ERJMO53-074/12 R1EO. No:
11/08/2013Rev. Date: Pag 2 of 19
ENGINEERING ORDER
FORM QA-073/96 TS-F R0
Date: 12/06/2012
EFFECTIVITY:
EMBRAER ERJ 190-100
EMBRAER ERJ 190-100
EMBRAER ERJ 190-100
EMBRAER ERJ 190-100
EMBRAER ERJ 190-100
EMBRAER ERJ 190-100
EMBRAER ERJ 190-100
EMBRAER ERJ 190-100
EMBRAER ERJ 190-100
EMBRAER ERJ 190-100
EMBRAER ERJ 190-100
EMBRAER ERJ 190-100
19000273
19000259
19000265
19000287
19000360
19000393
19000399
19000221
19000228
19000205
19000215
19000482
Several cases have been reported concerning of corrosion in the doubler assembler of the water
and waste box flange at Center Fuselage III.
For this reason, a modification of the water and waste box attachment at Center Fuselage III
(CF3) is needed, between frames 85 and 86, and frames 88 and 89.
This modification will protect the water and waste box against corrosion with this new
installation, avoiding water accumulation and premature corrosion as a consequence.
ENG. ASSESSMENT:
None.
None.
None.
None.
None.
None.
None.
None.
None.
None.
None.
None
AIRCRAFT MODEL /
COMPONENT
DESCRIPTION MSN FSN REMARKS
N984TA
N982TA
N983TA
N985TA
N986TA
N987TA
N988TA
N937TA
N938TA
N935TA
N936TA
N989TA
ERJMO53-074/12 R1EO. No:
11/08/2013Rev. Date: Pag 3 of 19
ENGINEERING ORDER
FORM QA-073/96 TS-F R0
Date: 12/06/2012
DISTRIBUTION LIST
(Planning will distribute all copies)
Technical Records
Stockroom
Reliability
Line Maintenance
Hangar Maintenance
Flight Operations
Quality Control
Quality Assurance
Technical Publicactions
Warranty
Other
..............
..............
..............
..............
..............
..............
..............
..............
..............
..............
..............
Comments:
PUBLICATIONS AFFECTED
Structural Repair Manual PART I
LABOR ESTIMATE:
DOCUMENT NUMBER DOCUMENT TYPE TITLE
SUPPORT DOCUMENTATION
SKILLS: CREW: MAN-HRS: ELAPSED:
06-41-00 & 06-49-00
20-00-00 & 20-13-21
38-11-03, 38-11-06, 38-32-13
38-32-17 & 38-32-18
50-32-04
51-21-02, 51-21-05 & 51-43-04
52-32-00
AMM
AMM
AMM
AMM
AMM
SRM
AMM
DIMENSIONS AND AREAS
STANDARD PRACTICES - AIRFRAME
WATER / WASTE
WATER / WASTE
CARGO AND ACCESSORY COMPARTMENTS
STANDARD PRACTICES AND STRUCTURES
DOORS
STRH
INS
2
1
20
1
10
0
TOTAL: 3 21
None
53-23-02
Chapter Publications
10
ERJMO53-074/12 R1EO. No:
11/08/2013Rev. Date: Pag 4 of 19
ENGINEERING ORDER
FORM QA-073/96 TS-F R0
Date: 12/06/2012
PARTS AND MATERIALS (Per Unit)
PART NUMBER DESCRIPTION QTY UNIT P.O./M.R. REMARKS
170-65911-601
PS870C-12
MEK
2007B002AM654SK
ECL-G-46/PC-233/TR109
MOD Kit
Polysulfide Sealant
Methyl Ethyl Ketone
Polysulfide Sealant
High solid polyure-
thane
1
1
1
1
1
EA
AR
EA
KIT
KIT
None
Or P/N NAFTOSEAL MC 780 C-12
Or Alternative
None
None
TOOLS
PART NUMBER DESCRIPTION QTY P.O. REMARKS
None None None
ENGINEERING ORDER E.O. No: ERJMO53-074/12 DATE: 11/08/2013 Rev. No: 1 PAGE: 5 of 19 SUBJECT: FUSELAGE - CENTER FUSELAGE III - CORROSION ON WATER AND WASTE BOX
FREQUENCY: N/A TAIL: STATION: DATE:
MECHANIC Q.C. INSTRUCTIONS
FORM QA-073/96-TS-F R0
XXX XXX ACCOMPLISHMENT INSTRUCTIONS
IMPORTANT: PLEASE READ THIS INFORMATION CAREFULLY BEFORE PROCEEDING WITH THE STEP-BY-STEP INSTRUCTIONS.
WARNING: MAKE SURE THAT YOU OBEY ALL THE WARNINGS AND ALL THE CAUTIONS
INCLUDED IN THE REFERENCED PROCEDURES.
XXX XXX A. GENERAL.
1. Make sure that the aircraft is electrically grounded (AMM PART II 24-40-02)
2. Make the aircraft safe for maintenance. Refer to AMM PART II 20-00-00
XXX XXX B. PROCEDURE.
XXX XXX 1. FUSELAGE - CENTER FUSELAGE III – CORROSION ON WA TER AND
WASTE BOX
XXX
a. Gain access to the waste service box by opening access doors 151AL and 152AR.
Refer to AMM MPP 06-41-00/101 - FUSELAGE ACCESS DOORS AND PANELS – COMPONENT LOCATION.
XXX b. Open the aft cargo door.
Refer to AMM SDS 52-32-00/1.
XXX
c. Gain access to the aft cargo compartment aft bulkhead and remove access panels 151BZ and 152BZ.
Refer to AMM TASK 50-32-04-000-801-A/400 - Aft Cargo-Compartment Aft Bulkhead - Removal and to AMM MPP 06-49-00/101 - CARGO-COMPARTMENT ACCESS DOORS AND PANELS - COMPONENT LOCATION.
XXX
d. Disconnect the rinse line from the waste and water box. Refer to the AMM TASK 38-32-17-000-801-A/400 - VWS Rinse Lines - Removal.
ENGINEERING ORDER E.O. No: ERJMO53-074/12 DATE: 11/08/2013 Rev. No: 1 PAGE: 6 of 19 SUBJECT: FUSELAGE - CENTER FUSELAGE III - CORROSION ON WATER AND WASTE BOX
FREQUENCY: N/A TAIL: STATION: DATE:
MECHANIC Q.C. INSTRUCTIONS
FORM QA-073/96-TS-F R0
XXX
e. Disconnect the electrical wires from the VWS service panel switch of the waste and water box. Refer to AMM TASK 38-32-18-000-801-A/400 - VWS Service Panel Switch - Removal.
XXX
f. Disconnect the vacuum-system tube from the drain cap of the waste box.
Refer to AMM TASK 38-32-13-000-801-A/400 - Vacuum Waste System Drain Lines - Removal.
XXX g. Disconnect the fill/drain nipple from the water box.
Refer to AMM TASK 38-11-06-000- 801-A/400 - Fill/Drain Nipple - Removal.
XXX h. Disconnect the water line from the water box.
Refer to AMM TASK 38-11-03-000-801- A/400 - Water Lines - Removal.
XXX XXX i. Modify the fixation of the water box PN 170-85093-403 in the CF3 , between
frames 85 and 86, as follows:
NOTE: If there are signs of corrosion, refer to the SRM to find the specific information applicable to your case. If the SRM does not contain the information related to your case or damage found out of the scope contact engineering.
XXX
1) Remove and discard doublers PN 170-86656-003 (01 position) and PN 170-86657-003 (01 position) by removing the existing fasteners (34 positions) from water box attached to the structure as indicated in Details B (Pre-mod) Figure 1, Sheet 1 of 7 and D (Pre-mod) Sheet 3 of 7, and Section B1-B1 (Pre-mod) Figure 1, Sheet 2 of 7. Refer to SRM PART II 51-43-04/1 - HI-LITE FASTENERS - FLUSH HEAD.
XXX
2) Remove and discard the existing fasteners (6 positions) from water box attached to the structure as indicated in Detail D (Pre-mod) Figure 1, Sheet 3 of 7. Refer to SRM PART II 51-43-04/1 - HI-LITE FASTENERS - FLUSH HEAD.
XXX 3) Clean the area with a clean cloth soaked with Methyl Ethyl Ketone (ASTM-D-740) MEK.
ENGINEERING ORDER E.O. No: ERJMO53-074/12 DATE: 11/08/2013 Rev. No: 1 PAGE: 7 of 19 SUBJECT: FUSELAGE - CENTER FUSELAGE III - CORROSION ON WATER AND WASTE BOX
FREQUENCY: N/A TAIL: STATION: DATE:
MECHANIC Q.C. INSTRUCTIONS
FORM QA-073/96-TS-F R0
4) Carry out the bonding procedure, method 3 as shown in Section B1-B1 (POSTMOD) Figure 1, Sheet 6 of 7. Refer to AMM TASK 20-13-21-910-801-A/200 - Types of Electrical Bonding and their Surface Preparation - Standard Procedures.
5) Install the water box attached to the structure using Polysulfide Interfaying Sealant Type IV Cl 12 (MIL-PRF-81733) NAFTOSEAL MC 780 C-12 for interface sealing, attaching pins PN HST11BJ-6- 6 (40 positions), washers PN NAS1149E0332P (40 positions) and collars PN HST79CK-6 (40 positions). Use Polysulfide Interfaying Sealant Type IV Cl 12 (MIL-PRF-81733) NAFTOSEAL MC 780 C-12 for wet installation of the pin. Refer to SRM PART II 51-21-05/1 - FASTENER SEALING, SRM PART II 51-43-04/1 - HI-LITE FASTENERS - FLUSH HEAD and Detail B (Post-mod) Figure 1, Sheet 5 of 7, Section B1-B1 (POST-MOD) Figure 1, Sheet 6 of 7, and Detail D (Post-mod) Figure 1, Sheet 7 of 7.
NOTE:
i. Refer to Figure 2, Sheet 1 of 1 for the holes and fasteners diameter dimension.
ii. Do not apply sealant on electrical bonding area. Refer to
Section B1-B1 (POST-MOD), Figure 1, Sheet 6 of 7.
iii. Apply a fillet of Polysulfide Interfaying Sealant Type IV Cl 12 (MIL-PRF- 81733) NAFTOSEAL MC 780 C-12 or similar as indicated in Section B1-B1 (POST-MOD), Sheet 6 of 7. Refer to SRM PART II 51-21-02/1 - FILLET SEALING.
iv. Apply Polysulfide Sealant (AMS3281) 2007B002AM654SK
to the fastener head. Refer to Section B1-B1 (POST-MOD), figure 1, Sheet 6 of 7 and to SRM PART II 51-21-05/1 - FASTENER SEALING.
6) Apply High Solids Polyurethane White Paint (MEP 10-069) ECL-G-
46/PC- 233/TR109 to paint the fasteners head. Refer to Section B1-B1 (POST-MOD), Figure 1, Sheet 6 of 7.
7) Carry out the bonding test. Refer to AMM TASK 20-13-21-720-801-
A/200 - Electrical Bonding Test - Standard Procedures.
ENGINEERING ORDER E.O. No: ERJMO53-074/12 DATE: 11/08/2013 Rev. No: 1 PAGE: 8 of 19 SUBJECT: FUSELAGE - CENTER FUSELAGE III - CORROSION ON WATER AND WASTE BOX
FREQUENCY: N/A TAIL: STATION: DATE:
MECHANIC Q.C. INSTRUCTIONS
FORM QA-073/96-TS-F R0
8) Carry out the bonding protection. Refer to AMM TASK 20-13-21-
910-802-A/200 - Electrical Bonding Protection – Standard Procedures.
XXX XXX j. Modify the fixation of the water box PN 170-85084-405 in the CF3, between
frames 88 and 89, as follows:
NOTE: If there are signs of corrosion, refer to the SRM to find the specific information applicable to your case. If the SRM does not contain the information related to your case or damage found out of the scope contact engineering.
XXX
1) Remove and discard doublers PN 170-86654-003 (01 position) and PN 170-86655- 003 (01 position) by removing the existing fasteners (40 positions) from water box attached to the structure as indicated in Details C (Pre-mod), Figure 1, Sheet 1 of 7 and E (Pre-mod) ,Figure 1, Sheet 4 of 7, and Section C1-C1 (Pre-mod), Sheet 2 of 7. Refer to SRM PART II 51-43-04/1 - HI-LITE FASTENERS - FLUSH HEAD.
XXX
2) Remove and discard the existing fasteners (10 positions) from water box attached to the structure as indicated in Detail E (Pre-mod), Figure 1, Sheet 4 of 7. Refer to SRM PART II 51-43-04/1 - HI-LITE FASTENERS - FLUSH HEAD.
XXX 3) Clean the area with a clean cloth soaked with Methyl Ethyl Ketone
(ASTM-D-740) MEK
4) Carry out the bonding procedure, method 3, as shown in Section C1-C1 (POST-MOD), Figure 1, Sheet 6 of 7. Refer to AMM TASK 20-13-21-910-801-A/200 - Types of Electrical Bonding and their Surface Preparation - Standard Procedures.
ENGINEERING ORDER E.O. No: ERJMO53-074/12 DATE: 11/08/2013 Rev. No: 1 PAGE: 9 of 19 SUBJECT: FUSELAGE - CENTER FUSELAGE III - CORROSION ON WATER AND WASTE BOX
FREQUENCY: N/A TAIL: STATION: DATE:
MECHANIC Q.C. INSTRUCTIONS
FORM QA-073/96-TS-F R0
5) Install the water box attached to the structure, using Polysulfide Interfaying Sealant Type IV Cl 12 (MIL-PRF-81733) NAFTOSEAL MC 780 C-12 for interface sealing, attaching pins PN HST11BJ-6- 6 (50 positions), washers PN NAS1149E0332P (50 positions) and collars PN HST79CK-6 (50 positions). Use Polysulfide Interfaying Sealant Type IV Cl 12 (MIL-PRF-81733) NAFTOSEAL MC 780 C-12 for wet installation of the pin. Refer to SRM PART II 51-21-05/1 - FASTENER SEALING, SRM PART II 51-43-04/1 - HI-LITE FASTENERS - FLUSH HEAD and Detail C (Post-mod), Figure 1 Sheet 5 of 7, Section C1-C1 (POST-MOD), Figure 1 Sheet 6 of 7 and Detail E (Post-mod), Figure 1, Sheet 7 of 7.
NOTE:
i. Refer to Figure 2, Sheet 1 of 1, for the holes and fasteners diameter dimension.
ii. Do not apply sealant on electrical bonding area. Refer to
Section C1-C1 (POST-MOD), Figure 1, Sheet 6 of 7.
iii. Apply a fillet of Polysulfide Interfaying Sealant Type IV Cl 12 (MIL-PRF- 81733) NAFTOSEAL MC 780 C-12 or similar as indicated in Section C1-C1 (POST-MOD), Figure 1, Sheet 6 of 7 Refer to SRM PART II 51-21-02/1 - FILLET SEALING
iv. Apply Polysulfide Sealant (AMS3281) 2007B002AM654SK
to the fastener head. Refer to Section C1-C1 (POST-MOD), Figure 1, Sheet 6 of 7 and to SRM PART II 51-21-05/1 - FASTENER SEALING.
6) Apply High Solids Polyurethane White Paint (MEP 10-069) ECL-G-
46/PC- 233/TR109 to paint the fasteners head. Refer to C1-C1 (POST-MOD), Figure 1, Sheet 6 of 7.
7) Carry out the bonding test. Refer to AMM TASK 20-13-21-720-801-A/200 - Electrical Bonding Test - Standard Procedures.
8) Carry out the bonding protection. Refer to AMM TASK 20-13-21-
910-802-A/200 - Electrical Bonding Protection - Standard Procedures.
ENGINEERING ORDER E.O. No: ERJMO53-074/12 DATE: 11/08/2013 Rev. No: 1 PAGE: 10 of 19 SUBJECT: FUSELAGE - CENTER FUSELAGE III - CORROSION ON WATER AND WASTE BOX
FREQUENCY: N/A TAIL: STATION: DATE:
MECHANIC Q.C. INSTRUCTIONS
FORM QA-073/96-TS-F R0
k. Reconnect the electrical wires from the VWS service panel switch of the waste and water box. Refer to AMM TASK 38-32-18-400-801-A/400 - VWS Service Panel Switch - Installation.
l. Reconnect the vacuum-system tube from the drain cap of the waste box. Refer to AMM TASK 38-32-13-400-801-A/400 - Vacuum Waste System Drain Lines - Installation.
m. Reconnect the fill/drain nipple from the water box. Refer to AMM TASK 38-11-06-400- 801-A/400 - Fill/Drain Nipple – Installation.
n. Reconnect the water line from the water box.
Refer to AMM TASK 38-11-03-400-801- A/400 - Water Lines - Installation.
o. Install the partition panels 151BZ and 152BZ. Refer to AMM TASK 50-32-04-400-801- A/400 - Aft Cargo-Compartment Aft Bulkhead - Installation.
p. Close the aft cargo door.
Refer to AMM SDS 52-32-00/1.
q. Close the access doors 151AL and 152AR. Refer to AMM MPP 06-41-00/101 - FUSELAGE ACCESS DOORS AND PANELS - COMPONENT LOCATION.
XXX XXX C. CLOSE UP.
1. Make sure the work area is clean and clear of tool and other items.
2. Return the aircraft to serviceable conditions.
XXX XXX End of this E.O.
XXX XXX The following step is for documentation purposes only and is not related to the actual tasks performed on the subject aircraft.
ENGINEERING ORDER E.O. No: ERJMO53-074/12 DATE: 11/08/2013 Rev. No: 1 PAGE: 11 of 19 SUBJECT: FUSELAGE - CENTER FUSELAGE III - CORROSION ON WATER AND WASTE BOX
FREQUENCY: N/A TAIL: STATION: DATE:
MECHANIC Q.C. INSTRUCTIONS
FORM QA-073/96-TS-F R0
XXX XXX
TECHNICAL RECORDS : Insert a copy of this Engineering Order in the records of the subject A/C.
Name: …………………………………………………… Title: …………………………………………………… Date: ……………………………………………………
Signature: ……………………………………………………
XXX XXX
TECHNICAL PUBLICATIONS : Notify the manufacturer that SB 190-53-0056 Rev. 0 has been embodied on the aircraft by sending confirmation to the e-mail:
Name: …………………………………………………… Title: …………………………………………………… Date: ……………………………………………………
Signature: ……………………………………………………
XXX XXX
MAINTENANCE PROGRAM ENGINEERING: Record that EMB SB 190-53-0056 Rev. 0 has been embodied on subject A/C.
Name: …………………………………………………… Title: …………………………………………………… Date: ……………………………………………………
Signature: ……………………………………………………
E.O. N°: ERJMO53-074/12 REV. N°: 01 DATE : NOV/ 08/2013 FIGURE: 1 SHEET : 1 OF 7 PAGE : 12 OF 19
FREQUENCY : N/A SUBJECT : FUSELAGE - CENTER FUSELAGE III – CORROSION ON WATER AND WASTE BOX.
FIGURE 1 – MODIFICATION OF THE WATER AND WASTE BOX FIXATION
(SHEET 01 OF 07)
E.O. N°: ERJMO53-074/12 REV. N°: 01 DATE : NOV/ 08/2013 FIGURE: 1 SHEET : 2 OF 7 PAGE : 13 OF 19
FREQUENCY : N/A SUBJECT : FUSELAGE - CENTER FUSELAGE III – CORROSION ON WATER AND WASTE BOX.
FIGURE 1 – MODIFICATION OF THE WATER AND WASTE BOX FIXATION
(SHEET 02 OF 07)
E.O. N°: ERJMO53-074/12 REV. N°: 01 DATE : NOV/ 08/2013 FIGURE: 1 SHEET : 3 OF 7 PAGE : 14 OF 19
FREQUENCY : N/A SUBJECT : FUSELAGE - CENTER FUSELAGE III – CORROSION ON WATER AND WASTE BOX.
FIGURE 1 – MODIFICATION OF THE WATER AND WASTE BOX FIXATION
(SHEET 03 OF 07)
E.O. N°: ERJMO53-074/12 REV. N°: 01 DATE : NOV/ 08/2013 FIGURE: 1 SHEET : 4 OF 7 PAGE : 15 OF 19
FREQUENCY : N/A SUBJECT : FUSELAGE - CENTER FUSELAGE III – CORROSION ON WATER AND WASTE BOX.
FIGURE 1 – MODIFICATION OF THE WATER AND WASTE BOX FIXATION (SHEET 04 OF 07)
E.O. N°: ERJMO53-074/12 REV. N°: 01 DATE : NOV/ 08/2013 FIGURE: 1 SHEET : 5 OF 7 PAGE : 16 OF 19
FREQUENCY : N/A SUBJECT : FUSELAGE - CENTER FUSELAGE III – CORROSION ON WATER AND WASTE BOX.
FIGURE 1 – MODIFICATION OF THE WATER AND WASTE BOX FIXATION (SHEET 05 OF 07)
E.O. N°: ERJMO53-074/12 REV. N°: 01 DATE : NOV/ 08/2013 FIGURE: 1 SHEET : 6 OF 7 PAGE : 17 OF 19
FREQUENCY : N/A SUBJECT : FUSELAGE - CENTER FUSELAGE III – CORROSION ON WATER AND WASTE BOX.
FIGURE 1 – MODIFICATION OF THE WATER AND WASTE BOX FIXATION
(SHEET 06 OF 07)
E.O. N°: ERJMO53-074/12 REV. N°: 01 DATE : NOV/ 08/2013 FIGURE: 1 SHEET : 7 OF 7 PAGE : 18 OF 19
FREQUENCY : N/A SUBJECT : FUSELAGE - CENTER FUSELAGE III – CORROSION ON WATER AND WASTE BOX.
FIGURE 1 – MODIFICATION OF THE WATER AND WASTE BOX FIXATION (SHEET 07 OF 07)
E.O. N°: ERJMO53-074/12 REV. N°: 01 DATE : NOV/ 08/2013 FIGURE: 2 SHEET : 1 OF 1 PAGE : 19 OF 19
FREQUENCY : N/A SUBJECT : FUSELAGE - CENTER FUSELAGE III – CORROSION ON WATER AND WASTE BOX.
FIGURE 2 - DRILLING FIT CLASSES
(SHEET 01 OF 01)