ercot it update ken shoquist vp, cio information technology board meeting august 2003
TRANSCRIPT
ERCOT IT Update
Ken ShoquistVP, CIO Information Technology
Board Meeting
August 2003
July 2003
page 2AgendaAgenda
Metrics Project Updates Security Texas Electric Market (TEM) Forum Update
July 2003
page 3IT HighlightsIT Highlights
Production – 27 missed intervals in EMMS environment (approx 1%) due to flawed code and internal processes. Vendors working code issues. ERCOT and Vendors working process issues.
Development – Continue to analyze architecture evolution. Issues of data access and quality, performance, and vendor support continue to remain as high priority. Architecture evolution will need to strike appropriate balance between focus on Market Redesign and IT Operations.
Security - Role of ERCOT Security continues to evolve in supporting Market.
Texas Electric Market IT Forum – Superior speakers and content; 118 Market Participants registered.
July 2003
page 4
21
2
11
6
2
27
050
100150200250300350400450500550600650700750
0
5
10
15
20
25
30
EMS (Frequency Control) 8 4 - 10 57 152 2
Market User Interface - - - - - 60 746
RTB Intervals Missed 2 1 2 11 6 2 27
Jan Feb Mar Apr May Jun Jul
2003 Mission Critical Unplanned EMMSEMMS Outages
Ceiling TargetEMS and MUI
45 minutes (99.9%)
OutageMinutes
IntervalsMissed
Ceiling Target3 RTB Intervals
System ReliabilitySystem Reliability
4 distinct software issues caused 27 intervals to be missed in July: 2 resolved by Alstom (EMMS vendor) 1 resolved by HP 1 issue remains under investigation
July 2003
page 5Transaction ProcessingTransaction Processing Infrastructure changes for performance continue with good results. Next major step will be
investment in support of Data Warehouse effort scheduled for end of year. Lack of high availability continues to be a challenge. This will need to take a higher priority in
project list. All major Commercial System Components are either on outdated application releases and/or are
operating on unsupported versions of the Oracle Database. The operational impact with respect to data quality, performance, reliability, and support cost will continue an issue until resolution. Business and IT have joint plan in place for driving resolution.
38.8
3435.134.632.131.5 30.5
0
5
10
15
20
25
30
35
40
45
Jan Feb Mar Apr May June July
Includes all 32 transaction types
Retail Transaction Volumes (In Millions)
January - July 2003
July 2003
page 6Reporting PerformanceReporting Performance
0
2000
4000
6000
0%
20%
40%
60%
80%
100%
Total Settlements 2,015 1,931 2,668 2,655 3,251 5,564 6,193
Missed Settlements 707 358 248 - 801 349 2,109
Settlement PCT 65% 81% 91% 100% 75% 94% 66%
Jan Feb Mar Apr May Jun Jul
2003 Report PostingSettlements
Volume increase represents BOD mandated resettlements of 2002 that began in mid-May and will continue through year-end.
Settlements success rate has decreased June to July due to increased volume issues, batch timing, and hardware and software implementations.
Performance improvements made in August are expected to reduce resource contention and batch processing time. Next level of tuning due by end of Q3.
July 2003
page 7
Change Request by AreaJanuary – July 2003
Change Requests by AreaChange Requests by Area
Package 1Package 2Package 3
Corporate Apps.Web Portal
TOTAL# CR - Total 121 91 103 116 110 128 86 755
121
91
103
116110
128
86
0
20
40
60
80
100
120
140
Jan Feb Mar Apr May June July
Total Monthly Change RequestsJanuary – July 2003
EMMS36%
Commercial34%
Data Warehouse8%
Corporate Apps.19%
Web Portal3%
Commercial Paperfree server upgrade SeeBeyond outage
EMMS SPD Code Errors Alstom user interface code error Hardware upgrade Real-time balancing error Digital certificate renewal
July Outage SummaryEMMS & Commercial Apps System Uptime
84%
86%88%
90%92%
94%
96%98%
100%
Jan Feb Mar Apr May June July
EMMS Commercial Apps
July 2003
page 8IT Project PerformanceIT Project Performance
IT Project Updates
Projects Deployed in July 2003 Year-to-date Priority 1 and 2 Projects: 32 complete, 17 in progress, and 19 in planning
Combined Cycle Settlements – PRR 369 for settling combined cycle plants
Outage Scheduler Phase 2 – Enhancement to Outage scheduler for operations
Internal Map Testing – EDI map testing and verification automation
SCADA Transmission Alarms – Enhance alarms for operations.
Monthly Activity Project Performance
0
5
10
15
20
25
30
April May June July
Completed In Planning In Progress
0%
20%
40%
60%
80%
100%
1st Qtr 2nd Qtr 3rd Qtr
On Time On Budget
July 2003
page 9Upcoming DeploymentsUpcoming Deployments
PUCT Market Monitoring Plan (Aug 2003)
QSE Market Testing (TBD) Increase availability Increase functionality
Portal Replacement (Oct 2003) Portfolio Mgmt Software (Nov 2003) Document Management (TBD) Lawson G/L Upgrade (Dec 2003) Enterprise Data Warehouse (TBD)
BUL / LAAR (Sept 2003) Load Research Sampling (TBD) Mismatched QSE Schedules (Aug 2003)
Commercial Dev/Test Systems (Nov 2003)
MIMO Long Term Market (Aug 2004) Market Coordination Team formed Requirements being finalized
Texas Set 1.6 (Dec 2003)
Energy Management Systems
Enterprise Operations
Settlement & Billing
Transaction Processing
July 2003
page 10
Project Objective: Support the PUCT requirements to effectively monitor the ERCOT market Joint effort between PUCT, ERCOT, Alstom and Potomac Economics
Business: Planning phase completed. Detailed work plan defined. High-level
architecture has been defined. General project requirements have been collected. Initial data requirements have been compiled. First draft on design documents completed (per schedule).
Technical: ERCOT Infrastructure, Network and Security teams preparing for
project implementation. ERCOT to host systems and provide data. Alstom and Potomac Economics locations will be linked by a secure
direct connection to ERCOT’s site.
7/1/03 8/1/03 9/1/03 10/1/03 11/1/03 12/1/03
Planning4 weeks
Design6 weeks
Build6 weeks
Int &Test4 weeks
Install & test4 weeks
Today Ship
PUCT Market Monitoring PUCT Market Monitoring SystemSystem
July 2003
page 11ERCOT’s Security TeamERCOT’s Security Team
Manager, Physical Security
(Former FBI Agent)
Manager, Cyber Security
(Former State of Georgia CISO)
Director, Corporate Security
(Former Naval Cryptologist)
July 2003
page 12
Department of Energy NERC/
CIPAG
ISO CIO Security Committee
ERCOTERCOT
Members
State Agency
Educate on Best Practices / Standards Provide Forum for Information Sharing Coordinate Security Incidents Distributing Information from Federal and State Agencies Solicit Federal and State Funding Where Appropriate Represent ERCOT Market’s Interest to Federal and State Agencies
Growing Interest in ERCOT Security Role in Texas MarketGrowing Interest in ERCOT Security Role in Texas Market
Department of Homeland Security
Federal Bureau of
Investigation
U.S. Secret Service
July 2003
page 13
118 participants registered 43 unique companies 79% ESIIDs represented 83% of load
Dynamic Guest Speakers Security Focused
Dept of Homeland SecurityFBISecret Service California ISONew England ISOPublic Utility Commission of Texas
IT TEM ForumIT TEM Forum
July 2003
page 14
Austin Energy Brazos Electric Bryan Texas Utilities CenterPoint Energy Cirro Energy City of Bastrop City of Georgetown Coral Power El Paso Electric Energy America Entergy Solutions Ltd Fire Fly Electricity FPL Gexa Energy Green Mountain Energy Company HILCO Electric cooperative Inc. LCRA New Mexico Natural Gas LP d/b/a
StarLight Electric
Occidental Petroleum Oncor Pedernales Electric Cooperative Public Utility Commission of Texas Reliant Resources Inc. Republic Power Sempra Shell Trading G&P North America South Texas Electric Coop Strategic Energy Taylor Electric Cooperative Tenaska Inc. TESI Texas Commercial Energy TNMP TNP Enterprises Tractebel North America Inc. TXU Energy Utility Choice Electric
TEM Forum Market ParticipantsTEM Forum Market Participants
July 2003
page 15SummarySummary
Production Management:
Resettlements will continue to focus development on tuning and capacity planning.
EMMS Stability remains high priority for improvement.
Commercial Systems Architecture:
Working with business to define requirements and select evolution path.
Data Warehouse will complete first phase late ’03.
TEM Forum:
Shaping into significant information sharing event.
118 Market Participants registered.