cooling, detector emergency power, and detector safety systems.

4.3 Level 4 and below

4.3.1 Levels at 4 and below will be defined by each subsystem estimator as required. In general most subsystems should be listed down to level 5 or 6.to provide sufficient detail for a meaningful estimate. At this final level costs should be in the 1 DOK$ to 500k$ range in most cases.

4.3.2 Although the specific line items below level 4 are subsystem specific, the elements within the construction element shall be listed according the the following format:

x.1 Subsystem component 1 x.2 Subsystem component 2

x.n Subsystem component n x.8 Subsystem installation x.9 Subsystem project management

x.9.1 Project management and administration

Page 8: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

x.9.2 Resource management x.9.3 ES&H x.9.4 Quality assurance x.9.5 System integration

4.3.3 Subsystem project management includes manpower for planning and control, Group or Division administrative personnel including supervisors and clerical support. ES&H and QA planning and controls, meetings, travel, reviews, developing plans and controls for detector subsystems and facility interfaces are also included. Procurement costs must identify office supplies, engineering service equipment and operating charges.

4.3.4 Interface Systems and Project Management will not be subdivided into the previously listed level 3 subsystems since they defined tasks that are common to all subsystems. Instead they are subdivided as follows:

5.2.2.3.8 Interface systems level 2 5.2.2.3.8.1 Experimental hall level 3 5.2.2.3.8.2 Surface facilities 5.2.2.3.8.3 Process utilities 5.2.2.3.8.4 Safety systems

5.2.2.3.9 Construction Project Management

5.0 Cost Matrix

5.2.2.3.9.1 Administration 5.2.2.3.9.2 Resource management 5.2.2.3.9.3 Environment, Safety and Health 5.2.2.3.9.4 Quality Assurance 5.2.2.3.9.5 System Integration

5.1 The cost matrix is the data set that will collect all information for the GEM cost estimate. All data will be input by each subsystem estimator in a format described below using the EXCEL computer spreadsheet. Each of the subsystem data bases will be compiled into a single spreadsheet that will be used to calculate total system costs and provide a mechanism for system-wide data analysis.

5.2 Table 3 shows that the cost matrix is actually divided into two separate data sets, a cost table (CT) and a supporting data table (SOT). This splitting of data is required to maintain legibility of the

Page 9: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

printed information when displayed on a single standard sheet of paper. The SOT shall be located in the EXCELL spreadsheet next to the CT and vertically synchronized with the CT so that the WBS elements line up horizontally,

5.2.1 The CT contains the basic cost information for the WBS elements. Material and labor costs are identified in each of 4 main functional categories: engineering/design, inspection/administration, procurement/fabrication and installation/assembly. Costs are estimated in FY 91 dollars. Roll ups of total costs from subelements to higher level elements are performed by equations imbedded in the EXCELL spreadsheet written by each subsystem estimator. Labor rates, material estimating strategies, and contingency methodology are defined in subsequent sections.

5.2.1 .1 Engineering/design Engineering/design includes only labor for all engineering design, engineering analysis, reliability analysis, design layout, and detailing and checking of fabrication drawings. Documentation for performance and fabrication specifications, safety analysis reports, design reviews, assembly procedures and testing or system checkout procedures are also included in this category.

5.2.1 .2 Inspection/QA/ Administration Inspection/QA/Administration collects all labor costs to administer fabrication and procurement contracts, scheduling of production, production inspection, pre and post assembly inspection of individual components of the detector subsystem. Also included is engineering administration labor associated with supervising both onsite and offsite assembly, installation and system checkout. Quality assurance planning, inspection, oversight, and documentation costs are also accumulated in this category. In addition, this functional category collects all costs associated with administering the project at either the subsystem or detector level. This includes project management, scheduling, planning, costing, and activities associated with implementing ES&H requirements. Material costs for travel, supplies and expenses, office and engineering service equipment and operating charges for that equipment are also included.

5.2.1.3 Procurement/fabrication

Page 10: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Procurement/fabrication includes costs for detector component material, fabrication, tooling, and equipment, necessary to construct the GEM detector and supporting facilities. Purchased labor contracts to perform tasks associated with engineering, installation, or assembly are not included in this category but rather in the specific category that they are associated with.

5.2.1 .4 Installation/assembly Installation/assembly includes labor and material necessary for the assembly and installation of the detector subsystem into the experimental hall. Fixturing, handling equipment and test equipment are included in this category. Supervision and inspection of the activities performed in this category are included in EDI/QA.

5.2.1.5 Contingency Contingency for the GEM detector cost estimate shall be based on a standardized risk analysis. Each estimator shall perform the risk analysis identified in Section 8.0 and enter the associated contingency in the CT. Depending upon the particular subsystem being analyzed contingency may be applied at the lowest WBS level or at a higher subassembly level. It is the responsibility of the estimator to make this determination. In any case, the estimators are responsible for assuring that each and every component has appropriate and defensible contingencies applied.

5.2.2 Support Data Table The SOT provides important supporting data to the cost estimates. Estimators are required to provide all input in this table as well as the CT. The information contained in the SOT is essential for interpreting the cost estimates, defending them and temporally distributing the costs to permit accurate cost projections to the end of the project. Data columns for this table, shown in Table 3, are defined below.

5.2.2.1 No./units The number and units columns identify the basic cost unit that was used to determine the cost and the total number of the unit that was assumed. Typical values used for units are tons, meters"2, channels, system, assembly, and fibers. Almost anything can be used but the more descriptive it is the more helpful it will be to a reviewer.

5.2.2.2 Estimate type

Page 11: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Each WBS element shall be tagged with a cost basis descriptor which characterizes the type of estimate that was used. Acceptable data entries are as follows:

1) Bottom-up (BU) 2) Specification analysis (SA) 3) Parametric study (PS) 4) Revision update (RU) 5) Trend analysis (TA) 6) Expert opinion (EO)

5.2.2.3 Risk factors The risk analysis described in Section 8.0 is used to calculate contingency. In the three columns provided in the SOT, technical, cost and schedule risk factors are input. Standard ranges for these parameters are as follows:

1) Technical risk - 1 to 10 2) Cost risk - 1 to 1 O 3) Schedule risk - 2 to 6

In some cases the standardized risk parameters may not be appropriate. Higher values may be used as described in Section 8.

5.2.2.4 Dates Start dates and completion dates for all activities must be assigned to permit appropriate application of escalation factors to the base cost estimates. The month and year (numerical) shall be identified for the end dates of the four main functional categories, engineering ./design, inspection/QA/administration, procurement/fabrication, and installation/assembly. These dates need only be input at WBS level 4. Costs at only this level will be used to escalate costs.

6.0 Labor rates

6.1 Estimators shall use their best discretion in selecting the labor rates that should be used for their GEM cost estimates. In making their decision, the estimators should determine where the work shall be performed and use the most accurate information available regarding the labor rates for that particular institution. Detailed backup information shall be provided in the cost book supporting any non-standard labor rate used. Rates used shall be fully burdened with all associated costs.

Page 12: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

6.2 In many cases the exact source of labor will not be known. In these cases standard labor rates are provided below and should be used selectively as required.

6.2.1 National Laboratories It is anticipated that the US National Laboratories will participate in many of the GEM subsystems. The following rates are average rates that may be used for work performed for any of these institutions. These rates include general overhead, support and payroll burden. If it is necessary to translate these rates to an hourly rate use 1800 hr/yr.

Type

Manager Secretary Eng in ear/physicist Desig ner/coordi nato r Senior technician Junior technician Craft

6.2.2 National average rates

Bate (k$/yr)

210 60 150 90 100 75 65

National average rates may be used for cases where the source of labor is completely unknown. If it is necessary to translate these rates to a yearly rate use 2080 hr/yr.

Type

Engineer/physicist Senior technician Junior technician Craft Machinist

6.2.3 SSC employees

Bate ($/hrl

62.00 50.00 38.00 25.50 25.50

Work performed by SSC employees shall be charged at the following rates which are fully burdened. If it is necessary to translate these rates to a yearly rate use 1800 hr/yr.

Type Bate ($/hrl

Page 13: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Manager Engineer/physicist Analystladm in istration Senior technician Technician/draftsman Clerks

6.2.4 Job/shop in Dallas area

61.55 36.10 23.13 23.13 17.27 13.27

If it is necessary to translate these rates to a yearly rate use 2080 hr/yr.

Type Rate ($/hr)

Engineer/physicist Software engineer Draftsman Junior technician Senior technician Average machinist Precision machinist

6.2.5 Contractor installation

47.00 47.00 26.10 18.00 25.00 30.00 39.00

For installation of equipment at the SSC site in Texas the appropriate Davis-Bacon wage rates are as follows. Rates are fully burdened. If it is necessary to translate these rates to an yearly rate use 2080 hr/yr.

Type

Crane operator Rigger Laborer Millwright Electrician Welder Pipefitter Carpenter Painter

7.0 Material costs

Rate 1$/hr)

26.64 24.28 13.23 22.35 20.04 24.28 21.50 22.35 15.31

Page 14: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

7 .1 Material costs shall include all hardware costs for the entire GEM project. WBS elements shall be listed to comprehensively cover projected requirements for each subsystem and for systems that span the needs of more than one subsystem. All costs shall be based on FY 1991 dollars and shall have backup details included in the subsystem cost books.

7.2 Material costs include all procurement and fabrication for all GEM assemblies and facilities. This includes detector hardware, equipment, fixturing, tooling, utilities, test equipment, assembly equipment, computer hardware, raw material, and material processing.

7.3 Detector costs must also include facility and utility costs not provided by SSCL. These include, but are not limited to, gas systems, access and structures in the experimental hall and surface facilities, non-conventional cooling, power distribution exceeding the baseline, and emergency power. Safety systems costed by GEM include fire extinguishing systems, fluid spill control system, radiation monitoring systems, oxygen deficiency system and nitrogen inerting system.

7.4 SSCL will cost the following facilities:

1) Underground detector facilities Collision hall, shafts and tunnels Power and electrical cabling HVAC Cooling

crw CHW LCW ICW

2) Surface facilities On-site assembly buildings Shaft headhouses Utility buildings Operations buildings Storage areas/hardstands General purpose machine shops Power and electrical cabling, routing and

distribution HVAC

Page 15: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Cooling CP'V'J CHN LCW ICW

3) Site infrastructure Roads Parking Water and waste water IR power distribution

8.0 Risk Analysis/Contingency

8.1 Risk analysis shall be performed for each WBS element. Results of this analysis will be related to a contingency which shall be listed for each WBS element. Risk analysis parameters shall be listed in the SDT; contingency values shall be listed in the CT. Risk analysis/contingency methodology shall, in general, comply with the SSCL recommended technique.

8.2 SSCL methodology This method is based on estimator evaluation of technical, cost and schedule risk for every WBS element. For technical risk, the value of 1 implies "normal industrial supplied off the shelf item" and 1 0 is reserved for components "way beyond the current state-of-the-art." For cost risk values, 1 is used to indicate "vendor quote or catalog price for a specific item" and 10 is used for guestimates where no data is available. The technical risk value is multiplied by 2o/o and the cost risk by 1 %. The schedule risk value is set between 2% and 6% based on the perceived criticality of the activity. The resulting percentages are added together to establish the total contingency allocation for a particular WBS element. The minimum contingency percentage under this approach is 5% and the maximum is 36%.

8.3 Good judgement There may be special cases where the parameter limitations defined above are inappropriate. Some high risk elements may truly deserve contingencies greater than 36%. In these cases, at the discretion of the the estimator and the approval of the cost review team, higher values may be used. Justification for these cases must be provided in the estimator's subsystem cost book.

Page 16: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

9.0 Escalation

Escalation factors will be applied to the base FY 1991 costs identified in each estimators cost table. Factors to be used will be supplied at a later date and will be implemented into the GEM detector cost by the cost coordinator. Subsystem estimators do not need to take any action except to include activity start and end dates for level 4 elements.

10.0 Subsystem Cost Books/Supporting Documentation

10.1 Each cost estimator shall provide a subsystem cost book. The books shall contain all information necessary to defend all data presented in the cost table. The cost books shall be available in preliminary form at the internal cost review and in final form at the time of the LOI presentation.

10.2 Contents of the cost book are as follows:

1) Cost Table 2) Supporting Data Table 3) System description

Brief narrative describing subsystem, performance, assumptions, and key technical issues

4) System drawings Top level assembly drawings which define system general configuration and interfaces with other subsystems

5) Parameter list List of key parameters (minimum of 20)which define the subsystem in sufficient detail to uniquely identify it to reviewers and to enable revision tracking of the design

11.0 Responsibilities

Cost estimating responsibilities are as follows:

Subsystem Responsible person

Magnet subsystem Muon subsystem

G. Deis F. Nimblett

Page 17: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Hadron calorimeter subsystem Electromagnetic calorimeter subsystem Central tracker subsystem Interface systems Project management

12.0 Review process

M. Rennich M. Rennich R. Barber C. Johnson A. Chargin

12.1 Prior to the submission of the LOI detector costs will be comprehensively reviewed to assure consistency, accuracy and completeness of all costs. Each subsystem estimator will defend his data before a review group of GEM collaborators. The review process is expected to last two days.

12.2 A chairman of the review process shall be selected and shall coordinate the meeting. Each subsystem estimator shall be present for all presentations to assure that all interfaces and subsystem interactions are considered. In addition several technical representatives of the collaboration shall be present to validate the assumed design basis and costing integrity. The chairman shall select these reviewers and coordinate their participation.

12.3 Subsystem cost estimators shall present their costs at this review. Vugraphs shall be prepared and presented to facilitate the discussion. The cost table, supporting data table, parameter list, and design description documents shall be discussed in detail.

13.0 Schedule

13.1 The schedule for the cost estimating effort is shown in Table 4.

13.2 Key milestone dates taken from the schedule are as follows:

Milestone

Subsystem WBS submitted WBS finalized Subsystem costs submitted Cost review Costs complete

Pate

9/27 1 0/4 1 0/1 8 1 0/25 11/1 5

Page 18: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

s ~

"' i:: :;: i::

8

~ -.Q :I U)

::s ~~ .5 E

>-

= -.. 0 - .Q

~!I

.Q -

af .!!

" li; 0 'ti/ d: ::&

"' e .,, "' -Ci: .8 0 .. Ci.-' . .. .5

:ii fll

li; tl :i ~ "'~ iS coll w

i:: .!!' .. -Cl) 0 c .Q

Ci!! i:: w

E !

U) 0 Ill

ll: i::

Table 1. GEM cost matrix

Page 19: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

5.2 Detectors 5.2.2 GEM

5.2.2.1 Research and Development 5.2.2.1.1 Magnet subsystem 5.2.2.1 .2 Muon subsystem 5.2.2.1.3 Hadron calorimeter subsystem 5.2.2.1.4 Electromagnetic calorimeter subsystem 5.2.2.1.5 Central tracker subsystem 5.2.2.1 .6 Trigger and data acquisition subsystem 5.2.2.1.9 R&D project management

5.2.2.2 Conceptual and preliminary design 5.2.2.2.1 Magnet subsystem 5.2.2.2.2 Muon subsystem 5.2.2.2.3 Hadron calorimeter subsystem 5.2.2.2.4 Electromagnetic calorimeter subsystem 5.2.2.2.5 Central tracker subsystem 5.2.2.2.6 Trigger and data acquisition subsystem 5.2.2.2.9 C/P design project management

5.2.2.3 Construction 5.2.2.3.1 Magnet subsystem 5.2.2.3.2 Muon subsystem 5.2.2.3.3 Hadron calorimeter subsystem 5.2.2.3.4 Electromagnetic calorimeter subsystem 5.2.2.3.5 Central tracker subsystem 5.2.2.3.6 Trigger and data acquisition subsystem 5.2.2.3.8 Interface systems

5.2.2.3.8.1 Experimental hall 5.2.2.3.8.2 Surface facilities 5.2.2.3.8.3 Process utilities 5.2.2.3.8.4 Safety systems

5.2.2.3.9 Project management 5.2.2.3.9.1 Administration 5.2.2.3.9.2 Resource management 5.2.2.3.9.3 Environment, safety and Health 5.2.2.3.9.4 Quality assurance 5.2.2.3.9.5 System integration

Table 2. GEM WBS hierarchy

Page 20: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

~ ii !'"

g !II. ; 3 !!l ~ ~ ~ ii'

9/13 9/20 9/27 10/4 10/11

4 .. WB drafts WBS co~ plete flnallzed ...

Comp lie mbsysten costs

10/18 10/25 11/1 11/8 11/15 11/22 11/29

lnltlal s ~bsystem costs s bmitted

Beg n cost rev I w

Subsyst1 In cost Colloat subsyste h updates' omplete costs

Rev ii ~cost est!~ ates

. lnc1 rporate in bLOI

LOlsu •milted

4 ...

Page 21: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

~ ... ·~ ...

~' 0

i~ ... ;; l! , "' .! Ii;!~ " ~ l:

'B V\ . ~ ... •

I~ ~M .. ~ " ~ ~ SM

I ~~ , "' ~IE ., <r r:

fl• j

j • ~ ... . ~ "' ~ ... ·~ < ...

~ "'E ..

" tt , 1t " !'e

• !~~

" B ... c. ~

l.S. ... :

l"f ~I~ e «';; ; ~

r~ -le w

• ~ ! :fl

"

Page 22: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

• :

'i I

• • I

~1 ;

tl !

11 i

'" ; 1j

I

,i 1 •

1~ • I

:

,H 1; .~ • i

I i

~ ! :

t~ i;

0

i,

I ,;

' • ~

~

~

' i

Page 23: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Tentative AGENDA Gem Magnet Advisory Panel

SSCL---Dallas, Texas

Wednesday, September 25, 1991 (Directorate Conference Room-Downstairs Building 4)

9:00

9:30

10:00

10:30

11:00

Introduction

General discussion of the first report of the Panel

Discussion of action items:

Coil manufacture

Vacuum vessel

Fringe field calculations vs depth

11:30 Quantitative comparisons of fringe fields

with existing facilities

1:30

2:00

2:30

3:00

3:30

Session on cost evaluation

Comparisons with SDC costs

GEM magnet cost details

Session on schedule evaluation

GEM schedule details

BREAK

Comparison with SDC magnet schedule

A model for facility requirements

Thin poles for the solenoid

Thursday, September 26, 1991 (Physics Conference Room, Building 4)

9:00

9:30

10:00

1:30

3:00

4:00

Presentation of preliminary conclusions

Assignment of working groups as necessary

Working groups

LUNCH

Reports of the working groups

Executive session to write summery of meeting

Collaboration closeout

Gilman

Stefanski

C. Johnson

C. Johnson

P. Marston

R. Woolley

D. Etherton

G. Deis

N. Gober/C. Johnson

D. Etherton

T. Prosapio

P. Marston

Stefanski

Stefanski

Stefanski

Page 24: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Superconducting Super Collider Laboratory 2550 Beckleymeade, Building 4 Dallas, Texas 75237-3946

Physics Research Division

TO: Mike Harris

FROM: Ron Hoffmann

DATE: June 19, 1991

SUBJECT: Detector 2 Magnetic Field vs Bridge Crane?

Per your request, I contacted Jim Nelson of Edderer Incorporated, Seattle, Wa. regarding the subject question. Jim called back late yesterday afternoon with the following information:

Edderer has built radio controlled cranes for the aluminum smelting industry which operate with no problems in magnetic fields considerably in excess of the 50 gauss expected in our case. Jim said that while it is no particular problem, it is definitely something which should be included in the crane purchase specification.

cc R. Stefanski

Page 25: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

~ --Superconducting Super Collider Laboratory 2550 Beckleymeade, Building 4 Dallas, Texas 75237-3946

Physics Research Division

TO:

FROM:

DATE:

SUBJECT:

Mike Harris

Ron Hoffma~d'ef · September 17, 1991

Transport of 20 mm by 31 mm coiled copper bar

Attached is a summary of the legal and special pennit limits for transporting loads over the highways of the contiguous continental states of the United Stated. This information was compiled from the Permit Manual of the Specialized Carriers & Rigging Association (SSCL Library TJ1363). If special permitting is to be avoided, the summary indicates that a total load height of 13.5 ft, width of 8 ft (8.5 ft if we can stay out of Alabama), and length of trailer of 48 ft are the limits. If we use a low bed trailer (one with a bed which is 2 ft above the road), we can accommodate a cylindrical package which is 11.5 ft in diameter by 8 ft long with the cylinder axis being crosswise to the trailer. This package will accommodate 78 turns of a 3.485 m diameter coil of the subject bar for a total, one piece length of 853.98 m.

If the long axis of the package is parallel to the long axis of the trailer, the crossection of the package could be elliptical, 11.5 ft high by 8 ft wide, and 48 ft long. By coiling the bar so that the axis of the coil is 43.5• to the plane of the coil, the package will accommodate 284 turns of a 3.485 m diameter coil of the subject bar for a total, one piece length of 3109.36 m.

cc R. Stefanski

Page 26: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

-- STATE HIGHWAY TRANSPORTATION LIMITS

STATE LEGAL LIMIT (ft) SPECIAL PERMIT LIMIT (ft) REMARXS WIDTH HEIGHT LENGTH WIDTH HEIGHT LENGTH

s.oo 13.50 113.50 16.00 16.00 150.00

Arizona s.110 14.00 117.50 14.00 16.00 120.00

Arkan•u s.110 13.50 113.50 20.00 17.00 NSL No Set Limit

California S.110 14.00 113.00 14.00 NSL 135.00 No Set Limit

Colorado S.150 14.50 157.33 17.00 NSL 1115.00 No Set Limit

Connecticut S.150 13.50 4S.00 16.00 15.00 120.00

Delawue S.110 13.50 153.00 NSL NSL NSL No Set Limit

D. OI c. S.l>O 13.150 46.00 20.00 NSL NSL No Set Limit

Florida S.150 13.50 4S.OO 14.00 15.00 NSL No Set Limit

Georei• S.150 13.150 113.00 14.00 115.33 NSL No Set Limit

Idaho 8.150 14.00 48.00 NSL NSL NSL No Set Limit

Jlllnol• S.150 13.50 153.00 14.150 115.00 1411.00

Indiana S.110 13.110 153.00 14.33 111.00 911.00

Iowa S.110 13.50 113.00 NSL NSL NSL No Set Limit

K.uuu S.llO 14.00 119.llO 16.llO 18.00 126.00

Iteotucky S.150 13.50 153.00 14.00 115.00 110.00

Loulalana S.50 13.50 59.50 lS.00 NSL NSL No Set Limit

Main S.150 13.50 4S.00 NSL NSL NSL No Set Limit

Maryland 8.150 13.50 4S.00 NSL 115.110 NSL No Set Limit

lluaachuett• 8.50 13.50 48.00 NSL NSL NSL No Set Limit

Mlchlfan S.150 13.50 153.00 14.00 15.00 150.00 IMIDDeaota 8.110 13.150 113.00 14.50 15.50 110.00

llllNIHlppl S.150 13.150 153.00 16.00 15.00 120.00 - s.110 14.00 153.00 16.00 14.50 150.00 Montana S.150 14.00 153.00 lS.00 17.00 95.00 Nebruka S.150 14.50 153.00 14.00 NSL NSL No Set Limit Nevada S.50 14.00 48.00 NSL NSL NSL No Set Limit New Hampshire S.110 13.50 48.00 22.00 18.00 90.00 New Jersey S.50 13.50 48.00 NSL NSL NSL No Set Limit New Medco S.50 14.00 157 .50 NSL NSL NSL No Set Limit New York S.150 13.50 48.00 16.00 13.92 100.00 See Note 1. North CaroliDa s.110 13.50 48.00 115.00 NSL NSL No Set Limit North Dakota S.50 13.50 53.00 18.00 18.00 120.00 Ohio S.110 13.50 113.00 NSL NSL NSL No Set Limit Oklahoma S.150 13.llO 119.150 16.00 21.00 NSL No Set Limit Orepn S.110 14.00 153.00 16.00 lS.00 NSL No SetLUDJt PeDDOyJvaDla S.110 13.50 153.00 16.00 14.50 160.00 Rhode loland S.110 13.llO 48.50 NSL NSL NSL No Set Limit South CaroliDa S.150 13.llO 113.00 115.00 NSL 1211.00 No Set Limit South Dakota S.150 14.00 153.00 24.00 NSL NSL No Set Limit Tennessee S.150 13.50 110.00 14.00 115.00 120.00 Tezao S.150 13.150 59.00 20.00 lS.00 110.00 u ..... S.110 14.00 48.00 111.00 17.110 105.00 Vermont S.150 13.50 4S.OO 14.00 15.00 100.00 Vlretnla S.150 13.llO 153.00 14.00 14.00 150.00 WuJUnaton S.150 14.00 4S.OO NSL NSL NSL No Set Limit West v1r111D1a S.150 13.llO 153.00 14.00 15.83 110.00 Wlaeoaaln S.50 13.50 53.00 16.00 NSL NSL No Set Limit Wyomlull S.50 14.00 60.00 18.00 17.00 1015.00

NOTES 1. New York lellal limit• do not Include the Bolland & LlocolD Tunoela 2. The leeal limit widths and helllht• ID some of the states Is for deolgDBted routes only. 3. The tranoport of all loada In exceA of tbe leeu limit• require opeclal permits. AD special permits

depend on the clearances of the chosen routca. Where special permit limits have been set, pcrmit1 for loads cxcccdln& thoee limits will not be issued regardless of the chosen routes.

Page l

Page 27: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

AGENDA

Wednesday, September 25, 1991 Rm 526Bldg3

9-12AM& 1:30- 5:00PM

1. Introduction Gilman 9:00

2. General discussion of the first report of the Panel Stefanski 9:30

3. Discussion of action items:

Coil manufacture Harris 10:00

Vacuum vessel C. Johnson 10:30

Fringe field calculations vs depth P. Marsten 11:00

Quantitative comparisons of fringe fields with existing facilities R. Wooley 11:30

4. Session on cost evaluation

Comparisons with SDC costs D. Etherton 1:30

GEM magnet cost details G. Deis 2:00

5. Session on schedule evaluation

GEM schedule details N. Gober 2:30

Comparison with SDC magnet schedule R. Turkovich 3:00

6. The manufacturing process C. Johnson 3:30

7. A model for facility requirements T. Prosapio 4:00

8. Thin poles for the solenoid P. Marsten 4:30

Thursday, September 26, 1991 Rm 526Bldg3

9-12AM & 1:30- 5:00PM

1. Presentation of preliminary conclusions Stefanski 9:00

2. Assignment of working groups as necessary Stefanski 9:30

3. Working groups 10:00

4. Reports of the working groups 1:30

5. Executive session to write summery of meeting 3:00

6. Collaboration closeout Stefanski 4:00

Page 28: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

GEM Magnet Reuiew Panel Members and Participants

Peter Clee, Rutherford Appleton Laboratoy (second & third session) Gary Deis, Lawrence Livermore National Laboratory Mike Harris, SSC Laboratory

~ Alain Herve, CERN (only third session) Coleman Johnson, Lawrence Livermore National Laboratory Robert Johnson, JBc Associates

"E. Klimenko, Kurchatov I RE Dennis Lieurance, General Dynamics Space Systems Peter Marston, Massachusetts Institute of Technology

1 Nickolai Martovetsky, Kurchatov I RE John Miller, Lawrence Livermore National Laboratory

xBruce Montgomery, Massachusetts Institute of Technology (first session only)

x:Dr. Roberto Penco, Ensaldo Compontenti Tom Prosapio, SSC Laboratory Robert Richardson, SSC Laboratory Dr. Gary Sanders, Los Alamos National Laboratory Dr. Ray Stefanski, SSC Laboratory Dr. Richard Stroynowski, Caltech High Energy Physics Francois Wittgenstein, CERN (only second session) Ronn Wooley, SSC Laboratory Phil Sanger, SSC Laboratory Don Edwards, SSC Labortory Jon Ives, SSC Laboratory George Mulholland, SSC Laboratory Ted Kozman, SSC Laboratory

PRRJ! CI PANTS

Howard Shaffer, Westinghouse Science & Technology Center Shaid K. Singh, Westinghouse Science & Technology Center Robert Swinderman, Pitt-Des Moines, Inc. Larry Darby, (Dr. Eyssa), BabCOK and WilCOK

Page 29: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

SEP-19-1991 12:19 FROM MIT PLASAFUSION TO 4-72676-12147080006 P.02

Dr· Ray Stefanski Plasma Fusion Center Physics Research Div• Massachusetts lnatltutt ot Technology SSCL ,..

1 d Cambridge, Massachu1etts 02139

25!50 Bee~ eymea e Avenue TelephOne: 6171253-8100 Mail Stop 2001, Suite 215 Dallas, Texas, 75237•3946

September 19, 1991

Dear Ray,

I am sorry to have to miss the next GEM Magnet Meetinq, as I will be in Japan. I am therefore droppin9 a note to report on some pr09ress since the last meeting, and on our meeting yesterday with Gary Sanders, Gary Deis, and Richard Stroynowski. Based on that progess I also enclose a suggested modification of page 9 on the First Meeting Report.

We took the task after the last meeting of analyzing the "Figure 1" conductor to see if, as written, it could be • ••• defended on all technical grounds... n

OUr analysis indicates that transient heat input from, say conductor motion, would reach the superconductor in about 2.5 msec, a time very short relative to the heat removal capacity of the cooling tube. The lack of adequate cooling surface in the tl.lbe and the poor thermal diffusion in the helium are at fault.

If the superconductor were internal to the tUbe (as in the alternate conductor considered at the meetinq, there is no such coolinq limitation. The stability against heat input is nearly two orders Of maqnitude higher in the alternate conductor.

We came to the conclusion in our meetinq here yesterday, that it would be wise to change to the alternate conductor, whose stability can be rigorously defended.

Accordin9ly I su99est a mark-up of the first meetin9 write-up to be more compatible with the conclusions we reached at the later time. Note that the diwensions on the figure used in the draft were incorrect.

Sincerely Yours,

~\.>.~--< D.Bruce Montqomery · \ Associate Director tel 617 2!53 5552 FAX 617 253 0807

Page 30: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

--/.,,.·

DRAFT 9/16/91

required for the magnet to discharge during a quench, and V d is the

vohage developed across the magnet during discharge.

• The quantity of superconductor and stabilizer used should give

very conservative margins in current and temperature (e.g. lop/le !

0.3 or 11 T cs i. 2K), where lop is the normal operating current. le is the

short sample limit, ~)1.e(

_ ... ..----...... -~--- .. -···· ....... .

~ ..• the temperature 111&%'9in between the operatin9 temperature and the current sharinq temperature.

The conductor pictured in fiqure l was chosen as the base case for further analysis of stability \lllder tranaient heat input (for example, conductor slippa9e.) Such a conductor can also serve as a baseline for cost and schedule studies on the basis of experience qained trom a number of other projects involvinq similar technology.

If analysis indicates insufficient stability, an alternate arran9ement of the basic components will be considered, in which the Nb'l'i cal:>le will be incorporate~ into the helium cooling channel.

Ground11lane insulatlOn

~~~~-,Copper stabifiztr

~i'5'"7~~~-- Forced-flow He cooling

~~~~~--Continuous tube

----- - ----- - ----- - ---- eou c:enterline

Figure 1

9

Page 31: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

I ~ I I

I I

I I I I

I

Page 32: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

~LABORATORY Physics Research Division

2550 Beckleymeade Avenue, MS: 2000 Dallas, Texas 75237 Tel: 214-708-6178 Tel: 214-708-6043 Fax: 214-708-6174

TELEFAX COVER SHEET

TO: PETER MARSTON

FAX: 617-253-0807

DATE:9-16-9! #PAGES f__.-6. (including cover page)

COMMENTS

You may remember one of the tasks at the last Technical Panel Meeting was to show the variance of the stray field in resnect to the different IR 's.

The importance of this work is building in momentum and would be submitted to Roy Schwitters for his comments at an early statge.

Can you please let me know if the figures could be made quickly according to the elevation data in the next sheet?

Will you be available for the GEM Engineering meeting on the 24th as well as the Technical Panel on the 25th?

Regards. V!ike Harris

Page 33: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Memorandum

To: Mike Harris

From: Jon Piles

Subject: IR Elevations

Date: 9/16/'Jl

Superconducting Super Collider Laboratory 2550 Beckleymeade Avenue, Mail Stop 2001

Dallas TX 75237-3946 (214) 708--0101

Fax: (214) 708-6174

Physics Research Division

Below is a table of elevations for the four IR sites. As understood from PB/MK these are the latest elevations for the proposed ring tilting.

Surface IR Site Elevation

IR1 IR4 IRS IRS

cc: Ray Stefanski Tim Thurston

<FT) 669 619 445 450

Beam Beam to Elevation Surface

(FT) (FT) 515 154 502 11 7 276 169 292 158

Page 34: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Printed By: Ray Stefanski

FLom: Dennis Lieurance (9/20/91)

To: Ray Stefanski

Subject:

OFFICE MEMO GEM Review Comments

9/23/91

You did a great job of editing! I only had one comment.

Pg 9, 2nd Para. Replace 1st Sentence:

Time:1:28 PM

Date: 9/20/91

"l'he conductor pictured in Figure 1 is technically adequate to assign a credible

cost and schedule on the basis of experience gained from a number of other

Pto jects involving similar technology."

See you Wednesday, Dennis

=~========================================~====================~======

Page: 1

Page 35: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

SERC Dr R Slefanski ssc Laboratory

23 September 1991

Rutherford Appleton Laboratory TECHNOLOGY DEPARTMENT R65, Rm 1.08

Chilton

DIDCOT

Ox on OXll OQX

Telephone (0235) 821900

Fax ( 0235) 4451108

Telex 83159 RUTHLB G

Dir.,ct !,ine: 0215 44 6649 Local Fax: 0235 44 6863 c•mail: [email protected]'IC.Rl,.1B

l recc\ved all the papers for the above meeting and have read lhem briefly.

We have run \.he parameters tor Lhe GEM Solenoid on our optimisation program and find tnal lhe conductor crass sect.ion is not adequate for protection during a quenyti. Fol' SOkA it would be n<>cessary to have a quench parameter {G) of ? x HJ

1 which from t.he attached graph you will see is not po"sible far a temperat.ure ris<> limited to lOOK. 'l'hc conductor given on page 9 of the 'Report of t.he First Meeting of U"' GEM Magnet l'ldvlsory Panel' is more appropriate to 25kA but that would require 800 turns. (Maybe there is something we have not understood).

J\ second point of interest iu the question of helium in the conductor. We do not follow this argument, as stability is related to the stresses the co11 is subjected lo, rather than the level of stored energy. GEM Magnet has much lower stresses bolh thermal and magnetic than magnets built to date. Our finding is that with higher st.orod energy magnets, Wh<:>re the conductor is slzed t.o give full protection during quench, then it is more stable. That is, where the ri.,ld is lower and the superconductor is being run at <SO\ of short sample.

PcrhapR we could clear the~e poinla and confirm the parameters of the magnet early in the proceedings of Wednesday's meetin9.

Finally in Appendix A you have me down as attendin<;1 th" second meeting only. I am ab.Le Lo be at t.he thtrd meeting and already havo my ticket and acconunodation booked.

Look forward lo """ing you Wednesday.

' Peter Clee H~ad r.lf r:ngin~9:ri.ng O'\,;i~lon

Page 36: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Extended Page 1. 1 • J •

pc028

An establishment of the

S<:icnce and Engineering Research Council

Page 37: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

1·5x1017

0·5x1017

- 32 -

Residual Resistivity Ratic~

• P <Rx) p(4.2K)

Copper

----

RRR 160 80

RRR --1000

------- 500

100 200 300 Temperctt.!!'S \.\1 ° K

Page 38: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Extended Page 2. 1

Figure 13 G(T111) vs Till for ::::?per .and .aluminii.un

Page 39: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Dr. Ray Stefanski Plasma Fusion center Physics Research Div· Massachusetts Institute of Technology SSCL k Cambridge, Massachusetts 02139 2550 Bee leymeade Avenue Telephone: 6171253-8100 Mail Stop 2001, Suite 215 Dallas, Texas, 75237-3946

September 19, 1991

Dear Ray,

I am sorry to have to miss the next GEM Magnet Meeting, as I will be in Japan. I am therefore dropping a note to report on some progress since the last meeting, and on our meeting yesterday with Gary Sanders, Gary Deis, and Richard Stroynowski. Based on that progess I also enclose a suggested modification of page 9 on the First Meeting Report.

We took the task after the last meeting of analyzing the "Figure l" conductor to see if, as written, it could be " ••• defended on all technical grounds... "

Our analysis indicates that transient heat input from, say conductor motion, would reach the superconductor in about 2.5 msec, a time very short relative to the heat removal capacity of the cooling tube. The lack of adequate cooling surface in the tube and the poor thermal diffusion in the helium are at fault.

If the superconductor were internal to the tube (as in the alternate conductor considered at the meeting, there is no such cooling limitation. The stability against heat input is nearly two orders of magnitude higher in the alternate conductor.

We came to the conclusion in our meeting here yesterday, that it would be wise to change to the alternate conductor, whose stability can be rigorously defended.

Accordingly I suggest a mark-up of the first meeting write-up to be more compatible with the conclusions we reached at the later time. Note that the dimensions on the figure used in the draft were incorrect.

Sincerely Yours,

~~~----< D.Bruce Montgomery · \ Associate Director tel 617 253 5552 FAX 617 253 0807

Page 40: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

,,,,,-

DRAFT 9/16/91

required for the magnet to discharge during a quench, and V d 1s the

voltage developed across the magnet during discharge.

• The quantity of superconductor and stabilizer used should give

very conservative margins in current and temperature (e.g. lop/le !.

0.3 or ~ T cs .?. 2K), where lop is the normal operating current, le is the

short sample limit: ~~

.-----·------ --· . . -----

~ ..• the temperature margin between the operating temperature and the current sharing temperature.

The conductor pictured in figure 1 was chosen as the base case for further analysis of stability under transient heat input (for example, conductor slippage.) Such a conductor can also serve as a baseline for cost and schedule studies on the basis of experience gained from a number of other projects involving similar technology.

If analysis indicates insufficient stability, an alternate arrangement of the basic components will be considered, in which the NbTi cable will be incorporated into the helium cooling channel.

Ground-plane insulation

?;~~~@--copper stabilizer

~'4"'4-:;4~4--- Forced·flow He cooling

ffe.+.~~~~r--- Continuous tube

----- ------ ------ ------ Coil centerline

Figure 1

9

Page 41: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Q) c:

Cl

i c:

§ 2l ~ e

8 Q) .i

~ ~ ::c .a

Q) N 3: "' <..> "

I :a .Q :J en 0 ..,. 0

i7 "' I

§ "' :J

'5 1;j .,, c:

.0

I .E

l ~ ·.;:; z en ~ c: :a 0 0 LL (.)

<..> 0

<..>

I E E

I E E

"' "'

I

I

Page 42: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Proposed GEM conductor

_.,-- Coilform

,'-- Ground-plane insulation

Copper stabilizer

36mm ~5555)))S'>>>>~ Forced-flow He cooling

~#~~ffl Continuous tube

6mm

-

0( Nb-Ti SC wire ~///;(.a,. /-l ___ Soft solder

~7LZ'.2

~20mm~ ~-----55 mm-------~

----- - - - - - - Coil centerline

Page 43: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

N OSI

11.

" ['-..... "' m ~ " ..... N ..... IT>

E

.. t)

0 0

I- c: 0 .... en ---0

t)

OI (/) L E

.., UJ I- > !;'! en (/)

c 0 a L - ....

(/) :::J u.

E 0 0: u.

IT> If)

"' OSI

..... "' "' .... I

['-.... I

11. UJ UJ

100

50

0

-50

-100

GEM 1 --- Baseline with Full Pole

Field tG) on 117-foot surface

-100

.l

.2

.3

.4 • • • •

1.0 c =J

0 Z-oxis Cbeomlinel, m

CONTOUR LEVELS fl02 )

~

J_~ LI-

l'i .. I I

'· I a ; i:

S; g

; ... -l c

" c 0 .. ~ .. I -~ ..: • -:i.

.! • • .a ::

J l

100

Page 44: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

ISl Q

'[:!

j " .... N .... en

F!

U1

fu I-

"' }-

"' e U1

ii'

~ ITT en (SJ

.... ~ .... ,[_ .... lb Ul

E

~

.i 0 c: 0 ..... (ll ·--0

4) (ll

<­.i > (ll c: 0 <-

1-

100

so

0

-so

-100

GEM 1 --- Basel\ne wlth Full Pole

Field CG) on 154-foot surface

-100

.s

1.0

1.5

0 Z-oxis Cbe0111linel, m

CONTOUR LEVELS c~o1 )

~

..lK 1

' I,

100

i I ~ ~ i:

;; a

! ~ .. cl

.! .! J &. . .. . -ii! ! • •• Cl .. l l

Page 45: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

~ ()_

" ['--.....

f ..... N ..... rn

D I-

~ in a ~

~ ll'i Kl ..... rn rn ..... I

['-­.....

fu U)

e •

D u c 0 ~ (II ·--0 t) (II

'­I> > (II c 0 (._

t--

100

50

0

-50

-100

GEM 1 --- Baseline with Full Pole

Field CG) on 158-foot surface

• 4

• 4

-100

.8

0 Z-axis (beomlinel. m

CONTOUR LEVELS f10 1 ) I

~

••

••

100

...LK.8

i I ~ ~ i

!t g

i ! .; : j I ;;: . .. . "' .! .. .. ,;; , J 1

Page 46: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

GEM 1 --- Baseltne with Full Pole ...LK~

Ill .,, Field (Gl on 169-foot surface CL a

" 100 I

c:-.... I l()

~ a c:- .8 " .... N .4 .... ! .... "' ,

1. 2 I '\. ;;; e 50 I. 6

; • i ..,

0

i 0 c I- 0 ..

en ·-"U • ) .., 0 c

" en '- J

Ul .., !I :E > LU ...

I- en I Ul c )-

0 Ul -.. '-z .

0 I- ... - • Ul -so -::J z LL

a

:E

~ .4 ~ ~

0 .4 • (}'.

'-·;;

LL / ,;; • .,,

~ ~ M .,, J .,,

.... .... -100 l "' "' I .... I

c:-.... I -100 0 100 fu

IJJ Z-oxis Cbeomlinel. m CONTOUR LEVELS fl01 l

I

Page 47: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

ft:A51'8)L\)'\

"' AcP-.\E\JEU~~ &f ~~'1Ce1~ ~ARAA..1~~~

" \.)t--)$1\-\S..'i)~~ ~Q\>~

o U>M.{)~\'~ UD\1°)\l~ Cos\~ sc.itmuLL-

Page 48: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

e ~'"M ~ c..A~ACl'f"\f \$ AvA>\..A'3LL

·\~ C-ON~0c.ntt._

(> C#NChlul>/l.... ~'EM\/10R.. t~ 1~svs1i1vc....

Tb S~L ~JG L.... ~ ~c:j'"'""""'"

Q l"\f.l....tvo-\ \$ CON~NEJ> Wff>h/N ~

''co~n.N0c:·l,.'.'.s f\J/~s

--

Page 49: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

o kJ.tif>l.L ~,~ ~~IS oi?- oPUAno~

~'~ ~~ c.U-Ovl-4..S

o S\,)Q(~4.~ S~£LO i~ ~~\110IS ~

1..-t~ Nr>N ~ O~~PT'aVE._ ~-vP

Page 50: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

5 o 7 'fikQ.s. ~l\C\JU) %L 5\)~C-l£tvr

c S1"-tPl...\Fl.C..A1-10~ /Ml/\Jt~l~TI~ Df: jClk.1~

I~ ~ Lo"--' 0'\..' C'n ~

. ' -· ... • ---· -' -

-<> MA'1-.,I M\)/V\ ~~- €. \l'L loNS~q\d~

c N~X\M\)t-\ ~~~L-+J1pt f!-o~ p~~4LLtL­~f>UCA\\~~

l\ t(

c \""if fli>oM. ~"-' f>UMA~fN) ii\)' l. ~ >~~ ~NO c~ ~,\L.. cvof!..u._

Page 51: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

o $~\Lt\'{ ~N~lU~ 4..~~l. ~ )

1~~1\\Vl~ Tc ~J\l....._ U>N~~r

o (l)N.\\N c:1~ c.t>U ~ ?~4ss - Fl\ •Nl"O s, ""P\..L ,, ~eA \..t -i;i:t(.,. "

o l..D~4 ; _L.~·"'-Gil~'\.S ...

~ CN -<b'fiE_ ~'5\C-0 0~ A.l..L.A-{IA.:1.:~}

we~~ .Sw'"-'( e~1(f_

Page 52: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

0 l)N - A)~<;;c;A~ I F B£t-\~ YI c-R-._., 1Ns~1T<v'L. TC ~A'--- c~-

.. : ~ .. • .. ··

9 A~f-~,:"~ -re ~111JO ~osl L1.lc£1.'-f

" FA J /..J_: tL It A.,/ (){JL. I/Ac c..·'tr'M ' ,..~JJ,.r ) .~

.- .

Page 53: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

" \)}fftCt..>L't"y M-- .jO,~ ·

o ~\ffit.va...~ Of ~~ ~ S\J Ptlcvt->&hJd't-A- ~ Ceo\Al.J~ IAS!ll44L.

'( "' t> O\.C: \ ~ \~ <( t.ec.L~ s,

~ \) \('fM ll'fi')~ ~~

o rt£.btc.t\b~ r~?'AL W- ~lll.j

Page 54: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

• ~>f"i"' 'bts1~~ As~.c~c:L

~~s~~

o S".c t>'b'lt:i~ Jtt"1~c:L rl•4'A. .'\l.A~L c::ao.:_' h\6tlCA~ <!>~ c.~~"c.t'tll. ~ ~~.4f&.'i

Gt:a.~ f COf.J ~~rs

o "-/AU-- A l.tlol.-'... CiJUIUJY., WI.~ N-

a- UNSthf•W 1e ll>ll.- ~NS ( ~vUlf

OtlsM'"" f;A11,.,) ~~/U ~ M~l . . . } , > J

- ...... • .~ .... . ->:

o <..ALWU.fi-/t•;,~A~;k.· ux> £fffchlll;_,~ .

eF i,-~cc5 .S~U/J 01->'i>vA:S ;,.;ccvd-'V ~ . I

_.,. .. -..

f~f!.iitlL Stf1EL.D .Sl{-11U>b£. /

.tJ6'ff) 61..1 £U.<-£... 6tJ ~

o lAul>£H'L. ·a>~ f SO:J-et1t,,.'LL ~ (i~AJsr · tfL.;,tzuC f)r.J J~~f):,£____ ;:; . . ~. ,,. ,/'/

·'

'. .

Page 55: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a
Page 56: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a
Page 57: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

S-/fJ/'il I

1) CvT T#E Fk~L 9'~/k-l>F£ /4"

It/ .llx/;1'2.. G.JF~l"~.f/ /l;v.) ..i t?T. 4 ~~t'A'.L

I

~ KlSE G£CrtJ/f!!;. Cll.V fii:--­

~tf)F° / ~/:~BJ..$"~,.,

M0t1v~l> 11.-1-t--. ~ J.//t,,(f. /'I/° _c:-

19V.) )15,f.SS.1;:-N&E_fl

1,V Mcw.ey.

/P T#~ s1:JE ~ #'S~~BiF.J;

Page 58: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

~ 1-'fl.l~/,4.,'/1p~ ( r()l¥.S PDtt.

lb l'lkF~

"~ .t s~cr~

ff: 1--- Jf 0 Cf

Lt..

~~/'IP# ~""" 4.F vs;.>

·' .

/J fJ n

Page 59: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

y'l}t. (IP~ //~~~#t. ~E ~)I

Ill/ HF##)" ST/t#crt'R.t JY S(l//Jt:Jer

~ ~ 11 fll/4/ sp!trc?P'~~ ro

MC VCl/11 7if! ~/( T ~

--- --- -

- - -

Page 60: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

' . ,,

Superconducting Magnet Design Options for GEM

John R. Miller

National High Magnetic Field Laboratory Florida State University

Tallahassee. Florida

Page 61: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

~

Magnet System Design Requirements

• Provide acceptable muon resolution • Ensure safe and reliable operation • Fit within the experimental hall • Conform to an electrical-power budget • Show feasiblity for on-site manufacture and

installation • Allow compatiblity with stray-field

constraints • Minimize the cost

MILLER 005 9.3.91

Page 62: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

'

The superconducting magnet options

Preliminary studies indicated that, for comparable total costs, both superconducting and resistive versions of the detector magnet system could be designed to meet most requirements, except that resistive versions had difficulty in conforming to electrical-power budgets. Superconducting variations that were examined showed significant differences in projected costs.

MILLER 006 9.3.91

Page 63: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

<

Superconducting solenoid with external iron Relative cost, approximately 1.9 (dominated by the additional cost of a 30-kt iron shell).

Coaxial superconducting solenoids (shielding by annular flux return between coils)

Relative cost, approximately 1.5

Single superconducting solenoid (unshielded) Relative cost, 1.0

MILLER 007 9.3.91

Page 64: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

MAGNET DESIGN PARAMETERS

Centeral induction (T) Inner radius, cryostat ("free bore") (m) Outer radius, overall (m) Inner length, door to door(m) Measurement lever arm (m) Mass of windings (t) Mass of cold structure (t) Mass of cryostat vessel (t) Mass of iron poles (each) (t) Radial pressure on windings (kPa) Stored energy (GJ) Inductance (H)

Single 0.8 8.3 9.5 29 3.8 440 330 550 2950 260 1.8 1.5

Double Coil 0.8 8.3 12 29 3.8

500/700* 450 845 7000

390/-11 O* 4.1 3.3

*outer-coil/inner-coil

MILLEA 012 9.3.91

Page 65: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Common features for superconducting coil design • Primary cooling by thermosyphon loop attached to Al-alloy

coil forms

• Conductor topology requiring minimal development and adapatable to any of the design options

• Single-layer winding secured against slippage under axial loads by radial ribs on the coil form

• Epoxy-impregnated glass wrap on the conductor for turn­turn electrical insulation and enhanced mechanical integrity of the windings (additional epoxy-impregnated

glass sheet between the windings and the coil form)

MILLER 008 9.3.91

Page 66: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

l.9 cm

FIG 2

MAGNET NATURAL CONVECTION (THERMAL SYPHONJ LOOP

1000 liter HELIUM RESERVOIR --._

3-5 M

52 COOLING TUBES

~2.5 cm I t

2.5 cm

COOLING TUBE CROSS SECTION

U.9 cm DIAl·

7.5 cm DIA

~ t

15 cm DIA

l.2% QUALITY

10 cm DIA

~--

5 cm DIA

,, •,' ~

'··

.)

::;· .. : f·

. ~-;} ..

' .. ~;

.. ,. ·-;;,: '.

'.

~·.

Page 67: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

L * LJKYUlicl\JlL/ ;::,r;:, lt.1Vl ;'.JL/t1t.JV1A lllJ lttt.LlU!VlJ,

l.05 ATM

" 0

IJ

Ii

50M

REFRIG. 2

1.2 ATM

1.3 ATM

3-5M

l 1

~BM

L

4.65K MAX TEMP -IN MAGNET

STORAGE DEWAR

LIQUID TRANSFER LINE

MAGNET SUPPLY DEWAR

• JI'. ' ' Jl: rl ·i. • •

CRYOGENIC ·i BUILDING ... I '.' .. ,

'

II . rir " ... '

GROUND ~EVEL

"

6 H LINE NA TUR AL CONVECll ON LOOP<

ceoo g/s fl ow)

'--------'------:_::~:i+---=---- 1.2 % VAPOR o0Au TY

20M

3 H LINE

.f-------UP 10--------.r !OM

. w.

MAGNE.T;

52 EACH 3/4" TUBES

Page 68: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

FIG 3

L * LIQUID NITROGEN SY~'l'l::~M t>CHt;MA lllJf.

GROUND LEVEL

160K LITER LN OE.WAR

11 MPS CSUBCOOLER) II PU

II

11 11

0.8 mPe ---85K LN2

LN SHIELDS I 7

;. ·.~ .... : .... , •,

" I . •. ·:·:··. 11

.. ·\·. 11 .. ' ' \~ '. .

.. : ~ ~. . 1 I

CRYOG~NlC BUILDING 1: ~

. ~~-·

. : ·~· :

" 11 . " .. II :.\: . ··.

,,:_·

··.:::·:j _.·

· ..... '. ·~·::' .

..... . . ; _:~

.- 0.5mPa .{ 90K : ':"~ · CSUBCOOLEO,; ·· SINGLE PHA$E. LIQUID) . . .:

"•;

( ~· .

!-."·".

' ~_ ... ~; .. . -:·:~

.,·.· ... ··.' ·~ .

.· ' .. ;

:i :. ·. ''

-, .. -y; .

. '~ :; ·:_·:.:':

Page 69: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

. \-FIG 4

L* CRYOGENIC BUILDING PLAN Vl~W (SHOWS ALL MAJOR EQUIPMENT)

COOL DOWN HEAT EXCHANGER

LIQUID NITROGEN CIRCULATING PUMPS CSUBCOOLERl

160K LITER LN DEWAR

1.5 KW REFRIGERATORS

60K LITER LHe DEWAR

I COMPRESSCJRj

l-8KiDs I

.:·:..

.. /

.. ;·,

... ';

: '.:.? •

. \: •I 1 .. .'r

" . ' ··1..: ··.

··• :'.:< .::~;

:11':· 12M ·,.

· I I :'~;

.>11 ;•'

1·'.

CONTROL ROOM .--------------------~····

ELECTRICAL PANELS

: : ' .~ '

24M .. · . '·'.·

Page 70: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

CONDUCTOR TOPOLOGY

•Cable of Cu-stabilized NbTi composite strands mated to a Cu extrusion to meet simultaneously and conservatively the constraints for protection and temperature margin

'tdischarge ~ 200 s Tmax~ 80 K

T margin> 2 K

•Secondary helium channel internal to the conductor for enhanced stability

Near-zero flow rate Minimum number of electrical-isolation breaks for maximum insurance against leaks

MILLER 009 9.3.91

Page 71: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

en c: 0 Q)

·- ..c +-' ctl a. 0

0 '"O Q) :t:: .... Q) fl)

Q) .!:::! E 0 Lo. a. .... ::::J a. 0 a. ::::J ·- E en -

0 en a> 0 +-' 0 a> I 0 (.) ....

a.. ::::J

::::J 0 :::::: '"C I-

..c c z 0 (.)

Page 72: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Proposed GEM conductor

012mm for forced-flow

He cooling

Copper Stabilizer

Nb Ti SC wire, 20 ea 1.6mm dia

soft solder

l 20 mm 36 mm

J 1 .. 6mm

i..-~~~~~-55mm~~~~~~~

Page 73: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Heat capacities at conductor components near the operating temperature range

-~ 106 Ct)

E ~- -- -- - . -. -- -----. -- --- -- . -- - ---. -- . ---- Helium (isochoric) """') -- 105 ctl Q)

I ()

;:;:::: 104 ·o

Q) 1 Cop~--------a. Cf) () 103 • - - - - -: - ~;uminum ·;:: -Q)

E :::J 0 102 >

5 6 7 8 9 10 Temperature (K)

MILLER 002 9.3.91

Page 74: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Allowed stabilizer current density vs. maximum allowed temperature during quench and dump

~ 9m f J2(T) dT = J~Tj = f y~~;) dO = U(Om).

0 o,

20,.--~~~-,--~~~-.-~~~---,~~~~,.-~~~,

15

~-'::;:

"' N .. "' g 10 ~

~ :>

-\\ " . <j~ \Q ""'

~Lut.\\tl\UIA Po ~

5 RRR=540

100 200 300 400 500

TEMPERATURE 9 ( K )

MILLEA 003 9.3.91

Page 75: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Contribution of conductor components to the protection allowable for conductor current density.

--. (\j 25 E

~ ~ 20 I/) c: Q)

"O 'E 15 ~ ::I 0 ..... 10 ~ ::I

"O c: 8 5 "O

~ <( 0 -

0

,... •

/ •

/ , / copper -

/ , / helium --~----------~-------- -----NbTi

20 40 60 80 100 Allowed maximum temperature (K)

MILLEA 010 9.3.91

Page 76: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Pressure vs temperature for He with constant density of 130 kg/m 3

so--r-~-t-~~-t--~-+-~--+~~_J__

40 <? a. e. 30 ~ ::J

~ 20 ~ a.

10

0 /

0

/ /

/ /

20

/

/ /

/ /

40

/ /

/

60

/ /

/

80 Temperature (K)

/_

/ /

100

MILLER 001 9.3.91

Page 77: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a
Page 78: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

COIL WINDING SCHEME COIL CLAMPING PLATE SPRING WASHER REMOVE. AFTER EPOXY CURING. '.

----------------------------7-----------j"""""'-"""•------- @ ~

@

®

~

'

• -FILLER ~ PIECES

·~ ~ ·~ ~

CONDUCTOR --­o~

' SPLICE JOINT

- COIL TO BOBBIN SHEAR RIB

' ' ' ' • __________________________________ ,.,,,.:-.,....,._ ____________________________________________________________ 1

Page 79: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

:z: 0

::z: ~ c lXI

CJ E- ::z: I:!=! s

::z:

u :s c,:)

~

a..~

c

i:c..:J C?Jc

cc

::!!!: Eb

Ct::

en ~~

c ...._ §!

......10

=:J

0 -~

8

8:::>

c,:)

:z: i:c..:J ... =

' ... ; __:)

0 u ;a

i ::z: UJ Ci5 CJ

~= ca:S ~ ~

C) ......

..... ~

......lr...u ~

.8a 0

•..

Page 80: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

30000 0

7388

n m (B -,'\ ~-'\ \

I -R 9500

,_ / ---/ ,_ /)\-R 8000

I\ I I Ii-END POLES \ I I

\ I rlOOOO

I I

I - -

I h rf-LR 2500

¢ 1s927 I ¢7400 I I I

I I 500

- -- -- - 0.00 I I

¢ 19000 I I I

I I I I

I L__ I I I \

I/ I

\, \

~; ~•1! .,.. ....

' :• s;; ' --.it ........ ,

"f' TIJ ' ' ' ' ' " ' w ' ' ..... yr--- --Vy 8-30-91 CENTRAL DETECTOR

SUPPORT CYLINDER NOTE: POLE SUPPORT

NOT SHOWN

----

V7/ ----v ~"""'\I

Page 81: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

457

LfJ N LfJ

TITANIUM AXIAL SUPPORT RODS H l~

7~Jo-m i,.I ~MM....+-J.-...., \, I 7388 I II ·I OUTER CRYO

TYP. 16X

OUTER LN SHIELD

BOBBIN

COIL

INNER LN

INNER CRYO 100 'In RADIAL SUPPORT BLK ROTATED INTO VIEW

50 --ni­CENTRAL

MEMBRANE PLATE

DETAIL A SCALE

i.-1000M M----!>oi

8-30-91

N (!) N

lil

" LfJ

¢100

ALLOWANCE FOR THERMAL SHIELD

RADIAL

~~~~~RT DETAIL B SCALE

i.-1000 M M---t

8-30-91

Page 82: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

" N '¢" 0 N

" N ("') 01

I

\ I \

./ ,-

" N (1)

co

'\

\

J

co 01 ("') N

~

c:i I

Cl en I

co

co 01 to

Page 83: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

TITANIUM ROD END

BOBBIN

3063

BOK INTERCEPT

TITANIUM RADIAL SUPPORT ROD TYP 16X

0-----

'E:J-1 1==:' p~:::===~ AXIAL SUPPORT ROD I

TYP 24X

SECTION SCALE

-IOOOM~

8-30-91

SPHER !CAL WASHER

RADIAL SUPPORT

BLOCK

Page 84: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

BOBBIN

L * COIL WINDING

COUNlER WEIGHT

CONDUCTOR REEL

lENT COVERING WORK AREA

Page 85: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

,5 M

SSC DETECTOR 2 MAGNET FABRICATION FACILITY

' . -1 ,, --- - ~ --)--1'"---n / ~ ~ -

"'"" , Il ~ , ( ' -() "'~ EJh -- 0 - --! --=rr \_____ _/ ... ·=v ·"~

'

\----o - --=e=- I

• -ISO "ETERS

,, .. L.. • " fl9WlR~ __, j .:!!fu ~)y1"7zz~zzn k;!PhJz~zzT.ZL2z -~ $)/hz2b£§!7J7),~zi"2z~ .

I 41.5 "ETEf

DEL lYERY AND STORAGE' AREA ACCEPTANCE TESTING

35 x 50

SHELL flJlRICATION AREA

35 x 35

COIL WINDING ANO CURING AREA

35 x 35

~AGNET ASSEMBLY ARU

35 x 35

MAGNET TEST AREA

25 x 35

Page 86: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

SSC DETECTOR 2 MAGNET FABRICATION FACILITY

AREA #1 - DELIVERY AND STORAGE ARENACCEPTANCE TESTING

•CONDUCTOR DELIVERY AND TESTING •BOBBIN SECTIONS, VACUUM SHELL SECTIONS.RADIATION SHIELD SECTIONS ........ INSPECTION AND STORAGE

•COMPLETED SHELL STORAGE (NESTED)

AREA #2 - SHELL FABRICATION AREA

•WELDING •GRINDING •GRIT BLASTING •STRAIGHTENING

AREA #3 - COIL WINDING AND CURING AREA

·SEGREGATED FROM FABRICATION PROCESSES AREAS FOR CLEANLINESS

AREA #4 - MAGNET ASSEMBLY AREA

•SUPERINSULA TION INSTALLATION •LEAK CHECKING

AREA #5 - MAGNET TEST AREA

·ROLL MAGNET ·WELD ON SUPPORTS ·COOL DOWN .

•FURTHER TESTS

OVERALL FACILITY DIMENSIONS­•LENGTH-180 METERS ·WIDTH-35 METERS ·HEIGHTH-41.5 METERS

Page 87: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

SHIPPING/ RECEIVING DOCK

AREA 1 DELIVERY ANO STORAGE AREA/ACCEPTANCE TESTING

0

COMPLETED SHELL STORAGE

FORKL !FT·· ACCESS

~/ I I

I I

L

0

-~ I I

I I

. _J Ir- -~ 11 SHELL SECTIONS 11

NESTED 1

Page 88: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

CRANE SUPPORT COLUMN

AREA 2 SHELL FABRICATION AREA

SHELL SECT JON

WALL SE PARAT JN G F AB AREA FR OM WINDING/CUR ING AREA

Page 89: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

" •

ADJUSTABLE HEUGHT CRANE

SEPARATION WALL

AREA 3 C 0 IL WINDING AND CUR ING ARE A

BOBBIN

CONDUCTOR REEL

SCAFFOLDING

Page 90: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

'

LEAK CHECKING

AREA 4 MAGNET ASSEMBLY AREA

~ CRANE SUPPORT

SUPER INSULATION INSTALL AT ION

Page 91: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

' AREA 5 MAGNET TEST AREA/ROLLOVER TRANSPORT PREP

GANTRY CRANE ACCESS

SUPPORTS -WELDED ON

REMOVABLE ROOF SECTION

MAGNET ROLLED FOR TRANSPORT

COOL DOWN IN PROGRESS

Page 92: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

1 0

WIN RA

MAGNET SUPPORT STRUCTURE CROSS SECTION

Jr

" I .

: 7m -· ITER DING JIUS

I~ ,-u u -

..J ~ J1 - - - ~

'

... 1.0m - I . 1

I RIBS TYPICAL

OUTER WINDING

COIL LENGTH CYLINDER 13.0m 44.5mm

u u

-

.,II -II - - - - ~ ~ ~

2.0m I

GUSSETS TYPICAL

- ~

J1 ·..r ~ ~ - ~

_l '

I

f 8mm ER DING INDER

WINDING 13.25m

RADIUS STRUCTURE LENGTH

Page 93: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

GEM BASELINE MAGNET

• Conservative

• Demonstrated technology

• Simple/reliable

Design to schedule considering logistics of on-site fabrication

Page 94: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

•••

INlllJ!Alm All'I LOID Cll COILS Z9 ,. HOOP SIRESS • .l<IMPo

JHIOQI I I -·· _, 10 Mr ' -lie POii rc•:i lOll 101" allD 1MSS -Ill rD CllYSIAI ( 111111111 C11 llUlll lllll • - t!Slll

8Allflf:l llUON CHAMBERS

CENIRALIDCT[CIORS

JOOOI

16 MODULES e • IOI EA.

EiC> CAP llUON CHAMIERS

11 MODULES ~ • 101 EA.

SUPPORT POINTS

GEM GLOBAL SUPPORT SCHEME

I

-·IQ.IS uP TO JOOOT EA. (10001 FOR IHIN POL[)

llOVAllLE llOIMT

Page 95: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

ISi

ISi

e

'" m l!8 151

.., er

jL

z CJ ... .... CJ IC _, ...... ~~

151

er

.,, m CD CD

• ISi ... er _, ISi IC

::c ISi .... "' z c ... .... u "" :c "' u "' a:: "' "" z "' ... z ca: :5 :::> > .... ru '.:::

I-

.. ISi

:> ~

CD " . .. IX-

UJ ...J CJ Cl..

~

a: ...J ..... a: ~

UJ 0 CJ Q.

...J .. ..... '- CJ 0 Q. Q.

L..J

:I .. '-.. D I! .. .t::. <> c 0 :> :c

a:

I!

J

CD

Page 96: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

'-., .t::. ~ ., 0

..._

0 -'

~

a: ::c ..... ~

0 c ., ., U1

> z CJ c a:

., .... '-

:c ..... ::i ~

u ..... '- .. ~

.... 0 c U1 ::c ~ 0.

., 0

u ., 0. '-

ID U1 a: :> .0

I

L!I .... U1 Ii

.. z 0 ..

0 .... U1 ~ '- :c

c oz .. UJ

., z a: .0 z .... ::i u-1 e ., cc

..._ :> I-

., '-.t::. ~

_J

ru " u c CL.

- - .. z

E c u z

CJ 0

.... f;] :>

cc :c .....

0 ..... 0 a: -' 151 .... ....

UJ :c:

0 .... a: ::c a: "'

,_ cc _J ..... cc ,_ UJ 0

_J ..... Cl w

., ~ "' .,,

"' .,, m "' :>

-e "' er er ID ID ID 'O ., ~

a:

Page 97: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

It I I

I ,, ·"- ~

, ;

~ r>lfi! p,..,,,, ...

I I I ... - I I or.l C.011. CoN<j?«Sf~ ..... .... .,_ ~- .,_ '<----l !

I ' I

- t•\v -ill'•D ~ ...

I I

""'"6---. _11- . t------ -I

' I I --12__ .

I . ! A I

T ! -- -· ,_ -- -·~· • 't:. ' /' .::--... . ..

"'' I / • • a,_ t I I tJ I o· / -....... ' " . .

(Oii. I . . -" . ·, I • I!' MOO

'

"; ......" r. -- '· . I I . '(·

I I •I.. ~ '\. ' j ·a '\' '\'

-'\. •

' I

•10•

I ! \: \. 1·r,--1 \, '\: • I I I .

'\i \: I .. -,._, • l .

\ \....;. ·1>11r D I

\: \: ... - -----'I& I ! -1n

\ I \ i : I I

' !

\! . ' \ ' '

• \: . •

·28 \ \ ~ I ·\n \

I ' ·'. I ' '

I

' I

I ·"'1'i

\· . ' I . • . • . \ i4 ...

.'

\: .

··"--- r_ ' , ,·" ~ ' I ..;,, _ v ... -

' UIK

I . I

-c.. --' J '

I ·Ln ; •

-----·----·--·------

Page 98: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

GEM Conduator Poro••f•rt

ALUll. THERllAI. MASS

ST STEEL CONDUIT

CABLE 480 STRAND

7.62DO'c• ( 3 In. )

2.5400 •• ( fl In. )

I = 52.5 kA "= 408

2.541; c• ( i \n. )

1.5532 c• ( 2.51 In.

L• = 55.92 • = 2201.1 In= 183.415 II Cable Area = 285 .... 2 Vaid Fraction= 30 S

Cand. Area a 199.5 ••·2 CABLE CURREMT DENSITY• 114.2 A/...,2 No. of strands = 480

STRAND Dlo = .723 .. cu/sc = 3 : I le= 388 ( 2 T, 4.2 K)

lop = 109 ( 28 S ) g/• = 3.435 ( 2.2& lb/1000 It )

Talal Cond Length • 22815 • ( 74853 It ) Total strand Longlh • 11.09 • 10•1 • Total strond ..,.1 = 38.1 • 10-1 g Total Conduit "'' • 31.3 TonllOI ( 90.658 lbs ) Alu• Area = 40.5 c.-2 Alu• Val = 92.4 .-3 Alu• ..,.1. = 255 Tonnes Talal Cand "'' • 332.4 Tonnes

Page 99: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

8x10B~-~-r~-~r---i-~--,;--~-~~~~

7x1oB+-~~-+-~~--t~~~+--~~-+-~~-1-~~-Y:V'

6x1e>8 I I I I I I ~ /I

(;' c ~ 5x1a8 I I ;: I I ~ I 'I 0 > A

• ~ 4x1o' I ; yf w I I ,g I I ,, l 3x1o' I r , "' . • Ii

rn I I I"· f ? < -I .,·,er r t • >"

I 'I , S.-1 ·. ··f I 2x108 I I , _ , ~~ ,.·:-··' .•

1x1a8 J I ~ .... ~.! .. ·· I I I

Ox100 l ,.·-;--, c;~ 0 I I I I I I I I I ,,,,,,,,I 1 I i i I

50 100 150 200 250 300 Temperature (K)

Copper

- Iron

Nickel

- Niobium

--Titanium

Tin

Aluminum '.

Teflon

Heffum:130kg/m"3

- - Helium:150kg/m"3

"

Page 100: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

GEM MAGNET TRUDEL I . 0 TRUOMP • 35 s RRR 40.0

~

'.::l.L ~

w a: .::J 1--er a: w Q_

.L w I-

3. 8 E ' ' ' I I ' I ' ' ~ ·= I I ! I I I I I I I I I 3 3.6

3. 'i

3.2

3. llJ

2.8

2.6

2.'l

2.2

2.0

l. 8

!. 6

l . 'i Uil I

~--~---------------1---------------1--------------

- - - - - - - - - - - - - .I - -> - - - - - - - - - - - - "" - - - - - - - - - ... - - - • - .. - - - - - - - - - - - - - - - .I - - - - - - - - - - - - - -

' ' ' ~-J---------------J-------·-------~---------------J--------------1 I I I

' ' ' _____ J _______________ J _______________ J _______________ J _____________ _

I I t O

'

-----~-------~---------------~---------------~---------------~--------------

' I I I I

_________ , _______________ , _______________ , _______________ , _____________ _

' ' ' ' ' -----------1---------------1---------------1--------------.-1--------------

• ' ' ------------~---------------1---------------~---------------1-----------i--

------------4---------------4---------------4---------------~--------------' ' I I I I _____________ j _______________ j _______________ j·--------------~--------------1 t t f

' ' I I f t

-------------~---------------i---------------~---------------~--------------0 '

' ' -------------~---------------~---------------~---------------4--------------, '

J.2t I I ' I I I I I I I I I I I I I 0 0

I i j I I I I t -j

102 . 2 .8 .'\ .6 I. 0

TIME !Sl

Page 101: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

GEM MAGNET TRUDEL I . 0 TRUOMP • 70 s ARR • L/0.0

~

~

w a: ~ I--a:: er_ lJ .J Q_

z w I--

s.0.---.----.~~~~~~~~~~~~~~~~~~~~~~~~~

'LS

lj. 0

3.5

3.0

2.5

2.0

I. 5

101

I. 0 0.

' -----------------,--- --------------,-------------------,------------------

------,-------------------,-------------------,------------------

-----------,-------------------,-------------------,------------------

' ' ' '

_______________ , ___________________ , ___________________ , _________________ _

' ' ' --·-------------,-------------------,-------------------,------------------

---·-------------,-------------------,-----·-------------,------------------

' ' -----------------,-------------------,-------------------,------------------

102 .5 I. 0 I. 5 2.0

TIME ( s)

Page 102: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

(9 (9 -•

0: 0: 0:

-

N . m

I I I I I I I I I - " - - • - - - "I· - - - - - - r - · - - - - r • - - • .... T - .. - • - .. ·1 • - .. - • ... • r - - - · - .. t • • • .. • • '"I• - - - • - .. , .. • - • -

I I I I I I

' . . '

0 , 0 1 I I ,. ............ , .......... r······r·-···-1··----~-----··r······r--·-·-,----···r···-

• I I I I I I ........ , ............ ~ .. -- .. --,.-----,.•·--·-~·-····-r·•··•• • • • '

' '

• .

' • ' ' .......... , ............ r····

' ' I t I I I 1 I • • .. • • T • .. • .. • .. '"I .....

!SI

(f)

OJ

N

···r······r···---,.------~---···-r······r···---, .......... , .... .

N N . N N N N

( )! )

CD

N

N ...

([)

w L -I-

Page 103: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

ISi •

N

I - (I") + .... "

,... •• II)

f) r-- 15? c LJ') x (.) -on ::> - _J

• II... f) ID ..... c .... z 0 ...., II ex +- Ole ..... Q ' - (/)

0 :r E z ISi 0

" - u '-m -0 com LL.. Q. + a: w 0 19 c !S>I (/)

~ • . a: ..... _m ::> > 0

• ..... 0... - lJ') z

0 a: ... • u z: ::c :I w I- 0 (.!) ....

-c ::c 0 u ISi -

• ISi

ISi co <D :r N ISi co <D :r N • - ISi • • • • • • • • • • ISi N - - - - - -{W z

Page 104: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

GEN --- Thin Pole Option~: Ca~e 2 ,f ~

MITMAP Vl.0 8/14/91 18:26 1

Contour I • 0.008E+00 Delta • 5.1116Sf+00

. 0 ~ I I J ., 7 J /'I I / 7 '; 7 '7' >' . ~ I I L

.8

6

4

2

0

8

6

Lt

2

0. 10 1 .5 1 . 0 1 • 5

A I ml CONTOURS OF CONSTANT FLUX

2.0 . :I I

' • I a •>«!'""""""' .. -~ ·~··

........

Page 105: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

(S)

N

('I") '

(T)

u N* .. ,....

" co~ "'

lf) x 0

_.,, ::::> - _J

LL.. •

" • c .... ..... 0

- II

z a:

~ c:no I-en

Q ' 0 -:14 E z IS) 0

tl -'-111 w

0 COCf - LL.. Q.. II.I

a: 0 SI

c cs.1 I ff)

cc .t: • • t-

_m ::::> 0

·> ..... • ~

Cl.- U1 ..... 0

a: ... • u z:: ::c 6 ll.J I- .... (.!) -c

l: 0 {,) -\S) -

• ISi

\S) ro <D :r N \S) ro <D -:14 N • • • • • • • • • • • -\S) ISi

N - - - - - -(W z

Page 106: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

GEN --- Thin Pole Option': C~'e ~

MITMAP Vl.0 8/14/91 18:25 Contour I • 0.088E+00 Delta • 5.073f+00

2 0 j I I I ) J I ~ I I '7 > I I > I I :::::- I I I • I II 117 ;>

l. 8

1. 6

1. 4

1. 2 -E

- 1. 0 N

.8

.6

• 'i

.2 10

1

~ I I I I I I I 'I'''''"" IU • i I I

0. 10 1

I .5 l~.0 1.5

R t ml CONTOURS OF CONSTANT FLUX

2.0

Page 107: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

-e

N

GEM --- Thin Pole Option': Co'e 5

MITMRP Vl.0 8/15/91 9:57 Contour l • 0.001E+00 Delta • 5.07qf+00

2 . 0 ~ I I ( } J I I I 7 I I '7 '; '.7 '7' :>-' I ~ I I L

1. 8

1. 6

1. 4

J. 2

1. 0

.8

.6

. ...

.2 10 1

r,i 1 1111111111111111111 ~- I ' I

0. 10

1 .5 l.0 1.5 R I Ml

CONTOURS Of CONSTANT FLUX

2.0

Page 108: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

.. 0 ... ~ ... £ ;

.. 0 ... '3 ... " ~ ;

l!!

IC

' lC :JI

,,. N ;;. N

"' ... ~ N ... "' .. ... a. a: lC -z

.. ., IO ,,. • . • . ...

.. ., IO ,,.

..; • • •

N .. ., IO ,,. "'- . • . . • . .... 1• I z

N .. ., IO ,,. "'- . • • . • • .... -I• I z

.. ,,. N

0 ;;. ... N

'3 ... " ~ ; "' ... ! ~

N ... i "' ' ..

...

; ' :IC -z

'! N

.. ,,. N

0 -Ill ... ... N

;z £ ., ; "' -- ...

'! =~ ! ~ N ...

-..,~ j "' "' • ...

"' a. i ~ -

-! z

-i...~~~~~~i..,.... ...... +...~""'"" ...... -'-!~~!-'-' ...... r"'

: ' . . . : ' . ·-·· ··-···· -··-··--·········-····-------· ......•. ·····--··· . . ' ' . . . ' i i i i i i i i : : : ' .

I j j I j •-• ••-i••••-••+••H•••·•••••-••i•-U••-i-o•••••••••••oOoo.;oooo-oo «> . ' . . ' ' .

l 1 l ! i 1 j i i i i i ; ;

------...i-------.i.. ........ t .... ___ ; ______ _J., •••.••• t ....... .,i •••• -.. "° • l l l l ; l l c . . . ' . ' : : : : : : i j i i i i

·-····-i····-··+····-···~--·--··:·-····-+· .. --.. ·~·······~·-··-·· r i i i i i i i : : : : : : :

______ j _____ ,.l ........ L ... -.. !. _____ J, ......... L ...... J .... ___ N

i i i i ! l I : : : : l ! : -.

ai

! I I i ; ! :

• Ill • ,,. ,.:

1!11

N7 • -. - •

-+'~~ ...... ~~!'-'"~~~~~~~~~~~~..,...· N

! I l ! ·-.... -. . . --· ····i·········-~- -.----·~· ;..---··'t ......... -~. ·-.. Ill

! . ! i i

. I i i . ' ' . . . ·--- ·-·;··-······'··········~····-···-'-·--·····•·······-~··-.. II e i i i i i i ! ! ! ! ! j ! ! l ! ! ! -····-·:··-······!······--··:--··-···:········:--·····-:··-·· ""

.. oO

; : ! l ! : ! ! i ! i ! l ! ! ! ! ! I I i ; t i .. • ,... • • .. • ui

llll

.. .. . ..; ._ N • ,,. -

Page 109: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

GE" --- 1h1n ,ole a,t ions• Cet1 l

HIJHAP YJ.8 8/26191 23•28 2.11 ........ ~. l. . .. . l . •

1.8]

1.6 [ l.'1"1 I I-

1.2., I .. • I.II., I .. ...

.8., I ..

.6 "I I J-

• 'I ., I .. .2 "1

18' I J-

"· ' . . • • I I • • • I

•• 11111 .5 1.8 1.5 2.8 ft I •I

ElfftfNIS

GEM --- lh1n Pole ••t1ons: Case 3

HITMAP Yl.8 8126191 23• 211

8.11 !

"I.Ill ! . ~ , _______ ............ ·-·-·-- ·-·-····-·· -· -....... _____ _. ______ .... ·-i ! j : : : l : ;

6.8 --········-·. ---: ·-. ···-. ·-·. ··· f-····· ... ·-- ---:---··· ........ --l l !

= s.a ~ i ! ••••••••••••••••.,-•-••••-••••••••~••••H•••••••• •-t•-••••••••••••••

i i i .. '1.8

3.8

111· 1

2.8

••

~ i i ·--·············r-····-········r···········- r··············· .............. ---!-----------····t-·---········-· --···--·---·-··.

! ~ i j I

u•••••••••••••••t•-••••-••••••••i••••••••••••••-••'•-••••••••

18' .s 1.8

Zf el 1.5 2.8

GE" ·-- 1h1n Pole Oot 1ons1 C111 l

HITMAP YI.I 8/26/91 23t21 c.e ... I • ··-· •••• • 1.17•••

2.11 J I '1 ~ I J' I) I /7'7 ;7 :? '::::::::-=t 1.8

1.6

I. 'I

1.2

• - I.II ...

~ ..

.8

.6

.'I

.2 1•' I. l ,'I''

8.

., . 6.

5.

'I.

3.

2. 1e·1

I.

•• .S I.Ill 1.5 ft I •I

z.111 18'

CONIGlllS Of COISIAlll fLUI

G£H ·-- 1~1n l'ole 8ot1ons• C••• 3

HITMAP YI.I 8126191 23•21

------·-·+-·-····-··i·--·-·····i·-········-+ ···--·· ~--·-·-····· ! ! ! ! ~

i~· l

1--·-·-····+·· ..... - . ·1--········i· •· · · · · · · ·· +-- ···-··I•···--·· · ·· . . . . . . . . . l l i ~

I•-•••••••• t •• •••··-•• t-· ••••••• 1" • • • • •• • • • •t • - • ·-•• ~ • •• • • • • • ·• • ! ! ! ! ! , ........... +···· ·-----:---·-····--:--·-· .... ··+--- .. --. : .......... . I I I I I : : : : :

•.••.••.•• .j. •.••••• ---i·-·······-i···········-i-·-· ____ j .......... . : : : : : ; ! l ; ;

········ ··r······-··1·--·······i-···· -··· ··t ·-· · ·--·1 -· · · · · -·· ·· ............ +----.---·!--····-···t··········+ --··· ---!-··········

j j ~ i : I. I • 2

II •• .6

"' .. .8 I.I J.2

Page 110: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

, " /I

--·-vnz·at1n111 rt11rJpU/fl/¢J'H2?,' ---K--1----- -- -- --- ------------ . ..,,e:. _____ -1-&-__

-- -- - -· - - ·-· -----,

1-J: - '

_z__j_ ___ .,..._..-----~ - ----- ---- --------++--

- ----- - -- - - '(J_ -- ___ )! -- ____ ------ - ----==r_ ~c_,,,'b~'---+-1---_.JJ4· fitl'-- <!>W)'l?dJf. __

~ ~-i=--~~~~~----------~ !if~-~-=============+=~~----- . ------- ----- ---1----__ !_ _ EtSL _f0 ~_3110 _ _______________________ --------I----

___.·"-- htrff: 3~'-? fq" _ · _ _J _ _=-_· [_ ,= 'f, 6M ==-riz.-))c~ ~eq~L_ 1it11~_ or-_-_t!Cl_f, __ ~----c-&-w--Z-~------+----

___:.i ___ ~ t1.rv ch#MJ.e,.'----+n-..--tt'-r-aF71 -1Afs.Jltf(( - I.~ - : -+----- ~,, _= _/h'it.f --J I-rd.tr -i-~~!_~~~~~

-:-·---rt;,,17_-__----- ~~---- . - --~--..-~---.......,. '.(f/J,.1-= _f.lSZ @2~0.11 _{"f_Cl!lt6:1)/[j,i:i_ 1 ~ _t1Jf4 Js,a[11. ,

~1!/t;.,_-; o.f~l0.7_f ~~.ftluj·-c;;~;Jfi9Le ~=--I!fJ;;;._: 0~1i_f;_l1J,Jl+~tr/1j{mJJ4 I

Page 111: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

" ... .. - i:i .. -O> i5 .. O> - "' .... .. .. .. 0 .. 0

" .. .. "' .. .. ~ ,, I

" 0 ... ... .. ... ::! " 0 " .. " 0 .. .... 0 .. > ~ .. - .. .. ... .. "

"' .. .. I I

"' .. .. g .. .. "'

-1Z.4A'10'-

;z.Z..x1oc.

------------------ --

-0 .. ... .. .. .. " 0 .. • •

.. • .. -• -= --0 u .. 0 ~ .. • ~

.. J ,, • -• ':! "'

Page 112: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

-

"'I -cw IW

. /

~ v

-

r-1 0

-

Page 113: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

-~ ---------- ) ...------- ~

~ -J """ :::;. --~ - '~

i§ -~

, ,. ~

ll E = , -

~ E b ' ~

• • IE D

• f IE p ~

H ~ IE D c

H F E D c

~

R F II! b c

n , IE D c

H ~ E lo

~ ~ E D

~ E ~ B -

T ~ IE ) c

• ' • t

O.IT Detector Dual Coll,Pole•.Flux (rA)

r-.._ r-.._ ......

• -- - • • ~ c D IE F

'

IA a D E ~ R

a

A IB Er • l II IE F •

l " " E • • " IA B E • II

" IA B ~ E • II

A IA B ~ E • • ··-A A II D E • II

• l B b II! • • ~ ' D E • ' ft: D I! • • 1-1

, '

_..i.--

N. \I

AllSYS 4.4A

AUG 14 1991

14:03:47

PLOT 1'0. 2

POST! STRESS

STEP•2

ITEll•lO

KAG

SM)f •-32.771

SKX •I . 13

zv -1

DIST•9.992

XF •6.922

TF -9.084

A --30.888

B ·-27.121

c •-23.3H

D --19.587

E --15.821

F --12.054

G •-8.287

B --4..521

I --0.753782

,.

Page 114: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

- ' .-JI '"""' '

D _JI ,,,.. ~ ' . - ,,P I.JI--~ r J. . JJ,,,...,._ _.Ii'-• _.l,....B r.-"'-

~

-' r _,_ ~

~- I I I

i ~ -" p ,,,;' 'w

Lt:.-' )' -..!; n n - - ... .,... - - n

y J; .J

• ' ~~·~ O.IT Detector Dual Coll,Pole•.Plax l•••n (T)

-..I f-..1 '--4 ~ -..i ~N ~ N

N: ~ .

... r

: -.I - ~ D D a

c

~ I

c I~

~ I A

~ I~

~ I~

:-..

c 'I ·~ ~ ·~ c

·~ c I~

c I

~ ~ )

9 - • ~

' r ; II

•v

. r -

'

-.J>,

AllSYS 4.4A

AUG 14 1991

14:03:55

PLOT 110. 3

POST! STRESS

STEP•2

ITEll•IO

BSUK (AVG l

SKll •0.010228

SllX •2.283

zv •l

DIST•9. 992

XF •6.922

TF •9.084

A •O. 136509

B •O. 389071

c •0.641633

D •0.894195

E •l.14'7

F • l. 399

G •l.652

B •!. 904

I •2. lS7

Page 115: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

~ ... ~.sc,,., ("".,,/s

BSVM / 0. 825637

~ " 0.743075

\ 0.66051•

0.577952

o.•9539

0.41H28

0.330266

0.247704

0.1651•2

0.08258

\ 0

I'.. • -T n •n 0 811.11119 30.9110 •11.11011

5 lS 25 34.9911 u. 9119

0.8T D•t-ctor Dual Coll,Pole•.Plgx Den•lty at Z·O•.fO••r•SO•) ----------------· ------- -----·

A.lfSYS "l.4A

AVG 14 1991

U:04:10

PLOT 110.

POSTI

STEP•2

ITER• 10

PATH PLOT

WODl•l

MOD2•40

BSllM

5

STRESS GLOBAL

zv •l

DIST•0.6666

- XF •0.5

YF •0.5

ZF •0.5

Page 116: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

BSUK

0. I 78E-04

0.161E-04

0. l45E-04

0.12BE-04

0. ll ll!:-04

0.944E-OS

o. ?r•E-05

~

0.610E-05 / ~~ I

0.443E-05

~ ..........

0.275E-05 ...... 1---~

I 0. IOBE-05 0 40 on 120

20 60 100

0.8T Dete~tor Dual Coll,Pole•.Flux Denalty at Z•0•,(50acr'2'0•)

160

HO 180

• Sllll

DIST

200

ANSYS 4..4.A

AUG 14 1991

14:04: 13

PLOT NO.

POSTI

STEP•2

ITEll•IO

PATH PLOT

NODl •40

lfOD2•!50

BSUK

6

STllESS GLOBAL

ZV •I

DIST•0.6666

XF •O. 5

YF •0.!5

ZF •O. 5

Page 117: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

BSUK

0.381E U4

,'\ O. 34~E-04

\ o.:>06E-04

\ 0.268E-04

\ 0.231E-04

\ ' \

0.193E-04 l/ \ o. 156E-04

\ O. l l8E-04

\ 0.806£-05

"' :~ 0.430E-05

~ 0.548£-06

n on 100 ISO

25 ,., 125

I O.~T ~~tPctor Dual Coll,Pole•.Flax Den•lty at r·50a,fO•z•~90•)

-

.. SIBT

200 250

175 225

AllSYS 4. U

AUG 14 1991

14:04:07

PLOT 110.

POST!

STEP•2

ITEll•lO

PATH PLOT

110Dl•40

NOD2•1'140

BSUH

4

STllESS GLOBAL

zv •l

DIST•0.6666

XF •O. 5

YF •0.5

ZF •0.5

Page 118: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

• N

GE" --- Thin Pole Dot1ons: tase 3 wt1h SC return

HITHAP Vl.8 8128191 13•'17 2.e+-'-'-~~ ........ ~~........,~~~ ....... ~~~-+-

1.6

1.6

1. 'I

1.2

1.0

.6

.6

• 'I

.2 111 1 e.~~~~

II. .5 1.5 2.111 1.0 R I •I

ElfNENTS 1111 1

GE" --- Thin Polt Oot1on': Ca5e 3 ..-.tb SC return

HITHRP Vl.8 8128191 13•'17

6.111 ·-------1·-~···r···--·-·····--·1·-···--·-·---···

! ! ! 7.0 ·-·--·-·-···-·---~-------····-···.; ....... ·····---~---·-···--·-····

i ! i : : :

6.0 ·················1·-····-········1············ -·-r--·············· - 5.111 I- - • •• ·- -· ••• - • • -- ·r · --· ·---· · · · · -· i-· ·-----·----- --r-----· -··· --··· · = ..

'I. Ill

J.0 1111·1

2.0

! ! i ··················1·-····-········r············-- :·--············ '··················1·-····-·······T············-····-··············

'·················+-····-········i··············-··f ·-

•• 1e1

i l ! .s 1.0

Zt •I 1,5 2.8

GEH --- Thin Pole Dot ions: Case 3 w11h SC return

HITKRP Vl.8 8128191 13:'17 c.t_. I • ·7 ... lf•ft 0.1•1 • 5.12lll•M

2.0-t--~~.,._.,.........,,.._._.__..,~ ......... ~"'"-I~~+

1.8

1.6

I. 'I

1.2

• - 1.0 N

~ ..

.8

.6

• 'I

.2 11'

0. j I I II I I i ;

8.

7.

6.

5.

'I.

3.

2. 10·1

I.

•• .s 1.111 1.5 11111

R I •I 2.111

CONTOIMIS Of CONST~f FLUX

GE" --- Thin Pole (lotions: case 3 w11h SC return

HITHRP Vl.8 8128/91 13•'17

. . . ! . ] ! ··~:.:.::--··--'.· .. ····--··r·-••o-• r··----~·--

:- -········ +-··-···---i----······~--···· ····+---··- .. f ••.••••. : : : : :

1--·-·-····l···-···---~-------··-t ......... r ·---- .. ! ........ . ! ~ i : ~

·-·-·····-+ ···-------i-----·-··-~----·-····· ·---- ---i---······· : : : : : i i i i j

1--·······--+··--------:·-----····~·-·---·-···+ .. ---:·-··----··· i i j ; i : : : : :

1--·· •. ·-·-• .;. ...... ----i. ---- -----.f- -· ·-· ...•. ..;.. .. . - .. i .... ·-· ... .

~ l i l l .... ·-..... .). ....... --. i --· ........... ---·-... .).. --· -i .......... .

f i ! i f .. .......... .,. •. -------. t· ---------1-.......... 't ·- --- •• t· -· .••••...

I I I I I : : : : :

I. I . 2 II -~ .6

RI •I .8 I.. 1.2

Page 119: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

GEM --- Thon Pole Option~: Ca~e 3 ~.th SC return

MITMRP Vl.0 8/28/91 9: 2 Contour I • -2.091E+02 Delta • 5.229E+00

1. 5

1. 4

1. 3

1. 2

1 • 1

1 • fZl

.9 ~

E .8

.7 N

.6

.5

.4

• 3

.2

-11 1 fZl

fZl • fZl. 2. 4. 6. 8.

R I ml CONTOURS OF CONSTRNT FLUX

Page 120: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

GEM --- Thin Pole Opt1on5:

MITMRP Vl.0 8/28/91 Contour l • 0.00BE+00 Delta •

1.5~ I '1' :~ 1 • 4

1. 3

1 • 2

1 • 1

1. 0

.9

Ca5e 3

15:21 5.070E+00

'E .8 ~

N .7

.6

.5

.4

.3

.2

10·11 0. l i I

1 I I I 1 I I I

(;1 I I I I I IU • ' I I ii I I I I I I I I I I 111111 I I I I \ I I J I \ I \ I 1 I 11 \ ,.,..

2. 4. 6. 8. R I ml

CONTOURS OF CONSTRNT FLUX

Page 121: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

7 mJ -CS>

N N N s .

N "" ai O> s N "" IT> Cl) 151 N "' s

("')

s 0 :::> -t 0 c: CJ) -,

0 Cf) en r 0 -< l'TI Cf) CJ)

("") cs - -t 0 • C"l rri z cs z

~ CSI -1 cs <: •• Cl "' N s + • c :::D

CSI W Cf) :D

cs (.f)

-t Cl> I>

Cl 3 ' ........ -.,, ....J G'i ...... I c:o .,, en ID -t

r 0 • c (!)

x ~ ..t: Cl>

• - Ul N

N . ,&:. ~ s -·~ ...:I w ...:I ITI + cs cs

N • en

.....

Page 122: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

1 .,

gdmagpan 1-1 9n.191

The Design-to-Cost Development of the

Initial GEM Magnet Baseline

Gary A. Deis, Applied Research Engineering Division, LLNL

GEM Magnet Panel Meeting 4-6 September, 1991

SSCL, Dallas TX

Page 123: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Outline

In this talk, I will discuss:

gdm•gpmt-2 912/'n

• Our design-to-cost effort (overview)

• The approach and methods we used

• The major steps in relaxing the magnet design requirements and reducing the cost.

• The next step

• Summary

LI

Page 124: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

The initial GEM magnet specifications

resulted from a "design to cost" effort

The overall objective was to develop a concept for an L*·like detector, estimated to cost less than $500M. .

gdmagpan1~3

9/2191

• We reduced the magnet cost (by changing the performance requirements) from $179M to $73M, In 3 major steps

• Because of the time available (1 month), detailed designs/costing were not performed at each step. We relied instead on a magnet/muon parametric cost model

• We do not regard the cost model predictions as "real" cost estimates, but rather a guide to the important trends.

• A complete design and a good cost estimate for the LOI is the objective of our present work

Lll

Page 125: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Our parametric cost model permitted overall system _®timizations

Malor Input parameters:

Magnet OD Magnet ID Magnetic Field Barrel OD No. muon wires/plane

Mechanical clearances Max/min sizes Unit cost factors

gdmagpanl-4 9n/91

~

Design Models

Magnet design algorithms

Muon design algorithms

Cost Models

Magnet cost algorithms

Muon cost algorithms

f Costs (byWBS)

Design parameters:

Numbers of parts Sizes, shapes, weights Mass of steel etc, etc, etc

Performance Model

Muon performance calc's

t Performance (muon L\p/p}

ll

Page 126: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

The magnet cost model was based on scaling from the L * LOI design Lii

Simple calculations were done to size conductor, vessels, poles, etc., then costs were scaled based on a variety of parameters:

gdmagpanl...S 9!2J'll

The cost for:

conductor coil winding vessels bobbins radiation shields cold-mass supports cryogenics poles

was scaled by:

$/Ampere-m (and design) $/kg and $/m $/m2 surface area $/Pa-m (mag press*dia) $/m2 surface area fixed fixed (except rad shields) $/kg

Page 127: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

f..-------------- 53.42 m --------------i

9.21 m

2.00 m

------- 31.00 m -------""1 i------- 27.00m ------

Hadron Calorimeter v Muon Chambers

Electromagnetic Calorimeter

L_ Central Tracker

7.5°

Page 128: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

The L * LOI provided the starting point for the development of the GEM design ~ L * was a fairly complete pre-conceptual design, which was costed in some detail, and was then reviewed by the Theriot Panel

gdmagpan1-6 9!2m

• The magnet was a 2-coil (ie shielded) superconducting solenoid with iron poles. (Separate (warm) solenoids were used for eta > 2. 7)

0.83T 17.Sm ID, 24.0m OD, 27m internal length $127M, not including contingency

• The muon subsystem was designed to achieve 3.2°/o muon resolution:

32/64/32 sense wires per plane $158M, not including contingency

• Total estimated base cost: $285M (magnet+ muon)

Page 129: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

We adopted the Theriot Panel's recommendations for all further costing Lll

• The Theriot panel recommended no change in the base cost estimates, but recommended increased EDIA, contingency, and R&D costs.

• We assumed these additions were uniform over all subsystems (conservative). This resulted in a 41o/o increase over our base costs:

$179M for magnet $223M for muon

$402M total (magnet+muon)

(The end point of the downscoping is a system costing $226M -including TF (the ''Theriot Factor") - for magnet and muon subsystems)

gdmagpanl-7 9/2191

Page 130: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

The first step in downscoping

was a reduction in coverage

gdmogpanl-9 9/2191

• Forward/Backward magnet and muon systems were eliminated. This sacrificed coverage for eta > 2.7 (or theta < 7.5°)

• The cost savings was $20M for magnet, $27M for muon

• Resulting costs (including TF) are: $159M for magnet $196M for muon

$355M total (magnet+muon)

II

Page 131: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

i--------------- 53.42m ---------------1 9.21 m

2.00m

1-------- 31.00m -------

i------- 27.00m ------i

Hadron Calorimeter Muon Chambers

'

Electromagnetic Calorimeter

L..- Central Tracker

STEP~I

Page 132: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Next, the muon resolution was relaxed II We changed the muon resolution from the L * LOI value of 3.21 % ap/p , to 5°k ap/p (both at 500 Gev and 90°) ·· . .

gdmagp.n t • 10 9f2J'll

• We reduced the magnet ID from 17.Sm to 16.6m, with no change in the OD. Savings came from:

reduced field in the annulus smaller/lighter parts (inner vessel, bobbin, and poles)

• This reduced the magnet cost by $33M, to $126M

• We reduced the overall size of, and number of sense wires in the muon subsystem. Savings came from:

fewer parts (sectors, chambers, wire planes, etc) halving the number of electronics channels:

32/64/32 wires changed to 16/32/16 • This reduced the muon cost by $43M, to $153M

• Total cost at this stage: $279M (magnet+muon, incl TF)

Page 133: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

.,, CD

0 c

: .,,

-::E ~ -.,, 0 0

w > !;( ..... w a:

350

300 -I

250

Outer Diameters

Muon/SC Magnet Cost Model • V1a

Cost vs Performance at BO = 0.83T

Data from "'CvsP/.828T/16,24,32/data"

I

\22

I

' • I I. 26 m 24 m

\ ' \ I I I

-\ I \ \

\ '. '\. \~

'

3.2% L" LOI design (32 wires)

'I).,

'"'o. ~, "'Q.._o. ........

..... , ........... ..... 'o---

5%, 2-coll design (16 wires)

\ I

m\ I I

q\

'~ ....

' \ ' ' \,'a

........ .. .. ..... -'.:.'=8: .... - ..... .:a

200-1-----...... ------.,..------...-----~-L--.....,...----..... ------.-----+-----....... ------1

1

CvsP/.828T/16&32/moda gd-3/26191-1025

2 3 4 5 6

ap/p {%)

BO : 0.83 T

Outer Radius (m) • No. wires

10.0. 32

---a----... ---------

Notes:

11.0·32

12.0· 32

13.0. 32

10.0·18

11.0-18

12.0 • 18 13.0-18

- Includes fib systems • does not Include TF

Page 134: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

::!: ... ~

Ill .. -0 c ti .. Ill --Ill 0 .. c 0 :I

370

350

330

310

::ii 290 + -ti c Q 270 <U ::!:

(_j

Muon/SC Magnet Cost Model

J------' ----• £ ----- ~ . ~ -'0-------------- --' - --o-- -------. -----

\ • . . - ' . • • .

'

·------- ·ii -----------u----------------1 ---- -----• '

1t ---.--------.-----.:: ' -0----------------0-------------.---

All cases: double coll 24mOD

--- 3.21% - 32 wires .- 5% - 32wlres ........ 7% - 32wtres

--i:J'-- 3.21% • 16 wires

---6-- 5% - 18 wires ---o--- 7% • 18 wires. '

.& .- LOI design

3.21% 24mOD 0.828T $355M

Noles: 250

0.8 ~ •

0.9 •

1.0 1.1

1. does not include costs tor forward systems

2. Includes AEDIA + conl (lotal A • 41%)

Figure 5-2

Central Magnetic Field, T

Variation In combined central mapet alld mllOll 111tem1 cost with resolullon, Reid and chamber C0111tnictlolt bitted upoa an Integrated parametric cOll model. The L • Letter ot lntHt desJan point II Indicated.

Page 135: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Finally, the magnet concept was changed L\I Without significantly changing the physics performance, the outer (shield) coil was eliminated

1¢m'8P""l-11 9/2/91

• The ID and central field was fixed, then the shield coil was removed and the end pole thicknesses were reduced. Savings came from:

elimination of one coil and intercoil structure reduction in size of outer vessel and poles

• The total extrapolation from our starting point was becoming large, so conservative assumptions were made:

no significant savings in cryogenic system "medium-thickness" end poles

• This reduced the magnet cost by $53M, to $73M

• Total cost $226M, incl TF

Page 136: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Baseline magnet configuration

E 0 ro rn

1.25 m

E 0 N t-

gdD2co!l:ih2- 4 7 /J.'j/91

CUITRAL OF.:T(CTOR surPon1 CYLINDER

27.00 m

10.QO m · 1

I i --r

E

·-·-·-·1·-·-·-· . ol. - · - · - · - · . - "':I ,_ I

SIC WINDING

1.25 m

El E 0 l.D

\12

0 co ~

L\I

Page 137: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

~ a;;

'i' "'

' ,'

S.C. Coil, Tapered Iron Pole, No Barrel 18 E I I ' ' I/ I/ y Ji/Y/VYYYCI I I I =t

16

14

12

Z (m) 10

8

6

4

2

00 5 10 15 R (m)

Contours of constant flux TIP-020$4

Page 138: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

420

:e 400 -~ 380 .,, ID -0

360 c ID G> 340 Ill --.,, 320 0 0

c 300 0 :::J

:::;;

+ 280 -ID 260 c DI

1111 I

"

Muon/SC Magnet Cost Model 1-coil Version - V1*

Data from "d/SC-1coll/17·25mOD,16&32"

•' I \iJ

/

3·2%, 2-coil L • LOI (w/o fib) $355M •' ,. . ' q\.

\.. ' ' Q - '•

\.. ' ' .. ' ' ~~ ' ... .. Cl .... .. tt ...... ...

Iii.

' .... __ --. .....

• It~-­-..~-.. ~--....... "'13.~ .............. """" ..... -~-... _

... ,,._,__ --.;;r .... .._ - -o.-.,.. _ -~!"-. ......

5%, 1-coll design (with thiek pole) $235M

501 1-coil design •--..--. -• •••••------• .,._ ~ --- ·~ ~ (with thin pole) - ----•---------------

$226M , .... <> • I ' I ' I . I • I 220 ' I

.. :::;;

240

1 2

C*vsP/1-coil, 17-25mOD, 16 6/4/91 - 1458 - gd

3 4

Ap/p (%)

5 6 7 8

All cases: single SC coil 16 wires

------- 25mOD

----- 24mOD ---o--- 23mOD

---...-- 22mOD

---a--- 21mOD

--~-- 20mOD ---r-- 19mOD

------- 18mOD

----- 17mOD

.-- LOI design 2-coil, 24m OD 3.21%, $355M

Notes: 1. No forward system 2. Includes AEDIA + cont

(total A - 41%)

Page 139: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Magnet downscoping summa_ry

L * LOI LOl-f /b 5°k. 2-coil 5°/o. 1-coil

Outer dia, m 24.0 24.0 24.0 Inner dia, m 17.8 17.8 16.6 Internal length, m 27.0 27.0 27.0 Central field, T 0.83 0.83 0.83 Max eta for muons 4.0 u 2.7 Muon res @ 90°, o/o 3.2 3.2 5.0 Shielded magnet yes yes yes

Magnet cost, $M 179 159 126 Muon cost, $M 223 196 153

Total cost, $M 402 355 279

(Underlining shows significant changes from previous design)

gdmagpanl-8 9111"1

17.8 16.6 27.0 0.83 2.7 5.0 DQ

73 153

226

LI

Page 140: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Magnet/Muon Cost Model

Subsystem Costs for Major Design Points

250.,.~~~~~~~~~~~~~~~~~~~~~~~~~-

200

.-:E .,. ~

II. 150 i .... u c

. 100 -ell 0 0

50

0

Csubsysvsdesign

..

L• LOI Design $402M

gd - 9/2/91 - 1137

L• LOI-fib Design $355M

5% 2-coll Design $279M

5%, 1-coll Design $230M

I Em Magnet Cost

• Muon Cost

Page 141: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Muon/Magnet Cost Model

Magnet Element Costs for Major Design Points 60,-~~~~~~~~~~~~~~~~~~~~~~~~~~~

50 -::E .... ~

LI. ... 40 ...

Jll II .5 ..: ., 0 0 .. c G> E

20 .! w .. G> c Cll ... 10

::E

0 Structures Coils. Cryogenics Power/Pro! Iron Poles

Cmagelmntvsdesign gd - 8/31/91 - 1531

Magnet Element

• L• LOI Design

Ill 5%, 2-coll Design

fl 5%, 1-coll BaseHne

Page 142: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

What's the next step?

The parametric cost model is not an acceptable way to do a real cost estimate at the LOI stage.

Ill

The present baseline concept is also quite different from the design we are using as a basis for extrapolating costs

gdmagpanl-12 9/2/'A

• We need to do a good point design for the baseline concept

• We need to do a credible cost estimate for this point design

• If necessary, we can construct a new cost model, based on the new baseline, for use in optimizing the overall design (after GEM LOI)

Page 143: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

GEMWBSRev1B printed 2:21 PM, 9/2/91

3.0 GEM Construction SSCL WBS 5,2 2,3(WBS by system/subsystem/etc)

3.1 Magnet subsystem 3.1 .1 Solenoid Magnet

3.1.1.1 Coil Assemblies 3.1.1.1.1 Coil Subassemblies

3.1.1.1.1.1 Bobbin 3.1.1.1.1.2 Conductor 3.1.1.1.1.3 Diagnostics 3.1.1.1.1.4 Winding Tooling 3.1.1.1.1.5 Assembly

3.1.1.1.1.5.1 Off-Site Assembly 3.1.1.1.1.5.2 On-Site Assembly

3.1.1.1.2 Radiation Shields 3.1.1.1.2.1 Inner Shield 3.1.1.1.2.2 Outer Shield

3.1.1.1.3 Cryostat Subassemblies 3.1.1.1.3.1 Inner Vessel 3.1.1.1.3.2 Outer Vessel 3.1.1.1.3.3 Vessel Ends

3.1.1.1.4 Cold Supports 3 .1 .1.1.5 Misc Supports 3.1.1.1.6 Cryogenic Current Leads 3.1.1.1.7 Assembly and Testing Equipment 3.1.1.1.8 Assembly

3.1.1.1.8.1 Off-site assembly 3.1.1.1.8.2 On-site assembly

3.1.1.1.9 Testing

3.1.1.2 End Poles/Supports 3.1.1.2.1 End Pole Subassemblies 3.1.1.2.2 End Pole Support Subassemblies

3.1.1.3 Detector Supports (If separate assemblies) 3.1.1.3.1 Muon Sector Supports 3.1.1.3.2 Central Detector Support

3.1.2 Power/Protection System 3.1.2.1 Power Supply 3.1.2.2 Buswork 3.1.2.3 Breakers and Dump Resistors 3.1.2.4 Quench Detection and Diagnostics

pages

Page 144: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

3.1.3 Cryogenics 3.1.3.1 Refrigerator 3.1.3.2 Dewars 3.1.3.3 Piping and Distribution 3.1.3.4 Thermosyphon Piping 3.1.3.5 He Recovery System 3.1.3.6 LN Subcooler

3.1.7 Installation Tooling 3.1.7.1 Central detector Support 3.1. 7 .2 Coil Assemblies 3.1. 7 .3 Pole Assemblies

3.1.8 Installation 3.1.8.1 Solenoid Magnet Installation

GEM WBS Rev 1 B printed 2:21 PM, 9/2/91

3.1.8.2 Power/Protection System Installation 3.1.8.3 Cryogenic System Installation

3.1.9 Subsystem Management & Integration 3.1.9.1 ES&H Assurance 3.1.9.2 Quality Assurance Program 3.1.9.3 Systems Integration

3.1.9.3.1 Interface Control 3.1.9.3.2 Conventional/Technical Facilities Interfacing

3.1.9.4 Subsystem Management 3.1.9.5 Subsystem Cost/Schedule Monitoring

page7

Page 145: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Summary

• The $73M GEM magnet concept descends directly from the Theriot-reviewed $179M L * LOI magnet design

• The cost reductions were achieved by relaxing performance requirements, in a design-to-cost approach

• The present cost "estimates" were generated by a parametric cost model, which scaled costs from the L * LOI design

• For the GEM LOI, we are at work on a thorough (though conceptual) point design and a credible cost estimate

We are looking forward to working with the GEM Magnet Panel in the development of this design/cost estimate!

gdmagpanl-13 9/1191

LI

Page 146: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Gem Engineering Meeting September 4-6, 1991 Robert A. Richardson

Superconducting Coil Cryogenic System

A. The following questions will need to be answered to determine what affects the cryogenic systems will have on the underground hall design. In order to respond for the GEFUR (Gem Experimental Facilities User Requirements) due October 28,1991, a response to these questions would be appreciated by October 21, 1991 or sooner.

1. The heat loads for the superconducting magnet including the various loads separately. The heat loads must include the vapor cooled lead liquefaction loads.

2. The additional heat loads during charging from eddy currents.

3 The cooldown requirements for the magnet. times, methods of cooldown, refrigerator sizing cooldown or use of stored liquid for cooldown.

Cooldown for

4. The quench recovery requirements for the magnet.

5. The type of magnet cooling system that is being proposed ie thermal siphon (natural convection), forced flow by compressors or pumps. Provide a schematic of the cooling system if it is different than the enclosed drawing R40000025000 & R40000042000.

6. Provide a proposed routing of the cryogenic lines from the surface to the detector. Review the enclosed GEM proposed cryogenic line routing and comment.

7. Surface facility layout for the cryogenic system.

RAR 9/4f)I 9:03 1 RR00024

Page 147: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

B. More detailed information including analysis of heat leaks through the insulation, structural straps, etc., will be needed to procure a refrigerator system that will support the coil sometime in 1992. The exact date is to be determined by more detailed schedules.

RAR 9/4/91 9:03 2 RR00024

Page 148: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

GEM Experimental Facllltles Schedule 1991 1992 1993 1994 1995 1996 1997

!Cryogenic System Group Tasks Finish

Design utlllty Bldg. 10/8192 ! i •11112 c:;= & mo i ! i . i ! ! i i i ! i i i i i i ·····(·····+· .. , ..... ·····.·····+·············· .......................... -. .. ·<I-·················+····+·····, ..... , ..... +····+···.,······· ····~······~·· . IR·1 Rudy Surface Facllllles

IBld I Award Utll. Bldg.

ICon•trucl U1111ty Bldg.

IBOD utlllty Bldg.

IConc Daslgn Coll Assy Bldg.

IDa•lgn Coll Assy Bldg.

Bid 6 Award Coll Assy. Bklg.

!Construct Coll Assy. Bldg.

Retrofit Coll Assy Bldg.

BOD Coll Assy. Bldg.

10124/94

1/19193 ··:-.,

9/11195

9/11195

6/12192

121221921

~-r-r ·····t····t·1

" 6/20n1"t

9/14194 ·-:+' 9/14194 ~=1~1 . . . . . . . 9/14194 0 'f I

6::; ::~:rJ : ·-r-r·r-r-r . i : ",.,.;-' · ·,

1SC Coll Dnlgn

SC Coll Manufacture

SC Coll Surface Tut Coll #1

..... L .. .J Concaptual Daalgn Cryo System 9/1/93 i ! -lnaJ Da•lgn Cryo system 511194 ---r-r tld I Award Cryo System 9/1194 ..... , .... .,.

onatruct Cryo System ~1194

lln1tall Cryo Sy•l•m·Hell/Sur 11/1/96

ISol•nold Installation (Detector) 9/4/97

~ryo System Toots 1213/97 1Sol~ld Cooldown & Test 1/5/98

IFleld Mopping 215/98

ther Detector lnstl I: checkout 9/23/99

DeW:tor Operation 9123199 ''i'" Prepared by: Robert A. Richardson

1998 1999 2000 2001

Wednesday, August 28, 1991

Page 149: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

Experimental Facllltles Schedule

1 991 1992

CRYOGENIC GROUP TASKS July I Aug i Sep ! Oct I Nov I Dec i Jan ! Feb Mar I Apr i May i June I July I Aug ! Sep ! Oct

Miiestones for GEM & IR • 1: .... ..!. ..... .,. .... Detector Mllstones i ;

1-----------------1·.,,-~.---.4.-,. .... GEFUR Revisions ! ! -----------------j······;l> Tiiie I Design

Tiiie II Design

!Tasks for GEM and IR • 1 Cryo System:

Perform Anal. & Select Sys Design

Prepare Datallad Schematics

Develop Performance Specification

cryo system eu11d1ng Layouts r··1·I·r:11 -Ft-.. t 1IT· i j ! l 1r·1 .. -1~:- .. i -· i ~t-ts;::t"· '. -=--t-+-cryo System Quote ....... , ....... r···· .... r ........... :1:"'"'"T""'"l1······r"'T"~""'i'"''''''''"r"·;····1"'''j"'"i'•••·· .... Tasks by·-· ......... "6.:;. .... , ....... ; ...... t""'t'"'" ---------------<· . . · , ' . · I ,....----... ·- . - !~~- -~-r--"' •

U/G & Surface Cryo Pipe Routing · ·

Transfer Line Dwgs

Transfer Lina Spec

Transfer Line Quote

l.

Deliverables: I l i l i I 1 11

l 1..J i l j I I l i l 1' l l · -----.+·--f-.v- - -:-·- --··..,.r-+-o-·--,---: ~ ...,.,,..j. ---i---~-~.,, ··-..,.t--t---- "'4·~ --i-.......,.,-+-· -·--~·---· ----+---·

=:.:.:·:: · .. _... 1+J~r· !+ri+t~·f··~·-i-··t··· .. -t .... +· .. ~·~t~+$·i ~~Jr ++ ~"' ~~ - ...... ~- ...J.y~-- ·r~-" ~ T~~

TransfarllnaSpec.&Dwgs. . i i ! i Ii i i <> ! ! i j l l ! l l l

Prepared by: Robert A. Richardson Wednesday, August 28, 1991

Page 150: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

FY 91-92 Milestones Experimental Facilities and Detector Engineering

• continued •

GEM (not a complete list)

• • • • • • • •

Approved to Proceed to LOI (PAC/SSCL) Magnet Design Meeting • 1st (GEM) Magnet Design Meeting • 2nd (GEM) PAC Tech. Progress Report (GEM) Magnet Design Meeting • 3rd (GEM) LOI Submitted (GEM) GEM Approved to Proceed to Tech. Prop. (PAC/SSCL) Technical Proposal Submitted (GEM)

IR 1 Facilities

• • • • • • •

U/G Pre-Title I Report Complete (CCDIPBMK) GEFUR Rev. A (PRD) GEFUR Rev. B (PRO) U/G Title I Design Begins (CCDIPBMK) Initial Surface Facility Design Begins (CCD/PBMK) GEFUR Rev. C (PRD) U/G Title Il Design Begins (CCDIPBMK)

Experimental Facilities • F/TPA

• •

• • • • •

Facility Support ror Detector Systems "Fixed" ror Technical Proposals (PRD)

Detector Assembly and Installation Schedules Developed (PRD)

Full- Operation or TIC (PRD) Detector Support Facilities Concepts Complete ror Tech .

Proposal (PRD) U/G Hall Title I Desi~ns Reviewed (PRD) Detector Surface Facility Requirements Updated (PRD) Detector Facility Conceptual Designs Complete (PRD) Detector Equipment Conceptual DesiJnS Complete (PRD) Proceed with Detector Facilities Equipment Design,

Procurement, Installation (PRD)

Jul 19 '91 Sep 04 '91 Sep 25 '91 Oct 03 '91 Oct 10 '91

Nov 30 '91 Jan 02 '92 Oct 01 '92

Oct 15 '91 Oct 28 '91 Jan 02 '92

-Jan IS '92 -Jan 15 '92 Jun 01 '92

-Jul 15 '92

Sep '91

Sep '91 Oct '91

Apr '92 Apr '92 Apr '92

May '92 May '92

Sep '92

OLE page 2 8/12/91 • 17:36

Page 151: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

COOL DOWI HE4T EXCHANGER LIQUID NITROGEN TO HELUM

3-5 M. L

THERMALEIPH&N CRYOG~IC SYSTEM S HE ATIC (HELi Ml

! :--~~#<S-=-·:.T:.::T:~-M~E~~----=-·:.-=-·:.-=-·:.-=-·:.-=-·:.-=-·:.-=-·:.-=-·:.-=-·:-~

.tW2. BOX

1.2 ATM

MAGNET He SUPPLY 11,000 L.l

FORCED FLOW ._ __ THROUGI! MAGNET

CONDUCTOR 2ATM

.. . , I. . '

He STORAGE DEWAR , I I.

CYROGEN!C BUl!.DING . ' LIQUID TRANSFER LINE .............

FORCED FLOW RETURN

~ M9 TO CGll"IESSOR SUCTION

--- rtm.il'ttl ... _.--- lM """*- COMWlCTION LOOI'

·us~&

~c.rr--""'

YAQUI WlSSEL

.... _ ·-

Page 152: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

NITROGEN SHIELDING SYSTEM SCHEMATIC

IOUID NITROGEN

TO REFRIGERATOR I ........ <: I --- SAFETY RELIEF

PRESSURE CONTROL

SUBCOOLER _ __,,

GROUND LEVEL PUMP---~·

PRESSURE GUACE --"""

~~~~~~~~~~~~~~~~~~~~~~~

0 MAGNET NITROGEN SHIELD

VACUUM VESSEL

·-

Page 153: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

t

I

Page 154: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

---•z

CENTERLINE OF DETECTOR MAGNET He

SUPPLY TANK

~---

GEM DETECTOR HALL

ti~ ~ CRYOGENIC PIPING

~

GEM PROPOSED CRYOGENIC

I INF ROI ITINr,

c

~$

Page 155: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

0 0 llli

) )

' .

icENTERLINE OF /DETECTOR

I

-l 1· .146

.146 ~ H-I _._ I I ' I

0.75" x 4• V .J. He LIQUID TRANSFER ' - - - - -0.75' x 4' V.J. He -............ ---------------- --- .,

2' x 4• V.J. N SUPPLY \ --------------- - .,

MAGNET He UPPLY TANK

TOP OF DETECTOR ~ I Ti/ I I I

I I I ' ' . I I I I I I I I

~ft! ~~ I .203

I a1 o 1 «i «I ~I ~I ol ol W 1 uJ1 I __J __J

01 ol I 0 0 ui u1._1 a::I a::l sl 01 0101

~I ~161 >1 >1U1 P..,I ...,,...,,

SECTION A-A <LOOKING WEST l

D X: IV y .u., I IC I .I 1\1'1 Lfl\IL

.,. .,. I' x 4' V .J. He LIQUID SUPPLY

00 ,.., " 7C.• v A' II ' ' '-

"' ..... .,. v A 1 \I I II.I ",...Tl 1011.1

00 .....

c I'--

"': ----------------------

Page 156: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

-' -' .. " a: 0 ,_ u w ,_ w CJ

:s -' -' ;1-----,

,4

0.75' x 4' V.J. He LIQUID SUPPLY

0.75' x 4' Y.J. He

2" x '4° V.J. N SUPPLY -------------

CRANE RAIL SUPPORT

'4 OFFSET

FOR I TUNNEL 1

(1

) 11 (~)----

t-,~,-----­F-----­

+Ji-------­~t-------

I I I 1-u: ~

I 1

4

I

.... I I ~l~t I

sl sl 1 51 z51 I ol ol I u u ,_ ""11

a:l 51 ~~I~ <1 "" 0 >I >lu1 ~ ~,,.,,

PLATFORM

SECTION B-B t LOOKING SOUTH l

... ,

CRANE

:;:1

§I .§~ \Q'..Y.·-b tl.! f!ETU~NJ:.!NE

I' x 4' V.J. He LIQUID SUPPLY

- - - - - - .Q . ..!§'.JC£ y.~H~ - - -

______ £'.!L 4_: y,,/.jlJl.E!URN __

Page 157: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

.323

CEILING

0. I~~~'!. .J. !l~ l,!OUIQ .IR_ANS.fER

1.250

- .292 I

0."!_5..'.._x_ £ '!_.J. !j~ - - - - - - - -f-E>-E>--- -- -- -- -- -~l 2' !..i'_V.J,_~S~PPh'!.__ _____ _

...; @@ii-----------

1 I ! TUNNEL

FLOOR

.254 ~ -· .254

03 -1 1-

0 0 < < w w ...J ...J 0 0 w w ...J ...J 0 0 0 0 u u ..... 0:: 0:: 5 0 0 0 a. a. z < < 0 > > u ;.,, ;.,, ,..,

SECTION C-C SECTION Cl-Cl

I LOOKING SOUTH l

(Ill ,...,

0 ,.._, 1'>1 ..!I

6' x 10' v,J. He RETURN LINE

I' x 4' V.J. He LIQUID SUPPLY

0.75' x 4' V.J. He

2' x 4' V .J. N RETURN

Page 158: lss.fnal.gov · 1.0 Scope The GEM collaboration will be submitting to the Superconducting Super Collider Laboratory (SSCL) a Letter of Intent (LOI) proposing the construction of a

~"s'ir.}r

-- z -- - - ..r1• x 4' V.J. He LIQUO $1.PPLY

I

11 I

I,' I ---------- -€> i

,,

'Z' x "1'V.J. NRETURN

3' VAPOR COOLED LEAD

SHAFT

-i=h ~--~~J L _________ 1_ I

..:rJ== = = =---=- ~~-~=========-r=-==-=,._,,---11 "I ~ I I : 1-------------

1 I I I i I I I •

Ji• VAPOR COOLED LEAD 7

L 2" )( 4' V.J. N 51.PPLY

' 0.15' x 4' V.J. He

• O. 75' x 4" Y .J. He LIQUI) TRANSFER

I

I CENTERLllE OF SHAFT

I

I

PLAN OF NORTH SHAFT

STAIRS