industrial training in ntpc

Upload: uppalpiyush

Post on 03-Jun-2018

233 views

Category:

Documents


4 download

TRANSCRIPT

  • 8/11/2019 Industrial Training in Ntpc

    1/57

    INDUSTRIAL TRAINING

    REPORT ON

    N.T.P.C DADRI

    (2014-2015)

    SUBMITTED BY: PIYUSH UPPAL

    ROLL NO: 12111502811

    BRANCH: ELECTRONICS & COMMUNICATION

  • 8/11/2019 Industrial Training in Ntpc

    2/57

    Training at NTPC DADRI

    I was appointed to do 4 week training at this esteemedorganization from 18th June to 18st July, 2014. I was assigned tovisit the divisions of the plant, which were:

    Gas power plant.Instrumentation and control room.

    These 4 weeks training was a very educational adventure for me.

    It was really amazing to see the plant by yourself and learn howelectricity, which is one of our daily requirements of life, isproduced. This report has been made by my experience at NTPCDadri.

    The material in this report has been gathered from my textbook,senior student reports and trainers manuals and power journalsprovided by training department. The specification and principles

    are as learned by me from the employees of each division ofNTPC Dadri.

  • 8/11/2019 Industrial Training in Ntpc

    3/57

    GENESIS OF NTPC

    Establishedin 1975 forbulksupply of cost effective power

    forrapid growthof India

    Oneof the best performing

    NavaratnaPSUs

    15 Coal, 7 Gas based & 4 in

    Joint Venture PowerStations

    InstalledCapacity more 33,000

    MW & a Maha Ratna company

    construction

    Plannedto become 75,000MW+

    companybyYear 2017

    Dadri

  • 8/11/2019 Industrial Training in Ntpc

    4/57

    Strategies of NTPC

  • 8/11/2019 Industrial Training in Ntpc

    5/57

    JOURNEY OF NTPC

  • 8/11/2019 Industrial Training in Ntpc

    6/57

    TOTAL CAPACITY

    OFN.T.P.C DADRI

    (A)THERMAL1)04x210 MW=840 MW

    2)02X490 MW=980 MWTOTAL=1820 MW

    (B)GAS =817 MW(C) SOLAR =05 MW

    GRAND TOTAL=2642 MW

  • 8/11/2019 Industrial Training in Ntpc

    7/57

    DADRI GAS POWER STATION

  • 8/11/2019 Industrial Training in Ntpc

    8/57

    STATION SALIENT FEATURES:

  • 8/11/2019 Industrial Training in Ntpc

    9/57

    INPUTS FOR GAS STATION

    FuelNatural gas (Primary) HSD (Alternate fuel)

    Source of gas- APM, PMT:ONGC/RIL/BRITISH GAS

    RLNG :GAIL, IOCL,GSPCL.

    KG-D6 : RIL

    TRANSPORTATION :From GAIL through HBJ Pipeline &

    RGTL.

    Source of HSD : IOCL, HPCL, BPCL through Rly. rakes.

  • 8/11/2019 Industrial Training in Ntpc

    10/57

    WATER FOR GAS STATION

    SOURCE:UPPER GANGA CANAL

    Consumptive requirement : 50 60 Cusec

  • 8/11/2019 Industrial Training in Ntpc

    11/57

  • 8/11/2019 Industrial Training in Ntpc

    12/57

    MAIN COMPONENTS OF GAS TURBINES

    POWER GENERATING PLANT:

    Starting system

    Air intake system

    Fuel supply system

    Compressor

    Combustion chamber

    Gas turbine

    Gas turbine exhaust diffuser/Diverter damper/Chimney

    Lub oil supply system

    Control oil supply system

    Turbo generator

    Generator circuit breaker

    Generator transformer

    Control and instrumentation system

  • 8/11/2019 Industrial Training in Ntpc

    13/57

    ADVANTAGES OF GAS TURBINE

    Environment Friendly

    Less installation Period

    High Efficiency (60% )

    Less manpower requirements

    Quicker response time

    Faster Acceleration/deceleration

    Modular replacement

    Less vibrations

    Less area required

    No by Product like ash.

  • 8/11/2019 Industrial Training in Ntpc

    14/57

    DISADVANTAGES OF GAS

    TURBINE

    High cost of maintenance.

    High frequency of inspection/overhauling.

    Hot gas path components under highthermal stress.

    Variation in output due to external factorslike ambient pressure, temp, relativehumidity, Grid Frequency.

    Running on secondary fuel or frequentstart stop reduces the components life.

  • 8/11/2019 Industrial Training in Ntpc

    15/57

    WHY COAL?

    Advantages of Coal Fuel Abundantly available in India Low cost Technology for Power Generation well developed

    Easy to handle, transport, store and use

    Shortcomings of Coal Low Calorific Value Large quantity to be Handled

    Produces pollutants, ash Disposal of ash is Problematic Reserves depleting fast

    Indias Coal Reserves are estimated to be 255billion tonnes. Present consumption is about 450

    million tonnes.

    Cost of coal for producing 1 unit of electricity (Costof coal Rs 1000/MT) is Rs 0.75.

    Cost of Gas for producing 1 unit of electricity (Costof Gas Rs 6/SMC) is Rs 1.20

  • 8/11/2019 Industrial Training in Ntpc

    16/57

    COAL PROPERTY

    1. Moisture - Air dried-5 to 7%

    - Total moisture-10 to 12%2. Ash - Washed coal-below 35%

    - Raw coal-38-40%3. VM(Volatile matter)- 20-26%(Hydro carbons i.e; ethen etc.)

    4. Fixed Carbon - 25-27%

    5. C.V.(Calorific value) - 3600-3800 kcal/kg

    COAL GRADE- Decided on UHV (Utilized H Value):-A - Above 6201 Kcal/kg

    B - 5601-6200C - 4941-5600D - 4201-4940E - 3361-4200F - 2401-3360G - 1301-2400

    Ungraded-Below1300

  • 8/11/2019 Industrial Training in Ntpc

    17/57

    COAL TRANSPORTATION

    SYSTEM

    Source of Coal - Piparwar block of NorthKaranpura coal field ofEastern coal field

    Means of - RailwayTransportation

    Route of Rly - KhalariGarwa road-Seonnogar-Mughal Sarai

    Allahabad-Kanpur-AligarhDadri-Plant Unloading area

    Total distance - 1124 km from khalori to Dadriwith electrified track fromSeonnogar

    Type of wagon -1. BOBR (Bogy Open BottomRapid Discharge Wagon) OR2. Box-N (3 doors on each side)3. Box-C (5 -do- )

    No of wagons/ rake - 59 wagons of 60-65 toncapacity

    No of rake reqd/day - 8 to 9Total cycle time of - Approximately 6 days

    One rakeType of locos - WDM-2 (2600 Hp)

  • 8/11/2019 Industrial Training in Ntpc

    18/57

    CRUSHER HOUSE

    No & make of Crusher- 4, Pennsylvenia,USA

    Type & size - Ring granulators,TKKGN-48093

    Main crusher Capacity- 875 tonne/hr each

    Max. coal size - 250 mmbefore crusher

    Coal size after crusher- 20 mm Motor rating - 800hp (597kw)

    Make - Kirloskar Elect Ltd.Power supply - 6.6kv, 30, 58HZ,RPM - 743Full load ampere - 69 AInsulation class - F

    No. of hammers - 60

  • 8/11/2019 Industrial Training in Ntpc

    19/57

    CONVEYOR

    No. of belt conv - 16 Design/rated capacity - 1540 tph/1400 tph Conv Capacity - 700 - 1400

    Belt speed - 2.63.36m/sec Belt width - 1000 - 1400mm Fabric type - Nylon-Nylon/ EP(Polamide-Synthetic) No of plies - 4 Belt rating - 6301250 Cover grade - Fire Resistant No of belt weigher - 6 No of metal detector - 4 No of sampling unit - 4 No & type of magnetic - 4, suspended type

    Separator (ILMS)No of magnetic separator- 2

  • 8/11/2019 Industrial Training in Ntpc

    20/57

    Coal to Electricity ..

    Basics

    Polluta

    nts

    Coal

    He

    at ASH

    Lo

    ss

    Sup

    er

    Heated

    Steam

    Heat

    Loss In

    Conden

    ser

    Turbine

    Torque

    Mech.

    Energy

    Loss

    Alternating

    current inStator

    Elet.

    Energy

    Loss

    Chemi

    cal

    Energ

    y

    Therm

    al

    Energ

    y

    Kineti

    c

    Energ

    y

    Electri

    cal

    Energy

  • 8/11/2019 Industrial Training in Ntpc

    21/57

  • 8/11/2019 Industrial Training in Ntpc

    22/57

    STOCK YARD

    Capacity - 45 days coal of stage-1requirement 5,00,000 m3of coal approx.

    No of coal plies in - 4Stockyard

    Length/height of - 470m/10meach plies

  • 8/11/2019 Industrial Training in Ntpc

    23/57

    MVW (MEDIUM VELOCITION WATER)SPRAY SYSTEM FOR COAL CONVEYOR

    Type of system - Deluge valve operated && actuation MVW spray system auto-matic

    (A) (electrical), remote,manual & local manual

    (Mechanical) Spray density - 10.2 lph /m2(of floor area +

    return belt area)

    Water pressure/ - 10.4 bar/5.0barDV Operating Pr.

    Type of detection - QBD,LHSC & infra Red detectorssystem

    Type of spray nozzlesa) for floor protection Open head up right

    sprayers with K-79

    (Metric)V-1b) for return belt - Open head directionalprotection sprayers with K-46

    Water reqd per zone - Limited to approx410 m3/hr

    No of zone sprayed - Adjacent three nos.at a time

  • 8/11/2019 Industrial Training in Ntpc

    24/57

  • 8/11/2019 Industrial Training in Ntpc

    25/57

    SALIENT FEATURES OF NTPC,

    DADRI

    Largest dry ash disposal system in India.

    Largest switch yard in India.

    Largest gas station in India.

    Unique storage of dry ash by constructingash mound (the only one in Asia)

  • 8/11/2019 Industrial Training in Ntpc

    26/57

    Inputs for Coal Station

    Washed Coal supplyfrom NorthKaranpura coalfields CCL inJharkhand,about 1200 kms from site.

    Transportation Indian Railways. Consumption

    3.66 Million tonnes per annum.

  • 8/11/2019 Industrial Training in Ntpc

    27/57

    Environment Management System atNTPC Dadri

    The station is certified for ISO 14001, ISO 9001, IS18001 & SA 8000 and is committed to sustenanceand continual improvement in Environmentmanagement , Quality management, Safetymanagement and Social accountability.

    NTPC Dadri is the first ISO 14001 certified power

    station amongst NTPC units since 1999.

    Initially Certification body was DNV & nowcertification body is BIS.

    Validity of current certificate is up to 21-03-2012. Now it is integrated with other ISO/IS systems. i.e.

    ISO 9001, IS 18001 since 2007.

  • 8/11/2019 Industrial Training in Ntpc

    28/57

    OPERATION OF A POWER PLANT

    Basic PrincipleAs per FARADAYs Law-Whenever the amount of magnetic flux

    linked with a circuit changes, an EMF is produced in the circuit.Generator works on the principle of producing electricity. To changethe flux in the generator turbine is moved in a great speed with steam.

    To produce steam, water is heated in the boilers by burning the

    coal.

    In a dadri Thermal Power Station, steam is produced and used tospin a turbine that operates a generator.

    Water is heated, turns into steam and spins a steam turbine which

    drives an electrical generator.

    After it passes through the turbine, the steam is condensed in

    a condenser.

    The electricity generated at the plant is sent to consumers through

    highvoltage power lines

    The Dadri Thermal Power Plant has Steam Turbine-Driven

    Generators which has a collective capacity of 1820MW.

    The fuel being used is Coal which is supplied from the Piparwar

    Mines,Jharkhand.

    Water supply is given from the Upper Ganga Canal.

  • 8/11/2019 Industrial Training in Ntpc

    29/57

    Basic Steps of Electricity Generation

    The basic steps in the generation of

    electricityfrom coal involves following steps:

    Coal to steam

    Steam to mechanical power

    Mechanical power to electrical power

  • 8/11/2019 Industrial Training in Ntpc

    30/57

    PARTS OF A POWER PLANT

  • 8/11/2019 Industrial Training in Ntpc

    31/57

    PARTS OF A POWER PLANT

    1. Cooling tower2. Cooling water pump3. Transmission line (3-phase)4. Unit transformer (3-phase)5. Electric generator (3-phase)6. Low pressure turbine7. Condensate extraction pump

    8. Condenser9. Intermediate pressure turbine10. Steam governor valve11. High pressure turbine12. Deaerator13. Feed heater14. Coal conveyor15. Coal hopper16. Pulverised fuel mill17. Boiler drum18. Ash hopper19. Super heater20. Forced draught fan21. Reheater22. Air intake

    23. Economiser24. Air preheater25. Precipitator26. Induced draught fan27. Flue Gas

  • 8/11/2019 Industrial Training in Ntpc

    32/57

    PROTECTION &

    TRIPPING

    1. Sequence tripping

    2. ZSS (Zero Speed Switch)3. BSS (Belt Sway Switch)4. PCS (Pull Cord Switch)5. MD (Metal Detector)6. MVW Spray (for Fire protection)

  • 8/11/2019 Industrial Training in Ntpc

    33/57

    MOTORSAC MOTORS:

    Squirrel cage motor

    Wound motor

    Slip ring induction motor

    In modern thermal power plant three phase squirrel cage induction motorsare used but sometimedouble wound motor is used when we need high starting torque e.g. in ballmill.

    THREE PHASE INDUCTION MOTOR

    Ns (speed) =120f/p

    Stator can handle concentrated single layer winding, with each coil

    occupying one stator slot

    The most common type of winding are:

    DISTRIBUTED WINDING :

    This type of winding is distributed over a number of slots.

    DOUBLE LAYER WINDING :

    Each stator slot contains sides of two different coils.SQUIRREL CAGE INDUCTION MOTOR

    Squirrel cage and wound cage have same mode of operation. Rotor

    conductors cut the rotatingstator magnetic field. an emf is induced across the rotor winding, currentflows, a rotor magnetic fieldis produced which interacts with the stator field causing a turning motion.The rotor does not rotateat synchronous speed, its speed varies with applied load. The slip speedbeing just enough to enablesufficient induced rotor current to produce the power dissipated by themotor load and motor losses.

  • 8/11/2019 Industrial Training in Ntpc

    34/57

    BEARING AND LUBRICATION:

    A good bearing is needed for trouble free operation of motor. Since it is verycostly partof the motor, due care has to be taken by checking it at regular intervals. So

    lubricatingplays an important role. Two types of lubricating are widely used

    Oil lubrication

    Grease lubrication

    Insulation

    INSULATIONWinding is an essential part so it should be insulated. Following types ofinsulation arewidely usedINSTRUMENTS SEENMICROMETERThis instrument is used for measuring inside as well as outside diameter ofbearing.MEGGARThis instrument is used for measuring insulation resistance.VIBRATION TESTERIt measures the vibration of the motor. It is measured in three dimensions-axial, verticaland horizontal.

  • 8/11/2019 Industrial Training in Ntpc

    35/57

    SWITCH GEAR

    Switchgear is one that makes or breaks the electrical circuit.

    It is a switching device that opens & closes a circuit that defined as apparatus usedfor switching, Lon rolling & protecting the electrical circuit & equipments.

    The switchgear equipment is essentially concerned with switching & interrupting

    currents either under normal or abnormal operating conditions.

    The tubular switch with ordinary fuse is simplest form of switchgear & is used to con

    & protect& other equipmentsin homes, offices etc.

    For circuits of higher ratings, a High Rupturing Capacity (H.R.C) fuse in condition wi

    a switch may serve the purpose of controlling & protecting the circuit.

    However such switchgear cannot be used profitably on high voltage system (3.3 KV

    for 2 reasons.

    Firstly, when a fuse blows, it takes some time to replace it & consequently there is

    interruption of service to customer.

    Secondly, the fuse cannot successfully interrupt large currents that result from the H

    Voltage System.

    In order to interrupt heavy fault currents, automatic circuit breakers are used.

    There are very few types of circuit breakers in B.P.T.S they are VCB, OCB, and SF6

    circuit breaker.

    The most expensive circuit breaker is the SF6 type due to gas.

    There are various companies which manufacture these circuit breakers: VOLTAS,

    JYOTI, and KIRLOSKAR.

    Switchgear includes switches, fuses, circuit breakers, relays & other equipments.

    In low tension switch gear thermal over load relays are used whereas in high tension

    different types of relays are used.

  • 8/11/2019 Industrial Training in Ntpc

    36/57

    THE EQUIPMENTS THAT NORMALLY FALLIN THIS CATEGORY ARE:-

    ISOLATOR

    Isolator cannot operate unless breaker is open

    Bus 1 and bus 2 isolators cannot be closed simultaneously

    The interlock can be bypass in the event of closing of bus coupler breaker.

    No isolator can operate when the corresponding earth switch is on

    SWITCHING ISOLATOR

    Switching isolator is capable of:

    Interrupting charging current

    Interrupting transformer magnetizing current

    Load transformer switching. Its main application is in connection with the

    transformer feeder as the unit makes it possible to switch gear one transformerwhile the other is still on load.

    CIRCUIT BREAKER

    One which can make or break the circuit on load and even on faults is referredto as circuit breakers. This equipment is the most important and is heavy dutyequipment mainly utilized for protection of various circuits and operations onload. Normally circuit breakers installed are accompanied by isolators.

    LOAD BREAK SWITCHES

    These are those interrupting devices which can make or break circuits. These

    are normally on same circuit, which are backed by circuit breakers

    EARTH SWITCHESDevices which are used normally to earth a particular system, to avoid any

    accident happening due to induction on account of live adjoining circuits. Theseequipments do not handle any appreciable current at all. Apart from thisequipment there are a number of relays etc. which are used in switchgear.

  • 8/11/2019 Industrial Training in Ntpc

    37/57

    Low Tension SWITCH GEAR

    MAIN SWITCH

    Main switch is control equipment which controls or disconnects the main

    supply. The main switch for 3 phase supply is available for the range 32A, 63A,100A, 200Q, 300A at 500V grade.

    FUSES

    With Avery high generating capacity of the modern power stations extremely

    heavy carnets would flow in the fault and the fuse clearing the fault would be

    required to withstand extremely heavy stress in process. It is used for supplyingpower to auxiliaries with backup fuse protection. With fuses, quick break, quickmake and double break switch fuses for 63A and 100A, switch fuses for200A,400A, 600A, 800A and 1000A are used.

    CONTACTORS

    AC Contractors are 3 poles suitable for D.O.L Starting of motors and

    protecting the connected motors.

    OVERLOAD RELAY

    For overload protection, thermal overload relay are best suited for this

    purpose. They operate due to the action of heat generated by passage of currentthrough relay element.

    AIR CIRCUIT BREAKERS

    It is seen that use of oil in circuit breaker may cause a fire. So in all circuits

    breakers at large capacity air at high pressure is used which is maximum at thetime of quick tripping of contacts. This reduces the possibility of sparking. The

    pressure may vary from 50-60kg/cm^2 for high and medium capacity circuitbreakers

  • 8/11/2019 Industrial Training in Ntpc

    38/57

    CONTRACTOR USED IN NTPC

    THERMAL OVERLOAD RELAY

  • 8/11/2019 Industrial Training in Ntpc

    39/57

  • 8/11/2019 Industrial Training in Ntpc

    40/57

  • 8/11/2019 Industrial Training in Ntpc

    41/57

    The main constituents of CHP plant are:-

    WAGON TIPPLER

    Wagon from coal yard come to the tippler and emptied here. There are 2

    wagon tipplers in the OCHP.CONVEYER

    Conveyer belts are used in the OCHP to transfer coal from one place toother as required ina convenient & safe way.

    ZERO SPEED SWITCH

    It is used as a safety device for the motor i.e. if the belt is not moving & themotor is ON, then it burns to save the motor. This switch checks the speed

    of the belt & switches off the motor when speed is zero.METAL DETECTOR

    As the conveyer belt take coal from wagon to crusher house, no metalpiece should go along with coal. To achieve this objective, metal detectors& separators are used.

    CRUSHER HOUSE

    Both the plants i.e. OCHP & NCHP use TATA crusher powered by BHELmotor. Crusher is designed to crush the pieces to 20 mm size i.e. practically

    considered as the optimum size for transfer via conveyer.ROTARY BREAKER

    If any large piece of metal of any hard substances like metal impuritiescomes in the conveyer belt which cause load on the metal separator, thenthe rotary breaker rejects them reducing the load on the metal detector.

    PULL GUARD SWITCH

    These are the switches which are installed at every 10m gap in a

    conveyer belt to ensure the safety of motors running the conveyer belts. Ifat any time some accident happens or coal jumps from belt and startscollecting at a place, then the switch can be used.

  • 8/11/2019 Industrial Training in Ntpc

    42/57

    ELECTRICAL MAINTENANCE

    DEPARTMENTII (EMD-II)

    It includes:

    GeneratorsTransformers

    Switch yard

  • 8/11/2019 Industrial Training in Ntpc

    43/57

    GENERATORS

    The generator works on the principle of electromagnetic

    induction. There are two components

    Stator and rotor. The rotor is the moving part and the

    Stator is the stationary part. The rotor, which has field

    winding, is given an excitation through a set of

    3000rpm to give the required frequency of HZ. The rotor is

    cooled by Hydrogen gas, which is locallyManufactured by the plant and has high heat carrying capacity

    of low density. If oxygen and hydrogen get mixed then they will

    form very high explosive and to

    Prevent their combining in any way there is seal oil system.

    The stator cooling is done by de-mineralized

    (DM) water through hollow conductors. Water is fed by one

    end by Teflon tube. A boiler and a turbine are coupled to

    electric generators. Steam from the boiler is fed to the turbine

    through the connecting pipe.

    Steam drives the turbine rotor.

    The turbine rotor drives the generator rotor which turns

    the electromagnet within the coil of wire conductors.

    Carbon dioxide is provided from the top and oil is provided

    from bottom to the generator. With the help

    of carbon dioxide the oil is drained out to the oil tank.

  • 8/11/2019 Industrial Training in Ntpc

    44/57

    RATINGS OF THE GENERATORSUSED

    Turbo generator 100MW

    TURBO GENERATOR 210 MW

    The 100 MW generator generates 10.75 KV and

    210 MW generates 15.75 KV. The voltage is

    stepped up to 220 KV with the help of generatortransformer and is connected to the grid.The voltage is stepped down to 6.6 KV with the

    help of UNIT AUXILLARY TRANSFORMER (UAT)

    and this voltage is used to drive the HT motors. The

    voltage is further stepped down to 415 V and then

    to 220 V and this voltage is used to drive Lt Motors.

  • 8/11/2019 Industrial Training in Ntpc

    45/57

    TRANSFORMERS

    It is a static machine which increases or decreases the AC voltagewithout changing the frequency of the supply.It is a device that:

    Transfer electric power from one circuit to another.

    It accomplishes this by electromagnetic induction.

    In this the two electric circuits are in mutual inductive influence of each

    other.

    WORKING PRINCIPLE:It works on FARADAYSLAWOF ELECTROMAGNETIC INDUCTION (selfor mutual induction depending on the type of transformer).

  • 8/11/2019 Industrial Training in Ntpc

    46/57

    COOLING OF TRANSFORMERSOF LARGE MVA

    As size of transformer becomes large, the rateof the oil circulating becomes insufficient todissipate all the heat produced & artificialmeans of increasing the circulation by electricpumps. In very large transformers, special

    coolers with water circulation may have to beemployed.

    TYPES OF COOLING:Air cooling

    Air Natural (AN)Air Forced (AF)Oil immersed coolingOil Natural Air Natural (ONAN)Oil Natural Air Forced (ONAF)Oil Forced Air Natural (OFAN)

    Oil Forced Air Forced (OFAF)Oil immersed Water coolingOil Natural Water Forced (ONWF)Oil Forced Water Forced (OFWF)

  • 8/11/2019 Industrial Training in Ntpc

    47/57

    MAIN PARTS

    OFTRANSFORMER

    1. Secondary Winding2. Primary Winding.3. Oil Level

    4. Conservator5. Breather6. Drain Cock7. Cooling Tubes.8. Transformer Oil.9. Earth Point10. Explosion Vent

    11. Temperature Gauge.12. Buchholz Relay13. Secondary Terminal14. Primary Terminal

  • 8/11/2019 Industrial Training in Ntpc

    48/57

    SWITCH YARD

    As we know that electrical energy cant be stored like cells, so what wegenerate should be consumed instantaneously. But as the load is notconstants therefore we generate electricity according to need i.e. thegeneration depends upon load. The yard is the places from where theelectricity is send outside. It has both outdoor and indoor equipments.OUTDOOR EQUIPMENTS

    BUS BAR.

    LIGHTENING ARRESTERWAVE TRAP

    BREAKER

    CAPACITATIVE VOLTAGE TRANSFORMER

    EARTHING ROD

    CURRENT TRANSFORMER.

    POTENTIAL TRANSFORMER

    LIGHTENING MASKS

    INDOOR EQUIPMENTS:

    RELAYS.

    CONTROL PANELS

    CIRCUIT BREAKERS

  • 8/11/2019 Industrial Training in Ntpc

    49/57

    BUS BARBus bars generally are of high conductive aluminum conforming toIS-5082 or copper of adequate cross section. Bus bar located in airinsulated enclosures & segregated from all other components .Busbar is preferably cover with polyurethane.BY PASS BUSThis bus is a backup bus which comes handy when any of thebuses become faulty. When any operation bus has fault, this bus isbrought into circuit and then faulty line is removed there byrestoring healthy power line.LIGHTENING ARRESTOR

    It saves the transformer and reactor from over voltage and overcurrents. It grounds the overload if there is fault on the line and itprevents the generator transformer.WAVE TRAPWAVETRAP is connected in series with the power (transmission)line. It blocks the high frequency carrier waves (24 KHz to 500KHz) and let power waves (50 Hz - 60 Hz) to passthrough.BREAKER

    Circuit breaker is an arrangement by which we can break thecircuit or flow of current. A circuit breaker in station serves thesame purpose as switch but it has many added and complexfeatures. The basic construction of any circuit breaker requires theseparation of contact in an insulating fluid that servers twofunctions:

    extinguishes the arc drawn between the contacts when circuit

    breaker opens.

    It provides adequate insulation between the contacts and from

    each contact to earth.

  • 8/11/2019 Industrial Training in Ntpc

    50/57

    EARTHING RODNormally un-galvanized mild steel flats are used for earthling.Separate earthing electrodes are provided to earth the lightening

    arrestor whereas the other equipments are earthed by connectingtheir earth leads to the rid/ser of the ground mar.CURRENT TRANSFORMERIt is essentially a step up transformer which step down the currentto a known ratio. It is a type of instrument transformer designed toprovide a current in its secondary winding proportional to thealternating current flowing in its primary.POTENTIAL TRANSFORMER

    It is essentially a step down transformer and it step downs thevoltage to a known ratio.RELAYSRelay is a sensing device that makes your circuit ON or OFF. Theydetect the abnormal conditions in the electrical circuits bycontinuously measuring the electrical quantities, which aredifferent under normal and faulty conditions, like current, voltagefrequency. Having detected the fault the relay operates to

    complete the trip circuit, which results in the opening of the circuitbreakers and disconnect the faulty circuit.There are different types of relays:Current relayPotential relayElectromagnetic relayNumerical relay etc.AIR BREAK EARTHING SWITCH

    The work of this equipment comes into picture when we want toshut down the supply for maintenance purpose. This help toneutralize the system from induced voltage from extra highvoltage. This induced power is up to 2KV in case of 400 KV lines.

  • 8/11/2019 Industrial Training in Ntpc

    51/57

    FIRE PROTECTION IN

    COAL HANDING

    PLANT

  • 8/11/2019 Industrial Training in Ntpc

    52/57

  • 8/11/2019 Industrial Training in Ntpc

    53/57

  • 8/11/2019 Industrial Training in Ntpc

    54/57

    FIRE HYDRANT SYSTEM

    Fire Hydrant SYSTEM

    Spacing 45 M max.

    External Fire Escape Staircases.

  • 8/11/2019 Industrial Training in Ntpc

    55/57

    FIRE WATER PUMPS

    MAIN HYDRANT PUMPS (03 NOS MOTORDRIVEN,O1 ENGINE DRIVEN) HORIZONTALCENTRIFUGAL PUMP, CAPACITY:410METRECUBE PER HOUR, HEAD 105MWC

    MAIN SPRAY PUMPS (01 NO MOTORDRIVEN, 01 NO ENGINE DRIVEN)-HORIZONTAL CENTRIFUGAL PUMP,CAPACITY:410 METRE CUBE PER HOUR,HEAD 120 MWC.

    JOCKEY PUMPS (02 NO MOTOR DRIVEN)-

    HORIZONTAL CENTRIFUGAL PUMP,

    CAPACITY:75METRE CUBE PER HOUR, HEAD105MWC BOOSTER PUMPS (01 NO MOTORDRIVEN AND 01 NO ENGINE DRIVEN)HORIZONTAL CENTRIFUGAL PUMP,

    CAPACITY:171METRE CUBE PER HOUR, HEAD45MWC

  • 8/11/2019 Industrial Training in Ntpc

    56/57

    FIRE PROTECTION

    Deluge valve

  • 8/11/2019 Industrial Training in Ntpc

    57/57

    THANK YOU