ATEP IVC First Building
ADVANCED TECHNOLOGY & EDUCATION PARK South Orange County Community College District
BI-WEEKLY PROGRESS UPDATE Through November 15, 2016
PROJECT STATUS:
Grading and pad elevation work completed
Building location and layout has been surveyed
Footings are being excavated
Main electrical conduit into the building is being installed
Survey of Building – Identifying building location and gridlines
![Page 2: BI-WEEKLY PROGRESS UPDATE Through November 15, 2016 · BI-WEEKLY PROGRESS UPDATE Through November 15, 2016 PROJECT STATUS: Grading and pad elevation work completed Building location](https://reader033.vdocuments.us/reader033/viewer/2022052722/5f0d22017e708231d438d734/html5/thumbnails/2.jpg)
First Bucket of dirt removal for the IVC First Building at ATEP
Excavation of Building Footings
![Page 3: BI-WEEKLY PROGRESS UPDATE Through November 15, 2016 · BI-WEEKLY PROGRESS UPDATE Through November 15, 2016 PROJECT STATUS: Grading and pad elevation work completed Building location](https://reader033.vdocuments.us/reader033/viewer/2022052722/5f0d22017e708231d438d734/html5/thumbnails/3.jpg)
Upcoming Activities: Complete excavation of all footings
Start underground plumbing system
Set anchor bolts
Conduits for main Electrical lines into building