how the city of san antonio increased payments for street maintenance using lean six sigma
TRANSCRIPT
LEAN SIX SIGMA BLACK BELT PROJECT STORYBOARD CITY OF SAN ANTONIO | TASK ORDER & INVOICING PROCESS TIMING
MARCH 24, 2016 JESSICA M. SHIRLEY-SAENZ PROJECT CONTROL MANAGER | TRANSPORTATION & CAPITAL IMPROVEMENTS DEPARTMENT
TABLE O
F CO
NT
ENT
S
DEFINE Project Charter | Tools
KEYWORDS 4
EXECUTIVE SUMMARY 3
DMAIC METHODOLOGY 5
MEASURE Data Collection | Baseline Measures | Tools
ANALYZE Root Cause Analysis | Tools
IMPROVE Solutions| Implementation Plan | Charts | Tools
CONTROL Control & Monitoring Plans | Next Steps | Lessons Learned
APPENDIX 23
TASK
OR
DER
& IN
VOIC
ING
TIM
ING
EXECUTIVE SUMMARY
Construction Management Problem Statement
Project Control
Compliance Business Case In April 2014, the City received complaints from on-call task order Contractors regarding how long it takes to receive payment for completing work on street maintenance projects. Contractors alleged that payments were taking longer than it use to, up to 30 or more days to receive. Consequently, if payments are delayed, Contractors and their subcontractors are not paid. If continued, Contractors would no longer bid on City projects which would delay the completion of street maintenance projects city-wide. If street maintenance projects are not completed this will negatively impact and potentially compromise the City’s infrastructure - namely, its safety, transportation conveniences and accessibility.
Project Results
Graphical Display of Improvement Root Cause Analysis Identified delays in efficiently processing task order payments was significantly attributed to: ▪ Payments Rejected for Incorrect Quantities – Due to inconsistent, redundant and non-transparent documentation of approved quantities. ▪ Delayed and Combined Payment Requests (Invoicing) – Due to invoices being submitted long after project completion, an additional review was being required to verify quantities.
Solutions Implemented
▪ Implemented a tolerance threshold for quantity yield calculations to reduce number of rejects for disputed quantity amounts ▪ Implemented new daily quantity process to centralize and standardize the documentation of daily quantities information ▪ Updated the payment workflow so City can invoice on behalf of Contractor to improve timeliness and eliminate the additional review of quantities
▪ Increased overall number of payments processed monthly for street maintenance task orders from an average of 97 payment requests to 116 payment requests ▪ Reduced the overall number of rejected payments for disputed quantity amounts from an average of 17 rejects to 12 rejects ▪ Reduced the overall percentage of rejected payments for disputed quantity amounts from 58% ($21.6 million) to 42% ($15 million)
KEY WORDS Lean Six Sigma Black Belt Project Storyboard
Task Order & Invoicing Process Timing
Construction Management
Responsible for the review and approval of task orders and invoices; and creation as well as closure of Task Order Purchase Orders in the City’s financial system (i.e. SAP).
City Fiscal Accountant
Project Control
Compliance
Contracts
Fiscal
Responsible for inspecting the work Contractors perform to ensure consistency with contract drawings and specification. Inspects the work as acceptable, documents construction quantities and approves payment.
City Inspector
Consists of City’s Project Manager (PM) (customarily, an Engineer) and Project Team. Oversees the work Contractors perform, is consistent with the contract drawings and specifications, affirms the completed work as acceptable, submits task orders and approves payment.
City Project Team
Responsible to perform construction work as defined by the contract drawings and specifications.
Contractor
Is a PRIMELink form used by the Contractor or City to bill (i.e. invoice) on behalf of the Contractor for work completed.
Payment Request
Is a hosted enterprise capital improvements project portal system. It manages the electronic routing and storage of capital project documents such as Task Orders, Invoices, Payment data and all other associated project documents (i.e. change orders, contracts, plans, RFIs, submittals, etc…).
PRIMELink System
Quantities refer to the itemized list of work, materials and any cost related items supplied by the contractor in order to complete the requested work. Actual billable quantities are verified by a City Inspector and included in the Payment Request so the Contractor is paid for those items.
Quantities
Is a PRIMELink form used by the City to authorize work consistent with the scope of the contract and within the existing contract dollar authorization. It is needed to create a Purchase Order (PO) for work to be completed.
Task Order
Transportation and Capital Improvements Department (TCI) oversees and directs the development and maintenance of the publicly owned infrastructure of the City of San Antonio.
TCI
DEFIN
E PROJECT CHARTER
Construction Management Problem Statement
Project Control
Compliance
Contracts
Goal Statement
Scope In/Out
Problem Statement
Timeline
Team Members
Business Case & Benefits On-call task order Contractors are complaining about how long it takes to receive payment after completing work on street maintenance projects. The average standard processing time is 13 days, if all of the quantities are correct and scope of work is pre-approved prior to the start of work.
POSITION PERSON
Executive Sponsor Mike Frisbie, TCI Director
Project Champion(s) Anthony Chukwudolue, TCI Streets Asst. Director
Debbie Racca-Sittre, TCI Support Services Asst. Director
Razi Hosseini, TCI Project Delivery Asst. Director
The goal is to increase the number of payment requests processed by decreasing the number of rejected invoices for disputed quantity amounts by 10% or more by the end of 4th Quarter in FY 2015 (September 2015) .
In Scope: Street Maintenance City Construction Task Order Contracts, Process Steps (Including Task Order, Payment & Associating Processes), System Upgrades Out of Scope: Street Maintenance Utility (Electric, Gas or Sewer) Work Task Orders
Improved timeliness of payment requests to Contractors will result in more timely payments to Subcontractors and restore Contractors’ confidence with the City’s invoicing process (as more reliable). Which will translate to Contractors wanting to continue to bid on City street maintenance projects; and, allow the City to release funds that would otherwise remain encumbered delaying completion of other projects.
PHASE PLANNED ACTUAL
Define April 28, 2014 April 28, 2014
Measure May 19, 2014 May 26, 2014
Analyze July 24, 2014 July 24, 2014
Improve August 25, 2014 *April 2, 2015
Control September 1, 2014 *August 3, 2015
*Project delays attributed to: (1) Team awaiting for completion
of FY 2015 budget to buy laptops needed for TCI inspectors to complete the new daily quantity log in the field.
(2) Team awaiting start of new
Street Maintenance Task Order contracts.
POSITION PERSON
Project Manager Jessica M. Shirley-Saenz
Core Team Members Contractors Fiscal PRIMELink Manager TCI Streets Engineering Project Teams TCI Inspectors
DEFIN
E SIPOC
Key Take Away: The scope of this project begins with the planning of the task order and includes when the work is initiated up through inspection of the work, ending with the payment for the work completed.
S I P O C Supplier Input Process Output Customer
Work Planning Agreed Upon Project Scope Planning Payment Contractor
Contractor Defined Project Limits Initial Phase of Task Order Completed Project Work
(City) Project Team Estimated Quantities Define Project Scope & Quantities Inspected Work
(City) Inspector Completion of Work Agreed Upon Quantities
Work Task Creation Inspection of Work Creation
Contractor Quantity Verification Task Order (Authorization/Approval of Work)
(City) Project Team
Work Completion
(Contractor) Work Crew Execution (Contractor) Superintendent Work Completion
CUSTOMER REQUIREMENTS (City) Inspector Inspection & Quantity Verification
Payment Timely & Consistent Payment
(Contractor) Fiscal Rep Payment Transparency
(Contractor) Superintendent Payment Request Creation Improved Communication
(City) Project Team Payment Request Approval
(City) Inspector
Close-Out Close-Out
(Contractor) Fiscal Rep Project Completion
(City) Project Team Coordination of Final Payment
(City) Inspector Final Task Order Completion
DEFIN
E VOICE OF THE CUSTOMER
Construction Management Problem Statement
Project Control
Compliance
Contracts
Fiscal
Customer Comment Gathering More Understanding Customer Requirement
“It takes forever to receive payment for work I complete”
Contractor not receiving payments timely Payments should be processed within 13 days or less
“I can’t invoice because the task order isn’t even processed yet”
Contractor completes work prior to task order being processed
Require the task order must be processed prior to work start
“I don’t submit invoices anymore because they just get rejected”
Contractor stop submitting payments because payments are rejected for incorrect quantities
Quantities are documented and accessible daily and agreed upon daily
“I’d be happy if I could just get paid for the work quantities we do agree upon, we can work out the ones we disagree with later”
Once the payment request is submitted the Contractor nor the City can modify or remove quantity pay items; one disputed item out of a list of many will hold up an entire Payment Request
Should have ability to generate an Payment Request with approved quantities only and pend disputing quantities until resolved
“I have to wait for quantities and when I do get them I have to hunt through emails or call inspector for quantities”
City Inspector documents quantities on various manual logs and provides quantities manually to the City’s Project Team and Contractor through email or by phone
Establish a consistent and standard process to document and provide quantity information to City staff and Contractor
Key Take Away: Project needs to address the documentation process of a project’s daily quantities. Specifically, the standardization, accessibility and consistency. Standardization of this process will help identify and rectify quantity errors in a more timely manner which will help reduce the number of rejected payments and in turn increase the number of timely payments made.
MEA
SUR
E DATA COLLECTION PLAN
Measure Data Type Operational Definition Stratification Factors Sampling Notes Who and How
Total Number of Task Orders
Continuous Street Maintenance City Task Orders not rejected . All task orders with a “Complete” status.
By Contractor By Purchase Order Line
Sample includes every task order processed in *Fiscal Years 2012 through 2015.
Project Lead retrieve from PRIMELink Administrator/PRIMELink
Total Number of Payments Processed
Continuous Street Maintenance City Payment Requests not rejected . All Payment Requests with a Payment Date.
By Contractor By Purchase Order Line
Sample includes every payment request processed in *Fiscal Years 2012 through 2015.
Project Lead retrieve from PRIMELink Administrator/PRIMELink
Timeliness of Payments Processed
Continuous Number of days to process payment. calculated by taking the difference between Payment Request creation date and payment date. List of payments processed within 30 days.
By Contractor By Payment Date By Day Ranges [5 days, 10 days, 15 days, 30 days and 30 days+]
Sample includes every payment request processed in *Fiscal Years 2012 through 2015.
Project Lead retrieve from PRIMELink Administrator/PRIMELink
Total Number of Payments Rejected
Continuous Street Maintenance City Payment Requests rejected. All payment requests with a “Rejected” status.
By Contractor By Reject Date
Sample includes every rejected payment request in *Fiscal Years 2012 through 2015.
Project Lead retrieve from PRIMELink Administrator/PRIMELink
Reject Types Discrete List of reasons for rejects. None Sample includes feedback retrieved from the contractor (with largest volume) and city staff approvers (inspectors, project team & fiscal)
Project Lead retrieve from interviews document top reasons and tally
Total Number of Rejected Payments by Reject Reason
Continuous Street Maintenance City Payment Requests rejected by the identified reasons retrieved from sampling above.
By Reject Reason Sample includes every rejected payment request processed in *Fiscal Years 2012 through 2015.
Project Lead from PRIMELink Administrator/PRIMELink
Key Take Away: Project lead is responsible for all data collection – team and subject matter experts (SMEs) made the appropriate adjustments to provide and/or make themselves available to accommodate the request for information.
*Fiscal Year = October 1st – September 30th
Task order Street Maintenance payment requests processed between October 2012 to June 2014 (1,531 Payment Requests valued at $69.3 million) was analyzed to understand within how many days are these payment requests being processed.
It is City’s policy that vendors (i.e. Contractors) be paid by the City within 30 days of the date a correct Payment Request is submitted for work performed for the City. The TCI department’s overall average payment processing time is 11 days.
Pareto shows that 95% of the Street Maintenance payment requests processed between October 2012 to June 2014 were processed within 30 days; and, less than 5% of the payment requests took more than 30 days to process.
BASELINE MEASURE Payment Request Timeliness
36% 34%
18%
7% 5%
DATA SUMMARY
Key Take Away: Average processing time for task order Street Maintenance payment requests is 13 days. Data shows that 95% of Street Maintenance payment requests when submitted with no issues were processed within 30 days.
Baseline Oct. 2012 - June 2014
BASELINE MEASURE Payment Rejects
Task order Street Maintenance payment requests rejected between October 2012 to June 2014 (322 valued at $21.6 million) was analyzed to understand the volume and reasons for rejected payment requests.
The Pareto shows that that payment requests were rejected for Disputed Amounts (83%) followed by Utility related disputes (14%) and Budget Adjustment (3%).
DATA SUMMARY
Key Take Away: Rejected payment requests delay payments made to the Contractor. Baseline data shows Street Maintenance payment requests are rejected more often for disputed amounts than any other reject reason. Team planned on gathering additional information from process experts to help identify what is causing the amounts to be disputed.
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0
50
100
150
200
250
300
Disputed Amount Utility Budget Adjustment
Num
ber
of R
ejec
ts
83%
14%
3%
Baseline Oct. 2012 - June 2014
AN
ALY
ZE
FISHBONE DIAGRAM
TOOLS
REPORTING
CITY PROCESS PAYMENTS
CITY PROCESS TASK ORDERS CITY STAFF
CONTRACTOR
No Transparency [For Quantities]
Inconsistent Documentation
Work Completed or Initiated Prior to Task Order
Approval Sequencing [Contractor Not Aware of Utility Rejects]
Task Order Not Processed
Rejected Payments
Quantity Discrepancies
Lack of Connectivity to PRIMELink in
the Field
Tracking & Report Duplication [Inspector, Project Team & Vendor Separately
Track]
Delayed Communication
Untimely Payment Request Submissions
Combining Payment Requests
Delayed Processing of Payment Requests (Payments to Contractors)
No Standardization [For Quantities]
Limited Accessibility [For Quantities]
Inconsistent Material “Ticket” Submissions
Delayed Utility Approvals
Key Take Away: Root Cause Analysis will focus on Daily Quantity documentation/reporting process and Payment Process.
Why are Payment Requests rejected for disputed amounts? -Contractor quantities included in Payment Request do not match City’s verified quantities -Why? Verified daily quantities information is not easily accessible or consistently provided to confirm quantities are correct -Why? Documentation and delivery of daily quantities varies by City Inspector - Why? There currently is no standard documentation and reporting process for daily quantities
AN
ALY
ZE
HYPOTHESIS TESTING RESULTS
Possible X Root Cause Hypothesis Hypothesis Test Results
Payment Request Time Period
Processing of Street Maintenance Task Order Payment Requests takes longer than it used to
One-Sample Sign False
Task Order Time Period
Processing of Street Maintenance Task Order takes longer than it used to
One-Sample Test False
Rejects
There are more payment request rejects than there used to be
One-Sample Sign True
Reject Types
Number of rejects seems to be higher for certain reject reasons
Mood’s Median True
Key Take Away: Hypothesis tests confirmed that rejected payments was a key area of focus.
ONE SIGN HYPOTHESIS TEST Hypothesis: Total payment processing time is taking longer than it use to.
Key Take Away: There was no significant change in total payment processing time. However, since “payment processing time” was a “critical X” and identified by the Contractor’s as a significant issue, the team decided they needed to complete some further analysis. The team discovered the data retrieved from PRIMELink did not capture the time expended from the Contractor with-holding and not submitting Payment Requests in PRIMELink to avoid Payment Requests from being rejected. If the with-holding days were accounted for then the total payment processing time would have reflected as taking longer than it use to. With this, the team then focused on what was causing the Contractor to not to enter payment requests in PRIMELink .
Team looked at the current payment processing time and compared it to the historical target.
P-value less than 0.05, so team rejected the null hypothesis (Ho).
Result - Total payment processing isn’t taking longer than it use to, i.e. there is no significant change in total payment processing time.
DATA SUMMARY
ONE SIGN HYPOTHESIS TEST Hypothesis: There are more payment request rejects than there use to be.
Key Take Away: There are more payment request rejects than there use to be. There was a total of 146 rejects in FY 2013 and 227 rejects in FY 2014. Improvement focused on the rejected Payment Requests. More specifically, why they are being rejected and how we can reduce the number of rejects to increase the number of payments .
Team looked at the historical reject volume and compared it to the historical target.
P-value is greater than 0.05, so team failed to reject the null hypothesis (Ho).
Result - There are more payment request rejects than there use to be.
DATA SUMMARY
0
5
10
15
20
25
30
Num
ber
of R
ejec
ts
Run Chart
MOOD’S MEDIAN TEST Hypothesis: Number of rejects seems to be higher for certain reject reasons
Key Take Away: Mood’s Median test confirmed there is a significant difference in the number of rejects for certain reject reasons. Data reflects that Payment Request rejects are largely attributed to disputed amounts. Team focused on identifying root causes and solutions on how to reduce rejects for disputed amounts.
Team met with staff and Contractor to retrieve information on reasons why Payment Requests are rejected and compared it to the reject data retrieved from PRIMELink.
P-value less than 0.05, so team rejected the null hypothesis (Ho).
Result: There is a significant difference in the number of rejects for certain reject reasons.
DATA SUMMARY
IMPRO
VE
IMPACT & EFFORT MATRIX Impact Effort Matrix
Objective: Increase Overall Number of Invoices Processed On-Time
Sponsor: TCI Project Delivery, Streets and Support Services Asst. Directors
Stakeholder: Contractor
High Impact
Hard Easy
Low Impact
1. Update PRIMELink workflows to optimize the sequencing of task order and payment request approval steps (i.e. adding the City as a Payment Request submitter and enabling the copy furnish feature to include Contractor on rejected items).
2. Facilitate the exchange of i-pads for laptop computers so Inspectors can document quantities in the field.
3. Implement a tolerance threshold for yield calculations to minimize quantities rejections for minor quantity threshold discrepancies.
4. Create an inspector quantity log in PRIMELink to allow inspector to log and track quantities and allow all authorized users (including the Contractor) to view quantities.
5. Document and implement a new quantity authorization process which will entail the documentation, acknowledgement and agreement of approved quantities.
6. Change invoicing process such that the City will create and initiate the Payment Request on behalf of the Contractor based on approved documented quantities.
1
2
3 4
5
6
Key Take Away: Leveraging the low/high impact quadrant, the team was able to prioritize the implementation of the solutions. Implementing “quick wins” first and gradually all of the rest the solutions as follows: 3, 1, 2, 4, 5 and 6.
IMPRO
VE
INNOVATION TRANSFER OPPORTUNITIES
PROCESS IMPROVEMENT [Innovation/Addition/Change/Removal]
PROCESS BENEFITS
IMPACTED ENTITY
[Area/Department/Business Unit]
Update task order PRIMELink workflow (i.e. enabled the copy furnish feature to include Contractor on rejected task orders)
• Expedites action needed on rejected task orders • Reduces time needed to process task order so payment requests can be submitted
• Contractor • Streets Engineering Project Team
Update payment request PRIMELink workflow (i.e. added the City as a Payment Request submitter)
• Provides Contractor option to continue to invoice or permit the City to invoice on their behalf
• Contractor • Fiscal
Implemented 5% tolerance threshold for quantity yield calculations
• Minimize and eliminate the unnecessary rejection of payment requests due to quantity discrepancies
• Contractor • Inspector
Established connectivity to PRIMELink for Inspectors in the field (i.e. facilitated the purchase and exchange of i-pads for laptops for all TCI Inspectors)
• Inspectors able to remotely access PRIMElink and shared drives in the field • Allow for near real time data entry of daily quantities, reports and approvals • Promote documentation standardization (i.e. provide a centralized and easily accessible way to report) • Eliminated the need for inspectors to drive to and from a service center to upload data, thus allowing more time to be spent in the field
• Inspector
Implemented new daily quantity log documentation and reporting process
• Improved transparency and communication • Report standardization • Reduce payment requests for incorrect quantities
• Contractor • Inspector •Streets Engineering Project Team
Implemented City initiated payment request (invoicing) process • Ensures timely and consistent payments based on approved quantities
• Contractor • Fiscal
IMPRO
VE
BEFORE & AFTER PAYMENT REQUEST REJECTS
Key Take Away: Implemented solutions decreased total number of payments rejected for disputed quantity amounts by 17% achieving the project goal of decreasing the number of rejects for disputed quantity amounts by 10% or better.
Fiscal Year Oct. 1 – Sept. 30
42% [ $15.1M] REJECTED
58% [ $21.6M] REJECTED
Mean: 15.10
0
5
10
15
20
25
30
Run
Cha
rt: D
ata
Run Chart
IMPRO
VE
RISK MANAGEMENT
Key Take Away: For each identified risk, leveraged training, visual management/procedural guides, system and/or procedural controls where needed to mitigate risks and proactively elevate issues.
CO
NT
ROL
MONITORING & RESPONSE PLAN MONITORING PLAN
MEASURE INPUT/OUTPUT/
PROCESS TRIGGER MEASURES MEASURMENT METHOD
CHECKING FREQUENCY
WHO MEASURES
Daily Quantities Timing Input Daily Quantity Log must be completed within 48 hours; No later than Tuesdays End of Day
Time Stamp When Log is Completed Daily Inspector Supervisor
Daily Quantities Discrepancies Output Zero quantity discrepancies prior to invoicing date (within two weeks of quantities being posted)
Time Stamp When Log is Completed Daily Contractor
Total Payment Requests Timing Process No greater than 15 days (Upper Control Limit) Time Stamp from When Payment Request is Submitted to When Payment Request is Paid
Monthly Fiscal Accountant
Total Number of Rejects Process No greater than 27 rejects (Upper Control Limit) Total Number of Rejects By Vendor for Disputed Amount
Monthly Performance Management Team
RESPONSE PLAN DAMAGE CONTROL PROCESS ADJUSTMENT EFFECTIVENESS ASSESSMENT CONTINOUS IMPROVEMENT
Daily Quantity Discrepancies Report any quantity discrepancies to the Inspector to either correct the discrepancy or agree to not include in Invoice until discrepancy can be corrected
Determine if discrepancy attributed to typo or missing documentation Project Team to verify quantities daily
Project Team to verify once material tickets are received to what is reflected on daily quantity log, verify daily entry
Corrected Daily Quantity Log Inspector to either (a) correct quantity on the appropriate daily quantity log (only if the log has not already been pulled for invoicing) or (b) create new daily log and reflect the corrected difference
Project Team and Inspector to review Daily Quantity Summary Report to monitor quantity and dollar balances
Project Team through review of balances can as necessary submit appropriate budget adjustment to elevate delays in invoicing; Inspector can know when quantities are not within or exceeding specifications.
Unable to Process Payment Request Due to Insufficient Funds
Report funding insufficiency to Project Manager so that a budget adjustment can be completed.
Project Team will run the summary daily quantity report to monitor potential over runs.
Project Team and Inspector working together to help proactively elevate the need for last minute adjustments at time of invoice rather complete adjustments sooner.
Rejected Payment Requests Fiscal Accountant to work with Contractor and/or Project Team on correction needed. If quantity related, work with Inspector to correct accordingly.
PRIMELink report regarding number of rejects and payment timing will be evaluated monthly.
Team to review control charts to help trigger additional investigation of causes and as needed adjustments to control limits.
Key Take Away: Team devised a monitoring and response plan to help sustain improvements and know how identify as well as handle issues should they arise.
IMPRO
VE
RACI MATRIX
TASK FREQUENCY DUE DATE
Responsibility Approver Consulted Informed The person responsible for producing the deliverable
and/or completing the task.
The person accountable for the deliverable.
The person or persons that must be consulted before a
decision can be made.
The person or persons that must be informed of any
decision that has been made.
Complete Daily Quantity Usage Record Daily Within 48 hours; No Later
than Tuesdays End of Day Inspector Inspector Supervisor Project Manager/Team Construction Management Manager
Run Daily Quantity Usage Reports Weekly or As Needed Wednesdays End of Day Inspector Supervisor Construction
Management Manager Project Manager/Team Project Delivery Assistant Director
Review Daily Quantity Usage Reports Weekly or As Needed Wednesdays End of Day Project Manager/Team Streets Engineering
Manager Inspector Supervisor Streets Assistant Director
Validate Daily Quantities Weekly or As Needed Wednesdays End of Day Contractor Contractor Owner Project Manager/Team Streets Assistant Director
Communicate Daily Quantity Discrepancies As Needed Within 2 Weeks of Quantities
being Posted Contractor Contractor Owner Project Manager/Team Streets Assistant Director
Complete Daily Quantity Discrepancy Revisions As Needed
Within 2 Weeks of Quantities being Posted or PM Team Notification
Inspector Inspector Supervisor Project Manager/Team Contractor
Consolidation of Daily Quantities (for City Issued Payment Requests)
Monthly or As Needed
First Wednesdays of Month or within 48 Hours of Receiving PM Team Notification
Fiscal Accountant Capital Fiscal Manager Project Manager/Team Contractor
Consolidation of Daily Quantities (for Vendor Payment Requests)
Monthly or As Needed Contractor Contractor Owner Project Manager/Team Streets Assistant Director
Creation & Submission of Payment Requests
Monthly or As Needed
First Fridays of Month or within 48 Hours of Receiving PM Team Notification
Fiscal Accountant Capital Fiscal Manager Project Manager/Team Contractor
Notification of Overruns Daily As Needed Project Manager/Team Streets Engineering Manager Inspector Supervisor Streets Assistant Director
Creation & Submission Task Orders (for Overruns or Project Close-Out) Daily As Needed Project Manager/Team Streets Engineering
Manager Inspector Supervisor Streets Assistant Director Updating Major Changes to Standard Operating Procedures Document As Needed As Needed Performance
Management Team Inspector Supervisor Project Manager/Team Project Delivery & Steets Assistant Director
CO
NT
ROL
CONTROL CHART
Key Take Away: Team is continuing to work on causes of variation and control limits. The control charts will be a key part of TCI’s on-going monitoring of the process in identifying ways to improve and address issues. As a result, of the immediate success of the 6-month pilot and overwhelming positive response from Contractors following the pilot, TCI has begun rolling-out the new Daily Quantity Log and Payment Request process for all Street Maintenance Improvement construction contracts and eventually all TCI managed construction contracts.
PAYMENT REQUESTS Avg. Process Timing Trigger = 15 Days or Greater
[Upper Control Limit = 16]
16.49
Mean CL: 12.875
9.26
0
5
10
15
20
25
Indi
vidu
als:
Dat
a
Individuals Control Chart Data UCL CL (Mean) LCL
26.76
15.1025641
3.44
0
5
10
15
20
25
30
C: D
ata
C (Count) Control Chart Rejects Data UCL CL (Mean) LCL
REJECTS No. Rejects Trigger = 20 Rejects or Greater
[Upper Control Limit = 27 Rejects]
NEXT STEPS Black Belt Project Storyboard
Task Order & Invoicing Process Improvement
EXTEND SUSTAIN
COLLABORATE IMPROVE
Roll out daily inspection quantity and invoicing process for all other capital construction contracts.
IMPROVEMENT Coordinate with local utilities to have them begin utilizing new daily inspection quantity and invoicing process for utility work on City projects.
Continue to retrieve feedback from process owner, staff and contractors. Follow through and review monitor and control plans.
Continue quarterly meeting with process owners and users to access process progress, identify ways to improve and address any associated issues.
LESSONS LEARNED
Lessons Learned
Lean Six Sigma methodology is not just applicable to manufacturing operations it can be applied in Municipal business functions and services. Lean Six Sigma methodology has provided a roadmap to not only implement but sustain improvements . Data does matter – performance and its established triggers are essential in maintaining efficient and effective delivery of services/deliverables.
Lean Six Sigma Methodology
Having a clear and consistent communication plan is key in sustaining success and ensuring issues are addressed accordingly. Communication helps fosters better collaboration and a greater awareness of the team’s overall goal and responsibilities.
Communication
Lack of standardized, documented and agreed upon policies/processes leads to variability which results in inconsistency, additional work and potentially costly processing delays. Creating uniform policies and procedures helps reduce confusion and improves communication for City staff and among Contractors. Information regarding policies and procedures should be accessible and easy to understand both for Contractors and City staff.
Standardized Processes
With out the involvement through the project and buy-in of the process owner of the improved process the realized improvements can not be sustained. Simply, “if its not important to the boss its not important to staff.”
Ownership
TASK
OR
DER
& IN
VOIC
ING
TIM
ING
STAKEHOLDER ANALYSIS
Key Take Away: There was no resistance to the process improvement and all appropriate key stakeholders were included as part of the team.
TASK
OR
DER
& IN
VOIC
E TIM
ING
AS-IS PROCESS MAPS
Key Take Away: Understanding the Task Order and associated Payment Process was instrumental in identifying areas of focus and has provided City staff a renewed and visible perspective of the entire process.
TASK
OR
DER
& IN
VOIC
ING
TIM
ING
FIVE (5) WHY’S
Why are Payment Requests rejected?
Why ?: Contractor quantities included in Payment Request do not match City’s verified quantities.
Why ?: Verified daily quantities information is not easily accessible or consistently provided to confirm quantities are correct.
Why?: Documentation and delivery of daily quantities information varies by City Inspector.
Why?: There currently is no standard documentation and reporting process for daily quantities.
Key Take Away: Payment Requests rejected for disputed quantities is attributable to the lack of a defined process and impacts the Contractor, City Project Team and City Inspector.
Expedite Project Delivery and Completion of Infrastructure
Projects City-Wide
City Staff
Contractor
City Processes
Reporting & Tools
MATCHING X & Y MEASURES
Key Take Away: X’s that impact Y (Expedited project delivery and completion of Infrastructure Projects city-wide) are as follows: City Staff (includes Project Team and Inspector), Contractor, City’s Processes and reporting/tools.
X 1 X 2 X 3 X 4 Y City Staff
Communication Report Duplication
Contractor
Communication Consistency
City Processes
Standardization Documentation
Reporting & Tools
Equipment Transparency Standardization Accessibility
Expedite Project
Delivery and Completion of Infrastructure Projects City-
Wide
TASK
OR
DER
& IN
VOIC
ING
TIM
ING
8 WASTES CHECK SHEET
Process Area: Daily Quantity Process
Waste Definition Level Description of Issues
D Defects Information, products and services that are incomplete or inaccurate High
Inconsistent documentation of daily project quantities makes it difficult to research, verify and approve quantities; instances of incorrect quantities more likely
O Overproduction Making more of something - making it earlier or faster- than it's needed High
Redundant and non-transparent documentation (i.e. quantities documented in emails and various manual logs by Contractor, Project Team and Inspectors)
W Waiting Waiting for information, equipment, materials, parts or people Medium
Daily quantities information is not centralized and easily assessable (i.e. project team and vendor have to await for information to be sent by Inspector )
N Non-Utilized Talent Not properly utilizing people's experience, skills, knowledge or creativity Medium
Inspectors are unable to leverage PRIMELink in the field consistently which forces inspectors to track and communicate manually requiring additional time as a opposed to documenting information in the system for all to access
T Transportation Unnecessary movement of materials, information or equipment High
Inspectors not able to document daily quantities in field so Inspectors manually track and transfer information to various logs and emails the same information
I Inventory Accumulation of parts, information, applications, etc. beyond what is required by the customer High
Since there is no daily log in PRIMELink Inspectors manually track quantities in the field and for most they wait until the end of the week or several days so they have to update manual logs and provide updates once
M Motion Any movement by people that is not of value to the customer Medium
Project team, vendor and inspector have to search through manual logs and emails to verify quantities to approve or reject payment requests
E Extra- Processing
Any steps that do not add value in the eyes of the customer Medium Project team, vendor and inspector each track quantities
on their own separate logs same information
TASK
OR
DER
& IN
VOIC
ING
TIM
ING
COMMUNICATION PLAN
Stakeholder Group Objectives/Actions Desired Message Delivery Method Timing
Executives (Project Champions) Inform of project findings, create buy-in and ownership
Results of analysis and hypothesis tests; solutions selected
Share at Regular Scheduled Executive Meeting Within1 Week
Construction Management & Street Engineering Supervisors
Inform of project findings, install confidence in team and process changes
Results of analysis and hypothesis tests; solutions selected Schedule Meeting Within 2 Weeks
Construction Management Inspectors
Inform of project findings, create buy-in and ownership, participate in pilot & roll- out
Pilot results, training and implementation plan Schedule Meeting Within 3 Weeks
Street Engineering Project Manager & Project Team Members
Inform of project findings, create buy-in and ownership, participate in pilot & roll- out
Pilot results, training and implementation plan Schedule Meeting Within 3 Weeks
Fiscal Purchase new laptops , inform of project findings, create buy-in and ownership, participate in pilot & roll-out
Purchasing new hardware, execution dates, training and implementation plan
Email After Executive and Manager Approval
Vendors Inform of project findings, create buy-in and ownership, participate in pilot & roll- out
Pilot results, training and implementation plan Schedule Meeting Within 3 Weeks
Key Take Away: Adhering to Communication Plan was instrumental in making sure the team and its project champions were informed on what was happening with the project and anticipated due dates.
TASK
OR
DER
& IN
VOIC
ING
TIM
ING
IMPLEMENTATION PLAN Plan Do Check Act
Action Responsible Due Date
Plan
Complete Test Task Order and Payment Request Work Flow Changes PRIMELink Manager 07/12/2014
Procure (32) Windows-based Laptops Project Team Leader, Fiscal, Information Technology 11/14/2014
Design Inspector Daily Quantity Log in PRIMELink PRIMELink Manager 12/15/2014
Design Daily Quantity Log Detailed & Summary PRIMELink Reports PRIMELink Manager 12/15/2014
Design Payment Request Detailed & Summary PRIMELink Reports PRIMELink Manager 12/15/2014
Facilitate Exchange I-pads for Laptops Project Team Leader, Fiscal, Construction Management 04/02/2015
Do
Create Inspector Daily Quantity Log in PRIMELink PRIMELink Manager 01/15/2015
Create Daily Quantity Log Detailed & Summary Reports in PRIMELink PRIMELink Manager 02/15/2015
Create Payment Request Detailed and Summary Reports in PRIMELink PRIMELink Manager 02/15/2015
Document Procedures, Visual Management Guide and Control Plan for Inspector Daily Quantity Log and Payment Process
Project Team Leader 04/15/2015
Train PRIMELink Helpdesk, Inspectors, Project Team, Fiscal & Contractor Project Team Leader, PRIMELink Manager 05/08/2015
Che
ck Deploy Pilot [Test Process & New Changes in PRIMELink with (1)
[Willing and Able Contractor] PRIMELink Manager 06/26/2015
Monitor Inspector Daily Quantity Log Completion, Payment Process Timing and Reject Volume for Team
Project Team Leader 07/26/2015
Act
Made Adjustments to Daily Quantity Log and Payment Process Based on Pilot
Project Team Leader, Construction Management Inspectors, Street Engineering Project Team, Fiscal
08/03/2015
Roll Out New Daily Quantity Log and Payment Process for All Other Street Maintenance Construction Contracts
Project Team Leader, Construction Management Inspectors, Street Engineering Project Team, Fiscal
09/01/2015
Key Take Away: Implementation Plan was used to organize key tasks and provide the team an overview of what is to be completed and the team’s role in tasks to be completed.
TASK
OR
DER
& IN
VOIC
ING
TIM
ING
CONTROL CHART
5
1
2 2
2 2
5 5 5
12.88
9.26
16.49
9.0010.0011.0012.0013.0014.0015.0016.0017.0018.0019.0020.0021.0022.00
Indi
vidu
als:
Dat
a
1.36
0.00
4.44
-1.000.001.002.003.004.005.006.007.008.00
MR
: Dat
a
Key Take Away: The I-MR-R chart turned out to be the visual tool to review payment processing time. Team has both a cumulative monthly and daily chart to illustrate the process’s progress and any variation. The Upper Control Limit and Response Plan trigger is 16 days.
I-MR Chart | Monthly Payment Processing Time