  • GOVERNMENT OF PAKISTAN

    PUBLIC SECTOR DEVELOPMENT PROGRAMME 2015-16

    MINISTRY OF PLANNING, DEVELOPMENT & REFORM

    PLANNING COMMISSION

    June, 2015

  • PREFACE

    The National Economic Council (NEC) in its meeting held on 1st June 2015 approved National Development Programme for 2015-16 at Rs 1,514 billion. The development programme 2015-16 includes Rs. 700 billion as federal PSDP including foreign assistance of Rs 146 billion.

    PSDP 2015-16 will help achieving the long term development objectives given in Vision 2025 by allocation of resources to projects for building social and human capital, projects leading to food, water and energy security, initiatives necessary for fostering private sector led growth, harnessing regional connectivity, and improving national competitiveness. A number of initiatives for implementing institutional and governance reforms have also been incorporated in the PSDP 2015-16.

    To benefit from the historic opportunity offered by CPEC, PSDP 2015-16 offers ample funds for the projects under China – Pakistan Economic Corridor. In the first phase, completion of projects relating to the western alignment of CPEC within the stipulated time frame has been accorded priority so that the economic benefits reach the general public as soon as possible.

    Reform and innovation are very important tools to put the economy on long term high growth path and create enough job opportunities to meet the needs of growing population. PSDP 2015-16 includes specific projects aiming to improve social sector outcomes and initiate reformatory measures to further improve governance and investment climate. Prime Minister’s health insurance scheme would also be launched during the year.

    To improve productivity in industrial and agriculture sectors with a view to achieving food security and enhancing exports, the Federal Government plans to initiate programmes for entrepreneurship promotion in these sectors. These include certification programme for SMEs, establishment of technology parks, training on industrial stitching units in clusters and other initiatives for cluster development based industrial transformation plan as envisioned in Vision 2025. Similar initiatives for agriculture and mining sectors’ transformation are also part of the PSDP.

    Resettlement of TDPs poses another challenge to the already stretched development budget. To facilitate the resettlement of TDPs, significant amount of funds are provided to meet the reconstruction needs in conflict areas to ensure resettlement in the respective areas in the shortest possible time.

    Hassan Nawaz Tarar

    Secretary June, 2015

  • Foreign Assistance

    Rupee Total Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8

    A. Federal Ministries:

    1 Aviation Division 0.0 1395.1 1395.1 2700.0 1200.0 3900.0

    2 Cabinet Division 0.0 5767.1 5767.1 0.0 654.2 654.2

    3 Capital Administration & Development Division 80.0 1726.0 1806.0 138.1 905.2 1043.3

    4 Climate Change Division 0.0 25.1 25.1 0.0 39.8 39.8

    5 Commerce Division 0.0 363.7 363.7 0.0 875.6 875.6

    6 Communications Division (other than NHA) 0.0 5152.5 5152.5 0.0 364.7 364.7

    7 Defence Division 1648.0 2637.8 4285.8 800.0 1658.2 2458.2

    8 Defence Production Division 0.0 937.3 937.3 0.0 900.0 900.0

    9 Economic Affairs Division 0.0 5.0 5.0 0.0 0.0 0.0

    10 Establishment Division 0.0 165.4 165.4 0.0 148.5 148.5

    11 Federal Education & Professional Training Division 0.0 3375.3 3375.3 0.0 2207.0 2207.0

    12 Federal Tax Ombudsman 12.8 0.0 12.8 9.7 0.0 9.7

    13 Finance Division 1213.2 12861.5 14074.7 250.0 8884.5 9134.5

    14 Foreign Affairs Division 0.0 255.2 255.2 0.0 60.0 60.0

    15 Higher Education Commission 459.3 24583.0 25042.3 271.1 20228.9 20500.0

    16 Housing & Works Division 0.0 4414.6 4414.6 0.0 2590.4 2590.4

    17 Industries & Production Division 0.0 1151.4 1151.4 0.0 790.9 790.9

    18 Information, Broadcasting & National Heritage Division 79.4 311.2 390.6 0.0 390.9 390.9

    19 Information Technology & Telecom Division 51.0 474.7 525.7 150.0 772.8 922.8

    20 Inter Provincial Coordination Division 0.0 1067.3 1067.3 0.0 609.6 609.6

    21 Interior Division 100.0 3830.2 3930.2 100.0 8199.5 8299.5

    22 Kashmir Affairs & Gilgit Baltistan Division 765.0 21325.0 22090.0 875.0 22362.0 23237.0

    23 Law, Justice & Human Rights Division 0.0 2352.2 2352.2 0.0 1500.0 1500.0

    24 Narcotics Control Division 240.0 87.8 327.8 135.0 95.4 230.4

    25 National Food Security & Research Division 0.0 1071.3 1071.3 0.0 1500.0 1500.0

    26 National Health Services, Regulations & Coordination Division

    2797.0 25017.7 27814.7 0.0 20701.9 20701.9

    27 Pakistan Atomic Energy Commission 17180.0 42095.0 59275.0 15461.0 14947.5 30408.5

    28 Pakistan Nuclear Regulatory Authority 0.0 230.0 230.0 0.0 321.0 321.0

    29 Petroleum & Natural Resources Division 0.0 166.7 166.7 0.0 348.9 348.9

    30 Planning, Development & Reform Division 20.0 6244.8 6264.8 10.0 13670.7 13680.7

    National Development Programme 2014-15 & 2015-16(Ministry/Division-wise Summary)

    (Million Rupees)S.

    No.Ministry / Division PSDP 2014-15 (Revised) PSDP 2015-16

  • Foreign Assistance

    Rupee Total Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8

    (Million Rupees)S.

    No.Ministry / Division PSDP 2014-15 (Revised) PSDP 2015-16

    31 Ports & Shipping Division 100.0 2476.1 2576.1 0.0 12000.0 12000.0

    32 Railways Division 400.0 39166.0 39566.0 0.0 41000.0 41000.0

    33 Religious Affairs & Inter Faith Harmony Division 0.0 0.0 0.0 0.0 3.0 3.0

    34 Revenue Division 29.0 218.5 247.5 2.0 333.1 335.1

    35 Science & Technological Research Division 0.0 1211.3 1211.3 0.0 1060.4 1060.4

    36 States & Frontier Regions Division 1920.0 17180.0 19100.0 373.3 19326.7 19700.0

    37 Statistics Division 0.0 278.4 278.4 0.0 100.0 100.0

    38 S U P A R C O 0.0 700.0 700.0 300.0 500.0 800.0

    39 Textile Industry Division 0.0 329.3 329.3 0.0 165.0 165.0

    40 Water & Power Division (Water Sector) 3800.0 42257.7 46057.7 1600.0 28520.0 30120.0

    Total (Federal Ministries): 30894.7 272907.1 303801.9 23175.3 229936.5 253111.7

    B. Corporations:

    1 WAPDA (Power) 33660.0 15592.8 49252.8 56161.4 56126.9 112288.3

    2 National Highway Authority 35133.0 74312.4 109445.4 63950.0 95650.0 159600.0

    Total (Corporations): 68793.0 89905.2 158698.150 120111.4 151776.9 271888.3

    C. Pak MDGs & Community Dev. Programme 0.0 12500.0 12500.0 0.0 20000.0 20000.0

    D. Special Federal Development Programme 0.0 10000.0 10000.0 0.0 28000.0 28000.0

    E. ERRA 2500.0 2500.0 5000.0 3000.0 4000.0 7000.0

    F. Special Development Programme for Temporarily Displaced Persons (TDPs) and Security Enhancement

    0.0 45000.0 45000.0 0.0 100000.0 100000.0

    G. Prime Minister's Youth Programme 0.0 7000.0 7000.0 0.0 20000.0 20000.0

    Total (Federal): 102187.7 439812.3 542000.0 146286.7 553713.3 700000.0

    H. Provinces 61885.0 584338.0 646223.0 85467.0 728250.0 813717.0

    Total (National): 164072.7 1024150.3 1188223.0 231753.7 1281963.3 1513717.0

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    On-going Schemes:

    1 Development of Sustainable Rain Water Resources / Dams (Construction of Ramma Dam) NIIA

    CDWP 31.03.2015

    1657.000 0.000 684.741 972.259 0.000 271.419 271.419

    2 Establishment of Basic Aerodrome Facilities in Mansehra (Land Acquisition)

    CDWP 04.03.2015

    1600.000 0.000 450.000 1150.000 0.000 200.000 200.000

    3 Establishment of Flood Forecasting & Warning System for Kalpani Nullah Basin, Mardan (KPK)

    CDWP18.06.2012

    230.000 0.000 21.718 208.282 0.000 10.000 10.000

    4 Establishment of Main Met. Office at New Islamabad International Airport at Islamabad

    CDWP 19.11.2013

    30.969 0.000 12.388 18.581 0.000 18.581 18.581

    5 New Gwadar International Airport (NGIA) (CPEC)

    ECNEC 12.01.2015

    22947.650 0.000 679.000 22268.650 2700.000 300.000 3000.000

    26465.619 0.000 1847.847 24617.772 2700.000 800.000 3500.000

    New Schemes:

    6 ASF Accommodation Barracks at NIIA Islamabad

    Un-Approved 2035.085 0.000 0.000 2035.085 0.000 400.000 400.000

    2035.085 0.000 0.000 2035.085 0.000 400.000 400.000

    Total (On-going)

    AVIATION DIVISION

    (Rupees Million)G. Sl.

    NoName of the Scheme Approval

    StatusEstimated Cost Expenditure

    upto 30.06.2015

    Total (New)

    Throw-forward as on

    01.07.2015

    Allocation 2015-16

    28500.704 0.000 1847.847 26652.857 2700.000 1200.000 3900.000Total (Aviation)

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    On-going Schemes:

    7 Construction / Upgradation of Mosque at Pak Secretariat, Islamabad

    CDWP02.05.2014

    211.689 0.000 3.000 208.689 0.000 100.000 100.000

    8 Construction of 104 Family Suites, Islamabad

    ECNEC21.01.2010

    2908.369 0.000 765.117 2143.252 0.000 300.000 300.000

    9 Security Arrangement at Parliament House Building, Islamabad

    CDWP22.11.2008

    98.133 0.000 53.103 45.030 0.000 27.042 27.042

    10 Upgradation / Strengthening of Cabinet Division, 6 - Aviation Squadron relief and Rescue Operations and Enhancement of Security

    CDWP13.02.2013

    314.320 0.000 97.188 217.132 0.000 167.132 167.132

    11 Upgradation of Cabinet Division's IT Infrastructure for E-Governance

    DDWP15.07.2014

    50.014 0.000 10.000 40.014 0.000 40.014 40.014

    3582.525 0.000 928.408 2654.117 0.000 634.188 634.188

    New Schemes:

    12 Digitization of the Holding of the National Archives of Pakistan

    Un-Approved 37.000 0.000 0.000 37.000 0.000 10.000 10.000

    13 Improvement of Record Preservation, Archives Management Infrastructure and Research Documentation

    DDWP16.04.2010

    (RUP)

    59.640 0.000 0.000 59.640 0.000 10.000 10.000

    Allocation 2015-16

    Total (On-going)

    CABINET DIVISION

    (Rupees Million)G. Sl.

    NoName of the Scheme Approval

    StatusEstimated Cost Expenditure

    upto 30.06.2015

    Throw-forward as on

    01.07.2015

    Research Documentation (RUP)

    96.640 0.000 0.000 96.640 0.000 20.000 20.000

    3679.165 0.000 928.408 2750.757 0.000 654.188 654.188Total (Cabinet)

    Total (New)

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    Health:

    On-going Schemes:

    14 Bone Marrow Transplant Center at PIMS, Islamabad

    DDWP2010 (RUP)

    43.344 0.000 17.855 25.489 0.000 25.489 25.489

    15 Construction of Female Doctors Hostel at FGPC

    DDWP 06.06.2007

    67.290 0.000 59.590 7.700 0.000 7.700 7.700

    16 Establishment of Federal Breast Cancer Screening Center at PIMS, Islamabad

    CDWP18.06.2012

    225.000 0.000 161.636 63.364 0.000 63.364 63.364

    17 Establishment of Safe Blood Transfusion Services Project in ICT

    CDWP12.03.2012

    683.000 475.000 131.895 551.105 138.100 55.000 193.100

    18 Up-Gradation of Critical Care Facilities at PIMS, Islamabad

    CDWP18.06.2012

    696.000 0.000 596.000 100.000 0.000 100.000 100.000

    19 Regional Training Institute, Islamabad (Population)

    CDWP14.06.2011

    139.000 0.000 115.445 23.555 0.000 23.555 23.555

    New Schemes:

    20 Establishment of Centre for Neurosciences at PIMS Islamabad

    Un-Approved 1000.000 0.000 0.000 1000.000 0.000 70.000 70.000

    21 Extension of FGPC (Acquisition of Land) Islamabad

    DDWP16.04.2011

    55.321 0.000 0.000 55.321 0.000 5.000 5.000

    2908.955 475.000 1082.421 1826.534 138.100 350.108 488.208

    Education:

    Total (Health)

    CAPITAL ADMINISTRATION AND DEVELOPMENT DIVISION

    (Rupees Million)G. Sl.

    NoName of the Scheme Approval

    StatusEstimated Cost Expenditure

    upto 30.06.2015

    Throw-forward as on

    01.07.2015

    Allocation 2015-16

    Education:

    On-going Schemes:

    22 Construction of Model Child Welfare Center at Humak, Islamabad

    DDWP 55.561 0.000 39.531 16.030 0.000 16.030 16.030

    23 Establishment of Federal Government College of Home Economics Management Sciences & Specialized Disciplines, F-11/1, Islamabad

    CDWP29.11.2013

    500.000 0.000 40.000 460.000 0.000 200.000 200.000

    24 Establishment of FG Degree College for Women at Bhara Kahu, Islamabad

    CDWP 30.10.2004

    75.000 0.000 65.800 9.200 0.000 9.200 9.200

    25 Up-lifting of Islamabad Model School for Boys (VI-X), G-11/2, Ibd by Providing Physical Facilities (Infrastructure, Furniture & Equipment)

    DDWP 25.02.2014

    59.991 0.000 12.000 47.991 0.000 47.991 47.991

    26 Up-lifting of Islamabad Model School for Boys, G-6/4, Ibd by Providing Physical Facilities (Infrastructure, Furniture & Equipment).

    DDWP 25.02.2014

    44.903 0.000 8.000 36.903 0.000 36.903 36.903

    New Schemes:

    27 Establishment of SMART Schools in ICT Un-Approved 500.000 0.000 0.000 500.000 0.000 100.000 100.000

    28 Upgradation of ICT High Schools Un-Approved 1000.000 0.000 0.000 1000.000 0.000 100.000 100.000

    29 Upgradation of National Special Education Center for Hearing Impaired Children from Higher Secondary to Graduation Level, H-9/4, Islamabad

    Under Process

    44.356 0.000 0.000 44.356 0.000 30.000 30.000

    30 Uplifting of Islamabad Model College for Boys G-10/4, Islamabad

    DDWP25.02.2014

    53.773 0.000 0.000 53.773 0.000 15.000 15.000

    2333.584 0.000 165.331 2168.253 0.000 555.124 555.124

    5242.539 475.000 1247.752 3994.787 138.100 905.232 1043.332

    Total (Education)

    Total (C.A.D)

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    On-going Schemes:

    31 Establishment of Geomatic Centre for Climate Change and Sustainable Development 2012-2015.

    DDWP29.01.2013

    48.885 0.000 3.606 45.279 0.000 8.596 8.596

    48.885 0.000 3.606 45.279 0.000 8.596 8.596

    New Schemes:

    32 Carbon Neutral Pakistan Under Process

    313.960 0.000 0.000 313.960 0.000 7.752 7.752

    33 Sustainable Land Management Programme to Combat Desertification in Pakistan (Federal Share)

    CDWP04.03.2015

    105.430 0.000 0.000 105.430 0.000 23.404 23.404

    419.390 0.000 0.000 419.390 0.000 31.156 31.156

    468.275 0.000 3.606 464.669 0.000 39.752 39.752

    Total (On-going)

    Total (New)

    Total (Climate Change)

    CLIMATE CHANGE DIVISION

    (Rupees Million)G. Sl.

    NoName of the Scheme Approval

    StatusEstimated Cost Expenditure

    upto 30.06.2015

    Throw-forward as on

    01.07.2015

    Allocation 2015-16

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    On-going Schemes:

    34 Purchase of Equipment, Furnishing, Curriculum Development and Training of Pakistan School of Fashion Design, Lahore

    ECNEC20.03.2007

    755.747 0.000 404.462 351.285 0.000 351.285 351.285

    35 Restructuring of Pakistan Institute of Trade and Development (PITAD), Islamabad

    CDWP11.05.2009

    (RUP)

    508.436 0.000 246.487 261.949 0.000 24.337 24.337

    1264.183 0.000 650.949 613.234 0.000 375.622 375.622

    New Schemes:

    36 Expo Centre Peshawar (JV) Un-Approved 2500.000 0.000 0.000 2500.000 0.000 500.000 500.000

    2500.000 0.000 0.000 2500.000 0.000 500.000 500.000

    3764.183 0.000 650.949 3113.234 0.000 875.622 875.622

    Total (On-going)

    Total (New)

    Total (Commerce)

    COMMERCE DIVISION

    (Rupees Million)G. Sl.

    NoName of the Scheme Approval

    StatusEstimated Cost Expenditure

    upto 30.06.2015

    Throw-forward as on

    01.07.2015

    Allocation 2015-16

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    On-going Schemes:

    37 Construction of Central Police Office (NH&MP) at Mauve Area, G-11/1, Islamabad

    CDWP28.04.2015

    298.436 0.000 12.641 285.795 0.000 156.137 156.137

    38 Construction of Complex for National Highways & Motorway Police at Rahim Yar Khan

    Under Revision

    167.000 0.000 113.903 53.097 0.000 20.000 20.000

    39 Enhancement of Training Capabilities of CTTI, (Phase-IV), Islamabad

    CDWP27.11.2008

    313.456 0.000 260.494 52.962 0.000 52.962 52.962

    40 Establishment of National Highways & Motorway Police Training Center at Sheikhupura

    CDWP21.03.2006

    95.226 0.000 81.847 13.379 0.000 25.000 25.000

    41 Green Line Bus Transit System from Municipal Park, Sadder to KESC Power House Chowrangi, Surjani, Karachi

    ECNEC 04.12.2014

    16085.000 0.000 4961.354 11123.646 0.000 100.000 100.000

    42 NTRC Operational Research Wing (ORW)

    CDWP 50.000 1.000 46.852 3.148 0.000 3.148 3.148

    17009.118 1.000 5477.091 11532.027 0.000 357.247 357.247

    New Schemes:

    43 NTRC Axle Load Survey on National DDWP 46 937 0 000 0 000 46 937 0 000 3 000 3 000

    Total (On-going)

    COMMUNICATIONS DIVISION

    (Rupees Million)G. Sl.

    NoName of the Scheme Approval

    StatusEstimated Cost Expenditure

    upto 30.06.2015

    Throw-forward as on

    01.07.2015

    Allocation 2015-16

    43 NTRC Axle Load Survey on National Highways & Motorways

    DDWP02.04.2013

    46.937 0.000 0.000 46.937 0.000 3.000 3.000

    44 NTRC Operational Research Programme DDWP02.04.2013

    45.560 0.000 0.000 45.560 0.000 4.500 4.500

    92.497 0.000 0.000 92.497 0.000 7.500 7.500

    17101.615 1.000 5477.091 11624.524 0.000 364.747 364.747

    On-going Schemes:

    45 Bridge over Indus linking N-5 with N-55 at Nishtar Ghat (District Rajanpur & RYK)

    ECNEC 21.01.2010

    5459.329 0.000 3736.205 1723.124 0.000 800.000 800.000

    46 Bridge over River Indus at Larkana ECNEC 21.01.2010RUP(Rs13 b)

    9225.338 0.000 10411.085 -1185.747 0.000 10.000 10.000

    47 Construction of Faisalabad-Khanewal Expressway (184 Km) M-4 (Faisalabad, TT Sindh, Jhang & Khanewal) (ADB)

    ECNEC 06.02.2008

    28564.540 22100.720 15657.191 12907.349 700.000 700.000 1400.000

    48 Construction of Bridge Across River Chenab Linking Shorkot and Garh Maharaja (Sultan Bahoo) (Jhang)

    ECNEC 10.04.2015

    4048.264 0.000 2699.764 1348.500 0.000 950.000 950.000

    49 Construction of Bridge on River Ravi at Syed Wala (Nankana Sahib)

    Under Process

    987.000 0.000 196.941 790.059 0.000 300.000 300.000

    50 Construction of Bridge over Indus River at Qazi Ahmed Amri including-Sakrand Bypass (Nawabshah)

    ECNEC 12.01.2015

    7189.108 0.000 4459.364 2729.744 0.000 1000.000 1000.000

    51 Design and Feasibility Studies 1750.000 0.000 639.032 1110.968 0.000 255.000 255.000

    52 Improvement of 78.2 km of Nowshera - Dir - Chitral Road (N-45) Takhtbai Flyover

    ECNEC 07.03.2007

    2399.270 0.000 2870.472 -471.202 0.000 200.000 200.000

    NATIONAL HIGHWAY AUTHORITY

    Total (New)

    Sub - Total

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    53 Kalat-Quetta-Chaman Section of N-25 (247 km)KHC

    ECNEC 03.07.2014

    19140.000 4017.000 7988.802 11151.198 0.000 50.000 50.000

    54 Karachi-Hyderabad Motorway M-9 (136 km) (Land Acquisition only)

    Under Process

    3700.000 0.000 330.379 3369.621 0.000 50.000 50.000

    55 Khanewal - Multan Inter District Road (Bosan Road)

    Approved 4570.022 0.000 4163.239 406.783 0.000 150.000 150.000

    56 Lowari Tunnel & Access Roads (Dir) ECNEC 11.11.2011

    18132.544 5877.438 11935.551 6196.993 0.000 2000.000 2000.000

    57 Lyari Expressway (16.5 km) (Karachi) CDWP12.01.2015

    12909.000 0.000 8249.953 4659.047 0.000 100.000 100.000

    58 M-4 / N-70 Motorway (8 km) Formerly Widening / Improvement of Intervening Road between Flyover at Double Phatak and Chowk Nag Shah at Multan (Old Shujjabad) (Multan)

    ECNEC 16.08.2012

    4028.500 0.000 3240.495 788.005 0.000 150.000 150.000

    59 M-4 Motorway 57 km Including Land Acquisition (Multan) (IDB)

    ECNEC 09.12.2010

    14494.942 10722.162 10083.050 4411.892 200.000 1100.000 1300.000

    60 National Highway Development Sector Improvement Program (NHDSIP) ADB- Revised (All Pakistan) i. Sukkur Jacobabad (N-65 68 km completed)ii. Qilla Saifullah Zhob N-50 (150Km Completed)

    ECNEC 21.01.2010

    49954.780 38268.740 38709.905 11244.875 400.000 400.000 800.000

    COMMUNICATIONS DIVISION

    (Rupees Million)G. Sl.

    NoName of the Scheme Approval

    StatusEstimated Cost Expenditure

    upto 30.06.2015

    Throw-forward as on

    01.07.2015

    Allocation 2015-16

    p )iii.Qilla Saifullah Waigum Rud 127 Km N-70

    61 Peshawar Northern Bypass (34 km) (Peshawar)

    ECNEC 21.01.2010

    9002.750 0.000 6548.464 2454.286 0.000 1000.000 1000.000

    62 Rakhi Gaj-Bewata (N-70) East West (34 km) Pk-57 (Dera Ghazi Khan) (Japan)

    ECNEC 10.04.2015

    18543.060 13514.600 947.980 17595.080 500.000 500.000 1000.000

    63 Ratodero-Dadu Sehwan ACW (200 KM) Sindh (PK-55) (Dadu, Jamshoro, Larkana) (JICA)

    ECNEC 07.03.2007

    12342.000 10404.306 15089.900 -2747.900 300.000 550.000 850.000

    64 Realignment of KKH and Barrier Lake Attabad, Hunza, Gilgit Baltistan (17 KM)New (7km Rehab) (Hunza Gilgit Baltistan) (China)

    ECNEC 16.08.2012

    26476.820 23545.142 16950.573 9526.247 500.000 700.000 1200.000

    65 Rehabilitation & Widening of Earthquake Affected Areas (Alpuri Besham) Section of N-90 (32 km) Shangla Hill

    CDWP28.11.2014

    2879.257 656.250 2136.101 743.156 0.000 150.000 150.000

    66 Rehabilitation of NHA Highways Network damaged during Floods 2010 (All Over Pakistan) (ADB Loan) Revised) includingi.Madyan Kalam 36 km N-95 ii. Kashmore - D.G. Khan - Ramak - D.I. Khan - Kohat - Peshawar N-55iii. Naran - Jalkhad - Chilas N-15

    ECNEC 10.04.2015

    49863.000 44877.000 15642.467 34220.533 200.000 500.000 700.000

    67 Provision for Sub-completed / Completed projects on clearance by PD&R

    0.000 251.000 251.000

    305659.524 173983.358 182686.913 122972.611 2800.000 11866.000 14666.000

    68 Construction of Islamabad - Mianwali - D.I. Khan CPEC Route including land acquisition and technical study (CPEC)

    Un-Approved 68000.000 0.000 0.000 68000.000 0.000 10000.000 10000.000

    Total (On-going)

    China-Pak Economic Corridor (CPEC)

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    Western Alignment CPEC

    69 Gwadar - Turbat - Hoshab Section (200 km) of Gwadar - Ratodero Road (892 km) M-8, including Khuzdar - Shahdadkot - Ratodero (143 km)-(Gwadar, Turbat, Khuzdar in Balochistan and Kamber, Shahdadkot & Larkana in Sindh)

    NHC 25.03.1999

    23168.660 0.000 23019.406 149.254 0.000 2800.000 2800.000

    70 Widening & Improvement of N-85, Hoshab-Nag - Basima - Surab Road (459 km) (Khuzdar, Panjgur)

    ECNEC 06.09.2007

    22412.464 0.000 10150.628 12261.836 0.000 2500.000 2500.000

    71 Zhob Mughal Kot 81 Km N-50 (NHDSIP, ADB)

    ECNEC 21.01.2010(Total Rs.

    49,954.78 M)

    9100.000 8190.000 0.000 9100.000 500.000 2500.000 3000.000

    72 Rehabilitation of D.I Khan Mughal Kot 50 km Section N-50 (FERP Phase-II)

    ECNEC 10.04.2015(Total Rs. 49,863 M)

    4025.846 3623.261 0.000 4025.846 500.000 1500.000 2000.000

    73 Land Acquisition / Construction of Western Alignment and other CPEC Projects

    Un-Approved 60000.000 0.000 0.000 60000.000 0.000 10000.000 10000.000

    Northern Alignment CPEC

    (Rupees Million)G. Sl.

    NoName of the Scheme Approval

    StatusEstimated Cost Expenditure

    upto 30.06.2015

    Throw-forward as on

    01.07.2015

    Allocation 2015-16

    COMMUNICATIONS DIVISION

    g

    74 Construction of Burhan-Havelian Expressway (E-35) 59.1 Km

    CDWP 03.07.2014

    39494.150 25920.028 2822.849 36671.301 1000.000 1300.000 2300.000

    75 Thakot to Havelian 120 KM (Construction) (Phase-I) (CPEC)

    ECNEC 4.12.2014

    95410.000 0.000 0.000 95410.000 13650.000 6850.000 20500.000

    76 Thakot to Havelian 120 KM(Land)(Phase-I) (CPEC)

    Un-Approved 8404.000 0.000 0.000 8404.000 0.000 5000.000 5000.000

    330015.120 37733.289 35992.883 294022.237 15650.000 42450.000 58100.000

    New Schemes:

    77 Approach Roads to New Islamabad International Airport (NIIA) (Land Acquisition+Shifting of Utilities) (Rawalpindi)

    Under Process

    4500.000 0.000 0.000 4500.000 0.000 1000.000 1000.000

    78 Construction of Overhead Flyover / Bridge at Shaheen Chowk on N-5 Gujrat

    Un-Approved 1264.190 0.000 0.000 1264.190 0.000 800.000 800.000

    79 Construction of Sialkot-Lahore Motorway (110 Km) (Land Acquisition)

    Un-Approved 3000.000 0.000 0.000 3000.000 0.000 1000.000 1000.000

    80 Construction of Sialkot-Lahore Motorway (110 Km) 30% VGF for BOT

    Un-Approved 14850.000 0.000 0.000 14850.000 0.000 1000.000 1000.000

    81 Construction of approach Roads to New Islamabad International Airport (NIIA) (Construction)i. Thalian Link (4 Lane 5.5 km)-including Periphery roads 2 lane 7. Km ( bid cost Rs. 1,900 million)ii. Main Link 13.5 Km)

    Under Process

    10420.000 0.000 0.000 10420.000 0.000 700.000 700.000

    82 Construction of Bridge Over River Indus connecting Layyah with Taunsa with Approach Roads including Land Acquisition etc. (Feasibility)

    Un-Approved 19.000 0.000 0.000 19.000 0.000 19.000 19.000

    Total (CPEC)

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    83 Construction of Highway from Athmuqam to Taobutt including two tunnels in Neelum Valley

    Un-Approved 9750.000 0.000 0.000 9750.000 0.000 300.000 300.000

    84 Construction of Muzaffarabad - Mirpur - Mangla (MMM) Expressway (196 Km)

    Un-Approved 75000.000 0.000 0.000 75000.000 0.000 100.000 100.000

    85 Dualization of (Gandhi Chowk to Sarai Narang) + (Domail to Rangeenabad) Old Bannu Road N-55

    Un-Approved 8000.000 0.000 0.000 8000.000 0.000 300.000 300.000

    86 Dualization of Balance Portion of Sukkur Bypass

    CDWP06.01.2015

    842.000 0.000 0.000 842.000 0.000 200.000 200.000

    87 Dualization of Indus Highway Remaining Portion (164 KM) (Kohat Sarai Gambila)

    Un-Approved 33500.000 0.000 0.000 33500.000 0.000 500.000 500.000

    88 Dualization of Multan - Muzaffargarh - D.G. Khan section of N-70 (80 km) Viability Gap Funding (VGF)

    Un-Approved 1866.000 0.000 0.000 1866.000 0.000 250.000 250.000

    89 Feasibility Study - Bela Awaran Road Un-Approved 10.000 0.000 0.000 10.000 0.000 10.000 10.000

    90 Feasibility Study - Construction of Bridge on River Indus to Link Kaloor Kot with D.I Khan

    Un-Approved 20.000 0.000 0.000 20.000 0.000 20.000 20.000

    91 Feasibility Study - Construction of road Un-Approved 20.000 0.000 0.000 20.000 0.000 20.000 20.000

    Allocation 2015-16G. Sl. No

    Name of the Scheme Approval Status

    Estimated Cost Expenditure upto

    30.06.2015

    Throw-forward as on

    01.07.2015

    COMMUNICATIONS DIVISION

    (Rupees Million)

    9 eas b ty Study Co st uct o o oadfrom Chowk Azam to Layyah

    U pp o ed 0 000 0 000 0 000 0 000 0 000 0 000 0 000

    92 Feasibility Study - Dualization of Indus Highway (under CAREC Initiative) Kotri - Kashmore - D.G. Khan - D.I. Khan - Kohat - Peshawar

    Un-Approved 40.000 0.000 0.000 40.000 0.000 40.000 40.000

    93 Feasibility Study - Widening /Rehabilitation of N-65 Dhahdar to Quetta including Pir Panjah

    Un-Approved 10.000 0.000 0.000 10.000 0.000 5.000 5.000

    94 Improvement & Widening of balance 51 Km of Kararoo Wad Section of N-25

    Un-Approved 5000.000 0.000 0.000 5000.000 0.000 100.000 100.000

    95 Improvement and Widening of Chakdara Chitral Section of N-45 (141 KM) Korean Exim Bank

    Un-Approved 8550.000 0.000 0.000 8550.000 0.000 1000.000 1000.000

    96 Improvement and Widening of Jaglot - Skardu Road (S-1, 167 km)

    ECNEC 09.12.2010

    22154.037 19938.633 0.000 22154.037 500.000 100.000 600.000

    97 Lahore Eastern Bypass on G.T. Road (13.5 km) Construction

    Un-Approved 13500.000 0.000 0.000 13500.000 0.000 500.000 500.000

    98 Lahore Eastern Bypass on G.T. Road (13.5 km) Land Acquisition etc

    Un-Approved 5000.000 0.000 0.000 5000.000 0.000 1300.000 1300.000

    99 Lahore-Abdul Hakeem Section (230 km) - PK Motorway

    Un-Approved 131000.000 0.000 0.000 131000.000 0.000 20000.000 20000.000

    100 Multan - Sukkur Section (387 km) Credit Financing (90:10) - PK Motorway

    ECNEC 03.07.2014

    259353.000 221384.705 0.000 259353.000 45000.000 5250.000 50250.000

    101 Sukkur - Hyderabad Section (296 km) - PK Motorway

    Un-Approved 148000.000 0.000 0.000 148000.000 0.000 5520.000 5520.000

    102 Road Yakmach-Kharan Un-Approved 18800.000 0.000 0.000 18800.000 0.000 1000.000 1000.000

    103 Sanan - Aab-e-Gum connecting road between Sibbi and District Kachhi (41 km) (50:50 basis)

    Un-Approved 1200.000 0.000 0.000 1200.000 0.000 90.000 90.000

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    104 Sangla Hill (Pendorian - Beranwala) Interchange on M-3

    CDWP06.01.2015

    344.500 0.000 0.000 344.500 0.000 200.000 200.000

    105 Technical Study Harnai to Sanjavi Un-Approved 10.000 0.000 0.000 10.000 0.000 10.000 10.000

    776022.727 241323.338 0.000 776022.727 45500.000 41334.000 86834.000

    1411697.371 453039.985 218679.796 1193017.575 63950.000 95650.000 159600.000

    1428798.986 453040.985 224156.887 1204642.099 63950.000 96014.747 159964.747Total (Communications)

    Allocation 2015-16

    Total (New)

    Total (NHA)

    G. Sl. No

    Name of the Scheme Approval Status

    Estimated Cost Expenditure upto

    30.06.2015

    Throw-forward as on

    01.07.2015

    COMMUNICATIONS DIVISION

    (Rupees Million)

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    On-going Schemes:

    106 Construction of 6 Maritime Petrol Vessels, PMSA

    Approved04.12.2014

    13871.000 11097.000 2100.000 11771.000 0.000 1000.000 1000.000

    107 Construction of Admin Block, Accommodation Block and other Allied Facilities at PMSA Base Keti Bandar (Thatta)

    DDWP 31.05.2012

    58.861 0.000 0.578 58.283 0.000 31.658 31.658

    108 Construction of Admin Block, Accommodation Block and other Allied Facilities at PMSA Base Ormara (JNB)

    DDWP 31.05.2012

    57.454 0.000 0.588 56.866 0.000 26.273 26.273

    109 Development of Training Area and Boundary Wall for Survey Training Institute at H-8/2, Islamabad

    DDWP25.01.2010

    20.816 0.000 11.000 9.816 0.000 9.816 9.816

    110 Installation of Security Equipment in Ministry of Defence, Rawalpindi

    DDWP21.02.2014

    57.776 0.000 22.944 34.832 0.000 9.436 9.436

    111 National Electronics Complex of Pakistan (Phase-I) NESCOM Islamabad.

    ECNEC29.07.2011

    10888.843 7822.630 5353.410 5535.433 800.000 400.000 1200.000

    112 Water Distribution Network for RCB/CCB based on Khanpur Dam Water Source (Phase-III) (Rawalpindi) Punjab

    ECNEC 08.04.2006

    699.500 0.000 568.500 131.000 0.000 131.000 131.000

    DEFENCE DIVISION

    (Rupees Million)G. Sl.

    NoName of the Scheme Approval

    StatusEstimated Cost Expenditure

    upto 30.06.2015

    Throw-forward as on

    01.07.2015

    Allocation 2015-16

    25654.250 18919.630 8057.020 17597.230 800.000 1608.183 2408.183

    New Schemes:

    113 Construction of Boundary Wall of Office Complex for Survey of Pakistan, Lahore

    Un-Approved 5.000 153.558 0.000 5.000 0.000 5.000 5.000

    114 Establishment of Geodetic Datum of Pakistan

    CDWP 19.11.2014

    219.369 153.558 0.000 219.369 0.000 45.000 45.000

    224.369 307.116 0.000 224.369 0.000 50.000 50.000

    25878.619 19226.746 8057.020 17821.599 800.000 1658.183 2458.183

    Total (On-going)

    Total (New)

    Total (Defence)

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    On-going Schemes:

    115 Installation of Ship Lift & Transfer System and Associated Machinery & Equipment to Provide Docking and Repair Facilities to Surface Ship, Submarines and Commercial Vessels of upto 7781 tonnage (Karachi)

    ECNEC26-5-2011

    5640.000 0.000 3727.435 1912.565 0.000 900.000 900.000

    5640.000 0.000 3727.435 1912.565 0.000 900.000 900.000Total

    DEFENCE PRODUCTION DIVISION

    (Rupees Million)G. Sl.

    NoName of the Scheme Approval

    StatusEstimated Cost Expenditure

    upto 30.06.2015

    Throw-forward as on

    01.07.2015

    Allocation 2015-16

  • Total ForeignAid

    ForeignAid

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    Ongoing Schemes:

    116 Construction of Additional 30 Rooms at Fatima Hostel at Civil Services Academy, Walton, Lahore

    DDWP01.03.2013

    58.946 0.000 41.746 17.200 0.000 17.200 17.200

    117 Construction of Auditorium for 500 Persons at Civil Services Academy, Walton, Lahore

    DDWP01.03.2013

    59.532 0.000 34.203 25.329 0.000 25.329 25.329

    118.478 0.000 75.949 42.529 0.000 42.529 42.529

    New Schemes:

    118 Construction of Hostel for Female Federal Government Employees at Wafaqi Colony, Lahore

    DDWP17.02.2012

    46.000 0.000 0.000 46.000 0.000 46.000 46.000

    119 Federal Secretariat Female Employees Hostel, G-7, Islamabad

    Un-Approved 200.000 0.000 0.000 200.000 0.000 50.000 50.000

    120 National University of Public Policy and Administration (NUPPA ), Lahore

    Un-Approved 1000.000 0.000 0.000 1000.000 0.000 10.000 10.000

    1246.000 0.000 0.000 1246.000 0.000 106.000 106.000

    1364.478 0.000 75.949 1288.529 0.000 148.529 148.529

    Allocation 2015-16

    Total (On-going)

    Total (New)

    Total (Establishment)

    G. Sl. No

    Name of the Scheme Approval Status

    Estimated Cost Expenditure upto

    30.06.2015

    Throw-forward as on

    01.07.2015

    ESTABLISHMENT DIVISION

    (Rupees Million)

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    On-going Schemes:

    121 Capacity Building of TTIs and Training of Elementary Schools Teachers in ICT, FATA, FANA & AJK

    CDWP01.10.2013

    730.828 0.000 669.556 61.272 0.000 61.272 61.272

    122 Construction of Hostel Building for 100 persons NTB Complex, Plot-39, H-9, Islamabad

    CDWP29.11.2013

    233.338 0.000 201.698 31.640 0.000 31.640 31.640

    123 Establishment & Operation of Basic Education Community Schools in the Country. All Pakistan including AJ&K, FATA and Gilgit Baltistan (Revised)

    ECNEC18.04.2014

    4282.049 0.000 2945.963 1336.086 0.000 1036.096 1036.096

    124 Financial Management for Good Governance (FMGG) Phase-II, Islamabad.

    DDWP06.04.2012

    43.223 0.000 24.662 18.561 0.000 18.561 18.561

    125 Improving Human Development Indicators in Pakistan with focus on MDGs relating to Education and six EFA Goals (Revised)

    CDWP13.03.2014

    2386.980 0.000 483.040 1903.940 0.000 500.000 500.000

    126 Mainstreaming of Madrassas DDWP2.12.2014

    50.000 0.000 5.000 45.000 0.000 45.000 45.000

    127 Modernization and Standardization of Examination System

    DDWP2 12 2014

    50.000 0.000 25.000 25.000 0.000 25.000 25.000

    FEDERAL EDUCATION & PROFESSIONAL TRAINING DIVISION

    (Rupees Million)G. Sl.

    NoName of the Scheme Approval

    StatusEstimated Cost Expenditure

    upto 30.06.2015

    Throw-forward as on

    01.07.2015

    Allocation 2015-16

    Examination System 2.12.2014

    128 President Programme for the Care of Highly Qualified Overseas Pakistanis

    CDWP 15.07.2009

    346.100 0.000 163.956 182.144 0.000 50.000 50.000

    129 Prime Minister's Special Initiatives (PMSI) for Hunarmand Pakistan Programme (NAVTTC)

    ECNEC30.4.2009

    4648.000 0.000 3156.400 1491.600 0.000 349.822 349.822

    130 Provision of Quality Education Opportunities for Students of Balochistan, FATA & 3 PMUs

    CDWP27.02.2007

    481.360 0.000 456.751 24.609 0.000 24.609 24.609

    13251.878 0.000 8132.026 5119.852 0.000 2142.000 2142.000

    New Schemes:

    131 National Best Teachers Awards Scheme Un-Approved 70.000 0.000 0.000 70.000 0.000 30.000 30.000

    132 National Curriculum Council Under Process

    100.000 0.000 0.000 100.000 0.000 35.000 35.000

    170.000 0.000 0.000 170.000 0.000 65.000 65.000

    13421.878 0.000 8132.026 5289.852 0.000 2207.000 2207.000

    Total (On-going)

    Total (New)

    Total (Education & Training)

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    On-going Schemes:

    133 Ombudsman: Institutional Capacity Building Islamabad (World Bank)

    CDWP12.04.2012

    40.864 40.864 31.127 9.737 9.737 0.000 9.737

    40.864 40.864 31.127 9.737 9.737 0.000 9.737Total (F.T.O):

    FEDERAL TAX OMBUDSMAN

    (Rupees Million)G. Sl.

    NoName of the Scheme Approval

    StatusEstimated Cost Expenditure

    upto 30.06.2015

    Throw-forward as on

    01.07.2015

    Allocation 2015-16

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    On-going Schemes:

    134 2 x 50 MW Power Plant from Syngas (IGCC - 2009) Tharparkar (District Tharparkar)

    ECNEC18-12-2010

    8898.700 0.000 3051.500 5847.200 0.000 1000.000 1000.000

    135 Automation Project of CDNS (Phase-II) (Islamabad)

    CDWP01.10.2013

    879.750 0.000 133.137 746.613 0.000 376.000 376.000

    136 Bridge Qamar-ud-Din / Surkach, Balochistan (Zhob)

    CDWP21-1-2011

    180.000 0.000 107.618 72.382 0.000 72.382 72.382

    137 Burns and Trauma Centre Peshawar CDWP14-3-2012

    217.570 0.000 153.430 64.140 0.000 64.140 64.140

    138 Capacity Building of Teachers Training Institutions & Training of Elementary Schools Teachers in Balochistan

    ECNEC30-11-2006

    734.714 0.000 588.407 146.307 0.000 146.307 146.307

    139 Capacity Building of Teachers Training Institutions & Training of Elementary Schools Teachers in Khyber Pakhtunkhwa

    ECNEC23.08.2006

    1077.740 0.000 1035.319 42.421 0.000 42.421 42.421

    140 Capacity Building of Teachers Training Institutions & Training of Elementary Schools Teachers in Sindh

    ECNEC30-11-2006

    1301.773 0.000 1261.773 40.000 0.000 40.000 40.000

    141 Capacity Building, MIS Development and Institutional Strengthening of Pakistan

    DDWP 26 05 2014

    20.000 0.000 10.000 10.000 0.000 10.000 10.000

    Allocation 2015-16G. Sl. No

    Name of the Scheme Approval Status

    Estimated Cost Expenditure upto

    30.06.2015

    Throw-forward as on

    01.07.2015

    FINANCE DIVISION

    (Rupees Million)

    Institutional Strengthening of Pakistan Mint, Lahore

    26.05.2014

    142 Construction / Upgradation of Dirgi Shabozai (N-70) to Taunsa (N-55) Road, Balochistan (Federal Share 60%)

    ECNEC13.09.2013

    4795.980 0.000 40.000 4755.980 0.000 300.000 300.000

    143 Construction /Improvement of various Roads in Taluka Hyderabad District (Rural) (Hyderabad Package)

    CDWP18-03-2010

    205.750 0.000 82.200 123.550 0.000 123.550 123.550

    144 Construction /Improvement of Roads in Hyderabad District (Urban) (Hyderabad Package)

    CDWP18-03-2010

    484.984 0.000 156.546 328.438 0.000 75.000 75.000

    145 Construction of B/T Road from Sui to Uch Field (57 km) (Dera Bugti Package)

    ECNEC30-03-2009

    797.710 0.000 446.953 350.757 0.000 100.000 100.000

    146 Construction of Black Top Road from Doli Check Post to Sighari Road 109 Bashha Pur Linking Kandh Kot and Jani Bari Road 238 District Dera Bugti (Dera Bugti Package)

    CDWP14-05-2007

    301.393 0.000 256.136 45.257 0.000 45.257 45.257

    147 Construction of Black Top Road from Lehri to Sangsilla Road Phase-I (Dera Bugti Package) (District Dera Bugti)

    CDWP21-01-2011

    841.480 0.000 244.000 597.480 0.000 100.000 100.000

    148 Construction of Black Topped from Dera Bugti to Pitokh, Habib Rahi, Vadera Killi Murad, Dera Bugti (Dera Bugti Package) (District Dera Bugti)

    CDWP14-03-2012

    335.690 0.000 152.280 183.410 0.000 183.410 183.410

    149 Construction of Eastern and Expansion of Southern Sewerage Treatment Plants (Hyderabad Package)

    ECNEC23-8-2006

    915.300 0.000 496.150 419.150 0.000 124.955 124.955

    150 Construction of Fish Landing Jetty & Allied Harbor Facilities at Pishukan, Gwadar (Revised)(Federal Share) (District Gwadar)

    ECNEC16-08-2012

    834.752 0.000 734.752 100.000 0.000 100.000 100.000

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    151 Construction of Fish Landing Jetty & Allied Harbor Facilities at Surbandar, East Bay Gwadar (Federal Share) (District Gwadar)

    ECNEC16-08-2012

    890.672 0.000 790.672 100.000 0.000 100.000 100.000

    152 Construction of Flyover at Koyala Phatak, Samangli Road, Quetta (District Quetta)

    ECNEC19.11.2009

    1499.225 0.000 996.105 503.120 0.000 100.000 100.000

    153 Construction of Flyover at Sariab Phatak, Quetta (District Quetta)

    ECNEC24.02.2011

    1581.343 0.000 1340.622 240.721 0.000 240.721 240.721

    154 Construction of Grid Station at Kohlu ECNEC9-12-2010

    330.043 0.000 272.243 57.800 0.000 57.800 57.800

    155 Construction of Road from Pangrio Sugar Mill to Village Kabir Rind to Tando Bago Pangrio Road Mile, Badin (District Badin)

    CDWP21.01.2011

    101.665 0.000 30.000 71.665 0.000 5.000 5.000

    156 Construction of Roads in District Nasirabad / Jaffarabad

    CDWP19-11-2009

    474.500 0.000 401.675 72.825 0.000 72.825 72.825

    157 Construction of Sibi Rakhni Road via Maiwand (Tall - Kohlu) Section km 24 - 164) (Kohlu Package) (Sibbi District)

    ECNEC9-12-2010

    4751.592 0.000 4751.592 0.000 0.000 100.000 100.000

    158 Construction of Various B/T Roads to link different Villages with Main Kohlu Town (Kohlu Package) (Distt. Kohlu)

    CDWP30-04-2009

    222.245 0.000 215.845 6.400 0.000 6.400 6.400

    Allocation 2015-16G. Sl. No

    Name of the Scheme Approval Status

    Estimated Cost Expenditure upto

    30.06.2015

    Throw-forward as on

    01.07.2015

    FINANCE DIVISION

    (Rupees Million)

    159 Dargah Hazrat Lal Shahbaz Qalandar, Sehwan, Sindh

    CDWP20.05.2005

    142.225 0.000 130.764 11.461 0.000 11.461 11.461

    160 Expansion of Raw Water Filtration Plant & Supply Network for Supplying Clean Water to Hyderabad (Hyderabad Package)

    CDWP18-03-2010

    935.000 0.000 665.044 269.956 0.000 100.000 100.000

    161 Greater Karachi Sewerage Plant (S-III) (Karachi)

    ECNEC18.07.2014

    3991.000 0.000 829.000 3162.000 0.000 100.000 100.000

    162 Greater Karachi Water Supply Scheme (K-IV) (Karachi)

    ECNCE 18.07.2014

    12755.000 0.000 2080.000 10675.000 0.000 500.000 500.000

    163 Gwadar Development Authority Approved 25000.000 0.000 7591.450 17408.550 0.000 2000.000 2000.000

    164 Improvement of Sui-Dera Bugti Road and Construction of Black Top Linked Road at Dera Bugti (Dera Bugti Package) (District Dera Bugti)

    CDWP21-1-2011

    592.042 0.000 329.620 262.422 0.000 132.000 132.000

    165 Institutional Strengthening of Finance Division (Islamabad)

    CDWP03.11.2010

    146.444 0.000 91.715 54.729 0.000 44.728 44.728

    166 Khyber Institute of Child Health & Children Hospital (District Peshawar)

    ECNEC16-8-2012

    2209.296 0.000 1095.000 1114.296 0.000 200.000 200.000

    167 Lyari Expressway Resettlement Project ECNEC6.11.2008

    7027.745 0.000 3405.460 3622.285 0.000 300.000 300.000

    168 Metalling of Road Linking Chitral and Gilgit (Improvement / B.T of Booni-Mastuj Shandoor Road, District Chitral) (Revised)

    CDWP09.03.2015

    2323.914 0.000 257.751 2066.163 0.000 150.000 150.000

    169 Public Sector Enterprises Reforms (PSER) Project

    CDWP 22.10.2014

    2276.540 2020.000 5.320 2271.220 250.000 31.940 281.940

    170 Shaheed Benazir Bhutto Mother & Child Health Care Centre, Nawabshah City (300 Bedded Hospital) (District Nawabshah)

    ECNEC30-7-2009

    1215.132 0.000 470.000 745.132 0.000 200.000 200.000

    171 Tubli - Badini Road (Max. Federal Share) CDWP26.12.2013

    789.606 0.000 748.131 41.475 0.000 41.475 41.475

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    172 Urban Water Supply Scheme, Benazirabad

    ECNEC18-3-2010

    783.500 0.000 463.710 319.790 0.000 10.000 10.000

    173 Water Supply & Drainage Scheme of Tando Jam (Hyderabad Package) (District Hyderabad)

    CDWP19-11-2009

    131.820 0.000 85.067 46.753 0.000 46.753 46.753

    174 Widening and Carpeting of Booni-Buzand Torkhow Road Chitral (District Chitral) (Revised)

    CDWP09.03.2015

    1108.420 0.000 76.450 1031.970 0.000 100.000 100.000

    94102.255 2020.000 36073.437 58028.818 250.000 7554.525 7804.525

    New Schemes:

    175 Cadet College, Kharan Un-Approved 400.000 0.000 0.000 400.000 0.000 100.000 100.000

    176 Construction of Approach Road for New Gwadar International Airport

    Un-Approved 503.000 0.000 0.000 503.000 0.000 30.000 30.000

    177 Development of Sui Town Un-Approved 300.000 0.000 0.000 300.000 0.000 100.000 100.000

    178 Development of Ziarat Town Un-Approved 1000.000 0.000 0.000 1000.000 0.000 1000.000 1000.000

    179 Shahi Bagh Heritage Theme Park Phase-I, Lahore

    Un-Approved 4183.500 0.000 0.000 4183.500 0.000 100.000 100.000

    Allocation 2015-16

    Total (On-going)

    G. Sl. No

    Name of the Scheme Approval Status

    Estimated Cost Expenditure upto

    30.06.2015

    Throw-forward as on

    01.07.2015

    FINANCE DIVISION

    (Rupees Million)

    6386.500 0.000 0.000 6386.500 0.000 1330.000 1330.000

    100488.755 2020.000 36073.437 64415.318 250.000 8884.525 9134.525Total (Finance)

    Total (New)

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    On-going Schemes:

    180 Furnishing of High Security Block & Conference Hall at Ministry of Foreign Affairs, G-5/2, Islamabad

    CDWP30.04.2007

    195.000 0.000 165.000 30.000 0.000 30.000 30.000

    195.000 0.000 165.000 30.000 0.000 30.000 30.000

    New Schemes:

    181 Pak-China Year of Friendly Exchanges Programme (CPEC)

    Un-Approved 100.000 0.000 0.000 100.000 0.000 30.000 30.000

    100.000 0.000 0.000 100.000 0.000 30.000 30.000

    295.000 0.000 165.000 130.000 0.000 60.000 60.000

    Total (On-going)

    Total (New)

    Total (Foreign Affairs)

    FOREIGN AFFAIRS DIVISION

    (Rupees Million)G. Sl.

    NoName of the Scheme Approval

    StatusEstimated Cost Expenditure

    upto 30.06.2015

    Throw-forward as on

    01.07.2015

    Allocation 2015-16

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    On-going Schemes:

    182 1000 Cuban Scholarships for Studies in General Comprehensive Medicine (Equivalent to MBBS)

    CDWP07.04.2011

    978.743 0.000 936.000 42.743 0.000 42.743 42.743

    183 Award of 100 Scholarships to the Bangladeshi Students in the field of Medicine, Engineering and IT

    CDWP01.01.2008

    77.000 0.000 61.888 15.112 0.000 15.112 15.112

    184 Award of 400 Scholarships to Students from Indian Occupied Kashmir in the field of Medicine, Engineering & IT

    CDWP05.10.2012

    355.000 0.000 227.511 127.489 0.000 50.000 50.000

    185 Capacity Building and Up gradation of selected Departments at University of the Punjab (Total Cost = Rs. 834.188, PSDP Share= Rs. 771.286 million + Uni Share = Rs. 62.902 million)

    CDWP16.01.2014

    771.286 0.000 250.000 521.286 0.000 100.000 100.000

    186 Commencement of 4 Year undergraduate program in water resources and petroleum engineering at UET Taxila

    CDWP04.05.2015

    928.639 0.000 10.000 918.639 0.000 150.000 150.000

    187 Commencement of New Engineering Programs and Infrastructure Development at NED University of Engineering and Technology, Karachi

    CDWP28.04.2015

    795.580 0.000 15.000 780.580 0.000 400.000 400.000

    HIGHER EDUCATION COMMISSION

    (Rupees Million)G. Sl.

    NoName of the Scheme Approval

    StatusEstimated Cost Expenditure

    upto 30.06.2015

    Throw-forward as on

    01.07.2015

    Allocation 2015-16

    188 Completion of left over work on academic blocks at Hazara University Mansehra

    CDWP 04.03.2015

    708.221 0.000 10.000 698.221 0.000 250.000 250.000

    189 Construction of Boys & Girls Hostel (100 capacity each) at Islamia College University Peshawar

    CDWP28.04.2015

    209.245 0.000 50.000 159.245 0.000 100.000 100.000

    190 Construction of Hostels at King Edward Medical University, Lahore

    CDWP 11.04.2014

    205.727 0.000 50.000 155.727 0.000 155.727 155.727

    191 Development of Infrastructure at Lasbela University of Agriculture, Water and Marine Sciences, Uthal, Balochistan

    CDWP21.10.2011

    974.820 0.000 171.700 803.120 0.000 125.000 125.000

    192 Development of Khyber Medical University, Peshawar (To be revised)

    CDWP11.10.2008

    477.800 0.000 477.800 0.000 0.000 50.000 50.000

    193 Development of New Campus of Government College University, Lahore at Kala Shah Kaku

    CDWP28.04.2015

    982.472 0.000 20.605 961.867 0.000 250.000 250.000

    194 Development of University of Balochistan, Quetta (To be revised).

    ECNEC30.11.2006

    971.878 0.000 971.878 0.000 0.000 124.862 124.862

    195 English Language Teaching Reform Project Phase-II, HEC

    DDWP 27.01.2010

    53.670 0.000 45.970 7.700 0.000 7.700 7.700

    196 Enhancement of Infrastructure at Institute of Management Sciences (IMS), Peshawar (PSDP Share: Rs. 387.503 million+ IMS Share+ Rs. 105.435 million = Rs. 492.938 million)

    CDWP06.09.2013

    387.503 0.000 90.000 297.503 0.000 100.000 100.000

    197 Enhancement of Research Facilities at University of Veterinary & Animal Sciences (UVAS), Ravi Campus Pattoki

    CDWP06.01.2015

    980.229 0.000 100.000 880.229 0.000 120.000 120.000

    198 Essential infrastructure for Lahore College for Women University (LCWU), Lahore, Jhang Campus

    CDWP27.01.2015

    836.478 0.000 180.000 656.478 0.000 100.000 100.000

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    199 Essential Needs of Strengthening and Development of MUET, Shaheed Z.A. Bhutto Campus, Khairpur Mir's

    CDWP21.10.2014

    891.668 0.000 40.000 851.668 0.000 150.000 150.000

    200 Establishment & Development of The Islamia University of Bahawalpur Sub Campus at Rahim Yar Khan (To be revised)

    CDWP30.06.2007

    416.694 0.000 416.694 0.000 0.000 50.000 50.000

    201 Establishment of College of Nursing and Strengthening of Community Medicine Department at Peoples University of Medical and health Sciences, for Women, Nawabshah

    CDWP27.01.2015

    577.288 0.000 30.000 547.288 0.000 150.000 150.000

    202 Establishment of COMSATS Institute of Information Technology at Jaffarabad

    CDWP21.03.2012

    853.499 0.000 5.000 848.499 0.000 15.000 15.000

    203 Establishment of COMSATS Institute of Information Technology Campus at Abbotabad

    CDWP16.01.2014

    873.417 0.000 105.000 768.417 0.000 150.000 150.000

    204 Establishment of Engineering Faculty at Gilgit and Skardu Campus of Karakuram International University, Gilgit

    CDWP04.03.2015

    887.023 0.000 10.000 877.023 0.000 100.000 100.000

    205 Establishment of I.T and Library Infrastructure for new disciplines of Food

    d E E i i d S i t

    CDWP04.03.2015

    1350.000 0.000 10.000 1340.000 0.000 120.000 120.000

    Throw-forward as on

    01.07.2015

    Allocation 2015-16

    HIGHER EDUCATION COMMISSION

    (Rupees Million)G. Sl.

    NoName of the Scheme Approval

    StatusEstimated Cost Expenditure

    upto 30.06.2015

    and Energy Engineering and Science at University of Agriculture, Faisalabad

    206 Establishment of Main Campus of Federal Urdu University of Arts, Science & Technology at Islamabad (PSDP Share: Rs.476.368 million + Uni Share : Rs. 167.940 million = Rs.644.308 million)

    CDWP26.12.2013

    476.368 0.000 150.000 326.368 0.000 150.000 150.000

    207 Establishment of Shaheed Mohtarma Benazir Bhutto Medical University Larkana

    CDWP14.03.2012

    949.747 0.000 520.500 429.247 0.000 200.000 200.000

    208 Establishment of Shaheed Benazir Bhutto University, Benazirabad, Sindh

    ECNEC 09.12.2010

    1556.781 0.000 417.430 1139.351 0.000 200.000 200.000

    209 Establishment of Sub-Campus University of Agriculture, Faisalabad at Depalpur (Okara)

    CDWP 27.08.2007

    475.395 0.000 226.856 248.539 0.000 50.000 50.000

    210 Establishment of the Facility for the Indigenous Development of Percutaneous Transluminal Coronary Angioplasty (PTCA) Balloon Catheters, NUST

    DDWP01.01.2014

    32.800 0.000 20.000 12.800 0.000 12.800 12.800

    211 Establishment of Seerat Chairs in Public Sector Universities (HEC)

    CDWP 06.1.2015

    192.000 0.000 189.980 2.020 0.000 75.000 75.000

    212 Establishment of University at Loralai ECNEC26.05.2011

    1518.751 0.000 314.358 1204.393 0.000 350.000 350.000

    213 Establishment of University at Turbat ECNEC26.05.2011

    1580.391 0.000 1166.991 413.400 0.000 413.400 413.400

    214 Establishment of University of Engineering & Technology, Lahore sub campus at Narowal (Revised)

    ECNEC31.12.2013

    2878.521 0.000 600.000 2278.521 0.000 400.000 400.000

    215 Establishment of Women University, Multan

    ECNEC 19.09.2009

    1144.621 0.000 630.000 514.621 0.000 200.000 200.000

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    216 Establishment University of Swat (Phase-I) (Province Share= Rs. 1496.682 already approved by PDWP + GOP Share + Rs. 1084.045 million, Total = Rs. 2580.727 million)

    CDWP27.01.2015

    1084.045 0.000 10.000 1074.045 0.000 150.000 150.000

    217 Expansion Programme of Quaid-e-Azam University, Islamabad. Phase I

    CDWP18.06.2012

    856.343 0.000 336.000 520.343 0.000 200.000 200.000

    218 Faculty Development Program of Bahauddin Zakariya University, Multan (100 Ph.D Foreign Scholarships)

    ECNEC30.03.2009

    832.105 0.000 496.000 336.105 0.000 140.000 140.000

    219 Human Resource Development Initiative MS Leading to PhD Program of Faculty Development for Engineering Universities/ UESTPs

    ECNEC 19.09.2007

    11806.139 0.000 2789.302 9016.837 0.000 980.000 980.000

    220 Indigenous PhD fellowship for 5000 Scholars, HEC (Phase-II)

    ECNEC11.11.2011

    9972.593 0.000 1270.000 8702.593 0.000 1273.886 1273.886

    221 Industrial Linkages - Technology Parks and Technology Incubators, HEJ Research Institute of Chemistry, Karachi University, Karachi (To be revised).

    CDWP12.01.2008

    184.000 0.000 184.000 0.000 0.000 135.000 135.000

    222 International Linkages of Pakistani Universities with Foreign Universities

    CDWP 17.12.2005

    308.772 0.000 236.930 71.842 0.000 71.842 71.842

    223 Jalozai Campus of University of ECNEC 6565 272 0 000 3605 643 2959 629 0 000 200 000 200 000

    (Rupees Million)G. Sl.

    NoName of the Scheme Approval

    StatusEstimated Cost Expenditure

    upto 30.06.2015

    Throw-forward as on

    01.07.2015

    Allocation 2015-16

    HIGHER EDUCATION COMMISSION

    223 Jalozai Campus of University of Engineering & Technology, Peshawar

    ECNEC19.09.2007

    6565.272 0.000 3605.643 2959.629 0.000 200.000 200.000

    224 Master Leading to PhD Scholarships Program (Indigenous and Overseas) for the Students of Balochistan (An Initiative of the Aghaz-e-Haqooq-e-Balochistan Package)

    ECNEC11.11.2011

    3138.692 0.000 70.000 3068.692 0.000 427.721 427.721

    225 Monitoring and Development of Programmes of HEC Islamabad. Phase-II, HEC

    DDWP04.11.2009

    55.658 0.000 48.658 7.000 0.000 7.000 7.000

    226 Overseas Scholarship for MS/M. Phil leading to Ph.D in selected fields (Phase II) HEC

    ECNEC 23.08.2006

    14522.350 0.000 11057.472 3464.878 0.000 800.000 800.000

    227 Overseas scholarship scheme for MS/M.Phil/ Ph.D

    ECNEC 07.01.2004

    4275.805 0.000 3912.297 363.508 0.000 100.000 100.000

    228 Pak-US Joint Academic & Research Program Phase-III (Revised)

    CDWP16.01.2009

    521.512 0.000 326.000 195.512 0.000 20.000 20.000

    229 PAK-USAID Merit and Needs Based Scholarship Program (Phase-II)(PSDP Share: Rs. 577.125 million+ USAID Share+ Rs. 2377.682 million = Rs.2954.808 million)

    ECNEC07.10.2013

    577.125 0.000 361.401 215.724 215.724 0.000 215.724

    230 PhD Fellowship for 5000 Scholars (Revised)

    ECNEC 11.08.2003

    6394.537 0.000 4997.580 1396.957 0.000 400.000 400.000

    231 Post Doctoral Fellowship Programme Phase II,

    ECNEC 14.12.2005

    1252.300 0.000 1202.300 50.000 0.000 50.000 50.000

    232 Prime Minister Programme for Development of Ph.Ds in Science & Technology (For On-going Scholars)

    ECNEC06.02.2008

    2898.980 0.000 200.000 2698.980 0.000 400.000 400.000

    233 Prime Minister's Gold Medal including Funding for PhD Abroad for overall Best Student of the Year NUST (Islamabad)

    DDWP01.01.2009

    33.947 0.000 15.873 18.074 0.000 18.074 18.074

    234 Provision of academic and allied facilities at University of Malakand

    CDWP04.05.2015

    996.317 0.000 10.000 986.317 0.000 100.000 100.000

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    235 Provision of academic and research facilities at Sardar Bahadur Khan Women’s University, Quetta.

    CDWP28.04.2015

    696.202 0.000 50.000 646.202 0.000 80.000 80.000

    236 Provision of basic academic and allied facilities at University of Swabi

    CDWP31.03.2015

    1001.274 0.000 10.000 991.274 0.000 200.000 200.000

    237 Provision of basic amenities at Balochistan University of Engineering & Technology, Khuzdar

    CDWP11.04.2014

    798.731 0.000 200.000 598.731 0.000 200.000 200.000

    238 Provision of Higher Education Opportunities For Students of Balochistan and FATA

    ECNEC 22.10.2007

    981.486 0.000 708.225 273.261 0.000 150.000 150.000

    239 Provision of Necessary Operational Facilities for King Abdullah Campuses, University of Azad Jammu & Kashmir, Muzaffarabad

    CDWP 31.03.2015

    574.139 0.000 20.000 554.139 0.000 100.000 100.000

    240 Strengthening of Allama Iqbal Open University, Islamabad

    CDWP27.02.2007

    389.655 0.000 159.000 230.655 0.000 100.000 100.000

    241 Strengthening of Faculty of Oral Health Sciences and Support Facilities at Dow University of Health Sciences, Karachi

    CDWP23.09.2014

    640.209 0.000 45.000 595.209 0.000 150.000 150.000

    242 Strengthening and Development of Sardar Bahadur Khan Women University, Q tt

    CDWP 21.01.2011

    806.040 0.000 457.897 348.143 0.000 125.000 125.000

    Throw-forward as on

    01.07.2015

    Allocation 2015-16

    HIGHER EDUCATION COMMISSION

    (Rupees Million)G. Sl.

    NoName of the Scheme Approval

    StatusEstimated Cost Expenditure

    upto 30.06.2015

    Quetta.

    243 Strengthening and Enhancement of Academic Provisions in the Faculty of Life & Environmental Sciences in the University of Peshawar (To be revised)

    CDWP22.07.2006

    464.695 0.000 464.695 0.000 0.000 82.520 82.520

    244 Strengthening and Expansion of the University of Gujrat and Allied Campuses

    CDWP28.04.2015

    2988.147 0.000 400.000 2588.147 0.000 450.000 450.000

    245 Strengthening and Upgradation of University of Engg. & Tech. Taxila and its Sub Campuses(PSDP Share: Rs. 685.307 million+ Uni Share+ Rs. 100.0 million = Rs.785.307 million)

    CDWP21.02.2013

    685.307 0.000 445.000 240.307 0.000 240.307 240.307

    246 Strengthening of Academic and Research Facilities at Gomal University D. I. Khan

    CDWP 27.01.2015

    839.072 0.000 10.000 829.072 0.000 120.000 120.000

    247 Strengthening of Academic Facilities at Shah Abdul Latif University, Khairpur

    CDWP06.01.2015

    712.607 0.000 15.000 697.607 0.000 150.000 150.000

    248 Strengthening of Agricultural Engineering and Women Development Programs, PMAS Arid Agriculture University, Rawalpindi.

    CDWP06.01.2015

    843.189 0.000 30.000 813.189 0.000 120.000 120.000

    249 Strengthening of Bahauddin Zakariya University, Multan

    CDWP19.11.2009

    971.537 0.000 550.000 421.537 0.000 194.740 194.740

    250 Strengthening of Existing Departments at Islamia University of Bahawalpur

    CDWP23.09.2014

    858.442 0.000 40.000 818.442 0.000 120.000 120.000

    251 Strengthening of Faculties of Lahore College for Women University (LCWU), Lahore

    CDWP 06.09.2013

    643.514 0.000 200.000 443.514 0.000 150.000 150.000

    252 Strengthening of Khyber Medical University Peshawar

    CDWP23.09.2014

    980.352 0.000 40.000 940.352 0.000 120.000 120.000

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    253 Strengthening of National Centre of Excellence in Geology (NCEG), University of Peshawar (Revised).

    ECNEC 25.02.2005

    797.299 0.000 605.563 191.736 0.000 191.736 191.736

    254 Strengthening of NED University of Engineering and Technology, Karachi

    22.10.2007 2193.000 0.000 2056.038 136.962 0.000 136.962 136.962

    255 Strengthening of Quaid-e-Awam University of Engineering, Science and Technology (QUEST), Nawabshah(PSDP Share Rs. 597.816 million + Uni Share: Rs. 100.0 million= Total Rs. 697.816 million)

    CDWP06.09.2013

    597.816 0.000 358.066 239.750 0.000 140.000 140.000

    256 Strengthening of Research Programs at HEJ Research Institute of Chemistry, University of Karachi (PSDP Share = Rs. 518.523 million + Uni Share = Rs. 62.420 million, Total = Rs. 580.943 million)

    CDWP 23.09.2014

    518.523 0.000 40.000 478.523 0.000 175.000 175.000

    257 Strengthening of the University of Poonch Rawalakot, AJ&K

    CDWP03.10.2014

    844.914 0.000 40.000 804.914 0.000 100.000 100.000

    258 Strengthening of University of Balochistan, Quetta and its Campuses

    CDWP19.11.2014

    895.931 0.000 15.000 880.931 0.000 100.000 100.000

    259 Strengthening of University of Engineering & Technology, Lahore.

    ECNEC12.11.2007

    5929.000 0.000 3560.697 2368.303 0.000 300.000 300.000

    260 St th i f U i it f P h CDWP 605 000 0 000 110 000 495 000 0 000 400 000 400 000

    (Rupees Million)G. Sl.

    NoName of the Scheme Approval

    StatusEstimated Cost Expenditure

    upto 30.06.2015

    Throw-forward as on

    01.07.2015

    Allocation 2015-16

    HIGHER EDUCATION COMMISSION

    260 Strengthening of University of Peshawar, Khyber Pukhtunkhwa

    CDWP21.10.2011

    605.000 0.000 110.000 495.000 0.000 400.000 400.000

    261 Strengthening of University of Sindh Jamshoro

    CDWP 11.21.2008

    491.601 0.000 418.000 73.601 0.000 73.601 73.601

    262 Strengthening/Up-gradation of Islamia College Peshawar

    CDWP22.11.2008

    476.496 0.000 393.500 82.996 0.000 82.996 82.996

    263 Strengthening of National Textile University, Faisalabad

    Un-Approved 647.920 0.000 20.000 627.920 0.000 50.000 50.000

    264 Up gradation of Academic Facilities at Sindh Agriculture University Tandojam.

    CDWP27.01.2015

    876.093 0.000 10.000 866.093 0.000 150.000 150.000

    265 Up gradation and Strengthening of Quaid-e-Azam University, Islamabad. Phase II (To be revised)

    CDWP21.12.2006

    485.457 0.000 485.457 0.000 0.000 98.127 98.127

    266 Upgradation of Federal Government College for Women F-7/2 to Federal Women University Islamabad

    CDWP19.11.2014

    1190.709 0.000 80.000 1110.709 0.000 100.000 100.000

    267 Up-gradation of University College of Engineering & Technology Mirpur into Mirpur University of Science & Technology, Mirpur, AJ&K ; (HEC Share; Rs. 1670.024, MUST Share; Rs. 220.00 million)

    ECNEC 26.05.2011

    1890.024 0.000 475.000 1415.024 0.000 300.000 300.000

    268 US-Need Based Merit Scholarship for Pakistani University Students enrolled in Agriculture and Business Administration study programs(USAID) (Revised)

    CDWP03.11.2010

    985.505 0.000 850.609 134.896 55.420 0.000 55.420

    128925.633 0.000 53013.364 75912.269 271.144 15651.856 15923.000

    New Schemes:

    269 Academic and Research Linkages with Different Countries / Agencies under Bilateral Agreements

    Un-Approved 860.000 0.000 0.000 860.000 0.000 20.000 20.000

    Total (On-going)

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    270 Area Study Centre China & CPEC, Quaid-e-Azam University, Islamabad

    Un-Approved 500.000 0.000 0.000 500.000 0.000 150.000 150.000

    271 Bridging the Job Market Skill Gap for General Post Graduate Degree Holders

    Un-Approved 500.000 0.000 0.000 500.000 0.000 25.000 25.000

    272 Capacity Building and Strengthening of the Centre of Excellence in Mineralogy, University of Balochistan, Quetta

    Un-Approved 150.000 0.000 0.000 150.000 0.000 25.000 25.000

    273 Capacity Building and Strengthening of the Pakistan Study Centre, University of Balochistan Quetta

    Un-Approved 110.000 0.000 0.000 110.000 0.000 30.000 30.000

    274 Construction of Boundary Wall at University of Agriculture, Peshawar

    Un-Approved 198.500 0.000 0.000 198.500 0.000 60.000 60.000

    275 Development of Fatima Jinnah Women University, Campus-II, (Phase-2) Chakri Road Rawalpindi

    Un-Approved 650.000 0.000 0.000 650.000 0.000 82.000 82.000

    276 Development of New Campus, Govt. College University (GCU), Faisalabad Phase-II

    Un-Approved 557.870 0.000 0.000 557.870 0.000 35.000 35.000

    277 Development of Shaheed Benazir Bhutto University Sheringal

    Un-Approved 985.347 0.000 0.000 985.347 0.000 50.000 50.000

    278 Enhancement of academic and research f iliti t Q id A U i it

    Un-Approved 850.000 0.000 0.000 850.000 0.000 100.000 100.000

    Allocation 2015-16G. Sl. No

    Name of the Scheme Approval Status

    Estimated Cost Expenditure upto

    30.06.2015

    Throw-forward as on

    01.07.2015

    HIGHER EDUCATION COMMISSION

    (Rupees Million)

    facilities at Quaid-e-Azam University, Islamabad.

    279 Enhancement of Facilities, Institute of Space Technology (IST), Islamabad(with IST share of Rs.125.506 m)

    Un-Approved 1583.605 0.000 0.000 1583.605 0.000 50.000 50.000

    280 Establishment and Upgrading of Core Engineering Departments in Mardan Campus of Khyber Pakhtunkhwa University of Engineering & Technology Peshawar

    Under Process

    986.093 0.000 0.000 986.093 0.000 50.000 50.000

    281 Establishment of AJK Women University, Bagh, AJ&K.

    Un-Approved 450.000 0.000 0.000 450.000 0.000 35.000 35.000

    282 Establishment of Central Asian Regional Economic Cooperation Universitiy

    Un-Approved 5000.000 0.000 0.000 5000.000 0.000 400.000 400.000

    283 Establishment of FATA University Un-Approved 4700.000 0.000 0.000 4700.000 0.000 250.000 250.000

    284 Establishment of Muhammad Nawaz Sharif University of Agriculture, Multan

    Un-Approved 654.000 0.000 0.000 654.000 0.000 30.000 30.000

    285 Establishment of National Science & Technology Park at Central Campus H-12, NUST

    Un-Approved 650.000 0.000 0.000 650.000 0.000 100.000 100.000

    286 Establishment of School and Professional Development at Sardar Bahadur Khan Women’s University, Quetta.

    Un-Approved 670.000 0.000 0.000 670.000 0.000 40.000 40.000

    287 Establishment of sub campus of Balochistan University of Information Technology and Management Sciences, Quetta at Muslim Bagh, Qila Saifullah

    Un-Approved 540.000 0.000 0.000 540.000 0.000 25.000 25.000

    288 Establishment of Sub-Campuses of Public Sector Universities at District Level (Umbrella Project HEC)

    Un-Approved 5000.000 0.000 0.000 5000.000 0.000 100.000 100.000

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    289 Establishment of Technology Development Fund for HEC scholars returning after completion of PhD to introduce new technologies application in Pakistan

    Un-Approved 5000.000 0.000 0.000 5000.000 0.000 300.000 300.000

    290 Establishment of University at Sibi, Balochistan

    Un-Approved 1500.000 0.000 0.000 1500.000 0.000 100.000 100.000

    291 Establishment of University of Baltistan Un-Approved 2000.000 0.000 0.000 2000.000 0.000 100.000 100.000

    292 Expansion and Upgradation of International Islamic University, Sector H-10, Islamabad

    Un-Approved 725.000 0.000 0.000 725.000 0.000 25.000 25.000

    293 Faculty Development Program for Pakistani Universities (HEC)

    Un-Approved 980.000 0.000 0.000 980.000 0.000 50.000 50.000

    294 Fulbright Scholarship Support Program HEC-USAID (Phase-II) (USAID Share: Rs.9896.548 m; HEC Share: Rs.2676.142 m)

    Un-Approved 2676.142 0.000 0.000 2676.142 0.000 100.000 100.000

    295 Innovation Center and Innovation Park at UET Lahore Sub-Campus

    Un-Approved 850.000 0.000 0.000 850.000 0.000 200.000 200.000

    296 Overseas Scholarships for MS/M.Phil Leading to Ph.D in selected fields (Phase III)

    Un-Approved 2500.000 0.000 0.000 2500.000 0.000 50.000 50.000

    Allocation 2015-16G. Sl. No

    Name of the Scheme Approval Status

    Estimated Cost Expenditure upto

    30.06.2015

    Throw-forward as on

    01.07.2015

    HIGHER EDUCATION COMMISSION

    (Rupees Million)

    297 Post Doctoral Fellowship Programme Phase-III

    Un-Approved 4000.000 0.000 0.000 4000.000 0.000 75.000 75.000

    298 Prime Minister's Merit Scholarships for Top Position Holders Enrolled at Pakistani Universities

    Un-Approved 650.000 0.000 0.000 650.000 0.000 25.000 25.000

    299 Provision of academic & allied facilities at University of Agriculture Peshawar Amir Muhammad Khan Campus Mardan

    Under Process

    937.968 0.000 0.000 937.968 0.000 50.000 50.000

    300 Provision of academic and research facilities, Air University, Islamabad

    Un-Approved 850.450 0.000 0.000 850.450 0.000 20.000 20.000

    301 Provision of Higher Education Opportunities For Students of Balochistan and FATA (Phase-II)

    Un-Approved 950.000 0.000 0.000 950.000 0.000 25.000 25.000

    302 Provision of new facilities and infrastructure for main campus, UET, Lahore

    Un-Approved 560.000 0.000 0.000 560.000 0.000 25.000 25.000

    303 Provision of Research and Academic facilities at Kohat University of Science & Technology, Kohat

    Un-Approved 725.000 0.000 0.000 725.000 0.000 25.000 25.000

    304 School of Dentistry, Shaheed Zulfiqar Ali Bhutto Medical University, Islamabad

    CDWP03.03.2015

    1346.196 0.000 0.000 1346.196 0.000 200.000 200.000

    305 Science Farming Scheme for Top Science Talent in Schools

    Un-Approved 1000.000 0.000 0.000 1000.000 0.000 450.000 450.000

    306 Smart Universities: Transformation towards Smart Classrooms

    Un-Approved 1200.000 0.000 0.000 1200.000 0.000 20.000 20.000

    307 Strengthening & Allied Health Facilities of University of Sargodha

    Un-Approved 654.000 0.000 0.000 654.000 0.000 35.000 35.000

    308 Strengthening & Upgradation of Universities of Backward Areas

    Un-Approved 1000.000 0.000 0.000 1000.000 0.000 100.000 100.000

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    309 Strengthening & Expansion of Balochistan University of Information Technology and Management Sciences, Quetta

    Un-Approved 780.000 0.000 0.000 780.000 0.000 35.000 35.000

    310 Strengthening of Academic & Professional Facilities at University of Peshawar

    Un-Approved 735.000 0.000 0.000 735.000 0.000 25.000 25.000

    311 Strengthening of Academic & Research Facilities at Pakistan Institute of Engineering & Applied Sciences (PIEAS), Islamabad

    Un-Approved 650.000 0.000 0.000 650.000 0.000 20.000 20.000

    312 Strengthening of Academic and Research Facilities of University of Health Sciences, Lahore.

    Under Process

    884.599 0.000 0.000 884.599 0.000 25.000 25.000

    313 Strengthening of Academic and Research Program at Bahria University Islamabad/Karachi

    Un-Approved 734.000 0.000 0.000 734.000 0.000 20.000 20.000

    314 Strengthening of Academic and Research Programs at University of the Punjab, Lahore.

    Un-Approved 800.000 0.000 0.000 800.000 0.000 25.000 25.000

    315 Strengthening of Academic and Research Programs at Mehran University of Engineering, Jamshoro

    Un-Approved 780.000 0.000 0.000 780.000 0.000 25.000 25.000

    316 St th i f A d i d R h U A d 745 125 0 000 0 000 745 125 0 000 20 000 20 000

    Allocation 2015-16G. Sl. No

    Name of the Scheme Approval Status

    Estimated Cost Expenditure upto

    30.06.2015

    Throw-forward as on

    01.07.2015

    HIGHER EDUCATION COMMISSION

    (Rupees Million)

    316 Strengthening of Academic and Research Programs at National University of Modern Languages (NUML), Islamabad

    Un-Approved 745.125 0.000 0.000 745.125 0.000 20.000 20.000

    317 Strengthening of Dawood University of Engineering & Technology, Karachi

    Un-Approved 450.000 0.000 0.000 450.000 0.000 20.000 20.000

    318 Strengthening of Infrastructure (Phase-I) at University of Karachi

    Un-Approved 870.000 0.000 0.000 870.000 0.000 25.000 25.000

    319 Strengthening of Institute of Bio-Technology at Bahauddin Zakariya University Multan

    Un-Approved 350.000 0.000 0.000 350.000 0.000 25.000 25.000

    320 Strengthening of Research Programs at Islamia College University, Peshawar.

    Un-Approved 666.771 0.000 0.000 666.771 0.000 25.000 25.000

    321 Subsidy to Scholars Abroad under Cultural Exchange Programme Phase-II.

    Un-Approved 709.218 0.000 0.000 709.218 0.000 50.000 50.000

    322 Technical University, Nowshehra (50:50 Cost Sharing by Federal and Provincial Govt.)

    Un-Approved 3000.000 0.000 0.000 3000.000 0.000 500.000 500.000

    323 Up-gradation and Strengthening of Essential Facilities at Sukkur IBA

    Un-Approved 560.000 0.000 0.000 560.000 0.000 25.000 25.000

    324 Upgradation of National Institute of Science & Technical Education (NISTE) Islamabad into Skill University

    Un-Approved 780.000 0.000 0.000 780.000 0.000 35.000 35.000

    325 Upgradation of University of Hazara Campus at Havelian to a Full-Fledged University

    Un-Approved 800.000 0.000 0.000 800.000 0.000 45.000 45.000

    69994.884 0.000 0.000 69994.884 0.000 4577.000 4577.000

    198920.517 0.000 53013.364 145907.153 271.144 20228.856 20500.000

    Total (New)

    Total (HEC)

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    On-going Schemes:

    326 Acq.of land & Const.of office-cum-Resdl. accommodation for I.B.Staff at D.I.Khan

    DDWP30.07.2009

    39.090 0.000 12.009 27.081 0.000 27.081 27.081

    327 Acq.of land & Const.of office-cum-Resdl. accommodation for I.B.Staff at Kohat

    DDWP30.07.2009

    39.320 0.000 14.157 25.163 0.000 25.163 25.163

    328 Const. of Addl. Block at Election House G-5/2, Islamabad

    DDWP29.06.2011

    58.348 0.000 39.644 18.704 0.000 18.704 18.704

    329 Const. of specialized commando training centre for anti dacoit at Sakrand Road, Benazirabad.

    CDWP07.04.2011

    298.160 0.000 267.769 30.391 0.000 30.391 30.391

    330 Const. of VIP Blocks No. 5 (32 Suits) at Federal Lodge-I, Qasr e Naz Karachi.

    CDWP23.07.2007

    145.406 0.000 87.368 58.038 0.000 58.038 58.038

    331 Const.of 22-Cat-IV Flats for low paid Federal Government Employees Hasan Garhi,Peshawar

    DDWP14.06.2009

    39.812 0.000 22.136 17.676 0.000 17.676 17.676

    332 Const/Extension of Residential accommodation for I.B Academy at H-11/1, Islamabad.

    DDWP16.04.2011

    58.930 0.000 55.596 3.334 0.000 3.334 3.334

    333 Const: of Prestressed Bridge at Mangri to CDWP 859.459 0.000 251.272 608.187 0.000 50.000 50.000

    HOUSING & WORKS DIVISION

    (Rupees Million)G. Sl.

    NoName of the Scheme Approval

    StatusEstimated Cost Expenditure

    upto 30.06.2015

    Throw-forward as on

    01.07.2015

    Allocation 2015-16

    g gFateh Pur Afghana on Nullah Bahian, Tehsil Shakargarh District Narowal

    19.04.2010

    334 Construction of Additional Block for District Accounts Officer, Fort Road, Peshawar

    DDWP19.06.2012

    59.984 0.000 40.420 19.564 0.000 19.564 19.564

    335 Construction of Drainage (Waste Water Channel) Existing Saim Nullah at Mamoon Kanjan, Tehsil Tandlianwala, District Faisalabad (Federal Share)

    CDWP22.11.2012

    251.000 0.000 37.000 214.000 0.000 110.000 110.000

    336 Construction of Federal Lodge-II, Shami Road, Peshawar

    DDWP07.01.2008(RUP Rs 73.771)

    39.512 0.000 36.760 2.752 0.000 2.752 2.752

    337 Construction of Metalled Road at Nankana Sahib

    CDWP04.06.2009(RUP 998.6

    M)

    494.420 0.000 488.407 6.013 0.000 100.000 100.000

    338 Construction of new road from Chandore Sharif to Hari Pur via Lassan adda Palsala Jhokan District Mansehra Phase-I

    CDWP28.11.2014

    100.650 0.000 25.000 75.650 0.000 75.650 75.650

    339 Construction of New Secretariat Block Constitution Avenue, Islamabad

    ECNEC28.12.2015

    4845.412 0.000 3848.262 997.150 0.000 500.000 500.000

    340 Construction of office building for NAB Head quarter at G-5/1,Islamabad

    CDWP04.03.2015

    1746.000 0.000 380.004 1365.996 0.000 200.000 200.000

    341 Construction of Officer's Mess, Bachelors Lodge in Premises of NAB (B) Complexes at Shahra-e-Gulistan, Quetta Cantt.

    DDWP23.05.2014

    53.829 0.000 10.274 43.555 0.000 43.555 43.555

    342 Construction of Residential accommodation at NAB (KPK) Hayatabad Peshawar

    CDWP14.04.2005

    524.186 0.000 296.436 227.750 0.000 40.000 40.000

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    343 Construction of Under pass Railway Crossing of Gujjar Khan District Rawalpindi

    CDWP2008

    424.708 0.000 375.557 49.151 0.000 49.150 49.150

    344 Dualization & Improvement of Mandra-Chakwal road Project (64Km)

    ECNEC03.07.2014

    4671.000 0.000 4386.600 284.400 0.000 284.400 284.400

    345 Dualization & Improvement of Sohawa-Chakwal road Project (66.405Km)

    ECNEC10.04.2015

    4789.000 0.000 330.000 4459.000 0.000 100.000 100.000

    346 Improvement of Security of Prime Minister's Secretariat, Islamabad

    DDWP23.08.2010

    14.643 0.000 13.643 1.000 0.000 1.000 1.000

    347 Musa Khail Tansa Road (35 Km) Stretch Road Zhob

    CDWP31.03.2006RUP (2991

    m)

    505.551 0.000 498.398 7.153 0.000 7.153 7.153

    348 Rehabilitation / Renovation and Refurbishment of Federal Lodge-I Quetta

    DDWP30.12.2014

    5.184 0.000 1.500 3.684 0.000 3.684 3.684

    349 Renovation & Rehabilitation 20-Cat-C & 32-Cat-D type flats at Government Officer Colony at Garden Road , Karachi (Phase-II)

    DDWP18.12.2007

    39.203 0.000 39.203 0.000 0.000 5.000 5.000

    350 Renovation / Construction of M/Road from Chan Chowk to Rouza Pull (along Canal) Complex District Sargodha

    CDWP22.02.2013

    203.000 0.000 149.735 53.265 0.000 53.265 53.265

    Throw-forward as on

    01.07.2015

    Allocation 2015-16

    HOUSING & WORKS DIVISION

    (Rupees Million)G. Sl.

    NoName of the Scheme Approval

    StatusEstimated Cost Expenditure

    upto 30.06.2015

    351 Renovation / Improvement of Victoria Railway bridge over Jhelum river at Chak Nizam District Mandi Bahauddin

    CDWP22.09.2012

    380.000 0.000 10.414 369.586 0.000 50.000 50.000

    352 Renovation/Re-habilitation of Minister's Residences at Islamabad

    DDWP26.01.2010

    47.740 0.000 42.534 5.206 0.000 5.206 5.206

    353 Re-settlement of Christian Colony at Quetta (Federal Full Share)

    CDWP10.10.2008

    248.683 0.000 234.728 13.955 0.000 13.955 13.955

    354 Up gradation and renovation of Qasar-e-Naz Karachi

    DDWP14.06.2006

    55.651 0.000 55.651 0.000 0.000 5.000 5.000

    355 Water supply schemes (Baradar, Bud hall, Poodnial) Oghi District Mansehra

    CDWP28.11.2014

    83.194 0.000 50.000 33.194 0.000 33.194 33.194

    356 Water supply schemes (Pharkayyan, Dhanaka Sherif, Lundi MalikPur) District Mansehra

    DDWP25.09.2014

    47.180 0.000 35.000 12.180 0.000 12.180 12.180

    21168.255 0.000 12135.477 9032.778 0.000 1945.095 1945.095

    New Schemes:

    357 Construction of Conference Room and Offices at Prime Minister's House, Islamabad

    Un-Approved 121.339 0.000 0.000 121.339 0.000 121.339 121.339

    358 Development Schemes in District Mansehra

    AUP 760.129 0.000 0.000 760.129 0.000 300.000 300.000

    359 Development Schemes in District Torghar AUP 272.928 0.000 0.000 272.928 0.000 200.000 200.000

    360 Improvement and Uplift of Gulshan-e-Jinnah, Islamabad

    DDWP31.12.2014

    59.795 0.000 0.000 59.795 0.000 10.000 10.000

    361 Water Supply Scheme Chachar Shareef, Shahpur District Sargodha

    AUP 14.000 0.000 0.000 14.000 0.000 14.000 14.000

    Total (New) 1228.191 0.000 0.000 1228.191 0.000 645.339 645.339

    22396.446 0.000 12135.477 10260.969 0.000 2590.434 2590.434Total (Housing & Works)

    Total (On-going)

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    On-going Schemes:

    362 Development Project of Pakistan Gems and Jewellery Development Company

    ECNEC19.09.2007

    1400.000 0.000 1090.720 309.280 0.000 60.000 60.000

    363 Establishment of 0.2 MGD Intake & Brine Disposal System / Civil Works for Desalination Plants at Gaddani, Jiwani & Pasni.

    CDWP21.01.2011

    287.380 0.000 260.697 26.683 0.000 26.683 26.683

    364 Establishment of Bostan Industrial Estate Bostan Phase-I

    CDWP 21.01.2011

    400.412 0.000 113.558 286.854 0.000 25.000 25.000

    365 Establishment of Castor Oil Solvent Extraction Plant at Uthal District Lasbela.

    CDWP21.01.2011

    300.000 0.000 22.384 277.616 0.000 5.000 5.000

    366 Establishment of CFC for Silk Cluster, Swat Khyber Pakhtunkhwa

    DDWP 25-11.2009

    57.530 0.000 38.371 19.159 0.000 17.530 17.530

    367 Establishment of Chromite Beneficiation Plant at Muslim Bagh.

    CDWP07.04.2011

    104.345 0.000 92.345 12.000 0.000 12.000 12.000

    368 Establishment of Design Institute Especially for Energy Sector Plants by Up-grading Existing Design Centre at HMC, Taxila

    CDWP 21.01.2011

    665.380 0.000 230.734 434.646 0.000 86.000 86.000

    369 Establishment of Gems and Jewellery DDWP 59.920 0.000 25.113 34.807 0.000 16.500 16.500

    INDUSTRIES & PRODUCTION DIVISION

    (Rupees Million)G. Sl.

    NoName of the Scheme Approval

    StatusEstimated Cost Expenditure

    upto 30.06.2015

    Throw-forward as on

    01.07.2015

    Allocation 2015-16

    yTraining and Processing Centre, Muzaffarabad

    03.05.2010

    370 Establishment of Infrastructure in Quetta Industrial and Trading Estate Phase-II

    CDWP 21.01.2011

    174.250 0.000 132.000 42.250 0.000 42.250 42.250

    371 Establishment of Turbines and Power Plant Equipment Manufacturing Facility at HMC, Taxila

    ECNEC26-05-2011

    21543.100 13454.100 117.167 21425.933 0.000 3.000 3.000

    372 Foundry Service Center (FSC), Lahore CDWP 30.04.2009

    206.310 0.000 182.766 23.544 0.000 10.000 10.000

    373 Hyderabad Engineering Support Centre (HESC)

    CDWP07.04.2011

    223.490 0.000 78.861 144.629 0.000 50.000 50.000

    374 Light Engineering Upgradation Centre for SMEs in Balochistan (LEUC)

    CDWP07.04.2011

    217.900 0.000 78.971 138.929 0.000 50.000 50.000

    375 Peshawar Light Engineering Centre (PLEC)

    CDWP07.04.2011

    230.560 0.000 66.952 163.608 0.000 50.000 50.000

    376 Provision of Infrastructure in Quetta Industrial Estate Phase IV

    CDWP 21.01.2011

    126.930 0.000 84.930 42.000 0.000 22.000 22.000

    377 Sialkot Business and Commerce Centre (SBCC), Sialkot

    CDWP02.05.2014

    484.610 0.000 243.340 241.270 0.000 241.270 241.270

    378 Up-gradation of NFC Institute of engineering & Technology Facilities, Multan

    CDWP21.10.2011

    100.000 0.000 76.352 23.648 0.000 23.648 23.648

    379 Water Supply Scheme for HITE Phase-II(Ext) Balochistan, Mouza Pathra, Tehsil Hub, District Lasbella

    CDWP02.07.013

    353.216 0.000 118.288 234.928 0.000 50.000 50.000

    26935.333 13454.100 3053.549 23881.784 0.000 790.881 790.881Total (I&P)

  • Total Foreign Assistance

    Foreign Assistance

    Rupee Total

    1 2 3 4 5 6 7 8 9 10

    On-going Schemes:

    380 Construction of Auditorium at Pakistan Academy of Letters, H-8/1, Islamabad

    DDWP 30.06.2008

    (RUP 98.206 M)

    39.630 0.000 39.630 0.000 0.000 28.000 28.000

    381 Dubbing of Pakistani Dramas in Foreign Languages

    DDWP12.01.2015

    44.179 0.000 14.000 30.179 0.000 30.179 30.179

    382 Establishment of Saut-ul-Quran FM Network (National)

    CDWP 27.01.2015

    82.156 0.000 25.000 57.156 0.000 31.000 31.000

    383 Media Monitoring and Tracking Center, Directorate of Electronic Media and Publications, B.F Building , Zero Point, Islamabad

    DDWP 26.04.2012

    54.000 0.000 30.836 23.164 0.000 23.164 23.164

    384 Preparation of Database of Paintings/Art Works PNCA F-5/1, Islamabad

    DDWP20.05.2009

    30.650 0.000 20.492 10.158 0.000 10.158 10.158

    385 Rebroadcast Station, Athmaqam Neelum Valley (AJ&K)

    DDWP 06.08.2013

    52.297 0.000 20.850 31.447 0.000 5.000 5.000

    386 Rebroadcast Station, Aliabad / Karimabad (Gilgit-Baltistan)

    DDWP 30.08.2012

    49.753 0.000 42.257 7.496 0.000 7.496 7.496

    387 Rebroadcast Station, Badin (Sindh) CDWP 06.09.2013

    91.453 0.000 57.970 33.483 0.000 33.483 33.483

    Allocation 2015-16G. Sl. No

    Name of the Scheme Approval Status

    Estimated Cost Expenditure upto

    30.06.2015

    Throw-forward as on

    01.07.2015

    INFORMATION, BROADCASTING & NATIONAL HERITAGE DIVISION

    (Rupees Million)

    388 Rebroadcast Station, Bar Khan (Balochistan)

    DDWP 06.08.2013

    55.384 0.000 33.860 21.524 0.000 5.000 5.000

    389 Rebroadcast Station, Besham (Maira) (Khyber Pakhtunkhwa)

    DDWP30.08.2012

    57.700 0.000 48.594 9.106 0.000 9.106 9.106

    390 Rebroadcast Station, Buneer (Khyber Pakhtunkhwa)

    DDWP 09.10.2013

    55.444 0.000 30.742 24.702 0.000 10.000 10.000

    391 Rebroadcast Station, Chilas (Gilgit-Baltistan)

    DDWP30.08.2012

    49.146 0.000 43.357 5.789 0.000 5.789 5.789

    392 Rebroadcast Station, Dhudhnial Neelum Valley (AJ&K)

    DDWP 15.03.2013

    50.731 0.000