july 13, 2010

16
July 13, 2010 Temporary Terminal Presentation

Upload: flavia-dorsey

Post on 02-Jan-2016

32 views

Category:

Documents


1 download

DESCRIPTION

Temporary Terminal Presentation. July 13, 2010. Program Status. Finalizing Temporary Terminal construction Striping and traffic changes in progress SFMTA and other operators move to Temporary Terminal on August 7 th Demolition of existing ramps and Terminal begin on August 14 th - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: July 13, 2010

July 13, 2010

Temporary Terminal Presentation

Page 2: July 13, 2010

Program Status

• Finalizing Temporary Terminal construction

• Striping and traffic changes in progress

• SFMTA and other operators move to Temporary Terminal on August 7th

• Demolition of existing ramps and Terminal begin on August 14th

• Seven year schedule for construction of the new Transit Center

Page 3: July 13, 2010

Temporary Terminal Access

Page 4: July 13, 2010

Temporary Terminal

Page 5: July 13, 2010

Phase 1 Temporary Terminal Operation

August to November 2010

10871

71L82X

5

3838L

4138

38L

Page 6: July 13, 2010

Temporary Terminal

Page 7: July 13, 2010

Phase 2 Temporary Terminal Operation

Page 8: July 13, 2010

Key Outreach Dates

• Install banners & re-launch website July 1st

• Handouts available at Terminal July 19th

• Ambassador Training July 19th

• Launch ambassador program July 21th

• Commemoration Event July 30th

• Open House at Temporary Terminal August 3rd

• Begin Operations at Temporary Terminal August 7th

• Transit Center Groundbreaking Event August 11th

Page 9: July 13, 2010

Outreach Signage

Page 10: July 13, 2010

Signage

Page 11: July 13, 2010

Wayfinding Signage

Page 12: July 13, 2010

Signage

Page 13: July 13, 2010

Outreach Materials

trifold

Page 14: July 13, 2010

Outreach Materials

Fold-out map

Page 15: July 13, 2010

Website

Page 16: July 13, 2010

Questions?