executive summary 1.1...

29
Project: Black Granite Mining Project Pre-Feasibility Report Applicant: M/s. Trinetra Granites 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The proposed mining lease of Black granite over an extent of 2.0 hects, in Sy.no. 617,Mulakaledu Village, Settur Mandal, Anantapur (Dist) Andhra Pradesh was granted to M/s. Trinetra Granites , proprietor for a period of 20 years by Director of Mines and Geology, Hyderabad. The proposed project is Black Granite mining having lease area of 1.0 ha and falls under Category- “B” as per EIA Notification 2006 and its amendments of the Ministry of Environment and Forests, New Delhi, Since The SEAC/SEIAA of AP is dissolved so the project is been submitted to Moef New Delhi. The mining lease is located in Sy.no. 617,Mulakaledu Village, Settur Mandal, Anantapur (Dist) Andhra Pradesh was granted to M/s. Trinetra Granites ., Andhra Pradesh.

Upload: others

Post on 21-Sep-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

Project: Black Granite Mining Project Pre-Feasibility Report Applicant: M/s. Trinetra Granites

1

Sri Sai Manasa Nature Tech Pvt Ltd

EXECUTIVE SUMMARY

1.1 Introduction The proposed mining lease of Black granite over an extent of 2.0 hects, in Sy.no. 617,Mulakaledu Village, Settur Mandal, Anantapur (Dist) Andhra Pradesh was granted to M/s. Trinetra Granites , proprietor for a period of 20 years by Director of Mines and Geology, Hyderabad.

The proposed project is Black Granite mining having lease area of 1.0

ha and falls under Category- “B” as per EIA Notification 2006 and its amendments of the Ministry of Environment and Forests, New Delhi, Since The SEAC/SEIAA of AP is dissolved so the project is been submitted to Moef New Delhi.

The mining lease is located in Sy.no. 617,Mulakaledu Village, Settur Mandal, Anantapur (Dist) Andhra Pradesh was granted to M/s. Trinetra Granites ., Andhra Pradesh.

Page 2: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

Project: Black Granite Mining Project Pre-Feasibility Report Applicant: M/s. Trinetra Granites

2

Sri Sai Manasa Nature Tech Pvt Ltd

1.2 Salient features of the project

Environmental setting

Project name Proposed Black Granite Mine Of M/s. Trinetra Granites

Mining Lease Area The area of the proposed mine is 1.0 ha. Location of mine Sy.no. 617,

Mulakaledu Village, Settur Mandal, Anantapur District, Andhra Pradesh

Latitude 14 0 18’ 46.09” N Longitude 76 0 56’ 49.02” E Toposheet number 57 B/15 Minerals of mine Black Granite Mining Proposed production of mine 529 m3/annum

Method of mining Opencast semi mechanized mining

Drilling/Blasting Drill-Hole patterns for primary and secondary smooth blasting

No of working days 300 days Water demand 2 KLD Sources of water Water will be supplied from bore wells of

the nearby area and also tankers Man power 26

Solid Waste 14980 m3/annum

Nearest railway station Challakere railway station is about 30.5 km due West from the lease area

Nearest airport Kempigowda Airport is about 148.0 km due West from lease area.

Page 3: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

Project: Black Granite Mining Project Pre-Feasibility Report Applicant: M/s. Trinetra Granites

3

Sri Sai Manasa Nature Tech Pvt Ltd

Proposed planning Mining method - Open Cast - Semi mechanized Project cost - Rs. 50 lakh Production - 529 m3/annum

Page 4: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

Project: Black Granite Mining Project Pre-Feasibility Report Applicant: M/s. Trinetra Granites

4

Sri Sai Manasa Nature Tech Pvt Ltd

2.0 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION 2.1 Identification of Project and Project Proponent

The project is proposed by T. Rajeswari Proprietor. The lease documents of mine are attached as Annexure II. The details of the project are given below:

Name of the applicant T. Rajeswari Name & Address of Applicant

W/o Late.T. Yerriswamy, Engilibanda(V),Kothepeta(Post), Gooty(M),Ananatapur (D),AP.

Mineral Black Granite Area (ha) 2.0 ha Postal Address W/o Late.T. Yerriswamy,

Engilibanda(V),Kothepeta(Post), Gooty(M),Ananatapur (D),AP.

Status of Mine Fresh application for Environmental Clearance

2.2 Brief Information about the Project The mining lease area of 2.0 ha is located in Government land, Sy.no. 617,Mulakaledu Village, Settur Mandal, Anantapur (Dist) Andhra Pradesh.

It has been proposed to produce approximately 529 m3/annum of Black granite.

Page 5: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

Project: Black Granite Mining Project Pre-Feasibility Report Applicant: M/s. Trinetra Granites

5

Sri Sai Manasa Nature Tech Pvt Ltd

2.3 Mining: Open cast method of mining is carried out in this mine by manually and

semi mechanization by using compressor operated jack hammer drills,

excavators, and dumper etc., Transportation will be made by trucks to

dispatching point.

2.3.1 Need for the Project and Its Importance to the Country or Region

Indian granite has a good market value in the world. Granite is an igneous, magma-formed rock that is generally made up of quartz, feldspar and mica. These minerals combine in varying percentages that account for the color, veining and crystallization patterns that make each granite deposit unique.

2.4 Demands-Supply Gap

The demand and supply for the color granite is growing which makes a lot of scope for revenue generation.

The earth crust is filled with different types of rock which ranges from igneous, sedimentary and metamorphic rocks. Granite is an igneous rock formed from the cooling of magma in an exothermic process. Granite popularly known as chippings /gravel is a very hard stone good for building and construction works globally. It is a common and widely occurring type of intrusive felsic, igneous rock. It has a medium to coarse texture occasionally with some individual crystals larger than the groundmass forming a rock known as porphyry. It can be pink to dark gray or even black depending on their chemistry and mineralogy. Granite is a hard, usually grey, stone used for building and

Page 6: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

Project: Black Granite Mining Project Pre-Feasibility Report Applicant: M/s. Trinetra Granites

6

Sri Sai Manasa Nature Tech Pvt Ltd

the most common rock type on the continental land masses. It is widely distributed throughout the continental crust of the earth and is the most abundant basement rock that underlies the relatively thin sedimentary veneer of the continents.

Its hard nature made it a very suitable and durable material for most Civil Engineering and Construction works. It is used in various ways as in;

Road Construction and Dimensional stones Building of Houses, Bridges and Drainages Manufacture of Marbles and Flooring Tiles Production of cement blocks Interior Decorations Art works (Antiquities) etc.

India is amongst the leading exporter countries of stones in the world. The major importers of Indian stones are USA, China, UK, Italy, Belgium, Germany, UAE, Hong Kong, Spain, Taiwan, Netherlands, Canada, Turkey, France, Russia and CIS countries. The growth is continuing and the demand for marble, granite, sandstone and other dimensional stones and stone products is anticipated to grow at around 15% CAGR.

2.5 Domestic/ Export Markets

Although granite is a minor mineral, it is a major contributor in foreign exchange earnings. India is the second largest exporter of raw granite after China and ahead of Brazil and South Africa.

Page 7: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

Project: Black Granite Mining Project Pre-Feasibility Report Applicant: M/s. Trinetra Granites

7

Sri Sai Manasa Nature Tech Pvt Ltd

2.6 Employment Generation

Proposed mining is semi -mechanized method and this project operation will provide livelihood to the 26 workers. It will provide employment to the people residing in vicinity.

Page 8: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

Project: Black Granite Mining Project Pre-Feasibility Report Applicant: M/s. Trinetra Granites

8

Sri Sai Manasa Nature Tech Pvt Ltd

3.0 PROJECT DESCRIPTION

3.1 Type of Project Including Interlinked and Interdependent

Projects, If Any.

The proposed Black Granite mine is of 2.0 ha. No interlinked projects were associated with this project.

3.2 Location

2.0 Hectares in Sy.no. 617,Mulakaledu Village, Settur Mandal, Anantapur (Dist) Andhra Pradesh. The mining lease area falls in Survey of India Toposheet No. : 57 B/15

Latitude : 14 0 18’ 46.09” N

Longitude : 76 0 56’ 49.02” E

Page 9: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

Project: Black Granite Mining Project Pre-Feasibility Report Applicant: M/s. Trinetra Granites

9

Sri Sai Manasa Nature Tech Pvt Ltd

Location of the mining lease in Anantapur District is shown in Fig – 1.

LOCATION MAP

Page 10: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

Project: Black Granite Mining Project Pre-Feasibility Report Applicant: M/s. Trinetra Granites

10

Sri Sai Manasa Nature Tech Pvt Ltd

Topo Map Showing 10 km Radius of Mine lease area is Enclosed as Fig-II.

Page 11: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

Project: Black Granite Mining Project Pre-Feasibility Report Applicant: M/s. Trinetra Granites

11

Sri Sai Manasa Nature Tech Pvt Ltd

3.3 Details of Alternate Sites

No alternate site was considered as the project is mineral specific and site specific.

3.4 Size or magnitude of operation

The proposed mine has lease over an area of 2.0 ha and the production rate is 529m3/annum

Production parameters

The mine plan is prepared for first five years. The Mineral production target for five years is given below:

Page 12: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

Project: Black Granite Mining Project Pre-Feasibility Report Applicant: M/s. Trinetra Granites

12

Sri Sai Manasa Nature Tech Pvt Ltd

Table Showing Year wise Production Programme

3.5 Geology and Reserves

3.5.1 Topography

The Lease Area is a mound raising to a height of 4mts. The area is devoid of any trees and Forest. In general area is plain studded undulating hillocks. 3.5.2 Local Geology

The subject area belongs to a mound raising to a height of about 4.0

m with boulders from ground level. The granite is exposed as a small hillock

in the centre portion with steep slopes and soil is covering the foot portion.

However the granite sheet rock is well exposed without any over burden. It

represents late magmatic injection of closepet granite.

Page 13: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

Project: Black Granite Mining Project Pre-Feasibility Report Applicant: M/s. Trinetra Granites

13

Sri Sai Manasa Nature Tech Pvt Ltd

3.5.3 Regional Geology

The Anantapur District forms a part of Indian Peninsular shield, which has

remained stable formation of the crust. They are exposed in the eastern part

of the district.

The area represents the Archaean granite greenstone terrain of the eastern

part of the Anantapur district.

The region is occupied by moulds, hillocks, sheet rocks and domal hills. The

granite gneiss ranging in composition from tonalite-trandhjenite to

granodiorite, migmatite gneiss and granodiorite-granite with compositional

variation between granodiorite,adamalite,granite and alkali feldspar

granite. All these rocks are traversed by dikes of picrite, norite, gabro and

dolerite composition.

The subject area is occupied by Multi Granite (Migmatite) which follow a

General trend of NE-SW.

3.5.4 EXPLORATION:

a) Present Status:

There is a pit on the eastern side of the Q.L Applied area. Prospecting

operation took place in the area 5 years ago. The pit directions are

9mts,length and 6mts width with a 3mts depth. The applied area does not

contain any forest cover. The annual production is 529 m3/annum.

Page 14: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

Project: Black Granite Mining Project Pre-Feasibility Report Applicant: M/s. Trinetra Granites

14

Sri Sai Manasa Nature Tech Pvt Ltd

3.5.5 Reserves Geological Reserves:

Life of the Mine: Mineable Reserves / Annual production

=18696 m3 /500 m3 =37 years life of mine.

Production for the First Five Years Plan period:-

Mining over the period of next five years is expected to produce about

2645m3 of market grade rough blocks with an average annual production of

529m3.

Page 15: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

Project: Black Granite Mining Project Pre-Feasibility Report Applicant: M/s. Trinetra Granites

15

Sri Sai Manasa Nature Tech Pvt Ltd

Year wise Granite Production: Table –2

3.6 PROJECT DESCRIPTION WITH PROCESS DETAILS 3.6.1 Method of Mining

Type of Mining: Open cast method of mining is carried out in this mine:

by manually and semi mechanization by using compressor operated

jack hammer drills, excavators, and dumper etc., Transportation will

be made by trucks to dispatching points. (Rail head/Port)

Brief Description: (Existing method of working):

The mining operations are carried out by semi-mechanization as

open cast mining. Hydraulic excavator and compressor operated jack

hammers were used for cutting the rock. Close spaced drilling of 0.2m

Page 16: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

Project: Black Granite Mining Project Pre-Feasibility Report Applicant: M/s. Trinetra Granites

16

Sri Sai Manasa Nature Tech Pvt Ltd

was adopted along a straight line and charged with low explosives to

avoid feather cracks.

c) Removal/Excavation of O.B. and other Quarry waste:

The South-Western side of the area is selected for dump yard for next

five years and the waste will be stocked over a length of 40mtrs. with

width of 35 mtrs. To a height of 9.0 mtrs. as enmarked in plate

no.4.Step dumping will be resorted. This material can be utilized to fill

the pits after quarry operations are over. When the dumps reach their

optimum height suitable greenery will be grown on this dumps to

stabilize them.

d) Separation of large primary Blocks from the mother rock by pre-splitting (Primary cut)

The mining will be followed in the form of linear cut method. This

involves loosing of the primary block from mother rock. Hence

primary cutting will be done by line drilling method where close

spaced parallel holes along straight line will be made. Line drilling

method is used for separation of primary blocks. i) Once the free face

is developed in working place, the primary cuts is taken up over a

maximum length of 10 mtrs with a width of 3 mtrs and to a depth of 6

mtrs. Depends upon the joints availability. These dimensions are

confirmed as for field studies. Primary block will be cut Into

secondary blocks by Jackhammer drilling and wedge cutting and this

block will be dislodged from in-situe position by an excavator.

Line drilling method will be used for cutting the primary blocks which involve drilling and blasting.

iii) The holes are charged with low explosive catridge like gun

powder and non-delay detonators for smooth blasting.

Page 17: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

Project: Black Granite Mining Project Pre-Feasibility Report Applicant: M/s. Trinetra Granites

17

Sri Sai Manasa Nature Tech Pvt Ltd

iv) The use of delay detonates causes fragmentation and cracks in

rocks. The non detonating cords are inserted into the holes and

the holes are stemmed with muck and plugged at the mouth

and fired.

v) Thus the block will separate from the mother rock, which is

pulled off from the face with cranes or shovel.

e) Sub Division of large Primary Blocks into Secondary Block: This will be done drilling close spaced holes (along a line) down to the

depth and the secondary block will be removed easily by just pulling it

with the help of proclain. Close spaced holes will be drilled to the

half the length of the block on either side of it by using wedges

blocks can be separated.

f) Production of Commercial Blocks:

After primary separation the rock mass will be carefully examined to

avoid hair line cracks, mineral seggregrations and veins etc., The

dressing of the rough blocks will be made by chipping the edges and

geometrically equating the edges of the block at the dressing yard.

The rough blocks obtained after primary cut it will be dressed for

obtained good geometric shape of granite. Thus the commercial

blocks are produced.

Extent of Mechanization: a. Since it has been decided to undertake semi-mechanized mining

Operations, the following mentioned mine machinery will be

deployed. Excavator — One (Bucket capacity 1m3, Boom length,

7m, Model: Tata Hitachi 200Lc)

Page 18: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

Project: Black Granite Mining Project Pre-Feasibility Report Applicant: M/s. Trinetra Granites

18

Sri Sai Manasa Nature Tech Pvt Ltd

i i . 50 CFM — AIR compressors - One

i i i . Jack Hammers — three units.

i v. 17 Tonnes Tippers — 2 Nos.

Minor Tools: Chisels, Crowbars, Pick of axes spades and hammers of

different sizes.

h) Employment Potential: Taking 25 working days in a month, there

will be 300 working days in a year. The expected output of raw material per day is about 2 to 3 CBM on an average. Based on the demands from the purchasers, labour force will be increased.

i) Loading Equipment: Loading of the blocks will be made by chain pulley with the help of crane or procline by the skilled labourers to the hired trucks to transport the material to the nearest ports/ destination of customer.

j) Organization Chart of the Quarry:-

1. Mines Manager: Diploma in Mining — with second class Mines 2. Blaster Cum Mate : S.S.C. with blaster certificate

holder 3. Excavator Operator : 1 No. 4. Compressor Operator: 1 No. 5. Tipper Operators 2 Nos. 6. Drillers 2 Nos. 7. Helpers 9Nos. 8. Cutters 8 Nos. 9. Watchman 1 No. 10. Blaster Cum Mate : 1 No.

Page 19: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

M/s. Stone Park Exports Pre-Feasibility Report

19

Sri Sai Manasa Nature Tech Pvt Ltd

k) Machinery to be Deployed:

The machinery to be utilized during the prospecting period are 1 proclain, 2 dumpers 1 compressor, 4 jack hammer drills.

Details of Production so far mined from beginning of Quarry.

There is no production as the Q.L not yet granted.

l) Labour to be Employed:

Daily 8 members of labours to be employed in this Mine. Drinking water and

first aid facilities were provided in this area.

m) Quantum of Excavation (OB & Granite): During this five years operations a total rock mass of 25650 m3 will be

excavated and 3335 cum of granite Blocks will be recoverable from this rock

mass and remaining material of about 22315 m3 will go as mineral waste.

n) Magazine:

Smooth blasting techniques and special explosives and silent non explosive

demolishing agents like ACCONEX will be used. An area is demarcated within the

lease area for portable magazine. This site is located at a safe distance from the

quarry, strictly adhering to the rules and regulations laid down for safe storage

and handling of the explosives as per the explosives Act. The applicant at the

moment is not in possession of blasting license. He will apply for a license as

soon as the Q.L. is granted.

Page 20: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

M/s. Stone Park Exports Pre-Feasibility Report

20

Sri Sai Manasa Nature Tech Pvt Ltd

p) Drilling and Blasting :

Drilling and Blasting plays vital role in determining the size and shape of rough

blocks. Drilling pattern is important in developing a working face and also

preparing the rough blocks suitable for their use in appropriate processing

units. Even though, there are no important places in and around the area,

blasting will be carried with all precautionary measures.

g) Drilling Parameters:

i. Drill holes diameter – 74/Pmm.

ii. Depth and inclination of the blast holes. 3 meter in case of

Separation primary blocks depending on the block size. Then the drill-hole

will be vertical.

iii. Spacing and burden : 1.5 x 3m.

iv. Stemming and charging of the blast hole. The Blast hole will be charged with

100 grams of explosives and filled with clan pills subsequently; the shot hole will

be stemmed.

v. Explosive type (1) Slurry based explosives or Gun Powder.

h) Broad Blasting Parameter :

Drill-Hole patterns for primary and secondary smooth blasting. Uniform

single line, equidistant holes (line drilling) will be deployed for separation

of blocks from mother rock. In the case of sheet rock the primary drilling

will be in the form of equidistant vertical holes to take out blocks of Gang

Saw.

Page 21: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

M/s. Stone Park Exports Pre-Feasibility Report

21

Sri Sai Manasa Nature Tech Pvt Ltd

i) Description of Processing plant if any:

There is no any processing plant.

j) Site Services:-

It is also proposed to provide the site services like Mines office and other

statutory constructions like rest shelter, first aid, work shed and drinking

water as required near the quarry lease. Drinking water is supplying to

the workers from the bore wells in the adjacent agricultural fields.

3.7 Raw Material Required Along With Estimated Quantity, Likely

Source, Marketing Area of Final Product/S, Mode of Transport of Raw Material and Finished Product

No raw material will be required in the proposed project. The operation involves the extraction of color granite and dumping in stock yard. The dressed dimensional will be transported through hired trucks to the granite market or sea port.

3.7.1 Use of Mineral

Black granite will be used domestic and international market. Its hard nature made it a very suitable and durable material for most Civil Engineering and Construction works. It is used in various ways as in;

Road Construction and Dimensional stones Building of Houses, Bridges and Drainages Manufacture of Marbles and Flooring Tiles Production of cement blocks Interior Decorations

Page 22: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

M/s. Stone Park Exports Pre-Feasibility Report

22

Sri Sai Manasa Nature Tech Pvt Ltd

Art works (Antiquities) etc.

3.7.2 Processing

Processing of granite is not involved in the lease area. 3.8 Resource Optimization/ Recycling and Reuse

Not envisaged. 3.9 Availability of Water Its Source, Energy/ Power Requirement and

Source Water Requirement

Water is required only for drinking purposes and dust suppression. The

number of working people is around 26 so the total water requirement will

be around 2 KLD. About 1 KLD will be required for dust suppression,

0.5KLD for drinking purpose and 0.5 KLD for Green Belt. This water will be

supplied from bore wells of nearby area.

3.10 QUANTITY OF WASTES TO BE GENERATED (LIQUID AND SOLID) AND

SCHEME FOR THEIR MANAGEMENT/ DISPOSAL

3.10.1 Solid Waste Generation & its Disposal

Mine waste of about 14980 m3 will be generated for next 5 years. Solid

waste generated for next 5 years will be dumped towards the SW side of

the area stocked over a length of 40mtrs,width of 20mtrs to a height of

6mtrs.

Page 23: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

M/s. Stone Park Exports Pre-Feasibility Report

23

Sri Sai Manasa Nature Tech Pvt Ltd

3.10.2 Liquid Effluent

No liquid effluent will be generated at the mine site. The domestic wastewater generated will be sent to septic tanks followed by soak pits.

Page 24: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

M/s. Stone Park Exports Pre-Feasibility Report

24

Sri Sai Manasa Nature Tech Pvt Ltd

3.11 SCHEMATIC REPRESENTATIONS OF THE FEASIBILITY DRAWING WHICH GIVEN INFORMATION OF EIA PURPOSE

Form-I, Pre-feasibility project report with proposed TOR to MoEF (EAC)

TOR approved by EAC

Draft EIA report to SPCB by project proponent

Public consultation process by SPCB

Proceedings of public consultation

Appraisal and recommendation by EAC

Approval by MoEF

Rejected Approved

Display on the MoEF

website

TOR rejected by MoEF on the recommendation of EAC

Summary EIA and Form-I display on the website by SPCB

Display at Panchayat, ZP, DM/DC/Dy. Com & on the SPCB website

To proponent for submission of final EIA report/Supplementary report to

draft EIA

Referred back to EAC under communication to the project

proponent Display on MoEF website & project proponent website

Post EC monitoring Submission of half yearly compliance

report to MoEF/RO-MoEF

Display of compliance report on

MoEF website

Project Concept and Site identification

Page 25: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

M/s. Stone Park Exports Pre-Feasibility Report

25

Sri Sai Manasa Nature Tech Pvt Ltd

4. SITE ANALYSIS 4.1 Connectivity 4.1.1 Nearest Railway Station

Challakere railway station is about 30.5 km due West from the lease area 4.1.2 Nearest Airport Kempigowda Airport is about 148.0 km due West from lease area. 4.2 LANDFORM, LANDUSE AND LAND OWNERSHIP The mining lease is located in Government Land and the entire area is covered with granite exposures. 4.3 Topography The Lease Area is a mound raising to a height of 4mts.

The area is devoid of any trees and Forest. In general area is plain studded

undulating hillocks. Mining will be done by developing Benches 6m height.

Page 26: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

M/s. Stone Park Exports Pre-Feasibility Report

26

Sri Sai Manasa Nature Tech Pvt Ltd

4.4 Climatic data from secondary sources

The peak summer will be in the month of May, Highest temperature of

41.6˚C is recorded in the area during the month of May and the lowest

temperature 17.60˚ C is recorded in the month of January, 2009.Normal

rain fall is 909mm, during 2008-2009 the rainfall of the area was of about

1026mm.

5.0 PLANNING BRIEF 5.1 Planning Concept

Lease Area has been approved by Department of mines and Geology, Govt. of A.P. (Proceedings No. 29010/R4-1/2009 dt: 1/6/2011)

Approved Mining plan Proceeding No: 3867/MP-ATP/2011 dated 14-9-2011.

It is proposed to produce 529 m3/annum of Black granite from the proposed mining lease.

5.2 Population projection

The project will employ mostly workers from nearby villages. There will not be any increase in population due to the project.

5.3 Land use planning

The Subject area is a Govt. land and an extent of about 1875 sqm area will

be sliced down during first 5 yrs to a depth of 10 mtrs.

Page 27: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

M/s. Stone Park Exports Pre-Feasibility Report

27

Sri Sai Manasa Nature Tech Pvt Ltd

5.4 Assessment of Infrastructure Demand (Physical & Social)

On the basis of the preliminary site visit, the infrastructure demand in the villages was assessed on the basis of need and priority. The assessment will be made in the socio economic survey.

5.5 Amenities/Facilities

Site Services like office cum rest shelter is already constructed in the lease area

6.0 PROPOSED INFRASTRUCTURE

6.1 Industrial Area (Processing Area)

No infrastructure is proposed.

6.2 Residential Area (Non Processing Area) As the local persons will be given employment, no residential area/ housing is proposed within the mining lease area.

6.3 Green Belt

Green belt will be developed in 7.5 buffer zone and on the backfilled area within the mine lease area.

6.4 Water Management

About 1 KLD will be required dust suppression purpose and greenbelt and about 0.5 KLD Green Belt and 0.5KLD for drinking therefore total water requirement is 2 KLD. This water will be supplied from bore wells of the nearby area.

Page 28: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

M/s. Stone Park Exports Pre-Feasibility Report

28

Sri Sai Manasa Nature Tech Pvt Ltd

6.5 Sewerage System

The domestic wastewater generated will be sent to septic tanks followed by soak pits.

6.6 Industrial Waste Management

Not applicable.

6.7 Solid Waste management

About 80% of the material from granite production is going to be generated as solid waste. The waste will be dumped in dump yard of the mining lease area and will be backfilled into the minedout pit at the end of the mining.

7 Rehabilitation And Resettlement (R&R) Plan

Not Applicable.

Page 29: EXECUTIVE SUMMARY 1.1 Introductionenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Aug_… · 1 Sri Sai Manasa Nature Tech Pvt Ltd EXECUTIVE SUMMARY 1.1 Introduction The

M/s. Stone Park Exports Pre-Feasibility Report

29

Sri Sai Manasa Nature Tech Pvt Ltd

8 PROJECT SCHEDULE & COST ESTIMATES

The Total cost of project would be around Rs. 50 lakhs.

Environmental Management Plan budget

9.0 Analysis Of Proposal (Final Recommendations) 9.1 Financial and Social Benefits with Special Emphasis on the Benefit to

the Local People Including Tribal Population, If Any, In the Area.

Although granite is a minor mineral, it is a major contributor in foreign exchange earnings. India is the second largest exporter of raw granite after China and ahead of Brazil and South Africa.

This project will also provide employment to local people helping them earn livelihood.

***********

S. No Component Amount in Lakhs 1 Dust suppression 1.0 2 Green Belt 0.5 3 Reclamation 0.5 Total 2.0 Recurring cost 0.5