machine protection @ lhc jörg wenninger cern accelerators and beams department operations group...
TRANSCRIPT
Machine Protection @ LHCMachine Protection @ LHC
Jörg Wenninger CERN Accelerators and Beams
Department Operations groupCERN-ITER meeting, Dec 2008
Introduction
215/12/2008 ITER-CERN WS - J. Wenninger
LHC history
3
1982 : First studies for the LHC project
1983 : Z0/W discovered at SPS proton antiproton collider (SppbarS)
1989 : Start of LEP operation (Z boson-factory)
1994 : Approval of the LHC by the CERN Council
1996 : Final decision to start the LHC construction
1996 : LEP operation > 80 GeV (W boson -factory)
2000 : Last year of LEP operation above 100 GeV
2001 : Birth of the LHC Machine Protection WG
2002 : LEP equipment removed
2003 : Start of the LHC installation
2005 : Start of LHC hardware commissioning
2008 : LHC commissioning with beam
15/12/2008 ITER-CERN WS - J. Wenninger
4
7 years of construction to replace :
LEP: 1989-2000
• e+e- collider• 4 experiments• max. energy 104 GeV • circumference 26.7 km
in the same tunnel by
LHC : 2008-2020+
• proton-proton & ion-ion collider in the LEP tunnel
• 4+ experiments• energy 7 TeV
ATLAS
CMS
LHCB
ALICE
15/12/2008 ITER-CERN WS - J. Wenninger
5
Tunnel circumference 26.7 km, tunnel diameter 3.8 mDepth : ~ 70-140 m – tunnel is inclined by ~ 1.4%
6
Top energy/GeV Circumference/m Linac 0.12 30PSB 1.4 157CPS 26 628 = 4 PSBSPS 450 6’911 = 11 x PSLHC 7000 26’657 = 27/7 x SPSLEIR
CPS
SPS
Booster
LINACS
LHC
3
45
6
7
8
1
2
Ions
protons
Beam 1
Beam 2
TI8
TI2
Note the energy gain/machine of 10 to 20 – and not more !The gain is typical for the useful range of magnets !!!
15/12/2008 ITER-CERN WS - J. Wenninger
7
IR6: Beam dumping system
IR4: RF + Beam
instrumentation
IR5:CMS
IR1: ATLAS
IR8: LHC-BIR2:ALICE
Injection ring 2
Injection ring 1
IR3: Momentum collimation (normal
conducting magnets)
IR7: Betatron collimation
(normal conducting magnets)
Beam dump blocks
LHC Layout8 arcs. 8 long straight sections (insertions), ~ 700 m long.beam 1 : clockwisebeam 2 : counter-clockwiseThe beams exchange their positions (inside/outside) in 4 points to ensure that both rings have the same circumference !
The main dipole magnets define the geometry of
the circle !
15/12/2008
The Challenge : stored energy
8
Increase with respect to existing accelerators :
•A factor 2 in magnetic field
•A factor 7 in beam energy
•A factor 200 in stored beam energy
15/12/2008
Dipole
9
7 TeV• 8.33 T• 11850 A• 7M J
Powering/circuit layout
10
Powering Sector
Sector 1
5
DC Power feed
3 DC Power
2
4 6
8
7LHC27 km Circumference
To limit the stored energy within one electrical circuit, the LHC is powered by sectors.
The main dipole circuits are split into 8 sectors to bring down the stored energy to ~1 GJ/sector.
Each main sector (~2.9 km) includes 154 dipole magnets (powered by a single power converter) and ~50 quadrupoles.
This also facilitates the commissioning that can be done sector by sector !
Quench protection - arcs
11
1. The quench is detected based on voltage measurements over the coils (U_mag_A, U_mag_B).
2. The energy is distributed over the entire magnet by force-quenching with quench heaters.
3. The power converter is switched off.
4. The current within the quenched magnet decays in < 200 ms, circuit current now flows through the ‚bypass‘ diode that can stand the current for 100-200 s.
5. The circuit current/energy is discharged into the dump resistors.
6. The beam is dumped.
>> 2-6 happen ‚in parallel‘
12
Top energy/GeV Stored E/MJLinac 0.12PSB 1.4 ~0.005CPS 26 ~0.2SPS 450 3
LHC 7000 360LEIR
CPS
SPS
Booster
LINACS
LHC
3
45
6
7
8
1
2
Ions
protons
Beam 1
Beam 2
TI8
TI2
In RED : accelerators where machine protection due to beam is critical.
15/12/2008 ITER-CERN WS - J. Wenninger
15/12/2008 ITER-CERN WS - J. Wenninger 13
The LBDSLHC Beam Dumping System
LBDS inventory
Extraction 15 Kicker Magnets + 15 generators
10 Septum Magnets + 1 power converter
Dilution 10 Kicker Magnets + 10 generators
Absorption One dump block
Electronics Beam energy measurement (BEM)
Beam energy tracking (BET)
Triggering and re-triggering
Post mortem diagnostics (check of every beam dump)
Beam line 975 m from extraction point to TDE
1) MKD
The 15 kicker magnets deflect the beam horizontally
4) MKB
The 10 kicker magnets dilute the beam energy
3) MSD
The 15 septum magnets deflect the beam vertically
5) TDE
The beam is absorbed in a graphite block
2) Q4
The quadrupole enhances the horizontal deflection
The beam sweep at the front face of the TDE absorber at 450 GeV
The dump block
14
Approx. 8 m
concrete shielding
beam absorber (graphite)
This is the ONLY element in the LHC that can withstand the impact of the full beam !
The block is made of graphite (low Z material) to spread out the hadronic showers over a large volume.
It is actually necessary to paint the beam over the surface to keep the peak energy densities at a tolerable level !
MPS mission
15/12/2008 ITER-CERN WS - J. Wenninger 15
The central mission of beam related machine protection at the LHC is to ensure that the beam is ALWAYS safely extracted to the dump block since there is no other element that can withstand the impact of the full LHC beam.
16
0
2000
4000
6000
8000
10000
12000
-4000 -2000 0 2000 4000
time from start of injection (s)
dip
ole
cu
rre
nt (A
)
energy
ramp
preparation and access
beam dump
injection phase
coast
coast
LHC cycle
L.Bottura
450 GeV
7 TeV
start of the
ramp
15/12/2008 ITER-CERN WS - J. Wenninger
Machine protection organization
17
The machine protection issues that we are discussing here concern only protection of the accelerator from beam related damage.
Protection of the personnel and equipment protection against non-beam hazards are dealt elsewhere.
15/12/2008 ITER-CERN WS - J. Wenninger
‘MPWG’ : Machine Protection Working Group
18
Machine Protection @ CERN concerns many different hardware systems Different CERN departments and groups responsible for the equipment
Up to 2000, no coordinated beam MP work, effort mostly concentrated on equipment ‘self-’protection. Quench protection for SC magnets …
In 2001 the MPWG was launched by R. Schmidt (J. Wenninger sc. secretary ) to ensure a coordinate MP effort. MPWG coordinates MP work, takes decisions (consensus) and, if needed,
resolves ‘conflicts’.
Individual equipment groups remain responsible of their equipment etc.
15/12/2008 ITER-CERN WS - J. Wenninger
MPWG activities and evolution
19
Reviews and external audits, initiated or encouraged by MPWG, are used to obtain external advice General review LHC Machine Protection System Audit of Beam Interlock System Audit of Beam Dumping System Audit of Beam Loss Monitoring System
Sub-working groups were launched as appropriate. Reliability studies sub-WG. Commissioning sub-WG.
Following the LHC startup with beam in 2008, the MPWG has been transformed and exists now as Machine Protection Panel (‘MPP’) with a reduced number of members. Follow up of MP issues at ‘running’ LHC. Defines limits for safe operation.
15/12/2008 ITER-CERN WS - J. Wenninger
20
MPS requirements Safety Assessment (‘reliability’)
– IEC 61508 standard defining the different Safety Integrity Levels (SIL) ranking from SIL1 to SIL4
– Based on Risk Classes = Consequence x Frequency– Machine Protection System for the LHC should be SIL3, taking definition
of Protection Systems, with a probability of failure between 10-8 and 10-7
per hour (because of short mission times)• Catastrophy = beam should have been dumped and this did not
take place; can possibly cause large damage Availability
– Definition:• Beam is dumped when it was not required• Operation can not take place because the protection system does
not give the green light (is not ready)– Requirement:
• Downtime comparable to other accelerator equipment; maximum tens of operations per year
15/12/2008 ITER-CERN WS - J. Wenninger
21
Dual approach
Prevent faults at the source. Equipment ‘design’ – reliability. Fast internal failure detection.
Detect the effect resulting from any fault, including beam instabilities, and react fast enough to prevent damage. Simulation of failures. Knowledge of damage levels.
15/12/2008 ITER-CERN WS - J. Wenninger
Failure studies
2215/12/2008 ITER-CERN WS - J. Wenninger
Failure categories
23
Beam loss over multiple turns due to many types of failures.
Fastest failures >= ~ 10-ish turns
Passive protection - Failure prevention (high reliability systems).- Intercept beam with collimators and absorber
blocks.
Active protection systems have no time to react !
Active Protection- Failure detection (by beam and/or equipment
monitoring) with fast reaction time (< 1 ms).- Fire beam dumping system
Beam loss over a single turn during injection, beam dump or any other fast ‘kick’.
In the event a failure or unacceptable beam lifetime, the beam must be dumped immediately and safely into the beam dump
block.
Two main classes for failures (with more subtle sub-classes):
15/12/2008 ITER-CERN WS - J. Wenninger
Failure categories
2415/12/2008 ITER-CERN WS - J. Wenninger
Collimation system
25
A multi-stage halo cleaning (collimation) system has been designed to protect the LHC magnets from beam induced quenches.
Halo particles are first scattered by the primary collimator (closest to the beam). The scattered particles (forming the secondary halo) are absorbed by the secondary collimators, or scattered to form the tertiary halo.
More than 100 collimators jaws are needed for the nominal LHC beam.Primary and secondary collimators are made of Carbon to survive severe beam impacts !
the collimators have a key role for protection as they define the aperture : in (almost) all failure cases the beam will touch collimators first !!
Primary collimator
Secondary collimators Absorbers
Protectiondevices
Tertiarycollimators
Tripletmagnets
Experiment
Beam
Primaryhalo particle Secondary halo
Tertiary halo
+ hadronic showers
hadronic showers
ITER-CERN WS - J. Wenninger
Collimator settings at 7 TeV
26
1 mm
Opening ~3-5 mm
The collimator opening corresponds roughly to the size of Spain !
For colliders like HERA, TEVATRON, RHIC, LEP collimators are/were used to reduce backgrounds in the experiments ! But the machines can/could actually operate without collimators !
At the LHC collimators are essential for machine operation as soon as we have more than a few % of the nominal beam intensity !
ITER-CERN WS - J. Wenninger
Collimator robustness
27
Around ~2001 when the MPWG started its work, the LHC collimation system consisted of Copper collimators :
Excellent for beam stability (low resistivity) Good for collimation itself (density). A single mis-injection would have damaged the collimators !!!
>> Failures were not considered in the design !!!!
A review of the collimation system requirements indicated that a major re-design was needed !!
Collimation project & collimation WG were launched. Work in close collaboration with MPWG.
Robust collimator design based on Carbon collimators – ‘phase 1’. The phase 1 collimator will not allow nominal beams due to beam
instability issues (Carbon resistivity).
>> Phase 2 collimator design in progress.
15/12/2008 ITER-CERN WS - J. Wenninger
Damage levels
2815/12/2008 ITER-CERN WS - J. Wenninger
Beam induced damage test
29
25 cm
>> organized a controlled beam experiment: Special target (sandwich of Tin, Steel, Copper plates) installed in an SPS
transfer line. Impact of 450 GeV LHC beam (beam size σx/y ~ 1 mm)
Beam
The effect of a high intensity beam impacting on equipment is not so easy to evaluate, in particular when you are looking for damage :
heating, melting, vaporization …>> very little experimental data available !
15/12/2008
Damage potential of high energy beams
30
A B D C
Shot Intensity / p+
A 1.2×1012
B 2.4×1012
C 4.8×1012
D 7.2×1012
Controlled experiment with 450 GeV beam to benchmark simulations:
• Melting point of Copper is reached for an impact of 2.5×1012 p, damage at 5×1012 p.
• Stainless steel is not damaged with 7×1012 p.
• Results agree with simulation.
Effect of beam impact depends strongly on impact angles, beam size…
Based on those results LHC has a limit for safe beam at 450 GeV of
1012 protons ~ 0.3% of the total intensity ~ 0.1 MJ
Scaling the results (beam size reduction etc) yields a limit @ 7 TeV of
1010 protons ~ 0.003% of the total intensity ~ 0.02 MJ
15/12/2008 ITER-CERN WS - J. Wenninger
When the MPS is not fast enough…
15/12/2008 ITER-CERN WS - J. Wenninger 31
• At the SPS the MPS was been ‘assembled’ in stages over the years, but not following a proper failure analysis.
• As a consequence the MPS cannot cope with every situation! It is now also covered by the MPWG but would require new resources…
• Here an example from …. 2008 ! The effect of an impact on the vacuum chamber of a 400 GeV beam of 3x1013 p (2 MJ).
• Vacuum chamber to atmospheric pressure, Downtime ~ 3 days.
Full LHC beam deflected into copper target
32
Target length [cm]
vaporisation
melting
Copper target
2 m
Energy density [GeV/cm3] on target axis
2808 bunches
The beam will drill a hole along the target axis !!
15/12/2008 ITER-CERN WS - J. Wenninger
Beams and damage
15/12/2008 ITER-CERN WS - J. Wenninger 33
Beam type No. protons
Safe @ 450 GeV
Safe @ 7 TeV
Comment
Probe bunch 2x109 YES !! ‘YES’
Nominal bunch 1x1011 YES NO Safe for collimators
Nominal injection (288 bunches)
3x1013 NO NO Safe for collimators at 450 GeV(*)
Full beam 4x1014 NO NO
At injection commissioning can be done safely with one bunch.
At 7 TeV even the smallest bunch is just about safe.
(*) : also tested with 450 GeV beams (same time as damage test). Note that a first test resulted in mechanical deformations that led to an improved design (that was retested with beam).
Lessons from the 19th September incident
15/12/2008 ITER-CERN WS - J. Wenninger 34
An severe incident occurred on 19th September during the last powering tests of one LHC sector (sector 34):
At 8.7kA a resistive zone developed in the dipole bus bar between dipoles.Most likely an electrical arc developed which punctured the helium enclosure.
Large amounts of Helium were released into the insulating vacuum.Rapid pressure rise inside the LHC magnets
– Large pressure wave travelled along the accelerator both ways.– Self actuating relief valves opened but could not handle all.– Large forces exerted on the vacuum barriers located every 2 cells.– These forces displaced several quadrupoles by up to ~50 cm.– Connections to the cryogenic line damaged in some places.– Beam ‘vacuum’ to atmospheric pressure
>> Repair of ~ 50 magnets.
>> Indicates that the collateral damage due to beam impact can be much more severe that anticipated consolidation under way !
Failure studies
3515/12/2008 ITER-CERN WS - J. Wenninger
Simulations
3615/12/2008 ITER-CERN WS - J. Wenninger
Many failures simulations were performed under the guidance of MPWG members.
They resulted in : Correct requirements for protection systems. Design changes and new developments.
Typical example :
Current decay curves of power converters are used to asses criticality of magnetic circuits.
PHD - A. Gomez
Simulation result examples
37
The evolution of the beam parameters, here beam orbit, is used to evaluate REACTION times for internal interlocks and for beam diagnostic systems (beam loss monitors).
Orbit along the ring Orbit around collimators
Collimator jaw
PHD - A. Gomez
Simulation result example
38
Using a certain transverse beam distributions (usually nominal size with Gaussian shape) it is possible to reconstruct the beam lost at various locations versus time to evaluate REACTION times for internal interlocks and for beam diagnostic systems (beam loss monitors).
PHD - A. Gomez
Failure studies outcome
3915/12/2008 ITER-CERN WS - J. Wenninger
Beam loss monitors
40
Ionization chambers to detect beam losses:– N2 gas filling at 100 mbar over-pressure, voltage 1.5 kV
– Sensitive volume 1.5 lRequirements (backed by simulations) :
– Very fast reaction time ~ ½ turn (40 s)– Very large dynamic range (> 106)
There are ~3600 chambers distributed over the ring to detect abnormal beam losses and if necessary trigger a beam abort !
FMCMs
41
BIS interface
resistivemagnet
Fast Magnet CurrentchangeMonitor
Power Converter
VIP
C6
26
VMECrate
CP
U +
CTR
P (
or
TG
8)
Voltage Divider& Isolation Amplifier
RS422 link
FMCM Test Example
42
Transfer line dipole PC:
>> Steep step programmed into the PC reference to simulate failure
FMCM interlock trigger time:I < 0.1 AI/I < 0.01% - specification : 0.1%
Zoom around step time
15/12/2008 ITER-CERN WS - J. Wenninger
Beam Interlock System
4315/12/2008 ITER-CERN WS - J. Wenninger
Interlock System Overview
44
Beam Interlock System
Beam Dumping System
Injection BIS
PIC essential+ auxiliary
circuitsWIC
QPS(several 1000)
Power Converters
~1500
AUG
UPS
Power Converters
Magnets
FMCM
CryoOK
RFSystem
Movable Devices
Experiments
BCMBeam Loss
Experimental Magnets
CollimationSystem
CollimatorPositions
Environmentalparameters
Transverse Feedback
Beam Aperture Kickers
FBCMLifetime
BTV
BTV screens Mirrors
Access System
Doors EIS
VacuumSystem
Vacuumvalves
AccessSafetyBlocks
RF Stoppers
BLM BPM in
IR6
Monitorsaperture
limits(some 100)
Monitors in arcs
(several 1000)
Timing System (Post Mortem)
CCC Operator Buttons
SafeMach.Param.
SoftwareInterlocks
LHCDevices
SEQ
LHCDevices
LHCDevices
Tim
ing
SafeBeamFlag
Over 10’000 signals enter the interlock system of the LHC !!
15/12/2008 ITER-CERN WS - J. Wenninger
45
Beam Interlock SystemBeam Interlock System
BIS Dump KickerBeam ‘Permit’
User permitsignals
Actors and signal exchange for the beam interlock system:
• ‘User systems’ : systems that survey equipment or beam parameters and that are able to detect failures and send a HW signal to the beam interlock system.
• Each user system provides a HW status signal, the user permit signal.
• The beam interlock system combines the user permits and produces the beam permit.
• The beam permit is a HW signal that is provided to the dump kicker (also injection or extraction kickers) : absence of beam permit dump triggered !
Hardware links and systems
15/12/2008 ITER-CERN WS - J. Wenninger
Beam Interlock System
46
User Interfaces
UserPermit
#1
#14
#2
Beam Interlock Controller
copper cables
User System #1
User System #2
User System #14
frontrear
Beam
Permit
Loops
(F.O.)
Unique Hw solution for connecting any user system (= interlock) via a copper cable. Fiber optic variant for long links (>1.2km)
BIC (Beam Interlock Controller) boards embedded in VME chassis.
Beam Permit Loops with Frequency signals connect the BICs with the corresponding kicker
system (extraction, injection, dump).
In operation at the SPS and the SPS/LHC transfer lines since 2006.
Inputs are: maskable (with safe beam)unmaskable
Architecture of the LHC BEAM INTERLOCK SYSTEM
Beam-1 / Beam-2 are Independent!
- fast reaction time (~ s)- safe- limited no. of inputs- Some inputs maskable for safe beam intensity
Up to 20 Users per BIC system:
6 x Beam-18 x Both-Beam
6 x Beam-2
Connected to injection IR2/IR8:-In case of an interlock (=NO beam permit),
the beam is dumped & injection is inhibited.
- It is not possible to inhibit injection
ALONE.
47
48
BIS Reaction TimesBIS Reaction Times
UserSystemprocess
a failure has been detected… beam dump
request
Beam Dumping System waiting for beam gap
89μs max
Signalssend
to LBDS
t2 t3
Beam Interlocksystemprocess
~70μs max.
t1
> 10μs
USER_PERMIT signal changesfrom TRUE to FALSE
Kicker fired
t4
all bunches have been extracted
~ 89μs
Achievable response time ranges between 100 s and 270 s
(between the detection of a dump request and the completion of a beam dump)
15/12/2008 ITER-CERN WS - J. Wenninger
In action…
4915/12/2008 ITER-CERN WS - J. Wenninger
First Emergency Dump
50
First “Emergency Dump” on Thurs 11th at 22:45:08
On 11th September 2008 during operation with circulating beam. At 22:45:08, beam 2 was dumped by the LBDS triggered by the BIS. The dump was caused by a water fault in the DC cables in the main quadrupole
circuit in LHC sector 81. This event allowed to address the performance of the interlock / machine
protection systems at a very early state, as well as to understand the functionality of the post mortem (transient data) recording
15/12/2008 ITER-CERN WS - J. Wenninger
First Dump
51
11 Sep 2008 22:45:08 (561437)11 Sep 2008 22:45:08 (561437)
11 Sep 2008 22:45:08 (561617)11 Sep 2008 22:45:08 (561484)
Data from Beam Interlock System
Beam Interlock Controller at IP8received dump request at 561.437 ms
Beam Interlock Controller at IP6received dump request- 50 s later (anti clockwise signal) - 180 s later (clockwise signal)
Beam Dump 561.523 ms
Post-mortem System
15/12/2008 ITER-CERN WS - J. Wenninger 52
As indicated on the previous slide the Post-mortem data is very important.
The diagnostics of failures is essential to: Understand what happened. Assess the performance / correct functioning of the MPS. For critical systems like beam dumping system, the PM analysis is
MANDATORY to ensure that the system is ‘as good as new’. At the LHC all equipment systems provide post-mortem data:
Circular buffers that are frozen on fault/beam abort. Accurate timestamps, down to s for fast systems. Data relevant for understanding of failures. Buffer depth and granularity dependent on system. Typical for beam
diagnostics is turn by turn (sometimes bunch by bunch).
>> ‘Expected’ data volume for LHC : 2-5 GBytes
Software interlocking
15/12/2008 ITER-CERN WS - J. Wenninger 53
In very large accelerators it is not always possible to cover all failure mechanisms with a hardware system: needs something more flexible.
Example : At the LHC the integrated bending field of horizontal steering magnets may bias the beam energy and cause problems
during beam aborts.
Provide flexibility to quickly add new interlocks (provided they are not too time critical).
Need to survey the integrity of the settings even with a MCS system:
Comparison of data and digital signatures between front end computers and DB.
>> Software Interlock System to survey the control system components relevant for machine protection as additional protection layer, with possibility to abort beam if necessary.
MPS settings control
15/12/2008 ITER-CERN WS - J. Wenninger 54
A Critical Settings Management (MCS) system has been developed for the LHC (and for CERN in general) to be able to control MPS settings (for example Beam loss monitor thresholds…) through the central controls database without loss of security.
MCS provides:
Critical settings that can only be changed by authorized groups of persons.
Parameters are visible to everyone that has access to the control system.
Authentication and Authorization of the user.
Verification that values of critical parameters have not changed since the authorized person has updated them:
Data transfer errors. ‘Hacking’. Data corruption – radiation, data loss during reboots…
Critical settings control
15/12/2008 ITER-CERN WS - J. Wenninger 55
Based on the concept of public & private key.
User logs in. The critical data receives a digital signature. Data and digital signature are:
• Send to the front-end system which verifies the data validity.
• Stored together in the DB - avoid direct DB access, reference for checks.
Documentation
15/12/2008 ITER-CERN WS - J. Wenninger 56
All presentations, minutes of meetings etc are accessible from the machine protection web site :
http://lhc-mpwg.web.cern.ch/lhc-mpwg/
which is however only accessible from INSIDE CERN. MP commissioning documents for SPS and LHC are on 2 other
sites:
https://sps-mp-operation.web.cern.ch/sps-mp-operation/
https://lhc-mp-operation.web.cern.ch/lhc-mp-operation/