euclidcreek.blogspot.com
Euclid Creek Tunnel
Community Update
May 21, 2013
![Page 2: euclid creek tunnel ppt may 2013](https://reader033.vdocuments.us/reader033/viewer/2022060123/55975afa1a28ab480e8b4575/html5/thumbnails/2.jpg)
euclidcreek.blogspot.com
Agenda
• Project Overview
• Construction Updates
• Shaft Updates
• Contact Info
![Page 3: euclid creek tunnel ppt may 2013](https://reader033.vdocuments.us/reader033/viewer/2022060123/55975afa1a28ab480e8b4575/html5/thumbnails/3.jpg)
euclidcreek.blogspot.com
Project Overview
![Page 4: euclid creek tunnel ppt may 2013](https://reader033.vdocuments.us/reader033/viewer/2022060123/55975afa1a28ab480e8b4575/html5/thumbnails/4.jpg)
euclidcreek.blogspot.com
Euclid Creek Tunnel: By the Numbers
• Tunnel
– 24’ diameter
– 11,650/17,750’
– 60,100,000 gallons
• ~30 near surface structures
– 11 complete
– 14 under construction
• Shafts: 5 total
– 24’ to 60’ diameter
– 185-225’ deep
– 3 full depth, 2 @ mid
• 2,440 linear feet of open cut pipe placed
• 2,110 linear feet of microtunnel complete
– 240 more to go
![Page 5: euclid creek tunnel ppt may 2013](https://reader033.vdocuments.us/reader033/viewer/2022060123/55975afa1a28ab480e8b4575/html5/thumbnails/5.jpg)
euclidcreek.blogspot.com
Construction Updates
• Mackenzie has “mined and lined” more than half of Euclid Creek Tunnel
• Nottingham at Lakeshore now opened
• E 174th at Lakeshore to Nottingham closed
• E 156th at Lakeshore temporarily closed (to be reopened by June)
![Page 6: euclid creek tunnel ppt may 2013](https://reader033.vdocuments.us/reader033/viewer/2022060123/55975afa1a28ab480e8b4575/html5/thumbnails/6.jpg)
euclidcreek.blogspot.com
Shaft #1: Construction Staging Site
• “Mackenzie” tunneled and lined 11,650’+
• Operating 24/7 with regularly-scheduled maintenance periods
• Lake Erie tunneling completed
• Tunneling beneath Beulah Park completed
![Page 7: euclid creek tunnel ppt may 2013](https://reader033.vdocuments.us/reader033/viewer/2022060123/55975afa1a28ab480e8b4575/html5/thumbnails/7.jpg)
Project Overview
![Page 8: euclid creek tunnel ppt may 2013](https://reader033.vdocuments.us/reader033/viewer/2022060123/55975afa1a28ab480e8b4575/html5/thumbnails/8.jpg)
euclidcreek.blogspot.com
![Page 9: euclid creek tunnel ppt may 2013](https://reader033.vdocuments.us/reader033/viewer/2022060123/55975afa1a28ab480e8b4575/html5/thumbnails/9.jpg)
euclidcreek.blogspot.com
Shaft #2: Easterly WWTP
• Shaft 2: 95 feet excavated
– Blasting last 100 feet; will begin this year
• Structure 2-2: installing final lining
• Structure 2-8: installing final lining
![Page 10: euclid creek tunnel ppt may 2013](https://reader033.vdocuments.us/reader033/viewer/2022060123/55975afa1a28ab480e8b4575/html5/thumbnails/10.jpg)
euclidcreek.blogspot.com
![Page 11: euclid creek tunnel ppt may 2013](https://reader033.vdocuments.us/reader033/viewer/2022060123/55975afa1a28ab480e8b4575/html5/thumbnails/11.jpg)
euclidcreek.blogspot.com
• East 156th Street
– Road temporarily closed for three weeks, to be reopened by June (close mid July)
– Detour for residents requiring access to East 156th
Street north of closure is via apartment complex
– West side sidewalk still closed
Shaft #3: Beulah Park
![Page 12: euclid creek tunnel ppt may 2013](https://reader033.vdocuments.us/reader033/viewer/2022060123/55975afa1a28ab480e8b4575/html5/thumbnails/12.jpg)
euclidcreek.blogspot.com
![Page 13: euclid creek tunnel ppt may 2013](https://reader033.vdocuments.us/reader033/viewer/2022060123/55975afa1a28ab480e8b4575/html5/thumbnails/13.jpg)
euclidcreek.blogspot.com
• Shaft 3
– Blasting to begin mid-June
• Internal Pre Blast Surveys
– For structures within 500’ with basements only
– 3 copies of letters distributed (2 copies via certified mail and 1 copy hand delivered)
– Surveys currently on going for those residents that replied to letter
Shaft #3: Beulah Park
![Page 14: euclid creek tunnel ppt may 2013](https://reader033.vdocuments.us/reader033/viewer/2022060123/55975afa1a28ab480e8b4575/html5/thumbnails/14.jpg)
euclidcreek.blogspot.com
Site #4: Triangle Park
• Excavation of shaft is complete at this site
• Nottingham Road is re-opened
• East 174th Street closed (Structures 4-5 and 4-6)
• Lakeshore Boulevard Relief Sewer begins construction before completion of baffle structure lining
![Page 15: euclid creek tunnel ppt may 2013](https://reader033.vdocuments.us/reader033/viewer/2022060123/55975afa1a28ab480e8b4575/html5/thumbnails/15.jpg)
euclidcreek.blogspot.com
YOU ARE HERE!
![Page 16: euclid creek tunnel ppt may 2013](https://reader033.vdocuments.us/reader033/viewer/2022060123/55975afa1a28ab480e8b4575/html5/thumbnails/16.jpg)
euclidcreek.blogspot.com
Site #4: Lakeshore Blvd. Relief Sewer
• New Shaft (4-1A) Constructed
– 22’ excavation diameter, 16’ finished diameter
– 70’ deep
• 66” trenchless sewer pipe, tunneled from Euclid Creek Pump Station to Shaft 4
![Page 17: euclid creek tunnel ppt may 2013](https://reader033.vdocuments.us/reader033/viewer/2022060123/55975afa1a28ab480e8b4575/html5/thumbnails/17.jpg)
![Page 18: euclid creek tunnel ppt may 2013](https://reader033.vdocuments.us/reader033/viewer/2022060123/55975afa1a28ab480e8b4575/html5/thumbnails/18.jpg)
euclidcreek.blogspot.com
Site #4: Lakeshore Blvd. Relief SewerConstruction Schedule
• July 2013 January 2015
– Construction of new Shaft by Euclid CreekPump Station
– Trenchless construction from Triangle Park tonew shaft by pump station
– Contractor: McNally/Kiewit ECT JV
• March 2014 September 2015
– Open cut construction on Lakeshore Blvd.,East Park Dr. & Crestland Rd. and rehabilitation of Euclid Creek Pump Station
– Contractor: TBD
![Page 19: euclid creek tunnel ppt may 2013](https://reader033.vdocuments.us/reader033/viewer/2022060123/55975afa1a28ab480e8b4575/html5/thumbnails/19.jpg)
euclidcreek.blogspot.com
Site #5: Nottingham & St. Clair
• Excavation complete of Shaft 5:225 feet excavated
• Concrete placement for final lining began week of April 8th
– 4,700 cy of concrete
• Continued excavation of Structure 5-4
• Closure of St. Clair at E 185th upcoming June/July
![Page 20: euclid creek tunnel ppt may 2013](https://reader033.vdocuments.us/reader033/viewer/2022060123/55975afa1a28ab480e8b4575/html5/thumbnails/20.jpg)
euclidcreek.blogspot.com
![Page 21: euclid creek tunnel ppt may 2013](https://reader033.vdocuments.us/reader033/viewer/2022060123/55975afa1a28ab480e8b4575/html5/thumbnails/21.jpg)
euclidcreek.blogspot.com
Stay Informed
• Blog
– EuclidCreek.blogspot.com
• Collinwood Observer
– Ads and articles
• Semi-Monthly Newsletter
– E-mail distribution
– [email protected] to be added to the list
![Page 22: euclid creek tunnel ppt may 2013](https://reader033.vdocuments.us/reader033/viewer/2022060123/55975afa1a28ab480e8b4575/html5/thumbnails/22.jpg)
euclidcreek.blogspot.com
How to Reach Us
Social Mediafacebook.com/yoursewerdistrict@neorsd | @wallywaterdrop
Customer Service (216) 881-8247
Emergencies: NEORSD ECT Field Office(216) 268-5469
Ryan Sullivan, [email protected] Elting, [email protected]
![Page 23: euclid creek tunnel ppt may 2013](https://reader033.vdocuments.us/reader033/viewer/2022060123/55975afa1a28ab480e8b4575/html5/thumbnails/23.jpg)
euclidcreek.blogspot.com
Next Meeting
Tuesday, June 18, 20136:00 p.m.Cleveland Public Library,Memorial-Nottingham Branch