king’s lynn b power station connection project... · to connect king’s lynn b to our system...

27
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. King’s Lynn B Power Station Connection Project Andrew Connolly – Project Manager

Upload: others

Post on 05-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.

King’s Lynn B Power Station Connection Project

Andrew Connolly – Project Manager

Page 2: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

2

The Transmission system provides the backbone of GB electricity supply reliability

Page 3: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

3

UK energy challenge

Gas from UK sources

~25%of total supplies by 2020

Sustainability

Affordability

Security of supply

Existing power station closures

~25%of total capacity by 2020

Page 4: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

4

Our Role

To keep the power flowing and the lights on

To connect King’s Lynn B to our system

Three times more power than KLA

To be economic and efficient with regard to others

Page 5: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

Programme Stages

DCO submission: Summer 12

Page 6: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

Route corridor options: 2.5 – 5 km PRC – East announced March 2011

Page 7: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

Consultation – Stage One

IPC notified Feb 2010

2 meetings with IPC

1.5km zone established, 2500 letters to residents

3 Parish, 1 Council & 1 MP briefing during Stage 1

3 public events March – April 2010

81 attendees, 53 responses

Statutory & non statutory consultees notified

Various levels of response

Press release in local papers, parish halls

Re-advertised May 2010

Commenced EIA walkover August 2010

Page 8: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

Conclusions – Stage 1

East Corridor is preferred route corridor

Statutory consultees preference is the East Corridor

Little material difference between corridors

Greatest opportunity for locating towers away from properties

Not the shortest route (Central)

Offers limited screening

SSSI in East noted, minor short term impact

RCA 16th March 2011

Page 9: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

Consultation – Stage Two

Stage Two – Example and interim alignment inc. siting with PRC:

SoCC

PIL events

Land access

Surveys

Example alignments

Consultation Events

Community Forums

NG LRS

Interim alignment

Draft DCO & EIA

Page 10: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

10

Why we chose the East Corridor

Addressed issues raised during consultation

Greatest opportunity to site line from individual dwellings

Lowest potential risk to migrating birds

Limited natural screening

Page 11: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

Stage Two Example Alignment One

Page 12: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

Stage Two Example Alignment Two

Page 13: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

Stage Two Interim Alignment

Page 14: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

King’s Lynn ConsultationStage Two, (March 11 to March 12)

IPC notified of RCA March 2011

1.5km zone established, 2500 letters to residents

SOCC re-issued including Stage Three

Consultation events:

2 Parish Council, 2 public - March 2011, + other 1-2-1’s

1 PIL – Lands Right Strategy, 2 community workshops & on site PIL discussions continue to date

66 attendees, 95 responses to the above

Statutory & non statutory consultees notified

Five press releases in local papers

Three radio interviews conducted

Page 15: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

Conclusions from Stage Two (to date)

Little uptake following RCA, prompting further comms

3D model very beneficial during workshops, good feedback

Example alignments at workshops well receivedDerived from known constraints in East Corridor & surveys

Example interim alignment reviewed by most affected and PILs

Developed via feedback from workshop 1 & constraints

Back checking confirmed SOR & RCA remain valid

Page 16: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

Conclusions from Stage Two

100% PILs signed access rights for survey works

Awaited harvest for survey access

Archaeology survey results – final intrusive works

Associated development defined

LOD’s agreed

Page 17: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

17

Proposed Route

Eight new towers, 2.85km one tower change on 4VV route

3D software available, fly, drive, walk etc.

Towers design as present – pgm too short for others & not in keeping with others due to distance

On going negotiations with land owners

Local residents issue with Construction traffic via Watlingtonvillage route

Advised and approved NCC HA route

Page 18: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

18

How we chose the route

Consultation and land owner discussions

Technical & environmental surveys

Minimise visual impact, least pylons

Does not oversail individual dwellings

Greatest opp. for distance from individaul dwellings

Most suitable construction route

Maximises use of limited screening

Minimises wirescape & environmental impact

Page 19: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

19

Proposed Route

Page 20: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

20

Stage Three consultation

Commenced 28 March, 2012 (IPC notified 12 March)

Consulted KL&WNBC and NCC on updated SoCC

Watlington village included

Closing date for consultation 11th May 2012; extension for WatlingtonParish Council to 25th May

Feedback sought from prescribed and non-prescribed consultees, PILs, local organisations, hard to reach groups, members of the community and other interested parties in vicinity – responses from 63 stakeholders to date

Letters of invitation with leaflets, advertisements, media publicity; plus website, freephone, inspection copies, mobile libraries, project email address, posters

Page 21: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

21

Stage Three consultation

Consultation events: 19 April (PILs: 4 attendees), 20 (8attendees), 21 April (9 attendees)

Exhibition boards, full project team, props, Stage 1 and 2 documentation, information DVDs, 3D interactive software

Visit to Saddlebow Caravan Park on 20 April

Advertisements: 40 project related advertisements 10 February to 18 April including: end of Stage Two, Legal Notices, SoCC, Application Notice, consultation events

Stage One consultation: 81 attendees; 53 responses

Stage Two consultation: 66 attendees; 95 responses

Stage Three consultation: 21 attendees; 130 responses

Page 22: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

22

Page 23: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

Example Access Plan for submission

Page 24: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

Example Land Plan for submission

Page 25: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

Example Works Plan for submission

Page 26: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

Milestones

20th March, Stage Two concludes

28th March, commenced Stage Three consultation

19th 20th & 21st April, public consultation events

11th May Stage Three concludes – 25th May Watlington

22nd June, LRS incentive period complete

DCO submission Summer 12

Page 27: King’s Lynn B Power Station Connection Project... · To connect King’s Lynn B to our system Three times more power than KLA ... Three radio interviews conducted. Conclusions from

27

Questions?