CON 4003 CVE 4073/5073 COST ESTIMATING HW#2 – RSMeans Estimating Prof. Ralph V. Locurcio, PE

Upload: dylan-fletcher

Post on 31-Dec-2015

240 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: HW#2 – RSMeans Estimating Prof. Ralph V. Locurcio, PE

CON 4003CVE 4073/5073

COST ESTIMATING

HW#2 – RSMeans Estimating

Prof. Ralph V. Locurcio, PE

Page 2: HW#2 – RSMeans Estimating Prof. Ralph V. Locurcio, PE

HW#2 USING RS MEANS

Page 3: HW#2 – RSMeans Estimating Prof. Ralph V. Locurcio, PE

Prob #1- Forms

Prob #1:

Calculate the price to construct 100lf of forms in place for concrete footings.

Footings are 4ft deep; two sides; use continuous plywood, 4 use. Use SFCA (square foot of contact area) for calculations.

Do not include concrete or rebar. Show the price for materials & labor in separate columns and a total cost for the wall, including 10% overhead & profit (combined).

Page 4: HW#2 – RSMeans Estimating Prof. Ralph V. Locurcio, PE

Prob #1 Solution

Prob #1

03 11 13.45-0150

Forms in place,

footings, continuous

wall, plywood, 4 use

Two forms are required Walls are 4ft deep x 100lf long = 400 SFCA per form 2 Forms required

                               

   

SFCA = 4' x 150' x 2 ea = 800SFCA

SFCA NA 800 $1.63 $1,304.00 $1.93 $1,544.00 $0.00 $0.00 $3.56 $2,848.00 $3,132.80 $5.10 $4,080.00 20  

    

                  $2,848.00     130.2%    

      

                               

Prob RS Means ItemItem

Description Calculations Units Size

Number

Cost/ Matl Labor/ Labor Equip/ Equip Total/ Total Bare Total Total Value Your

Units Unit Cost Unit Cost Unit Cost Unit (Bare)

Bare w/10% w/O&P w/O&P 0 - 5pts

Score

Page 5: HW#2 – RSMeans Estimating Prof. Ralph V. Locurcio, PE

RSMeans – Concrete Forming

Page 6: HW#2 – RSMeans Estimating Prof. Ralph V. Locurcio, PE

Prob #2 – Bond Beam

Prob #2:

Calculate the price to construct 100lf of concrete block, bond beam.

Use lightweight block, 6” thick

Do not include concrete or rebar. Show the price for materials & labor in separate columns and a total cost for the wall, including 10% overhead & profit (combined).

Page 7: HW#2 – RSMeans Estimating Prof. Ralph V. Locurcio, PE

Prob #2 Solution

Prob #2

04 22 10.16-0525

Concrete block bond beam, not including grout or

reinforcing, lightweight, 6"

thick

Bond beam is only the top course in the wall so you only need 1 row of blocks, pricing is per LF

                               

   

One row of blocks is required; 100lf long

LF NA 100 $2.55 $255.00 $2.10 $210.00   $4.65 $465.00 $511.50 $6.25 $625.00 20  

    

                  $465.00     122.2%    

Prob RS Means ItemItem

Description Calculations Units Size

Number

Cost/ Matl Labor/ Labor Equip/ Equip Total/ Total Bare Total Total Value Your

Units Unit Cost Unit Cost Unit Cost Unit (Bare)

Bare w/10% w/O&P w/O&P 0 - 5pts

Score

Page 8: HW#2 – RSMeans Estimating Prof. Ralph V. Locurcio, PE

RSMeans – Bond Beam

Page 9: HW#2 – RSMeans Estimating Prof. Ralph V. Locurcio, PE

Prob #3 – Steel Columns

Prob #3:

Calculate the total cost for 16 structural steel columns, concrete filled, extra strong pipe 8” diameter. Each column is 34’ long.

Columns are shop fabricated for 100ton; 2 story project; bolted connections.

Show costs for materials, labor, equipment and a total cost for all the columns. Do not include a cost for overhead & profit.

Page 10: HW#2 – RSMeans Estimating Prof. Ralph V. Locurcio, PE

Prob #3

05 12 23.17-0940

Columns, structural, recycled

materials; shop fab'd for 100-ton, 1-2

story project, bolted con, 8"

diameter

Provide 16 ea. columns; each 34lf long

                               

   

16ea columns x 34lf long

LF 34 16 $65.50 $35,632.00 $1.60 $870.40 $1.47 $799.68 $68.57 $37,302.08 $41,032.29 $76.50 $41,616.00 25  

    

                  $37,302.08     101.4%    

      

                               

Prob #3 Solution

Prob RS Means ItemItem

Description Calculations Units Size

Number

Cost/ Matl Labor/ Labor Equip/ Equip Total/ Total Bare Total Total Value Your

Units Unit Cost Unit Cost Unit Cost Unit (Bare)

Bare w/10% w/O&P w/O&P 0 - 5pts

Score

Page 11: HW#2 – RSMeans Estimating Prof. Ralph V. Locurcio, PE

RSMeans – Steel Columns

Page 12: HW#2 – RSMeans Estimating Prof. Ralph V. Locurcio, PE

Prob #4 Stud Wall

Prob #4:

Calculate the total cost for 2” x 4” wall framing (studs). Wall is 150’ long x 8’ high. Use a pneumatic nail gun. Cost for the nail gun and nails are included in the RS Means prices. Show the individual costs for materials & labor and the total cost for the wall, including 10% overhead & profit.

 

Page 13: HW#2 – RSMeans Estimating Prof. Ralph V. Locurcio, PE

Prob #4 Solution

Prob #4

06 11 10.40-5146

Wood framing, 2 x 4 studs, 8'

high wall

Construct 150lf of 2x4 wall; use pneumatic nailer; cost for nail gun & nails are included in RSMeans cost.

                               

   

150lf of 2x4 stud wall

LF 2x4x8 150 $0.33 $49.50 $0.41 $61.50   $0.74 $111.00 $122.10 $1.04 $156.00 20  

    

                  $111.00     127.8%    

      

                               

Page 14: HW#2 – RSMeans Estimating Prof. Ralph V. Locurcio, PE

RSMeans – Wood Framing

Page 15: HW#2 – RSMeans Estimating Prof. Ralph V. Locurcio, PE

Prob #5 Asphalt RoofingProb #5:

Calculate the cost for asphalt roll roofing for a flat roof 100’ x 47’.

Use asphalt, mineral surface roofing, 1 ply, #15 organic felt, 1 ply, mineral surfaced, selvage roofing, lap 19”, nailed and mopped. Roll roofing comes in standard 36” rolls Prices for nails & mopping are included. Prices are quoted per square = 100sf.

Show the individual costs for materials, labor & equipment and the total cost for the wall, including 10% overhead & profit.

Page 16: HW#2 – RSMeans Estimating Prof. Ralph V. Locurcio, PE

Prob #5 Solution

Prob #5

07 58 10.10-0300

Asphalt roll roofing, 1 ply, #15 organic felt,

mineral surfaced, selvage roofing, lap 19", nailed &

mopped

Provide asphalt roll roofing for flat roof 100lf x 47lf

                               

   

Roof area = 47' x 100' = 4700 sf / 100 = 47 squares

SQ 4700 47 $60.50 $2,843.50 $54.50 $2,561.50 $15.15 $712.05 $130.15 $6,117.05 $6,728.76 $182.00 $8,554.00 25  

    

                  $6,117.05     127.1%    

      

                               

Prob RS Means Item

Item Description Calculations Units Size

Number

Cost/ Matl Labor/ Labor Equip/ Equip Total/ Total Bare Total Total ValueYour

Units Unit Cost Unit Cost Unit Cost Unit (Bare)

Bare w/10% w/O&P w/O&P 0 - 5pts

Score

Page 17: HW#2 – RSMeans Estimating Prof. Ralph V. Locurcio, PE

RSMeans – Roll Roofing

Page 18: HW#2 – RSMeans Estimating Prof. Ralph V. Locurcio, PE

Prob #6 Wood Doors

Prob #6:

Calculate the cost to purchase and install 35 residential wood doors.

Doors are Luan, solid core, 1 ¾” thick, 7’0” high and 3’4” wide.

Show the individual costs for materials, labor & equipment and the total cost for the wall, including 10% overhead & profit.

Page 19: HW#2 – RSMeans Estimating Prof. Ralph V. Locurcio, PE

Prob #6 Solution

Prob RS Means Item

Item Description Calculations Units Size

Number

Cost/ Matl Labor/ Labor Equip/ Equip Total/ Total Bare Total Total ValueYour

Units Unit Cost Unit Cost Unit Cost Unit (Bare)

Bare w/10% w/O&P w/O&P 0 - 5pts

Score

Prob #6

08 14 33.20-1840

Residential wood doors, Luan, solid core, 1 3/4" thick;

7'0" high; 34" wide

Install 35 Luan solid wood doors

                               

   

35 doors

EA. 7'0" 35 $207.00 $7,245.00 $33.50 $1,172.50   $240.50 $8,417.50 $9,259.25 $283.00 $9,905.00 20  

      

                    $8,417.50     107.0%    

Total 130  

% 100%  

Page 20: HW#2 – RSMeans Estimating Prof. Ralph V. Locurcio, PE

RSMeans – Wood Doors

Page 21: HW#2 – RSMeans Estimating Prof. Ralph V. Locurcio, PE

My SolutionConstruction Cost Engineering

Name: Solution     HW # 1   Date:      

Prob RS Means Item Item Description Calculations Units Size

Number Cost/ Matl Labor/ Labor Equip/ Equip Total/ Total BareTotal Total

Units Unit Cost Unit Cost Unit Cost Unit (Bare) Bare w/10% w/O&P w/O&P

Prob #1 03 11 13.45-0150 Forms in place, footings, continuous wall, plywood, 4 use

Two forms are required Walls are 4ft deep x 100lf long = 400 SFCA per form 2 Forms required

                           

   

SFCA = 4' x 150' x 2 ea = 800SFCA

SFCA NA 800 $1.63 $1,304.00 $1.93 $1,544.00 $0.00 $0.00 $3.56 $2,848.00 $3,132.80 $5.10 $4,080.00

   

 

                  $2,848.00     130.2%

     

 

                           Prob #2 04 22 10.16-0525 Concrete block bond beam, not

including grout or reinforcing, lightweight, 6" thick

Bond beam is only the top course in the wall so you only need 1 row of blocks, pricing is per LF

                           

   

One row of blocks is required; 100lf long

LF NA 100 $2.55 $255.00 $2.10 $210.00   $4.65 $465.00 $511.50 $6.25 $625.00

   

 

                  $465.00     122.2%

     

 

                           Prob #3 05 12 23.17-0940 Columns, structural made from

recycled materials; shop fab'd for 100-ton, 1-2 story project, bolted

connections. 8" diameter

Provide 16 ea. columns; each 34lf long

                           

   

16ea columns x 34lf long

LF 34 16 $65.50 $35,632.00 $1.60 $870.40 $1.47 $799.68 $68.57 $37,302.08 $41,032.29 $76.50 $41,616.00

   

 

                  $37,302.08     101.4%

     

 

                           Prob #4 06 11 10.40-5146 Wood framing, 2 x 4 studs, 8'

high wallConstruct 150lf of 2x4 wall; use pneumatic nailer; cost for nail gun & nails are included in RSMeans cost.

                           

   

150lf of 2x4 studd wall

LF 2x4x8 150 $0.33 $49.50 $0.41 $61.50   $0.74 $111.00 $122.10 $1.04 $156.00

   

 

                  $111.00     127.8%

     

 

                           Prob #5 07 58 10.10-0300 Asphalt roll roofing, 1 ply, #15

organic felt, mineral surfaced, selvage roofing, lap 19", nailed &

mopped

Provide asphalt roll roofing for flat roof 100lf x 47lf

                           

   

Roof area = 47' x 100' = 4700 sf / 100 = 47 squares

SQ 4700 47 $60.50 $2,843.50 $54.50 $2,561.50 $15.15 $712.05 $130.15 $6,117.05 $6,728.76 $182.00 $8,554.00

   

 

                  $6,117.05     127.1%

     

 

                           Prob #6 08 14 33.20-1840 Residential wood doors, Luan,

solid core, 1 3/4" thick; 7'0" high; 34" wide

Install 35 Luan solid wood doors

                           

   

35 doors

EA. 7'0" 35 $207.00 $7,245.00 $33.50 $1,172.50   $240.50 $8,417.50 $9,259.25 $283.00 $9,905.00

     

 

                    $8,417.50     107.0%