HEXICONDoubling up on economy of scale –Hexicon to install 10 MW floating multi turbine platform
3/31/20172
FLOATING FOUNDATIONS
3/31/20173
SEMISUBMERSIBLE PLATFORM
• Three columns with buoyancy tanks provide stability in operational and extreme conditions
• Turret-based single point mooring system
• Facilities which can be installed on the platform or combined with it:o Solar panelso Transformero Fish farmso Desalination
• Quayside commissioning:o Safer working environmento No heavy lift at seao No barges or heavy lift vesselso Turbine erection in dry docko Most Commissioning in dry dock
3/31/20174
MULTI TURBINE PLATFORM
For certain installed power,compared to standalone turbines:
• Less use of sea area• Cost reduction of mooring system• Cost reduction of towing• Two WTGs installed in one operation• Less inter-array cables• Cheaper maintenance
3/31/20175
MULTI TURBINE PLATFORM IN OPERATION
Weather vaning:
• Driven by thrust force
• Yaws about the turret
Will turbine wake interaction cause loss of total power?
• Peer-reviewed research results indicate some increase in power compared to two isolated turbines (simulation models and wind tunnel tests, e.g. [1,2])
• No need to curtail or shut down any of the turbines due to misalignment.
[1] Local blockage effect for wind turbines, Takafumi Nishino och Scott Draper, Journal of Physics: Conference Series 625, no. 012010, Wake Conference 2015.[2] An investigation of in-field blockage effects in closely spaced lateral wind farm configurations, S. McTavish, S. Rodrigue, D. Feszty, och F. Nitzsche, Wind Energy (2014)
3/31/20176
THE DOUNREAY TRÌ PROJECT
• The Dounreay Trì Project comprises the development, construction and operation of the Hexicon floatingmulti turbine platform.
• The floating platform will be deployed in Scottish Territorial Waters in Summer 2018
• The Project consists of:
o A two turbine floating platform with an installed wind power capacity of 10 MW,off Dounreay, Caithness, Scotland
o A single export cable to shore
o The associated onshore electrical infrastructure.
3/31/20177
GOOD NEWS
3/31/20178
THE HEXICON PLATFORM FOR THE PROJECT
3/31/20179
MODEL TESTING
3/31/201710
FABRICATION PROGRAMME
The fabrication programme at ship yard:
• Final assembly in dry dock (at NEP, NIGG Energy Park)
• Towers erected and WTGs installed in the dry dock
• The complete platform is towed from dry dock to site
• Export cable, anchors and mooring system will be installed at the offshore site before arrival of the platform
• The overall fabrication programme will take approx. 12 months. Fabrication of the platform and installation of the cable, anchors and moorings will be done in parallel.
3/31/201711
THE PROJECT PLAN