environmental monitoring report - asian development bank · evn genco 3 thermal power projects...

69
Environmental Monitoring Report __________________________________________ Semestral Report January-June 2013 VIE: Mong Duong 1 Thermal Power Plant Prepared by Electricity of Vietnam and Thermal Power Projects Management Unit 1 for the Government of Viet Nam and the Asian Development Bank.

Upload: others

Post on 31-Aug-2019

1 views

Category:

Documents


0 download

TRANSCRIPT

Environmental Monitoring Report __________________________________________ Semestral Report January-June 2013

VIE: Mong Duong 1 Thermal Power Plant Prepared by Electricity of Vietnam and Thermal Power Projects Management Unit 1 for the Government of Viet Nam and the Asian Development Bank.

EVN GENCO 3

Thermal Power Projects Management Board 1 (TPMB1)

MONG DUONG (2 x 500MW) THERMAL POWER PLANT PROJECT

1st SEMI-ANNUAL

ENVIRONMENTAL MONITORING REPORT 2013

Period 01st January – 30

th June 2013

Contract No: TPMB1-EVN/ADB-2610L2MFF-Consulting-002

Page 2 of 68

CONTENTS

EXECUTIVE SUMMARY ................................................................................................... 5

1. INTRODUCTION...................................................................................................... 10

1.1 The project ............................................................................................................................... 10

1.2 Incorporation of Environmental Requirements into Project Contractual Arrangements ......... 10

1.3 Project Implementation Progress ............................................................................................. 11

1.4 Report Purpose ......................................................................................................................... 13

2. ENVIRONMENT COMPLIANCE INSPECTIONS .............................................. 13

2.1 Environment Compliance Inspections at the Construction Site ............................................... 13

2.2 Health, Safety & Environment (HES) Aspects ........................................................................ 14 2.2.1 Health, Safety & Environmental Management Plan (EMP) ............................................. 14 2.2.2 HSE Management Organization (EPC Contractor Hyundai E&C) .................................. 14 2.2.3 Total Man hours of the EPC Contractor and its Subcontractors ....................................... 14 2.2.4 Accident Free Man hours of the EPC Contractor and its Subcontractors ......................... 15 2.2.5 Health, Safety and Environmental Training ..................................................................... 15 2.2.6 Health Check .................................................................................................................... 16 2.2.7 Health, Safety & Environment Inspection and Result ...................................................... 20 2.2.8 Personal Protective Equipment (PPE) .............................................................................. 22 2.2.9 Security Status .................................................................................................................. 22 2.2.10 Social Aspects and Gender issues ..................................................................................... 22

2.3 Conclusions and Recommendations ........................................................................................ 22

3. ENVIRONMENTAL QUALITY MONITORING ................................................. 24

3.1 Air quality, Noise and Vibration Monitoring ........................................................................... 24 3.1.1 Monitoring of Air quality ................................................................................................. 24 3.1.2 Noise Monitoring .............................................................................................................. 27 3.1.3 Vibration Monitoring ........................................................................................................ 30 3.1.4 Overall Assessment Air & Noise and Vibration ............................................................... 32

3.2 Water Quality Monitoring ........................................................................................................ 33 3.2.1 Monitoring parameters and procedures ............................................................................ 33 3.2.2 Inspection Activities ......................................................................................................... 34 3.2.3 Monitoring results and assessment ................................................................................... 35 3.2.4 Overall Assessment Water Quality ................................................................................... 48 3.2.5 Recommendation .............................................................................................................. 49

Page 3 of 68

4. AQUACULTURE & FISHERY ............................................................................... 50

4.1 Overview .................................................................................................................................. 50

4.2 Inspection Activities ................................................................................................................ 50

4.3 Overall Assessment Aquaculture and Fishery ......................................................................... 51

5. MANGROVE REFORESTATION MONITORING ............................................. 52

5.1 Overview .................................................................................................................................. 52

5.2 Inspection Activities ................................................................................................................ 52

5.3 Overall Assessment Mangrove Reforestation .......................................................................... 54

6. OVERALL CONCLUSIONS AND RECOMMENDATIONS .............................. 55

6.1 Health, Safety & Waste Disposal Management ....................................................................... 55

6.2 Environmental Quality Monitoring .......................................................................................... 56 6.2.1 Air & Noise and Vibration Monitoring ............................................................................ 56 6.2.2 Water quality Monitoring ................................................................................................. 57 6.2.3 Aquaculture and Fishery Monitoring ................................................................................ 57 6.2.4 Mangrove Reforestation Monitoring ................................................................................ 58

Page 4 of 68

TABLES Table 1 Institutional Responsibilities for EMP Implementation (extended version) .......................................... 10 Table 2 The accident hours against cumulative total man-hours during the period January to June, 2013 ........ 14 Table 3 Health, Safety & Environment Training ............................................................................................... 17 Table 4 Safety & Environment Inspections and Result ...................................................................................... 21 Table 5 The monitoring location, monitoring parameters and monitoring equipment and analyzed methods for

air quality monitoring ................................................................................................................................. 24 Table 6 Monitoring results of TSP and PM10 .................................................................................................... 24 Table 7 The monitoring location, monitoring parameters and monitoring equipment and analyzed methods for

noise monitoring ......................................................................................................................................... 27 Table 8 Monitoring results for Noise at Residential sites ................................................................................... 27 Table 9 Monitoring result for noise at the working site ..................................................................................... 29 Table 10 The monitoring location, monitoring parameters and monitoring equipment and analyzed methods for

Vibration monitoring .................................................................................................................................. 30 Table 11 Monitoring results for Vibration at Residential sites ........................................................................... 31 Table 12 Monitoring and analyzing results of surface water .............................................................................. 36 Table 13 The coordinates of coastal water samples ........................................................................................... 38 Table 14 Monitoring and analyzing results of coastal water .............................................................................. 39 Table 15 The coordinates of underground water (Existing wells) samples ........................................................ 41 Table 16 Monitoring and analyzing results of underground water (Existing wells)........................................... 42 Table 17 The coordinates of underground water (Drilled wells) samples .......................................................... 44 Table 18 Monitoring and analyzing results of underground water (Drilled wells)............................................. 45 Table 19 Monitoring and analyzing results ........................................................................................................ 53

GRAPHICS Graphic 1 Results of 6 monitoring times of air quality. ..................................................................................... 26 Graphic 2 Result of 6 monitoring times of noise level at site ............................................................................. 28 Graphic 3 Result of 6 monitoring times for noise at site .................................................................................... 29 Graphic 4 Result of 6 monitoring times of vibration at residential site .............................................................. 32

FIGURES Figure 1 Accident situations during the period January to June, 2013 ............................................................... 15 Figure 2 Water quality environmental monitoring procedure ............................................................................ 34 Figure 3 Water quality monitoring site .............................................................................................................. 35 Figure 4 The coordinates of surface water samples............................................................................................ 35 Figure 5 Method for selection of sample ............................................................................................................ 52

APPENDIXS Appendix 1 Environmental Team Organization Chart ....................................................................................... 59 Appendix 2 HSE Organization Chart ................................................................................................................. 61 Appendix 3 Pictures of Air quality and Noise .................................................................................................... 62 Appendix 4 Pictures of Water Quality ............................................................................................................... 63 Appendix 5 Pictures of Aquaculture and fishery ................................................................................................ 64 Appendix 6 Pictures of Mangrove Reforestation ............................................................................................... 65 Appendix 7 Picture of HSE ................................................................................................................................ 66 Appendix 8 Picture of Gender ............................................................................................................................ 68

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 5 of 68

EXECUTIVE SUMMARY

The Mong Duong 1 Thermal Power Plant project has been classified as category A1 in

accordance with ADB’s Environmental Assessment Guidelines (2003). The Project EMP was

developed as an integral part of the Environmental Impact Assessment (EIA) process of the

Project that was completed and approved by ADB in 2006.

To ensure that negative environmental health and safety impacts are minimized and addressed

effectively throughout the project implementation and operational phase, an environmental

management plan (EMP) has been formulated detailing mitigation measures and a monitoring

program during various project phases of the Mong Duong 1 Thermal Power Plant project,

located in the northern province of Quang Ninh (Vietnam)

The report is highlighting on the environmental monitoring tasks and quality observations

performed by the various project entities on air & noise, vibration, water quality, aqua culture

and fishery development and a chapter on mangrove reforestation. It is further reporting on

health & safety issues at site as well as on social impacts on the affected communities including

gender issues related to man and women working together on the same project and sharing

common camp facilities.

It covers the works implemented during the period January to July 2013 and provides a summary

of current problems, conclusions and recommendations how to best mitigate the impacts on

affected parties and the environment.

The following environmental aspects were looked at for environmental compliance and

monitored for environmental quality during the reporting period

Air and noise quality

Water quality

Aquaculture and fisheries status

Mangrove reforestation

Health, Safety and Environment (HES)

Social impacts and Gender issues

Problem areas inspected for environmental compliance and monitored for environmental quality

during the reporting period relating to Air & Noise, Vibrations, Water quality and Aqua culture

were more affected in the current reporting period compared to the last 6 months period, mainly

due to the increased level of activities at the construction site or nearby locations serving the

Mong Duong project.

Air & Noise and Vibration Issues Regarding Air Quality comparing the monitoring results (dust) of affected areas between the last

6 months of 2012 and the first 6 months in 2013, it shows that the first 6 months of 2013 has a

higher concentration of air pollutants than the 6 months before, especially in the 3 months April,

May and June 2013 when the weather was dry, sunny and hot. The increase is mostly due to

increased traffic on the new no.18 and old 18A road likewise.

On the new no.18 road near the entrance of Mong Duong 1 and 3 2 power plants, heavy vehicles

travel a lot so the road is very dirty and dusty. The road needs regular water spraying to improve

the conditions, especially in the dry season. The appearance of construction waste in nearby

vacant land (along the new no.18 road such as concrete from bored piles and other construction

debris needs to be removed and kept neat and tidy at all times. Wheels of construction vehicles

leaving the site need to be cleaned before entering the public road. Excavated areas and heaps of

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project,

Page 6 of 68

backfill on the site shall be sprayed with water or covered with plastic sheeting to limit dust

migration to nearby residential areas.

Through 6 monitoring times of noise quality at the working site during 2 days each in the period

February to June 2013, the results show that the noise level monitored in 1 hour at the turbine

and boiler area is about 73,4 – 82,1 dB(A). Compared with the allowable noise level for the

working place they are lower than the allowable limit value in TCVN 3985:1999 (85 dB). And

the noise level during daytime from 7AM to 8AM and 5PM to 6PM are 0,7–2,6 dBA higher than

the allowable limited value in QCVN 26:2010/BTNMT. At nighttime the noise level is between

10PM and 11PM monitored at a point about 7m away from the road are also higher by 7,1-12,4

dBA than the allowable limited value in QCVN 26:2010/BTNMT

The increase in noise level at the various locations and times are mainly caused by increased

construction activities at site and material transports from and to the construction site on the old

18A road

Noticeable environmental impact during the reporting period has not only been caused by pile

driving activities, foundation digging, construction and soil conveying, but also due to social

environment changes caused by the gathering of the large work force in the Mong Duong

precinct which causes all sort of problems including increased traffic, particularly in the early

morning and evening time, when a large contingent of the labor force for both projects enter the

work space

In order to limit the noise level at Residential areas, particularly at night time, the Contractor

shall be requested to keep heavy construction works to day times and limit vehicle movements

after 10PM to a minimum required.

Through 6 monitoring times during 2 days each in the period February to June 2013, the

monitoring results for vibration levels at two (2) locations during the period 6AM to 9PM are

lower than the limited value permitted in QCVN 27:2011/BTNMT – National Technical

Regulations on vibration.

No issues at present. Furthermore since heavy construction activities are almost entirely

implemented during day time, no vibrations are experienced at nighttime

Water quality

Water quality is monitored for underground water and coastal water and results are

Almost all tested items of underground water at the sampling sites are within the limits of

the National technical regulation on underground water quality QCVN09/2008/BTNMT

except for (Cd) and (Cl-) content and content of micro-organisms (Coliform)

Concentration of microorganisms (Coliform) beyond permissible limits of the National

technical regulation on underground water quality were found at the sampling points of

PW-01, PW-02, PW-03, PW-04, PW-05, PW-06, PW-08, PW-09. This is explained by

the fact that water in existing wells are not usually utilized thus the water is not rotated

and easy to create conditions for microbial growing.

Concentrations of chloride (Cl-) beyond permissible limits of the National technical

regulation on underground water quality were found at the sampling points of PW-03,

GW-01-D, GW-08, GW-09 and GW-11. This is explained by the fact that the sampling

sites are located in the coastal areas, thus may be lightly saline

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project,

Page 7 of 68

Impact of obstacle removal activities in coastal surface water is monitored by coastal

surface water sampling sites. Parameters of them are all within limit in comparison with

QCVN 10: 2008/BTNMT

Impact of Mong Duong river alignment activities in coastal surface water is monitored by

coastal surface water sampling sites. Parameters of them are almost within the limit in

comparison with QCVN 08: 2008/BTNMT

Impact of transport activities in coastal surface water is monitored by coastal surface

water sampling sites. Parameters of them are within limit in comparison with QCVN 10:

2008/BTNMT

Two of the heavy water pollution sources are water discharged from coal mining areas

via the Mong Duong river and barges transporting coal in the nearby waterway. Spilled

coal from barges will dilute elements and compound to coastal waters.

In order to compensate for the two wells which were covered during the initial site fill activities,

the contractor should be requested to drill two additional wells with a depth of 25 to 30m to

ensure water quality sampling can be done at lower aquifers. Currently this is restricted to a

depth of 15m.

Contractor must maintain all current measures to avoid pollution of surface and underground

water resources by strict control on solid and liquid waste dumping and/or accidental spillage of

oil and chemicals.

To offset the problem of the polluted water discharge from coal mining activities, treatment of

discharged water from the coal mining process and a reduction in coal smuggling activity would

greatly improve the quality in the water way, but this may be difficult to achieve.

Aquaculture and Fisheries

Based on the results of the two surveys on fishing and aquaculture activities in Thac Thay, De

Dach and Mong Duong rivers and along the coastal line of Cam Hai commune during the first

half of 2013, it may be concluded that the construction phase of Mong Duong 1 power plant has

minor impacts on the aquatic resources in the inspected areas. There were no fishing activities in

De Dach and Mong Duong rivers due to heavy industrial pollution from mining and coal trading.

Number of aquatic species and their components in these areas are very limited. Some fishing

activities were observed in the Thac Thay river and Luong Gac areas, but there are no shrimp

activities along Cam Hai coastal line due to loss from shrimp diseases outbreak and flooding.

Normal fishing activities and aquaculture species are observed in the Thac Thay River and along

the coastal line of Cam Hai commune.

To reduce impacts of pollution from mining and coal trading, Contractor is strictly enforced to

execute the solid and liquid waste disposal management plan and prohibited dumping of

hazardous substances into nearby rivers and coastal water.

Mangrove Reforestation Program

To compensate for the loss of mangrove forest taken by the Mong Duong Project, 52ha of

mangrove has been re-planted in Dong Rui Commune, (Tien Yen district, Quang Ninh province)

Inspection result shows that mangrove quality develops well, branching off well, in the allocated

area of 52 ha of mangrove forest which was replanted, there is 95% survival rate of plants.

With the current results, the Mangrove planting project has met the requirement of ADB’s EIA.

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project,

Page 8 of 68

To sustain the good results, continuous protection and feeding of the mangrove is a must to

ensure their good development and branching off. Activities such as tree clearing, weeding and

replanting of failed areas must also be maintained

Dumping of waste in mangrove and forestry areas and resource extraction from mangroves and

plantation forestry areas must be prohibited

Health & Safety and Environment

Monitoring consists of daily observation and inspections of environmental pollution, soil

contamination, fire hazards, labor and site safety and other health or safety hazards. This topic

does not belong to the monitoring scheme of the assigned environmental experts of the

Consultant, but is observed and monitored by the Owner’s Consultant Site supervision staff

during their daily work activities and by the Consultant’s Occupational Health and Safety expert.

Current results show

Good overall performance of the EPC contractor’s appointed HSE team with the

Environmental Officer (OE) appointed as per the Contractor’s EMP

Good site safety management of the EPC contractor with regards to fire safety, plant and

equipment safety, labor safety, worker training before and access gate checks before

entering Site.

No fatality and No Lost Time accident occurred until now with the accumulated total

man-hours of 5’200’000 as of July 2013

No serious soil issues happened at site until now besides some small oil spillages which

were treated immediately as per the Contractor’s EMP

Waste management follows the contractor’s EMP by separating waste into different

groups and collected and disposed as per the EMP requirements.

All required permits are in place ie. Permit To Work, Confined Space Entry Permits, Gas

Test Certificates etc.

First Aid service is available 24/7

In order to maintain the good standard the EPC contractor must strictly enforce the site safety,

warn offenders and in repeat cases dismiss them from site (some recent incidents shown in the

attached pictures need to be corrected)

Newly legislated and/or revised environmental laws must be carefully examined in order to

determine whether or not they are required to be implemented during the project execution

Contractor has to ensure at all times that it complies with the EIA and the requirements specified

in chapter VI of the ADB environmental assessment guidelines, 2003. Contractor should once

every 6 months organize exercises based on likely accident scenarios at site in which the

contractor’s assigned key site personnel assumes their emergency response roles and periodically

evaluate the efficiency of the Project EMP in place.

Social and Gender Aspects

Most current results show that both men and women are well informed of potential health and

safety risks: HIV/AIDS control and prevention activities for both camp workers and offices were

carried out by the EPC contractor to educate awareness on personal hygiene and sexually

transmitted diseases. Drug education for construction and office workers are implemented and

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project,

Page 9 of 68

undergo test screenings every 6 months for early detection and manage health issues. Camp

workers and construction office workers are vaccinated and regularly checked for diseases by

healthcare provider taking care of construction workers and local villages.

A recent audit at one of the contractor’s labor camp (LLM 69.1) showed excellent results. The

rooms for women are in good condition and include bath room and toilet inside. Television and

Air conditioner are also provided. Water supply is from underground well treated by RO system

before using. Water is tested frequently for its safe use.

The condition of the site toilets is good with separate toilets available for both men and women.

Currently 76 toilets are provided at the Mong Duong 1 site for some 3’000 workers. They are

cleaned daily. As per the EPC contractor’s information the percentage of female workers is

approximately 15% split in field and office staff.

It is suggested that the Owner’s Consultant will continue to perform regular audits at the

contractor’s labor camps, especially with regards to gender issues, at the contractor’s offices and

at the construction site itself, to ensure the good standard regarding sanitary conditions is

maintained throughout the project construction phase.

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project,

Page 10 of 68

1. INTRODUCTION

1.1 The project

The Government of Viet Nam has requested assistance from the Asian Development Bank

(ADB) to part finance the construction of the Mong Duong 1 Thermal Power Plant (under Loan

No.2350, and 2610). The Project is a coal-fired, thermal power electricity generation project with

a generation capacity of 1,000 MW. The overall project comprises of two power plants on the

same plot of land with an ultimate generation capacity of 2’200 MW. The Mong Duong 1 power

plant will comprise of two 500 MW generating units, and associated supporting infrastructure

whereas the Mong Duong 2 power plant built under a BOT scheme comprises of two 600 MW

generating units.

The MD1 project has been classified as category A1 in accordance with ADB’s Environmental

Assessment Guidelines (2003). The EMP was developed as an integral part of the Environmental

Impact Assessment (EIA) process of the Project that was completed in 2006.

The Mong Duong 2 power plant project is not part of this report, although it may contribute to

the overall impact on the environment as the two plants are back to back located on the same

piece of land.

1.2 Incorporation of Environmental Requirements into Project Contractual

Arrangements

To ensure that any possible negative environmental impacts are minimized and addressed

effectively, an environmental management plan (EMP) has been formulated detailing mitigation

measures and a monitoring program during various project phases. The individual monitoring

tasks and its frequencies are determined by the EIA and the approved staffing plan of the Project

Owner of the Consultant’s experts conducting the monitoring tasks together with EVN appointed

environmental monitoring agencies of Quang Ninh province

Key organizations in the implementation of the EMP and their corresponding responsibilities are

presented in Table 1

Table 1 Institutional Responsibilities for EMP Implementation (extended version)

EMP Responsibilities Mong Duong 1 Responsibility

- Submit Government EIA/EMP to MONRE

- Successfully implement EMP

- Provide funds for EMP implementation

EVN/GENCO3 (Project owner)

- Coordinate and manage overall project

implementation and operation including

guiding and supervision of EMP

implementation during pre-construction,

construction, and operation phases

- Manage and coordinate environmental

monitoring

- Coordinate with other parties in relation to

environmental management activities

- Supervise civil work contractor during

construction, including implementation of

environmental management activities under

EMP

TPMB1

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project,

Page 11 of 68

EMP Responsibilities Mong Duong 1 Responsibility

- Manage EMP budget

- Integrate EMP specifications in contract

documents

- Prepare detailed design activities

incorporating relevant EMP requirements Detail design consultant

(PECC1)

- Implement environmental specifications

detailed in the construction contract Construction contractor

- Monitor EMP implementation during the

construction phase Environmental monitoring

consultant team

- Conduct periodic monitoring of compliance

to EIA/EMP provisions Quang Ninh DONRE

1.3 Project Implementation Progress

During the first half of 2013 of the construction phase of the Mong Duong 1 thermal power plant

project, construction activities increased commensurately with the ongoing progress of the

project.

Some of the main civil construction works carried out at the construction site during this period:

January 2013

Bored piles for the turbine building were completed.

Bored piles for the stack #1 were completed.

Bored piles for the cooling water pump house were completed

Foundation for boiler unit #1A/B area was completed

Structural steel erection commenced on boiler #1A

Tank erection commenced in water treatment area

February 2013

Pile head cutting for foundation of stack #1 was completed.

Foundation for stack #2 was completed.

Concrete pedestals and backfilling of boiler #1A/B area was completed.

Foundation for boiler #2A/B was completed.

Precast pile driving for fuel oil tank area was completed

CW supply pipeline excavation and installation commenced in block A

March 2013

Foundation for stack #1 was completed.

Foundation for waste water treatment plant area was completed.

Foundation for auxiliary boiler was completed.

Foundation for fuel oil tanks was completed

Precast pile driving for coal stock yard area was completed.

Precast pile driving for bottom ash silos #1A/B was completed.

Precast pile driving for condensate tanks #1/2 was completed.

Excavation work for ESP #1A/B was completed.

Structural steel erection commenced on boiler #1B

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project,

Page 12 of 68

Electrical equipment installation commenced in 110/500kV switchyard

April 2013

Backfill work for stack #1 foundation was completed.

Backfill work for boiler #2 foundation was completed

Concrete walls for waste water treatment plant were completed

Backfill for fuel oil tanks #1/2 was completed.

Excavation work for ESP #2A/B was completed.

Backfill for auxiliary boiler foundation was completed.

May 2013

Pre-stressed anchor installation for CW intake walls was completed.

Bottom slab foundation for CW intake facility was completed.

Foundation and backfill work for ESP #2A/B was completed

Asphalt topping for Fuel oil tank #1 and #2 and Diesel oil tank was completed.

Precast pile driving for water treatment clarifiers was completed.

Precast pile driving for seal pits #1/2 was completed.

Precast pile driving for main transformer #1 was completed.

Structural steel erection commenced on boiler #2A

June 2013

Backfill for waste water treatment plant area was completed

Backfill for 100/500kV switch yard was completed

Excavation for C.W pipe line block A/B was completed

Foundation for main transformer #2 was completed

Excavation for main transformer #1 was completed

Excavation for fly ash silo #1/2 was completed

Excavation for limestone grinding house and limestone storage shed was completed

Construction of the cofferdam for the limestone unloading jetty was completed

Boiler pressure part erection commenced on boiler #1A

Equipment erection commenced for water treatment plant

July 2013

Precast pile driving for CHP/AHP /LHP was completed

Foundation and concrete pavement for coal stock yard buildings was completed

Turbine pedestal for STG#1 was completed

Foundation and backfill for fly ash silos #1/2 was completed

Structural works for administration building, common service building, central control

building and switchyard control building was completed

Foundation and backfill for water treatment building was completed

Foundation for Coal handling control building and coal crusher tower was completed

Backfill for CW supply pipelines in block A and C was completed

Structural works for fuel oil pump house and fire water pump house was completed

Stack #1 windshield construction was completed

Precast pile driving for fuel oil unloading pump house and jetty was completed.

Structural steel erection commenced on boiler #2B

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project,

Page 13 of 68

1.4 Report Purpose

This report intends to describe the progress regarding implementation of the project EMP and

compliance issues and corrective actions for the first half of 2013 of the construction phase of

the Mong Duong 1 thermal power plant project.

The following environmental aspects were inspected for environmental compliance and

monitored for environmental quality:

Air, noise quality and vibration

Water quality

Health Safety and Environment (HES) aspects

Aquaculture and fisheries

Mangrove reforestation

2. ENVIRONMENT COMPLIANCE INSPECTIONS

2.1 Environment Compliance Inspections at the Construction Site

- Air quality impact:

Dust resulting from theremoval of vegetation and heavy earthmoving activities

The large number of construction equipment and heavy vehicles cause considerable dust

emissions

- Mitigation measures:

Spraying bare soil and heaps of excavation materials with water to minimize dust

generation during dry periods

Minimizing disturbance to vegetation and terrain features and providing cleared areas and

stockpiles with vegetative cover to serve as buffers between the Project and the

population

Fencing off construction areas to contain dust,

Covering trucks during transport of materials and impose speed limits

Avoid burning of domestic wastes

Contractors will be required to properly maintain equipment to minimize emissions

Ensuring the commitment of contractors and/or suppliers to undertake applicable

measures above

All trucks before leaving the construction site are required to clean the wheels

- Noise quality impact:

Noise impact and ground vibration during construction can disturb nearby communities

- Mitigation measures:

Construction schedules must optimize daytime working hours and scale down activities

at night.

Extensive earthmoving and movement of heavy equipment should be conducted only

during regular working hours

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project,

Page 14 of 68

2.2 Health, Safety & Environment (HES) Aspects

The following Health & Safety and Environment (HES) aspects were inspected / monitored

during the reporting period for compliance

Site safety issues

Site waste disposal management

Pollutants Spillage

Worker Camp and Sanitation issues

Social impacts and Gender issues

Health aspects

2.2.1 Health, Safety & Environmental Management Plan (EMP)

The EPC contractor’s Environmental Management Plan (Rev B) was issued to the Project Owner

on 30th

Nov 2012 under Doc No. MD1-0-T-070-01-00021 and approved as such.

2.2.2 HSE Management Organization (EPC Contractor Hyundai E&C)

The EPC contractor’s HSE organization structure is in line with their own EMP (refer to

Appendix 2)

Safety Engineers/Officers have Certificate of OHS and show good working experience.

Contractor’s Environmental Officer (OE) is appointed as per the EMP and portrays

excellent knowledge of the environmental management system (EMS) and the applicable

approved environmental impact assessment report (EIA)

2.2.3 Total Man hours of the EPC Contractor and its Subcontractors

Table 2 shows the accident hours against cumulative total man-hours during the period of

January and June, 2013

Table 2 The accident hours against cumulative total man-hours during the period January to June, 2013

Description Total (Cumulative)

Month Jan 13 Feb 13 Mar 13 Apr 13 May 13 Jun 13

Cumulative

total man-

hours

1,451,680 1,884,010 2,870,610 3,577,400 4,318,720 5,115,410

This month

total man-

hours

346,830 432,430 637,130 706,790 741,330 796,690

Lost time

accidents

(LTA)

- - - - - -

Fatality - - - - - -

Non-injurious 1 4 5 5 5 5

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project,

Page 15 of 68

2.2.4 Accident Free Man hours of the EPC Contractor and its Subcontractors

Figure 1 shows:

No Lost Time Accidents (LTA) and No Fatality

A large increase in First aid cases has been observed

Figure 1 Accident situations during the period January to June, 2013

2.2.5 Health, Safety and Environmental Training

Training content

Every month several training courses are organized on the following topics: Daily Tool Box

meeting before starting work; Induction Training for Safety/Environment; training for Rigger

and Signalman during Lifting work; training for people who work at height; Refreshment

training; Confined Space Work and Entry; Prevention of fire incident; HSE activities at Site; Fire

Fighting and Prevention at Site; Security training; Fire fighters at Site; Working at height for

BDCC workers who work in the Turbine area; Signal man for Licogi Corp workers; Working at

height for Licogi 18 workers who work in the Admin building area; Lifting activities and

working at the opening of grating for Lilama 69.1 workers who work in the Boiler No.1 area;

How to prevent fire from the site; How to operate the fire-fighting truck etc. The training records

and site inspection results related to safety and environmental aspects are presented in Table 3.

Non-injuriousaccidents

First aid cases

Near Miss ( Non-Conformance)

accidents

First aid cases 26 34 47 60 74 95

Near Miss (

Non-

Conformance)

16 16 16 18 18 2

Cumulative

hours since

last LTA

- - - - - -

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project,

Page 16 of 68

Training methodology

Power Point presentation for site safety training in both languages English and Vietnamese are

available and taught at Hyundai’s Site Safety office

All new employees/visitors need to pass the safety training before admission to site.

In case of an accident occurrence, involved persons are sent back to repeat training to

avoid incidents of similar nature

2.2.6 Health Check

All new employees are required to submit health certificate to the contractor at the time

of hiring

Regular health checks are conducted by Cam Pha hospital for contractors employees

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 17 of 68

Table 3 Health, Safety & Environment Training

Item

Trainer

Description

Jan 13 Feb 13 Mar 13 Apr 13 May 13 Jun 13

No. of No. of No. of No. of No. of No. of No. of No. of No. of No. of No. of No. of

training People training People training People training People training People training People

T.B.M. Safety

Engineer

Daily T.B.M. before

starting work Daily 3,486 Daily 20,444 Daily 38,998 Daily 704,177 Daily 740,481 Daily 72,279

Induction

Training

Safety

Engineer

Induction Training

for

Safety/Environment

24 565 29 886 31 1,416 30 1230 30 1,806 30 1,405

Rigger Safety

Engineer

For Rigger and

Signalman during

Lifting work

6 42 2 18 1 32 1 12

Working at

Height

Safety

Engineer

For people who

work at height 7 194 4 40 10 271 5 197 3 214 4 266

Refreshment

Training

Safety

Engineer

Refreshment

training 14 1,073

Confined

Space

Safety

Engineer

Confined Space

Work and Entry 4 120 1 24

Special

Training

Project

Director

Prevention fire

incident 1 40

Special

Training

Project

Director

HSE Activities on

the Site 1 35

Fire

Fighting

Prevention

Safety

Engineer

Fire Fighting and

Prevention on the

Site

25 1480 31 1416

Special

Training

Project

Director Security training

1 60

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project,

Page 18 of 68

Item

Trainer

Description

Jan 13 Feb 13 Mar 13 Apr 13 May 13 Jun 13

No. of No. of No. of No. of No. of No. of No. of No. of No. of No. of No. of No. of

training People training People training People training People training People training People

Special

Training

Fire-

fighting

Police

Fire Fighters on the

Site

1 54

Special

Training

Safety

Engineer

No alcohol before

start working 1 19 2 49

Special

Training

Safety

Engineer

Working at height

for BDCC workers

who work in the

Turbine area. 1 139

Special

Training

Safety

Engineer

Signal man for

Licogi Corp

workers. 1 8

Special

Training

Safety

Engineer

Working at height

for Licogi 18

workers who work

in the admin

building area. 1 74

Special

Training

Safety

Engineer

Lifting activities and

working at the

opening of grating

for Lilama 69.1

workers who work

in the Boiler No.1 1 85

Refreshment

Training

Safety

Engineer All subcontractors

32 2488

Fire-fighting

Training

Safety

Engineer

How to prevent fire

from the site 30 1,405

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project,

Page 19 of 68

Item

Trainer

Description

Jan 13 Feb 13 Mar 13 Apr 13 May 13 Jun 13

No. of No. of No. of No. of No. of No. of No. of No. of No. of No. of No. of No. of

training People training People training People training People training People training People

Fire-fighting

Training

Safety

Office

How to operate fire-

fighting truck 1 14

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 20 of 68

2.2.7 Health, Safety & Environment Inspection and Result

Current audit results show that both men and women are well informed of potential health and

safety risks: HIV/AIDS control and prevention activities for both camp workers and offices are

carried out by the EPC contractor to educate and promote awareness on personal hygiene and

sexually transmitted diseases. Moreover, drug education and awareness for construction worker

and office workers are implemented and have regular test screenings every 6 months to early

detect and manage health issues. Camp workers and construction office workers are vaccinated

and regularly checked for diseases by healthcare provider services taking care of construction

workers and local villages.

A recent audit at one of the contractor’s labor camp (LLM 69.1) showed good results. The rooms

for women are in good condition and include bath room and toilet inside. Television and Air

conditioner are also provided. Water supply is from underground well treated by RO system

before using. Water is tested frequently for its safe use.

The condition of the site toilets is good with separate toilets available for both men and women.

Currently 76 toilets are provided at site for 3’000 workers. They are cleaned daily. As per the

EPC contractor’s information the percentage of female workers is approximately 15% overall

split in field and office staff.

HDEC’s Health, Safety & Environment Inspection and Findings are presented in Table 4

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 21 of 68

Table 4 Safety & Environment Inspections and Result

Location Jan 13 Feb 13 Mar 13 Apr 13 May 13 Jun 13 Description

STG Daily Daily Improper working at height such as scaffolding

Boiler Daily Daily Daily Daily Daily Daily Working at height, lifting activities,…

Switch Yard Daily Daily Improper access and no guardrails

Admin Building Daily Daily Daily Daily Daily Daily Working at height, scaffolding condition, access etc.

Intake Daily

Poor management of gas cylinder and instruction for use of a

trolley.

Whole area Weekly Weekly Weekly Weekly Weekly Visual inspection of all cranes.

Field Tank Daily Daily Daily Daily

Electric condition (welding and panel board), scaffolding

condition, confined space condition

STB Daily Daily Daily Daily Working at height, scaffolding condition, access etc.

Whole area Daily (Vehicle’s speed, emergency lighting etc)

Chimney Daily Daily Daily Checking slipform, working at height, lifting activities.

Main Pipe Rack Daily

One small truck of Licogi Corp. was fallen down into an

excavated trench while it was unloading soil

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 22 of 68

2.2.8 Personal Protective Equipment (PPE)

All employees of the EPC contractor and all its subcontractors working, or anyone visiting the

work area, are required to wear hard hats (with exception of office, cafeteria, accommodation

and vehicles), safety shoes, high visibility vests and fluorescent gathers coverring the ankles

above the safety shoes. The use of safety harness is compulsory when working at heights greater

than 2 meters above ground. Safety harness to have double clip arrangement so the wearer is

always secure.

2.2.9 Security Status

EPC contractor has placed security guards 24/7 at all the access gates. (Main gate, CW

intake and material laydown area)

All gates implement inspections for workers and vehicles to prevent theft.

EPC contractor has prepared PPE for visitors at the main gate and check all workers and

vehicles if they have valid ID’s and/or vehicle cards

2.2.10 Social Aspects and Gender issues

This needs be reported regularly as a major concern for women and men throughout the

construction phase. The health issue of the labor force is one of the topics that requires close

monitoring as part of the health and safety management plan.

Current results show that both men and women are well informed of potential health and safety

risks: HIV/AIDS control and prevention activities for both camp workers and offices were carried

out by the EPC contractor to educate and promote awareness on personal hygiene and sexually

transmitted diseases. Moreover, drug education and awareness for construction worker and office

workers alike are implemented and have regular test screenings every 6 months to detect early

and manage health issues. Camp workers and construction office workers are vaccinated and

regularly checked for diseases by healthcare provider services taking care of construction

workers and local villages.

2.3 Conclusions and Recommendations

Conclusion

Good performance of the EPC contractor’s OHS.

Good site safety management of the EPC contractor in having all required permits in

place ie. Permit To Work, Confined Space Entry Permits, Gas Test Certificates etc.

Check list available for environmental performance monitoring program done weekly by

EPC contractor

First aid service available 24/7

Monthly and semi-annual reports issued to the Department of Labor Quang Ninh

province

A recent audit by Owner/ Consultant’s representative in the contractor’s labor camps and

the conditions of the toilet facilities at site are in good order and commensurate with the

regards to gender issues

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 23 of 68

Recommendations

EPC contractor needs to submit environmental monitoring report to Project Owner on a

regular basis (monthly)

Newly legislated and/or revised environmental laws shall be examined carefully in order

to determine whether they are required to be implemented during the project execution

Contractor needs to comply with the EIA and the requirements specified in chapter VI of

the ADB environmental assessment guidelines, 2003.

Contractor needs to comply with all relevant local regulations to the project

Contractor shall once every 6 months organize exercises based on likely site accident

scenarios in which the key site personnel assigned to emergency cases shall show their

capabilities to attend such incidents in their leading roles.

Contractor shall periodically review and evaluate the efficiency of the Project EMP in

their working place

It is recommended to repeat these Audits at regular intervals throughout the project

construction phase as the labor quota will further increase over time

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 24 of 68

3. ENVIRONMENTAL QUALITY MONITORING

3.1 Air quality, Noise and Vibration Monitoring

3.1.1 Monitoring of Air quality

The monitoring location, monitoring parameters, monitoring equipment and analyzed methods

for air quality monitoring are presented in Table 5.

Table 5 The monitoring location, monitoring parameters and monitoring equipment and analyzed methods

for air quality monitoring

Monitoring

Location

Monitoring

parameter

Equipment for

monitoring

Monitoring and

Analyzed Method

At two

residential

sites selected

in EMP.

Sampling and

analysis for:

+ TSP (1 hr

and 24 hrs)

+ PM10 (1 hr

and 24 hrs)

Compared to

QCVN

05:2009/BTN

MT – National

technical

Regulations on

Ambient Air

Quality.

+ Air Sampler

SL-20 –

SIBATA/Japan

+ Air Sampler

SL- 15P –

SIBATA/Japan

+ Air Sampler

MinivolTM

TAS –

Metrics/ USA

- Follow the validity Viet

Nam Standard for

environment in TCVN

5067:1995 – Air quality –

Weigh Method for

determination of

suspended dusts content.

Monitoring results of Air quality and analysis are presented in Table 6

Table 6 Monitoring results of TSP and PM10

Monitored Points

Results (unit: g/m3)

TSP 1hr

(17h00÷18h00)

TSP 24hr

PM10 1hr

(17h00÷ 18h00)

PM10 24hr

The 1st mobilization: from 4

th to 5

th Feb 2013:

KK1 272 195 107 76

KK2 226 173 88 67

The 2nd

mobilization: from 28th

to 1st of February 2013.

KK1 258 214 127 109

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 25 of 68

Monitored Points

Results (unit: g/m3)

TSP 1hr

(17h00÷18h00)

TSP 24hr

PM10 1hr

(17h00÷ 18h00)

PM10 24hr

KK2 239 195 112 98

The 3rd

mobilization: from 22nd

to 23rd

of March 2013.

KK1 421 296 207 167

KK2 389 274 184 158

The 4th

mobilization: from 11th

to 12th

April 2013:

KK1 327 283 164 142

KK2 351 265 171 154

The 5th

mobilization: from 13th

to 14th

May 2013:

KK1 391 261 215 178

KK2 368 247 194 161

The 6th

mobilization: from 13th

to 14th

June 2013:

KK1 415 296 225 192

KK2 387 269 213 173

QCVN

05:2009/BTNMT

300 20

0

- 150

0

50

100

150

200

250

300

350

400

450

The 1st The 2nd The 3rd The 4th The 5th The 6th

KK1

KK2

0

50

100

150

200

250

300

350

The 1st The 2nd The 3rd The 4th The 5th The 6th

KK1

KK2

QCVN 05:2009/BTNMT QCVN 05:2009/BTNMT

TSP 1hr (17h00-18h00) TSP 24hr

µg/m3

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 26 of 68

Graphic 1 Results of 6 monitoring times of air quality.

Assessment of the monitoring results:

Through 6 monitoring times during 2 days each in February (two times), March, April, May and

June 2013, the results show that:

The monitoring results for average 1 hr TSP at 2 monitoring points KK1 and KK2 in four

monitoring times (March, April, May and June) are higher than the limited value in

QCVN05:2009/BTNMT – National Technical Regulations on Ambient Air

Quality(higher than 1,09 – 1,93 times). Especially the 22th of March and 13th of June

monitoring times, the monitoring results for average 1 hr TSP at 2 monitoring points KK1

and KK2 are higher than the limited value in QCVN05:2009/BTNMT – National

Technical Regulations on Ambient Air Quality (higher than 1,29 – 1,4 times).

The monitoring results for average 24 hr TSP at 2 monitoring points KK1 and KK2 in all

four monitoring times (point KK1) and three mobilizations (point KK2) are higher than

the limited value in QCVN05:2009/BTNMT – National Technical Regulations on

Ambient Air Quality (higher than 1,135 – 1,71 times). Especially the 22th of March and

13th of June mobilization at monitoring point KK1, the monitoring results for average 24

hr TSP at 01 monitoring point KK1 are higher than the limited value (1,475 times).

The monitoring results for average 24 hr PM10 at monitoring points KK1 and KK2 in all

six monitoring times are approximations and higher than the limited value in

QCVN05:2009/BTNMT – National Technical Regulations on Ambient Air Quality

(higher than 0,975 – 1,48 times).

Comparison of monitoring results between KK1and KK2 shows that KK1 has higher

concentrations of air pollutants than those at KK2, because the population density at KK1

is higher than that at KK2.

The time that concentrations of average 1 hr TSP and average 1 hr PM10 at 2 monitoring

points reach maximum is the rush hour when traffic activities are the highest (17h00 ÷

18h00).

The weather in Mong Duong: During the first 6 monitoring times in 2013 because it`s

mostly sunny and hot ( especially in the four months: March, April, May and June), dry

roads, vehicles transport more, so the monitoring results for average TSP are high and

exceed the limits.

0

50

100

150

200

250

The 1st The 2nd The 3rd The 4th The 5th The 6th

KK1

KK2

0

50

100

150

200

250

The 1st The 2nd The 3rd The 4th The 5th The 6th

KK1

KK2

µg/m3

QCVN 05:2009/BTNMT

PM10 1hr (17h00-18h00) PM10 24hr

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 27 of 68

3.1.2 Noise Monitoring

The monitoring location, monitoring parameters, monitoring equipment and analyzed methods

for noise monitoring are presented in Table 7

Table 7 The monitoring location, monitoring parameters and monitoring equipment and analyzed methods

for noise monitoring

Monitoring

Location

Monitoring

parameter

Equipment for

monitoring

Monitoring and Analytic

Method

At two

residential sites

selected in EMP.

Compared with

QCVN

26:2010/BTNMT

– National

technical

Regulations on

Noise.

+ At 01

construction site

where workers

are impacted

Equivalent

acoustic

level A,

LeqdBA.

Integrating-

Averaging

Sound level

meter, Type

6226 –

ACO/Japan.

Follow the Viet Nam

Standard for environment

TCVN 7878-1: 2008 (ISO

1996-1: 2003); TCVN

7878-2: 2010 (ISO 1996-

2: 2003).

Monitoring results for noise level at residential sites are presented in Table 8

Table 8 Monitoring results for Noise at Residential sites

Monitored Points Results LAeq (1h) (dBA)

7h – 8h 17h – 18h 22h – 23h

The 1st mobilization: from 4

th to 5

th Feb 2013:

KK1 68,1 71,6 67,4

KK2 62,9 61,5 56,2

The 2nd

mobilization: from 28th

of Feb to 1st of March, 2013:

KK1 70,7 71,5 65,1

KK2 61,6 63,1 57,3

The 3rd

mobilization: from 22nd

to 23rd

of March 2013:

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 28 of 68

Monitored Points Results LAeq (1h) (dBA)

7h – 8h 17h – 18h 22h – 23h

KK1 71,5 72,6 64,7

KK2 62,4 65,8 59,5

The 4th

mobilization: from 11th

to 12th

April 2013:

KK1 68.2 71.7 62.1

KK2 57.3 62.7 49.9

The 5th

mobilization: from 13th

to 14th

May 2013:

KK1 68.9 70.8 63.2

KK2 59.3 58.7 51.3

The 6th

mobilization: from 13th

to 14th

June 2013:

KK1 68.5 71.5 64.6

KK2 62.3 61.7 55.8

QCVN

26:2010/BTNMT

70 70 55

Graphic 2 Result of 6 monitoring times of noise level at site

0

10

20

30

40

50

60

70

80

The 1st The 2nd The 3rd The 4th The 5th The 6th

KK1(7h-8h) KK2(7h-8h) KK1(17h-18h) KK2(17h-18h)

0

10

20

30

40

50

60

70

80

The 1st The 2nd The 3rd The 4th The 5th The 6th

KK1 KK2

QCVN 26:2010/BTNMT

QCVN 26:2010/BTNMT

LAeq 1hr (7h-8h) và (17h-18h) LAeq 1hr (22h-23h)

dBA

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 29 of 68

The monitoring results for noise level at working sites are presented in Table 9.

Table 9 Monitoring result for noise at the working site

Monitored Points Results LAeq (1h) dB(A)

9h – 10h

The 1st mobilization: from 4

th to 5

th Feb 2013:

KK3 78,5

The 2nd

mobilization: from 28th

of Feb to 1st of March, 2013:

KK3 79,3

The 3rd

mobilization: from 22nd

to 23rd

of March 2013:

KK3 82,1

The 4th

mobilization: from 11th

to 12th

April 2013:

KK3 77,3

The 5th

mobilization: from 13th

to 14th

May 2013:

KK3 73,4

The 6th

mobilization: from 13th

to 14th

June 2013:

KK3 74,2

Graphic 3 Result of 6 monitoring times for noise at site

68

70

72

74

76

78

80

82

84

The 1st The 2nd The 3rd The 4th The 5th The 6th

dBA

LAeq 1hr (9h-10h)

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 30 of 68

Assessment of Noise monitoring results:

Through 6 monitoring times during 2 days each in February (two times), March, April, May and

June 2013, the results show that:

The monitoring results for noise in the daytime of 7h - 8h and 17h - 18h during the period

of 6h - 21h at KK1 are approximate but higher than (about 0,7–2,6 dBA) the limited value

in QCVN 26:2010/BTNMT – National Technical Regulations on Noise; at KK2 are lower

than the limited value in QCVN 26:2010/BTNMT.

The monitoring results for noise in the nighttime of 22h – 23h during the period of 21h-

6h, at KK1, monitored point about 7m from the road are higher than (about 7,1-12,4 dBA)

the limited value in QCVN 26:2010/BTNMT – National Technical Regulations on Noise;

at KK2, monitored point about 20 m from the road, are higher than (about 0,8-4,5 dBA)

the limited value in QCVN 26:2010/BTNMT – National Technical Regulations on Noise.

Caused by transport activities increased on the old 18A road at night, such as: carrying

coal, materials when the weather in Mong Duong is sunny, hot and dry.

At the Working site:

Through 6 monitoring times during 2 days each in February (two times), March, April, May and

June 2013, the results show that:

The monitoring results for noise at the working site at all 6 monitoring times, the noise level

monitored in 1 hour at the turbine and boiler area is about 73,4 – 82,1 dB(A). If compared with

the allowable noise level for the working place, then they are lower than the limited value in

TCVN 3985:1999 (85 dB).

3.1.3 Vibration Monitoring

The monitoring location, monitoring parameters, monitoring equipment and analyzed methods

for vibration are presented in Table 10

Table 10 The monitoring location, monitoring parameters and monitoring equipment and analyzed

methods for Vibration monitoring

Monitoring Location Monitoring

parameter

Equipment for

monitoring

Monitoring and

Analyst Method

At two residential

sites selected in

EMP.

Vibration

Acceleration

(dB).

Compared with

QCVN

27:2010/BTNMT

– National

technical

Regulations on

Vibration.

Vibration meter

TYPE 3233 –

ACO/Japan.

Follow the validity

Viet Nam Standard

for environment in

TCVN 6963:2001

– Vibration and

shock – Vibration

emitted by

construction works

and factories –

Method of

measurement.

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 31 of 68

Monitoring for vibration level was conducted at the same time with noise monitoring at

monitoring points. Vibration is monitored in 3 directions and the highest result is used to

compare with the regulation. The results of vibration monitoring at residential sites are presented

in Table 11

Table 11 Monitoring results for Vibration at Residential sites

Monitored Points Results, dB (1h)

7h – 8h 17h – 18h 22h – 23h

The 1st mobilization: from 4

th to 5

th Feb 2013:

KK1 58,8 60,3 42,6

KK2 51,4 38,7 37,4

The 2nd

mobilization: from 28th

of Feb to 1st of March, 2013:

KK1 57,2 60,7 49,3

KK2 43,1 45,4 41,3

The 3rd

mobilization: from 22nd

to 23rd

of March 2013:

KK1 56.8 62.1 51.5

KK2 45.6 47.9 43.7

The 4th

mobilization: from 11th

to 12th

April 2013:

KK1 55.2 57.3 48.7

KK2 42.4 43.1 39.2

The 5th

mobilization: from 13th

to 14th

May 2013:

KK1 51,7 53,4 45,9

KK2 47,3 45,1 40,5

The 6th

mobilization: from 13th

to 14th

June 2013:

KK1 59.7 52.7 42.6

KK2 49.9 44.7 39.1

QCVN 27:2010/BTNMT

(6h – 22h) 75 -

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 32 of 68

Graphic 4 Result of 6 monitoring times of vibration at residential site

Assessment of the Vibration monitoring results:

Through 6 monitoring times during 2 days each in February (two times), March, April, May and

June 2013, the results show that:

Monitoring results for vibration level at 2 sites during the period of 6h – 21h are lower

than the limited value in QCVN 27:2011/BTNMT – National Technical Regulations on

Vibration.

Construction activities of Mong Duong 1 Thermal Power Plant are almost entirely

implemented during daytime, therefore no vibration is experienced during nighttime, from

21h-6h

3.1.4 Overall Assessment Air & Noise and Vibration

Implementation of Environmental Management measures by the Construction contractor is

following the guidelines under the EMP

Problems identified:

During the first 6 months in 2013, construction activities at the Site of Mong Duong 1

were considered normal with activities at site taking place such as pile driving, foundation

digging, concrete works for foundations of boiler, turbine and other equipment, building

works, soil conveying with transport vehicles and other executing plant and machinery.

The two monitoring stations KK1 and KK2 located at residential areas selected in the

EMP are not impacted during the construction phase of Mong Duong 1 thermal power

plant, but may be impacted during the operational phase, particularly from the higher

pollution sources (boiler, smoke stack)

0

10

20

30

40

50

60

70

The 1st The 2nd The 3rd The 4th The 5th The 6th

KK1(7h-8h) KK2(7h-8h) KK1(17h-18h) KK2(17h-18h)

0

10

20

30

40

50

60

The 1st The 2nd The 3rd The 4th The 5th The 6th

KK1 KK2

Vibration 1hr (7h-8h) và (17h-18h) Vibration 1hr (22h-23h)

dB

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 33 of 68

Air pollution sources (mainly dust) to the dense residential areas of Mong Duong Ward,

which is near the two sides of the old no.18A road are mainly caused by transport

activities (carrying coal, materials, car, motorcycles…); sorting out coal plant (near KK2),

coal discharge area (especially when the wind blows from south-east direction)

Air pollution (dust and other pollution) is also increasing on the new no.18 road due to

increased transport activities over the 6 months

Comparing monitoring results (dust) between the last 6 months of 2012 and the first 6

months of construction phase in 2013 shows that the first 6 months of 2013 has higher

concentrations of air pollutants than the 6 months before. Especially in the 3 months

(April, May and June) in 2013) when the weather was dry and hot.

3.2 Water Quality Monitoring

3.2.1 Monitoring parameters and procedures

Monitoring parameters

Ambient surface water: Temperature, pH, TSS, DO, COD, BOD5, Cl-, NH4+, heavy

metal (As, Cr, Cd, Cu, Pb, Zn, Ni, Hg, Fe, Mn, Se), oil and grease, Coliform, T-N, T-P.

Underground water: Temperature, pH, TSS, COD, Cl-, NH4+, NO3-, SO42-, heavy

metals (As, Cr, Cd, Cu, Pb, Zn, Ni, Hg, Fe, Mn, Se), VOC, SVOC, TPH, oil and grease

and Coliform

Monitoring procedure

Collecting information relating to the project.

Investigating scene and monitoring.

Analyzing in laboratory

Summarize and handle analytical data.

Assessing monitoring results.

Promoting treatment measures to minimize water environment pollutant

Preparing report of water environment condition

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 34 of 68

The Water quality environmental monitoring procedure are presented in Figure 2

Figure 2 Water quality environmental monitoring procedure

3.2.2 Inspection Activities

Water quality monitoring sites

The monitoring site and co-ordinates of sensitive sites are shown in Figure 3

Water Environment

monitoring

Measure at site

Synthesize and handle

data

Promote treatment measures to

minimize pollutant.

Assess monitoring results

Sampling, analyzing in

laboratory

Preparing the report

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 35 of 68

Figure 3 Water quality monitoring site

Environmental condition at monitoring time

No rain

No significant even at coastal water sampling time

No significant even at underground water sampling time

Drilling well no. 1, 2, 3, 4, 6, 8 were covered at sampling time

3.2.3 Monitoring results and assessment

A. Surface water quality

Water samples were collected from surface water bodies at the project site and its surrounding

area to establish the baseline database for the surface water quality. Eight water samples were

collected at selected locations. The locations of surface water sampling are shown in Figure 3.

The coordinates of the surface water samples are shown in Table 4.8

Figure 4 The coordinates of surface water samples

No. Item Co-ordinate

Description X Y

Surface water

1 SW-01 107021’00 E 21

004’10 N

2 SW-02 107021’01 E 21

004’29 N

3 SW-03a 107021’08 E 21

004’08 N

4 SW-06 107021’25 E 21

005’12 N

5 SW-07 107021’47 E 21

005’04 N

6 MD-1 107020.170 E 21

003.800 N

7 DD-1 107020.934 E 21

004.273 N

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 36 of 68

No. Item Co-ordinate

Description X Y

8 DD-4 107022.013 E 21

005.147 N

The surface freshwater resources in the studied area that will be affected by the Mong Duong

power plant development consists of the lower reaches of the western Mong Duong river which

discharges at the plant site, the lower estuary of the small De Dach rver to the north, and the

distant Thac Thay river to the north of Cam Hai commune. Mong Duong river drains into a small,

sparsely populated basin from the west that is dominated by the active open pit coal mine

activity. The river passes through Mong Duong town just before discharging into Luong Gac

channel at the plant site. The analytical results of the samples are summarized in Table 12

Table 12 Monitoring and analyzing results of surface water

Para

met

er

Unit

Sampling site

QC

VN

08:2

008

BT

NM

T

(B

2)

SW

-01

SW

-02

SW

-03a

SW

-06

SW

-07

MD

-01

DD

-1

DD

-4

On-site monitoring results

Temp. 0C 19.72 19.39 19.14 20.07 19.31 20.84 19.50 20.49 -

pH - 6.95 7.44 6.57 6.62 6.96 5.98 5.91 6.88 5.5-9

DO mg/l 4.9 5.3 5.0 4.5 5.1 3.9 4.5 4.7 ≥2

Laboratory monitoring results

TSS mg/l 27.61 20.13 15.68 22.15 18.03 38.30 22.70 18.94 100

COD mg/l 10.0 9.8 9.7 11.1 9.2 17.7 12.7 10.8 50

BOD mg/l 6.49 6.64 6.68 8.26 7.60 8.77 6.87 7.21 25

Cl- mg/l 250.55 336.27 600.85 643.01 800.09 166.90 281.87 373.79 -

NH4+ mg/l 0.399 0.301 0.283 0.243 0.245 0.299 0.268 0.222 1

As mg/l 0.0038 0.0045 0.0036 0.0029 0.0036 0.0038 0.0040 0.0034 0.1

Cr mg/l 0.0022 0.0018 0.0016 0.0026 0.0020 0.0033 0.0030 0.0026 -

Cd mg/l 0.0006 0.0008 0.0005 0.0008 0.0005 0.0013 0.0005 0.0005 0.01

Cu mg/l 0.0043 0.0035 0.0042 0.0129 0.0085 0.0259 0.0143 0.0098 1

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 37 of 68

Para

met

er

Unit

Sampling site

QC

VN

08:2

008

BT

NM

T

(B

2)

SW

-01

SW

-02

SW

-03a

SW

-06

SW

-07

MD

-01

DD

-1

DD

-4

Pb mg/l 0.0070 0.0068 0.0060 0.0073 0.0066 0.0080 0.0067 0.0051 0.05

Zn mg/l 0.0564 0.0506 0.0376 0.0548 0.0616 0.0710 0.0656 0.0591 2

Ni mg/l 0.0029 0.0023 0.0018 0.0019 0.0016 0.0028 0.0023 0.0015 0,1

Hg mg/l 0.0009 0.0006 0.0005 0.0013 0.0010 0.0015 0.0010 0.0007 0,002

Fe mg/l 0.8953 0.7600 0.4977 0.6566 0.5999 1.6098 0.7742 0.5789 2

Mn mg/l 0.2518 0.2217 0.1509 0.2565 0.1912 0.6281 0.3304 0.1584 -

Se mg/l 0.0010 0.0006 0.0007 0.0005 0.0071 0.0006 0.0007 0.0004 -

Oil and

Grease mg/l 0.276 0.136 0.050 0.146 0.100 0.269 0.163 0.090 0.3

Coliform

MPN/

100ml 559 468 592 704 593 851 693 584 10000

T-N mg/l 0.005 0.003 0.007 0.007 0.005 0.009 0.009 0.008 -

T-P mg/l 1.60 0.82 0.53 2.13 0.21 3.20 1.73 1.31 -

According to the analytical results for collected surface water samples all heavy metals, oils, total

suspended solids, ammonia, chloride, coliform, nitrogen and phosphor are lower than QCVN

08:2008/BTNMT, category B2– Water for Transport and other purposes with the requirements of low water

quality

B. Coastal water quality

The Mong Duong thermal power plant is situated in north western Bai Tu Long in northern

Vietnam. The coastal zone in this area is typical of Vietnam, being dominated by vast sandy

sediment deposits that extend from well above the high water mark to beyond 5km offshore.

Coastal water samples were collected from the following four zones that potentially would be

affected in different ways by the power plant development: (i) Near shore area of Cam Hai

commune; (ii) at the Ash pond; (iii) in the Van Don district (island group) far away about 1km

East of the project site and (vi) Luong Gac channel from Cam Hai commune south to Cua Ong.

At the three points (LG-1; LG-3; LG-4) for impact assessment of transportation activities to

coastal water environment, eight (8) coastal water samples were collected at selected locations.

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 38 of 68

The locations of coastal water sampling are shown in the Figure 3. The coordinates of coastal

water samples are shown in Table 13

Table 13 The coordinates of coastal water samples

No. Item Co-ordinate

Description X Y

Coastal water samples

1 SW-3b 107021’27 E 21

004’22 N

2 SW-04 107021’50 E 21

004’20 N

3 SW-05a 107021’11 E 21

004’56 N

4 SW-05b 107021’39 E 21

004’34 N

5 SW-08 107021’19 E 21

005’39 N

6 LG-1 107022.595 E 21

005.110 N

7 LG-3 107021.275 E 21

004.611 N

8 LG-4 107022.201 E 21

003.855 N

The lower reaches of the river starting at Mong Duong town are brackish and strongly influenced

by the tidal cycle of Luong Gac and Bai Tu Long. The delta at the mouth of the river below

Mong Duong town experiences annual flooding resulting from the combination of high runoff of

the rainy season and spring (full moon) tides. Turbidity and suspended sediment loads in the river

are high, caused by land erosion from human activity (open-pit coal mining) and the natural

sandy soils of the region.

The monitoring and analyzing results of coastal water are presented in Table 14

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 39 of 68

Table 14 Monitoring and analyzing results of coastal water

No.

Para

met

er

Unit

Sampling site

QC

VN

10:2

008/

BT

NM

T

(Oth

er)

SW

-3b

SW

-04

SW

-05a

SW

-05b

SW

-08

LG

-1

LG

-3

LG

-4

On-site monitoring result

1. Temp. 0C 18.68 18.71 18.57 18.99 18.42 18.12 18.56 18.85 -

2. pH - 8.43 8.10 7.86 8.28 8.10 8.22 8.21 8.10 6.5-8.5

3. DO mg/l 5.5 5.5 5.1 5.5 5.9 5.6 6.4 5.7 -

Laboratory result assessment of coastal water

4. TSS mg/l 9.76 9.54 10.70 10.08 8.07 9.03 7.92 12.41 -

5. COD mg/l 8.3 7.8 8.6 9.4 6.6 8.2 8.2 8.9 -

6. BOD mg/l 5.32 5.29 6.70 6.34 4.21 5.78 6.85 6.55 -

7. Cl- mg/l 1159.46 1222.21 1260.98 12117.84 1269.28 1218.26 1205.92 1216.97 -

8. NH4+ mg/l 0.213 0.196 0.179 0.168 0.182 0.157 0.152 0.176 0.5

9. As mg/l 0.0031 0.0031 0.0034 0.0036 0.0034 0.0039 0.0042 0.0028 0.05

10. Cr mg/l 0.0022 0.0018 0.0020 0.0013 0.0019 0.0024 0.0018 0.0014 -

11. Cd mg/l 0.0005 0.0006 0.0003 0.0006 0.0004 0.0004 0.0004 0.0004 0.005

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 40 of 68

No.

Para

met

er

Unit

Sampling site

QC

VN

10:2

008/

BT

NM

T

(Oth

er)

SW

-3b

SW

-04

SW

-05a

SW

-05b

SW

-08

LG

-1

LG

-3

LG

-4

12. Cu mg/l 0.0039 0.0046 0.0032 0.0029 0.0045 0.0052 0.0043 0.0044 1

13. Pb mg/l 0.0060 0.0056 0.0053 0.0047 0.0064 0.0055 0.0050 0.0066 0.1

14. Zn mg/l 0.0398 0.0504 0.0374 0.0340 0.0435 0.0363 0.0472 0.0402 2

15. Ni mg/l 0.0017 ND 0.0013 ND ND ND ND ND -

16. Hg mg/l 0.0006 0.0004 0.0009 0.0012 0.0006 0.0005 0.0007 0.0003 0.005

17. Fe mg/l 0.0427 0.0397 0.0356 0.0370 0.0325 0.0464 0.0504 0.0403 0.3

18. Mn mg/l 0.1656 0.0919 0.0788 0.0653 0.0536 0.0246 0.0207 0.0240 0.1

19. Se mg/l 0.0004 0.0007 0.0008 0.0004 ND ND ND ND -

20. Oil and

Grease mg/l 0.056 0.048 0.060 0.040 0.010 0.050 0.060 0.035 0.2

21.

Coliform

MPN

/100ml 410 410 377 360 411 332 375 550 1000

22. T-N mg/l 0.002 0.003 0.004 0.006 0.003 0.005 0.011 0.004 -

23. T-P mg/l 0.40 0.62 0.31 0.23 0.03 0.07 0.10 0.93 -

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 41 of 68

Recorded Mn concentrations at SW-3b exceed the QCVN standard for other uses. The indicators

of organic pollution of BOD show relatively clean conditions, which are consistent with the

sparsely populated basin. The presence of coliform in coastal water indicates the presence of

nearby Mong Duong town. The presence of oil reflects the observed heavy small-boat traffic in

the river. Heavy metal concentrations meet Vietnamese standards.

C. Underground water quality at Existing wells

Nine (9) groundwater samples from existing wells were collected at Cam Y, Cam Hai,

Van Don, Mong Duong. The locations of underground sampling points at existing wells are

shown in the Figure 3. The coordinates of the groundwater sampling points are shown more

detail in table15

Table 15 The coordinates of underground water (Existing wells) samples

No. Item Co-ordinate

Description X Y

Underground water (Existing wells)

1 PW-1 107o21’00E 21º05’03N

Mr Tan (replaced by Mrs Nguyen

Thi Muon), group 148, Cam Y

2 PW-2 107o20’59E 21º05’05N

Mr Phung Van Goong, Group 146,

Area 8

3 PW-3 107o20’19E 21º04’33N

Mr Ngo Van Tan, Group 146, Area

8

4 PW-4 107o19’28E 21º03’50N

Mr Pha (replaced by Mr Le Van

Cung) Group 17, Mong Duong Dist.

5 PW-5 107o23’58E 21º04’31N

Mr Tu Van Hiep, Trang Huong,

Doan Ket, Van Don.

6 PW-6 107o23’25E 21º03’54N

Mr Diep Van Son, Trang Huong,

Doan Ket, Van Don.

7 PW-7 107o20’52E 21º03’40N

Tran Van Bao (Group 3, Area I),

replaced by Nguyen Thi Thuy

Group 204 Area 11, Mong Duong

Dist.

8 PW-8 107o19’26E 21º03’59N

Mrs. Nguyen Thi Nhuy, Group 108,

Area 6, Mong Duong Dist.

9 PW-9 107o22’02E 21º05’30N

Mr Khong Minh Hoi, Hamlet 4,

Cam Hai. Dist.

Based on the analytical results, detected contaminants exceeding the referenced standards are

indicated in Table 16

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 42 of 68

Table 16 Monitoring and analyzing results of underground water (Existing wells)

No

Para

met

er

Unit

Sampling site

QC

VN

09

PW

-01

PW

-02

PW

-03

PW

-04

PW

-05

PW

-06

PW

-07

PW

-08

PW

-09

On-site monitoring result

1. Temp. 0C 24.6 25.9 25.3 24.6 23 25.3 23.7 23,4 26,3 -

2. pH - 6.82 6.73 6.37 6.63 5.97 5.86 5.82 6,61 6,58 5,5-8,5

Laboratory result assessment of underground water (existing wells)

3. TSS mg/l 3.21 3.89 4.34 2.90 2.46 2.92 5.60 3,36 4,29 -

4. COD mg/l 4.5 3.9 3.8 4.8 4.3 4.6 4.5 5,6 4,7 4

5. Cl- mg/l 236.22 85.75 439.76 430.72 86.18 87.06 268.10 207,89 416,27 250

6. NH4+ mg/l 0.054 0.099 0.075 0.164 0.042 0.034 0.076 0,084 0,065 0,1

7. NO3- mg/l 0.14 0.16 0.09 0.10 0.07 0.08 0.05 0,10 0,04 15

8.

SO42-

mg/l ND ND 137.691 98.901 46.053 42.834

135.80

9 101,648

231,74

8 400

9. As mg/l 0.0044 0.0038 0.0071 0.0080 0.0036 0.0051 0.0065 0,0057 0,0041 0,05

10. Cr mg/l 0.0024 0.0022 0.0033 0.0035 0.0017 0.0025 0.0020 0,0029 0,0033 -

11. Cd mg/l 0.0028 0.0024 0.0023 0.0035 0.0031 0.0038 0.0036 0,0035 0,0025 0,005

12. Cu mg/l 0.0408 0.0502 0.0303 0.0468 0.0330 0.0417 0.0472 0,0580 0,0639 1

13. Pb mg/l 0.0065 0.0072 0.0058 0.0044 0.0059 0.0067 0.0062 0,0056 0,0043 0,01

14. Zn mg/l 0.0090 0.0084 0.0134 0.0082 0.0071 0.0028 0.0445 0,0833 0,0926 3

15. Ni mg/l 0.0032 0.0036 0.0033 0.0039 0.0034 0.0023 0.0029 0,0019 0,0042 -

16. Hg mg/l 0.0007 0.0010 0.0005 0.0005 0.0007 0.0005 0.0005 ND 0,0005 0,001

17. Fe mg/l 0.0050 0.0055 0.0068 0.0042 0.0056 0.0065 0.0056 0,0044 0,0040 5

18. Mn mg/l 0.0073 0.0020 0.0064 0.0106 0.0031 0.0031 0.0078 0,0095 0,0036 0,5

19. Se mg/l 0.0007 0.0006 0.0008 0.0007 0.0005 0.0010 0.0008 ND 0,0006 0,01

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 43 of 68

No

Para

met

er

Unit

Sampling site

QC

VN

09

PW

-01

PW

-02

PW

-03

PW

-04

PW

-05

PW

-06

PW

-07

PW

-08

PW

-09

20. Clorof

orm μg/l ND ND ND ND ND ND ND ND ND -

21. Phenol μg/l ND ND ND ND ND ND ND ND ND -

22. Fluore

nce μg/l ND ND ND ND ND ND ND ND ND

23. TPH mg/l ND ND ND ND ND ND ND ND ND -

24. Oil

and

Grease mg/l 0.004 0.006 0.007 0.010 0.004 0.003 0.007 0,008 0,004 -

25.

Colifor

m

MPN/1

00ml 20 527 130 926 10 13 1109 13 15 3

Results of the groundwater sampling as in Table 16 show that:

COD concentration in most sampling points were relatively higher than the reference

standard

Cl- was relatively high in PW-03, PW-04, PW-07, PW-09 with concentration above the

reference standard QCVN09

NH4+ was detected higher than the reference standard at PW-04

Coliform at most stations were measured at levels above the reference standard

QCVN09:2008

D. Underground water quality in water of drilled Wells

The groundwater monitoring locations at the construction site of the MD1-TPP have been

backfilled during the process of ground backfill and leveling. The average backfilled depth from

the well’s bottom to ground surface is now in the range of 11,0 – 35,0 m. These wells have been

constructed and designed for monitoring the ground water quality inside the MD1-TPP’s

boundary following the EIA of ADB.

Eleven underground water samples of drilled wells were collected at the selected locations. The

locations of coastal water sampling are shown in the Figure 3. The coordinates of coastal water

samples are shown in Table 17.

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 44 of 68

Table 17 The coordinates of underground water (Drilled wells) samples

No. Item Co-ordinate Description

Underground water (Drilled wells) Depth (m)

1 GW – 01 – D 107o20’36E 21º04’36N 33.66

2 GW – 02 107o20’36E 21º04’43N 16.16

3 GW – 03 – D 107º20’45E 21º04’45N 35.33

4 GW – 04 107º20’54E 21º04’46N 13.63

5 GW – 05 107º21’18E 21º04’43N 15.88

6 GW – 06 107º21’19E 21º04’54N 22.00

7 GW – 07 – D 107º21’29E 21º05’12N 30.00

8 GW – 08 107º21’48E 21º04’48N 18.00

9 GW – 09 107º22’06E 21º04’35N 10.00

10 GW – 10 – D 107º22’10E 21º04’11N 30.00

11 GW – 11 107º22’04E 21º04’27N 11.00

It noted that that during the survey time at the construction site in March, 2013, two of the

underground water wells GW-08 and GW-06 have been filled by sand due to filling internal road

for slag dump area. To solve this problem, the Contractor has drilled new wells but the depth is

only 9m, so the Contractor should be requested to drill new wells to the depth of 22m and 18m as

shown in Table 17.

The monitoring and analyzing results of underground water (Drilled wells) are presented in Table

18

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 45 of 68

Table 18 Monitoring and analyzing results of underground water (Drilled wells)

No.

Para

met

er

Unit

Sampling site

QC

VN

09

GW

-01-D

GW

-02

GW

-03-D

GW

-04

GW

-05

GW

-06

GW

-07-D

GW

-08

GW

- 09

GW

-10-D

GW

- 11

On-site monitoring results

1. Temp. 0C - - - - 20.20 - 20.20 - 20.01 20,21 20,01 -

2. pH - - - - - 7.39 - 7.21 - 6.60 8,14 7,37 5,5-8,5

Laboratory result assessment of underground water (drilled wells)

TSS mg/l - - - - 2.08 - 3.17 - 2.11 2,04 1,56 -

3. COD mg/l - - - - 2.7 - 4.2 - 3.0 2,7 2,4 4

4. Cl- mg/l - - - - 422.79 - 840.75 - 7829.50 4073,17 4031,15 250

5. NH4+ mg/l - - - - 0.066 - 0.074 - 0.051 0,061 0,037 0,1

6. NO3- mg/l - - - - 0.62 - 0.93 - 0.32 0,15 0,12 15

7. SO42-

mg/l - - - - 124.740 - 88.573 - 69.911 83,331 76,661 400

8. As mg/l - - - - 0.0049 - 0.0074 - 0.0054 0,0063 0,0060 0,05

9. Cr mg/l - - - - 0.0025 - 0.0027 - 0.0036 0,0042 0,0033 -

10. Cd mg/l - - - - 0.0033 - 0.0043 - 0.0035 0,0054 0,0043 0,005

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 46 of 68

No.

Para

met

er

Unit

Sampling site

QC

VN

09

GW

-01-D

GW

-02

GW

-03-D

GW

-04

GW

-05

GW

-06

GW

-07-D

GW

-08

GW

- 09

GW

-10-D

GW

- 11

11. Cu mg/l - - - - 0.0354 - 0.0471 - 0.0662 0,0440 0,0400 1

12. Pb mg/l - - - - 0.0065 - 0.0067 - 0.0054 0,0064 0,0064 0,01

13. Zn mg/l - - - - 0.0088 - 0.0459 - 0.0941 0,0802 0,0792 3

14. Ni mg/l - - - - 0.0043 - 0.0039 - 0.0050 0,0060 0,0057 -

15. Hg mg/l - - - - 0.0009 - 0.0008 - 0.0007 0,0013 0,0008 0,001

16. Fe mg/l - - - - 0.0055 - 0.0058 - 0.0046 0,0062 0,0053 5

17. Mn mg/l - - - - 0.0146 - 0.0200 - 0.0150 0,0049 0,0094 0,5

18. Se mg/l - - - - 0.0013 - 0.0015 - 0.0011 0,0018 0,0013 0,01

19. Cloroform μg/l - - - - ND - ND - ND ND ND -

20. Phenol μg/l - - - - ND - ND - ND ND ND -

21. Fluorence μg/l - - - - ND - ND - ND ND ND -

22. TPH mg/l - - - - 0.006 - 0.006 - ND ND ND -

23. Oil and

Grease mg/l - - - - 0.004 - 0.004 - ND ND ND -

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 47 of 68

No.

Para

met

er

Unit

Sampling site

QC

VN

09

GW

-01-D

GW

-02

GW

-03-D

GW

-04

GW

-05

GW

-06

GW

-07-D

GW

-08

GW

- 09

GW

-10-D

GW

- 11

24.

Coliform

MPN/

100ml - - - - 14 - 10 - 8 20 10 3

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 48 of 68

According to the Monitoring and analyzing results for collected underground water (drilled

wells) samples:

Chloride and coliform was relatively high in GW-05, GW-06, GW-07-D, GW-08, GW-

09; GW-10-D, GW-11, with concentrations above the referenced standard

Cd and Hg were also detected in concentrations above reference standards in GW-10-D

3.2.4 Overall Assessment Water Quality

Through the results of monitoring and analyzing of surface water and groundwater at Mong

Duong 1 thermal power plant project, we have following comments:

At the time of the survey from January to June, 2013, obstacle removal and Mong Duong river

alignment activities were finished and construction activities under implementation

Drilled wells labeled GW-01, GW-02, GW-03, GW-04, GW-05 and GW-08 were covered during

site clearance and building. They are important ground water monitoring points. The

environmental consultant for water quality recommends that investor should drill new wells

which replace the covered wells.

Impact of obstacle remove activities in coastal surface water is monitored by coastal surface

water sampling sites labeled SW-3a, DD-1, SW-06, SW-07, SW-5a, SW-5b, DD-04, SW-08.

Parameters of them are within limit in comparison with QCVN 10: 2008/BTNMT, (others

column)

Impact of Mong Duong river alignment activities in coastal surface water is monitored by coastal

surface water sampling sites labeled SW-01, SW-03b, SW-04. Parameters of them are almost

within limit in comparison with QCVN 08: 2008/BTNMT, (B2 column.)

Impact of transport activities in coastal surface water is monitored by coastal surface water

sampling sites labeled LG-1, LG-3, LG-4. Parameters of them are within limit in comparison

with QCVN 10: 2008/BTNMT, (others column.)

Change of parameter’s concentration through surveys trend to decrease

Two of water pollution sources are water discharge from coal mining via Mong Duong river and

ships transport coal in the waterway. Spilled coal from ships will dilute element and compound to

coastal water (such as: Fe and Mn). So, decreasing trend may be the result of management and

treatment improving of water discharge from coal mining and the improvement of coal smuggle

management in the waterway.

Almost all tested items of underground water at sampling sites are within limit of the National

technical regulation on underground water quality QCVN09/2008/BTNMT except Cd, Cl-

content and content of microorganisms (Coliform).

Concentrations of chloride (Cl-) beyond permissible limits of National technical regulation on

underground water quality QCVN09:2008/BTNMT at the site PW-03, GW-01-D, GW-08, GW-

09 and GW-11. This is explained that sampling sites are located in the coastal and islands areas

thus they may be saline lightly.

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 49 of 68

Concentration of microorganisms (Coliform) beyond permissible limits of the National technical

regulation on underground water quality QCVN09/2008/BTNMT at the site PW-01, PW-02,

PW-03, PW-04, PW-05, PW-06, PW-08, PW-09. This is explained that water in existing wells

are not usually utilized thus water is not rotated and easy to make condition for microbial

growing.

Following surveys, change of underground water parameters at sampling sites are low and

relative stable.

3.2.5 Recommendation

From the above mentioned results at the monitoring times from January to June 2013, it may be

concluded that the impact of obstacle removal, Mong Duong river alignment and construction

activities to the coastal surface water and underground water is minor.

Contractor should be requested to drill new wells with the depth of 25 - 30m

Maintain the implementation of present measures to minimize environmental pollution.

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 50 of 68

4. AQUACULTURE & FISHERY

4.1 Overview

During the first half of 2013, the Environment Monitoring and Analyzing Centre (EMAC) of

Quang Ninh province carried out two surveys to monitor the aquaculture and fisheries activities

surrounding the project sites such as Thac Thay, De Dach and Mong Duong river and the coastal

area of Cam Hai. A number of methods to collect data and information were applied to assess the

implementation of the EMP requirements and project EIA through fishing activities and aquatic

resources monitoring. The methods included: fact-finding survey, direct interview, interview

through prepared questionnaire, reference method and statistic and comparison methods. In

addition, several meetings and site visits were conducted to gather the data contained in this

report. During the site visits photographs were taken to serve as proof of compliance or non-

compliance and reference documents were copied or photographs of these were also taken.

4.2 Inspection Activities

The inspection team conducted two surveys on aquatic resources and fisheries and aquaculture

activities in Thac Thay, De Dach and Mong Duong rivers and the coastal area of Cam Hai. The

first survey was done on the 22nd March, 2013 and the second one on 9st May, 2013.

Aquatic resources in term of species composition and abundant were poor in Mong Duong and

De Dach rivers. During the surveys, the inspection team observed some small pelagic fish such as

rabbit fish, mullet in De Dach and Mong Duong river at high tide, however there have not been

any large fish or other aquatic species at Mong Duong river at low tide (see pictures). Thus, there

were no fishing activities in these rivers. In both surveys water quality in these rivers was poor

due to the high turbidity of coal debris and clay in the river water. The Mong Duong stream was

narrow and water depth was very low. Thus, the changing of Mong Duong river at the

construction phase have impacted on the water speed and aquatic resources. It is concluded that

Mong Duong and Thac Thay river are environmentally impacted by of coal mining activities.

There were some fishing activities in the river mouth of De Dach and Mong Duong river.

Fishermen collected bivalves and small fish at mangrove forests. Fishing activities in these areas

are stable in capture production and species composition. That is because these areas are not

major fishing grounds and catching methods are simple. In addition, the construction of Mong

Duong 1 power plant may have little impact on the aquatic resources. Number of fishing boats

anchored at De Dach and Mong Duong river mouths were higher in the first survey than in the

second one. The second survey was in the capture season for fishermen, therefore almost every

fishing boat went to Vandon and Co To island for fishing. In addition, the equipment shipments

to the Mong Duong power plant project may have impact on fishing activities, especially by

anchoring the vessels nearby the project site.

Fishing activities were observed in the Thac Thay river, Luonggac and coastal line of Cam Hai

commune in both surveys. In the first survey, it was observed that fishermen are catching fish,

crustacean and mollusc in the Luonggac area. They use small boats to exploit fish or collect

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 51 of 68

mollusk and/or small fish at mangrove forests. In the second survey, we did not observe any

fishing activities in the Luong giac area. It is reported that fishermen went offshore for the South

marine fish exploitation season. The species composition and their abundance were naturally

stable during the surveys due to these areas are quite far away from the Mong Duong power

plant. There were no shrimp culture activities at Cam Hai commune due to loss from the shrimp

disease outbreaks and natural disaster (flooding).

4.3 Overall Assessment Aquaculture and Fishery

Based on the results of the two surveys on the fishing and aquaculture activities in Thac Thay, De

dach and Mong Duong river and along the coastal line of Cam Hai commune from January to

June 2013, it is concluded that:

The Construction phase of Mong Duong 1 power plant has minor impact on the aquatic

resources in the inspected areas

There were no fishing activities in De Dach and Mong Duong river due to heavy

industrial pollution from mining and coal trading. Number of aquatic species and their

components in these areas are limited.

Some fishing activities in the Thac Thay river and Luonggac areas were observed, but

there are no shrimp activities in Cam Hai coastal line due to loss from shrimp disease

outbreak and flooding.

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 52 of 68

Tow

ard

the

ba

nk

5. MANGROVE REFORESTATION MONITORING

5.1 Overview

To compensate the loss of mangrove forest taken by the Project, 52ha of mangrove has been re-

planted in Dong Rui Commune, Tien Yen District, Quang Ninh Province.

5.2 Inspection Activities

A. Content of Inspection:

Inspection of Mangrove development progress (diameter, height, branching off status,

number of leaves, survival rate of mangrove)

Inspection of environment condition for mangrove (climate, hydrography, irrigation

status)

Evaluate the Mangrove’s quality for Acceptance.

B. Methodology:

Sample Selecting Method:

Vertical divide from the mangrove bank toward the coastal with the distance of 300 m.

Select standard pilot 10m x 10m vertical, each standard cell has 300m distance.

Counting the number of mangrove survival to calculate density of plant; measuring the

height and diameter to calculate the average height.

300mToward the

coastal

300m

Figure 5 Method for selection of sample

Standard pilot

10m x 10m

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 53 of 68

C. Inspection Results:

In area of 52ha of mangrove forest which was replanted, there is 95% of plants survival.

Mangroves start branching off.

In Inspection in May, one tree has 12-15 leaves. Mangrove’s distance is 1m x 1m with the

height is about 55 cm.

In Inspection in July, one tree has 13 – 17 leaves with the average height is about 55cm –

65cm

In Inspection in November , we found that each one has 14 – 19 leaves with the average

height is about 55cm – 80cm

Measured Results in July 2013:

The smallest mangrove:

1. Base Diameter: 0.85cm

2. Diameter to branching off point: 0.5cm

The highest mangrove:

1. Base Diameter: 1.3cm

2. Diameter to branching off point: 0.6cm

The average height: 65cm – 90cm

The average of mangrove branching off is 3-4 branches

Number of leaves: average 20 – 25

Average density of plant: 95 mangrove/100m2, 95% of plants survival

The Monitoring and Analyzing results during a period form May 2012 to July 2013 are presented

in Table 19

Table 19 Monitoring and analyzing results

Inspection time Height Leaves Base Diameter:

May 55cm 12-15 0.8 cm

July 55cm-65cm 13-17 1.1 cm

November 65cm-80cm 14-19 1.2 cm

July 2013 65cm- 90cm 20-25 1.3cm

D. Condition of Nature and Environment.

Soil condition: Alluvial soil deposit, the flat topography support the mangrove’s

development.

Water condition: irrigation canal with the distance of 500m, the average depth is 0.8m –

1.0m, and the average width is 1.8m. These conditions will create the moisture to support

mangrove develops well.

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 54 of 68

5.3 Overall Assessment Mangrove Reforestation

Mangrove quality develops well, branching off well.

The natural and environmental conditions support the mangrove’s development.

With the results above, the Mangrove planting project has met the requirement of the EIA

EPC contractor’s construction workers need to be educated during the course of the

safety and environmental trainings on the need to avoid direct and/or indirect disturbance

of the mangroves.

Prohibit dumping of waste in mangrove and forestry areas

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 55 of 68

6. OVERALL CONCLUSIONS AND RECOMMENDATIONS

This chapter is providing the Overall Conclusions and Recommendations of the

Owner/Consultant regarding all health & safety and environmental aspects required to be

implemented by the EPC contractor.

6.1 Health, Safety & Waste Disposal Management

Conclusion

This topic covers Health and Social aspects, Site Safety and Security, Site Waste management

and Soil contamination issues

Generally good overall performance of the EPC contractor’s appointed HSE team with

responsible Environmental Officer (OE) in place

Good site safety management of the EPC contractor with regards to fire safety, plant and

equipment safety, labor safety, worker training before entering site, access gate checks

before entering site etc.

Until now No fatality and No Lost Time accident occurred with an accumulated total

man-hours reaching 5’200’000 as of July 2013

Until now no serious soil issues happened at site. Some small oil spillage occurred but

were treated immediately as per the Contractor’s EMS

Waste management follows the contractor’s EMS by separating waste into different

groups and collected and disposed as per the EMS requirements. Until now there is very

little hazardous waste at site such as oil and chemicals, but in time to come there will be

more of these materials to dispose of

All required permits are in place ie. Permit To Work, Confined Space Entry Permits, Gas

Test Certificates etc.

Checklist are submitted regularly to Project Owner for environmental performance

monitoring program done weekly by EPC contractor

First Aid service available 24/7

Monthly report issued to the Department of Labor Quang Ninh province for labor

movements

The health issue of the labor force is one of the topics that requires close monitoring as

part of the health and safety management plan

Current audit results show that both men and women are well informed of potential

health and safety risks: HIV/AIDS control and prevention activities for both camp

workers and offices

Recommendations:

EPC contractor to submit environmental monitoring reports and check lists to Project

Owner on a regular basis (monthly)

Contractor to inform Project Owner immediately of any incidence occurrence at site

whether it is concerning a vehicle accident, labor accident, fire accident, soil

contamination or other incident not further specified here.

EPC contractor to strictly enforce site safety and warn offenders or in repeat cases

dismiss from site (some recent incidents as shown in the attached pictures do not give a

good impression and need to be corrected)

Newly legislated and/or revised environmental laws shall be examined carefully in order

to determine whether they are required to be implemented during the project execution

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 56 of 68

Contractor to ensure that it complies with the EIA and the requirements specified in

chapter VI of the ADB environmental assessment guidelines, 2003.

Contractor to comply with all relevant local regulations to the project

Contractor shall once every 6 months organize exercises based on likely site scenarios in

which the key site personnel work through their emergency response roles.

Contractor shall periodically review and evaluate the efficiency of the Project EMS in

place

Number of site toilets to be increased as labor force increases

Owner/Consultant to perform regular audits at the contractor’s labor camps especially

with regards to gender issues. (next audit proposed at Licogi’s labor camp)

6.2 Environmental Quality Monitoring

This topic covers Air & Noise and Vibration, Water quality, Aqua culture and Fisheries and

Mangrove reforestation

6.2.1 Air & Noise and Vibration Monitoring

Conclusion

Construction activities at the site of Mong Duong 1 increased over time compared to the

last reporting period commensurate with ongoing progress in the first half of 2013.

Therefore construction activities impacted more on the air environment (dust) and noise

to nearby residential areas then in previous months

The two monitoring stations KK1 and KK2 located at residential areas selected in the

EMP are hardly impacted during the construction phase of Mong Duong 1 thermal power

plant, but may show an impact during the operation phase, particularly from the high

pollution sources (boiler, stack etc.).

Comparing the monitoring results (dust) between the last 6 months of 2012 and the first 6

months of construction phase in 2013, it shows that the first 6 months of 2013 has higher

concentrations of air pollutants than the 6 months before, especially in the 3 months

April, May and June 2013 when the weather was dry, sunny and hot. The increase is

mostly due to increased traffic on the new no.18 and old 18A road likewise.

Recommendations:

On the new no.18 road near the entrance of Mong Duong 1 and Mong Duong 2 power

plants, heavy vehicles travel a lot, so the road is very dirty and dusty. The road needs

regular water spraying to improve the conditions, especially in the dry season. The

appearance of construction waste in nearby vacant land (along the new no.18 road such

as concrete from bored piles and other construction debris needs to be removed and kept

neat and tidy at all times.

Noticeable environmental impact during the reporting period has not only been caused by

pile driving activities, foundation digging, construction and soil conveying, but also due

to social environment changes caused by the gathering of the large work force in the

Mong Duong precinct which causes all sort of problems ie. regarding to services, food

provision etc. These and related problems need to be evaluated in addition and mitigated

as much as possible.

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 57 of 68

6.2.2 Water quality Monitoring

Conclusion

Impact of obstacle removal activities in coastal surface water is monitored by coastal

surface water sampling sites named SW-3a, DD-1, SW-06, SW-07, SW-5a, SW-5b, DD-

04, SW-08. Parameters of them are within limit in comparing with QCVN 10:

2008/BTNMT, (Others column)

Impact of Mong Duong river alignment activities in coastal surface water is monitored by

coastal surface water sampling sites named SW-01, SW-03b, SW-04. Parameters of them

are almost within limit in comparing with QCVN 08: 2008/BTNMT, (B2 column)

Impact of transport activities in coastal surface water is monitored by coastal surface

water sampling sites named LG-1, LG-3, LG-4. Parameters of them are within limit in

comparing with QCVN 10: 2008/BTNMT, (Others column)

Change of parameter’s concentration through surveys trend to decrease

Two of the water pollution sources are water discharged from coal mining via Mong

Duong river and ships transport coal in the waterway. Spilled coal from ships will dilute

elements and compound to coastal waters (such as: Fe and Mn). So, decreasing trend may

be resulted of management and treatment improving of water discharge from coal mining

and the improvement of coal smuggle management in waterway.

Almost all tested items of underground water at the sampling sites are within the limits of

the National technical regulation on underground water quality QCVN09/2008/BTNMT

except Cd, Cl- content and content of microorganisms (Coliform).

Concentrations of chloride (Cl-) beyond permissible limits of the National technical

regulation on underground water quality QCVN09:2008/BTNMT are found at the site

PW-03, GW-01-D, GW-08, GW-09 and GW-11. This is explained by the fact that the

sampling sites are located in the coastal and islands areas, thus they may be saline lightly.

Concentration of microorganisms (Coliform) beyond permissible limits of the National

technical regulation on underground water quality QCVN09/2008/BTNMT are found at

the site PW-01, PW-02, PW-03, PW-04, PW-05, PW-06, PW-08, PW-09. This is

explained by the fact that water in existing wells are not usually utilized thus the water is

not rotated and easy to make condition for microbial growing.

Following surveys, change of underground water parameters at sampling sites are low

and relative stableness.

Recommendations

Contractor should drill two additional wells with a depth of 25 -30m to compensate for

the two that are now covered after the land backfill activity

Maintain implementation of all current measures to minimize environmental pollution of

all surface and underground water resources.

6.2.3 Aquaculture and Fishery Monitoring

Conclusion

Based on the results of the two surveys on fishing and aquaculture activities in Thac Thay, De

Dach and Mong Duong rivers and along the coastal line of Cam Hai commune during the first

half of 2013, it may be concluded that:

The construction phase of Mong Duong 1 power plant has minor impacts on the aquatic

resources in the inspected areas.

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 58 of 68

There were no fishing activities in De Dach and Mong Duong rivers due to heavy

industrial pollution from mining and coal trading. Number of aquatic species and their

components in these areas are very limited.

Some fishing activities in the Thac Thay river and Luong Gac areas were observed but

there are no shrimp activities along Cam Hai coastal line due to loss from shrimp diseases

outbreak and flooding.

Normal fishing activities and aquaculture are observed in the Thac Thay river and along

the coastal line of Cam Hai commune.

Recommendations

Contractor to strictly enforce his solid waste and waste water disposal management plan

and do not permit dumping of any hazardous substances into nearby rivers or sea.

6.2.4 Mangrove Reforestation Monitoring

Conclusion

Mangrove quality develops well, branching off well.

In the allocated area of 52 ha of mangrove forest which was replanted, there is 95%

survival rate of plants

The survey and inspection results of the mangrove reforestation shows that the mangrove

is developing well under the present environmental conditions at the project areas..

The advantage natural and environmental condition support for mangrove’s development.

With the current results, the Mangrove planting project has met the requirement of

ADB’s EIA

Recommendations

Keep protecting and feeding the mangrove to ensure of their good development and

branching off.

Continue with maintenance activities such as tree clearing, weeding and replanting of

failed areas (Using local labors for replanting and protecting mangrove area)

Educate construction workers on the need to avoid direct and indirect disturbance of the

mangroves

Prohibit dumping of waste in mangrove and forestry areas and resource extraction from

mangroves and plantation forestry areas.

Treat the mangrove forest in Dong Rui and Tien Yen as a special use forest, as this needs

4 years taking care (tree clearing, weeding , replanting of failed areas) and protecting.

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 59 of 68

Appendix 1 Environmental Team Organization Chart

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 60 of 68

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 61 of 68

Appendix 2 HSE Organization Chart

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 62 of 68

Appendix 3 Pictures of Air quality and Noise

Construction site Construction site

Monitoring point KK1 at Residential area of Mong

Duong ward

Monitoring point KK2 at Residential area of Mong

Duong ward

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 63 of 68

Appendix 4 Pictures of Water Quality

Monitoring water quality on the River Monitoring water at Residential area

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 64 of 68

Appendix 5 Pictures of Aquaculture and fishery

Collecting coal in Mong Duong River

(The picture is taken from Mong Duong bridge)

Mong Duong river at low tide

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 65 of 68

Appendix 6 Pictures of Mangrove Reforestation

Mangrove Area 1 Mangrove Area 2

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 66 of 68

Appendix 7 Picture of HSE

Traffic control at Mong Duong 1 and 2 Site Entrance Point

Security check at Mong Duong 1 Main gate

Site Safety Training

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 67 of 68

Emergency Case Training

Safety Net installation for Falling Objects Prevention

Gas cylinder, oxygen cylinder do not keep properly,

housekeeping is not good condition (Water

treatment area)

Unsafe Working at height (Unsafe scaffolding,

workers not wearing safety harness) at admin

building area

1st Semi-annual Environmental Monitoring Report 2013

Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 68 of 68

Appendix 8 Picture of Gender

Mess room in LILAMA worker camp Woman employee in construction site office

Health Checkup for employee Toilet for worker in construction site