july 13, 2010
DESCRIPTION
Temporary Terminal Presentation. July 13, 2010. Program Status. Finalizing Temporary Terminal construction Striping and traffic changes in progress SFMTA and other operators move to Temporary Terminal on August 7 th Demolition of existing ramps and Terminal begin on August 14 th - PowerPoint PPT PresentationTRANSCRIPT
July 13, 2010
Temporary Terminal Presentation
Program Status
• Finalizing Temporary Terminal construction
• Striping and traffic changes in progress
• SFMTA and other operators move to Temporary Terminal on August 7th
• Demolition of existing ramps and Terminal begin on August 14th
• Seven year schedule for construction of the new Transit Center
Temporary Terminal Access
Temporary Terminal
Phase 1 Temporary Terminal Operation
August to November 2010
10871
71L82X
5
3838L
4138
38L
Temporary Terminal
Phase 2 Temporary Terminal Operation
Key Outreach Dates
• Install banners & re-launch website July 1st
• Handouts available at Terminal July 19th
• Ambassador Training July 19th
• Launch ambassador program July 21th
• Commemoration Event July 30th
• Open House at Temporary Terminal August 3rd
• Begin Operations at Temporary Terminal August 7th
• Transit Center Groundbreaking Event August 11th