ere 500mw
TRANSCRIPT
-
7/30/2019 ere 500mw
1/127
E R E C T I O NM A N U A L
STEAM TURBINE500 MW
(KWU DESIGN)
DOCUMENT NO. TS-T1-08
Bharat Heavy Electricals Limited
POWER SECTORTECHNICAL SERVICES (HQ)NOIDA
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 1
-
7/30/2019 ere 500mw
2/127
FOREWORD
I am glad that Power Sector - Technical Services ( Head Quarters),
Noida has brought out this erection manual of 500 MW steam
turbine (KWU design) being produced by BHEL. This manual lays
emphasis on site optimisation techniques which aims at uniform
erection practices, improvement in quality, reduction in time cycle
and saving in cost.
I am sure, this manual will form the basis for site erection activities
so that the organisation can derive full benefit out of this. It is
needless to emphasize that upgrading of technology is a continuous
process and we have to review our methods of working and make
suitable changes, wherever required.
(K P Mathur)New Delhi Executive Director(PEM & TS)
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 2
-
7/30/2019 ere 500mw
3/127
-
7/30/2019 ere 500mw
4/127
1 TECHNICAL DATA T 1- 08-0101G
2 INSTRUCTION FOR HANDLING ANDSTORAGE OF TURBINE
T 1-08-0202G
3 ERECTION SEQUENCE T 1-08-0303G
4 ERECTION PROCEDURE T 1-08-0404G
5 GROUTING PROCEDURE T 1- 08-0505G
6 ASSEMBLY OF IP MODULE AT SITE T 1-08-0606G
7 SEALING AND ANTISEIZING COMPOUNDS T 1-08-0707G
8 CRITICAL ACTIVITIES T 1-08-0808G
9 SPRING LOADED FOUNDATION T 1- 08-0909G
10 ERECTION OF PIPING T 1-08-1010G
11 SPECIFICATION FOR GAS HEATING DEVICE T 1-08-1111G
12 SPECIFICATION FOR BREECH NUT HEATINGDEVICE
T 1-08-1212G
13 SPECIFICATION FOR THERMAL INSULATION T1-08-1313 G
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 4
-
7/30/2019 ere 500mw
5/127
The following codification system is used for numbering of instructions and thecodification of Log Sheets is as per FQA document.
XX X - XX XX XX XAlpha Numeric Numeric Numeric Numeric Alpha
Type ofInstruction
System Instruction No
System Designation
Rating of Main Equipment
Type of Manual
Product Code
1.1 PRODUCT CODE
B Boiler
BA Boiler Aux.
T Turbine
TA Turbine Aux.
G Generator
GA Generator Aux
P Power Plant Piping
CI C&I
1.2 TYPE OF MANUAL
1 Erection
2 Commissioning
3 Service
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 5
-
7/30/2019 ere 500mw
6/127
1.3 RATING OF MAIN EQUIPMENT
01 200/210 MW
02 120 MW
03 110 MW
04 60 MW
05 30 MW
06 100 MW
07 235 MW
08 500 MW KWU Design
09 210 MW KWU Design
10 120 MW KWU Design
11 60 MW KWU Design
12 70 MW KWU Design
13 Industrial Units
14 210 MW Tower Type Concrete Pylem
15 210 MW Tower Type Steel Structure
16 500 MW Tower Type Once through
17 250 MW
18 CCP
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 6
-
7/30/2019 ere 500mw
7/127
1.4 SYSTEM DESIGNATION
SNO DESCRIPTION
1. TECHNICAL DATA
2. INSTRUCTION FOR HANDLING AND STORAGEOF TURBINE
3. ERECTION SEQUENCE
4. ERECTION PROCEDURE
5. GROUTING PROCEDURE
6. ASSEMBLY OF IP MODULE AT SITE
7. SEALING AND ANTISEIZING COMPOUNDS
8. CRITICAL ACTIVITIES
9. SPRING LOADED FOUNDATION
10. ERECTION OF PIPING
11. SPECIFICATION FOR GAS HEATING DEVICE
12. SPECIFICATION FOR BREECH NUT HEATINGDEVICE
13. SPECIFICATION FOR THERMAL INSULATION
1.5 TYPE OF INSTRUCTION
G General
T Technical
L Log Sheet
C Check List
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 7
-
7/30/2019 ere 500mw
8/127
LOAD
RATED 500 MW
MAX. UNDER VALVE WIDE OPEN (VWO) CONDITION 524.2
CONSTRUCTION
THREE CYLINDER REHEAT CONDENSING TURBINE 500 MW
SINGLE FLOW HP TURBINE WITH 17 REACTION STAGES TYPE H30-100-2
DOUBLE FLOW IP TURBINE WITH 12 REACTION STAGES PERFLOW
TYPE M30-63
DOUBLE FLOW LP TURBINE WITH 6 REACTION STAGES PERFLOW
TYPE N30-2X10
2 MAIN STOP AND CONTROL VALVES TYPE EV320-1
2 REHEAT STOP AND CONTROL VALVES TYPE IV560
1 SWING CHECK VALVE IN COLD REHEAT LINEMAKE
DN-800BHEL,TIRUCHY
2 BYPASS STOP AND CONTROL VALVES DN-320
EXTRACTION SWING CHECK VALVES :
EXTRACTION-1 : NO VALVE -
EXTRACTION-2 : 1 SWING CHECK VALVE WITH ACTUATORMAKE
DN-800BHEL,TIRUCHY
EXTRACTION-3 : 1 SWING CHECK VALVE WITH ACTUATOR&1 SWING CHECK VALVE WITHOUTACTUATOR
MAKEDN-500
BHEL,TIRUCHY
EXTRACTION-4.1 : 2 SWING CHECK VALVE WITH ACTUATORMAKE
DN-500BHEL,TIRUCHY
EXTRACTION-4.2 : 2 SWING CHECK VALVE WITH ACTUATORMAKE
DN-500BHEL,TIRUCHY
EXTRACTION-5 : 1 SWING CHECK VALVE WITH ACTUATOR&1 SWING CHECK VALVE WITHOUT ACTUATOR
MAKEDN-400
BHEL,TIRUCHY
EXTRACTION-6 : NO VALVE
SPEED
RATED SPEED 50.0 /S
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 8
-
7/30/2019 ere 500mw
9/127
SPEED LIMITATION IN LOAD & STATION AUX. LOADOPERATION
MAX. SPEED, NO TIME LIMITATIONMIN. SPEED, NO TIME LIMITATION
PERMISSIBLE FOR A MAXIMUM OF 2 HRS. DURING THE LIFE OF
LP BLADING SPEEDBELOW
SPEEDABOVE
::
:
:
524.251.5 /S47.5 /S
47.5 /S
51.5 TO 60 /S
SPEED EXECUTION RANGE AT OPERATION WITHOUT LOAD* : 6.7 TO 47.5 /S
STANDARD OVER SPEED TRIP SETTING : MAX. 55.5 /s
* THIS SPEED RANGE SHOULD BE PASSED THROUGH IN ONE
SMOOTH OPERATION TO AVOID ENDANGERING THEBLADES DUE TO RESONANCE
STEAM PRESSURES
RATED* LONG TIMEOPERATION
SHORT TIMEOPERATION
INITIAL STEAM 166.7 166.7 20.7 BAR
BEFORE 1st HP DRUM STAGE 154.4 163.4 169.9 BAR
HP CYLINDER EXHAUST 44.9 52.0 57.4** BAR
IP CYLINDER STOP VALVE INLET 40.3 46.7 55.2** BAR
EXTRACTION 6 44.9 52.0 57.4 BAR
EXTRACTION 5 17.5 22.2 22.2 BAR
EXTRACTION 4 7.2 8.7 8.7 BAR
EXTRACTION 3 2.58 3.2 3.2 BAR
EXTRACTION 2 1.329 1.66 1.66 BAR
EXTRACTION 1 0.257 0.41 0.41 BAR
LP CYLINDER EXHAUST 0.1013 0.3 0.3 BAR
* THESE VALUES CORRESPOND TO 500 MW LOAD WITH 3% MAKE-UP AND 0.1013 BAR BACKPRESSURE WITH ALL HEATERS IN SERVICE AND RATED STEAM CONDITIONS.
** THE SAFETY VALVES MUST BE SET SO THAT THESE SHORT TIME VALUES ARE NOT EXCEEDED.
LONG TIME OPERATION : UPPER LIMIT VALUE, PERMISSIBLE WITHOUT TIME LIMIT.
SHORT TIME OPERATION : PERMISSIBLE MOMENTARY VALUE. THE AGGREGATE DURATION OFSUCH SWINGS MUST NOT EXCEED 12 HOURS IN ANY ONE YEAR.
ALL PRESSURES ARE ABSOLUTE PRESSURES
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 9
-
7/30/2019 ere 500mw
10/127
LOW VACUUM TRIP, STANDARD SETTING
HYDRAULIC LOW VACUUM TRIP : 0.3 BAR
ELECTRICAL LOW VACUUM TRIP : 0.3 BAR
HYDRAULIC LOW VACUUM TRIP BYPASS OPERATION : 0.6 BAR
SEAL STEAM SUPPLY SYSTEM
PRESSURE IN SEAL STEAM HEADER (ABOVE ATMOSPHERIC) : 35 MBAR
AXIAL SHIFT
ALARM TRIP
* 0.5 mm * 1 mm
* DIRECTION OF ROTATIONANTI CLOCK WISE WHEN VIEWED FROM FRONT PEDESTAL TOWARDS THEGENERATOR
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 10
-
7/30/2019 ere 500mw
11/127
STEAM TEMPERATURES
RATED
VAL.ANNUAL
MEAN
VALUE
LONG TIME
VALUE(WITHINANNUAL
MEANVAL.)
400 h
PERANNUM
80 h PER
ANNUMMAX. 15
MIN IN
INDIVIDUAL CASE
INITIAL STEAM 536.0 546.O 552.O 566.0OC
IP CYLINDER STOP VALVE INLET 536.0 546.3 552.0 566.0OC
RATEDVALVE *
LONGTIME
OPERATI
ON
80 h PERANNUM
MAX. 15
MIN ININDIVIDUAL CASE
INSPECIALCASES
AT NOLOAD
HP CYLINDER EXHAUST 340.0 360.0 440.0 500.0**OC
EXTRACTION 6 340.0 360.0 440.0 500.0**OC
EXTRACTION 5 413.9 421.9 459.9OC
EXTRACTION 4 292.1 304.1 346.4OC
EXTRACTION 3 187.3 195.3 242.3OC
EXTRACTION 2 128.3 139.3 184.3OC
EXTRACTION 1 66.5 86.5 136.5OC
LP CYLINDER EXHAUST 46.1 70.0 70.0OC
LONG TIME OPERATION : UPPER LIMIT VALUE, PERMISSIBLE WITHOUT TIMELIMIT.
* THESE VALUES CORRESPOND TO 500 MW LOAD WITH 3% MAKE-UP AND 0.1013 BARBACK PRESSURE WITH ALL HEATERS IN SERVICE AND RATED STEAM
CONDITIONS.
** ONLY VALID FOR THE NO LOAD PERIOD WITH HIGH REHEAT PRESSURE AFTERTRIP-OUT FROM FULL LOAD OPERATION. FOR INDIVIDUAL CASE APPROX. 15MINUTES
THE TURBINE IS IMMEDIATELY RE-LOADED OR THE BOILER IMMEDIATELYREDUCED TO MINIMUM LOAD IF NO LOAD OPERATION IS MAINTAINED.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 11
-
7/30/2019 ere 500mw
12/127
CASING TEMPERATURES
WALL TEMPERATURES ALARMAT
MACHINE MUST BESHUT DOWN AT
HP TURBINE CASING EXHAUST 480 500OC
OUTER CASING OF LP CYLINDER 90 110OC
PERMISSIBLE DIFFERENTIAL TEMP. BETWEEN PARALLEL STEAM SUPPLY LINES :
NO TIME LIMITATION : 17OC
SHORT TIME PERIOD (15 MIN.) : 28OC
IN THE HOTTEST LINE THE LIMITATIONS INDICATED FOR INITIAL STEAM & REHEAT TEMP. MUST NOT BE EXCEEDED.
SPRAY WATER TO LP TURBINE MUST BE SWITCHED ON AT 90O
C.
TEMPERATURES DIFFERENCE ALARMAT
MACHINE MUST BE
SHUT DOWN AT
DIFFERENCE BETWEEN UPPER & LOWERCASING HALVES HP TURBINE. MIDDLE
* 90 * 100 OC
LP TURBINE. FRONT * 30 * 45OC
LP TURBINE. REAR * 30 * 45OC
FEEDWATER HEATER OUT OF SERVICE
OPERATION WITH FEEDWATER HEATER OUT OF SERVICE MAIN STEAMFLOW Kg/s
LOADMW
EXTRACTION A6 = 0 395 500
EXTRACTION A5 = 0 421 500
EXTRACTION A3 = 0 423 500
EXTRACTION A2 = 0 425 500
EXTRACTION A1 = 0 423 500
EXTRACTION A6, A5 = 0 400 525
OUTPUT LIMIT DURING TESTING WITH AUTOMATIC TURBINE TESTER
TESTING OF MAIN STEAM STOP & CONTROL VALVE 400 M W
TESTING OF HRH STEAM STOP & CONTROL VALVE 200 - 500 M W
MOTORING :
MOTORING IS THE CONDITION IN WHICH THE TURBINE IS DRIVEN BY THE GENERATOR ATRATED SPEED WITH THE STOP & CONTROL VALVES CLOSED. IN THIS OPERATING MODE,CERTAIN TURBINE COMPONENTS ARE HEATED UP BY WINDAGE POWER IN THE BLADING.TO PREVENT HEAT-UP BEYOND PERMISSIBLE TEMPERATURES, MOTORING MUST NOT BEALLOWED TO CONTINUE FOR LONGER THAN ONE MINUTE. IF THE CONDENSER LOWVACUUM LIMIT OF 0.3 BAR IS EXCEEDED, MOTORING MUST NOT BE ALLOWED TO CONTINUEFOR MORE THAN 4 SECONDS.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 12
-
7/30/2019 ere 500mw
13/127
BEARING TEMPERATURES
ALARMAT
MACHINE MUST BE
SHUT DOWN AT
OPERATION TEMPERATURE BELOW 75OC 90 120
OC
OPERATION TEMPERATURE 75 TO 85OC 100 120
OC
OPERATION TEMPERATURE 85 TO 90OC 110 120
OC
OPERATION TEMPERATURE ABOVE 90OC 115 120
OC
VIBRATION
ABSOLUTE BEARINGHOUSING VIBRATION
ABSOLUTE SHAFTVIBRATION
STANDARD ALARM SETTING 30 m ABOVENORMAL LEVEL*
m
MAXIMUM ALARM SETTING 35 120 m
LIMIT VALUE FOR TRIPPING 45 200 m
* THE NORMAL LEVEL IS REPRODUCIBLE VIBRATIONAL BEHAVIOUR TYPICAL FOR THE MACHINE ANDDEPENDENT ON THE OPERATING CONDITIONS, VIBRATION READINGS INDICATED IN CONTROLROOM ARE HALF PEAK. THE ABOVE VALUES ARE ALSO GIVEN IN HALF PEAK.
WEIGHTS
HP TURBINE, COMPLETELY ASSEMBLED : 94.6 T
IP TURBINE. TOP HALF OUTER CASING : 25.7 T
IP TURBINE, TOP HALF INNER CASING, COMPLETE WITH BLADING : 15.5 T
LP TURBINE. TOP HALF OUTER CASING COMPLETE : 42.6 T
LP CYLINDER, TOP HALF OUTER SHELL OF INNER CASING, COMPLETEWITH BLADING, STATIONARY BLADE CARRIERS & DIFFUSER
: 38.5 T
HP TURBINE ROTOR, COMPLETE WITH BLADING : 16.3 T
IP TURBINE ROTOR, COMPLETE WITH BLADING : 23.1 T
LP TURBINE ROTOR, COMPLETE WITH BLADING : 85.8 T
MAIN STOP & CONTROL VALVE, COMPLETE WITH SERVO MOTORS,
WITHOUT BEND & PIPE SECTION
: 20.9 T
REHEAT STOP & CONTROL VALVE, COMPLETE WITH SERVOMOTORS, WITHOUT BEND & PIPE SECTION
: 32.2 T
ALL WEIGHTS HAVE BEEN CALCULATED WITH SAFETY ALLOWANCES. SLINGSCHOSEN MUST PROVIDE SUFFICIENT SECURITY.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 13
-
7/30/2019 ere 500mw
14/127
OIL SUPPLY
MAIN OIL TANK, RATED CAPACITY : 25/40 Cu . M
Ist OIL FILLING (ESTIMATED) : 47.5 Cu . M
FLUSHING OIL QUANTITY (ESTIMATED) : 28.5 Cu . M
OIL COOLER FOR OPERATION, NUMBER : 1 NO.
OIL COOLER FOR RESERVE, NUMBER : I NO.
OIL TEMP. AT COOLER OUTLET, UNIT IN OPERATION
MIN.NORMALMAX.
:::
384547
OC
OIL TEMP. AT COOLER OUTLET, UNIT SHUT DOWNMAX. : 75
OC
TEMP. RISE OF OIL IN BEARINGSNORMAL
MAX.
::
2025
OC
ESTIMATED OIL REQUIREMENTS OF BEARINGS :
BEARING 1(HP TURBINE, FRONT PEDESTAL) : 0.8 dm3/S
BEARING 2 : 15.4 dm3/S
BEARING 3 : 4.1 dm3/S
BEARING 4 : 8.6 dm3/S
GENERATOR FRONT BEARING : 7.92 dm3/S
GENERATOR REAR BEARING : 7.92 dm3/S
EXCITER BEARING : 0.70 dm3/S
1 DUPLEX OIL FILTER FOR BEARING OIL (FULL FLOW) : 200 mm
DUPLEX OIL FILTER . TYPE - 2.62.9. SIZE 355/750. MAKE : BOLL & KIRCH
FILTRATION PARTICLE SIZE OF DUPLEX FILTER ELEMENT : 37 m
FILTRATION PARTICLE SIZE OF MAIN OIL TANK FILTERELEMENT
: 250 m
SAFETY VALVE IN JACKING OIL SYSTEM, SETTING
MAX.
: 200 BAR
PRESSURE LIMITING VALVE IN JACKING OIL SYSTEM,SETTING
: 100 BAR
1 DUPLEX OIL FILTER FOR JACKING OIL : 25 mm
FILTRATION PARTICLE SIZE OF JACKING OIL FILTER : 37 m
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 14
-
7/30/2019 ere 500mw
15/127
OIL PUMPS
MAIN OILPUMP
AUXILIARYOIL PUMP
DCEMERGENCY
OIL PUMP
JACKINGOIL PUMP
QUANTITY 1 2 1 AC : 2 DC : 1
MAKER BHEL KSB KSB TUSHAKO
TYPE 97.22 dm3/S ETA-150-
50VVLETA-100-
33VVLSDF80
CAPACITY(RATED)
75 89.25 30 1.53 dm3/s
DISCHARGE
PRESSURE(GAUGE)
8.6 6.2 2.3 178 BAR
SPEED 50 24.75 24.3 49.42 /s
DRIVE TURBINE AC MOTOR DC MOTOR ACMOTOR
DCMOTOR
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 15
-
7/30/2019 ere 500mw
16/127
CONTROL FLUID SUPPLY
CONTROL FLUID TANK, RATED CAPACITY : 10/16 Cu . M
Ist FLUID FILLING (ESTIMATED) : 15 Cu . M
FLUSHING FLUID QUANTITY (ESTIMATED) : 10 Cu . M
CONTROL FLUID COOLER FOR OPERATION, NUMBER : 1 NO.
CONTROL FLUID COOLER FOR RESERVE, NUMBER : I NO.
CONTROL FLUID MAINTENANCE EQUIPMENT :
GEAR PUMPMANUFACTURER
TYPE
::
STEIMELBGK 2-24R
FLUID FLOW : 0.28 dm3/S
GAUGE PRESSURE : 3.06 at
SPEED : 25 S-1
MOTOR POWER : 0.75 KW
2 EARTH FILTERS
MANUFACTURERTYPE
::
ROTRINGPYG5-350
EARTH FILLING MESH : 140 Kg
1 FINE MESH FILTERMANUFACTURER
TYPE
::
ROTRINGS-1800-14-TUY
FILTRATION PARTICLE SIZE : 3-5 m
FILTER MATERIAL : COTTON
CONTROL FLUID SUPPLY SYSTEM
A FIRE RESISTANT FLUID IS USED FOR THE CONTROL SYSTEM
SCOPE
The document covers all steam turbine components and provides the handling,inspection and storage instructions for large steam turbine components at site.A strict adherence to these instructions is necessary to avoid damages duringhandling and storage at site.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 16
-
7/30/2019 ere 500mw
17/127
HANDLING OF EQUIPMENT :
In any kind of rigging work it is necessary to strictly observe the safety precautions,since even the slightest negligence and non observance of the rules may result
in accidents, which may cause damage to equipment or injury to men.
The site for the rigging work involving lifting and conveying of loads should be welllighted. The loads must not be lifted unless the crane operator can see clearlythe signals given by the rigger.
The positions where the slings are to be put, are marked on the packages and onthe drawings. While lifting/handling these packages/equipment, the slingsshould only be put at the proper places.
The slings of the proper sizes and lengths should only be used for handling theequipment/packages. The angle between the two arms of the sling at the
crane hook should be small (depending upon the dia of the sling) so as to haveproper loading of the sling.
The turbine rotors and cylinder covers (in assembled condition are lifted by theuse of special lifting devices supplied by BHEL. The use of these liftingdevices facilitates correct slinging and maintain horizontal position of thecomponents. These devices, after use, should be properly stored andconserved so as to ensure that they do not get damaged during storage.Before using them, they should be thoroughly inspected.
The work related to handling of the loads (packages or equipment) by crane or byother hoisting mechanism should be entrusted to trained riggers only. If
the rigger/operator is not sure of the weight of the item/package (load) tobe handled, he must ask for the required information before handling theequipment.
The rigger and the crane operator should see that the hook and the ropes of thecrane occupy vertical position, before hoisting the load. Dragging of the loadby slanting ropes is not allowed. The center of gravity of the load should bealigned with the vertical axis of the crane hook.
The eye bolts, 'D' shackles, turn buckles, and wire ropes of suitable sizes shouldonly be used for handling of the equipment. Before using, they should be
thoroughly inspected to their full threads, so as to avoid any chance ofslipping then the load comes on them.
Before giving a signal to lift the load, the rigger must check and ensure that there areno loose parts or tools on the load, which might fall during lifting. Then the loadmust be lifted 100 or 200 mm high for checking the uniformity of slingtensioning and reliability of lashing. If it is necessary to rearrange the slinglengths, the load must be lowered and then the slings rearranged.
Before horizontal conveyance of the load the rigger must see that the load has beenlifted to a height at least 0.5 M above the tallest object, on the path of the load.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 17
-
7/30/2019 ere 500mw
18/127
While the load is being conveyed, the rigger must accompany it and seethat it is not moved above any person. Prior to lowering the load the riggershould examine the ground on which the load will be, lowered and make surethat these is no risk of falling or slipping of the load.
If any one of the personnel present during lifting or lowering of the load detects some
defect of the crane or sling of notices some conditions jeopardizing the lifting orlowering operation, he must give a signal for emergency grounding of thepackage or components.
Smooth lifting and transportation of equipment must be ensured. Shocks and jerksshould be avoided.
All lifting devices, slings must be properly conserved after use and periodicallyinspected and tested.
In the turbines having diaphragms, it is prohibited to handle diaphragms by puttingslings in between the blades. For handling the welded diaphragms, special
lifting devices is supplied by BHEL and the cast diaphragms are handledby putting the eye bolts, for which the provision of threads holes have beenmade in the diaphragms.
While handling the bearings, it is prohibited to put the sling across the rabbit surface ofthe bearings. Threaded holes have been provided; in which the eye bolts haveto be put for handling of the bearings.
While handling the cylinders, it must be ensured that the slings or any other materialdoes not get rubbed at their horizontal and vertical parting planes or at anyother machined surface.
The handling of the long components such as longitudinal girder, endwall etc. shouldbe done with extra care. When they are placed on the floor, in addition to theend supports, few extra supports at the intermediate positions must be provided.
While handling LP rotor with free standing blades, care must be taken to ensure that noforce is exerted on the free standing blades to avoid collapsing of clampingpieces under blade root.
MARKINGS ON PACKING CASES
Various symbols are marked on the packing cases as per 0456.001 to facilitatestorage and handling of the crates and protection of equipment inside.
INSPECTION
Before storing the equipment it should be opened for visual examination or theinternal packing, protective coating and condition of the equipment. Anydamage to packing and conservation should be immediately rectified.
It is necessary to carryout first inspection within three weeks of arrival of theconsignment. Thereafter, all the equipment should be inspected once in everythree months to insure that the conservation is intact. During rainy season, theinspection should be done once in a month. At any time, if any original
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 18
-
7/30/2019 ere 500mw
19/127
conservation is found damaged, it should be reconserved as per relevantconservation instructions No. ST 33004.
While inspecting the packages containing rotors, special care should be taken to checkthe journals. In case of slightest sign of pitting on the journals and thrustcollar, immediate steps for rectification should be taken and equipment
reconserved as per relevant conservation instructions.
STORAGE
All steam turbine equipment should be accommodated in the designated place ofstorage immediately after arrival at destination. This is very essential particularlyduring the rainy season.
Store houses fall into the following categories
TYPE OF CONDITIONSSTOREHOUSE
TEMP. RELATIVEHUMIDITY
ARRANGEMENT
'P' +50 Cto
500 C
< 70 % Totally enclosed, rain proof, ventilatedand dry with cemented floor.
'Q' upto500 C
- Roofed area with walls (of brick /asbestos/ GI sheet ) around and
cemented / pucca hard floor.
'R' - - Raised platform with shed of asbestos /GI sheet / water proof tarapaulin.
'S' - - Raised Platform.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 19
-
7/30/2019 ere 500mw
20/127
The platforms and store-houses should be built up in conformity with the fireprevention rules and standards. Complete storage area especially the R & Scatagory must be adequately fenced & protected against theft & pilferage.
These store houses and areas around them should have proper drainage facility forthe sub-soil, surface and rain water. The water should not be allowed to stand
or get accumulated in these areas, especially where the material has beenstored.
Store house should be provided with proper ventilation facilities.
Level should be maintained for all the packages and equipment and should beuniformly supported to avoid distortion. The long packages should besupported at intermediate places also, so as to avoid sagging during storage.
Store houses should preferably be equipped with proper lifting devices to ensurenormal handling of equipment.
Small and medium size parts can be kept on shelves with proper identification tags.
Packages upto 5 tones can be placed on upon the other upto 2.5m in height usingrequired number of wooden spacers 50 mm thick. In doing so, lighterpackages would be laid upon heavier once to avoid any damage to lowerpackages.
Articles weighing more than 5 tones should be laid in a single tier.
For heavier components under Q, the roof/walls may be constructed/fabricated afterplacement of the component on cemented/pucca hard floor.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 20
-
7/30/2019 ere 500mw
21/127
STORAGE OF STEAM TURBINE COMPONENTS
SNO. DESCRIPTION OF THE COMPONENT TYPE OFSTORAGE
1. FOUNDATION BOLT Q
2. EMBEDDED PARTS (ADDITIONAL) R
3. COMPONENTS OF BASE PLATE ASSLY. Q
4. BASE PLATE LP CASING R
5. LP OUTER CASIONG R
6. LONGITUDINAL GIRDER (LEFT & RIGHT) R
7. LP FRONT WALL (TS&GS) R
8. LP SHAFT SEALING (FRONT & REAR) Q
9. AUXILIARIES OF TURBINE Q
10. HP/IP BEARING PEDESTAL Q
11. HP/IP BEARING PEDESTAL ASSEMBLY PARTS Q
12. IP/LP PEDESTAL ASSEMBLY Q
13. LP/GEN. PEDESTAL Q
14. BEARING PEDESTAL PARTS Q
15. FRONT BEARING PEDESTAL Q
16. LIFTING BEAM R
17. LP CASING EXTRACTION A1 R
18. LP EXTRACTION A2 R
19. LP EXTRACTION A3 R
20. LP EXTRACTION PIPE SHEATHING R
21. INNER GUIDE PLATE DIFFUSER R
22. DIFFUSER (UPPER & LOWER HALVES) R
23. LP INNER-OUTER CASING (VH) Q
24. LP INNER CASING ASSEMBLY (LH & VH) Q
25. HEATING DEVICE Q
26. LP CASING ASSEMBLY Q
27. LP INNER CASING ASSEMBLY (FASTENER) Q
28. INNER GUIDE PLATE DIFFUSER (GS) R
29. LP ROTOR Q
30. IP TURBINE Q
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 21
-
7/30/2019 ere 500mw
22/127
31. IP TURBINE PARTS Q
32. IP INLET PIPES Q
33. HP TURBINE Q
34. HP INLET ASSEMBLY Q
35. HP EXHAUST ELBOW Q
36. HPT RELATED PARTS Q
37. FRAME FOR SUSPENSION (ESV) R
38. SUSPENSION OF VALVE (ESV) Q
39. ESV & CV CASING WITH VALVE Q
40. ESV SERVOMOTORS WITH LIMIT SWITCH Q
41. HP CONTROL VALVE SERVOMOTORS Q
42. SUSPENSION OF VALVE (IV) Q
43. IV & CV CASING WITH VALVE Q
44. IV SERVOMOTORS WITH LIMIT SWITCH Q
45. IP CONTROL VALVE SERVOMOTORS Q
46. FRAME FOR SUSPENSION (IV) R
47. IV SERVOMOTORS WITH LIMIT SWITCH Q
48. STEAM BLOWING & HYD. TEST DEVICE Q
49. TOOLS FOR GOVERNING SYSTEM Q
50. SUSPENSION OF LPB VALVE Q
51. WATER INJECTION VALVES Q
52. CHEST LPB WITH STOP & CONTROL VALVE q
53. LPB STOP VALVE SERVOMOTOR Q
54. LPB CONTROL VALVES SERVOMOTORS Q
55. INJR. FOR SUCTION PIPE NB 350 R
56. INJR. FOR SUCTION PIPE NB 300 R
57. MAIN OIL TANK R
58. MAIN OIL TANK & NOZZLE ASSEMBLY R
59. OIL STRAINER Q
60. LEVEL MONITOR INSTALLATION Q
61. INSTRUMENTS Q
62. LEAKAGE / DIRTY FLUID TANK R
63. VARIABLE ORIFICES & THROTTLE Q
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 22
-
7/30/2019 ere 500mw
23/127
64. CONTROL FLUID TANK R
65. CONTROL FLUID TANK NOZZLE ARRANGEMENT R
66. EXPANSION TANK R
67. FILTER & PR. DAMPING DEVICES Q
68. CROSS AROUND PIPE R
69. SUPPORT FOR CAP R
70. CHANGE OVER VALVE R
71. RATING & MONOGRAM PLATES Q
72. OIL STRIPER R
73. HOUSING FOR HRH STEAM STRAINER R
74. HOUSING FOR MAIN STEAM STRAINER R
75. MS & HRH STR.HSG GASKET Q
76. STEAM STRAINER MS Q
77. STEAM STRAINER HRH Q
78. COMPENSATOR Q
79. TURBINE CONTROL LPB / SUPPLY RACK Q
80. TEMPERATURE & PRESSURE CONNECTIONS Q
81. PR. TRANSMITTERS BAR. PROBES THERMOCOUPLES Q
82. TRANSMITTERS & JUNCTION BOXES Q
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 23
-
7/30/2019 ere 500mw
24/127
STORAGE & PRESERVATION OF COMPONENTS OFTURBOGENERATOR, EXCITER AND SYSTEMS
SNO. DESCRIPTION OF THE COMPONENT TYPE OFSTORAGE
1. EMBEDDED PARTS R
2. FOUNDATION PARTS R
3. WOUND STATOR WITH GAS COOLERS Q
4. TURNION FOOT PLATES Q
5. ROTOR Q
6. ASSEMBLY OF PIPE CONTROL FOR GAS COOLERS R
7. END SHIELDS Q
8. FAN SHIELD, GEN VVIEW HEADER ASSEMBLY R
9. TERMINAL BUSHING AND HEADER ASSEMBLY Q
10. BEARING WITH BRUSH GEAR Q
11. SEAL BODY Q12. TEMP. CONNECTION Q
13. CASING FOR TURNIONS R
14. ERECTION MATERIALS Q
15. ERECTION DEVICES R
16. SHAFT SEALS Q
17. SEAL RINGS Q
18. ADOPTING RING Q
19. AUXILIARY BEARING Q
20. CENTRIFUGAL FAN Q
21. CARBON DIOXIDE VAPOURISER Q
22. FILTER O.C.P. Q
23. EXPANSION TANK R
24. OIL SEPARATOR R
25. PRE CHAMBER R
26. S.O.S.T. R
27. SEAL OIL UNIT Q
28. HYDROGEN DISTRIBUTION R
29. CARBON DIOXIDE DISTRIBUTION R
30. VALVES FOR AUXILIARY SYSTEMS P
31. GAS UNITS Q
32. FLEXIBLE LEADS Q
STORAGE & PRESERVATION OF COMPONENTS OFHEAT EXCHANGERS
SNO. DESCRIPTION OF THE COMPONENT TYPE OFSTORAGE
PRODUCT : CONDENSER
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 24
-
7/30/2019 ere 500mw
25/127
1. BOTTOM PLATE S
2. LOWER DOM WALL S
3. SIDE WALL S
4. WATER CHAMBER Q
5. UPPER DOM WALL S
6. STIFFENING PIPES S7. STIFFENING RODS S
8. TUBE SUPPORT PLATE R
9. WATER BOX R
10. AIR EXTRACTION PIPING R
11. HOTWELL S
12. SPRING ELEMENTS R
13. LOOSE ITEMS Q
14. INSTRUMENTS Q
15. CONDENSER TUBES (STAINLESS STEEL) R
16. CONDENSER TUBES (NON-FERROUS) Q
17. VACUUM PUMP Q18. EJECTOR R
19. AIR MEASURING DEVICE Q
PRODUCT : HEATER
1. GLAND STEAM CONDENSER R
2. STAND PIPE Q
3. INSTRUMENTS Q
4. DRAIN COOLER R
5. L.P.HEATERS R
PRODUCT : COOLER1. OIL COOLER R
2. CONTROL FLUID COOLER R
3. STATOR WATER COOLER R
4. HYDROGEN COOLER Q
5. EXCITER AIR COOLER Q
6. INSTRUMENTS / LOOSE ITEM Q
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 25
-
7/30/2019 ere 500mw
26/127
MAXIMUM PERMISSIBLE LOADING FOR WIRE ROPES IN KG.
NOMINAL SINGLE DOUBLE CORD WITH INCLUDED ANGLE OFDIA (d) OF
ROPES mm
CORD
0o
45o
90o
120o
9 522 1044 965 738 522
12 1170 2340 2070 1580 1170
18 2150 4300 4000 3060 2150
24 3850 7700 2100 5400 3850
30 6200 12400 11500 8800 6200
36 9000 18000 16600 12700 9000
42 12200 24400 22600 17300 12200
48 16000 32000 29500 22600 16000
54 20200 40400 37300 28500 20200
60 24900 49800 46000 35200 24900
66 30100 60200 55700 42600 30100
72 35800 71600 66200 50700 35800
78 42100 84200 77700 59500 42100
84 48800 97600 90200 69000 48800
90 56000 112000 103500 79200 56000
96 63700 127400 117700 90000 63700
102 71900 143800 132900 101700 71900
108 81000 162000 149700 114500 81000
114 89900 179800 166100 127100 89900
120 99700 199400 184300 141100 99700
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 26
-
7/30/2019 ere 500mw
27/127
ERECTION SEQUENCE
(For 500 MW Fixed pedestal type Turbine with spring loaded foundation)
1. Cleaning and checking of Turbine and Generator foundations as per the transverse
and longitudinal axis including their elevation.
2. Prepare and install LP base plates, HP front pedestal, HP rear pedestal, LP front
pedestal, LP rear pedestal along with their anchor bolts and anchor plates.
3. Provisionally align and level all the pedestal and LP base plates as per the
transverse and longitudinal axis including their elevation.
4. Matching of anchor plates of pedestal and LP base plates to ensure their perfect
seating.
5. Finally align and level HP front, HP rear, LP front and LP rear pedestals along with
LP base plates as per the transverse and longitudinal axis including their elevation
and catenary as per the design.
6. Prepare and install steel bars for LP casing centralising keys in foundation slab as
per the required center line .
7. Weld locating ring of LP front pedestal and steel bars of LP front and LP rear
centralising keys.
8. Prepare shuttering and grouting of the pedestals and LP base plates including
anchor plates of HP rear pedestal.
9. Prepare, install, align/ level both the LP girder along with their carrier plates.
10. Prepare , install and assemble LP front and rear end walls with the LP girders.
11. Level / align LP outer casing lower half as per the transverse and longitudinal axis
of the machine.
12. Install permanent packers of LP outer casing including their radial and axial keys.
13. Prepare and install LP inner outer casing along with gusset plates in position
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 27
-
7/30/2019 ere 500mw
28/127
14. Align LP inner outer casing lower half and level it. Install LP casing parting plane
platform .
15. Prepare and install LP front and LP rear lower half shaft seals housing and align it
provisionally.
16. Prepare and install LP rotor along with their bellows in position.
17. Align LP rotor radially and axially in position and record free run out of rotor.
18. Record/ Ensure radial and axial clearances of the LP casing including rotor float
including fitting of final axial keys of the LP inner casing .
19. Box up LP inner inner casing and heat tighten the parting plane bolts.
20. Box up LP inner outer casing .
21. Prepare and place HP module in position on temporary packers.
22. Transfer the load of HP rotor on bearings from the transport device and align it
radially and axially.
23. Check free run out of HP rotor on journal and coupling face including its float.
24. Prepare and place IP module in position on temporary packers. (In case IP module
is sent to site in disassembled condition, refer Instruction T1-08-0606G.
25. Loading of IP rear end of the shaft on bearing and removal of transport device.
26. Provisionally align HP , IP and LP rotor .
27. Couple HP / IP rotor on temporary Bolts and align rotor / casing radially and axially.
28. Record/ Ensure IP rotor float by shifting HP casing axially.
29. Conduct Horn drop test of HP casing without any radial and axial keys and pipe
lines.
30. Conduct Horn drop test of IP casing without IP inlet upper half pipe lines.
31. Assembly of breech nut of HP casing and Main Steam Stop & Control valve
assembly.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 28
-
7/30/2019 ere 500mw
29/127
32. Erection of Reheat Stop & Control valve assembly.
33. Weld IP inlet upper half pipe and record Horn drop values without radial-axial keys.
34. Alignment of HP/IP/LP rotors and their coupling on temporary bolts including its
couple runout.
35. Swing check of HP rotor on its front end with temporary alternate bolt tightened on
HP/IP coupling .
36. MOP alignment and its doweling.
37. Reaming/honing of HP/IP and LP/IP coupling including fitting of final coupling bolts.
38. Fixing of axial position of shaft and assembly of thrust bearing including its colour
matching.
39. Roll check of HP/IP casing and fixing of radial and axial keys of the casing (Casing
final packers need not to be put at this stage).
40. Assembly of bearings and checking of all clearances including fittings of side pads
of bearing, yoke keys etc.
41. Turbovisory works in all the pedestal i.e. assembly and calibration of thrust bearing
axial shift, LP rotor expansions pick up, Hall generator and thermocouples of
bearing .
42. Preparations of the bearing for oil flushing.
43. Oil flushing of the machine and normalizing the bearing after oil flushing.
44. Preparation and floating of TG deck as per Instruction No. T1-08-0909G.
45. Decoupling of HP / IP, LP/IP, LP/Gen., Gen./Exciter coupling and rechecking of
alignment/catenary after floating of TG deck spring.
46. Final tightening of HP/IP, IP/LP , LP/Generator and Generator / Exciter coupling
after correcting the alignment including their couple run out and swing check of rotor
on HP Front and exciter rotor.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 29
-
7/30/2019 ere 500mw
30/127
47. Checking /Correction of LP shaft seal clearance after floating of TG deck with CW
pump in operation and water in the hot well of condenser upto operating level.
48. Roll check of HP, IP casing in up and down direction only with TG deck in floating
condition and CW pump in operation including water in hot well upto normal level.
49. Assembly of final packers of the HP, IP casing after completing the roll check in up
and down direction.
50. Recording of final Horn drop of HP and IP casing after completing the welding of
HP inlet, HP exhaust , IP inlet and Cross around piping.
51. Preparation and boxing up of LP casing after competing the full Roll check of LP
casing and fitting of final casing packers and radial keys.
52. Barring gear.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 30
-
7/30/2019 ere 500mw
31/127
CHECKING OF FOUNDATION BEFORE CASTING
Customer to provide, center line and elevation point.
Check positioning of all the inserts and fixed points with respect to center line
in transverse and longitudinal direction as per BHEL Hardwar drawings.Check elevation of all points.
Check verticality of all the pipe sleeves with the help of plumb.
Ensure proper locking of all the insert and fixed points before grouting.
Ensure leveling on the fixed points of LP girder and LP rear pedestal.
Preserve machined surfaces of all the fixed points against any damages due toImproper handling.
Ensure proper flatness of the bottom seating plate of all the inserts.
Ensure proper stiffeners in all the vertical and horizontal embedment providedfor various purposes like hangers and supports etc.
Ensure proper cleaning of the area before casting.
Remove all unwanted material.
NOTE: In case of spring loaded TG deck refer Installation InstructionNo. T1-08-0909G prior to positioning of inserts etc.
CHECKS DURING CASTING/POURING OF CONCRETECasting of foundation\TG deck should be carried out immediately after
inspection of the foundation\TG deck i.e. within 3-4 days after finalinspection to avoid any disturbance to the inserts and fixed point.
Ensure no disturbance to the insert etc. during pouring of concrete whilevibrators are used.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 31
-
7/30/2019 ere 500mw
32/127
About 15-20 mm extra concrete may be left on top on all the pedestals and LPbase plate area for chipping/cleaning purpose at a later date.
Close all the pipe sleeve from top to avoid entry of concrete inside. Alternatelythe pipe sleeve should be filled with sand.
CHECKING OF FOUNDATION AFTER CASTING
Clean complete foundation and remove all shuttering etc.
Ensure there is no loose concrete layer in the region where the pedestal andbase plates are to be laid. No repair should be done in this region withoutconsulting the turbine erection engineer.
Cover all the opening before checking any dimensional measurement toavoid any accident.
Establish a suitable longitudinal axis considering the fixed point of the LP rear
pedestal and various pipe sleeves / inserts.
Establish a transverse axis as 90 degree with the help of the odolite.
Measure pitching/elevation of all the inserts and fixed points.
Measure elevation of all foundation on different pedestal and LP base plate area.
Check level of LP rear pedestal fixed points and if required correction maybe carried out.
PREPARATION OF FOUNDATION FOR PLACEMENT OFPEDESTALS AND BASE PLATES:
Foundation are to be cleaned and loose concrete are to be chipped off.
Maintain elevation of foundation to ensure correct thickness of non-shrinkgrout.
A reference point for elevation in respect of machine center line (equivalent to LPrear pedestal) is to be maintained at a proper place. This point is to bepreserved with proper protection. For making reference point a one sideground plate of about 200 x300 x20 mm may be used. This may bewelded on a I-beam near Generator. The ground position of the plate isto be kept on top side and all elevation are to be transferred from thispoint with the help of water level jar. A correct elevation reading is tobe punched on this plate. This reference point is to be used only during theturbine erection period.
Clean and deburr piping sleeves of the foundation on ID/OD of the pipe.
Ensure all corners of the foundation remains perfect during chipping of extraconcrete of foundation.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 32
-
7/30/2019 ere 500mw
33/127
PLACEMENT OF PEDESTALS
Open and clean the pedestal.
Ensure there is no paint/oil on bottom face of the pedestal sole plate.
Ensure there is no paint on inside surface or the pedestal and if required sandblasting may be carried out at site.
Ensure correct fitting/clearance of locating rings of LP rear pedestal.
The half bore error of pedestals is punched by manufacturing unit however incase it is not there, measure and punch half bore error of pedestal inleft/right side of the pedestal. If the error is nil then this may bepunched as zero-zero.
Ensure that the pedestal parting plane is feeler tight after tightening all theparting plane bolts. If required, colour matching may be carried out but
scraping/cutting is to be done on upper half cover only.
Check proper colour contact of spherical/cylindrical supports of the bearingwith the pedestal.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 33
-
7/30/2019 ere 500mw
34/127
Check contact between spherical Torus piece of bearing andspherical/cylindrical seat. In case of any variation in contact noscraping/cutting to be carried out at site and this may be referred tomanufacturing unit. Also refer T1-08-0808G. Check centering of individualbearing w.r.t. pedestal seal bores by fixing pianowire on individual
pedestal.
Ensure cleanliness of all pedestal oil lines. Close opening of oil lines ofpedestal to avoid any foreign material entering in these pipe lines duringerection at site.
Weld MOP suction and discharge pipe lines in HP front pedestal as per thedrawing before placement.
Assemble protection sheet in the foundation bolt holes of pedestals.
Assemble anchor bolts along with anchor plate of the pedestals. Ensure that
there is good contact available to the backing plate with thefoundation. If required colour matching/grinding may be carried out toachieve the contact.
Assemble protection sheet in the anchor bolt hole from bottom side of HP rearpedestal foundation to avoid entry of grout metal.
Ensure level of both anchor plate of H.P. rear pedestal with 70-90 mm gap forfilling of grouting concrete.
Adjust height of the Anchor Bolts as specified in the drawing.
PLACEMENT OF LP BASE PLATE, OVER THE FOUNDATION :Clean all the four base plates.
Mark/punch center line on the base plate as per drawing.
Ensure proper cleaning of base plate on bottom side.
Put identification marks on each base plate to avoid any mistake in positioning ofthe same.
Do colour matching of all the eight nos. carrier plate on both the faces.
Match LP base plate with the individual carrier plate.
Place all the four base plates in position along with their leveling screws andfoundation bolts.
Provisionally align and level all the four base plates.
Assemble protection sheet in the foundation bolt holes.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 34
-
7/30/2019 ere 500mw
35/127
ALIGNMENT OF PEDESTALS AND LP BASE PLATES
Provisionally align and level all the four pedestals including LP base plates withreference to the earlier marked longitudinal and transverse axis. Theelevation reference is to be taken from the already positioned plate forthis purpose.
Align and level LP rear pedestal and set the elevation as per machine center line.
Use piano wire arrangement with micrometer for centering of pedestal bore anduse water level jar for setting of elevation. Use measuring tape tomaintain pitching of the bearing from one pedestal to another. Pedestalsare to be set in level condition on both longitudinal and transversedirection. Align and level HP front, HP rear and LP front pedestals.Elevation of the pedestals are to be set as per catenary of the machineconsidering the half bore error of the pedestal if any.
Align and level, LP base plates. Elevation of LP base plate is to be kept higherthan the rear pair of LP base plate in line with catenary of rotor.
After alignment of LP rear pedestal weld the locating rings as mentioned in thedrawing.
During welding of locating ring, ensure that there is no movement in thepedestal in any of the direction.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 35
-
7/30/2019 ere 500mw
36/127
GROUTING OF PEDESTALS AND LP BASE PLATES
Fill 3 to 8 mm washed Pea-gravel in all the anchor bolts sleeves. These gravelare necessary to give damping effect to the anchor bolts during operationof the machine.
Seal anchor bolts holes after filling of gravel to avoid any entry of grout metal.Medical tape may be used for sealing of these anchor bolt holes.
Clean foundation with compressed air.
Make shuttering of all the pedestal and LP base plates. Use thick polythenesheet inside the shuttering to give better finish and avoid moistureabsorption by shuttering.
Shuttering should be made with maximum care to avoid any leakage of groutconcrete. All sides of the shuttering are to be sealed either with somesealing compound or with thick mixture of grout material to avoid leakage
of grout material.
Foundation are to be kept wet for about 6 hrs. before grouting.
Non shrinkage cement duly approved by BHEL is to be used for grouting of thepedestals and base plate.
Use fresh stock of the grouting material only and check the strength of thematerial before use.
During grouting, the mixture has to be poured from one end only and it has toflow to opposite end to avoid any blockage of air pocket.
Water curing is to be carried out for about 10 days duration.
All anchor bolts are to be stretched minimum after 21 days of grouting.
HP, IP & LP module placement work can be taken up after 24 hours of groutingof the pedestal and base plates.
For individual pedestal and base plate, grout mixture should be poured in one lotonly.
PLACEMENT OF HP MODULE IN POSITION
Ensure matching of all the four palms of the module where it is resting on thepedestals.
Ensure matching and parallelity of front and rear key block of the HP casing.
Assemble all four jacking screw of HPC and ensure their free movement.
Clean journals and coupling of the HP rotor.
Record journal dia, coupling hole sizes and spigot dia of HP rotor.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 36
-
7/30/2019 ere 500mw
37/127
Lift module in level condition and place it in position by keeping it 3 to 5 mmtoward front pedestal side.
During placement of module use temporary packers similar to permanent andadditionally support it by four jacking screws.
Ensure load on all four packers with the help of some additional shims ifrequired.
Install temporary radial and axial keys of the casing.
Prepare HP rotor for alignment (Ref. section 20 before placing the IP module.
PLACEMENT OF IP MODULE IN POSITION
Ensure matching of all the four palms of the module where it is resting on thepedestals.
Ensure matching and parallelity of front and rear key block of IP casing.
Assemble all four jacking screws of IP casing and ensure their freemovement. If these jacking screw holes are provided with the boltsfrom factory then same are to be removed before placement of module.
Clean IP rotor on both sides including coupling and journal.
Record spigot /recess, journal dia, and coupling hole sizes.
Lift the module in level condition and place the module in position by movingabout 7 to 8 mm towards generator end. Use temporary packers forplacement of module in position and additionally support the module withjacking screws.
Ensure load on all four packers with the help of some additional shims ifrequired.
Provisionally align the casing on front and rear pedestal bore. Install temporaryradial and axial keys of the casing with some shims.
Prepare IP rotor for alignment (Ref. section 20).
NOTE: In case IP module is sent to site in disassembled condition, referInstruction T1-08-0606G.
ASSEMBLY OF LP MODULE
This assembly can be divided in following sub assemblies:
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 37
-
7/30/2019 ere 500mw
38/127
Assembly of girder and end walls.
Assembly of LP inner inner and LP inner outer casing lower half.
Assembly / welding of LP outer casing.
Before starting assembly of LP casing in position, following works arealso to be completed :
- Positioning and welding of LP casing centering pin of front and rearside.
- Positioning of key block of LP casing axial keys.
- Positioning of all internal of condenser.
POSITIONING AND WELDING OF LP CASING CENTERINGPIN
Two nos. centering pins are to be located below LP front and LP rear pedestal.Necessary pipe along with two sq. end plates are already provided in thefoundation to take the radial load of the LP casing:
Plumb the center line from LP front and LP rear pedestal bore on both sideover the square plate of the foundation.
Establish accurate position of the pin and put a punch mark at a required height
and mark a circle and a controlling circle over all the four sq. Plates.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 38
-
7/30/2019 ere 500mw
39/127
Dia of the circle must be equal to pin dia. A template equivalent to pin dia hasto be made for this purpose with about 20 mm thick plate and a weldedpipe for using as an handle. The template dia must be very accurate andsame may be made on machine.
Make precise hole with gas cutting/grinding to match template on all four
embedded plate. Ensure that the template is fitted with minimumclearance and hole center are perfect as per marking.
Drill hole of about 10 mm dia on one of square plate of LP front and on oneplate of LP rear for air venting to avoid cracks during welding.
Insert both the pins and carry out the welding as per laid down procedure.Before welding set correct axial position of the pins.
Insert key block on both the pins and weld their locking ring also. Ensureproper clearances in key block before welding of its locking ring.
Preheating of 200 degree Celsius or more to be achieved before any welding.Dye penetrate test on root run and after final welding is to be carried out.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 39
-
7/30/2019 ere 500mw
40/127
ASSEMBLY OF GIRDER AND END WALL
Colour match side matching flange of girder with the surface plate.
Colour match seating flange of girder where it rests over the LP base plate.
Match and ensure parallality of axial key ways of girder.
Colour match side flanges of end wall.
Match and ensure parallality of key block of end wall.
Place left and right girder with carrier plate, spacer and lubrite packer on LPbase plate.
Provisionally align and level the girders. Set height of the girder equivalent tomachine center line maintaining catenary of the machine with the help ofwater level jar arrangement.
Assemble locking plate of the front and rear end wall to facilitate its assemblywith the girders.
Assemble front and rear end wall with the girders and ensure perfect partingplane level during tightening.
Align, level LP outer casing and ensure contact of packers by colourmatching/machining of spacer height.
Install LP casing radial and axial keys.
Assemble inner outer casing axial key blocks on left and right side of girder
and dowel them.
Lock with tack welding all the vertical joint bolts.
Put a seal weld run between girder and end wall joint all around except on topface.
Weld girder and end wall parting plane joint with argon welding. Beforewelding make a V groove with the help of a chisel and allow the projectionof material on surface. Do not make the groove by grinding.
Do colour matching with a surface plate on all four corner where argon welding
have been carried out.
ASSEMBLY OF LP INNER INNER AND LP INNER OUTERCASING LOWER HALF
The LP inner inner casing lower half is received from factory in assembledcondition with LP inner outer casing lower half.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 40
-
7/30/2019 ere 500mw
41/127
Clean the casing and check all the threaded holes.
Do colour matching on all four corners of the casing where it rest over thegirder.
Colour match all eight carrier plates of inner casing on both side.
Assemble all carrier plates on girder and do the colour matching withindividual carrier plate.
Prepare Gusset plate of front and rear side with temporary radial keys for fittingin LP inner casing.
Level and lift LP inner outer casing and assemble/weld both the gusset plateswith the help of some temporary support.
Lower the casing in position over the carrier plates fitted with spacer and lubrite
packer.
Provisionally align the casing radially and axially.
Support the gusset plate with the help of screw jack (about 10-15 tons) on frontand rear side by taking support from condenser stiffeners. Screw jack is tobe unscrewed after box-up.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 41
-
7/30/2019 ere 500mw
42/127
Adjust the height of the LP inner outer casing as per center line of the machineand then level it with the help of water level jar arrangement.
Ensure that all the eight packers have good contact. Loading of each packer isto be ensured.
Lower the casing by about 2 mm on all the eight packers with the help of shimsfor placement of LP rotor to avoid any fauling during placement of rotor.
Fit and weld all gusset plate stiffener pipes except pipe between LP inner outercasing and condenser. Do not make any weld connection betweencondenser and any of these stiffeners till neck welding of the condenseris over.
PLACEMENT OF LP ROTOR
Measure journal dia, spigot dia and coupling hole sizes.
Ensure centering of temporary bearing support in the LP front pedestal forplacement of LP rotor.
Place LP rear bearing in position.
Prepare shaft seal compensator along with gaskets (Gasket to be installed infully ring shape only ) and position them on LP rotor with the help ofsupplied supports of compensator.
Lift LP rotor with the supplied lifting beam in perfectly level condition and placeit in position. During lowering of rotor ensure radial clearance with thehelp of long feeler gauges in the LP casing.
WELDING OF LP OUTER CASING
The welding of LP outer cover is to be carried out before placement of LPRotor in position to avoid damage to the rotor.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 42
-
7/30/2019 ere 500mw
43/127
Colour match and remove all high spots of the matching flange of the LPouter casing.
Ensure good contact between parted diffuser of LP front and LP rear cover.
Colour match and remove all the high spots of the parted diffuser/vertical face
to ensure good contact with the compensator at a later stage.
Colour match and remove all burrs and high spots from parting plane of LP outercasing.
Side flange of LP front and rear cover are to be ensured in right angle toachieve good contact with their matching flanges.
Place LP front LP rear cover along with parted diffuser and ensure feeler tightjoint after tightening the parting plane bolts. The joint must be feelertight just after normal tightening of bolts. Do not over tighten partingplane bolts.
Ensure matching of parted diffuser face on both side of LP casing. If necessarycolour matching may be carried out to achieve a feeler tight joint.
Drill/ream all the parting plane holes as per drawings and install all dowel pins.
After fixing of LP front and rear cover measure the dimension forpositioning of both the center flanges. The dimension are to be recordedin such a way that there is no clearance after fitting of center flanges inposition on both side with the LP front and rear cover. The centerflanges are supplied in extra length on both sides from the factory andfinal length are to be maintained at site only.
Drill/ream dowel pin holes in center flanges and install all dowel pins in position.Ensure drilling and reaming of all dowel pin holes to equal depth.
Fit both the center pieces of the cover in position.
Achieve the fitting clearances for welding as per laid down procedure.
Weld/lock LP upper half flange with respect to lower half casing with the helpof metal cleats to minimise the distortion during welding of LP cover.The cleats may be welded at an interval of about one meter distance.
Carry out the welding as per the following welding procedure.
WELDING PROCEDURE
Tack weld the crowned seam joint. permanently welding approx. 100 mm at thegenerator end of the joint.
Opposite tack welded radial joint 2, permanently weld approx. 100 mm of thecrowned seam joint, pos. 1, staggering the two weld ends to ensure aperfect transition when the crowned seam joint is finish welded.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 43
-
7/30/2019 ere 500mw
44/127
Tack weld the crowned seam joint at regular intervals with a tack of 5T and pitchof 25T.
When welding radial joint 2, shell plates 1 & 2, tacked together, rest on but arenot tacked to the retaining strip in the region of joint 1, so that anyshrinkage occurring during welding of seam 2 is not obstructed.
The tacking & welding sequence applies for all shells courses.
Weld radial seam at TE according to welding sequence plan.
Align, adjust and tack weld radial seam at GE.
Weld radial seam at GE according to welding sequence plan.
Weld crowned seam joint.
Align shell courses on joint strips and tack weld,
Weld on joint strips from center & ends of shell plate.
Insert pins in top half casing, release top half casing and lift to insert and tackfiller piece between joint strips.
Unbolt top half casing and lift in order to weld and finish - machine filler pieces inthe region of the joint surface.
Check welds according to specifications.
ALIGNMENT AND COUPLING OF LP-IP & HP ROTORLP rotor is to be aligned on pedestal seal bore and LP inner outer casing is to becentralised in such a way that enough clearances are available to LP rotor,during alignment. Now this alignment activity of all the three rotor can bedivided as below :
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 44
-
7/30/2019 ere 500mw
45/127
Preparation of HP rotor for alignment.
Preparation of IP rotor for alignment.
Preparation of LP rotor for alignment.
Alignment of LP-IP & HP rotors.
Reaming, honing of the coupling holes.
Balancing of coupling bolts weight.
PREPARATION OF HP ROTOR FOR ALIGNMENT
Align HP rotor with reference to front and rear pedestal seal bore reading. Ifrequired move complete HP module along with the rotor.
Fix temporary radial and axial key of the casing on both front and rear side ofthe casing. Remove HP front upper half transportation device.
Lift module by 0.20 mm on front side by putting additional shims in frontpackers.
Insert HP front bearing in position.
Reduce 0.20 mm shims gradually and ensure about 0.10 mm load on the rotor. Ifrequired further lower the front side of the module to achieve the loadingon bearing by about 0.10 mm.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 45
-
7/30/2019 ere 500mw
46/127
Remove HP front lower half transport device gradually and ensure nomovement between HP casing and rotor. If necessary adjust shims ofHP casing front packers.
During loading of bearing always ensure that the rotor is not fouling inside the
casing with the shaft seals. This may be ensured by checking with feelergauge also.
Check axial position of HP rotor in front side on left; right and top positionfrom the rotor reference point to the HPC as given in the shop protocol.
Insert and load the bearing in HP rear end in similar way as carried out incase of HP front end and record axial position of rotor as per shopprotocol.
Lock axially HP rotor with some fixture along with the arrangement ofjacking screw for movement of rotor. This fixture may be mounted on rear
pedestal. Before locking of rotor ensure axial position of the shaft.
Center HP shaft with reference to HP casing front and rear spigot. If necessary,move the casing readily to achieve the centering. A fixture can befabricated at site for mounting the dial gauge on both the end of the rotorto check the centering of the shaft.
Use thick oil during rotation of shaft on the bearing.
Protect bearing from any of the dust particles. It is recommended to placeupper half of bearing in position to avoid dust and any other damage tothe shaft journal.
Realign the rotor shaft with respect to pedestal seal bore and if necessaryadjust the shims below spherical support of the bearing.
Care should be taken during alignment that radial and axial clearancesbetween rotor and casings does not get bridged.
Check HP rotor radial run out on journal and coupling.
Check axial run out on thrust collar and both the coupling faces of HP rotor.
Check axial float of the rotor. Compare values with shop protocol values. (Ref. T1-08-0802G). Deviations to be reported to Manufacturing Unit.
PREPARATION OF IP ROTOR FOR ALIGNMENT
The IP module is also to be prepared in line with the HP module. Howeveras IP rotor is provided with one side bearing and opposite side is coupledwith the HP rotor without a bearing, extra care is necessary duringalignment of rotor in IP casing. The additional point which are to be taken careare explained below :
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 46
-
7/30/2019 ere 500mw
47/127
Place IP rotor rear end on bearing similar to the HP rotor and removetransportation device.
Provisionally align HP/IP rotors and couple on temporary bolts by moving boththe modules. During coupling of the rotors, the transportation device of IPfront end is also to be taken out.
Check axial position of rotor w.r.t. IP casing and adjust as per shop protocol.
Check centering of IP rotor front and rear end w.r.t. IP casing (similar to the HProtor centering check).
Check float of the IP rotor. Compare values with the shop protocol values. (Ref.T1-08-0802G). During checking of float ensure HP casing is not foulingwith HP rotor. If required HP casing may be moved axially for this purpose.
Check facial runout on IP rear coupling face and radial runout on journals andcouplings.
PREPARATION OF LP ROTOR FOR ALIGNMENT
Provisionally align LP rotor in pedestal seal bore placing the front end of shafton auxiliary bearing and rear end on bearing.
Align LP inner outer casing radially with the help of long feeler gauges andinstall temporary radial keys in the gusset plate.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 47
-
7/30/2019 ere 500mw
48/127
Record all the radial and axial clearances of the LP casing without couplingthe LP-IP rotor. Variation if any in radial or axial clearances are to becorrected/approved at this stage.
Remove shims from the front end of auxiliary bearing and keep rotor on lifting
tackle.
Record radial run out of LP rotor coupling and journal and axial run out of thecoupling faces of the both end.
Record float of the LP rotor by moving the LP inner outer casing lower half.
After ensuring the radial and axial run out of the LP rotor the LP inner outercasing can be boxed up. Parting plane bolts of LP inner-inner casing are tobe heat tightened.
ALIGNMENT OF HP, IP AND LP ROTORS
Ensure radial and axial runout of all the three rotors are individually in order. Ifnecessary individual rotor module can be taken out for correction ofcoupling face runout. Any variation on radial runout of rotor is to bereferred to the factory.
Match coupling faces of two rotor as per the axial face reading of the rotor.Ensure that the higher point of the rotor coupling face and lower point ofanother rotor coupling face are matched together. This is to be comparedwith shop protocol also.
Preliminary align radially and axially all the three rotors and shift them in spigot
along with the casing to avoid fouling of rotor inside the casing.
During alignment achieve left and right movement of the rotor with the help ofshims in spherical / torus piece of the bearing. The up and downmovement of the rotor is to be achieved with the help of shims in thecylindrical/spherical support of the bearing . The adjustment of shims inthe bearing should be within the permissible limits only.
Ensure during alignment that the catenary of the shaft is maintained.
Check/record spigot clearance of HP-IP and LP-IP rotors by actually moving themin spigot.
Install four nos. supplied bolts along with one/two pins in HP-IP and LP-IPcoupling. Hand tighten the coupling bolts by keeping a gap of > 1.00 mmin coupling faces for alignment.
Rotate the rotor system and record the coupling gap at 90 Deg. interval onleft, right and top position. Ensure that the coupling, bolts and pinsremain free while recording the gap of the coupling for the alignmentpurposes.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 48
-
7/30/2019 ere 500mw
49/127
Check swing check value of the HP rotor with alternate bolts in position. Theabove value must be within the prescribed limit only otherwise acorrection must be carried out at site in consultation with designer.
Ensure free movement of rotor on their bearing. Do not rotate the rotor if itis tight during its rotation.
Ensue that the coupling holes are properly aligned to avoid unnecessaryenlargement of holes.
Ensure HP-IP-LP rotor radial run out after tightening with alternate clearancebolts. Release the couplings for reaming / honing of couplings.
In case of spring loaded TG decks, refer alignment procedure T1-08-0909G
REAMING / HONING OF COUPLING
Ensure that there is no disturbance on coupling during reaming/honingoperation.
First ream/hone two opposite holes of the coupling and install two pins/boltswith sliding fit and then take up all other holes.
Enlarge coupling holes to the minimum possible diameter and try to make all theholes to same dia.
Ensure that the finished holes are straight and there is no banana shape. Thiscan be ensured by checking hole with a straight ground finish pin having0.02/0.03 mm clearance.
The length of the pin should be equal to the bolt length. In case, few holes havegone considerably over size during reaming/honing at site/works, do notenlarge all the holes. As a special case in such cases these few holesmay be left as oversize.
Ensure that the holes during reaming/honing are perfectly finished as groundbore and size obtained should be within 0.005 mm. Ensure all the couplingbolts are fitted within 0.02/0.03 mm clearance with sliding fit and bolts areto be ground within an accuracy of 0.005 mm.
Coupling bolts are not to be hammered in the holes and these are to be fitted with
thumb pressure only.
Do not decouple the coupling in any case without ensuring the fitting of all thecoupling bolts.
BALANCING OF COUPLING BOLTS
After fitting the coupling bolts in all the holes these are to be balanced within 5gms accuracy and an accurate balance which can take a load of about 20 kg.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 49
-
7/30/2019 ere 500mw
50/127
may be used. During balancing of coupling bolts following points are to be takencare.
Final balancing of the coupling bolts are to be done along with the couplingnut of individual bolt.
If all the coupling bolt hole sizes are same before/after reaming and honingthen all the bolts can be kept of equal weight.
If necessary adjust the weight of the bolts by machining the metal from the bolthead.
When the holes of the coupling are of different sizes then it must be seen thatwhether excess enlargement have been done at site or works. In suchcases if excess cutting have been done at site in a particular hole thencoupling bolt with excess weight are to be used. The amount of excessweight must be equivalent to the excess enlargement of hole at site. If aparticular hole of excess dia. is noticed from factory then it is assured that
the particular rotor is balanced with excess dia hole and there is noneed of providing excess weight bolt at site.
COLOUR MATCHING OF THRUST BEARING
After completion of reaming/honing and preliminary tightening of the couplingbolts, the colour matching of the thrust bearing pad have to be carried out withrespect to the thrust collar of the HP Rotor. During colour matching a goodcontact on all the pads of front and rear side are to be ensured with respect torotor collar by moving the rotor in +/- direction during its hand rotation. Followingpoints are to be taken care during colour matching.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 50
-
7/30/2019 ere 500mw
51/127
Thrust bearing must be axially locked with the help of axial keys during thecolour matching of the pads. Axial keys to be fitted while finalising thealignment of thrust bearing with rotor collar without pads.
Few drops of oil is to be put on journal portion of the thrust bearing duringrotation of rotor to ensure that the oil is not entering in pad portion of the
bearing.
Colour is to be applied on the thrust collar of the rotor.
If necessary move the spherical support of the bearing pedestal to ensure theequal thickness of the pads before fittment of axial keys of the bearing.
During moving of the spherical support in front or rear direction ensure thatthere is no left - right movement to the support otherwise that maycause misalignment of the bearing.
After colour matching of the thrust pad the axial zero position of the rotor is
achieved and this can be taken for all other future reference for setting ofaxial position of HP, IP & LP casing.
HP, IP and LP lower casing are to be set axially after fixing the axial positionof the rotor and their final axial keys can be installed at this stage.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 51
-
7/30/2019 ere 500mw
52/127
ALIGNMENT OF HP, IP & LP CASING
After completion of colour matching of the thrust bearing pads the casingalignment work can be taken up. The following points are to be taken carewhile aligning HP, IP and LP casing.
The roll check have to be carried out in HP, IP and LP casing to ensure thecorrect radial clearances of the casing.
TG deck springs are to be kept in floating condition while recording the rollcheck of LP casing. However the roll check of HP/IP casing may be carriedout before floating of TG deck for fitting of their radial keys but up anddown roll check of HP/IP casings are to be done with TG deck in floatingcondition as per the procedure TS/ST/ 01/0008/00/96.
Ensure that there is no obstruction in the movement of LP inner casing due towelding of any of extraction piping. The one of the joint of extraction
piping may be left free till completion of roll check of the casing.
The welding of steam inlet pipes between LP inner casing and LP girders are tobe taken up after completion of roll check of the casing.
HP, IP and LP casing are to be fitted with final packers and axial key immediatelyafter the roll check. During fitting of casing axial keys and palm packersensure proper contact on lubrite coating of the keys/packers to avoid anydamage of these coating during operation of the machine,
After completion of fitting of final keys and packers only the casing are to becleared for further works of welding of various pipe lines.
The gland steam, balancing leak of lines, steam inlet and exhaust pipes are tobe welded with HP casing after fitting of final axial keys and packers of thecasing.
Center HP rotor w.r.t. casing front and rear spigots. Compare the readings withshop protocol and record the readings.
Offset center line of the HP, IP & LP casing w.r.t. respective rotor center line asper recommended logsheet.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 52
-
7/30/2019 ere 500mw
53/127
Check/record LP diffusers centering readings after roll check of the casing.
Before roll check of LP casing all the stiffener pipe welding work must becompleted. Refer T1-08-0909G.
FINAL TIGHTENING OF COUPLINGSIn case of spring loaded foundation after completing all other works the HP / IP ,IP/LP , LP/GEN , GEN/EXCITER couplings are to be reopened and realignedafter completing the reaming /honing . The rotors alignment are to be checkedwith TG deck in floating condition as per the laid down procedure. Afterchecking of alignment /catenary the final couplings are to be tightened includingtheir coupled run out and swing check of rotors on HP front and Exciter end ofthe shaft.
BOXING UP OF LP INNER INNER AND LP INNER OUTER
CASINGThe boxing up of LP inner inner and LP inner outer casing can be taken upbefore starting the alignment of HP-IP & LP rotor for coupling work. Thefollowing points are to be taken care before/during boxing up of these twocasings.
Ensure matching of all the parting plane holes, fitting of cap nuts andaccessibility of spanner .
Ensure feeler tightness of the parting plane joint of both the casing.
Check/record all the radial and axial clearances of the casing.
Ensure proper cleanliness of the LP inner inner and LP inner outer casing.
Ensure adequate clearance between LP inner inner casing and LP inner outercasing to avoid any obstruction during expansion of the LP inner casinginside the LP inner outer casing during operation of machines.
BOXING UP OF LP OUTER CASING
During the boxing up of the LP outer casing following points are to be taken care.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 53
-
7/30/2019 ere 500mw
54/127
Roll check of LP inner casing including the fitting of key, packers etc. must befinished.
All the works must be finished inside the LP casing before boxing up of LPcasing including LP extraction pipe line works.
Ensure matching of all parting plane holes and feeler tightness of the jointbefore boxing up of the casing.
Ensure feeler tightness of bursting diaphragm flange joint before boxing up ofthe casing.
Ensure proper assembly of parting plane rubber cord.
FINAL HORN DROP CHECK
After completing the welding of HP inlet, HP exhaust, IP inlet, IP exhaust
and other piping of HP/IP casing the final horn drop readings are recordedas per the laid down procedure mentioned in the manual for horn dropcheck. However the IP casing horn drop is also to be recorded with IPinlet upper half pipe welded with casing alone.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 54
-
7/30/2019 ere 500mw
55/127
Grouting of turbine base plates, bearing pedestals, foundation frame with shrink-free
grouting compound is intended to ensure uniform transmission of the force and vibration
of the TG unit to the foundation.
Caution:
Preparations for grouting, and grouting must be carried out with great care as it is no
longer possible to check and rectify the parts once they have been grouted.
CONBEXTRA GP-II or equivalent should be used as grouting compound. Further
details on the grouting depths, mixing time, quantity of water to be mixed, should be
refereed from the manufacturers brochures.
PROCEDURE
The foundation should be thoroughly cleaned. All foundation bolt holes should be filled
with pea-gravels and covered at the top to avoid entry and sticking of grouting materials
with the bolts.
NOTE:- Remove all rust preventive paints, grease etc. from surfaces by wire brushes
to ensure proper adhesion of the grouting compound.
SETTING UP OF SHUTTERING
Set up shuttering from suitable material in box like manner around the foundation plates
and secure it firmly.
NOTE:- Shuttering must be sealed well to prevent the liquid grouting compound from
running out. This can be done by using paste of grout materials and allowing it sets.
As the grouting compound remains workable for a limited time, to prevent air bubbles, it
must be poured from one side only. For this, a large size filling heaped should be used.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 55
-
7/30/2019 ere 500mw
56/127
PREPARATION OF GROUT MIX
Following measure must be taken before commencing mixing and grouting due tolimited time that the grouting compound remains workable.
Keep the foundation moist for at least 6 hours before the grouting.
-Set up mixers in the immediate vicinity of the foundation plates. The capacity of the
mixers, should be adequate to cope with the quantity of mixed cement required at a
time. Two or more mixers are required for grouting of bearing pedestal foundation
frame.
-Store the grouting compound next to mixer.
- Ensure that the compound is well within its expiry date.
-Provide the water hose and measuring pans near the mixers.
-Ensure uninterrupted power supply to the mixers and EOT Crane for handling the
ready mix.
-Provide adequate workmen for grouting.
-Ensure six empty cubes for filling the grout for strength testing. This is to be done as
per recommended FQP
-Take 80 % of the required water quantity first in the mixture. Then add gradually the
grout, ensuring that no lumps are found. It is desirable to add five or six large sizes
stones to break any lumps. Finally add the balance quantity of water and mix for at-
least another five minutes
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 56
-
7/30/2019 ere 500mw
57/127
This mixture is then taken into through heaped mesh. The hopper must be big enough
to make the full quantity of grout.
Than pour the grout with a hose through the filling hopper until the desired height is
achieved on the opposite side. (Flow may be accelerated by moving the grout in the
filling nozzles underneath the plates with chains or material strips.) This should be done
only if it is permitted by the grout supplier.
CAUTIONS
1. Do not use concrete vibrator.
2. Pour grout from one side only so that no air bubbles remains entrapped in thegrouting compound.
3. Due to short workability times, never mix more grouting compound at one time than
is required for one plate or volume to be grouted.
4. Pour in one continuous operation, without interruption.
5. Do not install any woven steel fabric reinforcing mats beneath the foundation plates.
6. It is desirable that in hot weather the grouting is done in the evening so that ambient
temperature is low during the initial setting time.
7. Water should be clean and free from dissolved chlorides, as these weaken the grout.
8. In case during the grouting operations heavy leakage is observed from the shuttering
that cannot be plugged during the grouting operation, and the level of grout has
fallen below the base plate level, it is desirable to wash out the complete grout. The
operation should be repeated after the shuttering has been rectified.
NOTE:- After at-least 72 hours setting time, work may be commenced on pre-
tensioning of the foundation both.
After the grouting compound has set (approximately. 24 hours after grouting), remove
all shuttering and smooth off the excess grout. The grouting compound is subjected to
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 57
-
7/30/2019 ere 500mw
58/127
compressive forces only. Resultant hair cracks are insignificant with regard to TG
stability. These can be avoided by covering the exposed areas of grout by polythene
sheets to avoid excess loss of moisture during initial setting.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 58
-
7/30/2019 ere 500mw
59/127
ASSEMBLY PROCEDURE OF IP MODULEDue to oversize dimension of the IP module (M30 - 63) and its limitation intransportation from Hardwar to site, the same will be dispatched to site in dismantledcondition in various packages after completing the shop assembly at Hardwar. Firstthe complete assembly of IP module will be done at works except the heat tightening ofparting plane bolts of IP inner and IP outer casing. Afterward complete casing will bedismantled and dispatched to site.
The above machines are equipped with the spring loaded foundation deck. As a
general requirement initially all the turbine and generator rotors will be aligned/coupled
without floating the TG deck. The coupling will be opened and again re-aligned after
floating of the TG deck which is generally done after erecting all the components of
Turbine -Generator including their piping etc.
ASSEMBLY PROCEDURE AT SITE :Place IP outer casing lower half in position after its cleaning over the pedestals by
supporting it on the Jacking screws at four corners of casing. Additionallysupport the casing on temporary packers with the pedestals also.
Align IP outer casing radially with the help of piano wire keeping the HP rear and IPfront pedestals seal as reference. Install temporary radial keys of the IP outercasing with the pedestal.
Clean and install IP inner casing lower half along with its radial keys (Drg. No. 0-106-01-27500 item No. 25) of front and rear end. During placement
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 59
-
7/30/2019 ere 500mw
60/127
of inner casing support it on its four nos. Jacking screws. (Drg no. 0-106-01-27500# 18). After placement of inner casing install its axial keys (drg N. 0-106-01-27500 # 20). Before placement of inner casing install its thermocouple,parting plane studs (drg N. 0-106-01-27500 # 33 & 34 ). Seal ring of inlet insert& extraction line (drg N. 0-106-01-27500 # 3,4,9,10,13,14 ).
Place IP inner casing upper half in position and tighten alternate parting plane bolts.During this process the heat tightening the bolts are not necessary as this isrequired for ensuring the feeler tight parting plane joints of the IP inner casing.The IP inner casing packers are also to be installed during tightening of the P/Pbolts and load of the inner casing is to be transferred on these casing packers(drg N0-106-01-27500 # 17) fter taking the load on the packers release thejacking screws of the IP casing.
Loosen IP inner casing parting plane bolts and remove IP inner casing upper half.Before loosening the IP inner casing parting plane bolts support inner casingagain on its four jacking screws and ensure that the parting plane level of lower
half inner casing is not disturbed and remain same as it was kept after tighteningof parting plane bolts with load on its four packers.
Place IP rotor in position after its cleaning. The front end of the rotor is to be placedover segment (drg N. 0-106-01-27500 # 21) and rear end of the rotor on itsbearing. During placement of IP rotor ensure that the rotor is free on its seal finsof IP inner casing and necessary the IP outer casing may be lowered on its rearend.
Provisionally align and couple HP/IP/LP/ Generator rotors and complete reaming/honing of the coupling including swing check etc. Before rotation of IP rotorremove segment (drg N. 0-106-01-27500 # 21).
Set axial position of the IP rotor as per the zero position of the thrust bearing and setaxial position of the IP outer casing as per Hardwar protocol on front and rearend of the IP outer casing.
Align radially IP outer casing with reference to the IP rotor on front and rear glands.Recheck/correct axial position of the IP casing.
Assemble IP inner casing upper half end tighten the alternate parting plane bolts toensure feeler tight joint.
Do roll check of IP inner casing by moving the IP outer casing in left/right direction andIP inner casing itself in up/down direction with the help of inner casing jacking
screws by removing the inner casing packers. Ensure / compare roll checkvalues with shop records.
Check IP rotor axial float in IP inner casing and compare with shop protocol.
Loosen IP inner casing bolts and remove IP inner casing upper half.
Decouple and lift IP rotor for assembly of rear end shaft seals of IP casing. The frontend of the seals may also be assembled now of afterward with the IP rotor inposition.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801GPage No. 60
-
7/30/2019 ere 500mw
61/127
Place IP rotor in position and provisionally couple it with HP rotor on temporary bolts.The IP rotor may not be coupled at its rear end with the LP rotor at this stage.
Assemble and heat tighten IP inner casing upper half as per required elongation ofparting plane bolts. Install seal rings of inlet insert and extraction pipe on IPinnercasing upper half (drg N. 0-106-01-27500 # 1,2,7,8,11,12). The taper pins
of IP inner casing parting planes are to be removed before placement of IP outercasing upper half after the heat tightening of IP inner casing bolts.
Assemble IP outer casing upper half and tighten the parting plane bolts to ensure feelertight joints. The heat tightening of the bolts are not to be done now. Beforeplacement of IP outer casing upper half assemble casing shaft seals of front &rear end also.
Do roll check & float of completely assemble IP turbine and compare it with factoryprotocol.
Heat tighten IP outer casing parting