ercot it update ken shoquist vp, cio information technology board meeting april 2004
TRANSCRIPT
ERCOT IT Update
Ken ShoquistVP, CIO Information Technology
Board Meeting
April 2004
Page 2
April 2004
Market Oversight and Monitoring System - Shoquist
Projects Update - Connell
CASUP Update - Galvin, Gruber, Judice,
AgendaAgenda
Market Oversight and Monitoring System
Project Update
Ken Shoquist
Page 4
April 2004Market Oversight and Monitoring SystemMarket Oversight and Monitoring System
Project began in mid-2003 to provide the PUCT with enhanced market monitoring capabilities. System went live in mid-February 2004.
Joint effort between multiple industry partners — PUCT, ERCOT, AREVA and Potomac Economics
Two Main Applications:
1. StudyMarket Application
Ability to simulate and analyze historical market clearing conditions in a standalone environment. Market information available to PUCT in near real-time after each interval.
2. Indices, Screens and Report (ISR) Application
Near real-time monitoring of market activity and behavior. Ability to generate reports on market indices and review of participant conduct.
Page 5
April 2004Market Oversight & Monitoring SystemMarket Oversight & Monitoring System
2. Indices, Screens and Report (ISR) Application (cont.)
Automated reports will detect bidding conduct or other events that warrant further investigation by MOD.
Screens and indices are designed to:
Identify generating units that have local market power.
Detect flaws in market rules or procedures that interfere with the efficient operation of the market or create gaming opportunities.
Detect bidding strategies or other conduct that may constitute economic or physical withholding.
Identify potential manipulation of transmission constraints.
Example Index: Residual Supply Index
Identifies when a supplier faces limited competition because its resources are needed (at any price).
Projects Update
Rob Connell – Director, Project Management
Page 7
April 2004Projects Completed First QuarterProjects Completed First Quarter
Projects Completed in January
Texas Set 1.6
Commercial Applications Development System (P-Test Prime)
Congestion Management Zones
Lawson Procurement System
Projects Completed in February
PUCT Market Monitoring System
Transmission Congestion Rights – Phase 1
Payment for Minimum Energy when OOMC Issued
SeeBeyond and PaperFree Upgrades
Projects Completed in March MS Project Server – Phase 1
Market Operations QSE Test Environment
Commercial Applications System Upgrade (CASUP) Project
Direct Load Control
Computer Room HVAC and PDU Upgrades
Facilities Expansion Construction at Taylor locations
Page 8
April 2004IT Project PerformanceIT Project Performance Project Process Improvements In 2004
6 completed 36 in progress 21 in planning Release 3 moved 11 projects to
in progress
Program Area Teams Launched CART (Continuous Analysis & Requirements
Teams) being implemented to plan releases and provide impact analysis
Project Activity Project Performance
0
5
10
15
20
25
30
35
40
4th Qtr Jan Feb Mar
Completed In Planning In Progress
0%
20%
40%
60%
80%
100%
4th Qtr Jan Feb Mar
On Time On Budget Deliverables
March 2004 Projects
Page 9
April 2004
Scope Provide a standalone, functional market operations test environment dedicated to
wholesale market participant testing that enables XML interface and business testing for qualified scheduling entity (QSE) market participants.
Budget = $735K. Actual Committed to Date = $494K Negotiations with EMP vendor saved ~$200K for separate license purchase.
5/19/03 10/21/03 2/16/04Today
Init/ Planning12 weeks
Design8 weeks
Build12 weeks
Prove-in4 wks
8/10/03
3/9/04 NGP 2
ERMSPDA 10.7.2.98
ITW2KT41 10.0.126.61
ERTWEBD 10.20.1.106
Market Operations Test Environment HW & SW
W2KPortal
(2 CPU) Jrun, Yahoo / Tibco, Server
Cert.
SoftwareLicenses
Policy / LDAP(1 CPU)
Metaframe, Server Cert. Netegrity
Siteminder, iPlanetLDAP
Solaris
Tru64
DMZ Firewall
MOS Web XML / API
(1 CPU) Apache Stronghold, Jrun,
Coldfusion, Server Cert.
MOS & EMS(4 CPU)
Habitat, EMP, Oracle
Active Directory(1 CPU)
Portal DB(2 CPU)
SQL Server
SPD(1 CPU)AIMMS
Database
Veritas & Measure Ware on All
ITSOLT01 10.0.126.106
ITW2KT40 10.20.2.42
ITW2KT39 10.0.126.60
ERMEMSA 10.7.2.100ERMMKTA 10.7.2.1013/9/04 NGP 2
ERMSPDA 10.7.2.98
ITW2KT41 10.0.126.61
ERTWEBD 10.20.1.106
Market Operations Test Environment HW & SW
W2KPortal
(2 CPU) Jrun, Yahoo / Tibco, Server
Cert.
SoftwareLicenses
Policy / LDAP(1 CPU)
Metaframe, Server Cert. Netegrity
Siteminder, iPlanetLDAP
Solaris
Tru64
DMZ Firewall
MOS Web XML / API
(1 CPU) Apache Stronghold, Jrun,
Coldfusion, Server Cert.
MOS & EMS(4 CPU)
Habitat, EMP, Oracle
Active Directory(1 CPU)
Portal DB(2 CPU)
SQL Server
SPD(1 CPU)AIMMS
Database
Veritas & Measure Ware on All
ITSOLT01 10.0.126.106
ITW2KT40 10.20.2.42
ITW2KT39 10.0.126.60
ERMEMSA 10.7.2.100ERMMKTA 10.7.2.101
Test4 weeks
1/15/04
Market Operation Test EnvironmentMarket Operation Test Environment
MOTE released on time using top tier portal! All 12 deliverables met. Major Deliverables:
Production-like HW (three platforms) Fully licensed environment
Ready for TML prerelease to QSE’s scheduled by Client Relations.
ERCOT is the ONLY ISO to provide such an environment!
Commercial Applications Systems Upgrade Project -
Project Update
Jim Galvin – Director, Market Operations
Richard Gruber – Director, Market Services
Kevin Judice – Director, IT Development
Page 11
April 2004CASUP Project
The CASUP project began in October 2003 to:
Evaluate the core systems that comprise the commercial systems platform –
Lodestar, PaperFree, SeeBeyond (TCH) and Siebel
Evaluate existing commercial software applications and other options that may
better meet ERCOT’s functional and cost-of-ownership requirements
Develop a set of business and technical requirements using a process that
includes representatives from both business and IT
Page 12
April 2004
Business Requirements for Commercial Systems
Used an agile approach, including the Rational Unified Process (RUP) and Joint
Requirements Planning (JRP) sessions, to capture and articulate requirements
Completed Enterprise Business Model (EBM)
Completed Business Use Cases
Requirements Gathering
Technical Specifications for Commercial Systems
Completed Supplementary Specification
Completed Technical Architecture Design
Page 13
April 2004Product Evaluation
Commercial Systems Software Product Evaluation
Request for Qualification (RFQ) process completed:
• 19 responses received • Responses evaluated by Project Leadership Team and rated using weighted scoring• List categorized and shortened to:
Full Solution: Excelergy, Lodestar, SAP Aggregation & Settlements: Alstom/AREVA(Eterra), ICF, OM Retail: Siebel
Product demonstration process completed:
• Demos focused on functional, technical and rough cost criteria• Products evaluated by ERCOT managers and SMEs - rated using weighted scoring• Solution Option alternatives developed by CASUP Team
Enterprise Application Integration (EAI) product evaluation process constructed
Page 14
April 2004Solution
Mid-term actions to improve vendor support level
Upgrade Lodestar wholesale to v3.7 to get current with vendor and gain advertised performance improvements
Upgrade Siebel to v7.0 and evaluate work flow capabilities
Develop enterprise-wide application integration strategy (EAI)
Long-term to improve reliability, scalability, and extensibility
Implement EAI application and architecture plan
Conduct a Proof-of-Concept (POC) to investigate using Lodestar to support retail business functions
Conduct a POC in support of future TNT initiatives, evaluate billing and settlements capability of AREVA’s Eterra and Lodestar’s 4.x products
Page 15
April 2004
AttachmentsAttachments
Page 16
April 2004Production MetricsProduction Metrics
Released six projects and 90 SIRs into production SIR procedure being updated and improved Currently in testing for TML portal launch three SAS 70 audit preparation and documentation continues for
May 1 start
EMMS Four intervals missed Focused on Release 3
Transaction Processing Vendor patch installed to correct
post update problems Processing times continue to
improve
Settlements 5,638 in Mar 99% on-time settlement posting
Project Management 6 completed 36 in process 21 in planning
Summary for MarchSummary for March
Page 17
April 2004
2 1 2
11
6
2
27
0
6
12
13
0
43
020406080
100120140160180200
0
5
10
15
20
25
30
EMS (Frequency Control) 8 4 - 10 57 152 2 26 - 43 - - - - -
Market User Interface - - - - - 60 746 - - - - - 2 2
RTB Intervals Missed 2 1 2 11 6 2 27 0 3 6 12 1 3 0 4
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
2003 Mission Critical Unplanned EMMSEMMS Outages
Ceiling TargetEMS and MUI
45 minutes (99.9%)
OutageMinutes
IntervalsMissed
Ceiling Target3 RTB Intervals
System ReliabilitySystem Reliability
Results and Challenges Action Items
746
Currently preparing for Release 3Opportunities for improved monitoring of hardware and network
Page 18
April 2004Transaction ProcessingTransaction Processing
ProcessingTime (hrs)
TransactionVolume (MM) 2003 Retail Transaction Processing
10.9
8.9
3.7 3.42.2
4.8
3.34.5
3.4 3.24.2
1.8 1.4 1.7 2.31.2
2.0 1.91.0
1.42.0
1.4 2.0 1.6 1.0 0.91.6 1.2 0.8 1.0 1.2 1.1 0.7 0.6 0.6 0.50.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
40.0
45.0
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
Total Txn (m illions) 31.7 37.3 29.5 28.8 31.5 30.5 32.1 34.6 35.1 34.0 38.8 35.9 33.4 28.4 31.6 37.1 33.1 29.7 34.4
Avg process ing tim e 814 10.9 8.9 3.7 3.4 2.2 4.8 3.3 4.5 3.4 3.2 4.2 1.8 1.4 1.7 2.3 1.2 2.0 1.9 1.0
Avg process ing tim e 867 1.4 2.0 1.4 2.0 1.6 1.0 0.9 1.6 1.2 0.8 1.0 1.2 1.1 0.7 0.6 0.6 0.5
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Average 814 transaction processing times exclude maintenance (type 20).
Results and Challenges Action Items Major vendor release end of Feb with post migration
issues that impeded transaction throughput in the first week of March
Vendor patch applied to address transaction issues
Page 19
April 2004Reporting PerformanceReporting Performance
Action Items
0
1000
2000
3000
4000
5000
6000
7000
8000
0%
20%
40%
60%
80%
100%
Total Settlements 2,015 1,931 2,668 2,655 3,251 5,564 6,193 6,434 7,351 7,093 5,289 7,009 5,584 4,767 5,638
Missed Settlements 707 358 248 - 801 349 2,109 1,006 1,122 1,456 41 840 371 - 59
Settlement PCT 65% 81% 91% 100% 75% 94% 66% 84% 85% 79% 99% 88% 93% 100% 99%
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
2003 Report Posting Settlements# Settlements Settlement %
Continuous system improvements in processing
Strengthening staff to improve production support