green belt development

20

Upload: others

Post on 28-Apr-2022

7 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Green Belt Development
Page 2: Green Belt Development

1

Point No. 1 AAQ Values in Siltara are high. Therefore, action plan to limit the PMemissions from the plant to less than 30 mg/Nm3 shall be submitted.

Reply:

All the stacks envisaged under the proposed expansion will have the emission level less than30 mg/Nm3. As far as existing stacks are concerned, the PM emission level is 50 mg/Nm3asper CECB Consent to Operate.

Therefore, GPIL shall achieve emission level below 30 mg/Nm3 in a time bond manner. Thedetails of existing as well as expansion stack details are enclosed herewith as Annexure-I.

With regard to the commitments to reduce emission level from our plant, the followingactivities are being/will be carried out on regular basis:

1. We will consistently bring down the emission level to less than 30 mg/Nm3.

2. Regular sprinkling of wateron stockyard to reduce fugitive emission.

3. Sweeping ofroads regularly with industrial vacuum cleaners and recycle the dustwithin plant.

4. Green belt all along the plant boundary is provided and to further strengthen greenbelt, avenue and gap plantation in the plant area shall be done.

5. All internal roads have been made pucca.

Road Sweeping Machine

Page 3: Green Belt Development

2

Green Belt Development

Page 4: Green Belt Development

3

Point No. 2 Action plan for phasing out of 10 Nos 7 T Induction Furnaces shall besubmitted.

Reply:

Action plan for phasing out 7 T furnaces to 12 T by Year 2022-2023

FurnaceNo. Particulars Year

1 7 T Furnace to 12 T 2020 -21

2 7 T Furnace to 12 T 2021 -22

3 7 T Furnace to 12T 2021 – 22

4 7 T Furnace to 12 T 2022 – 23

5 7 T Furnace to 12 T 2022 – 23

However, we shall make efforts for phasing out all furnaces within 12 months from thedate of grant of EC and Consents.

Point No. 3 Action plan for Green belt development covering 40% of the total projectarea inside the factory premises shall be furnished.

Reply:

As per mechanism for environmental management of CPAs and SPAs vide order no

CPCB/IPC-VII/CEPI/NGT/2019 dated 25.10.2019 issuedby CPCB for consideration of

proposals for grant of Environmental Clearance for new and expansion activities listed in

‘Red’ and ‘Orange’ Categories located in Critically Polluted Areas and Severely Polluted

area:-

i. Increase of green belt cover by 40% of the total land area beyond the permissiblerequirement of 33%, Wherever feasible for new projects.

ii. Stipulation of greenbelt outside the project premises such as avenue plantation,plantation in vacant areas, social forestry, etc.

Page 5: Green Belt Development

4

Plantation details within the plant premise are as follows:

Particulars Area No. of plants StatusExisting Plantation within plantarea.

29.70 Ha 73439 Completed

Additional plantation nearproposed slag crushing unit&mineral grinding unit

1.2625 Ha 3200 ProposedProposed

Total 30.9625 Ha(33%within plantpremises)

76639

At the time of initial planning of the plant, 33% of the area was reserved for plantation as perEC by MoEF&CC/Consents by CECB. Since, there is land lock position within the planrtarea, therefore, Hon’ble EAC may kindly permit to develop greenbelt for remaining areaoutside the project premises for avenue plantation and plantation in vacant areas.

Action Plan for Balance area:

Sl. No. Location Area Plantation Target Target Date1. Oxyzone (Within the

periphery of 5 Km fromPlant) as directed by StateGovernment.

32.36 Ha 37000 saplings Done

2. Plantation proposed at CSIDCLand, Phase–I SiltaraIndustrial Area (Within theperiphery of 5 Km from PlantSite)

4.046 Ha 10150 It will bedone within12 monthsfrom the dateof grant ofEC andConsents.

3. Roadside plantation asdirected by State Government.

73 kms 73000 saplings Done

Total 36.406 Ha(outsideplantpremiseswithin theperiphery of5 Km)

Page 6: Green Belt Development

5

Point No. 4 Action plan for rain water harvesting more than annual water consumptionshall be submitted.

Reply:

GPIL shall use ground water56100 m3/annum for Domestic purpose only. Potentialof rainwater harvesting is 483547 m3/ annum is more than the withdrawal quantity of groundwater.

Annual Rain Water Harvesting Potential

S.N. Proposed RWH Area(Sqmt.)

Area Coeff. AnnualRain Fall

Vol.PotentialAnnually(CUM)

1. Rooftop rain fall capturepotential - GPIL

108436 0.85 1.1 101388

2. Rooftop rain fall capturepotential- lauhnagar

3689 0.85 1.1 3449

3. Rain Water Harvestingthrough Reservoir – I (Size:Diameter -83)

5407 1.0 1.1 5949

4. Rain Water Harvestingthrough Reservoir – I(Size: 120m x 80 m)

9600 1.0 1.1 10560

5. Surface Water Harvesting-GPIL Drain off area-30Acre Scheme - NearPellet (1.5 MTPA)KachhaPond

121406 0.6 1.1 80127

6. Surface Water Harvesting-GPIL Drain off area - 45Acre Scheme – Phase-IISID,PP Stores area etc.

182108 0.6 1.1 120191

7. Surface Water Harvesting-GPIL Drain off area – 55Acre Scheme – Phase –IPP,FAD,SID area etc.

222577 0.6 1.1 146901

8. Surface Water HarvestingLauhNagari

20053 0.6 1.1 14982

Total Annual Rainwater Harvesting Potential (KL/Year) 483547

Page 7: Green Belt Development

6

The Rain Water Harvesting Scheme (potential and implementation action plan) of M/sGodawari Power &Ispat Ltd located at Siltara Industrial Area, Distt. Raipur (C.G.) isas follows :-

Rain WaterHarvestingSchemes

RWHPotential(m3/year)

RWHalreadyImplemented (m3/Year)

% ason30th

July2020

Further Commitment

%ImplementationPlan (m3/Year)

T.Date

Roof TopRWH System

104837 37911 36% 66926Before nextmonsoon(June, 2021)

64%

SurfaceWaterHarvesting(ThroughPonds)

378710 211849 56% 166861Before nextmonsoon(June, 2021)

44%

Total 483547 249760 52% 233787Before nextmonsoon(June, 2021)

48%

Overall %52 48

100

GPIL has already implemented Rain water Harvesting system for 249760 m3/Year of waterand will further strengthen the system to implement the RWH for 233787m3/Year beforethebeginning of next monsoon.

Page 8: Green Belt Development

7

Exiting Rainwater harvesting Structures

Point No. 5 Fourth hole extraction system shall be installed on SAF for fume extraction.

Reply:SAF emission is being captured by existing side suction and it is efficient for fumeextraction followed by air cooled heat exchanger & pulse jet bag filter and outlet emissionbeing achieved less than 30mg/Nm3. As per OEM installation of fourth hole is not feasible inSAF as it is a Semi Open Furnace. In case of EAF which is closed furnace, fourt hole isfeasible.In order to check possibility and feasibility of fourth hole extraction system, we haveapproached a leading expertto check feasibility for installation of fourth hole extraction onexisting SAF. Communication for the same is attached herewith as Annexure II.

Page 9: Green Belt Development

8

Point No. 6 Energy conservation measures to be taken in the present proposal shall besubmitted.

Reply:

Energy Conservation Measures undertaken by GPIL:

Sl.No Division Activity Target Date ResponsibilityEnergy beingConserved

1. PelletInstallation of VFDDrives in Flushwater Pumps

CompletedMr.K.V.S.N.Raveendra,President

saving of 100000Kwh Annually.

2. SIDUsing Mix of RB1Coal withDomestic Coal

CompletedMr.J.K.Sahu,

AVP

GSE (Gross SpecificEnergy) from 5.5 to5.10 and NSE (NetSpecific Energy)from 3.7 to 3.0G.cal.

3. SID

Use of Ceramic Pad(Micro PorousBoard) below therefractory

CompletedMr.J.K.Sahu,

AVP

reduce shelltemperature by 20-30 0C which resultsin reduction of Coalconsumption by 20-25 Kg Per ton ofSponge Iron. TotalCoal saving shall be15000Mt.

4. SID

Replacement ofBucket elevationsystem withConveying system inCoal circuit

CompletedMr.J.K.Sahu,

AVP

saving of electricalenergy Approx 2Lac Kwh Annually.

5. PowerInstallation of VFDDrives inCompressors

CompletedMr.VinayShandilya,President

saving of 446000Kwh Annually.

Page 10: Green Belt Development

9

In addition to above, the following energy conservation measures will be taken byGPIL:

Sl.No Activity Target Date Responsibility Remarks

1. SMS

To modernize threenumber ofInduction furnaces(1 X 12 mt and 2x15 mt) byreplacing existingcrucible and panelswith energyefficient panels(low frequency)

November, 2021Mr.RahulKarwal,

Vice President

To reduceSpecific powerconsumptionby 50 Kwh

2. SMS

Further after gettingEC Approval weshall replace 5furnaces of 7 MT to12 mt energyefficient furnaces

Within One Yearafter

EC Approval

Mr. RahulKarwal, Vice

President

Shall reduceour Specificpowerconsumptionby 100 kwh(950 kwh to850 kwh)

3. Power

Installation of newEnergy Efficient 48MW TG Set inplace of existing 3Nos. ageing TGSets

Within One Yearafter

EC Approval

Mr.VinayShandilya,President

there will be asaving of 749M3 water perday and5424000kwh/yearAuxiliarypower.

4. General

Replacement ofconventionallighting with energyefficient LEDlightings andinstallation of solarlights

Regular WorkMr.A.K.Jain,

AVPContinuousProcess

Page 11: Green Belt Development

10

Point No. 7 GHG emission inventory for the entire plant shall be prepared andmeasures to conserve energy shall be taken as annual targets.

Reply:

In the complex of Godawari Power and Ispat Ltd. (GPIL), the sources of GHG emission areas follows:

1. 7 MW Waste Heat Recovery Plant.2. 10 MW Waste Heat Recovery Plant.3. 25 MW Waste Heat Recovery Plant.4. 20 MW Biomass Power Plant, and5. 11 MW Coal Based Power Plant.

Based on our experience of CDM Projects which included the plants mentioned at 1, 2 & 3and Gold Standard Project at serial no. 4 above, we do have historical annual GHG inventorywhich are as under:

1. 7 MW Waste Heat Recovery Plant.

17,828 units of emission (average 2,547 units per MW)

2. 10 MW Waste Heat Recovery Plant.

50,620 units of emission (average 5,062 units per MW)

3. 25 MW Waste Heat Recovery Plant.

1,59,926 units of emission (average 6,397 units per MW)

4. 20 MW Biomass Power Plant.

91,307 units of emission (average 4,565 units per MW)

5. 11 MW Coal Based Power Plant.

Based on the above average figures of per MW generation at 1, 2, 3 & 4 the estimated annualemission units for 11 MW Coal based Power Plant can be put conservatively at 60,000 units.

While the above figures serve as a guide to stock taking of GHG inventory, it may be notedthat for fixing the annual target of energy conservation, we are guided by the targets fixed bythe Bureau of Energy Efficiency (BEE) of the Ministry of Power, Govt.of India. GPIL is oneof the Designated Consumers under PAT Scheme of Energy Conservation Act. In every PATCycle our energy conservation target is notified by BEE for our implementation.

Page 12: Green Belt Development

11

Energy Consumption Target & Achievement by GPIL during PAT Cycles of BEE.

Sl. No. PAT CycleReference

PAT CycleDuration

Specific EnergyConsumptionTarget notifiedby BEE

Specific EnergyConsumptionlevel achieved

1 PAT Cycle 1 1 Apr. 2012 to31 Mar. 2015

0.666 TOE/Tonof Product

0.623 TOE/Tonof Productcommunicatedto BEE after dueAudit

2 PAT Cycle 2 1 April 2016 to31 March 2019

0.4691TOE/Ton ofProduct

0.486 TOE/Tonof Productcommunicatedto BEE after dueAudit

Point No. 8 Sludge drying beds shall be replaced by filter presses and dry disposal ofsludge shall be practiced, Sludge from STP shall be recycled to biomass power plant ora sludge digester shall be used to generate energy.

Reply:

Sludge generated from STP will beused as a soil conditioner and manurefor plantation.Afilter press shall be installed to coagulate solids and improve drainability.

Point No. 9 Action plan for 100 % Fly ash utilization shall be submitted.

Reply:

Fly ash generated from plant is being/will be utilized by Cement Plants/Brick Manufacturingunits/Road Construction Agencies for road base making and Reclamation of low lying areas.Copy of MoU with Cement Plants/Brick manufacturing units is enclosed as Annexure- III.

Action plan for 100% fly ash utilization is given below:-

Total Ash generation in TPA 85071

Total Utilization (as per MoU) in

TPA

85071

Page 13: Green Belt Development

12

S.N

PLANT/BOILER

CAPACITYFUEL

ASHGENERATION

(TPA)

TOTALFLYASH

(TPA)

UTILIZATIONStatus

T.DATE/OBJECTIVES

1 70 TPH Coal 38630 85071 Supply tocementplants/brickmanufacturing units.

Utilization inembankmentof road.

Reclamationof low layingarea

MOU enclosedfor Fly AshUtilization withFly Ash Brickmanufactures asAnnexure IXwith the EIAReport.

Request letterfor utilization offly ash inconstruction ofNH 200 isenclosed.

2 100 TPH Biomass+ Coal

46441

Point No.10 Detail traffic study shall be conducted for the roads leading to plant gates.Details about vehicles parked on road side at day and night shall be furnished.

Reply:

A detailed Traffic Study has been conducted. Report is enclosed in EIA Report as AnnexureNo. VII.Traffic survey data clearly indicates that the existing road leading to plant gates arecatering to average density of traffic and it is expected that incremental increase in traffic dueto proposed expansion project will be marginal. There is dedicated road patch of 200 meterslength and 20 metres width before entry gate for waiting vehicles and there is sufficientparking space inside plant. Width of all the internal road in the Siltara Industrial Area is 15 to30 metres.

There is provision to park 110 - 120no. of trucks outside plant.

Average No. of Trucks parked at a time during day hours is 70-80&during night hours 30-40.

Page 14: Green Belt Development

13

Annexure-I

SN Unit LocationName ofPollution

Control DeviceCapacity

PMLimit asperconsent

Action plan to limitthe PM emissionsfrom the plant toless than 30mg/Nm3

PROPOSED PROJECTS

1 SMS SMS Bag Filter 80000 m3/Hr30mg/Nm3

Installation ofefficient Bag Filterswith 30 mt stack

2InductionFurnace in placeof Arc Furnace

InductionFurnace

Bag Filter 5000 m3/Hr30mg/Nm3

Installation ofefficient Bag Filterswith 30 mt stack

EXISTING PLANTS

3Power plantPhase – I

AFBC # 70TPH

ESP137800m3/Hr

50mg/Nm3

Though the PMemission limit as perconsent is 50mg/Nm3, we areacheving andmaintaing it in therange of 40 to 45mg/nm3.Further, emissionwill be reduced byadoptingfollowingcorrectivemeasures in ESPs :

Replacement ofcontroller pannels ofPrecicon III in all 4fields with highfrequencycontrollers.

AFBC # 100TPH

ESP187560m3/Hr

50mg/Nm3

Though the PMemission limit as perconsent is 50mg/Nm3, we areacheving andmaintaing it in therange of 40 to 45mg/nm3.Further, emissionwill be reduced byadopting

Page 15: Green Belt Development

14

followingcorrectivemeasures in ESPs :

Replacement ofcontroller pannels ofPrecicon III in all 4fields with highfrequencycontrollers.

100 TPHBUNKER

Bag Filter 8500 m3/Hr

DAY BINHOPPER

Bag Filter 12500 m3/Hr

U.G,TUNNEL

Bag Filter 16500 m3/Hr

CoalHandlingPlant

Duztcon System -

4Sponge IronPhase – I

Kiln no. 01 ESP137800m3/Hr

50mg/Nm3

Though the PMemission limit as perconsent is 50mg/Nm3, we areacheving andmaintaing it in therange of 40 to 45mg/nm3.Further, emissionwill be reduced byadopting followingcorrective measuresin ESPs :

Replacement ofcontroller pannels ofPrecicon III in all 4fields with highfrequencycontrollers.

Kiln no. 02 ESP207418m3/Hr

50mg/Nm3

Though the PMemission limit as perconsent is 50mg/Nm3, we areacheving andmaintaing it in therange of 40 to 45mg/nm3.Further, emissionwill be reduced by

Page 16: Green Belt Development

15

adopting followingcorrective measuresin ESPs :

Replacement ofcontroller pannels ofPrecicon III in all 4fields with highfrequencycontrollers.

PSB – II Bag Filter 60000 m3/Hr

CoalInjection kilnno. 01 & 02

20000 m3/Hr

PSB 01, K1& K2 CDBELT,BUCKETELV.

Bag Filter140000m3/Hr

MetsoCircuit

Duztcon System -

5Sponge IronPhase – II

Kiln no. 03

ESP195037m3/Hr

50mg/Nm3

Though the PMemission limit as perconsent is 50mg/Nm3, we areacheving andmaintaing it in therange of 40 to 45mg/nm3.Further, emissionwill be reduced byadopting followingcorrective measuresin ESPs :

Replacement ofcontroller pannels ofPrecicon III in all 4fields with highfrequencycontrollers.

Kiln no. 04

CoalInjection kilnno. 03 & 04

Bag Filter 20000 m3/Hr

By PassConveyor

Bag Filter 60000 m3/Hr

PSB Bag Filter 125000

Page 17: Green Belt Development

16

m3/Hr

CD Belt Kilnno. 03

Bag Filter 60000 m3/Hr

CD Belt Kilnno. 04

Bag Filter 60000 m3/Hr

PSB - III, A-BIN

Bulk Spout 40 TPH

PSB - IV, A-BIN

40 TPH

By Pass BagFilter

Pug-Mill 40 TPH

Bag Filter,PSB – III

40 TPH

Bag Filter,PSB – IV

40 TPH

Coal circuit Duztcon System -

6Pellet Plant 0.6MTPA

Pellet Plant0.6 MPTA

ESP500000m3/Hr

50mg/Nm3

Though the PMemission limit as perconsent is 50mg/Nm3, we areacheving andmaintaing it in therange of 40 to 45mg/nm3.Further, emissionwill be reduced byadopting followingcorrective measuresin ESPs :

Replacement ofcontroller pannels ofPrecicon III in all 4fields with highfrequencycontrollers.

BentoniteHopper(Proportionate Building)

Bag Filter 5000 m3/Hr

Lime Hopper(Proportionate Building)

3000 m3/Hr

Page 18: Green Belt Development

17

Ash Hopper(Proportionate Building)

3000 m3/Hr

ConveryorBC - 8 (AshDich -ProportionateBuilding)

8000 m3/Hr

EirichMixter 4000 m3/Hr

TG BuildingBC - 13recycleMaterial

25000 m3/Hr

AnnulerCooler(ProductDischargeBC - 14)

20000 m3/Hr

7 SMS SMS Bag Filter 80000 m3/Hr35mg/Nm3

Achieved the limitof 30 mg/Nm3

8 Ferro AlloysSAF - 9.5MVA

Bag Filter140000m3/Hr

35mg/Nm3

Achieved the limitof 30 mg/Nm3

9Pellet plant1.5 MTPA

Pellet Plant1.5 MPTA

ESP1100000m3/Hr

50mg/Nm3

Though the PMemission limit as perconsent is 50mg/Nm3, we areacheving andmaintaing it in therange of 40 to 45mg/nm3.Further, emissionwill be reduced byadopting followingcorrective measuresin ESPs :

Replacement ofcontroller pannels ofPrecicon III in all 4fields with highfrequencycontrollers.

BentoniteHopper(Proportionate Building)

Bag Filter 9530 m3/Hr

Page 19: Green Belt Development

18

Lime Hopper(Proportionate Building)

9530 m3/Hr

Ash Hopper(Proportionate Building)

9530 m3/Hr

EirichMixter 11054 m3/Hr

Page 20: Green Belt Development

19

Annexure-II