establishing the performance measurement baseline (v4)

34
Copyright 2011 © , Niwot Ridge, L.L.C. All Rights Reserved ESTABLISHING THE PERFORMANCE MEASUREMENT BASELINE (PMB) AACE WORKSHOP DENVER, COLORADO APRIL 16 TH , 2011 The Performance Measurement Baseline is a time–phased schedule of all the work to be performed, the budgeted cost for this work, and the organizational elements that produce the deliverables from this work. 1 /34

Upload: glen-alleman

Post on 18-Nov-2014

129 views

Category:

Technology


0 download

DESCRIPTION

The Performance Measurement Baseline is the "anchor" of any successful project. It tells the story of what is being developed, how much it will cost, when the work will be performances, and when the deliverables - that produce the value of the project - will be available for use

TRANSCRIPT

Page 1: Establishing the performance measurement baseline (v4)

Copyright 2011©, Niwot Ridge, L.L.C. All Rights Reserved

ESTABLISHING THE PERFORMANCE MEASUREMENT BASELINE (PMB)

AACE WORKSHOP DENVER, COLORADO APRIL 16TH, 2011

The Performance Measurement Baseline is a time–phased schedule of all the work to be performed, the budgeted cost for this work, and the organizational elements that produce the deliverables from this work.

1/34

Page 2: Establishing the performance measurement baseline (v4)

2/34

Page 3: Establishing the performance measurement baseline (v4)

3/34

Credible ! Capable of being credited or believed.

Page 4: Establishing the performance measurement baseline (v4)

Performance … Accomplishment of a given task measured against preset standards of accuracy, completeness, cost, and speed.

4/34

Page 5: Establishing the performance measurement baseline (v4)

Measurement … Values made meaningful by quantifying into specific units.

5/34

Page 6: Establishing the performance measurement baseline (v4)

6/34

Clearly defined starting point (point of departure) from where implementation begins, improvements judged, or comparison is made.

Page 7: Establishing the performance measurement baseline (v4)

Copyright Lewis & Fowler 2011 ©, All Rights Reserved

" Construct the Performance Measurement Baseline from the Work Breakdown Structure.

" Assign performance measures to Work Packages.

" Assign probabilistic measures of performance to the network of Work Packages.

" Use this information to make decisions.

Today We Will Learn The Steps Needed To …

7/34 1

Page 8: Establishing the performance measurement baseline (v4)

Copyright Lewis & Fowler 2011 ©, All Rights Reserved

The Overall Context Of Building The Performance Measurement Baseline has 4+1Major Activities.

8/34

Identify Needed Business

Capabilities

Establish a Performance Measurement

Baseline

Execute the Performance Measurement

Baseline

Capabilities Based Plan

Business Value Stream

Earned Value Performance

Technical Performance

Measures

Business Value Stream

Technical Requirements

Establish a Requirements

Baseline

Technical Performance

Measures

4

Page 9: Establishing the performance measurement baseline (v4)

Copyright Lewis & Fowler 2011 ©, All Rights Reserved

The Performance Measurement Baseline is really 3 baselines – Technical , Schedule, and Cost.

Cost Baseline

Schedule Baseline

Technical Baseline

Perform Functional

Analysis

Determine Scope and Approach

Develop Technical

Logic

Develop Technical Baseline

Develop WBS

Define Activities

Estimate Time

Durations

Sequence Activities

Finalize Schedule

Identify Apportioned Milestones

Determine Resource

Requirements

Prepare Cost

Estimate

Resource Load

Schedule

Finalize Apportioned Milestones

Determine Funding

Constraints

Approve PMB

9/34

Page 10: Establishing the performance measurement baseline (v4)

Copyright Lewis & Fowler 2011 ©, All Rights Reserved

The core elements of the Performance Measurement Baseline (PMB) …

… Are a collection of Work Packages, that define: ! The deliverables that fulfill the needed requirements

and project capabilities, ! The estimated duration and work effort for each Work

Package, ! The resources needed to produce these deliverables

within the needed time period, and ! Any dependencies – internal or external – needed to

start a Work Package.

10/34 6

Page 11: Establishing the performance measurement baseline (v4)

11/34

Let’s Build a BSL Level 4 Laboratory

Page 12: Establishing the performance measurement baseline (v4)

Deliverables Based Planning Handbook for A&D, Copyright © 2008, 2009, Lewis & Fowler

Decompose the Project Scope into a product based Work Breakdown Structure (WBS), then further into Work Packages describing the production of all deliverables traceable to the requirements

Decompose Scope into Work

Packages

Assign Responsibility to Work Packages (the groupings of deliverables) for the named owner accountable for the management of resource allocation and cost baseline and technical delivery

Assign Responsibility for Deliverables

Arrange the Work Packages in a well formed network with defined deliverables, milestones, internal and external dependencies, appropriate schedule and cost margin.

Arrange Work Packages in Logical Order

Develop a Time–Phased Budgeted Cost for Work Scheduled (BCWS) from labor and material costs in each Work Package and the Project as a whole. Assure proper resource allocations can be met and budget profiles match expectations of the project sponsor

Develop BCWS for Work

Packages

Assign object Measure of Performance (MOP) and Measures of Effectiveness (MOE) for each Work Package and summarize these for the Project as a whole

Assign WP Measures of Performance

Build a time–phased network of schedule activities describing the work to be performed, the budgeted cost for this work, the organizational elements that produce the deliverables, and the performance measures showing this work is proceeding according to plan.

Establish the Performance

Measurement Baseline A Baselined Schedule that Creates the Services or Products to Meet The Requirements

3.0

3.1

3.2

3.3

3.4

3.5

Establish a Performance Measurement Baseline (PMB) used to forecast Work Package and Project ongoing and completion cost and schedule metrics

Set Performance Measurement

Baseline

3.6

The information contained in this document is proprietary to Lewis & Fowler

7

Page 13: Establishing the performance measurement baseline (v4)

1 Decompose Scope Into

Work Packages

13/34

Page 14: Establishing the performance measurement baseline (v4)

Copyright Lewis & Fowler 2011 ©, All Rights Reserved

Capabilities, Requirements, WBS, and Work Packages are connected to define “Done.”

Business Capability Construct BSL Lvl-4

Bio Laboratory

1st Level BSL Lvl-4 design

basis

1st Level Bio product process

design basis

2nd Level Product storage

2nd Level Product Inventory

2nd Level Materials Handing

2nd Level Isolation processes

14/34 8

3.1

Dec

ompo

se S

cope

into

WPs

Page 15: Establishing the performance measurement baseline (v4)

Copyright Lewis & Fowler 2011 ©, All Rights Reserved

Connect the WBS to Work Packages (WP), then define the Tasks for the Deliverables to produce Value.

Business Need Build and Manage the

Bio Lab

1st Level BSL Level 4 Design

Basis

1st Level Bio product process

design basis

2nd Level Product Storage

2nd Level Product Inventory

2nd Level Materials Handing

2nd Level Isolation processes

Deliverables defined in WP

15/34

3.1

Dec

ompo

se S

cope

into

WPs

Page 16: Establishing the performance measurement baseline (v4)

2 Assign

Responsibilities

16/34

Page 17: Establishing the performance measurement baseline (v4)

Copyright Lewis & Fowler 2011 ©, All Rights Reserved

Assign accountability for each component of the Work Package.

#  Each Work Package has a single owner who is accountable for: ! Defining the deliverables ! Assigning resources ! Balancing the resource usage ! Defining the Earned Value measurement criteria !  Identifying any apportioned milestones ! Reporting physical percent complete

#  Name this person in the Work Package and the Master Schedule

17/34 23

3.2

Ass

ign

Resp

onsib

ilitie

s

Page 18: Establishing the performance measurement baseline (v4)

Copyright Lewis & Fowler 2011 ©, All Rights Reserved

Assign The Responsibilities And Make A Single Person Accountable

18/34

Page 19: Establishing the performance measurement baseline (v4)

3 Arrange

Work Packages

19/34

Page 20: Establishing the performance measurement baseline (v4)

“Arranging” the Work Packages Is An Iterative And Incremental Process

20/34

3.3

Arr

ange

WPs

with

Wor

k St

ream

s

Page 21: Establishing the performance measurement baseline (v4)

Copyright Lewis & Fowler 2011 ©, All Rights Reserved

Identify the Predecessors and Successors between Work Packages to sequence the work effort.

#  Give some thought about the sequence of the Work Packages, ! What deliverables come first? ! What deliverables come next?

#  The reason for this should be obvious. #  Use a Work Authorization (WA) processes to

keep the sequence of work intact.

21/34 24

3.3

Arr

ange

WPs

with

Wor

k St

ream

s

Page 22: Establishing the performance measurement baseline (v4)

Copyright Lewis & Fowler 2011 ©, All Rights Reserved

Start with a “notional” arrangement of the “Chunks” of work within a Workstream

# WPs should have No intermediate connections or outcomes.

7w

7w

5w

5w

1w 3w 3w

3w 2w

7w

5w

#  Long running WPs with negative or positive lags to maintain sequencing.

# Break the WP into separate deliverables and sequence Finish to Start.

22/34 27

3.3

Arr

ange

WPs

with

Wor

k St

ream

s

Page 23: Establishing the performance measurement baseline (v4)

4 Develop Budgets

For Work Packages

23/34

Page 24: Establishing the performance measurement baseline (v4)

Copyright Lewis & Fowler 2011 ©, All Rights Reserved

Develop a time–phased budget from the network of Work Packages based on resource loads

Duration of the Work Package

Bud

get

Duration of the Work Package

Bud

get

Duration of the Work Package

Bud

get

Duration of the Work Package B

udge

t

24/34 28

3.4

Dev

elop

Bud

get f

or th

e W

ork

Page 25: Establishing the performance measurement baseline (v4)

Copyright Lewis & Fowler 2011 ©, All Rights Reserved

Balance All The Work Packages Across The Project Before Setting The Baseline

25/34

25/34

Cost, Schedule, Technical Model†

WBS

Task 100

Task 101

Task 102

Task 103

Task 104

Task 105

Task 106

† This is a Key concept. This is the part of the process that integrates the cost and schedule risk impacts to provide the basis of a credible schedule.

Probability Density Function

"  Research the Project "  Find Analogies "  Ask Endless Questions "  Analyze the Results "  What can go wrong? "  How likely is it to go wrong? "  What is the cause? "  What is the consequence?

Monte Carlo Simulation Tool is Mandatory

1.0 .8 .6 .4 .2 0

Days, Facilities, Parts, People

Cumulative Distribution Function

Days, Facilities, Parts and People

3.4

Dev

elop

Bud

get f

or th

e W

ork

Page 26: Establishing the performance measurement baseline (v4)

5 Assign

Performance Measures

26/34

Page 27: Establishing the performance measurement baseline (v4)

Copyright Lewis & Fowler 2011 ©, All Rights Reserved

Identify objective measures of performance for each Work Package

#  Define the Planned Value (BCWS) for each Work Package completion or apportioned milestone within a Work Package.

#  Only Physical Percent Complete should be used to measure progress – no “opinions” of progress.

#  Answer the question, ! How are we going to recognize that progress is being

made? !  The passage of time and consumption of resources is NEVER

a measure of progress.

27/34 31

3.5

Ass

ign

Perf

orm

ance

Mea

sure

s

Page 28: Establishing the performance measurement baseline (v4)

Copyright Lewis & Fowler 2011 ©, All Rights Reserved

Assign BOE data for measuring performance of the Baseline before actually building the schedule

#  The contents of the Work Packages. #  The person accountable for the Work Package. #  The Earned Value method. #  The cross plan dependencies. #  Any value stream attributes.

28/34 32

3.5

Ass

ign

Perf

orm

ance

Mea

sure

s

Page 29: Establishing the performance measurement baseline (v4)

6 Set

Performance Baseline

29/34

Page 30: Establishing the performance measurement baseline (v4)

Copyright Lewis & Fowler 2011 ©, All Rights Reserved

Baseline the schedule to establish the planned budget spreads for each Work Package

#  Baselining the Performance Measurement Baseline (PMB) is the first step in successfully of Executing the project plan.

#  Without the baseline and the rigorous change control over the baseline, the needed credible performance predictions will be not possible.

30/34 32

3.6

Set P

erfo

rman

ce B

asel

ine

Page 31: Establishing the performance measurement baseline (v4)

Copyright Lewis & Fowler 2011 ©, All Rights Reserved

"  Lack  of  predic-ve  variance  analysis.  

" Un-mely  and  unrealis-c  Latest  Revised  Es-mates  (LRE).  

" Progress  not  monitored  in  a  regular  and  consistent  manner.  

"  Lack  of  ver-cal  and  horizontal  traceability  cost  and  schedule  data  for  correc-ve  ac-on.  

"  Lack  of  internal  surveillance  and  controls.  

" Managerial  ac-ons  not  demonstrated  using  Earned  Value.  

"  InaDen-on  to  budgetary  responsibili-es.  

" Work  authoriza-ons  that  are  not  always  followed  

"  Issues  with  Budget  and  data  reconcilia-on.  

"  Lack  of  an  integrated  management  system.  

" Baseline  fluctua-ons  and  frequent  replanning.  

" Current  period  and  retroac-ve  changes.  

"  Improper  use  of  management  reserve.  

"  EV  techniques  that  do  not  reflect  actual  performance.  

The image cannot be displayed. Your computer may not have enough memory to open the image, or the image may have been corrupted. Restart your computer, and then open the file again. If the red x still appears, you may have to delete the image and then insert it again.

Mary K. Evans Picture Library

3.6

Set P

erfo

rman

ce B

asel

ine

The Train Wrecks Starts When There is… 31/34

Page 32: Establishing the performance measurement baseline (v4)

32/34

Page 33: Establishing the performance measurement baseline (v4)

33/34

Page 34: Establishing the performance measurement baseline (v4)

34/34

Glen B. Alleman Niwot Ridge Consulting

4347 Pebble Beach Drive Niwot, Colorado 80503

303.241.9633 [email protected]

Performance-Based Project Management®

Integrated Master Plan Integrated Master Schedule

Earned Value Management Systems Risk Management

Proposal Support Services