Progress Update (Nr. 7)Week ending 18th December
![Page 2: ITS Building Project - progress update 7](https://reader031.vdocuments.us/reader031/viewer/2022030219/588525ef1a28abf7538b639b/html5/thumbnails/2.jpg)
Programme Update - ITS For Period : Mon 7th December – Friday 18th December
- Completed external steelwork installation
- Completed installation of ground floor slab
- Commenced installation of external system scaffold around new steelwork structure
- Completed overboarding of existing ceilings to all floors within existing building
- Continued internal builders work within existing building
- Commenced internal plastering works to walls within existing building
![Page 3: ITS Building Project - progress update 7](https://reader031.vdocuments.us/reader031/viewer/2022030219/588525ef1a28abf7538b639b/html5/thumbnails/3.jpg)
Progress Photos – External
Completed external steelwork installation
![Page 4: ITS Building Project - progress update 7](https://reader031.vdocuments.us/reader031/viewer/2022030219/588525ef1a28abf7538b639b/html5/thumbnails/4.jpg)
Progress Photos – External
Completed external steelwork installation
![Page 5: ITS Building Project - progress update 7](https://reader031.vdocuments.us/reader031/viewer/2022030219/588525ef1a28abf7538b639b/html5/thumbnails/5.jpg)
Progress Photos – External
Poured ground floor concrete slab of extension
![Page 6: ITS Building Project - progress update 7](https://reader031.vdocuments.us/reader031/viewer/2022030219/588525ef1a28abf7538b639b/html5/thumbnails/6.jpg)
Progress Photos – External
Ground floor slab shuttering stripped and perimeter ‘stoned up’ in preparation for scaffold
![Page 7: ITS Building Project - progress update 7](https://reader031.vdocuments.us/reader031/viewer/2022030219/588525ef1a28abf7538b639b/html5/thumbnails/7.jpg)
Progress Photos – Internal
Commenced wiring to sockets of rooms within existing building
![Page 8: ITS Building Project - progress update 7](https://reader031.vdocuments.us/reader031/viewer/2022030219/588525ef1a28abf7538b639b/html5/thumbnails/8.jpg)
Progress Photos – Internal
Commenced lining of internal walls within basement
![Page 9: ITS Building Project - progress update 7](https://reader031.vdocuments.us/reader031/viewer/2022030219/588525ef1a28abf7538b639b/html5/thumbnails/9.jpg)
Progress Photos
UoL external hoarding graphics installed
![Page 10: ITS Building Project - progress update 7](https://reader031.vdocuments.us/reader031/viewer/2022030219/588525ef1a28abf7538b639b/html5/thumbnails/10.jpg)
Next Few Weeks………..A look ahead to works commencing within the next 2 weeks :
- Complete installation of external system scaffold around new steelwork structure
- Commence below ground brickwork
- Complete intumescent sprayed coating to external steel frame
- Complete new wall linings to basement
- Complete internal builders work within existing building
- Continue plastering works to walls and ceilings within existing building