GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Concreting of Rimando Road Baguio
City
BCEO 02.28.94 05.13.94
Concreting of Lourdes Road Baguio City
BCEO 02.28.94 05.20.94
Concreting of Upper/Lower Assumption Road Baguio
City
BCEO 02.28.94 05.20.94
Concreting of Maryhurst Road Baguio City
BCEO 02.28.94 07.14.94
Concreting of Dahlia St., QM Baguio City
BCEO 03.25.94 07.15.94
Concreting of Camelia St., QM Baguio
City
BCEO 04.18.94 06.20.94
Concreting of UP Drive, Govt. Center Baguio City
DPWH-BCDEO 04.28.94 05.25.94
Concreting of Mirador Hill Baguio
City
DPWH-BCDEO 06.14.94 07.18.94
Concreting of Philex-Kias Road Kias,
Itogon to Padcal,
Tuba, Benguet
Philex Mining
Corporation
05.01.94 02.28.95
Rehabilitation of City Camp Lagoon Baguio
City
DPWH-BCDEO 11.11.94 02.16.95
Concreting of Leonard Wood Road, Phase II Baguio City
DPWH-BCDEO 01.10.95 02.27.95
Concreting of Santo Tomas, Green Valley Tuba,
Benguet
DPWH-BCDEO 01.12.95 03.10.95
Concreting of Leonard Wood Road, Phase III Baguio
City
DPWH-BCDEO 02.01.95 03.23.95
Construction of Retaining Walls and Concreting of Harrison Road
Baguio City
DPWH-BCDEO 03.03.95 05.09.95
13
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Improvement of Harrison Road 1 & 2 Baguio
City
DPWH-BCDEO 03.10.94 06.12.95
Concreting of Kayang Road Baguio City
DPWH-BCDEO 05.05.95 06.26.95
Improvement of Asin Road Widening & Concreting Baguio
City
DPWH-BCDEO 01.02.96 03.07.96
Improvement of Padcal Road Baguio City
DPWH-BCDEO 02.04.96 05.18.96
Improvement of Sto-Tomas- Mt. Cabuyao Road Baguio City
DPWH-CAR 02.16.96 06.27.96
Improvement of Sgt. Floresca Street Baguio
City
DPWH-BCDEO 03.18.96 08.15.96
Improvement of Pacdal Road- Supplemental Baguio City
DPWH-BCDEO 06.11.96 11.07.96
Improvement of Sto. Tomas - Mt. Cabuyao Road -
Supplemental
Baguio
City
DPWH-CAR 06.11.96 11.07.96
Concreting Along Baguio-Bua-Itogon Road Itogon,
Benguet
DPWH-CAR 06.19.96 12.04.96
Preventive Maintenance Along Bokawkan & Harrison Road 1
Baguio City
DPWH-BCDEO 09.15.96 11.26.96
Improvement/Widening Along Bokawkan - Magsaysay
Road
Baguio
City
DPWH-CAR 10.04.96 02.04.97
Concreting of Kias-Balatoc Poblacion Road Itogon, Benguet
DPWH-CAR 11.19.96 12.14.96
Concreting of Antamok Tram-Keystone Midas Road Itogon,
Benguet
DPWH-CAR 11.27.96 01.14.97
Construction of Access Road Along Magsaysay Avenue Baguio
City
Dr. Margarita
Fernandez
12.04.96 01.11.97
Widening Along Magsaysay Avenue Baguio City
DPWH-BCDEO 12.28.96 03.26.97
14
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Concreting of Gibraltar Road Baguio
City
DPWH-BCDEO 01.15.97 02.04.97
Concreting of Tuding Gumatdang Road Itogon, Benguet
DPWH-CAR 02.10.97 03.30.97
Concreting of Happy Glenn Loop Road Baguio
City
DPWH-BCDEO 01.11.97 06.20.97
Concreting of Kias-Balatoc/Bua-Itogon Road Supplemental Contract
Itogon, Benguet
DPWH-CAR 02.22.97 06.04.97
Concreting of Navy Base Road, Saint Joseph Village Barangay
Baguio City
DPWH-CEO 04.18.97 09.24.97
Improvement/Construction of Leonard Wood Road Baguio
City
DPWH-BCDEO 06.25.97 08.09.97
Improvement Along Tacay Longlong Road Baguio City
DPWH-BCDEO 06.25.97 10.23.97
Improvement Along Tacay Longlong Road, Balete La
Trinidad, Benguet
DPWH-CAR 06.15.97 01.09.98
Repair/Rehab. of Klondykes Section, Kennon Road (Phase 1)
Tuba, Benguet
DPWH-BED 02.10.98 11.27.98
Repair/Rehab. of Klondykes Section, Kennon Road
(Phase II)
Tuba,
Benguet
DPWH-BED 02.10.98 11.27.98
Repair/Rehab. of Klondykes Section, Kennon Road (Phase III)
Tuba, Benguet
DPWH-BED 02.10.98 11.27.98
Improvement of Leonard Wood Road Baguio
City
DPWH-BCDEO 11.30.98 12.19.98
Improvement of Kennon Road Baguio
City
DPWH-BCDEO 02.28.99 03.22.99
Improvement of Leonard Wood Road Baguio City
DPWH-BCDEO 04.14.99 05.25.99
Improvement of Kennon Road Baguio
City
DPWH-BCDEO 05.13.99 06.12.99
15
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Improvement Along Baguio-Bontoc Road Baguio
City
DPWH-CAR 06.28.98 09.02.99
Improvement Along Pico-Lamtang Road Baguio City
DPWH-CAR 03.26.99 09.23.99
Improvement of Government Center Cut-Off Road Baguio
City
DPWH-BCDEO 02.26.99 10.19.99
Finishing of Klondykes Section, Kennon Road Tuba, Benguet
DPWH-BED 08.28.99 04.07.00
Improvement Along Twin River Dalupirip Road, Km. 265+184 - Km. 267+000(v.s.)
Itogon, Benguet
DPWH-BED 01.04.00 03.17.00
Improvement Along Twin River Dalupirip Road, Km.
265+484 - Km. 269+000(v.s.)
Itogon,
Benguet
DPWH-BED 02.14.00 04.12.00
Improvement Along Twin River Dalupirip Road, Km. 267+500 - Km. 269+500(v.s.)
Itogon, Benguet
DPWH-BED 02.14.00 04.14.00
Improvement Along Kennon Road Baguio
City
DPWH-BCDEO 06.20.00 10.16.00
Improvement Along Kennon Road Baguio
City
DPWH-BCDEO 08.20.00 10.16.00
Improvement Along Carantes Road Itogon, Benguet
DPWH-BED 04.10.00 11.05.00
Improvement of Session Road 1 & 2 Baguio
City
DPWH-BCDEO 09.12.00 11.17.00
Road Concreting at South Drive Baguio City
BCEO 11.21.00 01.15.01
Improvement Along Twin River Dalupirip Road, Km.
265+040 - Km. 275+000(v.s.)
Itogon,
Benguet
DPWH-BCDEO 02.14.00 03.19.01
Improvement Along Labilab Brgy. Road Itogon,
Benguet
DPWH-CAR 01.14.01 05.31.01
Conc/Improvement of Session Road, Baguio City
DPWH-BCDEO 08.21.01 09.11.01
16
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Conc/Improvement Along Gibraltar Road, Baguio
City
DPWH-BCDEO 09.05.01 09.21.01
Improvement of Kennon Road (Camp 6) Baguio City
DPWH-BCDEO 07.12.01 10.29.01
Improvement of Kennon Road (Camp 7) Baguio
City
DPWH-BCDEO 07.26.01 11.19.01
Improvement Along Lake Drive-Abad Santos Drive,
Burnham Park
Baguio
City
DPWH-BCDEO 12.19.01 04.15.02
Restoration Along Kennon Road, Km. 223+150 - Km.
223+170
Tuba,
Benguet
DPWH-BCDEO 12.15.01 01.22.02
Restoration Along Kennon Road, Km. 230+944 - Km. 231+055
Tuba, Benguet
DPWH-BCDEO 12.15.01 01.23.02
Restoration Along Kennon Road, Km. 235+800 - Km.
235+847
Tuba,
Benguet
DPWH-BCDEO 12.15.01 01.22.02
Restoration Along Kennon Road, Km. 231+060 - Km.
231+090
Tuba,
Benguet
DPWH-BCDEO 12.15.01 01.23.02
Road Concreting and Improvement of Drainage Projects Baguio
City
City Government
of Baguio
02.11.02 04.18.02
a. Quezon Hill Cut-off, Quezon Hill Proper Brgy.
b. Queen of Angels, Lourdes proper Brgy.
c. Bado Dangwa, Cresencia Village Brgy.
d. Baltazar Street, Gibraltar Brgy.
e. Ruiz Castro Street, Gibraltar Brgy.
f. Recto Street, Navy Base Brgy.
g. Teachers Camp Barangay
h. Felipe Street, Lualhati Barangay
17
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Improvement of Drainage & Road Conc. Along Baguio
City
DPWH-BCDEO 06.10.02 07.16.02
a. Chanum Street
b. Magsaysay Avenue-Kabayanihan Barangay
c. Magsaysay Avenue-Upper Magsaysay Brgy.
Improvement Along Baguio-Asin Road, Km. 262+262 -
Km. 264+074
Tuba,
Benguet
DPWH-CAR 04.29.02 11.25.02
Construction of Teachers Camp Road Baguio City
DPWH-BCDEO 05.28.03 08.18.03
Rehab. of Baguio-Bontoc-Banaue
Road (Halsema Highway) Package:
Section II KM 295+312 – KM 340+967
Halsema,
Benguet
DAEWOO
Engineering &
Construction Co. LTd.
10.01.02 02.01.05
Rehab./Improvement along City Limit-Asin Proper (Phase
I)
Tuba,
Benguet
Province of
Benguet
03.10.03 11.20.03
Rehab./Improvement along City Limit-Asin Proper (Phase II)
Tuba, Benguet
Province of Benguet
03.10.03 11.20.03
Rehab./Improvement along City Limit-Asin Proper (Phase
III)
Tuba,
Benguet
Province of
Benguet
03.10.03 11.20.03
Improvement of Marcos Highway to Sta. Lucia Road, Km.
250+621 - Km. 252+037
Baguio
City
DPWH-BCDEO 03.28.03 11.30.03
Improvement of Drainage System, Burnham Park to Magsaysay Avenue
Baguio City
DPWH-BCDEO 12.15.03 05.26.04
Restoration and Dredging Works of Camp 1 Bridge Along
Kennon Road
Tuba,
Benguet
DPWH-CAR 01.05.04 10.30.04
Opening/Improvement of Buyagan-Gayasi-Kesbeng Road (Phase I & II)
La Trinidad,
Benguet
DPWH-CAR 04.06.04 04.15.05
Completion of Drainage in Burnham Park Baguio
City
DPWH-BCDEO 06.21.04 10.07.04
18
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Completion of Drainage System fr. Magsaysay Ave. to
Brgy. Sto. Nino Slaughter Cpd.
Baguio
City
DPWH-BCDEO 04.25.05 10.03.05
Improvement of Camp 7 Loakan Kadaclan Junction Package 1 Km. 245+162 - Km. 246+800
Baguio City
DPWH-CAR 06.15.05 10.10.05
Improvement /Rehabilitation along Bokawkan Road Baguio
City
DPWH-BCDEO 11.20.05 12.20.05
Rehabilitation of Bokawkan Road Baguio City
DPWH-BCDEO 01.16.06 01.24.06
Improvement/Rehabilitation of Kennon Road, Km.241+308-km.241+530
Baguio City
DPWH-BCDEO 05.08.06 06.23.06
Restoration of Eroded Slope Protection at Lopez Jaena Baguio
City
Municipal Gov’t.
of Baguio
10.06.06 12.15.06
MRF & Composting Site Development at the MRF site Induyan Alno
La Trinidad,
Benguet
Municipality of La Trinidad
10.11.06 12.30.06
MRF AND Composting Site Development at Induyan Alno La Trinidad,
Benguet
Municipality of Trinidad
11.23.06 01.30.08
Restoration of Collapsed Retaining Wall and Drainage
System Along Baguio-Bauang Road
Baguio
City
DPWH-BCDEO 12.16.06 02.23.06
Improvement of Pico Lamtang Road, km.254+790.50-km.254+840.50
La Trinidad,
Benguet
DPWH-BED 12.16.06 02.23.06
Improvement/Upgrading along Baguio-Bauang Road, Km. 304+315 - Km. 304+918 (v.s.)
Baguio City
DPWH-BCDEO 12.16.06 02.24.06
Improvement of Betag-Swamp-Puguis Trading Post FTMR La
Trinidad
Benguet
DPWH-BED 12.27.06 02.09. 07
Improvement of Happy Hollow to Country Club km.250+240-km.251+280
Baguio City
DPWH-BCDEO 01.15.07 08.30.07
19
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Rehab./Restoration of Retaining Wall at Trinidad Road
Magsaysay Ave., and Road Cut at P. Burgos Street
Baguio
City
DPWH-BCDEO 01.18.07 02.21.07
Rehabilitation of Magsaysay and Burgos Road Baguio City
DPWH-BCDEO 01.18.07 03.19.07
Improvement of Tunnel#2 km.262.647+km.262.7028-
km.264.5025+km.264.7201 at Asin Nangalisan Road
Tuba
Benguet
Provincial
Government of Benguet
02.05.07 04.10.07
Improvement Rehabilitation of Loakan Airport Road
Military Circle up to NFA km.249+674-km.250+674
Baguio
City
DPWH-BCDEO 02.28.07 05.23.07
Improvement/Concreting of Bontoc-Tinglayan Bdry.
Road, and Improvement of Baguio-Bontoc-Banaue Road
Mt.
Province
DPWH-CAR 03.21.07 04.21.08
a. (Package 1) Km.394+870-km.396+500
b. (Package 2) km.396+500-km.398+400
c. (Package 3) km.400+620-km.401+950
d. (Package 4) km.401+950-km.403+750
e. (Package 5) km.403+750-km.405+200
f. Km.363+100-km.367+243
g. Km.367+243-km.369+413
h. Km.369+413-km.370+666
i. Km.380+774-km.383+450
Rehabilitation of Kennon Road km.242+966-km.243+000 and km.245+268-km.245+563
Baguio City
DPWH-BCDEO 03.26.07 06.25.07
20
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Improvement of Pico Lamtang Road, km.254+830.50-
km.960.50
La
Trinidad, Benguet
DPWH-BED 05.10.07 08.21.07
Restoration and Dredging along Camp 1Bridge, Bued
River Kennon Road
Tuba,
Benguet
Province of
Benguet
06.05.07 07.31.07
Const. of Baguio Flyover and Approaches (Phase I) at BGH Rotunda Marcos Highway-Gov. Pack-Kisad Road to
Kennon Road Junction
Baguio City
DPWH-CAR 09.10.07 12.12.07
Const. of Baguio Flyover and Approaches (Phase III) at
BGH Rotunda Marcos Highway-Gov. Pack-Kisad Road to Kennon Road Junction
Baguio
City
DPWH-CAR 09.10.07 12.17.07
Const. of Baguio Flyover and Approaches (Phase 1V) at
BGH Rotunda Marcos Highway-Gov. Pack-Kisad Road to Kennon Road Junction
Baguio
City
DPWH-CAR 09.10.07 12.17.07
Const. of Baguio Flyover and Approaches (Phase V) at
BGH Rotunda Marcos Highway-Gov. Pack-Kisad Road to Kennon Road Junction
Baguio
City
DPWH-CAR 09.10.07 01.03.08
Repair/Rehabilitation of Flood Control along Kennon Road-Agat, km.216+654-km.217+689 (vs)
Tuba Benguet
DPWH-CAR 01.21.08 02.18.08
Dredging of Riverbed at Camp 1 Bridge Tuba
Benguet
DPWH-CAR 01.21.08 02.21.08
Rehabilitation/Concreting of Cervantes-Sabangan Road, km.398+446-km.405+543.59
Mountain Province
DPWH-CAR 04.04.08 09.24.09
Rehabilitation/Improvement of Outlook Drive,
km.254+316-km.255+197 (v.s.)
Baguio
City
DPWH-BCDEO 06.27.08 08.19.08
Rehabilitation/Improvement of Ferguson Road,
km.306+077-km.306+367
Baguio
City
DPWH-BCDEO 06.27.08 08.19.08
Rehabilitation/Improvement of Kennon Road, km.244+183-km.247+202 w/ exception
Baguio City
DPWH-BCDEO 06.27.08 08.19.08
Rehabilitation/Improvement of Balatoc Road,
km.248+008-km.248+896.5 (v.s.)
Baguio
City
DPWH-BCDEO 06.27.08 08.19.08
21
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Rehabilitation/Improvement of Loakan Road,
km.245+580-km.246+113
Baguio
City
DPWH-BCDEO 06.27.08 08.19.08
Rehabilitation along City Limit-Santo Tomas Road, km.255+000-km.264+268 (various section)
Tuba, Benguet
DPWH-CAR 09.15.08 12.11.08
Rehabilitation along Itogon-Dalupirip-San Manuel
Boundary Road, km.267+000-km.278+587 (vs)
Itogon,
Benguet
DPWH-CAR 09.15.08 02.20.09
Improvement/Concreting of Loakan Road, Phase 2 Baguio City
DPWH-BCDEO 12.02.08 01.13.09
Const. of Baguio Flyover and Approaches at BGH Rotunda Marcos Highway-Gov. Pack-Kisad Road to
Kennon Road Junction
Baguio City
DPWH-CAR 12.24.08 02.13.09
Improvement of Road Leading to Assumption Convent Crystal Cave, Bakakeng Central
Baguio City
DPWH-BCDEO 01.14.09 04.06.09
Rehabilitation, Reconstruction of Damaged National
Roads Generated from Pavement System/Highway Development and Management (HDM-4) along
a.) Kennon Road
b.) Loakan Road c.) Outlook Drive
Baguio
City
DPWH-BCDEO 03.26.09 07.23.09
One Cluster Concreting & Improvement Project along
Benguet 1 a.) Concreting along Itogon-Dalupirip Road
b.) Improvement along Baguio City Limit Sto. Tomas Road
Itogon Benguet
Tuba Benguet
DPWH-BFDEO 04.13.09 07.24.09
Rehabilitation/Construction of Gurel-Bokod-Kabayan-
Buguias-Abatan Road, km.300+138-km.364+500
Benguet DPWH-CAR 04.15.09
04.28.10
Repair/Rehab. of Road Slip & Slope Protection along
Palispis (Marcos) Highway km.268+400-km.268+960 (Phase 1)
Tuba,
Benguet
DPWH-BFDEO 02.15.10 04.15.10
22
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Binga- Guisset Refurbishment Itogon,
Benguet
SN Aboitiz
Power-Benguet, Inc.
09.21.09 02.26.10
Ambuklao, Itogon Benguet – Equipment Rental Itogon,
Benguet
SN Aboitiz
Power-Benguet, Inc.
05.10.09 05.30.09
Road Widening at Guisset Road,
Binga – Guisset Maintenance,
Road Widening of various sectionsalong Guiesst – Binga Road, and
Clearing of Slides at Guisset – Binga Road
Itogon,
Benguet
SN Aboitiz
Power-Benguet,
Inc.
10.15.09 05.10.10
Clearing of Slides at Binga-Ambuklao Road (1) Clearing of Slides at Binga-Ambuklao Road (2)
Itogon, Benguet
SN Aboitiz Power-Benguet,
Inc.
10.05.09 11.10.09
Earth Balling – Equipment Rental Widening at BALOI Checkpoint
Clearing of Mountain Slope- BHEPP
Claering of Slides at Ongkalew, Barangay Tinongdan, and Laydown Area
Itogon, Benguet
SN Aboitiz Power-Benguet,
Inc.
11.10.09 03.15.10
Slope Protection Project at Sitio Libong, ,Ambuklao,
Itogon Benguet – Equipment Rental
Itogon,
Benguet
SN Aboitiz
Power-Benguet, Inc.
11.05.09 12.05.09
Clearing of Mountain Slope - Powerhouse Itogon,
Benguet
SN Aboitiz
Power-Benguet, Inc.
09.15.09 01.20.10
Construction of 2 Sections Riprap Walls near the Bridge
along Ambuklao Road
Itogon,
Benguet
SN Aboitiz
Power-Benguet,
Inc.
12.05.09 01.25.10
Hauling of Surplus Materials at Ambuklao Itogon, Benguet
SN Aboitiz Power-Benguet,
Inc.
12.20.09 07.30.10
23
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Repair/Rehab. along Palispis (Marcos) Highway,
km.267+380-km.267+410 (Phase II)
Tuba,
Benguet
DPWH-BFDEO 01.21.10 02.28.10
Improvement of Happy Hollow to Happy Hollow (CPEL 4) Happy Hollow Barangay
Baguio City
DPWH-BCDEO 06.06.06 07.10.10
24
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Concreting of Rimando Road Baguio
City
DPWH-BCDEO 02.28.94 05.13.94
Concreting of Lourdes Road Baguio City
DPWH-BCDEO 02.28.94 05.20.94
Concreting of Upper/Lower Assumption Road Baguio
City
DPWH-BCDEO 02.28.94 05.20.94
Concreting of Maryhurst Road Baguio City
DPWH-BCDEO 02.28.94 07.14.94
Concreting of Dahlia St., QM Baguio City
DPWH-BCDEO 03.25.94 07.15.94
Concreting of Camelia St., QM Baguio
City
DPWH-BCDEO 04.18.94 06.20.94
Concreting of UP Drive, Govt. Center Baguio City
DPWH-BCDEO 04.28.94 05.25.94
Concreting of Mirador Hill Baguio
City
DPWH-BCDEO 06.14.94 07.18.94
Concreting of Philex-Kias Road Kias,
Itogon to Padcal,
Tuba, Benguet
Philex Mining
Corporation
05.01.94 02.28.95
Rehabilitation of City Camp Lagoon Baguio
City
DPWH-BCDEO 11.11.94 02.16.95
Concreting of Leonard Wood Road, Phase II Baguio City
DPWH-BCDEO 01.10.95 02.27.95
Concreting of Santo Tomas, Green Valley Tuba,
Benguet
DPWH-BCDEO 01.12.95 03.10.95
Concreting of Leonard Wood Road, Phase III Baguio
City
DPWH-BCDEO 02.01.95 03.23.95
25
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Construction of Retaining Walls and Concreting of
Harrison Road
Baguio
City
DPWH-BCDEO 03.03.95 05.09.95
Improvement of Harrison Road 1 & 2 Baguio City
DPWH-BCDEO 03.10.94 06.12.95
Concreting of Kayang Road Baguio
City
DPWH-BCDEO 05.05.95 06.26.95
Improvement of Asin Road Widening & Concreting Baguio City
DPWH-BCDEO 01.02.96 03.07.96
Improvement of Padcal Road Baguio City
DPWH-BCDEO 02.04.96 05.18.96
Improvement of Sto-Tomas- Mt. Cabuyao Road Baguio
City
DPWH-CAR 02.16.96 06.27.96
Improvement of Sgt. Floresca Street Baguio City
DPWH-BCDEO 03.18.96 08.15.96
Improvement of Pacdal Road- Supplemental Baguio
City
DPWH-BCDEO 06.11.96 11.07.96
Improvement of Sto. Tomas - Mt. Cabuyao Road -
Supplemental
Baguio
City
DPWH-CAR 06.11.96 11.07.96
Concreting Along Baguio-Bua-Itogon Road Itogon, Benguet
DPWH-CAR 06.19.96 12.04.96
Preventive Maintenance Along Bokawkan & Harrison
Road 1
Baguio
City
DPWH-BCDEO 09.15.96 11.26.96
Improvement/Widening Along Bokawkan - Magsaysay Road
Baguio City
DPWH-CAR 10.04.96 02.04.97
Concreting of Kias-Balatoc Poblacion Road Itogon,
Benguet
DPWH-CAR 11.19.96 12.14.96
Concreting of Antamok Tram-Keystone Midas Road Itogon,
Benguet
DPWH-CAR 11.27.96 01.14.97
Construction of Access Road Along Magsaysay Avenue Baguio City
Dr. Margarita Fernandez
12.04.96 01.11.97
26
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Widening Along Magsaysay Avenue Baguio
City
DPWH-BCDEO 12.28.96 03.26.97
Concreting of Gibraltar Road Baguio City
DPWH-BCDEO 01.15.97 02.04.97
Concreting of Tuding Gumatdang Road Itogon,
Benguet
DPWH-CAR 02.10.97 03.30.97
Concreting of Happy Glenn Loop Road Baguio City
DPWH-BCDEO 01.11.97 06.20.97
Concreting of Kias-Balatoc/Bua-Itogon Road Supplemental Contract
Itogon, Benguet
DPWH-CAR 02.22.97 06.04.97
Concreting of Navy Base Road, Saint Joseph Village
Barangay
Baguio
City
DPWH-CEO 04.18.97 09.24.97
Improvement/Construction of Leonard Wood Road Baguio City
DPWH-BCDEO 06.25.97 08.09.97
Improvement Along Tacay Longlong Road Baguio
City
DPWH-BCDEO 06.25.97 10.23.97
Improvement Along Tacay Longlong Road, Balete La
Trinidad, Benguet
DPWH-CAR 06.15.97 01.09.98
Repair/Rehab. of Klondykes Section, Kennon Road
(Phase 1)
Tuba,
Benguet
DPWH-BED 02.10.98 11.27.98
Repair/Rehab. of Klondykes Section, Kennon Road (Phase II)
Tuba, Benguet
DPWH-BED 02.10.98 11.27.98
Repair/Rehab. of Klondykes Section, Kennon Road
(Phase III)
Tuba,
Benguet
DPWH-BED 02.10.98 11.27.98
Improvement of Leonard Wood Road Baguio
City
DPWH-BCDEO 11.30.98 12.19.98
Improvement of Kennon Road Baguio City
DPWH-BCDEO 02.28.99 03.22.99
Improvement of Leonard Wood Road Baguio
City
DPWH-BCDEO 04.14.99 05.25.99
27
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Improvement of Kennon Road Baguio
City
DPWH-BCDEO 05.13.99 06.12.99
Improvement Along Baguio-Bontoc Road Baguio City
DPWH-CAR 06.28.98 09.02.99
Improvement Along Pico-Lamtang Road Baguio
City
DPWH-CAR 03.26.99 09.23.99
Improvement of Government Center Cut-Off Road Baguio City
DPWH-BCDEO 02.26.99 10.19.99
Finishing of Klondykes Section, Kennon Road Tuba, Benguet
DPWH-BED 08.28.99 04.07.00
Improvement Along Twin River Dalupirip Road, Km.
265+184 - Km. 267+000(v.s.)
Itogon,
Benguet
DPWH-BED 01.04.00 03.17.00
Improvement Along Twin River Dalupirip Road, Km. 265+484 - Km. 269+000(v.s.)
Itogon, Benguet
DPWH-BED 02.14.00 04.12.00
Improvement Along Twin River Dalupirip Road, Km.
267+500 - Km. 269+500(v.s.)
Itogon,
Benguet
DPWH-BED 02.14.00 04.14.00
Improvement Along Kennon Road Baguio
City
DPWH-BCDEO 06.20.00 10.16.00
Improvement Along Kennon Road Baguio City
DPWH-BCDEO 08.20.00 10.16.00
Improvement Along Carantes Road Itogon,
Benguet
DPWH-BED 04.10.00 11.05.00
Improvement of Session Road 1 & 2 Baguio City
DPWH-BCDEO 09.12.00 11.17.00
Road Concreting at South Drive Baguio
City
BCEO 11.21.00 01.15.01
Improvement Along Twin River Dalupirip Road, Km.
265+040 - Km. 275+000(v.s.)
Itogon,
Benguet
DPWH-BCDEO 02.14.00 03.19.01
Improvement Along Labilab Brgy. Road Itogon, Benguet
DPWH-CAR 01.14.01 05.31.01
28
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Conc/Improvement of Session Road, Baguio
City
DPWH-BCDEO 08.21.01 09.11.01
Conc/Improvement Along Gibraltar Road, Baguio City
DPWH-BCDEO 09.05.01 09.21.01
Improvement of Kennon Road (Camp 6) Baguio
City
DPWH-BCDEO 07.12.01 10.29.01
Improvement of Kennon Road (Camp 7) Baguio City
DPWH-BCDEO 07.26.01 11.19.01
Improvement Along Lake Drive-Abad Santos Drive, Burnham Park
Baguio City
DPWH-BCDEO 12.19.01 04.15.02
Restoration Along Kennon Road, Km. 223+150 - Km.
223+170
Tuba,
Benguet
DPWH-BCDEO 12.15.01 01.22.02
Restoration Along Kennon Road, Km. 230+944 - Km. 231+055
Tuba, Benguet
DPWH-BCDEO 12.15.01 01.23.02
Restoration Along Kennon Road, Km. 235+800 - Km.
235+847
Tuba,
Benguet
DPWH-BCDEO 12.15.01 01.22.02
Restoration Along Kennon Road, Km. 231+060 - Km.
231+090
Tuba,
Benguet
DPWH-BCDEO 12.15.01 01.23.02
Road Concreting and Improvement of Drainage Projects Baguio
City
City Government
of Baguio
02.11.02 04.18.02
a. Quezon Hill Cut-off, Quezon Hill Proper Brgy.
b. Queen of Angels, Lourdes proper Brgy.
c. Bado Dangwa, Cresencia Village Brgy.
d. Baltazar Street, Gibraltar Brgy.
e. Ruiz Castro Street, Gibraltar Brgy.
f. Recto Street, Navy Base Brgy.
g. Teachers Camp Barangay
h. Felipe Street, Lualhati Barangay
29
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Improvement of Drainage & Road Conc. Along Baguio
City
DPWH-BCDEO 06.10.02 07.16.02
a. Chanum Street
b. Magsaysay Avenue-Kabayanihan Barangay
c. Magsaysay Avenue-Upper Magsaysay Brgy.
Improvement Along Baguio-Asin Road, Km. 262+262 -
Km. 264+074
Tuba,
Benguet
DPWH-CAR 04.29.02 11.25.02
Construction of Teachers Camp Road Baguio City
DPWH-BCDEO 05.28.03 08.18.03
Rehab. of Baguio-Bontoc-Banaue
Road (Halsema Highway) Package:
Section II Km. 295+312 – Km. 340+967
Halsema,
Benguet
DAEWOO
Engineering &
Construction Co. LTd.
10.01.02 02.01.05
Rehab./Improvement along City Limit-Asin Proper
(Phase I)
Tuba,
Benguet
Province of
Benguet
03.10.03 11.20.03
Rehab./Improvement along City Limit-Asin Proper (Phase II)
Tuba, Benguet
Province of Benguet
03.10.03 11.20.03
Rehab./Improvement along City Limit-Asin Proper
(Phase III)
Tuba,
Benguet
Province of
Benguet
03.10.03 11.20.03
Improvement of Marcos Highway to Sta. Lucia Road, Km.
250+621 - Km. 252+037
Baguio
City
DPWH-BCDEO 03.28.03 11.30.03
Improvement of Drainage System, Burnham Park to Magsaysay Avenue
Baguio City
DPWH-BCDEO 12.15.03 05.26.04
Restoration and Dredging Works of Camp 1 Bridge Along
Kennon Road
Tuba,
Benguet
DPWH-CAR 01.05.04 10.30.04
Opening/Improvement of Buyagan-Gayasi-Kesbeng Road (Phase I & II)
La Trinidad,
Benguet
DPWH-CAR 04.06.04 04.15.05
Completion of Drainage in Burnham Park Baguio
City
DPWH-BCDEO 06.21.04 10.07.04
30
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Completion of Drainage System fr. Magsaysay Ave. to
Brgy. Sto. Nino Slaughter Cpd.
Baguio
City
DPWH-BCDEO 04.25.05 10.03.05
Improvement of Camp 7 Loakan Kadaclan Junction Package 1 Km. 245+162 - Km. 246+800
Baguio City
DPWH-CAR 06.15.05 10.10.05
Improvement /Rehabilitation along Bokawkan Road Baguio
City
DPWH-BCDEO 11.20.05 12.20.05
Rehabilitation of Bokawkan Road Baguio City
DPWH-BCDEO 01.16.06 01.24.06
Improvement/Rehabilitation of Kennon Road, Km.241+308-km.241+530
Baguio City
DPWH-BCDEO 05.08.06 06.23.06
Restoration of Eroded Slope Protection at Lopez Jaena Baguio
City
Municipal Gov’t.
of Baguio
10.06.06 12.15.06
MRF & Composting Site Development at the MRF site Induyan Alno
La Trinidad,
Benguet
Municipality of La Trinidad
10.11.06 12.30.06
MRF AND Composting Site Development at Induyan Alno La Trinidad,
Benguet
Municipality of Trinidad
11.23.06 01.30.08
Restoration of Collapsed Retaining Wall and Drainage
System Along Baguio-Bauang Road
Baguio
City
DPWH-BCDEO 12.16.06 02.23.07
Improvement of Pico Lamtang Road, km.254+790.50-km.254+840.50
La Trinidad,
Benguet
DPWH-BED 12.16.06 02.23.07
Improvement/Upgrading along Baguio-Bauang Road, Km. 304+315 - Km. 304+918 (v.s.)
Baguio City
DPWH-BCDEO 12.16.06 02.24.07
Improvement of Betag-Swamp-Puguis Trading Post FTMR La
Trinidad
Benguet
DPWH-BED 12.27.06 02.09. 07
Improvement of Happy Hollow to Country Club km.250+240-km.251+280
Baguio City
DPWH-BCDEO 01.15.07 08.30.07
31
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Rehab./Restoration of Retaining Wall at Trinidad Road
Magsaysay Ave., and Road Cut at P. Burgos Street
Baguio
City
DPWH-BCDEO 01.18.07 02.21.07
Rehabilitation of Magsaysay and Burgos Road Baguio City
DPWH-BCDEO 01.18.07 03.19.07
Improvement of Tunnel#2 km.262.647+km.262.7028-
km.264.5025+km.264.7201 at Asin Nangalisan Road
Tuba
Benguet
Provincial
Government of Benguet
02.05.07 04.10.07
Improvement Rehabilitation of Loakan Airport Road
Military Circle up to NFA km.249+674-km.250+674
Baguio
City
DPWH-BCDEO 02.28.07 05.23.07
Improvement/Concreting of Bontoc-Tinglayan Bdry.
Road, and Improvement of Baguio-Bontoc-Banaue Road
Mt.
Province
DPWH-CAR 03.21.07 04.21.08
a. (Package 1) Km.394+870-km.396+500
b. (Package 2) km.396+500-km.398+400
c. (Package 3) km.400+620-km.401+950
d. (Package 4) km.401+950-km.403+750
e. (Package 5) km.403+750-km.405+200
f. Km.363+100-km.367+243
g. Km.367+243-km.369+413
h. Km.369+413-km.370+666
i. Km.380+774-km.383+450
Rehabilitation of Kennon Road km.242+966-km.243+000 and km.245+268-km.245+563
Baguio City
DPWH-BCDEO 03.26.07 06.25.07
32
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Improvement of Pico Lamtang Road, km.254+830.50-
km.960.50
La
Trinidad, Benguet
DPWH-BED 05.10.07 08.21.07
Restoration and Dredging along Camp 1 Bridge, Bued
River Kennon Road
Tuba,
Benguet
Province of
Benguet
06.05.07 07.31.07
Const. of Baguio Flyover and Approaches (Phase I) at BGH Rotunda Marcos Highway-Gov. Pack-Kisad Road to
Kennon Road Junction
Baguio City
DPWH-CAR 09.10.07 12.12.07
Const. of Baguio Flyover and Approaches (Phase III) at
BGH Rotunda Marcos Highway-Gov. Pack-Kisad Road to Kennon Road Junction
Baguio
City
DPWH-CAR 09.10.07 12.17.07
Const. of Baguio Flyover and Approaches (Phase 1V) at
BGH Rotunda Marcos Highway-Gov. Pack-Kisad Road to Kennon Road Junction
Baguio
City
DPWH-CAR 09.10.07 12.17.07
Const. of Baguio Flyover and Approaches (Phase V) at
BGH Rotunda Marcos Highway-Gov. Pack-Kisad Road to Kennon Road Junction
Baguio
City
DPWH-CAR 09.10.07 01.03.08
Repair/Rehabilitation of Flood Control along Kennon Road-Agat, km.216+654-km.217+689 (vs)
Tuba Benguet
DPWH-CAR 01.21.08 02.18.08
Dredging of Riverbed at Camp 1 Bridge Tuba
Benguet
DPWH-CAR 01.21.08 02.21.08
Rehabilitation/Concreting of Cervantes-Sabangan Road, km.398+446-km.405+543.59
Mountain Province
DPWH-CAR 03.04.08 09.22.09
Rehabilitation/Improvement of Outlook Drive,
km.254+316-km.255+197 (v.s.)
Baguio
City
DPWH-BCDEO 06.27.08 08.19.08
Rehabilitation/Improvement of Ferguson Road,
km.306+077-km.306+367
Baguio
City
DPWH-BCDEO 06.27.08 08.19.08
Rehabilitation/Improvement of Kennon Road, km.244+183-km.247+202 w/ exception
Baguio City
DPWH-BCDEO 06.27.08 08.19.08
Rehabilitation/Improvement of Balatoc Road,
km.248+008-km.248+896.5 (v.s.)
Baguio
City
DPWH-BCDEO 06.27.08 08.19.08
33
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Rehabilitation/Improvement of Loakan Road,
km.245+580-km.246+113
Baguio
City
DPWH-BCDEO 06.27.08 08.19.08
Rehabilitation along City Limit-Santo Tomas Road, km.255+000-km.264+268 (various section)
Tuba, Benguet
DPWH-CAR 09.15.08 12.11.08
Rehabilitation along Itogon-Dalupirip-San Manuel
Boundary Road, km.267+000-km.278+587 (vs)
Itogon,
Benguet
DPWH-CAR 09.15.08 02.20.09
Improvement/Concreting of Loakan Road, Phase 2 Baguio City
DPWH-BCDEO 12.02.08 01.13.09
Const. of Baguio Flyover and Approaches at BGH Rotunda Marcos Highway-Gov. Pack-Kisad Road to
Kennon Road Junction
Baguio City
DPWH-CAR 12.24.08 02.13.09
Improvement of Road Leading to Assumption Convent Crystal Cave, Bakakeng Central
Baguio City
DPWH-BCDEO 01.14.09 04.06.09
Rehabilitation, Reconstruction of Damaged National
Roads Generated from Pavement System/Highway Development and Management (HDM-4) along
d.) Kennon Road
e.) Loakan Road f.) Outlook Drive
Baguio
City
DPWH-BCDEO 03.26.09 07.23.09
One Cluster Concreting & Improvement Project along
Benguet 1 a.) Concreting along Itogon-Dalupirip Road
b.) Improvement along Baguio City Limit Sto. Tomas Road
Itogon Benguet
Tuba Benguet
DPWH-BFDEO 04.13.09 06.26.09
Rehabilitation/Construction of Gurel-Bokod-Kabayan-
Buguias-Abatan Road, km.300+138-km.364+500
Benguet DPWH-CAR 04.15.09
04.28.10
Repair/Rehab. along Palispis (Marcos) Highway,
km.267+380-km.267+410 (Phase II)
Tuba,
Benguet
DPWH-BFDEO 01.21.10 02.28.10
34
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Repair/Rehab. of Road Slip & Slope Protection along
Palispis (Marcos) Highway km.268+400-km.268+960 (Phase 1)
Tuba,
Benguet
DPWH-BFDEO 02.15.10 04.15.10
Improvement of Happy Hollow to Happy Hollow (CPEL 4)
Happy Hollow Barangay
Baguio
City
DPWH-BCDEO 06.06.06 08.13.10
Restoration of Various National Roads in Baguio City: a. Road cut/Slope Protection & Removal of Landslide,
Marcos Highway
i. km.282+550-km.282+575 ii. km.282+600-km.282+630
b. Road cut/Slope Protection & Removal of Landslide, Bokawkan Road, km.306+187-km.306+307
c. Road cut & Road Slip, Kennon Road, km.245+000- km.245+10
d. Road cut & Road Slip, Baguio-Bauang Road (Intermittent Sections)
Baguio City
DPWH-BCDEO 03.26.10 08.16.10
Road upgrading along Itogon-Dalupirip-San Manuel Bdry.
Road
Itogon,
Benguet
DPWH-BFDEO 04.04.10 08.18.10
Regravelling along Gurel-Bokod-Kabayan-Buguias-Road,
km.322+500-km.325+700 (v.s.)
Kabayan,
Benguet
DPWH-CAR 06.29.10 07.20.10
35
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
1a) Construction of Baguio Circumferential Road
1b) Rehabilitation, Reconstruction of Damaged National Roads Generated from Pavement Management
System/Highway Development and Management (HDM4):
a. Kennon Road (Including Protection Works) b. Magsaysay Avenue (Trinidad Road) East Service
Road.
c. Marcos Highway d. Outlook Drive
Baguio
City
DPWH-BCDEO 03.25.10 12.20.10
Rehabilitation/Repair of Roadside/Road within and
surrounding the Burnham Area, Session Road, Magsaysay Road, Malcolm Square, Igorot Garden,
Naguilian-Bokawkan Road and Marcos Highway - BGH Junction
Baguio
City
DPWH-BCDEO 01.17.11 02.10.11
Site Development of Goldrich Homes Subdivision Phase
1, Located at Km.9, Bayacsan, Taloy Sur
Tuba,
Benguet
Godrich Realty
and
Development Corporation
08.15.09 02.23.11
Stabilization of Irisan Dumpsite, Phase 1, at Irisan
Barangay Baguio City
Baguio
City
City Government
of Baguio
01.12.11 04.08.11
Stabilization of Irisan Dumpsite, Phase II, at Irisan Barangay, Baguio City
Baguio City
City Government of Baguio
04.10.11 09.28.11
Rehab./Reconstruction/Upgrading of Damaged Paved
National Roads, Bokawkan Road K0+000-K1+150
Baguio
City
DPWH-BCDEO 05.24.11 08.29.11
Contract Package:
A.) Rehabilitation/Improvement of Loakan Road B.) Rehab./Reconstruction/Upgrading of Damaged
Paved National Roads, Loakan Road, K0247+835- K0247+2035
Baguio
City
DPWH-BCDEO 05.24.11 11.294.11
36
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Rehab./Improvement of Marcos Highway K0281+437-
K0282+815 w/ exception
Baguio
City
DPWH-BCDEO 01.19.12 02.06.12
Rehab./Reconstruction/Upgrading of Damaged Paved National Roads, A. Bonifacio Road Chainage
0000+Chainage 0465
Baguio City
DPWH-BCDEO 02.16.12 04.24.12
Rehab./Reconstruction/Upgrading of Damaged Paved National Roads, Kisad Road K0249+(-759)-K0249+299
Baguio City
DPWH-BCDEO 03.23.12 04.24.12
Rehab./Reconstruction/Upgrading of Damaged Paved
National Roads, Governor Pack Road K0249+001) -
K0249+261 v.s.
Baguio
City
DPWH-BCDEO 01.27.12 06.23.12
Rehab./Reconstruction/Upgrading of Damaged Paved National Roads, Manuel Roxas Road K0253+(-007)-
K0254+481
Baguio City
DPWH-BCDEO 03.26.12 07.08.12
Completion/Continuation of Perimeter Fence at Burnham Park
Baguio City
DPWH-BCDEO 09.04.12 10.06.12
Opening/Improvement of Baguio Circumferential Road,
K0247+766 – K0248+223.61 w/ exception Section 3
Bakakeng to Balacbac Barangay, Baguio City
Baguio
City
DPWH-CAR 08.17.12 08.17.12
Concreting of M. Roxas – Leonard Wood Road Baguio
City
DPWH-BCDEO 11.12.12 12.13.12
Dredging of Burnham Lake, Burnham Park Baguio City
DPWH-BCDEO 01.10.13 02.12.13
Restoration of Collapsed Retaining Wall, Irisan Dumpsite Baguio
City
DPWH-CAR 01.08.13 06.06.13
Rehabilitation/Reconstruction/Upgrading of Damaged
Paved National Roads Quezon Hill Road #1 KO306+002-KO306+601-KO306+601-KO307+209-KO307+209+291-
KO307+619
Baguio
City
DPWH-BCDEO 02.20.13 06.20.13
37
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Contract Package 1: Preventive Maintenance (Intermittent Sections) along:
a. Leonard Wood Road, KO250+175-KO251+415 b. Session Road #01, Chainage 0000-Chainage 0590
(SO0413LZ), Chainage 0000-Chainage 0590 (SO04715LZ)
c. A. Bonifacio Road, Chainage 0462-Chainage 0600-Chainage 0600+Chaiange 1260
d. Sto. Tomas-Mt. Cabuyo Road, KO252+(-363)-
KO252+(-003), KO252+291-KO252+641
Baguio City
DPWH-BCDEO 02.18.13 05.10.13
Contract Package 3: Preventive Maintenance (Intermittent Sections) along:
a. Abanao Extension, Chainage 0000-Chainage 0278 b. Abanao Road, Chainage 0000-Chainage 0270,
Chainage 0080-Chainage 0160 c. Chanum Street, Chainage 0000-Chainage 0080
d. Kayang Street, Chainage 0000-Chainage 0300
e. Goc. Pack Road, Chainage 0000-Chainage 0200
Baguio City
DPWH-BCDEO 03.01.13 05.13.13
Contract Package 5: Preventive Maintenance (Intermittent Sections) along:
a. Harrison Road 1, Chainage 0503-Chainage 0807 b. Harrison Road 1, Chainage 0414-Chainage 0807
c. Lake Drive 2, Chainage 0000-Chainage 0335 – Chainage 0000-Chainage 0068
d. Magsaysay Ave., (Trinidad Road) Chainage 0000-Chainage 0290 – Chainage 0000-Chaiange 0080
e. Chanum Street, Chainage 0000-Chainage 0080
f. Abanao Road, Chainage 0160-Chaiange 0350
Baguio City
DPWH-BCDEO 02.18.13 05.13.13
38
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Replacement/Rehabilitation/Strengthening of
Permanent Bridges along National Roads Ferguson Bridge 2 along Ferguson Road and
Rehabilitation/Reconstruction/Concreting of its Approaches
Baguio
City
DPWH-BCDEO 03.01.13 08.19.13
Opening/Improvement of Baguio Circumferential
Road (Western Link) Section 1: Kennon Road Junction to Montecillo,
KO245+440-KO245+957
Section 2: Ciudad Grande to saint Louis University, KO245+1748-KO245+1910
Section 3: Bakakeng to Balacbac, KO247+766 -KO248+223.61
Section 4: Balacbac to Marcos Highway, 248+1875 -248+2347
Section 5: Happy Hollow, 246+1690 - 246+3860 (Eastern Link)
Baguio
City
DPWH-CAR 02.21.12 04.29.13
Contract Package 4: 1. Preventive Maintenance: Loakan Road
KO245+(1227)-KO245+1665 2. Preventive Maintenance: Marcos Highway:
Chainage 0000 - Chainage 0140 3. Preventive Maintenance: Marcos Highway:
KO283+334-KO283+454 4. Rehabilitation/Reconstruction/Upgrading of
Damaged Paved National Road: Loakan Road a.)
Reconstruction (Reblocking) K245+(-158) –K0245+466 with exception b.)
Improvement/Concreting of Shoulder: KO245+300-KO245+720 (RS); KO245+1043 -
KO245+1344 (LS) and KO245+1625-KO245+1665 (RS)
Baguio City
DPWH-BCDEO 05.24.13 08.16.13
39
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Restoration of Collapsed Retaining Wall,
Irisan Dumpsite
Baguio
City
DPWH-CAR 11.11.13 12.13.13
Restoration of Collapsed Retaining Wall, Irisan Dumpsite
Baguio City
DPWH-CAR 12.01.13 12.13.13
Widening of Baguio Circumferential Road, Baguio City Baguio
City
DPWH-BCDEO 12.12.13
04.10.14
Declared/Strategic Tourist Destination (DSTD) Upgrading (Gravel to Concrete) Camp John Hay Gate
3 to Country Club and Happy Hollow to Loakan
Baguio City
DPWH-BCDEO 01.21.13
01.20.14
Contract Package 10: Asset Preservation (Preventive
Maintenance) – HDM – 4 along: a. Kisad Road, K0249+(-038) – K0249+222
b. Leonard Wood Road, K0252+600 – K0252+980 c. PMA Road, Chainage 0000 – Chainage 0110
d. Gov’t. Center Road (Baguio City), Chainage 0000 - Chainage 0102
e. Gov’t. Center Road (Baguio City),
Chainage 0000 - Chainage 0141 f. Gov’t. Center Road (Baguio City),
Chainage 0141 - Chainage 0185
Baguio
City
DPWH-BCDEO 01.30.14
03.31.14
Asset Preservation of National Roads – Preventive Maintenance based on Pavement Management
System/Highway Development and Management – 4 (HDM-4) (Intermittent Section) along Manuel Roxas
Road, K0253+(-622) – K0253+(-002)
Baguio City
DPWH-BCDEO 06.11.14
08.22.14
Restoration of Collapsed Protection along Sto. Tomas
Road, K0252+400 – K0253+000 Intermittent Section
Baguio
City
DPWH-BCDEO 06.23.14
08.22.14
40
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Rehabilitation/Reconstruction/Upgrading of Damaged
Paved National Roads including drainage based on Pavement Management System/Highway
Development and Management – 4 (HDM-4) (Intermittent Sections) Asin Road, K0305+(-534)-
K0310+422 w/ exception
Baguio
City
DPWH-BCDEO 06.24.14
02.20.15
Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Roads including drainage based on
Pavement Management System/Highway
Development and Management – 4 (HDM-4) (Intermittent Sections) Quirino Highway (Baguio-
Bauang Road, K0299+086 - K0303+776 w/ exception
Baguio City
DPWH-BCDEO 07.03.14
02.22.15
Rehabilitation/Reconstruction/Upgrading of Damaged
Paved National Roads including drainage based on Pavement Management System/Highway
Development and Management – 4 (HDM-4)
(Intermittent Sections) Rimando-Ambiong Road, Chainage 0000 – Chainage 2402
Baguio
City
DPWH-BCDEO 06.24.14
02.14.15
Rehabilitation/Reconstruction/Upgrading of Damaged
Paved National Roads including drainage based on Pavement Management System/Highway
Development and Management – 4 (HDM-4) (Intermittent Sections) Kennon Road, K0244+360 -
K0247+300 w/ exception
Baguio
City
DPWH-BCDEO 07.03.14
03.05.15
Construction/Maintenance of Flood Control Mitigation
Structures and Drainage Systems, 4. Construction/Rehabilitation of Flood Control
Mitigation Facilities along Balili River, Baguio City Lone District
Baguio
City
DPWH-BCDEO 01.15.16
03.05.16
41
GOLDRICH CONSTRUCTION AND TRADING
Company Profile
Road Concreting Projects
Marcos Highway, Central Poblacion, Tuba, Benguet
Tel. Nos. 442-66-67, 442-21-45, 445-72-37
Telefax Nos. 074-442-21-45 loc. 124
Project Description Location Owner Date
Started
Date
Finished
Rehabilitation/Reconstruction/Upgrading of Damaged
Paved National Roads including drainage based on Pavement Management System/Highway
Development and Management – 4 (HDM-4) (Intermittent Sections) Asin Road, K0305+(-534)-
K0310+422 w/ exception
Baguio
City
DPWH-BCDEO 06.11.14
02.20.15
Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Roads including drainage based on
Pavement Management System/Highway
Development and Management – 4 (HDM-4) (Intermittent Sections) Quirino Highway (Baguio-
Bauang Road, K0299+086 - K0303+776 w/ exception
Baguio City
DPWH-BCDEO 06.11.14
02.22.15
Rehabilitation/Reconstruction/Upgrading of Damaged
Paved National Roads including drainage based on Pavement Management System/Highway
Development and Management – 4 (HDM-4)
(Intermittent Sections) Rimando-Ambiong Road, Chainage 0000 – Chainage 2402
Baguio
City
DPWH-BCDEO 06.11.14
02.14.15
Rehabilitation/Reconstruction/Upgrading of Damaged
Paved National Roads including drainage based on Pavement Management System/Highway
Development and Management – 4 (HDM-4) (Intermittent Sections) Kennon Road, K0244+360 -
K0247+300 w/ exception
Baguio
City
DPWH-BCDEO 06.11.14