long lead items list
TRANSCRIPT
7/26/2019 Long Lead ItemS List
http://slidepdf.com/reader/full/long-lead-items-list 1/20
KING ABDULAZIZ INTERNATIONAL AIRPORT
DEVELOPMENT PROJECT (KAIA)
CONTRACT:
J-10-421-PF-00
To the Construction Manager:
DAR AL HANDASAH (DAR)
Document Type
DOCUMENT SUBMITTAL
Document No.
421-DCS-SPC-32002-R0
Document Title:
EFPS-AMAN/DMAN System Long Lead Item List
Date: 31st
January 2013
7/26/2019 Long Lead ItemS List
http://slidepdf.com/reader/full/long-lead-items-list 2/20
AviBit GmbH
421-DCS-SPC-32002-R0
EFPS-AMAN/DMAN System Long Lead Item List 2/20
AviBit Document Control
Edition No. 0.1 Draft
Edition Issue Date 31.01.2013
Author G. Reiter
AviBit Reference ICAD-ATM/CDRL-040/LLIL-D0.1
Copy No. Stamp here
Copyright Notice
© 2012, 2013 AviBit data processing GmbH, Austria
All rights reserved.
No part of this publication may be reproduced, stored in a retrieval system, or transmitted in any form orby any means, electronic, mechanical, photocopying, recording or otherwise, without the prior writtenpermission of AviBit.
7/26/2019 Long Lead ItemS List
http://slidepdf.com/reader/full/long-lead-items-list 3/20
421-DCS-SPC-32002-R0
EFPS-AMAN/DMAN System Long Lead Item List 3/20
Approval Table
AviBit Date Signature ICAD Date Signature
ProjectManager
P. Venton
31.01.2013
QualityManager
T. Leitner
31.01.2013
Document Identification
Full Title: EFPS-AMAN/DMAN System Long Lead Item List
Total Number of Pages: 20
Distribution
COPY No. Role Organisation
1 Primary Contractor ICAD
Edition History
Edition No. Issue Date Author Reason
0.1 31.01.2013 G. Reiter Initial draft
7/26/2019 Long Lead ItemS List
http://slidepdf.com/reader/full/long-lead-items-list 4/20
421-DCS-SPC-32002-R0
EFPS-AMAN/DMAN System Long Lead Item List 4/20
Review Table
Edition No. Review type, scope,depth & focus
Reviewers Date Conclusion
0.1 Complete Document P. Venton 31 Jan 2013 OK
System Release
System Release: Edition No.:
TBP
7/26/2019 Long Lead ItemS List
http://slidepdf.com/reader/full/long-lead-items-list 5/20
421-DCS-SPC-32002-R0
EFPS-AMAN/DMAN System Long Lead Item List 5/20
Table of Contents
1. Scope ....................................................................................................................... 7
1.1. Identification ................................................................................................................... 7
1.2. Purpose of this Document ............................................................................................. 7
2. Introduction ............................................................................................................. 8
3. Long Lead Item List ................................................................................................ 9
4. S YSTEM DESCRIPTION ............................................................................................... 10
5. COMPLIANCE STATEMENTS........................................................................................ 11
6. MATERIAL LIST ......................................................................................................... 13
7. DATA SHEETS........................................................................................................... 15
8. TEST CERTIFICATES .................................................................................................. 16
9. SPARE PARTS .......................................................................................................... 17
10. Appendix A: ACRONYMS ................................................................................... 19
7/26/2019 Long Lead ItemS List
http://slidepdf.com/reader/full/long-lead-items-list 6/20
421-DCS-SPC-32002-R0
EFPS-AMAN/DMAN System Long Lead Item List 6/20
List of Tables
Table 1 – Aerodrome System Deployment ............................................................................................... 7
7/26/2019 Long Lead ItemS List
http://slidepdf.com/reader/full/long-lead-items-list 7/20
421-DCS-SPC-32002-R0
EFPS-AMAN/DMAN System Long Lead Item List 7/20
1. SCOPE
1.1. IDENTIFICATIONThis document describes the Long Lead Item List used for the ICAD New Jeddah Tower Project.
King Abdulaziz International Airport (KAIA) is expanding its runway and passenger capability. To facilitatethis expansion, a new Air Traffic Control Tower (ATCT), a new West Support Tower, a new passengerterminal, transport facilities and support buildings will be constructed.
The new airport will initially support up to 30 million passengers per year, growing to 45 million in the firstfew years to an eventual capacity of 80 million passengers per year.
The expansion creates a need to extend and add to the Air Traffic Management Systems in order toprovide safe and efficient air traffic control services as the volume of air traffic increases.
These systems will be fully integrated giving users access to timely, accurate and consistent information
as and when needed as well as the control functions necessary for reliable and effective management ofair operations.
This project foresees deployment for the AviBit systems shown in the following table at KAIA in Jeddah:
Aerodrome System to be delivered
KAIA JeddahDIFLIS®;
AMAN/DMAN;
Table 1 – Aerodrome System Deployment
1.2. PURPOSE OF THIS DOCUMENT
This document identifies those items that should be ordered before the provisioning conference and thesubsequent spares order, because of the extensive production lead time.
7/26/2019 Long Lead ItemS List
http://slidepdf.com/reader/full/long-lead-items-list 8/20
421-DCS-SPC-32002-R0
EFPS-AMAN/DMAN System Long Lead Item List 8/20
2. INTRODUCTION
The Long Lead Item List (LLIL) is provided to identify those recommended spare items that, because ofextensive production lead time, should be ordered before the provisioning conference and thesubsequent selected spares order. An item qualifies as "long lead" if its production lead time is more thanone year.
7/26/2019 Long Lead ItemS List
http://slidepdf.com/reader/full/long-lead-items-list 9/20
421-DCS-SPC-32002-R0
EFPS-AMAN/DMAN System Long Lead Item List 9/20
3. LONG LEAD ITEM LIST
None of the system parts used by AviBit are considered long lead items. All production lead times areless than one year.
7/26/2019 Long Lead ItemS List
http://slidepdf.com/reader/full/long-lead-items-list 10/20
421-DCS-SPC-32002-R0
EFPS-AMAN/DMAN System Long Lead Item List 10/20
4. SYSTEM DESCRIPTIONNOT APPLICABLE FOR THIS DOCUMENT
7/26/2019 Long Lead ItemS List
http://slidepdf.com/reader/full/long-lead-items-list 11/20
421-DCS-SPC-32002-R0
EFPS-AMAN/DMAN System Long Lead Item List 11/20
5. COMPLIANCESTATEMENTS
NOT APPLICABLE FOR THIS DOCUMENT
7/26/2019 Long Lead ItemS List
http://slidepdf.com/reader/full/long-lead-items-list 12/20
421-DCS-SPC-32002-R0
EFPS-AMAN/DMAN System Long Lead Item List 12/20
Material Compliance with Project Specifications
Submittal Title: Rev. No. Facility Code:
Sub-Contractor: Area of Application:
Project Specifications Material SpecificationsCompliance
RemarksSpecifications
SpecificationsStandard
ReferenceSpecifications
Standard
ReferenceNo. Clause Supplier Contractor
7/26/2019 Long Lead ItemS List
http://slidepdf.com/reader/full/long-lead-items-list 13/20
The Construction Manager: King Abdulaziz
International Airport
Development Project
(Phase I) Jeddah, KSA
The Contractor:
421-DCS-SPC-32002-R0
EFPS-AMAN/DMAN System Long Lead Item List 13/20
6. MATERIAL LISTNOT APPLICABLE FOR THIS DOCUMENT
7/26/2019 Long Lead ItemS List
http://slidepdf.com/reader/full/long-lead-items-list 14/20
The Construction Manager: King Abdulaziz
International Airport
Development Project
(Phase I) Jeddah, KSA
The Contractor:
421-DCS-SPC-32002-R0
EFPS-AMAN/DMAN System Long Lead Item List 14/20
Sr.# Product Number Product Description
Sub-Header
Sub-Header
7/26/2019 Long Lead ItemS List
http://slidepdf.com/reader/full/long-lead-items-list 15/20
The Construction Manager: King Abdulaziz
International Airport
Development Project
(Phase I) Jeddah, KSA
The Contractor:
421-DCS-SPC-32002-R0
EFPS-AMAN/DMAN System Long Lead Item List 15/20
7. DATA SHEETSNOT APPLICABLE FOR THIS DOCUMENT
7/26/2019 Long Lead ItemS List
http://slidepdf.com/reader/full/long-lead-items-list 16/20
The Construction Manager: King Abdulaziz
International Airport
Development Project
(Phase I) Jeddah, KSA
The Contractor:
421-DCS-SPC-32002-R0
EFPS-AMAN/DMAN System Long Lead Item List 16/20
8. TEST CERTIFICATESNOT APPLICABLE FOR THIS DOCUMENT
7/26/2019 Long Lead ItemS List
http://slidepdf.com/reader/full/long-lead-items-list 17/20
The Construction Manager: King Abdulaziz
International Airport
Development Project
(Phase I) Jeddah, KSA
The Contractor:
421-DCS-SPC-32002-R0
EFPS-AMAN/DMAN System Long Lead Item List 17/20
9. SPARE PARTSNOT APPLICABLE FOR THIS DOCUMENT
7/26/2019 Long Lead ItemS List
http://slidepdf.com/reader/full/long-lead-items-list 18/20
The Construction Manager: King Abdulaziz
International Airport
Development Project
(Phase I) Jeddah, KSA
The Contractor:
421-DCS-SPC-32002-R0
EFPS-AMAN/DMAN System Long Lead Item List 18/20
Sr.# Product Number Product Description Qty
Sub-Header
Sub-Header
7/26/2019 Long Lead ItemS List
http://slidepdf.com/reader/full/long-lead-items-list 19/20
421-DCS-SPC-32002-R0
EFPS-AMAN/DMAN System Long Lead Item List 19/20
10. APPENDIX A: ACRONYMS
Acronym Description
A
AMAN Arrival Manager
ATCT Air Traffic Control Tower
ATM Air Traffic Management
C
CDRL Contract Deliverables Requirements List
D
DAR Dar Al Handasah
DIFLIS Departure Information Flight List System
DMAN Departure Manager
I
ICAD Innovative Contractors for Advanced Dimensions
K
KAIA King Abdul Aziz International Airport
KSA Kingdom of Saudi Arabia
L
LLIL Long Lead Item List
T
TBP To Be Provided
W
7/26/2019 Long Lead ItemS List
http://slidepdf.com/reader/full/long-lead-items-list 20/20
DOCUMENT FINAL PAGE