Career Fair-homework Attend the Annual Career Fair that will be held in the Clemente Center on October 3d from 1000am to 300pm. Interview at least 3 of the employers who hire civil engineers Turn in a summary sheet of the information you obtained (see syllabus for due date) Give your resume & cover letter to a prospective firms you might like to work forTRANSCRIPT
![Page 1: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/1.jpg)
CVE 4070
Construction EngineeringProject Budget & Cost ControlProf. Ralph V. Locurcio, PE
![Page 2: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/2.jpg)
Career FairFlorida Institute of Technology
FALL CAREER FAIR 2007Wednesday, October 3, 2006
10:00 a.m. - 3:00 p.m.Clemente Center
OPEN ONLY TO FLORIDA TECH STUDENTS & ALUMNI
List of firms: http://www.fit.edu/career/2007CareerFair.html
![Page 3: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/3.jpg)
Career Fair-homework Attend the Annual Career Fair that will be held in
the Clemente Center on October 3d from 1000am to 300pm.
Interview at least 3 of the employers who hire civil engineers
Turn in a summary sheet of the information you obtained (see syllabus for due date)
Give your resume & cover letter to a prospective firms you might like to work for
![Page 4: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/4.jpg)
Career Fair-interviews Name each of the companies that you
interview and include the following in your summary as a minimum:
•What type of services do they provide?•Who are the principal clients or customers?•Do they employ civil engineers?•What types of jobs are they hiring for?•What are typical responsibilities for entry level engineers?•Do they have a development program for young engineers?•Do they use project management?•How are their project managers trained?•How are personnel evaluated? •Is a PE license required?•What benefits are provided: health, 401k, dental, vacation? •Does the employer participate in paying for these benefits?•Would you like to work for this company?
![Page 5: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/5.jpg)
Career Fair Homework…
![Page 6: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/6.jpg)
Notebook items to date… 1-Course Syllabus & Update(s) 2-Construction Tour Worksheet 3-Disaster Recovery Class Handout (Blackboard) 4-Career Fair Interview 5-Final Resume 6-Pyramid Study-Handout & Homework 7-Pyramid Schedule 8-Pyramid Cost Estimate 9-Construction Change Order 10-Handout on Cost Estimating 11-Test #1 12-Test #2 13-Test #3 14-Handout on Legal Issues in Construction 15-Class Notes
![Page 7: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/7.jpg)
Project Controls
![Page 8: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/8.jpg)
Accuracy of cost estimates
![Page 9: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/9.jpg)
How do you eat an elephant?
![Page 10: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/10.jpg)
One bite at a time!!!
![Page 11: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/11.jpg)
Cost of Change
0% 50% 100% Concept Design Construction
![Page 12: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/12.jpg)
Work Breakdown Structure (WBS)Systematically break down the total scope of work into logical, independent & manageable task elements; each with it’s own budget and schedule so that each task & budget can be tracked as work progresses.
Level I – Major Element – Building, Roadway, Bridge…Level II – Components – Sitework, Foundation, Frame…Level III – Component Tasks – Excavate, Pile, Cap…Level IV – Task Sequence – Form, Rebar, Concrete…Level V – Task/time – Shop Drawing/5, Cut & Fab/9…Level VI – Assignment – John, Jim, Jane
![Page 13: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/13.jpg)
![Page 14: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/14.jpg)
Work Breakdown Structure
Level 1
Level II
Level III
Level IV
![Page 15: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/15.jpg)
Work Breakdown by Cost Account
![Page 16: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/16.jpg)
Charging work
![Page 17: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/17.jpg)
Work Breakdown by cost account
![Page 18: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/18.jpg)
Costs to be tracked
![Page 19: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/19.jpg)
Sum of all work packages
![Page 20: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/20.jpg)
Time Phased Budget Control
![Page 21: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/21.jpg)
![Page 22: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/22.jpg)
Hidden Costs
![Page 23: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/23.jpg)
Worker Productivity
![Page 24: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/24.jpg)
Cost Monitoring… Cost categories
Labor or field forces Overhead costs Materials & supplies Support services Consultant services
Cost control chart S-Curve format Schedule of values Generally monthly plot
Performance plot
![Page 25: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/25.jpg)
Month 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Schedule-$ 10 10 12 1424 36 66 88
105 111 110 115 87 76 55 34 22 13 9 2 0
Cum - S$ 10 20 32 4670 106 172 260
365 476 586 701 788 864 919 953 975 988 997 999
999
Actual - $ 12 16 18 2226 30 50 70 88 87 110 116 99 96 64 30 33 22 6 4 0
Cum - A$ 12 28 46 6894 124 174 244
332 419 529 645 744 840 904 934 967 989 995 999
999
Schedule of Values & S-CurvePlanned Monthly Payments
![Page 26: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/26.jpg)
Month 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Schedule-%
1.0
1.0
1.2
1.4
2.4 3.6 6.6 7.8
10.5
10.0
10.0 9.0 8.5 7.7 4.6 4.2 3.5 2.8 2.5 1.7 0.0
Cum - S%1.0 2
3.2
4.6 7
10.6
17.2 25
35.5
45.5
55.5
64.5 73
80.7
85.3
89.5 93
95.8
98.3
100
100
Actual - % 11.6
1.8
2.2
2.6 3 5 7 8.8 8.7 11
11.6 9.9 9.6 6.4 3.1 3.3 2.3 0.6 0.5 0
Cum - A% 12.6
4.4
6.6
9.2
12.2
17.2
24.2 33
41.7
52.7
64.3
74.2
83.8
90.2
93.3
96.6
98.9
99.5
100
100
Performance PlotPercent Complete(Based on $$$$)
![Page 27: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/27.jpg)
Progress
Payments ($000)
Month 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Schedule-$ 10 10 12 14 24 36 66 88 105 111 110 115 87 76 55 34 22 13 9 2 0
Cum - S$ 10 20 32 46 70 106 172 260 365 476 586 701 788 864 919 954 976 989 9981000
1000
Actual - $ 12 16 18 22 26 35 55 90 101 110 110 112 88 80 58 30 21 10 5 1 0
Cum - A$ 12 28 46 68 94 129 184 274 375 485 595 707 795 875 933 963 984 994 9991000
1000
Cum - A$/10
1.2
2.8
4.6
6.8
9.4
12.9
18.4
27.4
37.5
48.5
59.5
70.7
79.5
87.5
93.3
96.3
98.4
99.4
99.9 100 100
Schedule-%
1.0
1.0
1.2
1.4
2.4 3.6 6.6 7.8
10.5
10.0
10.0 9.0 8.5 7.7 4.6 4.2 3.5 2.8 2.5 1.7 0.0
Cum - S%1.0 2
3.2
4.6 7
10.6
17.2 25
35.5
45.5
55.5
64.5 73
80.7
85.3
89.5 93
95.8
98.3 100 100
Actual - % 11.4
1.5
1.4
2.6 3.5 5.5 9
10.1 11 11
11.6 8.8 8.8 5.8 3.1 2.7 1 0.5 0.1 0
Cum - A% 12.4
3.9 5 6 9.5 12 21 33 54 65 70
78.8 80
85.8 88 88 88 88 88 88
Performance Plot - Forecast
![Page 28: CVE 4070 Construction Engineering Project Budget Cost Control Prof. Ralph V. Locurcio, PE](https://reader035.vdocuments.us/reader035/viewer/2022062413/5a4d1b697f8b9ab0599b23e9/html5/thumbnails/28.jpg)
Progress
Payments ($000)
Month 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Schedule-$ 10 10 12 14 24 36 66 88 105 111 110 115 87 76 55 34 22 13 9 2 0
Cum - S$ 10 20 32 46 70 106 172 260 365 476 586 701 788 864 919 954 976 989 9981000
1000
Actual - $ 12 16 18 22 26 35 55 90 101 110 110 112 88 80 58 30 21 10 5 1 0
Cum - A$ 12 28 46 68 94 129 184 274 375 485 595 707 795 875 933 963 984 994 9991000
1000
Cum - A$/10
1.2
2.8
4.6
6.8
9.4
12.9
18.4
27.4
37.5
48.5
59.5
70.7
79.5
87.5
93.3
96.3
98.4
99.4
99.9 100 100
Schedule-%
1.0
1.0
1.2
1.4
2.4 3.6 6.6 7.8
10.5
10.0
10.0 9.0 8.5 7.7 4.6 4.2 3.5 2.8 2.5 1.7 0.0
Cum - S%1.0 2
3.2
4.6 7
10.6
17.2 25
35.5
45.5
55.5
64.5 73
80.7
85.3
89.5 93
95.8
98.3 100 100
Actual - % 11.4
1.5
1.4
2.6 3.5 5.5 9
10.1 11 11
11.6 8.8 8.8 5.8 3.1 2.7 1 0.5 0.1 0
Cum - A% 12.4
3.9 5 6 9.5 12 21 33 54 65 70
78.8 80
85.8 88 88 94 96 98 100
Performance Plot – With Correction
CorrectiveAction Applied