friday, december 11 , 2015 to: unitron power systems

49
66 Long Wharf - Boston, MA 02110 (T) 617.723.1700 - (F) 617.742.0947 www.aecom.com Page 1 of 1 Terminal IE Renovation and Enhancements Friday, December 11 th , 2015 To: Unitron Power Systems Massport AECOM From: AECOM Subject: L1346-C2 Terminal E Renovation and Enhancement PBB's, RFP # 5276 Question: Per Section 16800, 400 HZ Ground Power Unit Specification, Part 2, line 2.19, will other manufacturers be approved to bid on the 180-kVA frequency converters? Answer: Alternates will be considered for all Ground Support Products, including 400hz, PCA, and Potable Water Cabinets. Contractors shall follow the specification criteria for the basis of design guidelines for tendering purposes and during the submittal process all al- ternates with accompanied experience references, financial history, after- market support references, technical documentation, electrical and me- chanical code compliances along with their manufacturing processes will be evaluated accordingly.

Upload: others

Post on 04-May-2022

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Friday, December 11 , 2015 To: Unitron Power Systems

6 6 L o n g W h a r f - B o s t o n , M A 0 2 1 1 0 ( T ) 6 1 7 . 7 2 3 . 1 7 0 0 - ( F ) 6 1 7 . 7 4 2 . 0 9 4 7

w w w . a e c o m . c o m

Page 1 of 1 Terminal IE Renovation and Enhancements

Friday, December 11th, 2015 To: Unitron Power Systems Massport AECOM From: AECOM

Subject: L1346-C2 Terminal E Renovation and Enhancement PBB's, RFP # 5276

Question: Per Section 16800, 400 HZ Ground Power Unit Specification, Part 2, line2.19, will other manufacturers be approved to bid on the 180-kVAfrequency converters?

Answer: Alternates will be considered for all Ground Support Products,including 400hz, PCA, and Potable Water Cabinets. Contractorsshall follow the specification criteria for the basis of designguidelines for tendering purposes and during the submittal process all al-ternates with accompanied experience references, financial history, after-market support references, technical documentation, electrical and me-chanical code compliances along with theirmanufacturing processes will be evaluated accordingly.

Page 2: Friday, December 11 , 2015 To: Unitron Power Systems

6 6 L o n g W h a r f - B o s t o n , M A 0 2 1 1 0 ( T ) 6 1 7 . 7 2 3 . 1 7 0 0 - ( F ) 6 1 7 . 7 4 2 . 0 9 4 7

w w w . a e c o m . c o m

Page 1 of 2 Terminal IE Renovation and Enhancements

Friday, December 11th, 2015 To: JBT Corporation Massport AECOM From: AECOM Subject: Additional requests related to MASSPORT RQ# 5276 L1346-C2

Terminal E Renovation and Enhancements

1. In the Customer specification 13041, item 2.3 A., page 4, states the existing serialnumber for both the “Storage Facility – E8A and E8B” bridge as 38777. Should theE8A bridge serial number be identified as “38776” (an A3 64/131) and the E8Bbridge serial number be identified as “38777” (an A3 68/141)? Please clarify.

Per Massport’s existing equipment inventory table, Gate E8A is S/N 38776 Jet-way A3-64/131 and Gate E8B is S/N 38777 Jetway A3-68/141.

2. In the Customer specification 13041, item 2.13 A., page 16, states A ramp servicedoor, landing, and service stair shall be provided at the aircraft end of the bridge orwalkway for apron access by authorized personnel. These shall be positioned perthe engineers designated location. (Pre-Bid discussion meeting). The Customerdrawings, identified as PL.801 PL.802, depict the PBB1 (inboard) position with theservice stair/landing coming from the fixed walkway/corridor section at the terminalend and the PBB2 (outboard) position does not show a service stair on the bridge atall. Do you want us to quote to have a right-side service door and landing along witha maintenance access ladder, but no stair, on the “new” PBB2 (outboard) bridgepositons? Do you want us to quote to place a service door, landing, and stairassembly in the “new” walkway/corridors? Please clarify.

Per Drawings PL.801 and PL.802, no service door, landing, or maintenance ac-cess ladder for upper-deck PBB2. A service door, landing, and baggage con-veyance shall be mounted to the new fixed walkway of INS-level PBB1.

3. In reviewing the Customer drawing, identified as PL.801, the PBB # 2 position bridgewill only be used to service the A380-U1 (upper-deck) door position. Pleaseconfirm that this is correct and that the PBB # 2 bridge will not be used to serviceany other aircraft.

We are only depicting PBB2 docked to the A380 because the slope is not withinADA slope compliance for unassisted access for all other widebody aircraft.Massport or the tenant may want to use assisted access for the greater than al-lowable slope conditions; therefore, the bidder shouldassume the PBB will be used for other widebody aircraft. We as thedesigner cannot release a PBB design document or recommend a scenario thatdoes not comply with the standard, and relies on an operationalrestriction.

Page 3: Friday, December 11 , 2015 To: Unitron Power Systems

6 6 L o n g W h a r f - B o s t o n , M A 0 2 1 1 0 ( T ) 6 1 7 . 7 2 3 . 1 7 0 0 - ( F ) 6 1 7 . 7 4 2 . 0 9 4 7

w w w . a e c o m . c o m

Page 2 of 2 Terminal IE Renovation and Enhancements

EXTENSION OF QUOTES DUE DATE:

4. In reviewing the Customer drawing, identified as PL.801, the “AIRSIDEEQUIPMENT SCHEDULE” has a column identified as “REQUIRED PBBOPERATIONAL RANGE”. Please confirm how this range is defined; is it measuredfrom rotunda-pivot to cab-pivot or is it measured from rotunda-pivot to end of the cabbumper? Based upon the size of the existing bridges for the PBB # 1 bridge, itwould appear that the range is measured from the rotunda-pivot to the cab-pivot. Please note the following:

Measured from rotunda-pivit to cab-pivit.

a. The Gate E10 and E12 PBB # 2 bridge are listed with a “REQUIRED PBBOPERATIONAL RANGE” of 58’-131’. This would require a travel range of 73feet, JBT-Jetway does not have a 3-tunnel bridge that can satisfy this rangeof travel and meet both the retract and extend dimension regardless of how itis measured.

Bidder shall recommend alternate/comparable 3-tunnel PBB model for ap-proval, which accommodates the design aircraft fleet mix.

b. The Gate E11 PBB # 2 bridge is listed with a “REQUIRED PBBOPERATIONAL RANGE” of 45’-92’. This would require a travel range of 47feet, JBT-Jetway does not have a 3-tunnel bridge that can satisfy this rangeof travel and meet both the retract and extend dimension regardless of how itis measured.

Bidder shall recommend alternate/comparable 3-tunnel PBB model for ap-proval, which accommodates the design aircraft fleet mix.

5. Please consider providing AutoCAD drawing file of the project gates, etc. andallowing the bridge manufacturers to define and quote the bridge models that wouldwork with your aircraft layout as represented on the Customer drawing PL.801. CAD

file attached.

Currently, the answers to questions and requests are due to come out by Addendum on14 Dec 2015. We’ll need to send our quote out very shortly after (16 Dec) in order tohave it arrive on time. In light of the important technical and commercial questions thatwe’re hoping to have answered in that Addendum, we respectfully request an extensionto the bids-due-date to perhaps 23 Dec 2015 so that we may have enough time toprocess that new information.

Massport has decided to extend the due-date to December 23, 2015, see Adden-dum 1.

Page 4: Friday, December 11 , 2015 To: Unitron Power Systems

JBT Questions  Massachusetts Port Authority  

RFP #5276  

 

Drawing PL.802 1. Can the gate sign be mounted to our standard right side mounting location on 

the cab in lieu of where shown on the drawing? Response: Quote as specified. Design intent is to ensure gate sign doesn’t conflict with ancillary gate equipment or adjacent PBB operations.  

 2. The drawing shows the PCA as mounted on the rotunda. With the required 

120ton unit size and weight, we suggest either mounting the PCA units on a stand for the existing units and under the PBB C‐tunnel on the new units. Please accept.  

Response: Quote as specified.  3. The drawing depicts one (1) TAD Tube and a single outlet PCA unit. A 120Ton 

unit will require 2 outlets which would require 2ea TAD Tubes and 2ea hose management systems per PBB.  Please clarify the mounting configuration for dual outlet PCA, TAD tubes, and hose management systems. 

Response: PCA unit shall be manufactured with “one” outlet. One TAD Tube shall be provided. Two Hose Management Systems shall be provided for each 120 ton unit.  

4. Please clarify if both a bag slide and bag conveyance system are required on the service stair of the refurbished PBB’s.   

Response: One bag “slide” and one “wheel chair lift” shall be provided.    Division IIB 1. Reference Sub Clause 1.2: This states the project consists of the design and 

documentation to build a temporary jet bridge at Terminal E Gate 7B. This gate currently consists of the PBB that is to be refurbished and relocated to new gate E10. Please explain “build a temporary jet bridge at Terminal E Gate 7B”.  

Page 5: Friday, December 11 , 2015 To: Unitron Power Systems

Response: Answered in Addendum 1.  2. Reference Sub Clause 68.2 Field Office: This section describes the requirement 

to furnish a field office with a desk, chairs, meeting table, file cabinet, locker, fax machine, computer, printer, shelving, telephone, etc. Please remove this section as this won’t be required for a project of this size and duration.  

Response: This requirement applies to the Construction Manager only.  Section 13041 Aircraft Passenger Loading Bridges  1. Reference Sub Clause 2.1.G Wind Load: The wind loads are listed at 25 psf. The 

ASCE manual lists higher load requirements for the Boston area. Please clarify.  Response: Industry standard PBB loading requirements per NFPA 415 are sufficient.  

2. Reference Sub Clause 2.1.K Lighting: This section describes the fixed walkway to include fluorescent light fixtures containing 2 lamps spaced 8ft on center. Our standard interior lighting design consists of 2’ X 4’ light fixtures containing 3 lamps spaced on 12ft centers running parallel to the bridge center line. Please accept our standard lighting design. 

Response: Accepted.  3. Reference Sub Clause 2.4.H Walkway loads: Please provide walkway floor 

loads as per Internal Building Massport codes. Response: Industry standard PBB loading requirements per NFPA 415 are sufficient. 

 4. Reference Sub Clause 2.8.C.4.b Tire Size: This section calls for 16” diameter 

tires. Our standard is 40” Please accept our standard tire configuration. Response: Contractor shall provide suitable size industry standard “solid tires” to accept all operational parameters of PBB and design aircraft fleet mix operations. 

 5. Reference Sub Clause 2.9.F Swing door width 44”: Our standard swing door 

clear width is 43” Please accept.   Response: Accepted.  

Page 6: Friday, December 11 , 2015 To: Unitron Power Systems

 6. Reference Sub Clause 2.13.B.1 Service door width 2’ 8”: Our standard 3 tunnel 

service door width is 2’ 6”. Please accept.  Response: Accepted. 

 7. Reference Sub Clause 2.14.A: The specification states to supply 12ea smart 

sensors to gather and collect data stream on a “real time” basis of input and trending information. Please provide the supplier of these sensors systems and clarify who is responsible for the installation of the sensors.   

Response: See attached Smart Sensor datasheet.  8. Reference Sub Clause 2.14.I.7 Gate Sign: The provided drawing shows an LED 

light in the gate sign and the specification shows a fluorescent light. Please clarify. 

Response: Provide LED lighting for gate signs.   9. Reference Sub Clause 2.15.A.5 Ribbed Rubber: This section calls for ¼” ribbed 

rubber to be installed in the bubble/cab area and on the transition ramps. Our standard ribbed rubber is 3/16” thick. Please accept our standard ribbed rubber. 

Response: Accepted.  10. Reference Sub Clause 2.16.3: This section calls for Bridge Cool ducted from the 

PCA unit. We propose to provide a 5ton Roof Top A/C Unit in lieu of the specified pre‐cool. We believe this would result in some cost savings to the Owner as well as simplify the dual hose management system/duct splitter issues mentioned above.   

Response: Quote as specified.  

11. Reference Sub Clause 2.18.C Gate Signage: Please clarify if the 9ea existing gate signs are to be replaced, or are just the lenses to be replaced? 

Response: All gate signs shall be replaced with new complete gate sign assembly, and all gate signs shall be consistent in materials and finishes on all gates.   

 

Page 7: Friday, December 11 , 2015 To: Unitron Power Systems

 Section 13983 Preconditioned Air 1. Reference Sub Clause 1.1.B Mounting: See comments from Drawing PL.802. 2. Reference Sub Clause 2.1.B.1 Acceptable Manufacturers: Please accept JBT as 

an approved PCA Manufacturer.  Response: All alternates and substitutions will be considered for all Ground Support Equipment, including Pre‐Conditioned Air Units and 400hz units. Contractors shall follow the specification criteria for the basis of design guidelines for tendering purposes. During the submittal process all alternates and substitutions will be evaluated with the following documentation. Company profile, history and references, technical documentation, electrical and mechanical compliance codes, manufacturing process, quality control manual, after market support guidelines, warranty manual and spare parts list. 

 3. Reference Sub Clause 2.2.A.4: The specification states to supply 12ea smart 

sensors to gather and collect data stream on a “real time” basis of input and trending information. Please provide the supplier of these sensors systems and clarify who is responsible for the installation of the sensors. 

Response: See attached Smart Sensor datasheet. Brown Industries will ensure an operational installation along with commissioning of stand‐alone system. 

 4. Reference Sub Clause 2.2.B.4: This section refers to Table 1. Please provide.  

Response:

12. Reference Sub Clause 3.4.B.D Spare Parts: This section says to provide a separate line item price for the above spare parts however there is no spot on the Bid Forms to include this. Please indicate where we are to include this separate line item pricing.  

Response: Please provide in‐house cost estimate form for  individual line items.   

Page 8: Friday, December 11 , 2015 To: Unitron Power Systems

TABLE 1

MODEL

ELT-500

Tons Nominal (Actual Compressor Tonnage) at 60 HZ Ratings

130

Refrigerant R-410A

Power (Voltage/Hertz/Phase) 480-60-3

Rated Amps 400 Compressors, Scroll @ 60HZ Rating (2) 25 Tons

(4) 20 Tons Blower H.P. 60 Design Airflow lb/min 500 Static at Aircraft inches w.c. 40 Cooling Discharge Temperature at the unit.

12°F– 20°F

Heating Discharge Temperature at the unit. 100°F –160°F

PHYSICAL DESCRIPTION

Length inch (cm) 195

Width inch (cm) 87

Height inch (cm) 69

Weight pound (kg) 9950

Materials of construction Steel/Aluminum

UL APPROVED ELECTRICAL XLT500 RLA 305 MOP 388 Circuit Breaker Inside Unit 400 Recommended Power Cable 350 MCM Recommended Circuit Breaker at Disconnect

400 AMPS

* NOTE: These are general performance characteristics. Ambient conditions and alternative unit configurations will alter these general performance characteristics.

Page 9: Friday, December 11 , 2015 To: Unitron Power Systems

5. Reference Sub Clause 2.4.I: We provide a ¼” SAE valve in lieu of the 3/8” flare shut off valve specified. This will prevent accidental refrigerant discharge. Please accept.  

Response: Quote as specified.  6. Reference Sub Clause 2.4.L: This section requires 4‐pole totally enclosed fan 

cooled (TEFC) motors.  Our standard 120 ton unit uses 6‐pole totally enclosed air over (TEAO) motors.  6‐pole motors are used to reduce noise and TEAO motors are used because of size limitations.  TEFC motors will not fit inside our unit. Please accept our standard design.  

Response: Quote as specified.  7. 2.1.I. requires the PCA unit to be provided with required hardware, software, 

databases and any required site licenses to provide remote monitoring and control features as specified herein.  2.2.A.4. requires the PCA control system to consist of twelve (12) smart sensors that will be able to gather and collect data stream on a real time basis of inputs and trending information.  Our PCA unit is capable of providing multiple points for monitoring using the PLC in the PCA unit with no additional smart sensors required.  Is the remote monitoring supposed to be provided in addition to the 12 smart sensor monitoring?    

Response: Quote as specified. The smart sensors are stand‐alone in addition to the PCA monitoring provisions.  

 Section 13990 Relocation and Refurbishment of Passenger Boarding Bridges 1. We would like to inspect the existing bridges and site. Please provide a contact 

person who could help arrange a site visit for the inspection.  Response: For site information, please contact: Peter Brooks: 617‐366‐9469, or Jim Theodos: 857‐321‐0776.  For additional information on the existing PBB’s, please refer to attachments “E8A Removal Report” and “E8B Removal Report”.   

 

Page 10: Friday, December 11 , 2015 To: Unitron Power Systems

2. Reference Sub Clause 3.3.B.2&3 PCA & 400Hz Mounting: This section states that the PBB’s are to be equipped with mounting provisions for PCA and 400hz as well as the provision of BOOM AIR hose management and cable hoists for 180kVA units. Please clarify who is responsible to provide and install the PCA and 400Hz units on the relocated/refurbished PBB’s. 

Response: Installation of all PCA and 400hz equipment and accessories shall be installed by each OEM (original equipment manufacturer) using factory certified technicians. 

 Section 16800 400Hz Ground Power Unit 1. Reference Sub Clause 2.2.D.11: The specification calls for efficiency of 93%. 

Our unit is typically between 91 and 92%. Please accept.  Response: Quote as specified. 

 2. Reference Sub Clause 2.5.A.3: The specification calls for an Amber light to 

indicate the output contactor is on. On the JBT unit, the Amber light indicates input voltage is applied. We use a green light to indicate the output contactor is on. Please accept. 

Response: Quote as specified.  3. Reference Sub Clause 2.8.B: The specification calls for dimensions to be 60 x 53 

x 23.2 inches. Our standard 180kVA height dimension is 30 inches. Please accept. 

Response: Quote as specified.  4. Reference Sub Clause 2.8.C: The specification calls for the enclosure to use 

aluminum panels over a steel frame. Our frame and enclosure are both aluminum. Please accept our standard enclosure.  

Response: Quote as specified.  

Page 11: Friday, December 11 , 2015 To: Unitron Power Systems
salamb
Text Box
JET BRIDGE E8A
Page 12: Friday, December 11 , 2015 To: Unitron Power Systems
Page 13: Friday, December 11 , 2015 To: Unitron Power Systems
Page 14: Friday, December 11 , 2015 To: Unitron Power Systems
Page 15: Friday, December 11 , 2015 To: Unitron Power Systems

Scheduled Completed Comments

‐ Conduct survey 08/11/15 08/11/15 Ameribridge Survey Attached

‐ Test/Run PC Air Unit 08/11/15 08/11/15

‐ Run Bridge 08/11/15 08/11/15

‐ Disconnect Power 08/11/15 08/11/15 Work performed by EG Sawyer

‐ Drop Electrical Lines 08/11/15 08/11/15 Work performed by EG Sawyer

‐ Lower Bridge 08/11/15 08/11/15

‐ Remove PC Air Unit 08/11/15 08/11/15

‐ Remove Rotunda 08/13/15 08/13/15

‐ Crane arrival & check‐out 08/12/15 08/12/15

‐ Hook Bridge 08/12/15 08/12/15

‐ Remove Wheel Boogie 08/12/15 08/12/15

‐ Back trailer under bridge 08/12/15 08/12/15

‐ Set bridge on trailer 08/12/15 08/12/15

‐ Haul bridge to North Campsite 08/12/15 08/12/15

‐ Off‐load bridge 08/12/15 08/12/15 Side Stairs stored on Bridge Roof

‐ Secure/Wrap/Protect PBB's 08/12/15 08/12/15 Secured plywood at platform end.

‐ Conduct survey 08/12/15 08/11/15 Ameribridge Survey Attached

‐ Test/Run PC Air Unit 08/12/15 08/11/15

‐ Run Bridge 08/12/15 08/11/15

‐ Disconnect Power 08/12/15 08/11/15 Utilized EG Sawyer for day

‐ Drop Electrical Lines 08/12/15 08/11/15 Utilized EG Sawyer for day

‐ Lower Bridge 08/12/15 08/11/15

‐ Remove PC Air Unit 08/12/15 08/12/15

‐ Remove Rotunda 08/13/15 08/13/15

‐ Hook Bridge 08/13/15 08/13/15

‐ Remove Wheel Boogie 08/12/15 08/12/15

‐ Back trailer under bridge 08/13/15 08/13/15

‐ Set bridge on trailer 08/13/15 08/13/15

‐ Haul bridge to North Campsite 08/13/15 08/13/15

‐ Off‐load bridge 08/13/15 08/13/15 Side Stairs stored on Bridge Roof

‐ Secure/Wrap/Protect PBB's 08/13/15 08/13/15

‐ Crane Demobilize / Vacate Site 08/13/15 08/13/15

‐ Clean‐up Site 08/14/15 08/14/15 Swept and Rolled area with Magnet

‐ Demobilize / Vacate Site 08/14/15 08/14/15

TERMINAL E JET BRIDGE  E8A & E8B REMOVAL SCHEDULE

E8A & E8B

E8B

E8A

E8B

E8A

Task / Activity

Page 16: Friday, December 11 , 2015 To: Unitron Power Systems

E8A Jet Bridge as installed

E8A Jet Bridge lowered for disassembly

‐ Prepped for PC Air Unit removal

E8A Jet Bridge lowered for disassembly

‐  PC Air Unit removed

TERMINAL E PBB E8A REMOVAL and STORAGE

Page 17: Friday, December 11 , 2015 To: Unitron Power Systems

E8A jet bridge Removed

E8A Jet Bridge Entrance Protection

Page 18: Friday, December 11 , 2015 To: Unitron Power Systems

E8A Jet Way A Tunnel

‐ See Ameribridge Condition Checklist

E8A Jet Way B Tunnel

‐ See Ameribridge Condition Checklist

‐ Missing Handrail ‐ Left Side

E8A Jet Way B Tunnel

‐ Carpet Stain

Page 19: Friday, December 11 , 2015 To: Unitron Power Systems

E8A Jet Way Cab

‐ See Ameribridge Condition Checklist

‐ Wall Panels ‐ Left side

E8A Jet Way Cab

‐ See Ameribridge Condition Checklist

‐ Wall Panels ‐ Right side

Page 20: Friday, December 11 , 2015 To: Unitron Power Systems

E8A Jet Way Control Panel

‐ See Ameribridge Condition Checklist

E8A Jet Way Platform

‐ See Ameribridge Condition Checklist

‐ Canopy Top Bumper torn/ripped

E8A Jet Way Platform

‐ See Ameribridge Condition Checklist

‐ Bottom Right Bumper missing

Page 21: Friday, December 11 , 2015 To: Unitron Power Systems

Jet Way E8A

‐ Main supply Disconnect

Jet Way E8A

‐ Ground Power Disconnect

Page 22: Friday, December 11 , 2015 To: Unitron Power Systems

E8B Jet Way

‐ Stored at North Campsite

‐ Exposed Wire Ends Wrapped & Taped

E8B Jet Way

‐ Stored at North Campsite

‐ Exposed Wire Ends Wrapped & Taped

E8B Jet Way

‐ Stored at North Campsite

‐ Exposed Wire Ends Wrapped & Taped

Page 23: Friday, December 11 , 2015 To: Unitron Power Systems

Jet Way E8A

‐ Storage at North Campsite

Jet Way E8A

‐ Storage at North Campsite

Jet Way E8A

‐ Storage at North Campsite

Page 24: Friday, December 11 , 2015 To: Unitron Power Systems
Page 25: Friday, December 11 , 2015 To: Unitron Power Systems
salamb
Text Box
Jet Bridge E8B
Page 26: Friday, December 11 , 2015 To: Unitron Power Systems
Page 27: Friday, December 11 , 2015 To: Unitron Power Systems
Page 28: Friday, December 11 , 2015 To: Unitron Power Systems
Page 29: Friday, December 11 , 2015 To: Unitron Power Systems

Scheduled Completed Comments

‐ Conduct survey 08/11/15 08/11/15 Ameribridge Survey Attached

‐ Test/Run PC Air Unit 08/11/15 08/11/15

‐ Run Bridge 08/11/15 08/11/15

‐ Disconnect Power 08/11/15 08/11/15 Work performed by EG Sawyer

‐ Drop Electrical Lines 08/11/15 08/11/15 Work performed by EG Sawyer

‐ Lower Bridge 08/11/15 08/11/15

‐ Remove PC Air Unit 08/11/15 08/11/15

‐ Remove Rotunda 08/13/15 08/13/15

‐ Crane arrival & check‐out 08/12/15 08/12/15

‐ Hook Bridge 08/12/15 08/12/15

‐ Remove Wheel Boogie 08/12/15 08/12/15

‐ Back trailer under bridge 08/12/15 08/12/15

‐ Set bridge on trailer 08/12/15 08/12/15

‐ Haul bridge to North Campsite 08/12/15 08/12/15

‐ Off‐load bridge 08/12/15 08/12/15 Side Stairs stored on Bridge Roof

‐ Secure/Wrap/Protect PBB's 08/12/15 08/12/15 Secured plywood at platform end.

‐ Conduct survey 08/12/15 08/11/15 Ameribridge Survey Attached

‐ Test/Run PC Air Unit 08/12/15 08/11/15

‐ Run Bridge 08/12/15 08/11/15

‐ Disconnect Power 08/12/15 08/11/15 Utilized EG Sawyer for day

‐ Drop Electrical Lines 08/12/15 08/11/15 Utilized EG Sawyer for day

‐ Lower Bridge 08/12/15 08/11/15

‐ Remove PC Air Unit 08/12/15 08/12/15

‐ Remove Rotunda 08/13/15 08/13/15

‐ Hook Bridge 08/13/15 08/13/15

‐ Remove Wheel Boogie 08/12/15 08/12/15

‐ Back trailer under bridge 08/13/15 08/13/15

‐ Set bridge on trailer 08/13/15 08/13/15

‐ Haul bridge to North Campsite 08/13/15 08/13/15

‐ Off‐load bridge 08/13/15 08/13/15 Side Stairs stored on Bridge Roof

‐ Secure/Wrap/Protect PBB's 08/13/15 08/13/15

‐ Crane Demobilize / Vacate Site 08/13/15 08/13/15

‐ Clean‐up Site 08/14/15 08/14/15 Swept and Rolled area with Magnet

‐ Demobilize / Vacate Site 08/14/15 08/14/15

TERMINAL E JET BRIDGE  E8A & E8B REMOVAL SCHEDULE

E8A & E8B

E8B

E8A

E8B

E8A

Task / Activity

Page 30: Friday, December 11 , 2015 To: Unitron Power Systems

E8B Jet Bridge as installed

E8B Jet Bridge lowered for disassembly

‐ Prep for PC Air Removal

PC Air Unit disconnected and removed

TERMINAL E PBB E8B REMOVAL and STORAGE

Page 31: Friday, December 11 , 2015 To: Unitron Power Systems

E8B Jet Way Removed

E8B Jet Way Rotunda prepped for removal

Page 32: Friday, December 11 , 2015 To: Unitron Power Systems

E8B Rotunda separated from terminal

E8B Jet Way Entrance Protection

Page 33: Friday, December 11 , 2015 To: Unitron Power Systems

E8B Rotunda Carpet Damaged

‐ See Ameribridge Check List Report

E8B A Tunnel Carpet Damage

‐ See Ameribridge Check List Report

E8B Cab Flooring Damage

‐ See Ameribridge Check List Report

Page 34: Friday, December 11 , 2015 To: Unitron Power Systems

E8B Jet Way A Tunnel

‐ Lighting

‐ Ceiling Panels

‐ Wall Panels

‐ Flooring

‐ See Ameribridge Check List Report

E8B Jet Way B Tunnel

‐ Flooring ‐ Water Stained & Damaged

‐ See Ameribridge Check List Report

E8B Jet Way B & C Tunnel

‐ Lighting ‐ Not Working

‐ Ceiling Panels ‐ Not Visible

‐ Wall Panels ‐ Not Visible

‐ Flooring‐ Not Visible

‐ See Ameribridge Check List Report

Page 35: Friday, December 11 , 2015 To: Unitron Power Systems

E8B Jet Way PC Air Unit

‐ Air Discharge Outlets

‐ Electric Panel & Disconnect

E8B Jet Way PC Air Unit

‐ Electric Panel & Disconnect

‐ Disconnect Shaft Missing

Page 36: Friday, December 11 , 2015 To: Unitron Power Systems

E8B Jet Way Main Power Panel

‐ Power Disconnect

E8B Jet Way Main Power Panel

‐ Power Disconnect

‐ Missing Disconnect Shafts

‐ Missing Disconnect Interconnectors

Page 37: Friday, December 11 , 2015 To: Unitron Power Systems

E8B Jet Way Main Power Panel

‐ Power Disconnect

‐ Disconnect Shafts interconnection Parts

E8B Jet Way Main Power Panel

‐ Power Disconnect

‐ Disconnect Shafts Shown for Refernce

Page 38: Friday, December 11 , 2015 To: Unitron Power Systems

E8B Jet Way Canopy

‐ Extended Canpoy ‐ Torn & Worn

‐ See Ameribridge Check List Report

E8B Jet Way Canopy

‐ Canpoy ‐ Torn & Worn

‐ See Ameribridge Check List Report

Page 39: Friday, December 11 , 2015 To: Unitron Power Systems

E8B Jet Way Canopy

‐ Top Bumber Pad Missing

‐ See Ameribridge Check List Report

E8B Jet Way Canopy

‐ Bottom Bumper Corner Missing

‐ Corner Bumper Pad Missing

‐ See Ameribridge Check List Report

Page 40: Friday, December 11 , 2015 To: Unitron Power Systems

E8B Jet Way

‐ Stored at North Campsite

‐ Exposed Wire Ends Wrapped & Taped

E8B Jet Way

‐ Stored at North Campsite

‐ Exposed Wire Ends Wrapped & Taped

E8B Jet Way

‐ Stored at North Campsite

‐ Exposed Wire Ends Wrapped & Taped

Page 41: Friday, December 11 , 2015 To: Unitron Power Systems

E8B Jet Way

‐ Stored at North Campsite

E8B Jet Way

‐ Stairs & Shoot Stored on Roof

E8B Jet Way

‐ Opening Protection

Page 42: Friday, December 11 , 2015 To: Unitron Power Systems

Jet Way E8B

‐ Storage at North Campsite

Jet Way E8B

‐ Storage at North Campsite

Jet Way E8B

‐ Storage at North Campsite

Page 43: Friday, December 11 , 2015 To: Unitron Power Systems
Page 44: Friday, December 11 , 2015 To: Unitron Power Systems

Address: ThyssenKrupp Airport Systems, Inc. 3201 N. Sylvania Ave., Suite 117 Fort Worth, Texas 76111   

Phone: (817) 210‐5000 Fax: (817) 210‐5043 Mail: [email protected]  

Internet: www.thyssenkrupp‐airports.com   

 

ThyssenKrupp Airport Systems  

 

 

 

December 07, 2015 

 

 

 

Massachusetts Port Authority 

Logan Office Center 

One Harborside Drive 

Suite 200S 

East Boston, MA 02128 

 

Email: [email protected] 

 

Reference:    Bid #5726 ‐ Terminal E Enhancements  

   

We have completed the review of the Bid Package and would like to submit the following questions:  

 

1. Section 13041‐17, 2.14 Electrical System and Components; Section 13983‐3, 2.2 System 

Performance Requirements; Section 13990‐6, 2.4 Spreadsheet Guideline Scope of Work: ‐‐‐‐

Q: These sections mention a requirement for “smart sensors”, but no specifications are 

identified. Can more information please be provided for these sensors? 

Response – The sensor manufacturer will ensure the commissioning and installation of all 

sensors.  Please see Addendum 1 and attached Smart Sensor product datasheet. 

 

2. On Drawing PL.802 there is a requirement for a baggage conveyor mounted to the service 

stairs, but in Section 13041‐16, 2.13 Service Door, Landing and Stair it mentions a 

requirement for a wheel chair lift and late bag slide to be mounted to the service stair 

landing. 

Q: There seems to be a conflict with the requirements. Please advise as to what is to be 

required and where.  

Response – Contractor shall provide a wheel chair lift and bag slide at the landing, which is 

attached to the fixed walkway tunnel. 

 

3. On Drawing PL.802, the service stairs and landing are depicted to be mounted at the 

walkway and not on the PBB. 

Q: Is the requirement of relocating the service stairs/landing to be typical of ALL PBB’s at each 

gate, including the Refurbished/Relocated PBB’s? 

Response – Please reference General Note 3.  The service stair, landing, and baggage 

conveyance are only mounted to the INS level PBBs (refurbished/relocated PBBs). The club 

level PBBs do not have service stair, landing, or baggage conveyance. 

    

Page 45: Friday, December 11 , 2015 To: Unitron Power Systems

Page: 2 

Date: December 10, 2015 

 

Address: ThyssenKrupp Airport Systems, Inc. 3201 N. Sylvania Ave., Suite 117 Fort Worth, Texas 76111   

Phone: (817) 210‐5000 Fax: (817) 834‐6985 Mail: [email protected]  

Internet: www.thyssenkrupp‐airports.com  

ThyssenKrupp Airport Systems 

4. Please confirm that a point‐of‐use pre‐conditioned air unit is to be mounted at the rotunda 

with a telescoping air duct and flexible air ducting connecting to the hose management 

system and not a point‐of‐use PCA unit mounted at the outermost tunnel section with 

flexible ducting connecting to the hose management system?  

a. Please confirm that this is to be typical of ALL PBB’s at each gate, including the 

Refurbished/Relocated PBB’s. 

Response – All PCA units are to be mounted on rotunda column per specifications.  

See item 5 below. 

 

5. Please confirm that ALL PBB’s at each gate are to have 120 Ton PCA units with two hose 

management system units each, including the Refurbished/Relocated PBB’s.  

a. Also, would this require two telescoping ducts per PBB since the PCA units are dual 

output? 

Response – Correct.  Two 120 ELT PCA units, two hose management systems. One 

telescoping air duct with a two connector splitter.   

 

6. Please confirm who is responsible for the supply and installation of the bollards depicted in 

Drawing PL.802. If we, as the bidder, are required to supply and install the bollards, can the 

structural drawings please be provided as stated? Please confirm if the bollards are just to be 

provided for the three (3) potable water cabinets or other.  

 Response – Civil Contractor is responsible for the supply and installation of bollards.  The 

bollards shall protect the potable water cabinets and the operational range/swing of the PCA 

unit mounted to the rotunda column. 

 

7. Section 13041‐22, 2.18 Gate Signage: The Bidder is to replace the PBB signage at adjacent 

existing gates. 

             Q: Please confirm if we are just to replace the panels or the complete gate sign.  

Response – Contractor shall provide new complete gate sign assemblies for all PBBs. All gate 

signs should match with consistent materials and finishes. 

  

8. Please confirm that there is not a goal for M/WBE at this time for this project. 

Response – There are no M/WBE goals for this scope of the project.  See Addendum 1. 

 

9. Paragraph 2.1.B of specification section 13983 for Preconditioned Air Units only lists 

TwistAero as an approved vendor.  Can ITW GSE Hobart also be added as an approved 

vendor? 

Response – All alternates and substitutions will be considered for all Ground Support 

Equipment, including Pre‐Condition Air Units and 400hz units , . Contractors shall follow the 

specification criteria for the basis of design guidelines for tendering purposes. During the 

submittal process all alternates and substitutions will be evaluated with the following 

documentation. Company profile ,  history and references, technical documentation, 

electrical and mechanical compliance codes, manufacturing process, quality control manual, 

after market support guidelines, warranty manual and spare parts list. 

 

Page 46: Friday, December 11 , 2015 To: Unitron Power Systems

Page: 3 

Date: December 10, 2015 

 

Address: ThyssenKrupp Airport Systems, Inc. 3201 N. Sylvania Ave., Suite 117 Fort Worth, Texas 76111   

Phone: (817) 210‐5000 Fax: (817) 834‐6985 Mail: [email protected]  

Internet: www.thyssenkrupp‐airports.com  

ThyssenKrupp Airport Systems 

10. The specifications and drawings call for the PCA unit to be mounted to the rotunda.  The 

physical size of a 120 ton DX PCA unit makes this very difficult or not possible.  Would you 

consider under‐bridge mounting on the c‐tunnel or ground mounted as an alternative? 

Response – Quote to specifications. 

 

11. Please confirm who is to be considered the Construction Manager. 

Response – Suffolk Construction. 

 

12. Please provide more information regarding the smart sensors and their interface. 

Response – See item #1.  

 

13. Q: The specified paint system is based on using hot rolled steel. Thyssen uses cold formed 

galvanized / galvannealed steel panels that requires a special paint system. Thyssen’s paint 

system meets and exceeds what is specified. As provided for previous equipment to Boston, 

would you please accept our paint system designed for galvannealed steel and suited for the 

Boston climate?  

Response – Accepted, provide documentation. 

 

14. Section 13041‐20, B. Exterior:   Q: ThyssenKrupp has supplied many bridges throughout the world without issue of the 

  finishes. If we demonstrate that our finish process and material is equal to or better than is 

 what is specified, would our standard exterior and interior finishing process be accepted? 

Response – Accepted. 

 

15. Chapter VII – Legal Relations and Responsibility to Public; Article 37.1‐Insurance Requirements 

This section indicates, “Limits shall be provided on a per project basis.” 

We respectfully request ‘per project aggregate’ requirement be deleted from this section.  If 

required, we can, however, add the ‘per project’ endorsement for an additional cost. In lieu 

of a ‘per project aggregate’ we can provide up to a $10,000,000 general aggregate limit 

(primary) and an additional $20,000,000 excess limit at no additional cost. 

Response – Providing up to $10M general aggregate insurance and additional $20M excess 

limit is acceptable to Massport. 

 

15. Chapter VII – Legal Relations and Responsibility to Public; Article 37.5‐Pollution Legal 

Liability 

This section indicates, “Construction Manager shall provide Pollution Legal Liability coverage 

with a minimum limit of $5,000,000.” 

Please confirm Pollution Legal Liability is required for this scope of work. 

Response – Pollution Liability Insurance is not required for this scope of the project. 

    

Page 47: Friday, December 11 , 2015 To: Unitron Power Systems

Page: 4 

Date: December 10, 2015 

 

Address: ThyssenKrupp Airport Systems, Inc. 3201 N. Sylvania Ave., Suite 117 Fort Worth, Texas 76111   

Phone: (817) 210‐5000 Fax: (817) 834‐6985 Mail: [email protected]  

Internet: www.thyssenkrupp‐airports.com  

ThyssenKrupp Airport Systems 

16. Chapter IX – Measurement and Payment; Article 76‐Partial Payment 

This section indicates, “Within fifteen (15) days after receipt from the Construction Manager 

of a periodic estimate requesting payment of the amount due for the preceding month, the 

Authority will make a periodic payment to the Construction Manager for the Work performed 

during the preceding month and for the materials not incorporated in the Work but delivered 

and suitably stored at the site (or at some location agreed upon in writing) to which the 

Construction Manager has title or to which a  Subcontractor has title and has authorized…” 

Please confirm it will be acceptable to include progress billings for engineering, material, and 

labor costs incurred during the manufacturing process and prior to delivery. 

Response – Massport will entertain progress billings so long appropriate documentation of 

material ownership and insurance is provided with the requisitions. 

 

17. Division IIB – Special Provision; Section 5‐Liquidated Damages 

This section indicates, “Milestone 1: $2,500 per calendar day”. 

We respectfully request liquidated damages be capped at 10% of the contract value. 

Response – Capping LD’s to 10% of the contract value is acceptable to Massport. 

 

18. Please confirm that our standard galvannealed floor construction will be acceptable for 

the tunnel sections.  

Response – Accepted. 

 

19. Section 2.4 Fixed Walkway, H: Fixed Walkway loads for roof and flooring must exceed 

the local Internal Building Codes adopted by Massport. 

Please confirm that the PBB industry standard loads of 40 pounds per square for floor 

structure, roof loads of 25 pounds per square foot over the total roof area, and a wind load of 

25 pounds per square foot. If not, please define the acceptable loads.  

Response – We accept industry standard loads.  

 

 

 Best Regards, 

 

 

 

Tony Thompson 

Sales/Estimation 

 

ThyssenKrupp Airport Systems, Inc. 

Fort Worth, Texas 76111 

Tel.: +1 (817) 210‐5009 

Fax: +1 (817) 210‐5043 

E‐mail: [email protected] 

 

Page 48: Friday, December 11 , 2015 To: Unitron Power Systems

Brown Technologies, Inc www.bti-corp.com

5141 California Ave Irvine, CA 92697

(866) 526-7067

A I R P O R T P R E D I C T I V E A S S E T M A N A G E M E N T

With shrinking budgets and growing costs, airports of all

sizes, now more than ever, need to leverage their existing

resources to improve operational performance and

travelers’ experiences.

Assets are not the same. Even if they start out the same,

they are used differently. The different usage greatly

affects their life expectancy. If the usage profile is not

taken into account, assets can fail unexpectedly hurting

operational performance and travelers’ experiences.

Brown Technologies, with its AB500 series Smart Sensors

and Analytics Platform, installs sensors that monitors

motors, rollers and other industrial equipment.

The AB500 Series Smart Sensors monitors temperature,

vibration, volts and amps as well as other operational

parameters.

The Analytics Platform analyzes in real time the sensors

and understands the usage profile for each equipment

and the impact that profile has on asset life. The Analytics

Platform leverages Machine Learning to understand the

different usage profiles of each equipment and how they

contribute to the overall life and efficiency of each asset.

The system scales from one asset to hundreds of

thousands of assets.

Predictive Asset Management Platform

ment Platform

• OPC

• ModBus

• MQTT

• TCP/UDP

Ingestion

• Derive Physical Calculations

• Metrics

• Thresholds

Engineering Model • Machine Learning

• Logistic Regression

• Thresholding

• Event Recognition

Analyze / Predict

• Maintenance

• Escalate

• Change Operation

Act• Vendor

Performance

• Bad/MistrainedActors

• Warranty

Report

Analysis Performed:

Thresholding

Vibration Analysis

Power Analysis

Machine Learning

Predictive asset management extends the efficiency of aviation

assets while reducing unplanned down time and helping minimize

major repairs.

Benefits:

Longer Asset Life

Visibility of Asset Usage Profiles

Prediction of future performance (Peak/Load)

Intelligent control of assets

Page 49: Friday, December 11 , 2015 To: Unitron Power Systems

Brown Technologies, Inc www.bti-corp.com

5141 California Ave Irvine, CA 92697

(866) 526-7067

A I R P O R T P R E D I C T I V E A S S E T M A N A G E M E N T

Sensors

Sensors

Gateway

PASSENGER LOADING BRIDGE USE CASE

Analytics Platform pulls the data in real-

time from the AB500 Smart Sensors

over wired or wireless communications

and the analyzes the assets for their

current and historical usage profile.

MANY OTHER APPLICATIONS:

Baggage Distribution Systems

Boilers

Central Utility Plant

Chillers

Cooling Towers

Pumps

Sensors