FALAJ AL QABIL ROUNDABOUTFALAJ AL QABIL ROUNDABOUT 608 30-Oct-13 29-Jun-15 741411
PREPARATORY WORKSPREPARATORY WORKS 608 30-Oct-13 29-Jun-15 0
GENERALGENERAL 608 30-Oct-13 29-Jun-15 0
CONTRACTUAL & PRELIMINARIESCONTRACTUAL & PRELIMINARIES 608 30-Oct-13 29-Jun-15 0
MILESTONE & MOBILIZATIONMILESTONE & MOBILIZATION 608 30-Oct-13 29-Jun-15 0
MILESTONESMILESTONES 608 30-Oct-13 29-Jun-15 0
CONTRACTUAL DATESCONTRACTUAL DATES 608 30-Oct-13 29-Jun-15 0
A0000 Contract Award Date 0 30-Oct-13 0 0 A6230, A6080, A6670, A6630,
A6080 Mobilization 60 30-Oct-13 28-Dec-13 0 0 A0000 A6230, A6240, A6255, A6250, A6260, A6680
A6720 Construction Duration 548 29-Dec-13 29-Jun-15 0 0 A6680 A6100
A6100 Project Completion Date 0 29-Jun-15 0 0 A5640, A6690, A6720, A57
CONSTRUCTIONAL DATESCONSTRUCTIONAL DATES 608 30-Oct-13 29-Jun-15 0
A6670 Project Commencement 0 30-Oct-13 0 0 A0000 A6680
A6680 Mobilization Completion 0 28-Dec-13 0 0 A6230, A6240, A6255, A6250, A6260, A6080, A6670A6690, A6720, A1260, A6110, A10620
A10580 Resolution of Falaj Location under Bridge 0 09-Feb-14 0 0 A999 A6100
A6700 Commence Traffic Diversions from Existing Roads to Temporary Roads 0 11-Feb-14 0 0 A1010 A6730, A6710
A6800 Resolution of all Expropriations about SR-2 0 25-Feb-14 0 0 A1330, A1340, A1400, A1410
A6710 Complete Traffic Diversion from Temporary Roads to Batinah Highway 0 01-Jan-15 0 0 A5490, A6700, A6770, A6790, A3940A6690, A9900
A6730 Complete Traffic Diversion from Temporary Roads to Sohar-Buraimi Road 0 03-Mar-15 0 0 A5640, A6700 A6690
A6690 Completion of all works 0 29-Jun-15 0 0 A6680, A6710, A6740, A6730A6100
A6740 Complete Traffic Diversion from Temporary Roads to New Service Roads 0 29-Jun-15 0 0 A5780, A5940, A9640 A6690
MOBILIZATIONMOBILIZATION 60 30-Oct-13 28-Dec-13 0
GENERALGENERAL 60 30-Oct-13 28-Dec-13 0
A6230 Obtain NOC's 60 30-Oct-13 28-Dec-13 0 0 A0000, A6080 A6240, A6260, A6255, A6680, A6660
A6240 Setting-up Engineer's Offices 38 09-Nov-13 16-Dec-13 0 0 A6230, A6080 A6250, A6680
A6260 Erection of Laboratory & Store 45 14-Nov-13 28-Dec-13 0 0 A6230, A6080 A6680
A6250 Setting-up Contractor's Offices 38 16-Nov-13 23-Dec-13 0 0 A6240, A6080 A6680
A6255 Setting-up of Contractor's Camp 35 24-Nov-13 28-Dec-13 0 0 A6230, A6080 A6680
TRAFFIC MANAGEMENTTRAFFIC MANAGEMENT 53 06-Nov-13 28-Dec-13 0
GENERALGENERAL 53 06-Nov-13 28-Dec-13 0
A6630 Submit Traffic Mangement Plans 15 06-Nov-13 20-Nov-13 0 0 A0000 A6640
A6640 Approve Traffic Mnagement Plans 15 17-Nov-13 01-Dec-13 0 0 A6630 A6650
A6650 Obtain Traffic NOC's 15 02-Dec-13 16-Dec-13 0 0 A6640 A6660
A6660 Obtain Approval from ROP Police 12 17-Dec-13 28-Dec-13 0 0 A6650, A6230 A1260, A1070
SHOP DRAWINGSSHOP DRAWINGS 535 29-Dec-13 16-Jun-15 0
GENERALGENERAL 535 29-Dec-13 16-Jun-15 0
A10620 Prepare & Submit Shop Drawings 520 29-Dec-13 01-Jun-15 A6680 A10630
A10630 Approval of Shop Drawings 520 13-Jan-14 16-Jun-15 A10620
PROCUREMENTPROCUREMENT 578 29-Nov-13 29-Jun-15 0
MATERIALMATERIAL 561 16-Dec-13 29-Jun-15 0
PRECAST MSE WALL PANELSPRECAST MSE WALL PANELS 75 16-Dec-13 28-Feb-14 0
A6300 Submit Material for Approval 15 16-Dec-13 30-Dec-13 0 0 A0000 A6310
A6310 Obtain Material Approval 20 31-Dec-13 19-Jan-14 0 0 A6300 A6320
A6320 Delivery to Site 40 20-Jan-14 28-Feb-14 0 0 A6310 A5020
POT BEARINGSPOT BEARINGS 170 03-Jan-14 21-Jun-14 0
A6450 Submit Material for Approval 20 03-Jan-14 22-Jan-14 0 0 A0000 A6460
A6460 Obtain Material Approval 30 23-Jan-14 21-Feb-14 0 0 A6450 A6470
A6470 Delivery to Site 120 22-Feb-14 21-Jun-14 0 0 A6460 A1640, A3500, A3850, A4310
EXPANSION JOINTEXPANSION JOINT 170 11-Jan-15 29-Jun-15 0
A10590 Submit Material for Approval 20 11-Jan-15 30-Jan-15 0 0 A10600
A10600 Obtain Material Approval 30 31-Jan-15 01-Mar-15 0 0 A10590 A10610
A10610 Delivery to Site 120 02-Mar-15 29-Jun-15 0 0 A10600
LIGHTING POLES & LUMINARIESLIGHTING POLES & LUMINARIES 140 03-Mar-14 20-Jul-14 0
A6330 Submit Material for Approval 20 03-Mar-14 22-Mar-14 0 0 A0000 A6340
J J J J J J J J J
2014 2015 2016
29-Jun-15, FALAJ AL QABIL
29-Jun-15, PREPARATORY WORKS
29-Jun-15, GENERAL
29-Jun-15, CONTRACTUAL
29-Jun-15, MILESTONE & M
29-Jun-15, MILESTONES
29-Jun-15, CONTRACTUAL DATES
Contract Award Date
Mobilization
Construction Duration
Project Completion Date
29-Jun-15, CONSTRUCTIONAL DATES
Project Commencement
Mobilization Completion
Resolution of Falaj Location under Bridge
Commence Traffic Diversions from Existing Roads to T
Resolution of all Expropriations about SR-2
Complete Traffic Diversion from Temp
Complete Traffic Diversion from Te
Completion of all works
Complete Traffic Diversion fr
28-Dec-13, MOBILIZATION
28-Dec-13, GENERAL
Obtain NOC's
Setting-up Engineer's Offices
Erection of Laboratory & Store
Setting-up Contractor's Offices
Setting-up of Contractor's Camp28-Dec-13, TRAFFIC MANAGEMENT
28-Dec-13, GENERAL
Submit Traffic Mangement Plans
Approve Traffic Mnagement Plans
Obtain Traffic NOC's
Obtain Approval from ROP Police16-Jun-15, SHOP DRAWINGS
16-Jun-15, GENERAL
Prepare & Submit Shop Drawings
Approval of Shop Drawings29-Jun-15, PROCUREMENT
29-Jun-15, MATERIAL
28-Feb-14, PRECAST MSE WALL PANELS
Submit Material for Approval
Obtain Material Approval
Delivery to Site21-Jun-14, POT BEARINGS
Submit Material for Approval
Obtain Material Approval
Delivery to Site29-Jun-15, EXPANSION JOINT
Submit Material for Approval
Obtain Material Approval
Delivery to Site20-Jul-14, LIGHTING POLES & LUMINARIES
Submit Material for Approval
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 1 of 17
Data Date: 30-Oct-13 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A6340 Obtain Material Approval 20 23-Mar-14 11-Apr-14 0 0 A6330 A6350
A6350 Delivery to Site 100 12-Apr-14 20-Jul-14 0 0 A6340 A4670, A5990, A5010
PRECAST CONC. BARRIER MOLDSPRECAST CONC. BARRIER MOLDS 75 06-May-14 19-Jul-14 0
A6270 Submit Material for Approval 15 06-May-14 20-May-14 0 0 A0000 A6280
A6280 Obtain Material Approval 20 21-May-14 09-Jun-14 0 0 A6270 A6290
A6290 Delivery to Site 40 10-Jun-14 19-Jul-14 0 0 A6280 A4550, A3920, A5400
RC STORM SEWERRC STORM SEWER 50 28-Dec-13 15-Feb-14 0
A6360 Submit Material for Approval 15 28-Dec-13 11-Jan-14 0 0 A0000 A6370
A6370 Obtain Material Approval 15 12-Jan-14 26-Jan-14 0 0 A6360 A6380
A6380 Delivery to Site 20 27-Jan-14 15-Feb-14 0 0 A6370 A5100, A5140
GUARDRAILGUARDRAIL 100 09-Aug-14 16-Nov-14 0
A6420 Submit Material for Approval 20 09-Aug-14 28-Aug-14 0 0 A0000 A6430
A6430 Obtain Material Approval 20 29-Aug-14 17-Sep-14 0 0 A6420 A6440
A6440 Delivery to Site 60 18-Sep-14 16-Nov-14 0 0 A6430 A5460
ROAD SIGNSROAD SIGNS 60 18-Sep-14 16-Nov-14 0
A6390 Submit Material for Approval 20 18-Sep-14 07-Oct-14 0 0 A0000 A6400
A6400 Obtain Material Approval 20 08-Oct-14 27-Oct-14 0 0 A6390 A6410
A6410 Delivery to Site 20 28-Oct-14 16-Nov-14 0 0 A6400 A5470, A5930, A5620, A5760
S/CS/C 233 29-Nov-13 19-Jul-14 0
ELECTRICAL S/CELECTRICAL S/C 75 15-Dec-13 27-Feb-14 0
A6510 Select S/C 15 15-Dec-13 29-Dec-13 0 0 A0000 A6520
A6520 Approve S/C 15 30-Dec-13 13-Jan-14 0 0 A6510 A6530
A6530 Mobilization to Site 45 14-Jan-14 27-Feb-14 0 0 A6520 A1360, A1100, A4800, A4910
WATER S/CWATER S/C 75 20-Dec-13 04-Mar-14 0
A6540 Select S/C 15 20-Dec-13 03-Jan-14 0 0 A0000 A6550
A6550 Approve S/C 15 04-Jan-14 18-Jan-14 0 0 A6540 A6560
A6560 Mobilization to Site 45 19-Jan-14 04-Mar-14 0 0 A6550 A1280, A1020
TELEPHONE S/CTELEPHONE S/C 75 15-Dec-13 27-Feb-14 0
A6570 Select S/C 15 15-Dec-13 29-Dec-13 0 0 A0000 A6580
A6580 Approve S/C 15 30-Dec-13 13-Jan-14 0 0 A6570 A6590
A6590 Mobilization to Site 45 14-Jan-14 27-Feb-14 0 0 A6580 A1450, A1890, A1210
PILING S/CPILING S/C 75 29-Nov-13 11-Feb-14 0
A6480 Select S/C 15 29-Nov-13 13-Dec-13 0 0 A0000 A6490
A6490 Approve S/C 15 14-Dec-13 28-Dec-13 0 0 A6480 A6500
A6500 Mobilization to Site 45 29-Dec-13 11-Feb-14 0 0 A6490 A1540, A3160
POST TENSIONING S/CPOST TENSIONING S/C 75 06-May-14 19-Jul-14 0
A6600 Select S/C 15 06-May-14 20-May-14 0 0 A0000 A6610
A6610 Approve S/C 15 21-May-14 04-Jun-14 0 0 A6600 A6620
A6620 Mobilization to Site 45 05-Jun-14 19-Jul-14 0 0 A6610 A1670
BATINAH HIGHWAYBATINAH HIGHWAY 548 29-Dec-13 29-Jun-15 609312
HIGHWAY & SLIP ROADSHIGHWAY & SLIP ROADS 530 29-Dec-13 11-Jun-15 571511
SOL1, SOL5, SOL6SOL1, SOL5, SOL6 407 29-Dec-13 08-Feb-15 480323
TEMPORARY DIVERSION FOR EXISTING NORTHERN SERVICE ROADTEMPORARY DIVERSION FOR EXISTING NORTHERN SERVICE ROAD 21 29-Dec-13 18-Jan-14 327
SR1 (CH 0+000 to CH 0+797)SR1 (CH 0+000 to CH 0+797) 21 29-Dec-13 18-Jan-14 327
GENERALGENERAL 21 29-Dec-13 18-Jan-14 327
A1260 Laying of Asphalt of Temp. Road over SR-1 15 29-Dec-13 12-Jan-14 327 M3 A6660, A6680 A10330
A10330 Placing Plastic Barriers 5 14-Jan-14 18-Jan-14 0 0 A1260 A1270
A1270 Shift Traffic from Existing Northern Service Road to Temp. SR-1 0 18-Jan-14 0 0 A10330 A9940, A1330, A1340, A1400, A1410, A10490
TEMPORARY DIVERSION FOR EXISTING HIGHWAY - NORTH BOUNDTEMPORARY DIVERSION FOR EXISTING HIGHWAY - NORTH BOUND 45 29-Dec-13 11-Feb-14 655
SOL1-NORTH (CH 21+100 to CH 25+300)SOL1-NORTH (CH 21+100 to CH 25+300) 45 29-Dec-13 11-Feb-14 655
GENERALGENERAL 45 29-Dec-13 11-Feb-14 655
A1070 Protection of services 15 29-Dec-13 12-Jan-14 0 0 A6660 A1000, A999
A1000 Laying of Asphalt on Temp. new Road Adjacent to SOL1-NB 30 13-Jan-14 11-Feb-14 655 M3 A1070, A999 A1005, A9910
A1005 Placing of Plastic Barriers 8 04-Feb-14 11-Feb-14 0 0 A1000 A1010
A999 Resolution of Falaj Relocation Under Temp. Diversion 0 09-Feb-14 A1070 A1000, A10580
J J J J J J J J J
2014 2015 2016
Obtain Material Approval
Delivery to Site19-Jul-14, PRECAST CONC. BARRIER MOLDS
Submit Material for Approval
Obtain Material Approval
Delivery to Site15-Feb-14, RC STORM SEWER
Submit Material for Approval
Obtain Material Approval
Delivery to Site16-Nov-14, GUARDRAIL
Submit Material for Approval
Obtain Material Approval
Delivery to Site16-Nov-14, ROAD SIGNS
Submit Material for Approval
Obtain Material Approval
Delivery to Site19-Jul-14, S/C
27-Feb-14, ELECTRICAL S/C
Select S/C
Approve S/C
Mobilization to Site04-Mar-14, WATER S/C
Select S/C
Approve S/C
Mobilization to Site27-Feb-14, TELEPHONE S/C
Select S/C
Approve S/C
Mobilization to Site11-Feb-14, PILING S/C
Select S/C
Approve S/C
Mobilization to Site19-Jul-14, POST TENSIONING S/C
Select S/C
Approve S/C
Mobilization to Site29-Jun-15, BATINAH HIGHWAY
11-Jun-15, HIGHWAY & SLIP ROADS
08-Feb-15, SOL1, SOL5, SOL6
18-Jan-14, TEMPORARY DIVERSION FOR EXISTING
18-Jan-14, SR1 (CH 0+000 to CH 0+797)
18-Jan-14, GENERAL
Laying of Asphalt of Temp. Road over SR-1
Placing Plastic BarriersShift Traffic from Existing Northern Service Road to Temp. SR-1
11-Feb-14, TEMPORARY DIVERSION FOR EXISTING
11-Feb-14, SOL1-NORTH (CH 21+100 to CH 25+300)
11-Feb-14, GENERAL
Protection of services
Laying of Asphalt on Temp. new Road Adjacent to SOL1-NB
Placing of Plastic BarriersResolution of Falaj Relocation Under Temp. Diversion
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 2 of 17
Data Date: 30-Oct-13 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A1010 Shift Traffic from Existing Main Road NB to Temp. diversion 0 11-Feb-14 0 0 A1005 A6700, A2940, A2800, A5090, A1540, A2660, A3160, A5310
TEMPORARY DIVERSION FOR EXISTING SOUTHERN SERVICE ROADTEMPORARY DIVERSION FOR EXISTING SOUTHERN SERVICE ROAD 48 19-Jan-14 07-Mar-14 655
SR2 (CH 0+000 to CH 1+450)SR2 (CH 0+000 to CH 1+450) 48 19-Jan-14 07-Mar-14 655
GENERALGENERAL 48 19-Jan-14 07-Mar-14 655
A10490 Protection of services 15 19-Jan-14 02-Feb-14 0 0 A1270 A9940, A10500
A9940 Laying of Asphalt Adjacent to SR-2 30 03-Feb-14 04-Mar-14 655 M3 A1270, A10490, A1330, A1340, A1400, A1410A9950
A1330 Resolution of expropriation of Fuel Station (SR-2 CH 1+140) 0 25-Feb-14 0 0 A1270 A6800, A9940
A1340 Resolution of expropriation of Graveyard (SR-2 CH 0+900) 0 25-Feb-14 0 0 A1270 A6800, A9940
A1400 Resolution of expropriation of Al-Falaj Shopping (SR-2 CH 0+380) 0 25-Feb-14 0 0 A1270 A6800, A9940
A1410 Resolution of expropriation of Shopping Buildings (SR-2 CH 0+300) 0 25-Feb-14 0 0 A1270 A6800, A9940
A9950 Placing Plastic Barriers 3 05-Mar-14 07-Mar-14 0 0 A9940 A10340
A10340 Shift Traffic from Existing Southern Service Road Temp. SR-2 0 07-Mar-14 0 0 A9950 A9910
TEMPORARY DIVERSION FOR EXISTING HIGHWAY - SOUTH BOUNDTEMPORARY DIVERSION FOR EXISTING HIGHWAY - SOUTH BOUND 57 25-Jan-14 22-Mar-14 764
SOL1-SOUTH (CH 25+300 to CH 21+100)SOL1-SOUTH (CH 25+300 to CH 21+100) 57 25-Jan-14 22-Mar-14 764
GENERALGENERAL 57 25-Jan-14 22-Mar-14 764
A10500 Protection of services 15 25-Jan-14 08-Feb-14 0 0 A10490 A9910
A9910 Laying of Asphalt on Temp. Road Adjacent to SOL-1 SB over SOLs 4&7 35 09-Feb-14 15-Mar-14 764 M3 A1000, A10340, A10500 A9920
A9920 Placing Plastic Barriers 7 16-Mar-14 22-Mar-14 0 0 A9910 A9930
A9930 Shift Traffic from Existing Main Road SB to Temp. diversion 0 22-Mar-14 0 0 A9920 A2940, A2800, A10350, A2660, A4000, A1360
INVESTIGATIONINVESTIGATION 33 29-Dec-13 30-Jan-14 0
GEOTECHNICAL INVESTIGATIONGEOTECHNICAL INVESTIGATION 33 29-Dec-13 30-Jan-14 0
GENERALGENERAL 33 29-Dec-13 30-Jan-14 0
A6110 Site Survey 10 29-Dec-13 07-Jan-14 0 0 A6680 A6120
A6120 Setting up Drilling Rigs 7 08-Jan-14 14-Jan-14 0 0 A6110 A6130, A1540, A3160, A6140
A6130 Execution of Trial Pits 7 15-Jan-14 21-Jan-14 0 0 A6120 A6140
A6140 Execution of Trial Boreholes 7 15-Jan-14 21-Jan-14 0 0 A6130, A6120 A6150
A6150 (SPT) Test 5 22-Jan-14 26-Jan-14 0 0 A6140 A6160
A6160 Laboratory Testing Report 4 27-Jan-14 30-Jan-14 0 0 A6150 A6170
GENERAL CIVIL WORKSGENERAL CIVIL WORKS 114 12-Feb-14 05-Jun-14 11743
CLEARING & EXCAVATIONCLEARING & EXCAVATION 114 12-Feb-14 05-Jun-14 11743
GENERALGENERAL 114 12-Feb-14 05-Jun-14 11743
A5310 Clearing & Grubbing 30 12-Feb-14 13-Mar-14 4259 M2 A1010 A5320
A5320 Removal of Structures & Obstructures 60 26-Feb-14 26-Apr-14 1 LS A5310 A5330
A5330 Utilities Trench Ear thworks 60 26-Feb-14 26-Apr-14 1641 M3 A5320 A5340, A1450
A5340 Structural & Road Way Excavation 100 26-Feb-14 05-Jun-14 5842 M3 A5330 A4580
UTILITIESUTILITIES 56 28-Feb-14 24-Apr-14 14200
GENERALGENERAL 56 28-Feb-14 24-Apr-14 14200
TELEPHONETELEPHONE 30 28-Feb-14 29-Mar-14 2200
A1450 Installation of New (GTO) Omantal Line 12 28-Feb-14 11-Mar-14 1100 0 A5330, A6590 A1455, A1890, A1360, A1990
A1455 Obtain Shutdown & Connect to Existing 15 12-Mar-14 26-Mar-14 0 0 A1450 A1457
A1457 Remove & Dispose Existing (GTO) Omantal Line 3 27-Mar-14 29-Mar-14 1100 0 A1455 A5030
ELECTRICAL (11 KV)ELECTRICAL (11 KV) 56 28-Feb-14 24-Apr-14 6400
A1360 Installation of New 11 Kv Overhead Lines 30 28-Feb-14 29-Mar-14 3000 0 A1450, A6530, A9930 A1365, A1970, A1280, A1376
A1365 Obtain Shutdown & Connect to Existing 15 30-Mar-14 13-Apr-14 0 0 A1360 A1367
A1367 Remove & Dispose Existing 11 Kv Overhead Lines 7 14-Apr-14 20-Apr-14 400 0 A1365 A1376, A1315
A1376 Remove & Dispose Existing 11 Kv Under Ground Lines 4 21-Apr-14 24-Apr-14 3000 0 A1367, A1360 A5020
ELECTRICAL (33 KV)ELECTRICAL (33 KV) 10 07-Apr-14 16-Apr-14 400
A1335 Obtain Shutdown & Connect to Existing 7 07-Apr-14 13-Apr-14 0 0 A0000 A1315
A1315 Remove & Dispose Existing 33 Kv Ovehead Lines 3 14-Apr-14 16-Apr-14 400 0 A1367, A1335 A1300
WATERLINESWATERLINES 47 05-Mar-14 20-Apr-14 5200
A1280 Installation of New Irrigation Pipes 25 05-Mar-14 29-Mar-14 2600 0 A1360, A6560 A1290, A1850
A1290 Obtain Shutdown & Connect to Existing 15 30-Mar-14 13-Apr-14 0 0 A1280 A1300, A2950
A1300 Remove & Dispose Existing Irrigation Pipes 7 14-Apr-14 20-Apr-14 2600 0 A1290, A1315 A2800, A2660, A2940
UTILITIES (P.S.)UTILITIES (P.S.) 54 05-Mar-14 27-Apr-14 0
GENERALGENERAL 54 05-Mar-14 27-Apr-14 0
J J J J J J J J J
2014 2015 2016
Shift Traffic from Existing Main Road NB to Temp. diversion
07-Mar-14, TEMPORARY DIVERSION FOR EXISTIN
07-Mar-14, SR2 (CH 0+000 to CH 1+450)
07-Mar-14, GENERAL
Protection of services
Laying of Asphalt Adjacent to SR-2Resolution of expropriation of Fuel Station (SR-2 CH 1+140)
Resolution of expropriation of Graveyard (SR-2 CH 0+900)
Resolution of expropriation of Al-Falaj Shopping (SR-2 CH 0+380)
Resolution of expropriation of Shopping Buildings (SR-2 CH 0+300)
Placing Plastic BarriersShift Traffic from Existing Southern Service Road Temp. SR-2
22-Mar-14, TEMPORARY DIVERSION FOR EXISTIN
22-Mar-14, SOL1-SOUTH (CH 25+300 to CH 21+100)
22-Mar-14, GENERAL
Protection of services
Laying of Asphalt on Temp. Road Adjacent to SOL-1 S
Placing Plastic BarriersShift Traffic from Existing Main Road SB to Temp. diversion
30-Jan-14, INVESTIGATION
30-Jan-14, GEOTECHNICAL INVESTIGATION
30-Jan-14, GENERAL
Site Survey
Setting up Drilling Rigs
Execution of Trial Pits
Execution of Trial Boreholes
(SPT) Test
Laboratory Testing Report05-Jun-14, GENERAL CIVIL WORKS
05-Jun-14, CLEARING & EXCAVATION
05-Jun-14, GENERAL
Clearing & Grubbing
Removal of Structures & Obstructures
Utilities Trench Ear thworks
Structural & Road Way Excavation24-Apr-14, UTILITIES
24-Apr-14, GENERAL
29-Mar-14, TELEPHONE
Installation of New (GTO) Omantal Line
Obtain Shutdown & Connect to Existing
Remove & Dispose Existing (GTO) Omantal Line24-Apr-14, ELECTRICAL (11 KV)
Installation of New 11 Kv Overhead Lines
Obtain Shutdown & Connect to Existing
Remove & Dispose Existing 11 Kv Overhead Lines
Remove & Dispose Existing 11 Kv Under Ground Lines16-Apr-14, ELECTRICAL (33 KV)
Obtain Shutdown & Connect to Existing
Remove & Dispose Existing 33 Kv Ovehead Lines20-Apr-14, WATERLINES
Installation of New Irrigation Pipes
Obtain Shutdown & Connect to Existing
Remove & Dispose Existing Irrigation Pipes27-Apr-14, UTILITIES (P.S.)
27-Apr-14, GENERAL
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 3 of 17
Data Date: 30-Oct-13 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
TELEPHONETELEPHONE 30 05-Mar-14 03-Apr-14 0
A1890 Provide & Install New Utilities 12 05-Mar-14 16-Mar-14 0 0 A1450, A6590 A1900, A1920
A1920 Remove & Relocate of Existing Utilities 22 05-Mar-14 26-Mar-14 0 0 A1890 A1910
A1900 Obtain Shutdown & Connect to Existing 15 17-Mar-14 31-Mar-14 0 0 A1890 A1910
A1910 Remove & Dispose of Existing Utilities 3 01-Apr-14 03-Apr-14 0 0 A1900, A1920 A1990
ELECTRICALELECTRICAL 54 05-Mar-14 27-Apr-14 0
A1970 Provide & Install New Utilities 30 05-Mar-14 03-Apr-14 0 0 A1360 A1980, A2000
A2000 Remove & Relocate of Existing Utilities 47 05-Mar-14 20-Apr-14 0 0 A1970 A1990
A1980 Obtain Shutdown & Connect to Existing 15 04-Apr-14 18-Apr-14 0 0 A1970 A1990
A1990 Remove & Dispose of Existing Utilities 7 21-Apr-14 27-Apr-14 0 0 A1980, A2000, A1910, A1450A1870
WATERLINESWATERLINES 49 10-Mar-14 27-Apr-14 0
A1850 Provide & Install New Utilities 25 10-Mar-14 03-Apr-14 0 0 A1280 A1860, A1880
A1880 Remove & Relocate of Existing Utilities 42 10-Mar-14 20-Apr-14 0 0 A1850 A1870
A1860 Obtain Shutdown & Connect to Existing 15 04-Apr-14 18-Apr-14 0 0 A1850 A1870
A1870 Remove & Dispose of Existing Utilities 7 21-Apr-14 27-Apr-14 0 0 A1860, A1880, A1990 A6100
BOX CULVERTS - STAGE 1BOX CULVERTS - STAGE 1 208 02-Apr-14 26-Oct-14 27584
GENERALGENERAL 208 02-Apr-14 26-Oct-14 27584
52 CELLS BOX CULVERT AT CH 21+98552 CELLS BOX CULVERT AT CH 21+985 149 02-Apr-14 28-Aug-14 10543
A2940 Structural Excavation 19 02-Apr-14 20-Apr-14 1110 M3 A1010, A9930, A1300 A2950, A1795
A2950 Blinding of Concrete 17 11-Apr-14 27-Apr-14 194 M3 A2940, A1290 A2960
A2960 Casting of Base Slab 93 13-Apr-14 14-Jul-14 820 M3 A2950 A2970
A2970 Casting of Walls 90 01-May-14 29-Jul-14 793 M3 A2960 A2980, A3000
A2980 Casting of Top Slab 92 17-May-14 16-Aug-14 811 M3 A2970 A2990, A2890
A3000 Casting of Apron Slab & W ing Walls 60 19-Jun-14 17-Aug-14 529 M3 A2970 A2990
A2990 Backfilling 11 18-Aug-14 28-Aug-14 6286 M3 A2980, A3000 A5350
9 CELLS BOX CULVERT AT CH 22+6509 CELLS BOX CULVERT AT CH 22+650 68 15-Apr-14 21-Jun-14 3477
A2800 Structural Excavation 6 15-Apr-14 20-Apr-14 351 M3 A1010, A9930, A1300 A2810
A2810 Blinding of Concrete 4 19-Apr-14 22-Apr-14 46 M3 A2800 A2820
A2820 Casting of Base Slab 18 21-Apr-14 08-May-14 159 M3 A2810 A2830
A2830 Casting of Walls 32 05-May-14 05-Jun-14 282 M3 A2820 A2840, A2860
A2860 Casting of Apron Slab & W ing Walls 22 31-May-14 21-Jun-14 194 M3 A2830 A2850, A10400
A2840 Casting of Top Slab 18 02-Jun-14 19-Jun-14 159 M3 A2830 A2850, A10370
A2850 Backfilling 4 18-Jun-14 21-Jun-14 2286 M3 A2840, A2860 A5350
1 CELL BOX CULVERT AT CH 23+0001 CELL BOX CULVERT AT CH 23+000 20 17-Jun-14 06-Jul-14 875
A10350 Structural Excavation 2 17-Jun-14 18-Jun-14 117 M3 A9930 A10360
A10360 Blinding of Concrete 1 19-Jun-14 19-Jun-14 11 M3 A10350 A10370
A10370 Casting of Base Slab 4 20-Jun-14 23-Jun-14 35 M3 A10360, A2840 A10380
A10380 Casting of Walls 8 24-Jun-14 01-Jul-14 71 M3 A10370 A10390, A10400
A10390 Casting of Top Slab 4 02-Jul-14 05-Jul-14 35 M3 A10380 A10410
A10400 Casting of Apron Slab & W ing Walls 4 03-Jul-14 06-Jul-14 35 M3 A10380, A2860 A10410, A2650, A2590
A10410 Backfilling 1 06-Jul-14 06-Jul-14 571 M3 A10390, A10400 A5350
1 CELLS BOX CULVERT AT CH 23+7601 CELLS BOX CULVERT AT CH 23+760 20 03-Jul-14 22-Jul-14 964
A2590 Structural Excavation 2 03-Jul-14 04-Jul-14 117 M3 A10400 A2600
A2600 Blinding of Concrete 1 05-Jul-14 05-Jul-14 11 M3 A2590 A2610
A2610 Casting of Base Slab 4 06-Jul-14 09-Jul-14 53 M3 A2600 A2620
A2620 Casting of Walls 8 10-Jul-14 17-Jul-14 88 M3 A2610 A2630, A2650
A2630 Casting of Top Slab 4 18-Jul-14 21-Jul-14 53 M3 A2620 A2330
A2650 Casting of Apron Slab & W ing Walls 4 19-Jul-14 22-Jul-14 71 M3 A2620, A10400 A2640, A2370, A2310
A2640 Backfilling 1 22-Jul-14 22-Jul-14 571 M3 A2650 A5350
2 CELL BOX CULVERT AT CH 23+2002 CELL BOX CULVERT AT CH 23+200 28 19-Jul-14 15-Aug-14 875
A2310 Structural Excavation 2 19-Jul-14 20-Jul-14 117 M3 A2650 A2320
A2320 Blinding of Concrete 1 21-Jul-14 21-Jul-14 11 M3 A2310 A2330
A2330 Casting of Base Slab 6 22-Jul-14 27-Jul-14 35 M3 A2320, A2630 A2340
A2340 Casting of Walls 10 28-Jul-14 06-Aug-14 71 M3 A2330 A2350, A2370
J J J J J J J J J
2014 2015 2016
03-Apr-14, TELEPHONE
Provide & Install New Utilities
Remove & Relocate of Existing Utilities
Obtain Shutdown & Connect to Existing
Remove & Dispose of Existing Utilities27-Apr-14, ELECTRICAL
Provide & Install New Utilities
Remove & Relocate of Existing Utilities
Obtain Shutdown & Connect to Existing
Remove & Dispose of Existing Utilities27-Apr-14, WATERLINES
Provide & Install New Utilities
Remove & Relocate of Existing Utilities
Obtain Shutdown & Connect to Existing
Remove & Dispose of Existing Utilities26-Oct-14, BOX CULVERTS - STAGE 1
26-Oct-14, GENERAL
28-Aug-14, 52 CELLS BOX CULVERT AT CH 21+985
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling21-Jun-14, 9 CELLS BOX CULVERT AT CH 22+650
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Apron Slab & W ing Walls
Casting of Top Slab
Backfilling06-Jul-14, 1 CELL BOX CULVERT AT CH 23+000
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling22-Jul-14, 1 CELLS BOX CULVERT AT CH 23+760
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling15-Aug-14, 2 CELL BOX CULVERT AT CH 23+200
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 4 of 17
Data Date: 30-Oct-13 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A2350 Casting of Top Slab 8 07-Aug-14 14-Aug-14 35 M3 A2340 A2360, A2400
A2370 Casting of Apron Slab & W ing Walls 6 08-Aug-14 13-Aug-14 35 M3 A2340, A2650 A2360, A2440, A2380
A2360 Backfilling 1 15-Aug-14 15-Aug-14 571 M3 A2350, A2370 A5350
1 CELL BOX CULVERT AT CH 23+9971 CELL BOX CULVERT AT CH 23+997 20 12-Aug-14 31-Aug-14 875
A2380 Structural Excavation 2 12-Aug-14 13-Aug-14 117 M3 A2370 A2390
A2390 Blinding of Concrete 1 14-Aug-14 14-Aug-14 11 M3 A2380 A2400
A2400 Casting of Base Slab 4 15-Aug-14 18-Aug-14 35 M3 A2390, A2350 A2410
A2410 Casting of Walls 8 19-Aug-14 26-Aug-14 71 M3 A2400 A2420, A2440
A2420 Casting of Top Slab 4 27-Aug-14 30-Aug-14 35 M3 A2410
A2440 Casting of Apron Slab & W ing Walls 4 28-Aug-14 31-Aug-14 35 M3 A2410, A2370 A2430
A2430 Backfilling 1 31-Aug-14 31-Aug-14 571 M3 A2440 A5350
5 CELLS BOX CULVERT AT CH 23+5005 CELLS BOX CULVERT AT CH 23+500 38 16-Apr-14 23-May-14 1834
A2660 Structural Excavation 5 16-Apr-14 20-Apr-14 292 M3 A9930, A1010, A1300 A2670
A2670 Blinding of Concrete 1 21-Apr-14 21-Apr-14 11 M3 A2660 A2680
A2680 Casting of Base Slab 8 22-Apr-14 29-Apr-14 71 M3 A2670 A2690
A2690 Casting of Walls 14 30-Apr-14 13-May-14 123 M3 A2680 A2700, A2720
A2720 Casting of Apron Slab & W ing Walls 14 10-May-14 23-May-14 123 M3 A2690 A2710, A2230
A2700 Casting of Top Slab 8 14-May-14 21-May-14 71 M3 A2690 A2710, A2190, A2170
A2710 Backfilling 2 22-May-14 23-May-14 1143 M3 A2700, A2720 A5350
3 CELLS BOX CULVERT AT CH 21+2603 CELLS BOX CULVERT AT CH 21+260 30 18-May-14 16-Jun-14 1057
A2170 Structural Excavation 3 18-May-14 20-May-14 175 M3 A2700 A2180
A2180 Blinding of Concrete 1 21-May-14 21-May-14 11 M3 A2170 A2190
A2190 Casting of Base Slab 6 22-May-14 27-May-14 53 M3 A2180, A2700 A2200
A2200 Casting of Walls 12 28-May-14 08-Jun-14 106 M3 A2190 A2210, A2230
A2230 Casting of Apron Slab & W ing Walls 10 07-Jun-14 16-Jun-14 88 M3 A2200, A2720 A2220, A2300
A2210 Casting of Top Slab 6 09-Jun-14 14-Jun-14 53 M3 A2200 A2220, A2260, A2240
A2220 Backfilling 1 16-Jun-14 16-Jun-14 571 M3 A2210, A2230 A5350
1 CELL BOX CULVERT AT CH 21+4851 CELL BOX CULVERT AT CH 21+485 20 12-Jun-14 01-Jul-14 875
A2240 Structural Excavation 2 12-Jun-14 13-Jun-14 117 M3 A2210 A2250
A2250 Blinding of Concrete 1 14-Jun-14 14-Jun-14 11 M3 A2240 A2260
A2260 Casting of Base Slab 4 15-Jun-14 18-Jun-14 35 M3 A2250, A2210 A2270
A2270 Casting of Walls 8 19-Jun-14 26-Jun-14 71 M3 A2260 A2280, A2300
A2280 Casting of Top Slab 4 27-Jun-14 30-Jun-14 35 M3 A2270 A2290, A2750, A2540
A2300 Casting of Apron Slab & W ing Walls 4 28-Jun-14 01-Jul-14 35 M3 A2270, A2230 A2290, A2790, A2730
A2290 Backfilling 1 01-Jul-14 01-Jul-14 571 M3 A2280, A2300 A5350
2 CELLS BOX CULVERT AT CH 22+2002 CELLS BOX CULVERT AT CH 22+200 26 28-Jun-14 23-Jul-14 964
A2730 Structural Excavation 2 28-Jun-14 29-Jun-14 117 M3 A2300 A2740
A2740 Blinding of Concrete 1 30-Jun-14 30-Jun-14 11 M3 A2730 A2750
A2750 Casting of Base Slab 6 01-Jul-14 06-Jul-14 53 M3 A2740, A2280 A2760
A2760 Casting of Walls 10 07-Jul-14 16-Jul-14 88 M3 A2750 A2770, A2790
A2790 Casting of Apron Slab & W ing Walls 8 16-Jul-14 23-Jul-14 71 M3 A2760, A2300 A2780, A2510
A2770 Casting of Top Slab 6 17-Jul-14 22-Jul-14 53 M3 A2760 A2780, A2470, A2450
A2780 Backfilling 1 23-Jul-14 23-Jul-14 571 M3 A2770, A2790 A5350
1 CELL BOX CULVERT AT CH 24+2351 CELL BOX CULVERT AT CH 24+235 20 20-Jul-14 08-Aug-14 875
A2450 Structural Excavation 2 20-Jul-14 21-Jul-14 117 M3 A2770 A2460
A2460 Blinding of Concrete 1 22-Jul-14 22-Jul-14 11 M3 A2450 A2470
A2470 Casting of Base Slab 4 23-Jul-14 26-Jul-14 35 M3 A2460, A2770 A2480
A2480 Casting of Walls 8 27-Jul-14 03-Aug-14 71 M3 A2470 A2490, A2510
A2490 Casting of Top Slab 4 04-Aug-14 07-Aug-14 35 M3 A2480 A2500, A2890, A2540
A2510 Casting of Apron Slab & W ing Walls 4 05-Aug-14 08-Aug-14 35 M3 A2480, A2790 A2500, A2520
A2500 Backfilling 1 08-Aug-14 08-Aug-14 571 M3 A2490, A2510 A5350
1 CELL BOX CULVERT AT CH 24+5701 CELL BOX CULVERT AT CH 24+570 22 05-Aug-14 26-Aug-14 893
A2520 Structural Excavation 2 05-Aug-14 06-Aug-14 117 M3 A2510 A2530
A2530 Blinding of Concrete 1 07-Aug-14 07-Aug-14 11 M3 A2520 A2540
J J J J J J J J J
2014 2015 2016
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling31-Aug-14, 1 CELL BOX CULVERT AT CH 23+997
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling23-May-14, 5 CELLS BOX CULVERT AT CH 23+500
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Apron Slab & W ing Walls
Casting of Top Slab
Backfilling16-Jun-14, 3 CELLS BOX CULVERT AT CH 21+260
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Apron Slab & W ing Walls
Casting of Top Slab
Backfilling01-Jul-14, 1 CELL BOX CULVERT AT CH 21+485
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling23-Jul-14, 2 CELLS BOX CULVERT AT CH 22+200
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Apron Slab & W ing Walls
Casting of Top Slab
Backfilling08-Aug-14, 1 CELL BOX CULVERT AT CH 24+235
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling26-Aug-14, 1 CELL BOX CULVERT AT CH 24+570
Structural Excavation
Blinding of Concrete
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 5 of 17
Data Date: 30-Oct-13 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A2540 Casting of Base Slab 5 08-Aug-14 12-Aug-14 44 M3 A2530, A2280, A2490 A2550
A2550 Casting of Walls 8 13-Aug-14 20-Aug-14 71 M3 A2540 A2560, A2580
A2560 Casting of Top Slab 5 21-Aug-14 25-Aug-14 44 M3 A2550 A2570, A2890, A2870
A2580 Casting of Apron Slab & W ing Walls 4 23-Aug-14 26-Aug-14 35 M3 A2550 A2570, A5170
A2570 Backfilling 1 26-Aug-14 26-Aug-14 571 M3 A2560, A2580 A5350
8 CELLS BOX CULVERT AT CH 21+8388 CELLS BOX CULVERT AT CH 21+838 68 20-Aug-14 26-Oct-14 3477
A2870 Structural Excavation 6 20-Aug-14 25-Aug-14 351 M3 A2560 A2880
A2880 Blinding of Concrete 4 24-Aug-14 27-Aug-14 46 M3 A2870 A2890
A2890 Casting of Base Slab 18 26-Aug-14 12-Sep-14 159 M3 A2880, A2980, A2490, A2560A2900
A2900 Casting of Walls 32 09-Sep-14 10-Oct-14 282 M3 A2890 A2910, A2930
A2930 Casting of Apron Slab & W ing Walls 22 05-Oct-14 26-Oct-14 194 M3 A2900 A2920, A5170
A2910 Casting of Top Slab 18 07-Oct-14 24-Oct-14 159 M3 A2900 A2920
A2920 Backfilling 4 23-Oct-14 26-Oct-14 2286 M3 A2910, A2930 A5350
PEDESTRIAN UNDERPASS 2 (SOL1 CH 23+300) - STAGE 1PEDESTRIAN UNDERPASS 2 (SOL1 CH 23+300) - STAGE 1 201 11-Apr-14 28-Oct-14 6329
GENERALGENERAL 201 11-Apr-14 28-Oct-14 6329
UNDERPASS STRUCTUREUNDERPASS STRUCTURE 130 11-Apr-14 18-Aug-14 5517
A1795 Structural Excavation 10 11-Apr-14 20-Apr-14 584 M3 A2940 A1800
A1800 Blinding of Concrete 12 14-Apr-14 25-Apr-14 137 M3 A1795 A1810
A1810 Casting of Base Slab 35 23-Apr-14 27-May-14 309 M3 A1800 A1820, A3070
A1820 Casting of Walls 70 14-May-14 22-Jul-14 617 M3 A1810 A1830, A3055
A1830 Casting of Top Slab 50 24-Jun-14 12-Aug-14 441 M3 A1820 A3010, A8300, A10290
A3010 Backfilling 6 13-Aug-14 18-Aug-14 3429 M3 A1830 A5350
ENTRANCE & EXISTENTRANCE & EXIST 77 13-Aug-14 28-Oct-14 812
A10290 Casting of Floor Slab 22 13-Aug-14 03-Sep-14 194 M3 A1830 A10300
A10300 Casting of Walls 35 04-Sep-14 08-Oct-14 309 M3 A10290 A10310, A10320
A10320 Casting of Landing Slabs & Stair Case 35 24-Sep-14 28-Oct-14 309 M3 A10300 A10310
A10310 Casing of Beams & Roof Slab 20 09-Oct-14 28-Oct-14 0 0 A10300, A10320 A6100
PEDESTRIAN UNDERPASS 1 (SOL1 CH 22+800) - STAGE 1PEDESTRIAN UNDERPASS 1 (SOL1 CH 22+800) - STAGE 1 199 18-May-14 02-Dec-14 6329
GENERALGENERAL 199 18-May-14 02-Dec-14 6329
UNDERPASS STRUCTUREUNDERPASS STRUCTURE 128 18-May-14 22-Sep-14 5517
A3055 Structural Excavation 10 18-May-14 27-May-14 584 M3 A1820 A3060
A3060 Blinding of Concrete 12 21-May-14 01-Jun-14 137 M3 A3055 A3070
A3070 Casting of Base Slab 35 28-May-14 01-Jul-14 309 M3 A3060, A1810 A3080
A3080 Casting of Walls 70 18-Jun-14 26-Aug-14 617 M3 A3070 A3090
A3090 Casting of Top Slab 50 29-Jul-14 16-Sep-14 441 M3 A3080 A3120, A10250
A3120 Backfilling 6 17-Sep-14 22-Sep-14 3429 M3 A3090 A8400, A5350
ENTRANCE & EXISTENTRANCE & EXIST 77 17-Sep-14 02-Dec-14 812
A10250 Casting of Floor Slab 22 17-Sep-14 08-Oct-14 194 M3 A3090 A10260
A10260 Casting of Walls 35 09-Oct-14 12-Nov-14 309 M3 A10250 A10270, A10280
A10280 Casting of Landing Slabs & Stair Case 35 29-Oct-14 02-Dec-14 309 M3 A10260 A10270
A10270 Casing of Beams & Roof Slab 20 13-Nov-14 02-Dec-14 0 0 A10260, A10280 A6100
FLYOVER AT FALAJ AL QABIL (NORTH BOUND)FLYOVER AT FALAJ AL QABIL (NORTH BOUND) 243 12-Feb-14 12-Oct-14 73649
SUBSTRUCTURESSUBSTRUCTURES 123 12-Feb-14 14-Jun-14 69375
PIER P3PIER P3 63 12-Feb-14 15-Apr-14 1903
A1540 Boring & Casting of Piles 14 12-Feb-14 25-Feb-14 269 LM A6500, A1010, A6120 A1550, A5020, A1590
A1550 Blinding for Pier Pile Cap 3 26-Feb-14 28-Feb-14 34 M3 A1540 A1560
A1560 Casting of Pier Pile Cap 15 01-Mar-14 15-Mar-14 132 M3 A1550 A1570
A1570 Bituminous Paint 3 16-Mar-14 18-Mar-14 1221 M2 A1560 A1580
A1580 Casting of Pier & Pier Cap 28 19-Mar-14 15-Apr-14 247 M3 A1570 A1640, A3500
ABUTMENT AB1ABUTMENT AB1 76 26-Feb-14 12-May-14 29968
A1590 Boring & Casting of Piles 20 26-Feb-14 17-Mar-14 384 LM A1540 A1600, A3310
A1600 Blinding for Abutment Pile Cap 7 18-Mar-14 24-Mar-14 80 M3 A1590 A1610, A3030
A3030 Fixing of MSE Wall 46 18-Mar-14 02-May-14 0 M2 A1600 A3110
A1610 Casting of Abutment Pile Cap 42 25-Mar-14 05-May-14 370 M3 A1600 A1620, A1640
J J J J J J J J J
2014 2015 2016
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling26-Oct-14, 8 CELLS BOX CULVERT AT CH 21+838
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Apron Slab & W ing Walls
Casting of Top Slab
Backfilling28-Oct-14, PEDESTRIAN UNDERPASS 2
28-Oct-14, GENERAL
18-Aug-14, UNDERPASS STRUCTURE
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Backfilling28-Oct-14, ENTRANCE & EXIST
Casting of Floor Slab
Casting of Walls
Casting of Landing Slabs & Stair Case
Casing of Beams & Roof Slab02-Dec-14, PEDESTRIAN UNDERPAS
02-Dec-14, GENERAL
22-Sep-14, UNDERPASS STRUCTURE
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Backfilling02-Dec-14, ENTRANCE & EXIST
Casting of Floor Slab
Casting of Walls
Casting of Landing Slabs & Stair Case
Casing of Beams & Roof Slab12-Oct-14, FLYOVER AT FALAJ AL QABIL
14-Jun-14, SUBSTRUCTURES
15-Apr-14, PIER P3
Boring & Casting of Piles
Blinding for Pier Pile Cap
Casting of Pier Pile Cap
Bituminous Paint
Casting of Pier & Pier Cap12-May-14, ABUTMENT AB1
Boring & Casting of Piles
Blinding for Abutment Pile Cap
Fixing of MSE Wall
Casting of Abutment Pile Cap
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 6 of 17
Data Date: 30-Oct-13 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A3110 Backfilling 46 28-Mar-14 12-May-14 26286 M3 A3030 A5350
A1620 Bituminous Paint 7 06-May-14 12-May-14 2848 M2 A1610 A5170
PIER P4PIER P4 62 18-Mar-14 18-May-14 1884
A3310 Boring & Casting of Piles 13 18-Mar-14 30-Mar-14 250 LM A1590 A3320, A3360
A3320 Blinding for Pier Pile Cap 3 31-Mar-14 02-Apr-14 34 M3 A3310 A3330
A3330 Casting of Pier Pile Cap 15 03-Apr-14 17-Apr-14 132 M3 A3320 A3340
A3340 Bituminous Paint 3 18-Apr-14 20-Apr-14 1221 M2 A3330 A3350
A3350 Casting of Pier & Pier Cap 28 21-Apr-14 18-May-14 247 M3 A3340 A3500
ABUTMENT AB2ABUTMENT AB2 76 31-Mar-14 14-Jun-14 29968
A3360 Boring & Casting of Piles 20 31-Mar-14 19-Apr-14 384 LM A3310 A3370, A4000
A3370 Blinding for Abutment Pile Cap 7 20-Apr-14 26-Apr-14 80 M3 A3360 A3380, A3410
A3410 Fixing of MSE Wall 46 20-Apr-14 04-Jun-14 0 M2 A3370 A3420
A3380 Casting of Abutment Pile Cap 42 27-Apr-14 07-Jun-14 370 M3 A3370 A3390, A3500
A3420 Backfilling 46 30-Apr-14 14-Jun-14 26286 M3 A3410 A5350
A3390 Bituminous Paint 7 02-Jun-14 09-Jun-14 2848 M2 A3380 A5170
PIER P2PIER P2 62 12-Feb-14 14-Apr-14 1884
A3160 Boring & Casting of Piles 13 12-Feb-14 24-Feb-14 250 LM A6500, A6120, A1010 A3170, A3210
A3170 Blinding for Pier Pile Cap 3 25-Feb-14 27-Feb-14 34 M3 A3160 A3180
A3180 Casting of Pier Pile Cap 15 28-Feb-14 14-Mar-14 132 M3 A3170 A3190
A3190 Bituminous Paint 3 15-Mar-14 17-Mar-14 1221 M2 A3180 A3200
A3200 Casting of Pier & Pier Cap 28 18-Mar-14 14-Apr-14 247 M3 A3190 A1640
PIER P1PIER P1 62 25-Feb-14 27-Apr-14 1884
A3210 Boring & Casting of Piles 13 25-Feb-14 09-Mar-14 250 LM A3160 A3220, A3260
A3220 Blinding for Pier Pile Cap 3 10-Mar-14 12-Mar-14 34 M3 A3210 A3230
A3230 Casting of Pier Pile Cap 15 13-Mar-14 27-Mar-14 132 M3 A3220 A3240
A3240 Bituminous Paint 3 28-Mar-14 30-Mar-14 1221 M2 A3230 A3250
A3250 Casting of Pier & Pier Cap 28 31-Mar-14 27-Apr-14 247 M3 A3240 A1640
PIER P5PIER P5 62 10-Mar-14 10-May-14 1884
A3260 Boring & Casting of Piles 13 10-Mar-14 22-Mar-14 250 LM A3210 A3270, A4100
A3270 Blinding for Pier Pile Cap 3 23-Mar-14 25-Mar-14 34 M3 A3260 A3280
A3280 Casting of Pier Pile Cap 15 26-Mar-14 09-Apr-14 132 M3 A3270 A3290
A3290 Bituminous Paint 3 10-Apr-14 12-Apr-14 1221 M2 A3280 A3300
A3300 Casting of Pier & Pier Cap 28 13-Apr-14 10-May-14 247 M3 A3290 A3500
SUPERSTRUCTURESUPERSTRUCTURE 135 28-Apr-14 09-Sep-14 3660
SPAN BETWEEN AB1 & P3SPAN BETWEEN AB1 & P3 114 28-Apr-14 19-Aug-14 1830
A1640 Erection of Scaffold & Shutter 55 28-Apr-14 21-Jun-14 0 0 A3250, A1580, A1610, A3200, A6470A1650
A1650 Fixing of Pot Bearings 7 22-Jun-14 28-Jun-14 12 NO. A1640 A1660
A1660 Casting of Box Girder 21 29-Jun-14 19-Jul-14 1818 M3 A1650 A1670
A1670 Prestressing Operation 10 20-Jul-14 29-Jul-14 0 0 A1660, A6620 A6760, A6790, A4550
A6760 Deshuttering of Scaffold 21 30-Jul-14 19-Aug-14 0 0 A1670 A3850
SPAN BETWEEN AB2 & P3SPAN BETWEEN AB2 & P3 114 19-May-14 09-Sep-14 1830
A3500 Erection of Scaffold & Shutter 55 19-May-14 12-Jul-14 0 0 A1580, A3300, A3380, A3350, A6470A3510
A3510 Fixing of Pot Bearings 7 13-Jul-14 19-Jul-14 12 NO. A3500 A3520
A3520 Casting of Box Girder 21 20-Jul-14 09-Aug-14 1818 M3 A3510 A3530
A3530 Prestressing Operation 10 10-Aug-14 19-Aug-14 0 0 A3520 A3570, A4550
A3570 Deshuttering of Scaffold 21 20-Aug-14 09-Sep-14 0 0 A3530 A4310
FINISHING WORKSFINISHING WORKS 29 14-Sep-14 12-Oct-14 614
GENERALGENERAL 29 14-Sep-14 12-Oct-14 614
A4550 Concrete Bridge Parapet (N.J Barrier) 22 14-Sep-14 05-Oct-14 555 M A6290, A3530, A1670, A5080A4560
A4560 Laying of Bituminous Wearing Course 6 30-Sep-14 05-Oct-14 0 0 A4550 A4570, A5450, A5430
A4570 Fixing of Expansion Joints 7 06-Oct-14 12-Oct-14 59 M A4560 A3940
FLYOVER AT FALAJ AL QABIL (SOUTH BOUND)FLYOVER AT FALAJ AL QABIL (SOUTH BOUND) 285 23-Mar-14 01-Jan-15 73914
SUBSTRUCTURESSUBSTRUCTURES 123 23-Mar-14 23-Jul-14 69410
PIER P2PIER P2 62 20-Apr-14 20-Jun-14 1884
J J J J J J J J J
2014 2015 2016
Backfilling
Bituminous Paint18-May-14, PIER P4
Boring & Casting of Piles
Blinding for Pier Pile Cap
Casting of Pier Pile Cap
Bituminous Paint
Casting of Pier & Pier Cap14-Jun-14, ABUTMENT AB2
Boring & Casting of Piles
Blinding for Abutment Pile Cap
Fixing of MSE Wall
Casting of Abutment Pile Cap
Backfilling
Bituminous Paint14-Apr-14, PIER P2
Boring & Casting of Piles
Blinding for Pier Pile Cap
Casting of Pier Pile Cap
Bituminous Paint
Casting of Pier & Pier Cap27-Apr-14, PIER P1
Boring & Casting of Piles
Blinding for Pier Pile Cap
Casting of Pier Pile Cap
Bituminous Paint
Casting of Pier & Pier Cap10-May-14, PIER P5
Boring & Casting of Piles
Blinding for Pier Pile Cap
Casting of Pier Pile Cap
Bituminous Paint
Casting of Pier & Pier Cap09-Sep-14, SUPERSTRUCTURE
19-Aug-14, SPAN BETWEEN AB1 & P3
Erection of Scaffold & Shutter
Fixing of Pot Bearings
Casting of Box Girder
Prestressing Operation
Deshuttering of Scaffold09-Sep-14, SPAN BETWEEN AB2 & P3
Erection of Scaffold & Shutter
Fixing of Pot Bearings
Casting of Box Girder
Prestressing Operation
Deshuttering of Scaffold12-Oct-14, FINISHING WORKS
12-Oct-14, GENERAL
Concrete Bridge Parapet (N.J Barrier)
Laying of Bituminous Wearing Course
Fixing of Expansion Joints01-Jan-15, FLYOVER AT FALAJ AL Q
23-Jul-14, SUBSTRUCTURES
20-Jun-14, PIER P2
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 7 of 17
Data Date: 30-Oct-13 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A4000 Boring & Casting of Piles 13 20-Apr-14 02-May-14 250 LM A3360, A9930 A4010, A3800
A4010 Blinding for Pier Pile Cap 3 03-May-14 05-May-14 34 M3 A4000 A4020
A4020 Casting of Pier Pile Cap 15 06-May-14 20-May-14 132 M3 A4010 A4030
A4030 Bituminous Paint 3 21-May-14 23-May-14 1221 M2 A4020 A4040
A4040 Casting of Pier & Pier Cap 28 24-May-14 20-Jun-14 247 M3 A4030 A4310
ABUTMENT AB1ABUTMENT AB1 79 03-May-14 20-Jul-14 29995
A3800 Boring & Casting of Piles 20 03-May-14 22-May-14 384 LM A4000 A3810, A3950
A3810 Blinding for Abutment Pile Cap 7 23-May-14 29-May-14 80 M3 A3800 A3820, A4150
A4150 Fixing of MSE Wall 46 23-May-14 07-Jul-14 0 M2 A3810 A4160
A3820 Casting of Abutment Pile Cap 45 30-May-14 13-Jul-14 397 M3 A3810 A3830, A4310
A4160 Backfilling 46 04-Jun-14 20-Jul-14 26286 M3 A4150 A5350
A3830 Bituminous Paint 7 14-Jul-14 20-Jul-14 2848 M2 A3820 A5170
PIER P5PIER P5 62 23-May-14 23-Jul-14 1884
A3950 Boring & Casting of Piles 13 23-May-14 04-Jun-14 250 LM A3800 A3960
A3960 Blinding for Pier Pile Cap 3 05-Jun-14 07-Jun-14 34 M3 A3950 A3970
A3970 Casting of Pier Pile Cap 15 08-Jun-14 22-Jun-14 132 M3 A3960 A3980
A3980 Bituminous Paint 3 23-Jun-14 25-Jun-14 1221 M2 A3970 A3990
A3990 Casting of Pier & Pier Cap 28 26-Jun-14 23-Jul-14 247 M3 A3980 A3850
PIER P3PIER P3 62 23-Mar-14 23-May-14 1884
A4100 Boring & Casting of Piles 13 23-Mar-14 04-Apr-14 250 LM A3260 A4110, A3750
A4110 Blinding for Pier Pile Cap 3 05-Apr-14 07-Apr-14 34 M3 A4100 A4120
A4120 Casting of Pier Pile Cap 15 08-Apr-14 22-Apr-14 132 M3 A4110 A4130
A4130 Bituminous Paint 3 23-Apr-14 25-Apr-14 1221 M2 A4120 A4140
A4140 Casting of Pier & Pier Cap 28 26-Apr-14 23-May-14 247 M3 A4130 A3850, A4310
PIER P1PIER P1 62 05-Apr-14 05-Jun-14 1884
A3750 Boring & Casting of Piles 13 05-Apr-14 17-Apr-14 250 LM A4100 A3760, A4050
A3760 Blinding for Pier Pile Cap 3 18-Apr-14 20-Apr-14 34 M3 A3750 A3770
A3770 Casting of Pier Pile Cap 15 21-Apr-14 05-May-14 132 M3 A3760 A3780
A3780 Bituminous Paint 3 06-May-14 08-May-14 1221 M2 A3770 A3790
A3790 Casting of Pier & Pier Cap 28 09-May-14 05-Jun-14 247 M3 A3780 A4310
PIER P4PIER P4 62 18-Apr-14 18-Jun-14 1884
A4050 Boring & Casting of Piles 13 18-Apr-14 30-Apr-14 250 LM A3750 A4060, A4170
A4060 Blinding for Pier Pile Cap 3 01-May-14 03-May-14 34 M3 A4050 A4070
A4070 Casting of Pier Pile Cap 15 04-May-14 18-May-14 132 M3 A4060 A4080
A4080 Bituminous Paint 3 19-May-14 21-May-14 1221 M2 A4070 A4090
A4090 Casting of Pier & Pier Cap 28 22-May-14 18-Jun-14 247 M3 A4080 A3850
ABUTMENT AB2ABUTMENT AB2 79 01-May-14 18-Jul-14 29995
A4170 Boring & Casting of Piles 20 01-May-14 20-May-14 384 LM A4050 A4180
A4180 Blinding for Abutment Pile Cap 7 21-May-14 27-May-14 80 M3 A4170 A4190, A4220
A4220 Fixing of MSE Wall 46 21-May-14 05-Jul-14 0 M2 A4180 A4230
A4190 Casting of Abutment Pile Cap 45 28-May-14 11-Jul-14 397 M3 A4180 A4200, A3850
A4230 Backfilling 46 31-May-14 15-Jul-14 26286 M3 A4220 A5350
A4200 Bituminous Paint 7 12-Jul-14 18-Jul-14 2848 M2 A4190 A5170
SUPERSTRUCTURESUPERSTRUCTURE 135 20-Aug-14 01-Jan-15 3660
SPAN BETWEEN AB2 & P3SPAN BETWEEN AB2 & P3 114 20-Aug-14 11-Dec-14 1830
A3850 Erection of Scaffold & Shutter 55 20-Aug-14 13-Oct-14 0 0 A4140, A4090, A6760, A4190, A3990, A6470A3860
A3860 Fixing of Pot Bearings 7 14-Oct-14 20-Oct-14 12 NO. A3850 A3870
A3870 Casting of Box Girder 21 21-Oct-14 10-Nov-14 1818 M3 A3860 A3880
A3880 Prestressing Operation 10 11-Nov-14 20-Nov-14 0 0 A3870 A6770, A3920
A6770 Deshuttering of Scaffold 21 20-Nov-14 11-Dec-14 0 0 A3880 A6710
SPAN BETWEEN AB1 & P3SPAN BETWEEN AB1 & P3 114 10-Sep-14 01-Jan-15 1830
A4310 Erection of Scaffold & Shutter 55 10-Sep-14 03-Nov-14 0 0 A4040, A3570, A4140, A3790, A3820, A6470A4320
A4320 Fixing of Pot Bearings 7 04-Nov-14 10-Nov-14 12 NO. A4310 A4330
A4330 Casting of Box Girder 21 11-Nov-14 01-Dec-14 1818 M3 A4320 A4340
J J J J J J J J J
2014 2015 2016
Boring & Casting of Piles
Blinding for Pier Pile Cap
Casting of Pier Pile Cap
Bituminous Paint
Casting of Pier & Pier Cap20-Jul-14, ABUTMENT AB1
Boring & Casting of Piles
Blinding for Abutment Pile Cap
Fixing of MSE Wall
Casting of Abutment Pile Cap
Backfilling
Bituminous Paint23-Jul-14, PIER P5
Boring & Casting of Piles
Blinding for Pier Pile Cap
Casting of Pier Pile Cap
Bituminous Paint
Casting of Pier & Pier Cap23-May-14, PIER P3
Boring & Casting of Piles
Blinding for Pier Pile Cap
Casting of Pier Pile Cap
Bituminous Paint
Casting of Pier & Pier Cap05-Jun-14, PIER P1
Boring & Casting of Piles
Blinding for Pier Pile Cap
Casting of Pier Pile Cap
Bituminous Paint
Casting of Pier & Pier Cap18-Jun-14, PIER P4
Boring & Casting of Piles
Blinding for Pier Pile Cap
Casting of Pier Pile Cap
Bituminous Paint
Casting of Pier & Pier Cap18-Jul-14, ABUTMENT AB2
Boring & Casting of Piles
Blinding for Abutment Pile Cap
Fixing of MSE Wall
Casting of Abutment Pile Cap
Backfilling
Bituminous Paint01-Jan-15, SUPERSTRUCTURE
11-Dec-14, SPAN BETWEEN AB2 & P3
Erection of Scaffold & Shutter
Fixing of Pot Bearings
Casting of Box Girder
Prestressing Operation
Deshuttering of Scaffold01-Jan-15, SPAN BETWEEN AB1 & P3
Erection of Scaffold & Shutter
Fixing of Pot Bearings
Casting of Box Girder
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 8 of 17
Data Date: 30-Oct-13 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A4340 Prestressing Operation 10 02-Dec-14 11-Dec-14 0 0 A4330 A6790, A3920
A6790 Deshuttering of Scaffold 21 12-Dec-14 01-Jan-15 0 0 A4340, A1670 A6710
FINISHING WORKSFINISHING WORKS 28 02-Dec-14 29-Dec-14 844
GENERALGENERAL 28 02-Dec-14 29-Dec-14 844
A3920 Concrete Bridge Parapet (N.J Barrier) 22 02-Dec-14 23-Dec-14 793 M A6290, A3880, A4340 A3930
A3930 Laying of Bituminous Wearing Course 6 18-Dec-14 23-Dec-14 0 0 A3920 A3940, A5490
A3940 Fixing of Expansion Joints 6 24-Dec-14 29-Dec-14 51 M A3930, A4570 A6710
MSE WALL (RAMPS OF FLYOVER)MSE WALL (RAMPS OF FLYOVER) 197 01-Mar-14 13-Sep-14 10167
MSE RWs & RAMPS OF FLYOVERMSE RWs & RAMPS OF FLYOVER 197 01-Mar-14 13-Sep-14 10167
GENERALGENERAL 197 01-Mar-14 13-Sep-14 10167
A5020 Excavation to Reduce Level 55 01-Mar-14 24-Apr-14 0 0 A1540, A1376, A6320 A5030
A5030 Preparation of Foundations 100 09-Mar-14 16-Jun-14 0 0 A5020, A1457 A5040
A5040 Installing & Bracing of MSE Wall Panels 155 16-Mar-14 17-Aug-14 8800 M2 A5030 A5050
A5050 Place & Compact Selected Fill up 155 20-Mar-14 21-Aug-14 0 0 A5040 A5060
A5060 Connect & Tighten Soil Reinforcement 155 25-Mar-14 26-Aug-14 0 0 A5050 A5070
A5070 Place & Compact Random Backfill 155 04-Apr-14 05-Sep-14 0 0 A5060 A5080, A4580
A5080 Casting of Coping Beam 155 12-Apr-14 13-Sep-14 1367 M3 A5070 A4550
ROAD LIGHTING & ELECTRICAL INSTALLATIONROAD LIGHTING & ELECTRICAL INSTALLATION 312 03-Apr-14 08-Feb-15 9331
GENERALGENERAL 312 03-Apr-14 08-Feb-15 9331
CIVIL WORKS & CABLINGCIVIL WORKS & CABLING 189 03-Apr-14 08-Oct-14 9331
A4580 Trench for Low Voltage Cables 160 03-Apr-14 09-Sep-14 7097 M A5340, A5070 A4590
A4590 Laying of Ducts 160 10-Apr-14 16-Sep-14 2054 M A4580 A4600
A4600 Laying of Cables 160 17-Apr-14 23-Sep-14 0 0 A4590 A4610
A4620 High Masts Concrete Foundations 90 11-Jul-14 08-Oct-14 0 0 A4610 A4630, A4670
A4610 Lighting Columns Concrete Foundations 90 11-Jul-14 08-Oct-14 180 NO. A4600 A4620, A5350
A4630 Concrete Foundations for Transformer Stations & Feeder Pillars 60 10-Aug-14 08-Oct-14 0 0 A4620 A4640
COLUMNS, HIGH MASTSCOLUMNS, HIGH MASTS 90 21-Jul-14 18-Oct-14 0
A4670 Fixing of High Masts 90 21-Jul-14 18-Oct-14 0 0 A4620, A6350 A4680
A4680 Fixing of Lighting Poles 90 21-Jul-14 18-Oct-14 0 0 A4670 A5010, A5990
TRANSFORMERS & FEEDER PILLARSTRANSFORMERS & FEEDER PILLARS 173 20-Aug-14 08-Feb-15 0
A4650 Installation of Feeder Pillar 60 20-Aug-14 18-Oct-14 0 0 A4640 A4660
A4640 33 KV & 11 KV Pad Mounted & Pole Mounted Transformers Substations 60 20-Aug-14 18-Oct-14 0 0 A4630 A4650
A4660 Power Supply Connections to Feeder Pillar 60 11-Dec-14 08-Feb-15 0 0 A4650 A9460
SLOPE PROTECTION & STABILIZATIONSLOPE PROTECTION & STABILIZATION 100 08-Aug-14 15-Nov-14 19093
RIPRAP, GABIONRIPRAP, GABION 100 08-Aug-14 15-Nov-14 19093
GENERALGENERAL 100 08-Aug-14 15-Nov-14 19093
A5170 Laying of Filter Membrane Fabric for Protection Works 80 08-Aug-14 26-Oct-14 5133 M2 A2580, A2930, A1620, A3390, A3830, A4200A5180
A5180 Fixing of Gabion Cages 90 13-Aug-14 10-Nov-14 2487 M3 A5170 A5190
A5190 Installation of Mortared Stone Riprap 90 13-Aug-14 10-Nov-14 3473 M3 A5180 A5200
A5200 Grouted Stone Ditch Lining 60 17-Sep-14 15-Nov-14 8000 M2 A5190 A6100
DRAINAGE WORKSDRAINAGE WORKS 80 12-Feb-14 02-May-14 35947
RC PIPESRC PIPES 80 12-Feb-14 02-May-14 35947
GENERALGENERAL 80 12-Feb-14 02-May-14 35947
A5090 Trench Excavation Work 60 12-Feb-14 12-Apr-14 1641 M3 A1010 A5100
A5100 Laying of Drainage Pipes (RCC) 60 16-Feb-14 16-Apr-14 0 0 A5090, A6380 A5110
A5110 Construction of Manholes 60 22-Feb-14 22-Apr-14 20 0 A5100 A5120
A5120 Backfilling 60 04-Mar-14 02-May-14 34286 M3 A5110 A5350
ROAD FINISHING WORKSROAD FINISHING WORKS 167 19-Jul-14 01-Jan-15 189636
GENERALGENERAL 167 19-Jul-14 01-Jan-15 189636
EMBANKMENT, SUBBASE & AGGREGATE BASEEMBANKMENT, SUBBASE & AGGREGATE BASE 144 19-Jul-14 09-Dec-14 128077
A5350 Backfilling to Embankment 120 19-Jul-14 15-Nov-14 68571 M3 A4610, A3010, A3120, A29 A5370
A5370 Preparation of Granular Subbase 110 04-Aug-14 21-Nov-14 18355 M3 A5350 A5380
A5380 Preparation of Aggregate Base Course 120 12-Aug-14 09-Dec-14 41151 M3 A5370 A5390, A5430
MEDIAN & SIDEWALK PAVINGMEDIAN & SIDEWALK PAVING 157 20-Jul-14 23-Dec-14 42833
A5390 Installation of Precast Concrete Curbs 150 20-Jul-14 16-Dec-14 15393 M A5380 A5400
J J J J J J J J J
2014 2015 2016
Prestressing Operation
Deshuttering of Scaffold29-Dec-14, FINISHING WORKS
29-Dec-14, GENERAL
Concrete Bridge Parapet (N.J Barrier)
Laying of Bituminous Wearing Course
Fixing of Expansion Joints13-Sep-14, MSE WALL (RAMPS OF FLYOVER)
13-Sep-14, MSE RWs & RAMPS OF FLYOVER
13-Sep-14, GENERAL
Excavation to Reduce Level
Preparation of Foundations
Installing & Bracing of MSE Wall Panels
Place & Compact Selected Fill up
Connect & Tighten Soil Reinforcement
Place & Compact Random Backfill
Casting of Coping Beam08-Feb-15, ROAD LIGHTING & ELE
08-Feb-15, GENERAL
08-Oct-14, CIVIL WORKS & CABLING
Trench for Low Voltage Cables
Laying of Ducts
Laying of Cables
High Masts Concrete Foundations
Lighting Columns Concrete Foundations
Concrete Foundations for Transformer Sta18-Oct-14, COLUMNS, HIGH MASTS
Fixing of High Masts
Fixing of Lighting Poles08-Feb-15, TRANSFORMERS & FE
Installation of Feeder Pillar
33 KV & 11 KV Pad Mounted & Pole Moun
Power Supply Connections to Feeder Pillar15-Nov-14, SLOPE PROTECTION & STABILIZATION
15-Nov-14, RIPRAP, GABION
15-Nov-14, GENERAL
Laying of Filter Membrane Fabric for Protection Works
Fixing of Gabion Cages
Installation of Mortared Stone Riprap
Grouted Stone Ditch Lining02-May-14, DRAINAGE WORKS
02-May-14, RC PIPES
02-May-14, GENERAL
Trench Excavation Work
Laying of Drainage Pipes (RCC)
Construction of Manholes
Backfilling01-Jan-15, ROAD FINISHING WORKS
01-Jan-15, GENERAL
09-Dec-14, EMBANKMENT, SUBBASE
Backfilling to Embankment
Preparation of Granular Subbase
Preparation of Aggregate Base Course23-Dec-14, MEDIAN & SIDEWALK PAVING
Installation of Precast Concrete Curbs
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 9 of 17
Data Date: 30-Oct-13 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A5400 Installation of Concrete Barriers 150 20-Jul-14 16-Dec-14 6600 M A5390, A6290 A5410
A5410 Installation of Interlocking Tiles 150 27-Jul-14 23-Dec-14 20840 M2 A5400 A6100
NEW BITUMINOUS LAYERSNEW BITUMINOUS LAYERS 82 06-Oct-14 26-Dec-14 17242
A5430 Bituminous Base Course 75 06-Oct-14 19-Dec-14 12483 M3 A5380, A4560 A5450
A5450 Bituminous Wearing Course 38 19-Nov-14 26-Dec-14 4759 M3 A5430, A4560 A5460, A5490
GUARDRAILS, HIGHWAY SIGNS & ROAD MARKINGGUARDRAILS, HIGHWAY SIGNS & ROAD MARKING 46 17-Nov-14 01-Jan-15 1484
A5460 Fixing of Guardrails 45 17-Nov-14 31-Dec-14 1415 M A5450, A6440 A5470
A5470 Fixing of Highway Signs Single & Multiple Poles 45 17-Nov-14 31-Dec-14 65 NO. A5460, A6410 A5480
A5480 Fixing of Overhead & Gantry Signs 30 02-Dec-14 31-Dec-14 4 NO. A5470 A6100
A5490 Traffic Lines & Road Studs 30 03-Dec-14 01-Jan-15 0 0 A3930, A5450 A6710, A6100
SOL2, SOL4, SOL7SOL2, SOL4, SOL7 161 02-Jan-15 11-Jun-15 91188
SHIFT TRAFFIC TO SOL1- SB & TEMP SERVICE ROAD SR-2SHIFT TRAFFIC TO SOL1- SB & TEMP SERVICE ROAD SR-2 7 02-Jan-15 08-Jan-15 0
Start (CH 25+300) & End (CH 21+100)Start (CH 25+300) & End (CH 21+100) 7 02-Jan-15 08-Jan-15 0
GENERALGENERAL 7 02-Jan-15 08-Jan-15 0
A9900 Placing of Plastic Barriers 7 02-Jan-15 08-Jan-15 0 0 A6710 A6810
A6810 Shift Traffic from Southern & Northeren Temp. Diversions back to new Main Road 0 08-Jan-15 0 0 A9900 A9650, A8400, A8300, A8090, A7600, A7880
GENERAL CIVIL WORKSGENERAL CIVIL WORKS 99 12-Jan-15 20-Apr-15 11159
CLEARING & EXCAVATIONCLEARING & EXCAVATION 99 12-Jan-15 20-Apr-15 11159
GENERALGENERAL 99 12-Jan-15 20-Apr-15 11159
A9650 Clearing & Grubbing 30 12-Jan-15 10-Feb-15 4259 M2 A6810 A9660
A9660 Removal of Structures & Obstructures 60 14-Jan-15 15-Mar-15 1 LS A9650 A9670
A9670 Utilities Trench Ear thworks 60 17-Jan-15 17-Mar-15 1641 M3 A9660 A9680, A7010
A9680 Structural & Road Way Excavation 90 21-Jan-15 20-Apr-15 5258 M3 A9670 A9390
UTILITIESUTILITIES 52 21-Jan-15 13-Mar-15 14200
GENERALGENERAL 52 21-Jan-15 13-Mar-15 14200
TELEPHONETELEPHONE 32 21-Jan-15 21-Feb-15 2200
A7010 Installation of New (GTO) Omantal Line 12 21-Jan-15 01-Feb-15 1100 0 A9670 A7030, A7340, A6920, A6960, A7440
A7030 Obtain Shutdown & Connect to Existing 15 02-Feb-15 16-Feb-15 0 0 A7010 A7040
A7040 Remove & Dispose Existing (GTO) Omantal Line 5 17-Feb-15 21-Feb-15 1100 0 A7030 A6960
ELECTRICAL (11 KV)ELECTRICAL (11 KV) 52 21-Jan-15 13-Mar-15 6400
A6920 Installation of New 11 Kv Overhead Lines 30 21-Jan-15 19-Feb-15 3000 0 A7010 A6890, A7420, A6840, A6960, A6900
A6890 Obtain Shutdown & Connect to Existing 15 20-Feb-15 06-Mar-15 0 0 A6920 A6970
A6970 Remove & Dispose Existing 11 Kv Overhead Lines 7 07-Mar-15 13-Mar-15 400 0 A6890 A6960
A6960 Remove & Dispose Existing 11 Kv Under Ground Lines 5 09-Mar-15 13-Mar-15 3000 0 A6970, A6920, A7040, A7010A6100
ELECTRICAL (33 KV)ELECTRICAL (33 KV) 10 13-Feb-15 22-Feb-15 400
A7290 Obtain Shutdown & Connect to Existing 7 13-Feb-15 19-Feb-15 0 0 A0000 A6900
A6900 Remove & Dispose Existing 33 Kv Ovehead Lines 3 20-Feb-15 22-Feb-15 400 0 A6920, A7290 A6100
WATERLINESWATERLINES 37 26-Jan-15 03-Mar-15 5200
A6840 Installation of New Irrigation Pipes 25 26-Jan-15 19-Feb-15 2600 0 A6920 A6850, A7300
A6850 Obtain Shutdown & Connect to Existing 15 10-Feb-15 24-Feb-15 0 0 A6840 A6860
A6860 Remove & Dispose Existing Irrigation Pipes 7 25-Feb-15 03-Mar-15 2600 0 A6850 A8090, A7600, A7880
UTILITIES (P.S.)UTILITIES (P.S.) 54 26-Jan-15 20-Mar-15 0
GENERALGENERAL 54 26-Jan-15 20-Mar-15 0
TELEPHONETELEPHONE 30 26-Jan-15 24-Feb-15 0
A7340 Provide & Install New Utilities 12 26-Jan-15 06-Feb-15 0 0 A7010 A7350, A7370
A7370 Remove & Relocate of Existing Utilities 22 26-Jan-15 16-Feb-15 0 0 A7340 A7360
A7350 Obtain Shutdown & Connect to Existing 15 07-Feb-15 21-Feb-15 0 0 A7340 A7360
A7360 Remove & Dispose of Existing Utilities 3 22-Feb-15 24-Feb-15 0 0 A7350, A7370 A7440
ELECTRICALELECTRICAL 54 26-Jan-15 20-Mar-15 0
A7420 Provide & Install New Utilities 30 26-Jan-15 24-Feb-15 0 0 A6920 A7430, A7450
A7450 Remove & Relocate of Existing Utilities 47 26-Jan-15 13-Mar-15 0 0 A7420 A7440
A7430 Obtain Shutdown & Connect to Existing 15 25-Feb-15 11-Mar-15 0 0 A7420 A7440
A7440 Remove & Dispose of Existing Utilities 7 14-Mar-15 20-Mar-15 0 0 A7430, A7450, A7360, A7010A7320
WATERLINESWATERLINES 49 31-Jan-15 20-Mar-15 0
A7300 Provide & Install New Utilities 25 31-Jan-15 24-Feb-15 0 0 A6840 A7310, A7330
J J J J J J J J J
2014 2015 2016
Installation of Concrete Barriers
Installation of Interlocking Tiles26-Dec-14, NEW BITUMINOUS LAYERS
Bituminous Base Course
Bituminous Wearing Course01-Jan-15, GUARDRAILS, HIGHWAY
Fixing of Guardrails
Fixing of Highway Signs Single & Multiple Poles
Fixing of Overhead & Gantry Signs
Traffic Lines & Road Studs11-Jun-15, SOL2, SOL4, SOL7
08-Jan-15, SHIFT TRAFFIC TO SOL
08-Jan-15, Start (CH 25+300) & End (CH 21+100)
08-Jan-15, GENERAL
Placing of Plastic BarriersShift Traffic from Southern & Northere
20-Apr-15, GENERAL CIVIL WORKS
20-Apr-15, CLEARING & EXCAVATION
20-Apr-15, GENERAL
Clearing & Grubbing
Removal of Structures & Obstructures
Utilities Trench Ear thworks
Structural & Road Way Excavation13-Mar-15, UTILITIES
13-Mar-15, GENERAL
21-Feb-15, TELEPHONE
Installation of New (GTO) Omantal Line
Obtain Shutdown & Connect to Existing
Remove & Dispose Existing (GTO)13-Mar-15, ELECTRICAL (11 KV)
Installation of New 11 Kv Overhead Lines
Obtain Shutdown & Connect to Existing
Remove & Dispose Existing 11 Kv
Remove & Dispose Existing 11 Kv22-Feb-15, ELECTRICAL (33 KV)
Obtain Shutdown & Connect to Existing
Remove & Dispose Existing 33 Kv 03-Mar-15, WATERLINES
Installation of New Irrigation Pipes
Obtain Shutdown & Connect to Existing
Remove & Dispose Existing Irrigation Pipes20-Mar-15, UTILITIES (P.S.)
20-Mar-15, GENERAL
24-Feb-15, TELEPHONE
Provide & Install New Utilities
Remove & Relocate of Existing Utilities
Obtain Shutdown & Connect to Existing
Remove & Dispose of Existing Utilities20-Mar-15, ELECTRICAL
Provide & Install New Utilities
Remove & Relocate of Existing Utilities
Obtain Shutdown & Connect to Existing
Remove & Dispose of Existing Utilities20-Mar-15, WATERLINES
Provide & Install New Utilities
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 10 of 17
Data Date: 30-Oct-13 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A7330 Remove & Relocate of Existing Utilities 42 31-Jan-15 13-Mar-15 0 0 A7300 A7320
A7310 Obtain Shutdown & Connect to Existing 15 25-Feb-15 11-Mar-15 0 0 A7300 A7320
A7320 Remove & Dispose of Existing Utilities 7 14-Mar-15 20-Mar-15 0 0 A7310, A7330, A7440 A6100
BOX CULVERTS - STAGE 2BOX CULVERTS - STAGE 2 26 04-Mar-15 29-Mar-15 6201
GENERALGENERAL 26 04-Mar-15 29-Mar-15 6201
9 CELLS BOX CULVERT AT CH 22+6509 CELLS BOX CULVERT AT CH 22+650 23 04-Mar-15 26-Mar-15 1517
A8090 Structural Excavation 3 04-Mar-15 06-Mar-15 175 M3 A6810, A6860 A8100
A8100 Blinding of Concrete 2 07-Mar-15 08-Mar-15 23 M3 A8090 A8110
A8110 Casting of Base Slab 4 09-Mar-15 12-Mar-15 35 M3 A8100 A8120, A10440
A8120 Casting of Walls 7 13-Mar-15 19-Mar-15 62 M3 A8110 A8130, A8140
A8130 Casting of Top Slab 5 20-Mar-15 24-Mar-15 44 M3 A8120 A8150, A10440, A10420
A8140 Casting of Apron Slab & W ing Walls 4 20-Mar-15 23-Mar-15 35 M3 A8120 A9610
A8150 Backfilling 2 25-Mar-15 26-Mar-15 1143 M3 A8130 A9690
1 CELL BOX CULVERT AT CH 23+0001 CELL BOX CULVERT AT CH 23+000 10 20-Mar-15 29-Mar-15 752
A10420 Structural Excavation 2 20-Mar-15 21-Mar-15 117 M3 A8130 A10430
A10430 Blinding of Concrete 1 22-Mar-15 22-Mar-15 11 M3 A10420 A10440
A10440 Casting of Base Slab 2 23-Mar-15 24-Mar-15 18 M3 A10430, A8110, A8130 A10450
A10450 Casting of Walls 3 25-Mar-15 27-Mar-15 26 M3 A10440 A10460, A9610
A10460 Casting of Top Slab 1 28-Mar-15 28-Mar-15 9 M3 A10450 A10480
A10480 Backfilling 1 29-Mar-15 29-Mar-15 571 M3 A10460 A9690
2 CELLS BOX CULVERT AT CH 23+2002 CELLS BOX CULVERT AT CH 23+200 26 04-Mar-15 29-Mar-15 893
A7880 Structural Excavation 2 04-Mar-15 05-Mar-15 117 M3 A6810, A6860 A7890
A7890 Blinding of Concrete 1 06-Mar-15 06-Mar-15 11 M3 A7880 A7900
A7900 Casting of Base Slab 6 07-Mar-15 12-Mar-15 53 M3 A7890 A7910
A7910 Casting of Walls 10 13-Mar-15 22-Mar-15 88 M3 A7900 A7920, A9610
A7920 Casting of Top Slab 6 23-Mar-15 28-Mar-15 53 M3 A7910 A7940
A7940 Backfilling 1 29-Mar-15 29-Mar-15 571 M3 A7920 A9690
1 CELL BOX CULVERT AT CH 23+7601 CELL BOX CULVERT AT CH 23+760 12 04-Mar-15 15-Mar-15 787
A7600 Structural Excavation 2 04-Mar-15 05-Mar-15 117 M3 A6810, A6860 A7610
A7610 Blinding of Concrete 1 06-Mar-15 06-Mar-15 11 M3 A7600 A7620
A7620 Casting of Base Slab 2 07-Mar-15 08-Mar-15 18 M3 A7610 A7630, A7970
A7630 Casting of Walls 3 09-Mar-15 11-Mar-15 26 M3 A7620 A7640, A7650, A7670
A7640 Casting of Top Slab 1 12-Mar-15 12-Mar-15 9 M3 A7630 A7660, A7690
A7650 Casting of Apron Slab & W ing Walls 4 12-Mar-15 15-Mar-15 35 M3 A7630 A7720
A7660 Backfilling 1 13-Mar-15 13-Mar-15 571 M3 A7640 A9690
1 CELL BOX CULVERT AT CH 23+9971 CELL BOX CULVERT AT CH 23+997 12 10-Mar-15 21-Mar-15 787
A7670 Structural Excavation 2 10-Mar-15 11-Mar-15 117 M3 A7630 A7680, A7950
A7680 Blinding of Concrete 1 12-Mar-15 12-Mar-15 11 M3 A7670 A7690
A7690 Casting of Base Slab 2 13-Mar-15 14-Mar-15 18 M3 A7680, A7640 A7700, A7970
A7700 Casting of Walls 3 15-Mar-15 17-Mar-15 26 M3 A7690 A7710, A7720
A7710 Casting of Top Slab 1 18-Mar-15 18-Mar-15 9 M3 A7700 A7730
A7720 Casting of Apron Slab & W ing Walls 4 18-Mar-15 21-Mar-15 35 M3 A7700, A7650 A8000
A7730 Backfilling 1 19-Mar-15 19-Mar-15 571 M3 A7710 A9690
5 CELLS BOX CULVERT AT CH 23+5005 CELLS BOX CULVERT AT CH 23+500 20 10-Mar-15 29-Mar-15 1465
A7950 Structural Excavation 2 10-Mar-15 11-Mar-15 117 M3 A7670 A7960
A7960 Blinding of Concrete 1 12-Mar-15 12-Mar-15 11 M3 A7950 A7970
A7970 Casting of Base Slab 4 13-Mar-15 16-Mar-15 35 M3 A7960, A7620, A7690 A7980
A7980 Casting of Walls 7 17-Mar-15 23-Mar-15 62 M3 A7970 A7990, A8000
A8000 Casting of Apron Slab & W ing Walls 7 22-Mar-15 28-Mar-15 62 M3 A7980, A7720 A9610
A7990 Casting of Top Slab 4 24-Mar-15 27-Mar-15 35 M3 A7980 A8010
A8010 Backfilling 2 28-Mar-15 29-Mar-15 1143 M3 A7990 A9690
PEDESTRIAN UNDERPASS 2 (SOL4 CH 00+935) - STAGE 2PEDESTRIAN UNDERPASS 2 (SOL4 CH 00+935) - STAGE 2 80 09-Jan-15 29-Mar-15 2990
GENERALGENERAL 80 09-Jan-15 29-Mar-15 2990
UNDERPASS STRUCTUREUNDERPASS STRUCTURE 80 09-Jan-15 29-Mar-15 2990
J J J J J J J J J
2014 2015 2016
Remove & Relocate of Existing Utilities
Obtain Shutdown & Connect to Existing
Remove & Dispose of Existing Utilities29-Mar-15, BOX CULVERTS - STAGE 2
29-Mar-15, GENERAL
26-Mar-15, 9 CELLS BOX CULVE
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling29-Mar-15, 1 CELL BOX CULVER
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Backfilling29-Mar-15, 2 CELLS BOX CULVE
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Backfilling15-Mar-15, 1 CELL BOX CULVER
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling21-Mar-15, 1 CELL BOX CULVER
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling29-Mar-15, 5 CELLS BOX CULVE
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Apron Slab & W ing Walls
Casting of Top Slab
Backfilling29-Mar-15, PEDESTRIAN UNDE
29-Mar-15, GENERAL
29-Mar-15, UNDERPASS STRUCTURE
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 11 of 17
Data Date: 30-Oct-13 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A8300 Structural Excavation 10 09-Jan-15 18-Jan-15 584 M3 A6810, A1830 A7220, A1510
A7220 Blinding of Concrete 12 12-Jan-15 23-Jan-15 137 M3 A8300 A7230
A7230 Casting of Base Slab 21 23-Jan-15 12-Feb-15 185 M3 A7220 A7240
A7240 Casting of Walls 21 13-Feb-15 05-Mar-15 185 M3 A7230 A7250
A7250 Casting of Top Slab 21 06-Mar-15 26-Mar-15 185 M3 A7240 A8310, A10030
A8310 Backfilling 3 27-Mar-15 29-Mar-15 1714 M3 A7250 A9690
PEDESTRIAN UNDERPASS 1 (SOL4 CH 00+435) - STAGE 2PEDESTRIAN UNDERPASS 1 (SOL4 CH 00+435) - STAGE 2 80 09-Jan-15 29-Mar-15 2990
GENERALGENERAL 80 09-Jan-15 29-Mar-15 2990
UNDERPASS STRUCTUREUNDERPASS STRUCTURE 80 09-Jan-15 29-Mar-15 2990
A8400 Structural Excavation 10 09-Jan-15 18-Jan-15 584 M3 A6810, A3120 A8350
A8350 Blinding of Concrete 12 12-Jan-15 23-Jan-15 137 M3 A8400 A8360
A8360 Casting of Base Slab 21 23-Jan-15 12-Feb-15 185 M3 A8350 A8370
A8370 Casting of Walls 21 13-Feb-15 05-Mar-15 185 M3 A8360 A8380
A8380 Casting of Top Slab 21 06-Mar-15 26-Mar-15 185 M3 A8370 A8410
A8410 Backfilling 3 27-Mar-15 29-Mar-15 1714 M3 A8380 A9690
ROAD LIGHTING & ELECTRICAL INSTALLATIONROAD LIGHTING & ELECTRICAL INSTALLATION 56 05-Feb-15 01-Apr-15 1168
GENERALGENERAL 56 05-Feb-15 01-Apr-15 1168
CIVIL WORKS & CABLINGCIVIL WORKS & CABLING 41 05-Feb-15 17-Mar-15 1168
A9390 Trench for Low Voltage Cables 20 05-Feb-15 24-Feb-15 887 M A9680 A9400
A9400 Laying of Ducts 20 12-Feb-15 03-Mar-15 257 M A9390 A9410
A9420 Concrete Foundations for Transformer Stations & Feeder Pillars 30 16-Feb-15 17-Mar-15 0 0 A9430 A9470
A9410 Laying of Cables 20 19-Feb-15 10-Mar-15 0 0 A9400 A9440
A9430 High Masts Concrete Foundations 25 21-Feb-15 17-Mar-15 0 0 A9440 A9420, A9480
A9440 Lighting Columns Concrete Foundations 12 06-Mar-15 17-Mar-15 24 NO. A9410 A9430, A9690
COLUMNS, HIGH MASTSCOLUMNS, HIGH MASTS 30 03-Mar-15 01-Apr-15 0
A9480 Fixing of High Masts 30 03-Mar-15 01-Apr-15 0 0 A9430 A9490
A9490 Fixing of Lighting Poles 30 03-Mar-15 01-Apr-15 0 0 A9480 A9730
TRANSFORMERS & FEEDER PILLARSTRANSFORMERS & FEEDER PILLARS 30 26-Feb-15 27-Mar-15 0
A9450 Installation of Feeder Pillar 30 26-Feb-15 27-Mar-15 0 0 A9470 A9460
A9460 Power Supply Connections to Feeder Pillar 30 26-Feb-15 27-Mar-15 0 0 A9450, A4660 A6100
A9470 33 KV & 11 KV Pad Mounted & Pole Mounted Transformers Substations 30 26-Feb-15 27-Mar-15 0 0 A9420 A9450
SLOPE PROTECTION & STABILIZATIONSLOPE PROTECTION & STABILIZATION 55 18-Apr-15 11-Jun-15 9547
RIPRAP, GABIONRIPRAP, GABION 55 18-Apr-15 11-Jun-15 9547
GENERALGENERAL 55 18-Apr-15 11-Jun-15 9547
A9610 Laying of Filter Membrane Fabric for Protection Works 40 18-Apr-15 27-May-15 2567 M2 A8000, A7910, A10450, A8140A9620
A9620 Fixing of Gabion Cages 45 23-Apr-15 06-Jun-15 1243 M3 A9610 A9630
A9630 Installation of Mortared Stone Riprap 45 23-Apr-15 06-Jun-15 1737 M3 A9620 A9640
A9640 Grouted Stone Ditch Lining 30 13-May-15 11-Jun-15 4000 M2 A9630 A6740
ROAD FINISHING WORKSROAD FINISHING WORKS 83 26-Feb-15 19-May-15 42933
GENERALGENERAL 83 26-Feb-15 19-May-15 42933
EMBANKMENT, SUBBASE & AGGREGATE BASEEMBANKMENT, SUBBASE & AGGREGATE BASE 44 26-Feb-15 10-Apr-15 27648
A9690 Backfilling to Embankment 32 26-Feb-15 29-Mar-15 18286 M3 A9440, A8410, A8310, A8150, A10480, A7940, A7660, A7730, A8010A9710
A9710 Preparation of Granular Subbase 15 20-Mar-15 03-Apr-15 2503 M3 A9690 A9720
A9720 Preparation of Aggregate Base Course 20 22-Mar-15 10-Apr-15 6859 M3 A9710 A9730, A9770
MEDIAN & SIDEWALK PAVINGMEDIAN & SIDEWALK PAVING 52 29-Mar-15 19-May-15 11383
A9730 Installation of Precast Concrete Curbs 50 29-Mar-15 17-May-15 5131 M A9720, A9490 A9750
A9750 Installation of Interlocking Tiles 45 05-Apr-15 19-May-15 6252 M2 A9730 A6100
NEW BITUMINOUS LAYERSNEW BITUMINOUS LAYERS 17 02-Apr-15 18-Apr-15 3833
A9770 Bituminous Base Course 14 02-Apr-15 15-Apr-15 2330 M3 A9720 A9790
A9790 Bituminous Wearing Course 12 07-Apr-15 18-Apr-15 1503 M3 A9770 A9800, A9830
GUARDRAILS, HIGHWAY SIGNS & ROAD MARKINGGUARDRAILS, HIGHWAY SIGNS & ROAD MARKING 45 10-Mar-15 23-Apr-15 69
A9800 Fixing of Guardrails 45 10-Mar-15 23-Apr-15 0 M A9790 A9810
A9810 Fixing of Highway Signs Single & Multiple Poles 45 10-Mar-15 23-Apr-15 65 NO. A9800 A9820
A9830 Traffic Lines & Road Studs 30 23-Mar-15 21-Apr-15 0 0 A9790 A6100, A1500
A9820 Fixing of Overhead & Gantry Signs 30 25-Mar-15 23-Apr-15 4 NO. A9810 A6100
J J J J J J J J J
2014 2015 2016
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Backfilling29-Mar-15, PEDESTRIAN UNDE
29-Mar-15, GENERAL
29-Mar-15, UNDERPASS STRUCTURE
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Backfilling01-Apr-15, ROAD LIGHTING & E
01-Apr-15, GENERAL
17-Mar-15, CIVIL WORKS & CABLING
Trench for Low Voltage Cables
Laying of Ducts
Concrete Foundations for Transfo
Laying of Cables
High Masts Concrete Foundations
Lighting Columns Concrete Foundations01-Apr-15, COLUMNS, HIGH MASTS
Fixing of High Masts
Fixing of Lighting Poles27-Mar-15, TRANSFORMERS &
Installation of Feeder Pillar
Power Supply Connections to Feeder Pillar
33 KV & 11 KV Pad Mounted & Po11-Jun-15, SLOPE PROTEC
11-Jun-15, RIPRAP, GABION
11-Jun-15, GENERAL
Laying of Filter Membrane Fab
Fixing of Gabion Cages
Installation of Mortared Stone Riprap
Grouted Stone Ditch Lining19-May-15, ROAD FINISHING WORKS
19-May-15, GENERAL
10-Apr-15, EMBANKMENT, SUB
Backfilling to Embankment
Preparation of Granular Subbase
Preparation of Aggregate Base Course19-May-15, MEDIAN & SIDEWALK PAVING
Installation of Precast Concrete Curbs
Installation of Interlocking Tiles18-Apr-15, NEW BITUMINOUS LAYERS
Bituminous Base Course
Bituminous Wearing Course23-Apr-15, GUARDRAILS, HIGH
Fixing of Guardrails
Fixing of Highway Signs Single &
Traffic Lines & Road Studs
Fixing of Overhead & Gantry Signs
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 12 of 17
Data Date: 30-Oct-13 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
SERVICE ROADSSERVICE ROADS 73 18-Apr-15 29-Jun-15 37801
SR1, SR2 & SR3SR1, SR2 & SR3 73 18-Apr-15 29-Jun-15 37801
SHIFT TRAFFIC FROM SERVICE ROADS TO NEW SLIP ROADS (SOL 4/5/6/7)SHIFT TRAFFIC FROM SERVICE ROADS TO NEW SLIP ROADS (SOL 4/5/6/7) 4 18-Apr-15 21-Apr-15 0
SR2 - (CH0+0 TO CH1+300) & SR-1(CH0+0 TO CH0+797)SR2 - (CH0+0 TO CH1+300) & SR-1(CH0+0 TO CH0+797) 4 18-Apr-15 21-Apr-15 0
GENERALGENERAL 4 18-Apr-15 21-Apr-15 0
A1500 Placing of Plastic Barriers & Temporary Signs 4 18-Apr-15 21-Apr-15 0 0 A9830 A1510
A1510 Shift Traffic from Existing Southern & Northeren Service Roads to New Main Road 0 21-Apr-15 0 0 A1500, A8300 A6000, A10090, A10030, A1840, A3100
GENERAL CIVIL WORKSGENERAL CIVIL WORKS 17 22-Apr-15 08-May-15 1421
CLEARING & EXCAVATIONCLEARING & EXCAVATION 17 22-Apr-15 08-May-15 1421
GENERALGENERAL 17 22-Apr-15 08-May-15 1421
A6000 Clearing & Grubbing 10 22-Apr-15 01-May-15 1420 M2 A1510 A6010
A6010 Removal of Structures & Obstructures 15 24-Apr-15 08-May-15 1 LS A6000 A6020
A6020 Road Way Excavation 10 26-Apr-15 05-May-15 0 0 A6010 A5950, A9960, A10510
BOX CULERTS - STAGE 3BOX CULERTS - STAGE 3 24 06-May-15 29-May-15 1822
GENERALGENERAL 24 06-May-15 29-May-15 1822
1 CELL BOX CULVERT AT CH 23+0001 CELL BOX CULVERT AT CH 23+000 20 06-May-15 25-May-15 875
A10510 Structural Excavation 2 06-May-15 07-May-15 117 M3 A6020 A10520
A10520 Blinding of Concrete 1 08-May-15 08-May-15 11 M3 A10510 A10530
A10530 Casting of Base Slab 4 09-May-15 12-May-15 35 M3 A10520 A10540
A10540 Casting of Walls 8 13-May-15 20-May-15 71 M3 A10530 A10550, A10560
A10550 Casting of Top Slab 4 21-May-15 24-May-15 35 M3 A10540 A10570
A10560 Casting of Apron Slab & W ing Walls 4 22-May-15 25-May-15 35 M3 A10540 A6100
A10570 Backfilling 1 25-May-15 25-May-15 571 M3 A10550 A5830
2 CELLS BOX CULVERT AT CH 23+2002 CELLS BOX CULVERT AT CH 23+200 24 06-May-15 29-May-15 947
A9960 Structural Excavation 2 06-May-15 07-May-15 117 M3 A6020 A9970
A9970 Blinding of Concrete 1 08-May-15 08-May-15 11 M3 A9960 A9980
A9980 Casting of Base Slab 6 09-May-15 14-May-15 53 M3 A9970 A9990
A9990 Casting of Walls 8 15-May-15 22-May-15 71 M3 A9980 A10010, A10000
A10000 Casting of Apron Slab & W ing Walls 8 20-May-15 27-May-15 71 M3 A9990
A10010 Casting of Top Slab 6 23-May-15 28-May-15 53 M3 A9990 A10020
A10020 Backfilling 1 29-May-15 29-May-15 571 M3 A10010 A5830
PEDESTRIAN UNDERPASS 1 (SR2 CH 00+725) - STAGE 3PEDESTRIAN UNDERPASS 1 (SR2 CH 00+725) - STAGE 3 67 22-Apr-15 27-Jun-15 2997
GENERALGENERAL 67 22-Apr-15 27-Jun-15 2997
UNDERPASS STRUCTUREUNDERPASS STRUCTURE 44 22-Apr-15 04-Jun-15 2363
A10090 Structural Excavation 5 22-Apr-15 26-Apr-15 292 M3 A1510 A10100, A3100
A10100 Blinding of Concrete 5 24-Apr-15 28-Apr-15 57 M3 A10090 A10110
A10110 Casting of Base Slab 12 29-Apr-15 10-May-15 106 M3 A10100 A10120
A10120 Casting of Walls 10 11-May-15 20-May-15 88 M3 A10110 A10130
A10130 Casting of Top Slab 12 21-May-15 01-Jun-15 106 M3 A10120 A10140
A10140 Backfilling 3 02-Jun-15 04-Jun-15 1714 M3 A10130 A5830
ENTRANCE & EXITENTRANCE & EXIT 67 22-Apr-15 27-Jun-15 634
A3100 Casting of Floor Slab 22 22-Apr-15 13-May-15 194 M3 A10090, A1510 A3130
A3130 Casting of Walls 25 14-May-15 07-Jun-15 220 M3 A3100 A3140, A3150
A3150 Casting of Landing Slabs & Stair Case 25 29-May-15 22-Jun-15 220 M3 A3130 A3140
A3140 Casing of Beams & Roof Slab 20 08-Jun-15 27-Jun-15 0 0 A3130, A3150 A6100
PEDESTRIAN UNDERPASS 2 (SR2 CH 01+210) - STAGE 3PEDESTRIAN UNDERPASS 2 (SR2 CH 01+210) - STAGE 3 67 22-Apr-15 27-Jun-15 2997
GENERALGENERAL 67 22-Apr-15 27-Jun-15 2997
UNDERPASS STRUCTUREUNDERPASS STRUCTURE 44 22-Apr-15 04-Jun-15 2363
A10030 Structural Excavation 5 22-Apr-15 26-Apr-15 292 M3 A1510, A7250 A10040, A1840
A10040 Blinding of Concrete 5 24-Apr-15 28-Apr-15 57 M3 A10030 A10050
A10050 Casting of Base Slab 12 29-Apr-15 10-May-15 106 M3 A10040 A10060
A10060 Casting of Walls 10 11-May-15 20-May-15 88 M3 A10050 A10070
A10070 Casting of Top Slab 12 21-May-15 01-Jun-15 106 M3 A10060 A10080
A10080 Backfilling 3 02-Jun-15 04-Jun-15 1714 M3 A10070 A5830
ENTRANCE & EXITENTRANCE & EXIT 67 22-Apr-15 27-Jun-15 634
J J J J J J J J J
2014 2015 2016
29-Jun-15, SERVICE ROADS
29-Jun-15, SR1, SR2 & SR3
21-Apr-15, SHIFT TRAFFIC FR
21-Apr-15, SR2 - (CH0+0 TO C
21-Apr-15, GENERAL
Placing of Plastic Barriers & Temporary SignsShift Traffic from Existing Southe
08-May-15, GENERAL CIVIL WORKS
08-May-15, CLEARING & EXCAVATION
08-May-15, GENERAL
Clearing & Grubbing
Removal of Structures & Obstructures
Road Way Excavation29-May-15, BOX CULERTS - STAGE 3
29-May-15, GENERAL
25-May-15, 1 CELL BOX CUL
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling29-May-15, 2 CELLS BOX CU
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Apron Slab & W ing Walls
Casting of Top Slab
Backfilling27-Jun-15, PEDESTRIAN U
27-Jun-15, GENERAL
04-Jun-15, UNDERPASS STRUCTURE
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Backfilling27-Jun-15, ENTRANCE & EXIT
Casting of Floor Slab
Casting of Walls
Casting of Landing Slabs & Stair Case
Casing of Beams & Roof Slab27-Jun-15, PEDESTRIAN U
27-Jun-15, GENERAL
04-Jun-15, UNDERPASS STRUCTURE
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Backfilling27-Jun-15, ENTRANCE & EXIT
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 13 of 17
Data Date: 30-Oct-13 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A1840 Casting of Floor Slab 22 22-Apr-15 13-May-15 194 M3 A1510, A10030 A3020
A3020 Casting of Walls 25 14-May-15 07-Jun-15 220 M3 A1840 A3040, A3050
A3050 Casting of Landing Slabs & Stair Case 25 03-Jun-15 27-Jun-15 220 M3 A3020 A3040
A3040 Casing of Beams & Roof Slab 20 08-Jun-15 27-Jun-15 0 0 A3020, A3050 A6100
ROAD LIGHTING & ELECTRICAL INSTALLATIONROAD LIGHTING & ELECTRICAL INSTALLATION 45 26-Apr-15 09-Jun-15 888
GENERALGENERAL 45 26-Apr-15 09-Jun-15 888
CIVIL WORKS & CABLINGCIVIL WORKS & CABLING 30 26-Apr-15 25-May-15 888
A5950 Trench for Low Voltage Cables 15 26-Apr-15 10-May-15 665 M A6020 A5960
A5960 Laying of Ducts 15 01-May-15 15-May-15 193 M A5950 A5970
A5970 Laying of Cables 15 06-May-15 20-May-15 0 0 A5960 A5980
A5980 Lighting Columns Concrete Foundations 19 07-May-15 25-May-15 30 NO. A5970 A5990, A5830
COLUMNS, HIGH MASTSCOLUMNS, HIGH MASTS 25 16-May-15 09-Jun-15 0
A5990 Fixing of Lighting Poles 25 16-May-15 09-Jun-15 0 0 A5980, A4680, A6350 A5870
ROAD FINISHING WORKSROAD FINISHING WORKS 48 13-May-15 29-Jun-15 27676
GENERALGENERAL 48 13-May-15 29-Jun-15 27676
EMBANKMENT, SUBBASE & AGGREGATE BASEEMBANKMENT, SUBBASE & AGGREGATE BASE 35 13-May-15 16-Jun-15 19316
A5830 Backfilling to Embankment 23 13-May-15 04-Jun-15 13143 M3 A5980, A10080, A10140, A10020, A10570A5860
A5860 Preparation of Aggregate Base Course 18 30-May-15 16-Jun-15 6173 M3 A5830 A5870, A5900
MEDIAN & SIDEWALK PAVINGMEDIAN & SIDEWALK PAVING 23 02-Jun-15 24-Jun-15 4831
A5870 Installation of Precast Concrete Curbs 20 02-Jun-15 21-Jun-15 2052 M A5860, A5990 A5880
A5880 Installation of Interlocking Tiles 20 05-Jun-15 24-Jun-15 2779 M2 A5870 A6100
NEW BITUMINOUS LAYERSNEW BITUMINOUS LAYERS 18 10-Jun-15 27-Jun-15 3500
A5900 Bituminous Base Course 12 10-Jun-15 21-Jun-15 1997 M3 A5860 A5920
A5920 Bituminous Wearing Course 12 16-Jun-15 27-Jun-15 1503 M3 A5900 A5930, A5940
HIGHWAY SIGNS & ROAD MARKINGHIGHWAY SIGNS & ROAD MARKING 21 09-Jun-15 29-Jun-15 29
A5930 Fixing of Highway Signs Single & Multiple Poles 20 09-Jun-15 28-Jun-15 29 NO. A5920, A6410 A6100
A5940 Traffic Lines & Road Studs 15 15-Jun-15 29-Jun-15 0 0 A5920 A6740, A6100
SOHAR-BURAIMI ROADSOHAR-BURAIMI ROAD 475 12-Mar-14 29-Jun-15 132099
MAIN ROADMAIN ROAD 357 12-Mar-14 03-Mar-15 110776
SOL3 (CH 0+0 to 1+200)SOL3 (CH 0+0 to 1+200) 357 12-Mar-14 03-Mar-15 110776
INVESTIGATIONINVESTIGATION 24 12-Mar-14 04-Apr-14 0
GEOTECHNICAL INVESTIGATIONGEOTECHNICAL INVESTIGATION 24 12-Mar-14 04-Apr-14 0
GENERALGENERAL 24 12-Mar-14 04-Apr-14 0
A6170 Site Survey 4 12-Mar-14 15-Mar-14 0 0 A6160 A6180
A6180 Setting up Drilling Rigs 5 16-Mar-14 20-Mar-14 0 0 A6170 A6190
A6190 Execution of Boreholes 5 21-Mar-14 25-Mar-14 0 0 A6180 A6200
A6200 Execution of Trial Pits 4 26-Mar-14 29-Mar-14 0 0 A6190 A6210
A6210 (SPT) Test 3 30-Mar-14 01-Apr-14 0 0 A6200 A6220
A6220 Laboratory Testing Report 3 02-Apr-14 04-Apr-14 0 0 A6210 A6030
GENERAL CIVIL WORKSGENERAL CIVIL WORKS 114 05-Apr-14 27-Jul-14 5736
CLEARING & EXCAVATIONCLEARING & EXCAVATION 114 05-Apr-14 27-Jul-14 5736
GENERALGENERAL 114 05-Apr-14 27-Jul-14 5736
A6030 Clearing & Grubbing 8 05-Apr-14 12-Apr-14 1136 M2 A6220 A6040
A6040 Removal of Structures & Obstructures 15 12-Apr-14 26-Apr-14 1 LS A6030 A6050
A6050 Utilities Trench Excavation & Backfilling 40 19-Apr-14 28-May-14 1094 M3 A6040 A6060, A1210
A6060 Structural & Road Way Excavation 60 29-May-14 27-Jul-14 3505 M3 A6050 A4800, A5130
UTILITIESUTILITIES 30 29-May-14 27-Jun-14 3000
GENERALGENERAL 30 29-May-14 27-Jun-14 3000
TELEPHONETELEPHONE 30 29-May-14 27-Jun-14 800
A1210 Installation of New (GTO) Omantal Line 10 29-May-14 07-Jun-14 400 0 A6050, A6590 A1215, A1100, A2050, A1105, A2150
A1215 Obtain Shutdown & Connect to Existing 15 08-Jun-14 22-Jun-14 0 0 A1210 A1218
A1218 Remove & Dispose Existing (GTO) Omantal Line 5 23-Jun-14 27-Jun-14 400 0 A1215 A1105
ELECTRICAL (11 KV)ELECTRICAL (11 KV) 30 29-May-14 27-Jun-14 1100
A1100 Installation of New 11 Kv Overhead Lines 10 29-May-14 07-Jun-14 500 0 A1210, A6530 A1102, A1020, A2130
A1102 Obtain Shutdown & Connect to Existing 15 08-Jun-14 22-Jun-14 0 0 A1100 A1105, A1170, A1058
J J J J J J J J J
2014 2015 2016
Casting of Floor Slab
Casting of Walls
Casting of Landing Slabs & Stair Case
Casing of Beams & Roof Slab09-Jun-15, ROAD LIGHTING
09-Jun-15, GENERAL
25-May-15, CIVIL WORKS & CABLING
Trench for Low Voltage Cables
Laying of Ducts
Laying of Cables
Lighting Columns Concrete Foundations09-Jun-15, COLUMNS, HIGH MASTS
Fixing of Lighting Poles29-Jun-15, ROAD FINISHING WORKS
29-Jun-15, GENERAL
16-Jun-15, EMBANKMENT, S
Backfilling to Embankment
Preparation of Aggregate Base Course24-Jun-15, MEDIAN & SIDEW
Installation of Precast Concrete Curbs
Installation of Interlocking Tiles27-Jun-15, NEW BITUMINOUS LAYERS
Bituminous Base Course
Bituminous Wearing Course29-Jun-15, HIGHWAY SIGN
Fixing of Highway Signs Sing
Traffic Lines & Road Studs29-Jun-15, SOHAR-BURAIMI ROAD
03-Mar-15, MAIN ROAD
03-Mar-15, SOL3 (CH 0+0 to 1+200)
04-Apr-14, INVESTIGATION
04-Apr-14, GEOTECHNICAL INVESTIGATION
04-Apr-14, GENERAL
Site Survey
Setting up Drilling Rigs
Execution of Boreholes
Execution of Trial Pits
(SPT) Test
Laboratory Testing Report27-Jul-14, GENERAL CIVIL WORKS
27-Jul-14, CLEARING & EXCAVATION
27-Jul-14, GENERAL
Clearing & Grubbing
Removal of Structures & Obstructures
Utilities Trench Excavation & Backfilling
Structural & Road Way Excavation27-Jun-14, UTILITIES
27-Jun-14, GENERAL
27-Jun-14, TELEPHONE
Installation of New (GTO) Omantal Line
Obtain Shutdown & Connect to Existing
Remove & Dispose Existing (GTO) Omantal Line27-Jun-14, ELECTRICAL (11 KV)
Installation of New 11 Kv Overhead Lines
Obtain Shutdown & Connect to Existing
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 14 of 17
Data Date: 30-Oct-13 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A1105 Remove & Dispose Existing 11 Kv Overhead Lines 5 23-Jun-14 27-Jun-14 100 0 A1102, A1218, A1210 A1170
A1170 Remove & Dispose Existing 11 Kv Under Ground Lines 2 26-Jun-14 27-Jun-14 500 0 A1105, A1102 A1058
ELECTRICAL (33 KV)ELECTRICAL (33 KV) 9 19-Jun-14 27-Jun-14 100
A1065 Obtain Shutdown & Connect to Existing 7 19-Jun-14 25-Jun-14 0 0 A0000 A1058
A1058 Remove & Dispose Existing 33 Kv Ovehead Lines 2 26-Jun-14 27-Jun-14 100 0 A1170, A1102, A1065 A5650
WATERLINESWATERLINES 30 29-May-14 27-Jun-14 1000
A1020 Installation of New Irrigation Pipes 10 29-May-14 07-Jun-14 500 0 A1100, A6560 A1030, A2010
A1030 Obtain Shutdown & Connect to Existing 15 08-Jun-14 22-Jun-14 0 0 A1020 A1040
A1040 Remove & Dispose Existing Irrigation Pipes 5 23-Jun-14 27-Jun-14 500 0 A1030 A5210
UTILITIES (P.S.)UTILITIES (P.S.) 45 03-Jun-14 17-Jul-14 0
GENERALGENERAL 45 03-Jun-14 17-Jul-14 0
TELEPHONETELEPHONE 30 03-Jun-14 02-Jul-14 0
A2050 Provide & Install New Utilities 10 03-Jun-14 12-Jun-14 0 0 A1210 A2060, A2080
A2080 Remove & Relocate of Existing Utilities 25 03-Jun-14 27-Jun-14 0 0 A2050 A2070
A2060 Obtain Shutdown & Connect to Existing 15 13-Jun-14 27-Jun-14 0 0 A2050 A2070
A2070 Remove & Dispose of Existing Utilities 5 28-Jun-14 02-Jul-14 0 0 A2060, A2080 A2150
ELECTRICALELECTRICAL 40 03-Jun-14 12-Jul-14 0
A2130 Provide & Install New Utilities 10 03-Jun-14 12-Jun-14 0 0 A1100 A2140, A2160
A2140 Obtain Shutdown & Connect to Existing 15 13-Jun-14 27-Jun-14 0 0 A2130 A2150
A2160 Remove & Relocate of Existing Utilities 25 13-Jun-14 07-Jul-14 0 0 A2130 A2150
A2150 Remove & Dispose of Existing Utilities 5 08-Jul-14 12-Jul-14 0 0 A2140, A2160, A2070, A1210A2030
WATERLINESWATERLINES 45 03-Jun-14 17-Jul-14 0
A2010 Provide & Install New Utilities 10 03-Jun-14 12-Jun-14 0 0 A1020 A2020, A2040
A2020 Obtain Shutdown & Connect to Existing 15 13-Jun-14 27-Jun-14 0 0 A2010 A2030
A2040 Remove & Relocate of Existing Utilities 25 13-Jun-14 07-Jul-14 0 0 A2010 A2030
A2030 Remove & Dispose of Existing Utilities 5 13-Jul-14 17-Jul-14 0 0 A2020, A2040, A2150 A5260
PEDESTRIAN UNDERPASS 3 (SOL3 CH 00+050) - STAGE 1PEDESTRIAN UNDERPASS 3 (SOL3 CH 00+050) - STAGE 1 199 03-Jul-14 17-Jan-15 6329
GENERALGENERAL 199 03-Jul-14 17-Jan-15 6329
UNDERPASS STRUCTUREUNDERPASS STRUCTURE 128 03-Jul-14 07-Nov-14 5517
A5210 Structural Excavation 10 03-Jul-14 12-Jul-14 584 M3 A1040 A5220
A5220 Blinding of Concrete 12 06-Jul-14 17-Jul-14 137 M3 A5210 A5230
A5230 Casting of Base Slab 35 13-Jul-14 16-Aug-14 309 M3 A5220 A5240
A5240 Casting of Walls 70 03-Aug-14 11-Oct-14 617 M3 A5230 A5250
A5250 Casting of Top Slab 50 13-Sep-14 01-Nov-14 441 M3 A5240 A5260, A4800, A5270
A5260 Backfilling 6 02-Nov-14 07-Nov-14 3429 M3 A5250, A2030 A5500
ENTRANCE & EXISTENTRANCE & EXIST 77 02-Nov-14 17-Jan-15 812
A5270 Casting of Floor Slab 22 02-Nov-14 23-Nov-14 194 M3 A5250 A5280
A5280 Casting of Walls 35 24-Nov-14 28-Dec-14 309 M3 A5270 A5290, A5300
A5300 Casting of Landing Slabs & Stair Case 35 14-Dec-14 17-Jan-15 309 M3 A5280 A5290
A5290 Casing of Beams & Roof Slab 20 29-Dec-14 17-Jan-15 0 0 A5280, A5300 A6100
ROAD LIGHTING & ELECTRICAL INSTALLATIONROAD LIGHTING & ELECTRICAL INSTALLATION 89 13-Sep-14 10-Dec-14 2920
GENERALGENERAL 89 13-Sep-14 10-Dec-14 2920
CIVIL WORKS & CABLINGCIVIL WORKS & CABLING 79 13-Sep-14 30-Nov-14 2920
A4800 Trench for Low Voltage Cables 50 13-Sep-14 01-Nov-14 2218 M A5250, A6060, A6530 A4810
A4810 Laying of Ducts 50 20-Sep-14 08-Nov-14 642 M A4800 A4820
A4820 Laying of Cables 50 27-Sep-14 15-Nov-14 0 0 A4810 A4850
A4850 Lighting Columns Concrete Foundations 30 01-Nov-14 30-Nov-14 60 NO. A4820 A4852
A4852 High Masts Concrete Foundations 30 01-Nov-14 30-Nov-14 0 0 A4850 A4855, A5500
A4855 Concrete Foundations for Transformer Stations & Feeder Pillars 20 11-Nov-14 30-Nov-14 0 0 A4852 A4857, A4890
COLUMNS, HIGH MASTSCOLUMNS, HIGH MASTS 30 11-Nov-14 10-Dec-14 0
A4890 Fixing of High Masts 30 11-Nov-14 10-Dec-14 0 0 A4855 A4900
A4900 Fixing of Lighting Poles 30 11-Nov-14 10-Dec-14 0 0 A4890 A4860
TRANSFORMERS & FEEDER PILLARSTRANSFORMERS & FEEDER PILLARS 20 21-Nov-14 10-Dec-14 0
A4860 Installation of Feeder Pillar 20 21-Nov-14 10-Dec-14 0 0 A4900 A4870
J J J J J J J J J
2014 2015 2016
Remove & Dispose Existing 11 Kv Overhead Lines
Remove & Dispose Existing 11 Kv Under Ground Lines27-Jun-14, ELECTRICAL (33 KV)
Obtain Shutdown & Connect to Existing
Remove & Dispose Existing 33 Kv Ovehead Lines27-Jun-14, WATERLINES
Installation of New Irrigation Pipes
Obtain Shutdown & Connect to Existing
Remove & Dispose Existing Irrigation Pipes17-Jul-14, UTILITIES (P.S.)
17-Jul-14, GENERAL
02-Jul-14, TELEPHONE
Provide & Install New Utilities
Remove & Relocate of Existing Utilities
Obtain Shutdown & Connect to Existing
Remove & Dispose of Existing Utilities12-Jul-14, ELECTRICAL
Provide & Install New Utilities
Obtain Shutdown & Connect to Existing
Remove & Relocate of Existing Utilities
Remove & Dispose of Existing Utilities17-Jul-14, WATERLINES
Provide & Install New Utilities
Obtain Shutdown & Connect to Existing
Remove & Relocate of Existing Utilities
Remove & Dispose of Existing Utilities17-Jan-15, PEDESTRIAN UNDERPA
17-Jan-15, GENERAL
07-Nov-14, UNDERPASS STRUCTURE
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Backfilling17-Jan-15, ENTRANCE & EXIST
Casting of Floor Slab
Casting of Walls
Casting of Landing Slabs & Stair Case
Casing of Beams & Roof Slab10-Dec-14, ROAD LIGHTING & ELEC
10-Dec-14, GENERAL
30-Nov-14, CIVIL WORKS & CABLING
Trench for Low Voltage Cables
Laying of Ducts
Laying of Cables
Lighting Columns Concrete Foundations
High Masts Concrete Foundations
Concrete Foundations for Transformer 10-Dec-14, COLUMNS, HIGH MASTS
Fixing of High Masts
Fixing of Lighting Poles10-Dec-14, TRANSFORMERS & FEEDER PILLARS
Installation of Feeder Pillar
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 15 of 17
Data Date: 30-Oct-13 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A4870 Power Supply Connections to Feeder Pillar 20 21-Nov-14 10-Dec-14 0 0 A4860
A4857 33 KV & 11 KV Pad Mounted & Pole Mounted Transformers Substations 20 21-Nov-14 10-Dec-14 0 0 A4855
DRAINAGE WORKSDRAINAGE WORKS 40 29-May-14 07-Jul-14 11996
RC PIPESRC PIPES 40 29-May-14 07-Jul-14 11996
GENERALGENERAL 40 29-May-14 07-Jul-14 11996
A5130 Trench Excavation Work 20 29-May-14 17-Jun-14 547 M3 A6060 A5140
A5140 Laying of Drainage Pipes (RCC) 20 03-Jun-14 22-Jun-14 0 0 A5130, A6380 A5150
A5150 Construction of Manholes 20 10-Jun-14 29-Jun-14 20 0 A5140 A5160
A5160 Backfilling 20 18-Jun-14 07-Jul-14 11429 M3 A5150 A5500
ROAD FINISHING WORKSROAD FINISHING WORKS 133 22-Oct-14 03-Mar-15 80795
GENERALGENERAL 133 22-Oct-14 03-Mar-15 80795
EMBANKMENT, SUBBASE & AGGREGATE BASEEMBANKMENT, SUBBASE & AGGREGATE BASE 74 22-Oct-14 03-Jan-15 60026
A5500 Backfilling to Embankment 50 22-Oct-14 10-Dec-14 28571 M3 A4852, A5260, A5160 A5510
A5510 Subgrade Preparation 40 11-Nov-14 20-Dec-14 11064 M2 A5500 A5520
A5520 Preparation of Granular Subbase 40 18-Nov-14 27-Dec-14 6674 M3 A5510 A5530
A5530 Preparation of Aggregate Base Course 40 25-Nov-14 03-Jan-15 13717 M3 A5520 A5540
MEDIAN & SIDEWALK PAVINGMEDIAN & SIDEWALK PAVING 47 11-Dec-14 26-Jan-15 9662
A5540 Installation of Precast Concrete Curbs 40 11-Dec-14 19-Jan-15 4105 M A5530 A5560
A5560 Installation of Interlocking Tiles 40 18-Dec-14 26-Jan-15 5557 M2 A5540 A5570
NEW BITUMINOUS LAYERSNEW BITUMINOUS LAYERS 59 25-Dec-14 21-Feb-15 11084
A5570 Bituminous Prime Coat 38 25-Dec-14 31-Jan-15 0 0 A5560 A5580
A5580 Bituminous Base Course 38 01-Jan-15 07-Feb-15 6325 M3 A5570 A5590
A5590 Bituminous Tack Coat 38 08-Jan-15 14-Feb-15 0 0 A5580 A5600
A5600 Bituminous Wearing Course 38 15-Jan-15 21-Feb-15 4759 M3 A5590 A5620
HIGHWAY SIGNS & ROAD MARKINGHIGHWAY SIGNS & ROAD MARKING 20 12-Feb-15 03-Mar-15 23
A5620 Fixing of Highway Signs Single & Multiple Poles 15 12-Feb-15 26-Feb-15 22 NO. A5600, A6410 A5630
A5630 Fixing of Overhead & Gantry Signs 15 12-Feb-15 26-Feb-15 1 NO. A5620 A5640
A5640 Traffic Lines & Road Studs 10 22-Feb-15 03-Mar-15 0 0 A5630 A1520, A6100, A6730
SURVICE ROADSSURVICE ROADS 118 04-Mar-15 29-Jun-15 21323
SR2 (CH 1+200 to 1+477.488)SR2 (CH 1+200 to 1+477.488) 118 04-Mar-15 29-Jun-15 21323
TRAFFIC SHIFTINGTRAFFIC SHIFTING 4 04-Mar-15 07-Mar-15 0
TO NEW MAIN ROADTO NEW MAIN ROAD 4 04-Mar-15 07-Mar-15 0
GENERALGENERAL 4 04-Mar-15 07-Mar-15 0
A1520 Placing of Plastic Barriers & Temporary Signs 4 04-Mar-15 07-Mar-15 0 0 A5640 A1530
A1530 Shift Traffic from Existing Southern & Northeren Service Roads to New Main Road 0 07-Mar-15 0 0 A1520 A5790
GENERAL CIVIL WORKSGENERAL CIVIL WORKS 16 08-Mar-15 23-Mar-15 711
CLEARING & EXCAVATIONCLEARING & EXCAVATION 16 08-Mar-15 23-Mar-15 711
GENERALGENERAL 16 08-Mar-15 23-Mar-15 711
A5790 Clearing & Grubbing 5 08-Mar-15 12-Mar-15 710 M2 A1530 A5800, A10190
A5800 Removal of Structures & Obstructures 5 10-Mar-15 14-Mar-15 1 LS A5790 A5820
A5820 Road Way Excavation 12 12-Mar-15 23-Mar-15 0 0 A5800 A4910
PEDESTRIAN UNDERPASS 3 (SR2 CH 01+320) - STAGE 2PEDESTRIAN UNDERPASS 3 (SR2 CH 01+320) - STAGE 2 108 08-Mar-15 23-Jun-15 3802
GENERALGENERAL 108 08-Mar-15 23-Jun-15 3802
UNDERPASS STRUCTUREUNDERPASS STRUCTURE 76 08-Mar-15 22-May-15 2990
A10190 Structural Excavation 10 08-Mar-15 17-Mar-15 584 M3 A5790 A10150
A10150 Blinding of Concrete 12 11-Mar-15 22-Mar-15 137 M3 A10190 A10160
A10160 Casting of Base Slab 21 18-Mar-15 07-Apr-15 185 M3 A10150 A10170, A10210
A10170 Casting of Walls 21 08-Apr-15 28-Apr-15 185 M3 A10160 A10180
A10180 Casting of Top Slab 21 29-Apr-15 19-May-15 185 M3 A10170 A10200
A10200 Backfilling 3 20-May-15 22-May-15 1714 M3 A10180 A5650
ENTRANCE & EXISTENTRANCE & EXIST 77 08-Apr-15 23-Jun-15 812
A10210 Casting of Floor Slab 22 08-Apr-15 29-Apr-15 194 M3 A10160 A10220
A10220 Casting of Walls 35 30-Apr-15 03-Jun-15 309 M3 A10210 A10230, A10240
A10240 Casting of Landing Slabs & Stair Case 35 20-May-15 23-Jun-15 309 M3 A10220 A10230
A10230 Casing of Beams & Roof Slab 20 04-Jun-15 23-Jun-15 0 0 A10220, A10240 A6100
J J J J J J J J J
2014 2015 2016
Power Supply Connections to Feeder Pillar
33 KV & 11 KV Pad Mounted & Pole Mo
07-Jul-14, DRAINAGE WORKS
07-Jul-14, RC PIPES
07-Jul-14, GENERAL
Trench Excavation Work
Laying of Drainage Pipes (RCC)
Construction of Manholes
Backfilling03-Mar-15, ROAD FINISHING WORKS
03-Mar-15, GENERAL
03-Jan-15, EMBANKMENT, SUBBASE
Backfilling to Embankment
Subgrade Preparation
Preparation of Granular Subbase
Preparation of Aggregate Base Course26-Jan-15, MEDIAN & SIDEWALK PAVING
Installation of Precast Concrete Curbs
Installation of Interlocking Tiles21-Feb-15, NEW BITUMINOUS LAYERS
Bituminous Prime Coat
Bituminous Base Course
Bituminous Tack Coat
Bituminous Wearing Course03-Mar-15, HIGHWAY SIGNS & R
Fixing of Highway Signs Single & Multiple Poles
Fixing of Overhead & Gantry Signs
Traffic Lines & Road Studs29-Jun-15, SURVICE ROADS
29-Jun-15, SR2 (CH 1+200
07-Mar-15, TRAFFIC SHIFTING
07-Mar-15, TO NEW MAIN ROAD
07-Mar-15, GENERAL
Placing of Plastic Barriers & Temporary SignsShift Traffic from Existing Southern
23-Mar-15, GENERAL CIVIL WORKS
23-Mar-15, CLEARING & EXCAVATION
23-Mar-15, GENERAL
Clearing & Grubbing
Removal of Structures & Obstructures
Road Way Excavation23-Jun-15, PEDESTRIAN UN
23-Jun-15, GENERAL
22-May-15, UNDERPASS STRUCTURE
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Backfilling23-Jun-15, ENTRANCE & EXIST
Casting of Floor Slab
Casting of Walls
Casting of Landing Slabs & Stair Case
Casing of Beams & Roof Slab
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 16 of 17
Data Date: 30-Oct-13 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
ROAD LIGHTING & ELECTRICAL INSTALLATIONROAD LIGHTING & ELECTRICAL INSTALLATION 32 12-Mar-15 12-Apr-15 706
GENERALGENERAL 32 12-Mar-15 12-Apr-15 706
CIVIL WORKS & CABLINGCIVIL WORKS & CABLING 27 12-Mar-15 07-Apr-15 706
A4910 Trench for Low Voltage Cables 12 12-Mar-15 23-Mar-15 532 M A5820, A6530 A4920
A4920 Laying of Ducts 12 17-Mar-15 28-Mar-15 154 M A4910 A4930
A4930 Laying of Cables 12 22-Mar-15 02-Apr-15 0 0 A4920 A4960
A4960 Lighting Columns Concrete Foundations 10 29-Mar-15 07-Apr-15 20 NO. A4930 A5010, A5650
COLUMNS, HIGH MASTSCOLUMNS, HIGH MASTS 10 03-Apr-15 12-Apr-15 0
A5010 Fixing of Lighting Poles 10 03-Apr-15 12-Apr-15 0 0 A4960, A4680, A6350 A5690
ROAD FINISHING WORKSROAD FINISHING WORKS 50 11-May-15 29-Jun-15 16104
GENERALGENERAL 50 11-May-15 29-Jun-15 16104
EMBANKMENT, SUBBASE & AGGREGATE BASEEMBANKMENT, SUBBASE & AGGREGATE BASE 24 11-May-15 03-Jun-15 12361
A5650 Backfilling to Embankment 12 11-May-15 22-May-15 6857 M3 A4960, A10200, A1058 A5660
A5660 Subgrade Preparation 7 18-May-15 24-May-15 1936 M2 A5650 A5670
A5670 Preparation of Granular Subbase 7 23-May-15 29-May-15 1168 M3 A5660 A5680
A5680 Preparation of Aggregate Base Course 7 28-May-15 03-Jun-15 2400 M3 A5670 A5690
MEDIAN & SIDEWALK PAVINGMEDIAN & SIDEWALK PAVING 10 31-May-15 09-Jun-15 1691
A5690 Installation of Precast Concrete Curbs 7 31-May-15 06-Jun-15 718 M A5680, A5010 A5710
A5710 Installation of Interlocking Tiles 7 03-Jun-15 09-Jun-15 973 M2 A5690 A5720
NEW BITUMINOUS LAYERSNEW BITUMINOUS LAYERS 22 06-Jun-15 27-Jun-15 2042
A5720 Bituminous Prime Coat 7 06-Jun-15 12-Jun-15 0 0 A5710 A5730
A5730 Bituminous Base Course 7 11-Jun-15 17-Jun-15 1165 M3 A5720 A5740
A5740 Bituminous Tack Coat 7 16-Jun-15 22-Jun-15 0 0 A5730 A5750
A5750 Bituminous Wearing Course 7 21-Jun-15 27-Jun-15 877 M3 A5740 A5760
HIGHWAY SIGNS & ROAD MARKINGHIGHWAY SIGNS & ROAD MARKING 7 23-Jun-15 29-Jun-15 10
A5760 Fixing of Highway Signs Single & Multiple Poles 7 23-Jun-15 29-Jun-15 10 NO. A5750, A6410 A5780
A5780 Traffic Lines & Road Studs 5 25-Jun-15 29-Jun-15 0 0 A5760 A6100, A6740
J J J J J J J J J
2014 2015 2016
12-Apr-15, ROAD LIGHTING &
12-Apr-15, GENERAL
07-Apr-15, CIVIL WORKS & CABLING
Trench for Low Voltage Cables
Laying of Ducts
Laying of Cables
Lighting Columns Concrete Foundations12-Apr-15, COLUMNS, HIGH MASTS
Fixing of Lighting Poles29-Jun-15, ROAD FINISHING WORKS
29-Jun-15, GENERAL
03-Jun-15, EMBANKMENT, S
Backfilling to Embankment
Subgrade Preparation
Preparation of Granular Subbase
Preparation of Aggregate Base Course09-Jun-15, MEDIAN & SIDEWALK PAVING
Installation of Precast Concrete Curbs
Installation of Interlocking Tiles27-Jun-15, NEW BITUMINOUS LAYERS
Bituminous Prime Coat
Bituminous Base Course
Bituminous Tack Coat
Bituminous Wearing Course29-Jun-15, HIGHWAY SIGN
Fixing of Highway Signs Sing
Traffic Lines & Road Studs
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 17 of 17
Data Date: 30-Oct-13 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A