jacksonville harbor mile point · 2014. 11. 14. · industry day presentation november 13, 2014 ....

40
JACKSONVILLE HARBOR MILE POINT Duval County, Florida Industry Day Presentation November 13, 2014

Upload: others

Post on 30-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

JACKSONVILLE HARBOR MILE POINT Duval County Florida Industry Day Presentation November 13 2014

AGENDA Opening Remarks (1000 ndash 1005)

Technical Presentation (1005 ndash 1035)

Break (1035 ndash 1045)

DiscussionQampA (1045 ndash 1115)

Closing Remarks (1115 ndash 1125)

BUILDING STRONGreg2

TOPICS OF DISCUSSION 1) Project Overview

Jason Harrah Project Manager 2) Engineering Aspects

Steve Conger Lead Engineer West Leg Training Wall

Geo-textile Tubes

Flow Improvement Channel

East Leg Training Wall

Existing Training Wall Demolition

Sequencing of Work (USCG etc)

Height Restrictions (Navy Flight Path)

3) Coast Guard Range Towers Mike Tomasi AtoN Officer USCG

4) Environmental Monitoring Paul Stodola Biologist Mike Hollingsworth Biologist

5) Procurement Strategy Tedra Thompson Contract Specialist

6) Schedule (Jason Harrah Project Manager)

7) Small Business Opportunities Beth Myers Small Business Deputy

8) DiscussionQuestions

BUILDING STRONGreg3

JACKSONVILLE HARBOR MILE POINT

JACKSONVILLE HARBOR St Johns River

Atlan

tic Ocean

4 BUILDING STRONGreg

MILE POINT PROJECT PURPOSE Eliminate or reduce difficult crosscurrents at the confluence of the IWW and the St Johns River at ebb tide

Navigation Restrictions during the ebb tide on vessels transiting with a draft gt33 feet or 34 feet depending upon the vessel type

Concerns about how the crosscurrents impact the Mile Point shoreline

BUILDING STRONGreg5

MILE POINT THE BOTTOM LINE

= Navigation Restrictions

Difficult Crosscurrents at Ebb Tide

= Economic Costs

(tidal delays to reach terminals)

Authorization ldquohellip in the interest of navigation and related purposes with particular reference to erosion of the Mile Point shorelinerdquo

6

BLOUNT ISLAND

DAMES POINT

MILE POINT

NAVAL STATION

MAYPORT

TALLEYRAND TERMINAL

NAVY FUEL DEPOT

US MARINE CORPS

TERMINAL

ENGINEERING Steve Conger Lead Engineer

BUILDING STRONGreg7

MILE POINT TRAINING WALL RELOCATIONRECONFIGURATION

Existing Training Wall (~3000 feet)

Training Wall Removal (western ~3110 feet)

New Training Wall (western leg ~4250 feet relocated eastern leg ~2050 feet)

Great Marsh Island Restoration (beneficial use of dredged material)

Flow Improvement Channel (~80 feet wide ~6 feet deep ~3623 feet length)

BUILDING STRONGreg8

PROJECT FEATURES OVERVIEW

1

2

3

4

5

6

1 West Leg Training Wall 4 Existing Training Wall Demolition 2 Material Placement Area 5 Main Dredging Area 3 Flow Improvement Channel 6 East Leg Training Wall

BUILDING STRONGreg9

bull 10

20

_

pound I

10

M~UC Lftl[UIAT10N nML

TYPICAL CROll lliCTION

bull20

bull 10 bull10

10

20

10 _

--

It I

-------t--- --- ----1 _~- I s

-----

-10 10 20 UP I CAL CROSS R CJION

bull20

bull10

10

20

10 70

(1) WEST LEG TRAINING WALL

10

ltI ltI ltI

lti_ bull

D

~ ltI cl f middot~~ J f 4lt J ~

__ ~middot ( ~ i ~ bull bullbullbullbull cl cl cl i r bull 1 bullbull J bullbullbullbull bullbull bull bull bull bull bull ~ bull bull bull bull bull bullbullbull bull bull bull ~ bull ~middot bullbull bullbullbullbull bull

bullbull bull bullbullbull ~middot f bull bull ~ ~middot bull bull ~ ~ bull ~ tl bullbull bull bull cl t1 ~ ~ ( bullbull bullbull t bull yen bullbull cl bull bull bull bull bull bull cl bull tgt ~ (

~ lt ~ bullbull ~ J lt bull ~ bull bull 11 ~ bull tgt bull II I bull bull I tr bull II I II bull I bull tgt bull II ~ bull I I ~ tgt bull I tgt t gt I bull I bull I bull I 1 I tgt bull I tgt ~ middot~middotbull t clcl bull ~middot bull middot ~middot bull ~middot

bullbull bull cl cl cl bullbull bull ~ ~~-~ ~~ bull ~ I ~ I tgt ~ f f1 bull ~ ~ ~ _ bull bull ~middot

~ f bullbullbullbull ~middot

~middot middot ~ bull ~ bull P I ~ + -1 ~ 0 bull bull -gt middot bull

ltI ~ I ltI ltI J 1gt 1gt I ltI ltI I ltI i Jl bull r r lt1 r 01

-~~~-middot ~J)~ IltI JJ

bullbull ~ ~ ~ I

bullbullbullbull bull o) ~ bullbullbullbull ~ ~ bull ltI I ltI ~middot bullbull bullbull bull

J ~ J J J ltI I 1 bull 1 ~ tl gt II ~ ~

t ~ I ltI gt ~ yen I Jl

~lt1lt1bullcl( lbull II ~ I ltI bull - - bull J- _ ) t bull ol

bull ltI _ II R tf bull _ bull bull bullbull bull bull bull bull bull Igt bullbull

~~ ~gt~gt~gtJI~~~tltltl

bull II tl rl gt ~ 1 ltI_ ltI Of II tl

C-32

(2) MATERIAL PLACEMENT AREA

ENVIRONMENTAL PROTECTION AREA

11

MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT

Typical Covered ampPlanted Section Geotube Filling Operation

12 BUILDING STRONGreg

MITIGATION CONTAINMENT ALTERNATIVES

AQUA-DAM WATER CONTAINMENT APPLICATIONS

BUILDING STRONGreg13

(3) FLOW IMPROVEMENT CHANNEL

BUILDING STRONGreg14

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

4

5

15

~ROSS SECTION bull IEXTW ITA 0+50 c-a ~middotJColllrmiddotmiddot

llRTbull ampJUr

(~ ~ROSS SE~TION bull IEXTW ITA 3+00

~middot

C20

CROIIIIiC110N UIW I TA 1 1+00 HOR bull ~f A

llRTmiddot~

CROSS SECTION bull EXTW STA 9+00

-

__ - middot middot middot_ -- --- __ lr_ - --bullbull - middot middotbullmiddotbull middot_middot middot ~------------------middot - -~---- -- ~~~~_ - ~middot- y r

CROSS S ICTION bull DlW S TA Z4bull00

I IC ~

bull

I

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

16

AI~ reg Sic

(6) EAST LEG TRAINING WALL

BUILDING STRONGreg17

HEIGHT RESTRICTIONS DISCUSSION

BUILDING STRONGreg18

COAST GUARD RANGE TOWERS Mike Tomasi AtoN Officer USCG Sector Jacksonville

19

CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT

20

PROPOSED SITE PLAN FOR MILE POINT RANGES

21

PROPOSED RANGE DESIGN

22

ENVIRONMENTAL Paul Stodola

Senior Biologist (NEPA Lead) Mike Hollingsworth

Senior Biologist (Permit Lead)

BUILDING STRONGreg23

ENVIRONEMNTAL COMPLIANCE

EA prepared and coordinated (Includes mitigation plan)

ESA coordination completed

SHPO coordination completed

Coordination on Section 401 WQC completed

BUILDING STRONGreg24

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 2: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

AGENDA Opening Remarks (1000 ndash 1005)

Technical Presentation (1005 ndash 1035)

Break (1035 ndash 1045)

DiscussionQampA (1045 ndash 1115)

Closing Remarks (1115 ndash 1125)

BUILDING STRONGreg2

TOPICS OF DISCUSSION 1) Project Overview

Jason Harrah Project Manager 2) Engineering Aspects

Steve Conger Lead Engineer West Leg Training Wall

Geo-textile Tubes

Flow Improvement Channel

East Leg Training Wall

Existing Training Wall Demolition

Sequencing of Work (USCG etc)

Height Restrictions (Navy Flight Path)

3) Coast Guard Range Towers Mike Tomasi AtoN Officer USCG

4) Environmental Monitoring Paul Stodola Biologist Mike Hollingsworth Biologist

5) Procurement Strategy Tedra Thompson Contract Specialist

6) Schedule (Jason Harrah Project Manager)

7) Small Business Opportunities Beth Myers Small Business Deputy

8) DiscussionQuestions

BUILDING STRONGreg3

JACKSONVILLE HARBOR MILE POINT

JACKSONVILLE HARBOR St Johns River

Atlan

tic Ocean

4 BUILDING STRONGreg

MILE POINT PROJECT PURPOSE Eliminate or reduce difficult crosscurrents at the confluence of the IWW and the St Johns River at ebb tide

Navigation Restrictions during the ebb tide on vessels transiting with a draft gt33 feet or 34 feet depending upon the vessel type

Concerns about how the crosscurrents impact the Mile Point shoreline

BUILDING STRONGreg5

MILE POINT THE BOTTOM LINE

= Navigation Restrictions

Difficult Crosscurrents at Ebb Tide

= Economic Costs

(tidal delays to reach terminals)

Authorization ldquohellip in the interest of navigation and related purposes with particular reference to erosion of the Mile Point shorelinerdquo

6

BLOUNT ISLAND

DAMES POINT

MILE POINT

NAVAL STATION

MAYPORT

TALLEYRAND TERMINAL

NAVY FUEL DEPOT

US MARINE CORPS

TERMINAL

ENGINEERING Steve Conger Lead Engineer

BUILDING STRONGreg7

MILE POINT TRAINING WALL RELOCATIONRECONFIGURATION

Existing Training Wall (~3000 feet)

Training Wall Removal (western ~3110 feet)

New Training Wall (western leg ~4250 feet relocated eastern leg ~2050 feet)

Great Marsh Island Restoration (beneficial use of dredged material)

Flow Improvement Channel (~80 feet wide ~6 feet deep ~3623 feet length)

BUILDING STRONGreg8

PROJECT FEATURES OVERVIEW

1

2

3

4

5

6

1 West Leg Training Wall 4 Existing Training Wall Demolition 2 Material Placement Area 5 Main Dredging Area 3 Flow Improvement Channel 6 East Leg Training Wall

BUILDING STRONGreg9

bull 10

20

_

pound I

10

M~UC Lftl[UIAT10N nML

TYPICAL CROll lliCTION

bull20

bull 10 bull10

10

20

10 _

--

It I

-------t--- --- ----1 _~- I s

-----

-10 10 20 UP I CAL CROSS R CJION

bull20

bull10

10

20

10 70

(1) WEST LEG TRAINING WALL

10

ltI ltI ltI

lti_ bull

D

~ ltI cl f middot~~ J f 4lt J ~

__ ~middot ( ~ i ~ bull bullbullbullbull cl cl cl i r bull 1 bullbull J bullbullbullbull bullbull bull bull bull bull bull ~ bull bull bull bull bull bullbullbull bull bull bull ~ bull ~middot bullbull bullbullbullbull bull

bullbull bull bullbullbull ~middot f bull bull ~ ~middot bull bull ~ ~ bull ~ tl bullbull bull bull cl t1 ~ ~ ( bullbull bullbull t bull yen bullbull cl bull bull bull bull bull bull cl bull tgt ~ (

~ lt ~ bullbull ~ J lt bull ~ bull bull 11 ~ bull tgt bull II I bull bull I tr bull II I II bull I bull tgt bull II ~ bull I I ~ tgt bull I tgt t gt I bull I bull I bull I 1 I tgt bull I tgt ~ middot~middotbull t clcl bull ~middot bull middot ~middot bull ~middot

bullbull bull cl cl cl bullbull bull ~ ~~-~ ~~ bull ~ I ~ I tgt ~ f f1 bull ~ ~ ~ _ bull bull ~middot

~ f bullbullbullbull ~middot

~middot middot ~ bull ~ bull P I ~ + -1 ~ 0 bull bull -gt middot bull

ltI ~ I ltI ltI J 1gt 1gt I ltI ltI I ltI i Jl bull r r lt1 r 01

-~~~-middot ~J)~ IltI JJ

bullbull ~ ~ ~ I

bullbullbullbull bull o) ~ bullbullbullbull ~ ~ bull ltI I ltI ~middot bullbull bullbull bull

J ~ J J J ltI I 1 bull 1 ~ tl gt II ~ ~

t ~ I ltI gt ~ yen I Jl

~lt1lt1bullcl( lbull II ~ I ltI bull - - bull J- _ ) t bull ol

bull ltI _ II R tf bull _ bull bull bullbull bull bull bull bull bull Igt bullbull

~~ ~gt~gt~gtJI~~~tltltl

bull II tl rl gt ~ 1 ltI_ ltI Of II tl

C-32

(2) MATERIAL PLACEMENT AREA

ENVIRONMENTAL PROTECTION AREA

11

MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT

Typical Covered ampPlanted Section Geotube Filling Operation

12 BUILDING STRONGreg

MITIGATION CONTAINMENT ALTERNATIVES

AQUA-DAM WATER CONTAINMENT APPLICATIONS

BUILDING STRONGreg13

(3) FLOW IMPROVEMENT CHANNEL

BUILDING STRONGreg14

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

4

5

15

~ROSS SECTION bull IEXTW ITA 0+50 c-a ~middotJColllrmiddotmiddot

llRTbull ampJUr

(~ ~ROSS SE~TION bull IEXTW ITA 3+00

~middot

C20

CROIIIIiC110N UIW I TA 1 1+00 HOR bull ~f A

llRTmiddot~

CROSS SECTION bull EXTW STA 9+00

-

__ - middot middot middot_ -- --- __ lr_ - --bullbull - middot middotbullmiddotbull middot_middot middot ~------------------middot - -~---- -- ~~~~_ - ~middot- y r

CROSS S ICTION bull DlW S TA Z4bull00

I IC ~

bull

I

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

16

AI~ reg Sic

(6) EAST LEG TRAINING WALL

BUILDING STRONGreg17

HEIGHT RESTRICTIONS DISCUSSION

BUILDING STRONGreg18

COAST GUARD RANGE TOWERS Mike Tomasi AtoN Officer USCG Sector Jacksonville

19

CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT

20

PROPOSED SITE PLAN FOR MILE POINT RANGES

21

PROPOSED RANGE DESIGN

22

ENVIRONMENTAL Paul Stodola

Senior Biologist (NEPA Lead) Mike Hollingsworth

Senior Biologist (Permit Lead)

BUILDING STRONGreg23

ENVIRONEMNTAL COMPLIANCE

EA prepared and coordinated (Includes mitigation plan)

ESA coordination completed

SHPO coordination completed

Coordination on Section 401 WQC completed

BUILDING STRONGreg24

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 3: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

TOPICS OF DISCUSSION 1) Project Overview

Jason Harrah Project Manager 2) Engineering Aspects

Steve Conger Lead Engineer West Leg Training Wall

Geo-textile Tubes

Flow Improvement Channel

East Leg Training Wall

Existing Training Wall Demolition

Sequencing of Work (USCG etc)

Height Restrictions (Navy Flight Path)

3) Coast Guard Range Towers Mike Tomasi AtoN Officer USCG

4) Environmental Monitoring Paul Stodola Biologist Mike Hollingsworth Biologist

5) Procurement Strategy Tedra Thompson Contract Specialist

6) Schedule (Jason Harrah Project Manager)

7) Small Business Opportunities Beth Myers Small Business Deputy

8) DiscussionQuestions

BUILDING STRONGreg3

JACKSONVILLE HARBOR MILE POINT

JACKSONVILLE HARBOR St Johns River

Atlan

tic Ocean

4 BUILDING STRONGreg

MILE POINT PROJECT PURPOSE Eliminate or reduce difficult crosscurrents at the confluence of the IWW and the St Johns River at ebb tide

Navigation Restrictions during the ebb tide on vessels transiting with a draft gt33 feet or 34 feet depending upon the vessel type

Concerns about how the crosscurrents impact the Mile Point shoreline

BUILDING STRONGreg5

MILE POINT THE BOTTOM LINE

= Navigation Restrictions

Difficult Crosscurrents at Ebb Tide

= Economic Costs

(tidal delays to reach terminals)

Authorization ldquohellip in the interest of navigation and related purposes with particular reference to erosion of the Mile Point shorelinerdquo

6

BLOUNT ISLAND

DAMES POINT

MILE POINT

NAVAL STATION

MAYPORT

TALLEYRAND TERMINAL

NAVY FUEL DEPOT

US MARINE CORPS

TERMINAL

ENGINEERING Steve Conger Lead Engineer

BUILDING STRONGreg7

MILE POINT TRAINING WALL RELOCATIONRECONFIGURATION

Existing Training Wall (~3000 feet)

Training Wall Removal (western ~3110 feet)

New Training Wall (western leg ~4250 feet relocated eastern leg ~2050 feet)

Great Marsh Island Restoration (beneficial use of dredged material)

Flow Improvement Channel (~80 feet wide ~6 feet deep ~3623 feet length)

BUILDING STRONGreg8

PROJECT FEATURES OVERVIEW

1

2

3

4

5

6

1 West Leg Training Wall 4 Existing Training Wall Demolition 2 Material Placement Area 5 Main Dredging Area 3 Flow Improvement Channel 6 East Leg Training Wall

BUILDING STRONGreg9

bull 10

20

_

pound I

10

M~UC Lftl[UIAT10N nML

TYPICAL CROll lliCTION

bull20

bull 10 bull10

10

20

10 _

--

It I

-------t--- --- ----1 _~- I s

-----

-10 10 20 UP I CAL CROSS R CJION

bull20

bull10

10

20

10 70

(1) WEST LEG TRAINING WALL

10

ltI ltI ltI

lti_ bull

D

~ ltI cl f middot~~ J f 4lt J ~

__ ~middot ( ~ i ~ bull bullbullbullbull cl cl cl i r bull 1 bullbull J bullbullbullbull bullbull bull bull bull bull bull ~ bull bull bull bull bull bullbullbull bull bull bull ~ bull ~middot bullbull bullbullbullbull bull

bullbull bull bullbullbull ~middot f bull bull ~ ~middot bull bull ~ ~ bull ~ tl bullbull bull bull cl t1 ~ ~ ( bullbull bullbull t bull yen bullbull cl bull bull bull bull bull bull cl bull tgt ~ (

~ lt ~ bullbull ~ J lt bull ~ bull bull 11 ~ bull tgt bull II I bull bull I tr bull II I II bull I bull tgt bull II ~ bull I I ~ tgt bull I tgt t gt I bull I bull I bull I 1 I tgt bull I tgt ~ middot~middotbull t clcl bull ~middot bull middot ~middot bull ~middot

bullbull bull cl cl cl bullbull bull ~ ~~-~ ~~ bull ~ I ~ I tgt ~ f f1 bull ~ ~ ~ _ bull bull ~middot

~ f bullbullbullbull ~middot

~middot middot ~ bull ~ bull P I ~ + -1 ~ 0 bull bull -gt middot bull

ltI ~ I ltI ltI J 1gt 1gt I ltI ltI I ltI i Jl bull r r lt1 r 01

-~~~-middot ~J)~ IltI JJ

bullbull ~ ~ ~ I

bullbullbullbull bull o) ~ bullbullbullbull ~ ~ bull ltI I ltI ~middot bullbull bullbull bull

J ~ J J J ltI I 1 bull 1 ~ tl gt II ~ ~

t ~ I ltI gt ~ yen I Jl

~lt1lt1bullcl( lbull II ~ I ltI bull - - bull J- _ ) t bull ol

bull ltI _ II R tf bull _ bull bull bullbull bull bull bull bull bull Igt bullbull

~~ ~gt~gt~gtJI~~~tltltl

bull II tl rl gt ~ 1 ltI_ ltI Of II tl

C-32

(2) MATERIAL PLACEMENT AREA

ENVIRONMENTAL PROTECTION AREA

11

MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT

Typical Covered ampPlanted Section Geotube Filling Operation

12 BUILDING STRONGreg

MITIGATION CONTAINMENT ALTERNATIVES

AQUA-DAM WATER CONTAINMENT APPLICATIONS

BUILDING STRONGreg13

(3) FLOW IMPROVEMENT CHANNEL

BUILDING STRONGreg14

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

4

5

15

~ROSS SECTION bull IEXTW ITA 0+50 c-a ~middotJColllrmiddotmiddot

llRTbull ampJUr

(~ ~ROSS SE~TION bull IEXTW ITA 3+00

~middot

C20

CROIIIIiC110N UIW I TA 1 1+00 HOR bull ~f A

llRTmiddot~

CROSS SECTION bull EXTW STA 9+00

-

__ - middot middot middot_ -- --- __ lr_ - --bullbull - middot middotbullmiddotbull middot_middot middot ~------------------middot - -~---- -- ~~~~_ - ~middot- y r

CROSS S ICTION bull DlW S TA Z4bull00

I IC ~

bull

I

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

16

AI~ reg Sic

(6) EAST LEG TRAINING WALL

BUILDING STRONGreg17

HEIGHT RESTRICTIONS DISCUSSION

BUILDING STRONGreg18

COAST GUARD RANGE TOWERS Mike Tomasi AtoN Officer USCG Sector Jacksonville

19

CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT

20

PROPOSED SITE PLAN FOR MILE POINT RANGES

21

PROPOSED RANGE DESIGN

22

ENVIRONMENTAL Paul Stodola

Senior Biologist (NEPA Lead) Mike Hollingsworth

Senior Biologist (Permit Lead)

BUILDING STRONGreg23

ENVIRONEMNTAL COMPLIANCE

EA prepared and coordinated (Includes mitigation plan)

ESA coordination completed

SHPO coordination completed

Coordination on Section 401 WQC completed

BUILDING STRONGreg24

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 4: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

JACKSONVILLE HARBOR MILE POINT

JACKSONVILLE HARBOR St Johns River

Atlan

tic Ocean

4 BUILDING STRONGreg

MILE POINT PROJECT PURPOSE Eliminate or reduce difficult crosscurrents at the confluence of the IWW and the St Johns River at ebb tide

Navigation Restrictions during the ebb tide on vessels transiting with a draft gt33 feet or 34 feet depending upon the vessel type

Concerns about how the crosscurrents impact the Mile Point shoreline

BUILDING STRONGreg5

MILE POINT THE BOTTOM LINE

= Navigation Restrictions

Difficult Crosscurrents at Ebb Tide

= Economic Costs

(tidal delays to reach terminals)

Authorization ldquohellip in the interest of navigation and related purposes with particular reference to erosion of the Mile Point shorelinerdquo

6

BLOUNT ISLAND

DAMES POINT

MILE POINT

NAVAL STATION

MAYPORT

TALLEYRAND TERMINAL

NAVY FUEL DEPOT

US MARINE CORPS

TERMINAL

ENGINEERING Steve Conger Lead Engineer

BUILDING STRONGreg7

MILE POINT TRAINING WALL RELOCATIONRECONFIGURATION

Existing Training Wall (~3000 feet)

Training Wall Removal (western ~3110 feet)

New Training Wall (western leg ~4250 feet relocated eastern leg ~2050 feet)

Great Marsh Island Restoration (beneficial use of dredged material)

Flow Improvement Channel (~80 feet wide ~6 feet deep ~3623 feet length)

BUILDING STRONGreg8

PROJECT FEATURES OVERVIEW

1

2

3

4

5

6

1 West Leg Training Wall 4 Existing Training Wall Demolition 2 Material Placement Area 5 Main Dredging Area 3 Flow Improvement Channel 6 East Leg Training Wall

BUILDING STRONGreg9

bull 10

20

_

pound I

10

M~UC Lftl[UIAT10N nML

TYPICAL CROll lliCTION

bull20

bull 10 bull10

10

20

10 _

--

It I

-------t--- --- ----1 _~- I s

-----

-10 10 20 UP I CAL CROSS R CJION

bull20

bull10

10

20

10 70

(1) WEST LEG TRAINING WALL

10

ltI ltI ltI

lti_ bull

D

~ ltI cl f middot~~ J f 4lt J ~

__ ~middot ( ~ i ~ bull bullbullbullbull cl cl cl i r bull 1 bullbull J bullbullbullbull bullbull bull bull bull bull bull ~ bull bull bull bull bull bullbullbull bull bull bull ~ bull ~middot bullbull bullbullbullbull bull

bullbull bull bullbullbull ~middot f bull bull ~ ~middot bull bull ~ ~ bull ~ tl bullbull bull bull cl t1 ~ ~ ( bullbull bullbull t bull yen bullbull cl bull bull bull bull bull bull cl bull tgt ~ (

~ lt ~ bullbull ~ J lt bull ~ bull bull 11 ~ bull tgt bull II I bull bull I tr bull II I II bull I bull tgt bull II ~ bull I I ~ tgt bull I tgt t gt I bull I bull I bull I 1 I tgt bull I tgt ~ middot~middotbull t clcl bull ~middot bull middot ~middot bull ~middot

bullbull bull cl cl cl bullbull bull ~ ~~-~ ~~ bull ~ I ~ I tgt ~ f f1 bull ~ ~ ~ _ bull bull ~middot

~ f bullbullbullbull ~middot

~middot middot ~ bull ~ bull P I ~ + -1 ~ 0 bull bull -gt middot bull

ltI ~ I ltI ltI J 1gt 1gt I ltI ltI I ltI i Jl bull r r lt1 r 01

-~~~-middot ~J)~ IltI JJ

bullbull ~ ~ ~ I

bullbullbullbull bull o) ~ bullbullbullbull ~ ~ bull ltI I ltI ~middot bullbull bullbull bull

J ~ J J J ltI I 1 bull 1 ~ tl gt II ~ ~

t ~ I ltI gt ~ yen I Jl

~lt1lt1bullcl( lbull II ~ I ltI bull - - bull J- _ ) t bull ol

bull ltI _ II R tf bull _ bull bull bullbull bull bull bull bull bull Igt bullbull

~~ ~gt~gt~gtJI~~~tltltl

bull II tl rl gt ~ 1 ltI_ ltI Of II tl

C-32

(2) MATERIAL PLACEMENT AREA

ENVIRONMENTAL PROTECTION AREA

11

MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT

Typical Covered ampPlanted Section Geotube Filling Operation

12 BUILDING STRONGreg

MITIGATION CONTAINMENT ALTERNATIVES

AQUA-DAM WATER CONTAINMENT APPLICATIONS

BUILDING STRONGreg13

(3) FLOW IMPROVEMENT CHANNEL

BUILDING STRONGreg14

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

4

5

15

~ROSS SECTION bull IEXTW ITA 0+50 c-a ~middotJColllrmiddotmiddot

llRTbull ampJUr

(~ ~ROSS SE~TION bull IEXTW ITA 3+00

~middot

C20

CROIIIIiC110N UIW I TA 1 1+00 HOR bull ~f A

llRTmiddot~

CROSS SECTION bull EXTW STA 9+00

-

__ - middot middot middot_ -- --- __ lr_ - --bullbull - middot middotbullmiddotbull middot_middot middot ~------------------middot - -~---- -- ~~~~_ - ~middot- y r

CROSS S ICTION bull DlW S TA Z4bull00

I IC ~

bull

I

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

16

AI~ reg Sic

(6) EAST LEG TRAINING WALL

BUILDING STRONGreg17

HEIGHT RESTRICTIONS DISCUSSION

BUILDING STRONGreg18

COAST GUARD RANGE TOWERS Mike Tomasi AtoN Officer USCG Sector Jacksonville

19

CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT

20

PROPOSED SITE PLAN FOR MILE POINT RANGES

21

PROPOSED RANGE DESIGN

22

ENVIRONMENTAL Paul Stodola

Senior Biologist (NEPA Lead) Mike Hollingsworth

Senior Biologist (Permit Lead)

BUILDING STRONGreg23

ENVIRONEMNTAL COMPLIANCE

EA prepared and coordinated (Includes mitigation plan)

ESA coordination completed

SHPO coordination completed

Coordination on Section 401 WQC completed

BUILDING STRONGreg24

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 5: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

MILE POINT PROJECT PURPOSE Eliminate or reduce difficult crosscurrents at the confluence of the IWW and the St Johns River at ebb tide

Navigation Restrictions during the ebb tide on vessels transiting with a draft gt33 feet or 34 feet depending upon the vessel type

Concerns about how the crosscurrents impact the Mile Point shoreline

BUILDING STRONGreg5

MILE POINT THE BOTTOM LINE

= Navigation Restrictions

Difficult Crosscurrents at Ebb Tide

= Economic Costs

(tidal delays to reach terminals)

Authorization ldquohellip in the interest of navigation and related purposes with particular reference to erosion of the Mile Point shorelinerdquo

6

BLOUNT ISLAND

DAMES POINT

MILE POINT

NAVAL STATION

MAYPORT

TALLEYRAND TERMINAL

NAVY FUEL DEPOT

US MARINE CORPS

TERMINAL

ENGINEERING Steve Conger Lead Engineer

BUILDING STRONGreg7

MILE POINT TRAINING WALL RELOCATIONRECONFIGURATION

Existing Training Wall (~3000 feet)

Training Wall Removal (western ~3110 feet)

New Training Wall (western leg ~4250 feet relocated eastern leg ~2050 feet)

Great Marsh Island Restoration (beneficial use of dredged material)

Flow Improvement Channel (~80 feet wide ~6 feet deep ~3623 feet length)

BUILDING STRONGreg8

PROJECT FEATURES OVERVIEW

1

2

3

4

5

6

1 West Leg Training Wall 4 Existing Training Wall Demolition 2 Material Placement Area 5 Main Dredging Area 3 Flow Improvement Channel 6 East Leg Training Wall

BUILDING STRONGreg9

bull 10

20

_

pound I

10

M~UC Lftl[UIAT10N nML

TYPICAL CROll lliCTION

bull20

bull 10 bull10

10

20

10 _

--

It I

-------t--- --- ----1 _~- I s

-----

-10 10 20 UP I CAL CROSS R CJION

bull20

bull10

10

20

10 70

(1) WEST LEG TRAINING WALL

10

ltI ltI ltI

lti_ bull

D

~ ltI cl f middot~~ J f 4lt J ~

__ ~middot ( ~ i ~ bull bullbullbullbull cl cl cl i r bull 1 bullbull J bullbullbullbull bullbull bull bull bull bull bull ~ bull bull bull bull bull bullbullbull bull bull bull ~ bull ~middot bullbull bullbullbullbull bull

bullbull bull bullbullbull ~middot f bull bull ~ ~middot bull bull ~ ~ bull ~ tl bullbull bull bull cl t1 ~ ~ ( bullbull bullbull t bull yen bullbull cl bull bull bull bull bull bull cl bull tgt ~ (

~ lt ~ bullbull ~ J lt bull ~ bull bull 11 ~ bull tgt bull II I bull bull I tr bull II I II bull I bull tgt bull II ~ bull I I ~ tgt bull I tgt t gt I bull I bull I bull I 1 I tgt bull I tgt ~ middot~middotbull t clcl bull ~middot bull middot ~middot bull ~middot

bullbull bull cl cl cl bullbull bull ~ ~~-~ ~~ bull ~ I ~ I tgt ~ f f1 bull ~ ~ ~ _ bull bull ~middot

~ f bullbullbullbull ~middot

~middot middot ~ bull ~ bull P I ~ + -1 ~ 0 bull bull -gt middot bull

ltI ~ I ltI ltI J 1gt 1gt I ltI ltI I ltI i Jl bull r r lt1 r 01

-~~~-middot ~J)~ IltI JJ

bullbull ~ ~ ~ I

bullbullbullbull bull o) ~ bullbullbullbull ~ ~ bull ltI I ltI ~middot bullbull bullbull bull

J ~ J J J ltI I 1 bull 1 ~ tl gt II ~ ~

t ~ I ltI gt ~ yen I Jl

~lt1lt1bullcl( lbull II ~ I ltI bull - - bull J- _ ) t bull ol

bull ltI _ II R tf bull _ bull bull bullbull bull bull bull bull bull Igt bullbull

~~ ~gt~gt~gtJI~~~tltltl

bull II tl rl gt ~ 1 ltI_ ltI Of II tl

C-32

(2) MATERIAL PLACEMENT AREA

ENVIRONMENTAL PROTECTION AREA

11

MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT

Typical Covered ampPlanted Section Geotube Filling Operation

12 BUILDING STRONGreg

MITIGATION CONTAINMENT ALTERNATIVES

AQUA-DAM WATER CONTAINMENT APPLICATIONS

BUILDING STRONGreg13

(3) FLOW IMPROVEMENT CHANNEL

BUILDING STRONGreg14

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

4

5

15

~ROSS SECTION bull IEXTW ITA 0+50 c-a ~middotJColllrmiddotmiddot

llRTbull ampJUr

(~ ~ROSS SE~TION bull IEXTW ITA 3+00

~middot

C20

CROIIIIiC110N UIW I TA 1 1+00 HOR bull ~f A

llRTmiddot~

CROSS SECTION bull EXTW STA 9+00

-

__ - middot middot middot_ -- --- __ lr_ - --bullbull - middot middotbullmiddotbull middot_middot middot ~------------------middot - -~---- -- ~~~~_ - ~middot- y r

CROSS S ICTION bull DlW S TA Z4bull00

I IC ~

bull

I

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

16

AI~ reg Sic

(6) EAST LEG TRAINING WALL

BUILDING STRONGreg17

HEIGHT RESTRICTIONS DISCUSSION

BUILDING STRONGreg18

COAST GUARD RANGE TOWERS Mike Tomasi AtoN Officer USCG Sector Jacksonville

19

CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT

20

PROPOSED SITE PLAN FOR MILE POINT RANGES

21

PROPOSED RANGE DESIGN

22

ENVIRONMENTAL Paul Stodola

Senior Biologist (NEPA Lead) Mike Hollingsworth

Senior Biologist (Permit Lead)

BUILDING STRONGreg23

ENVIRONEMNTAL COMPLIANCE

EA prepared and coordinated (Includes mitigation plan)

ESA coordination completed

SHPO coordination completed

Coordination on Section 401 WQC completed

BUILDING STRONGreg24

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 6: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

MILE POINT THE BOTTOM LINE

= Navigation Restrictions

Difficult Crosscurrents at Ebb Tide

= Economic Costs

(tidal delays to reach terminals)

Authorization ldquohellip in the interest of navigation and related purposes with particular reference to erosion of the Mile Point shorelinerdquo

6

BLOUNT ISLAND

DAMES POINT

MILE POINT

NAVAL STATION

MAYPORT

TALLEYRAND TERMINAL

NAVY FUEL DEPOT

US MARINE CORPS

TERMINAL

ENGINEERING Steve Conger Lead Engineer

BUILDING STRONGreg7

MILE POINT TRAINING WALL RELOCATIONRECONFIGURATION

Existing Training Wall (~3000 feet)

Training Wall Removal (western ~3110 feet)

New Training Wall (western leg ~4250 feet relocated eastern leg ~2050 feet)

Great Marsh Island Restoration (beneficial use of dredged material)

Flow Improvement Channel (~80 feet wide ~6 feet deep ~3623 feet length)

BUILDING STRONGreg8

PROJECT FEATURES OVERVIEW

1

2

3

4

5

6

1 West Leg Training Wall 4 Existing Training Wall Demolition 2 Material Placement Area 5 Main Dredging Area 3 Flow Improvement Channel 6 East Leg Training Wall

BUILDING STRONGreg9

bull 10

20

_

pound I

10

M~UC Lftl[UIAT10N nML

TYPICAL CROll lliCTION

bull20

bull 10 bull10

10

20

10 _

--

It I

-------t--- --- ----1 _~- I s

-----

-10 10 20 UP I CAL CROSS R CJION

bull20

bull10

10

20

10 70

(1) WEST LEG TRAINING WALL

10

ltI ltI ltI

lti_ bull

D

~ ltI cl f middot~~ J f 4lt J ~

__ ~middot ( ~ i ~ bull bullbullbullbull cl cl cl i r bull 1 bullbull J bullbullbullbull bullbull bull bull bull bull bull ~ bull bull bull bull bull bullbullbull bull bull bull ~ bull ~middot bullbull bullbullbullbull bull

bullbull bull bullbullbull ~middot f bull bull ~ ~middot bull bull ~ ~ bull ~ tl bullbull bull bull cl t1 ~ ~ ( bullbull bullbull t bull yen bullbull cl bull bull bull bull bull bull cl bull tgt ~ (

~ lt ~ bullbull ~ J lt bull ~ bull bull 11 ~ bull tgt bull II I bull bull I tr bull II I II bull I bull tgt bull II ~ bull I I ~ tgt bull I tgt t gt I bull I bull I bull I 1 I tgt bull I tgt ~ middot~middotbull t clcl bull ~middot bull middot ~middot bull ~middot

bullbull bull cl cl cl bullbull bull ~ ~~-~ ~~ bull ~ I ~ I tgt ~ f f1 bull ~ ~ ~ _ bull bull ~middot

~ f bullbullbullbull ~middot

~middot middot ~ bull ~ bull P I ~ + -1 ~ 0 bull bull -gt middot bull

ltI ~ I ltI ltI J 1gt 1gt I ltI ltI I ltI i Jl bull r r lt1 r 01

-~~~-middot ~J)~ IltI JJ

bullbull ~ ~ ~ I

bullbullbullbull bull o) ~ bullbullbullbull ~ ~ bull ltI I ltI ~middot bullbull bullbull bull

J ~ J J J ltI I 1 bull 1 ~ tl gt II ~ ~

t ~ I ltI gt ~ yen I Jl

~lt1lt1bullcl( lbull II ~ I ltI bull - - bull J- _ ) t bull ol

bull ltI _ II R tf bull _ bull bull bullbull bull bull bull bull bull Igt bullbull

~~ ~gt~gt~gtJI~~~tltltl

bull II tl rl gt ~ 1 ltI_ ltI Of II tl

C-32

(2) MATERIAL PLACEMENT AREA

ENVIRONMENTAL PROTECTION AREA

11

MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT

Typical Covered ampPlanted Section Geotube Filling Operation

12 BUILDING STRONGreg

MITIGATION CONTAINMENT ALTERNATIVES

AQUA-DAM WATER CONTAINMENT APPLICATIONS

BUILDING STRONGreg13

(3) FLOW IMPROVEMENT CHANNEL

BUILDING STRONGreg14

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

4

5

15

~ROSS SECTION bull IEXTW ITA 0+50 c-a ~middotJColllrmiddotmiddot

llRTbull ampJUr

(~ ~ROSS SE~TION bull IEXTW ITA 3+00

~middot

C20

CROIIIIiC110N UIW I TA 1 1+00 HOR bull ~f A

llRTmiddot~

CROSS SECTION bull EXTW STA 9+00

-

__ - middot middot middot_ -- --- __ lr_ - --bullbull - middot middotbullmiddotbull middot_middot middot ~------------------middot - -~---- -- ~~~~_ - ~middot- y r

CROSS S ICTION bull DlW S TA Z4bull00

I IC ~

bull

I

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

16

AI~ reg Sic

(6) EAST LEG TRAINING WALL

BUILDING STRONGreg17

HEIGHT RESTRICTIONS DISCUSSION

BUILDING STRONGreg18

COAST GUARD RANGE TOWERS Mike Tomasi AtoN Officer USCG Sector Jacksonville

19

CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT

20

PROPOSED SITE PLAN FOR MILE POINT RANGES

21

PROPOSED RANGE DESIGN

22

ENVIRONMENTAL Paul Stodola

Senior Biologist (NEPA Lead) Mike Hollingsworth

Senior Biologist (Permit Lead)

BUILDING STRONGreg23

ENVIRONEMNTAL COMPLIANCE

EA prepared and coordinated (Includes mitigation plan)

ESA coordination completed

SHPO coordination completed

Coordination on Section 401 WQC completed

BUILDING STRONGreg24

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 7: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

ENGINEERING Steve Conger Lead Engineer

BUILDING STRONGreg7

MILE POINT TRAINING WALL RELOCATIONRECONFIGURATION

Existing Training Wall (~3000 feet)

Training Wall Removal (western ~3110 feet)

New Training Wall (western leg ~4250 feet relocated eastern leg ~2050 feet)

Great Marsh Island Restoration (beneficial use of dredged material)

Flow Improvement Channel (~80 feet wide ~6 feet deep ~3623 feet length)

BUILDING STRONGreg8

PROJECT FEATURES OVERVIEW

1

2

3

4

5

6

1 West Leg Training Wall 4 Existing Training Wall Demolition 2 Material Placement Area 5 Main Dredging Area 3 Flow Improvement Channel 6 East Leg Training Wall

BUILDING STRONGreg9

bull 10

20

_

pound I

10

M~UC Lftl[UIAT10N nML

TYPICAL CROll lliCTION

bull20

bull 10 bull10

10

20

10 _

--

It I

-------t--- --- ----1 _~- I s

-----

-10 10 20 UP I CAL CROSS R CJION

bull20

bull10

10

20

10 70

(1) WEST LEG TRAINING WALL

10

ltI ltI ltI

lti_ bull

D

~ ltI cl f middot~~ J f 4lt J ~

__ ~middot ( ~ i ~ bull bullbullbullbull cl cl cl i r bull 1 bullbull J bullbullbullbull bullbull bull bull bull bull bull ~ bull bull bull bull bull bullbullbull bull bull bull ~ bull ~middot bullbull bullbullbullbull bull

bullbull bull bullbullbull ~middot f bull bull ~ ~middot bull bull ~ ~ bull ~ tl bullbull bull bull cl t1 ~ ~ ( bullbull bullbull t bull yen bullbull cl bull bull bull bull bull bull cl bull tgt ~ (

~ lt ~ bullbull ~ J lt bull ~ bull bull 11 ~ bull tgt bull II I bull bull I tr bull II I II bull I bull tgt bull II ~ bull I I ~ tgt bull I tgt t gt I bull I bull I bull I 1 I tgt bull I tgt ~ middot~middotbull t clcl bull ~middot bull middot ~middot bull ~middot

bullbull bull cl cl cl bullbull bull ~ ~~-~ ~~ bull ~ I ~ I tgt ~ f f1 bull ~ ~ ~ _ bull bull ~middot

~ f bullbullbullbull ~middot

~middot middot ~ bull ~ bull P I ~ + -1 ~ 0 bull bull -gt middot bull

ltI ~ I ltI ltI J 1gt 1gt I ltI ltI I ltI i Jl bull r r lt1 r 01

-~~~-middot ~J)~ IltI JJ

bullbull ~ ~ ~ I

bullbullbullbull bull o) ~ bullbullbullbull ~ ~ bull ltI I ltI ~middot bullbull bullbull bull

J ~ J J J ltI I 1 bull 1 ~ tl gt II ~ ~

t ~ I ltI gt ~ yen I Jl

~lt1lt1bullcl( lbull II ~ I ltI bull - - bull J- _ ) t bull ol

bull ltI _ II R tf bull _ bull bull bullbull bull bull bull bull bull Igt bullbull

~~ ~gt~gt~gtJI~~~tltltl

bull II tl rl gt ~ 1 ltI_ ltI Of II tl

C-32

(2) MATERIAL PLACEMENT AREA

ENVIRONMENTAL PROTECTION AREA

11

MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT

Typical Covered ampPlanted Section Geotube Filling Operation

12 BUILDING STRONGreg

MITIGATION CONTAINMENT ALTERNATIVES

AQUA-DAM WATER CONTAINMENT APPLICATIONS

BUILDING STRONGreg13

(3) FLOW IMPROVEMENT CHANNEL

BUILDING STRONGreg14

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

4

5

15

~ROSS SECTION bull IEXTW ITA 0+50 c-a ~middotJColllrmiddotmiddot

llRTbull ampJUr

(~ ~ROSS SE~TION bull IEXTW ITA 3+00

~middot

C20

CROIIIIiC110N UIW I TA 1 1+00 HOR bull ~f A

llRTmiddot~

CROSS SECTION bull EXTW STA 9+00

-

__ - middot middot middot_ -- --- __ lr_ - --bullbull - middot middotbullmiddotbull middot_middot middot ~------------------middot - -~---- -- ~~~~_ - ~middot- y r

CROSS S ICTION bull DlW S TA Z4bull00

I IC ~

bull

I

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

16

AI~ reg Sic

(6) EAST LEG TRAINING WALL

BUILDING STRONGreg17

HEIGHT RESTRICTIONS DISCUSSION

BUILDING STRONGreg18

COAST GUARD RANGE TOWERS Mike Tomasi AtoN Officer USCG Sector Jacksonville

19

CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT

20

PROPOSED SITE PLAN FOR MILE POINT RANGES

21

PROPOSED RANGE DESIGN

22

ENVIRONMENTAL Paul Stodola

Senior Biologist (NEPA Lead) Mike Hollingsworth

Senior Biologist (Permit Lead)

BUILDING STRONGreg23

ENVIRONEMNTAL COMPLIANCE

EA prepared and coordinated (Includes mitigation plan)

ESA coordination completed

SHPO coordination completed

Coordination on Section 401 WQC completed

BUILDING STRONGreg24

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 8: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

MILE POINT TRAINING WALL RELOCATIONRECONFIGURATION

Existing Training Wall (~3000 feet)

Training Wall Removal (western ~3110 feet)

New Training Wall (western leg ~4250 feet relocated eastern leg ~2050 feet)

Great Marsh Island Restoration (beneficial use of dredged material)

Flow Improvement Channel (~80 feet wide ~6 feet deep ~3623 feet length)

BUILDING STRONGreg8

PROJECT FEATURES OVERVIEW

1

2

3

4

5

6

1 West Leg Training Wall 4 Existing Training Wall Demolition 2 Material Placement Area 5 Main Dredging Area 3 Flow Improvement Channel 6 East Leg Training Wall

BUILDING STRONGreg9

bull 10

20

_

pound I

10

M~UC Lftl[UIAT10N nML

TYPICAL CROll lliCTION

bull20

bull 10 bull10

10

20

10 _

--

It I

-------t--- --- ----1 _~- I s

-----

-10 10 20 UP I CAL CROSS R CJION

bull20

bull10

10

20

10 70

(1) WEST LEG TRAINING WALL

10

ltI ltI ltI

lti_ bull

D

~ ltI cl f middot~~ J f 4lt J ~

__ ~middot ( ~ i ~ bull bullbullbullbull cl cl cl i r bull 1 bullbull J bullbullbullbull bullbull bull bull bull bull bull ~ bull bull bull bull bull bullbullbull bull bull bull ~ bull ~middot bullbull bullbullbullbull bull

bullbull bull bullbullbull ~middot f bull bull ~ ~middot bull bull ~ ~ bull ~ tl bullbull bull bull cl t1 ~ ~ ( bullbull bullbull t bull yen bullbull cl bull bull bull bull bull bull cl bull tgt ~ (

~ lt ~ bullbull ~ J lt bull ~ bull bull 11 ~ bull tgt bull II I bull bull I tr bull II I II bull I bull tgt bull II ~ bull I I ~ tgt bull I tgt t gt I bull I bull I bull I 1 I tgt bull I tgt ~ middot~middotbull t clcl bull ~middot bull middot ~middot bull ~middot

bullbull bull cl cl cl bullbull bull ~ ~~-~ ~~ bull ~ I ~ I tgt ~ f f1 bull ~ ~ ~ _ bull bull ~middot

~ f bullbullbullbull ~middot

~middot middot ~ bull ~ bull P I ~ + -1 ~ 0 bull bull -gt middot bull

ltI ~ I ltI ltI J 1gt 1gt I ltI ltI I ltI i Jl bull r r lt1 r 01

-~~~-middot ~J)~ IltI JJ

bullbull ~ ~ ~ I

bullbullbullbull bull o) ~ bullbullbullbull ~ ~ bull ltI I ltI ~middot bullbull bullbull bull

J ~ J J J ltI I 1 bull 1 ~ tl gt II ~ ~

t ~ I ltI gt ~ yen I Jl

~lt1lt1bullcl( lbull II ~ I ltI bull - - bull J- _ ) t bull ol

bull ltI _ II R tf bull _ bull bull bullbull bull bull bull bull bull Igt bullbull

~~ ~gt~gt~gtJI~~~tltltl

bull II tl rl gt ~ 1 ltI_ ltI Of II tl

C-32

(2) MATERIAL PLACEMENT AREA

ENVIRONMENTAL PROTECTION AREA

11

MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT

Typical Covered ampPlanted Section Geotube Filling Operation

12 BUILDING STRONGreg

MITIGATION CONTAINMENT ALTERNATIVES

AQUA-DAM WATER CONTAINMENT APPLICATIONS

BUILDING STRONGreg13

(3) FLOW IMPROVEMENT CHANNEL

BUILDING STRONGreg14

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

4

5

15

~ROSS SECTION bull IEXTW ITA 0+50 c-a ~middotJColllrmiddotmiddot

llRTbull ampJUr

(~ ~ROSS SE~TION bull IEXTW ITA 3+00

~middot

C20

CROIIIIiC110N UIW I TA 1 1+00 HOR bull ~f A

llRTmiddot~

CROSS SECTION bull EXTW STA 9+00

-

__ - middot middot middot_ -- --- __ lr_ - --bullbull - middot middotbullmiddotbull middot_middot middot ~------------------middot - -~---- -- ~~~~_ - ~middot- y r

CROSS S ICTION bull DlW S TA Z4bull00

I IC ~

bull

I

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

16

AI~ reg Sic

(6) EAST LEG TRAINING WALL

BUILDING STRONGreg17

HEIGHT RESTRICTIONS DISCUSSION

BUILDING STRONGreg18

COAST GUARD RANGE TOWERS Mike Tomasi AtoN Officer USCG Sector Jacksonville

19

CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT

20

PROPOSED SITE PLAN FOR MILE POINT RANGES

21

PROPOSED RANGE DESIGN

22

ENVIRONMENTAL Paul Stodola

Senior Biologist (NEPA Lead) Mike Hollingsworth

Senior Biologist (Permit Lead)

BUILDING STRONGreg23

ENVIRONEMNTAL COMPLIANCE

EA prepared and coordinated (Includes mitigation plan)

ESA coordination completed

SHPO coordination completed

Coordination on Section 401 WQC completed

BUILDING STRONGreg24

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 9: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

PROJECT FEATURES OVERVIEW

1

2

3

4

5

6

1 West Leg Training Wall 4 Existing Training Wall Demolition 2 Material Placement Area 5 Main Dredging Area 3 Flow Improvement Channel 6 East Leg Training Wall

BUILDING STRONGreg9

bull 10

20

_

pound I

10

M~UC Lftl[UIAT10N nML

TYPICAL CROll lliCTION

bull20

bull 10 bull10

10

20

10 _

--

It I

-------t--- --- ----1 _~- I s

-----

-10 10 20 UP I CAL CROSS R CJION

bull20

bull10

10

20

10 70

(1) WEST LEG TRAINING WALL

10

ltI ltI ltI

lti_ bull

D

~ ltI cl f middot~~ J f 4lt J ~

__ ~middot ( ~ i ~ bull bullbullbullbull cl cl cl i r bull 1 bullbull J bullbullbullbull bullbull bull bull bull bull bull ~ bull bull bull bull bull bullbullbull bull bull bull ~ bull ~middot bullbull bullbullbullbull bull

bullbull bull bullbullbull ~middot f bull bull ~ ~middot bull bull ~ ~ bull ~ tl bullbull bull bull cl t1 ~ ~ ( bullbull bullbull t bull yen bullbull cl bull bull bull bull bull bull cl bull tgt ~ (

~ lt ~ bullbull ~ J lt bull ~ bull bull 11 ~ bull tgt bull II I bull bull I tr bull II I II bull I bull tgt bull II ~ bull I I ~ tgt bull I tgt t gt I bull I bull I bull I 1 I tgt bull I tgt ~ middot~middotbull t clcl bull ~middot bull middot ~middot bull ~middot

bullbull bull cl cl cl bullbull bull ~ ~~-~ ~~ bull ~ I ~ I tgt ~ f f1 bull ~ ~ ~ _ bull bull ~middot

~ f bullbullbullbull ~middot

~middot middot ~ bull ~ bull P I ~ + -1 ~ 0 bull bull -gt middot bull

ltI ~ I ltI ltI J 1gt 1gt I ltI ltI I ltI i Jl bull r r lt1 r 01

-~~~-middot ~J)~ IltI JJ

bullbull ~ ~ ~ I

bullbullbullbull bull o) ~ bullbullbullbull ~ ~ bull ltI I ltI ~middot bullbull bullbull bull

J ~ J J J ltI I 1 bull 1 ~ tl gt II ~ ~

t ~ I ltI gt ~ yen I Jl

~lt1lt1bullcl( lbull II ~ I ltI bull - - bull J- _ ) t bull ol

bull ltI _ II R tf bull _ bull bull bullbull bull bull bull bull bull Igt bullbull

~~ ~gt~gt~gtJI~~~tltltl

bull II tl rl gt ~ 1 ltI_ ltI Of II tl

C-32

(2) MATERIAL PLACEMENT AREA

ENVIRONMENTAL PROTECTION AREA

11

MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT

Typical Covered ampPlanted Section Geotube Filling Operation

12 BUILDING STRONGreg

MITIGATION CONTAINMENT ALTERNATIVES

AQUA-DAM WATER CONTAINMENT APPLICATIONS

BUILDING STRONGreg13

(3) FLOW IMPROVEMENT CHANNEL

BUILDING STRONGreg14

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

4

5

15

~ROSS SECTION bull IEXTW ITA 0+50 c-a ~middotJColllrmiddotmiddot

llRTbull ampJUr

(~ ~ROSS SE~TION bull IEXTW ITA 3+00

~middot

C20

CROIIIIiC110N UIW I TA 1 1+00 HOR bull ~f A

llRTmiddot~

CROSS SECTION bull EXTW STA 9+00

-

__ - middot middot middot_ -- --- __ lr_ - --bullbull - middot middotbullmiddotbull middot_middot middot ~------------------middot - -~---- -- ~~~~_ - ~middot- y r

CROSS S ICTION bull DlW S TA Z4bull00

I IC ~

bull

I

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

16

AI~ reg Sic

(6) EAST LEG TRAINING WALL

BUILDING STRONGreg17

HEIGHT RESTRICTIONS DISCUSSION

BUILDING STRONGreg18

COAST GUARD RANGE TOWERS Mike Tomasi AtoN Officer USCG Sector Jacksonville

19

CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT

20

PROPOSED SITE PLAN FOR MILE POINT RANGES

21

PROPOSED RANGE DESIGN

22

ENVIRONMENTAL Paul Stodola

Senior Biologist (NEPA Lead) Mike Hollingsworth

Senior Biologist (Permit Lead)

BUILDING STRONGreg23

ENVIRONEMNTAL COMPLIANCE

EA prepared and coordinated (Includes mitigation plan)

ESA coordination completed

SHPO coordination completed

Coordination on Section 401 WQC completed

BUILDING STRONGreg24

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 10: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

bull 10

20

_

pound I

10

M~UC Lftl[UIAT10N nML

TYPICAL CROll lliCTION

bull20

bull 10 bull10

10

20

10 _

--

It I

-------t--- --- ----1 _~- I s

-----

-10 10 20 UP I CAL CROSS R CJION

bull20

bull10

10

20

10 70

(1) WEST LEG TRAINING WALL

10

ltI ltI ltI

lti_ bull

D

~ ltI cl f middot~~ J f 4lt J ~

__ ~middot ( ~ i ~ bull bullbullbullbull cl cl cl i r bull 1 bullbull J bullbullbullbull bullbull bull bull bull bull bull ~ bull bull bull bull bull bullbullbull bull bull bull ~ bull ~middot bullbull bullbullbullbull bull

bullbull bull bullbullbull ~middot f bull bull ~ ~middot bull bull ~ ~ bull ~ tl bullbull bull bull cl t1 ~ ~ ( bullbull bullbull t bull yen bullbull cl bull bull bull bull bull bull cl bull tgt ~ (

~ lt ~ bullbull ~ J lt bull ~ bull bull 11 ~ bull tgt bull II I bull bull I tr bull II I II bull I bull tgt bull II ~ bull I I ~ tgt bull I tgt t gt I bull I bull I bull I 1 I tgt bull I tgt ~ middot~middotbull t clcl bull ~middot bull middot ~middot bull ~middot

bullbull bull cl cl cl bullbull bull ~ ~~-~ ~~ bull ~ I ~ I tgt ~ f f1 bull ~ ~ ~ _ bull bull ~middot

~ f bullbullbullbull ~middot

~middot middot ~ bull ~ bull P I ~ + -1 ~ 0 bull bull -gt middot bull

ltI ~ I ltI ltI J 1gt 1gt I ltI ltI I ltI i Jl bull r r lt1 r 01

-~~~-middot ~J)~ IltI JJ

bullbull ~ ~ ~ I

bullbullbullbull bull o) ~ bullbullbullbull ~ ~ bull ltI I ltI ~middot bullbull bullbull bull

J ~ J J J ltI I 1 bull 1 ~ tl gt II ~ ~

t ~ I ltI gt ~ yen I Jl

~lt1lt1bullcl( lbull II ~ I ltI bull - - bull J- _ ) t bull ol

bull ltI _ II R tf bull _ bull bull bullbull bull bull bull bull bull Igt bullbull

~~ ~gt~gt~gtJI~~~tltltl

bull II tl rl gt ~ 1 ltI_ ltI Of II tl

C-32

(2) MATERIAL PLACEMENT AREA

ENVIRONMENTAL PROTECTION AREA

11

MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT

Typical Covered ampPlanted Section Geotube Filling Operation

12 BUILDING STRONGreg

MITIGATION CONTAINMENT ALTERNATIVES

AQUA-DAM WATER CONTAINMENT APPLICATIONS

BUILDING STRONGreg13

(3) FLOW IMPROVEMENT CHANNEL

BUILDING STRONGreg14

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

4

5

15

~ROSS SECTION bull IEXTW ITA 0+50 c-a ~middotJColllrmiddotmiddot

llRTbull ampJUr

(~ ~ROSS SE~TION bull IEXTW ITA 3+00

~middot

C20

CROIIIIiC110N UIW I TA 1 1+00 HOR bull ~f A

llRTmiddot~

CROSS SECTION bull EXTW STA 9+00

-

__ - middot middot middot_ -- --- __ lr_ - --bullbull - middot middotbullmiddotbull middot_middot middot ~------------------middot - -~---- -- ~~~~_ - ~middot- y r

CROSS S ICTION bull DlW S TA Z4bull00

I IC ~

bull

I

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

16

AI~ reg Sic

(6) EAST LEG TRAINING WALL

BUILDING STRONGreg17

HEIGHT RESTRICTIONS DISCUSSION

BUILDING STRONGreg18

COAST GUARD RANGE TOWERS Mike Tomasi AtoN Officer USCG Sector Jacksonville

19

CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT

20

PROPOSED SITE PLAN FOR MILE POINT RANGES

21

PROPOSED RANGE DESIGN

22

ENVIRONMENTAL Paul Stodola

Senior Biologist (NEPA Lead) Mike Hollingsworth

Senior Biologist (Permit Lead)

BUILDING STRONGreg23

ENVIRONEMNTAL COMPLIANCE

EA prepared and coordinated (Includes mitigation plan)

ESA coordination completed

SHPO coordination completed

Coordination on Section 401 WQC completed

BUILDING STRONGreg24

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 11: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

ltI ltI ltI

lti_ bull

D

~ ltI cl f middot~~ J f 4lt J ~

__ ~middot ( ~ i ~ bull bullbullbullbull cl cl cl i r bull 1 bullbull J bullbullbullbull bullbull bull bull bull bull bull ~ bull bull bull bull bull bullbullbull bull bull bull ~ bull ~middot bullbull bullbullbullbull bull

bullbull bull bullbullbull ~middot f bull bull ~ ~middot bull bull ~ ~ bull ~ tl bullbull bull bull cl t1 ~ ~ ( bullbull bullbull t bull yen bullbull cl bull bull bull bull bull bull cl bull tgt ~ (

~ lt ~ bullbull ~ J lt bull ~ bull bull 11 ~ bull tgt bull II I bull bull I tr bull II I II bull I bull tgt bull II ~ bull I I ~ tgt bull I tgt t gt I bull I bull I bull I 1 I tgt bull I tgt ~ middot~middotbull t clcl bull ~middot bull middot ~middot bull ~middot

bullbull bull cl cl cl bullbull bull ~ ~~-~ ~~ bull ~ I ~ I tgt ~ f f1 bull ~ ~ ~ _ bull bull ~middot

~ f bullbullbullbull ~middot

~middot middot ~ bull ~ bull P I ~ + -1 ~ 0 bull bull -gt middot bull

ltI ~ I ltI ltI J 1gt 1gt I ltI ltI I ltI i Jl bull r r lt1 r 01

-~~~-middot ~J)~ IltI JJ

bullbull ~ ~ ~ I

bullbullbullbull bull o) ~ bullbullbullbull ~ ~ bull ltI I ltI ~middot bullbull bullbull bull

J ~ J J J ltI I 1 bull 1 ~ tl gt II ~ ~

t ~ I ltI gt ~ yen I Jl

~lt1lt1bullcl( lbull II ~ I ltI bull - - bull J- _ ) t bull ol

bull ltI _ II R tf bull _ bull bull bullbull bull bull bull bull bull Igt bullbull

~~ ~gt~gt~gtJI~~~tltltl

bull II tl rl gt ~ 1 ltI_ ltI Of II tl

C-32

(2) MATERIAL PLACEMENT AREA

ENVIRONMENTAL PROTECTION AREA

11

MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT

Typical Covered ampPlanted Section Geotube Filling Operation

12 BUILDING STRONGreg

MITIGATION CONTAINMENT ALTERNATIVES

AQUA-DAM WATER CONTAINMENT APPLICATIONS

BUILDING STRONGreg13

(3) FLOW IMPROVEMENT CHANNEL

BUILDING STRONGreg14

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

4

5

15

~ROSS SECTION bull IEXTW ITA 0+50 c-a ~middotJColllrmiddotmiddot

llRTbull ampJUr

(~ ~ROSS SE~TION bull IEXTW ITA 3+00

~middot

C20

CROIIIIiC110N UIW I TA 1 1+00 HOR bull ~f A

llRTmiddot~

CROSS SECTION bull EXTW STA 9+00

-

__ - middot middot middot_ -- --- __ lr_ - --bullbull - middot middotbullmiddotbull middot_middot middot ~------------------middot - -~---- -- ~~~~_ - ~middot- y r

CROSS S ICTION bull DlW S TA Z4bull00

I IC ~

bull

I

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

16

AI~ reg Sic

(6) EAST LEG TRAINING WALL

BUILDING STRONGreg17

HEIGHT RESTRICTIONS DISCUSSION

BUILDING STRONGreg18

COAST GUARD RANGE TOWERS Mike Tomasi AtoN Officer USCG Sector Jacksonville

19

CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT

20

PROPOSED SITE PLAN FOR MILE POINT RANGES

21

PROPOSED RANGE DESIGN

22

ENVIRONMENTAL Paul Stodola

Senior Biologist (NEPA Lead) Mike Hollingsworth

Senior Biologist (Permit Lead)

BUILDING STRONGreg23

ENVIRONEMNTAL COMPLIANCE

EA prepared and coordinated (Includes mitigation plan)

ESA coordination completed

SHPO coordination completed

Coordination on Section 401 WQC completed

BUILDING STRONGreg24

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 12: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT

Typical Covered ampPlanted Section Geotube Filling Operation

12 BUILDING STRONGreg

MITIGATION CONTAINMENT ALTERNATIVES

AQUA-DAM WATER CONTAINMENT APPLICATIONS

BUILDING STRONGreg13

(3) FLOW IMPROVEMENT CHANNEL

BUILDING STRONGreg14

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

4

5

15

~ROSS SECTION bull IEXTW ITA 0+50 c-a ~middotJColllrmiddotmiddot

llRTbull ampJUr

(~ ~ROSS SE~TION bull IEXTW ITA 3+00

~middot

C20

CROIIIIiC110N UIW I TA 1 1+00 HOR bull ~f A

llRTmiddot~

CROSS SECTION bull EXTW STA 9+00

-

__ - middot middot middot_ -- --- __ lr_ - --bullbull - middot middotbullmiddotbull middot_middot middot ~------------------middot - -~---- -- ~~~~_ - ~middot- y r

CROSS S ICTION bull DlW S TA Z4bull00

I IC ~

bull

I

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

16

AI~ reg Sic

(6) EAST LEG TRAINING WALL

BUILDING STRONGreg17

HEIGHT RESTRICTIONS DISCUSSION

BUILDING STRONGreg18

COAST GUARD RANGE TOWERS Mike Tomasi AtoN Officer USCG Sector Jacksonville

19

CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT

20

PROPOSED SITE PLAN FOR MILE POINT RANGES

21

PROPOSED RANGE DESIGN

22

ENVIRONMENTAL Paul Stodola

Senior Biologist (NEPA Lead) Mike Hollingsworth

Senior Biologist (Permit Lead)

BUILDING STRONGreg23

ENVIRONEMNTAL COMPLIANCE

EA prepared and coordinated (Includes mitigation plan)

ESA coordination completed

SHPO coordination completed

Coordination on Section 401 WQC completed

BUILDING STRONGreg24

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 13: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

MITIGATION CONTAINMENT ALTERNATIVES

AQUA-DAM WATER CONTAINMENT APPLICATIONS

BUILDING STRONGreg13

(3) FLOW IMPROVEMENT CHANNEL

BUILDING STRONGreg14

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

4

5

15

~ROSS SECTION bull IEXTW ITA 0+50 c-a ~middotJColllrmiddotmiddot

llRTbull ampJUr

(~ ~ROSS SE~TION bull IEXTW ITA 3+00

~middot

C20

CROIIIIiC110N UIW I TA 1 1+00 HOR bull ~f A

llRTmiddot~

CROSS SECTION bull EXTW STA 9+00

-

__ - middot middot middot_ -- --- __ lr_ - --bullbull - middot middotbullmiddotbull middot_middot middot ~------------------middot - -~---- -- ~~~~_ - ~middot- y r

CROSS S ICTION bull DlW S TA Z4bull00

I IC ~

bull

I

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

16

AI~ reg Sic

(6) EAST LEG TRAINING WALL

BUILDING STRONGreg17

HEIGHT RESTRICTIONS DISCUSSION

BUILDING STRONGreg18

COAST GUARD RANGE TOWERS Mike Tomasi AtoN Officer USCG Sector Jacksonville

19

CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT

20

PROPOSED SITE PLAN FOR MILE POINT RANGES

21

PROPOSED RANGE DESIGN

22

ENVIRONMENTAL Paul Stodola

Senior Biologist (NEPA Lead) Mike Hollingsworth

Senior Biologist (Permit Lead)

BUILDING STRONGreg23

ENVIRONEMNTAL COMPLIANCE

EA prepared and coordinated (Includes mitigation plan)

ESA coordination completed

SHPO coordination completed

Coordination on Section 401 WQC completed

BUILDING STRONGreg24

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 14: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

(3) FLOW IMPROVEMENT CHANNEL

BUILDING STRONGreg14

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

4

5

15

~ROSS SECTION bull IEXTW ITA 0+50 c-a ~middotJColllrmiddotmiddot

llRTbull ampJUr

(~ ~ROSS SE~TION bull IEXTW ITA 3+00

~middot

C20

CROIIIIiC110N UIW I TA 1 1+00 HOR bull ~f A

llRTmiddot~

CROSS SECTION bull EXTW STA 9+00

-

__ - middot middot middot_ -- --- __ lr_ - --bullbull - middot middotbullmiddotbull middot_middot middot ~------------------middot - -~---- -- ~~~~_ - ~middot- y r

CROSS S ICTION bull DlW S TA Z4bull00

I IC ~

bull

I

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

16

AI~ reg Sic

(6) EAST LEG TRAINING WALL

BUILDING STRONGreg17

HEIGHT RESTRICTIONS DISCUSSION

BUILDING STRONGreg18

COAST GUARD RANGE TOWERS Mike Tomasi AtoN Officer USCG Sector Jacksonville

19

CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT

20

PROPOSED SITE PLAN FOR MILE POINT RANGES

21

PROPOSED RANGE DESIGN

22

ENVIRONMENTAL Paul Stodola

Senior Biologist (NEPA Lead) Mike Hollingsworth

Senior Biologist (Permit Lead)

BUILDING STRONGreg23

ENVIRONEMNTAL COMPLIANCE

EA prepared and coordinated (Includes mitigation plan)

ESA coordination completed

SHPO coordination completed

Coordination on Section 401 WQC completed

BUILDING STRONGreg24

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 15: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

4

5

15

~ROSS SECTION bull IEXTW ITA 0+50 c-a ~middotJColllrmiddotmiddot

llRTbull ampJUr

(~ ~ROSS SE~TION bull IEXTW ITA 3+00

~middot

C20

CROIIIIiC110N UIW I TA 1 1+00 HOR bull ~f A

llRTmiddot~

CROSS SECTION bull EXTW STA 9+00

-

__ - middot middot middot_ -- --- __ lr_ - --bullbull - middot middotbullmiddotbull middot_middot middot ~------------------middot - -~---- -- ~~~~_ - ~middot- y r

CROSS S ICTION bull DlW S TA Z4bull00

I IC ~

bull

I

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

16

AI~ reg Sic

(6) EAST LEG TRAINING WALL

BUILDING STRONGreg17

HEIGHT RESTRICTIONS DISCUSSION

BUILDING STRONGreg18

COAST GUARD RANGE TOWERS Mike Tomasi AtoN Officer USCG Sector Jacksonville

19

CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT

20

PROPOSED SITE PLAN FOR MILE POINT RANGES

21

PROPOSED RANGE DESIGN

22

ENVIRONMENTAL Paul Stodola

Senior Biologist (NEPA Lead) Mike Hollingsworth

Senior Biologist (Permit Lead)

BUILDING STRONGreg23

ENVIRONEMNTAL COMPLIANCE

EA prepared and coordinated (Includes mitigation plan)

ESA coordination completed

SHPO coordination completed

Coordination on Section 401 WQC completed

BUILDING STRONGreg24

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 16: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

~ROSS SECTION bull IEXTW ITA 0+50 c-a ~middotJColllrmiddotmiddot

llRTbull ampJUr

(~ ~ROSS SE~TION bull IEXTW ITA 3+00

~middot

C20

CROIIIIiC110N UIW I TA 1 1+00 HOR bull ~f A

llRTmiddot~

CROSS SECTION bull EXTW STA 9+00

-

__ - middot middot middot_ -- --- __ lr_ - --bullbull - middot middotbullmiddotbull middot_middot middot ~------------------middot - -~---- -- ~~~~_ - ~middot- y r

CROSS S ICTION bull DlW S TA Z4bull00

I IC ~

bull

I

(4) EXISTING WALL DEMOLITION (5) MAIN DREDGING AREA

16

AI~ reg Sic

(6) EAST LEG TRAINING WALL

BUILDING STRONGreg17

HEIGHT RESTRICTIONS DISCUSSION

BUILDING STRONGreg18

COAST GUARD RANGE TOWERS Mike Tomasi AtoN Officer USCG Sector Jacksonville

19

CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT

20

PROPOSED SITE PLAN FOR MILE POINT RANGES

21

PROPOSED RANGE DESIGN

22

ENVIRONMENTAL Paul Stodola

Senior Biologist (NEPA Lead) Mike Hollingsworth

Senior Biologist (Permit Lead)

BUILDING STRONGreg23

ENVIRONEMNTAL COMPLIANCE

EA prepared and coordinated (Includes mitigation plan)

ESA coordination completed

SHPO coordination completed

Coordination on Section 401 WQC completed

BUILDING STRONGreg24

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 17: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

AI~ reg Sic

(6) EAST LEG TRAINING WALL

BUILDING STRONGreg17

HEIGHT RESTRICTIONS DISCUSSION

BUILDING STRONGreg18

COAST GUARD RANGE TOWERS Mike Tomasi AtoN Officer USCG Sector Jacksonville

19

CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT

20

PROPOSED SITE PLAN FOR MILE POINT RANGES

21

PROPOSED RANGE DESIGN

22

ENVIRONMENTAL Paul Stodola

Senior Biologist (NEPA Lead) Mike Hollingsworth

Senior Biologist (Permit Lead)

BUILDING STRONGreg23

ENVIRONEMNTAL COMPLIANCE

EA prepared and coordinated (Includes mitigation plan)

ESA coordination completed

SHPO coordination completed

Coordination on Section 401 WQC completed

BUILDING STRONGreg24

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 18: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

HEIGHT RESTRICTIONS DISCUSSION

BUILDING STRONGreg18

COAST GUARD RANGE TOWERS Mike Tomasi AtoN Officer USCG Sector Jacksonville

19

CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT

20

PROPOSED SITE PLAN FOR MILE POINT RANGES

21

PROPOSED RANGE DESIGN

22

ENVIRONMENTAL Paul Stodola

Senior Biologist (NEPA Lead) Mike Hollingsworth

Senior Biologist (Permit Lead)

BUILDING STRONGreg23

ENVIRONEMNTAL COMPLIANCE

EA prepared and coordinated (Includes mitigation plan)

ESA coordination completed

SHPO coordination completed

Coordination on Section 401 WQC completed

BUILDING STRONGreg24

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 19: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

COAST GUARD RANGE TOWERS Mike Tomasi AtoN Officer USCG Sector Jacksonville

19

CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT

20

PROPOSED SITE PLAN FOR MILE POINT RANGES

21

PROPOSED RANGE DESIGN

22

ENVIRONMENTAL Paul Stodola

Senior Biologist (NEPA Lead) Mike Hollingsworth

Senior Biologist (Permit Lead)

BUILDING STRONGreg23

ENVIRONEMNTAL COMPLIANCE

EA prepared and coordinated (Includes mitigation plan)

ESA coordination completed

SHPO coordination completed

Coordination on Section 401 WQC completed

BUILDING STRONGreg24

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 20: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT

20

PROPOSED SITE PLAN FOR MILE POINT RANGES

21

PROPOSED RANGE DESIGN

22

ENVIRONMENTAL Paul Stodola

Senior Biologist (NEPA Lead) Mike Hollingsworth

Senior Biologist (Permit Lead)

BUILDING STRONGreg23

ENVIRONEMNTAL COMPLIANCE

EA prepared and coordinated (Includes mitigation plan)

ESA coordination completed

SHPO coordination completed

Coordination on Section 401 WQC completed

BUILDING STRONGreg24

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 21: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

PROPOSED SITE PLAN FOR MILE POINT RANGES

21

PROPOSED RANGE DESIGN

22

ENVIRONMENTAL Paul Stodola

Senior Biologist (NEPA Lead) Mike Hollingsworth

Senior Biologist (Permit Lead)

BUILDING STRONGreg23

ENVIRONEMNTAL COMPLIANCE

EA prepared and coordinated (Includes mitigation plan)

ESA coordination completed

SHPO coordination completed

Coordination on Section 401 WQC completed

BUILDING STRONGreg24

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 22: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

PROPOSED RANGE DESIGN

22

ENVIRONMENTAL Paul Stodola

Senior Biologist (NEPA Lead) Mike Hollingsworth

Senior Biologist (Permit Lead)

BUILDING STRONGreg23

ENVIRONEMNTAL COMPLIANCE

EA prepared and coordinated (Includes mitigation plan)

ESA coordination completed

SHPO coordination completed

Coordination on Section 401 WQC completed

BUILDING STRONGreg24

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 23: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

ENVIRONMENTAL Paul Stodola

Senior Biologist (NEPA Lead) Mike Hollingsworth

Senior Biologist (Permit Lead)

BUILDING STRONGreg23

ENVIRONEMNTAL COMPLIANCE

EA prepared and coordinated (Includes mitigation plan)

ESA coordination completed

SHPO coordination completed

Coordination on Section 401 WQC completed

BUILDING STRONGreg24

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 24: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

ENVIRONEMNTAL COMPLIANCE

EA prepared and coordinated (Includes mitigation plan)

ESA coordination completed

SHPO coordination completed

Coordination on Section 401 WQC completed

BUILDING STRONGreg24

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 25: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

ENVIRONMENTAL MONITORING Turbidity Standard 29 NTUs

over background

Endangered Species Manatees Sea Turtles Sturgeon

Migratory Birds WATER QUALITY PERMIT SITE httpwwwsajusacearmymilAboutDivisions OfficesPlanningEnvironmentalBranch EnvironmentalComplianceaspxDuval

BUILDING STRONGreg25

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 26: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

PROCUREMENT STRATEGY Tedra Thompson Contract Specialist

BUILDING STRONGreg26

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 27: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

COMPETITIVE ACQUISITION

Best Value Continuum Award will be made based on the best overall

(ie best value) proposal that is deemed most beneficial to the Government with appropriate consideration given to the evaluation factors

To receive consideration for award a rating of no less than Acceptable must be achieved for the Technical Merit factor

BUILDING STRONGreg27

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 28: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

COMPETITIVE ACQUISITION Best Value Continuum This process permits Tradeoffs among costprice and

non-cost factors and allows the Government to accept other than the lowest priced proposal

Offerors are cautioned that the award may not necessarily be made to the lowest priced offer

Award could be made to other than lowest priced offeror

Award could be made to other than highest technically rated offeror

BUILDING STRONGreg28

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 29: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

PROJECT SCHEDULE

Jason Harrah Project Manager

BUILDING STRONGreg29

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 30: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

PROJECT SCHEDULE Key Dates (tentative dates)

Dec 2014 SynopsisAdvertisement (subject to approval of key waivers by USACE)

Feb 2015 Award (subject to approval of key waivers by USACE)

Construction Duration 18 months Cost Magnitude $25M-$50M

BUILDING STRONGreg30

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 31: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

SMALL BUSINESS OPPORTUNITIES Beth Myers Deputy Small Business

BUILDING STRONGreg31

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 32: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

SMALL BUSINESS OPPORTUNITIES FAR 19201 ndash Government policy (a) It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to small business veteran-owned small business service-disabled veteran-owned small business HUBZone small business small disadvantaged business and women-owned small business concerns Such concerns must also have the maximum practicable opportunity to participate as subcontractors in the contracts awarded by any executive agency consistent with efficient contract performance

Small Business Participation Subcontracting Plan (Large Business concerns only)

FAR 19701 ldquoSubcontractrdquo Any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies andor services required for performance of the contractor subcontract

BUILDING STRONGreg32

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 33: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions Breaking out contract work requirements into economically feasible units as

appropriate to facilitate small business participation

Conducting market research to identify small business subcontractors and suppliers through all reasonable means such as performing on-line searches on the Central Contractor Registration posting Notices of Sources Sought andor Requests for Proposal on SBArsquos SUB-Net participating in business Matchmaking events and attending pre-bid conferences

Soliciting small business concerns as early in the acquisition process as practicable to allow them sufficient time to submit a timely offer for the subcontract

Providing interested small businesses with adequate and timely information about the plans specifications and requirements for performance of the prime contract to assist them in submitting a timely offer for the subcontract

BUILDING STRONGreg33

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 34: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Negotiating in good faith with interested small businesses

Directing small businesses that need additional assistance to SBA

Assisting interested small businesses in obtaining bonding lines of credit required insurance necessary equipment supplies materials or services

Utilizing the available services of small business associations local state and Federal small business assistance offices and other organizations and

Participating in the formal mentor-proteacutegeacute program with one or more small business proteacutegeacutes that results in developmental assistanceto the proteacutegeacute(s)

BUILDING STRONGreg34

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 35: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

WHAT ACTIONS SHOULD OTHER THAN SMALL BUSINESS CONTRACTORS TAKE TO ENHANCE

MAXIMUM PRACTICABLE OPPORTUNITY (MPO) Efforts to provide the maximum practicable subcontracting opportunities for small business concerns may include as appropriate for the procurement one or more of the following actions

Additional actions may include

Advertising subcontracting opportunities in FedBizOpps Encouraging joint ventures Providing technical management and financial training and counseling Keeping the playing field level allowing all bidders equal time to respond Providing the same information to all prospective subcontractors at the

same time

Notifying SB SDB WOSB VOSB SDVOSB and HUBZone SB firms that trade union membership is not a FAR (contract) requirement but that payment of the Davis-Bacon prevailing wage rates is a FAR (contract) requirement and

Providing debriefings to unsuccessful small business offerors

BUILDING STRONGreg35

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 36: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

SMALL BUSINESSSUB-CONTRACTING Potential Opportunities exist for Various environmental monitoring requirements

(turbidity endangered species migratory birds etc)

Hydrographic surveying

Procurement amp Delivery (ie stone)

Geo-tubes

West Leg Training Wall Concrete Structural Units

Dredging (potential)

Fuel Delivery

BUILDING STRONGreg36

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 37: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES

System for Award Management wwwsamgov

Dynamic Small Business Search httpdsbssbagovdsbssearchdsp_dsbscfm SB firms keep profile current wbonding

past performance and capabilities LBprime contractors can use many filters to locate

SDB HUBZone WOSB SDVOSB specific firms and their location

FEDBIZOpps wwwfbogov SB firms register as an interested party for the solicitation

BUILDING STRONGreg37

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 38: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

CONTACT INFORMATION Beth Myers Deputy for Small Business

(904) 232-1150

elizabethrmyersusacearmymil

Florida Procurement Technical Assistance Center httpwwwfptacorgcontactushtm

Jacksonville District WebPages wwwsajusacearmymil

How do I contact Small Business

FY2015 Forecast Frequently Asked Questions

BUILDING STRONGreg38

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 39: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

WORKING SAFELY ON THE RIVER Ship traffic is extremely heavy throughout Jacksonville Harbor Working near the channel takes tremendous coordination with the Bay Pilots and the Port

Communication among all was critical for the successful completion of the drilling program

BUILDING STRONGreg39

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS
Page 40: JACKSONVILLE HARBOR MILE POINT · 2014. 11. 14. · Industry Day Presentation November 13, 2014 . AGENDA Opening Remarks (10:00 – 10:05) Technical Presentation (10:05 – 10:35)

CLOSING REMARKS httpwwwsajusacearmymilMissions

CivilWorksNavigation

BUILDING STRONGreg40

  • Slide Number 1
  • Slide Number 2
  • Slide Number 3
  • Slide Number 4
  • Slide Number 5
  • Slide Number 6
  • Slide Number 7
  • Slide Number 8
  • Slide Number 9
  • Slide Number 10
  • Slide Number 11
  • MARSH DEVELOPMENT WITH GEOTUBE CONTAINMENT
  • MITIGATION CONTAINMENT ALTERNATIVES
  • Slide Number 14
  • Slide Number 15
  • Slide Number 16
  • Slide Number 17
  • Slide Number 18
  • Slide Number 19
  • CURRENT MILE POINT UPPER AND LOWER RANGE FRONT LIGHT
  • PROPOSED SITE PLAN FOR MILE POINT RANGES
  • PROPOSED RANGE DESIGN
  • Slide Number 23
  • ENVIRONEMNTAL COMPLIANCE
  • ENVIRONMENTAL MONITORING
  • Slide Number 26
  • COMPETITIVE ACQUISITION
  • COMPETITIVE ACQUISITION
  • Slide Number 29
  • PROJECT SCHEDULE
  • Slide Number 31
  • SMALL BUSINESS OPPORTUNITIES
  • Slide Number 33
  • Slide Number 34
  • Slide Number 35
  • SMALL BUSINESSSUB-CONTRACTING
  • LOOKING FOR OPPORTUNITIES IN ALL THE RIGHT PLACES
  • CONTACT INFORMATION
  • WORKING SAFELY ON THE RIVER
  • CLOSING REMARKS