BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District1
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District
PRESENTATION TITLE
BUILDING STRONG® U.S. ARMY CORPS OF ENGINEERS | Jacksonville District
JACKSONVILLE HARBOR PROJECTSDuval County, Florida
Jason Harrah, Project ManagerDecember 9, 2016
BUILDING STRONG® U.S. ARMY CORPS OF ENGINEERS | Jacksonville District
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District2
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District
TOPICS1. MILE POINT
Overview Phase 1 - Schedule Phase 2 – Schedule USCG Coordination Change of Conditions (Pilots)
2. HARBOR DEEPENING Overview Funding Schedule USCG Coordination
3. O&M DREDGING FY16 Awarded Contract FY17 Advertised Contract
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District3
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District
MILE POINT PROJECT PURPOSEEliminate or reduce difficult crosscurrents at the confluence of the IWW and the St. Johns River at ebb tide:
► Concerns about how the crosscurrents impact the Mile Point shoreline
► Navigation Restrictions during the ebb tide on vessels transiting with a draft >33 feet or 34 feet depending upon the vessel type
3BUILDING STRONG®
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District4
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District
MILE POINT: THE BOTTOM LINE
=Navigation Restrictions
Difficult Crosscurrents at Ebb Tide
=Economic Costs
(tidal delays to reach terminals)
Authorization: “…. in the interest of navigation and related purposes, with particular reference to erosion of the Mile Point shoreline.”
4
BLOUNTISLAND
DAMESPOINT
MILEPOINT
NAVAL STATION
MAYPORT
TALLEYRAND TERMINAL
NAVY FUELDEPOT
U.S. MARINECORPS
TERMINAL
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District5
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District
MILE POINT TRAINING WALLRELOCATION/RECONFIGURATION
Training Wall Removal (western ~3110 feet)
Existing Training Wall(~3000 feet)
New Training Wall(western leg ~4250 feet; relocated eastern leg ~2050 feet)
Great Marsh Island Restoration(beneficial use of dredged material)
Flow Improvement Channel(~80 feet wide, ~6 feet deep, ~3623 feet length)
5 BUILDING STRONG®
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District6
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District
PHASE 1 CONTRACT UPDATE
6
Contract Awarded to Manson Construction – 24 April 2015
Contract Completion scheduled for Spring 2017
40,000 tons of stone placed for West Leg Training Wall
615,000 CY dredged from Flow Improvement Channel and other areas
26,000 CY of stone removed from East Leg Training Wall
186 manatee sightings
100 Least Tern Bird Nests
4 Gopher Tortoises
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District7
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District
PHASE 2 CONTRACT
7
Total Cost ~$3.1M
Award Anticipated 2019 (6-12 months completion)
Contract includes Salt Marsh Mitigation, Oyster Bed Mitigation, Biological Surveys, etc.
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District8
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville DistrictBUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District
• Reduce navigation transportation costs to and from Jacksonville Harbor
• Accommodate existing and future vessels• Reduce navigation constraints facing harbor pilots and
their operating practices including limited one-way traffic in certain reaches.
• Develop an alternative that is environmentally acceptable.
47’ DEEPENING
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District9
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District
RECOMMENDED PLAN
MILE 13MILE 13
BRILLSCUTTB
BRILLSCUTTB
BLOUNTISLAND
TB
BLOUNTISLAND
TB
12
DEEPENING:Entrance Channel to ~ River Mile 13 from existing 40-foot depth to 47 feet
WIDENING:Areas 1 and 2: ~ 100 to 300 feet
NEW TURNING BASINS:Blount Island: ~ 2700' long by 1500' wide Basin Brills Cut: ~ 2500' long by 1500' wide
~8 nautical miles
LOCATION OF ODMDS
Not to ScaleNot to Scale4
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District10
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville DistrictBUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District
Deepening Areas: ► Deepen from the Entrance Channel to approximately River Mile 13
from the existing 40-foot depth to 47 feet (LPP), 45 feet (NED) Widening Areas:
► Area 1: Mile Point: increase to the north by 200 feet for Cuts 8, 9, 10, 11, 12, & 13Training Wall Reach: increase to the south 100 feet by Cuts 14/15 & 16 transitioning to 250 feet for Cut 17 and back to 100 feet for Cuts 18 & 19
► Area 2: St. Johns Bluff Reach/White Shells Cut: both sides of the channel by varying amounts of up to 300 feet for Cuts 40 & 41
Turning Basin Areas:► Blount Island: ~ 2700' long by 1500' wide located in Cut 42► Brills Cut: ~2500' long by 1500' wide located in Cut 45
DEEPENING SPECIFICS
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District11
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District
HARBOR DEEPENING CONTRACT BREAKOUTContract A – BaseContract B – Base w/5 OptionsContract C – Base w/5 OptionsContract D – Base w/3 Options
Contract A~$45M
Contract B~$200MContract C
~$250M
Contract D~$130M
Note: All costs shown above are estimates that include district labor, monitoring, etc. These numbers are subject to change in the future!
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District12
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District
Water Quality Monitoring Stations (Northern Study Area)
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District13
BUILDING STRONG® US ARMY CORPS OF ENGINEERS | Jacksonville District
JACKSONVILLE HARBOR O&M
FY16 Contract ► Cut-41 through Cut-55 and Cut-G► Awarded Sep 2016► Disposal @ Bartram Cell A► (Estimated Start mid Jan 2017 - 45 days to complete
FY17 Contract ► Cuts 3-9► Awarded 28 Dec 2016► Disposal @ Buck Cell A► (Estimated Start mid Jan 2017 - 120 days to complete