![Page 1: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/1.jpg)
1
Kopeopeo Canal Remediation ProjectCommunity Liaison Group Meeting
24 April 2018
![Page 2: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/2.jpg)
2
Meeting agenda topics• Welcome & introduction – John Pullar
• Approval of minutes from previous meeting
• Communications update – Abby Tozer
• Project update – Brendon Love/Ken Tarboton
• Independent Monitor – Matt James
• Cultural Monitor – Eula Toko
• Health, Safety and Monitoring – Des McCleary
• Other business
• Light lunch
![Page 3: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/3.jpg)
3
Communications• Website www.boprc.govt.nz/kopeopeo
• Project page updates
• Pedestrian accessway open
• CLG site tour
![Page 4: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/4.jpg)
4
Project page• Register to follow the project
• You’ll get email alerts when updates are published
• You can unfollow at any time
![Page 5: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/5.jpg)
5
Kopeopeo – Orini Public Access Path
![Page 6: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/6.jpg)
6
CLG Site Tour
![Page 7: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/7.jpg)
7
Project updateOverview
• Progress made over previous period
• Dredging (progress, monitoring, validation)
• CS3 Enabling works
• CS3 Works
• Public access
• Activities planned for upcoming period
![Page 8: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/8.jpg)
8
Overview of progress (5 March – 20 April) Main dredging completed to Paroa Road First section complete and validated Second lift over bridge completed CS3 enabling works mostly complete CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to Paroa Road Alternative pedestrian access to Whakatāne river
stopbank constructed
![Page 9: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/9.jpg)
9
Dredging progress
270m
660mS1. 270m
S2. 390m
1180m
S3. 520m
1850m
S4. 670m
Containment Site 1CS1
FCS West
Dredged to date 20-04-2018
Validated to date 20-04-2018
Lift over bridge 1Lift over bridge 2
Lift over Paroa RdBridge 3
Lift over SH30Bridge 4
![Page 10: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/10.jpg)
10
Geobags filled
Bags 2-7
full & closed
Bags 9-10actively being filled
Bag 8Unrolled ready to
fill Bag 1 initial bag partially
full
![Page 11: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/11.jpg)
11
Barge lift over second bridge
![Page 12: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/12.jpg)
12
Sand bug operations
![Page 13: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/13.jpg)
13
Weed removal
![Page 14: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/14.jpg)
14
Wood pellet processing
![Page 15: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/15.jpg)
15
CS3 preliminary works
![Page 16: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/16.jpg)
16
CS3 works
![Page 17: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/17.jpg)
17
Activities planned for upcoming period
• Progress dredging in Section 4
• CS3 construction based on final design
• Processing of eels
• Ongoing weed removal ahead of large objects
• Sand-bug dredging under bridges and Kope/Orini pump intake channel
![Page 18: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/18.jpg)
18
Independent Monitor monthly report available on website
See the Reports and Key documents page
![Page 19: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/19.jpg)
19
Independent Monitor update• Powerpole incident investigation ongoing
• CLG site visit
• Excavator removing weed ahead of dredging
• Complaints received – Dredging and dust
• Eel removal report reviewed
• MP8 turbidity monitor installed
• Bone finds at CS3
• FCS-East fixed
• Sand bug dredging
![Page 20: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/20.jpg)
20
ACM & Wood Waste at CS3
![Page 21: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/21.jpg)
21
Canal Sediment Validation
The canal sediment Total PCDD/F WHO-TEQUpperbound results ranged between 23 and 45 pg/g, which is below the remedial target of 60 pg/g.
![Page 22: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/22.jpg)
22
Dioxin Air & Groundwater Monitoring
– Tested – Awaiting results for review
Air Tested – Awaiting results for review
Groundwater Six groundwater samples (including two duplicates ) were collected from the four monitoring wells located at CS1. Total PCDD/F I-TEQ Upperbound results of between 6.67 and 9.53 pg/L were recorded in the water samples. All were below the adopted Tier 1 trigger level criteria outlined in the Environmental Monitoring and Validation Plan (EMVP) of 13.5 pg/L and the consented limit of 30 pg/g.
Geobags Tested – Awaiting results for review
Over-sized bulk bags
Tested – Awaiting results for review
![Page 23: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/23.jpg)
23
Cultural Monitor update
• Recent finds –determined by Archaeologist to be modern, not archaeological artefacts
• Modified protocol
![Page 24: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/24.jpg)
24
Health, Safety & Environment
• Safety incident regarding overhead powerlines investigated
• CS3 Site closed to public
• Asbestos find at CS3 and sampling
• Disposal of material from trial site
![Page 25: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/25.jpg)
25
Dust Monitoring – CS3
At Kope/Orini Pump station Mobile dust monitor at CS3
Example false alarm3:47am 27 March
No dust exceedances in period
![Page 26: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/26.jpg)
26
Traffic Management
• CS3 traffic management
• Road closures associated with each crane lift
![Page 27: Kopeopeo Canal Remediation Project...2018/04/24 · CS3 final design approved by Consent Authority Pump station canal dredging started Weed removal carried out to ParoaRoad Alternative](https://reader036.vdocuments.us/reader036/viewer/2022081620/6104c0dc9fe59d61e611629e/html5/thumbnails/27.jpg)
27
Other Business
• Next meeting: Tuesday 29th May 2018
• Tech Talk at next meeting – Monitoring system by Karam de Lacey of Control Tech