its building project - progress update 4
TRANSCRIPT
![Page 1: ITS Building Project - progress update 4](https://reader034.vdocuments.us/reader034/viewer/2022052514/58f041921a28ab95578b4623/html5/thumbnails/1.jpg)
![Page 2: ITS Building Project - progress update 4](https://reader034.vdocuments.us/reader034/viewer/2022052514/58f041921a28ab95578b4623/html5/thumbnails/2.jpg)
Progress Update (Nr. 4)
Week ending 6th November
![Page 3: ITS Building Project - progress update 4](https://reader034.vdocuments.us/reader034/viewer/2022052514/58f041921a28ab95578b4623/html5/thumbnails/3.jpg)
Programme Update - ITS
For Period : Mon 26th October – Friday 6th October
- Completed excavations, reinforcement and formwork to perimeter retaining walls
- Completed installation of reinforcement to basement slab and concrete pour
- Commenced installation of holding down bolts in preparation for steelwork
- Completed internal damp-proofing works to basement walls
- Commenced internal builders work and the removal of remaining load bearing walls:
including installing necessary concrete lintels
- Continue first fix mechanical and electrical works within existing building to all floors
![Page 4: ITS Building Project - progress update 4](https://reader034.vdocuments.us/reader034/viewer/2022052514/58f041921a28ab95578b4623/html5/thumbnails/4.jpg)
Progress Photos – External
Basement floor slab & lift
pit concrete pour complete
![Page 5: ITS Building Project - progress update 4](https://reader034.vdocuments.us/reader034/viewer/2022052514/58f041921a28ab95578b4623/html5/thumbnails/5.jpg)
Progress Photos – External
Retaining wall steelwork
reinforcement installed
throughout perimeter walls
![Page 6: ITS Building Project - progress update 4](https://reader034.vdocuments.us/reader034/viewer/2022052514/58f041921a28ab95578b4623/html5/thumbnails/6.jpg)
Progress Photos – External
Retaining wall
formwork/shuttering
installed and also
temporary props positioned
in preparation for next
phase concrete pour
![Page 7: ITS Building Project - progress update 4](https://reader034.vdocuments.us/reader034/viewer/2022052514/58f041921a28ab95578b4623/html5/thumbnails/7.jpg)
Progress Photos – Internal
First fix mechanical and
electrical works continued
within the existing building
through all floors
![Page 8: ITS Building Project - progress update 4](https://reader034.vdocuments.us/reader034/viewer/2022052514/58f041921a28ab95578b4623/html5/thumbnails/8.jpg)
Progress Photos – Internal
Internal structural
builderswork ongoing
including installation of load
bearing lintels
![Page 9: ITS Building Project - progress update 4](https://reader034.vdocuments.us/reader034/viewer/2022052514/58f041921a28ab95578b4623/html5/thumbnails/9.jpg)
Progress Photos – Internal
Commenced infill of new
plasterboard ceilings to
rooms and corridors
throughout floors
![Page 10: ITS Building Project - progress update 4](https://reader034.vdocuments.us/reader034/viewer/2022052514/58f041921a28ab95578b4623/html5/thumbnails/10.jpg)
Next Few Weeks………..A look ahead to works commencing within the next 2 weeks :
- Complete excavations to new ground floor slab and pad foundations
- Complete concrete pours to perimeter retaining walls
- Commence ‘making good’ to walls within rooms of existing building
- Commence self level screeding and preparatory overboarding to existing sub-floors
- Continue internal builders work; including installing required lintels and steelwork
- Continue first fix mechanical and electrical works within existing building to all floors