ITER MACHINE ASSEMBLY TOOLS The ITER Organization has overall responsibility for the integration and assembly of components delivered to the ITER site by the seven ITER Members. In order to successfully pre-assemble and manoeuvre hundreds of large components, to very tight tolerances, a made-to-order set of 128 tools will be required. www.iter.org Sector Sub-Assembly tool: 22 m high, nearly 800 tonnes ASSEMBLY TOOL FACTS The In-Pit Assembly tool is made up of a central tower and a series of beams. This tool will support the vacuum vessel sub-assemblies (three groups of three sectors) and align them while the vacuum vessel is welded together. Two bridge cranes will work in tandem to lift and transport loads of up to 1,500 tonnes between the Assembly Building, where components are pre-assembled, and the Tokamak Pit. The Sector Sub-Assembly tool (seen in full, at left) will suspend the vacuum vessel sectors while carefully positioning and installing – via the rotary motion of the "wings" – the vacuum vessel thermal shielding and toroidal field coils. Two of these 800-tonne, 22-metre-tall tools will be positioned side-by-side during ITER assembly. custom-designed tools to assemble, lift and finally manoeuvre ITER's supersized components into place 128 of tolerance in the assembly of components that, in some cases, stand 20 metres tall and weigh hundreds of tonnes 2-3 mm estimated hours of labour to assemble the ITER machine over a four-year period 1.5 million

Upload: others

Post on 15-Oct-2021

7 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ITER MACHINE ASSEMBLY TOOLS

ITER MACHINEASSEMBLY TOOLS

The ITER Organization has overall responsibility for the integration and assembly of components deliveredto the ITER site by the seven ITER Members. In order to successfully pre-assemble and manoeuvre hundredsof large components, to very tight tolerances, a made-to-order set of 128 tools will be required.

w w w . i t e r . o r g

Sector Sub-Assembly tool: 22 m

high, nearly 800 tonnes

ASSEMBLY TOOL

FACTS

The In-Pit Assembly tool is made up of a central tower and a series of beams. This tool will support thevacuum vessel sub-assemblies (three groups of three sectors) and align them while the vacuum vessel iswelded together.

Two bridge cranes will work in tandem to lift and transport loads of up to 1,500 tonnes between theAssembly Building, where components are pre-assembled, and the Tokamak Pit.

The Sector Sub-Assembly tool (seen in full, at left) will suspend the vacuum vessel sectors while carefullypositioning and installing – via the rotary motion of the "wings" – the vacuum vessel thermal shieldingand toroidal field coils. Two of these 800-tonne, 22-metre-tall tools will be positioned side-by-side duringITER assembly. 

custom-designed tools to assemble, lift andfinally manoeuvre ITER's supersizedcomponents into place

128

of tolerance in the assembly of componentsthat, in some cases, stand 20 metres tall andweigh hundreds of tonnes

2-3 mm

estimated hours of labour to assemble theITER machine over a four-year period1.5 million