environmental management plan updatedarmwater.am/files/adb/english/emp/i. armavir_emp-eng/i. armavir...
TRANSCRIPT
![Page 1: ENVIRONMENTAL MANAGEMENT PLAN updatedarmwater.am/files/adb/english/EMP/I. Armavir_EMP-eng/I. Armavir E… · Voskehat and Ferik rural communities, providing the inhabitants with safe](https://reader034.vdocuments.us/reader034/viewer/2022043018/5f3adde70cde062d180a4aec/html5/thumbnails/1.jpg)
ASIAN DEVELOPMENT BANK FUNDED
WATER SUPPLY AND SANITATION SECTOR PROJECT - ADDITIONAL FINANCING
Date of preparation - 2013
Updated July - 10.07.2015
SUBPROJECT I IMPROVEMENT OF ARMAVIR REGION
SETTLEMENTS WATER SUPPLY SYSTEMS L2860-ICB-1-01/1 IMPROVEMENT OF WATER SUPPLY
SYSTEMSIN OSHAKAN, VOSKEVAZ, VOSKEHAT AND FERIK VILLAGES
ENVIRONMENTAL MANAGEMENT PLAN updated
![Page 2: ENVIRONMENTAL MANAGEMENT PLAN updatedarmwater.am/files/adb/english/EMP/I. Armavir_EMP-eng/I. Armavir E… · Voskehat and Ferik rural communities, providing the inhabitants with safe](https://reader034.vdocuments.us/reader034/viewer/2022043018/5f3adde70cde062d180a4aec/html5/thumbnails/2.jpg)
TABLE OF CONTENTS
1. BACKGROUND OF THE PROJECT ........................................................................................... 4
2. ENVIRONMENTAL AND SOCIAL SAFEGUARD DOCUMENTS ......................................... 4
3. INTRODUCTION ......................................................................................................................... 4
4. SCOPE OF WORKS...................................................................................................................... 5
4.1. Description of existing water supply systems ................................................................................. 5
4.2.Description of proposed rehabilitation works .................................................................................. 6
5. BASELINE ENVIRONMENTAL CONDITIONS ....................................................................... 7
5.1 Geographic location and climate of Oshakan, Voskevaz, Voskehat and Ferik villages of Aragatsotn region ......................................................................................................................... 7
5.2 Biodiversity ....................................................................................................................................... 8
6. ENVIRONMENTAL AND SOCIAL IMPACTS .......................................................................... 9
7. ENVIRONMENTAL IMPACT MITIGATION MESUERES .................................................... 10
8. INSTITUTIONAL FRAMEWORK OF ENVIRONMENTAL MANAGEMENT ..................... 11
9. GRIEVANCE MECHANISM FOR AFFECTED PUBLIC ........................................................ 14
10. ENVIRONMENTAL MANAGEMENT PLAN .......................................................................... 15
LIST OF APPENDICES
APPENDIX 1. ENVIRONMENTAL MANAGEMENT MATRIX ............................................................ 16
APPENDIX 2. FIELD VISITS CHECKLIST ............................................................................................ 18
APPENDIX 3. COMPLAINTS LOG ......................................................................................................... 21
APPENDIX 4. UNANTICIPATED IMPACT / SIGNIFICANT INCIDENT / ACCIDENT NOTICE ..... 22
APPENDIX 5. EMISSIONS / AMBIENT MONITORING FORM .......................................................... 23
APPENDIX 6. LIST OF PARTICIPANTS OF ENVIRONMENTAL CONSULTATIONS ...................... 24
![Page 3: ENVIRONMENTAL MANAGEMENT PLAN updatedarmwater.am/files/adb/english/EMP/I. Armavir_EMP-eng/I. Armavir E… · Voskehat and Ferik rural communities, providing the inhabitants with safe](https://reader034.vdocuments.us/reader034/viewer/2022043018/5f3adde70cde062d180a4aec/html5/thumbnails/3.jpg)
LIST OF ABBREVIATIONS RA – Republic of Armenia
RA MoNP – RA Ministry of Nature Protection
RA MoH - RA Ministry of Healthcare
RA MoT&C – RA Ministry of Transport and Communication
RA MoC – RA Ministry of Culture
JV – Joint Venture
LSGB- Local Self-Governmental Bodies
EIA – Environmental Impact Assessment
AWSC ADB PMU–Armenian Water and Sewage Company/ Project Management Unit of Asian
Development Bank
EMP - Environmental Management Plan
IEE- Initial Environmental Examination
DD - Detail Design
![Page 4: ENVIRONMENTAL MANAGEMENT PLAN updatedarmwater.am/files/adb/english/EMP/I. Armavir_EMP-eng/I. Armavir E… · Voskehat and Ferik rural communities, providing the inhabitants with safe](https://reader034.vdocuments.us/reader034/viewer/2022043018/5f3adde70cde062d180a4aec/html5/thumbnails/4.jpg)
1. BACKGROUND OF THE PROJECT
WSSP Project will improve public health and environment for about 400,000 people
(households and other consumers) living in 18 towns and up to 92 villages1 through safe, reliable
and sustainable water supply. The outcome of the Project is improved access to safe, reliable,
and sustainable WSS services managed on commercial principles and environmentally sound
practices.
The Project will also support poverty reduction by (i) reducing the incidence of waterborne
diseases and costs of medical care; (ii) improving the time poverty of women due to labor intensive
housework such as water collection, which may allow them to participate more in social and
economic activities; (iii) providing safer and more reliable water supply; and (iv) improving the
quality of life of households in all the project towns and villages by improving their access to safe
and sustainable drinking water.
Similar to the original WSSP, the Additional Financing Project will fund two project components
which include: (i) municipal infrastructure rehabilitation and improvement; and (ii) management
improvement and development which include gender features.
2. ENVIRONMENTAL AND SOCIAL SAFEGUARD DOCUMENTS
In accordance with the ADB Environmental policy (2002), the Subproject is ranked to B category,
which does not need extended EIA. According to the RA law on “Environmental Impact
Assessment and Expertise” (issued on June 21, 2014) and the RA Government decree on “The
activities subject to expertise of environmental impact” (N-193, 30 March 1999), this design
documentation, which summarizes the types of activities planned under the sub-project, is not
subject to environmental impact assessment and expertise, based on the insignificant impact of
the planned activity on the environment.
As a B Category Project ADB Policy requires development of Initial Environmental Examination/
IEE report for each Subproject and site specific Environmental Management Plan/EMP (separate
report for each of the subprojects).
3. INTRODUCTION
The very report is developed for the Subproject on the Improvement of W&W Systems in
Oshakan, Voskevaz, Voskehat and Ferik villages of Aragatsotn region, the design of which has
been performed by the JV of HGSN and JINJ LLCs. The Water supply systems rehabilitation
involves activities on reconstruction and repair of water distribution systems, as well as
construction of new water pipelines, regulating and water measuring junc.
As a result of the construction work implementation, as well as further operation and maintenance
of the water supply systems there might be undesirable negative impacts on the environment.
1 The number of towns and villages may change subject to further detailed assessments.
![Page 5: ENVIRONMENTAL MANAGEMENT PLAN updatedarmwater.am/files/adb/english/EMP/I. Armavir_EMP-eng/I. Armavir E… · Voskehat and Ferik rural communities, providing the inhabitants with safe](https://reader034.vdocuments.us/reader034/viewer/2022043018/5f3adde70cde062d180a4aec/html5/thumbnails/5.jpg)
It is expected that the impacts during construction work implementation will be the least and
temporary, probably involving vegetation cut, soil erosion, air and water resource pollution by
lubricants, household and construction waste.
At the Operation Stage the environmental impact, the main reason of which might be improper
execution of operation requirements, will decrease.
The improvement activities will be considered environmentally friendly in case of water resource
conservation, as well as rational and steady use.
The social and economic effect as a result of water supply system improvement are expected to
be long-term, mostly positive, excluding potable and waste waters mix, minimization of water
pollution risk, prevention and exclusion of infection disease agents penetration into potable water,
as well as water supply extension, providing steady water supply and rational water use.
The EMP Part 5 introduces description of possible impacts and facilitating measures required
during different stages of Water Supply Systems Rehabilitation Project.
Designing stage
The design works on water systems have been performed by the JV of HGSN and JINJ, which
has been selected as a Consultant who provides services on civil works and public awareness
campaign within the framework of “Water Supply and Sanitation Sector Project – Additional
Financing”. The EMP includes articles on climatic conditions, relief, natural soil types, hydrology
and biodiversity of the very package, requirements on obtaining the RA MoNP and other
Ministries’ agreements, as well asfulfillment of executive parties’ contractual commitments during
all stages. The Design documentation includes adequate environmental and social articles and
separateMatrix of the very EMP Subproject. The Project Consultant is in charge to follow the
appropriate statements of the RA Environmental and social legislation, as well as ADB
instructions and strategy requirements.
Construction stage
The list of measures required to mitigate the environmental impact during construction stage is
separately provided in the EMP matrix (Appendix 1).
Operation Stage
The Contractor should strictly follow the requirements on environmental impact mitigation
measures, which are involved in the EMP.
During the Construction Stage the Operation should be performed in accordance with the
Operational Rules and Standards.
4. SCOPE OF WORKS
4.1. Description of existing water supply systems
The total length of water supply distribution network in Oshakan, Voskevaz, Voskehat and Ferik
rural communities is about 50 km, which is fed through the ground springs of Ashtarak region.
![Page 6: ENVIRONMENTAL MANAGEMENT PLAN updatedarmwater.am/files/adb/english/EMP/I. Armavir_EMP-eng/I. Armavir E… · Voskehat and Ferik rural communities, providing the inhabitants with safe](https://reader034.vdocuments.us/reader034/viewer/2022043018/5f3adde70cde062d180a4aec/html5/thumbnails/6.jpg)
The water supply of Oshakan community is mainly performed through DN300mm conduit running
to the village from 500 m3 DRR. A number of north-eastern areas are fed through DN250 mm
water main Kheres.
The water supply of Voskevaz community is performed through 150 mm diameter steel pipes fed
through 2x500 m3DRRs.
Voskevaz water supply is mainly performed through 500 m3 DRR with pump station and 80m3
capacity reservoir fed from DN 500mm conduit Bazmaghbyur by gravity.
The water supply pipelines of the settlements are in poor condition. The inner network is laid with
steel pipes which are corroded. The most of the settlements distribution pipelines are deteriorated
causing significant leakages. Non-counted water of the abovementioned communities makes
about 88%. The system consumed water recording is not performed completely.
In 2010 within the framework of “Improvement of W&W systems of the RA settlements” Project
funded by ADB there were performed some works, partially, reconstruction of reservoirs and
coming out of them conduits, distribution system pipelines and valve junc.
4.2.Description of proposed rehabilitation works
The very Subproject aims at rehabilitation of water supply system of Oshakan, Voskevaz,
Voskehat and Ferik rural communities, providing the inhabitants with safe potable water and
improving water distribution and accounting systems.
Population number in Oshakan, Voskevaz, Voskehat and Ferik villages, according to 01.01.2012,
makes 12030 in total. The clients total number in the rural communities is 2469.
Taking into account the population prospective growth by 2040, assuming 0.43% annual growth,
the rural communities dwellers number is supposed to be 13335 men.
For the settlements, considering also the leakages, the mean daily water demand rate is assumed
to be 200 l/day per man.
The average hourly discharge of maximal daily water demand of the rural communities makes
Qav..h=117.4 l/sec.
Based on the technical and economical calculations done in the Preliminary Design, as well as
submitted justifications, in the Detailed Design there have been developed activities on the water
supply rehabilitation.
By the very Detailed Design the works designed for the improvement of water supply system in
Oshakan, Voskevaz, Voskehat and Ferik rural communities are as follows:
Construction of de50-de200 diameter 42641 lm long polyethylene pipelines
Construction of valve junc. – 49 sets
Construction of private house connections - 24310 lm
Installation of private houses water metering junc. - 2192 sets
The aggregative indexes of the designed works in the Subproject rural communities are
introduced in Table 1
![Page 7: ENVIRONMENTAL MANAGEMENT PLAN updatedarmwater.am/files/adb/english/EMP/I. Armavir_EMP-eng/I. Armavir E… · Voskehat and Ferik rural communities, providing the inhabitants with safe](https://reader034.vdocuments.us/reader034/viewer/2022043018/5f3adde70cde062d180a4aec/html5/thumbnails/7.jpg)
Table 1
According to the agreement between the Contractor, Consultant and rural communities, the
mentioned beneath works should be implemented by the construction completion, in spite of the
pipeline diameter and its function.
1. To restore the asphalt concrete pavement of roads which were previously in favorable
condition, providing the same cover quality,
2. To perform backfilling of the trenches in the destroyed and half-destroyed streets paved with
asphalt concrete, then 10-15 cm gravelling with compaction.
5. BASELINE ENVIRONMENTAL CONDITIONS
5.1 Geographic location and climate of Oshakan, Voskevaz, Voskehat and Ferik villages
of Aragatsotn region
The studied area of Aragatsotn region area is situated premountain zone where the relief is
slightly steep, not so hilly, somewhere partioned by small ravines. The settlements are 3-5 km far
south-west from Ashtarak town, and 20-22 km far from Yerevan. The regional center is Ashtarak
town.
The climate of the studied area is acutely continental characterized by hot summerand rather cold
winter. The site air average annual temperature is +9,1C, and absolute minimal temperature
reaches +38C. The average annual atmospheric rainfalls make 447mm, the maximal 715 mm.
In winter the snow average cover reaches 28 cm, the maximal – 68 cm. The ground freezing
maximal depth is 79 cm. The air average many-year relative humidity makes 62%. The wind
average annual velocity is 28m/sec.
The northern part of the area boarders on the south lower slopes of Aragatsmountain, where the
geological structure contains Armenian Upland volcanic formations.
Works M/U
Voskevaz v
.
Voskehat
v.
Oshakan v
.
Ferik v
.
To
tal
Reconstruction of de50-de200 diameter polyethylene pipeline of water supply internal system
lm 15,000 3,700 20,900 3,041 42,641
Testing, washing, disinfection of the abovementioned system
lkm 15 3.7 20.9 3.9 43.5
Construction of valve junc. set 20 9 14 6 49
Construction of private houses connections
lm 8,580 1,350 13,550 830 24,310
Installation of private houses water metering junc.
set 700 104 1,300 88 2,192
![Page 8: ENVIRONMENTAL MANAGEMENT PLAN updatedarmwater.am/files/adb/english/EMP/I. Armavir_EMP-eng/I. Armavir E… · Voskehat and Ferik rural communities, providing the inhabitants with safe](https://reader034.vdocuments.us/reader034/viewer/2022043018/5f3adde70cde062d180a4aec/html5/thumbnails/8.jpg)
Among exogenic phenomena there are surface erosion, change and deepening of the gullies
formed due to the rainfall permanent and temporary flows, and some techno-genic phenomena,
etc.
The inhabited part of the studied area is situated at 950-1100m elevation marks.
5.2 Biodiversity
The most area lands are under agriculture use with the exception of some little “islands” of wild
nature. The lands soil is commonly brown and semi-desert type.
From the geo-morphological aspect the area represents a hilly lava covered plateau with common
scoria wedges and gorges. It is situated within the Kasakh River basin where the relief is
commonly channeled by pre-mountainravines.
The area geological structure represents the Armenian Upland Upper Pliocene volcanic deposits.
The rocks are of Quaternary period represented by basalts, dacites, tuffs and theirclastic
sediments. Since the volcanic formations are subject to intensive weathering, with typical strong
fracturing, the ground watersare infiltrated rather deep - at 15-20m depth.
There are no negative physical and geological phenomena within the area. The region is situated
in 9 magnitude seismicity zone.
Flora The plant species of the studied areas are introduced by the typical of Aparan and Erevan
florisic region vegetation types, that is meadow, steppe and semi-desert types.
From the true grasses (Poaceae) the couch grass (Phleum sp.), bluegrass (Poa sp.), fescue grass
(Festuca sp.) are widely spread, mainly Artemisia fragransformation. The steppe species are
introduced byfeather-grass, fescue-grass andvegetative formations, with prevalence of
Festucavalesiaca, Prairie June Grass (Koeleriacristata), Stipatirsa, etc. There is also observed
significant presence of thyme species, Festucaovina, low sedge, etc. Besides, there are also
occurPlantago(plantain), Tragopogon, Taracsacum(dandelion), Betonica (betony), Vicia(vetch),
Trifolium (shamrock), Cirsium(thistle), Euphorbia (spurge), Papaver (poppy), and from the bush
species: Rosa (dog rose), Paliurus (jujube), Acantholimon (prickly thrift).
From the tree species there occurpoplar (Populus), acacia (Robinia), maple (Acer), mulberry
(Morus), wild apricot (Armeniaca), hawthorn tree(Crataegus), willow-leafed pear
(Pyrussalicifolia), common and Caucasian Ash (Fraxsinus excelsior, F.oxycarpa),
spirea(Spiraeacrenata), Berberisorientalis, Cotoneaster integerrima, Loniceraiberica,
Jasminumfruticans, Ulmus, Prunus, Elaeagnus, willow– Salix.
Within the studied areas there also occur endangered species like Hohenackeriaexscapa (Stev.)
K.-Pol, recorded in the new version of the RA Red Book.
Fauna In the studied area commonly occurred invertebrate species are locust species
(Oedopodacoerulescensd), Oe. Miniata, Pholidopterasatunini, Scintharistanotabilis,
Tmethisfestivus, Spingotus),crickets (Phytodrymadusa armeniaca), double-wing (Tomomyza
araxana, Bombiluss chelkovnikovi) species, and from the scorpions only yellow species (Buttus
caucasicus).
![Page 9: ENVIRONMENTAL MANAGEMENT PLAN updatedarmwater.am/files/adb/english/EMP/I. Armavir_EMP-eng/I. Armavir E… · Voskehat and Ferik rural communities, providing the inhabitants with safe](https://reader034.vdocuments.us/reader034/viewer/2022043018/5f3adde70cde062d180a4aec/html5/thumbnails/9.jpg)
From mammals there are widely spread hares (Lepuseuropaeus), foxes (Vulpesvulpes), and
wolves (Canis lupus). The area widely spread rodents are mouse species (Muridae), especially
common field vole (Microtinae).
From the bird species the widely spread are sparrow (Passeriformes) and falcon
(Falconoformes) species.
From the creepers the typical for the studied areaspecies are Snake-eyed Lizard
(Ophisopselegans), Strauch's (Eremiasstrauchi) and Transcaucasion (E.pleskei)racerunners, etc
6. ENVIRONMENTAL AND SOCIAL IMPACTS
Due to the implementation of works aimed at the improvement of W&W systems of Oshakan,
Voskevaz, Voskehat and Ferik villages the expected positive environmental and population health
effects are as follows:
water resource protection and sustainable use,
excluding mixing of drinking, irrigation and sewerage water,
preventing, excluding penetration of infectious disease viruses into drinking water,
reduction of drinking water pollution hazard,
providing high drinking water quality,
improvement of health condition of population,
water loss reduction,
increasing duration of water supply to population,
introduction of water metering system,
increasing water consumption efficiency.
IEE reveals that the implementation of works aimed at W&W systems improvement in Oshakan,
Voskevaz, Voskehat and Ferik villages of Aragatsotn region will have no harmful effects on the
selected for this purpose area - either landscape or flora and fauna.
The probable negative effects might be mainly caused by construction works implementation, and
expected to do little damage and be temporal. To prevent negative impacts, or facilitate them
there have been developed facilitating measures which are involved into the EMP.
EMP is the integral part of bidding document and based on the IEE the expected negative impacts
are as follows:
air pollution
noise
traffic and pedestrian roads damage and loading
soil erosion and soil eroding processes
environment pollution by construction and household waste
soil and water resources pollution by fuels and lubricants,
soil and water resources pollution by chlorine.
Subproject implementation will have positive social effects directly improving the population life
quality providing sustainable and reliable water supply and water resource rational use for about
11788 men.
![Page 10: ENVIRONMENTAL MANAGEMENT PLAN updatedarmwater.am/files/adb/english/EMP/I. Armavir_EMP-eng/I. Armavir E… · Voskehat and Ferik rural communities, providing the inhabitants with safe](https://reader034.vdocuments.us/reader034/viewer/2022043018/5f3adde70cde062d180a4aec/html5/thumbnails/10.jpg)
7. ENVIRONMENTAL IMPACT MITIGATION MESUERES
The probable harmful impacts on the environment and people’s health, caused by the works
aimed at the W&W internal system improvement of Oshakan, Voskevaz, Voskehat and Ferik rural
communities, depend on construction works of water pipeline trenches and pits for control and
water measuring junc.
To prevent soil erosion processes the following measures are to be implemented on the inclined
sites of the waterline route for retaining the inclinations, minimizing the time of any trenches and
pits intended for regulating and water metering units leaving open.
The inclinations should be retained to prevent soil erosion and intensive side erosion process
nearby the rivers and tributaries.
- After completion of construction works all sites are to be cleaned from construction waste
providing initial condition of the area;
- To recover the asphalt* - concrete coat of the busy streets providing its previous quality,
- Provide graveling with compaction on the streets with damaged and half-destroyed asphalt-
concrete pavement, as well as on earth roads
*Note: The asphalt will be bought from specialized asphalt plant which is responsible for taking
environmental impact mitigation measures. All asphalt plants function in accordance with RA
Environmental legislation.
To prevent the topsoil layer damage, or landscape degradation, the topsoil should be hauled and
stored on the assigned for it site, thereafter used for the areas restoration. The construction site
should be cleaned from the household and construction waste providing the previous state of
landscape.
To exclude land and water resources pollution with fuels and lubricants, the latter must be stored
on a sealed surface, away from water resources, plan use of special tanks for their storage, which
will then be removed to special sites envisaged for re-treatment.
To prevent environment pollution with construction and household waste, remove construction
waste to corresponding landfill of the community, having in advance a contract agreement with
the community heads or landfill operators.
The excess soil resulted due to trenching are to be hauled to the allotted for them community site,
having in advance a contract agreement with the community heads.
As a result of the project, the disposal of old equipment and pipes as scrap metals is not
anticipated. The old pipeline of internal system will be under operation until the end of construction
works. At the moment when new pipeline considers ready (after being disinfected and tested),
the old waterline will be cut-down and the new waterline will be put into operation. The old pipes
will remain underground and no scrap metals will be generated. The old pipeline is the property2
of community and will remain under the discretion of community.
After the completion of each construction phase the Contractor must organize disposal of
construction waste to the sites allotted for the purpose of waste accumulation, according to the
established order.
To exclude land and water resources pollution with chlorine, the works for washing the water
supply distribution network with chlorine should be organized according to calculations, providing
2 The Government Resolution N51 of 14 March, 1997
![Page 11: ENVIRONMENTAL MANAGEMENT PLAN updatedarmwater.am/files/adb/english/EMP/I. Armavir_EMP-eng/I. Armavir E… · Voskehat and Ferik rural communities, providing the inhabitants with safe](https://reader034.vdocuments.us/reader034/viewer/2022043018/5f3adde70cde062d180a4aec/html5/thumbnails/11.jpg)
appropriate technical means, including chlorine discharge to surface water body or land area after
washing the pipes according to the regime planned under the design.
To reduce dust during the construction works, the construction site and roads are to be regularly
watered and kept wet to exclude dust during wind and operating of machines.
To prevent air pollution, closed/covered trucks are to be used during transportation of dusty
construction material, In case it is impossible to avoid dust during the works, the workers shall be
provided with protective masks.
To prevent noise impact, night work in residential areas is to be limited, and usage of
machines/equipment with extra noise is to be avoided; installation of silencers if needed.
The construction equipment is to be examined on a regular basis and not allow the noise exceed
the allowable standard. The workers operating equipment with over 85 dB noise shall be provided
with protective devices (mufflers).
To reduce disturbance to population because of overloaded roads safe area for trucks is to be
provided; construction and household waste must not be accumulated and burnt on the
construction site. Construction should be implemented by stages, providing adequate notice of
construction activities to the population. The traffic flow should be regulated, if required, including
set-up of road signs, safety tapes, temporary safety foot bridges as alternative walk way.
Adequate street lighting should be provided in places when passers-by or entry by public is likely.
To prevent hazards for workers and the population during the construction, the following must be
implemented: fencing the construction site; control unauthorized persons’ access to the site; place
warning signs in dangerous places; carry out regular examination of equipment by qualified staff,
as well as make regular safety audits; provide first aid and safety training to construction team.
Provide community participation in subproject design, which will minimize disruption to community
social activities.
Drinking water quality change: Environmental monitoring plan must include also control over
water quality and residual chlorine level as well as hygiene and sanitation safety of drinking water.
To provide potable water quality in Oshakan, Voskevaz, Voskehat and Ferik rural communities,
the AWSC should perform routine sampling from the springs feeding the communities, testing the
water for all criteria required by the MoH. Water quality monitoring is also performed by the State
Hygiene Anti-Epidemic Inspectorateaccording to the document “Potable water. Requirements on
water quality of centralized water supply systems. Sanitation rules and norms of quality inspection
№ 2-III-A2-1” (recorded on 28.12.2002), which specifies the potable water quality requirements,
including the rules of quality inspection of water produced and supplied through water distribution
systems to the residential areas.
Since water disinfection is performed by chlorine, the monitoring of residual chlorine level is also
of great importance.
8. INSTITUTIONAL FRAMEWORK OF ENVIRONMENTAL MANAGEMENT
The organizational obligations for the proposed mitigating measures are distributed among the
following agencies:
Executive agencies responsible for implementation of the measure.
![Page 12: ENVIRONMENTAL MANAGEMENT PLAN updatedarmwater.am/files/adb/english/EMP/I. Armavir_EMP-eng/I. Armavir E… · Voskehat and Ferik rural communities, providing the inhabitants with safe](https://reader034.vdocuments.us/reader034/viewer/2022043018/5f3adde70cde062d180a4aec/html5/thumbnails/12.jpg)
1. For this special task the executive agency (HGSN Ltd and JINJ Ltd. joint venture) must
provide in the design stage obtaining of all the required agreements and permits from
corresponding state and local authorities, before tendering the construction works;
- conclusion of environmental expert examination (if needed),
- Agreement of the State Agency for Protection of Historical and Cultural Monuments, if
impact is envisaged by the design.
2. The executive agencies in the construction stage (construction contractors) will be
responsible for physical implementation of mitigating measures planned under the EMP,
as well as for obtaining of all permits and agreements required during the construction
implementation. Those are:
Agreements from the local self-governing authorities for the sites allotted for hauling
construction wastes, garbage and soil disposal,
Permission of the Ministry of Culture, if historical and cultural or archaeological
monuments are discovered accidently during the construction implementation.
3. Before commencement of the construction, the following permits and certificates must be
obtained from PMU, if needed:
- cadaster certificate on the land allotment;
- Water use permit, if needed.
Controlling agencies responsible for supervising the executive units to provide
implementation of the EMP measures by the latter
1. AWS CJSC/ADB PMU environmental specialist will be responsible for timely, due and
reliable implementation of the works and measures under the EMP and SSEMP. The
mentioned specialist will regularly visit the construction sites to provide due implementation
of the measures aimed at work impact mitigation. During the visits the possible gaps will
be identified and the infringements in implementation of mitigating measures will be
discovered, in accordance with the site visits checklist (Appendix 2).
The AWS CJSC/ADB PMU has the right also to require and check whether all permits are
available and valid, all the measures and monitoring part under the EMP are implemented
during the construction, in accordance with ADB guidelines and the RA environmental and
social legislation.
2. HGSN LLC and JINJ LLC joint venture will also implement control of implementation of
mitigating measures during the construction. The environmental specialist shall make visits
to control the EMP and SSEMP implementation and assess the situation according to the
Emissions/Ambient Inspection Monitoring Form (Appendix 5).
State monitoring agencies responsible for observing the extent and efficiency of
EMP implementation and making amendments in the project, if needed.
The state monitoring agencies are as follows:
- State Environmental Inspectorate under the Ministry of Nature Protection, RA
- Public Health State Inspectorate under the Ministry of Healthcare, RA
- The State Agency for Protection of Historical and Cultural Monuments, RA
- The RA local self-governance bodies,
- The RA Ministry of Transport and Communication.
![Page 13: ENVIRONMENTAL MANAGEMENT PLAN updatedarmwater.am/files/adb/english/EMP/I. Armavir_EMP-eng/I. Armavir E… · Voskehat and Ferik rural communities, providing the inhabitants with safe](https://reader034.vdocuments.us/reader034/viewer/2022043018/5f3adde70cde062d180a4aec/html5/thumbnails/13.jpg)
The sums of money envisaged for implementation of environmental measures included in the
EMP and SSEMP are included in the detailed design.
Implementation of mitigating measures for environmental impacts will be controlled regularly
through visits to the construction sites. With the help of the specially developed check list the gaps
and drawbacks will be discovered.
In case of not implementing or infringing the implementation of the mitigating measures,
after warning, the next payment will be terminated until the infringement is completely
eliminated.
9. ENVIRONMENTAL CONSULTATIONS
During the meetings organized within the framework of public awareness campaigns, the
Consultant presented the environmental and social impacts to the Subproject beneficiary and
affected communites.
To provide the presence of all beneficiaries, preliminary agreements were gained with the
community head (heads of the villages), Water company staff, Public organizations functioning in
Armavir region and other stakeholders.
In Ferik village the meeting was held on April 14, during which the local population showed active
participation. The meeting was held in the administrative center of the village involving
participation of the head of the mentioned village, staff of the administrative centre,
representatives of the council, housewives and elderly citizens (total - 15 people).
Women and elderly people highly concerned in water supply system improvement showed active
participation. The list of meeting participants of Ferik village is brought in Appendix 6.
During the meetings the detailed design and works planned were introduced, after which the
environmental specialist informed about the possible adverse environmental impacts which are
summarized in the EMP.
The latter is the description of the negative impacts on the environment, population health and
safety of construction workers, which are possible during the subproject implementation in design,
construction and operation stages. The list of the measures mitigating or preventing these
possible negative impacts was also represented.
The community residents were mainly concerned with the following possible problems arising
during the construction works:
- infringement of traffic and pedestrians normal regime because of trenches left open for a
long time, as well as improper rehabilitation of roads after the construction,
- hazardous situation for children and elders because of the absence of warning signs and
not limiting the construction site entry with safety tapes,
- pollution of the settlement with construction and household waste during the construction,
failing to remove them after the construction,
- long-term termination of water supply (sometimes for 1-2 days) during the construction.
After representing the EMP, the environmental specialist asked all communities’ residents to get
acquainted in detail with the environmental management plan and during the construction follow
implementation of the measures included in the plan.
![Page 14: ENVIRONMENTAL MANAGEMENT PLAN updatedarmwater.am/files/adb/english/EMP/I. Armavir_EMP-eng/I. Armavir E… · Voskehat and Ferik rural communities, providing the inhabitants with safe](https://reader034.vdocuments.us/reader034/viewer/2022043018/5f3adde70cde062d180a4aec/html5/thumbnails/14.jpg)
The environmental management plan was copied and disseminated among the meeting
participants, as well as in the rural administrative centre.
Public consultation
v. Ferik
10. GRIEVANCE MECHANISM FOR AFFECTED PUBLIC
A grievance mechanism for external stakeholders and affected public is a process focused mainly
on receiving, evaluating, and addressing project-related grievances from affected communities at
the level of the WSSSP. The grievance mechanism differ from other forms of dispute resolution
(e.g. courts, administrative systems, etc.) in that it offers the advantage of a locally based,
simplified, and mutually beneficial way to settle issues within the framework of the relationship
between the WSSSP and the community.
Properly designed and implemented grievance management processes can benefit both the
WSSSP and communities by increasing the likelihood of resolving minor disputes quickly,
inexpensively, and fairly with solutions that reasonably satisfy both sides without taking the
grievances to other (formal) dispute resolution body. Grievance mechanisms can help to identify
and resolve issues before they are elevated to formal dispute resolution methods, including the
courts. For a grievance mechanism to function effectively, it is important to define the grievance
processing structure and to assign responsibilities for the mechanism’s implementation and make
them clear for the stakeholders.
Contact details for questions, complains and recommendations from the external stakeholders of
the WSSSP are as follows:
Hot line 1 71 - AWSC Customers Support Calling Center,
Investment Program Coordination Department
Mrs. Lilit Hovhannisyan - Environmental and Social Impact Specialist
Address 8a Vardanants blind alley, Yerevan 0010, Armenia
Phone / Fax (+374 10) 542877
E-mail: [email protected]
The Complaints Log form is provided in Appendix 3. The foremen of the construction sites should
be provided with the Complaints Log to organize the registration of complaints. AWS CJSC
customer service (hotline) employees also will register all the complaints.
![Page 15: ENVIRONMENTAL MANAGEMENT PLAN updatedarmwater.am/files/adb/english/EMP/I. Armavir_EMP-eng/I. Armavir E… · Voskehat and Ferik rural communities, providing the inhabitants with safe](https://reader034.vdocuments.us/reader034/viewer/2022043018/5f3adde70cde062d180a4aec/html5/thumbnails/15.jpg)
The focus of the grievance mechanism on the needs of affected communities is justified by the
fact that they are directly, and in some cases significantly, affected during the project
implementation but often lack viable options or capacity for raising their concerns through formal
structures such as the courts. This is especially true for disadvantaged groups within
communities. The WSSSP should periodically review the adequacy of the grievance process, with
the participation of communities, and agree on modifications. The contact details will be provided
in construction information posters and information leaflets distributed in the project affected
communities during the public consultations. Questions and comments expressed during the
public meetings will be recorded and addressed during the design and implementation of the
WSSSP.
A grievance mechanism will be available to allow an AP appealing any disagreeable decision,
practice or activity arising from disturbance during the construction works. APs during public
consultation will be fully informed of their rights and of the procedures for addressing complaints
whether verbally or in writing during consultation, survey, and time of compensation. This can be
obtained through by ensuring full participation and consultation with the APs, and by establishing
extensive communication and coordination among the affected communities, the PMU and town
or community heads. The below grievance mechanism does not limit the citizen’s right to submit
the case to the court of law just in the first stage of grievance process.
11. ENVIRONMENTAL MANAGEMENT PLAN
The EMP and the SSEMP will be based on the results of IEE prepared by subproject and will
include appropriate mitigation measures.
EMP consists of two components:
1. Mitigation measures and institutional responsibilities for implementation;
2. Environmental monitoring.
In case if an unanticipated environmental impact arises during the construction, the Table
provided in Appendix 4. Unanticipated Impact / Significant Incident / Accident Notice will be filled
up and attached to the varied orders.
The Contractor should strictly follow the environmental mitigation measures prescribed in the
EMP and SSEMP. The costs foreseen for the implementations of all the measures prescribed in
the EMP and SSEMP are included the total value of the Contract.
Notice on the failure to implement measures prescribed by the Technical Supervision Company
(TSC) or the Client would be sent to the Contractor in written. After the Notice to Correct, the next
recorded violation would trigger charging of liquidated damages in the amount of 0, 1% of the
total value of the contract. The liquidated damages do not relieve the Contractor from remedying
the violation. The recorded violation should be remedied in two working days period. Liquidated
damages would be retained from the next Performance Certificate and after the completion of the
construction activities the liquidated damages for the recorded violation will be retained from the
Retention Money. In case of three liquidated damages the Contract could be terminated
unilaterally.
Above described remedies of EMP violation will be included in the contracts for provision of works
concluded by AWSC under the W&W project.
![Page 16: ENVIRONMENTAL MANAGEMENT PLAN updatedarmwater.am/files/adb/english/EMP/I. Armavir_EMP-eng/I. Armavir E… · Voskehat and Ferik rural communities, providing the inhabitants with safe](https://reader034.vdocuments.us/reader034/viewer/2022043018/5f3adde70cde062d180a4aec/html5/thumbnails/16.jpg)
16
APPENDIX 1. ENVIRONMENTAL MANAGEMENT MATRIX
Works and possible impacts
Proposed mitigating measures Monitoring Responsible
bodies
Civil works
1. Air pollution, noise
Dust and noise during the construction works
- regularly water the construction site and streets/roads - limit night work in residential areas - avoid usage of machines/equipment with extra noise; installation
of silencers, if needed - provide safe area for trucks - do not accumulate and burn waste on the construction site - carry out construction by stages, awaring the population about
construction activities
Daily site inspection
Constructor, Consultant, PMU
2.Soil and water pollution
Soil erosion and erosion processes
Environment pollution with construction waste
Land and water resources pollution with fuels and lubricants
Land water resources pollution with chlorine
- On inclined waterline sites to carry out measures for retaining the inclinations
- Minimize the time leaving open the trenches and pits excavated for regulation and metering junctions
- Rehabilitate damaged surfaces as soon as possible after completion of construction activity, according to the design
- Store oil, fuels and lubricants on a sealed surface, away from water resources
- Remove construction waste to corresponding landfill of the community, having in advance a contract agreement with the community heads or landfill operators
- Organize works for washing the water supply distribution network with chlorine according to technical calculations providing adequate technical means
- Implementation of chlorine discharge to surface water body or land area after washing the pipes, according to the regime planned under the design, MPV
Daily inspection throughout construction and operating stage.
Daily site inspection
Constructor, Consultant, PMU
3. Traffic overload - Disturbance to population because of overloaded roads
- Provide road signs, by-pass or barricades,
- Provide adequate street lighting on the sites, if necessary,
Daily supervision of construction site
Constructor, Consultant, PMU
![Page 17: ENVIRONMENTAL MANAGEMENT PLAN updatedarmwater.am/files/adb/english/EMP/I. Armavir_EMP-eng/I. Armavir E… · Voskehat and Ferik rural communities, providing the inhabitants with safe](https://reader034.vdocuments.us/reader034/viewer/2022043018/5f3adde70cde062d180a4aec/html5/thumbnails/17.jpg)
17
Works and possible impacts
Proposed mitigating measures Monitoring Responsible
bodies
- Provide proper lighting where passers-by or entry by public is likely,
- Provide community participation in subproject design, which will minimize disruption to community social activities
4. Health and Safety
Hazards for workers and population
- Fencing the construction site
- Control unauthorized persons’ access to the site
- Place warning signs in the right place in dangerous places
- Carry out regular examination of equipment by highly qualified staff, as well as make regular safety audits,
- Provide first aid and safety training to construction staff
Daily inspection throughout construction stage. Monthly inspection of accident reports and complaints registering
Constructor, Consultant,
PMU,
Population
![Page 18: ENVIRONMENTAL MANAGEMENT PLAN updatedarmwater.am/files/adb/english/EMP/I. Armavir_EMP-eng/I. Armavir E… · Voskehat and Ferik rural communities, providing the inhabitants with safe](https://reader034.vdocuments.us/reader034/viewer/2022043018/5f3adde70cde062d180a4aec/html5/thumbnails/18.jpg)
18
APPENDIX 2. FIELD VISITS CHECKLIST
Ընդհանուր
տեղեկատվություն
General information
Ամիս/ամսաթիվ D/M/Y
Ենթածրագիր / Subproject
Տեղակայում / Location
Շինարարականկազմակերպություն/
Constriction contractor
Մարզ / Marz
Նախագծում
Design
Անհրաժեշտ
թույլտվություններ
Required permissions
Բնապահպանականփորձ, եզրակացություն /
EEC
Այո
Yes
Ոչ No
Ո/Կ
N/A
Հողհատկացմանգրավորհամաձայնություն / writen
consent on land acquisition
Այո
Yes
Ոչ No
Ո/Կ
N/A
Պատմամշակութայինփորձաքննություն / assessment
of impact on cultural heritage
Այո
Yes
Ոչ No
Ո/Կ
N/A
Շինարարություն
Construction
Անհրաժեշտթույլտ
վություններ
Required permissions
Շին.թափոնների տեղադրման գրավոր
համաձայնություն / written consent on disposal of
construction waste
Այո
Yes
Ոչ No
Ո/Կ
N/A
Անսպասելիորեն հայտնաբերման դեպքում
պատմամշակ. համաձայնություն / written consent in
case of sudden discovery of cultural heritage
Այո
Yes
Ոչ No
Ո/Կ
N/A
Հասարակությանիրազեկում
Public awereness
Շին.աշխատանքների վերաբերյալ բնակչության
համապատասխան իրազեկում համաձայն
նախագծին / awareness of population regarding
construction works according to the project design
Այո
Yes
Ոչ No
Ո/Կ
N/A
Համայնքի մասնակցություն շինարարական
աշխատանքներին համաձայն նախագծին /
community's participation in construction works according to the project design
Այո
Yes
Ոչ No
Ո/Կ
N/A
Անվտանգություն
Safety
Բանվորների
անվտանգություն
Safety of workers
Բանվորների անվտանգության հանդերձանքի
առկայություն /ականջակալներ, շնչադիմակ/
availability of safety uniforms (earflaps,mask)
Այո
Yes
Ոչ No
Ո/Կ
N/A
Շինարարության մեջ ներառված տեխնիկական
միջոցների պարբերական զննումներ`
անվտանգությունը ապահովելու նպատակով / regular
study of equipment used for construction for safety matter
Այո
Yes
Ոչ No
Ո/Կ
N/A
![Page 19: ENVIRONMENTAL MANAGEMENT PLAN updatedarmwater.am/files/adb/english/EMP/I. Armavir_EMP-eng/I. Armavir E… · Voskehat and Ferik rural communities, providing the inhabitants with safe](https://reader034.vdocuments.us/reader034/viewer/2022043018/5f3adde70cde062d180a4aec/html5/thumbnails/19.jpg)
19
Բնակչության
անվտանգություն
Safety of population
Երթևեկության սահմանափակման կամ խախտման
ժամանակ համապատասխան ճանապարհային
նշանների կամ պատնեշների տեղադրում, շրջանցի
կազմակերպում / Installation of road signs or fences,
organization of a bypass during interrupted or limited traffic
Այո
Yes
Ոչ No
Ո/Կ
N/A
Շինարարության իրականացման ժամանակ կառավարման միջոցառումներ
Management measures during construction
Շին.հրապարակի/
տեղանքիշահագոր
ծում /
Operation on area/construction site
Շին.հրապարակի/տեղանքի պարբերաբար ջրում /
regular sprinkling to area/construction site
Այո
Yes
Ոչ No
Ո/Կ
N/A
Մեքենաների համար ապահով տարածքի
առկայություն շին.հրապարակում / availability of safe
place at the construction site for vehicles
Այո
Yes
Ոչ No
Ո/Կ
N/A
Յուղերի և քսուկների համապատասխան
պահեստների առկայություն շին. հրապարակում /
availability of storagefor oils and lubricants at the appropriate part of the construction site
Այո
Yes
Ոչ No
Ո/Կ
N/A
Օդի ժամանակավոր աղտոտում
Temporary air pollution/dust
Շինանյութ տեղափոխող բեռնատարների վրա ծածկի
օգտագործում / use of cover for the vehicle
transporting construction waste
Այո
Yes
Ոչ No
Ո/Կ
N/A
Շինարարության տարածքի խոնավեցում ջրի շիթով /
moisturing of the construction site by water
Այո
Yes
Ոչ No
Ո/Կ
N/A
Հողի էրոզիա
Soil erosion
Զառիվարտեղերումհողիէրոզիայիկանխարգելմանմի
ջոցառումներիիրականացումըստնախագծի / soil
erosion prevention measures at the slope places according to the project design
Այո
Yes
Ոչ No
Ո/Կ
N/A
Փոսորակներիժամանակինհետլիցք / timely coverage
of holes by soil
Այո
Yes
Ոչ No
Ո/Կ
N/A
Շին.աշխատանքների ավարտից հետո վնասված
մակերեսների վերանորոգում ըստ նախագծի / repair
of damaged surface after completion of construction works
Այո
Yes
Ոչ No
Ո/Կ
N/A
Ջրի աղտոտում
Water pollution
Ջրի աղտոտում քսանյութերով և վառելանյութերով /
water pollution caused by fuel and lubricants
Այո
Yes
Ոչ No
Ո/Կ
N/A
Խողովակների լվացումից հետո քլորի արտահոսք
համապատասխան նախագծով նախատեսված
ռեժիմի / Leakage of chlorine after wash up of the
pipes according to the scheduled regime.
Այո
Yes
Ոչ No
Ո/Կ
N/A
Աղմուկ բնակավայրերի տարածքին մոտ
Noise close to settlements
Աշխատանքների իրականացում սահմանված
աշխատանքային ժամերին, հակառակ դեպքում
Այո
Yes
Ոչ No
Ո/Կ
N/A
![Page 20: ENVIRONMENTAL MANAGEMENT PLAN updatedarmwater.am/files/adb/english/EMP/I. Armavir_EMP-eng/I. Armavir E… · Voskehat and Ferik rural communities, providing the inhabitants with safe](https://reader034.vdocuments.us/reader034/viewer/2022043018/5f3adde70cde062d180a4aec/html5/thumbnails/20.jpg)
20
սահմանված կարգով / implementation of the works
during working hours, otherwise in projected manner
Շինարարական և կենցաղային թափոնների տեղադրում
Construction west disposal
Շինարարական և կենցաղային աղբի տեղափոխում և
տեղադրում և համայնքի համապատասխան
աղբավայրում / transportation and disposal of
construction and consumer waste in appropriate community landfill
Այո
Yes
Ոչ No
Ո/Կ
N/A
Շահագործում
Operation
Խմելու ջրի
աղտոտում /
Drinking water pollution
Մնացորդային քլորի քանակի համապատասխանում
խմելու որակի ջրի նորմերին / Correspondence of
balance quantity of residual chlorine to the quality of potable water
Այո
Yes
Ոչ No
Ո/Կ
N/A
![Page 21: ENVIRONMENTAL MANAGEMENT PLAN updatedarmwater.am/files/adb/english/EMP/I. Armavir_EMP-eng/I. Armavir E… · Voskehat and Ferik rural communities, providing the inhabitants with safe](https://reader034.vdocuments.us/reader034/viewer/2022043018/5f3adde70cde062d180a4aec/html5/thumbnails/21.jpg)
21
APPENDIX 3. COMPLAINTS LOG
COMPLAINT LOG SHEET Region, community, Subproject ______________________________________________________________________
Co
mp
lain
t n
um
ber Date of
the complaint acceptan
ce
Method of complaint
submission (personally, by phone, by letter, by internet,
etc.)
Complaint content
(issue description)
Complaint solution method /mitigation
activity
State of the complaint sollution*
Does the complainant follow through the process of the
issue solution? Yes / No
Notes
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
*<Open> or <Closed> (If closed, include date) Filed by PMU Environmental Specialist:________________________________________________ Date: ___________________________
![Page 22: ENVIRONMENTAL MANAGEMENT PLAN updatedarmwater.am/files/adb/english/EMP/I. Armavir_EMP-eng/I. Armavir E… · Voskehat and Ferik rural communities, providing the inhabitants with safe](https://reader034.vdocuments.us/reader034/viewer/2022043018/5f3adde70cde062d180a4aec/html5/thumbnails/22.jpg)
22
APPENDIX 4. UNANTICIPATED IMPACT / SIGNIFICANT INCIDENT / ACCIDENT NOTICE
Date/ Location
of incident
Description of incident/Impact including magnitude and control action taken at
the time
Assessment of results
Corrective action required including deadline,
and lessons learned
Jointly signed by: Site Supervision Engineer:_______________________________________ Date:___________________________ Contractor:________________________________________________ Date:___________________________ Appendices: (e.g. photographs, laboratory reports, etc.)
![Page 23: ENVIRONMENTAL MANAGEMENT PLAN updatedarmwater.am/files/adb/english/EMP/I. Armavir_EMP-eng/I. Armavir E… · Voskehat and Ferik rural communities, providing the inhabitants with safe](https://reader034.vdocuments.us/reader034/viewer/2022043018/5f3adde70cde062d180a4aec/html5/thumbnails/23.jpg)
23
APPENDIX 5. EMISSIONS / AMBIENT MONITORING FORM
Parameter Date /
location
Measured
by
Monitoring
method /
equipment used
Result Performance standard %
Exceedence
Reason for
exceedence and
corrective action
request if it is work
related
Resolution
status of
previous CAR
![Page 24: ENVIRONMENTAL MANAGEMENT PLAN updatedarmwater.am/files/adb/english/EMP/I. Armavir_EMP-eng/I. Armavir E… · Voskehat and Ferik rural communities, providing the inhabitants with safe](https://reader034.vdocuments.us/reader034/viewer/2022043018/5f3adde70cde062d180a4aec/html5/thumbnails/24.jpg)
24
APPENDIX 6. LIST OF PARTICIPANTS OF ENVIRONMENTAL CONSULTATIONS
v. Ferik