machine protection @ lhc jörg wenninger cern accelerators and beams department operations group...

56
Machine Protection @ LHC Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Upload: erick-morris

Post on 14-Jan-2016

224 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Machine Protection @ LHCMachine Protection @ LHC

Jörg Wenninger CERN Accelerators and Beams

Department Operations groupCERN-ITER meeting, Dec 2008

Page 2: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Introduction

215/12/2008 ITER-CERN WS - J. Wenninger

Page 3: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

LHC history

3

1982 : First studies for the LHC project

1983 : Z0/W discovered at SPS proton antiproton collider (SppbarS)

1989 : Start of LEP operation (Z boson-factory)

1994 : Approval of the LHC by the CERN Council

1996 : Final decision to start the LHC construction

1996 : LEP operation > 80 GeV (W boson -factory)

2000 : Last year of LEP operation above 100 GeV

2001 : Birth of the LHC Machine Protection WG

2002 : LEP equipment removed

2003 : Start of the LHC installation

2005 : Start of LHC hardware commissioning

2008 : LHC commissioning with beam

15/12/2008 ITER-CERN WS - J. Wenninger

Page 4: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

4

7 years of construction to replace :

LEP: 1989-2000

• e+e- collider• 4 experiments• max. energy 104 GeV • circumference 26.7 km

in the same tunnel by

LHC : 2008-2020+

• proton-proton & ion-ion collider in the LEP tunnel

• 4+ experiments• energy 7 TeV

ATLAS

CMS

LHCB

ALICE

15/12/2008 ITER-CERN WS - J. Wenninger

Page 5: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

5

Tunnel circumference 26.7 km, tunnel diameter 3.8 mDepth : ~ 70-140 m – tunnel is inclined by ~ 1.4%

Page 6: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

6

Top energy/GeV Circumference/m Linac 0.12 30PSB 1.4 157CPS 26 628 = 4 PSBSPS 450 6’911 = 11 x PSLHC 7000 26’657 = 27/7 x SPSLEIR

CPS

SPS

Booster

LINACS

LHC

3

45

6

7

8

1

2

Ions

protons

Beam 1

Beam 2

TI8

TI2

Note the energy gain/machine of 10 to 20 – and not more !The gain is typical for the useful range of magnets !!!

15/12/2008 ITER-CERN WS - J. Wenninger

Page 7: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

7

IR6: Beam dumping system

IR4: RF + Beam

instrumentation

IR5:CMS

IR1: ATLAS

IR8: LHC-BIR2:ALICE

Injection ring 2

Injection ring 1

IR3: Momentum collimation (normal

conducting magnets)

IR7: Betatron collimation

(normal conducting magnets)

Beam dump blocks

LHC Layout8 arcs. 8 long straight sections (insertions), ~ 700 m long.beam 1 : clockwisebeam 2 : counter-clockwiseThe beams exchange their positions (inside/outside) in 4 points to ensure that both rings have the same circumference !

The main dipole magnets define the geometry of

the circle !

15/12/2008

Page 8: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

The Challenge : stored energy

8

Increase with respect to existing accelerators :

•A factor 2 in magnetic field

•A factor 7 in beam energy

•A factor 200 in stored beam energy

15/12/2008

Page 9: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Dipole

9

7 TeV• 8.33 T• 11850 A• 7M J

Page 10: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Powering/circuit layout

10

Powering Sector

Sector 1

5

DC Power feed

3 DC Power

2

4 6

8

7LHC27 km Circumference

To limit the stored energy within one electrical circuit, the LHC is powered by sectors.

The main dipole circuits are split into 8 sectors to bring down the stored energy to ~1 GJ/sector.

Each main sector (~2.9 km) includes 154 dipole magnets (powered by a single power converter) and ~50 quadrupoles.

This also facilitates the commissioning that can be done sector by sector !

Page 11: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Quench protection - arcs

11

1. The quench is detected based on voltage measurements over the coils (U_mag_A, U_mag_B).

2. The energy is distributed over the entire magnet by force-quenching with quench heaters.

3. The power converter is switched off.

4. The current within the quenched magnet decays in < 200 ms, circuit current now flows through the ‚bypass‘ diode that can stand the current for 100-200 s.

5. The circuit current/energy is discharged into the dump resistors.

6. The beam is dumped.

>> 2-6 happen ‚in parallel‘

Page 12: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

12

Top energy/GeV Stored E/MJLinac 0.12PSB 1.4 ~0.005CPS 26 ~0.2SPS 450 3

LHC 7000 360LEIR

CPS

SPS

Booster

LINACS

LHC

3

45

6

7

8

1

2

Ions

protons

Beam 1

Beam 2

TI8

TI2

In RED : accelerators where machine protection due to beam is critical.

15/12/2008 ITER-CERN WS - J. Wenninger

Page 13: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

15/12/2008 ITER-CERN WS - J. Wenninger 13

The LBDSLHC Beam Dumping System

LBDS inventory

Extraction 15 Kicker Magnets + 15 generators

10 Septum Magnets + 1 power converter

Dilution 10 Kicker Magnets + 10 generators

Absorption One dump block

Electronics Beam energy measurement (BEM)

Beam energy tracking (BET)

Triggering and re-triggering

Post mortem diagnostics (check of every beam dump)

Beam line 975 m from extraction point to TDE

1) MKD

The 15 kicker magnets deflect the beam horizontally

4) MKB

The 10 kicker magnets dilute the beam energy

3) MSD

The 15 septum magnets deflect the beam vertically

5) TDE

The beam is absorbed in a graphite block

2) Q4

The quadrupole enhances the horizontal deflection

The beam sweep at the front face of the TDE absorber at 450 GeV

Page 14: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

The dump block

14

Approx. 8 m

concrete shielding

beam absorber (graphite)

This is the ONLY element in the LHC that can withstand the impact of the full beam !

The block is made of graphite (low Z material) to spread out the hadronic showers over a large volume.

It is actually necessary to paint the beam over the surface to keep the peak energy densities at a tolerable level !

Page 15: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

MPS mission

15/12/2008 ITER-CERN WS - J. Wenninger 15

The central mission of beam related machine protection at the LHC is to ensure that the beam is ALWAYS safely extracted to the dump block since there is no other element that can withstand the impact of the full LHC beam.

Page 16: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

16

0

2000

4000

6000

8000

10000

12000

-4000 -2000 0 2000 4000

time from start of injection (s)

dip

ole

cu

rre

nt (A

)

energy

ramp

preparation and access

beam dump

injection phase

coast

coast

LHC cycle

L.Bottura

450 GeV

7 TeV

start of the

ramp

15/12/2008 ITER-CERN WS - J. Wenninger

Page 17: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Machine protection organization

17

The machine protection issues that we are discussing here concern only protection of the accelerator from beam related damage.

Protection of the personnel and equipment protection against non-beam hazards are dealt elsewhere.

15/12/2008 ITER-CERN WS - J. Wenninger

Page 18: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

‘MPWG’ : Machine Protection Working Group

18

Machine Protection @ CERN concerns many different hardware systems Different CERN departments and groups responsible for the equipment

Up to 2000, no coordinated beam MP work, effort mostly concentrated on equipment ‘self-’protection. Quench protection for SC magnets …

In 2001 the MPWG was launched by R. Schmidt (J. Wenninger sc. secretary ) to ensure a coordinate MP effort. MPWG coordinates MP work, takes decisions (consensus) and, if needed,

resolves ‘conflicts’.

Individual equipment groups remain responsible of their equipment etc.

15/12/2008 ITER-CERN WS - J. Wenninger

Page 19: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

MPWG activities and evolution

19

Reviews and external audits, initiated or encouraged by MPWG, are used to obtain external advice General review LHC Machine Protection System Audit of Beam Interlock System Audit of Beam Dumping System Audit of Beam Loss Monitoring System

Sub-working groups were launched as appropriate. Reliability studies sub-WG. Commissioning sub-WG.

Following the LHC startup with beam in 2008, the MPWG has been transformed and exists now as Machine Protection Panel (‘MPP’) with a reduced number of members. Follow up of MP issues at ‘running’ LHC. Defines limits for safe operation.

15/12/2008 ITER-CERN WS - J. Wenninger

Page 20: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

20

MPS requirements Safety Assessment (‘reliability’)

– IEC 61508 standard defining the different Safety Integrity Levels (SIL) ranking from SIL1 to SIL4

– Based on Risk Classes = Consequence x Frequency– Machine Protection System for the LHC should be SIL3, taking definition

of Protection Systems, with a probability of failure between 10-8 and 10-7

per hour (because of short mission times)• Catastrophy = beam should have been dumped and this did not

take place; can possibly cause large damage Availability

– Definition:• Beam is dumped when it was not required• Operation can not take place because the protection system does

not give the green light (is not ready)– Requirement:

• Downtime comparable to other accelerator equipment; maximum tens of operations per year

15/12/2008 ITER-CERN WS - J. Wenninger

Page 21: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

21

Dual approach

Prevent faults at the source. Equipment ‘design’ – reliability. Fast internal failure detection.

Detect the effect resulting from any fault, including beam instabilities, and react fast enough to prevent damage. Simulation of failures. Knowledge of damage levels.

15/12/2008 ITER-CERN WS - J. Wenninger

Page 22: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Failure studies

2215/12/2008 ITER-CERN WS - J. Wenninger

Page 23: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Failure categories

23

Beam loss over multiple turns due to many types of failures.

Fastest failures >= ~ 10-ish turns

Passive protection - Failure prevention (high reliability systems).- Intercept beam with collimators and absorber

blocks.

Active protection systems have no time to react !

Active Protection- Failure detection (by beam and/or equipment

monitoring) with fast reaction time (< 1 ms).- Fire beam dumping system

Beam loss over a single turn during injection, beam dump or any other fast ‘kick’.

In the event a failure or unacceptable beam lifetime, the beam must be dumped immediately and safely into the beam dump

block.

Two main classes for failures (with more subtle sub-classes):

15/12/2008 ITER-CERN WS - J. Wenninger

Page 24: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Failure categories

2415/12/2008 ITER-CERN WS - J. Wenninger

Page 25: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Collimation system

25

A multi-stage halo cleaning (collimation) system has been designed to protect the LHC magnets from beam induced quenches.

Halo particles are first scattered by the primary collimator (closest to the beam). The scattered particles (forming the secondary halo) are absorbed by the secondary collimators, or scattered to form the tertiary halo.

More than 100 collimators jaws are needed for the nominal LHC beam.Primary and secondary collimators are made of Carbon to survive severe beam impacts !

the collimators have a key role for protection as they define the aperture : in (almost) all failure cases the beam will touch collimators first !!

Primary collimator

Secondary collimators Absorbers

Protectiondevices

Tertiarycollimators

Tripletmagnets

Experiment

Beam

Primaryhalo particle Secondary halo

Tertiary halo

+ hadronic showers

hadronic showers

ITER-CERN WS - J. Wenninger

Page 26: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Collimator settings at 7 TeV

26

1 mm

Opening ~3-5 mm

The collimator opening corresponds roughly to the size of Spain !

For colliders like HERA, TEVATRON, RHIC, LEP collimators are/were used to reduce backgrounds in the experiments ! But the machines can/could actually operate without collimators !

At the LHC collimators are essential for machine operation as soon as we have more than a few % of the nominal beam intensity !

ITER-CERN WS - J. Wenninger

Page 27: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Collimator robustness

27

Around ~2001 when the MPWG started its work, the LHC collimation system consisted of Copper collimators :

Excellent for beam stability (low resistivity) Good for collimation itself (density). A single mis-injection would have damaged the collimators !!!

>> Failures were not considered in the design !!!!

A review of the collimation system requirements indicated that a major re-design was needed !!

Collimation project & collimation WG were launched. Work in close collaboration with MPWG.

Robust collimator design based on Carbon collimators – ‘phase 1’. The phase 1 collimator will not allow nominal beams due to beam

instability issues (Carbon resistivity).

>> Phase 2 collimator design in progress.

15/12/2008 ITER-CERN WS - J. Wenninger

Page 28: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Damage levels

2815/12/2008 ITER-CERN WS - J. Wenninger

Page 29: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Beam induced damage test

29

25 cm

>> organized a controlled beam experiment: Special target (sandwich of Tin, Steel, Copper plates) installed in an SPS

transfer line. Impact of 450 GeV LHC beam (beam size σx/y ~ 1 mm)

Beam

The effect of a high intensity beam impacting on equipment is not so easy to evaluate, in particular when you are looking for damage :

heating, melting, vaporization …>> very little experimental data available !

15/12/2008

Page 30: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Damage potential of high energy beams

30

A B D C

Shot Intensity / p+

A 1.2×1012

B 2.4×1012

C 4.8×1012

D 7.2×1012

Controlled experiment with 450 GeV beam to benchmark simulations:

• Melting point of Copper is reached for an impact of 2.5×1012 p, damage at 5×1012 p.

• Stainless steel is not damaged with 7×1012 p.

• Results agree with simulation.

Effect of beam impact depends strongly on impact angles, beam size…

Based on those results LHC has a limit for safe beam at 450 GeV of

1012 protons ~ 0.3% of the total intensity ~ 0.1 MJ

Scaling the results (beam size reduction etc) yields a limit @ 7 TeV of

1010 protons ~ 0.003% of the total intensity ~ 0.02 MJ

15/12/2008 ITER-CERN WS - J. Wenninger

Page 31: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

When the MPS is not fast enough…

15/12/2008 ITER-CERN WS - J. Wenninger 31

• At the SPS the MPS was been ‘assembled’ in stages over the years, but not following a proper failure analysis.

• As a consequence the MPS cannot cope with every situation! It is now also covered by the MPWG but would require new resources…

• Here an example from …. 2008 ! The effect of an impact on the vacuum chamber of a 400 GeV beam of 3x1013 p (2 MJ).

• Vacuum chamber to atmospheric pressure, Downtime ~ 3 days.

Page 32: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Full LHC beam deflected into copper target

32

Target length [cm]

vaporisation

melting

Copper target

2 m

Energy density [GeV/cm3] on target axis

2808 bunches

The beam will drill a hole along the target axis !!

15/12/2008 ITER-CERN WS - J. Wenninger

Page 33: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Beams and damage

15/12/2008 ITER-CERN WS - J. Wenninger 33

Beam type No. protons

Safe @ 450 GeV

Safe @ 7 TeV

Comment

Probe bunch 2x109 YES !! ‘YES’

Nominal bunch 1x1011 YES NO Safe for collimators

Nominal injection (288 bunches)

3x1013 NO NO Safe for collimators at 450 GeV(*)

Full beam 4x1014 NO NO

At injection commissioning can be done safely with one bunch.

At 7 TeV even the smallest bunch is just about safe.

(*) : also tested with 450 GeV beams (same time as damage test). Note that a first test resulted in mechanical deformations that led to an improved design (that was retested with beam).

Page 34: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Lessons from the 19th September incident

15/12/2008 ITER-CERN WS - J. Wenninger 34

An severe incident occurred on 19th September during the last powering tests of one LHC sector (sector 34):

At 8.7kA a resistive zone developed in the dipole bus bar between dipoles.Most likely an electrical arc developed which punctured the helium enclosure.

Large amounts of Helium were released into the insulating vacuum.Rapid pressure rise inside the LHC magnets

– Large pressure wave travelled along the accelerator both ways.– Self actuating relief valves opened but could not handle all.– Large forces exerted on the vacuum barriers located every 2 cells.– These forces displaced several quadrupoles by up to ~50 cm.– Connections to the cryogenic line damaged in some places.– Beam ‘vacuum’ to atmospheric pressure

>> Repair of ~ 50 magnets.

>> Indicates that the collateral damage due to beam impact can be much more severe that anticipated consolidation under way !

Page 35: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Failure studies

3515/12/2008 ITER-CERN WS - J. Wenninger

Page 36: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Simulations

3615/12/2008 ITER-CERN WS - J. Wenninger

Many failures simulations were performed under the guidance of MPWG members.

They resulted in : Correct requirements for protection systems. Design changes and new developments.

Typical example :

Current decay curves of power converters are used to asses criticality of magnetic circuits.

PHD - A. Gomez

Page 37: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Simulation result examples

37

The evolution of the beam parameters, here beam orbit, is used to evaluate REACTION times for internal interlocks and for beam diagnostic systems (beam loss monitors).

Orbit along the ring Orbit around collimators

Collimator jaw

PHD - A. Gomez

Page 38: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Simulation result example

38

Using a certain transverse beam distributions (usually nominal size with Gaussian shape) it is possible to reconstruct the beam lost at various locations versus time to evaluate REACTION times for internal interlocks and for beam diagnostic systems (beam loss monitors).

PHD - A. Gomez

Page 39: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Failure studies outcome

3915/12/2008 ITER-CERN WS - J. Wenninger

Page 40: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Beam loss monitors

40

Ionization chambers to detect beam losses:– N2 gas filling at 100 mbar over-pressure, voltage 1.5 kV

– Sensitive volume 1.5 lRequirements (backed by simulations) :

– Very fast reaction time ~ ½ turn (40 s)– Very large dynamic range (> 106)

There are ~3600 chambers distributed over the ring to detect abnormal beam losses and if necessary trigger a beam abort !

Page 41: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

FMCMs

41

BIS interface

resistivemagnet

Fast Magnet CurrentchangeMonitor

Power Converter

VIP

C6

26

VMECrate

CP

U +

CTR

P (

or

TG

8)

Voltage Divider& Isolation Amplifier

RS422 link

Page 42: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

FMCM Test Example

42

Transfer line dipole PC:

>> Steep step programmed into the PC reference to simulate failure

FMCM interlock trigger time:I < 0.1 AI/I < 0.01% - specification : 0.1%

Zoom around step time

15/12/2008 ITER-CERN WS - J. Wenninger

Page 43: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Beam Interlock System

4315/12/2008 ITER-CERN WS - J. Wenninger

Page 44: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Interlock System Overview

44

Beam Interlock System

Beam Dumping System

Injection BIS

PIC essential+ auxiliary

circuitsWIC

QPS(several 1000)

Power Converters

~1500

AUG

UPS

Power Converters

Magnets

FMCM

CryoOK

RFSystem

Movable Devices

Experiments

BCMBeam Loss

Experimental Magnets

CollimationSystem

CollimatorPositions

Environmentalparameters

Transverse Feedback

Beam Aperture Kickers

FBCMLifetime

BTV

BTV screens Mirrors

Access System

Doors EIS

VacuumSystem

Vacuumvalves

AccessSafetyBlocks

RF Stoppers

BLM BPM in

IR6

Monitorsaperture

limits(some 100)

Monitors in arcs

(several 1000)

Timing System (Post Mortem)

CCC Operator Buttons

SafeMach.Param.

SoftwareInterlocks

LHCDevices

SEQ

LHCDevices

LHCDevices

Tim

ing

SafeBeamFlag

Over 10’000 signals enter the interlock system of the LHC !!

15/12/2008 ITER-CERN WS - J. Wenninger

Page 45: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

45

Beam Interlock SystemBeam Interlock System

BIS Dump KickerBeam ‘Permit’

User permitsignals

Actors and signal exchange for the beam interlock system:

• ‘User systems’ : systems that survey equipment or beam parameters and that are able to detect failures and send a HW signal to the beam interlock system.

• Each user system provides a HW status signal, the user permit signal.

• The beam interlock system combines the user permits and produces the beam permit.

• The beam permit is a HW signal that is provided to the dump kicker (also injection or extraction kickers) : absence of beam permit dump triggered !

Hardware links and systems

15/12/2008 ITER-CERN WS - J. Wenninger

Page 46: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Beam Interlock System

46

User Interfaces

UserPermit

#1

#14

#2

Beam Interlock Controller

copper cables

User System #1

User System #2

User System #14

frontrear

Beam

Permit

Loops

(F.O.)

Unique Hw solution for connecting any user system (= interlock) via a copper cable. Fiber optic variant for long links (>1.2km)

BIC (Beam Interlock Controller) boards embedded in VME chassis.

Beam Permit Loops with Frequency signals connect the BICs with the corresponding kicker

system (extraction, injection, dump).

In operation at the SPS and the SPS/LHC transfer lines since 2006.

Inputs are: maskable (with safe beam)unmaskable

Page 47: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Architecture of the LHC BEAM INTERLOCK SYSTEM

Beam-1 / Beam-2 are Independent!

- fast reaction time (~ s)- safe- limited no. of inputs- Some inputs maskable for safe beam intensity

Up to 20 Users per BIC system:

6 x Beam-18 x Both-Beam

6 x Beam-2

Connected to injection IR2/IR8:-In case of an interlock (=NO beam permit),

the beam is dumped & injection is inhibited.

- It is not possible to inhibit injection

ALONE.

47

Page 48: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

48

BIS Reaction TimesBIS Reaction Times

UserSystemprocess

a failure has been detected… beam dump

request

Beam Dumping System waiting for beam gap

89μs max

Signalssend

to LBDS

t2 t3

Beam Interlocksystemprocess

~70μs max.

t1

> 10μs

USER_PERMIT signal changesfrom TRUE to FALSE

Kicker fired

t4

all bunches have been extracted

~ 89μs

Achievable response time ranges between 100 s and 270 s

(between the detection of a dump request and the completion of a beam dump)

15/12/2008 ITER-CERN WS - J. Wenninger

Page 49: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

In action…

4915/12/2008 ITER-CERN WS - J. Wenninger

Page 50: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

First Emergency Dump

50

First “Emergency Dump” on Thurs 11th at 22:45:08

On 11th September 2008 during operation with circulating beam. At 22:45:08, beam 2 was dumped by the LBDS triggered by the BIS. The dump was caused by a water fault in the DC cables in the main quadrupole

circuit in LHC sector 81. This event allowed to address the performance of the interlock / machine

protection systems at a very early state, as well as to understand the functionality of the post mortem (transient data) recording

15/12/2008 ITER-CERN WS - J. Wenninger

Page 51: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

First Dump

51

11 Sep 2008 22:45:08 (561437)11 Sep 2008 22:45:08 (561437)

11 Sep 2008 22:45:08 (561617)11 Sep 2008 22:45:08 (561484)

Data from Beam Interlock System

Beam Interlock Controller at IP8received dump request at 561.437 ms

Beam Interlock Controller at IP6received dump request- 50 s later (anti clockwise signal) - 180 s later (clockwise signal)

Beam Dump 561.523 ms

Page 52: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Post-mortem System

15/12/2008 ITER-CERN WS - J. Wenninger 52

As indicated on the previous slide the Post-mortem data is very important.

The diagnostics of failures is essential to: Understand what happened. Assess the performance / correct functioning of the MPS. For critical systems like beam dumping system, the PM analysis is

MANDATORY to ensure that the system is ‘as good as new’. At the LHC all equipment systems provide post-mortem data:

Circular buffers that are frozen on fault/beam abort. Accurate timestamps, down to s for fast systems. Data relevant for understanding of failures. Buffer depth and granularity dependent on system. Typical for beam

diagnostics is turn by turn (sometimes bunch by bunch).

>> ‘Expected’ data volume for LHC : 2-5 GBytes

Page 53: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Software interlocking

15/12/2008 ITER-CERN WS - J. Wenninger 53

In very large accelerators it is not always possible to cover all failure mechanisms with a hardware system: needs something more flexible.

Example : At the LHC the integrated bending field of horizontal steering magnets may bias the beam energy and cause problems

during beam aborts.

Provide flexibility to quickly add new interlocks (provided they are not too time critical).

Need to survey the integrity of the settings even with a MCS system:

Comparison of data and digital signatures between front end computers and DB.

>> Software Interlock System to survey the control system components relevant for machine protection as additional protection layer, with possibility to abort beam if necessary.

Page 54: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

MPS settings control

15/12/2008 ITER-CERN WS - J. Wenninger 54

A Critical Settings Management (MCS) system has been developed for the LHC (and for CERN in general) to be able to control MPS settings (for example Beam loss monitor thresholds…) through the central controls database without loss of security.

MCS provides:

Critical settings that can only be changed by authorized groups of persons.

Parameters are visible to everyone that has access to the control system.

Authentication and Authorization of the user.

Verification that values of critical parameters have not changed since the authorized person has updated them:

Data transfer errors. ‘Hacking’. Data corruption – radiation, data loss during reboots…

Page 55: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Critical settings control

15/12/2008 ITER-CERN WS - J. Wenninger 55

Based on the concept of public & private key.

User logs in. The critical data receives a digital signature. Data and digital signature are:

• Send to the front-end system which verifies the data validity.

• Stored together in the DB - avoid direct DB access, reference for checks.

Page 56: Machine Protection @ LHC Jörg Wenninger CERN Accelerators and Beams Department Operations group CERN-ITER meeting, Dec 2008

Documentation

15/12/2008 ITER-CERN WS - J. Wenninger 56

All presentations, minutes of meetings etc are accessible from the machine protection web site :

http://lhc-mpwg.web.cern.ch/lhc-mpwg/

which is however only accessible from INSIDE CERN. MP commissioning documents for SPS and LHC are on 2 other

sites:

https://sps-mp-operation.web.cern.ch/sps-mp-operation/

https://lhc-mp-operation.web.cern.ch/lhc-mp-operation/