long baseline workshop, june ‘06 - laughton the deep underground science and engineering...
TRANSCRIPT
Long Baseline Workshop, June ‘06 - Laughton
The Deep Underground Science and Engineering Laboratory (DUSEL)
-------------Challenges and Opportunities
for the Rock Engineering Community
Chris LaughtonFermi National Accelerator Laboratory
Universities Research AssociationUnited States Department of Energy
Long Baseline Workshop, June ‘06 - Laughton
Large-Deep ExcavationsA Research Proposal
• Large-Deep Permanent Cavern– 1 km + is deep– 50 m + span is large– ZERO PRECEDENTS
• Not such a trivial engineering exercise.. – Merits the consideration of
an Engineering R&D package – working with H&H engineers
• Deep & High Stress Mining Workshop Abstract...
Large Cavity Construction at the Deep Underground Science and Engineering Laboratory
- Draft for Review - C.Laughtona*, M..Kuchtab, & W. Roggenthenc
a Fermi National Accelerator Laboratory, Batavia, Illinois, USA. bColorado School of Mines, USA. cSouth Dakota School of Mines & Technology, USA.
ABSTRACT
Construction of a Deep Underground Science and Engineering Laboratory (DUSEL) has been proposed under the auspices of the US National Science Foundation. The DUSEL facility will provide a diverse group of scientists and engineers with a dedicated underground facility capable of supporting a broad spectrum of fundamental and applied research at depth in the Earth’s crust.
The main research partners included within the scope of the DUSEL umbrella are physicists, biologists, geoscientists and rock engineers. Rock engineers will not only be responsible for the construction of facilities for the use of others, but will also have the opportunity to develop their own purpose-built experimental areas in the deep subsurface. DUSEL offers mining and civil engineers a rare chance to study key aspects of excavation and support at depth, notably under conditions of high stress, a principal challenge faced by today’s underground community.
DUSEL rock engineers will both extend the capabilities of the underground science while providing safe and cost-effective construction of the laboratory facilities required by their research partners. The potential range of research is wide, and as plans advance opportunities for crosscutting synergy will be developed between the research partners. DUSEL experimental proposals currently call for the study of large volumes of in-place rock material and the excavation of a network of tunnels and caverns, from 3-4 m span exploratory galleries to 60m span experimental caverns.
The location of the DUSEL site is, as yet, undecided. NSF has selected two sites for conceptual study. The two sites are the Henderson Mine in Colorado and the Homestake Mine in South Dakota. Both sites take advantage of existing mine facilities to provide access and infrastructure support to the DUSEL facilities.
This paper will introduce the project to the deep mining community and discuss some key aspects of a proposed engineering research program associated with the excavation and support of large permanent caverns at depth. These excavations will be designed for a new generation of large physics detectors aimed at supporting basic research into the fundamental properties of matter. The paper will outline an integrated design-research program to improve the design and construction process for DUSEL excavations. The program will focus on identifying some potential areas where research could help advance the state-of-the-art in underground construction in general, and increase the viability of a proposed Large-Deep cavern, in particular. The paper will also underline the importance of the early site investigation, design and construction work. This work will ensure that the rock mass characteristic conditions and behaviours are well defined before the design of the later, more challenging larger and deeper excavations begins in earnest.
Corresponding Author E-mail address: [email protected]
Long Baseline Workshop, June ‘06 - Laughton
DUSEL - A Basic Research Facility• Multidisciplinary Program..
– “Pure” Research - no specific end-use targets (e.g. military, nuclear waste..) that could limit research scope
– Wide-ranging expertise and cross-cutting ideas for the “next” generation” of underground experiments
– Many research proposals already submitted….
• Large, Diverse Research Platform..• Multi-level Campuses
– Laboratory Clusters – Self-Contained (Workshops, Offices..)
• Isolated Research Stations– Alcoves for Geo-Bio Drilling/Probing – Engineering Research Sites, etc…– Small to Large Scale studies all possible
• Methods, Machines, Materials Proving Ground
– Keystone Research Program - partnering makes it work• Expensive - partners share the costs = economy of scale• Shared ideas too.. synergy is already taking place..
• DUSEL Research >> Sum of its parts..– Exciting “Frontier Research”– Good “Research Value”
Physics
Engineering
DUSEL GeologyBiology
“Four-in-One”
Long Baseline Workshop, June ‘06 - Laughton
Not Just Sciences, Engineering too..• DUSEL offers opportunities to
advance the state-of-the-art in underground engineering;
• Not only to meet science needs...– Excavations
• spans up to 60 m• under high stresses (2km + deep)
– Liquid Argon containment in a “warm rock” environment
– Accelerator stability requirements– Clean-Dry environments– Etc..
• But also for engineering research..– Fundamental Studies in
• Rock Mass under Stress (Pre-Failure & Post-Failure…)
• Water in Fractured Rock (Flow, Pressure etc..)
– Technical Innovation..– Education and Training – Etc..
TBM~4mØ Drill/Blast~3m HS
DUSEL - Mined Cross-Sections for Hard Rock Tunnels (Cookie Cutter Design Approach)
Potential Excavation Functions
Likely Categories Representative Sizing
Representative Cross-Sectional Envelopes Methods & Means -~ Approximate Dimensions
Galleries 3 - 4 m Ø
• Exploration • Experiments (RM/Hydro/Geo) • Construction Access • Utilities (ducts/cables/pipes..) • Light Vehicle/Personnel Access/Egress
Main Tunnels 6-8 m Ø
Experimental Caverns • Single Purpose • Multi-use Modules
Mega-Detector Cavern • "Swimming Pool" • Drained Rock Mass • Watertight Lining or • Liquid Argon • Cryogenic Storage
• Drill Rig Sites • Clean Rooms • Stability & Dryness Criteria
• Experiment/Module Access • Construction/Operation • Equipment • Materials Utilties (ducts/cables/pipes.. TBM~8mØ Drill/Blast~6m HS
Drill/Blast ~15x19m
Drill/Blast ~ 60x64m
• Special space provisions - O/H Crane headroom - Drill-rig headroom - clean room - stability (accelerators)
0 20m
Drill/Blast~30x34m
• Special enviro provisions - Temperature & RH ranges - dryness (dripping-watertight)
"Swimming Pool Concept" • Drained Rock Mass • Watertight Lining (analogous to watertight membranes only pure water to be kept in!) or "Cryogenic Concept" • Liquid Argon • Cryogenic Temperatures (analogous to LNG storage but at an even lower temperature!) or TBD..
Long Baseline Workshop, June ‘06 - Laughton
Proposed Sites - Hard-Blocky Rocks
• Located in the Black Hills ~ 60km N-W of Rapid City, SD.
• Housed in footprint of recently closed Homestake Mine.
• In meta-sedimentary and meta-volcanic rock mass.
• Located in front range of the Rocky Mountains, ~ 80 km W of Denver, CO.
• Adjacent to and accessed from the operating Henderson mine.
• In a granitic rock mass.
Homestake Mine
Henderson Mine
Homestake Mine Henderson Mine
Long Baseline Workshop, June ‘06 - Laughton
Large-Deep Cavern Challenging Design Criteria..
• State-of-the-industry design-construction format adequate for most early design/construction work (~small, ~shallow excavations adjacent to/within previously mined volumes), but…
• Later excavation may “push the envelope” notably for permanent Large-Deep cavern construction. Research may be of value*.. – Consider research – potential value to the project
– Incorporate and perform research tasking as part of the overall program – > ensure shared research ownership by academia and industry
– Ideally maximize excavation research performed during the earliest phases of construction so that recommendations can be incorporated in to subsequent design work
~1.2 to 1.5 km
60 m
180 m
Physics Detector NeedsProton Decay - UNO)
60 m
Long Baseline Workshop, June ‘06 - Laughton
Larger Physics Caverns• Physics Laboratories
– Accelerator Detectors ~ 0.1 to 0.2 km• Large Electron Positron • Large Hadron Collider
– Shielded Detector ~ 0.5 to 2 km• Kamioka, Japan• Gran Sasso, Italy• Korean Invisible Mass Search• Sudbury, Canada
• Civil-Mining “Limits” for Large Permanent Excavations (>15m span)– Span Limit ~ Gjovik– Depth Limit ~ Western Deep Mine
• Larger, “Self-Supported” Cavities...– Standing Stopes - 50 m+ span– Natural Caverns - 200 m+ span
No intrinsic reason why the Large-Deep Cavern requirements cannot be met at site
20 40 60
Korea Invisible Mass Search (Yang Yang HEPPS)
LHC (CERN)
LEP (CERN)
Super Kamikande (Kamioka Mine)
SNOLab (Creighton Mine)
Approximate Cavern Span, m
Approximate Depth, km
Gjovik (Ice Rink)
Western Deep (Crusher Room)
1
2
3
Gran Sasso (Road Tunnel)
Domed CavernPrismatic Cavern
0
Long Baseline Workshop, June ‘06 - Laughton
Cavern Spans in Industry
40
80
120
160
15 20 25 30 35 40 45 50 55 60 65 70 75 80
Number of Case Histories
Gjovik Ice Arena
CERN - LHC
CERN - LEP Gran Sasso SNO
Kamioka
Mine Stopes
Man-Made Solution-Mined Cavities
Natural Caverns
100 m +
400 m +
75 m +
(e.g. Joma Cu Mine, ref. Lachel)
(e.g. Hauterives Rock Salt, ref. Lachel)
(e.g. Sarawak, ref. Fairhurst)
Span, m
Cavern Span Histogram (>15m) – ’05 literature review of existing data bases
Engineering R&D
Long Baseline Workshop, June ‘06 - Laughton
Cavern Depths in Industry• Most industrial caverns have drive-in
access• Adequate design cover at depths <0.5km
– Fresh (~unweathered) host rock mass– Below water table (hydro + oil/gas storage..)– Within a “Preferred Range” of In Situ Stresses
• High enough to mobilize shear strength, but• Low enough not to induce zones of overstress• Horseshoe Cross-section
• Large-Deep Caverns…– Fracture + Stress Regime…cost/risk drivers – Engineering Feasibility vs. Economic
Viability• Any engineering feasibility study will not find
that the cavern can’t be built! (CL opinion!)• Ultimately - viability of Large-Deep
experiments may be limited by cost/risk - down-size early to avoid spending design $ on unaffordable options..
– “Strategic Research” to reduce costs/risk…maybe good value...
100
200
300
400
500
600
1000
2000
Salt Cavities
Detector Laboratories
3000
Mine Housings
0 10 20 30 40
Number of Case Histories
Depth, m
Accelerator Detector
Laboratories
Cavern Depths Bar Plot
Long Baseline Workshop, June ‘06 - Laughton
Large-Deep Physics Caverns in Japan
• At the Kamioka Mine two domed caverns:– Kamiokande ~ 20m dome
– Super-K ~ 40 m dome
• Twin horseshoe caverns are planned:– Hyper-K ~ 50m span
Long Baseline Workshop, June ‘06 - Laughton
Large-Deep Physics Caverns in Europe
• At Frejus, Franco-Italian Border, 3 Domed Caverns are planned ~ 50m span adjacent to an alpine road tunnel….an early concept
• At Gran Sasso, Italy 3 Horseshoe-Section Caverns ~ 20m span have been constructed adjacent to an Apennines road tunnel. Gran Sasso
Fréjus
Long Baseline Workshop, June ‘06 - Laughton
Large-Deep Physics Caverns in North American
• In the United States, various detector options are under consideration, larger ones include:
– MPD ~ 50 m domed cavern
– UNO ~ 60 m horseshoe cavern
– LAr - 70m domed cavern
• In Canada, a ~20 domed cavern was Constructed with the boundaries of the Creighton Mine, adjacent to a deep shaft within the country rock.
Highwaytunnel
Detector
Perliteinsulation
h =20 m
70 m
Electronic crates
A. Rubbia
SNO
UNO MPD
LAr
Long Baseline Workshop, June ‘06 - Laughton
A Likely Hard-Blocky Scenario• Assuming that more
marginal conditions (soil-like fracture zones, dikes, heavy water inflows..) can be located by site investigation and avoided. There are still issues…
• Engineering Factors..– Stress– Structure– Water– (Variability)
• Acting Singly or in Combination
Geo-Structure
WaterStress
StructureStress Water
+ +
Both mines have relatively low inflows
Long Baseline Workshop, June ‘06 - Laughton
Rock Structure ~ Scale Dependent• Discontinuity-bound blocks, if unfavorably
oriented -> liable to slide or fall-out under the action of gravity
• Fall-Out Considerations– Impact…Scale-Dependent
• Severity (block size)• Frequency
– Design Mitigation• Requirements
– Size – Orientation– Shape
• Rock Engineering– Shear strength– Normal force– Etc..
Rock Mass Structure on an Absolute Scale
8 meters
Rock Mass Structure on the "Tunnel Scale"
8 meters 4 meters 2 metersBored Diameter
Tunnel Diameter
Fewer Potential Blocks/Wedges
Smaller Span/Diameter
A modicum of fracture can be a good thing -> reduce ability to store large
amount of potential rock burst energy
Long Baseline Workshop, June ‘06 - Laughton
Stress ~ Scale Independent• At Depth In Situ Stress will increase
– Deep campus ~ 2km deep– Overstress encountered at depth at/adjacent
to proposed DUSEL sites and at other Deep Lab sites e.g. Kamioka, SNO, Gran Sasso..at CERN squeezing behavior
– Key engineering research topic at DUSEL too..
• Rock Mass Behavior(s) under stress• Rock Support System(s) performance
• Overstress Considerations..– Impact is Scale Independent
• Problems in smallest tunnel/largest cavern• Mitigation more problematic in large
openings• Rock bursting particularly dangerous..
potential MUST be addressed early– Design Mitigation..
• Requirements – Shape, Orientation ~ ovaloid
» Align major axis to principal stresses
» Proportion axes to principal stresses
• Rock Engineering – Treatments - property modifiers &/or
standardizers» Pre-Condition» De-stress
– Reinforcement» Bolts, “Ribs”, Dowels
– Liners» Swimming Pool, Steel Tanks» Rock-Burst Containment
(shotcrete, mineguard..)
A modicum of stress can be a good thing – normal stress mobilizes shear
force against gravity sliding or fall-out
Long Baseline Workshop, June ‘06 - Laughton
Spatial Variabilitylarger volume - > more variability
• Geo-Variability: a fact of geo-engineering life.. – Classically-trained engineers beware– Rock properties and loading vary spatially more
than is soils..– In a hard rock setting, one can find significant
volumes of..• Fresh intact rock many times stronger than concrete• Residual clay or running sand..
• Change itself is a challenge!– Site condition changes require
methods/means responses?
?
?
?
?
Uniaxial Compressive Strength (UCS), MPa
Block Size Index, Ib, cm
20 40 60 80 100 120 140 160 180
~RQD
100
75
5025 0
1
10
100
200
0
2
20
50
5
Weathered, Altered or Fault Gouge Materials
Box & Whiskers based on site
investigation data
Arrows Indicate lextended range likely to
be found in the field
200
concrete
rock
Long Baseline Workshop, June ‘06 - Laughton
Engineering Factors in Combinations• In addition to stress and fracture..
– Water Pressure and Flow – Long-Term Creep or Deterioration– Etc..
• Site Investigation only gets you so far..• Every site is somewhat unique, but most
issues can be mitigated/managed using established technologies.. the challenge is to predict/identify all the problems (severity, locations and extents) and address them before excavation begins.. – Avoidance…ideal– Mitigation
• through “negotiated” adjustment in end-user requirements
• Use cost-effective engineering technology (mitigate short and long-term problems most cost-effectively)
– Manage!• In all but the most uniform of rock masses
one generally needs to plan to address a variety of problems…
Rock Mass Classification "Ingredients"
Intact Strength
Stress Environment
Discontinuity Alternation Water Conditions
Discontinuity Frequency
Discontinuity Roughtness
End-User Critiera
Cookie Cutter Apporach to Design
Long Baseline Workshop, June ‘06 - Laughton
Large-Deep Research Program• Current Status
– Several concepts and solutions (detectors/sites in combination)– Significant divergence in costs/durations…decision drivers– Minimal discussion of the nature, frequency and size of risks– Need engineering framework to optimize/compare experiments..
• Proposal - to support a Large-Deep Cavern Design– Build “engineering consensus” between the various proposals
(initially generic hard rock setting.. site-specific after down-select)– Develop self-consistent engineering models that provides for a
“first look” at cost, schedule, and risk - experiment viability maybe a direct function of construction cost, schedule and risk
– Identify, detail and schedule-out an engineering research roadmap to support the design and construction of Large-Deep Cavern(s).
– Provide design feedback/interact with to end-user WG
Long Baseline Workshop, June ‘06 - Laughton
Proposed Tasking (a work-in-progress*)..• 1) Identify and Document Core End-User Requirements & Site Constraints
– Requirements - Identify Main Options and Establish Requirement Lists– Best Guess Site Constraints - Host Rock Mass at depth in a Hard-Blocky Rock– Develop a short-list of key early site investigation activities (STRESS & FRACTURE..)
• 2) Develop Excavation and Support Concept(s)– End-user/geo-parameters driving design
• 3) Baseline Schedule and Parametric Cost Model(s)– Parameters driving cost/duration– Bottoms-up approach with simplification for key “what if” parameters ($ & t sensitivity)
• 4) Risk Analyses– Comprehensive Risk Analysis..major multi-year undertaking - credibility on the line!– Highlight dependence on rock mass…
• 5) Research Roadmap ~ “VE-style”– a) Identify and prioritize “worthwhile” research opportunities that could be incorporated
in to the design and construction of DUSEL (faster, cheaper, better, more reliable) with additional emphasis on the value of research to the underground industry-at-large
– b) Integrate research activities in to the Baseline Schedule - if it isn’t planned it will not get done!
– c) Develop a detailed research “roadmap” and scope for more promising ideas* Coordination with Henderson & Homestake
Long Baseline Workshop, June ‘06 - Laughton
Task 1 - Requirements & Constraints• Space - Size, Shape, Orientation, Volume, Connections..• Structures (end-user driven)
– Anchors, partitions, rails, cranes, trays, racks, shields..– Short and long-term movements.. vibrations, de-stress, overstress,
swell..• Services (ideally some reuse of construction utilities)
– HVAC, Water, Power, Communication, Data Acquisition..• ES&H (on-site and off-site)
– Egress, access, air quality, noise, groundwater, lighting etc..• Optimize engineering aspects of design
– enhance self-supporting ability of rock and– improve practicality and – safety of construction – while respecting core functions
Long Baseline Workshop, June ‘06 - Laughton
Task 2 - Excavation & Support Concepts• Likely Adverse Behaviors..
– Fall-Out under Gravity– Burst &/or Squeeze under Stress– Just add water……?– Extents and severities?
• Ground Treatment– Pre- and Post-systems to alter strength, permeability..
• Excavation Sizing/Phasing– Blasting techniques..cautious? Pre-, post split etc..– Avoid overstressing etc..
• Reinforcement Systems – Pre- and post-systems –active/passive (Cables, bolts
dowels, ribs, etc..)• Liner Systems
– Pop Rock Containment – shotcrete, mineguard..– Watertight “overlap, wallpaper-lining swimming pool
Pre-Support Concepts
Long Baseline Workshop, June ‘06 - Laughton
Task 3 – Schedule & Cost Models
Excavation & Reinforcement Costs Nk/m3
15 20 25
80
60
40
20
“Bad Rock”
“Good Rock”
0
Excavation
Span, m (Top Heading & 3 Benches - see model configuration)
Top Headings
Bench 1
Bench 2
Bench 3
Access Tunnel
• Even if it is technically-viable can we afford it?– Large Span requirement may be a
major cost/risk driver..– Understand cost drivers and their
influence on costs– Technical trade-offs first– Involve an experienced cost
estimator - viability probably more likely to be deciding factor than feasibility - feasibility study = self-fulfilling prophesy (avoid engineers’ “can-do” response! – get a hard dollar estimators perspective)
– Address these hard questions first.. research needs &/or scope reduction?
Cost-Effective Layout -> for Volume
Long-Section Cross-Section
StabilityCosts
Long Baseline Workshop, June ‘06 - Laughton
Theta 13 Scope Underground Construction(Cal Poly Workshop March 2004)
– Braidwood• 2 Vertical Shafts - 10m Ø & 120m deep• 1 Tunnel - 300m long 8m span
horseshoe tunnel. Uniform 1% tunnel gradient to shaft.
• Firewall-Isolated Excavations accessed from the Running Tunnel/Shafts
– 3 Detector Rooms » 1 x Near Detector Room - 32 m
long 12 m span» 2 x Far Detector Rooms with 8 m
span access tunnels - 16 m long x 12 m span
– 1 Underground Emergency Refuge (at end of tunnel)
» 6 m long 4m span» separately ventilation 2-hour fire
rated wall– Utility/Sump Room 4 m horseshoe
» nominal 8m length
– Diablo Canyon• 1 Portal Entrance -10 m long• 1 Tunnel - 850m long 6m span
horseshoe tunnel. Uniform 1% tunnel gradient to portal.
• Firewall-Isolated Excavations accessed from the Running Tunnel
– 2 Detector Rooms » 2 x 40m long 10m span
chambers– 1 Underground Emergency Refuge
» Nominal 6 m long 4m span» Equipped with 2-hour fire
rated wall and self-rescuers
http://theta13.lbl.gov/calpoly04/talks/Laughton
Long Baseline Workshop, June ‘06 - Laughton
Cost & Schedule - The Estimating Process (Cal-Poly Workshop March 2004)
– Proposal should be based on a reliable cost estimate. – “The only kind of estimate that is worth anything is the one that is clearly defined
on paper and bears the signature of the author.” J.S.Redpath, (1980). Theta 13 has underground estimates that are:
• Well-documented and site-specific - developed “from the bottom up”• Estimated independently by an experienced, tunneling professional.• Reviewed independently by experienced, tunneling professionals.
– Underground estimate scopes include:• Underground Structural Shell and Utilities• Utilities left in place (power, ventilation, water, air lines, communication..). • Permanent facilities installed (groundwater pumps, elevators and refuge firewall, surface water
treatment facilities).
– Estimates exclude:• Engineering, Design, Inspection and Administration (EDIA), Surface Buildings, Technical
Installations, Life Cycle Costs
Long Baseline Workshop, June ‘06 - Laughton
Cost & ScheduleBottoms-up Estimates’ Bottom-lines
• Braidwood– Duration 39 months
• “First” detector site delivered in17 or 20 months (far or near)
– Cost $34.6M• General Mobilization ~3.3M• Shafts ~ 15.9M• Tunnel ~ $9.1M• Detector Rooms ~ $6.0M• Refuge ~$0.3M• 40% contingency.• Initial comments: equipment
selection, crew sizing and productivity OK. Shorter shafts could use cranes.
• Diablo Canyon– Duration 24 months– Cost $23 M
• General Mobilization ~$2.9M• Portal Cost ~$0.3M• Tunnel ~ 16.5M• Detector Rooms ~$3.2M• Refuge ~$0.1M• 30% contingency.• Initial comments: equipment
selection, crew sizing and productivity OK. Some relatively conservative production factors - mucking might be done more quickly.
Long Baseline Workshop, June ‘06 - Laughton
Task 4: Risks - Threats & Opportunities• For such an unprecedented combination of depth and span,
it will be critical to establish a disciplined approach to risk identification, mitigation and management form the start:– Complement design team expertise – look for broadest technical-
geotechnical perspective. Underground there is a room for differences in opinion.. (like a horse race…so many expert…so little consensus)
– Select those who have been responsible for similar work– Nothing wrong with optimism but, the more realistic the
Baseline….the lower the contingency…• Cost + Contingency may be prohibitive…Some research
seed money invested early-on as part of the design effort may help address issues of cost and/or risk:– Site investigation and characterization– Design and construction
Long Baseline Workshop, June ‘06 - Laughton
Task 5 - Research “Metro” Map• Be selective..not all engineering
research appropriate for DUSEL..– Resources are limited– Best performed elsewhere by others– Generally, not enough reward..too risky,
too long, too costly..
• DUSEL Research Shortlist– Hand-picked review team
• Expertise + “opinion-diversity”
– Brainstorm ideas first• More than one route..
– Consider relative merits..• all ideas worthy - not an academic
exercise or productivity issue • Risk versus reward…• Intrinsic value to Industry too• Achieve strong shortlist consensus
– Integrate in to the Plan..
ExploratoryWorks
Rock Mass Instrumentation
EngineeringModels
Geo-InterpretiveModels
TreatmentSystems
Rock Under Stress
Fractured Rock Aquifer Engineering
Geophysics BoreholeInvestigation
Geo-VariationModels
Design-as-you-Go
Cavern Concepts
Real-Time Data Collection
SupportSystems
ExcavationSystems
Cost/Time BallparkRisk Analyses
CavernRequirements
Engineeringfor Safety
DiscontinuaDesign
In Situ StressMeasurement
DeskStudies
Integration
Potential Engineering Research Areas
Long Baseline Workshop, June ‘06 - Laughton
Cavern Research in Design e.g. Exploration
• Designers need better data in order to produce better designs and contracts..
• Key Questions..partially answered– Rock Structure– Stress Regime
Soft Ground Not Easy Ground
Excavator Rescues TBM Job
...Tunnel Slips Behind
Collapse Halts...Metro Tunnelling Again
The...Tunnel Financial Black Hole
Arbitration Looms Over...Dispute
The Subway to Nowhere, No Time Soon
Subway Tunnel Halted
Twice This Month
Claims Row Halts...Tunnel
Difficult Ground Halts TBM
Bad Rock Stalls TBM
Too many surprises…
Cross-Hole TomographyEngineering Press - Headlines
Long Baseline Workshop, June ‘06 - Laughton
Cavern Research in Construction e.g. Design as you Go
• Office designs ~ at best, only as “good” as ground predictions are accurate... • Discrepancies between the “as-predicted” and “as-found” are commonplace...• There is a need to adjust methods/means to as-found conditions in Real-Time...
– Real-Time design feedback at the heading• Map/Photogrammetry/models/images…geologic/technical conditions at the heading• What lies beyond the rock walls and heading?....Monitor rock drills, geophysics etc..• Monitor Deformation and Stress.. (before, during after…long-term creep too)• Adjust rock treatment, excavation, reinforcement and lining system(s)• Update predictions of “what’s ahead”..probing, geophysics, monitoring of the drill rig etc..• Model versus Reality “Instant Interface”.. ”Design-as-you-go”..
Evaluate Rock Mass at Heading & Update Drill &
Blast Plan and Support Design
Drill
Charge
Blast
Vent
Muck
Support
Design as you Go
What miners do at the heading - absent
designer feedback!
Long Baseline Workshop, June ‘06 - Laughton
Cavern Research During Early Operatione.g. Rock Mass under Stress
• Rock blocks dedicated to rock engineering research...– Site Preparation
• Site Investigation..boreholes, geophysics• Pre-Instrumentation • Stress Measurements
– Main Variables• Multi-Pass Reaming Processes• Stresses - pillar thickness• Pre-Treatments (conditioning..)• Support Systems - types and timing
– Potential measures/observations• “Ground Truthing” (“mine-backs”)• Pre-’ & Post-Failure Phenomena• Load Transfer rock->supports• Hard Rock Creep
Inclinometer Array
Extensometer Array
Stress Field
+/- HomogeneousRock Mass Block
Borer
Boring Head
Access
Tunnels Instrumentation Cluster Sites
“Organ Pipe”Configuration
Long Baseline Workshop, June ‘06 - Laughton
Technical Innovation During Operation Too..e.g. Mechanized Excavation
TunnelingData Handling
Communication
Information
Manpower Reduction
Remote Control Automation
Equipment Reliaibility
Operations
Maintenance
Unit-Operation Capabilities
Muck Transport
Rock Excavation Rock Mass Support
Rock MassPrediction
…some ideas for rapid tunneling research, Laughton ‘02
• DUSEL offers many techno-opportunities too.. – Instrumentation– Equipment– Materials– Methods– Training– Etc..
Other engineering disciplines too: Safety, Environment, Elec-Mech, Aquifer, Geothermal..
Long Baseline Workshop, June ‘06 - Laughton
Conclusions• In general, DUSEL research can contribute towards a better
understanding of the rock mass as an engineering material and promote innovation underground.
• In particular, research targeted at delivering a safe, cost-effective Large-Deep Cavern facility can contribute significantly to the viability of “frontier physics.”
• Key (Engineering) People - Charles Fairhurst (PI), Mark Kuchta (CSM & Henderson Mine), Bill Roggenthen (SDSMT & Homestake Mine).. all to be involved with the program once the Site CDR’s are delivered to NSF (June 23rd)….
• Key Web Sites (program TBD..proposals welcome..).. – General Site - http://www.dusel.org/– Henderson - http://nngroup.physics.sunysb.edu/husep/– Homestake - http://www.lbl.gov/nsd/homestake/