Element 2Hydrocarbon Process Safety 1
• Contractor Management
• Process Safety Management (PSM)
• Permit-to-Work Procedures
• Key Principles of a Safe Shift Handover
• Plant Operations and Maintenance
• Start Up and Shut Down
© RRC Training
The Scale of Contractor Use
• Support vessels
• Diving services
• Work on drilling and exploration rigs
• Etc.
Contractor Management
© RRC Training
To achieve safe working with contractors:
• Risk assess the contractor’s job
• Make sure contractors follow site rules
• Good comms - ensure all contractor employees know identity of site contact person (and how to contact)
• Include contractors in safe working procedures/PTW systems
Contractor Management
•24/2/2014
•2
© RRC Training
Contractor Management – 5 Steps
1 •Planning
2 •Choosing a contractor
3 •Contractors working on site
4 •Keeping a check
5 •Reviewing the Work
© RRC Training
Assessing contractor competence:
• Experienced in the type of work?
• Trained in offshore safety requirements?
• Any recent enforcement action taken against them?
• Etc.
Contractor Management
© RRC Training
Safe Shift Handover – Understanding the Hazards/Issues
• Enough time allowed?
• Formal meetings held?
• Conflict between the shifts (how much the off-going shift actually achieved, etc.) ?
• Off-going shift left work they don’t want to do?
• Included contractors?
• Etc.
Contractor Management
© RRC Training
Process Safety Management (PSM)Some methodologies used to classify Fire and Explosion risk:
• Dow Fire and Explosion Hazard Index (DF&EI) • Mond Fire and Explosion and Toxicity Index (MFETI)
Risk Classifications from the Dow index
•24/2/2014
•3
© RRC Training
How the Dow Index works:
Awards a characteristic for each factor in the fire/explosion hazard analysis:
• Main items (material factor): MF
• General process hazards factor: F1
• Special process hazards factor: F2
• Process unit hazards factor: F3 (F3 = F1 x F2)
• Fire & Explosion Index (F&EI) = F3 x MF
Process Safety Management
© RRC Training
Dow IndexAdvantages Disadvantages
Reproducible Intended for designer use at early stages
Requires evaluation of all aspects of a process unit that increases the potential severity of a fire or explosion
harder to apply to existing plant
Easy to use Not good at determining normal expected loss
Based on actual loss experience Interpretation requires judgement
Recognised by industry as good for ranking chemical process risks
© RRC Training
Some PSM controls:
• Inventory control
• Spacing of operating plant
• Positioning and protection of control rooms and critical equipment (isolation)
• Administrative controls, e.g. Management of change (MoC)
Process Safety Management (PSM)
© RRC Training
MoC control will be needed when, e.g.
• equipment is replaced with non-identical parts
• new items or equipment is added to the system
• changes are made to the operating procedures (if outside established design basis and safe operating envelope).
Process Safety Management
•24/2/2014
•4
© RRC Training
MoC Procedures should identify:
• the scope of the changes (what needs to change)
• the roles and responsibilities of those managing and making the changes
• how risk analysis is to be undertaken
• methods used to communicate the changes
• training of personnel involved
Process Safety Management
© RRC Training
Some documentation that may be involved in the MoC evaluation:
• Original process system designs (basis for design)
• Process flow diagrams
• Cause and effect diagrams
• List of control, alarm and trip settings
• Equipment specifications
• Drawings detailing classification of hazardous areas
Process Safety Management
© RRC Training
Roles and Responsibilities –Making The Change
• Map the organisational changes (prevent gaps)
• Match personnel and skills to the task (further training?)
• Phase the changes.
Process Safety Management
© RRC Training
Change proposal document design elements and issues:
• Description of the proposed change
• Date of proposal
• Reasoning for the change (why needed etc).
Process Safety Management
• Authorisation (personnel) for different types of change
• Involve competent personnel to assess changes
• Monitoring of adherence to procedures
• Independent auditing of SMS
•24/2/2014
•5
© RRC Training
The Role and Purpose of a Permit-to-Work System
• To ensure non-routine/hazardous work is assessed, planned, authorised and carried out safely.
Permit-to-Work Procedures
© RRC Training
The Typical Features of a Permit-to-Work Document
• Title and permit number • Reference to other permits/isolation certificates in place• Equipment, distribution board, circuit or job location; plant
identification• Description of job• Hazards identified and precautions necessary • Protective equipment and PPE required• Authorisation• Date, time and duration of the permit• Identification of employees in control of the work • Permit acceptance• Extension/Handover arrangements (e.g. shift handover)• Returning to service on completion of work• Cancellation
Permit-to-Work Procedures
© RRC Training
Roles and Responsibilities of those using Permits-to-Work:
• Permit applicant
• Issuing authority
• Performing Authority
• Permit user
Permit-to-Work Procedures
NB need for Training and Competence in use of system.
© RRC Training
Permit-to-Work Procedures
Types of Permits-to-Work
Separate permits are required for different tasks, e.g.:
• Hot work• Live electrical or high voltage work• Working at height• Working over water• Work in confined spaces
•24/2/2014
•6
© RRC Training
Interfaces with Adjacent Plant
Need to consider implications/interactions e.g.
• Permit issued to shut down one item of plant when another, exactly the same, is already shut down for work.
(Remember Piper Alpha disaster!)
Permit-to-Work Procedures
© RRC Training
Interfaces with Contractors
Treat contractors as employees in the permit-to-work system.
Permit-to-Work Procedures
Work role PTW Role
Contractor Permit user
Manager appointing contractor Issuing authority
© RRC Training
Safe Isolation, Lock-Out and Tag-Out Systems
Permit-to-Work Procedures
Principal requirements:
• Removal (isolation) of energy sources
• Method of prevention of accidental re-application of the energy source
• Adequate warnings and safeguards for those working on isolated equipment and machinery
© RRC Training
SAFE ISOLATION STEPS
• Stop machine/plant normally.
• Discharge residual energy.
• Stop all moving parts (in safe position)
• Switched OFF main electrical isolator.
• Fit lock (labelled/coded) to isolator to secure in OFFposition.
Permit-to-Work Procedures
Safe isolation must always be proven before commencing the work to be done.
•24/2/2014
•7
© RRC Training
LOCK-OUT / TAG-OUT SYSTEMS (for multiple lock-offs)
• Safety clamp – where > 1 person requires access
• A warning notice
Permit-to-Work Procedures
© RRC Training
Fuse removal – if TOTAL SEPARATION from an electricity supply is needed.
Permit-to-Work Procedures
Other energy sources may need -
• Pipe disconnection• Blanking (with locks)• Locking of valves
Other considerations
Physical restraints to prevent fall” of machinery parts after isolation of the power
© RRC Training
RE-CONNECTION PROCEDURE
• Tidy away all tools used• Correctly refit removed items
• Lock ‘owner’ unlocks and removes it (may need alternative for shift change-over)
• Remove clamp (if multiple locks)
• Warning notice ‘owner’ removes it
• Person who carried out isolation to check if safe to re-connect the energy source(s).
• Reconnect
Permit-to-Work Procedures
© RRC Training
Shift Handover communication problems:• During plant maintenance running across > 1 shift.
• Where safety systems may have been over-ridden (e.g. fire deluge switched onto manual).
• During deviations from normal working (e.g. breakdowns).
• During extended absences by workers.
• Handover between experienced and inexperienced staff.
Key Principles of Safe Shift Handover
•24/2/2014
•8
© RRC Training
To make handovers more effective:
• Make shift change-over comms a high priority
• Conduct handovers face-to-face
• 2-way - ensure BOTH shift crews take joint responsibility for information accuracy
• Allow sufficient TIME
• Use verbal and written
• Analyse information needs of incoming crew
• Etc.
Key Principles of Safe Shift Handover
© RRC Training
Asset Integrity
The ability of an ‘asset’ to carry out its intended function effectively and efficiently over its planned lifecycle, at the same time safeguarding the health and safety of those exposed and the operating environment.
Plant Operations and Maintenance
© RRC Training
Plant Operations and MaintenanceLifecycle phase Example
deliverables/activities
Design Safety studies
Construction and hook up Procurement quality plans
Commission Function test
Operation Maintenance
Modification MoC process
Decommission Decommissioning plan
© RRC Training
Inspection and testing often legal requirement (e.g. lifting equipment) but generally required:
Plant Operations and Maintenance
•24/2/2014
•9
© RRC Training
• Pressure vessels (including pipelines) – in accordance with a written scheme of examination. Safety of pressure vessels, internal and external inspection and hydraulic testing every 10 years.
• Lifting equipment – six monthly if persons carried ; 12 months for other, unless specified in written scheme by the operator.
Plant Operations and Maintenance
Examples of Inspection/Testing requirements
© RRC Training
Maintenance Strategies:
• Emergency / Breakdown maintenance• Opportunity maintenance• Working adjustments
Plant Operations and Maintenance
• Running repairs• Servicing and inspection• Shutdown maintenance• Planned preventive maintenance (PPM)• Routine condition-monitoring
© RRC Training
Some Corrosion Types:
• General wastage of material (uniform corrosion)• Galvanic corrosion (dissimilar metals in contact)• Pitting (localised attack)• Intergranular corrosion• Stress corrosion• Erosion corrosion• Corrosion fatigue• High temperature oxidation• Hydrogen embrittlement
Plant Operations and Maintenance
© RRC Training
Corrosion control practice and procedures include:
• Selection of (inherently corrosion resistant) materials, e.g. C-Mnsteel of offshore vessels and pipework
• Chemical treatments e.g. corrosion inhibiters in pipelines
• Surface coatings e.g. paints
• Cathodic protection
• Process and environmental controls
• Initial design
• Monitoring/inspection/testing for corrosion
Plant Operations and Maintenance
•24/2/2014
•10
© RRC Training
Corrosion Inspection and monitoring will include risk-based assessment of:
• The operating environment• The composition of produced fluids• Metal wastage• Pitting corrosion• Erosion caused corrosion• Cracking• Assessment of the corrosivity of fluids• Development of biological activity
Plant Operations and Maintenance
© RRC Training
Three monitoring system types:
In-line systems – devices placed in the system that have to be removed for monitoring, such as corrosion (weight-loss) coupons, bio-studs, etc.
On-line techniques – using corrosion monitoring devices fixed in the system or process equipment
Off-line monitoring – which requires inspection and non-destructive testing
Plant Operations and Maintenance
© RRC Training
Asset Integrity Competency and Training, e.g. for:
• Asset integrity managers e.g. performance standards for SCEs
• Others, e.g. corrosion awareness
Plant Operations and Maintenance
© RRC Training
Plant Operations and MaintenanceRisk based Maintenance and Inspection Strategy
1• Ensure the risks are reduced to ALARP
2• Optimise the inspection schedules
3• Inspect the most critical items of plant, equipment
and components
4• Use the most appropriate inspection methods
•24/2/2014
•11
© RRC Training
Techniques, Principles and Importance of Safe Operation Procedures and Maintenance
Safe Operation
Safe operation requires planned activities, controlled timetables and full operational guidelines to be in place.
Plant Operations and Maintenance
Standard Operation Procedures
Day-to-day procedures (“standards of performance”) to ensure that “normal” activities are conducted safely.
© RRC Training
Control of Ignition Sources in Maintenance and Operations
• Electrical equipment –routine inspection and testing
• Smoking – restrict to designated areas
• Cooking and heating appliances – designated areas (galley), master (gas) isolator valve clearly visible (gas).
• Mechanical overheating – maintenance
• Arson – security
• Hot work (welding, burning etc) – use of permit-to-work
Plant Operations and Maintenance
© RRC Training
Hot Work Permit Requirements• Area safety inspection
• Fire-fighting equipment available
• Location and nature of the work
• Name of the person in charge
• Permitted time-span of the activity and the level of supervision required
• Actions to be taken when the work is finished e.g. fire checks
• If done in confined space – then additional precautions!
Plant Operations and Maintenance
© RRC Training
• Cleaning and Gas Freeing (‘degassing’)
• Purging
• Venting
• Draining of water, product, oxygen and non-condensibles (NCD)
• Inerting
Plant Operations and MaintenanceOther Activities undertaken:
•24/2/2014
•12
© RRC Training
Safe Start up/shut down of HC-containing equipment
For maintenance – usually controlled within permit-to-work system (described earlier)
Start Up and Shut Down
Water and Hydrates Presence and Removal
• Hydrates may cause blockages in gas systems - removal may require shut down and venting
© RRC Training
Testing, Commissioning and Hook-Up
• Tests on pressures, temperatures and flow-rates may be required, and assurance that relief valves, diverter valves, bursting discs, etc. are functioning correctly.
• Leak testing
• NDT e.g. on weld integrity
• Commissioning and hook up may require PTW system
Start Up and Shut Down