fqi-mpr-2014-12
DESCRIPTION
Monthly progress report for the month of December 2014 for the project Falaj al Qabail Interchange in Oman.TRANSCRIPT
SULTANATE OF OMAN
MINISTRY OF TRANSPORT AND COMMUNICATIONS DIRECTORATE GENERAL OF ROADS & LAND TRANSPORT
MUSCAT
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT TENDER NO. 51/2012
MONTHLY PROGRESS REPORT NO. 12
DECEMBER 2014
CONSULTANT:
RENARDET S.A. & PARTNERS CONSULTING ENGINEERS LLC. P.O. Box 579, Muscat, P.C. 100, Sultanate of Oman
CONTRACTOR:
CONSOLIDATED CONTRACTORS CO. LLC P.O. Box 614, Muscat, P.C. 100, Sultanate of Oman
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 1
Table of Contents
1. PROJECT PARTICULARS .............................................................................................................................................. 2
2. SCOPE OF WORK ....................................................................................................................................................... 3
3. TYPICAL CROSS SECTIONS .......................................................................................................................................... 4
4. SITE VISITS/ MEETINGS .............................................................................................................................................. 6
5. ENGINEER’S SITE STAFF ............................................................................................................................................. 7
6. PROGRESS S-CURVE ................................................................................................................................................... 8
7. STATUS OF MAJOR ACTIVITIES ................................................................................................................................ 10
8. BRIDGE PROGRESS SCHEDULE ................................................................................................................................. 11
9. MSE WALLS PROGRESS SCHEDULE ........................................................................................................................... 12
10. BOX CULVERTS PROGRESS SCHEDULE ...................................................................................................................... 14
11. PROGRESS STATUS OF UTILITY CROSSING DUCTS .................................................................................................... 18
12. PROJECT PROGRESS STRIP CHART ........................................................................................................................... 21
13. FINANCIAL STATUS OF PAYMENTS .......................................................................................................................... 27
14. DETAILS OF EQUIPMENT AVAILABLE AT SITE ........................................................................................................... 28
15. DETAILS OF MANPOWER AVAILABLE AT SITE .......................................................................................................... 30
16. QA/QC REPORTS ...................................................................................................................................................... 32
17. STATUS OF MATERIAL APPROVALS .......................................................................................................................... 36
18. ENGINEER’S COMMENTS ......................................................................................................................................... 38
19. CORRESPONDENCE DURING THE MONTH................................................................................................................ 39
20. PROGRESS PHOTOGRAPHS ...................................................................................................................................... 42
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 2
1. Project Particulars
Client: Ministry of Transport & Communications
P.O. Box 684, Muscat, Postal Code 113
Directorate General of Roads
Sultanate of Oman.
Consultant: Renardet S.A & Partners L.L.C.
P.O. Box 579, Muscat, Postal Code 100
Sultanate of Oman.
Contractor: Consolidated Contractors Company L.L.C.
P.O. Box 614, Muscat, Postal Code 100
Sultanate of Oman.
Project Commencement Date: 30.10.2013
Mobilization Period: 60 Days
Construction Period: 548 Days
Completion date: 29.06.2015
Original Contract Value:
(Including Contingencies) R.O. 17,884,403.000
Amount of Contingencies: R.O. 1,402,155.613
Original Contract Value:
(Excluding Contingencies) R.O. 16,482,247.387
Planned Physical Progress for December
2014 8.32%
Actual Physical Progress for December
2014 6.89%
Planned physical progress cumulative up to
end of December 2014
63.86%
Achieved physical progress cumulative up
to end of December 2014 58.30%
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 3
2. Scope of Work
This project is located in Batinah Region on existing Batinah Highway in the Wilayat Sohar and
consists of construction of an interchange in place of existing roundabout along with allied works.
Total length of the project along Batinah highway is about 4.0 km which shall be converted from four
lanes to six lanes with tapering back to 4lanes, all as shown on plans. Also included in the scope of
work is the construction of service roads, pedestrian underpasses.
The work also includes expropriation of properties, relocation/protection of services (sewerage,
telephone, electricity, water, irrigation) road lighting works and traffic signals.
Major items within the scope of work consist of but not limited to the following:
Removal of existing asphalt surface, extension of existing embankment and earthwork to
achieve the designed profile and gradient.
Removal of existing drainage structures and construction of new ones including protection
works as shown on construction drawings and as directed.
Expropriation of open/built up properties and removal of existing structures thereupon.
Construction of interchange ramps, Box Girder Bridge, roundabout, pedestrian underpasses and
service roads.
Provision of new street lighting system/traffic signals and removal/disposal of existing street
light poles including conductors/cables, transformers, feeder pillars, foundations etc., all for the
proper completion of the job.
Construction of earthen embankment/sub grade, sub-base, aggregate base course, bituminous
base course and bituminous wearing course as per details on the construction drawings.
Installation of road side furniture (traffic signs, road marking etc.) and protection works on
embankment slopes.
Relocation/Protection of existing LT, 11KV and 33KV transmission lines and allied items
(transformers etc.) as per the requirements of concerned authority.
Relocation/Protection of existing utilities (sewerage, telephone, electricity, water lines and
irrigation) as per the requirements of concerned authorities.
Provision of ducts for future utilities as per the requirements of utility operator.
Construction of concrete safety barriers, fixing of guard rails and paving tiles.
Provision of traffic diversion in coordination with concerned authorities
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 4
3. Typical Cross Sections
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 5
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 6
4. Site visits/ Meetings
S. No. Details of Site Visit/ meeting Date Final Outcome/ Decisions
1 Visit to M/s Assarain Concrete
Products, Muscat for inspection of
Process control of Paving Blocks
11.12.2014 Found that the process and quality
control measures are effectively
implemented.
2 Monthly review meeting at DGR Office 25.12.2014 The project progress and various
project issues are discussed.
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 7
5. Engineer’s Site Staff
S.
No. Name Designation
Date of
Joining
1. Roberto Benigni Head Supervision Projects
2. Muneer Abdul Resident Engineer 19.03.2014
3. Hussein Shah Material Engineer 04.01.2014
4. Ernesto B. Paredes Bridge Engineer 16.04.2014
5. Sande H Tangaras Civil Engineer 08.06.2014
6. Danilo Quantity Surveyor 19.06.2014
6. Mohamed Safie Land Surveyor 04.01.2014
7. Aseef Iqbal Site Inspector 10.02.2014
8. Alaa Aldin Abdelfatah Site Inspector 30.03.2014
9. Walid Samy Abdoh Mostafa Material Inspector 01.04.2014
10. Haneefa Mohmmed Al Zadjali Secretary 13.04.2014
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 8
6. Progress S-Curve
2013
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
0.01 0.25 1.42 4.23 7.25 10.06 9.42 9.73 10.21 9.79 8.49 5.72 4.55 3.56 2.79 3.83 3.55 3.47 1.67 - - - -
0.11 0.14 0.23 0.28 1.71 3.18 6.84 9.16 9.14 9.08 7.69 7.98 8.32 6.96 6.50 4.68 3.59 3.34 4.42 3.29 1.64 1.11 0.62
- 0.28 0.18 1.01 3.39 5.15 5.18 7.36 7.30 9.33 6.20 6.02 6.89 - - - - - - - - - -
0.01 0.26 1.67 5.91 13.15 23.21 32.64 42.37 52.58 62.37 70.86 76.59 81.13 84.69 87.48 91.31 94.86 98.33 100.00 100.00 100.00 100.00 100.00
0.11 0.25 0.48 0.76 2.47 5.64 12.48 21.64 30.78 39.87 47.55 55.53 63.86 70.81 77.31 81.99 85.59 88.93 93.35 96.64 98.27 99.38 100.00
- 0.28 0.45 1.46 4.86 10.01 15.19 22.55 29.86 39.18 45.39 51.41 58.30
CUMULATIVE PROGRESS
CL14 Org Plan Cumulative %
Actual Cumulative
2014 2015
MONTHLY PROGRESS
CL14 Org Plan per Month %
Actual per Month
Revised Sch. per Month %
Revised Sch. Cummulative %
0.00
20.00
40.00
60.00
80.00
100.00
120.00
-
2
4
6
8
10
12
Dec
Jan
Fe
b
Ma
r
Apr
Ma
y
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Fe
b
Ma
r
Apr
Ma
y
Jun
Jul
Aug
Sep
Oct
2013 2014 2015
% C
um
ula
tive
% M
ON
TH
LY
MONTHS
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT PROJECT - OMANMONTHLY CL 14 PLANNED VS. ACTUAL MANHOURS
CL14 Org Plan per Month % Revised Sch. per Month % Actual per Month CL14 Org Plan Cumulative % Revised Sch. Cummulative % Actual Cumulative
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 9
REV.: 0
PERIOD ENDING: Dec-14
2013
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
CL14 Plan % 0.30 8.67 19.23 26.89 31.77 36.64 41.51 46.39 51.26 56.13 61.01 65.88 70.76 75.63 80.50 85.38 90.25 95.13 100.00 100.00 100.00 100.00 100.00
Revised Plan % 4.11 9.30 17.58 24.18 30.90 35.16 38.97 42.78 46.60 50.41 54.23 58.04 61.86 65.67 69.48 73.30 77.11 80.93 84.74 88.56 92.37 96.18 100.00
Actual - 6.62 13.03 22.36 37.31 43.00 44.11 51.21 56.24 60.13 65.67 69.96 74.25
CL14 Plan % 0.00 0.00 0.38 20.37 47.70 48.33 48.33 48.33 48.33 48.33 48.33 48.33 48.33 59.91 77.84 90.27 94.93 100.00 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - 7.40 29.85 78.13 78.13 78.13 78.13 78.13 78.13 78.13 78.13 78.13 78.13 80.66 87.59 88.57 100.00 100.00 100.00
Actual - 10.09 10.09 17.59 19.52 77.42 69.96 70.18 70.18 70.18 83.49 84.12 84.95
CL14 Plan % 0.00 0.00 0.00 0.78 6.58 16.76 29.38 41.37 58.64 66.60 74.18 82.85 84.75 84.75 85.24 92.34 92.34 98.36 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - - - 3.32 12.89 28.83 43.89 60.03 74.82 90.03 95.24 95.95 95.95 96.09 98.30 99.46 99.54 100.00 100.00
Actual - - - - 4.35 4.89 - 5.27 14.93 29.52 47.15 47.31 67.50
CL14 Plan % 0.00 0.00 1.01 9.21 29.30 45.91 56.90 62.24 64.59 67.94 69.08 69.08 75.05 82.85 93.48 98.64 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - 4.26 8.17 16.03 32.68 53.13 67.05 67.47 67.47 67.90 68.32 68.32 68.32 81.11 93.02 97.11 100.00 100.00 100.00
Actual - - - 5.00 5.00 53.23 62.16 74.91 78.29 91.86 98.62 115.33 148.20
CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11.07 26.27 41.98 59.98 78.73 79.90 79.90 85.20 89.45 92.60 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - - - - - - - 3.58 17.42 31.37 51.32 75.82 75.82 75.82 75.82 87.25 87.25 98.60 100.00
Actual 1.26 3.19 5.42 10.68
CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.08 7.77 19.32 31.22 44.94 51.98 52.14 90.14 90.14 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - - - - - - - - - 0.08 8.44 22.42 46.57 51.97 51.97 86.66 90.05 93.03 100.00
Actual
CL14 Plan % 0.00 0.00 0.23 1.43 2.97 10.17 23.65 36.51 51.47 63.06 74.26 75.97 77.37 80.05 82.40 88.97 92.13 98.55 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - 0.26 2.64 7.33 20.62 35.14 50.06 62.76 68.40 72.78 74.07 74.67 83.42 84.04 84.30 87.32 95.58 98.11 99.44 100.00 100.00
Actual - - - 0.48 1.26 5.59 14.93 27.72 40.08 55.38 66.20 71.35 77.45
CL14 Plan % 0.00 0.00 4.02 15.21 34.62 57.89 69.26 81.40 83.38 83.46 84.50 92.89 99.96 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - 2.77 7.75 13.76 22.09 29.64 39.02 49.64 59.51 71.33 85.14 87.00 93.50 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Actual - - - 0.01 6.05 14.73 18.14 22.33 26.30 30.75 34.14 46.19 56.00
CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.38 1.21 2.63 3.42 4.23 5.50 6.08 6.08 34.35 99.38 99.76 99.76 100.00 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - - - - - - 8.09 26.17 57.85 78.53 94.70 94.70 94.70 94.70 98.41 100.00 100.00 100.00 100.00
Actual - - - 2.50 49.42 14.39 13.24 16.19 16.72 27.56 21.22 41.44 54.32
CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.80 17.87 43.85 61.59 72.98 81.15 83.94 84.42 85.35 92.86 96.39 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - - - - - - 7.02 20.33 38.29 50.60 59.52 72.89 81.07 83.55 86.89 90.26 95.34 98.27 100.00
Actual - - - - - 2.61 4.98 6.42 8.31 10.67 12.36 14.45 16.54
CL14 Plan % 0.00 0.00 0.00 4.43 17.23 33.36 49.13 65.07 80.79 93.82 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - 0.99 2.30 17.26 33.64 49.01 64.70 79.88 95.44 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Actual - - - 6.16 9.87 17.63 25.69 35.90 49.03 65.95 72.27 72.29 83.86
CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.17 0.79 1.43 5.65 13.41 21.84 30.56 32.94 70.94 75.04 94.02 96.43 100.00 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - - - 0.33 2.34 9.42 17.07 23.51 31.40 41.66 47.49 47.55 47.55 83.28 93.95 97.61 100.00 100.00 100.00
Actual - - - 0.13 5.52 9.26 13.38 16.87 17.75 20.45 14.38 26.70 24.67
Revised Plan 0.11 0.25 0.48 0.76 2.47 5.64 12.48 21.64 30.78 39.87 47.55 55.53 63.86 70.81 77.31 81.99 85.59 88.93 93.35 96.64 98.27 99.38 100.00
Actual Cum - 0.28 0.45 1.46 4.86 10.01 15.19 22.55 29.86 39.18 45.39 51.41 58.30 - - - - - - - - - -
2013
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
0.01 0.25 1.42 4.23 7.25 10.06 9.42 9.73 10.21 9.79 8.49 5.72 4.55 3.56 2.79 3.83 3.55 3.47 1.67 - - - -
0.11 0.14 0.23 0.28 1.71 3.18 6.84 9.16 9.14 9.08 7.69 7.98 8.32 6.96 6.50 4.68 3.59 3.34 4.42 3.29 1.64 1.11 0.62
- 0.28 0.18 1.01 3.39 5.15 5.18 7.36 7.30 9.33 6.20 6.02 6.89
0.01 0.26 1.67 5.91 13.15 23.21 32.64 42.37 52.58 62.37 70.86 76.59 81.13 84.69 87.48 91.31 94.86 98.33 100.00 100.00 100.00 100.00 100.00
0.11 0.25 0.48 0.76 2.47 5.64 12.48 21.64 30.78 39.87 47.55 55.53 63.86 70.81 77.31 81.99 85.59 88.93 93.35 96.64 98.27 99.38 100.00
- 0.28 0.45 1.46 4.86 10.01 15.19 22.55 29.86 39.18 45.39 51.41 58.30
2014 2015
MONTHLY PROGRESS
CL14 Org Plan per Month %
Actual per Month
CUMULATIVE PROGRESS
CL14 Org Plan Cumulative %
Actual Cumulative
MMEP Works &
Ducts4.03
TOTAL 100.000
Revised Sch. per Month %
Revised Sch. Cummulative %
83,264
2,063,644
L MSE walls 6.84
J Drainage Works 1.50
KIncidental
Construction13.33
30,920
275,037
141,190
IConcrete for
Bridge22.12
H
Concrete for
Box Culvert
/Underpas
38.19788,138
456,522
GBituminous
Pavement3.57
FSubbase &
Aggregate Base2.4250,004
73,724
EStructural
Excavation0.72
D Embankment 3.5974,043
14,821
C
Clearing &
Removal of
Obstructions
0.95
2015
B Road Diversions 2.73
Budgeted
Man-Hrs
56,423
19,558
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT - OMAN
MANHOURS OVERALL PROJECT S-CURVE
Item Description Wtd.
%
Plan/
Actual
2014
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 10
7. Status of Major Activities
Sl. No.
Description Unit BOQ Qty.
(Revised)
Actual Qty.
% Completion
1 Clearing & Grubbing M2 162,000 138,801 85.67%
2 Borrow Excavation (to embankment)
M3 340,000 221,412 65.12%
3 Granular Sub-base M3 28,700 10,499 36.58%
4 Concrete for Culverts (1st stage)
M3 15,000 13,207 88.04%
5 Concrete for Bridge M3 9,500 4,696 49.43%
6 Steel reinforcement Fixing ton 4,900 2,974 60.69%
7 Working Piles M3 2,826 2,826 100.00%
8 Mortared Stone Riprap M3 5,210 0.00 0.00%
9 MSE Walls Fixing M2 13,030 8,461 64.93%
10 RCC Drainage Pipes LM 4,530 1,856 40.97%
11 Aggregate Base Course M3 70,300 2,220 3.16%
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 11
8. Bridge Progress Schedule
ACTIVITY AB1 L P1L P2L P4L P5L AB2 L
PEDESTAL/POT BEARING 9-Nov-14 9-Nov-14 9-Nov-14 15-Nov-14 - - - -
PIER N/A - - - - N/A
2nd Lift - 13-Aug-14 19-Aug-14 29-Sep-14 4-Sep-14 -
Height (m) - 6.920 6.920 6.920 6.920 -
1st Lift - 23-Jul-14 7-Aug-14 15-Sep-14 10-Aug-14 -
Height (m) - 1.153 1.210 1.248 1.225 -
BIT. PAINTING - 28-May-14 26-Jun-14 4-Sep-14 23-Jun-14 -
PILE CAP (Pier & Abut.) 4-Nov-14 17-May-14 18-Jun-14 25-Aug-14 11-Jun-14 -
F/P & BLINDING 21-Oct-14 11-May-14 11-Jun-14 17-Aug-14 3-Jun-14 24-Dec-14
ACTIVITY AB1 R P1R P2R P4R P5R AB2 R
PEDESTAL/POT BEARING 16-Oct-14 14-Oct-14 14-Oct-14 16-Oct-14 - - - -
PIER N/A - - - - N/A
2nd Lift - 9-Jun-14 28-Jun-14 20-Sep-14 10-Jul-14 -
Height (m) - 6.920 6.920 6.920 6.920 -
1st Lift - 20-May-14 11-Jun-14 10-Sep-14 22-Jun-14 -
Height (m) - 0.366 0.423 0.461 0.438 -
BIT. PAINTING - 12-May-14 25-May-14 4-Sep-14 31-May-14 -
PILE CAP (Pier & Abut.) 9-Oct-14 4-May-14 13-May-14 27-Aug-14 20-May-14 22-Dec-14
F/P & BLINDING 2-Oct-14 27-Apr-14 7-May-14 20-Aug-14 14-May-14 14-Dec-14
SUB-STRUCTURE WORK PROGRESS (RHS)
SUB-STRUCTURE WORK PROGRESS (LHS)
P3L
24-Jul-14
6.920
29-Jun-14
1.440
17-May-14
-
8-May-14
1-May-14
0.649
8-May-14
30-Apr-14
22-Apr-14
P3R
-
22-Jun-14
6.920
26-May-14
AB1 L P1L P2L P3L P3L P4L P5L AB2 L
EXPANSION JOINT - N/A N/A - - N/A N/A -
CONCRETE BARRIER
Grouting
Prestressing
TOP SLAB (DECK) - - - - - - - -
WEB: - - - - - - - -
W1 16-Dec-14 16-Dec-14 16-Dec-14 16-Dec-14 - - - -
W2 16-Dec-14 16-Dec-14 16-Dec-14 16-Dec-14 - - - -
W3 16-Dec-14 16-Dec-14 16-Dec-14 16-Dec-14 - - - -
W4 16-Dec-14 16-Dec-14 16-Dec-14 16-Dec-14 - - - -
BOTTOM SLAB 7-Dec-14 7-Dec-14 7-Dec-14 7-Dec-14 - - - -
AB1 R P1R P2R P3R P3R P4R P5R AB2 R
EXPANSION JOINT - N/A N/A - - N/A N/A -
CONCRETE BARRIER
Grouting
Prestressing
TOP SLAB (DECK) 26-Nov-14 26-Nov-14 26-Nov-14 26-Nov-14 - - - -
WEB: - - - - - - - -
W1 10-Nov-14 10-Nov-14 10-Nov-14 10-Nov-14 - - - -
W2 10-Nov-14 10-Nov-14 10-Nov-14 10-Nov-14 - - - -
W3 10-Nov-14 10-Nov-14 10-Nov-14 10-Nov-14 - - - -
W4 10-Nov-14 10-Nov-14 10-Nov-14 10-Nov-14 - - - -
BOTTOM SLAB 28-Oct-14 28-Oct-14 28-Oct-14 28-Oct-14 - - - -
12/13/2014
12/7/2014
-
-
-
-
Dec-14 -
- -
-
-
ACTIVITY (RHS)SUPER-STRUCTURE (BRIDGE 1 - RHS)SUPER-STRUCTURE (BRIDGE 2 - RHS)
BRIDGE SUPER-STRUCTURE PROGRESS SCHEDULE (BOX GIRDER)
SUPER-STRUCTURE (BRIDGE 4 - LHS)SUPER-STRUCTURE (BRIDGE 3 - LHS)ACTIVITY (LHS)
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 12
9. MSE Walls Progress Schedule
PREVIOUS LA ST M ON T H THIS MONTH
DATE Elevation DATE
FROM TO FOUNDATION FROM TO FOUNDATION
22+702.653 22+760 2-Oct-14 22+718.936 22+810 17-Sep-14
3-Oct-14 18-Sep-14
22+760 22+825 30-Sep-14 22+810 22+893.032 9-Aug-14
1-Oct-14 10-Aug-14
22+825 22+840 13-Jul-14 22+893.032 22+976.294 13-Aug-14
14-Jul-14 14-Aug-14
22+840 22+880 6-Jul-14 22+976.294 23+040 18-Aug-14
13-Jul-14 19-Aug-14
22+880 22+908.387 10-Aug-14 23+040 23+088.046 26-Jul-14
11-Aug-14 27-Jul-14
22+908.387 22+969.478 3-Jul-14 23+088.046 23+130 21-Jul-14
5-Jul-14 22-Jul-14
22+969.478 23+000 4-Aug-14 23+130 23+191.774 7-Jul-14
5-Aug-14 10-Jul-14
23+000 23+025 20-Jul-14 23+191.774 23+270.800 26-Jun-14
21-Jul-14 27-Jun-14
23+025 23+070 17-Jul-14
18-Jul-14
23+070 23+140 30-Jun-14
1-Jul-14 DATE
23+140 23+164.573 16-Jun-14 FROM TO FOUNDATION
17-Jun-14 23+270.762 (L) 23+270.800 (R ) 26-Jun-14
23+164.573 23+237.536 23-Jun-14 27-Jun-14
24-Jun-14
23+237.536 23+270.762 17-Jun-14
18-Jun-14El. 22.00
El. 22.80
El. 22.00
El. 20.40
El. 22.80
MSE WALL MONTHLY SCHEDULE (FOUNDATION @ APPROACH 1)
El. 21.20
LOCATION (AB 1)
Elevation
Elevation
LOCATION (LHS)
El. 21.20
El. 22.00
El. 22.00
LOCATION (RHS)
El. 20.40
El. 22.00
DATE DATE
FROM TO FOUNDATION FROM TO FOUNDATION
23+508.239 23+520 15-Sep-14 23+508.239 (L) 23+508.197 (R ) 15-Sep-14
16-Sep-14 16-Sep-14
23+520 23+580.877 20-Aug-14
21-Aug-14
23+580.877 23+650 26-Aug-14 Elevation RHS DATE
27-Aug-14 FROM TO FOUNDATION
23+650 23+735 1-Sep-14 23+508.197 23+607.634 8-Sep-14
2-Sep-14 9-Sep-14
23+735 23+790 19-Sep-14 23+607.634 23+740 22-Sep-14
20-Sep-14 23-Sep-14
23+790 23+827.635 10-Oct-14 23+740 23+750 16-Oct-14
11-Oct-14 17-Oct-14
23+827.635 23+949.895 15-Oct-14 23+750 23+950.153 3-Nov-14
16-Oct-14 4-Nov-14
MSE WALL MONTHLY SCHEDULE (FOUNDATION @ APPROACH 2)
El. 23.30
El. 24.90
El. 24.10
El. 23.30
LOCATION (LHS) LOCATION (AB 2)Elevation
El. 24.10
Elevation
El. 23.30
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 13
PREVIOUSP R EVIOUS
M ON T HTHIS MONTH
22+825 22+840 22+880 22+908.387 22+969.478 22+991 23+084 23+164.573 23+237.536 23+270.762
31.600 - - - - - - - - - -30.800 - - - - - 22+975 - - - -30.000 - - - - - - - 13-Nov-14 13-Nov-14 13-Nov-1429.200 - - - - - 28-Dec-14 28-Dec-14 19-Oct-14 1-Oct-14 1-Oct-1428.400 - - - - 22+922 22-Dec-14 22-Dec-14 18-Oct-14 24-Sep-14 24-Sep-1427.600 - - - - - 16-Dec-14 16-Dec-14 20-Sep-14 18-Sep-14 18-Sep-1426.800 - - - - 9-Dec-14 9-Dec-14 18-Nov-14 9-Sep-14 15-Sep-14 15-Sep-1426.000 - - - - 4-Dec-14 4-Dec-14 20-Oct-14 4-Sep-14 28-Aug-14 28-Aug-1425.200 - - - - 5-Nov-14 5-Nov-14 16-Sep-14 26-Aug-14 19-Aug-14 19-Aug-1424.400 22+727 - 25-Nov-14 25-Nov-14 29-Oct-14 29-Oct-14 4-Sep-14 18-Aug-14 6-Aug-14 6-Aug-1423.600 - 10-Nov-14 10-Nov-14 10-Nov-14 21-Sep-14 17-Sep-14 27-Aug-14 13-Aug-14 24-Jul-14 24-Jul-1422.800 27-Dec-14 22-Sep-14 22-Sep-14 22-Sep-14 11-Sep-14 24-Aug-14 9-Aug-14 28-Jul-14 - 13-Jul-1422.000 27-Nov-14 3-Sep-14 3-Sep-14 3-Sep-14 28-Aug-14 - - - - -21.200 - 28-Aug-14 28-Aug-14 28-Aug-14 - - - - - -
20.400 - - - - - - - - - -
22+810 22+893.03222+976.294 23+035 23+088.04623+191.77423+270.80023+270.762 (L)23+270.8 (R )
32.400 - - - - - - - - -31.600 - - - - - 23+116 - - -30.800 - - - - - - - - -30.000 - - - 23+005 - 24-Dec-14 24-Dec-14 - -29.200 - - - - - 16-Nov-14 30-Sep-14 28-Sep-14 28-Sep-1428.400 - - 22+941 24-Dec-14 24-Dec-14 30-Sep-14 24-Sep-14 24-Sep-14 24-Sep-1427.600 - - - 22-Dec-14 22-Dec-14 27-Sep-14 18-Sep-14 19-Sep-14 19-Sep-1426.800 - - 31-Dec-14 16-Nov-14 16-Nov-14 13-Sep-14 13-Sep-14 11-Sep-14 11-Sep-1426.000 - - 1-Dec-14 20-Oct-14 20-Oct-14 2-Sep-14 31-Aug-14 28-Aug-14 28-Aug-1425.200 22+791 22+833 18-Nov-14 18-Oct-14 18-Oct-14 24-Aug-14 18-Aug-14 18-Aug-14 18-Aug-1424.400 - - 23-Oct-14 20-Sep-14 20-Sep-14 13-Aug-14 6-Aug-14 7-Aug-14 7-Aug-1423.600 20-Dec-14 20-Dec-14 25-Sep-14 8-Sep-14 8-Sep-14 9-Aug-14 24-Jul-14 24-Jul-14 24-Jul-1422.800 15-Dec-14 15-Dec-14 18-Sep-14 21-Aug-14 18-Aug-14 - 13-Jul-14 13-Jul-14 13-Jul-1422.000 27-Nov-14 23-Sep-14 26-Aug-14 - - - - - -21.200 - 4-Sep-14 - - - - - - -
20.400 - - - - - - - - -
RHS (AB 1), from Sta. 22+718.936 to Sta. 23+270.800
LHS (AB 1), from Sta. 22+702.653 to Sta. 23+270.762
MSE WALL MONTHLY SCHEDULE (PANELS FIXING @ APPROACH 1)
ELEV.
ELEV.
AB 1 Face
23+520 23+580 23+650 23+703 23+730 23+827 23+949
29.700 - - - - - - -28.900 - - 24-Dec-14 24-Dec-14 24-Dec-14 - -28.100 22-Dec-14 22-Dec-14 22-Dec-14 22-Dec-14 22-Dec-14 31-Dec-14 -27.300 6-Dec-14 6-Dec-14 6-Dec-14 6-Dec-14 6-Dec-14 27-Dec-14 -26.500 8-Nov-14 8-Nov-14 15-Nov-14 15-Nov-14 24-Nov-14 22-Dec-14 22-Dec-1425.700 29-Oct-14 29-Oct-14 1-Nov-14 1-Nov-14 16-Nov-14 20-Dec-14 20-Dec-1424.900 13-Oct-14 13-Oct-14 26-Sep-14 26-Sep-14 13-Nov-14 - -24.100 25-Sep-14 25-Sep-14 - - - - -23.300 - - - - - - -
23+508 (L) 23+508 (R ) 23+607 23+690 23+740 23+95028.900 - - - - - -28.100 22-Dec-14 22-Dec-14 28-Dec-13 28-Dec-13 - -27.300 16-Dec-14 6-Dec-14 10-Dec-13 24-Dec-13 - -26.500 26-Nov-14 26-Nov-14 8-Dec-14 29-Nov-14 29-Nov-14 -25.700 5-Nov-14 5-Nov-14 11-Nov-14 25-Nov-14 25-Nov-14 22-Dec-1424.900 16-Oct-14 16-Oct-14 15-Oct-14 15-Oct-14 21-Nov-14 -24.100 30-Sep-14 30-Sep-14 9-Oct-14 - - -23.300 - - - - - -
MSE WALL MONTHLY SCHEDULE (PANELS FIXING @ APPROACH 2)
ELEV.AB 2 Face
LHS (AB 2), from Sta. 23+508.239 to Sta. 23+949.895ELEV.
RHS (AB 2), from Sta. 23+508.197 to Sta. 23+950.153
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 14
10. Box Culverts Progress Schedule
Note: Precast RCBC were used for all 1 cell - 2.0m x 1.5m locations. PREVIOUS LAST MONTH THIS MONTH
Rebars Concrete Rebars Concrete Rebars Concrete
1 21+260 3 cells - 2.0 x 1.5 25.546 0 - - - - - - - -LHS Block 1 3 cells - 2.0 x 1.5 19.526 0 19-Oct-14 26-Oct-14 27-Oct-14 9-Nov-14 9-Nov-14 9-Nov-14 9-Nov-14 26-Nov-14RHS Block 2 3 cells - 2.0 x 1.5 14.473 0 19-Oct-14 4-Nov-14 4-Nov-14 15-Nov-14 15-Nov-14 15-Nov-14 15-Nov-14 26-Nov-14RHS Block 3 3 cells - 2.0 x 1.5 6.000 0 - - - - - - - -
2 21+485 1 cell - 2.0 x 1.5 39.750 0 - - - - - - - -Block 1a 1 cell - 2.0 x 1.5 3.000 0 - - - - - - - -Block 1b 1 cell - 2.0 x 1.5 17.290 0 1-Jul-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 1-Sep-14Block 2a 1 cell - 2.0 x 1.5 7.710 0 1-Jul-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 1-Sep-14Block 2b 1 cell - 2.0 x 1.5 10.000 0 19-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14Block 2C 1 cell - 2.0 x 1.5 11.730 0 - - - - - - - -
3 21+838 2 x 4 cells (8) - 2.0 x 1.5 52.210 0 - - - - - - - -Block 1a 1 x 4 cells - 2.0 x 1.5 5.000 0 21-Jul-14 4-Sep-14 5-Sep-14 13-Oct-14 13-Oct-14 13-Oct-14 13-Oct-14 26-Nov-14Block 1b 1 x 4 cells - 2.0 x 1.5 17.600 0 3-Jul-14 4-Sep-14 5-Sep-14 13-Oct-14 13-Oct-14 13-Oct-14 13-Oct-14 26-Nov-14Block 2 1 x 4 cells - 2.0 x 1.5 22.600 0 3-Jul-14 20-Aug-14 20-Aug-14 30-Oct-14 30-Oct-14 30-Oct-14 30-Oct-14 26-Nov-14Block 3 1 x 4 cells - 2.0 x 1.5 5.000 0 3-Jul-14 8-Dec-14 8-Dec-14 16-Dec-14 16-Dec-14 16-Dec-14 16-Dec-14 -
Block 3a 1 x 4 cells - 2.0 x 1.5 6.970 0 - - - - - - - -Block 4a 1 x 4 cells - 2.0 x 1.5 5.000 0 21-Jul-14 10-Sep-14 12-Sep-14 18-Oct-14 19-Oct-14 18-Oct-14 19-Oct-14 26-Nov-14Block 4b 1 x 4 cells - 2.0 x 1.5 17.600 0 3-Jul-14 10-Sep-14 12-Sep-14 18-Oct-14 19-Oct-14 18-Oct-14 19-Oct-14 26-Nov-14Block 5 1 x 4 cells - 2.0 x 1.5 22.600 0 3-Jul-14 23-Sep-14 24-Sep-14 24-Oct-14 25-Oct-14 24-Oct-14 25-Oct-14 26-Nov-14Block 6 1 x 4 cells - 2.0 x 1.5 5.000 0 3-Jul-14 21-Dec-14 21-Dec-14 27-Dec-14 27-Dec-14 27-Dec-14 27-Dec-14 -
Block 6a 1 x 4 cells - 2.0 x 1.5 6.970 0 - - - - - - - -4 21+972.4 11 x 4 cells (44) - 3.0 x 2.0 57.629 0 - - - - - - - -
Block 1 1 x 4 cells - 3.0 x 2.0 28.038 0 24-May-14 5-Jun-14 5-Jun-14 24-Jun-14 24-Jun-14 15-Jul-14 16-Jul-14 16-Aug-14Block 2 1 x 4 cells - 3.0 x 2.0 28.031 0 24-May-14 9-Jul-14 10-Jul-14 3-Aug-14 4-Aug-14 13-Aug-14 14-Aug-14 8-Sep-14Block 3 1 x 4 cells - 3.0 x 2.0 28.026 0 17-May-14 25-May-14 25-May-14 3-Jun-14 3-Jun-14 23-Jun-14 23-Jun-14 8-Sep-14Block 4 1 x 4 cells - 3.0 x 2.0 28.022 0 18-May-14 12-Jul-14 13-Jul-14 5-Aug-14 6-Aug-14 18-Aug-14 19-Aug-14 1-Oct-14Block 5 1 x 4 cells - 3.0 x 2.0 28.019 0 18-May-14 29-May-14 29-May-14 8-Jun-14 8-Jun-14 2-Jul-14 2-Jul-14 1-Oct-14Block 6 1 x 4 cells - 3.0 x 2.0 28.018 0 18-May-14 31-Jul-14 31-Jul-14 12-Aug-14 13-Aug-14 27-Aug-14 28-Aug-14 1-Oct-14Block 7 1 x 4 cells - 3.0 x 2.0 28.019 0 18-May-14 10-Jun-14 10-Jun-14 1-Jul-14 1-Jul-14 23-Jul-14 24-Jul-14 5-Oct-14Block 8 1 x 4 cells - 3.0 x 2.0 28.022 0 26-May-14 9-Aug-14 10-Aug-14 25-Aug-14 26-Aug-14 9-Sep-14 10-Sep-14 26-Nov-14Block 9 1 x 4 cells - 3.0 x 2.0 28.026 0 26-May-14 15-Jun-14 15-Jun-14 7-Jul-14 8-Jul-14 4-Aug-14 5-Aug-14 26-Nov-14
Block 10 1 x 4 cells - 3.0 x 2.0 28.031 0 28-May-14 17-Aug-14 18-Aug-14 14-Sep-14 14-Sep-14 24-Sep-14 25-Sep-14 26-Nov-14Block 11 1 x 4 cells - 3.0 x 2.0 28.038 0 28-May-14 19-Jun-14 19-Jun-14 20-Jul-14 20-Jul-14 2-Sep-14 3-Sep-14 25-Sep-14
F/P &
BLINDING
LHS
RHS
TYPE & DIMENSIONSTATIONBASE SLAB WALL
NO.TOP SLAB Bituminous Paint
(2 Coats)LENGTH (m) SKEW ( ° )
RHS
LHS
LHS
RHS
LHS
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 15
Rebars Concrete Rebars Concrete Rebars Concrete
Block 12 1 x 4 cells - 3.0 x 2.0 21.015 0 10-Aug-14 25-Aug-14 26-Aug-14 2-Sep-14 3-Sep-14 1-Oct-14 1-Oct-14 26-Nov-14Block 13 1 x 4 cells - 3.0 x 2.0 21.010 0 27-Jul-14 22-Sep-14 22-Sep-14 29-Sep-14 29-Sep-14 18-Oct-14 19-Oct-14 26-Nov-14Block 14 1 x 4 cells - 3.0 x 2.0 21.006 0 27-Jul-14 12-Oct-14 12-Oct-14 15-Oct-14 15-Oct-14 26-Oct-14 27-Oct-14 26-Nov-14Block 15 1 x 4 cells - 3.0 x 2.0 21.003 0 25-Jul-14 23-Aug-14 23-Aug-14 8-Sep-14 8-Sep-14 18-Sep-14 19-Sep-14 26-Nov-14Block 16 1 x 4 cells - 3.0 x 2.0 21.001 0 16-Jun-14 27-Jul-14 27-Jul-14 14-Aug-14 14-Aug-14 3-Sep-14 4-Sep-14 26-Nov-14Block 17 1 x 4 cells - 3.0 x 2.0 21.000 0 16-Jun-14 14-Sep-14 15-Sep-14 23-Sep-14 24-Sep-14 14-Oct-14 15-Oct-14 26-Nov-14Block 18 1 x 4 cells - 3.0 x 2.0 21.001 0 12-Jun-14 24-Oct-14 24-Oct-14 30-Oct-14 31-Oct-14 7-Nov-14 7-Nov-14 26-Nov-14Block 19 1 x 4 cells - 3.0 x 2.0 21.003 0 12-Jun-14 16-Oct-14 17-Oct-14 21-Oct-14 21-Oct-14 30-Oct-14 30-Oct-14 26-Nov-14Block 20 1 x 4 cells - 3.0 x 2.0 21.006 0 8-Jun-14 29-Sep-14 30-Sep-14 1-Oct-14 1-Oct-14 21-Oct-14 21-Oct-14 26-Nov-14Block 21 1 x 4 cells - 3.0 x 2.0 21.010 0 8-Jun-14 1-Sep-14 2-Sep-14 21-Sep-14 21-Sep-14 30-Sep-14 30-Sep-14 26-Nov-14Block 22 1 x 4 cells - 3.0 x 2.0 21.015 0 8-Jun-14 25-Jun-14 25-Jun-14 30-Jul-14 30-Jul-14 16-Sep-14 17-Sep-14 25-Sep-14Block 23 1 x 4 cells - 3.0 x 2.0 6.635 0 - - - - - - - -Block 24 1 x 4 cells - 3.0 x 2.0 6.782 0 - - - - - - - -Block 25 1 x 4 cells - 3.0 x 2.0 6.819 0 - - - - - - - -Block 26 1 x 4 cells - 3.0 x 2.0 7.217 0 - - - - - - - -Block 27 1 x 4 cells - 3.0 x 2.0 7.975 0 - - - - - - - -Block 28 1 x 4 cells - 3.0 x 2.0 8.571 0 - - - - - - - -Block 29 1 x 4 cells - 3.0 x 2.0 9.267 0 - - - - - - - -Block 30 1 x 4 cells - 3.0 x 2.0 9.949 0 - - - - - - - -Block 31 1 x 4 cells - 3.0 x 2.0 10.260 0 - - - - - - - -Block 32 1 x 4 cells - 3.0 x 2.0 10.262 0 - - - - - - - -Block 33 1 x 4 cells - 3.0 x 2.0 10.265 0 - - - - - - - -
5 22+655 2 x 4 cells (8) - 2.0 x 2.0 95.482 45° R - - - - - - - -(9 cells) 1 cell - 2.0 x 2.0 - - - - - - - -Block 1 1 x 4 cells - 2.0 x 2.0 9.675 45° R 24-Nov-14 29-Nov-14 29-Nov-14 4-Dec-14 4-Dec-14 10-Dec-14 10-Dec-14 -Block 2 1 x 4 cells - 2.0 x 2.0 32.711 45° R 30-Jun-14 6-Aug-14 7-Aug-14 1-Sep-14 2-Sep-14 1-Sep-14 2-Sep-14 13-Oct-14Block 3 1 x 4 cells - 2.0 x 2.0 32.711 45° R 24-Jun-14 21-Jul-14 21-Jul-14 17-Aug-14 18-Aug-14 17-Aug-14 18-Aug-14 13-Oct-14Block 4 1 x 4 cells - 2.0 x 2.0 11.850 45° R 11-Sep-14 12-Oct-14 13-Oct-14 22-Oct-14 22-Oct-14 22-Oct-14 22-Oct-14 -
Block 4a 1 x 4 cells - 2.0 x 2.0 13.130 45° R - - - - - - - -Block 5 1 x 4 cells - 2.0 x 2.0 19.035 45° R 24-Nov-14 4-Dec-14 4-Dec-14 8-Dec-14 8-Dec-14 18-Dec-14 18-Dec-14 -Block 6 1 x 4 cells - 2.0 x 2.0 32.711 45° R 29-Jun-14 27-Jul-14 28-Jul-14 13-Sep-14 14-Sep-14 13-Sep-14 14-Sep-14 13-Oct-14Block 7 1 x 4 cells - 2.0 x 2.0 32.711 45° R 24-Jun-14 28-Aug-14 28-Aug-14 24-Sep-14 26-Sep-14 24-Sep-14 26-Sep-14 13-Oct-14Block 8 1 x 4 cells - 2.0 x 2.0 10.95 45° R - - - - - - - -Block 9 1 cell - 2.0 x 2.0 25.03 45° R 24-Nov-14 13-Dec-14 13-Dec-14 18-Dec-14 18-Dec-14 24-Dec-14 24-Dec-14 -
Block 10 1 cell - 2.0 x 2.0 32.711 45° R 28-Jun-14 20-Aug-14 23-Aug-14 2-Oct-14 3-Oct-14 2-Oct-14 3-Oct-14 13-Oct-14Block 11 1 cell - 2.0 x 2.0 32.711 45° R 29-Jun-14 3-Aug-14 4-Aug-14 2-Oct-14 3-Oct-14 2-Oct-14 3-Oct-14 13-Oct-14Block 12 1 cell - 2.0 x 2.0 4.960 45° R - - - - - - - -
RHS
RHS
LHS
RHS
LHS
RHS
LHS
RHS
NO. STATION TYPE & DIMENSION LENGTH (m) SKEW ( ° )F/P &
BLINDING
BASE SLAB WALL TOP SLAB Bituminous Paint
(2 Coats)
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 16
Rebars Concrete Rebars Concrete Rebars Concrete
6 23+492 1 x 4 cells (4) - 3.0 x 2.0 79.065 15° R - - - - - - - -(5 cells) 1 cell - 3.0 x 2.0 - - - - - - - -Block 1 1 x 4 cells - 3.0 x 2.0 6.457 15° R - - - - - - - -Block 2 1 x 4 cells - 3.0 x 2.0 31.546 15° R 24-Jun-14 9-Jul-14 9-Jul-14 30-Jul-14 30-Jul-14 16-Aug-14 17-Aug-14 6-Sep-14Block 3 1 x 4 cells - 3.0 x 2.0 31.546 15° R 24-Jun-14 14-Jul-14 15-Jul-14 3-Aug-14 3-Aug-14 21-Aug-14 21-Aug-14 6-Sep-14Block 4 1 x 4 cells - 3.0 x 2.0 7.982 15° R 9/172014 23-Sep-14 24-Sep-14 28-Sep-14 28-Sep-14 1-Oct-14 2-Oct-14 18-Oct-14Block 5 1 cell - 3.0 x 2.0 7.039 15° R - - - - - - - -Block 6 1 cell - 3.0 x 2.0 31.546 15° R 24-Jun-14 5-Aug-14 5-Aug-14 9 & 20/8/2014 9 & 23/8/2014 28-Aug-14 28-Aug-14 4-7/9/2014Block 7 1 cell - 3.0 x 2.0 31.546 15° R 24-Jun-14 6-Aug-14 6-Aug-14 11 & 25/8/2014 11 & 26/8/2014 31-Aug-14 1-Sep-14 4-7/9/2014Block 8 1 cell - 3.0 x 2.0 5.525 15° R 17-Sep-14 28-Sep-14 28-Sep-14 2-Oct-14 2-Oct-14 11-Oct-14 11-Oct-14 18-Oct-14
11-Oct-14 11-Oct-14 - - -7 23+756.5 1 cell - 2.0 x 1.5 67.550 0 - - - - - - - -
Block 1 1 cell - 2.0 x 1.5 12.090 0 - - - - - - - -Block 2 1 cell - 2.0 x 1.5 20.180 0 12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14
Block 3a 1 cell - 2.0 x 1.5 14.430 0 12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 3b 1 cell - 2.0 x 1.5 8.700 0 11-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 28-Aug-14Block 4 1 cell - 2.0 x 1.5 12.090 0 - - - - - - - -
8 23+997 1 cell - 2.0 x 1.5 70.268 0 - - - - - - - -Block 1 1 cell - 2.0 x 1.5 16.128 0 - - - - - - - -
Block 2a 1 cell - 2.0 x 1.5 4.933 0 - - - - - - - -Block 2b 1 cell - 2.0 x 1.5 13.860 0 8-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 3a 1 cell - 2.0 x 1.5 16.300 0 8-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 3b 1 cell - 2.0 x 1.5 4.942 0 10-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 31-Aug-14Block 4a 1 cell - 2.0 x 1.5 7.848 0 10-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 31-Aug-14Block 4b 1 cell - 2.0 x 1.5 6.197 0
9 24+235 1 cell - 2.0 x 1.5 59.106 0 - - - - - - - -Block 1a 1 cell - 2.0 x 1.5 15.566 0 - - - - - - - -Block 1b 1 cell - 2.0 x 1.5 15.000 0 12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 2a 1 cell - 2.0 x 1.5 8.900 0 12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 2b 1 cell - 2.0 x 1.5 15.600 0 10-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 31-Aug-14Block 2c 1 cell - 2.0 x 1.5 4.020 0 - - - - - - - -
10 24+570 1 cell - 2.0 x 1.5 51.953 0 - - - - - - - -LHS Block 1 1 cell - 2.0 x 1.5 25.846 0 14-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 31-Aug-14
Block 2a 1 cell - 2.0 x 1.5 13.500 0 14-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 31-Aug-14Block 2b 1 cell - 2.0 x 1.5 12.587 0 24-Nov-14 1-Dec-14 1-Dec-14 1-Dec-14 1-Dec-14 1-Dec-14 1-Dec-14 6-Dec-14
RHS
LHS
LHS
LHS
RHS
RHS
LHS
LHS
RHS
RHS
RHS
BASE SLABNO. STATION TYPE & DIMENSION LENGTH (m) SKEW ( ° )
F/P &
BLINDING
WALL TOP SLAB Bituminous Paint
(2 Coats)
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 17
Rebars Concrete Rebars Concrete Rebars Concrete
1 21+300 2 cells - 4.0 x 3.0 37.700 0 - - - - - - - -LHS Block 1 2 cells - 4.0 x 3.0 15.780 0 19-Oct-14 26-Oct-14 27-Oct-14 1-Nov-14 2-Nov-14 12-Nov-14 2-Nov-14 26-Nov-14RHS Block 2 2 cells - 4.0 x 3.0 21.900 0 - - - - - - - -
2 24+600 2 cells - 4.0 x 3.0 44.051 0 - - - - - - - -LHS Block 1 2 cells - 4.0 x 3.0 21.620 0 22-Oct-14 3-Nov-14 3-Nov-14 11-Nov-14 12-Nov-14 19-Nov-14 20-Nov-14 -RHS Block 2 2 cells - 4.0 x 3.0 22.411 0 - - - - - - - -
PREVIOUSPREVIOUS
MONTHTHIS MONTH
Rebars Concrete Rebars Concrete Rebars Concrete
1 23+284.40, SOL-1 1 cells - 4.0 x 4.0 - 0 - - - - - - - -LHS Block 1 1 cells - 4.0 x 4.0 - 0 - - - - - - - -RHS Block 2 1 cells - 4.0 x 4.0 - 0 - - - - - - - -
2 24+360, SOL-1 1 cells - 4.0 x 4.0 59.614 0 - - - - - - - -LHS Block 1 1 cells - 4.0 x 4.0 9.000 0 - - - - - - - -LHS Block 2 1 cells - 4.0 x 4.0 20.777 0 15-Sep-14 1-Oct-14 1-Oct-14 19-Oct-14 19-Oct-14 30-Oct-14 31-Oct-14 -RHS Block 3 1 cells - 4.0 x 4.0 22.777 0 9-Dec-14 15-Dec-14 15-Dec-14 21-Dec-14 21-Dec-14 30-Dec-14 30-Dec-14 -RHS Block 4 1 cells - 4.0 x 4.0 7.000 0 - - - - - - - -
3 0+050, SOL-3 1 cells - 4.0 x 4.0 83.223 0 - - - - - - - -LHS Block 1 1 cells - 4.0 x 4.0 17.721 0 - - - - - - - -LHS Block 2 1 cells - 4.0 x 4.0 17.721 0 - - - - - - - -LHS Block 3 1 cells - 4.0 x 4.0 17.721 0 - - - - - - - -RHS Block 4 1 cells - 4.0 x 4.0 30.000 0 25-Nov-14 2-Dec-14 2-Dec-14 14-Dec-14 14-Dec-14 25-Dec-14 25-Dec-14 -
NO.
VEHICLE UNDERPASS PROGRESS SCHEDULE (BARREL)
TOP SLAB Bitu. Paint (2
Coats)
TOP SLAB Bitu. Paint (2
Coats)STATION
STATIONBASE SLAB WALL
F/P &
BLINDING
BASE SLAB WALLNO.
LENGTH (m) SKEW ( ° )F/P &
BLINDINGTYPE & DIMENSION
PEDESTRIAN UNDERPASS PROGRESS SCHEDULE (BARREL)
TYPE & DIMENSION LENGTH (m) SKEW ( ° )
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 18
11. Progress Status of Utility Crossing Ducts
DRAWING NO. OFSETOUT/EX
CV/BED
NO. DIA TYPE WAYS STAGE LAYING CONCRETE BACKFILL
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT 24-Sep-14 24-Sep-14 18-Oct-14 UTL-LAY- 104 UTL-CON-131A
MIDDLE
RIGHT
LEFT 15-May-14 15-May-14 18-May-14 12-Jun-14 UTL-LAY- 81 UTL-CON- 65 UTL-BF- 01
MIDDLE 11-Jun-14 11-Jun-14 12-Jun-14 10-Jul-14 UTL-LAY- 104 UTL-CON- 83 UTL-BF- 20
RIGHT
LEFT 19-May-14 19-May-14 20-May-14 4-Jun-14 UTL-LAY- 87 UTL-CON- 66 UTL-BF- 03
MIDDLE 14-Jun-14 14/06/014 14-Jun-14 21-Jun-14 UTL-LAY- 108 UTL-CON- 84 UTL-BF- 21
RIGHT
LEFT 19-May-14 19-May-14 20-May-14 31-May-14 UTL-LAY- 85 UTL-CON- 63 UTL-BF- 02
MIDDLE 15-Jun-14 15-Jun-14 15-Jun-14 UTL-LAY- 107 UTL-CON- 85
RIGHT
LEFT 20-May-14 20-May-14 25-May-14 4-Jun-14 UTL-LAY- 86 UTL-CON- 64 UTL-BF- 05
MIDDLE 15-Jun-14 15-Jun-14 15-Jun-14 8-Jul-14 UTL-LAY- 109 UTL-CON- 87 UTL-BF- 23
RIGHT
LEFT 25-May-14 25-May-14 25-May-14 4-Jun-14 UTL-LAY- 90 UTL-CON-68 UTL-BF- 07
MIDDLE 16-Jun-14 16-Jun-14 17-Jun-14 10-Jul-14 UTL-LAY- 111 UTL-CON- 88 UTL-BF- 28
RIGHT
LEFT 17-Jun-14 17-Jun-14 18-Jun-14 9-Jul-14 UTL-LAY- 112 UTL-CON- 89 UTL-BF- 33
MIDDLE 20-Jul-14 20-Jul-14 21-Jul-14 27-Jul-14 UTL-LAY- 131 UTL-CON- 106 UTL-BF-44
RIGHT
LEFT 19-Jun-14 19-Jun-14 19-Jun-14 6-Jul-14 UTL-LAY- 114 UTL-CON- 92 UTL-BF- 31
MIDDLE 20-Jul-14 20-Jul-14 21-Jul-14 17-Jul-14 UTL-LAY- 132 UTL-CON- 107 UTL-BF-46
RIGHT
LEFT 19-Jun-14 19-Jun-14 19-Jun-14 5-Jul-14 UTL-LAY- 113 UTL-CON- 91 UTL-BF- 30
MIDDLE 20-Jul-14 20-Jul-14 21-Jul-14 17-Jul-14 UTL-LAY- 133 UTL-CON- 108 UTL-BF-45
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT 26-May-14 26-May-14 26-May-14 8-Jun-14 UTL-LAY- 88 UTL-CON- 69 UTL-BF- 08
MIDDLE 11-Jun-14 11-Jun-14 11-Jun-14 22-Jul-14 UTL-LAY-106 UTL-CON- 81 UTL-BF-26
RIGHT
LEFT
MIDDLE
RIGHT
LEFT 16-Jun-14 16-Jun-14 16-Jun-14 20-Jul-14 UTL-LAY- 102 UTL-CON- UTL-BF-19
MIDDLE 8-Jul-14 8-Jul-14 9-Jul-14 27-Jul-14 UTL-LAY- 125 UTL-CON-99 UTL-BF-42
RIGHT
LEFT 25-May-14 25-May-14 26-May-14 14-Jun-14 UTL-LAY- 91 UTL-CON- 71 UTL-BF- 06
MIDDLE 11/06/201 11-Jun-14 11-Jun-14 23-Jun-14 UTL-LAY- 105 UTL-CON- 82 UTL-BF- 25
RIGHT
LEFT 27-May-14 27-May-14 27-May-14 17-Jun-14 UTL-LAY- 92 UTL-CON- 72 UTL-BF- 09
MIDDLE
RIGHT
LEFT 28-May-14 28-May-14 28-May-14 17-Jun-14 UTL-LAY- 93 UTL-CON- 70 UTL-BF- 10
MIDDLE
RIGHT
LEFT 29-May-14 29-May-14 29-May-14 17-Jun-14 UTL-LAY- 94 UTL-CON- 73 UTL-BF- 11
MIDDLE 30-Jul-14 12-Aug-14 30-Jul-14 26-Aug-14 UTL-LAY-142 UTL-CON- 115 UTL-BF-48
RIGHT
LEFT 29-May-14 2-Jun-14 2-Jun-14 17-Jun-14 UTL-LAY- 95 UTL-CON- 75 UTL-BF- 15
MIDDLE 14-Jul-14 14-Jul-14 14-Jul-14 20-Aug-14 UTL-LAY- 124 UTL-CON- 102 UTL-BF- 36
RIGHT
LEFT 29-May-14 2-Jun-14 2-Jun-14 17-Jun-14 UTL-LAY-97 UTL-CON- 76 UTL-BF- 13
MIDDLE 14-Jul-14 14-Jul-14 15-Jul-14 20-Aug-14 UTL-LAY- 127 UTL-CON- 101 UTL-BF- 38
RIGHT
LEFT
MIDDLE 10-Aug-14 11-Aug-14 11-Aug-14 26-Aug-14 UTL-LAY-149AUTL-CON- 120A UTL-BF- 58
RIGHT 27-Oct-14 27-Oct-14 27-Oct-14 UTL-LAY- 206 UTL-CON- 153
LEFT 29-May-14 2-Jun-14 3-Jun-14 19-Jun-14 UTL-LAY- 98 UTL-CON- 77 UTL-BF- 14
MIDDLE 6-Aug-14 6-Aug-14 9-Aug-14 13-Aug-14 UTL-LAY- 134-R1UTL-CON- 109A UTL-BF- 53
RIGHT
3
2
3
3
3
2
2
2
3
1
1
3
4
3
4
3
1
3
23+820
23+900
23+980
200
200
200
150
300
900
UPVC
UPVC
UPVC
UPVC
UPVC
UPVC
UPVC
UPVC
UPVC
150
150
150
RC
UPVC
UPVC
UPVC
UPVC
UPVC
RC
UPVC24 CCC/FQI/EL/11
19 CCC/FQI/EL/13
CCC/FQI/EL/0820
CCC/FQI/EL/0921
23+060
23+210
23+240
23+560
CCC/FQI/EL/1022
CCC/FQI/WA/0323
150
150
150
150
600
BACKFILLI
NG
RFI REF.
S.NO. CHAINAGE
PIPE
2
2UPVC
INSTALLAT
ION
CONCRET
E
1CCC/FQI/IR/06
SERVICE ROAD-30+030 200 UPVC
2 CCC/FQR/IR/11 SOL-2 0+150 300
2
3
2
4CCC/FQR/WA/05 SR-
10+600 300 UPVC
5 CCC/FQI/EL/01
9 CCC/FQI/EL/03 21+880
CCC/FQI/EL/04 22+260
11
2
300 UPVC
7 CCC/FQI/EL/02 21+660
10
150
6 CCC/FQI/IR/01 21+460
UPVC
8 CCC/FQI/IR/02 21+780 300
CCC/FQI/EL/05 22+510 150
14CCC/FQI/IR/05
JUNCTION CROSSING22+587 LHS
12 CCC/FQI/IR/03
21+360 150 UPVC
23A CCC/FQI/SL/11 23+960 UPVC
18 CCC/FQI/EL/07
15 CCC/FQI/EL/06
22+520
13CCC/FQI/IR/04
JUNCTION CROSSING22+520 LHS
CCC/FQI/WA/01
CCC/FQI/WA/02
JUNCTION16
17
23+008 LHS
23+020
22+760
150
23 CCC/FQR/IR/10 SOL-3 0+300 200 UPVC
CCC/FQI/SL/01 21+160 150 UPVC 44A
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 19
DRAWING NO. OFSETOUT/EX
CV/BED
NO. DIA TYPE WAYS STAGE LAYING CONCRETE BACKFILL
LEFT
MIDDLE
RIGHT
LEFT 3-Jun-14 4-Jun-14 4-Jun-14 23-Jun-14 UTL-LAY- 99 UTL-CON- 78 UTL-BF- 16
MIDDLE 11-Aug-14 11-Aug-14 19-Aug-14 26-Aug-14 UTL-LAY-140 R1UTL-CON-114 UTL-BF- 52
RIGHT
LEFT 4-Jun-14 5-Jun-14 10-Jun-14 23/06/201 UTL-LAY- 100 UTL-CON- 79 UTL-BF- 17
MIDDLE 23-Jul-14 24-Jul-14 19-Aug-14 26-Aug-14 UTL-LAY-139 UTL-CON-112-R1UTL-BF- 47
RIGHT
LEFT 9-Jun-14 9-Jun-14 10-Jun-14 23-Jun-14 UTL-LAY- 101 UTL-CON- 80 UTL-BF- 18
MIDDLE 6-Aug-14 6-Aug-14 6-Aug-14 26-Aug-14 UTL-LAY-138-R1UTL-CON-111-B UTL-BF- 56
RIGHT
LEFT 5-Jul-14 5-Jul-14 5-Jul-14 19-Aug-14 UTL-LAY- 123 UTL-CON- 94 UTL-BF- 39R1
MIDDLE 4-Des-14 14-Dec-14 14-Dec-14 UTL-LAY- 222 UTL-CON- 97 R1..
RIGHT .
LEFT 16-Jul-14 16-Jul-14 17-Jul-14 6-Nov-14 UTL-LAY- 130 UTL-CON- 105 UTL-BF- 41R1
MIDDLE 27-Oct-14 27-Oct-14 27-Oct-14 27-Oct-14 UTL-LAY-190R1UTL-CON- 148 UTL-BF- 72
RIGHT
LEFT 14-Sep-14 14-Sep-14 14-Oct-14 20-Oct-14 UTL-LAY- 166 UTL-CON-125 UTL-BF-81
MIDDLE 27-Oct-14 30-Oct-14 27-Oct-14 10-Dec-14 UTL-LAY- 205 UTL-CON- 150 UTL-BF-99
RIGHT
LEFT 16-Sep-14 20-Sep-14 UTL-LAY- 173
MIDDLE 27-Oct-14 27-Oct-14 27-Oct-14 9-Nov-14 UTL-LAY- 203 UTL-CON- 149 UTL-BF-100
RIGHT
LEFT 3-Nov-14 10-Nov-14 11-Nov-14 7-Dec-14 UTL-LAY- 211 UTL-CON- 155 UTL-BF-106
MIDDLE
RIGHT
LEFT 21-May-14 21-May-14 21-May-14 4-Jun-14 UTL-LAY- 89 UTL-CON- 67 UTL-BF- 04
MIDDLE 16-Jun-14 16-Jun-14 18-Jun-14 10-Jul-14 UTL-LAY- 110 UTL-CON- 90 UTL-BF- 29
RIGHT
LEFT 29-May-14 31-May-14 31-May-14 17-Jun-14 UTL-LAY- 96 UTL-CON- 74 UTL-BF- 12
MIDDLE 10-Jul-14 10-Jul-14 13-Aug-14 26-Aug-14 UTL-LAY- 120 R1UTL-CON- 95 UTL-BF- 49
RIGHT
LEFT 21-Jul-14 4-Aug-14 5-Aug-14 UTL-LAY-137-R1UTL-CON- 118
MIDDLE 8-Aug-14 9-Aug-14 9-Aug-14 22-Sep-14 UTL-LAY-148AUTL-CON- 117 UTL-BF- 57
RIGHT 16-Sep-14 16-Sep-14 16-Sep-14 UTL-LAY-172 UTL-CON- 126
LEFT 7-Jul-14 8-Jul-14 8-Jul-14 UTL-LAY-103AUTL-CON-98
MIDDLE 12-Aug-14 13-Aug-14 14-Aug-14 15-Aug-14 UTL-LAY-150 UTL-CON-122A UTL-BF- 37A
RIGHT
LEFT
MIDDLE
RIGHT
LEFT 9-Jul-14 9-Jul-14 9-Jul-14 UTL-LAY- 116 UTL-CON-100
MIDDLE 12-Aug-14 13-Aug-14 14-Aug-14 25-Sep-14 UTL-LAY-151 UTL-CON-121 UTL-BF-81
RIGHT 12-Oct-14 13-Oct-14 12-Oct-14 8-Nov-14 UTL-LAY-187 UTL-CON-137 UTL-BF-99
LEFT 2-Jul-14 3-Jul-14 3-Jul-14 UTL-LAY-122 UTL-CON-93R1
MIDDLE 10-Jul-14 10-Jul-14 14-Jul-14 UTL-LAY-126 UTL-CON-103
RIGHT 22-Jul-14 22-Jul-14 23-Jul-14 20-Aug-14 UTL-LAY-136 UTL-CON-110 UTL-BF- 50
LEFT 30-Aug-14 31-Aug-14 14-Sep-14 30-Sep-14 UTL-LAY-158 UTL-CON-96 UTL-BF-64
MIDDLE 27-Nov-14 14-Dec-14 23-Dec-14 UTL-EXC-63 UTL-CON-162 UTL-BF-115
RIGHT 24-Nov-14 SL-CON-54
LEFT 9/7/2014 9/7/2014 14-Oct-14 27-Oct-14 UTL-LAY-162 UTL-CON-124 UTL-BF-69
MIDDLE 14-Sep-14 27-Oct-14 4-Nov-14 UTL-LAY-162R1 UTL-BF-94
RIGHT 9/16/2014 28-Oct-14 17-Nov-14 17-Nov-14 UTL-LAY-207 UTL-CON-152 UTL-BF-92
LEFT 16-Sep-14 17-Sep-14 30-Sep-14 8-Nov-14 UTL-LAY-174 UTL-CON-127 UTL-BF-83R1
MIDDLE 14-Oct-14 18-Oct-14 14-Oct-14 UTL-LAY-188 UTL-CON-138
RIGHT 27-Oct-14 27-Oct-14 27-Oct-14 UTL-LAY-204 UTL-CON-151
LEFT 2-Oct-14 2-Oct-14 2-Oct-14 UTL-LAY-184 UTL-CON-135
MIDDLE
RIGHT
LEFT 2-Oct-14 2-Oct-14 2-Oct-14 UTL-LAY-164 R1UTL-CON-134
MIDDLE
RIGHT
LEFT 2-Oct-14 2-Oct-14 2-Oct-14 UTL-LAY-185 UTL-CON-136
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT 4-Nov-14 4-Nov-14 UTL-EXC-55 UTL-CON-156 not done
MIDDLE
RIGHT
150CCC/FQI/SL/01
21+620 450
24+220
24+340
24+520
UPVC
UPVC
42
43
44
450
CO
NC
PIP
E
45 CCC/FQI/SD/09
47
CCC/FQI/SD 23+400 60046
CO
NC
PIP
E
4
2
3
2
3
2
UPVC150
24+000
24+020
24+120
23+740 150
UPVC
UPVC
UPVC
150
UPVC
37 CCC/FQI/OMANTEL.1
33
CCC/FQI/OMANTEL.2 100
150
38 0+140 SOL-3
22+810 100
100
21+870
23+580
24+720
150
100
100
15040 22+990
UPVC300
300
RC
UPVC
UPVC
UPVC
26
34
35
36
CCC/FQI/EL/14
CCC/FQI/IR/08
CCC/FQI/EL/15
CCC/FQI/EL/16
CCC/FQI/IR/09
CCC/FQI/EL/17
CCC/FQI/NAW.2
CCC/FQI/NAW.3
CCC/FQI/NAW.4
CCC/FQI/EL/1227
CCC/FQI/WA/0425
24+820
24+960
25+160
28
29
30
31
32
UPVC 2
CCC/FQI/SD/07
CCC/FQI/SD/08
UPVC
UPVC
UPVC
CCC/FQI/EL/21 23+965 200 UPVC 2
24+850
450
CO
NC
PIP
EC
ON
C P
IPE
CCC/FQI/SL/04
UPVC 2-4WAY
UPVC 4
39 CCC/FQI/SL/03 Rev A 22+820 150 UPVC
41 CCC/FQI/SL/02 4
21+500
21+560
42 CCC/FQI/EL/19
S.NO. CHAINAGE
PIPEINSTALLAT
ION
CONCRET
E
BACKFILLI
NG
RFI REF.
4
2
4
22+080
2
3
1
2
600
300
150
150
3
3
CCC/FQI/IR/07
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 20
DRAWING NO. OFSETOUT/EX
CV/BED
NO. DIA TYPE WAYS STAGE LAYING CONCRETE BACKFILL
LEFT 9/4/2014 9/28/2014 UTL-LAY-159-BUTL-CON-132
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT 16-Sep-14 17-Sep-14 30-Sep-14 18-Oct-14 UTL-LAY-167 UTL-CON-128 UTL-BF-78
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
4UPVC
4
2A CCC/FQI/Omantel/02
UPVC
6
CCC/FQI/SL/14
CCC/FQI/SL/15
CCC/FQI/SL/16
CCC/FQI/SL/17
0+415 1503
2
4
CCC/FQI/SL/13 UPVC 2
0+140 150
1 CCC/FQI/Omantel/02
0+130 150
0+138.348 110
5
UPVC 2
UPVC 6
SOL-3 Ch.
0+300150 UPVC 2
0+054.459 150
UPVC 2 SOL-3 Ch.
0+427.623150
S.NO. CHAINAGE
PIPEINSTALLAT
ION
CONCRET
E
BACKFILLI
NG
RFI REF.
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 21
12. Project Progress Strip Chart
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 22
SUBGRADE IN CUT COMPLETED 21+150-21+500 As of DEC 2014BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmSubgrade Layr 9Layr 8Layr 7Layr 6Layr 5Layr 4Layr 3Layr 2
EMBANKMENT Layer 1 BED PREPRATION
OGL SURVEY
21+0
00
21+0
20
21+0
40
21+0
60
21+0
80
21+1
00
21+1
20
21+1
40
21+1
60
21+1
80
21+2
00
21+2
20
21+2
40
21+2
60
21+2
80
21+3
00
21+3
20
21+3
40
21+3
60
21+3
80
21+4
00
21+4
20
21+4
40
21+4
60
21+4
80
21+5
00
OGL SURVEY
BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer 4layer 5layer 6layer 7layer 8layer 9Subgrade
GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm
21+500-22+000BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmsub gradeLayer 9Layer 8Layer 7Layer 6Layer 5Layer 4Layer 3Layer 2
EMBANKMENT Layer 1BED PREPRATION OGL SURVEY
21+5
00
21+5
20
21+5
40
21+5
60
21+5
80
21+6
00
21+6
20
21+6
40
21+6
60
21+6
80
21+7
00
21+7
20
21+7
40
21+7
60
21+7
80
21+8
00
21+8
20
21+8
40
21+8
60
21+8
80
21+9
00
21+9
20
21+9
40
21+9
60
21+9
80
22+0
00
OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3 3rd rock soillayer 4 top of embankmentlayer 5layer 6layer 7layer 8layer 9sub grade
GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm
RH
SLH
SR
HS
LHS
3 cell & U.pass
3 cell & U.pass
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 23
COMPLETED 22+000-22+500 As of DEC 2014BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cm GSBLayr 10 SUB GRADE LAYER Layr 9Layr 8Layr 7Layr 6 Subgrdae Layr 5 embank 2Layr 4 embankLayr 3 3rd rock soilLayr 2EMBANKMENT Layer 1 BED PREPRATION OGL SURVEY
22+0
00
22+0
20
22+0
40
22+0
60
22+0
80
22+1
00
22+1
20
22+1
40
22+1
60
22+1
80
22+2
00
22+2
20
22+2
40
22+2
60
22+2
80
22+3
00
22+3
20
22+3
40
22+3
60
22+3
80
22+4
00
22+4
20
22+4
40
22+4
60
22+4
80
22+5
00
OGL SURVEY BED PREPRATION EMBANKMENT Layer 1 1st rock soillayer 2 2nd rock soillayer 3 3rd rock soil 3rd rock soillayer 4 4th rock soillayer 5 5th rock soillayer 6 6th rock soillayer 7 embankmen 1layer 8 embankment 2 layer 9layer 10 SUBGRADEGSB 20 cm GSBABC 1 ST 15 cm abc 1st ABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm
22+500-23+000BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayer 10 10 th rock soilLayer 9Layer 8Layer 7 7th layer roock soil 7th layer of rock soil Layer 6 layer 15Layer 5Layer 4 4th rock soilLayer 3Layer 2 2nd rock soilEMBANKMENT Layer 1BED PREPRATION OGL SURVEY
22+5
00
22+5
20
22+5
40
22+5
60
22+5
80
22+6
00
22+6
20
22+6
40
22+6
60
22+6
80
22+7
00
22+7
20
22+7
40
22+7
60
22+7
80
22+8
00
22+8
20
22+8
40
22+8
60
22+8
80
22+9
00
22+9
20
22+9
40
22+9
60
22+9
80
23+0
00
OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2 2nd rock soillayer 3layer 4 4th rock soillayer 5layer 6 layer 15layer 7 7th layer roock soil 7th layer of rock soil layer 8layer 9 10 rock soillayer 10 SUB G emabnkment layers GSB 20 cm GSBABC 1 ST 15 cm ABC 1stABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm
LHS
RH
SLH
SR
HS
9 cell
9 cell
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 24
COMPLETED 23+000-23+500 As of DEC 2014BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayr 10Layr 9Layr 8Layr 7 7th layer of rock soil Layr 6 layer 15 of embankmentLayr 5 3th layer of rock soil Layr 4 Embankment layer no 28Layr 3Layr 2EMBANKMENT Layer 1 BED PREPRATION OGL SURVEY
23+0
00
23+0
20
23+0
40
23+0
60
23+0
80
23+1
00
23+1
20
23+1
40
23+1
60
23+1
80
23+2
00
23+2
20
23+2
40
23+2
60
23+2
80
23+3
00
23+3
20
23+3
40
23+3
60
23+3
80
23+4
00
23+4
20
23+4
40
23+4
60
23+4
80
23+5
00
OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer 4 Embankment layer no 28layer 5 3th layer of rock soil layer 6 layer 15 of embankmentlayer 7 7th layer of rock soil layer 8layer 9 10th layer of rock soil layer 10 top embankment GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm
23+500-24+000BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayer 10 Rock soil 15 th layer sub grade Layer 9Layer 8 Rock siol 11th layerLayer 7Layer 6Layer 5 5th rock soilLayer 4 4th rock soil Layer 3Layer 2 2nd rock soilEMBANKMENT Layer 1BED PREPRATION OGL SURVEY
23+5
00
23+5
20
23+5
40
23+5
60
23+5
80
23+6
00
23+6
20
23+6
40
23+6
60
23+6
80
23+7
00
23+7
20
23+7
40
23+7
60
23+7
80
23+8
00
23+8
20
23+8
40
23+8
60
23+8
80
23+9
00
23+9
20
23+9
40
23+9
60
23+9
80
24+0
00
OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2 2nd rock soillayer 3layer 4 4th rock soil layer 5 5th layer rock soillayer 6layer 7layer 8 Rock siol 11th layerlayer 9 top embankmentlayer 10 Rock soil 15 th layer
GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm
LHS
RH
SLH
SR
HS
Bridge
Bridge
Bridge
Bridge
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 25
COMPLETED 24+000-24+500 As of DEC 2014
BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayer 10 top sub grade Layer 9Layer 8Layer 7Layer 6Layer 5Layer 4Layer 3Layer 2 2nd rock soilEMBANKMENT Layer 1 1st rockBED PREPRATION OGL SURVEY
24+0
00
24+0
20
24+0
40
24+0
60
24+0
80
24+1
00
24+1
20
24+1
40
24+1
60
24+1
80
24+2
00
24+2
20
24+2
40
24+2
60
24+2
80
24+3
00
24+3
20
24+3
40
24+3
60
24+3
80
24+4
00
24+4
20
24+4
40
24+4
60
24+4
80
24+5
00
OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2 2nd rock soillayer 3layer 4layer 5layer 6layer 7layer 8layer 9layer 10 top embankmentGSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm
24+500-25+000
BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayer 10Layer 9Layer 8Layer 7Layer 6Layer 5Layer 4Layer 3Layer 2
EMBANKMENT Layer 1BED PREPRATION OGL SURVEY
24+5
00
24+5
20
24+5
40
24+5
60
24+5
80
24+6
00
24+6
20
24+6
40
24+6
60
24+6
80
24+7
00
24+7
20
24+7
40
24+7
60
24+7
80
24+8
00
24+8
20
24+8
40
24+8
60
24+8
80
24+9
00
24+9
20
24+9
40
24+9
60
24+9
80
25+0
00
OGL SURVEY BED PREPRATION EMBANKMENT Layer 1 Subgrade in cut layer 2layer 3layer 4layer 5layer 6layer 7layer 8layer 9layer 10
GSB 20 cm GSBABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm
LHS
RH
SLH
SR
HS
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 26
COMPLETED 25+000-25+500 As of DEC 2014BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Layr 10
Layr 9
Layr 8
Layr 7
Layr 6
Layr 5
Layr 4
Layr 3
Layr 2
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY
25+0
00
25+0
20
25+0
40
25+0
60
25+0
80
25+1
00
25+1
20
25+1
40
25+1
60
25+1
80
25+2
00
25+2
23
25+2
40
25+2
60
25+2
80
25+3
00
25+3
20
25+3
40
25+3
60
25+3
80
25+4
00
25+4
20
25+4
40
25+4
60
OGL SURVEY
BED PREPRATION sub grade in cut
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5
layer 6
layer 7
layer 8
layer 9
layer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
LHS
RH
S
End
of th
e pr
ojec
t
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 27
13. Financial Status of Payments
Sl. No. DESCRIPTIONPAYMENT FOR
THE MONTH OF
GROSS
AMOUNT
(R.O.)
GROSS
AMOUNT
CLAIMED (R.O.)
NET AMOUNT
CLAIMED
(R.O.)
DATE
SUBMITTED
AMOUNT
CERTIFIED (R.O.)DATE CERTIFIED
AMOUNT
RECEIVED
(R.O.)
DATE
PAYMENT DUE
DATE
PAYMENT
RECEIVED
1PAYMENT APPLICATION No. 1
(ADVANCE PAYMENT)Dec-13 1,648,225 1,648,225 1,648,225 23-Nov-13 1,648,225 29-Jan-14 1,648,225 6-Feb-14
2 PAYMENT APPLICATION No. 2 Jan-14 2,291,277 643,052 514,442 12-Feb-14 514,442 02-Apr-14 513,608 10-Apr-14
3 PAYMENT APPLICATION No. 3 Feb&Mar-14 2,808,644 517,367 504,147 06-Apr-14 434,917 03-May-14 414,674 6-Aug-14
4 PAYMENT APPLICATION No. 4 Apr-14 3,315,692 507,048 417,900 08-May-14 407,538 05-Jun-14 395,257 6-Aug-14
5 PAYMENT APPLICATION No. 5 May-14 4,109,460 793,768 650,802 05-Jun-14 445,708 04-Jul-14 374,172 6-Aug-14
6 PAYMENT APPLICATION No. 6 Jun-14 4,293,764 184,304 382,116 15-Jul-14 382,116 16-Jul-14 418,721 9-Sep-14
7 PAYMENT APPLICATION No. 7 Jul&Aug-14 5,749,546 1,455,782 1,164,626 14-Sep-14 1,123,023 18-Sep-14 1,123,023 19-Oct-14
8 PAYMENT APPLICATION No. 8 Sep-14 6,857,752 1,108,206 928,167 21-Oct-14 928,805 06-Nov-14 3-Jan-15
9 PAYMENT APPLICATION No. 9 Oct&Nov-14 8,550,924 1,693,172 1,398,920 17-Dec-14 29-Feb-00
10 PAYMENT APPLICATION No. 10 Dec-14
11 PAYMENT APPLICATION No. 11 Jan-15
12 PAYMENT APPLICATION No. 12 Feb-15
13 PAYMENT APPLICATION No. 13 Mar-15
14 PAYMENT APPLICATION No. 14 Apr-15
15 PAYMENT APPLICATION No. 15 May-15
16 PAYMENT APPLICATION No. 16 Jun-15
17 PAYMENT APPLICATION No. 17 Jul-15
18 PAYMENT APPLICATION No. 18 Aug-15
19 PAYMENT APPLICATION No. 19 Sep-15
20 PAYMENT APPLICATION No. 20 Oct-15
8,550,924 8,550,924 7,609,345 5,884,774 4,887,679 TOTAL AMOUNT (R.O.)
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 28
14. Details of Equipment Available At Site
Sl.
No.CCC HIRED
TOTAL
AVAILABLE
AT SITE
1 COMPRESSOR
2 AIR COMPRESSOR 2 1 3
3 MILLER WELDING MECHINE 2 2
4 GENERATOR 2 1 3
5 CRANES -
6 CRANES 30 TON / 25 TON / 70 TON 2 3 5
7 VEHICLES H.D. -
8 DIESEL TANKER -
9 FLAT TRAILER 2 2
10 HIAB TRUCK 2 2
11 P/MOVER + TIPPING TRAILER 4 5 9
12 TIPPER TRUCKS 11 4 15
13 WATER TANKER 5000 & 10000 GAL 1 6 7
14 EARTH MOVING PLANT
15 BOBCAT 1 2 3
16 EXCAVATOR 1 1
17 JCB 4CX / 3CX 1 6 7
18 SHOVEL / WHEEL LOADER 4 3 7
19 DOZER D9N/D8R 2 2
20 TELEHANDLER -
21 CIVIL ENGINEERING EQUIPMENT
22 GREENE STABILIZER PLANT 1 1
23 DYNAPAC TYRE ROLLER 2 2
24 E/WORK ROLLER 1 4 5
25 MOTOR GRADER 1 4 5
26 TITAN PAVER MACHINE -
27 TYRE / PTR ROLLER -
28 PAVER MACHINE 1 1
29 L. D. VEHICLES & TRUCKS
30 DYNA TRUCK 1 2 3
31 MAINTENANCE TRUCKS 1 1
32 ASHOK LEYLAND BUS 55 SEAT 5 5
33 TOYOTA COASTER BUS 24 S 1 1
34 TOYOTA COROLLA/CIVIC/YARIS 12 12
35 TOYOTA PICKUP/ISUZU 5 8 13
36 NISSAN PATHFINDER/X-TRAIL 5 5
37 TOYOTA LAND CRUISER/FORTUNER 4 4
38 Total 49 77 126
DESCRIPTION
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 29
Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Total
PLANNED TOTAL PER MONTH 47 68 87 95 93 107 110 108 102 100 98 87 82 79 77 66 53 41 1500
REVISED PLANNED TOTAL PER MONTH 68 87 95 93 107 110 108 102 100 98 87 82 79 77 66 53 41
PLANNED CUMULATIVE 47 115 202 297 390 458 545 640 733 840 950 1,058 1,160 1,260 1,358 1,445 1,527 1,606 1,683 1,749 1,802 1,843
ACTUAL TOTAL PER MONTH 33 55 66 68 77 86 88 100 109 112 120 126 1040
ACTUAL CUMULATIVE 33 88 154 222 299 385 473 573 682 794 914 1,040
2014 2015
47
68
87
95
93
10
7 11
0
10
8
10
2
10
0
98
87
82
79
77
66
53
41
33
55
66 68
77
86 88
10
0
10
9 11
2
12
0 12
6
68
87
95 93
107110 108
102 100 98
8782
79 77
66
53
41
0
20
40
60
80
100
120
140
Ja
n-1
4
Fe
b-1
4
Ma
r-1
4
Ap
r-1
4
Ma
y-1
4
Ju
n-1
4
Ju
l-1
4
Au
g-1
4
Se
p-1
4
Oc
t-1
4
No
v-1
4
Dec
-14
Ja
n-1
5
Fe
b-1
5
Ma
r-1
5
Ap
r-1
5
Ma
y-1
5
Ju
n-1
5
Ju
l-1
5
Au
g-1
5
Se
p-1
5
Oc
t-1
5
No
. o
f E
QU
IPM
EN
T
PROJECT MONTHS
PLANNED TOTAL PER MONTH
ACTUAL TOTAL PER MONTH
REVISED PLANNED TOTAL PER MONTH
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 30
15. Details of Manpower Available At Site
BUDGET ACTUAL BUDGET ACTUAL BUDGET ACTUAL
A - MANAGEMENT *** 3 3
B - COMMERCIAL STAFF * 7 1 8
C - ENGINEERS 7 7
D - FOREMAN & C/H 22 2 24
E - ENGINEERING TECHNICIANS ** 22 5 27
F - DAILY RATED EMPLOYEES :
1 - SKILLED CRAFTSMEN 142 64 206
2 - SEMI-SKILLED/UNSKILLED 495 55 550
TOTAL AS OF END OF THE MONTH 0 698 0 127 0 825
G - SUBCONTRACTORS
Number of Personnel employed by Subcontractor: 46
STAFF & LABOUR
EXPATRIATES NATIONALS TOTAL
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 31
2013Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Total
PLANNED TOTAL PER MONTH - ( DIRECT ) 6 34 186 375 586 791 792 799 794 793 701 480 381 269 246 307 307 305 149 8301
565 756 754 750 700 652 667 554 516 387 297 276 365 271 135 92 51 7788
PLANNED TOTAL PER MONTH - ( INDIRECT ) 5 23 36 50 52 57 59 59 60 61 63 61 61 57 51 47 44 35 30 914
REVISED - PLANNED TOTAL PER MONTH-(INDIRECT) 63 84 84 83 78 72 74 61 57 43 33 31 40 30 15 10 6 862
PLANNED TOTAL PER MONTH - ( DIRECT + INDIRECT ) 11 57 222 425 638 848 851 858 854 854 764 541 442 326 297 354 351 340 179 9215
REVISED - PLANNED - ( DIRECT + INDIRECT ) 627 840 838 833 778 725 741 616 573 429 330 306 406 301 150 102 57 8651
PLANNED CUMULATIVE 11 68 291 715 1,353 2,202 3,052 3,910 4,764 5,618 6,383 6,923 7,365 7,691 7,988 8,342 8,693 9,033 9,212 9,212
ACTUAL TOTAL PER MONTH - ( DIRECT ) 322 365 550 581 603 691 709 756 734 773 767 765 756 8372
ACTUAL TOTAL PER MONTH - ( INDIRECT ) 18 26 46 49 54 57 64 69 68 70 71 71 69 732
ACTUAL TOTAL PER MONTH - ( DIRECT + INDIRECT ) 340 391 596 630 657 748 773 825 802 843 838 836 825 0 0 0 0 0 0 9104
ACTUAL CUMULATIVE 340 731 1,327 1,957 2,614 3,362 4,135 4,960 5,762 6,605 7,443 8,279 9,104
REVISED - PLANNED TOTAL PER MONTH - ( DIRECT )
2014 2015
11
57
22
2
42
5
63
8
84
8
85
1
85
8
85
4
85
4
76
4
54
1
44
2
32
6
29
7
35
4
35
1
34
0
17
9
34
0
39
1
59
6 63
0 65
7
74
8 77
3
82
5
80
2 84
3
83
8
83
6
82
5
0 0 0 0 0 0
0
100
200
300
400
500
600
700
800
900
Dec
-13
Ja
n-1
4
Fe
b-1
4
Ma
r-1
4
Ap
r-1
4
Ma
y-1
4
Ju
n-1
4
Ju
l-1
4
Au
g-1
4
Se
p-1
4
Oc
t-1
4
No
v-1
4
Dec
-14
Ja
n-1
5
Fe
b-1
5
Ma
r-1
5
Ap
r-1
5
Ma
y-1
5
Ju
n-1
5
Ju
l-1
5
Au
g-1
5
Se
p-1
5
Oc
t-1
5
No
. of
Me
n
PROJECT MONTHS
PLANNED TOTAL PER MONTH - ( DIRECT + INDIRECT ) ACTUAL TOTAL PER MONTH - ( DIRECT + INDIRECT ) REVISED - PLANNED - ( DIRECT + INDIRECT )
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 32
16. QA/QC Reports
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 33
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 34
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 35
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 36
17. Status of Material Approvals
CCC/FQI/REN/MAS/001 MAS/CCC/FQI/BBC/001 Bituminous Base Course Tarmac Zawawi LLC Oman 22/12/2013 Renardet APPROVED 01/04/2014 SO/FQI/CCC/087 07/04/2014
CCC/FQI/REN/MAS/002 MAS/CCC/FQI/GTI/002 Geotechnical Investigation Swissboring & Company LLC 26/12/2013 Renardet APPROVED 02/02/2014 SO/FQI/CCC/015 12/02/2014
CCC/FQI/REN/MAS/003 MAS/CCC/FQI/MSE/003 MSE Wall System Freyssinet Arabian Sea LLC 26/12/2013 Renardet APPROVED 02/02/2014 SO/FQI/CCC/014 12/02/2014
CCC/FQI/REN/MAS/004 MAS/CCC/FQI/PVC/004 UPVC Pipes Amiantit Oman 26/12/2013 Renardet APPROVED 09/02/2014 SO/FQI/CCC/019 18/02/2014
CCC/FQI/REN/MAS/005 MAS/CCC/FQI/HDPE/005 HDPE Pipes & Fittings Amiantit Oman 26/12/2013 Renardet APPROVED 09/02/2014 SO/FQI/CCC/020 18/02/2014
CCC/FQI/REN/MAS/006 MAS/CCC/FQI/PW/006 Piling Works APCC LLC 26/01/2014 Renardet APPROVED 19/02/2014 SO/FQI/CCC/026 25/02/2014
CCC/FQI/REN/MAS/007 MAS/CCC/FQI/MC/007 Bitnuminous Prime Coat (MC-70) Emirates Lube Oil Co. (Muscat) 30/01/2014 Renardet APPROVED 09/03/2014 SO/FQI/CCC/069 27/03/2014
CCC/FQI/REN/MAS/008 MAS/CCC/FQI/RS/008 Reinforcing Steel Muscat Steel Industries 02/02/2014 Renardet APPROVED 20/03/2014 SO/FQI/CCC/063 24/03/2014
CCC/FQI/REN/MAS/009-1 MAS/CCC/FQI/PT/009-1 Post Tensioning Work - Anchorage Freyssinet Arabian Sea LLC 22/02/2014 Renardet APPROVED 27/03/2014 SO/FQI/CCC/089 14/04/2014
CCC/FQI/REN/MAS/009-2 MAS/CCC/FQI/PT/009-2 Post Tensioning Work - Duct Freyssinet Arabian Sea LLC 22/02/2014 Renardet APPROVED 27/03/2014 SO/FQI/CCC/090 14/04/2014
CCC/FQI/REN/MAS/009-3 MAS/CCC/FQI/PT/009-3 Post Tensioning Work - Strand Freyssinet Arabian Sea LLC 22/02/2014 Renardet APPROVED 27/03/2014 SO/FQI/CCC/091 14/04/2014
CCC/FQI/REN/MAS/010A-R1 MAS/CCC/FQI/PB/010A-R1 Bridge Pot Bearings Al Ammar International 07/05/2014 Renardet Not Approved --- REN/FQI/CCC/111 13/05/2014
CCC/FQI/REN/MAS/010B MAS/CCC/FQI/PB/010B Bridge Pot Bearings Building Supplies & Services 11/05/2014 Renardet APPROVED 25/05/2014 REN/FQI/CCC/122 31/05/2014
CCC/FQI/REN/MAS/011 MAS/CCC/FQI/HDPE/011 HDPE Water Pipes Amiantit Oman 22/02/2014 Renardet APPROVED 09/03/2014 SO/FQI/CCC/038 11/03/2014
CCC/FQI/REN/MAS/012 MAS/CCC/FQI/RCBC/012 Single cell Precast Box Culvert Amiantit Oman 22/02/2014 Renardet APPROVED 25/03/2014 SO/FQI/CCC/064 26/03/2014
CCC/FQI/REN/MAS/013 MAS/CCC/FQI/BP/013 Bituminous Paint Material (Rubberized) Al Inma Building Materilal LLC 02/03/2014 Renardet Not Approved 20/04/2014 REN/FQI/CCC/105 05/05/2014
CCC/FQI/REN/MAS/013A MAS/CCC/FQI/BP/013A Bituminous Paint Material (Rubberized) Henkel Polybit Industries Ltd. 17/06/2014 Renardet APPROVED 03/07/2014 REN/FQI/CCC/146 13/07/2014
CCC/FQI/REN/MAS/014A-R1 MAS/CCC/FQI/EJ/014A-R1 Bridge Expansion Joints Al Ammar International 07/05/2014 Renardet APPROVED 20/05/2014 REN/FQI/CCC/123 31/05/2014
CCC/FQI/REN/MAS/014B MAS/CCC/FQI/EJ/014B Bridge Expansion Joints Ocean Rubber Factory LLC 09/11/2014 Renardet
CCC/FQI/REN/MAS/014C MAS/CCC/FQI/EJ/014C Bridge Expansion Joints Mageba (India) 02/12/2014 Renardet
CCC/FQI/REN/MAS/015 MAS/CCC/FQI/RC/015Reinforced Concrete Pipe
(450,600,700mm dia)Amiantit Oman 02/03/2014 Renardet APPROVED 23/03/2014 SO/FQI/CCC/077 02/04/2014
Renardet
Letter
Dated
Reference No. MAR No. Material/ Work Manufacturer/Supplier/
Subcontractor
Submitte
d To
Remarks
By MOTC
MOTC
Comments
dated
Via Renardet
Letter Ref. No.
Date
Submitted
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 37
CCC/FQI/REN/MAS/016 B MAS/CCC/FQI/WS/016 B Water Stop G EE-25 Sika LLC Oman 25/03/2014 Renardet APPROVED 16/04/2014 REN/FQI/CCC/099 28/04/2014
CCC/FQI/REN/MAS/017 MAS/CCC/FQI/TW/017 Telephone Works National Telephone Services 12/03/2014 Renardet APPROVED 17/03/2014 SO/FQI/CCC/082 03/04/2014
CCC/FQI/REN/MAS/019 MAS/CCC/FQI/EW/019 Electrical Works United Engineering Projects 22/03/2014 Renardet APPROVED 29/05/2014 REN/FQI/CCC/131 16/06/2014
CCC/FQI/REN/MAS/020 MAS/CCC/FQI/EC/020 MV & LV Cables United Engineering Projects 19/03/2014 Renardet APPROVED 27/03/2014 SO/FQI/CCC/083 03/04/2014
CCC/FQI/REN/MAS/021 MAS/CCC/FQI/PS/021 Package Substation United Engineering Projects 22/03/2014 Renardet ---- ----
CCC/FQI/REN/MAS/021A MAS/CCC/FQI/PS/021A Package Substation Voltamp Energy SAOG 16/09/2014 RenardetAPPROVED
as Noted3/11/2014 REN/FQI/CCC/202 30/11/2014
CCC/FQI/REN/MAS/022 MAS/CCC/FQI/LL/022 Street Lighting Luminaries Majees Lighting Industries LLC 27/03/2014 Renardet APPROVED 14/08/2014 REN/FQI/CCC/158 17/08/2014
CCC/FQI/REN/MAS/023A MAS/CCC/FQI/LP/023A Street Lighting Poles (Mid-Hinged)Al Babtain Power &
Telecomunication Co., 22/05/2014 Renardet APPROVED 14/08/2014 REN/FQI/CCC/157 17/08/2014
CCC/FQI/REN/MAS/024 MAS/CCC/FQI/FP/024 Street Lighting Feeder Pillar Stars Light LLC 27/03/2014 Renardet APPROVED 08/06/2014 REN/FQI/CCC/130 16/06/2014
CCC/FQI/REN/MAS/025 MAS/CCC/FQI/JS/025 Joint Sealant (Polyseal) Al Inma Building Materilal LLC 27/03/2014 Renardet APPROVED 16/04/2014 REN/FQI/CCC/100 28/04/2014
CCC/FQI/REN/MAS/026 MAS/CCC/FQI/GT/026 Geotextile Modern East Trading & Con. 21/05/2014 RenardetNo meet the
HDS--- REN/FQI/CCC/119 27/05/2014
CCC/FQI/REN/MAS/026A MAS/CCC/FQI/GT/026A Geotextile (Bonar NW16) Bonar Technical Fabrics 15/06/2014 Renardet APPROVED 14/08/2014 REN/FQI/CCC/159 17/08/2014
CCC/FQI/REN/MAS/027 MAS/CCC/FQI/MS/027
Masterseal 915
(formerly known as Masterflow 410
Plus)
OBasf The Chemical Company 10/08/2014 RenardetAPPROVED
as Noted21/10/2014 REN/FQI/CCC/196 17/11/2014
CCC/FQI/REN/MAS/028 MAS/CCC/FQI/GG/028 Gully Gratings & Frames RBA Ferro Industries PVT. Ltd. 17/08/2014 Renardet APPROVED 25/09/2014 REN/FQI/CCC/192 15/10/2014
CCC/FQI/REN/MAS/030 MAS/CCC/FQI/FLC/030MasterRoc FLC 100 (Cable Grout
Admixture)BASF-The Chemical Company 02/10/2014 Renardet
CCC/FQI/REN/MAS/031 MAS/CCC/FQI/CG/031 Cebex Cable Grout Plus Al Gurg Fosroc 22/12/2014 Renardet
CCC/FQI/REN/MAS/032 MAS/CCC/FQI/GR/032 Guardrails GK Wire Industries LLC 29/10/2014 Renardet
CCC/FQI/REN/MAS/032A MAS/CCC/FQI/GR/032A Guardrails United Metal Galvanizing Services24/12/2014 Renardet
CCC/FQI/REN/MAS/033 MAS/CCC/FQI/PVC-D/033 1/2" to 8" UPVC Pipe (Class D) Oman Plast 03/11/2014 Renardet
CCC/FQI/REN/MAS/034 MAS/CCC/FQI/SS1H/034 Tack Coat (SS1H) Bitu Trade Industrial LLC 15/11/2014 Renardet
CANCELLED
Reference No. MAR No.
MOTC
Comments
dated
Via Renardet
Letter Ref. No.
Renardet
Letter
Dated
Material/ Work Manufacturer/Supplier/
Subcontractor
Date
Submitted
Submitte
d To
Remarks
By MOTC
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 38
18. Engineer’s Comments
The Planned progress as per the revised Project Execution Program for the month of
December is 8.32% and the Actual progress is 6.89% which shows 1.43% of delay
for the month of December. The actual cumulative progress up to December is
58.30% against Planned Cumulative Progress of 63.86% showing a lagging of
5.56%. The delayed progress is mainly due to the additional works undertaken
during the last few months which may increase in the coming months.
The second Box Girder of Superstructure is ready for casting deck slab and works
are in progress for third Box Girder.
Works for the 02 newly proposed Vehicular Underpasses are in progress.
Extension of Time for the Project Completion Date is approved for 109 days and
Variation Order No. 1 is under preparation for the increase or decrease of Project
Scope.
Utilities relocation works are in progress and affected by Land appropriation
problems.
Contractor requested for second Extension of Time to project completion date
which is under review.
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 39
19. Correspondence during the month
S.
No.
Date
ReceivedFrom
Reference
NoSubject
Reply
dateRemarks
1 12/1/2014 CCC
FQI-REN-TR-
319
Street lighting pull box chamber details
Rev.b 12/1/2014 Approved
2 12/1/2014 CCC
FQI/RENARDE
T/282
Asphalt Mix Design from AlTurki
Asphalt Plant- Sohar
3 12/2/2014 CCC
FQI-REN-TR-
320
Retaining Wall plan , section& Elevation
@ ch .22+300.000 TO 22+486.700 12/22/2014 Approved
4 12/3/2014 CCC
FQI/RENARDE
T/283
Monthly Progress Report No. 11 -
November 2014
5 12/3/2014 CCC
FQI-REN-TR-
321
Shop Drawing for Gantry and Cantilever
sign Layout Plan at ch .21+150 to 21+600
( sheet 1 to 9 ) Rev.A
6 12/4/2014 CCC
FQI/RENARDE
T/284
Material Test Certificates for 37C15
Anchor Block & Jaws - S/c Freysinnet
Arabian Sea LLC
7 12/4/2014 CCC
FQI-REN-TR-
322
Cross Section Drawings for SOL-5 (
Batinah Highway) from Ch.0+200 to
0+360, Rev.B 12/8/2014 Approved
8 12/4/2014 CCC
FQI-REN-TR-
323
Shop Drawings for pedstrian underpass
& section Details at ch.23+284_SOL-1 (
Sheet 1 of 10 ) Rev .b 12/8/2014 Approved as Noted
9 12/7/2014 CCC
FQI-REN-TR-
324
Bar Bending Schedule for Retaining wall
from ch.21+280.405 to 21+235.405, LHS ,
Rev0 12/8/2014 Approved
10 12/7/2014 CCC
FQI-REN-TR-
325
Shop Drawing for Pedestrian Upgrading
of falaj Alqabail RA at Sservice Road 1
Information of SR1 at ch.22+720 to
23+460, Rev .0- UEP 12/17/2014 Approved
11 12/7/2014 CCC
FQI/RENARDE
T/285
Calibration test Certifaicates of Jacks &
Pressure Gauges - S/C Freyssinnet
Arabian sea LLC
12 12/7/2014 CCC
FQI/RENARDE
T/286
Test Report for pot Bearing -S/C
Builging Supplies & services LLC
13 12/8/2014 CCC
FQI/RENARDE
T/287
Calibration test Certifaicates Pressure
Gauges , Wika - S/C Fressinet Gulf LLC
14 12/8/2014 CCC
FQI-REN-TR-
326
Shop Drawing for Bridge Shoring (AB2-
P3)PE4R1-Sheet 1 to 3, Rev.A 12/13/2014 Approved
15 12/8/2014 CCC
FQI-REN-TR-
327
MSE Wall Elevation of wall SW-A 1 & SW-
A2 ( Abutment 1 & 2) Design Section-
SC freyssint Arbian Sea LLC 12/10/2014 Approved as Noted
16 12/10/2014 CCC
FQI-REN-TR-
328
Sign & Road Marking layout plans from
21+150 to 25+223.009 & ch .0+000 to
17 12/10/2014 CCC
FQI-REN-TR-
329
Typical Road Marking Details ( Line &
Arrows ) - Rev.A 12/21/2014 Approved
18 12/10/2014 CCC
FQI/RENARDE
T/288
Stressing Results for Bridge 1 , S/C
Freyssinet Arabian sea LLC
19 12/11/2014 CCC
FQI-REN-TR-
330 Structural Details for Road Signs 12/16/2014 Approved
20 12/11/2014 CCC
FQI-REN-TR-
331
30 Meter Street Linghting Foundation
Co-Ordinates layout plan (SOL-2)-Rev.A 12/16/2014 Approved as Noted
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 40
S.
No.
Date
ReceivedFrom
Reference
NoSubject
Reply
dateRemarks
21 12/14/2014 CCC
FQI-REN-TR-
332
2 Way # 300 mm upvc ducts for Water
line @ ch.0+590(SR_1) -Rev.B 12/16/2014 Approved
22 12/16/2014 CCC
FQI-REN-TR-
333
Curb Stone , Interlock Tiles & Guard
Rails Plans@ ch.21+150 to 21+600 (
sheet 0 1 of 09)
23 12/17/2014 CCC
FQI/RENARDE
T/289
Approved Shop Drawing - From Majan
Electric Co. Relocation of Existing 11
KVA Cable
24 12/17/2014 CCC
FQI/RENARDE
T/290
Calibration Certificate of Stressing Jack
( Freyssinet Gulf LLC)
25 12/17/2014 CCC
FQI/RENARDE
T/291 Tiles Pattern
26 12/17/2014 CCC
FQI/RENARDE
T/292 Interim Payment Application No.09
27 12/17/2014 CCC
FQI/RENARDE
T/293
ALTurki (AL tasnim) BBC & BWC Class B-
Mix Design
28 12/18/2014 CCC
FQI-REN-TR-
334
Retaining Wall plan ( SOL-3 )at@
ch.0+130 to 0+310 LHS ( Sheet 1 to 09 )
29 12/21/2014 CCC
FQI/RENARDE
T/294
Original Test Reports for pot Bearings (
Building Supplies & Services LLC-
Mageba)
30 12/21/2014 CCC
FQI-REN-TR-
335
2 Way # 300mm upvc Irrigation Ducts @
ch . 0+145 ( SOL-2) 12/22/2014 Approved
31 12/21/2014 CCC
CCC/FQI/REN
/MAS/031
Approval for Cebex ( Cable Grout
Admixture) MAR .
NO.MAS/CCC/FQI/CG/031
32 12/22/2014 CCC
FQI-REN-AS
BUILT -TR-01
Relocation of Existing falaj Channel @
ch . 23+411.400
33 12/22/2014 CCC
FQI-REN-TR-
336
Omantel Cable New Location @
ch.0+015 to 0+140 RHS (SOL-3 ) 12/23/2014 Approved
34 12/22/2014 CCC
FQI-REN-TR-
337 Bridge Drainage Inlet Cover 12/23/2014 Approved
35 12/23/2014 CCC
FQI-REN-TR-
338
pedestrian underpass lighying plan at
ch.0+050 (SOL-3) 12/24/2014 Approved
36 12/23/2014 CCC
FQI-REN-AS
BUILT -TR-02
1 Way 100mm & 1 way 150mm upvc
Ducts @ch .0+125.60( Sohar Airport
Cargo Access Road)
37 12/23/2014 CCC
FQI-REN-AS
BUILT -TR-03
2 Way #100mm upvc Omantel Ducts @
ch. 0+011.10( Sohar Airport Cargo Access
Road)
38 12/23/2014 CCC
FQI-REN-AS
BUILT -TR-04
Protwction of Existing water Line #
125mm & #200mm @ ch.0+016( Sohar
Airport Cargo Access Road )
39 12/23/2014 CCC
FQI-REN-AS
BUILT -TR-05
2 Way #100mm upvc Electrical Ducts @
ch. 0+013.760( Sohar Airport Cargo
Access Road)
40 12/23/2014 CCC
FQI-REN-AS
BUILT -TR-06
2Way #150mm upvc street lighting
Ducts @ ch.0+320( Sohar Airport Cargo
Access Road )
41 12/24/2014 CCC
FQI-REN-AS
BUILT -TR-07
Sohar Airport Cargo Acces Road ( Batina
Highway) cross Sections at Ch.0+010
42 12/24/2014 CCC
FQI-REN-TR-
339
Bar Bending Schedule for Retaining wall
from ch.0+130.000 to 0+141.150 ( SOL-3 )
LHS ,
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 41
S.
No.
Date
ReceivedFrom
Reference
NoSubject
Reply
dateRemarks
43 12/24/2014 CCC
FQI-REN-TR-
340
Bar Bending Schedule for Deck Slab
from Abutment 1 to pier 3 12/28/2014 Rejected
44 12/24/2014 CCC
CCC/FQI/REN
/MAS/032A
Approval for Guardrails MAR .
NO.MAS/CCC/FQI/CG/032A
45 12/28/2014 CCC
FQI-REN-TR-
341
Bar Bending Schedule for Retaining
wall from 0+241.776 to 0+254.268 ( SOL-
3) LHS
46 12/28/2014 CCC
FQI-REN-TR-
342
Bar Bending Schedule for Underpass at
ch.23+284.40 (SOL-1) BLOCK#01 to 04
47 12/28/2014 CCC
FQI-REN-TR-
343
Typical Section ( Type -2 to Type -7)
Retaining Wall Reinforcement Details
48 12/28/2014 CCC
FQI-REN-TR-
344
SOL-1 (Batina Highway) Cross Section at
ch.25+080
49 12/28/2014 CCC
FQI-REN-TR-
345 Guard Rail Details ( W-Beam Type )
50 12/29/2014 CCC FQI/MOTC/12
Additional Items of Works Not Covered
Under BOQ
51 12/30/2014 CCC
FQI/RENARDE
T/295 Prophets Birthday Holiday
52 12/30/2014 CCC
FQI/RENARDE
T/296
ALTurki (AL tasnim) BBC Class A-Mix
Design
53 12/30/2014 CCC
FQI-REN-TR-
346 Structural Details for Road Signs
54 12/30/2014 CCC
FQI-REN-TR-
347
SR-1(Batina Highway ) cross section at
ch.0+000
55 12/31/2014 CCC
FQI-REN-TR-
348
Electrical Relocation Work at Falaj
AlQabail Roundabout for 11 KVA Cable
at SOL-03
56 12/31/2014 CCC
FQI-REN-TR-
349
Proposed of Existing 11 KVA Electrical
Cable @ch.0+277.100 to 1+002.900 LHS-
SR-02
57 12/31/2014 CCC
FQI-REN-TR-
350
Bar Bending Schedule for Underpass
Entrance at ch.23+284.40 (SOL-1) LHS
58 12/31/2014 CCC
FQI-REN-TR-
351
Bar Bending Schedule for Underpass
Entrance at ch.23+284.40 (SOL-1)RHS
59 12/31/2014 CCC
FQI-REN-TR-
352
Dimension & Details of 1 cell Box
Culvert ( 2.0*1.0-skew angle 0 )at
ch.25+170
60 12/31/2014 CCC
FQI/RENARDE
T/297 Unit Built Rates
61 12/31/2014 CCC
FQI/RENARDE
T/298
Project Monthly Progress Videos &
Pictures
62 12/31/2014 CCC
FQI-REN-TR-
353
Access Door & Diapgragm Opening &
Bridge Barrier Reinforcement - Typical
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 42
20. PROGRESS PHOTOGRAPHS
Pouring o
f C
oncre
te in B
ox G
irder
of F
lyover
Bridge
No
. 4
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 43
Superstructure of Bridge No. 1 after De-shuttering
Project Activities at a glance
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 44
Pouring of Concrete in Abutment Cap for Bridge No. 2
Post Tensioning of Box Girder in Bridge No. 1
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 45
Rounding of Median at the Start of Project
8 Cells Box Culvert Works in Progress
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 46
Aggregate Base Course Trail in Progress
Work in Progress in Buraimi Road
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report – December 2014
RENARDET S.A. & PARTNERS Page 47
Installation of Drainage Pipes
Installation of Future Service Ducts