environmental impact assessment (eia) of dudh koshi-5 ... eia report... · environmental impact...
TRANSCRIPT
Environmental Impact Assessment (EIA) of
Dudh Koshi-5 Hydropower Project
(110 MW)
Submitted to:
Ministry of Forests and Environment
Through
Ministry of Energy, Water Resources and Irrigation
Submitted by
Department of Electricity Development
April, 2019
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
ii| P a g e Department of Electricity Development
TABLE OF CONTENTS
LIST OF TABLES ...........................................................................................................................IV LIST OF FIGURES ........................................................................................................................ VII LIST OF ANNEXES .................................................................................................................... VII ACCRONYMS/ABBREVATIONS ................................................................................................... VIII SFO {SF/L ; F/ F+; .......................................................................................................................................... A
EXECUTIVE SUMMARY .................................................................................................................. J 1.NAME AND ADDRESS OF THE INDIVIDUAL/INSTITUTION PREPARING THE REPORT .... 1
1.1The Proponent .............................................................................................................................................. 1 1.2Organization Responsible for Preparing the Report ................................................................................... 1 1.3Rationality of EIA Study ............................................................................................................................... 1 1.4Objectives of EIA ......................................................................................................................................... 2 1.5Scope of EIA Study ....................................................................................................................................... 2
2.INTRODUCTIONOF THE PROPOSAL ............................................................................................. 3 2.1Background .................................................................................................................................................. 3 2.2Project objectives, Need and Relevancy ...................................................................................................... 4 2.3Location and Accessibility ........................................................................................................................... 4 2.4Salient features of the Project ...................................................................................................................... 5 2.5Project Components ................................................................................................................................... 13 2.6Transmission Line ...................................................................................................................................... 17 2.7Project Activities ........................................................................................................................................ 18 2.8Construction Planning ............................................................................................................................... 18 2.9River Diversion during Construction ......................................................................................................... 22 2.10Project Cost ............................................................................................................................................. 22
3.STUDY METHODOLOGY ............................................................................................................... 23 3.1Literature Review and Consultation with the Stakeholders ....................................................................... 23 3.2Impact Area Delineation ............................................................................................................................ 23 3.3Field Study ................................................................................................................................................. 24 3.4Data Analysis and Processing ................................................................................................................... 32 3.5Public Consultation ................................................................................................................................... 32 3.6Draft Report Preparation .......................................................................................................................... 32 3.7Public Hearing ........................................................................................................................................... 33 3.8Recommendation Letters from the affected Rural Municipality/Wards ..................................................... 34 3.9Finalization of EIA Report ......................................................................................................................... 34 3.10Study Team ............................................................................................................................................... 34 3.11Estimated Budget for EIA study ............................................................................................................... 35
4.EXISTING ENVIRONMENTAL CONDITION ............................................................................... 36 4.1Physical Environment ................................................................................................................................ 36 4.2Biological Environment ............................................................................................................................. 57 4.3Socio-economic and Cultural Environment ............................................................................................... 83
5.ENVIRONMENTAL IMPACTS ..................................................................................................... 103 5.1Beneficial Impacts .................................................................................................................................... 103 5.2Adverse Impacts ....................................................................................................................................... 105 5.3Evaluation of the Impacts ........................................................................................................................ 122
6.ALTERNATIVE ANALYSIS .......................................................................................................... 129 6.1Design Alternative ................................................................................................................................... 129 6.2Construction Method Alternatives ........................................................................................................... 129 6.3Project Alternatives ................................................................................................................................. 130 6.4Construction Material Alternative ........................................................................................................... 130 6.5Construction Schedule Alternatives ......................................................................................................... 131 6.6No Forest Option ..................................................................................................................................... 131 6.7No Project Alternative ............................................................................................................................. 131 6.8Operation Procedure ............................................................................................................................... 132 6.9Fish Ladder Alternative ........................................................................................................................... 132
7.ENHANCEMENT AND MITIGATION MEASURES ................................................................... 134 7.1EnvironmentalEnhancement Measures .................................................................................................... 134 7.2Community Support Program (CSP) ....................................................................................................... 136
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
iii| P a g e Department of Electricity Development
7.3Environmental Mitigation Measures........................................................................................................ 137 8.ENVIRONMENTAL MANAGEMENT PLAN .............................................................................. 150
8.1Introduction ............................................................................................................................................. 150 8.2Planning150 8.3Summary of Environmental Mitigation, Monitoring andManagement Cost ............................................ 173
9.REVIEW OF PLANS, POLICIES, ACTS, REGULATIONS, GUIDELINES, STANDARDS,
CONVENTIONS ................................................................................................................................. 174 9.1The Constitution ....................................................................................................................................... 174 9.2Plans and Polices ..................................................................................................................................... 174 9.3Strategies ................................................................................................................................................. 178 9.4Act and Rules ........................................................................................................................................... 180 9.5Guidelines and Manuals .......................................................................................................................... 187 9.6Working Procedures/Work Plans ............................................................................................................. 189 9.7Standards ................................................................................................................................................. 192 9.8International Instruments ......................................................................................................................... 193 9.9Relevant Institutions ................................................................................................................................. 194
10.ENVIRONMENTAL MONITORING ........................................................................................... 197 10.1Environmental Monitoring Plan ............................................................................................................ 197 10.2Baseline Monitoring ............................................................................................................................... 197 10.3Compliance Monitoring ......................................................................................................................... 199 10.4Impact Monitoring ................................................................................................................................. 202
11.ENVIRONMENTAL AUDITING ................................................................................................. 207 11.1Introduction ........................................................................................................................................... 207 11.2Physcical Environment .......................................................................................................................... 207 11.3Biological Environment ......................................................................................................................... 207 11.4Socio-economic and Cultural Environment ........................................................................................... 207 11.5Approach and Methodology ................................................................................................................... 208 11.6Schedule ................................................................................................................................................. 208 11.7Required Human Resources ................................................................................................................... 208 11.8Estimated Cost ....................................................................................................................................... 208 11.9Organizational Responsibility ................................................................................................................ 209
12.CONCLUSIONS ............................................................................................................................ 210 13.REFERENCES ............................................................................................................................... 211 ANNEXES .......................................................................................................................................... 212
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
iv| P a g e Department of Electricity Development
LIST OF TABLES
Table 2-1: Details of the access roads for the proposed DK5HPP ................................................ 5
Table 2-2: Comparative Salient Features of Dudh Koshi-5 HPP (as per ToR and revised) .......... 9
Table 2-3: Details of Adit Tunnel for the construction of the proposed DK-5 HPP ................... 17
Table 2-4: Acquisition of land for different project component .................................................. 18
Table 2-5: Estimate of construction materials required ............................................................... 19
Table 3-1: Description and categorization of the project impact area ......................................... 23
Table 3-2: Stand size classifications ............................................................................................ 26
Table 3-3: FGD Locations and Participant Details ...................................................................... 31
Table 3-4: Details on KII ............................................................................................................. 31
Table 3-5: Issues raised during public hearing ............................................................................ 33
Table 4-1: Catchment Characteristics .......................................................................................... 37
Table 4-2: Discharge Measurement of the Dudh Koshi River .................................................... 38
Table 4-3: Estimated Mean monthly flow ................................................................................... 40
Table 4-4: Low flows at the Intake Site, m3/s .............................................................................. 43
Table 4-5: Low Flow Analysis by Weibul Method ..................................................................... 43
Table 4-6: Flood Flow at Intake Site (m3/s)................................................................................. 44
Table 4-7: Flow of tributaries in the Dewatered Zone (m3/s) ...................................................... 45
Table 4-8: Ambient air quality at project area and national permissible limits ........................... 54
Table 4-9: Noise level measured in the different project area ..................................................... 54
Table 4-10: Water Quality Test Results....................................................................................... 55
Table 4-11: Land use pattern of Solukhumbu district (Ha) ......................................................... 56
Table 4-12: Land Use Pattern of Project Area ............................................................................. 57
Table 4-13: List of Community Forests in and around the project area ...................................... 60
Table 4-14: Recorded species of tree vegetation in the project area ........................................... 60
Table 4-15: Recorded Species of Shrubs in the project area ....................................................... 61
Table 4-16: Recorded Climbers Species in the project area ........................................................ 61
Table 4-17: Recorded herbs species in the project area ............................................................... 62
Table 4-18: Project Components and Major Tree Species .......................................................... 63
Table 4-19: Tree Category along Different Project Structures .................................................... 64
Table 4-20: Tree Basal Area, Volume and Biomass in Project Area .......................................... 64
Table 4-21: Tree Volume and Biomass Distribution with Project Structures ............................. 65
Table 4-22: Tree Volume and Biomass Distribution along with Project Structures ................... 71
Table 4-23: Importance Value Index of plant species in Herb Strata .......................................... 73
Table 4-24: Regeneration Status of Trees .................................................................................... 74
Table 4-25: Land Ownership of Forest Land ............................................................................... 75
Table 4-26: Ethno-botanical Uses Practiced in the Proposed Project Area ................................. 76
Table 4-27: Protected Plants in the Proposed Project Area ......................................................... 77
Table 4-28: Reported Mammals in the Proposed Project Area ................................................... 78
Table 4-29: Reported Birds in the Proposed Project Area ........................................................... 78
Table 4-30: List of Herpeto-Fauna Recorded in Project Area ..................................................... 80
Table 4-31: Reported and Observed Fish Fauna in the Dudh Koshi River ................................. 81
Table 4-32: Fish Migratory Pattern.............................................................................................. 82
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
v| P a g e Department of Electricity Development
Table 4-33: Species Diversity and Distribution ........................................................................... 82
Table 4-34: Fish Abundance at Sampling Sites ........................................................................... 82
Table 4-35: Catch per Unit Effort (CPUE) at Different Sampling Stations ................................ 83
Table 4-36: Protected Wild Animals in Project Area .................................................................. 83
Table 4-37: Land Use Pattern of Solukhumbu District ............................................................... 84
Table 4-38: Population of project affected Mapya Dudh Koshi Gaunpalika .............................. 86
Table 4-39: Population by caste/ethnicity and sex ...................................................................... 86
Table 4-40: Population distribution by mother tongue in the project Wards .............................. 87
Table 4-41: Religion of sampled households ............................................................................... 87
Table 4-42: Population migration pattern in the project area ...................................................... 88
Table 4-43: Households by outer wall of house/housing units .................................................... 89
Table 4-44: Vulnerable and disadvantage groups in the project area .......................................... 90
Table 4-45: Working age population (15 to 59) year of the project wards.................................. 90
Table 4-46: Production of Major Crops in the Project Area ........................................................ 91
Table 4-47: Major occupation of the Project Area ...................................................................... 91
Table 4-48: Livestock Herding in Project Area ........................................................................... 92
Table 4-49: Households by type of toilet facilities ...................................................................... 92
Table 4-50: Households by sources of drinking water ................................................................ 93
Table 4-51: Households by Type of fuel used for cooking in the project Wards ........................ 94
Table 4-52: Households by source of lighting ............................................................................. 94
Table 4-53: Distribution of Affected Population by Different Categories .................................. 97
Table 4-54: Age structure of the population of the sample HHs ................................................. 97
Table 4-55: Religious groups of sampled households ................................................................. 98
Table 4-56: Education Level of PAFs ......................................................................................... 98
Table 4-57: Land Categorization of Project Area ........................................................................ 99
Table 4-58: Income Source of Sampled HHs of Project Area ..................................................... 99
Table 4-59: Average Yearly Expenditure Range of the Sample Households .............................. 99
Table 4-60: Food Sufficiency in the Sample HHs ..................................................................... 100
Table 4-61: Sources of drinking water in the Sample HHs ....................................................... 100
Table 4-62: Sampled Households by type of toilets .................................................................. 100
Table 4-63: Distribution of Respondents by Perception about the Project ................................ 101
Table 4-64: Affected HHs by their preference on Modes of Compensation ............................. 102
Table 4-65: Distributions of Affected Households by Types of Cooking Fuel Used ................ 102
Table 5-1: Community Forestwise Forest Area Loss by Project components ........................... 111
Table 5-2: Standing Tree Loss due to the Proposed DK5HPP .................................................. 112
Table 5-3: Tree Basal Area, Volume and Biomass Loss Due to Proposed DK5HPP ............... 112
Table 5-4: Valuation of lost timbers and fuelwood ................................................................... 113
Table 5-5: Total Loss of Rare Endangered/Endemic Floral Species ......................................... 114
Table 5-6: Land required for construction of the project ........................................................... 117
Table 5-7: Annual loss of agricultural production and their valuation ...................................... 119
Table 5-8: Evaluation of Beneficial Impacts ............................................................................. 124
Table 5-9: Evaluation of Adverse Impacts ................................................................................ 126
Table 8-1: Awareness, Orientation and Training Plan............................................................... 150
Table 8-2: Permit and Approval Plan ........................................................................................ 151
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
vi| P a g e Department of Electricity Development
Table 8-3: Resettlement and Rehabilitiation Plan ..................................................................... 151
Table 8-4: Construction Camps and Traffic Management Plan ................................................ 152
Table 8-5: Pollution Abatement Plan ......................................................................................... 153
Table 8-6: Terrestrial Ecology (Forest Loss Management) Management Plan ......................... 156
Table 8-7: Aquatic Ecology Management Plan ......................................................................... 157
Table 8-8: Erosion Abatement and Muck/Spoil Management Plan .......................................... 159
Table 8-9: Public Health and Occupational Safety Management Plan ...................................... 161
Table 8-10: Rehabilitation Management Plan ........................................................................... 162
Table 8-11: Emergency Management Plan ................................................................................ 163
Table 8-12: Implementation Cost for Social and Environment Protection Measures ............... 168
Table 8-13: Estimated Cost for Environmental Monitoring ...................................................... 171
Table 8-14: Summary of the Project Environmental Costs ....................................................... 173
Table 10-1: Plan for Baseline Monitoring ................................................................................. 197
Table 10-2: Plan for compliance monitoring ............................................................................. 200
Table 10-3: Plan for impact monitoring..................................................................................... 203
Table 11-1: Environmental Audit Cost for DK5HPP ................................................................ 209
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
vii| P a g e Department of Electricity Development
LIST OF FIGURES
Figure 2-1: Project Location in Nepal map.................................................................................... 6
Figure 2-2: Project location in District Map .................................................................................. 7
Figure 2-3: Wards of Mapya Dudhkoshi Rural Municipality ........................................................ 7
Figure 2-4: Location Map of DK5HPP on Topographical map .................................................... 8
Figure 3-1 Plot Design (Nested quadrate plot) ............................................................................ 26
Figure 4-1: Catchment Area of Dudh Koshi River ...................................................................... 38
Figure 4-2: Flow Hydrograph ...................................................................................................... 41
Figure 4-3: Flow Duration Curve for Dudhkoshi River .............................................................. 41
Figure 4-4: Energy Table ............................................................................................................. 42
Figure 4-5: Low Flow Analysis by Weibul Method .................................................................... 43
Figure 4-6: GLOF events recorded in Nepal (after Mool et al. 1995, 2001a; Yamada 1998a;
Bajracharya et al. 2008; Ives et al. 2010)..................................................................................... 47
Figure 4-7: Simplified geological map of the Himalaya showing major litho-tectonic divisions
(After Gansser, 1964)................................................................................................................... 48
Figure 4-8: Generalized geological map of Nepal (modified afterUpreti and Le Fort, 1999) ..... 50
Figure 4-9: Geological Map of Eastern Nepal ............................................................................. 51
Figure 4-10: Geomorphic view of the powerhouse and surge tank area ..................................... 53
Figure 4-11: Project Location and Sagarmatha National Park .................................................... 58
Figure 4-12: Vegetation Zone in Project Area ............................................................................. 59
Figure 4-13: Tree Fern Habitat in Project Area ........................................................................... 77
Figure 4-14: House Structures and Settlement Patterns .............................................................. 89
Figure 8-1: Organogram of the Environmental Management Unit for Dudhkoshi-5 Hydropower
Project ........................................................................................................................................ 167
LIST OF ANNEXES
Annex 1 : Terms of Reference
Annex 2 : Project Components and Layout Maps
Annex 3 : Project Schedule and Environmental Monitoring Schedule
Annex 4 : Component Wise Cost Estmation
Annex 5 : Water Quality Test Reports
Annex 6 : Minutes of the FGDs and attendance Photographs
Annex 7 : Checklists, Questionnaires and Data Sheets used for Data Collection
Annex 8 : Social and Biological Details
Annex 9 : Public Hearing Related
Annex 10 : Recommendation Letters
Annex 11 : Photographs
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
viii| P a g e Department of Electricity Development
ACCRONYMS/ABBREVATIONS
AAPA : Aquatic Animals Protection Act
amsl : Above mean sea level
ARO : Assessment and Review Office
BOD : Biological Oxygen Demand
CAR : Catchment Area Ratio
CBD : Convention on Biological Diversity
CBO : Community Based Organizations
CDMA : Code Division Multiple Access
CF : Community Forest
CFC : Compensation Fixation Committee
cft : Cubic Feet
CFUG : Community Forest Users Group
CITES : Convention on International Trade in Endangered Species
of Wild Fauna and Flora
CPU : Catch Per Unit
DADO : District Agriculture Development Office
DBH : Diameter at Breast Height
DCC : District Coordination Committee
DFO : Division Forest Office
DHM : Department of Hydrology and Meteorology
DK 5 HPP : Dudh Koshi -5 Hydro Power Project
DO : Dissolved Oxygen
DoED : Department of Electricity Development
DPR : Detailed Project Report
DSS : Dissolved Suspended Solid
EA : Environmental Audit
EC : Electrical Conductivity
EIA : Environmental Impact Assessment
EMP : Environmental Management Plan
EMU : Environment Management Unit
EPA : Environment Protection Act
EPR : Environment Protection Rule
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
ix| P a g e Department of Electricity Development
FDD : Fisheries Development Directorate
FGD : Focus Group Discussion
FSL : Full Supply Level
GHG : Green House Gas
GIS : Geographic Information Systems
GLOF : Glacial Lake Outburst Floods
GoN : Government of Nepal
GRU : Grievances Redress Unit
GWh : Giga Watt per Hour
ha : hectare
HFT : Himalayan Frontal Thrust
HH : Households
IEE : Initial Environmental Examination
INGO : International Non-Government Organization
INPS : Integrated Nepal Power System
IUCN : International Union for Conservation of Nature
JMC : Joint Monitoring Committee
KII : Key Informant Interviews
kVA : Kilo Volt per Ampere
kWh : Kilo Watt per Hour
LARS : Land Acquisition and Rehabilitation Section
LCF : Local Consultative Forum
masl : Meter above seal level
MBT : Main Boundary Thrust
MCT : Main Central Thrust
MIS : Mitigation Implementation Section
MoEWRI : Ministry of Energy, Water Resources and Irrigation
MoFE : Ministry of Forests and Environment
MT : Mahabharat Thrust
MW : Mega Watt
NBSIP : Nepal Biodiversity Implementation Plan
NCS : National Conservation Strategy
NEA : Nepal Electricity Authority
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
x| P a g e Department of Electricity Development
NEFIS : Nepal Fisheries Society
NEPAP : Nepal Environmental Policy and Action Plan
N/L : Number per Liter
NGO : Non-Governmental Organization
NPWCA : National Park and Wildlife Conservation Act
NTFP : Non-Timber Forest Products
NWP : National Water Plan
PAF : Project Affected Families
PAP : Project Affected Persons
PIC : Project Information Center
PM : Particulate matter
PMO : Project Management Office
PoE : Panel of Expert
ppm : Parts per Millions
RM : Rural Municipality
SLC : School Leaving Certificate
SPAF : Severely Project Affected Families
TDS : Total Dissolved Solids
ToR : Term of Reference
TSS : Total Suspended Solids
TWL : Tailrace water level
UNFCCC : United Nations Framework Convention on Climate
Change
WECS : Water and Energy Commission Secretariat
WHO : World Health Organization
WRS : Water Resources Strategy
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
A| P a g e Department of Electricity Development
sfo{sf/L ;f/f+;
! k[i7e"ld
b'wsf]lz % hnljB't cfof]hgf ef}uf]lns ;d;+Vos cIff+z @&)@('$^'' pQ/ b]lv @&
)##'#)'' pQ/ / b]zfGt/
*^)$)'))'' k"j{ b]lv *^
)$#'#&'' k"j{ df cjl:yt 5 . h'g g]kfnsf] k|b]z gDa/ ! sf] ;f]n'v'Da' lhNnfdf kb{5
. o; cfof]hgfn] b'wsf]zL glbsf] kfgLnfO{ pkof]u ug]{5 h'g pRr lxdfnL If]q af6 pTkGg x'G5 . o;
cfof]hgfsf] k|:tfjs ljB't ljsf; ljefu /x]sf] 5 .
jftfj/0f ;+/If0f lgodfjnL, cg';'rL @ n] b'wsf]lz % hnljB't cfof]hgfnfO{ jftfj/0fLo k|efj d"NofÍg
(EIA) ug'{kg]{ ;d'xdf ;'rLs[t u/]sf] 5 . o; jftfj/0fLo k|efj d"NofÍg k|ltj]bg g]kfn ;/sf/sf] cfjZostf
nfO{ kl/k"lt{ ug{ tof/ u/LPsf] 5 .
@ cfof]hgf
cfof]hgf glbsf] axfjdf cwfl/t (Run of the River) k|sf/sf] k|:tfljt !!) d]ufjf6 Ifdtfsf] / l8hfOg
l8:rfh{ %@=$^ 3g dL6/ k|lt ;]s]08sf] /x]sf] 5 . sl/a !*=!) ld cUnf] jfFw yfg] vf]nf / b'wsf]zL glbsf]
bf]efg eGbf sl/j $% ld6/ tn dfKo b'wsf]zL ufpFkflnsfsf] jf8{ g= @ sf] /fK5f glhs} cjl:yt /xg]5 .
vf]nfsf] bflxg] lsgf/fdf jfFw;+u} /x]sf] kfgLsf] k|j]z dfu{n] kfgL lyufg]{ kf]v/L (Desilting/Settling basin)df
kfgL k|jfx ug]{ 5 / To; kfgLnfO ^!!$=)@ ld nfdf] ;'?Ë / ##@=$$ ld nfdf] el6{sn ;fkm\6÷OgSnfO8
;fkm\6÷k]g:6saf6 dfKo b'wsf]zL ufFpkflnsfsf] j8f gDa/ $, n"gd8fF8fsf] d'lg b'wsf]zL gbL / sf++s' vf]nfsf]
bf]efg eGbf &%) ld6/ dfly lgdf{0f ul/g] e"ldut ljB't u[xdf nlug]5 . cfof]hgfaf6 pTkflbt ljB'tnfO{
sl/a %=* ls= ld= nfdf] l;Ën ;ls{6 !#@ s]= eL= k|;f/0f nfO{g dfkm{t k|:tfljt b'wsf]lz $ hnljB't
cfof]hgfsf] k|:tfj ul/Psf] ;j:6];gdf nlug] 5 . cfof]hgfsf] ljlzi6 ?k (Salient Features) tnsf] tflnsf
! df lbOPsf] 5 .
Tfflnsf !M cfof]hgfsf] ljlzi6 ?k
;fdfGo
cfof]hgfsf] gfd b'wsf]lz % hn ljB't cfof]hgf
ljsf; k|sf/ gbLsf]] axfjdf cwfl/t
gbLsf] gfd b'wsf]zL
Gflhs}sf] ahf/ ;Nn]/L
:yfg ;f]n'v'Da' lhNNffsf] dfKo b'wsf]zL ufpFkflnsf jf8{ g= !, @, #, $ / & -
;fljssf] sfFs', jf;f, jfs' / h'ljª uf=lj=;= x?_
lhNnf ;f]n'v'Da'
k|b]z !
b]zfGt/ / cIff+z @&)@(' $^'' pQ/ @&
)##' #)'' pQ/
*^)$)' ))'' k"j{ *^
)$#' #&'' k"j{
afFw If]qsf] hnlj1fg
Hfnfwf/ If]q -afFw If]q ;Dd_ !%()=(# ju{ lsnf]ld6/
Hfnfwf/ If]q -ljB'tu[x_ !^!$=)* ju{ lsnf]ld6/
l8hfO{g k|jfx %@=$^ 3gld6/ k|lt;]s]08 -$) k|ltzt clwstfsf] ;Defjgf_
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
B| P a g e Department of Electricity Development
hl8t Ifdtf !!) d]ufjf6
;fdfGo hn ;tx !@%!=@% ld ;d'Gb|L ;txaf6
pRrtd hn ;tx !@%@=&% ld ;d'Gb|L ;txaf6
af‘w
afFwsf] lsl;d s+s|L6 afFw
afFwsf] nDafO{ / prfO{ $$ ld6/ nfdf] / !*=!) ld6/ cUnf]
kfgLsf] k|j]z dfu{ (Intake)
lsl;d cf]l/lkm; 6fO{k ;fO{8 OG6]s
;+Vof / k|sf/ (=% ld6/ km/flsnf] / % ld6/ pRr -@ j6f_
kfgL lyU|ofpg] kf]v/L (Settling
basin)
!% ld -Rff}8fO{_ x !(=^ ld -prfO{_x !%) ld -nDafO{_ -@j6f_
x]8/]; ;'?Ë (Headrace Tunnel)
nDafO{ ^!!$=)@ ld6/
qm|;;]S;g leqL k/L ;dfKt Jof; % ld6/
cl86 ;'?Ë –! @^% ld nfdf] / Jof; $ ld6/
;h{ ;fˆ6
lsl;d uf]nfsf/, hldg d'gL] /xg]
lelq Jof; !^ ld6/
prfO{ ^@=! ld6/
cl86 ;'?Ë –@ $%) ld nfdf] / Jof; $=%, #=% / @=% ld6/
cl86 ;'?Ë –@ s !@&=)^ ld6/ nfdf]] / $=% ld6/ Jof;
cl86 ;'?Ë –# $)$=@ ld6/ nfdf]] / $=% ld6/ Jof;
cl86 ;'?Ë –$ $#=@@ ld6/ nfdf]] / $=% ld6/ Jof;
cl86 ;'?Ë –% !#(=)@ ld6/ nfdf]] / ^=) ld6/ Jof;
cl86 ;'?Ë –% s *(=**ld6/ nfdf]] / %=) ld6/ Jof;
cl86 ;'?Ë –% v !()=$) ld6/ nfdf]] / $=% ld6/ Jof;
k]g:6s
Jof; #=% ld
nDafO{ #@$=$$ ld
ljB't u[x (kfj/ xfp;)
lsl;d e"ldut
cfsf/ &^=#) ld nfdf], !% ld km/flsnf] / #%=%) ld cUnf]
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
C| P a g e Department of Electricity Development
6]n/];
cfsf/ Uff]nfsf/
nDafO{ !*)=%( ld6/
6af{Og
6af{O{gsf] lsl;d km|flG;;
OsfO{ ;+Vof # j6f
zlQm / phf{ pTkfbg
;d|ut x]8 @%*=)( ld6/
cg'dflgt cjlzi6 x]8 @$!=&* ld6/
aflif{s cg'dflgt phf{ ^!*=*) uLufjf6 306f
;'Vvf (Dry) df};dsf] phf{ !))=#( uLufjf6 306f
aiff{ (Wet)df};dsf] phf{ %!*=$! uLufjf6 306f
k|j]z dfu{
bfDs' b]lv x]8jS;{ ^=! lsnf] ld6/ - %=^ ls=ld= lgdf{0f eO;s]]sf]_
bfDs' b]lv ljB't u[x &=$ lsnf] ld6/
cl86 @ ;Dd !=! lsnf] ld6/
;h{ 6ofÍ ;Dd )=$)# lsnf] ld6/
lgdf{0f cjlw $ jif{
cfly{s ;'rsx?
s'n nfut -g]=?=_ @)=@)$ ca{
cfof]hgfsf cGo cfjZos ;'ljwfx?df OlGhlgo/, 7]s]bf/ / >ldsx?sf] lzlj/, 9'ËfvfgL÷j/f] lk6, lgdf{0f
zlQmx?, lu§L km'6fpg], ;+u|x :yfg, Joflrª Knf06 / d]sflgsn of8{, :kf]On nfO{ k|jGw ug]{ :yfg /x]sf 5g\ .
oL ;a} ;'ljwfx? x]8jS;{ / ljB't u[x glhs /xg]5g\ . cfof]hgfsf nflu s/Lj @%=*#$ x]S6/ hldgsf]
cfjZostf kg]{5 h;dWo] @$=#@$ x]S6/ :yfoL ?kdf / !=%! x]S6/ c:yfoL ?kdf cfjZos kg]{5 . lgdf{0f
cjlwdf s/Lj %)) sfdbf/x? b}lgs ?kdf cfjZos kg]{5 . cfof]hgfsf] lgdf{0f $ jif{df ;+kGg ul/g] of]hgf
ul/Psf] 5 . cfof]hgfn] k|ToIf tyf ck|ToIf ?kdf ;f]n'v'Da' lhNNffsf] dfKo b'wsflz ufpFkflnsfsf] ;ft -&_
j6f j8fx? nfO{ k|efj kfb{5 .
# cWoogsf] k¢lt
k|:t't k|ltj]bg jftfj/0fLo k|efj d"NofÍgsf] nflu tof/ ul/Psf] :jLs[t If]q lgwf{/0f tyf sfo{;'rLsf] 9fFrf,
jftfj/0f ;+/If0f P]g, @)%#, jftfj/0f ;+/If0f lgodfjnL, @)%$, /fli6«o jftfj/0f k|efj d"Nofª\sg lgb]{lzsf,
!((# tyf cGo k|rlnt P]g, lgod tyf lgb]{lzsfx? adf]lhd tof/ ul/Psf] 5 . cWoogsf] qmddf :ynut
e|d0f, /fli6|o, :yfgLo tyf ;/f]sf/jfnfx? / ;/sf/L lgsfosf ljleGg k|ltlglwx? ;+u cGtls|{of ul/Psf] lyof]
. k"j{ tof/L cWoogdf cfof]hgfsf] lj:t[t cfof]hgf k|ltj]bg tyf cGo cfof]hgfx?sf] EIA k|ltj]bgx?
k"g/fjnf]sg ul/Psf] 5 . cfof]hgf :ynsf] cWoog, nlIft ;d'xdf 5nkmn tyf :yflgo JolQmx?;+u cGtjf{tf{
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
D| P a g e Department of Electricity Development
tyf k|ZgfjnL ;j]{If0f ul/ d:of}bf tof/ ul/Psf] ;fy} ;fj{hlgs ;'g'jfO{ kZrft ;/f]sf/jfnfx?sf] /fo ;'wmfj
;dfj]z ul/ tof/ ul/Psf] 5 .
$ P]g, lgod, sfg'g tyf gLltx?sf] ;dLIff
k|:tfljt cfof]hgfsf] jftfj/0fLo k|efj d"NofÍg k|ltj]bg tof/ ug]{ s|ddf hnljB't ljsf; ;+u ;DalGwt
ljBdfg jftfj/0fLo kIf;+u hf]l8Psf g]kfn ;/sf/sf] ljleGg of]hgf, gLlt, lgod, lgodfjnL, P]g,sfg'gx?sf]
;fy} cGt/f{li6«o ;lGw ;Demf}tfsf] ;dLIff ul/Psf] 5 . o:tf sfg'gL k|fjwfgx?sf] ;dLIff ug'{sf]d'Vo p4]Zo
hnljB't cfof]hgf lgdf{0fsf] ljleGg r/0fdf cfslif{t x'g] gLlt tyf lgodx? nfu' ug'{ xf] .;fy} /fli6|o
k|fyldstf k|fKt cfof]hgfsf] nflu /fli6|o jgIf]q k|of]u ug]{ ;DaGwL sfo{lalw, @)&$, d'n'sL b]jfgL P]g -
;lx+tf_, @)&$Ù x?sf] ;ldIff ul/Psf] 5 .
% ljBdfg jftfj/0fLo cj:yf
%=! ef}lts jftfj/0f
o; cfof]hgf If]q g]kfnsf] kxf8L If]qdf kb{5 . pQm cfof]hgfsf] afFw gbLdf / kfj/xfp; gbLsf] bfofF lsgf/df
/xg] 5 eg] s/La ^=!!$ ls= ld= ;'?ªsf] clwsf+; efu pQm :yfgdf cjl:yt kxf8sf] d'lgaf6 ;'?ªsf] lgdf{0f
ul/ hldg d'lgaf6 hfg] 5 . pQm If]qsf] r§fg tNnf] lxdfnL s'~h ju{sf] r§fg kb{5 h;df d'Vo ul/ lkmnfO{6
tyf lg; r§fgx? kfO{Psf 5g .
pQm cfof]hgfsf] afFw If]q vf]nfsf] au/ If]qdf kb{5 eg] To;sf] glhs} /x]sf] kxf8 hxfFaf6 ;'?ªsf] lgdf{0f
u/g] xf] pQm 8fF8f lg;tyf Sjfhf{O{6 r§fgx?n] ag]sf] 5 . sl/a ^=!!$ ls=ld= ;'?ª ljz]ift lg; / lkmnfO{6
h:tf vlghn] ag]sf] r§fg leqaf6 ;h{ 6ofÍ ;Dd k'Ub5 . ;h{ 6ofÍ /xg] If]qdf sf]n'lePn df6f] /x]sf] 5 .
kfj/xfp; If]qdf @) ld6/ ulx/fO ;Dd sf]n'lePn / Pn'lePn ldl>t df6f] /x]sf] 5 / @) ld6/ kl5 lg;
r6\6fg /x]sf] 5 .
of] cfof]hgf If]q ;d'Gb| ;tx b]vL !)#) / !#(% ld6/sf] prfOdf /x]tf klg glbsf] hnfwf/ If]q &)))
ld6/sf] prfO;Dd km}lnPsf] 5 . t;y{, hnjfo'sf] lx;fan] cfof]hgf If]q ;dlztf]i0f hnjfo' If]qdf kb{5 .
dg;'g dWo h'gdf z'? eO{ dWo ;]K6]Da/ ;Dd /xG5 . ;fwf/0ftof k'jL{o dg;'g aiff{ d] dlxgfdf x'G5 . l;:6
/ Sjfhf{O6 o; cfof]hgf If]qdf kfOg] d'Vo 9'Ëfx? x'g\ . o; If]qsf] jfo', kfgL / WjgLsf] cj:yf /fd|f] /x]sf]
5 . o; cfof]hgfsf] hnfwf/ If]qsf] cfsf/ 8]g8«fOl6s 5 / of] !%()=(# ju{ lsdL If]qdf km}lnPsf] 5 .
k|:tfljt cfof]hgf ;dlztf]i0f xfjfkfgL kfO{g] If]qdf kb{5 . o; If]qdf cf};t clwstd tfkqmd -@%-#) );]=_
/ cf};t Go"gtd tfkqmd dlxgfdf -–@ b]lv +@ );]=_ /]s8{ ul/Psf] 5 . k|:tfljt If]q g]kfnsf] bf];|f] ;]l:ds
hf]g (seismic zone) cGt{ut kb{5 eg] e' pkof]u sf] cfwf/df h+unL If]q, afFemf] hldg, s[lif of]Uo hldg
tyf jl:tx? kfO{Psf 5g\ .
%=@ h}ljs jftfj/0f
of] cfof]hgf If]q ;dl;tf]i0f hnjfo' If]qdf kb{5 . o; If]qdf lrnfpg]—s6'; / vf]6];Nnf]—rf}8fkft] jg kfO{G5
. cfof]hgf If]qsf] jl/k/L ;a} u/]/ & j6f ;fd'bflos jgx? kfO{G5g\ . ;Nnf], plQ;, lrnfpg], df}jf, c+u]/L]
cflb ?vx? cfof]hgf If]qsf d'Vo k|hfltx? x'g\ . ef]u6], ufOltxf/], P];]n', lrKn], w';'/, v/]6f] cflb a'6\ofg
k|hfltx¿ kfOG5g\ eg] xs{6f], cf+Vn], v¿sL, ljleGg k|sf/sf pGo", ltt]kflt, l;:gf]], v/ cfbL dl;gf la?jf
/ 3fF; k|hfltsf kfOG5g\ .
cfof]hgf If]qsf] jl/k/L !^ k|hfltsf :tgwf/L k|f0fLx? /]s8{ ul/Psf] 5 . ltlgx? dWo] jfFb/, :ofn, b'D;L,
v/fof] cflb d'Vo x'g\ . lrt'jf / 3f]/n 5]p5fpsf] hËndf slxn]sflx+ b]lvG5g\ . oxfF kfOg] d'Vo r/fx?df
sflnh, 9's'/, sfu, h'/]nL, k/]jf, sf]OnL / h+unL sfu cflb /x]sf 5g\ . 3;|g] hgfj/x?df 5]kf/f], ;k{x?
kfOG5g\ . oxfF d'Vo u/L r'Rr] c;nf, a'Rr] c;nf, ltt] / sfa|] hftsf df5fx? kfO{G5g\ .
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
E| P a g e Department of Electricity Development
%=# ;fdflhs cfly{s tyf ;fF:s[lts jftfj/0f
/fli6«o hgu0fgf, @)^* cg';f/ cfof]hgf k|efljt ;f]n'v'Da' lhNnfdf @#&*% 3/w'/L /x]sf 5g\ hxfsf] cf}ift
3/w'/L kl/jf/ $=$% /x]sf] 5 . pQm lhNnfsf] s"n hg;+Vof !)%**^ /x]sf] 5 h;df s"n dlxnfsf] hg;+Vof
%$^*^ -%!=^%%_ tyf s"n k'?ifsf] hg;+Vof %!@)) -$*=#%%_ /x]sf] 5 .
cfof]hgf k|efljt dfKo b'wsf]zL ufFpkflnsfdf @*)# 3/w'/L /x]sf 5g\ hxfFsf] cf}ift 3/w'/L kl/jf/ $=&*
/x]sf] 5 . k|efljt ufpFkflnsfsf] s"n hg;+Vof !#$!$ /x]sf] 5 . h;df s"n dlxnfsf] hg;+Vof ^**% tyf
s"n k'?ifsf] hg;+Vof ^%@( 5 . !$ jif{ d'lgsf] hg;+Vof #*=#( Ü 5 eg] ^) jif{ dflysf] hg;+Vof !(=@!
Ü 5 . !% jif{ b]lv %( jif{ ljrsf] hg;+Vof $@=#( Ü /x]sf] 5 . k|efljt ufpkflnsfdf s'n'Ë /fO{ hfltsf]
%!=%( Ü jfx'Notf /x]sf] 5 / z]kf{ !#=$* /x]sf 5g . cGo hfthfltx?df du/, tfdfË, a|fDX0f, If]qL, vflnË,
blnt cflb /x]sf 5g . To; If]qdf lxGb' / lxGb', af}¢ b'j} wd{ dfGg] dflg;x? kfOG5g . dfKo b'wsf]zL
ufpFkflnsfdf !) k|sf/sf efiffsf] k|of]u ul/G5 h;df d'Vo %)=$# Ü dflg;n] vflnË dft[efiff tyf g]kfnL
efiff af]nLrfnLsf] efiffsf ?kdf k|of]u ul/G5 . cfof]hgf If]qdf :jf:Yo, ;/;kmfO{, vfg]kfgL / kmfxf]/
Joj:yfkgsf cj:yf /fd|f] /x]sf] 5 . s[lif, kz'kfng, Aofkf/ tyf j}b]lzs /f]huf/L o; If]qsf k|d'v k]zfx?
x'g\ .;u/dfyf hfg] k}bn dfu{ oxL af6 ePsfn] el/of agL k}bn ofqf uP/ k};f sdfpg] klg ub{5g\ .
:yfgLon] of] bf];|f] Joj;fosf] ?kdf lnPsf 5g\ .cfof]hgf If]qsf w]/} h;f] afl;Gbfx? lxGb' wd{ dfG5g\
eg] s]xLn] af}4 wd{ dfG5g\ . oxfF dgfO{g] k|d'vrf8kj{x?df bz}+, ltxf/, Nxf];f/, df3] ;+qmfGtL, kmfu' k'0fL{df,
a'4 hoGtL, hg}k"0fL{df, >L k~rdL / tLh cflb kb{5g\ .
hDdf !)^ 3/w'/L pQm cfof]hgfaf6 k|ToIf k|efljt x'g] 5g . hxfFsf] cf}ift 3/w'/L kl/jf/ ;+Vof $=() 5 .
!$ jif{ d'lgsf] hg;+Vof @#=@) Ü 5 eg] ^) jif{ dflysf] hg;+Vof !@=)# Ü 5 . !% jif{ b]lv %( jif{ ljrsf]
hg;+Vof ^$=&^ Ü /x]sf] 5 . k|efljt 3/w'/Ldf /fO{ hfltsf]-%!=%(Ü_ jfx'Notf /x]sf] 5 . cGo hfthfltx?df
If]qL -^=@(Ü_ / z]kf{ -!#=$*Ü_ /x]sf 5g\ . sl/a %)Ü 3/w'/L lxGb' /x]sf 5g eg] $^=^& Ü 3/w'/Ln] lxGb',
af}¢ b'j} wd{ dfGg] ub{5g\ . ^!=@@Ü hg;+Vof ;fIf/ /x]sf 5g . sl/a ^$=@( Ü k|efljt 3/sf dflg;x? s[lif
k]zf ub{5g eg] sl/a $=%% Ü ljb]lzPsf 5g . cGo dflg;x? Aokf/ #=( Ü tyf gf]s/L &=&(Ü k]zfdf cfj¢
/x]sf 5g\ .
sl/a $)Ü k|efljt 3/w'/LnfO{ jif{e/L cfˆgf] pTkfbgn] vfgf k'Ub5 eg] !!=^& Ü 3/w'/LnfO{ # dlxgf vfgf
k'Ub}g / #^=^& Ü 3/w'/LnfO{ ^ dlxgf ;Dd vfgf k'Ub}g . vfgf gk'Ug] sl/a ^$=&% Ü 3/w'/Ln] cGo sfdaf6
/sd h'6fpg] ub{5g\ . !(=^@ Ü 3/w'/Ln] Hofnfdhb'/L tyf afsL j}b]lzs /f]huf/, Aofkf/ tyf gf]s/Laf6
vfgfsf] aGbf]a:t ldnfpb5g\ .
k|efljt kl/jf/sf] aflif{s cfo g]=?= @!^(*#=)) /x]sf] 5 h;dWo] @!Ü s[lifaf6, !%=&^ Ü Aofkf/ tyf
gf]s/Laf6 / afFsL Hofnf dhb'/L, ljk|]if0faf6 cfp5 . sl/a $%%kl/jf/sf] afli{fs vr{ g]=?= @))))) b]lv
#))))) lar /x]sf] 5, eg] sl/a *Ü kl/jf/sf] afli{fs vr{ g]=?= @))))) eGbf sd /x]sf] 5 .
^ ljsNkx?sf] ljZn]if0f
ljgf cfof]hgf ljsNknfO{ c:jLsf/ ul/Psf] 5 . lsgsL o;n] gt b]zsf] jt{dfg phf{ ;Í6nfO{ j9f]Q/L ug{
dBt u5{ g cfof]hgf lgdf{0f If]qsf :yfgLo jfl;Gbfsf] ljsf; pT;'stf nfO{ d4t u5{ . ljB't zlQmsf] cGo
ljsNkx?nfO{ cl:jsf/ ul/Psf] 5 lsgsL hnljB't b]zdf k|r'/ dfqfdf /x]s]f gljs/0fLo phf{sf] >f]t xf] .
hjsL cGo ljsNkx?n] phf{ ljsf;sf] nflu ljeLGg k|fljlws / k"gef{jL ljlQo ef/sf] ;fdgf ug'{ kg]{ x'G5 .
cfof]hgf :ynsf] ljsNkx?nfO{ lbOPsf] ef}uf]lns ;d;+Vosx?;+u d'Nof+sg u/LPsf] lyof] . jftfj0fLo
tyf cly{s b[li6«sf]0fn] k|:tfljt :yn / l8hfOgsf] ljsNknfO{ pQd dflgPsf] 5 .
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
F| P a g e Department of Electricity Development
& k|d"v jftfj/0fLo k|efjx?
o; cfof]hgfn] lgdf{0fsf qmddf s/La ^))-*)) c:yfoL /f]huf/Lsf] cj;/ ;[hgf ug]{5 h;df :yfgLonfO{
k|fyldstf lbOg] 5 . o;sf cltl/Qm, sfdbf/sf] pkl:yltn] /f;g nufotsf] cfk'lt{ ;DaGwL cGo Jofkf/sf]
cj;/ k|bfg ug]{5 . o; cfof]hgfn] :yfgLo:t/df k'jf{wf/ tyf ;fdflhs ;]jfsf] ljsf;df d2t k'¥ofpg] 5
h;n] :yfgLosf] hLjg:t/df ;'wf/ Nofpg] 5 . ;+rfngsf qmddf :yflgo hgtfnfO{ :yfoL /f]huf/sf] cj;/
;[hgf ug]{5 . ;a} eGbf dxTjk"0f{, o;n] k|lt jif{ ^!*=*) luufjf6 3G6f ljh'nL pTkfbg u/L b]zdf /x]sf]
phf{ ;+s6 s]lx xb;Dd ;dfwfg ug{ d2t ug]{5 . ;/sf/n] /fhZj / /f]olN6sf] ?kdf cltl/Qm cfDbfgL ug]{5
h;sf] dxTjk"0f{ lx:;f k|efljt If]qsf] ljsf;df vr{ ug{ kfOg]5 . cfof]hgf k|efljt If]qdf ;~rfng ul/g]
;fIf/tf jf cf}krfl/s–cgf}krfl/s lzIff, ;Lk ljsf; / cfo–cfh{gsf tflndn] :yfgLo ;/f]sf/jfnfnfO{ yk
cj;/ l;h{gf x'g]5 .
cGo ljsf; cfof]hgfx? h:t} o; cfof]hgfn] klg ;sf/fTds / gsf/fTds b'j}vfn] c;/ kfg]{ 5 . cfof]hgfn]
;/sf/L / lghL u/]/ hDdf @%=*#$ x] hUuf :yfoL / c:yfoL ?kdf csf]{ e"–pkof]udf kl/0ft ug]{5 . lgdf{0f
;DalGw ultljlw h:t} pTvgg\, 9fn s6fg, ;Dofpg] cflbn] :yfgLo e'agf]6nfO{ kl/jt{g ug]{5, 9fnnfO{
sdhf]/ agfpg], e"Ifo a9fpg] / gbLsf] kfgLdf wldnf]kgf a9fpg]5 . lgdf{0f sfo{, lgdf{0f ;fdlu|sf] 9'jfgL,
pTvgg\, l8«lnª, Anfl:6ª, x]le OlSjkd]G6sf] ;+rfng, qmz/ ;~rfng cflb sfo{n] jftfj/0fdf w'Fjf, w'nf], Wjlg
cfbL pT;h{g u/L jftfj/0fnfO{ k|b'lift agfpg]5 . lgdf{0fhGo / SofDksf] 3/]n' kmf]x/d}nf / 9nsf] sf/0f hn
/ hldg k|b'if0f x'g] ;Defjgf /xG5 . ;+rfngsf qmddf jftfj/0fsf] ef}lts cjojdf kg]{ c;/ vf]nfsf] axfj,
kmf]x/d}nf / sd{rf/L cfjf;sf] 9n Joj:yfkg;Fu ;DalGwt 5g\ .
cfof]hgfn] jftfj/0fsf] h}ljs cjojdf kfg]{ k|efjsf] ;DaGwdf jg / jg:kltdf kg]{ k|efjnfO{ dxTjk'0f{ dfGg
;lsG5 . cfof]hgf / o;sf ;xfos ;+/rgfx?sf] lgdf{0fsf] nflu s'n !%=!)$ x]S6/ jgn] cf]u6]sf] hUuf
lng'kg]{ x'G5 . cfof]hgf lgdf{0f ubf{ jgaf6 s'n #%!$ j6f ?vx? sf6\g' kg]{ b]lvG5 . o;sf cltl/Qm
jghËnaf6 pknAw x'g] jg k}bfjf/ tyf ;]jfsf] klg Ifo x'G5 . To;}u/L cfof]hgffsf sfdbf/ / u}/sfdbf/n]
ug{ ;Sg] sf7bfp/fsf] k|of]u, u}/ sfi7 jg k}bfjf/sf] k|of]u, h+unL hLjhGt'sf] rf]/L–l;sf/Ln] jgnfO{ k|ToIf
k|efj kfg]{ ;Defjgf /xG5 . o;n] ubf{ :yfgLo h}ljs ljljwtf / ltgsf] jf;:yfgdf gsf/fTds k|efj kg{
;Sb5 .
cfof]hgf ;+rfng cjwLdf jfFwn] hnr/Lo lhjx?nfO{ k'/\ofpg] /f]sfj6nfO{ dxTjk"0f{ gsf/fTds k|efj
dflgPsf] 5 . To;}u/L vf]nfsf] kfgLnfO{ jfFw If]qjf6 df]8\g' klg hnr/Lo kof{j/0f ;d:of ;+u ;DjlGwt 5 .
lsgeg] o;n] b'wsf]zL gbLsf] jfFw If]q b]lv dfx'/L vf]nfsf] ;+ud :yn;Ddsf] kfgLsf] dfqfnfO{ sd ub{5 .
lgdf{0f ultljlwaf6 pTkGg x'g] WjgL / sDkgn] / rf]/L–l;sf/Ldf sfdbf/sf] ;+nUgtfsf sf/0f jGohGt'sf]
;+Vofdf gsf/fTds c;/ kfg]{5 . jgsf] Iflos/0f / cfof]hgfsf] ;+/rgfsf] pkl:yltsf sf/0f jGohGt'sf]
cfjfudgdf :yfoL ?kdf c;/ kg]{5 . lgdf{0f ultljlwn] ;[hgf ug]{ c;xh kl/l:yltsf sf/0f jGohGt'sf]
cfjfudg, r/g / cGo Jojxf/df c;/ ug]{5 . gbL k|b'if0f, wf/ tyf jxfj kl/jt{gsf sf/0f df5f nufot
hnLo kfl/l:yltsLo k|0ffnLdf gsf/fTds c;/ kg]{ b]lvG5 . cfof]hgfjf6 x'g] sl/a @$=#@ x]S6/ hldgsf]
:yfoL clwu|x0fn] !)^ 3/w'/Lx?nfO{ k|ToIf ?kdf k|efj kf5{ . hldgsf] :yfoL clwu|x0fn] s'g} klg 3/w'/Lx?
ef}lts / cfly{s ?kdf :yfgfGt/0f x'g' kg]{ eg] 5}g . s[lifof]Uo hldgdf ljsf;sf ;+/rgf agfpbf To;df x'g]
pTkfbg 36\g]5 . lgdf{0fdf sfd ug]{ sfdbf/ / cGo Jofj;flos cj;/sf] vf]lhdf cfpg] le8sf sf/0f :yfgLo
;]jf;'ljwf ;DaGwL ;+w;:yf h:t} ljBfno, :jf:Yo ;+:yf, vfg]kfgL ljt/0f k|0ffnL, k|zf;lgs ;]jf, sfg"gL
;]jf, :yfgLo ahf/df cltl/Qm bjfj kg'{sf ;fy} ;du| ;/;kmfO{df k|efj kg]{5 . :yfgLo / jfx\o sfdbf/sf
ljrdf åGb ;[hgf x'g ;Sb5 . sfdbf/x?sf] Joj;fl;s :Jff:Yo / ;'/Iff klg dxTjk"0f{ ljifo xf] . hf]lvdk"0f{
sfo{df gfjfnssf] k|of]u, n}+lus Pj+ hftLo lje]bsf] klg ;d:of x'g ;Sb5g\ . zf/Ll/s lgs6tfsf sf/0f
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
G| P a g e Department of Electricity Development
3fts of}g/f]ux? km}lng] ;Defjgf klg /xG5 . ;+rfnsf qmddf lgdf{0fhGo /f]huf/Lsf] / cj;/sf] cGTosf
sf/0f :yfgLo hgtfsf] cfly{s ultljlw k|efljt x'g] b]lvG5 .
* gsf/fTds k|efj Go"gLs/0f tyf ;sf/fTds k|efjsf] a9f]Q/L
*=! gsf/fTds k|efj Go"gLs/0f
jftfj/0fLo tyf ;fdflhs k|efj Go"gLs/0fsf] k|lqmof cjnDag ug]{ lhDd]jf/L k|d'v ?kdf k|jw{ssf] /xG5 .
jftfj/0fLo tyf ;fdflhs ;'wf/sf pkfo tyf lqmofsnfkx?sf] sfof{Gjogsf] nflu cfj:os jh]6 klg oxfF
5'6\ofOPsf] 5 . sa'lnotdf lnOPsf] hldg hUufwgLnfO{ k'j{jt l:yltdf kmsf{Og] 5 . s[lifof]Uo hUufsf] dlnnf]
df6f] Ifo x'g glbg To;nfO{ ;+sng u/]/ ;'/lIft :yfgdf e08f/0f ul/g]5 . le/sf] s6fO{ ubf{ To;n] yfDg
;Sg] u/L dfq ul/g]5 . 7f8f / t];f{ gfnfx?sf] lgdf{0f ul/ e"IfonfO{ sd ul/g]5 . tNnf] t6Lo If]qdf ;'/IffTds
kvf{n, tyf t6aGw lgdf{0f ul/ gbLsf] :j?knfO{ ;'/Iff k|bfg ul/g]5 . gbLhGo pkhsf] pTvgg\ tyf ;+sng
ubf{ gbLsf] :j?knfO{ xfgL gk'¥ofO{ ul/g]5 .
w'nf] p8\g glbg k|d'v ;8sdf / sfo{:yndf kfgL 5ls{g] Joj:yf ldnfOg]5 . ;jf/L;fwgsf] lgoldt r]s
hfFr u/L To;af6 x'g] k|b'if0fsf] ;DaGwdf cfjZos sbd rflng]5 . kmf]x/d}nfnfO{ To;sf] k|sf/ cg';f/
5'6\ofO{ Pj+ l/tn] Joj:yfkg ul/g]5 . sfdbf/sf] ;+Vofsf] cfWff/df rlk{ / kfgLsf] Joj:yf ldnfOg]5 . lgdf{0fsf
qmddf pTkfbg x'g] df6f]nfO{ vfN6fv'N6L k'g{sf] nflu k|of]u ul/g]5 / afFsL plrt 9Ën] Joj:yfkg ul/g]5 .
c:yfoL ;+/rfgfx? cfof]hgf ;DkGg ePkl5 x6fOg]5 .
;/sf/L jg If]q / Toxfaf6 sfl6g] ?vsf] IftLk"tL{ jg tyf e"–;+/If0f k|rlnt sfg"gn] tf]s] adf]lhd ul/g] 5
. cfof]hgfn] cf]u6]sf] jg If]q a/fa/sf] hUuf lsgL ;/sf/nfO{ :jfldTj x:tfGt/0f ul/g] 5 . sf6\g'kg]{
?vx?nfO{ cWofjlws u/L, lrGx nfufO{ cfjZos dfqfdf dfq sl6g]5 . ;/sf/L jgaf6 sfl6g] k|To]s ?vsf]
abnfdf @% jf6f :yfgLo k|hfltsf lj?jfsf] jgIf]qsf] Ifltk"lt{jfkt lbOPsf] jftf]lsPsf] :yfgdf j[Iff/f]k0f
ul/g] 5 . ksfpg] ttfpg] k|of]hgsf] nflu bfp/fsf] k|of]u sd ug{ sfdbf/sf nflu dl§t]n jf Uof;sf] Joj:yf
ldnfOg]5 . sfdbf/nfO{ rf]/Llzsf/L ug{ / jg k}bfjf/x?sf] ;+sng ug{ /f]s nfufOg] 5 / o;sf] Joj:yf
cfrf/ ;+lxtf dfkm{t ul/g]5 . afFwjf6 vf]nfdf dfl;s k|jfxsf] !) k|ltzt kfgL jftfj/0fLo k|jfxsf] nflu
5f]l8g]5 / jfFwjf6 tNnf] tl6o vf]nfdf jftfj/0fLo k|jfxsf] sfof{GjognfO{ pko"Q ?kdf ul/g] 5 . lgdf{0f
sfo{nfO{ lbgsf] ;dodf dfq l;ldt ul/g]5 . cgfjZos pHofnf] alQx? Afflng] 5}g . t]n / /;fogx? ;xL
tl/sfn] pkof]u ul/g]5 . kmf]x/d}nf Joj:yfkgsf] plrt k|jGw ldnfOg]5.
hUufwlg;Fusf] bf]xf]/f] ;dembf/L cg';f/ cfjZos hUuf k|flKtsf] s'/f] ldnfOg]5 . c:yfoL ;+/rgf h:t}
sfdbf/sf] c:yfoL cfjf;, e08f/0f:yn cfbL sa'lnot jf ef8fdf lnOg]5 . v]taf/Ldf ePsf] jfnL gfz x'g]
cj:yfdf To;sf] k|rlnt ahf/d'Nosf] cfwf/df plrt Ifltk'lt{ lbOg]5 . :yfgLo ;]jf ;'ljwfdf bjfj sd ug{
7]s]bf/n] b}lgs pkef]Uo cfjZostf h:t} vfg] kfgL, ;+rf/, ljh'nL tyf vfgf ksfpg] OGwg, cflbsf] Joj:yf
SofDkleq} ug]{ 5 . lgdf{0f ultljlwsf sf/0f s'g} ef}lts ;+/rgfdf Iflt x'g uPdf To;sf] k'glg{df{0f jf
k'g:yf{kgf ul/g] 5 . k|efljt If]qsf :jf:Yo tyf lzIf0f ;+:yfsf] ;'wf/sf] nflu cfjZos ;xof]u k|bfg ul/g]5
. vfg]kfgL tyf l;+rfO{sf ;DaGwdf pknAw ljsNkx?sf] klxrfg ug]{ / ljBdfg ;|f]tx?sf] ;+/If0f ug]{ sfo{sf]
nflu k|fljlws tyf cfly{s ;xof]u pknAw u/fOg]5 . sfdbf/nfO{ /S;L vfg] / h'jf v]Ng] h:tf s[ofsnfkdf
;+nUg g/xg k|]l/t ul/g]5 . :yfgLo AolQmnfO{ cfof]hgfsf] /f]huf/Ldf k|fyldstf lbOg] 5 . k]zfut :jf:Yo /
;'/Iffsf] ;/f]sf/sf nflu cfjZos tof/L ul/g] 5 . sfdbf/x?nfO{ x]Nd]6, kGhf, a'6, ;'/IffTds k]6L, r:df,
df:s cflb k|bfg ul/g] 5 . lgdf{0f / e08f/0f:yndf cgflws[t k|j]z / ultljlw /f]Sg vt/fsf ;+s]tx?,
5]saf/ Pj+ kfn]sf] Joj:yf ul/g] 5 . gfjfnsnfO{ sfdbf/sf] ?kdf k|of]u ul/g]5}g .
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
H| P a g e Department of Electricity Development
cfof]hgfn] ln+u / hftsf] cfwf/df lje]b ug]{5}g . dfgj cf];f/k;f/nfO{ glhs af6 lgu|fgL ug]{ Joj:yf
ldnfOg]5 . lgdf{0f kZrft klg cfly{s s[ofsnfkdf :yfgLonfO{ ;+nUg u/fpg a}slNks lhljsf]kfh{gsf
;DaGwdf ljleGg tflndx? lbOg]5 .
cfof]hgf k|efljt kl/jf/x?nfO{ cfof]hgfn] lng] pgLx?sf] hUuf tyf ;DklQsf] nflu ;d'lrt Ifltk'lt{ lbOg]5
. pgLx?nfO{ cfof]hgf ;DalGw /f]huf/Lsf cj;/x?df / cfof]hgfn] ;~rfng ug]{ ljleGg lsl;dsf
tflndx?df klxnf] k|fyldstf lbOg]5 .
*=@ ;sf/fTds k|efjsf] a9f]Q/L
cfof]hgfn] ;fd"bflos ;fxfotf sfo{s|d cGtu{t cfof]hgf nfutsf] )=%)Ü /sd 5'§ofPsf] 5 / ljleGg
ef}lts tyf ;]jf k|bfossf sfo{s|dx? tyf ljleGg tflndx?cfof]hgfn] k|bfg ug]{5 .
( Jftfj/0fLo Aoj:yfkg of]hgf
jftfj/0fLo Aoj:yfkg of]hgfn] cfof]hgfsf lqmofsnfkx?sf] nflu k"j{ lgdf{0fsfn, / ;+rfngsfndf ul/g]
jftfj/0fLo cg'udg cfwf/ /]lvo cg'df]bg / k|efj cg'udg nfO{ ;dfj]; ub{5 . cg'udg–cfwf//]lvo,
cg'df]bg / k|efj cg'udgnfO{ ;dfj]z ub{5 . cg'udgsf] nflu dfkg ug{ ;lsg] ;'rsx?sf] >]0fLsf] 5gf]6
ul/Psf]5 . / ;fy} cg'udg ug]{ t/Lsfx? cg'udgsf] jf/Dj/tf cg'udg ul/g] :yn / cg'udgs]f nfuL
lhDd]jf/ sfo{sf/LnfO{ ;dj]z u/LPsf] 5 / ;fy} cg'udgsf nfuL cfjZos kg]{ nfut klg lbOPsf] 5 .
cfof]hgf k|efljt If]qdf cfof]hgf lgdf{0f / ;+rfngsf jftfj/0fLo kIf nfO{ pko'Qm lx;fan] cffof]hgf hLjg
rqmdf ;'gLZrLt ug{ ;+v'Jff vf]nfhnljB't cfof]hgf Joj:yfkg, k|fylds hLDd]jf/ ;+:yf ePsf]n] o;
jftfj/0Lo Joj:yfkg of]hgfdf zt{sf;fy cl3 ;fl/Psf d'Vo tTjx?nfO{ sfof{Gjog ug]{5 . jftfj/0Lo
Joj:yfkg of]hgfsf b'O{ k'/sx? x'g]5g\– jftfj/0Lo Joj:yfkg ult / sfof{Gjog ug]{ cË .
cfof]hgf jftfj/0fLo Joj:yfkg lqmofsnfkx?nfO{ tnsf lzif{sx?df lj:tf/Lt ?kdf ;dfj]z u/LPsf] 5 –
cg'dtL / :jLs[t of]hgf jftfj/0fLo tfnLd of]hgf k'g/jf; / k'g:yfkgf of]hgf lgdf{0f lzlj/ / 6«flkms
Joj:yfkg o]fhgf, k|b'if0f Go"gLs/0f of]hgf, hldgL kof{j/0f Joj:yfkg of]hgf, hnr/Lo kof{j/0f Joj:yfkg
of]hgf, e"–Ifo Go"lgs/0f tyf ds ÷ :KjfOn Aoj:yfkg of]hgf, hg:jf:Yo tyf Joj;foLs ;'/Iff Joj:yfkg
of]hgf, cfsl:ds Joj:yfkg of]hgf / k'g:yf{kgf of]hgf . dflysf of]hgfdf pNn]lvt tTjx? ;t{sf ;fy
cfof]hgfsf] hLjgrqm ;+u;u} hfg]5g\ .
g]kfnL jftfj/0f ;+/If0f gLodfjnL adf]hLd cfof]hgfsf] jftfj/0Lo Joj:yfkgsf] bfloTj k|:tfjssf] x'G5 .
l8hfOg ul/Psf cg'udgsf of]hgfx? tyf jftfj/0Lo Joj:yfkg of]hgfnfO{, ;/f]sf/jfnfdf plrt l/tn]
;'lgl:rt sfof{Gjog, cg'udg, d"Nofsg, ;'–;'lrt u/L k|ltls|of lng / ;'wf/ ug{ b'wsf]lz % hn ljB't
cfof]hgftyf kL Pd cf] n] cnu jftfj/0f tyf ;d'bfo ljsfz PsfO sf] :yfkgf ug]{5 . k|:tfljt jftfj/0f
tyf ;d'bfo ljsfz O{sfO{sf] d'Vou/L rf/ j6f sfo{x? x'g]5 . klxn]f o;n] k|efljt kIfx?sf] hUuf tyf
;Dkltsf] clwu|x0f, k'g{Zjf; tyf k'g{:yfkgfsf] sfof{Gjog tyf sfo{ lgikfbg ug]{5 . bf];|f]df o;n]
j9f]Q/Lsfsfo{qmdx?sf] cfof]hgf k|efljt If]qx?df sfof{Gjog tyf sfo{ lgKkfbg ug]{5 . t];|f]df o;n]
cfof]hgfsf ;/f]sf/jfnfx?df ;"rgf k|rf/Lt ug'{sf] ;fy} ljleGg lgsfox?nfO{ ;+of]hLt ug]{5 . rf}yf]df o;n]
jftfj/0fLo tyf ;fdflhs pkfox? / logsf sfdsfhsf] cg'udg ug]{5 . h'g jftfj/0fLo Aoj:yfkg of]hgf
tyf jftfj/0fLo cg'udg of]hgf jdf]lhd x'g]5 .
cfof]hgfsf] jftfj/0f tyf ;d'bfo ljsfz O{sfO{sf] :yfkgf cfof]hgfsf] l;eLn lgdf{0f sfo{sf] lg0f{o ug'{ eGbf
5 dlxgf klxn] ul/g]5 . cfof]hgfdf ;+nUg ljleGg ;/f]sf/jfnfx?n] ljleGg ;+:yfx?sf] k|ltlglwTj u5{g\ .
To;}n] k/:kl/o lgsfo ;dGjosf] h?/t k5{ . b'wsf]lz % hnljB't cfof]hgf Joj:yfkg sfof{nosf] jftfj/0f
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
I| P a g e Department of Electricity Development
tyf ;d'bfo ljsfz O{sfO{ k/:kl/o lgsfo ;dGjo ug]{ d'Vo lgsfo x'g]5 . lsgls o;nfO{ cfof]hgf :yndf
;"rgf k|rf/Lt ug{ / cfof]hgfsf] ;"rgf s]Gb| ;+rfng ug]{ k|d'v sfo{sf] nfuL lgo'Qm u/LPsf] 5 . :yflgo
;/f]sf/jfnfx? ljz]if u/L cfof]hgf k|efljt If]qsf lhNnf, ufpFkflnsf/ jf8{ ;+jlGwt ;/f]sf/jfnfx?;+u
5nkmnnfO{ Joj:yf ug{ jftfj/0f tyf ;d'bfo ljsfz O{sfO{ k|d'v lhDd]jf/ x'g]5g\ . cfof]hgfsf ultljlwx?,
k|ultx? / kIfx?sf] d"Vo ;"rgf lbgsf nflu jftfj/0f tyf ;d'bfo ljsfz O{sfO{ k|d'vn] sDtLdf b'O{ dlxgfsf]
Ps k6s k/:k/Lo ;dGjo 5nkmn jf]nfpg] 5g\ h;n] ;xefuLo ljlw dfkm{t ljjfb cflbsf] ;dfwfg ug]{5.
;/f]sf/jfnfx?n] p7fPsf] rf;f]x?sf] sfo{ k|ult ;DjGwL ;'emfjx?nfO{ :yflgo ;/f]sf/jfnfx? ;+usf] 5nkmndf
afl8g]5g\ . b'wsf]lz % hnljB't cfof]hgfsf] jftfj/0fLo n]vf kl/If0f cfof]hgf ;dfkgsf] b'O{ jif{ kl5 z'?
ul/g]5 . b'wsf]lz % hnljB't cfof]hgfn] n]vf k/Lif0fsf] nfuL cfjZos k|jGw g]kfn ;/sf/ jf cGo dgf]gLt
n]vf k/LIfs dfkm{t ug]{5 .
!) jftfj/0fLo Go"gLs/0f, cg'udg, n]vf k/LIf0f tyf Joj:yfkg nfut
jftfj/0fLo cg'udgsf] nflu hDdf g]=? ((,^),)))÷– 5'§ofOPsf] 5 . o; kl/of]hgfsf] jftfj/0fLo
Aoj:yfkg, jftfj/0fLo clej[l4, ;fd'bflos ;xof]u sfo{qmd tyf jftfj/0fLo kl/If0f sfo{qmdsf] nflu hDdf
cg'dflgt g]= ? @&$,)$$,@()÷– 5'§ofOPsf] 5 .
!!= lg:sif{
of] cfof]hgfn] lghL ;DklQdf a9L k|efj kfg]{5 eg] ;fj{hlgs ;DklQdf Go"g vfnsf] k|efj kfg]{5 . cfof]hgfn]
clwu|x0f ug]{ hUuf, ;DklQ tyf vfBfGg jfnLsf] nflu gub /sd g} Ifltk"lt{ lbg k|:tfj u/]sf] 5 .
cfof]hgfsf] k|s[lt, :yfg, hgtfsf] cfof]hgf k|ltsf] ;sf/fTds ;f]r, d"Nofª\sg ul/Psf jftfj/0fLo
k|efjsf] k|s[lt Pj+ sfof{Gjog ug{ ;lsg] k|efj Go"gLs/0fsf pkfox?, hn;|f]tsf] pkof]u Pj+ jftfj/0f
;DaGwL ljBdfg gLlt tyf sfg'gnfO{ Wofgdf /fVbf of] cfof]hgf sfof{Gjog ug{ pko'Qm x'g] b]lvPsf]n]
sfof{Gjogsf] nfuL ;'emfj ul/Psf] 5 . cfof]hgfsf] :jLs[ltsf] nflu yk jftfj/0fLo cWoog cfjZos
b]lvb}+g . xfn klxrfg gePsf t/ lgdf{0fsf] cj:yfdf b]vfkg{ ;Sg] jftfj/0fLo k|efjx?nfO{ ;s];Dd
rfF8f] Go"gLs/0f ug'{kg]{ 5 .
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
J| P a g e Department of Electricity Development
EXECUTIVE SUMMARY
1. Background Dudhkoshi 5 Hydropower Project (DK5HPP) located in between the geographical coordinates,
latitudes 27°29’46” N to 27°33’30” N and longitudes 86°40’00” E to 86°43’37” E in Solukhumbu
district of Province Number 1 of Nepal. This project will utilize water resources of theDudhkoshi
River, a natural river originated from high Himalayas. Department of Electricity Development
(DoED) is the project proponent. The Environment Protection Rule Schedule II classifies
DK5HPP as an Environmental Impact Assessment (EIA) category project. This Environmental
Impact Assessment Report is prepared to meet the requirements of the Government of Nepal.
2. The Project The project is a run-of-river (R-o-R) type with a proposed installed capacity of 110 MW with a
design discharge 52.46 m3/s (40 percentile flow). The diversion weir of height 18.10 m will be
constructed about 45 m downstream from the confluence of Thane Khola and Dudhkoshi River
near Ranem in Ward no. 2 of Mapya Dudhkoshi Rural Municipality. The intake on the right bank
will feed the settling basin and is diverted to the underground Powerhouse located at the right
bank of the Dudhkoshi River nearLunam villfgxage in Ward no. 4 of Mapya Dudhkoshi Rural
Municipality through 6114.02 m long headrace tunnel and 332.4 m long vertical shaft/inclined
shaft/penstock. A 5.8 km long 132 kV single circuit transmission line from powerhouse to the
proposed substation of Dudhkoshi 4 hydropower project will be used for evacuation of energy
generated by the Project. The salient features of the project are presented in Table 1.
Table 1: Salient Features of the Project
GENERAL
Type of Project : Run-of-River
Name of River : Dudh Koshi
Nearest Town : Salleri
Rural Municipality : Mapya Dudhkoshi Rural Municipality (Previously Waku, Kaku, Basa
and Jubing VDCs)
District : Solukhumbu
Province No. : 1
GEOGRAPHICAL COORDINATES
Latitude : 27°29’46” N to 27°33’30”N
Longitude : 86°40’00” E to 86°43’37”E
HYDROLOGY
Catchment Area at Intake : 1590.93 km2
Catchment Area at
Powerhouse
: 1614.08 km2
Design Flow (Q40) : 52.46 m3/s
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
K| P a g e Department of Electricity Development
Normal Water Level
(NWL)
: 1251.25 masl
Maximum Water Level
(MWL)
: 1252.75 masl
DIVERSION WEIR
Type : Concrete Gravity ( 3 numbers of gate)
Crest Length : 44 m
Maximum Height : 18.1 m above bed level up to weir crest
Design Flood Discharge : 4353.08 m3/s
GRAVEL TRAP
Type : Integrated with Intake
Numbers : 2
Size (L x B x H) : 16 m x 9.5 m x 16 m
Bed Load Size to Trap : 5 mm
APPROACH TUNNEL
Type : Inverted D-shaped
Numbers : 2
Diameter of Tunnel : 4.4 m
Length
Approach Tunnel- 1 : 194.53 m
Approach Tunnel- 2 : 167.61 m
Bed Slope : 1:500
DESANDING BASIN
Type : Underground/Dufour
No. of Chambers : 2
Nominal Size of Trapped
Particle
: 0.2 mm
Trap Efficiency : 90%
Size (L x B x H) : 150 m x 15 m x 19.6 m
Normal Operating Level : 1250.715 masl
Maximum Water Level : 1252.215 masl
HEADRACE TUNNEL
Diameter : 5 m
Length : 6114.02 m
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
L| P a g e Department of Electricity Development
Finish Shape : Circular
SURGE TANK
Type : Restricted Orifice, RCC lined
Shaft Diameter : 16 m
Orifice Diameter : 2.2 m
Height : 62.1 m
Shape : Circular
PENSTOCK TUNNEL/SHAFT
Type : Circular, Steel Lined
Length : 324.44 m
Finish Internal Diameter : 3.5 m
POWERHOUSE
Type : Underground
Dimension (L x B x H) : 76.3 m x 15 m x 35.5 m
Turbine Axis Level : 985.0 masl
SWITCHYARD
Type : Underground
Dimension (L x B x H) : 80 m x 12.9 m x 16.1 m
TAILRACE
Type : Pressurized Tunnel
Diameter : 5 m
Length : 180.59 m
POWER FACILITIES
Installed Capacity : 110 MW
GENERATORS
POWER TRANSFORMERS
CONSTRUCTION
PERIOD
: 4 yrs.
FINANCIAL INDICATORS
Total Project Cost : 20.204 billion NRs.
Other project facility requirements are the camps for engineers, contractors, and labours;
quarry/burrow pits; construction powers, aggregate crushing, storage yards, Batching plants and
mechanical yards; spoil disposal sites etc. All of these facilities will be located close to the
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
M| P a g e Department of Electricity Development
headworks and powerhouse sites. A total of 25.834 ha of land will be required for the project. Of
the total, 24.324 ha is permanent land requirement while 1.51 ha is temporarily required.
A total of about 600-800 construction workforces is required on daily basis during construction
period. The project is planned for construction within a period of four years. The project will
affect either directly and/or indirectly all 7 wards of Mapya Dudhkoshi Rural Muncipality (dfKo
b'wsf]zL ufpFkflnsf) of Solukhumbu district.
3. Study Methodology The EIA process followed the Environment Protection Act, 1997 (EPA 2053), EPR, 1997 (2054)
and National EIA Guidelines, 1993. The EIA report was prepared as per the legal provisions of
the GoN and based on the approved Scoping and ToR. Field studies by the team of professionals,
interaction and consultation with the local people, stakeholders and the official of GoN line
agencies were conducted. Likewise, review of pertinent literatures, field survey, observation,
sampling, checklist and questionnaire administration, group meetings and impact assessment
matrix were the main methodologies applied for the Environmental Impact Assessment study of
the proposed project.
4. Legal aspects and Compliance requirements The prevailing plans, policies, acts, rules/regulations, guidelines, standards, conventions and
strategies related with development of the hydropower projects in Nepal were reviewed during
the preparation of EIA report.
According to Environment Protection Act (EPA), 1997 and Environment Protection Rule
(EPR),1997 this project has to conduct Environmental Impact Assessment (EIA) study and get
approval from the Ministry of Forests and Environment (MoFE). Apart from this, this EIA study
has followed Nepal Government different Policies, Guidelines, Acts, Rules and Regulations,
Standards, Manuals, Directives and International Conventions which includes Constitution of
Nepal, Hydropower Development Policy 2058 B.S., Forest policy 2071 B.S., National EIA
Guideline-2050, Water Resources Act and Regulations, Forest Act 2049 B.S., National Parks and
Wildlife Conservation Act 2029 B.S., Aquatic Animal Protection Act,/fli6«o k|fy{ldstf k|fKt
cfof]hgfsf nflu /fli6«o jg k|of]u ug{ lbg] ;DalGw sfo{ljlw @)&$, hUufsf] xbalGb 5'6 lbg] ;DalGw cfb]z
@)&$, ;+s6fkGg jGohGt' tyf jg:kltsf] cGt{/fli6«o Jokf/ lgoGq0f P]g, Convension on International
Trade in Endangered Species of Wild Fauna and Flora (CITES), 1993, Muluki Civil Act (Code),
2073, Convention on Biodiversity 1992,Convention (No.169), Concerning to Indigenus and
Tribal People Independent Countries 1991 etc.
5. Existing Environmental Condition The elevation varies from 980 m amsl at Powerhouse area to 1260 m amsl at the weir. The
catchment of DK5HPP at headworks is 1593.90 sq.km. The project area lies in the middle
mountain physiographic zone.
The project area has a rugged topography with steep hills and deep river valleys. The project area
experiences sub-tropical climate. According to the data recorded in the nearest meteorological
stations, mean annual rainfall in Dudhkoshi catchment is 2111 mm. Gneiss, phyllite and schist
are the main rock types in the project area. Minor activities of landslides were observed near to
the project construction sites. There is no risk of GLOF and its impact on the project structures.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
N| P a g e Department of Electricity Development
Water from the Dudhkoshi River does not find any consumptive use like drinking water supply,
micro-hydro, water mills and irrigation purposes at the immediate upstream and throughout the
low flow zone of the project. The average monthly flow data reflects that the lowest flow of 14.82
m3/s during the month of March and highest flow recorded 259.11 m3/s in the month of August
at the proposed intake site of the project. Since the area is located in rural natural setting, the
ambient air quality, water quality and noise levels are not influenced by the industrial pollutions.
The project area is composed of mixed broadleaved forest. The overall project area is dominated
by Hill Sal and the other associated species include Chilaune, Siris, Uttis, Khirro, Gayo etc.
Plantation of Okhar was also observed in the private land in the project area. The project will
acquire 15.104 ha of forest. Altogether16 mammalian species, 58 species of birds and 16 species
ofHerpeto fauna have been reported in the project area. Similarly, 4 species of fish were reported
from th river stretch within the project area.
The total population of the affected area is 13,414 (6,529 male and 6,885 female) with average
household size of 4.78. The population of the area is dominated by Kulung Rai (51.59 %)
followed by the Tamang, Magar, Chhetri, Kami, and other groups.
Total of 106 households will be affected by the project having average household size of 4.90.
The Household survey shows that about 23.20 % of the populations are children. Likewise, 12.03
% of the population is above 60 years of age and 64.76 % of the population is between the age of
16 and 60 years. Rai (51.59%) is the dominant caste group among the affected households
followed by Chhetri (6.29%) and Sherpa (13.48%). Of the surveyed households, 50% follow
Hinduism and 46.67 % follow both hindu and budhist religion. Sparse population follow
Christianity as well. The literacy rate accounts about 61.22 %.
More than 64.29% of the households are involved in agriculture for their primary livelihood.
Besides agriculture, 4.55 % are in foreign employment, 3.90 % in business, 7.79% are engaged
in service, 5.06% are employed in trekking (potter), and 5.32 % in wage labor etc.
Only 40% households have food sufficiency for 12 months. Among the remaining households,
about 26.23% households have inadequate food for 3 months, 38.52% households have food
deficit for 6 months. Food deficient 64.75% households manage from other sources of income.
19.29% households manage from wage labour and remaining households manage from foreign
employment, business and services.
The average annual gross income of the surveyed HHs of the project area is estimated to be NRs.
2,16,983.00 per household which includes 21% from agriculture, 30.58% from business and
services and remaining from wage labour and remmitance.
Average annual gross expenditure per household of the sampled HHs shows that the majority of
the households (45.00%) expend 200,000 to 300, 000 per year range and about 8% of the
household expend less than NRs. 200,000 per year.
6. Alternative Analysis The no project alternative is rejected as it does not help relieve the current ongoing load shedding
inthe country, nor does it help development aspirations of the local area people of the
projectdevelopment site.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
O| P a g e Department of Electricity Development
Other alternatives to electricity power were rejected, as hydropower is a renewable resource
abundant in the country while others require a number of technical and recurrent financial burdens
for the power development.
The project location alternatives within the given geographical coordinates were evaluated and
location and design alternative is considered the best from the environmental and economical
perspective.
7. Environmental Impacts During construction phase, the project will provide temporary employment opportunities to 600-
800 people and priority will be given to local people. Additionally, the presence of workforce will
provide subsidiary business opportunities related to provisioning and recreations to the local
people. The project will support development of local infrastructures and social services facilities
and their service delivery system in the project impacted area which will enhance the living
standard of the local people.
During operation and maintenance, it will provide permanent employment opportunities to local
people. Above all, it will generate 618.80 GWh energy annually and help to address the energy
crisis of the country to some extent. The government will get additional benefit from royalty and
revenue.
The GoN will benefit from additional income in terms of revenue and royalty which will be shared
for the development of affected area. Local people will get additional opportunities from the
formal and informal education, skill development and income-generating trainings to be
implemented in the project area.
Like any other development projects, this project is also likely to produce both beneficial and
adverse impacts on the existing natural settings and society. A total of 25.834 ha of land will be
acquired permanently and temporarily for the project and changed to another land use for project
implementation. The construction activities like excavation, slope cutting and grading will lead
to changes in local topography, disturb the fragile slopes and make soil loose eventually causing
erosion and siltation of the water body. The construction works, transportation and handling of
construction material, excavation, drilling, blasting use of heavy equipment, operation of crushing
and batching plant, etc., will emit significant amount of dust and emissions causing air pollution
during construction phase.
Solid and liquid waste generated from construction works and camping activities will degrade
water quality and pollute land. The impact on physical environment during operation phase is
related with the reduced flow of water, solid waste form residential camp and camp wastewater
management. Regarding the impact of project on biological domain of environment, major impact
is envisaged on forest, wildlife and aquatic life. Sitting of the project features and ancillary
facilities will acquire about 15.104 ha of forest area. Altogether, 3514 of trees different species
will be felled from the forest during project construction. This will also result loss of forest goods
and services. Similarly, during the construction period, worker and non-workers are likely to cut
down trees for firewood and timber to build residences, stalls and shades. They may also be
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
P| P a g e Department of Electricity Development
involved in illegal collection and selling of NTFPs. All this will have negative consequence on
local biodiversity and habitat.
The barrier created by the weir structure to the aquatic life is a significant adverse impact of the
project in the operation phase. Similarly, the diversion of water is the other issue of aquatic
ecology concern as it dewaters the stretch of the river downstream till the confluence with the
Mahuri River.
Noise and vibration produced by project activities and hunting/poaching by project labour force
may affect the population of wildlife in the area. The loss of forest due to placement of project
structures and facilities will produce long term localized impact on movement of the wildlife.
Construction disturbances resulting from drilling, vehicle movement and other related activities
would interrupt normal movement, feeding and other activities of animals. Water pollution,
reduction in current and discharge will have negative implication on fish and aquatic ecosystem.
The project affects 106 households directly by permanent land acquisition of about 4.133 ha. No
households will be physically and/or economically displaced by the project permanent land
acquisition.
Change in the cultivable land into development will reduce the agricultural production. Influx of
people in the form of workforce and subsidiary business opportunity seekers will put pressure on
the social service institutions particularly educational facilities, health services, water supply
systems, administrative services, law and order maintaining institutions, local markets and supply
institutions and above all the sanitation of the area. Conflict may arise between the local people
and outsider labours during the project construction. The construction workforces will be exposed
to a number of constructions related health risks and hazards. Child labour, gender and racial
discrimination may occur in project area. The cultural and traditional activities in the local area
will be influenced. Sexual intimacy between workers and local people may spread diseases like
HIV/AIDS and STDs. Due to the decline in construction related works, the economic activities
of local people will be influenced in operation phase.
8. Mitigation of Adverse Impacts and Enhancement of Beneficial Impacts
8.1 Mitigation of Adverse Impacts
Proponent will have the prime responsibility for implementation of mitigation and enhancement
method. Necessary budget has been allocated for the implementation of these measures. The
leased land will be returned to the owner after proper treatment/rehabilitation. To conserve top
soil, the top soil shall be collected and stored in a safe place protected from washout and fanning.
Slope of the cutting areas shall be maintained at less than the angle of repose to the extent possible.
Both vertical and horizontal drains will be provided to minimize the soil erosion problem.
Extraction of riverbed materials will be done without affecting the existing river morphology.
Water spraying will be carried out and vehicles will comply with the national emission standards
and regular (monthly) check-up for maintenance. Wastes will be separated, recycled, reused or
disposed as per its type. Camps will be provided with toilet and drinking water facility depending
on the number of workforces.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
Q| P a g e Department of Electricity Development
Generated spoil will be used as back fill materials as far as possible and remaining spoil will be
managed properly. The temporary facilities will be dismantled after construction works are over.
The forest area and trees felled will be compensated as per the prevailing law. Land equaling the
area of forest to be acquired by the project will be bought and handed over to GoN. Trees that are
likely to be removed shall be counted, marked and harvested with the proper forest techniques.
The project will plant at least 25 saplings of locally suitable species for the loss of each tree at the
compensated land or site designated for plantation. Alternative fuels such as kerosene or LPG
will be introduced for cooking and heating purpose to reduce use of forest resources. In order to
avoid or minimize potential threat such as illegal cutting and collection of forest products, it is
recommended for best utilization of the forest products extracted as a part of site clearance. The
proponent will prohibit the project workers from game hunting and poaching and any kind of
illegal activities through code of conduct. A minimum of 10% of the monthly flow will be
released in the dewatered section and the releasing mechanism will be properly ensured.
Construction works shall be scheduled in daytime. The oil and lubricants will be handled properly
creating an impervious surface. Proper solid waste management plan will be implemented. All
the land to be acquired will be settled by bilateral negotiation with landowners. Area required for
the other project activities such as work camp, borrow areas, spoil disposal area, and stockpile
area for the construction materials, etc. will be taken on lease or rent. Standing crop will be
compensated as per the local market price. The contractor will manage utilities like, lighting and
cooking energy, drinking water supply, etc., within the camp so as to avoid the pressure on local
services. Infrastructural and educational support will be provided to the schools of the project area
on priority basis. Support will be provided to upgrade existing educational institutions and health
service facilities. Alternative source of drinking water will be identified and developed or existing
water resources and infrastructures will be improved. Workforce will be discouraged to involve
in activities like gambling and alcoholism. Local people will be given maximum priority in
employment. Safety equipment such as helmets, boots, gloves, safety glasses and masks will be
provided for workers those working in the construction sites. Guards, fences, barricades and
informative signposts will be installed at construction sites and storage yard to prevent
unauthorized entry. Child labour will be prohibited totally. Gender and racial discrimination will
not be entertained by the project. The prohibitory law against human trafficking and prostitution
will be strictly enforced and local security force as well as concern community will be informed
about the need of effective surveillance. Project will promote alternative livelihood activities by
training on improved agriculture and other off-farm activities.
The Project Affected Families will be provided respectable compensation for the land and
property they lose to the project. They will be given primary priority in project related
employment opportunities and all types of training opportunities.
8.1 Enhancement of Beneficial Impacts
Project has allocated 0.50% of total project cost as a Community Support Program and different
infrastructure and service supports and training programs will be provided by proponent.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
R| P a g e Department of Electricity Development
9. Environmental Management Plan Environmental monitoring plans include the environmental monitoring during pre-construction,
construction and operation phases for baseline, compliance and impact monitoring of the project
activities. A set of measurable indicators have been selected for the monitoring and the plan
includes methods of monitoring, monitoring frequency, monitoring location, and personnel
responsible for monitoring along with the costs required for monitoring.
To ensure that the environmental issues of the project development and operation in the project
impact areas are properly addressed during the project life cycle, the DK5HPP project
management, as the primary responsible institution, will implement the key elements prescribed
in the environmental management plan. The environmental management plan has two
components: the environmental management activities and implementing organ.
The environmental management for the project is broadly included in the following headings:
permits and approval plan; environmental training plan, resettlement and rehabilitation plan;
construction camps and traffic management plan; pollution abatement plan; terrestrial ecology
management plan, erosion abatement and muck/spoil management plan, public health and
occupational safety management plan, emergency management plan, and rehabilitation plan. The
elements mentioned in the above plan go hand in hand throughout the project life cycle.
As per the Environment Protection Rules, environmental management of the project is the
responsibility of the proponent. To ensure that the designed monitoring plans and environmental
management plans are duly implemented, monitored, assessed, evaluated and disseminated to the
stakeholders for feedback and improvement, the DK5HPP, Project Management Office (PMO)
should establish a separate Environment Management Unit (DK5-EMU). The proposed DK5-
EMU has four major roles to play. First it will implement and administer land and property
acquisition, resettlement and rehabilitation of affected parties. Second it will implement and
administer the enhancement program in the project-affected areas. Third it will disseminate
information to the project's stakeholders and co-ordinate with the different line agencies. Fourth
it will monitor the environmental and social measures and its performance as per environmental
management plan and environmental monitoring plan.
The project DK5-EMU shall be established at least six months before the project's civil
construction award. The stakeholders involved in the project represent different institutions.
There is a need to have an interagency coordination. DK-EMU of the DK5HPP project
management office is the key agency which will be involved in the interagency coordination as it
has been assigned key role in the information dissemination and operation of the project
information center at the project site. The DK5-EMU Manager will be responsible for the
organization of meetings with the local stakeholders, particularly district, rural municipalities and
ward-based stakeholders of the project affected area.
Environmental audit of DK5HPP will begin after two years of the commencement of the project.
The project will make necessary arrangements for this audit through GoN or its nominated
auditor.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
S| P a g e Department of Electricity Development
10. Environmental Mitigation, monitoring, auditing andManagement Costs For the environmental monitoring total NRs. 99,60,000/- have been allocated. An amount of NRs.
274,044,290.00/- has been allocated for mitigation measures, enhancement activities CSP and
auditing.
11. Conclusions The project will have significant impacts on the private property and insignificant impacts on
public property. Cash compensation for the acquisition of land and crops has been proposed.
Taking into consideration the nature of project, its location, people's positive response, evaluated
environmental impacts and practical mitigation measures, including existing policies and laws on
water resources utilization and the environment, this project is recommended for implementation.
However, unforeseen environmental impacts identified during the construction stage will have to
be mitigated in a timely manner.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
1| P a g e Department of Electricity Development
1. NAME AND ADDRESS OF THE INDIVIDUAL/INSTITUTION
PREPARING THE REPORT
1.1 The Proponent
Department of Electricity Development (DoED) is the proponent of the Dudh Koshi-5
Hydropower Project (DK5HPP). The detail of the proponent and contact address is given
below:
Department of Electricity Development
Sano Gaucharan, Kathmandu, Nepal
Phone: (977-1-) 5244326
Fax: (977-1-) 5244257
Email: [email protected]
1.2 Organization Responsible for Preparing the Report
This EIA report has been prepared by the JV of Silt Consultants (P.) Ltd., Insight Engineering
Consult (P.) Ltd. and Rajdevi Engineering Consultants (P.) Ltd on behalf of Department of
Electricity Development.
The detail address of the consultant is given below:
SILT Consultants (P.) Ltd.
Insight Engineering Consult (P.) Ltd.
Rajdevi Engineering Consultants (P.) Ltd.
Ratopul, Goushala, Kathmandu, Nepal
P.O. Box: 2724, Kathmandu
Tel: +977-1-4487598, 4475139; Fax: 00977-1-4473573
Email:[email protected], [email protected], Website:www.silt.com.np
1.3 Rationality of EIA Study
The policies of Nepal encourage the proponent to minimize adverse issues of the development
proposal on the environment and the legal regime on the environment obliges to prepare the
EIA Report before the project implementation. As per EPR, 2054 (1997) and its subsequent
amendment, pertaining to Schedule 2.E.2 and Schedule 2. A. 121, an EIA is mandatory for the
hydropower generation project of more than 50 MW capacity, projects requiring felling of
forests with an area of more than 5 ha. Since the proposed project has the installed capacity of
110 MW and requires felling of forest with an area of more than 5 ha falls in Schedule 2.pm.2
and Schedule 2.c=12 of EPR, 2054, it requires to conduct EIA study. The EPA, 2053 (1997)
and EPR, 2054 (1997) empowers the Ministry of Forests and Environment to approve the
Scoping document, Terms of References (ToR) and EIA report. This EIA document is prepared
to fulfill the provisions made in EPR, 2054.
1 EPR Schedule 2, Sector -Water Resource and Power Sector, Sub-rule 2 states EIA requirement for projects
above 50MW installed Capacity; EPR, Schedule 2, Sector Forest, Sub-rule 12 states EIA requirement for projects
needing more than 5 ha of forest area clear felling.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
2| P a g e Department of Electricity Development
Until the Interim Report, the Installed Capacity of the project was adopted as 102 MW. Later,
as per the mandatory requirement of desander flushing channel to be above the 500 years flood
level, the level of desander had to be raised. Accordingly, the crest level of diversion weir also
increased. Consequently, the installed capacity also increased from 102 MW to 110 MW. The
comparative salient feature for both installed capacities has been shown under Table 2-2.
1.4 Objectives of EIA
The objective of the EIA study is to assess whether the proposed project is acceptable or not
from the environmental point of view and make the proposed project technically and
environmentally sustainable. The objectives of the EIA study are to:
• Collect baseline data and environmental conditions of the project area
• Carry out alternative analyses of the project features from the environmental point of
view
• Identify and predict environmental impacts of the selected alternative in terms of
magnitude, extent and duration potential to arise from the project implementation
• Identify the critical environmental problems that require further studies and/or
monitoring.
• Suggest mitigation measures for adverse impacts and enhancement measures for
beneficial impacts
• Develop an Environmental Management and Monitoring Plan and assess the
institutional arrangements and capacity for the implementation of the Environmental
Management and Monitoring Plan
• Develop information dissemination and consultation strategy for the implementation of
the project
• Consult and inform the project affected parties and other stakeholders, and ensure active
people's participation
• Advise decision makers regarding the environmental implementation of the project
1.5 Scope of EIA Study
The scope of work under this study is to conduct Environmental Impact Assessment (EIA) of
the project following the National EIA Guidelines and adhering to the approved ToR and the
requirements of EPA and EPR 1997 and subsequent amendments. This EIA study of DK5HPP
only includes hydropower generation components (headworks, powerhouse, surge shaft, adits,
penstock etc.) and project facilities like project component access road, permanent housing at
powerhouse and headworks, quarry sites, crusher plants, batching plants and muck disposal
area etc. of DK5HPP. However, the transmission line for the power evacuation is beyond the
scope of the study.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
3| P a g e Department of Electricity Development
2. INTRODUCTION OF THE PROPOSAL
2.1 Background
Nepal is blessed with enormous water resources and if harnessed quickly and efficiently Nepal
can be one of the major exporters of electricity among the South-Asian countries. The perennial
nature of the rivers and the steep gradients of the country’s topography provide an ideal
condition for the development of hydroelectric projects. Despite serious efforts by concerned
agencies, development of such hydroelectric projects is slow primarily due to lack of funds and
basic infrastructure. As a result, Nepal is suffering from the shortage of electricity even after
importing about 250 MW (in an average) of power from India; elecricity imported from India
accounted for around 35% of the total energy consumed in the country in FY 2016/2017 (NEA,
2017). This bitter reality is adversely affecting in daily life of the people in general and
development activities of the country as a whole and consequently adversely affecting overall
economic development of the country. Therefore, considering the annual increase in electricity
demand by 8-9%, it has been now of utmost importance to develop hydropower projects at the
earliest possible time to be undertaken by the Government to meet the ever-increasing demand
for electricity.
The GoN in its most recent budget for FY 2018/19 has put emphasis to the development and
expansion of hydroelectricity and all types of renewable energy to provide clean energy to all
Nepali household within the coming three years and to avail electricity to all households as per
demand within the next five years (at the end of FY 2016/17, only 65% of the total household
in Nepal are connected to grid electricity) [NEA, 2017]. The Government has declared the
period of 2018-2028 year as Energy Decade. The Government’s vision also extends up to
reducing dependency over petroleum products through the necessary production and
distribution of electricity to meet the demand of the household, commercial and industrial
sector, replacing cooking gas and developing electrical transportation system. In this regard, to
commensurate with the GoN’s target to meet the increasing domestic power demand, the
Department of Electricity Development (DoED) under Ministry of Energy, Water Resources
and Irrigation (MoEWI) has made serious efforts in identification of possible hydropower
projects available throughout the country. The Dudh Koshi-5 Hydropower Project (Dudh
Koshi-5 HPP) is one among many such projects identified by the DoED.
In view of the project preparation for its implementation, Government of Nepal intends to carry
out Feasibility studies and Environmental Impact Assessment (EIA) study of the proposed
Dudh Koshi-5 hydropower project under hydropower study program by utilizing Nepal
Government’s own resources through local consultants, in view of which, the Joint Venture of
Silt Consultants (P.) Ltd., Insight Engineering Consult (P.) Ltd. and Rajdevi Engineering
Consultants (P.) Ltd. was awarded the contract by the DoED to carry out feasibility study and
EIA study of the proposed Dudh Koshi-5 Hydropower Project, Solukhumbu, Nepal.
This EIA report is prepared for the proposed Dudh Koshi-5 HPP, Solukhumbu, Province #1,
Nepal in commensuration with the regulatory provisions of Environment Protection Act, 1997
and Environment Protection Rules, 1997. In commensuration with the EPR, 1997 (Rule 4 and
Rule 5), the proponent (the DoED) prepared Scoping document and Terms of Reference (ToR)
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
4| P a g e Department of Electricity Development
document for the EIA study which was approved by the Ministry of Forests and Environment
(the then Ministry of Population and Environment) on 20-07-2017 (Annex 1).
This EIA report is prepared in lieu with the approved ToR following necessary legal and
regulatory provisions of EPA, 1997 and EPR, 1997 and all other applicable statutory of GoN.
Scope of the present EIA study is limited to generation component of the proposed Dudh
Koshi-5 HPP.
2.2 Project objectives, Need and Relevancy
The purpose of the proposed DK5HPP is to harness the hydropower potential of the Dudh
Koshi River within the project coordinates by utilizing available flow of Dudh Koshi River
ensuring minimum possible adverse impacts on project area environment thereby contributing
to the local, regional and national economic development.
The main objective of the proposal is to develop 110 MW Hydropower project along the
Dudhkoshi River at Mapya Dudhkoshi Rural Municipality of Solukhumbu District. The project
lies within the coordinate of latitude 27029' 46" N to 27033' 30" N and longitude 86040' 00" E
to 86043' 37" E.
The other objectives of the proposal are to construct project facilities during construction phase
of Hydropower project. The proponent shall construct labor camps, construction yards,
stockpiling sites for store the construction materials, muck disposal sites, quarrying of
construction materials, stone crusher and batching plants.
2.3 Location and Accessibility
The whole Project area of the proposed DK5HPP lies in the Mapya Dudh Koshi Gaunpalika of
Solukhumbu district, Province #1 of Federal Republic of Nepal. Major project components
such as headworks (including intake, desanding basin, approach canal), water way alignment
(including headrace tunnel, surge shaft, penstock tunnel and tailrace tunnel) and powerhouse
facility as well as the switchyard station are proposed to be located on the right bank of Dudh
Koshi River, which is one of the major tributaries of the Sapta Koshi River in ward no. 1,2,3,4,
and 7 of Mapya Dudh Koshi Gaunpalika. Geographically, the proposed project lies between
86°40’00” E to 86°43’37” E longitude and 27°29’46” N to 27°33’30” N latitude. The elevation
within the project area varies between 1,102 masl to 3,079 masl. The catchment area of Dudh
Koshi River is bounded by Simhalila Dada in the East, Tuplung and Simramlase peaks in the
North, Dabala Dada and Iwa Nagi in the South and Deurali Dada in the West direction. The
geographical grid of the project does not fall inside the boundary of any National Park, Wildlife
Reserve, Hunting Reserve, Wildlife Sanctuary and conservation area.
The project area lies at an approximate road distance of 30 km north east from the district
headquarter Salleri. Salleri is located at around 266 km north east of Kathmandu. Also, Salleri
is connected to regular air flights from Kathmandu. From Salleri, four-wheel drives, goods
carrying Tractors and Jeeps only are available to reach Basa via seasonal earthen road from
Salleri. However, the intake site and powerhouse site are not connected by road yet.
The project site is accessible by earthen road from Phaplu airport of Solukhumbu to Basa and
accessible through a foot trail from Basa and alternative foot trails from Damku village. For
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
5| P a g e Department of Electricity Development
the construction of the project the project has to build the remaining project roads from Bodu
to Headworks and Bhumethan to Powehouse location. Alternatively, the project site can be
accessed by the roads constrcted by the Dudh Koshi-4 HPP.
Site access shall be provisioned by constructing internal access roads to reach to various project
component sites. The details of the access roads are provided in Table 2-1 below.
Table 2-1: Details of the access roads for the proposed DK5HPP
Code Description Length Road
Width Passage Bay
AR-1 Access Road from Damku towards Headworks
(From Damku towards headworks around 5.6 km
road has already been constructed) AR1
6.1 km 3.5 m at every 300 m
AR-2 Access Road from Damku towards Powerhouse
AR2 7.4 km 3.5 m at every 300 m
AR-3 Access Road towards Adit 2 (AR3) 1.1 km 3.5 m at every 300 m
AR-4 Access Road towards Surge Tank (AR4) 0.403 km 3.5 m Source: Feasibility Report, 2019
• Access Road to Headworks (AR-1):
The access road to headworks shall be provided through construction of a 6.1 Km long access
road from Damku on the right bank of Dudh Koshi River.
• Access Road to Powerhouse (AR-2):
The access road to headworks shall be provided through construction of a 7.4 Km long access
road from Damku on the right bank of Dudh Koshi River.
• Access Road to Adit-2 (AR-3):
A 1.1 Km long access road shall be constructed from nearest road head at AR-2 to reach to
Adit-2 portal location.
• Access Road to Surge Tank (AR-4):
A 403 m long access road shall be constructed from nearest road head at AR-2 to reach to surge
tank access portal or Adit-3.
2.4 Salient features of the Project
The project is RoR type with a proposed installed capacity of 110 MW with a design discharge
52.46m3/s in which river water will be diverted by constructing a 55 m wide and 18.1 m high
diversion weir to generate annual average energy of about 618.80 GWh. Entire project
components are sited on/along the right bank of Dudh Koshi River in ward no. 1,2,3,4 and 7 of
Mapya Dudh Koshi Gaunpalika (Basa). The salient features of the project are presented in
Table 2.2. The location map, district map and the project layout maps are presented below.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
6| P a g e Department of Electricity Development
Figure 2-1: Project Location in Nepal map
ProjectLocation
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
7| P a g e Department of Electricity Development
Figure 2-2: Project location in District Map
Figure 2-3: Wards of Mapya Dudhkoshi Rural Municipality
dfKo b'wsf]zL ufpFkflnsf
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
8| P a g e Department of Electricity Development
Figure 2-4: Location Map of DK5HPP on Topographical map
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
9| P a g e Department of Electricity Development
Table 2-2: Comparative Salient Features of Dudh Koshi-5 HPP (as per ToR and revised)
GENERAL
Type of Project : Run-of-River
Name of River : Dudh Koshi
Nearest Town : Salleri
Rural Municipality : Mapya Dudhkoshi Rural Municipality (Previous Kaku, Waku, Basa
and Jubing VDCs)
District : Solukhumbu
Province No. : 1
GEOGRAPHICAL COORDINATES
Latitude : 27°29’46” N to 27°33’30” N
Longitude : 86°40’00” E to 86°43’37” E
HYDROLOGY for 110 MW for 102 MW
Catchment Area at Intake : 1590.93 km2 same
Catchment Area at Powerhouse : 1614.08 km2 same
Average Flow : 86.06 m3/s same
Design Flow (Q40) : 52.46 m3/s same
Afflux : 16.845m 13.845 m
Normal Water Level (NWL) : 1251.25 masl 1254.25 masl
Maximum Water Level (MWL) : 1252.75 masl 1255.75 masl
RIVER DIVERSION FACILITIES (Coffer Dam)
Design Diversion Discharge : 133.81 m3/s same
Height of Coffer Dam : 4.6 m above bed level same
Top Width : 3.5 m same
Side Slopes : 1:01 same
Length of 1st Stage Coffer Dam : 153 m same
Length of 2nd Stage Coffer Dam : 116.59 m same
DIVERSION WEIR
Type : Concrete Gravity ( 3 numbers of gate) same
Type of Gate : Radial Gate same
Crest Elevation : 1239.0 masl 1236 masl
Crest Length : 44 m same
Maximum Height : 18.1 m above bed level 15m above bed level
SPILLWAY
Type : Ogee Spillway same
No. of Bays : 3 same
Crest Elevation : 1239.0 masl same
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
10| P a g e Department of Electricity Development
for 110 MW for 102 MW
Maximum Flood Level (1000 yrs.
Return Period) :
1253.95 masl same
Width : 36 m same
Design Flood Discharge : 4353.08 m3/s same
UNDERSLUICE
Size (W x H) : 7 m x 5 m same
Number : 1 same
Invert Level : 1236.5 masl 1236 masl
Type of Gate : Radial Gate same
INTAKE
Number : 2 same
Type : Side Intake same
Invert Level : 1240.0 masl same
Size (W x H) : 9.5 m x 5 m same
GRAVEL TRAP
Type : Integrated same
Number : 2 same
Size (L x B x H) : 16 m x 9.5 same
Bed Load Size to Trap : 5 mm same
APPROACH TUNNEL
Type : Inverted D-shaped same
Numbers : 2 same
Diameter of Tunnel : 4.4 m same
Length .
Approach Tunnel- 1 : 194.53 m same
Approach Tunnel- 2 : 167.61 m same
Bed Slope : 1:500 same
DESANDING BASIN
Type : Underground/Dufour same
No. of Chambers : 2 same
Nominal Size of Trapped Particle : 0.2 mm same
Trap Efficiency : 0.9 same
Size (L x B x H) : 150 m x 15 m x 19.6 m same
Normal Operating Level : 1250.715 masl 1248 m amsl
Maximum Water Level : 1252.215 masl 1249.5 m amsl
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
11| P a g e Department of Electricity Development
HEADRACE TUNNEL
for 110 MW for 102 MW
Type : Low pressure RCC lined tunnel same
Diameter : 5 m same
Length : 6114.02 m same
Hydraulic Slope : 1:200 same
Excavation Shape : Horse Shoe same
Finish Shape : Circular same
SURGE TANK
Type : Restricted Orifice, RCC lined same
Shaft Diameter : 16 m same
Orifice Diameter : 2.2 m same
Height : 62.1 m same
Shape : Circular same
Normal Water Level : 1247.529 masl 1237.58 masl
Maximum Upsurge Level : 1266.23 masl 1258.12 masl
Maximum Down Surge Level : 1217.296 masl 1210.82 masl
PENSTOCK TUNNEL/SHAFT
Type : Circular, Steel Lined same
Length : 324.44 m same
Finish Internal Diameter : 3.5 m same
Manifolds (Nos., Length,
Diameter) : 3, 36.6 m, 1.8 m same
POWERHOUSE
Type : Underground same
Dimension (L x B x H) : 76.3 m x 15 m x 35.5 m same
Turbine Axis Level : 985.0 masl 982 masl
SWITCHYARD
Type : Underground same
Dimension (L x B x H) : 80 m x 12.9 m x 16.1 m same
TAILRACE
Type : Pressurized Tunnel same
Diameter : 5 m same
Length : 180.59 m same
Excavation Shape : Horse Shoe same
Finish Shape : Circular same
Tail Water Level : 993.16 masl 993 masl
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
12| P a g e Department of Electricity Development
POWER FACILITIES
for 110 MW for 102 MW
Gross Head : 258.09 m 255.25
Net Rated Head : 241.78 m 229.98
Installed Capacity : 110 MW 102MW
Average Annual Energy after
Outage : 618.80 GWh 588.07 Gwh
Dry Energy : 100.39 GWh 98.52 Gwh
Wet Energy : 518.41 GWh 486.23 Gwh
TURBINES
Type of Turbine : Vertical Shaft Francis same
No. of Units : 3 same
Unit Discharge : 17.49 m3/s same
Rated Speed : 500 rpm same
Rated Efficiency : 0.91 same
Number inlet valves : 3 same
Rated Output Capacity per unit : 39 MW 35 MW
GENERATORS
No. of Units : 3 same
Generator Type : 3 phase AC Synchronous same
Excitation : Brushless Excitation same
Rated Voltage : 11 kV same
Power Factor : 0.85 Lagging same
Layout : Vertical same
Rated Efficiency : 0.98 same
Rated Output : 43.5 MVA same
Rated Frequency : 50 Hz same
POWER TRANSFORMERS
Type : Step Up Power Transformer same
Rated Efficiency : 0.99 same
Rated Capacity : 14.5 MVA same
No of Units : 10 (1 Spare) same
Types of Connection : Star with Neutral Point Brought Out same
Type of cooling : ONAN same
Voltage ratio same
Primary (LV side) : 11 kV same
Secondary (HV side) : 132 kV same
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
13| P a g e Department of Electricity Development
TRANSMISSION FACILITIES
for 110 MW for 102 MW
Length of Transmission Line : 5.8 km same
Connection Point : Dudh-Koshi -4 HPP Substation same
Type of Circuit : Single Circuit same
Conductor : BEAR ACSR same
Transmission Voltage : 132 kV same
CONSTRUCTION PERIOD : 4 yrs. same
FINANCIAL INDICATORS
Total Project Cost : NRs. 20.204 billion NRs. 18.437 billion
Cost per MW : NRs.183.676 million NRs. 180.75 million
Interest Rate of Loan : 0.11 same
IRR : 0.1893 0.1755
B/C Ratio : 1.55 1.44
NPV : NRs.11.141 billion NRs. 10.33 billion
Source: Feasibility Report, Dudhkoshi-5 Hydropower Project, 2019
2.5 Project Components
Figure 2-5 above presents the general layout of the project and the location of the key project
components. The section below briefly highlights the features of the different project
components. The major civil components of the project are:
2.5.1 Headworks
The headworks of the proposed Dudh Koshi-5 Hydropower Project comprise of a gated
diversion weir of concrete gravity type, a gated undersluice section and a side intake placed
adjacent to the undersluice. An ogee shaped free flow spillway is in-built at the downstream
face of the weir for the purpose of passing flood discharge to downstream. The following design
criteria are applied in the design of headworks structures:
• The headworks shall be capable of withdrawing the discharge of 62.95 m3/s (20% more
than design discharge of 52.46 m3/s) including discharge required for flushing. The
crest elevation of the gated spillway shall, therefore, be fixed based upon the invert
level of the intake and minimum operatinglevel of the plant.
• The diversion weir including the undersluice portion shall permit safe passage of design flood of 4353.08 m3/s, which is equivalent to 1 in 1000-year flood.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
14| P a g e Department of Electricity Development
• Wing walls on either sides of the river and the deck level of the undersluice and intake
shallbe provided above the Maximum Flood Level (MFL) corresponding to the 1 in
1000 yearflood.
(i) Diversion Weir
The diversion weir is a concrete gravity type with provision of gates and an ogee shaped free
overflow spillway at downstream face, having length of 44 m. The shape of overflow crest and
the capacity of spillway are designed in accordance with the recommendations of United States
Bureau of Reclamation (USBR). The crest level of the spillway is fixed at 1239.0 masl to divert
the discharge of 62.95 m3/s (20% more than design discharge of 52.46 m3/s) including flushing
discharge and to provide sufficient head to flush the sediment from the gravel trap. The water
level on the weir is controlled through the provision of radial gates which are three in numbers.
The height of the weir is 18.1 m from river-bed. The head over the weir during 1000 years
flood, which is equivalent to 4353.08 m3/s, is calculated to be 14.345 m and accordingly the
top level of abutment on either side of the weir are fixed as 1256.0 masl, which is 2.65 m above
the 1000 years flood level.
The horizontal apron type stilling basin is designed just downstream of the sloping glacis of
the weir for the dissipation of energy. The length of the concrete apron is 62.28 m. A boulder
riprap of length 28 m is provided further downstream of the apron.
(ii) Undersluice
A gated undersluice is proposed on the right side of the diversion weir to prevent the entry of
bed load of the river to the intake and built-up of sediment deposition in front of the side intake.
The crest level of the undersluice is kept at 1236.5 masl. The undersluice section has a radial
gate and the opening is of height 5 m. Stop log guides are provided upstream of the breast wall
to allow maintenance of the undersluice gate and embedded parts. The section is capable of
passing 352.31 m3/s discharge, which is about 8.09% of the maximum discharge at 1 in 1000
years flood.
(iii) Side Intake
A RCC side intake is located immediately upstream and adjacent to the undersluice to withdraw
the discharge of 62.95 m3/s (20% more than design discharge of 52.46 m3/s) including the
discharge required for flushing at normal water level of 1251.25 masl. The invert level of the
intake is fixed at 1240.0 masl, which is 3.5 m above the crest level of undersluice to prevent
the intrusion of bed load into the intake chamber from the river. The intake will have two
openings, each of which is 9.5 m wide and 5.0 m high. The trash rack is kept at an inclination
of 75o with the horizontal direction. Stop logs are provided upstream of the intake trash racks
to permit maintenance works of trash racks. The deck level as well as side walls are fixed at
1256.0 masl, which is 2.65 m above the 1 in 1000 years flood level.
(iv) Gravel Trap
Two gravel traps are provided within the intake chamber to trap the gravels from the river. The
gravel traps lie immediately after the trash rack whose size is 16 m length, 9.5 m width and 16
m depth. The bed load size to be trapped by the basin is 5 mm.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
15| P a g e Department of Electricity Development
2.5.2 Approach Tunnel
The water from intake is conveyed to the desanding basin through approach tunnel. The shape
of tunnel is inverted D-shaped with diameter of 4.4m. Two numbers of approach tunnel is
provided since there are two numbers of desanding basin. The lengths of approach tunnel are
194.53m and 167.61m. The tunnel is lined with RCC and shotcrete.
2.5.3 Desanding Basin
A desanding basin is required to trap the sediment particles before entering into the turbines.
The following design criteria are applied in the design of desanding basin:
• On the basis of general trend with recent studies carried out on hydroelectric projects
in Nepal, the desanding basin shall have at least 90 % trapping efficiency for the particle
size of 0.2 mm.
• The critical velocity for the design particle size of 0.2 mm is 0.2 m/s, whereas the
settling velocity is 0.02 m/s.
• The settled sediment particles shall be effectively flushed out to Dudhkoshi river.
Two numbers of underground desanding basins with two chambers each hopper type is
proposed on the right bank of the river. The design length, width and height for basin is 150 m,
15 m and 10.66 m respectively. Additional depth of 3.06 m is provided for the sediment storage.
Taking account of effective area of the basin, flow velocity in the basin will be 0.20 m/s and
the trapping efficiency of the basin will be more than 90 % for particle size greater than 0.2
mm. Transition length of 26 m is provided at upstream end of the basin to achieve the smooth
flow condition. The normal water level inside the basin will be maintained at 1250.715 m.
Vertical lift control gates and stop log grooves are provided just after the outlet to control the
flow inside the basin.
The proposed desanding basin is designed as an intermittent type, though there is provision of
continuous flushing during high flood period. The flushing duct is 1.0 m wide and 1.5 m high.
The bed slope of the flushing duct is 1 in 40. There is a vertical lift flushing gate at the end of
the basin to control the flushing discharge. The settled silt particles will be flushed back to
Dudhkoshi river through the flushing culvert followed by the boulder riprap.
2.5.4 Headrace Tunnel
The length of the low-pressure flow headrace tunnel from inlet portal up to surge tank is
6114.02 m. The excavation shape of the tunnel is horse-shoe while the finished internal shape
is circular. The finishing diameter of the tunnel is 5 m. The size of the tunnel is calculated for
the design discharge of 52.46 m3/s with the tunnel slope of 1:200 in concrete lined section.
2.5.5 Surge Tank
A surge tank acts as a cushion at the end of headrace tunnel. Surge tank is primarily necessary
to provide the cushion against the sudden load rejection at the power plant and to provide a
temporary storage of water to smoothen the flow in the headrace and pressure shaft preventing
intrusion of air inside the pressure shaft during sudden load acceptance. The size of the surge
tank should be sufficient to accommodate a potential upsurge due to sudden load rejection and
down surge due to load acceptance.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
16| P a g e Department of Electricity Development
The type of surge tank provided here is restricted orifice surge tank. The surge tank is
cylindrical concrete structure having height of 62.1 m and 16.0 m shaft diameter. The diameter
of orifice is 2.2 m. The full supply level at tank is 1247.529 masl. The maximum upsurge that
can happen in surge tank is 1266.23 masl and maximum down surge is 1217.296 masl.
2.5.6 Valve Chamber
Excavation of the valve chamber was required to house the butterfly valve introduced in the
water conveying system for emergency closure of the power tunnel at the upstream end of the
steel lined pressure tunnel immediately downstream of the surge tank. The valve chamber is a
cavern having a length of 15 m, a width of 8 m and a height of 10.6 m.
2.5.7 Penstock Shaft
Penstock shaft is provided to connect tunnel-surge shaft junction and inlet of turbine. The total
length of the pressure flow conduit is 324.44 m. The circular shaped pressure shaft has the
finished internal diameter of 3.5 m and is steel lined inside. Three number of manifolds of
diameter 1.8 m and length 36.6 m are provided to distribute the water to the turbine units in the
powerhouse.
2.5.8 Powerhouse
Powerhouse is basically designed to in-house the turbine and generator and other necessary
electromechanical equipments. In addition, it must have an area for service and maintenance
and room for mounting control panel, transformer and high voltage panel in addition to an
office room. Generally, to lift the heavy installations in the powerhouse an overhead traveling
crane or a suitable mechanism having chain pulley is equipped. Generator floor of the
powerhouse is made safe from a possible flood of 1000 year return period that can happen in
the river basin.
Dudh Koshi-5 Hydropower consist of underground type powerhouse consisting of three units
of vertical axis Francis turbine. The size of the powerhouse is 76.3 m long, 15.0 m wide and
35.5 m high from its lowest level. Office area, control panel area, high voltage room,
transformer room etc. are suitably arranged inside the powerhouse. Erection bay of 10.2 m
width and 12.0 m long is provided at the main entrance of the powerhouse. Other
electromechanical accessories such as unit control panel and excitation panel are placed on the
side of the generator. For the hoisting of turbine and generator for the maintenance and other
purpose an overhead traveling gantry crane having 20 tons main hoist capacity will be installed
in the powerhouse.
2.5.9 Switchyardand Transformer Cavern
Underground switchyard and transformer cavern is provided adjacent to the powerhouse to
house the power transformers and other electrical equipments. The size of the cavern is 80 m
length, 12.9 m width and 16.1 m height. Access tunnel of diameter 5 m is provided to reach the
cavern.
2.5.10 Tunnel adits and portals
Eight number of tunnels adits are to be constructed for the facilitation of construction of
underground structures and for access to the structures, details of which are presented below in
Table 2-3.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
17| P a g e Department of Electricity Development
Table 2-3: Details of Adit Tunnel for the construction of the proposed DK-5 HPP
Code Length Diameter Description Location
Adit-1 218.16 m 4.0 m i. Access tunnel to desander ii. Lap village, 265m
downstream of weir axis
Adit-2 454.58 m 4.5 m, 3.5 m
nd 2.5 m Desander flushing tunnel
Lap village, 450m
downstream of weir axis
Adit-2A 127.06 m 4.5 m iii. HRT construction adit iv. Lap village, branch of
Adit-2
Adit-3 404.2 m 4.5 m v. HRT construction adit vi. Khastap village, at
chainage 4.7km of HRT
Adit-4 43.22 m 4.5 m vii. Access tunnel to valve
chamber
viii. Bhumethan village
Adit-5 139.02 m 6.0 m ix. Access tunnel to
powerhouse
x. Bhumethan village, 950m
upstream of confluence of
Kaku and Dudhkoshi river
Adit-5A 89.88 m 5.0 m xi. Access tunnel to
switchyard
xii. Bhumethan village, branch
of Adit-5
Adit-5B 190.40 m 4.5 m xiii. Penstock shaft
construction adit
xiv. Bhumethan village, branch
of Adit-5
Source: Feasibility Report, 2019
2.5.11 Tailrace
Tailrace tunnel is designed to pass the discharge safely to the river downstream after it has been
utilized for power generation. Tailrace tunnel is circular in shape having diameter of 5.0 m and
laid at slope of 1:500. The length of tunnel is 180.59m. The flow inside tailrace tunnel is
pressurized. A weir is provided at outlet of tailrace to maintain the tail water level. A gate is
provided at the outlet to control the flood water from entering into the powerhouse. The normal
water level at tailrace outlet is maintained at 993.16 masl while the water level at 1000 years
flood is 997.96 masl.
2.5.12 Access/Project Roads
There is already the provision of access road which has been constructed as village road by the
local authorities in the project site. For the project road up to headworks, a total road length of
6.10 km is proposed from Bodu. Similarly, the project road up to powerhouse site is to be
constructed which covers a total length of 7.4 km from Damku upto the project powerhouse
site.
Additionally, there is a provision of project road which needs to be constructed for accessibility
to various adit tunnels apart from those constructed for accessibility up to powerhouse and
headworks. For construction adit, a total project road of 1.1 km is proposed and for access up
to the surge tank, the total project road of 403 m is to be constructed.
2.6 Transmission Line
The project will be connected to the switchyard of Dudhkoshi – 4 Hydropower Project via a
5.8 km approx. 132 kV single circuit overhead transmission line with BEAR ACSR conductor
suspended on self-supporting steel lattice towers.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
18| P a g e Department of Electricity Development
2.7 Project Activities
The main project activities are given below;
Pre-Construction Work: This includes feasibility study, environmental study, approval
procedures, necessary agreements, land acquisition/procurement and other necessary
procurements, preparing land for camp facilities, etc.
Construction Work: The construction work consists of civil construction, hydro-mechanical
works, electromechanical works and electrical works.
Post Construction Work: The post construction work includes dismantling of temporary
facilities, rehabilitation of land covered by temporary facilities, termination of land lease
contract and handover of the land back as well as the operation of the project.
2.8 Construction Planning
2.8.1 Land Requirement
Major project components such as approach tunnel to settling basin, settling basin, headrace,
surge tank, penstock, powerhouse complex, switchyard and tailrace are sited underground.
Hence, for project execution land is required only for construction of diversion weir, intake,
gravel traps, spoil disposal sites, camps, workshops and stores, quarry and borrow sites and
project internal access roads. An estimated land area of about 25.834 ha is required for
construction of the project components and provisioning for project facilities of which 24.324
ha will be required permanently for project component construction and the remaining 1.51 ha
will be required temporarily (for quarry, borrow and spoil disposal sites). Out of the 24.324 ha
land to be permanently acquired, 4.033 ha is cultivated land and 13.747 ha is community forest
land. For temporarily leased land, 0.133 ha is cultivated, 1.357 ha is forest, and 0.01 ha is river
and flood plain.
Table 2-4: Acquisition of land for different project component
Project
component
Type of land (ha) River
flood
plain
Land
acquisition
type (ha) Total
(ha) Forest Cultivated Barren
Temp Perm
Govt. CF Govt. Pvt. Govt. Pvt.
Govt.
(Land
Reform)
Pvt.
Headworks 1.499 5.333 √ 6.832
Adit Portal
Area
0.392 √ 0.392
Surge Shaft
and
penstock
pipe Area
0.071 √ 0.071
Powerhouse 0.111 √ 0.111
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
19| P a g e Department of Electricity Development
and
Switchyard
Quarry
Area
1.109 0.02 √ 1.129
Disposal
Area
7.358 1.211 √ 8.569
Access road 4.316 3.993 √ 8.309
Camp Area
(Engineer’s)
0.04 √ 0.04
Camp Area
(Labor’s)
0.133 √ 0.133
Crusher and
batching
area
0.248 √ 0.248
Total (ha) 15.104 4.166 6.564 25.834
2.8.2 Human Resources
Following assumptions were made in the assumption of human resources requirement:
• Project construction period of about 4 years and
• Wok operation by 8 separate workforce team in different locations
A reasonable estimate based on the consultant’s experience in other similar hydroelectric
project for skilled, semi-skilled and unskilled human resources for a project of this size is about
600 to 800 during the peak construction period.
2.8.3 Construction Materials Requirement
Estimated volume of 180,900 m3 of concrete is required for the project construction. The main
construction materials and their estimated quantity are presented in Table 2-5.
Table 2-5: Estimate of construction materials required
Construction materials Estimated Quantity
Cement (bags) 2,043,205
Aggregate (m3) 153,500
Sand (m3) 76,750
Reinforcement Bars (ton) 5,384 ton
Source: Feasibility Report, 2019
All local materials such as sand, gravel, stones etc. will be extracted from designated quarry
and borrow sites. Availing timber for construction from the project area forest shall be strictly
prohibited. The Contractor shall purchase other construction materials such as cement,
reinforcement bars, steel plates etc. from the factory and transported to the project site by
appropriate means of transportation.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
20| P a g e Department of Electricity Development
2.8.4 Project Implementation Schedule
The project construction (implementation) schedule has been derived on the basis of calculated
quantities of works to be done and the time that is required to design, fabricate, supply and
install major project components. The total project construction period up to the commissioning
of the project is estimated to be 4 years. The time required for further investigations during
detailed design phase, preparation time for contract and tendering including negotiations and
contract awards has been considered appropriately while preparing the implementation
schedule. As can be seen from the implementation activities expect pre-construction works
such as access road construction, land acquisition, construction power establishment, contract
documents preparation etc. will be completed before. The Construction (Implementation)
Schedule is attached in Annex – 3.
2.8.5 Construction Power Requirement
At present, the project area is devoid of connection to National Grid (INPS). Therefore, unless
the project area is connected with INPS while the construction commences, two diesel
generator sets each with 1.5 MW capacities will be required at the headworks site and
powerhouse location, respectively to meet the electricity demand of the construction purpose
and for lighting of construction camps. In case, the project sites get connected with the INPS
while the project goes for construction, power from the nearest appropriate connecting point
will be derived for the purpose.
2.8.6 Employer’s Camp, Contractor’s Camp and Labor Camp
Two numbers of project camps (one each at headworks and powerhouse location) are proposed
to accommodate Contractor’s construction workforce as personnel of supervising Engineers
and the Employer’s staff. The camps are located on the right bank of the Dudhkoshi River.
2.8.7 Quarry Sites and Borrow Pits
Various probable quarry sites have been identified based on geological investigation which is
presented below in Table 2-6.
Table 2-6: Proposed Borrow and Quarry Sites
Naming Easting Northing Location Source of
Material
Quantity
(m3)
QS 1 470874.77 3048864.633 Left bank,
intake area
Hard and
strong gneiss
as bedrock
quarry
700
QS 2 470959.907 304898.424 Left bank,
adit-1 area
Terrace
deposit (silty
sand)
20,000
QS 3 470831.63 3048686.186 Right bank,
intake area
River bar
alluvium
deposit
2,000
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
21| P a g e Department of Electricity Development
Naming Easting Northing Location Source of
Material
Quantity
(m3)
QS 4 470756.305 3048698.801
Right bank,
uphill side of
desanding
basin at Lap
village
Colluvium
deposit and
scree deposit
20,000
QS 5 470796.207 3048464.724
Right bank,
uphill side of
adit-2 area at
Lap village.
Cohesive
material
deposit
150,000
Note: QS- Quarry Site, Source: Feasibility Report, 2019
2.8.8 Batching Plants and Aggregate Crushing Plants
The facilities for aggregate crushing and batching plants will be located at the headwork and
powerhouse sites close to the active construction sites. These facilities will be operated with
provisions of air pollution control, noise control/arresting facilities, and water and waste water
management facilities. These will be temporary facilities to be demolished at the end of the
construction period. The areas occupied by these facilities will be rehabilitated to original land
conditions and returned to the respective owners. The details of Batching Plant and Crushing
plants are shown in the table 2-7.
2.8.9 Material Storage and Mechanical Workshop
Material storage and mechanical workshops are located on the left bank of Dudhkoshi River
both at headworks and the powerhouse location. The details of Material Storage and
Mechanical Workshop are shown in the table 2-7.
Table 2-7: Co-ordinates of Material Storage and Mechanical Workshop
Naming Easting Northing Location
CR-1, MS-1 and MWS-1 470873.378 3048499.947 At adit-1 area, Lap village, right bank
of Dudhkoshi river
CR-2, MS-2 and MWS-2 469739.941 3042334.352 At tailrace outlet area, Bhumethan
village, right bank of Dudhkoshi river
Note: CR- Crusher, MS- Material Storage, MWS- Mechanical Workshop
2.8.10 Muck disposal
About 592,900 cubic meters of spoils has been estimated to be generated due to excavation for
project component construction. The excavated volume of spoil needs safe and environment
friendly disposal. Three numbers of spoil disposal sites are proposed for the purpose all of
which are on the right bank of DudhKoshi River. Selection of spoil disposal sites are based on
available area so as to accommodate generated muck volume, terrain condition (slope gradient
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
22| P a g e Department of Electricity Development
and stability), proximity to water sources, proximity to settlement and land use type (so as to
avoid prime agricultural and/or forest land).
Table 2-8: Proposed Spoil Disposal Sites
Naming Easting Northing Location
SD-1 471216.804 3048172.201 At headworks area around adit-2 location, Lap
village, right bank of Dudhkoshi river
SD-2 469912.985 3043313.682 At adit-3 area, Khastap village, right bank of
Dudhkoshi river
SD-3 469801.978 3042732.085 At adit-5 area, Bhumethan village, right bank of
Dudhkoshi river
Note: SD- Spoil Deposit , Source: Field Investigation Report, 2016
2.9 River Diversion during Construction
Temporary diversion of Dudhkoshi River is required to facilitate the construction of the
headworks structures of the project. As the headworks structures are planned to be constructed
in dry season of the year, the river diversion scheme during construction is designed for a return
period of 1 in 20 years dry season flood of 133.81 m3/s. The diversion of the river at the
proposed headworks site will be carried out in two stages covering two seasons. In the first
stage, during the dry season of the first year of the construction, the river flow will be diverted
to the left part of the river by construction of a coffer dam along and across the undersluice
portion. During this period, the undersluice, divide wall and intake will be constructed. In the
second stage, during the dry season of the second year of the construction, the river flow will
be diverted to the right part of the river through the undersluice by construction of cofferdams
across the river at upstream and downstream of the weir and stilling basin structures. The
diversion weir, stilling basin and wing walls will be constructed during this period. After
construction of all structures, coffer dams will be demolished and leveled up to the designed
shape and size. The cofferdams are gravity type with impervious core inside and excavated
shell materials outside with boulder aprons in upstream and downstream faces.
2.10 Project Cost
The total project cost of Dudh Koshi-5 Hydropower Project with transmission line is estimated
as NRs. 20.204 billion. (Feasibility Report, 2019).
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
23| P a g e Department of Electricity Development
3. STUDY METHODOLOGY
This EIA for Dudhkoshi-5 Hydropower Project has been conducted in accordance with the
methodology described in the Terms of Reference approved by MoPE (now MoFE) on
2074/4/5. The following methodologies have been applied to the collect baseline information
and impact prediction:
3.1 Literature Review and Consultation with the Stakeholders
The literature review process started at the very beginning of the EIA study and intermittently
carried out during the whole study till the final stage of draft EIA report preparation. At the
very beginning, the approved Scoping Document and TOR document for EIA of Dudhkoshi-5
Hydropower Project is thoroughly studied and reviewed. The Field report and preliminary
Feasibility Report, 2017 prepared by the design consultant is reviewed and consulted for
technical information related to project. Available published literature, documents and maps
(GON's topographic map, 2786 06 and 2786 10 with scales 1: 50,000, land use maps, aerial
photographs, cadastral survey maps, Google maps etc.) related to the project area were
reviewed. Previously studied environmental assessment reports of hydropower projects and
other related projects (EIA of Kabeli A HEP, ESIA of Tamakoshi III HEP etc.) were looked
through. Solukhumbu District Profile, 2074, Strategic Road Network Report of Department of
Roads (2007), reports published by Central Bureau of Statistics (CBS) etc. were used for
collecting existing rural municipality and district level information on physical, biological and
socio-economic environment. Climate related data were sourced from Department of
Hydrology and Meteorology (DHM).
Relevant laws, acts, rules & regulation, policies, guidelines, strategies were reviewed in order
to avoid any form of non-compliance. The published literatures on the biomass, flora and fauna,
rare/endangered /protected species in and around the project area were reviewed.
To justify to the local concerns and local information available in the secondary literatures,
officials of the local and district level, particularly Rural Municipality, District Coordination
Committee, District Forest Office, Community Forest User Groups, District Soil Conservation
Offices and District Land Revenue Office were also consulted to seek site-specific information
of the project area. Furthermore, the local and national institutions working in the project area
were consulted to verify the project specific information related to environmental and social
aspects.
3.2 Impact Area Delineation
For the EIA study purpose, the project affected areas are classified as Direct Impact Area and
Indirect Impact Area based on the proximity to the project sites and the intensity of the impacts
resulting from project implementation, the description and the categorization of the project
impact area are presented below in Table 3-1.
Table 3-1: Description and categorization of the project impact area
Categories Description Specification
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
24| P a g e Department of Electricity Development
Direct Impact Area
High impact area includes those areas
where different types of project activities
takes place such as construction of
different project components including
headworks structures, water conveyance
arrangements, power generation facilities
and switchyard, access road and internal
project road, project offices and camps,
operation of borrow and quarry sites,
spoil disposal sites etc. which directly
affects the physical, biological and socio-
economic environment and resources
Immediate project activity area
in Ward no. 1, 2, 3, 4 6 and 7 of
Mapya Dudh Koshi Rural
Municipality
Indirect Impact Area
Low impact area is further away from
project activity area. Physical and
biological environment of this area may
experience minimal impact, but socio-
economic impact can be of importance
because these areas may supply labor and
agricultural goods to the project area.
Wards 5 and 7 and Remaining
areas of aforementioned wards
of Mapya Dudh Koshi Rural
Municipality
3.3 Field Study
The field investigation was carried out by a multidisciplinary team, which comprised of a
wildlife expert, physical environment expert, environmental engineer, hydropower engineer,
biologist and fishery experts. The design and hydropower engineers of the proponent also
assisted the team member during the field survey. Field visit was conducted in wards 3 and 4
(settlements: Khuskum, Basa, Dirlung, Majhagau, Lapa, Patame, Palamdu, Boldu) of the
Mapya Dudhkoshi Rural Municipality over a period of October 21-29, 2017 to collect the
baseline information. The study team carried out field visit in project affected wards of
Dudhkoshi Rural Municipality of Solukhumbu district. The required baseline information on
physical and biological environment of direct and indirect impact areas of the project were
collected during the field visit. The information on different environmental components was
collected by using the following tools.
3.3.1 Physical Environment
In order to collect baseline information on the physical environment, an intensive field
investigation along the proposed project area was carried out. Land use patterns, topography
and soil erosion were carried out through direct observation and field mapping.
Four water samples were taken from Dudhkoshi River at proposed intake site, powerhouse site
and one water samples were taken from a private tap at the proposed camp site. The samples
were taken on 4/2/2074.
The methods employed for the data collection were indirect assessment of air quality; water
sample collection at four locations (headworks and dewater zone) of Dudhkoshi River and
laboratory analysis on different parameters like BOD, DO, TSS, TDS, etc. for water quality;
and direct observation & measurements of sound pressure level at two locations (headworks
and powerhouse) for noise quality.
Collected water samples were analyzed in Water Engineering and Training Center P. Ltd.,
Dillibazar Kathmandu. Six physical parameters (Turbidity, electrical conductivity, total
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
25| P a g e Department of Electricity Development
dissolved solid & total suspended solid), 9 chemical parameters (Total alkalinity, BOD, COD,
DO, Iron and Sulfate) and 2 microbial parameters (Total coliform and Faecal coliform) were
tested for the collected samples. Temperature, pH and electrical conductivity were measured
both in the field and in the laboratory using a pH meter. All other parameters were tested in
laboratory. The test methods and test units are provided in Annex 5.
The slope stability and landslides, fan deposits and rock fall within the project area were studied
thorough site observation and on-site delineation in maps. Apart from the above information,
discussions were carried out with local communities to fill the information gaps such as
flooding events, GLOF events, seismic history, landslide events and locations and land
degradation process etc.
3.3.2 Biological Environment
For biological parameters, both primary and secondary sources of information were used.
Primary sources were basically used floral and faunal diversity. Information on fauna and flora,
protected, rare and endangered species and sensitive habitats in the project areas were collected
through site visit and transect walk survey. Existing situation and possible impacts on wild
fauna were studied in relation to risk of project implementation. Forest inventory was done
through purposive sampling with nested quadrate methods within the project area to estimate
number of tree and volume of timber to be cleared. Local people of the project impact area
were consulted on use and management of forest resources in including availability and use of
NTFPs as well as MAPs, ethno-botanical importance of the plant species, problems
encountered in use and management of forest resources and the possible impacts of the project
on the local flora. Agro-biodiversity of the project area is recorded in a data sheet (Annex 5)
through consultations with local informants. Information on availability of fauna was also
collected in consultation with local informants, members of forest user groups and other
knowledgeable locals. Interaction with local people and photography consultation with local
communities were done for wildlife diversity. The loss of protected, rare and endangered
species based on the CITES Appendix, IUCN Red Data and Government of Nepal protected
lists were enumerated in the field throughout the project area.
Forest and Vegetation
Forest inventory was done with purposive sampling in the areas where project structures and
facilities will be made. Broadly the samplings were done in 6 sites— i) intake and headwork
site, ii) surge tank, iii) power house portal and tailrace area, iv) spoil disposal sites, v)
construction adit portals and vi) construction material sites.
Plot Design:
Nested quadrate was prepared in each sampling point. Initially 20x20 m2 square shaped tree
plot was prepared for tree. Then 5x5 m2 square plots for shrubs and 1x1m2 square plots for
herbs were laid down at the centre of 20x20 m2 of tree plots (Figure 4.1). Thus 3 plots were
laid down in each sampling points. Altogether 27 sampling points were laid down. Thus, a total
area of 10,800 m2 for tree, 675 m2 for shrub and 27 m2 for herb were surveyed. All tree species
having DBH greater than 10 cm were considered within 20x20 m2 pot. DBH and height of all
trees were measured with the help of DBH tape and clinometer respectively. Crown cover
percentage of trees within the sampling plots was estimated occularly for the determination of
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
26| P a g e Department of Electricity Development
stocking of forest. Number of all shrub species having height greater than 10 cm, and tree
species with less than 10 cm DBH and greater than 10 cm height were studied within nested
quadrate of 5x5 m2. Similarly, the number of all herb species and seedlings of shrub and tree
with height less than 10 cm were counted in 1x1 m2 nested plot.
Stand Size:
The stand size classification is presented in Table 4.1. The classification has been modified
based on Forest Inventory Division (FSRC, 1995).
Table 3-2: Stand size classifications
Symbol Stand Size DBH (cm)
1 Poles 10 - 25
2 Small saw timber >25 - 50
3 Large saw timber > 50
Figure 3-1 Plot Design (Nested quadrate plot)
Tree Volume:
Basal area and height were measured for calculation of standing trees trunk volume. This was
estimated as
𝑇𝑟𝑒𝑒 𝑉𝑜𝑙𝑢𝑚𝑒 =BA× H
2…………….. (i)
Where, BA was basal area at 1.3-meter height, which is πr2, where r is radius (in meter) at 1.3
m height of the tree and H = height (in meter) of the tree (DoF 2061).
Timber and Fuelwood Volume:
Timber volume is calculated as follows (DoF 2061):
𝑇𝑖𝑚𝑏𝑒𝑟 𝑉𝑜𝑙𝑢𝑚𝑒 = 𝑇𝑟𝑒𝑒𝑉𝑜𝑙𝑢𝑚𝑒 × 𝑄𝑢𝑎𝑙𝑖𝑡𝑦 𝑜𝑓 𝑇𝑟𝑒𝑒…………….. (ii)
Where, tree volume is from eq. (i) and quality of tree is based on DoF 2061. If the tree is of 1st
class, tree volume is multiplied by 2/3, while 1/2 for 2nd class tree and 0 for 3rd class tree.
Fuelwood volume is calculated as follows (DoF 2061):
𝐹𝑢𝑒𝑙𝑤𝑜𝑜𝑑𝑉𝑜𝑙𝑢𝑚𝑒 = 𝑇𝑟𝑒𝑒 𝑉𝑜𝑙𝑢𝑚𝑒 × 𝑄𝑢𝑎𝑙𝑖𝑡𝑦 𝑜𝑓 𝑇𝑟𝑒𝑒 + 𝐵𝑟𝑎𝑛𝑐ℎ 𝑉𝑜𝑙𝑢𝑚𝑒……… (iii)
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
27| P a g e Department of Electricity Development
Where, tree volume is from eq. (i) and quality of tree is based on DoF 2061. If the tree is of 1st
class, tree volume is multiplied by1/3, while 1/2 for 2nd class tree and 1 for 3rd class tree.
Tree Biomass:
Tree standing volume was multiplied with its dry wood density to get stem biomass of tree.
Using stem biomass, branch biomass and foliage biomass were calculated using ratio of branch
to stem biomass and foliage to stem biomass for various species (HMGN, 1988).
𝑆𝑡𝑒𝑚 𝐵𝑖𝑜𝑚𝑎𝑠𝑠 = 𝑇𝑟𝑒𝑒𝑉𝑜𝑙𝑢𝑚𝑒 𝑋 𝑇𝑟𝑒𝑒 𝑊𝑜𝑜𝑑 𝐷𝑒𝑛𝑠𝑖𝑡𝑦…………….. (iv)
Where, tree volume is from eq. (i), and tree wood density was obtained from various sources
such as DoF (2010), Sharma E.R. and Pukkala T. (1990) and Master plan for forestry Sector
(1988).
𝑇𝑟𝑒𝑒 𝐵𝑖𝑜𝑚𝑎𝑠𝑠 = 𝑆𝑡𝑒𝑚 𝐵𝑖𝑜𝑚𝑎𝑠𝑠 + 𝐵𝑟𝑎𝑛𝑐ℎ 𝐵𝑖𝑜𝑚𝑎𝑠𝑠 + 𝐿𝑒𝑎𝑓 𝐵𝑖𝑜𝑚𝑎𝑠𝑠…………….. (v)
Importance Value Index
The dominancy of any species in an area is estimated with respect to its importance value which
is the combined effect of relative density, relative frequency and relative basal area. The basal
area is replaced by coverage in case of shrubs and herbs.
𝐼𝑉𝐼 = RD + RF + RBA or RC … … … … ..…….. (vi)
Where,
RD = Relative Density
RF= Relative Frequency
RBA = Relative Basal Area (for tree)
RC= Relative Coverage (for shrubs and herbs)
Density:
Shrub/Herb density is calculated as follows;
𝐷𝑒𝑛𝑠𝑖𝑡𝑦 (𝑁𝑜./ℎ𝑎) =I
AXNx 100…………………. (vii)
Where,
I = Total number of individuals
A = Area of each sampling plot
N = Total number of plots
𝑅𝑒𝑙𝑎𝑡𝑖𝑣𝑒 𝐷𝑒𝑛𝑠𝑖𝑡𝑦 (%) =D
TDx100……………... (viii)
Where, D = Density of an individual species; TD = Total density of all species
Frequency:
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
28| P a g e Department of Electricity Development
𝐹𝑟𝑒𝑞𝑢𝑒𝑛𝑐𝑦 (%) =E
Nx100 ……………………. (ix)
Where,
E = Encounter (Total Number of plots in which an individual species occurred)
N = Total number of plots
𝑅𝑒𝑙𝑎𝑡𝑖𝑣𝑒𝐹𝑟𝑒𝑞𝑢𝑒𝑛𝑐𝑦 (%) =F
TFX100…………. (x)
Where, F = Frequency of an individual species; TF = Total frequency of all species
Coverage:
𝐶𝑜𝑣𝑒𝑟𝑎𝑔𝑒 (%) = CI ………………………….. (xi)
Where,
CI = Coverage of an individual species in a sampling plot
𝑅𝑒𝑙𝑎𝑡𝑖𝑣𝑒 𝐶𝑜𝑣𝑒𝑟𝑎𝑔𝑒 (%) =TCI
TCX100………… (xii)
Where, TCI = Total coverage an individual species; TC = Total coverage of all species
Basal Area:
𝐵𝑎𝑠𝑎𝑙 𝐴𝑟𝑒𝑎 (𝑚2) =d2
4… … … … … … … … … … (xiii)
Where,
d (m) = diameter at breast height of an individual tree
𝑅𝑒𝑙𝑎𝑡𝑖𝑣𝑒 𝐵𝑎𝑠𝑎𝑙 𝐴𝑟𝑒𝑎 (%) =TIBA
TBAX100…….. (xiii)
Where, TIBA = Total basal area of an individual tree; TBA = Total basal area of all trees
Wildlife and Avian Fauna
Information on wildlife (including mammalian and herpetofauna as well as amphibians and
avian fauna) of the project area was gathered using both direct and indirect methods.
Direct method involved transect walk which was proposed on observing status of wildlife in
forest and immediate surroundings within project’s impact area. Animals, reptiles and birds
spotted along the route and information on the habitat where such observations were made
were recorded. Moreover, identification of pug marks/footprints, droppings/pellets, ground
digging and uprooting, tree scratching and marking, animal remains such as skin, fur, feathers,
and carcasses, dwellings such as nests, holes and burrows etc. were used in order to document
presence of particular wild animals, herpetofauna and birds. Calls and singings of birds were
recorded as far as identified. The collection of the wildlife specimens was carried out whenever
possible and photographs were taken of uncollected items for the purpose of identification of
specimens. Such information was also validated by means of consultation with local
informants. Special faunal record data sheets were prepared and used to record faunal presence,
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
29| P a g e Department of Electricity Development
their abundance and other associated features in the project area (Annex I). Additional
information on animal presence, movements issues and conflicts were obtained by using
indirect methods i.e. discussions with a range of stakeholders that included local people, forest-
goers or cattle grazers, CFUGs and Ilaka range post staff, etc.
Fish
Fish samples were collected at three different stations (weir Site, downstream of weir site-at
middle of dewatered zone and tailrace area; of the Dudh Koshi River with the help of cast nets
and by mobilizing the local fishermen. The number of efforts employed by the fishermen was
recorded to determine catch per unit effort (CPUE). The collected fish were identified at site.
Measurements of total length, weight and other morphological characteristics were recorded.
A detailed study of local fishes was carried out for determining the dominant species, species
diversity, taxonomic and endemic characteristics for local and global listing.
The important secondary sources of information which were reviewed include district profile,
village profile, energy and environment plan, district management plan and so on. Others
included many reports and researches related to EIA, Forest maps, statistical reports, and
websites of MoFE, DoF and DNPWC including other available useful information.
3.3.3 Socio-economic and Cultural Environment
Data on socio-economic status and cultural aspects were collected from direct and indirect
impact areas. The methods utilized for collection of socio-economic data from the primary
sources include followings:
Household survey: Household (HH) survey of direct and indirect impact areas was conducted
by using structured questionnaires to obtain baseline information on demographic and
educational status, ownership patterns and farm practices, economic status, energy sources,
basic health conditions, common diseases, etc. Furthermore, project related issues such as
compensation and expectation from the project were also addressed by questionnaire interview.
The household level questionnaire used for the survey is given in Annex 8.
At the first stage of field investigation a total of 48 households were surveyed in the project
affected wards 3 and 4 (settlements: Khuskum, Basa, Dirlung, Majhagau, Lapa, Patame,
Palamdu, Balku) of the Dudh Koshi Rural Municipality over a period of October 21-29, 2017.
For such surveys two enumerators were employed who were trained for enumeration prior
mobilizing them to the field. A field supervisor was also appointed to supervise the works of
the enumerators at field.
Regular informal public consultation was a part of the EIA study. Local people were consulted
in a number of occasions and forums during the EA process. A total of 7 FGDs with the local
people have been conducted in different location of the project are as to identify the various
issues related to the project development and its socioeconomic consequences and
corresponding mitigation measures. FGDs were conducted with following specific objectives;
i. To provide factual information on the project location, particularly the main project
structures such as weir, tunnel, adit portals, powerhouse, surge tank, tailrace and the
project access roads besides tentative locations of the quarry sites, construction camps
and operation camps of the project.
ii. To clarify the objective of the Project SA and its procedures.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
30| P a g e Department of Electricity Development
iii. To provide potential impacts of the project from technical considerations during
project construction and operation in the project area's physical, biological, social,
socio-economic and cultural domain.
iv. To collect information on the project areas physical, biological and socio-economic and
cultural environments from the local peoples’ perspective
v. To collect opinion of the people on the project areas
vi. To get feedback on the potential impacts of the project in the eyes of the local people
particularly on the local infrastructure, social norms and culture and on the physical and
biological environments
vii. To solicit opinion of the local people on the alternative mitigation measures to abate,
or avoid the potential impacts
viii. To solicit opinion of the local people with regard to the development aspiration of the
project.
The focus group discussion meetings were formal and informal meetings. To start the meeting,
lead member of the study team first introduced the consulting members with a note on the
objective of the meeting. Then the project layout and its different components and their
physical location in the field were explained with details of the type of construction and
operation activities of the project. Then the forum was opened for public debate on the different
issues. Land acquisition and mode of compensation, livelihood related issues due to the loss of
land, dewatering, prior information dissemination practices, ILO 169 and rights of the IPs, rural
electrification, current uses of Dudhkoshi river, perceptions towards project, socio-cultural
practices associated with Dudhkoshi river, local development needs, likely impacts due to the
various project structures and corresponding mitigation measures were the major issues
discussed during the FGDs. The participants freely discussed on the issues and expressed their
ideas, views, suggestion, and comments on the various components of the project. The
moderator (study team member) introduced the issues and agendas of the discussion and kept
the discussion going and tried to prevent domination of the discussion by a few participants.
Information pertaining to the optimum environmental mitigation option and environmental
enhancement measures was also obtained from the discussions and consultation with the local
people. The information solicited will be used extensively in the preparation of this EIA report,
particularly for the environmental baseline, prediction of environmental impacts; design of
mitigation and monitoring and in the preparation of environmental enhancement programs.
The FGD meeting was organized by giving a prior verbal notice through a runner. Separate
FGD were organized for indigenous peoples, women, Dalits and affected households and other
marginalized groups as they may have different agendas, interests and aspirations than the
dominant groups. The details of FGDs and consultation meeting conducted during the field
investigation period are provided hereunder in Table 4.2.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
31| P a g e Department of Electricity Development
Table 3-3: FGD Locations and Participant Details
S.N. FGD
Location Date
No of
Participants Discussed topic Remarks
1 Damku
(RM Hall)
October
25, 2017
Female: 3
Male: 11
Integrated development
planning for direct influence
area, royalties, local people
share, local people
employment/training
supporting for education and
health etc,
Including Elected
members of the
Mapya Dudh Koshi
RM at RM office
2
Damku
(Local
organization)
October
24, 2017
Female: 5
Male: 10
Income come generation
Training for kitchen
gardening, animal rearing,
tailoring, weaving, women
supported activities regular
checkup system for health
Members of Indreni
Cooperative Groups
3 Basa October
24, 2017
Female: 5
Male: 9
Improvement of Salleri to
Basa road section, protection
of the land slide, spring etc
Bazar area people
4
Padma Kanya
Basic School,
Basa
October
23, 2017
Female: 2
Male: 3
Employment, Supporting for
local level stakeholders etc
School teachers
5 Bodhu October
23, 2017
Female: 2
Male: 4
Limited land for cultivation so
that access road alignment
should be changed
Villagers
6
Rapcha CFUG
Office,
Lemchi
October
26, 2017
Female: 4
Male: 12
Employment opportunity/
affected area electrification
/10% share from local people/
trees plantation provision etc
Rapcha CFUC
members at CFUG
office
7 Dhirochan -7 October
23, 2017
Female :1
Male:4
Drinking water/ drip irrigation/
Kitchen gardening
Local people at
Damku
The list of persons consulted in the Community Forest User Group Meetings as well as minutes
of the FGD meetings along with attendance of the participant is presented in Annex 6.
b) Key Informant Interview
Key informant interviews are qualitative in-depth interviews with people who possess in-depth
knowledge of one or more aspect of the community. The purpose of key informant interviews
is to collect information from a wide range of people—including community leaders,
professionals, or residents—who have first-hand knowledge about the community. Table 3-4
hereunder provides details of KII conducted for EIA of the proposed DK-5 HPP.
Table 3-4: Details on KII
S.N. Subject Key Informant
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
32| P a g e Department of Electricity Development
1 Education Chairman- Management Committee, Shree Padma
Kanya Lower Secondary School
2 Community health, Diseases In-charge, Khastap Sub-health post
3 Fish and Fishing Practice Part time fisherman, Waku
4
Project area history, settlement patterns,
landslides and GLOF events, Disaster
events
Elder residents of Damku and Rapcha (2)
3.4 Data Analysis and Processing
Primary and secondary data were processed and analyzed using computer-based tools.
Available maps were interpreted. Information was tabulated. The information was cross
checked and analyzed. The data were processed using computer-based spread sheet and
presented in tabular and graphical formats.
The identification and prediction of impacts was done by considering the proposed project
actions/activities in terms of their relation to the baseline data of the area. The impacts of the
activities on biological resources in the defined influence area were analyzed. The impacts were
classified in terms of extent (site specific, local, and regional), magnitude (low, medium, and
high) and duration (short term, medium term and long term) as well as nature (reversible,
irreversible) and level (low, moderate, and significant). The likely impacts were assessed
covering both adverse and beneficial ones. The methodology adopted for impact identification
and prediction were standard checklists and matrix methods and expert judgment.
Furthermore, the identified impacts were prioritized and significant impacts were described in
the EIA report as indicated in the National EIA guidelines.
3.5 Public Consultation
Public Consultation was sought at the different stages of EIA report preparation. First of all, a
15-days public notice was published in a national daily newspaper for the scoping exercise. A
reconnaissance site visit was made to prepare the scoping document for the EIA study, during
which interactions with local people were carried out for identifying issues and concerns.
Suggestions from concerned Gaupalika/wards were collected for preparing the terms of
reference (ToR) for the study. During the EIA study phase, interactions with the local people
were made through focused group discussions and household survey of project affected
families. The photographs of the project area and the Focus Group Discussion are presented in
Annex-11.
3.6 Draft Report Preparation
Based on the processed data, the draft EIA report had been prepared and presented. The draft
EIA report comprised of baseline information on physical, biological, socio-economic and
cultural environment, project impacts both beneficial and adverse, which were identified and
predicted taking into consideration the baseline environmental conditions. The draft report also
includes benefit augmentation measures to enhance the beneficial impacts and mitigation
measures for adverse impacts to avoid, minimize and/or compensate adverse impacts. The
proposed compensatory and mitigation measures are based on the consultant’s earlier
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
33| P a g e Department of Electricity Development
experience of EIA study of development projects and government decisions on the
compensatory measures for the loss of forest area and tree due to the project implementation.
An Environmental Management Plan (EMP) has been included as an integral part of the EIA
report, which focused on the implementation of the environment protection measures,
environmental monitoring and auditing requirements along with implementation
responsibilities, organization, staffing, reporting, budget, and co-ordination aspects.
3.7 Public Hearing
A public hearing programme on “Environmental Impact Assessment Study of Dudhkoshi -5
Hydropower Project was organised by the proponent, DoED on 17th September 2018 (01 Ashoj
2075) in the premises of Samiksha Hall of Mapya Dudhkoshi Rural Municipality, Mapya Dudh
Koshi RM-3, Basa, Khastap of Solukhumbu District. The program was chaired by Mr. Narayan
Kaji Karki, Ward chairman of Mapya Dudh Koshi ward no. 3, Mr. Buddhi Kiran Rai, Chairman
of Mapya Dudh Koshi RM as the Chief Guest. The representatives from all the wards of Mapya
Dudh Koshi RM, representatives of members of parliament, different schools around the RM,
local pol, ice post community forests and political parties participated in the program. Other
participants included the representatives from local youth club, Aama Samuha, Mahila Samuha
and journalist of local media. Besides, local communities and the members from affected
families had also participated in the program. Out of them 127 people have signed on the public
hearing attendance sheet. The list of participants of the public hearing is given in Annex 9.
Summary of Issues raised by Stakeholders
During the Public hearing suggestion and quarries were noted and summary of the issues raised
in the program are listed below:
Table 3-5: Issues raised during public hearing
S. N. Issues Raised Where considered in Report
1 Data on actual forest loss is needed Incorporated under section
5.2.2,
2 Can Forest Users use electricity free of cost or not? 7.1.2
3 What compensation measures are there for forest loss,
there should be in report?
7.3.3.1
4 What types of benefits will be given to forest users in
return of forest loss, there should be in report?
7.2.5
5 There should be support programmes for livelihood
activities to locals who are partially of fully
dependent on fishing in Dudhkoshi river
7.2
6 While making tunnel, what could be the impacts the
structures lying over the ground such as Dipendra
Primary School and Basa Khali Secondary School?
These structures lie at an
approx. distance of 1.8 km
from the headrace tunnel.
Temporary vibration impact
will be there but insignificant.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
34| P a g e Department of Electricity Development
S. N. Issues Raised Where considered in Report
7 Employment opportunity should be given to locals. 7.1.1
8 Institutional share must be provided. 7.1.2 (v)
9 Free electricity should be given to impacted
households.
Comment Repeated
10 Individual share should be provided. 7.1.2 (v)
11 Public network should be maintained and there
should be mechanism of public participation in
project development
8.2.2
12 EIA report should address about tourism
development in project area.
7.1.1
13 All seven wards should be kept in impact zone of
project.
3.2
3.8 Recommendation Letters from the affected Rural Municipality/Wards
As per Rule 10 of EPR, 1997, recommendation letter from the directly affected Mapya
Dudhkoshi Gaupalika and Indirectly affected wards of Mapya Dudhkoshi Rural Municipality
were collected for the project implementation. Similarly, the recommendation letters from the
affected community forest user groups were also collected and are presented in Annex 10.
3.9 Finalization of EIA Report
This Draft Final EIA report has been prepared incorporating the issues/suggestions
raised/provided during the public hearing meeting and will be submitted to the Ministry of
Forests and Environment through the Ministry of Energy, Water Resources and Irrigation. The
Ministry (MoFE) will publish 30-day public notice seeking the opinion and suggestions from
the general public. A presentation of this final EIA report will be made in MoFE. The Report
will be finalized incorporating the valid comments of the EIA Review Committee and general
public if any.
3.10 Study Team
This EIA study has been performed and the report has been prepared by a multidisciplinary
team ofexperts and are presented in the Table 3-6. Declaration forms signed by the members
of study team are presented in the Annex-11.
Table 3-6: EIA Study Team
Name of Expert Expertise Education Position in
the Team
Shiv Shanker Karki Environment Environmental Engineering Team Leader
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
35| P a g e Department of Electricity Development
Sunil Thapa Hydropower
Engineer
Civil Engineering Team Member
Bhaskar Kafle Environment Environmental Engineering Team Member
Shiva Prasad Dhakal Sociology Sociology Team Member
Deep Bahadur Swar Aquatic Life
Expert
Zoology Team Member
Yogendra Yadav Ecologist Botany Team Member
Navaraj Pokhrel EMP Expert Environmental Science Team Member
3.11 Estimated Budget for EIA study
A total contracted amount of NRs. 2,866,000.00/- has been allocated to complete the EIA study
of DK5HPP.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
36| P a g e Department of Electricity Development
4. EXISTING ENVIRONMENTAL CONDITION
This section describes the existing baseline environmental situation of the project area. The
information provided is based on the detailed on-site environmental studies for the project area
during the EIA study phase.
The objective of the environmental baseline assessment is to assess the present state of the
environmental conditions in the project area (Site Specific, Project Rural Municipality and
Project District) in order to evaluate environmental impacts and issues of the project
development and operations.
4.1 Physical Environment
4.1.1 Climate
The project area has a cool-temperate type of climate. Climate of the area is influenced by the
physiography of the region. Dudh Koshi is a perennial river from the snow melt; however, it
tends to be influenced from south-west monsoon type climate. The project area has a moderate
summer season with a maximum temperature ranging from 25o C to 30o C. The minimum
temperature during winter ranges from -2o to + 2oC. The average annual rainfall is
approximately 1,736 mm.
4.1.2 Hydrology
Catchment Characteristics
Dudhkoshi River, one of the major tributaries of Sapta Koshi River has its origin in Mahalungur
Himal as Nojumba Glacier. Deku Khola, Luia Khola, Chhuserma Khola, Thado Koshi Khola,
Nagbuwathenja Khola, Manjo Khola and BhoteKoshi Nadi are the main tributaries of the Dudh
Koshi River. The catchment area of the Dudh Koshi River at the proposed intake site is about
1,590.93 square km. Geographically, the basin is located between longitudes 8631'00'' to
8659'00'' East and latitudes 2732'00'' to 2806’30'' North in the Solukhumbu District,
Province 1 of Nepal. The catchment area of Dudh Koshi River is bounded by Simhalila Dada
in the East, Tuplung and Simramlase peaks in the North, Dabala Dada and IwaNagi in the
South and Deurali Dada in the West side. The local gradient of the river is 3.23% at the
proposed headworks area. The width of the river at the proposed intake varies between 20 m
to 30 m.
The catchment area of Dudh Koshi River has elevations ranging from 1,235 m amsl near the
intake to about 8,188 m amsl. The catchment is covered with snow in higher altitudinal areas
and dense forest starts with hills to elevation of 4000 m amsl at Thyangboche. The area above
the El. 5000 m amsl is noted to be nearly 804.59 square km and above EL. 3000 m amsl is
1440.47 square km. Catchment area at intake site and the powerhouse location of the proposed
DK-5 HPP is 1,590.93 Km2 and 1,614.08 Km2respectively.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
37| P a g e Department of Electricity Development
Table 4-1: Catchment Characteristics
S. No. Description Units
Values for
Intake Site Powerhouse
Site
1 Catchment Area km2 1590.93 1614.08
2 Perimeter km 298.74 304.37
3 Area below 5000 m km2 786.82 809.96
4 Area below 3000 m km2 150.23 173.37
5 Elevation Minimum m 1225 1102
6 Elevation Maximum m 2978 3079
7 Longest Flow Profile
i. Length Km 81.80 87.62
ii. DS Elevation m 1225 1102
iii. US Elevation m 6660 6660
iv. Average Slope % 6.6 6.3
8 Basin Centroid m 2198 2099
Longitude Decimal
Degree
86.7127 86.7127
Latitude Decimal
Degree
27.8625 27.8576
Elevation m 5237 4767
Source: Feasibility Report 2019
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
38| P a g e Department of Electricity Development
Figure 4-1: Catchment Area of Dudh Koshi River
Establishment of Gauging Station
For the study of the discharge and sediment pattern of the Dudh Koshi River at the Proposed
Dudhkoshi Hydropower project hydrological station was established at Waku, Mapya
Dudhkoshi Rural Municipality-6 of Solukhumbu District. Since no previous records of flow
exist of the proposed Hydropower project, a manual type hydrological gauging station (3m
gauge height) was installed. The gauging station is 200 m upstream from the suspension bridge
and 1.5 km downstream of intake site.
Table 4-2: Discharge Measurement of the Dudh Koshi River
S. No. Date Discharge (m3/s) S. No. Date Discharge
(m3/s)
1 15 Jun, 2015 101.454 18 19 Feb, 2016 16.741
2 28 Jun, 2015 114.620 19 2 Mar, 2016 18.602
3 12 July, 2015 111.946 20 6 April, 2016 21.228
4 27 July, 2015 106.522 21 9 May, 2016 24.110
5 10 Aug, 2015 111.918 22 21 June, 2016 115.068
6 23 Aug, 2015 117.376 23 16 October, 2016 84.768
7 5 Sep, 2015 119.527 24 17 November,
2016 53.805
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
39| P a g e Department of Electricity Development
S. No. Date Discharge (m3/s) S. No. Date Discharge
(m3/s)
8 18 Sep, 2015 110.030 25 24 Dec, 2016 19.526
9 3 Oct, 2015 104.075 26 14 January, 2017 19.852
10 26 Oct, 2015 83.191 27 8 February, 2017 14.993
11 9 Nov, 2015 60.565 28 8 March, 2017 15.219
12 22 Nov, 2015 44.622 29 17 April, 2017 15.284
13 11 Dec, 2015 29.185 30 10 May, 2017 14.924
14 26 Dec, 2015 26.386 31 15 May, 2017 122.370
15 9 Jan, 2016 24.605 32 13 October, 2017 122.433
16 21 Jan, 2016 23.693 33 20 Nov, 2017 62.430
17 4 Feb, 2016 22.020 34 7 Dec, 2017 60.863
Source: Feasibility Report, 2019
Mean Monthly Flow
For comparison mean monthly flow weighted average from catchment correlation using
stations 670, 647, WECS/DHM (Hydest) method and MIP method were done. The weight for
flow from stations 647 is assigned 0.1 and 670 is assigned 0.60 whereas for linearly correlated
data with the average from 647 and 670 was assigned 0.3 whereas for WECS/DHM and MIP
method no weights are assigned. They are shown here just for the comparison. Even though
the catchment area is greater than 100 km2, the estimated value from WECS/DHM method was
very low compared to other methods, similarly as MIP method is recommended for use in
catchments with area less than 100 km2 and the catchment here is very large than 100 km2. The
mean monthly flow for the river from various methods are presented in table below:
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
40| P a g e Department of Electricity Development
Table 4-3: Estimated Mean monthly flow
Month Flow (Dudhkoshi)
(m3/s)
Flow (Tamakoshi)
(m3/s) Flow (Hydest) (m3/s) MIP (Average) (m3/s)
Linear correlated
(m3/s) Accepted Flow (m3/s)
Jan 18.99 15.90 9.66 29.91 19.15 18.73
Feb 15.60 13.87 8.22 20.75 15.74 15.47
Mar 14.93 13.41 7.60 15.23 15.07 14.82
Apr 17.81 15.40 8.40 11.04 17.96 17.61
May 30.82 28.31 12.09 20.75 31.03 30.63
Jun 105.16 89.06 75.65 34.54 105.73 103.72
July 243.33 228.58 116.94 149.43 244.54 242.22
Aug 257.61 268.71 138.35 275.91 258.89 259.11
Sep 190.73 168.09 105.43 229.88 191.69 188.75
Oct 80.62 67.35 45.95 115.00 81.07 79.43
Nov 38.22 32.01 38.71 55.18 38.47 37.67
Dec 24.94 20.94 25.26 41.39 25.12 24.59
Source: Feasibility Study Report, 2019
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
41| P a g e Department of Electricity Development
Figure 4-2: Flow Hydrograph
Figure 4-3: Flow Duration Curve for Dudhkoshi River
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
42| P a g e Department of Electricity Development
Figure 4-4: Energy Table
Low Flow Analysis
WECS/DHM Method
The low flow study is important for knowing whether there is any risk to turbines during
operation perioddue to unusually low river flow for which the frequency analysis of the
minimum flow is required. The low flow analysis is carried out using the WECS/DHM method
and the values for various return periods are given in table below
Energy Calculation
Unit wt. of water 9.81 KN/m3
NWL at inlet of HRT 1251.25 masl
NWL at tailrace 993.160 masl
Gross head 258.09 m
Turbine efficiency 93 %
Generator efficiency 97 %
Transformer efficiency 98 %
Overall efficiency 88.406 %
S.no. Dry Season
1 0.5 %
2 0.5 %
3 1 %
4 1 %
Total 4 3 %
3 %
4 %
River
Flow
Riparian
Flow
Available
Flow
Turbine
discharge
Head
loss
Net
head
Generation
capacity
Dry season
energy
Wet season
energy
m3/s m3/s m3/s m3/s m m kw kwh kwh
Jan 31 18.73 1.48 17.248 17.248 1.819 256.271 38334.382 27665156.517
Feb 28 15.47 1.48 13.988 13.988 1.212 256.878 31162.498 20312962.943
Mar 31 14.82 1.48 13.338 13.338 1.108 256.982 29726.516 21453031.781
Apr 30 17.61 1.48 16.128 16.128 1.591 256.499 35876.960 12528234.370 12399077.315
May 31 30.63 1.48 29.148 29.148 5.059 253.031 63963.574 45685343.272
Jun 30 103.72 1.48 102.238 52.460 16.305 241.785 110003.767 76034603.503
Jul 31 242.22 1.48 240.738 52.460 16.305 241.785 110003.767 78569090.287
Aug 31 259.11 1.48 257.628 52.460 16.305 241.785 110003.767 78569090.287
Sep 30 188.75 1.48 187.268 52.460 16.305 241.785 110003.767 76034603.503
Oct 31 79.43 1.48 77.948 52.460 16.305 241.785 110003.767 78569090.287
Nov 30 37.67 1.48 36.188 36.188 7.764 250.326 78563.395 54303018.316
Dec 31 24.59 1.48 23.108 23.108 3.202 254.888 51081.203 18432141.134 18242119.060
100.3915267 518.4060358
Total annual energy generated (GWH) 618.7975626
Wet Season
0.5
0.5
2
1
Types of losses
Station Consumption
Forced Outage/ System trip
Planned Outage/ Overhaulings
Transmission losses
Month
Numbers of
operating
days/ month
Total seasonal energy (GWH)
Dry season outage
Wet season outage
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
43| P a g e Department of Electricity Development
Table 4-4: Low flows at the Intake Site, m3/s
Return Period
(yrs)
Duration
(Days) Low Flow Discharge (m3/s)
2
1 5.98
7 6.25
15 6.94
monthly 7.26
10
1 4.36
7 4.67
15 5.34
monthly 5.63
20
1 3.96
7 4.31
15 4.99
monthly 5.27
Low Flow Analysis by Statistical method
Considering the DHM data of the instantaneous low flow at Rabuwa bazaar the analysis of the
low Flow has been made using Weibul method. The result obtained from the low flow analysis
has been presented in the table and figure below:
Figure 4-5: Low Flow Analysis by Weibul Method
The summary of the major return period flow is presented the Table 4-5 also.
Table 4-5: Low Flow Analysis by Weibul Method
Return Period (Year) Flow (m3/s)
43 5.20
21.5 6.98
0.00
5.00
10.00
15.00
20.00
25.00
30.00
35.00
40.00
45.00
0 5 10 15 20 25 30 35 40 45 50
Min
imu
m F
low
(C
um
ecs)
Return Period (Yr)
Low Flow Analysis
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
44| P a g e Department of Electricity Development
Return Period (Year) Flow (m3/s)
10.75 7.37
4.3 9.54
1.72 12.49
1 41.91
Extreme Discharge Calculation
For the study of extreme discharge, the data from Station 670 and Station 647 were used and
comparisons were done between results from these two methods. Gumbel’s method, log normal
and log Pearson type III methods were used to estimate the extreme discharges for different
return periods. Standard error was calculated for each method and based on the standard error,
the accepted maximum discharge values were calculated using the weighted average method.
The weightage of 0.4 was assigned to Log Pearson type III from Station 647 and 0.2 value was
assigned to Log Pearson from Station 670 and 0.1 was assigned for values from others. From
this calculation, the accepted extreme discharge value for 100 years return period is 2431.22
m3/s. During the calculation of extreme discharge, the values from WECS/DHM method was
not used in this study as the computed discharge was different from other methods. The
computed extreme discharge is given in Table4-6:
Table 4-6: Flood Flow at Intake Site (m3/s)
Return
period
(T)Years
Discharge from different stations using different methods, m3/s
From Dudhkoshi @ Rabuwa Bazar
(Station (#stn.670)
From Tamakoshi @ Busti
(# Stn.647)
Accepted
Gumbel Log
Normal
Log
Pearson
type III Gumbel
Log
Normal
Log
Pearson
Type III
2 787.00 959.09 903.50 627.48 715.63 709.66 812.25
5 1383.20 1265.49 1284.63 810.68 842.91 845.07 1113.09
10 1777.94 1482.34 1638.28 931.97 925.42 937.59 1354.60
20 2156.58 1697.71 2072.66 1048.31 1002.60 1027.55 1625.09
25 2276.69 1767.43 2233.44 1085.22 1026.71 1056.34 1720.25
50 2646.70 1986.44 2811.46 1198.91 1100.03 1145.91 2046.97
100 3013.97 2210.46 3532.90 1311.76 1171.67 1236.39 2431.22
200 3379.90 2440.67 4436.08 1424.20 1242.26 1328.43 2888.82
300 3593.63 2578.56 5067.49 1489.87 1283.24 1383.18 3198.16
400 3745.17 2677.94 5569.41 1536.43 1312.21 1422.49 3439.44
500 3862.68 2755.95 5992.93 1572.54 1334.65 1453.26 3640.41
1000 4227.55 3003.59 7527.41 1684.65 1404.21 1550.56 4353.08
S.E. 18.19 12.24 8.81 4.43 1.46 1.35
Source: Feasibility Report, 2019
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
45| P a g e Department of Electricity Development
Tributaries in the Dewatered Zone
Seven streams drain to the potential dewatered zone of the Dudhkoshi in the project area. The
average discharge of the streams calculated based on the HYDEST method is presented in
Table 4-7 for the different months of the year.
Table 4-7: Flow of tributaries in the Dewatered Zone (m3/s)
SN Month
Mean monthly discharge (m3/s)
Tributary 1
(@ 1.27 km
from weir)
Tributary 2
(@ 1.7 km
from weir)
Tributary 3
(@ 2.27 km
from weir)
Tributary 4
(@ 3 km
from weir)
Tributary 5
(@ 3.5 km
from weir)
Tributary 6
(@ 6.2 km
from weir,
Mahuri
Khola)
Tributary 7
(@ 7.46 km
from weir,
Chelsi
Khola)
1 Jan 0.03 0.04 0.04 0.04 0.07 0.07 0.04
2 Feb 0.03 0.04 0.03 0.03 0.06 0.06 0.04
3 Mar 0.02 0.03 0.03 0.03 0.05 0.05 0.03
4 Apr 0.02 0.03 0.02 0.02 0.04 0.05 0.03
5 May 0.02 0.03 0.03 0.03 0.05 0.05 0.03
6 Jun 0.06 0.11 0.09 0.09 0.18 0.21 0.10
7 Jul 0.32 0.46 0.39 0.41 0.68 0.76 0.42
8 Aug 0.41 0.58 0.49 0.52 0.86 0.97 0.54
9 Sep 0.32 0.46 0.39 0.41 0.68 0.76 0.42
10 Oct 0.14 0.20 0.17 0.18 0.30 0.33 0.19
11 Nov 0.04 0.07 0.06 0.06 0.12 0.13 0.06
12 Dec 0.03 0.05 0.04 0.04 0.08 0.09 0.04
4.1.3 Watershed Characteristics
The entire upstream catchment area is covered by the forest with dense shrubs. The catchment
area also covers snow fed zone. The hill side slope in the catchment area ranges from steep to
mild. Slopes along the left bank of Dudh Koshi River comprise of forest, widely cultivated land
and settlement of Damku and Bodu villages. The right bank has forest, cultivated land and
settlement of Khanigaun and Budhabare. The underground powerhouse is proposed nearby the
confluence of MahuriKhola and Dudh Koshi River, wherein, forest area exists.
The hills are covered with forests and very little plain land is available for cultivation. Most of
the reach of the river is covered with large boulders. Dudh Koshi watershed lies in three
districts – Solukhumbu in the North, Okhaldhunga in the South-West and Khotang in the
South-East.
4.1.4 Sediments
The collection of the samples for the suspended sediment was done on daily basis for the
monsoon season and the sample was collected from the headworks site regularly for the period
of 2 months. 60 regular sediments were extracted with the help of samplers and 10
instantaneous observations were taken during high floods. The samples are collected by depth
integration method as generally used by the DHM for the rivers having the depth greater than
1 m. The results of this analysis show that the maximum concentration of suspended sediment
in Dudh Koshi River is about 504 ppm on 24 July 2016 (2073/04/09), whereas there are some
samples which have concentration of 4 ppm (16 June 2016 and 5July 2016).
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
46| P a g e Department of Electricity Development
Mineral composition analysis was carried out under the binocular microscope at Central
Department of Geology. For this propose several samples were analyzed under several field of
vision. In average, ~ 60% grains are of quartz, ~22% muscovite/biotite, ~10% rock fragments
and opaques and ~8% feldspar. The hardness of these grains is not similar. According to Mohr's
Scale of Hardness, the hardness of investigated particles are as follows: Quartz=7, Feldspar=6,
Biotite/Muscovite= 3.5, Rock fragments/opaques= variable (~ 5 in average).
4.1.5 Glacial Lake Outburst Flood (GLOF)
The Dudh Koshi Sub-basin is the one that contains the highest number of glacial lakes as well
as lakes associated with glaciers. The potentially dangerous lakes of the Dudh Koshi Sub-basin
are Lumding Tsho, Dig Tsho, Chokarma Cho, Imja Tsho, Tam Pokhari, Hungu Lake, East
Hungu 1, East Hungu 2, and West Chamjang. Among these, Dig Tsho and Tam Pokhari already
had outburst events in 1985 and1998 respectively. There were numbers of events of GLOFs in
Dudh Koshi basin. On 3rd September 1977 a relatively small glacial lake located at a higher
elevation discharged into Nare Lake, located below the peak of Mt Ama Dablam. The rapid
inflow of water caused Nare Lake to overtop its end-moraine dam and discharge into the Imja
Khola (river) and thereafter down the Dudh Koshi valley. The hydrological recording gauge at
Rabuwa Bazar, 90 km downstream from the source, showed a prominent discharge peak on 3
September 1977. Nevertheless, this attenuated GLOF discharge peak was far below those
recorded on the 26th, 27th, and 28th August 1977, due to ’normal’ summer monsoon peak
floods (ICIMOD, 2011). (4 August 1985, there was a catastrophic GLOF on Dig Tsho.
Vuichard and Zimmermann (1986, 1987) estimated that 6–10 million cubic metres of water
drained from the lake in about four hours, making the average rate of discharge about 500
cumecs. They estimated an actual peak discharge of water as high as 2,000 cumecs. From
accounts given by local eye witnesses, it appears that there were two or more distinct surges
because the bridge at Jubing, 40 km downstream from the source, washed out 90 minutes after
the initial flood wave had passed. On 3rd September, 1998 GLOF was triggered in Tam Pokhari
Lake when an ice avalanche hit the frontal lake and induced a surge wave which overtopped
the end moraine dam. (ICIMOD, 2011).
The glacial Chokarma Chohas also drained out in the past (source: ICIMOD, 2001). Similarly,
Imja Tsho, which seems to be a probable out bursting lake has drained by Nepal Army in year
2016.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
47| P a g e Department of Electricity Development
Figure 4-6: GLOF events recorded in Nepal (after Mool et al. 1995, 2001a; Yamada
1998a; Bajracharya et al. 2008; Ives et al. 2010)
4.1.6 Geology and Geomorphology
Regional Geology
The project area is located in the Lesser Himalayan Zone in the eastern part of Nepal about 296
km east of Kathmandu, which lies in the eastern part of the Himalayan Arc. The lesser
Himalaya covers about one- third (800 km) of the Himalayan Arc. The Great Himalayan Arc
is thought to be formed by the collision between the Indian plate and Eurasian tectonic plates
spreading over a distance of 2400 Km from Pakistan in the west and to Burma in the east.
The Himalaya is the youngest mountain system in the world and extends in an east west trend
with an approximate length of 2400 km. Geologically, it is divided into five sections, after
Bordet (1961) and Gansser (1964). From west to east these are the Punjab Himalaya, Kumaon
Himalaya, Nepal Himalaya, Sikkim-Bhutan Himalaya, and the North East Frontier Agency
(NEFA) Himalaya. The Nepal Himalaya extending from the Mahakali River in the west to the
Mechi River in the east, running the entire length of Nepal is a part of the Great Himalayan
Range. The Nepal Himalaya occupies the central part (800 km) of the 2400 km long
southwardly convex Himalayan arc. The major five morphogenetic zones of the Nepal
Himalaya from south to north as per “Gansser, 1964, Hagen, 1969”, and “Amatya and Jnawali,
1994” are given below.
Project Location
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
48| P a g e Department of Electricity Development
Figure 4-7: Simplified geological map of the Himalaya showing major litho-tectonic divisions (After Gansser, 1964).
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
49| P a g e Department of Electricity Development
The Lesser Himalaya lies between the Main Boundary Thrust (MBT) in the south and the Main
Central Thrust (MCT) in the north. In general, stratigraphy of the Lesser Himalaya of Nepal
can be divided into four major groups as: Nuwakot Complex/Group (Stöcklin and Bhattarai,
1977; Stöcklin, 1980; Paudyal and Paudel, 2013 in central Nepal), Tansen Group (Sakai, 1983
and 1985, in western Nepal), Dang-Salyan Group (Dhital and Kizaki, 1987, mid-western
Nepal) and Pokhara Subgroup of the Midland Group of Department of Mines and Geology
(DMG, 1987, in eastern to western Nepal).
Project Area Geology
Locally, Dudh Koshi-5 Hydropower Project area lies to the Pokhara Sub-Group of the Lesser
Himalayan Zone in eastern Nepal. The total project area lies within the Seti Formation (DMG,
1987) which is a succession of grey to greenish grey, gritty phyllites and quartzites with minor
conglomerate layer. Basic intrusions are also noted within the succession. The Main Central
Thrust (MCT) is the only major thrust near the area and is located at about 10 km North from
the project area. The lithological succession (rock type) of the project area can be divided into
two unit.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
50| P a g e Department of Electricity Development
Figure 4-8: Generalized geological map of Nepal (modified afterUpreti and Le Fort, 1999)
Project Area
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
51| P a g e Department of Electricity Development
Figure 4-9: Geological Map of Eastern Nepal
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
52| P a g e Department of Electricity Development
Engineering geological condition of each project component is described as follows:
(i) Intake Area
The proposed intake site is located approximately 500 m downstream of the confluence of
Thane Khola with Dudh Koshi River at altitude of around 1225 m. This site is proposed for the
weir axis. The left bank of the river at weir axis contains alluvial terrace followed by bed rocks
of fresh gneiss while the right bank contains rocky slope covered with colluvial soil mixed with
minor amounts of alluvial soil of Dudh Koshi terrace.
Gneiss unit is well exposed at and around the intake area. It is predominantly composed of
gneiss with minor amounts of white quartzite. Well-developed pockets of augen gneiss are
found in the fresh exposures. The gneiss is medium-to coarse-grained, thickly-foliated and non-
calcareous in nature. Overall composition of the rock is dominated by psammatic minerals (e.g.
quartz and feldspar) over pelitic minerals like micas and chlorites. The general dipping of this
unit is northwards in intake area. The beds at the intake area are dipping towards north having
the dip amount of about 20°-35°. The degree of weathering is moderate in general as indicated
by the discoloration and bleaching effects seen in the fresh minerals. In some places, feldspar
is deeply weathered to the kaoline.
(ii) Desander area
Desander area is located at right bank of the Dudh Koshi River about 200 m downstream from
the proposed weir axis. The desander basin is composed of bed rocks (gneiss) thinly covered
by colluviums. Vegetation is thick and is grown in the weathered bed rocks and colluviums.
No potential geological hazards like shear zone, fracture zones etc. are found around the
desander area.
(iii) Tunnel Alignment
About 6.11 km long headrace tunnel passes through the Gneiss unit. The rocks of the proposed
inlet portal are of fresh augen gneiss. However, immediate to the up stratigraphic section to
this succession there is a fairly laminated succession of metasandstone in low dip. The total
section of tunnel passes through the gneissic rocks and not from the overlying phyllite and
metasandstone rocks.
In general, the rock along the tunnel is considered to be good rock (Geological Strength Index
(GSI)~60 and Rock Mass Rating (RMR)~10). For construction of Tunnel Support Type I is
enough in the normal case as observed from the outcrops at the surface both for headrace,
penstock and adit tunnels.
(iv) Surge Tank Area
It lies in the 950m elevation. The area is covered with medium to sparsely covered mixed forest.
Slope of the area is steep (~ 650), however it is straight and smooth. The geology consists of a
monotonous succession of gneiss with minor amounts of quartzites. Most of the area is well-
covered by the direct exposure of bed rocks while the remaining area is covered with shallow
layers of colluviums. No major landslides or faults are found as adverse geological conditions.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
53| P a g e Department of Electricity Development
(v) Powerhouse Area
The powerhouse is located about 1.7 km downstream from the confluence of the Mahuri Khola
and the Dudh Koshi River, at the right bank of the Dudh Koshi. There is exposure of bed rocks
covered with thin layers of both colluvial and alluvial admixtures. It has steep slope made up
of bed rocks (gneiss) at the up-hill section. Geomorphology of the powerhouse area including
the surge tank shows quite rugged with several streams having steep gradient flowing towards
the Dudh Koshi River.
Figure 4-10: Geomorphic view of the powerhouse and surge tank area
(vi) Landslide, slope stability
The major landslides are distributed in the Phyllite-Metasandstone Unit, a younger stratigraphy
of the area. Some of the earthquake triggered landslides are also observed at the lower reaches
of the Basa village. Rate of soil erosion is found higher at the sides of the small streams joining
to the Dudh Koshi. A most remarkable feature is the indication of creeping at the up section of
the intake area. Next is the presence of a dry debris flow about 50 m downstream of the
confluence of the Dudh Koshi and Thane Khola, at the right bank side of the Dudh Koshi. It is
about 300 m upstream of the presently proposed weir axis. Geologically, there is uniform
structure from the intake to the power house area. However, there is no any major thrust passing
through the project area.
Detail discontinuity survey was carried out at and around the rocky slopes of the project area
to assess the stability condition. Stereographic projection of major joint sets and hill slope
measured in the right bank of Dudh Koshi River in intake area shows that the area is prone to
plane failure. The condition for wedge failure also exits.
4.1.7 Air and noise quality
The project area lies in a rural setting with no industrial activities. No major parameters
affecting air quality at present are found in the area and its vicinity. Use of firewood for cooking
purpose has some impact. Field observations showed that there is no point-source for degrading
the air quality and hence air quality is also found to be good. The equivalent sound level
measured by the sound level meter in the headworks and powerhouse sites were 34.9 dBA and
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
54| P a g e Department of Electricity Development
35.4 dBA respectively. The particulate matter concentration of SPM and PM10 measured at
Rapcha was found to be 193.6μg/m3 and 86.2μg/m3; considerably above the other measured
sites as shown in table 4.8. The major contributors to these particulate matters are related to
vehicle blew dust from recently constructed rural earthen roads and dust arising from soil
disturbance while preparing the field for agriculture.
Table 4-8: Ambient air quality at project area and national permissible limits
Station
code
Date of
sampling
Hrs. of
sampling Name of the Location
Total SPM
mass (µg/m3)
Total PM10
mass (µg/m3)
National Ambient Air Quality Standard for Nepal, 2003 230 120
S-1 5th Jan 2019 24 hrs. Headwork 119.0 54.3
S-2 6th Jan 2019 24 hrs. Powerhouse 137.2 61.5
S-3 7th Jan 2019 24 hrs. Settlement (Rapcha) 193.6 86.2 Source: EIA Field Survey, 2017/18
Since the project area is located in a rural area and there are no industries within the project
area. No vehicular activities are also found in the project area. The maximum (Rapcha) and
minimum (Headwork) noise levels recorded were 57.2 dBA and 21.3 dBA, respectively as
shown in table 4.9. The maximum sound levels recorded at settlement is mostly attributed to
house construction, vehicular and human movement.
Table 4-9: Noise level measured in the different project area
Station
code
Date of
monitoring
Number of
spot
measurement
Location
Sound pressure (dBA)
Maximum Minimum Average
S-1 5th Jan 2019 5 Headwork 47.3 21.3 34.9
S-2 6th Jan 2019 5 Powerhouse 48.8 24.3 35.4
S-3 7th Jan 2019 5 Settlement
(Rapcha) 57.2 30.7 42.6
Source: EIA field Survey, 2017/18
4.1.8 Water quality
The water quality analysis of Dudh Koshi River was carried out on November 10th 2017 and
March 3rd 2018 at two locations namely: Sampling station 1 (at the intake site), and Sampling
station 2 (at the powerhouse site). The turbidity of Dudh Koshi River varies according to the
time of year the sample is taken.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
55| P a g e Department of Electricity Development
Table 4-10: Water Quality Test Results
S.
N. Parameters
Test
Methods
Observed values
Drinking
Water, Basa-
2
Drinking Water,
Dudhkoshi-4
River Water,
(Intake)
River Water,
(Powerhouse)
1 Turbidity,
NTU
2130 B,
APHA, 21st
EDITION
<1.0 <1.0 52 2.0
2 Conductivity,
µS/cm
2150 B,
APHA, 21st
EDITION
10 28 41 53
3 pH @ 20oC 4500-H+ B,
APHA, 21st
EDITION
6.1 6.7 6.5 6.8
4 Total
Dissolved
Solids, (mg/l)
2540 C,
APHA, 21st
EDITION
6.0 17 24 32
5 Total
Suspended
Solids, (mg/l)
2540 D,
APHA, 21st
EDITION
<1.0 <1.0 31 1.0
6 Total
Hardness as
CaCO3,
(mg/l)
2340 C,
APHA, 21st
EDITION
18 16 32 36
7 Total
Alkalinity as
CaCO3,
(mg/l)
2320 B,
APHA, 21st
EDITION
8.0 14 16 20.0
8 Dissolved
Oxygen, mg/l
4500-0 A,
APHA 21st
EDITION
7.9 8.4 8 6.3
9 Iron, mg/l 3111 B,
APHA, 21st
EDITION
0.01 <0.01 1.6 0.63
10 Sulphate,
mg/l
4500-SO4,
APHA, 21st
EDITION
<5.0 <5.0 <5.0 <5.0
11 BOD, mg/l 5210 B,
APHA, 21st
EDITION
1.9 0.8 6.3 16.8
12 E-Coli,
CPU/100 ml
9222 D,
APHA, 21st
EDITION
12 nil 110 1
APHA: American Public Health Association
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
56| P a g e Department of Electricity Development
The water samples were tested at Water Engineering & Training Centre Private Limited in
Kathmandu. The test reveals that the quality parameters are suitable for sustaining fish and
aquatic life. The dissolved oxygen content (an index of water quality in relation to flora and
fauna) was found to be between 6.3 mg/L and 8.4 mg/L which is an acceptable level (dissolved
oxygen content below 5 mg/L is unsuitable for fish and aquatic life). The pH level of the water
at sampling site was between 6.1 and 6.8, which is suitable for aquatic life. A pH level lower
than 5 (acidic water) is most damaging to eggs and larvae of aquatic organisms. Most aquatic
life (except for some bacteria and algae) cannot survive a pH < 4. Variation in temperature has
an important influence on all the organisms including fish since feeding, respiration and all
other physiological activities are influenced by temperature. Total water hardness, which
ranges from 32 to 36 mg CaCO3/L between the intake site and powerhouse sites respectively,
is considered to be suitable for fish growth. Finally, all the observed values of all the tested
parameters were found to be within the limit of Nepal’s National Drinking Water Quality
Standards, 2062 (NDWQS). However, activities like open defecation and use of water for
different domestic purposes like bathing, washing utensils, etc are common among the
settlements residing along the riverbank and is likely to be contaminated by microbial
contamination. The complete analysis results are presented in Annex 5.
4.1.9 Land use pattern
Solukhumbu district lies between 27o20’39” to 28o6’24” North and 86o0’21” to 87o0’1” East.
The total area of the district is 339776 ha which comprises 33312 ha agriculture land
(Cultivated-21435 ha and Non-cultivated-11877 ha), 49849 ha pasture land, 105330 ha forest
land and 151285 ha other land. The total area of the district is 339776 ha; majority of the area
is covered with 31.27 % (105330 ha.) forest area and 9.8% (33312 ha.) agricultural land. Table
4-11 represents the land use pattern of the District.
Table 4-11: Land use pattern of Solukhumbu district (Ha)
Physical
Condition
Agriculture (ha.) Non-Agriculture (ha.)
Total (ha.) Cultivated
Non-
Cultivated Pasture Forest Others
High Himalaya 503 89 31,808 10,937 149,174 192,511
High Mountain 19,602 11,314 17,812 93,673 2,063 144,464
Mid Mountain 1,330 474 229 720 48 2,801
Total 21,435 11,877 49,849 105,330 151,285 339,776
Source: District Profile of Solukhumbu, 2074
The land use pattern of the project area can be broadly divided into agriculture land, barren
land, forest land (including degraded shrub area), river and flood plain. Within the project area
boundary, agriculture land along with the settlement accounts for the major portion of land use,
which is about 66.2% of total land. Similarly, forest area, barren pubic land and river and flood
plain account for 15.3%, 11.3% and 7.2%, respectively.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
57| P a g e Department of Electricity Development
Table 4-12: Land Use Pattern of Project Area
S.N. Land use type Percent (%)
1 Forest Area 15.30
2 Agricultural area (Khet and Bari land) including settlement 66.20
3 Barren land 11.30
4 River and Flood plain 7.20
Total 100
Source: Feasibility study/Field survey, 2017
4.2 Biological Environment
4.2.1 Forest Types of Solukhumbu District
The forests of the district are broadly classified into five types, namely, subtropical deciduous
hardwood forest, lower temperate mixed deciduous and coniferous hardwood forest, upper
temperate mixed deciduous and coniferous hardwood forest, high altitude coniferous forest and
shrub. Subtropical hardwood forest covers an area of 3535.20 Ha with the species of Sal, Harro,
Barro etc. and is found in the southern region of the district below 1000 masl and rivers. Lower
temperate mixed deciduous and coniferous hardwood forest is found in altitudes between
1000m and 2000 m and occupies 24,748.40 Ha of area. The main species of trees are
rhododendrons, Pinus wallichina. Upper temperate mixed deciduous and coniferous forest is
found in altitudes between 2000m and 3000 m, and occupies 36,873.40 Ha of area. The major
species of trees include rhododendrons, Quercus spp, Alnus nepalensis. High altitude
coniferous forest is found between the attitudes of 2500m to 3500 m with the species of thingre
sallo (Tsuga dumosa), khasru (Quercus semecarpfolia), and maple. This type of forest occupies
an area of 20324 Ha. Shrub forest occurs above 3500 m altitude and occupies 19.84 Ha area of
the district (DFO- Solukhumbu, 2068). Sagarmatha National Park, a national park in the
Himalayas of eastern Nepal, is situated in the Solukhumbu District. The park is situated at a
distance of about 24 km from the Dudhkoshi-5 Hydropower Project area and it is shown in the
Figure 4-11 below.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
58| P a g e Department of Electricity Development
Figure 4-11: Project Location and Sagarmatha National Park
4.2.2 Vegetation and Forest Type in the Project Area
Broadly the project area lies in central midlands with nine different vegetation zones of Central
Biogeographic region in Subtropical Life Zone (Figure 4-12). But the project components lies
within only two vegetation zone—Schima Castanopsis Forest and Chir Pine-Broadleaved
Forest. The project area with surge tank, power house and tailrace lies in Schima-Castanopsis
Forest while rest of the project area lies in Chir Pine –Broadleaved Forest Zone. Although the
lower part lies in Schima-Castanopsis Forest, the forest is Chir Pine due to reforestation in
community forests. Schima-Castanopsis forest is largely dominated by Castanopsis indica.
When mixed with Schima wallichii, it has a number of other associates as well such as Lyonia
ovalifolia, Eurya acuminata, and Engelhardia spicata. The chir pine-broadleaved forest occurs
between 1000-2000 m. It is generally composed of Pinus roxburghii, Quercus incana, Q.
lanata, Rhododendron arboreum, L. ovalifolia, E. spicata, Erythrina stricta and S. wallichii.
In the project area, S. wallichii and E. spicata remains the main associated species.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
59| P a g e Department of Electricity Development
Figure 4-12: Vegetation Zone in Project Area
Community Forestry is common in Solukhumbu district. The total number of private forest is
121 and community forest is 169 in Solukhumbu district.There are 5 types of forest such as
Sub-tropical deciduous broad-leaved hardwood forest, which lie at altitude less than 1000m;
Lower-temperate mixed deciduous and coniferous hardwood forest, which lie at altitude of
1000m to 2000m; Upper-temperate mixed deciduous and coniferous hardwood forest, which
lie at altitude of 2000m to 3000m; High altitude coniferous forest, which lie at altitude of 2500
m to 3500m; and shrubs.
4.2.3 Community Forests in the Project Area
Within the Mapya Dudh Koshi Rural Municipality, there are 27 community forests registered
in Division Forest Office (old District Forest Office), Solukhumbu. Among them 7 lies within
the project area. Details of community forests located within the project area are presented in
the table below.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
60| P a g e Department of Electricity Development
Table 4-13: List of Community Forests in and around the project area
S.N. Name and
Address of CF Location
Total Area
(ha.) Major Tree Species Remarks
1
Dudh Koshi CF,
Mapya Dudh
Koshi RM-1
Just above of weir
Site (left bank) 419.80
Uttis, Mauwa,
Albizzia, Pine
Affected by backwater flow
due to damming
2
Rapchha CF,
Mapya Dudh
Koshi RM-2
weir site (right
bank) 496.80
Uttis, Mauwa,
Albizzia,
Affected by backwater flow
due to damming, weir&
Reservoir, Intake and
Flushing Tunnel, CMS2, SD2
3
Bhirkuna CF,
Mapya Dudh
Koshi RM-6/7
weir site and In
between the route
(left bank)
394.20
Uttis, Mauwa,
Albizzia, Sallo,
Mauwa, Chhilaune,
Khirro
Affected by backwater flow
due to damming, weir&
Reservoir
4 Waku CF, Mapya
Dudh Koshi RM-6
In between the
route (left bank)
and left bank of
Power House
74.32 Uttis, Mauwa,
Albizzia, Sallo,
Mauwa, Chhilaune,
Khirro
No direct impact
5 Basa CF, Mapya
Dudh Koshi RM-3
In between the
route (right bank)
110.80 Sallo, Mauwa, Uttis,
Chhilaune, Khirro SD2, SD3
6 Lemchikharka CF,
Dudh Koshi RM-3
In between the
route (right bank)
58.37 Sallo, Mauwa,
Chhilaune, Khirro Adit portal, SD4
7 Bijai CF, Dudh
Koshi RM-4
Power house site
(right bank)
75.60 Saj, Khirro, Sallo,
Mallato Power house, Tailrace, CMS3
Source: Field survey, 2017
4.2.4 Forest/Vegetation Species
The major species of tree, shrubs and herbs vegetation recorded from the project area during
walkthrough survey of the proposed project site is presented in Table 4.14 below.
Table 4-14: Recorded species of tree vegetation in the project area
S.N. Local Name Scientific Name
1 Gurans Rhododendron arboreum
2 Khote sallo Pinus roxburghii
3 Gobre sallo Pinus wallichiana
4 Khirro Sapium insigne
5 Chilaune Schima wallichii
6 Mauwa Engelhardtia spicata
7 Uttis Alnus nepalensis
8 Phaledo Erythrina variegata
9 Siris Albbizia sp.
10 Amala Phyllanthus emblica
11 Tuni Toona ciliata
12 Simal Bombax ceiba
13 Pahele Litsea oblonga
14 Angeri Lyonia ovalifolia
15 Khanyu Ficus semicordata
16 Bhalayo Semecarpus anacardium
17 Bhakkiamilo Rhus parviflora
18 Badahar Artocarpus lakoocha
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
61| P a g e Department of Electricity Development
19 Daar Boehmeria regulosa
20 Tanki Bauhinia purpurea
21 Koiralo Bauhinia variegate
Source: Field Observation and Consultation, 2017/2018
Table 4-15: Recorded Species of Shrubs in the project area
S.N. Local Name Scientific Name
1 Titepati Artemisia indica
2 Bhende kuro Barleria cristata
3 Chutro Berberis asiatica
4 Gargalo Boehmeria platyphylla
5 Gwello Callicarpa macrophylla
6 Hinguwa Camellia kissi
7 Nilo dhusure Caryopteris odorata
8 Barkule Casearia glomerata
9 Bhati Clerodendrum sp.
10 Dhusure Colebrookea oppositifolia
11 Machhaino Coriaria napalensis
12 Allo Girardinia diversifolia
13 Punwale Ilex excels
14 Phusre ghans Indigofera pulchella
15 Gai tihare Inula cappa
16 Asuro Justicia adhatoda
17 Masino kanda Lantana camara
18 Ban kangiyo Luculia gratissima
19 Chiple ghans Oreocnide frutescens
20 Seto chulsi Osbeckia nepalensis
21 Rato chulesi Osbeckia stellata
22 Chuwa Phlogacanthus thyrsiflorus
23 Khareto Phyllanthus parvifolius
24 Ghangaru Pyracantha crenulata
25 Basanti kanda Randia tetrasperma
26 Majitho Rubia manjith
27 Ainselu Rubus ellipticus
28 Phitiphiya Sarcococca coriacea
29 Dursul Solanum erianthum
30 Simali Vitex negundo
31 Dhanyaro Woodfordia fruticosa
32 Timur Zanthoxylum armatum
Source: Field Observation and Consultation, 2017
Table 4-16: Recorded Climbers Species in the project area
S.N. Local Name Scientific Name
1 Mirke laharo Ceropegia pubescens
2 Batulo pate Cissampelos pareira
3 Bhyakur Dioscorea bulbifera
4 Bhyakur Dioscorea deltoidea
5 Bokri lahara Hedyotis scandens
6 Pani lahara Tetrastigma serrulatum
7 Singame lahara Thunbergia coccinea
8 Dudhe lahara Trachelospermum lucidum
9 Indreni Trichosanthes wallichiana
10 Cat claw Uncaria scandens
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
62| P a g e Department of Electricity Development
Source: Field Survey, 2017/18
Table 4-17: Recorded herbs species in the project area
S.N. Local Name Scientific Name
1 Apamarga Achyranthes aspera
2 Ganmane ghans Ageratum conyzoides
3 Rato charpate Anisomeles indica
4 Phurke Arundinella nepalensis
5 Kurkur Bidens pilosa
6 Beardgrass Bothriochola sp
7 Amala jhar Cassia mimosoides
8 Salimo Chrysopogon gryllus
9 Chandigava Coelogyne sp.
10 Batule silam Craniotome furcata
11 Orchids Dendrobium Sp.
12 Banmara Eupatorium adenophorum
13 Piringo Hedyotis corymbosa
14 Arthunge Heteropogon contortus
15 Siru Imperata cylindrica
16 Phulphar Justicia procumbens
17 Bhendi phul Lindenbergia grandiflora
18 Kodi Paspalum scrobiculatum
19 Amilo pire laharo Persicaria perfoliata
20 Rudilo Pogostemon glaber
21 Nilo butte ghans Scutellaria discolor
22 Melastomataceae Sonerila tenera
23 Nalu kuro Urena lobata
24 Jhurjhure Vernonia cinerea
Source: Field Survey, 2017/18
4.2.5 Vegetation Composition in the project area
Most of the vegetation around the project area is of mixed type and sporadic in nature. The
forest composition at different project locations is described below:
Vegetation at headworks (Weir, intake, gravel trap, desanding basin), QS2, SD1 and
Flushing Tunnel Portal Area
Vegetation at Headwork (Weir, intake, weir, gravel trap, desanding basin), CMS-1/2/3/4/5,
SD1, CR-1, MS &MWS-1, and Flushing Tunnel Portal Area:
In headwork areas, Uttis (Alnus nepalensis) is dominant tree species followed by Chilaune (S.
wallichii), Mauwa (E. spicata), Malata (Macaranga pustulata) and Jamun (Syzygium cumin).
Although the area lies in Chir Pine-Broad Leaved Forest, local humidity and other edaphic
factors favor other species such as Uttis (A. nepalensis), Okar (Juglans regia) and Gurans
(Rhododendron arboretum) are also there. Based on standing tree category, the forest in
headwork area seems good (Table 4-10 and Annex 8). The trees in left bank are very scanty
and are along with river banks as there is very steep slope in upwards area.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
63| P a g e Department of Electricity Development
Vegetation at Access Road, Adit Portal and SD2:
Access road from Damku to Power House passes through Basa CF and Rapcha CF. The area
is at narrow stream valley of Rechepu Khola. On its left bank, Basa CF lies while Rapcha CF
is at right bank. The area lies in the Basa CF. Khote salla (Pinus roxburghii) and Chilaune (S.
wallichii) are major tree species at the area. Large saw timber category trees are absent. On the
right bank, the trees are sparse and almost no trees in upward slope due to steepness of the area.
Uttis (A. nepalensis) and, Mauwa (E. spicata) are major tree species in the area. Around Adit
portal, the area lies in Lemchikharka CF. Mauwa (E. spicata) and Khote salla (P. roxburghii)
are dominant tree species. The forest seems good in terms of DBH category of trees as it holds
all types of tree category.
Surge Tank and Access Road to Surge Tank
The area lies in zone of Schima-Castanopsis Forest. The land belongs to individual persons as
well of Bijai CF. Mauwa (E. spicata) and Uttis (A. nepalensis) are dominating tress in the area.
Access Road from Surge Tank to PH, Portal Access to PH, Tailrace, CR-2, Labour Camp-
2, MS and MWS & CMS-2
All the areas lie in Bijai CF. Khote salla (P. roxburghii), Saj (Terminalia alata), Mauwa (E.
spicata) and Malata (Macaranga pustulata) are dominant tree species in the area. Mature trees
are scanty while poles are nearly 75% of total trees.
Table 4-18: Project Components and Major Tree Species
SN Project Component Forest Types Dominant Tree Species
1
Headwork (Weir, intake, gravel
trap, desanding basin), CMS-
1/2/3/4/5, SD1, CR-1, MS
&MWS-1, and Flushing Tunnel
Portal Area
Chir Pine-Broadleaved
Forest
Alnus nepalensis, Schima wallichii,
Engelhardia spicata, Macaranga
pustulata, Syzygium cumini
2 Access Road, Adit Portal and
SD2 Chir Pine-Broadleaved
Forest
Alnus nepalensis, Engelhardia
spicata, Pinus roxburghii, Schima
wallichii,
3 Surge Tank and Access Road to
Surge Tank Schima-Castanopsis
Forest Engelhardia spicata, Alnus nepalensis
4
Access Road from Surge Tank
to PH, Portal Access to PH,
Tailrace, CR-2, Labour Camp-
2, MS and MWS & CMS-2
Schima-Castanopsis
Forest
Pinus roxburghii, Terminalia alata,
Engelhardia spicata, Macaranga
pustulata
Note: PH- Powerhouse, CR-Crusher Plant, MS- Material Storage, MWS- Mechanical
Workshop, CMS- Construction Material Site
Source: Field Survey, 2017/18
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
64| P a g e Department of Electricity Development
Table 4-19: Tree Category along Different Project Structures
Project Component Tree Category (No./ha)
Total (No./ha) Pole
Small Saw
Timber Large Saw
Timber Headwork (Weir, intake, gravel trap, desanding basin),
CMS-1/2/3/4/5, SD1, CR-1, MS &MWS-1, and Flushing
Tunnel Portal Area 142 54 48 244
Access Road, Adit Portal and SD2 150 75 17 242 Surge Tank and Access Road to Surge Tank 135 25 10 170 Access Road from Surge Tank to PH, Portal Access to
PH, Tailrace, CR-2, Labour Camp-2, MS and MWS &
CMS-2 125 42 4 171
4.2.6 Tree Basal Area, Volume and Biomass
In an average the tree basal area is only 23.04 m2/ha in the project area. Similarly, tree volume
and biomass were found to be 460.91 m3/ha and 562658.31kg/ha respectively. Similarly,
timber volume and fuelwood volume were 162.13 m3/ha and 867.76 m3/ha respectively. In
terms of Basal Area (BA), volume and biomass, forest in headwork seems good (Table 4-20,
Annex 8).
Table 4-20: Tree Basal Area, Volume and Biomass in Project Area
SN Project Component
Number of
Standing Trees
(no./ha)
Basal
Area
(m2/ha)
Standing
Tree
Volume
(m3/ha)
Timber
Volume
(m3/ha)
Fuelwood
Volume
(m3/ha)
Total
Biomass
(Kg/ha) Pole Trees
1
Headwork (Weir,
intake, gravel trap,
desanding basin),
CMS-1/2/3/4/5,
SD1, CR-1, MS
&MWS-1, and
Flushing Tunnel
Portal Area
142 102 54.40 1037.51 462.12 1553.57 1239843.62
2 Access Road, Adit
Portal and SD2 150.00 92.00 10.78 400.42 141.91 490.13 426764.73
3 Surge Tank and
Access Road to
Surge Tank 135.00 35.00 19.76 191.12 18.21 446.53 303243.01
4
Access Road from
Surge Tank to PH,
Portal Access to
PH, Tailrace, CR-
2, Labour Camp-2,
MS and MWS &
CMS-2
125.00 46.00 7.21 214.60 26.30 980.82 280781.89
Note: PH- Powerhouse, CR-Crusher Plant, MS- Material Storage, MWS- Mechanical
Workshop, CMS- Construction Material Site, SD- Spoil Deposit
Source: Field Survey, 2017/2018
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
65| P a g e Department of Electricity Development
Table 4-21: Tree Volume and Biomass Distribution with Project Structures
S.N. Scientific Name
Number of Standing
Trees (No./ha) Basal
Area
(m2/ha)
Standing
Volume
(m3/ha)
Timber
Volume
(m3/ha)
Fuelwood
Volume
(m3/ha)
Biomass (Kg/ha)
Stem Branch Foliage Total Poles Trees Total
A. Headworks (Weir, intake, gravel trap, desanding basin), CMS2, SD1 and Flushing Tunnel Portal
1 Alnus nepalensis 42 46 88 10.81 197.47 120.74 338.17 77014.78 107014.40 5754.30 189783.49
2 Boehmeria rugulosa 4 4 0.05 0.32 0.00 0.24 189.60 141.82 40.01 371.43
3 Bridelia retusa 2 2 0.02 0.10 0.00 0.08 85.62 64.05 18.07 167.73
4 Cassine glauca 4 4 0.05 0.25 0.00 0.19 149.49 111.82 31.54 292.86
5 Chekrasi 2 2 0.71 16.34 10.89 24.45 9706.20 11288.31 1766.53 22761.04
6 Cinnamomum tamala 8 8 0.17 2.59 0.00 1.94 1539.10 1151.25 324.75 3015.10
7 Elaeagnus parvifolia 2 2 0.02 0.10 0.00 0.08 60.77 45.46 12.82 119.05
8 Engelhardia spicata 8 17 25 18.61 365.65 0.00 978.04 217198.78 364291.75 44042.21 625532.74
9 Eurya cerasifolia 6 6 0.05 0.35 0.00 0.26 209.73 156.88 44.25 410.86
10 Homalium napaulense 2 2 0.02 0.10 0.00 0.08 61.28 45.83 12.93 120.04
11 Juglans regia 6 6 2.41 33.18 22.12 48.16 19710.17 22037.25 3597.26 45344.68
12 Lyonia ovalifolia 2 2 0.02 0.13 0.00 0.12 79.66 71.45 40.31 191.42
13 Macaranga pustulata 17 8 25 1.32 21.03 9.39 26.57 12489.98 11652.29 2373.35 26515.61
14 Maesa chisia 2 2 0.09 0.81 0.00 0.61 482.21 360.69 101.75 944.65
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
66| P a g e Department of Electricity Development
S.N. Scientific Name
Number of Standing
Trees (No./ha) Basal
Area
(m2/ha)
Standing
Volume
(m3/ha)
Timber
Volume
(m3/ha)
Fuelwood
Volume
(m3/ha)
Biomass (Kg/ha)
Stem Branch Foliage Total Poles Trees Total
15 Malami Kath 4 4 4.06 89.83 59.89 134.42 53360.19 62057.90 9711.55 125129.64
16 Rhododendron arboreum 4 4 0.10 0.68 0.00 0.37 434.33 236.27 120.31 790.91
17 Rhus sp. 2 2 0.02 0.12 0.00 0.09 70.90 53.03 14.96 138.89
18 Schima wallichii 13 19 32 16.19 432.57 286.38 217.54 298038.25 50720.85 9894.91 358654.01
19 Syzygium cumini 2 8 10 2.01 34.86 21.96 19.33 26838.60 4991.98 939.35 32769.93
20 Trichilia connaroides 4 4 0.03 0.20 0.00 0.15 175.97 131.62 37.13 344.72
21 Wendlandia puberula 8 8 0.09 0.50 0.00 0.37 297.06 222.20 62.68 581.95
Sub-total 126 116 242 56.84 1197.20 531.38 1791.24 718192.68 636847.11 78940.97 1433980.76
B. CMS1
1 Castanopsis tribuloides 50 50 0.68 2.41 1.81 1447.88 1083.01 305.50 2836.39
2 Elaeagnus parvifolia 25 25 0.87 3.03 2.27 1800.93 1347.10 380.00 3528.03
3 Engelhardia spicata 75 75 1.76 10.37 9.59 6160.63 5698.58 1946.76 13805.97
4 Pinus roxburghii 25 25 0.50 2.77 0.52 1797.71 339.77 181.57 2319.05
5 Schima wallichii 50 50 1.28 7.59 3.94 5226.80 2717.94 334.52 8279.26
6 Wendlandia puberula 25 25 0.24 0.71 0.53 423.54 316.81 89.37 829.72
Sub-total 250 0 250 5.32 26.88 0.00 18.67 16857.50 11503.21 3237.71 31598.41
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
67| P a g e Department of Electricity Development
S.N. Scientific Name
Number of Standing
Trees (No./ha) Basal
Area
(m2/ha)
Standing
Volume
(m3/ha)
Timber
Volume
(m3/ha)
Fuelwood
Volume
(m3/ha)
Biomass (Kg/ha)
Stem Branch Foliage Total Poles Trees Total
C. SD2
1 Alnus nepalensis 75 8 83 3.60 553.75 25.93 662.47 215962.98 253308.76 21388.43 490660.18
2 Engelhardia spicata 58 8 66 3.26 106.99 0.00 228.18 63550.93 91929.62 14332.72 169813.27
3 Ghoge 8 8 1.45 60.27 0.00 119.69 35797.63 35296.47 6586.76 77680.87
4 Macaranga pustulata 8 8 1.16 67.38 44.92 88.89 40020.75 39460.46 7363.82 86845.03
5 Quercus glauca 8 8 0.13 3.21 0.00 2.40 2983.75 2231.85 629.57 5845.17
6 Rhodingo 8 8 16 1.83 89.25 35.29 105.65 53017.45 52275.20 9755.21 115047.86
7 Rhus javanica 8 8 0.38 14.93 0.00 11.17 8867.57 6632.94 1871.06 17371.57
8 Sapium insigne 8 8 1.16 52.94 0.00 105.13 31444.88 31004.65 5785.86 68235.38
9 Sterculia villosa 8 8 0.13 2.67 0.00 2.00 1588.13 1187.92 335.09 3111.14
10 Syzygium cumini 8 8 16 0.99 42.61 0.00 39.19 32812.85 30175.62 6284.63 69273.10
Sub-total 173 56 229 14.07 994.00 106.14 1364.78 486046.91 543503.48 74333.15 1103883.55
D. SD3
1 Engelhardia spicata 25 25 2.55 3.82 0.00 3.77 2268.23 2236.48 417.35 4922.06
2 Pinus roxburghii 100 100 200 9.82 69.62 31.47 32.06 45250.56 10608.29 2882.60 58741.45
3 Schima wallichii 50 50 0.95 4.85 0.00 2.52 3339.50 1736.54 213.73 5289.76
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
68| P a g e Department of Electricity Development
S.N. Scientific Name
Number of Standing
Trees (No./ha) Basal
Area
(m2/ha)
Standing
Volume
(m3/ha)
Timber
Volume
(m3/ha)
Fuelwood
Volume
(m3/ha)
Biomass (Kg/ha)
Stem Branch Foliage Total Poles Trees Total
Sub-total 150 125 275 13.31 78.28 31.47 38.34 50858.29 14581.31 3513.68 68953.28
E. Construction Adit Portal (Right Bank of Mahuri Khola)
1 Engelhardia spicata 62 25 87 3.40 251.39 0.00 441.53 149323.05 178669.91 39578.47 367571.43
2 Pinus roxburghii 37 13 50 3.42 409.54 234.17 233.47 266197.85 75654.16 11360.68 353212.70
3 Sapium insigne 12 13 25 0.78 45.95 0.00 93.09 27295.49 30646.09 5044.55 62986.13
4 Schima walichii 25 25 1.43 117.17 61.51 77.45 80729.88 15015.76 2825.55 98571.19
5 Syzygium cumini 25 25 0.36 14.48 0.00 10.83 11149.96 8340.17 2352.64 21842.77
6 Wendlandia puberula 13 13 0.12 3.71 0.00 2.78 2205.95 1650.05 465.46 4321.46
Sub-total 174 51 225 9.51 842.24 295.68 859.15 536902.19 309976.15 61627.34 908505.69
F. Surge Tank and Access Road to Surge Tank
1 Alnus nepalensis 45 45 0.96 4.90 0.00 3.94 1912.41 1535.67 323.20 3771.28
2 Casearia graveolens 5 5 0.05 0.18 0.00 0.13 105.11 78.62 22.18 205.92
3 Engelhardia spicata 50 10 60 14.91 154.78 0.00 405.54 91939.10 152214.63 18962.58 263116.30
4 Malami/Anau Kath 5 5 0.04 0.05 0.00 0.04 30.24 22.62 6.38 59.24
5 Pinus roxburghii 10 10 1.32 14.28 1.90 8.42 9284.48 2376.83 427.09 12088.40
6 Quercus lanata 5 5 0.08 0.32 0.00 0.24 283.50 211.77 64.92 560.20
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
69| P a g e Department of Electricity Development
S.N. Scientific Name
Number of Standing
Trees (No./ha) Basal
Area
(m2/ha)
Standing
Volume
(m3/ha)
Timber
Volume
(m3/ha)
Fuelwood
Volume
(m3/ha)
Biomass (Kg/ha)
Stem Branch Foliage Total Poles Trees Total
7 Schima walichii 10 5 15 0.67 5.43 0.61 2.82 3741.98 893.72 148.14 4783.83
8 Terminalia alata 10 5 15 1.40 9.49 1.13 9.28 9015.55 6138.19 410.31 15564.05
9 Trichilia connaroides 5 5 10 0.32 1.68 0.00 3.08 1443.03 1380.45 270.33 3093.80
Sub-total 135 35 170 19.76 191.12 3.64 433.48 117755.40 164852.50 20635.12 303243.01
G. Access Road from Surge Tank to PH, Portal Access to PH, Tailrace, CMS3
1 Bauhinia variegata 4 4 8 0.30 3.45 0.00 15.72 2415.80 2304.03 453.35 5173.18
2 Bridelia retusa 4 4 0.14 1.50 0.00 1.12 1248.24 933.69 263.38 2445.31
3 Casearia graveolens 4 4 0.17 2.71 0.00 2.02 1607.37 1202.31 339.15 3148.84
4 Cassine glauca 4 4 0.08 0.79 0.00 0.59 466.71 349.10 98.48 914.29
5 Engelhardia spicata 17 4 21 0.72 18.37 0.00 91.66 10914.51 14720.12 2581.35 28215.98
6 Ficus benghalensis 4 4 0.03 0.24 0.00 0.18 141.80 106.06 29.92 277.78
7 Ficus religiosa 4 4 0.07 1.23 0.00 0.92 729.24 545.47 153.87 1428.58
8 Homalium napaulense 4 4 0.06 1.14 0.00 0.85 674.95 504.86 142.42 1322.23
9 Lyonia ovalifolia 4 4 0.06 0.94 0.00 0.70 555.84 415.77 117.28 1088.90
10 Macaranga pustulata 8 9 17 0.63 10.57 3.38 31.47 6279.58 5905.48 1187.91 13372.97
11 Mallotus tetracoccus 13 13 0.20 3.65 0.00 2.73 2170.30 1623.39 457.93 4251.62
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
70| P a g e Department of Electricity Development
S.N. Scientific Name
Number of Standing
Trees (No./ha) Basal
Area
(m2/ha)
Standing
Volume
(m3/ha)
Timber
Volume
(m3/ha)
Fuelwood
Volume
(m3/ha)
Biomass (Kg/ha)
Stem Branch Foliage Total Poles Trees Total
12 Olea glandulifera 4 4 0.28 6.02 0.00 31.03 3577.54 3527.45 658.27 7763.25
13 Pinus roxburghii 21 13 34 1.02 30.75 15.26 39.13 19988.79 4774.65 1200.62 25964.07
14 Rhus wallichii 4 4 0.03 0.44 0.00 0.27 263.34 158.27 37.66 459.26
15 Sapium insigne 8 8 2.25 105.20 0.00 559.71 62491.10 72086.84 11380.05 145957.99
16 Schima wallichii 4 4 0.42 11.49 7.66 18.10 7917.35 1472.63 277.11 9667.08
17 Terminalia alata 25 25 0.66 15.18 0.00 11.36 14424.47 10789.51 3043.56 28257.54
18 Trichilia connaroides 4 4 0.06 0.92 0.00 0.69 547.74 409.71 115.57 1073.02
Sub-total 124 46 170 7.21 214.60 26.30 808.25 136414.67 121829.34 22537.88 280781.89
Total 161.71 61.29 223.00 18.00 506.33 142.09 759.13 294718.23 257584.73 37832.26 590135.23
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
71| P a g e Department of Electricity Development
4.2.7 Shrub Stratum
Various shrubs found in various proposed project structure sites are given below in table 4-22.
Table 4-22: Tree Volume and Biomass Distribution along with Project Structures
SN Scientific Name Density (No/ha) RD (%) RF (%) RC (%) IVI
A. Headwork (Weir, intake, gravel trap, desanding basin), CMS-1/2/3/4/5, SD1, CR-1, MS
&MWS-1, and Flushing Tunnel Portal Area 1 Acacia Sp. 61.54 0.51 1.20 0.66 2.38 2 Aeschynanthus parviflorus 61.54 0.51 1.20 0.66 2.38 3 Alnus nepalensis 153.85 1.27 2.41 2.65 6.33 4 Berberis sp. 153.85 1.27 2.41 1.32 5.01 5 Boehmeria platyphylla 1323.08 10.94 6.02 6.62 23.59 6 Bridelia retusa 92.31 0.76 2.41 1.32 4.50 7 Casearia graveolens 61.54 0.51 1.20 0.66 2.38 8 Callicarpa arborea 30.77 0.25 1.20 0.66 2.12 9 Capparis spinosa 92.31 0.76 1.20 0.66 2.63
10 Caryopteris odorata 123.08 1.02 1.20 0.66 2.88 11 Castanopsis tribuloides 338.46 2.80 2.41 2.65 7.86 12 Cyphostemma auriculatum 215.38 1.78 2.41 1.32 5.52 13 Engelhardia spicata 92.31 0.76 2.41 1.99 5.16 14 Eurya cerasifolia 246.15 2.04 3.61 3.97 9.62 15 Flacortia sp. 1969.23 16.28 4.82 15.23 36.34 16 Homalium napaulense 523.08 4.33 4.82 4.64 13.78 17 Inula cappa 461.54 3.82 3.61 1.99 9.42 18 Lyonia ovalifolia 153.85 1.27 3.61 2.65 7.54 19 Maesa chisia 461.54 3.82 4.82 5.30 13.93 20 Osbeckia nepalensis 123.08 1.02 1.20 0.66 2.88 21 Osbeckia stellata 369.23 3.05 3.61 2.65 9.32 22 Phoebe lanceolata 123.08 1.02 2.41 1.99 5.41 23 Phyllanthus parvifolius 584.62 4.83 6.02 3.31 14.17 24 Pilea scripta 2276.92 18.83 4.82 15.89 39.54 25 Quercus glauca 30.77 0.25 1.20 0.66 2.12 26 Rhododendron arboreum 61.54 0.51 2.41 1.32 4.24 27 Rhus javanica 30.77 0.25 1.20 0.66 2.12 28 Rhus wallichii 61.54 0.51 1.20 0.66 2.38 29 Ribes himalense 307.69 2.54 2.41 1.99 6.94 30 Rubus sp. 184.62 1.53 3.61 1.99 7.13 31 Saurauia napaulensis 61.54 0.51 1.20 0.66 2.38 32 Schefflera venulosa 61.54 0.51 1.20 1.32 3.04 33 Schima wallichii 276.92 2.29 4.82 3.31 10.42 34 Smilax sp. 276.92 2.29 3.61 1.99 7.89 35 Solanum surattense 338.46 2.80 1.20 1.32 5.33 36 Syzygium cumini 30.77 0.25 1.20 0.66 2.12 37 Trichilia connaroides 30.77 0.25 1.20 0.66 2.12 38 Wendlandia coriacea 246.15 2.04 2.41 2.65 7.09 Subtotal 12092.31
B. SD-2, Construction Adit portal/Access Road 1 Maesa macrophylla 533.33 5.41 8.70 10.71 24.82 2 Desmodium sp. 666.67 6.76 8.70 7.14 22.60 3 Grewia tiliaefolia 266.67 2.70 8.70 7.14 18.54 4 Homalium napaulense 133.33 1.35 4.35 3.57 9.27 5 Inula cappa 3066.67 31.08 13.04 14.29 58.41 6 Lyonia ovalifolia 266.67 2.70 4.35 3.57 10.62
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
72| P a g e Department of Electricity Development
SN Scientific Name Density (No/ha) RD (%) RF (%) RC (%) IVI 7 Phyllanthus parvifolius 2000.00 20.27 13.04 14.29 47.60 8 Quercus lanata 400.00 4.05 4.35 7.14 15.54 9 Rubus sp. 400.00 4.05 8.70 7.14 19.89
10 Smilax sp. 666.67 6.76 8.70 7.14 22.60 11 Tinospora sp. 400.00 4.05 8.70 7.14 19.89 12 Wendlandia coriacea 266.67 2.70 4.35 3.57 10.62 13 Woodfordia fruticosa 800.00 8.11 4.35 7.14 19.60 Subtotal 9866.67
C. Access Road/Surge Tank/SD3/Labour Camp 1 Boehmeria rugulosa 400.00 4.63 4.17 3.03 11.83 2 Caryopteris odorata 400.00 4.63 4.17 3.03 11.83 3 Casearia graveolens 160.00 1.85 4.17 3.03 9.05 4 Colebrookea oppositifolia 880.00 10.19 12.50 9.09 31.78 5 Desmodium sp. 640.00 7.41 8.33 6.06 21.80 6 Flacortia sp. 640.00 7.41 8.33 9.09 24.83 7 Inula cappa 1200.00 13.89 12.50 9.09 35.48 8 Lyonia ovalifolia 80.00 0.93 4.17 3.03 8.12 9 Maesa macrophylla 1120.00 12.96 12.50 27.27 52.74
10 Osbeckia stellata 400.00 4.63 4.17 3.03 11.83 11 Phyllanthus parvifolius 640.00 7.41 4.17 3.03 14.60 12 Swida oblonga 160.00 1.85 4.17 3.03 9.05 13 Wendlandia coriacea 80.00 0.93 4.17 3.03 8.12 14 Luculia gratissima 160.00 1.85 4.17 3.03 9.05 15 Woodfordia fruticosa 1680.00 19.44 8.33 12.12 39.90 16 Subtotal 8640
D. Access Road from Surge Tank to PH, Access Tunnel to Powerhouse and Switchyard ,
Tailrace, CR-2, MS & MWS-2 1 Caryopteris odorata 466.67 10.45 6.67 5.88 23.00 2 Casearia graveolens 333.33 7.46 6.67 5.88 20.01 3 Colebrookea oppositifolia 1200.00 26.87 13.33 41.18 81.38 4 Engelhardia spicata 200.00 4.48 6.67 2.35 13.50 5 Flacortia sp. 200.00 4.48 6.67 5.88 17.03 6 Flemingia macrophylla 333.33 7.46 6.67 5.88 20.01 7 Inula cappa 533.33 11.94 13.33 10.59 35.86 8 Maesa macrophylla 133.33 2.99 6.67 2.35 12.00 9 Phyllanthus parvifolius 400.00 8.96 6.67 5.88 21.50
10 Sida sp. 466.67 10.45 20.00 8.24 38.68 11 Terminalia alata 200.00 4.48 6.67 5.88 17.03 12 Subtotal 4466.67 Total 8766.41
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
73| P a g e Department of Electricity Development
4.2.8 Herb stratum
Various herbs found in various proposed project structure sites are given below in table 4.22.
Table 4-23: Importance Value Index of plant species in Herb Strata
SN Scientific Name Density (No/ha) RD (%) RF(%) RC (%) IVI
A. Headwork (Weir, intake, gravel trap, desanding basin), CMS-1/2/3/4/5, SD1, CR-1, MS
&MWS-1, and Flushing Tunnel Portal Area 1 Acer sp. 1538.46 0.32 1.54 0.48 2.34 2 Adiantum sp. 3076.92 0.64 1.54 0.48 2.66 3 Ageratina adenophora 49230.77 10.19 9.23 10.58 30.00 4 Ageratum conyzoides 12307.69 2.55 1.54 5.77 9.86 5 Asparagus racemosus 3846.15 0.80 3.08 0.96 4.83 6 Bidens pilosa 4615.38 0.96 1.54 0.48 2.97 7 Boehmeria sp. 20000.00 4.14 4.62 7.21 15.97 8 Capillipedium assimile 16923.08 3.50 1.54 1.92 6.96 9 Chirita urticifolia 121538.46 25.16 9.23 16.83 51.22 10 Chrysopogon gryllus 23076.92 4.78 1.54 3.85 10.16 11 Compositae 1 4615.38 0.96 1.54 0.48 2.97 12 Coniogramme japonica 3076.92 0.64 1.54 0.48 2.66 13 Coniogramme pubescens 2307.69 0.48 1.54 0.48 2.50 14 Coniogramme serrulata 3076.92 0.64 1.54 1.44 3.62 15 Cyperus sp. 15384.62 3.18 4.62 1.92 9.72 16 Cyphostemma auriculatum 769.23 0.16 1.54 0.48 2.18 17 Diplazium dilatatum 15384.62 3.18 1.54 2.40 7.13 18 Dryopteris sp (1) 1538.46 0.32 1.54 0.48 2.34 19 Girardinia diversifolia 12307.69 2.55 6.15 2.40 11.11 20 Globba clarkei 769.23 0.16 1.54 0.48 2.18 21 Imperata cylindrica 11538.46 2.39 1.54 0.96 4.89 22 Ipomia sp. 769.23 0.16 1.54 0.48 2.18 23 Lindenbergia grandiflora 2307.69 0.48 1.54 1.92 3.94 24 Lindsaea ensifolia 3076.92 0.64 1.54 0.48 2.66 25 Nephrolepis cordifolia 46153.85 9.55 6.15 8.65 24.36 26 Oplismenus burmannii 1538.46 0.32 1.54 0.48 2.34 27 Piper chaba 34615.38 7.17 9.23 8.65 25.05 28 Pogostemon glaber 4615.38 0.96 1.54 0.96 3.46 29 Pteris arisanensis 12307.69 2.55 3.08 3.85 9.47 30 Pteris normalis 21538.46 4.46 3.08 3.85 11.38 31 Pteris sp. 2307.69 0.48 1.54 0.48 2.50 32 Rubus sp. 769.23 0.16 1.54 0.48 2.18 33 Solanum virginianum 1538.46 0.32 1.54 0.48 2.34 34 Urtica sp. 24615.38 5.10 6.15 8.65 19.90 Subtotal 483076.92
B. SD-2, Construction Adit portal/Access Road 1 Ageratina adenophora 283333.33 23.42 11.76 31.25 66.43 2 Asparagus racemosus 6666.67 0.55 5.88 1.56 8.00 3 Asplenium sp. 46666.67 3.86 5.88 6.25 15.99 4 Capillipedium assimile 386666.67 31.96 17.65 17.19 66.79 5 Cheilanthes argentea 16666.67 1.38 5.88 1.56 8.82 6 Chrysopogon gryllus 300000.00 24.79 11.76 18.75 55.31 7 Cyperus sp. 46666.67 3.86 11.76 3.13 18.75 8 Cystopteris sp. 10000.00 0.83 5.88 1.56 8.27 9 Lepidagathis sp. 10000.00 0.83 5.88 1.56 8.27 10 Nephrolepis cordifolia 83333.33 6.89 11.76 10.94 29.59
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
74| P a g e Department of Electricity Development
SN Scientific Name Density (No/ha) RD (%) RF(%) RC (%) IVI 11 Pteris normalis 20000.00 1.65 5.88 6.25 13.79 Subtotal 1210000.00
C. Access Road/Surge Tank/SD3/Labour Camp 1 Ageratina adenophora 222000.00 28.98 22.22 38.10 89.30 2 Artemisia indica 20000.00 2.61 5.56 5.95 14.12 3 Bidens pilosa 8000.00 1.04 5.56 1.19 7.79 4 Capillipedium assimile 150000.00 19.58 11.11 8.33 39.03 5 Cheilanthes argentea 10000.00 1.31 5.56 1.19 8.05 6 Chromolaena odorata 6000.00 0.78 5.56 1.19 7.53 7 Chrysopogon gryllus 200000.00 26.11 11.11 17.86 55.08 8 Indigofera sp. 2000.00 0.26 5.56 1.19 7.01 9 Nephrolepis cordifolia 104000.00 13.58 11.11 15.48 40.16 10 Pteris normalis 32000.00 4.18 11.11 5.95 21.24 11 Urtica sp. 12000.00 1.57 5.56 3.57 10.69 Subtotal 766000.00
D. Access Road from Surge Tank to PH, Access Tunnel to Powerhouse and Switchyard ,
Tailrace, CR-2, MS & MWS-2 1 Ageratina adenophora 223333.33 35.08 21.05 40.48 96.61 2 Asparagus racemosus 1666.67 0.26 5.26 1.19 6.72 3 Capillipedium assimile 83333.33 13.09 10.53 7.14 30.76 4 Chrysopogon gryllus 83333.33 13.09 5.26 9.52 27.88 5 Cystopteris sp. 5000.00 0.79 5.26 1.19 7.24 6 Lepidagathis sp. 33333.33 5.24 5.26 3.57 14.07 7 Nephrolepis cordifolia 145000.00 22.77 15.79 17.86 56.42 8 Pteris normalis 26666.67 4.19 21.05 7.14 32.38 9 Urtica sp. 35000.00 5.50 10.53 11.90 27.93 Subtotal 636666.67 Average 773935.90
Source: Field Survey, 2017/18
4.2.9 Regeneration Status
Regeneration of tree species in various proposed project structure sites are given below in table
4-24. Regeneration of tree species has been given in Annex 8.
Table 4-24: Regeneration Status of Trees
SN Project Structure Regeneration Category
(No./ha)
Seedling Sapling Total
1 Headwork (Weir, intake, gravel trap, desanding basin), CMS-
1/2/3/4/5, SD1, CR-1, MS &MWS-1, and Flushing Tunnel
Portal Area 5077 73 5150
2 SD-2, Construction Adit portal/Access Road 1333 108 1441 3 Access Road/Surge Tank/SD3/Labour Camp 1680 95 1775
4 Access Road from Surge Tank to PH, Access Tunnel to
Powerhouse and Switchyard, Tailrace, CR-2, MS & MWS-2 600 24 624
Total 8690 300 8990
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
75| P a g e Department of Electricity Development
4.2.10 Forest Land Ownership
Forest area covered by project components is 15.1051 ha. All the forest area is community
forest (Table 4-25). Nearly 50% of total forest area is of Rapcha CF followed by Lemchikharka
(20%) and Bijai CF (10%). Forest area as per project component has been given Annex 8.
Table 4-25: Land Ownership of Forest Land
Forest Ownership Project Components Forest Area Covered by
Project Structures m2 ha
Basa CF Access Road 8326.26 0.8326
Bhirkuna CF Borrow and Quarry Site: CMS#1 &
CMS#2 2070.00 0.2070
Bijai CF
Surge tank, Adit-4 Portal (Valve
chamber Access Portal), Adit-5 Portal
(Powerhouse Access Tunnel), Tailrace
Outlet Portal, Access Road, CR, MS and
MWS-2, Camp Site 2 (Labor)
15446.52 1.5447
Lemchikharka CF Adit-3 Portal (Construction Adit), Spoil
Dispossal Sites: SD#2 29675.65 2.9676
Rapcha CF
Intake, Adit-1 Portal (Access tunnel to
desander), Adit-2 Portal (Desander
Flushing), Access Road, Spoil Disposal
Site: SD#1, Borrow and Quarry Site:
CMS#4, Borrow and Quarry Site:
CMS#5, Crusher, Mechanical Workshop
and Material:CR, MS and MWS-1
Storage, Camp Site 1 (Labor)
74264.31 7.4264
Lemchikharka/Bijai
CFs Access Road and Disposal Sites: SD#3 7063.65 0.7064
Rapcha/Bhirkuna/Dhu
dhkoshi CFs Pondage area 14204.32 1.4204
Total 151050.71 15.1051
4.2.11 Ethno-botanical information
Surrounding forests are a major source of fodder, fuel wood, timber, bedding material for
livestock for the local people. A few tree species such as Saj (T. tomentosa), Khote salla (P.
roxburghii) and Chilaune (S. wallichii) are used for timber. However, Amala, Gayo (B. retusa),
Katus (C. indica) and Banjh (Q. lanata) are mainly used as fodder plants. Kaphal (M.
esculanta), and Ainselu (R. ellipticus) are edible and consumed by local people. Stems of Daar
(Boehmeria rugulosa) are used for making wooden vessels known as “theki", while brooms
are made from the inflorescences of Amliso (Thysanolaena maxima). Tuberous roots of Tarool
(Dioscoreaspp.) are used as a vegetable.
According to local informants, residents prefer to receive treatment from modern (allopathic)
medicine as opposed to traditional herbal (ayurvedic) medicine. This is mainly due to the
facilities available at nearby health post. However, some people in the project area still use
traditional treatments using plant parts from surrounding forests provided by local healers
(Dhami, Jhakri).
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
76| P a g e Department of Electricity Development
Table 4-26: Ethno-botanical Uses Practiced in the Proposed Project Area
S.N. Scientific Name Vernacular name Habit Uses
1 Bauhinia purpurea Tanki Tree Fodder, Fuelwood, Vegetables
2 Castanopsis indica Katus Tree Edible fruit, Fodder, Fuelwood
3 Castanopsis tribuloides Musure Katus Tree Edible fruit, Fodder, Fuelwood
4 Cinnamomum tamala Tejpat Tree Medicine, Spice
5 Ficus religiosa Peepal Tree Religious use, Fodder
6 Ficus semicordata Khaneu Tree Edible fruit and fodder
7 Myrica esculenta Kafal Tree Edible fruit and fodder
8 Phyllanthus emblica Amala Tree Edible fruit, Medicine
9 Rhododendron
arboreum Laligurans Tree Medicine
10 Rhus javanica Bhakimlo Tree Medicine, Edible Fruit
11 Ficus bengalensis Bar Tree Religious use, Fodder
12 Pinus roxburghii Sallo Tree Timber, Fuelwood
13 Terminalia alata Saaj Tree Timber, Fuelwood
14 Alnus nepalensis Uttis Tree Timber, Fuelwood
15 Duabanga grandiflora Lampate Tree Timber, Fuelwood
16 Maesa chisia Bilaaune Tree Fodder, Fuelwood
17 Bridelia retusa Gaayo Tree Fodder, Fuelwood
18 Bauhinia variegata Koiralo Tree Medicine, Vegetable
19 Syzygium cumini Jaamun Tree Medicine, Timber, Fuelwood
20 Psidium guajava Amba Tree Edible Fruit, Medicine
21 Juglans regia Okhar Tree Medicine
22 Ficus lacor Kabro Tree Vegetable, Fodder
23 Engelhardia spicata Mauwa Tree Fuelwood
24 Trichilia connaroides Aankha Taruwa Tree Medicine
25 Berberis sp. Chutro Shrub Medicine, Edible Fruit
26 Colebrookea
oppositifolia Dhusure Shrub Medicine
27 Dichroa febrifuga Vasak Shrub Medicine
28 Inula cappa Gaitihare Shrub Medicine
29 Jatropha curcas Sajiwan Shrub Medicine
30 Justicia adhatoda Asuro Shrub Medicine, Green Manure
31 Rubus sp. Aiselu Shrub Edible fruits
32 Woodfordia fruticosa Dhairo Shrub Medicine, Fodder
33 Zanthoxylum armatum Timur Shrub Medicine, Spice
34 Achyranthes aspera Apamarga Herb Medicine
35 Ageratina adenophora Banmara Herb Medicine
36 Artemisia indica Titepati Herb Medicine
37 Asparagus racemosus Kurilo Herb Medicine
38 Bambusasp. Bans Herb Food, Fodder, Construction
Materials
39 Centella asiatica Ghortaapre Herb Medicine
40 Cynodon dactylon Dubo Herb Religious, Medicine
41 Eulaliopsis binata Babiyo Herb Household use (rope making)
42 Girardinia diversifolia Lekali Sisnu Herb Medicine, Vegetable
43 Osbeckia nepalensis. Angeri Herb Medicine
44 Urtica dioica Sisnu Herb Medicine, Vegetable
45 Diplazium sp. Niguro Fern Vegetable
46 Dryopteris cochelata Niguro Fern Vegetable
47 Dioscorea bulbifera Ban tarul Climber Medicine, Vegetable
48 Dioscorea deltoidea Tarul Climber Vegetable
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
77| P a g e Department of Electricity Development
S.N. Scientific Name Vernacular name Habit Uses
49 Rubia manjith Majitho Climber Medicine
50 Smilax sp. Kukurdaino Climber Medicine
51 Piper chaba Chabo Climber Medicine
4.2.12 Protected Plant Species
Among various plants found in project area, seven are protected by GoN and other international
conventions. A prime habitat of tree fern was found in head work area (near flushing tunnel)
where 30 tree ferns were noted in the area of 1200 m2. Similarly, another habitat outside project
activity area was also in upstream of same stream, where 16 such tree ferns were noted.
Table 4-27: Protected Plants in the Proposed Project Area
S.N. Scientific Name Nepali Name
CITES
Appen
dix
IUCN
Red List
GoN Remarks
1 Ceropegia pubescens Mirke laharo II - - Outside Sampling Sites
2 Dioscorea deltoidea Bhyakur II Threatened - Outside Sampling Sites
3 Juglan regia Protected In sampling plots
4 Orchids Sunakhari II Endangered - Outside Sampling Sites
5 Lichens Jhyau Protected Outside Sampling Sites
6 Cyathea spinulosa Rukh Unyu II Endangered Outside Sampling Sites
Figure 4-13: Tree Fern Habitat in Project Area
4.2.13 Wildlife
It has been reported that the community forests around the project area provide habitat for some
wild mammals such as Ghoral, Hare, Barking Deer, Jackal, Common Leopard, Monkey,
Porcupine, Dhedu and Lokharke.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
78| P a g e Department of Electricity Development
Table 4-28: Reported Mammals in the Proposed Project Area
S.N. Common Names Scientific Names Status of occurrence
Common Sparse Rare
1 Indian Hare Lepus nigricollis √
2 Five-striped Palm Squirrel Funambulus pennantii √
3 House Rat Rattus rattus √
4 Brown Rat Rattus norvegicus √
5 Indian Porcupine Hystrix indica √
6 Small Indian Mongoose Herpestes auropunctatus √
7 Bengal Fox Vulpes bengalensis √
8 Golden Jackal Canis aureus √
9 Asian House Shrew Suncus murinus √
10 Tarai Grey Langur Semnopithecus hector √
11 Rhesus Macaque Macaca mulatta √
12 Barking Deer Muntiacus muntjak √
13 Common Goral Naemorhedus goral √
14 Common Leopard Panthera paradus √
15 Yellow-Throated Marten Martes flavigula √
16 Bat Scotophilus heathi √ Source: Field Survey, 2017/18
4.2.14 Birds
Different types of birds are found in the project area. The forest, mountain and riverine
ecosystems of the project area favor a variety of avifauna species like Kalij (Lophura spp.),
Dhukur (Streptopelia sp.), Crow (Corvus splendens), Jureli (Pyconotus cafer), Parewa
(Columba livia), Cuckoos (Cuculus spp.), jungle crow (Corvus macrorhychos), and kalij
pheasant (Lophura leucomelanos) have been reported prominent bird species from the project
area. Other species recorded in the project area is given in table 4.28.
Table 4-29: Reported Birds in the Proposed Project Area
S.N. Order/Family/Common Name Scientific Name
1 Northern Goshawk Accipiter gentilis
2 Besra Accipiter virgatus
3 Jungle Myna Acridotheres fuscus
4 Bank Myna Acridotheres ginginianus
5 Common Myna Acridotheres tristis
6 Red-throated Pipit Anthus cervinus
7 Tree Pipit Anthus trivialis
8 House Swift Apus affinis
9 Common Swift Apus apus
10 Grey Heron Ardea cinerea
11 Eurasian Eagle Owl Bubo bubo
12 Cattle Egret Bubulcus ibis
13 Rosefinch Carpodacus sp.
14 Rufous Woodpecker Celeus brachyurus
15 Bush Warbler Cettia sp.
16 Rock Pigeon (Common Pigeon) Columba livia
17 Oriental Magpie Robin Copsychus saularis
18 Indian Roller Coracias benghalensis
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
79| P a g e Department of Electricity Development
S.N. Order/Family/Common Name Scientific Name
19 Large-billed Crow Corvus macrorhynchos
20 House Crow Corvus splendens
21 Common Quail Coturnix coturnix
22 Eurasian Cuckoo (Common Cuckoo) Cuculus canorus
23 Indian Cuckoo Cuculus micropterus
24 Nepal House Martin Delichon nipalensis
25 Rufous Treepie Dendrocitta vagabunda
26 Black Drongo Dicrurus macrocercus
27 Red Junglefowl Gallus gallus
28 Pale-headed Woodpecker Gecinulus grantia
29 Common Crane Grus grus
30 Vulture Gyps sp.
31 Barn Swallow Hirundo rustica
32 Long-tailed Shrike Lanius schach
33 Kalij Pheasant Lophura leucomelanos
34 Blue-throated Barbet Megalaima asiatica
35 Great Barbet Megalaima virens
36 Black Kite Milvus migrans
37 Wagtail Motacilla sp.
38 Blue Whistling Thrush Myophonus caeruleus
39 Indian Grey Hornbill Ocyceros birostris
40 House Sparrow Passer domesticus
41 Indian Peafowl Pavo cristatus
42 Scarlet Minivet Pericrocotus flammeus
43 Green-billed Malkoha Phaenicophaeus tristis
44 Great Cormorant Phalacrocorax carbo
45 Indian Pitta Pitta brachyura
46 Alexandrine Parakeet Psittacula eupatria
47 Red-vented Bulbul Pycnonotus cafer
48 Spotted Dove Streptopelia chinensis
49 Oriental Turtle Dove Streptopelia orientalis
50 Common Shelduck Tadorna tadorna
51 Common Woodshrike Tephrodornis pondicerianus
52 Orange-breasted Green Pigeon Treron bicincta
53 Jungle Babbler Turdoides striatus
54 Small Button quail Turnix sylvatica
55 Barn Owl Tyto alba
56 Grass Owl (Eastern Grass Owl) Tyto longimembris
57 River Lapwing Vanellus duvaucelii
58 Red-wattled Lapwing Vanellus indicus
Source: Field Survey, 2017/18
4.2.15 Reptiles and Amphibians
Ten (10) species of reptiles and six (6) amphibians were recorded from the project area.
According to the local people, project area consists of snakes, rat snake (Ptyas mucosus)
mountain pit viper (Ovophis monticola), green pit viper (Trimeresurus albolabris) and garden
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
80| P a g e Department of Electricity Development
lizard (Calotes versicolor). The presence of frog (Euphlyctis cyanophlyctis) and toad
(Duttaphrynus melanostictus) were also noted in ditches and pools at the intake, powerhouse
sites and the communities around. Others are given in table 4.29.
Table 4-30: List of Herpeto-Fauna Recorded in Project Area
S.N. Common Name Scientific Name
1 The Bengal monitor or common Indian monitor Varanus bengalensis
2 Golden tree snake Chrysopelea ornata
3 Many-keeled grass skink Eutropis carinata
4 Large mountain lizard Japalura major
5 Tuberculated agama Laudakia tuberculata
6 Mountain pitviper Ovophis monticola
7 Sikkim ground skink or bronzy-brown skink) Asymblepharus sikimmensis
8 Oriental ratsnake, Indian rat snake Ptyas mucosa
9 Green pit viper Trimeresurus albolabris
10 Garden lizard Calotes versicolor
11 Himalaya sucker frog, Himalaya cascade frog, or
Himalaya frog Amolops himalayanus
12 Himalayan toad Duttaphrynus himalayanus
13 Nepal paa frog, tiny frog, small paa frog Nanorana minica
14 Indian burrowing frog Sphaerotheca breviceps
15 Indian skipper frog or skittering frog Euphlyctis cyanophlyctis
16 Asian common toad, Asian black-spined toad, Asian
toad, black-spectacled toad Duttaphrynus melanostictus
4.2.16 Butterflies
Varieties of butterflies were recorded between the intake and powerhouse area. The presence
of black bodied sward tails (Papilo spp.), dukes (Euthalia sahadeva), town tiger (Danaus
aglea) and demons (Notocrypta curvifascia) were recorded at the intake site, whereas barons
(Euthalia monima), sailers (Neptis hylas) and common mep (Cyrestis thyodamas) were
recorded from the powerhouse area.
4.2.17 Fish Species
A total of 4 species of fish were reported to be found in Dudh Koshi River. Two days sampling
using a fish net and fish hook resulted in catch of only Chuche Asala i.e. Schizothorax
progastus and Buche Asala (Schizothorax richardsoni) in three sites i.e. Dudh Koshi River at
Weir and Intake Area, Dewatered Zone near Tari (Suspension Bridge) and Powerhouse and
Tailrace Area. Other 2 species (Kabre, Tite) were reported by local informants.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
81| P a g e Department of Electricity Development
Table 4-31: Reported and Observed Fish Fauna in the Dudh Koshi River
S.N. Local Name Scientific Name
Mig
rato
ry S
tatu
s
Sites
Du
dh
Ko
shi
Riv
er a
t
Wei
r a
nd
In
tak
e A
rea
Dew
ate
r Z
on
e o
f
DK
5H
PP
, N
ear
Ta
ri
(Su
spen
sio
n B
rid
ge
Are
a)
Po
wer
ho
use
an
d
Ta
ilra
ce A
rea
O R O R O R
1 Chuche Asala Schizothorax progastus MM + + + + + +
2 Buche asala Schizothorax richardsoni MM + + + + + +
3 Kabre Glyptothorax pectinopterus R + + +
4 Tite Psilorhynchus pseudecheneis R + + +
Source: Field Survey, 2017; Note: MM: Middle Distance Migratory, LM: Long Distance Migratory, R:
Residential; Note: O= Observed; R= Reported
A. Species Description
i. Schizothorax richardsonii (Blunt–nosed Asala) and Schizothoraichthys progastus
(Pointed nose -Asala)
Asala is the dominant mid distance migratory fish species (belonging to Cyprinidae family) in
the Dudh Koshi River. These two fishes are omnivorous fishes and feed on algae, pieces of
aquatic plants and insects. Asala breeds twice in a year in autumn (September/October) and
spring (March/April). These species prefer rapids, pools and riffle types of habitats. A local
informant reported catch of a maximum 2 Kg Chuche Asala from the Dudh Koshi River. Asala
could be found in Dudh Koshi River in all seasons but the local informant reported that
abundance is higher during April-May.
ii. Glyptothorax pectinopterus (Kabre)
Kabre is a residential fish from Sisoridae family. It is more abundant in the Dudh Koshi River
during June to September. These are small, benthic species inhabiting pool and run areas of
streams and also found in the mountain rapids. This species inhabits swift-flowing rivers with
a substrate of sand and rocks.
iii. Psilorhynchus pseudecheneis(Tite)
‘Tite’ is one of the residential fishes having medicinal value. Its body is elongated, depressed
and flattened with 3 to 5 distinct transverse folds on the ventral side. Generally, the body colour
is darker with greenish spangle on the dorsal side. The head is bluish brown while the ventral
yellowish. A light dark band is present along the pectoral fin from just behind the operculum
to the base caudal. A few dark blotches and bands are present in front of the dorsal fin as well
as behind. Its scales are pigmented black. It grows up to 150 mm. The stone carp is said to have
an acrid taste and is therefore called Tite. It has a medicinal value. Tite is more abundant during
August-September.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
82| P a g e Department of Electricity Development
B. Fish migration and migratory path
Some fish species of migratory nature were observed on the basis of interactions with the local
fishermen, direct observation and relevant literatures. Among reported 4 fish species, two
species (Schizothorax progastus and Schizothorax richardsoni) were medium distance
migratory species and the rest two were residential species. The migration pattern of the fishes
is shown in Table 4.32.
Table 4-32: Fish Migratory Pattern
Fish Species J F M A M J J A S O N D
Schizothorax progastus (Chuche
Asala) ↑ ↑ ↑ ↓ ↓
Schizothorax richardsoni (Buche
Asala) ↑ ↑ ↑ ↓ ↓
Source: Field Survey, 2017/18; Note: ↑= Upstream Migration; ↓= Downstream Migration
C. Species Abundance
A total of 26 fish of a single species were collected from the three sampling sites of Dudh Koshi
River. In all three sampled sites, only two fish species were caught. Among 26 individual
fishes, 15 were caught from power house and tailrace areas, 3 from dewater zone and 8 from
headwork areas. The length of the caught fishes ranged from 10 cm to 23 cm. Maximum weight
of a single fish is recorded to be 230 gm. The combined weight of all caught fishes was 2.35
Kg.
Table 4-33: Species Diversity and Distribution
Common Name Scientific Name Site*
Total 1 2 3
Buche Schizothorax richardsoni 2 2 11 15
Chuchche Schizothorax progastus 6 1 4 11
Total 8 3 15 26
Source: Field Survey, 2017, *Note: 1=Power House and Tailrace Area; 2=Dewater Zone and
*3=Headwork Area
Table 4-34: Fish Abundance at Sampling Sites
Site
No. Sites
Number of
Fish Caught
Total Weight
of Fish
Caught (gm)
Numbe
r of
Species
Catch
Percentag
e
Percentage of
fish caught by
Weight
1 Headwork Site 8 750 2 30.77 31.91
2 Dewater Zone 3 450 2 11.54 19.15
3 Powerhouse and
Tailrace Area 15 1150 2 57.69 48.94
Total 26 2350 6 100.00 100.00
Source: Field Survey, 2017
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
83| P a g e Department of Electricity Development
D. Catch per Unit Effort (CPUE)
A total of 26 fish were caught at 3 Sites. The catch per unit effort for site 1 is 1:0.53, site 2 is
1: 0.33, site 3 is 1:0.56, with the highest ratio at downstream.
Table 4-35: Catch per Unit Effort (CPUE) at Different Sampling Stations
Sites
No. Sites
Level of
Effort
No. of Fish
caught
Catch per unit
effort (CPUE)
Attempt
Catch
Ratio
1 Headwork Site 15 8 0.53 1:0.53
2 Dewater Zone 9 3 0.33 1:0.33
3 Powerhouse and Tailrace Area 27 15 0.56 1:0.56
Total 51 26 0.51 1:0.51
Source: Field Survey, 2017
E. Fishing Trends and Practices
The Dudh Koshi River is a high gradient mountain river carrying moderate discharge in dry
season. The River is good in terms of fish resources. The field interviews with local informant
revealed that there are no families in project affected areas who entirely depend on fishes of
Dudh Koshi River for their living. Fishing is a part-time job and for fun in the area.
4.2.18 Protected Wildlife
Among various wild animals reported/observed from project area, eleven (11) species are
protected. Of which 5 were mammals, 5 birds and 1 reptile.
Table 4-36: Protected Wild Animals in Project Area
S.N. Common Names Scientific Names CITES
Appendix
IUCN
Red List GoN Remarks
1 Golden Jackal Canis aureus III Mammals
2 Rhesus Monkey Macaca mulatta II LR/nt Mammals
3 Yellow-throated
Marten Martes Flacigula III Mammals
4 Common Leopard Panthera Pardus I LR/nt Mammals
5 Bengal fox Vulpes
bengalensis III DD Mammals
6 Besra Sparrow
Hawk Accipiter virgatus II Birds
7 Cattle Egret Bubulcus ibis III Birds
8 Vulture Gyps sp. Birds
9 Indian Pitta Pitta brachyura II Birds
10 Barn Owl Tyto alba II Birds
11 Asiatic Rat Snake Ptyas mucosus II Reptiles
Source: Field Survey, 2017
4.3 Socio-economic and Cultural Environment
4.3.1 District Profile
(i) Introduction
Solukhumbu district, a part of province 1 of Nepal, is surrounded by Bhojpur and
Sankhuwasabha district in the East, by Tibet in the North, Dolakha and Ramechhap in the West
and by Okhaldhunga and Khotang district in the South. It lies 266 km north east from the capital
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
84| P a g e Department of Electricity Development
district Kathmandu. It lies between 27o20’39” to 28o6’24” North and 86o0’21” to 87o0’1” East.
The total area of the district is 339776 ha. Which comprises 33312 ha agriculture land
(Cultivated-21435 ha and Non-cultivated-11877 ha), 49849 ha pasture land, 105330 ha forest
land and 151285 ha other land. The total area of the district is 339776 ha; majority of the area
is covered with31.27 % (105330 ha.) forest area and 9.8% (33312 ha.) agricultural land.
Table 4-37: Land Use Pattern of Solukhumbu District
Physical
Condition
Agriculture (ha.) Non-Agriculture (ha.)
Total (ha.) Cultivated
Non-
Cultivated Pasture Forest Others
High Himalaya 503 89 31,808 10,937 149,174 192,511
High Mountain 19,602 11,314 17,812 93,673 2,063 144,464
Mid Mountain 1,330 474 229 720 48 2,801
Total 21,435 11,877 49,849 105,330 151,285 339,776
Source: District Profiles of Solukhumbu, 2074
This district consists of one constituent area. It has one municipality and seven Gaunpalika.
The population census of the district in 2011 showed 105886 constituting 51200 (48.35%)
males and 54686 (51.65%) females. There were 23785 households with average household size
4.45 persons. Salleri is the headquarter of the district. Ethnically, major groups are Rai, Sherpa,
Chhettri, Tamang and kulung respectfully Kami, Magar, Brahman, Newar, Gharti and others.
(ii) Caste/Ethnic Composition
Solukhumbu district has diverse ethnic distribution. There are more than 40 caste ethnic groups.
It has a predominant ethnic Rai 19.61%, following Sherpa 16.71%, Chhetri 15.06%, Tamamg
9.90%, Kulung 8.90%, Kami 5.59%, Magar 4.91% and Brahman 4.62% population, making
up about 85.30% of the total population. After this there are Nachhiring, Newar, Gharti/Bhujel,
Damai/Dholi, Thulung, Gurung, Dashnami/Sanyasi, Sarki Khaling, Sunuwar, Kalar, Majhi and
others who makes 14.70 % predominantly inhabit the district.
(iii) Economic Activities
About 50.72 percent of total population of the district is economically active, of which about
58% totally depend upon agriculture. The remaining 42% are engaged in non-agricultural
occupation such as trade/business, transport, services etc.
The main cereal crops of the district are paddy, maize, wheat, phaper, millet, and barley with
the annual production of 3366 MT, 32517mt, 6957 MT 192 MT, 26880 MT and 200 MT
respectively. Potato 153723 MT is the main cash crop in the district in 20016/17 as per district
profile. A total of 8555 MT of milk, 2513 MT of meat, 4185,000 eggs, and 6832 MT of wool
were produced as the livestock products of the district in 20016/17. The district is a food deficit
district of Nepal.
Other major economic activity in the district is tourism. The tourism industry has provided
employment to more than 2000 persons. Solukhumbu district consists of famous trekking route
for the international trekkers and climbers to Sagarmatha base camp. Pike dada, Ratnange dada,
Chiwang gumba, Junbesi gumba Tashithanmen Mahabir gumba, Jyalsa, Salleri Thekchhen
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
85| P a g e Department of Electricity Development
Pema Chholing gumba, Merapik, Dhaemapik, Salpa pokhari and many other places of Namche,
Khumjung and Chaurikharka are in the trekking route, and large numbers of lodges and
restaurants are in operation in the trekking areas. More than 25000 trekkers use the trekking
route every year. The per capita income of the district is high than other district of Nepal.
(iv) Social Services
a) Education
There are total 280 schools, in which 172 primary; 64 lower secondary, 20 secondary and 24
higher secondary schools in the district. Six private campuses and 248 pre-primary schools are
also there in the district. The literacy rate of 6 years of age and above in the district is 67.5%
in 2016/17 in the district.
b) Health
The district has one district hospital, 2 health centre, 14 health posts, 18 sub-health posts and
one Ayurvedic Aushadhalaya (clinic). About 500 women health volunteers are active in
providing the health services to the women of the district. The most common diseases prevalent
in the district are skin diseases, diarrhoea, and worm gastritis.
c) Communication
There is one district post office, 8 regional divisional post offices and 25 additional post offices
in the district. Beside this two-courier service are in the district. There 455 telephone lines have
been distributed in the district. At about 16150 CDMA, 3570 Ncell and 13080 Namaste mobiles
are distributed in the district.
d) Water Supply and Sanitation
About 89.50 percent of total households have tapped water supply in the district. About 75
percent of the total population of the district have toilet facilities and other go to field, khola
and khet bari for open defecation.
e) Electrification
About 20 percent of the total population of the district enjoys electricity supply in their houses
through small hydropower, Peltric set and Micro hydropower projects. Local people have also
installed individual solar panels.
f) Transportation
This district is connected with 55 km of National Highway and it is about 266 km from
Kathmandu with black top road. The district is also connected with Kathmandu through air
transport services between Phaplu and Syangboche Airports of the district and Tribhuvan
International Airport in Kathmandu.
4.3.2 Project Affected Rural Municipality (Gaunpalika), Wards and Project Area
The DK5HPP is situated within one rural municipality– Mapya Dudhkoshi Rural Muncipality
of Solukhumbu district. All 7 Wards of Mapya Dudhkoshi rural municipality will be affected
by the project.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
86| P a g e Department of Electricity Development
(i) Population size and Dynamics
The project affected rural municipality has population of 13,414 residing in 2,803 households.
Among total population in the project affected rural municipality, 48.67% are male and the
remaining 51.33% are female. The project affected rural municipality account for around
11.78% of the total households and around 12.76% of the total population of the project district.
Average family size of the project affected rural municipality is 4.78 which is slightly higher
than that of project district.
Table 4-38: Population of project affected Mapya Dudh Koshi Gaunpalika
Ward No. Households Population Male Female Sex Ratio HH Size
1 335 1524 741 783 94.64 4.55
2 308 1543 753 790 95.32 5.01
3 368 1713 821 892 92.04 4.65
4 338 1529 761 768 99.09 4.52
5 491 2261 1073 1188 90.32 4.60
6 541 2566 1255 1311 95.73 4.74
7 422 2278 1125 1153 97.57 5.40
Total 2803 13,414 6,529 6,885 94.83 4.78 Source: CBS, 2011
(ii) Social Demography
Caste and ethnicity
Project area is inhabited by diverse caste and ethnic/Janajatis, and linguistic groups. Among
them Rai is predominant in terms of population. Rai is the largest Janajati group having 51.59%
of the total population of the project wards followed by Sherpa (13.48%), Kami (5.02%),
Magar (8.50), Chhetri (6.29%), Tamang (5.45%) and other groups.
Table 4-39: Population by caste/ethnicity and sex
S. N. Wards and
caste/ethnicity
Jubing
(1) %
Basa
(2,3)
Kaku
(4,5)
Baku
(6,7) Total
Percent
(%)
1 All Caste 1524 3256 3790 4844 13414 100
2 Rai 555 36.42 1775 1922 2669 6921 51.59
3 Sherpa 607 39.83 0 482 719 1808 13.48
4 Kami 139 9.12 291 428 380 1238 9.23
5 Magar 152 9.97 286 0 702 1140 8.50
6 Chhetree 8 0.52 613 123 100 844 6.29
7 Tamang 15 0.98 0 691 25 731 5.45
8 Brahman - Hill 9 0.59 0 22 129 160 1.19
9 Damai/Dholi 11 0.72 87 38 23 159 1.18
10 Gharti/Bhujel 0 0 156 0 0 156 1.16
11 Khaling 6 0.39 0 66 0 72 0.54
12 Newar 0 0 0 0 45 45 0.33
13 Tharu 6 0.39 11 0 0 17 0.14
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
87| P a g e Department of Electricity Development
14 Others 16 1.05 37 18 52 123 0.92
Source: CBS 2011
Language
Census 2011 recorded, more than 11 languages in the project affected rural municipality.
Among these 11 languages, the most widely spoken languages are: Khaling (50.43%) followed
by Nepali (20.25%), Sherpa (13.64%), Magar (7.75%), Tamang (5.22%), Thulung (0.59%) and
other languages.
Table 4-40: Population distribution by mother tongue in the project Wards
Wards and
Mother Tongue
Ward 1
(Jubing)
Ward 2,3
(Basa)
Ward 5
(Kaku)
Ward 6,7
(Baku)
Total Percent
(%)
Khaling 504 1742 1911 2608 6765 50.43
Nepali 235 1137 623 721 2716 20.25
Sherpa 604 0 483 743 1830 13.64
Magar 105 254 0 681 1040 7.75
Tamang 10 0 690 0 700 5.22
Thulung 22 0 46 11 79 0.59
Rai 10 24 13 29 76 0.57
Bhujel 0 60 0 0 60 0.45
Tharu 5 11 0 0 16 0.12
Nachhiring 0 0 0 15 15 0.11
Maithili 0 0 0 12 12 0.11
Others 29 28 24 24 105 0.76
Source: CBS 2011
Religion
Hinduism and Buddhism are mostly practiced in the area and most of them celebrate Hindu
festivals. Household survey indicated that there are 47 % Buddhists, 51 % Hindus and 2 %
Christians. However, Sholukhambhu District comprises of 63% Hindus and 35% Buddhists.
Dashain, Tihar, Teej, Chaite, Janaipurnima, Baishakh Purnima, Maghe Sangkranti and Lhosar
are the important festivals celebrated in the area.
Table 4-41: Religion of sampled households
Religions Numbers of HHs HH percentage
Hindus 99 50.51
Buddhists 92 46.94
Christians 4 2.04
Others 1 0.51
Total 196 100.00
Source: Field Survey, 2018
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
88| P a g e Department of Electricity Development
Gender roles and social networks
Women constitute about 51.32 % of the total population in the project affected rural
municipality as per national census survey of 2011. They do all the household chores including
cooking, cleaning, rearing children, tending cattle and even work in the fields. The literacy rate
among them is also low as compared to men. Women perform most of the HH work and farm
activities. The working hours of women are comparatively longer than that of men in this area.
Women from and around the project site are also equipped with skills such as sewing and
knitting of woolen cap and etc. However, all household and other decisions are made by men,
and women are often ignored in the decision-making process, although their contribution is
immensely valuable.
Literacy and education
When compared the literacy rate (5 years or above) of the project area, Basa-2 &3 stood first
with 66.58% followed by Jubing-1 (65.52%), Kaku-4 & 5 (64.80%) and Baku-6 & 7 (58.51%).
In the project wards, a total of population 7,642 (63.06%) can read and write, whereas 385
(3.18%) persons can only read and 4084 (33.7%) persons can neither read nor write as reported
in the Census 2011 (CBS 2011).
According to the Census 2011, the record of educational attainment of project area population
is good. There were 7700 (96.82%) persons who have passed formal degree, including SLC
(CBS, 2011). Based on the Census 2011, within the entire project area, only11 males and 3
females had completed Masters’ degree.
The project area has 9-primary and 4 secondary schools. There is one high school in ward no-
3 Damku at project area. Students of the project area have to go to Kathmandu & Salleri bazaar
for higher level education. Students, who are economically sound, prefer to go to either Salleri
bazaar or Kathmandu for higher education.
Migration
The out-migration is a regular phenomenon which occurs mostly in an economically active age
group. Usually people migrate to Salleri Bazar (district headquarter), Kathmandu, Qatar, Dubai
and Malaysia especially during off farming season either for employment purpose or for long
term migration.
Of the respondents, 770 of the sampled population 182 (25.70%) has gone out for seeking jobs.
Among the migrated people of the sample area, 5 percent of the people are in Qatar, 3 percent
in India, 7 percent in Dubai, 8 percent in Malaysia and remaining sixty -nine percent are within
the country. Women migration is nominal. However, they migrate together with their husbands
and families. Seasonal migration is still common.
Table 4-42: Population migration pattern in the project area
Sampled
HHs Qatar Malaysia Dubai
Saudi
Arabia/Bahrain India
Within
country Other Total
160 10 16 13 12 6 136 5 198
Percent 5.05 8.08 6.57 6.06 3.03 68.69 2.53 100.00
Source: Field Survey, 2018
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
89| P a g e Department of Electricity Development
Housing and settlement pattern
Both cluster and scattered settlement were observed in the district during the site visit. Cluster
settlement were observed mainly in district headquarter and market/bazaar area, whereas
scattered settlement was observed in remote hills and other places. The settlement in the project
area is scattered type. In the village area, houses are mostly made up with locally available
materials like mud and stone with stone/slate, metal (tin) sheet and thatched roof, whereas RCC
houses were observed in district headquarter, market/bazaar areas and along the access road.
Figure 4-14: House Structures and Settlement Patterns
By the type of outer wall of housing, 95.70% (3098) housing units were constructed by mud
bonded stones, 1.79% (58) housing units were constructed by using Bamboo and using Wood.
As the data shows, about 99% households are built by using mud/stones, bamboo and woods
(Table 4-43).
Table 4-43: Households by outer wall of house/housing units
Wards Total Type of outer wall
Mud
bonded
bricks/stone
Cement
bonded
bricks/stone
Wood/
planks
Bamboo Unbaked
brick
Others Not
Stated
Jubing 769 721 3 35 9 0 0 1
Basa 676 659 3 1 5 4 0 4
Kaku 829 804 0 11 8 0 2 4
Baku 963 914 0 11 36 0 0 2
Total 3,237 3,098 6 58 58 4 2 11
Percent (%) 95.7 1.79 1.79
Source: CBS 2011
Vulnerable and disadvantaged groups
This study identified Persons with Disability (PWDs), children, Dalits, and elderly people as
the vulnerable and disadvantage groups in the project areas. Persons belong to these categories
are vulnerable because of their specific characteristic which put them at a higher risk of relative
disadvantages in access to resources, employment opportunities and income level. Moreover,
it is also likely to argue that people from such categories are at a higher risk of being
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
90| P a g e Department of Electricity Development
marginalized, compared to other people since they cannot capture the benefits that might be
accrued from the project. The Census 2011 data shows that population from the vulnerable
groups (disabled people, children, dalits, elderly people) comprised 48.13% of the total
population in the project Wards. Table 4-44 shows the total population of the vulnerable
groups.
Table 4-44: Vulnerable and disadvantage groups in the project area
Wards PWDs Children
(0-14) years Dalits
Elderly People
(65 and above) Total
Percentage
(%)
1 49 481 150 81 761 10.40
2,3 61 1164 378 155 1758 24.02
4,5 195 1252 466 253 2166 29.60
6,7 160 1821 403 249 2633 35.98
Total 465
(3.47%)
4718
(35.17%)
1397
(10.41%)
738
(5.50%)
7318
(54.55%)
100
Source: CBS 2011
(iii) Economic demography
Economically active population
The working age population (15 to 59) years of the project wards are shown in the Table 4-45
below. As per the Census report, the working age population was 56.22% (7,541) of the total
population of rural municipality which is slightly lower than the national working age
population (57%). When compared to Ward wise working age population, Jubing-1 had highest
working age population with 60.69% followed by Kaku-4 & 5 with 56.46%, Basa-2 & 3 with
56% and Baku-6&7 with 54.77%.
Table 4-45: Working age population (15 to 59) year of the project wards
Wards Total Populatiom Working population (15 to 59) Year
Percent (%) Male Female Total
Jubing (Ward 1) 1524 448 477 925 60.69
Basa (2,3) 3256 865 958 1823 56.00
Kaku (4,5) 3790 964 1176 2140 56.46
Baku (6,7) 4844 1278 1375 2653 54.77
Total 13,414 3,555 3,986 7541 56.20
Source: CBS 2011
Land use and farming
Land use pattern in the project area is diverse and has direct bearing on agricultural production
and food security. Lands are, for instance, used as forest area, agriculture/cultivated land,
pasture/grass land, shrub land, sandy area, water bodies, barren land etc.
It has been found that over 60% of the people are dependent on agriculture-based occupation.
Maize, Millets, Paddy and wheat are the major crop produced in the area. Production of maize
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
91| P a g e Department of Electricity Development
accounts for 37% of total agriculture production, which is very high as compared to the other
crops. Agricultural activities are performed intensively with manual labor. However, overall
economy of the project area primarily depends on agriculture and tracking sector, which has
been integrated with livestock. Agriculture production depends upon a variety of conditions
such as timely onset of monsoon and the input of modern agriculture services, etc. Majority of
the land at the intake area depends on monsoon rains due to the lack of irrigation facilities.
Table 4-46: Production of Major Crops in the Project Area
S.N. Crops Production
(Muri)
Production
(Muri)
Production
(Kg)
Average
Production/HHs
Percent
(%)
1 Paddy 163 163 11410 58.21 8.48
2 Maize 157.3 638.8 44716 228.14 33.23
3 Wheat 49.85 181.85 12729.5 64.95 9.46
4 Potato 75.1 349.1 24437 124.68 18.16
5 Millet 128.85 583.85 40869.5 208.52 30.37
6 Mustard
& Others 4 6 420 2.14 0.31
Total 1922.6 134582 686.64 100.00
Source: Field Survey, 2018
Employment
Self-employment is only option to keep oneself as employed. The overwhelming majority of
the local people are employed in the agricultural sector (subsistence farming). Livestock
rearing and rain fed farming are the major agricultural activities of the project area. Few
households also practice small scale trade with combined focus on household commodities,
goats, and alcohol. At the local level, employment opportunity is very low.
Agriculture is the main occupation of the project area. More than 64.29% of the respondents
are involved in agriculture for their primary livelihood. Besides agriculture, 9.09% are students,
5.06% are employed in trekking (porter), 4.55 % are in foreign employment 7.79% are engaged
in service, 3.90 % in business and 5.32 % in Labor works including mason and carpenter etc.
Table 4-47: Major occupation of the Project Area
Major Occupation Population Percent (%)
Agriculture 495 64.29
Services 60 7.79
Labors/Mason etc 41 5.32
Trekking 39 5.06
Foreign employment 35 4.55
Business 30 3.90
Others 70 9.09
Total 770 100.00
Source: Field Survey, 2017/2018
Fishing
There are only few fishermen in the project area. Estimation of fishermen population in the
area is difficult, mainly because they did not claim themselves as professional fishermen.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
92| P a g e Department of Electricity Development
Fishing is practiced mainly by communities living in immediate vicinity nearby Dudh Koshi
River. They use different types of fishing gears. They are tango (Balchhi), gill net
(LaharePasso), and cast net (HaateJal), to catch the fish from the river. Fishing was reported
to be practiced mainly from September to November and some minor fishing during the rest of
the monsoon season. The price of fresh fish is reported to be about NRs. 450 per kg. They sell
fish often in the local market and occasionally in Basa and Damku.
Livestock
Livestock is an important part of the agriculture system of the project area. 89% of the people
own cows and bulls. Cattle and buffaloes are the main providers of manures too.
Table 4-48: Livestock Herding in Project Area
Livestock Total Percent Avg. Livestock /HHs
Cow/Bull 505 19.22 2.58
Buffalo 236 8.98 1.20
Hen/Duck 1052 40.05 5.37
Goat 677 25.77 3.45
Pigs 157 5.98 0.80
Total 2627 100.00 4.04 Source: Field Survey, 2018
Most of the animal products such as milk, butter and ghee are consumed locally. People usually
make ghee for self-consumption and selling purpose. While some house owners with many
cattle sell these products at the nearest market areas like Damku Bazar.
(iv) Access to civic amenities
Drinking water and sanitation
Based on the Census 2011, the situation of drinking water and sanitation in the project area is
not bad. For instance, majority of the households 76.98% (2158) have access to ordinary toilet
facilities. Out of 2803 total households, 5.24% (147) have access even to flush toilet facility.
However, the census reported that more than 17.62% (494) households have no access to toilet
facilities (See Table 4-49).
Table 4-49: Households by type of toilet facilities
Wards Total
HHs
Households without
toilet facility
Households with toilet
facility of Toilet
facility
not stated Flush toilet Ordinary
toilet
Jubing (Ward
1) 335 39 53 243 0
Basa (2,3) 676 132 32 511 1
Kaku (4,5) 829 160 31 636 2
Baku (6,7) 963 163 31 768 1
Total 2,803 494 147 2,158 4
Percent (%) 100 17.62 5.24 76.98 0.16
Source: CBS 2011
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
93| P a g e Department of Electricity Development
The main source of water for drinking water supply in the project affected wards is local
springs. As for the access to drinking water, 90.51% (2537) have access to tap or piped drinking
water supply. There were 1.75% (49) households who have no access to tap or pipe drinking
water supply and they sourced drinking water supply from nearby river and streams. Beside
this, another sources of drinking water used by 2.32% (65) households was Kuwa.
Table 4-50: Households by sources of drinking water
Wards Total HHs
Main source of drinking water
Ta
p/p
iped
wa
ter
Co
ver
ed
wel
l/k
uw
a
Un
cov
ered
wel
l/k
uw
a
Sp
ou
t w
ate
r
Riv
er
/str
eam
Oth
ers
No
t S
tate
d
Jubing (1) 335 283 2 6 33 11 0 0
Basa (2,3) 676 656 4 8 0 7 0 1
Kaku (4,5) 829 775 0 7 23 22 0 2
Baku (6,7) 963 823 3 44 83 8 0 1
Total 2,803 2537 9 65 139 49 0 4
Percent (%) 90.51 0.32 2.32 4.96 1.75 0 0.15
Sources: CBS 2011
Public health
Water borne diseases: Water borne diseases such as diarrhea, dysentery, typhoid and fever are
common in the project affected wards of rural municipality. Moreover, cough and cold, gastric,
eye diseases, respiratory diseases (bronchitis), malnutrition, skin diseases, heart diseases, blood
pressure and tuberculosis are also recorded in the area. However, there was no record of
HIV/AIDS in the project area.
Health treatment facilities:
There are four health posts in the project affected area. The nearest health post (with limited
health facilities) is located at Basa, which is 2-3 hours walking distance from the project intake
area and 1.5 hour from proposed powerhouse area. As per government rules, one Assistant
Health Worker (AHW), one Maternal Child Health Worker (MCHW) and one Field Health
Worker need to be engaged in each health post. However, the facilities such as staff and
medicines are inadequate most of the time in the health post.
Sources of energy use
According to the Census 2011 report, almost 2792 (99.60%) out of the total 2803 households
use firewoodas cooking fuel, and only negligible households 5 (0.18%) and 1 (0.03%) reported
to have used Kerosene and LP gas as cooking fuel respectively. This shows that local people
heavily depend on the forests for collecting firewood required for cooking. However, it was
observed that households and business houses like hotel and lodges in the market area use LPG
(Liquefied Petroleum Gas) and Kerosene as an alternative source of energy for cooking (Table
4-51).
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
94| P a g e Department of Electricity Development
Table 4-51: Households by Type of fuel used for cooking in the project Wards
Wards Total
HHs
Fuel usually used for cooking
Wo
od
/
fire
wo
od
Ker
ose
ne
LP
ga
s
Sa
nth
i/
gu
ith
a
(co
w d
un
g)
Bio
ga
s
Ele
ctri
city
Oth
ers
No
t S
tate
d
Jubing (1) 335 335 0 0 0 0 0 0 0
Basa (2,3) 676 675 0 0 0 0 0 0 1
Kaku (4,5) 829 826 1 0 0 0 0 0 2
Baku (6,7) 963 956 4 1 0 1 0 0 1
Total 2,803 2792 5 1 0 1 0 0 4
Percent (%) 100 99.60 0.18 0.03 0 0.03 0 0 0.16
Source CBS, 2011
As for the lighting, electricity is recorded as the major sources of energy used for lighting in
the project area in the Census 2011. Other than cooking fuel, the Census data reveals that
majority of the households 1809 (64.54%) use electricity for lighting, 439 (15.66%) households
use kerosene, 377 (13.45%) households use Solar Power and remaining 178(6.35%)
households use other means of energy for the lighting.
Table 4-52: Households by source of lighting
Wards Total
HHs
Fuel usually used for lighting
Electricity Kerosene Bio gas Solar Others Not
Stated
Jubing (1) 335 318 11 0 3 3 0
Basa (2,3) 676 659 14 0 2 0 1
Kaku (4,5) 829 526 173 0 89 39 2
Baku (6,7) 963 306 241 64 283 68 1
Total 2,803 1,809 439 64 377 110 4
Percent (%) 100 64.54 15.66 2.28 13.45 3.92 0.15
Source: CBS, 2011
(v) Local institutions and services
In the past, presence of government institutions was mostly limited to the district headquarters
and local people from the project area had to go to the respective district headquarter for
fulfilling all legal and administrative services. After the promulgation of the new Constitution
and consequent re-structuring of the local governance units (Rural Municipalities and Ward)
as the basic governing units have increased local people’s access to the government services at
the local level. Field interactions with local people revealed that local institutions like mother
groups, co-operatives, youth clubs, forest user's groups, etc. are also in operation and are
engaged in forest conservation, saving and credit, environmental conservation, health and
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
95| P a g e Department of Electricity Development
sanitation, community development programs and raising awareness programs in the project
area.
A number of national and international NGOs and INGOs are launching different kinds of
development and capacity building programs in the district. However, there are few NGOs and
INGOs working in the project affected Rural Municipality. Some Mother's Group, Youth club,
and CFUGs are engaged in forest conservation, saving and credit, environmental conservation,
health and sanitation, community development programs and raising awareness programs in
the project site. The local NGO, Himalayan Foundation, based in Salleri, is to empower
women, children, poorest and marginalized groups of people by promoting self-reliance
through organizational activities, awareness-building activities and economic self-dependence.
Like was REED Nepal based in Kathmandu, is supporting for school building and educational
materials at Basa & Baku areas. Other NGOs like Gorkha Welfare Society (GWS) support
agriculture and livestock-based activities to uplift the economic status of the beneficiaries, like
was Himalayan Development Foundation working in the field of education in Mapya
Dudhkoshi Gaunpalika
(vi) Transportation and communication
Transportation:
The access to the district headquarters Salleri bazaar from Kathmandu is through an all-weather
road about 266 km long, BP Highway connecting at Khurkot, at Sindhuli district. The
construction work for earthen track opening has been completed from the road head at Salleri
bazar of district headquarter up to the Basa near Gaunpalika headquarter through powerhouse
area at Thane khola.
Communication:
There are no telephone lines in the project area. However, the Nepal Telecommunications
Corporation (NTC) and NCELL networks especially Cell Phone services have access in the
project area. The post office of the project area is alsofound in the project areas.
As observed during the fieldwork, most of the areas are connected with mobile services. Code
Division Multiple Access (CDMA) phone facilities, NTC, and Ncell mobile services are
available in most parts of the project area. It was also observed that some of the households
had access to Dish Home cable network television. Young generation were found using internet
services, though limited to certain parts of the project area.
(vii) Archaeology and culture and heritage
No specific archaeological, historical sites of local importance were identified in the project
area. In the project site, there are some Bhumepuja (Bhumesthan), Bas, small temples,
Bhumesthans are near of mostly located in the Kirat Khulung Rai communities, whereas
temples and shrines are found in Brahmin and Chhettri communities. Religious places of Kirat,
Khaling Rai Bhumesthan at ward no 2 and Khaling Rai Bhumesthan at ward no 3, which are
located at Bodhu about 1.5 km and 4 km from the headworks and 4 km from the powerhouse
tunnel respectively. There are important religious places of the project affected areas, besides
these there are small temple at ward no 6, Jaleswor temple at Basa, Shiva temple at Damku,
Krishna temple Majha Gaun ward no-3, Somabare Sarwarati temple at Himalayan Secondary
School ward no-3 etc.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
96| P a g e Department of Electricity Development
(viii) Water use of the Dudhkoshi River
In the project area, water-based infrastructure in operation was not observed. However, two
small hydropower company were running and one is under construction at Jubing ward no 1.
Two small hydropowers were operating in the project areas, whose installed capacity is 70 &
30 MW respectively. The project is located in Andheri Khola ward number 1.
(ix) Cremation Practices
Kirat, Buddhist and Christian community in the project area practice burying of the body after
death, whereas the Hindu community strictly performs cremation by burning of the dead body
usually on the bank of the River. One cremation site is located near the confluence of Thane
Khola and Dudh Koshi River used by people of wards 6 and 7 of Mapya Dudhkoshi rural
municipality. Cremation site is located approximately 1 km downstream from the proposed
weir site on either bank of the river. Left bank is mostly used by Magar community of ward 6
of Mapya Dudhkoshi rural municipality. Right bank is mostly used by Brahmins, Chhetris,
Kamis and Damais of ward 3 of Mapya Dudhkoshi rural municipality. There are no physical
structures.
(x) Tourism
The project area is located near a tourist area (Sagarmatha base camp, Kalapatthar) of the
country, a famous trekking route to the Sagarmatha Base Camp & Sagarmatha National Park /
wildlife Conservation Area (SCA). Sagarmatha Base Camp is Nepal's most popular trekking
destination with over 38000 trekkers visiting each year. Usually, tourists come to Salleri Bazaar
by bus from Kathmandu and they either spend the night in Salleri Bazaar or head out directly
on the trek. Generally, trekkers stop at Lukla Bazaar to spend the night. Hence, the economy
of the impact area relies on tourism to some extent and particularly on food provision for
restaurants and lodges. Porters from Dudh Koshi Gaunpalika are also hired by trekkers to go
around the Sagarmatha base camp but most of them are hired in Lukla, Kathmandu or Salleri
bazaar.
4.3.3 Project affected households
This section describes the socioeconomic baseline of the project affected households based on
the finding of the household survey. Total of 60 households locating near the project area
directly or indirectly affected were surveyed to understand the demographic, economic and
cultural environment of the affected families, their perception regarding the project, expected
compensation for the lost property, types of resettlement package desired etc.
Defining Project Affected Families (PAF)
All those households/persons whose land(s) are to be acquired were considered as project
affected households. The project affected households include households residing within the
project component or the project facility occupied areas, who will be adversely affected by
construction of the project structures and project facilities. Of the total surveyed affected
households, 31 households are from Mapya Dudhkoshi Rural Municipality-2 (Basa), 10
households are from ward-3, 9 households are from Mapya Dudhkoshi Rural Muncipality-4 &
5 (Kaku) and 10 households are from Mapya Dudhkoshi Rural Muncipality- 6 & 7 (Baku).
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
97| P a g e Department of Electricity Development
These are further categorized as:
Project Affected Families (PAFs):
The households losing up to 50% of their total land are categorized under this category; and
Severely Project Affected Families (SPAFs):
The households/families who are physically displaced from their residences or commercial
establishments and those who are severely affected through loss of more than 50% of their
land. The households losing residential structures are also included in this category.
Detail socioeconomic profile of these households are presented in the following sections:
(i) Demographic Features of the Affected Households
Population, Age structure, Caste/ethnicity, Sex Ratio and Family Size
The total population of 160 affected households is 785 of which 51.08 % are females and 48.92
% are males with the average family size of 4.9 persons. The overall sex ratio (female to male)
is 0.93. In terms of the caste/ ethnicity, Rai are the dominant caste groups (97.5%), followed
by Chhetri (1.875%) and Sherpa (0.625%).
Table 4-53: Distribution of Affected Population by Different Categories
Categories Male Female Total Sex Ratio
(Female/Male)
Family
Size
By Caste/Ethnicity No % No % No %
Rai 375 48.76 394 51.24 769 97.96 1.05 4.90
Chhetri 6 54.50 5 45.50 11 1.40 0.83 5.5
Sherpa 3 60.00 2 40.00 5 0.64 0.67 5.0
Total / Overall 384 48.92 401 51.08 785 100 1.04 4.90
Source: Field Survey 2017/18
Total population of the sampled households (60) is 247 (Male 125, Female 122) with an
average HHs size of 4.11, which is slightly less when compared to the municipality average
(4.78). The Household survey shows that about 23.20 % of the populations are children, among
them about 3.9% are below one year. Likewise, 12.04 percent of the population is above 60
years of age and 64.76 percent of the population is between the age of 16 and 60 years. It shows
that about 35.24 percent of the population is dependent and 64.76 percent of population is
economically active.
Table 4-54: Age structure of the population of the sample HHs
Age Group Population Total Percentage
Male Female
<5 5 6 11 4.47
6 to 15 24 22 46 18.73
16 to 59 81 79 160 64.76
> 60 16 14 30 12.04
Total 126 121 247 100.00 Source: Household Survey, 2017/2018
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
98| P a g e Department of Electricity Development
(ii) Languages and Religions
The Janajati/Adhibasi groups like Kulung speak in their own mother tongue to communicate
with each other. However, almost all family members of these groups can also communicate
in Nepali language. Rai is the most dominant mother tongue among the PAFs (97.5%), Nepali
is spoken by 1.25%, Sherpa by 1.25%.
As per sample household survey, 50% project affected families follow Hindu religion and
remaining 46.67% and 2.33 % households follow Buddhist religion and other religion
respectively. The Chhetri caste of the project area mostly follows Hindu religion and the Rai
and Sherpa caste among the PAFs follows Hindu as well as Buddhist religion.
Table 4-55: Religious groups of sampled households
Religions Numbers of HHs HH percentage
Hindus 30 50.00
Buddhists 28 46.67
Christians 2 2.33
Total 60 100.00
Source: Field Survey, 2017/18
(iii) Literacy and Education Status
Out of the surveyed household population (aged 5 years and above), about 61.22 % of the
population is reported to be literate.
Table 4-56: Education Level of PAFs
Categories HHs Population
above 5 years
age
Percentage
Illiterate 23 52 38.78
Literate 18 41 30.61
Primary (1-3) 3 6 4.59
Lower Secondary (4-8) 5 11 7.65
Secondary (9-10) 7 16 11.73
Higher Secondary 2 6 4.08
Bachelor's & above 2 3 2.56
Total 60 135 100.00
Source: Field Survey, 2017/18
(iv) Occupation
Agriculture is the main occupation of the project affected households. More than 64.29% of
the households are involved in agriculture for their primary livelihood. Besides agriculture,
9.09% are students, 5.06% are employed in trekking (potter), 4.55 % are in foreign employment
7.79% are engaged in service, 3.90 % in business and 5.32 % in Labor works including mason
and carpenter etc.
(v) Land Tenure and Landholdings
In general, land has been divided into two categories. One is Khet (in which paddy can be
grown) and another is Bari (in which paddy cannot be grown). The total land of the sampled
households is estimated to be 3235 ropanies (164.55 ha) Khet is 435 ropanies (22.13 ha) and
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
99| P a g e Department of Electricity Development
Bari is 3235 ropani (164.55 ha). The average household land holding size is 16.51 ropanies
(0.84 ha).
Table 4-57: Land Categorization of Project Area
Sampled HHs Khet Bari Total
Ropani Ha Ropani Ha Ropani Ha
60 133.20 6.77 857.15 43.60 990.35 50.37
Average land
holding / HHs 2.22 0.113 14.286 0.73 16.506 0.843
Note: 1ha =19.66 ropani Source: Field Survey, 2017/18
(vi) Income and Expenditure Characteristics
The average annual gross income of the sampled HHs of the project area is estimated to be
NRs. 2,16,938.75 per household indicating the average per capita income NRs. 52,783.
However, it includes all the income of the households, i.e. income from agriculture, business,
service as well as income from outside the country (remittance). The agriculture production is
consumed by the HHs themselves and there is no surplus to sell in the market. The grain
production has been calculated in cash by the market price (value).
Table 4-58: Income Source of Sampled HHs of Project Area
Income Sources Total Amount (NRs.) Percent (%)
Agriculture 2,733,428.60 21.00
Business 2,056,579.60 15.80
Services 1,923,813.00 14.78
Labour 2,564,216.35 19.70
Remittance 2,749,048.00 21.12
Other 989,239.40 7.60
Total 13,016,324.95 100
Source: Household Survey, 2017/18
Average annual gross expenditure per household of the sampled HHs shows that the majority
of the households (45.00%) expend 200,001 to 300, 000 per year range and about 8% of the
household expend less than NRs. 200,000 per year.
Table 4-59: Average Yearly Expenditure Range of the Sample Households
S. N. Expenditure Range (NRs.) No. of HHs Percent (%)
1 <50,000 2 3.33
2 50,001-130,500 1 1.67
3 130,501-200,000 5 8.33
4 200,001-300,000 27 45.00
5 300,001-400,000 20 33.33
6 400,001-500,000 3 5.00
7 >500,000 2 3.33 Total 60 100
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
100| P a g e Department of Electricity Development
(vii) Food Sufficiency
Food is not sufficient for the majority of the people round the year from the agricultural sector.
They have to buy food from the market. Only 40% have food sufficiency for 9 to 12 months.
The remaining population has inadequate food throughout the year. Rice/Dhido and vegetables
are the common food usually taken during lunch and dinner.
Table 4-60: Food Sufficiency in the Sample HHs
S.N. Duration Number of
HHs Percent (%)
1 No Production 1 1.67
2 > 3 months 6 10.00
3 3-6 months 13 21.67
4 6-9 months 9 15.00
5 9-12 months 24 40.00
6 ˂12 & selling 7 11.66
Total 60 100 Source: Field Survey, 2017/18
(viii) Drinking Water and Sanitation
As per the sampled HHs survey, on an average, 83.33% have access to tapped drinking water
supply. Rest use spout, river, spring for the drinking purpose.
Table 4-61: Sources of drinking water in the Sample HHs
Source Number of HH Percent of HHs
Tap/Piped Water 50 83.33
Spout Water 2 3.33
River/Stream 7 11.67
Others 1 1.67
Total 60 100
Source: Household Survey, 2017
More than 90% of the total households in project affected households have toilet facilities,
majority of which are ordinary toilet type are 73.33 %.
Table 4-62: Sampled Households by type of toilets
Type of Toilet Number of HHs Percent of HHs
No Toilet 1 1.67
Pit Toilet 3 5.00
Flush Toilet 12 20.00
Ordinary Toilet 44 73.33
Total 60 100.00
Water borne diseases:
Water borne diseases such as diarrhea, dysentery, typhoid and fever are common in the project
affected wards of rural municipality. Moreover, cough and cold, gastric, eye diseases,
respiratory diseases (bronchitis), malnutrition, skin diseases, heart diseases, blood pressure and
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
101| P a g e Department of Electricity Development
tuberculosis are also recorded in the area. However, there was no record of HIV/AIDS in the
project area.
Health treatment facilities:
There are four health posts in the project affected areas. The nearest health post (with limited
health facilities) is located at Basa, which is 2-3 hours walking distance from the project intake
area and 1.5 hour from proposed powerhouse area. As per government rules, one Assistant
Health Worker (AHW), one Maternal Child Health Worker (MCHW) and one Field Health
Worker need to be engaged in each health post. However, the facilities such as staff and
medicines are inadequate most of the time in the health post.
Majority of the population (76%) prefer to go to health posts for treatment, 10 % prefer to go
to hospitals. Other traditional practices like treatment by healer (6%) are also commonly found
in the project area. Only 10% of the population prefers to go to the hospital when treatment is
not possible at the health posts.
Expenditure on health care:
In order to find out the average annual expenditure on health care of the people, the respondents
were asked how much money they spent on their family member(s) on health care in the past
one year. According to the respondents, the average annual HH expenditure on health care is
NRs 6,000, which is about 8 percent of the total expenditure of the household. It shows that
they are also conscious about health care.
(ix) Perception about the Project and Preferred Modality of Compensation
Study carried out in various locations of the project area indicate that local people have positive
attitude toward the construction of the project. However, household survey data shows that
about 86.67% households interviewed expressed their positive thoughts over the project and
the remaining 13.33 % households were unknown about the project. Expectation of jobs,
quality health services, education, availability of reliable electricity and improved physical
infrastructures were the main reasons to support the project.
Table 4-63: Distribution of Respondents by Perception about the Project
Categories Positive About project Do Not Know Total
By Location
Mapya Dudhkoshi RM-2 (Basa), 29 (93.55) 2 (6.45) 31
Mapya Dudhkoshi RM-4 & 5 (Kaku) 7 (77.77) 2 (22.23) 9
Mapya Dudhkoshi RM- 6 & 7 (Baku) 16 (80) 4 (20) 20
Total / Overall 52 (86.67) 8 (13.33) 60 (100)
Source: Field Study, 2017
Project affected household were asked to specify their preference for compensation in case
their land need to be acquired for the construction of the project. Majority of the affected
households (81.67%) expressed desires for cash compensation for the lands to be acquired by
the project while about 13.33 % households show willingness to get land for land compensation
and the rest household preferred to be rehabilitated by the developers.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
102| P a g e Department of Electricity Development
Table 4-64: Affected HHs by their preference on Modes of Compensation
Categories Cash Land for Land Rehabilitated by
developers
Total
By Location
Mapya Dudhkoshi RM-2 (Basa) 27 (87.10) 4 (12.90) 0 31
Mapya Dudhkoshi RM-4 & 5
(Kaku)
6 (66.67) 2 (22.22) 1 (11.11) 9
Mapya Dudhkoshi RM- 6 & 7
(Baku)
16 (80) 2 (10) 2 (10) 20
Total / Overall 49 (81.67) 8 (13.33) 3 (5.00) 60
(100)
Source: Field Study, 2017
The affected households use various sources and types of energy for lighting, heating/cooking
purposes. Electricity is mainly used for lighting; firewood and LP gas is used for cooking and
heating. Electricity facilities are available to all affected households and they use electricity
mainly for lighting purposes. The project affected households use firewood as major sources
of energy for cooking. Among the surveyed households, about 83.33% use firewood as only
the source of energy for cooking and 16.67% households use both firewood and LP gas as
sources of energy for cooking.
Table 4-65: Distributions of Affected Households by Types of Cooking Fuel Used
Categories Firewood
Only
Firewood & LP
Gas
Total
By Location
Mapya Dudhkoshi RM-2
(Basa)
26 (83.87) 5 (16.13) 31
Mapya Dudhkoshi RM-4 & 5
(Kaku)
7 (77.77) 2 (22.23) 9
Mapya Dudhkoshi RM- 6 & 7
(Baku)
17 (85) 3 (5) 20
Total / Overall 50 (83.33) 10 (16.67) 60 (100)
Source: Field Survey, 2017/18
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
103| P a g e Department of Electricity Development
5. ENVIRONMENTAL IMPACTS
This Chapter addresses the potential impacts likely to accrue as a result of the implementation
of the proposed DK5HPP. Based on the project details and the baseline environmental status,
potential impacts as a result of the construction and operation have been identified.
Environmental impacts of the proposed project have been identified for the project structures
and facilities covering the physical, biological, and socioeconomic and cultural environments.
The impacts associated with construction and operation of the project component roads is
discussed under physical, biological, and socioeconomic and cultural environment under
respective headings. The beneficial impacts are given in subheading 5.1 and adverse impacts
are mentioned in sub-heading 5.2.
5.1 Beneficial Impacts
The proposed Dudh Koshi-5 HPP is associated with the beneficial impacts to the project area,
region and in a large scale to the nation. Identified beneficial impacts are described below.
5.1.1 Construction Phase
i. Employment opportunities for local people and impact on local economy and skill
development
Approximately 600-800 unskilled, semiskilled and skilled workers will be employed at the
peak construction period with priority given to workers from the project affected area based on
their skills and qualifications. Construction jobs will provide cash income to bolster the local
economy, provide investment possibilities and raise the standard of living in the region.
However, as the project area is predominantly agro-pastoral, local workforces will require
some specific skill development. Once the project construction is completed, these skills will
also enable people to get employment in other similar projects.
During the construction period, workers from outside the project area will reside in the project
area for considerable period of time, since they will have good purchasing power, there will be
increased demand for different types of food, beverage and other daily necessary items. More
tea stalls, grocery shops and restaurants might be operated and/ or existing hotels will expand
and cater services. As a result of this, significant amount of cash will be channeled into the
local economy.
The impact will be direct in nature, high in magnitude, local in extent and short term in
duration.
ii. Benefits as a result of access road and pconstruction
The project requires all weather roads for the transportation of equipment and materials to the
construction site. Therefore, the project shall upgrade existing road to the project area. Further,
the project will construct about 6.1 km access road to reach to the headwork and about 7.4 km
access road to reach to the powerhouse site. Also, 1.1 km and 403 m road shall be constructed
to access the Adit-3 and surge tank respectively. Round the year maintenance of the main
access road is a direct benefit to the local communities of the project area. The improved
condition of road is envisaged to provide easy access for better education, health care and
market facilities, including agricultural extension services, communication etc. In this way, the
project will contribute in improving the road system of the project area, which will benefit not
only to the local people in the project area but also to the wards and settlements outside of the
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
104| P a g e Department of Electricity Development
project area. The impact will be indirect in nature, high in magnitude, local in extent and long
term in duration.
iii. Benefits from community and social support programs
The project has allocated 0.5% of total project cost as Community Support Program and
suggested improvement of local services like health posts, schools, drinking water and social
services. Project also support to improve water supply facilities, educational institutions, health
care institutions, etc. beforehand commencement of construction as some of these are necessary
for its construction crew as well. These programs are envisaged to help develop local
infrastructures and social services in the project impacted area helping local people to improve
their quality of life.
The impact will be direct in nature, moderate in magnitude, local in extent and long term in
duration.
iv. Benefits from implementation of environmental mitigation programs and benefit
augmentation measures
The project will implement environmental mitigation programs and benefit augmentation
measures as proposed in the EIA report. It will benefit the people of project affected area and
the whole rural municipality at large. The impact will be indirect in nature, moderate in
magnitude, local in extent and long term in duration.
v. Increase in economic activities in the project area and associated beneficial impacts
in local economy through micro-enterprise development
An expanded local market will be created by the in-migration of workers. Local residents can
take advantage of these new opportunities by expanding their existing local industries and
establishing new ones. The impact will be indirect in nature, moderate in magnitude, local in
extent and short term in duration.
vi. Benefits for Exposure of local population to new technologies and technology
transfer
The project requires professional technical persons for implementation of the construction
works. Local people who will get opportunities to work with these professionals will get
opportunities to learn knowledge and skills from the professionals. With the knowledge and
skills learned during the construction of the project, local people will be able to get employment
in similar projects elsewhere. Such knowledge and skills will be obtained, particularly in the
areas of tunnel construction, heavy equipment operation, masonry, construction of dry walls,
gabion walls and bio-engineering etc. The impact will be direct in nature, low in magnitude,
local in extent and long term in duration.
5.1.2 Operation Phase
i. Benefits to be incurred from addition of 110 MW of power to INPS
The implementation of the proposed DK5HPP will generate 618.80 GWh of hydroelectricity
per year and feed into the national grid and simultaneously, will help to improve the energy
situation. This will be big input in the national level power planning as the country is facing
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
105| P a g e Department of Electricity Development
heavy power shortage. Moreover, Hydroelectric being clean renewable energy will also protect
the environment.
The impact will be direct in nature, high in magnitude, regional in extent and long term in
duration.
ii. Changes in local economic activities
With the project in their background, local people can involve in business supplying groceries
and equipment needs of the project and its resident workers. Additionally, more reliable
electricity supply will encourage small and medium scale industries based on local resources.
These will have positive impact on local economy. The impact will be indirect in nature,
moderate in magnitude, local in extent and long term in duration.
iii. Changes in micro and macro economy
With the increase in the economic activities, the local area micro economy will be drastically
changed. Currently people are practicing subsistent agriculture for livelihood. There will be a
shift in the agriculture practice from subsistence to commercial farming. Many people will
establish cottage industries based on local resources as electrical energy will be available for
the industries. This will bring a substantial change in the macro-economy of the entire district.
Dependency on agricultural activities will be minimized by the introduction of industrial and
service-oriented enterprises in the local area. The impact will be indirect in nature, low in
magnitude, local in extent and long term in duration.
iv. Sharing of electricity royalty to concerned state and concerned local level
As per the provisions in the Intergovernmental Fiscal Arrangement Act, 2074, 50 % of the total
royalty obtained will be allocated to the Government of Nepal, 25% to the concerned state and
25% to the concerned local level. The impact will be direct in nature, moderate in magnitude,
regional in extent and long term in duration.
5.2 Adverse Impacts
Considering the project activities, environmental impacts have been assessed as per the
National Environmental Impact Assessment Guidelines 1993 for magnitude, extent, and
duration. Identified and predicted environmental impacts have been evaluated to know the level
of significance. The following sub-sections include the impacts identified or predicted.
5.2.1 Physical Environment
(i) Construction Phase
i. Change in Land Use
Areas under different land use patterns will be required for the project construction. In the case
of DK5HPP, forest area, private land and river banks will be utilized for the project
construction. About 25.834 ha of land is planned to be acquired temporarily and permanently
for project infrastructure construction. Out of the total land to be acquired, project requires
24.324 ha permanently for the construction of different project component. The topography of
the project area will be changed since the land use will be changed in the area. The local
topography of cropland and forested land will be replaced by infrastructure of project like
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
106| P a g e Department of Electricity Development
intake, power house, and staff quarters. Impact on the topography will also occur by the
disturbance of fragile slopes, clearance of land and disposal of muck.
The impact will be direct in nature, moderate in magnitude, site specific in extent and long
term in duration.
ii. Possible Glacier Lake Outburst Flood (GLOF) and associated impacts
The impacts of potential outbursts of glacial lakes upstream of the Dudh Koshi are expected to
be significant. However, GLOFs occur in many different forms and can vary in character from
catastrophic to insignificant and unrecorded. The downstream impact of any lake outburst
depends on the size of the lake, depth of the lake, type of dam of the lake, distance from the
project, nature of dam break, slope of the river channel downstream, possible obstruction to
high floods by narrow cross sections downstream and other factors. A major lake outburst may
release enormous amounts of stored water that, together with the debris flow, can causes
serious flood damages downstream along the river channel. Impacts of GLOFs, unrelated to
the Project, are expected to be from moderate to extreme in magnitude, all along the river and
for a short duration whilst the Project will serve to reduce damage due to relocation of
infrastructure, prior warning when events do happen and implementation of risk reduction
measures.
iii. Landslides and soil erosion
Construction activities will include land excavation, slope cutting, grading, use of heavy
equipment etc, which will change the existing slope of land. So these activities on slopes may
induce slope failure and mass wasting. Use of explosives for excavation during the construction
of tunnel will disturb the stable rock and rock fall may occur. Blasting will cause vibrations
which may initiate landslides.
The clearing activities of forest and agricultural land for the construction of project structures
will make the soil surface loose. So, soil erosion may occur during the rainy season especially
in the steep slopes. The eroded particles may be transported to the river by monsoon runoff and
exacerbate sedimentation in river.
The impact is direct, moderately significant, site specific in extent and short term in duration.
iv. Possible impacts on spring sources above and below along the tunnel alignment
Experiences from previous studies showed that construction of tunnel can dewater the land
area above the level of tunnel within an influence area of hundred meters from the right of way
of the tunnel alignment. Dewatering or draining of the groundwater above the level of tunnel
is high in the initial phase of construction and again re-established after many years of
construction. These water sources are likely to be impacted by the tunnel excavation works.
Provided these spring water sources are drained to the tunnel, the population depending upon
these sources will have to travel long distance for the drinking water purpose and the
agricultural products based on the irrigation water from these sources will not be available to
the local communities with implication on livelihood. The impact will be moderate on the
communities’ dependent on these water sources, site specific and for a long-term in duration.
v. Impact on river morphology
The diversion of water through the tunnel will have an impact on the river flow and
morphology. The river will divert up to 52.46m3/s of flow through the tunnel to the powerhouse
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
107| P a g e Department of Electricity Development
located downstream. Therefore, the river stretch of about 7.9 km between the proposed intake
and powerhouse site can be classified as a dewatered reach.
The basin hydrology and flow regime of Dudh Koshi will not be impacted by the Project during
the construction phase. Shortly downstream of the weir construction site, the river will be
running in its natural state until dam closure and diversion to the power station commences. A
more concentrated river course along the left bank will therefore be established during
construction and the braided pattern will disappear. Possible extraction of large boulders from
the riverbank for construction purposes may have some impact on the river morphology in the
long run. The impact will be direct in nature, moderate in magnitude, site specific in extent and
short term in duration.
vi. Generation of spoils and spoil disposal related issues
The tunnel excavation will be generating about 592,900 m3 of the muck. Management of the
large volume of the wastes would be challenging. Improper disposal of the large volume of
spoil may result in destruction of productive land and vegetation, increased turbidity of river
water, increased dust in project environment, adverse impact on aquatic life, and ugly scars in
the landscape. This impact is predicted to be direct in nature, moderate in magnitude, short
term in terms of temporal coverage and site-specific in terms of spatial coverage.
vii. Water quality management and waste water disposal issues
Changes in the water quality of surface water bodies are likely to occur due to construction
activities. In major stretches of the Dudh Koshi, there is limited space available on both river
banks, and as most of the construction activities will be located close to the river, there is an
increased possibility of water quality deterioration.
There will be a temporary increase in the turbidity and sediment content of the river due to
unavoidable disturbance of river beds and banks and likely accidental spills of sediment
producing material in the river. In addition, potential uncontrolled spillage of petrochemicals,
oils, paints, cement slurry, dynamite residue and hazardous substances may also have an
adverse impact on the river water quality. The impacts will be felt most during the dry season.
Besides this, some wastewater from labour camps are likely to pollute the water
microbiologically and add inorganic elements like carbon, nitrogen and phosphorus. Such
pollution will take place in spite of project efforts to contain discharges and limit the extent as
far as possible. The discharge of the camps’ effluent into the water bodies could be significant
with far reaching implications to the water users downstream, but mitigation measures to
prevent this are included in the project. Improper management of waste, both solid and liquid,
generated by the people directly or indirectly involved in the project will probably take place,
and increased BOD and Fecal coliform in Dudh Koshi can be expected to a certain degree. The
potential for adverse impacts is nevertheless short-term in nature.
The first flushing of the tunnel system will result in a sudden discharge to the river water loaded
with toxic chemical residue from dynamite used in blasting operations. Such events have been
known to result in massive fish kills when allowed to happen uncontrolled and at an
unfavorable time. Unless properly mitigated such impacts will be severe although short term
in nature.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
108| P a g e Department of Electricity Development
The impact will be indirect in nature, moderate in magnitude, short term in duration and local
in terms of spatial coverage.
viii. Loss of fertile top soil
Total of 4.166 hectares of agricultural land will be used by the project. The top soil, estimated
to be about 16650 m3, in the fertile land will be destroyed if not removed before construction
and cannot be used for cultivation.
The impact will be direct in nature, low in magnitude, site specific in extent and short term in
duration.
ix. Clogging of natural drainages
Excavation works results in change in existing topography. Stockpiling of construction
materials and disposal of spoil or muck on the river banks might create disturbances to local
natural drainage that might appear during rainy season. In this way, the construction works
have an adverse impact on natural drainage system of the project area.
This impact is indirect in nature, low in magnitude, local in extent and short-term duration.
x. Noise and vibration related impacts
Construction activities and operation of diesel plants, vehicles, ventilators, cement batching
and aggregate crushing plants at various project sites will generate noise and vibrations. The
increase in ambient noise levels will have pronounced impacts on settlements in close
proximity to noise sources at the headworks, powerhouse site and some sections of the access
road. Blasting will generate the loudest noise levels, producing short lived noise in the range
of (100-140 dBA) near the source. The impact is expected to be moderate in magnitude and for
short durations. Strong vibrations and overpressure can damage nearby houses and other
structures. The main sites of vibration generation will be at blasting sites, tunnel portals and
entrances, adits and intake, etc.
The impact is direct in nature, moderate in magnitude, site specific in extent and short term in
duration.
xi. Issues relating haphazard stockpiling of construction material
The project has designated separate areas for the stockpiling of construction materials such as
sand, aggregates, iron rods, steel frames, cement, etc for the project construction period.
However open and haphazard stockpiling is a potential to degrade the aesthetic beauty of the
stockpiling areas. During the construction phase, there will be significant quantity of
construction materials such as gravels, aggregates, bricks, cement, etc. around the construction
area. Seepage and leakages from the stockpiled construction materials can directly impact soil
and water quality of the river. Additionally, if not properly managed, the beauty of local
topography might be affected. The impact will be direct in nature, low in magnitude, site
specific in extent and short term in duration.
xii. Issues relating to generation of solid waste and their management
During the construction phase large number of labors will be required so that there might
establish the camp sites for labor and construction yard. Solid waste will be generated from the
camp site and construction yards. This will cause the environmental problem in and around the
camp site if not managed properly. Both organic and inorganic form of wastes will be generated
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
109| P a g e Department of Electricity Development
due to construction activities and also from camps and housing areas. In construction sites the
construction wastes like mucks, tins, smaller scraps, empty sacs will accumulate. The rubbishes
and garbage from the camps and local shops in the project areas will also increase. The project
area is literally free from solid waste at present.
The impact is indirect, moderate in magnitude, site specific in extent and short-term in
duration.
xiii. Air pollution related issues
During construction period, the activities such as transportation of man and material,
excavation, blasting, use of heavy equipments and operation of crushing plant will generate
dust and vehicular emission. This impact on air quality will however be short in duration and
for the most part be limited to the project site. The impact will be most severe at weir site,
powerhouse site, along the access road, crushing plant, concrete mixing sites and the spoil
disposal area. Specially, when air movement is small during light winds, dust particles, aerosols
and noxious gases may build-up in construction area. However, this will be periodically washed
away or diluted and dispose particularly in the rainy season.
Other potential impacts on air quality are unpleasant odor due to improper management of
sewage and solid waste and indoor smoke pollution due to cooking activities. Because, during
construction period, there will be large number of construction worker in the project area.
Increased dust in the air will impair the health of people through increased incidence of Acute
Respiratory Infections (ARI), wheezing, shortness of breath and dust allergies. Prolonged
exposures to dust can cause in respiratory diseases like Asthma and Bronchitis.
However, the impact will be direct in nature, low in magnitude, local in extent and short term
in duration.
(ii) Operation Phase
i. GLOF and associated impacts
As a GLOF event could in theory happen any time, with particular risks during the monsoon
season, there is in principle no difference between construction and operation phase of the
project. However, vulnerability of people and property is higher during construction due to the
number of people being exposed to the dangers of GLOF events. Impacts of GLOFs, unrelated
to the project, are expected to be from moderate to extreme in magnitude, all along the river
and for a short duration.
ii. Impacts on river flow regime downstream of diversion weir (dewatered stretch of
Dudh Koshi River) and possible microclimatic changes
The diversion of Dudhkoshi River in intake site will eventually result in some impacts on the
downstream dewatered zone. Low volume of water is likely to increase the temperature in the
dewatered zone. The change in flow during wet season is not considered significant but in dry
period (7 months) the flow will be significantly reduced which causes adverse impact on river
morphology. This will be a residual impact until the project will be in operation.
There will be some change in the water quality in the dry season in the dewatered stretch of the
river between weir and tailrace. Because of the reduction of the flow discharge and contribution
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
110| P a g e Department of Electricity Development
of nutrients, there will be growth of blue filamentous algae in the dewatered stretch of the river.
The dissolved oxygen level will slightly drop while the water temperature will slightly increase.
The impact will be direct in nature, moderate in magnitude, local in extent and long term in
duration.
iii. Land submergence created by 18.1m high diversion weir and associated impacts
The diversion structure and creation of reservoir in front of the diversion structure in the
operation phase divide the existing river morphology into distinct three sections as under:
• Undisturbed section upstream the upper limit of the reservoir
• Reservoir section of about 50 m length
• Dewatered section of about 7.9 km length
As the existing aquatic life are co-existing with the undisturbed river morphology for ages will
find difficulties to sustain their life cycle in the changed morphological and water conditions
of the changed river stretches. Major changes in aquatic life will occur in the reservoir section
and in the dewatered section through November to May every year.
The impact will be direct in nature, low in magnitude, local in extent and long term in duration.
iv. Management/final disposal of solid waste and wastewater (both black water and grey
water)
Solid waste pollution in and around project area during operation phase will be very low as
compared to that during construction period. The solid waste generation sources will reduce
drastically as all of the construction work force will leave project area after project
construction. However, some amount of solid waste may be generated from the project
permanent camp and office.
This impact is indirect in nature, low in magnitude, site specific and long term in duration.
v. Noise and vibration
During operation period, the impact due to noise is expected to exist in the powerhouse due to
the running of turbines. As the powerhouse is a closed system and is located away from the
settlements, the impact of noise is confined to the powerhouse operating workers only. A
minimal amount of impulse noise will be generated due to the movement of vehicles along the
road in the project area. However, as during operation phase the vehicular movement is too
infrequent, the noise impact is insignificant.
The noise impact is direct in nature, low in magnitude, site specific and short term in duration.
5.2.2 Biological Environment
(i) Construction Phase
i. Loss of forest area
Total forest land required by the project is 15.10 ha. The project will require 13.747 ha of CF
area permanently and 1.357 ha of CF land temporarily. The clearance is required for
construction of weir, approach canal, gravel trap and desander basin, the access road to
headworks, adit portals, spoil disposal sites, access road to camp sites, mechanical yards and
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
111| P a g e Department of Electricity Development
aggregate crushing plants, mechanical workshops, adits and other project components (Table
5-1). Impact is of direct in nature, moderate magnitude, local extent and long-term duration.
Table 5-1: Community Forestwise Forest Area Loss by Project components
SN Project Component Forest Area
(Ha) Community Forest
1 Headworks (weir)
1.1 Pondage area 1.4204 Rapcha/Bhirkuna/Dudhkoshi CFs 1.2 Intake 0.0788 Rapcha CF 2 Adits and Portal
2.1 Adit-1 Portal (Access tunnel to
desander) 0.0973 Rapcha CF
2.2 Adit-2 Portal (Desander Flushing) 0.0962 Rapcha CF 2.3 Adit-3 Portal (Construction Adit) 0.0630 Lemchikharka
2.4 Adit-4 Portal (Valve chamber
Access Portal) 0.0363 Bijai CF
2.5 Adit-5 Portal (Powerhouse Access
Tunnel) 0.0994 Bijai CF
2.6 Tailrace Outlet Portal 0.1113 Bijai CF 3 Surge tank 0.0707 Bijai CF 4 Disposal Sites 4.1 SD#1 5.5238 Rapcha CF 4.2 SD#2 1.1275 Lemchikharka CF 4.3 SD#3 0.7064 Lemchikharka/Bijai CFs 5 Borrow and Quarry Sites 5.1 CMS#1 0.0070 Bhirkuna CF 5.2 CMS#2 0.2000 Bhirkuna CF 5.4 CMS#4 0.4000 Rapcha CF 5.5 CMS#5 0.5029 Rapcha CF 6 Project Road Access Road at headwork Area 0.3891 Rapcha CF Access Road at powerhouse Area 0.9597 Bijai CF
Access Road to SD#2/Surge
Tank/Powerhouse 0.8326 Basa CF
Access Road to SD#2/Surge
Tank/Powerhouse 1.7771 Lemchikharka
7 Crusher, Mechanical Workshop
and Material Storage
7.1 CR, MS and MWS-1 0.1240 Rapcha CF 7.2 CR, MS and MWS-2 0.1240 Bijai CF 8 Access Road to Camp site 8.1 Camp Site 1 (Labor) 0.2144 Rapcha CF 8.2 Camp Site 2 (Labor) 0.1434 Bijai CF Total 15.104
ii. Impacts on forest vegetation and overall forest diversity
Estimated total number of seedlings is 53185, sapling 1180, poles 2148 and trees 1366 needs
to be cut down for various proposed project structures. Due to felling of these trees, 560 m2
tree basal area, 11379 m3 tree standing volume, 4776 m3 timber volume, 17702 m3 fuelwood
and 13497475 kg tree biomass will be lost. Total value of lost timber is estimated to be NRs.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
112| P a g e Department of Electricity Development
51,492,308 and for fuelwood NRs. 14,145,432. The impact will be direct in nature, moderate
in magnitude, site specific in extent and long term in duration.
Table 5-2: Standing Tree Loss due to the Proposed DK5HPP
SN Project Structure Regeneration (No) Number of Standing Trees (No)
Pole
s
Small
Saw
Timber
Large
Saw
Timber
Total 1 Headworks (weir) Seedling Sapling
1.1 Pondage area 7211 104 202 76 68 347
1.2 Intake 400 6 11 4 4 19
2 Adits and Portal
2.1 Adit-1 Portal (Access tunnel to desander) 494 7 14 5 5 24
2.2 Adit-2 Portal (Desander Flushing ) 488 7 14 5 5 23
2.3 Adit-3 Portal (Construction Adit ) 84 7 9 5 1 15
2.4 Adit-4 Portal (Valve chamber Access Portal) 61 3 5 1 0 6
2.5 Adit-5 Portal (Powerhouse Access Tunnel) 60 2 12 4 0 17
2.6 Tailrace Outlet Portal 67 3 14 5 0 19
3 Surge tank 42 2 10 2 1 12
4 Disposal Sites
4.1 SD#1 28044 404 786 297 266 1349
4.2 SD#2 1503 122 169 85 19 272
4.3 SD#3 1187 67 95 18 7 120
5 Borrow and Quarry Sites
5.1 CMS#1 36 1 1 0 0 2
5.2 CMS#2 1015 15 28 11 10 49
5.4 CMS#4 2031 29 57 22 19 98
5.5 CMS#5 2553 37 72 27 24 123
6 Project Road
6.1 Access Road at headwork Area 1975 28 55 21 19 95
6.2 Access Road at powerhouse Area 576 23 120 40 4 164
6.3 Access Road to SD#2/Surge
Tank/Powerhouse 1110 90 125 62 14 201
6.4 Access Road to SD#2/Surge
Tank/Powerhouse 2369 193 267 133 30 429
7 Crusher, Mechanical Workshop and
Material Storage
7.1 CR, MS and MWS-1 629 9 18 7 6 30
7.2 CR, MS and MWS-2 74 3 15 5 1 21
8 Access Road to Camp site
8.1 Camp Site 1 (Labor) 1089 16 31 12 10 52
8.2 Camp Site 2 (Labor) 86 3 18 6 1 24
Total 53185 1180 2148 853 513 3513
Table 5-3: Tree Basal Area, Volume and Biomass Loss Due to Proposed DK5HPP
SN Project Structure BA
(m2) SV
(m3) TV
(m3) FV
(m3) TB (Kg)
1 Headworks (weir)
1.1 Pondage area 77.28 1473.71 656.41 2206.74 1761113.55
1.2 Intake 4.29 81.76 36.42 122.43 97707.12
2 Adits and Portal
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
113| P a g e Department of Electricity Development
2.1 Adit-1 Portal (Access tunnel to desander) 5.29 100.95 44.96 151.16 120636.78
2.2 Adit-2 Portal (Desander Flushing ) 5.23 99.81 44.46 149.45 119272.96
2.3 Adit-3 Portal (Construction Adit ) 0.68 25.23 8.94 30.88 26886.18
2.4 Adit-4 Portal (Valve chamber Access Portal) 0.72 6.94 0.66 16.21 11007.72
2.5 Adit-5 Portal (Powerhouse Access Tunnel) 0.72 21.33 2.61 97.49 27909.72
2.6 Tailrace Outlet Portal 0.80 23.88 2.93 109.13 31241.20
3 Surge tank 1.40 13.51 1.29 31.56 21434.73
4 Disposal Sites
4.1 SD#1 300.51 5730.97 2552.65 8581.58 6848622.15
4.2 SD#2 12.15 451.48 160.00 552.62 481179.79
4.3 SD#3 13.96 135.00 12.86 315.41 214200.25
5 Borrow and Quarry Sites
5.1 CMS#1 0.38 7.26 3.23 10.87 8678.91
5.2 CMS#2 10.88 207.50 92.42 310.71 247968.72
5.4 CMS#4 21.76 415.00 184.85 621.43 495937.45
5.5 CMS#5 27.36 521.74 232.39 781.25 623483.88
6 Project Road
6.1 Access Road at headwork Area 21.17 403.71 179.82 604.51 482436.79
6.2 Access Road at powerhouse Area 6.92 205.95 25.24 941.27 269460.20
6.3 Access Road to SD#2/Surge Tank/Powerhouse 8.97 333.40 118.15 408.10 355335.20
6.4 Access Road to SD#2/Surge Tank/Powerhouse 19.15 711.57 252.17 870.99 758386.11
7 Crusher, Mechanical Workshop and Material
Storage
7.1 CR, MS and MWS-1 6.74 128.61 57.28 192.58 153687.30
7.2 CR, MS and MWS-2 0.89 26.60 3.26 121.58 34804.88
8 Access Road to Camp site
8.1 Camp Site 1 (Labor) 11.66 222.45 99.08 333.09 265828.67
8.2 Camp Site 2 (Labor) 1.03 30.77 3.77 140.62 40254.86
Total 560 11379 4776 17702 13497475
Note: BA=Basal Area; SV=Standing Volume; TV=Timber Volume; FV=Fuelwood Volume and TB=Total Biomass
Source: Field Survey, 2017/2018
Table 5-4: Valuation of lost timbers and fuelwood
S
N Scientific Name
Timber Volume
(CFT)
Fuelwood Volume
(Chatta)
Valuation in NRs.
Timber Fuelwood
1 Alnus nepalensis 35636.46 199.72 8,018,203.45 2,296,815.57
2 Bauhinia variegata 1.79 20,635.16
3 Boehmeria rugulosa 0.14 1,620.74
4 Bridelia retusa 0.80 9,154.70
5 Casearia graveolens 1.35 15,574.38
6 Cassine glauca 0.50 5,787.10
7 Castanopsis tribuloides 0.09 1,021.07
8 Chekrasi 3215.13 14.43 723,404.02 165,976.21
9 Cinnamomum tamala 0.00 1.11 12,756.83
10 Elaeagnus parvifolia 0.00 0.15 1,762.39
11 Engelhardia spicata 0.00 615.38 7,076,825.92
12 Eurya cerasifolia 0.00 0.14 1,638.33
13 Ficus benghalensis 0.00 0.12 1,369.98
14 Ficus religiosa 0.00 0.61 7,045.63
15 Homalium napaulense 0.00 0.61 7,004.63
16 Juglans regia 6026.67 26.24 2,109,334.95 301,775.00
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
114| P a g e Department of Electricity Development
S
N Scientific Name
Timber Volume
(CFT)
Fuelwood Volume
(Chatta)
Valuation in NRs.
Timber Fuelwood
17 Lyonia ovalifolia 0.00 0.53 6,124.10
18 Macaranga pustulata 2729.38 18.53 477,642.03 213,062.90
19 Maesa chisia 0.00 0.33 3,804.91
20 Malami/Anau Kath 16315.65 73.24 3,671,022.11 842,283.99
21 Mallotus tetracoccus 0.00 1.82 20,968.59
22 Olea glandulifera 0.00 3.15 36,238.55
23 Pinus roxburghii 16209.36 47.11 5,673,276.09 541,756.93
24 Quercus lanata 0.00 0.01 0.00
25 Rhododendron
arboreum 0.00 0.20 2,313.27
26 Rhus sp. 0.00 0.05 559.43
27 Rhus wallichii 0.00 0.21 2,468.16
28 Sapium insigne 0.00 68.47 787,402.30
29 Schima wallichii 82037.25 130.34 28,713,038.94 1,498,958.06
30 Syzygium cumini 5982.90 13.55 2,094,013.86 155,824.75
31 Terminalia alata 35.35 7.71 12,373.09 88,627.04
32 Trichilia connaroides 0.58 6,724.73
33 Wendlandia puberula 1.00 11,551.19
Total 1,681,88.16 1230.04 51,492,308.55 14,145,432.55
iii. Impact on aquatic life including fishery resources of the Dudh Koshi River
The undisturbed Dudhkoshi aquatic habitat will be altered by construction of weir at the
headworks. Moreover, the aquatic habitats would be disturbed due to extraction of river bed
materials for construction purpose at different stretches. Contamination of river by spillage of
chemical as well as solid wastes of different kind have a negative impact on the aquatic fauna
including fishes. There are no fishery dependent households in the project area as the fish catch
is too low. However, the above-mentioned activities would affect upon 4 different species of
fishes those are found in the Dudhkoshi. This impact is predicted to be direct nature, of
moderate magnitude, site-specific in extent and short term in duration.
iv. Possible impacts on protected species of flora and fauna
Six species of plant of conservation significance are to be affected due to the implementation
of the proposed Dudh Koshi-5 HPP. The affected species are abundant in the other project not
affected areas within the project rural municipality and other areas also.
The impact will be direct in nature, low in magnitude, site specific in extent and long term in
duration.
Table 5-5: Total Loss of Rare Endangered/Endemic Floral Species
SN Protection
Category Name Tree Pole Saplings Seedling
Remarks
2 GON
Protected
Lichen Abundant
3 Juglans regia 52 0 0
5 CITES/IUCN
Cyathea spinulosa 30 individuals
6 Ceropegia pubescens Abundant
Note: * Listed in IUCN list, ** Listed in IUCN and CITES list
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
115| P a g e Department of Electricity Development
v. Impact on wildlife and avian population
Although about 15.104 ha of the forest area will be cleared for the construction purpose, there
are no prime habitat of the wildlife. The forest area in the community forest are also too less
used by the bigger wildlife as their habitat as it is on the edge of the forest closer to the foot
trails with movement of people. The impacted forest areas are occasionally used by the wildlife
as feeding ground. Hence, impact on wildlife due to habitat loss is less prominent. Direct loss
of wildlife by the land use change is not expected.
This impact is predicted to be indirect in nature, of low magnitude, local and short term in
duration.
vi. Impact on Non-Timber Forest Products/MAPs
Bantarul (Dioscorea deltoidea), Amala (Phyllanthus emblica) and bankurilo (Aesparagus
racemosus) are the major NTFPs that would be affected due to clearing activities during project
construction. The affected NTFPs are abundant in the other parts of the project area as well as
outside the project area also.
The impact will be indirect in nature, moderate in magnitude, site-specific in extent and short
term in duration.
vii. Possible Risk of forest fire
In and around the construction area, there will be many types of fuel that create fire hazards,
such as slash accumulation of timber cutting, dryden grass and debris accumulation, large
accumulation of flammable leaves, dead trees, dry bushes etc., as well as gasoline for vehicles
and machinery. Fire might be set accidentally due to inadvertently thrown cigarette stub and
left campfire or deliberately by some ruffian. Small fire can turn huge forest fire. Improper
garbage disposal and improper storage of inflammable gases and liquids at the construction site
can aggravate the situation.
The impact will be indirect in nature, low in magnitude, local in extent and short term in
duration.
viii. Disturbance to wildlife due to construction activities
Once the construction starts the construction related activities such as excavation works,
drilling and blasting of rocks, movement of vehicles, operation of heavy machineries etc will
disturb the wildlife and birds around. The wildlife population such as the Rhesus monkey,
Langoor, porcupine etc. may get decreased due to the annoyance to the noise. Decrease of
population of wild animals such as monkeys and porcupine have a positive effect also as these
are the major problematic animals for crop depredation of the local farmers. However, the wild
animal population is expected to increase after the construction work is over. The impact will
be direct in nature, low in magnitude, site specific in extent and short term in duration.
(ii) Operation Phase Impacts
i. Impacts on fish and aquatic fauna and their habitat
Barrier effect: The presence of weir will limit access of migratory fish species to some
upstream spawning areas. The diversion of the Dudh Koshi river water creates the barrier for
the upstream and downstream migration of mid range migratory fish species. Nevertheless, in
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
116| P a g e Department of Electricity Development
a long-term view, this prevention of upstream fish migration could reduce fish access to
upstream and downstream breeding and rearing habitats.
However, the effect is expected to be of minimum significance due to following reasons:
• Only a small portion of snow trout use upstream habitats for spawning,
• Several spawning sites are available downstream of the intake site,
• Low height of weir (18.1 m above natural bed rock),
• The project is a RoR type,
• A minimum flow of 10 % of the lowest mean monthly flow (1.48 m3/s) on the river
shall be maintained, and
Diversion of water: Water diversion to the tunnel will reduce the flow in the Dudh Koshi River
particularly in the section between the intake and powerhouse site. Flow reduction will affect
spawning and breeding of fishes, particularly during the dry season (i.e. March and April).
However, the availability of many downstream spawning and breeding grounds will minimize
this impact. Reduced flow will also increase the water temperature and reduce food availability,
thus causing an overall decline in fish productivity. The low flow will also affect the fish
population as fishermen can more easily exploit fish in this area.
The impact is direct, moderately significant, local in extent and long-term in duration.
ii. Change in composition of fish fauna in upstream section of diversion weir
One of the largest upstream impacts of weir construction (both storage and Run of the river
type) is submergence. The area flooded by the reservoir is a strong proxy variable for many
environmental and social impacts (Goodland, 1997). The argument that the loss of riverine
habitat associated with impoundments is balanced by the creation of lake-habitat is somewhat
deceptive as natural lakes and wetlands often function in very different ways. The water levels
maintained in large impoundments are generally not constant as a result of which the
productive littoral areas are rarely sustained. Moreover, as compared to natural stream levels,
water levels in these impoundments are usually significantly elevated, flooding part of the
terrestrial–aquatic interface and creating a new littoral zone with steeper banks, less complex
aquatic habitat, and different physicochemical conditions for aquatic plants and animals
(Walker and others 1992).
The impact will be direct in nature, moderate in magnitude, local in extent and long term in
duration.
iii. Possible disturbance to the wildlife activities
Habitat disturbances: Placement of facilities such as the housing camps and other project
features will create some disturbances. Operation of these structures may create habitat
disturbances and interrupt the regular movement of fauna. However, most of the area's fauna
is confined to the uphill-forests of villages.
The impact will be direct in nature, low in magnitude, site specific in extent and long term in
duration.
Sudden release of water: The sudden release of water to the downstream may flood and wash
away the wildlife along the flow direction when the wildlife visits the downstream river banks
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
117| P a g e Department of Electricity Development
for drinking purposes. According to local respondents, however, wildlife movement is not
frequent near the river banks.
The impact is direct, moderate in magnitude, site specific in extent, and long-term in duration.
iv. Possible Forest Fires
As the project area is in the forest area and /or close by the forest area, there is likelihood of
incidence of the forest fire caused by workforce indiscipline. The grass species and pine trees
present in project construction sites are vulnerable to fire, especially during the dry season.
Even a small fire in the form of cigarettes, buds and match stick used by the construction crew
could be a crucial factor for fire hazard. Likewise, the leakage of fuel from vehicles could also
be the cause of fire. The forest fire could create a big fire hazard affecting the whole region.
The impact will be indirect in nature, low in magnitude, local in extent and short term in
duration.
5.2.3 Socioeconomic and Cultural Environment
(i) Construction Phase
i. Land acquisition and Land compensation related issues
An estimated land area of about 25.834 ha is required for construction of the project
components and provisioning for project facilities of which 24.324 ha will be required
permanently for project component construction and the remaining 1.51 ha will be required
temporarily (for quarry, borrow and spoil disposal sites). Out of the 24.324 ha land to be
permanently acquired, 4.033 ha is cultivated land and 13.747 ha is community forest land. For
temporarily leased land, 0.133 ha is cultivated, 1.357 ha is forest, and 0.01 ha is river and flood
plain. The permanent structure of the project will be constructed in the permanently acquired
land and temporary project ancillaries will be constructed in leased land.
The impact is direct, moderate in magnitude, local in extent and long-term in duration.
Table 5-6: Land required for construction of the project
Project
component
Type of land (ha)
River
flood
plain
Land
acquisition
type (ha) Total
(ha)
Forest Cultivated Barren Temp Perm
Govt. CF Govt. Pvt. Govt. Pvt.
Govt.
(Land
Reform)
Pvt.
Headworks 1.499 5.333 √ 6.832
Adit Portal
Area
0.392 √ 0.392
Surge Shaft
and
penstock
pipe Area
0.071 √ 0.071
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
118| P a g e Department of Electricity Development
Project
component
Type of land (ha)
River
flood
plain
Land
acquisition
type (ha) Total
(ha)
Forest Cultivated Barren Temp Perm
Govt. CF Govt. Pvt. Govt. Pvt.
Govt.
(Land
Reform)
Pvt.
Powerhouse
and
Switchyard
0.111 √ 0.111
Quarry
Area
1.109 0.02 √ 1.129
Disposal
Area
7.358 1.211 √ 8.569
Access road 4.316 3.993 √ 8.309
Camp Area
(Engineer’s)
0.04 √ 0.04
Camp Area
(Labor’s)
0.133 √ 0.133
Crusher and
batching
area
0.248 √ 0.248
Total (ha) 15.104 4.166 6.564 25.834
ii. Loss of community forest resources and compensation related issues
The project will occupy about 15.104 ha of community forest land belonging to 7 Community
Forests in the project area. Though the scale of the impact is low, the project activities will
contribute to loss of trees and vegetation which could provide timber, fodder and fuelwood to
the CF user households. This impact is predicted to be direct in nature, of moderate magnitude,
local and long-term duration.
iii. Loss of agricultural land and crop production
Utilization of agricultural lands for different project features will decrease the agricultural
production in the area. Furthermore, possible diversion of labour from agricultural practices
into project construction activities may result in lower seasonal yields causing additional food
shortages in the area. As per local production trends, about 32.89 tons of paddy, the same
amount of wheat and approximately 9.73 tons of maize is expected to be lost in annual
production due to acquisition of agriculture land. Thus, acquisition of land will also have direct
impact on agriculture production and economic condition of the local people.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
119| P a g e Department of Electricity Development
With the implementation of the proposed project, there will be loss in annual production of
agricultural products as the project will be acquire temporary the agricultural lands in form of
Khet and Bari for the quarry and disposal sites. Estimated loss of major crops and its valuation
is provided in Table 5.7.
Table 5-7: Annual loss of agricultural production and their valuation
S. N. Crop Annual loss in production
(Ton)
Estimated
Valuation in NRs.
1 Paddy 32.89 105,248.00
2 Wheat 32.89 111,826.00
3 Maize 9.73 34,055.00
4 Millet 1.56 7,488.00
5 Buckwheat 1.80 10,080.00
6 Potato 22.86 80,010.00
7 Mustard 0.50 10,000.00
8 Seasonal vegetables 1.12 14,560.00
Total 373,267.00 Source Field Survey 2017/18
Note: Market Price 2018, Paddy= 3200/Ton, Wheat= 3400/T, Maize= 3500/T, Millet= 4800/T,
Potato= 3500/T, Buckwheat= 5600/T; Mustard= 20000/Ton; Vegetables= 14,560/Ton
The impact will be direct in nature, moderate in magnitude, site specific in extent and long
term in duration.
iv. Pressure on existing facilities, services and resources of the project area
There will be increased pressure in social service and facilities due to the migrant work force
and outsider’s population. Apart from the migrant workforce, during construction period there
may be influx of outsider population aiming to make trades and businesses in the project area.
Such outsiders may come along with their families. In this way, the population of a relatively
smaller project area can become crowded with addition of the outsiders. The addition of the
outsider population creates pressure in social service providing institutions in the area.
Experience of hydropower projects construction in Nepal, reveals pressure on the social service
institutions particularly educational facilities, health services, water supply systems,
administrative services, local law and order maintaining institutions, telecommunication
services, local markets and supply institutions and above all the sanitation management of the
area. The implication is shortages in rooms, benches, teachers in the nearby schools; shortages
of medicine, and medical personnel in nearby health posts; shortages in water supply; increase
in thefts, quarrels over resources with a burden to local administration and law and order
institutions; price inflation of local as well outside market commodities; and above all increase
in solid waste, human waste and degradation of the overall sanitation status of the area. The
impact will be indirect in nature, moderate in magnitude, site specific in extent and short term
in duration.
v. Possible interference with village trails
Interference with local village trails as an impact is predicted to be of indirect in nature, low
magnitude, local in extent and for short term duration.
vi. Occupational health and safety related issues
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
120| P a g e Department of Electricity Development
The construction activities such as blasting, using heavy equipment and working in the river,
tunnel and on steep slopes, may cause accidents and injuries. The most common injuries that
might occur are due to accidental falls from scaffoldings or other structures, injuries due to
falling objects such as rocks or other construction equipment, collapse of tunnel or other
excavations, traffic accidents and drowning. The victims will most probably be construction
worker although injuries to local people arealso possible. Similarly, construction practice
without use of Personal Protective Equipment (PPE) like glove, boot and helmet results into
the minor accidents. Health hazard may also occur due to gases emission while constructing
tunnel. Work related injuries and vehicle accidents are the likely impacts predicted due to
implementation of the proposed project.
The impact will be direct in nature, high in magnitude, site specific in extent and short term in
duration.
vii. Issues relating to public health and sanitation and as well as public safety
Public safety during construction phase is also an issue of concern. People unknowingly can
get into accidents during blasting operations. Also, the spilled chemical, hazardous explosive
materials, sharp construction materials pose threat to public safety unless adequate awareness
is provided and strict regulations are formulated.
The impact will be indirect in nature, low in magnitude, site specific in extent and short term
in duration.
viii. Socio cultural issues such as community conflict with the outside work force
Another socio-cultural impact in the project area during construction will be an overall
disruption of the traditional cultural ways of people living in and near the project area.
Disruption of social life will also be caused by the presence of the construction workforce and
an anticipated influx of job seekers during construction period of the project. For example, it
is likely that the influx of construction workers will result in increased cases of inter-caste
marriages locally. Eventually, some changes in ethnic and community solidarity and
occupational patterns can be expected in the area. It is also likely that the construction workers,
contractors and engineers and their families, would interact with the local people that could
expose them to wide range of information opinions and ideas outside of their areas. Thus, the
project will have some impacts on social, cultural and religious features of the project areas.
These impacts are expected to be direct, low in magnitude, local in extent and of short term.
ix. Issues relating to increased gambling, alcoholism and prostitution
With the beginning of construction of projects involving numbers of migrant workforce
introduced to new areas, there is always risk of introduction of new communicable diseases
carried by the migrant workforce from elsewhere. While there are risks of communicable
diseases being brought into the project area, the situation gets worst as these diseases spread to
the local population and turn to an epidemic. As evident from other projects in Nepal, the risks
of sexually transmitted diseases (STD) including HIV and AIDS increases in the project area.
With a number of outsider population introduced to the area, there is always likelihood of
conflicts between the locals and the outsiders. The locals have their own way of living as guided
by the traditional cultures and practices. The outsider populations have a different way of living
life as they are from a different area with different societal settings and customary traditions.
This difference between the locals and outsiders creates a cultural gap and with any kind of
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
121| P a g e Department of Electricity Development
intrusion to the existing traditions in the local area by the outsiders there will be conflicts
generated. Moreover, with increased migrant workforce in the area, there will be increased
alcoholism, gambling, prostitution in the project area and thereby the law and order situation
may get vandalized. The impact will be indirect in nature, moderate in magnitude, local in
extent and short term in duration.
x. Loss of Private Land and Property
About 4.133 ha of private lands will be lost from the project implementation but there will be
no loss of private property. The impact is predicted to be of direct nature, moderate magnitude,
local extent and long term duration.
xi. Economic inflation
All the hydropower projects are capital-intensive scheme. Therefore, the economic activities
will be very high and intense during construction phase in the form of employment, business,
and compensation etc. Land prices in the area will inflate. The people's behavior will be
changed due to the big cash amount received from the compensation of their land. People in
the local area after getting employment in the project will earn cash and there is likelihood of
expending the cash earned in alcoholism and gambling.
The impact is expected to be of indirect nature, moderate in magnitude, local in extent, short
term in duration.
(ii) Operation Phase
i. Occupational health and safety related issues of the power station workers
Occupational Health and Safety issues during operation phase are particularly associated with;
• Long term exposures to noise from turbine operation
• Accidents due to electrocution causing injuries and deaths
Occupational health impacts are direct in nature, moderate in magnitude, site specific in extent
and long-term duration.
ii. Public Safety Related Issues/Movement of people in dangerous places
Local people with ignorance may not know about new structures and dangerous places such as
the switch yard. They may visit these areas and risk their well-being. Children are especially
susceptible to such hazards, which can result in accidents.
The impact will be direct in nature, moderate in magnitude, site specific in extent and long
term in duration.
iii. Issues relating to upstream and downstream (dewatered stretch of the Dudh Koshi
River) water uses and conflicts
The bank at about 100m downstream from the proposed Powerhouse, Sub-station and
Switchyard site is used as cremation place by the Hindus of the project area. Especially, the
people from ward no. 2, 3, 4, 6, and 7 of Mapya Dudh Koshi Rural Municipality use the place
for cremation. Though there is no infrastructure for the cremation such as cremation platform,
will be affected of traditional cremation ground is a sensitive issue. The project needs to arrange
an alternative cremation ground upstream from the proposed weir site with facilities such as
cremation platform, steel truss hut etc.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
122| P a g e Department of Electricity Development
Similarly, implementation of the proposed Dudh Koshi hydropower will affect downstream
purpose Dudh Koshi-4, hydropower headworks at ward-4. The purpose Dudh Koshi -4
hydropower activities will be carried out at about 200m-500m downstream from the proposed
power house and switchyard of Dudh Koshi HP. The project has a plan to coordinate with Dudh
Koshi -4 HPP.
The impact will be direct in nature, moderate in magnitude, site specific in extent and long
term in duration.
iv. Issues relating to sudden release of water to downstream
Water is released suddenly to downstream area to flush out the sediment load from settling
basin especially during the wet season. Children may go swimming, local people may cross the
river, and fishermen may go fishing in the downstream areas. People may be washing in the
river if they are unaware of the situation. Thus, there is a high risk of accidents and even loss
of life if people are unknown and are not informed about the sudden release of water. The
impact will be direct in nature, moderate in magnitude, site specific in extent and long term in
duration.
v. “Boom Town” effect and its impact on local economy
The first and foremost impact during the operation phase is the withdrawal of economic
activities which flourished during the construction phase since majority of the construction
workforce will leave the project areas. However, it is likely that some economic activities will
continue or be further promoted in these areas.
During operation phase when the energy is sold to NEA in bulk, the economic activities will
be much less, only about 2~3 percent of total investment is necessary for annual expenditure.
The labour requirement will decrease drastically, and so will be the income opportunities.
Similarly, the business "boom" will decrease substantially and employment opportunity will
be drastically reduced during this phase. Local people might feel that, the natural resources
from their area has been utilized / exploited, but most of the benefits have been ripped off by
the outsiders. Lack of public awareness and participation in the development effort will
generate negative impact in the local people. The impact will be indirect in nature, low in
magnitude, local in extent and long term in duration.
5.3 Evaluation of the Impacts
In general, direct impacts are identified, and indirect impacts predicted. The significance of the
impacts has been evaluated using the words significant, moderately significant and
insignificant. Assumption has also been made to evaluate the significant impacts. For example,
the direct impacts or direct loss of land and property, forests and demolition of infrastructures
as a part of site clearance are as significant impacts; the project induced impacts are considered
moderately significant; and impact that may occur outside the project area, and/or which is not
directly related with the project activity is considered insignificant for this project.
For convenience, direct impacts having total score of over 75 are considered significant;
impacts having 50 to 75 score are considered moderately significant; and impacts having total
score of less than equal to 50 are considered insignificant for this project. However, some of
the impacts whose total score exceeds 50 may not be significant in view of the nature of the
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
123| P a g e Department of Electricity Development
predicted impacts. Some impacts having less than 50 score could also be considered significant.
The logical base for such ranking has been given in the remarks. It has been done so as the
impacts are related to the subjective judgment on magnitude, extent and duration of the impacts
(Table 5-8 and 5-9). For example, impacts likely to occur outside the project's direct impact
zone and of indirect nature may not be significant although the total score exceeds 50. This
ranking has provided a basis to select and propose environmental protection measures, i.e.,
beneficial impacts augmentation measures, and adverse impacts mitigation measures.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
124| P a g e Department of Electricity Development
Table 5-8: Evaluation of Beneficial Impacts
SN Likely Impacts
Natu
re
Magn
itu
de
Exte
nt
Du
rati
on
Tota
l S
core
Significance
1. Construction Stage
1.1
Employment opportunities for local people and impact on local
economy and skill development
D H (60) L (20) ST (05) 85 Significant
1.2 Benefits as a result of access road construction
ID H (60) L (20) LT (20) 100 Significant
1.3 Benefits from community and social support programs D M (20) L (20) LT (20) 60 Moderately
Significant
1.4 Benefits from implementation of environmental mitigation
programs and benefit augmentation measures
ID M (20) L (20) LT (20) 60 Significant
1.5 Increase in economic activities in the project area and associated
beneficial impacts in local economy through micro-enterprise
development
ID M (20) L (20) ST (05) 45 Insignificant
1.6 Benefits for Exposure of local population to new technologies
and technology transfer
D L (10) L (20) LT (20) 50 Insignificant
2. Operational Stage
2.1 Benefits to be incurred from addition of 110 MW of power to
INPS
D H (60) R (60) LT (20) 140 High Significant
2.2 Changes in local economic activities ID M (20) L (20) LT (20) 60 Moderately
Significant
2.3 Changes in micro and macro economy ID L (10) L (20) LT (20) 50 Moderately
significant
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
125| P a g e Department of Electricity Development
SN Likely Impacts
Natu
re
Magn
itu
de
Exte
nt
Du
rati
on
Tota
l S
core
Significance
2.4 Sharing of electricity royalty to concerned state and concerned
local level
D M (20) R (60) LT (20) 100 Highly
significant
Note: D = Direct, ID = Indirect, S= Site specific, L= Local, R= Regional, ST=Short Term, LT= Long Term, H = High, M=Moderate, LO= Low
Value in the parenthes are based on neumaric value provided in National Environmental Impact Assessment
Guideline, 1993. Priority rank; 1 (sum of numerical value 70 or above) = highly significant; 2 (sum of numerical value 45- 70) = moderately significant; 3 (sume of numeric
value below 45) = low significant.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
126| P a g e Department of Electricity Development
Table 5-9: Evaluation of Adverse Impacts
SN Likely Impacts
Natu
re
Magn
itu
de
Exte
nt
Du
rati
on
Total
Score Significance
1. Physical Environment
1.1 Construction Stage
1.1.1 Change in land use D M (20) SS (10) LT (20) 50
Moderately
Significant
1.1.2 Possible Glacier Lake Outburst Flood (GLOF) and associated
impacts IN H (60) L (20) ST (05) 85 Significant
1.1.3 Landslide and soil erosion D M (20) SS (10) ST (05) 35 Insignificant
1.1.4 Possible impacts on spring sources above and below along the tunnel
alignment D M (20) SS (10) LT (20) 50
Moderately
significant
1.1.5 Impact on river morphology D M (20) SS (10) ST (05) 35 Insignificant
1.1.6 Generation of spoils and spoil disposal related issues D M (20) SS (10) ST (05) 35 Insignificant
1.1.7 Water quality management and waste water disposal issues ID M (20) L (20) ST (05) 35 Insignificant
1.1.8 Loss of fertile top soil D L (10) SS (10) ST (05) 25 Insignificant
1.1.9 Clogging of natural drainages ID L (10) L (10) ST (05) 25 Insignificant
1.1.10 Noise and vibration related impacts D M (20) SS (10) ST (05) 35 Insignificant
1.1.11 Issues relating haphazard stockpiling of construction material D L (10) SS (10) ST (05) 25 Insignificant
1.1.12 Issues relating to generation of solid waste and their management ID M (20) SS (10) ST (05) 35 Insignificant
1.1.13 Air pollution related issues D L (10) L (20) ST (05) 35 Insignificant
1.2. Operational Phase
1.2.1 GLOF and associated impacts ID H (60) L (20) ST (05) 85 Significant
1.2.2 Impacts on river flow regime downstream of diversion weir
(dewatered stretch of Dudh Koshi River) and possible microclimatic
changes
D M (20) L (20) LT (20) 60 Moderately
Significant
1.2.3 Land submergence created by 15m high diversion weir and
associated impacts D L (10) L (20) LT (20) 50
Moderately
Significant
1.2.4 Management/final disposal of solid waste and wastewater (both
black water and grey water) ID L (10) SS (10) ST (05) 25 Insignificant
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
127| P a g e Department of Electricity Development
SN Likely Impacts
Natu
re
Magn
itu
de
Exte
nt
Du
rati
on
Total
Score Significance
1.2.5 Noise and vibration D L (10) SS (10) ST (05) 25 Insignificant
2. Biological Environment
Adverse Impacts
2.1. Construction Stage
2.1.1 Loss of forest area D M (20) SS (10) LT (20) 50
Moderately
significant
2.1.2 Impacts on forest vegetation and overall forest diversity D M (20) SS (10) LT (20) 50
Moderately
significant
2.1.3 Impact on aquatic life including fishery resources D M (20) SS (10) ST (05) 35 Insignificant
2.1.4 Possible impacts on protected species of flora and fauna D L (10) SS (10) LT (20) 40 Low significant
2.1.5 Impact on wildlife and avian population ID L (10) L (20) ST (05) 35 Insignificant
2.1.6 Impact on Non Timber Forest Products/MAPs ID M (20) SS (10) ST (05) 35 Insignificant
2.1.7 Possible Risk of forest fire ID L (10) L (20) ST (05) 35 Insignificant
2.1.8 Disturbance to wildlife due to construction activities D L (10) SS (10) ST (05) 25 Insignificant
2.2. Operational Stage
2.2.1 Impacts on fish and aquatic fauna and their habitat D M (20) L (20) LT (20) 60 Moderately
significant
2.2.2 Change in composition of fish fauna in upstream section of diversion
weir D M (20) L (20) LT (20) 60
Moderately
significant
2.2.3 Possible disturbance to the wildlife activities D L (10) SS (10) LT (20) 40 Low significant
2.2.4 Possible Risk of forest fire ID L (10) L (20) ST (05) 35 Insignificant
3. Socio economic and Cultural Environment
Adverse Impacts
3.1. Construction Stage
3.1.1 Land acquisition and Land compensation related issues D M (20) L (20) LT (20) 60
Moderately
significant
3.1.2 Loss of community forest resources and compensation related issues D M (20) L (20) LT (20) 60
Moderately
significant
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
128| P a g e Department of Electricity Development
SN Likely Impacts
Natu
re
Magn
itu
de
Exte
nt
Du
rati
on
Total
Score Significance
3.1.3 Loss of agricultural land and crop production D M (20) SS (10) LT (20) 50
Moderately
significant
3.1.4 Pressure on existing facilities, services and resources of the project
area ID M (20) SS (10) ST (05) 35 Insignificant
3.1.5 Possible interference with village trails ID L (10) L (20) ST (05) 35 Insignificant
3.1.6 Occupational health and safety related issues D H (60) SS (10) ST (05) 75 Significant
3.1.7 Issues relating to public health and sanitation and as well as public
safety ID L (10) SS (10) ST (05) 25 Insignificant
3.1.8 Socio cultural issues such as community conflict with the outside
work force D L (10) L (20) ST (05) 35 Insignificant
3.1.9 Issues relating to increased gambling, alcoholism and prostitution ID M (20) L (20) ST (05) 45 Significant
3.1.10 Loss of Private Land and Property D M (20) L (20) LT (20) 60 Significant
3.1.11 Economic inflation ID M (20) L (20) ST (05) 45 Significant
3.2. Operation Phase
3.2.1 Occupational health and safety related issues of the power station
workers D M (20) SS (10) LT (20) 50 Significant
3.2.2 Public Safety Related Issues/Movement of people in dangerous
places D M (20) SS (10) LT (20) 50 Significant
3.2.3 Issues relating to upstream and downstream (dewatered stretch of the
Dudh Koshi River) water uses and conflicts D M (20) SS (10) LT (20) 50 Significant
3.2.4 Issues relating to sudden release of water to downstream D M (20) SS (10) LT (20) 50 Significant
3.2.5 “Boom Town” effect and its impact on local economy
indirect in nature, low in magnitude, local in extent and long term ID L (10) L (20) LT (20) 50 Significant
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
129| P a g e Department of Electricity Development
6. ALTERNATIVE ANALYSIS
Alternative analysis is considered as an integral part of project feasibility study. Alternative
analysis is primarily governed by the factors like technical feasibility, economic viability and
environmental acceptability. This section focuses on the assessment and evaluation of the
following aspects of the available alternatives: (i) choice of design (ii) selection of fish
migration structure; (iii) analysis of potential alternative project sites; and (iv) Technology,
Procedures of Operation, Time Schedules, Energy and Raw Materials to be used for DK-5 HPP.
The aim of the proposed Dudh Koshi-5 HPP is to construct and install a system having 110
MW installed capacity which can generate 618.80 GWh of energy annually in the national grid
of Nepal. The various alternatives to achieve the project objectives of Dudh Koshi-5 HPP with
no or minimum environmental damages are discussed in the following sections.
6.1 Design Alternative
In the desk study conducted DK 5 HPP was proposed as a simple runof-river (SRoR) scheme
with an installed capacity of 102 MW. Further desk studies and field investigations conducted
during the initial stages of the present study indicated that the project could be developed as a
pondage run-of-river (PRoR) scheme. Accordingly, the project was studied as pondage run of
river scheme considering different alternatives. Optimization of the installed capacity of DK 5
HPP was carried out to establish the optimal plant size for power production from the
hydropower scheme. For this purpose, various installed capacities of the project and the
corresponding flow conveyance systems were considered for economic analyses, keeping the
full supply level at the headworks and the tail water level at the powerhouse fixed. To identify
the optimum installed capacity of the project, seven installed capacities, ranging 46.12 to
154.27 MW, were considered. For a fixed design head, the increase in installed capacity was
achieved by varying the flow in the conveyance system through variations in the dimensions
of the desanding basin, headrace tunnel, surge tank, penstock, power station and tailrace canal.
For each alternative scheme, preliminary cost estimates of the requisite works were prepared
based on quantity takeoffs from preliminary designs and rates from projects of similar nature.
Likewise, power generation and annual energy productions, together with dry and wet energy,
were computed for each alternative based on the hydrological data generated during the present
study and base energy prices offered by Nepal Electricity Authority.
6.2 Construction Method Alternatives
Construction methodology will be based on intensive technologies of construction equipment
and maximum utilization of local resources to the extent possible. This is to ensure lowest
possible cost for project development and ensure quality in the works undertaken. Due priority
will be given for the recruitment of local people which will minimize the requirement of
temporary camp, reduce fuel wood and timber requirement, enhance local skill and economy
and develop better relationship between the project and local people. The surface construction
work will be scheduled in daylight and night construction will be limited to underground work.
Controlled blasting will be practiced at all times while excavating the underground area to have
a minimum vibration impact on the house structures located close to the tunnel alignment. This
will minimize the impact on local topography, structural damages in nearby settlement and
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
130| P a g e Department of Electricity Development
unnecessary disturbances to local community. Drilling work site will be selected away from
the settlement whereas movement of vehicle in suspicious areas will be controlled to minimize
the likely damage. The implementation of the project will require sand and aggregate which
will be used from the proposed quarry sites and crushing the excavated materials from tunnel.
6.3 Project Alternatives
Such alternative seeks other modes of electricity facility to fulfill similar requirements for the
regional development as would be achieved by installation of hydropower. The people within
the zone of influence require safe, efficient, cheap and healthy energy for daily lighting and
cooking activities. At the same time, there is an urgent need to conserve the environment in
terms of physical, biological, social and cultural aspects. Possible alternative options to achieve
above-said prospect would include solar power, wind power, thermal power, fossil fuel and
firewood. Power import from neighboring countries is another option. Solar and wind power
are also sources of clean energy which create or produce very less environmental degradation.
However, the potentiality of both solar and wind power on large extent depends on the sunshine
hour and wind velocity which may not be available all the time. Besides, there are problems
associated with these sources. Imported solar panels are complex in technology and expensive
in maintenance. Power generated from solar power is very small to be used for heating and
cooking purpose. Some household in the project affected area have small solar panels for
lightening purpose that is not sufficient as they need more power for cooking, lightening,
heating, running electronic and electrical equipments and others. Related problems in the
operation of wind power are lack of time series data of wind & trained human resources and
intricate design of wind turbines. Thus, the solar and wind power could not be an appropriate
alternate for this size project. Thermal power plant is associated with serious environmental
problems like air pollution due to CO2 emission, sludge handling, high noise, high temperature
and fire hazard. Besides, petroleum products are imported from abroad, price is continuously
increasing, and there is a problem of spare parts and their high cost. Nepal is surrounded by
India on south, east and west and China on north. Nepal has been importing power from India
where the power is already in acute shortage. Various problems are stumbled during its import
such as lack of high voltage transmission line, low voltage at certain time of the day and
irregular supply schedule. High mountain barrier has made power import inaccessible and
costly from China. Thus, it is an optimum necessity to seek out the permanent source of
electricity in nation itself for the continuous supply of electricity. For these reasons, power
import from neighboring countries can never be a sustainable solution for Nepal. Considering
the above alternatives, hydropower can be the best option to serve the purpose of electricity
requirement of the country.
6.4 Construction Material Alternative
Physical resources are consumed for the construction of proposed project. The materials to be
used are boulders (stones) for gabion and walls, gabion wires, masonry wall, brick or concrete
block, aggregates for concreting. Other local resources will be quarry and burrow used from
the area. Reinforcement bars and cement will also need to be transported from other places of
the country or outside of country. Electro-mechanical equipments need to be imported from
overseas manufacturers. There are no other cost-effective alternatives for the above materials
in construction works of the project. The construction is intended to be carried out by
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
131| P a g e Department of Electricity Development
conventional method, whereas earthwork, construction of simple structure such as drains,
gabion walls, bio-engineering works etc. will be carried out manually.
6.5 Construction Schedule Alternatives
The estimated project construction period is 4 years from the date of commencement of the
work. The construction works are mainly of two types - surface construction works and
underground construction works. The surface construction works is to be carried out only in
dry season. But the underground structures such as desander, tunnel, surge tank, powerhouse
and other structures can be constructed throughout the year irrespective of weather and climatic
conditions. All the surface work will be scheduled in day light.
6.6 No Forest Option
The no forest option helps to conserve and protect forest areas for optimal option selected for
the project. It will obviously provide ecosystem services, soil and nutrient conservation, habitat
for wildlife, source of fuel wood, forage and fodder to local people and other forest based raw
materials but it will seriously undermine the development of proposed option that is renewable
and clean source of energy. The long-term operation of the project far outweighs the ecosystem
and economic services provided by the forest under project effect. It will provide continuous
source of clean energy that will displace existing use of fossils fuels and fuel woods, helps to
conserve more forest area that will obviously degraded in the future that has negative impact
on forest and human health on long run. The project's layout option is such that minimal forest
area is required. Except for forest land required by reservoir, project component roads, adits
and other components of the project are laid underground and hence forest requirement is
limited which will be compensated as per Procedural Guideline for the use of Forest Land
(2063) and other mitigation programs as proposed in the EIA report.
6.7 No Project Alternative
This alternative prevents the implementation of the Proposal and will therefore forfeit the
beneficial impacts identified in Chapter 5. This Proposal aims to provide electricity to remote
rural areas of project affected district and adding up in the national power supply as required.
Similarly, limitation exists to access clean energy in rural areas. This situation calls for rapid
expansion of power projects. Furthermore, electricity is synonymous with development.
Household amenities, commerce and industry all depend on the reliable power supply. Thus,
the Project is a necessity of the country. According to the power forecast of NEA, annual
increment of the power demand is well above 50 MW. The Fourteenth Three Year plan intends
to generate 704 MW of hydropower. Hence, do-nothing scenario will be against the
government’s Three Years plan and/or national commitment. If hydropower generation is not
continued, power shortage will continue and hamper the overall socio-economic development
of the country. Electricity consumption is one of the parameters to assess the prosperity of the
people. Activities like running rice mill, flour mill, saw mill, oil mill, nursing home operation
(x-ray, pathology, operation), photo processing, secretarial services (computer typing, printing,
email and internet operation, sending and receiving fax) these all and other activities depend
on electricity. In fact, the demand for electricity is increasing and there are difficulties in
meeting the requirement. Access to power is an addiction, without which life becomes
miserable. In this age of information technology, the power availability must be increased.
Therefore, absence of project alternative does not hold any merit. Similarly, No project
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
132| P a g e Department of Electricity Development
alternative means the non-use of potential power generation, loss of job opportunity,
continuation on power shortage, and also depriving of the other economic benefit due to the
project implementation. In a country where unemployment is very high and clean energy is in
shortage, do nothing scenario is a regressive approach and is very difficult to accept. The do-
nothing situation will prevent some of the environmental adverse impacts at the cost of
isolation, difficulty in access, remoteness, malnutrition and severe poverty. In balancing the
trade-offs with the No-action option, this alternative is regarded as not acceptable in the interest
of national development.
6.8 Operation Procedure
Operation of the project comprises of semi automatic control system. A team of qualified staff
will run the project and no adverse impact is anticipated to the local population or environment.
It would rather benefit the local community through increased employment opportunities,
communication facilities and supply for rural electricity. The project will be operated as per
requirement of INPS.
6.9 Fish Ladder Alternative
There are various options to mitigate the effects of restriction to fish migration due to diversion
weir; however, the effectiveness of the applied measures may be quite different for the different
measures depending upon the local field conditions, behavior of the existing aquatic fish
species etc. Commonly used mitigation options are:
• Fish Trapping, Hauling and Release;
• Fish Lock Alternative;
• Fish Ladder Alternative;
• Cold water Fish Hatchery annexed with open water stocking of mid-range and long-
distance migrants
The Fish Trapping, Hauling and Release alternative is cost effective, labor intensive and
provide direct benefit to the local economy as this will be based on the employment of the local
fisherman community. For the trapping of fish, various fish traps can be used. The commonly
used fish traps for upstream and downstream migrant fishes are bamboo weir fish traps, fish
wheels, fyke or Hoop Nets and pot gears. The trapped fish then can be hauled using
transportation vehicles. To transport the fish upstream and downstream, specially designed
insulated water tanks with facilities for aeration and water circulation will be needed. Such
tanks can be designed and manufactured in Nepal. The only drawback of this option is that the
handling of the fish during trapping and hauling may result in high mortality of the fish.
The Fish Lock Alternative is the automated mechanical device designed and placed in the weir
structure. A special fish lock structure below, above the weir attracts, and lock the fishes. The
locked fishes are then hauled across the weir by a specially designed lift automatically. Such
devices have been brought into operation at number of dams in other parts of the world. Owing
to the fish release conflict, difficulties in attracting fish in the lock area and difficulty for fish
to access the trap area in the turbulent water condition released from the spillway in monsoon,
this alternative may not function effectively at times when it is required the most.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
133| P a g e Department of Electricity Development
The Fish Ladder Alternative provides a natural migratory path to the migrating fish without
human intervention in the migrating season. Since very little is known on the swimming speed
of the targeted fish species and required flow conditions of water, it is difficult to confirm the
efficiency of fish ladder. There are many projects planned in the Dudhkoshi basin creating
dewatered zones along the river alignment. For example, in this project, there will be
approximately 8 km of dewatered zone. Therefore, for this long-dewatered zone, the
compensation flow equivalent to 1.48 m3/s will disappear in the average width of 25m of
Dudhkoshi River. The fish ladder therefore, will help in the vicinity of the weir site only and
does not help for the migratory fish to swim in the dewatered zone.
On-site cold-water fish hatchery annexed with open water stocking of mid-range and long-
distance migrant species annually in the upper catchment of the Dudh Koshi is the other
alternative. But this alternative will require maintenance of an on-site fish hatchery of the
targeted fish species for the production of the targeted numbers of fingerlings from hatchery
and hauling of the fish fingerlings for open water stocking in the Dudhkosh River. Experience
of cold-water fish hatchery in Nepal (Kali Gandaki “A”, Pokhara, Trishuli, and Godavari)
reveals that the target 14 fish species including the IUCN red list species could be breed in the
hatchery in captivity. This option though costly in terms of infrastructure eand operation
investments has advantages over the other options as it ensures the conservation of the IUCN
red list species in the River and may even conserve the native species.
An analysis of the various options reveals that the Fish Trapping and Trucking and Fish Lock
Alternatives are relatively cheap and do not require high investment costs compared to fish
ladder and cold-water fish hatchery alternatives but would require an effective and efficient
management throughout the project operation period. The effective and efficient management
in the context of Nepalis highly questionable. Therefore, the on-site cold-waterfish hatchery
annexed with the open water fish stocking are the best alternatives to minimise the barrier effect
to fish migration vis-á-vis conservation of the IUCN red list species. Apart from this, the cold-
waterfish hatchery will compensate for some of the impacts on fish diversity and population of
the upstream Dudh Koshi River. In the downstream section, the habitats provided by the Dudh
Koshi River are anticipated tomitigate the impacts on fish diversity and population.
Summarizing, the project will provide an onsite cold-water fish hatchery for a selection of the
migratory fish species including the IUCN red list species and operate the fish hatchery for the
production of fish fingerlings for open water fish stocking in the Dudh Koshi River.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
134| P a g e Department of Electricity Development
7. ENHANCEMENT AND MITIGATION MEASURES
This section identifies the environmental mitigation measures to address the potential adverse
impacts of the project. It also presents the environmental enhancement measures for
augmenting the benefits of the project. Mitigation measures are developed by considering all
possible impacts from the implementation of the project-construction and operation.
Appropriate mitigation measures are recommended to eliminate, reduce or avoid the potential
adverse impacts on physical, biological, socio-economic, and cultural environment resulting
from the implementation of Dudh Koshi-5 Hydropower Project. Cost effective and practical
enhancement and mitigation measures have been devised in order to address the anticipated
impacts of the project implementation. These recommended actions include preventive
compensatory, corrective measures for adverse impacts and enhancement measures for
beneficial impacts which will be implemented during project construction and operation phase.
The responsibility of implementing proposed enhancement and mitigation measures lies with
the proponent and the proponent needs to ensure that all the proposed measures are fully
implemented.
7.1 Environmental Enhancement Measures
The benefit from the project could be enhanced or made more effective if they are planned
properly. The following are the possible augmentation measures to enhance the benefit(s).
7.1.1 Construction Phase
i. Employment opportunities for local people and impact on local economy and skill
development
The project will give first priority to the PAFs and local people who want to work in the project.
The project will maintain the roster of the PAFs and at least a member of PAF will be employed
during the project construction period. The project will provide necessary training to the SPAFs
and PAFs, if necessary, depending upon the nature of the work offered.
The project will include a binding clause in the contractor's agreement to give first priority to
PAFs while hiring both skilled and unskilled labor forces and to give daily wages or monthly
wages not less than the district approved rates. The next priority will be given to local people
for employment. The employment to the local people will be coordinated through the
Coordination Committee. Local people will be recruited for administrative and technical works
as per their qualifications and skills.
Table 7-1: Cost allocated for training program
SN Particular Number
of trainees
Per
trainees’
cost
Training
Duration as
per CTEVT
Estimated
Total Cost
(NPRs)
1 Off seasonal vegetable
production 45 12,000.00 20 days 540,000.00
2 Cardamom production &
Processing 15 25,000.00 1month 375,000.00
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
135| P a g e Department of Electricity Development
SN Particular Number
of trainees
Per
trainees’
cost
Training
Duration as
per CTEVT
Estimated
Total Cost
(NPRs)
3
Improvement Livestock
farming (Buffalo, Cow,
goat, pig &chicken)
65 18,000.00 45 days 1,170,000.00
Sub-Total 125 2,085,000.00
Table 7.2: Estimated Cost for the Skill Development Training
SN Particular Number of
trainees
Per trainee
cost
Training
Duration/Period
as per CTEVT
Total Cost
(NRs.)
1 Electrical /Plumbing
training 15 55,000.00 390 Hrs 825,000.00
2 Driving 15 32.000.00 1Month 480,000.00
3 Plywood making 10
33,000.00 1 Month 330,000.00
4 Tourism hostility& Cook 25
38,000.00 45 Days 950,000.00
5 Meson 15
18,000.00 15 Days 270,000.00
6 Netting, stitching
&trailering etc 45
22,000.00 45 Days 990,000.00
7 Other training will be
proposed as local interest 30 55,000.00 45 Days 1,650,000.00
Total 155 5,015,480.00
ii. Increase in economic activities in the project area and associated beneficial impacts
in local economy through micro-enterprise development
The project staff and its workers would require local products such as vegetables, rice, pulses,
eggs, milks, ghee, chicken, mutton etc and other consumption goods such as edible oil, soap,
LPG, noodles, biscuits, clothes etc. They could be fulfilled by the local vendors.
Apart from that the project will allocate budget for training to one person each PAFs willing to
enhance skills in modern techniques of cash crop and livestock farming, tourism activities for
example homestay trekking, or the enhancement of the technical skills and know–how. The
project will encourage its staff members and construction workers to purchase local products
in order to uplift the economic condition of local farmers.
iii. Benefits for Exposure of local population to new technologies and technology
transfer
The project will launch training programs in specialized area such as electro–mechanical works
of Hydroelectric, house wiring and maintenance, road slope stabilization, spoil handling etc.
First priority will be given to the seriously project affected people (SPAFs), project affected
people (PAFs) and local people to the extent they are interested to get involved in the
construction activities.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
136| P a g e Department of Electricity Development
7.1.2 Operation Phase
i. Benefits to be incurred from addition of 110 MW of power to INPS
As the project is aimed for selling the energy to Integrated Nepal Power System owned by the
NEA, there will be additional availability of power/energy to INPS. The locals will also be
facilitating due to availability of electricity, if NEA plans to carry out rural electrification works
there acquiring the support from the government.
ii. Benefits from Community Support Program (CSP)
This issue is described in section 7.2.
iii. Benefits from implementation of environmental mitigation programs and benefit
augmentation measures
Various benefit augmentation measures and environmental mitigation measures as proposed in
EIA shall be implemented effectively which will have multi fold benefits during the operation
phase also.
iv. Benefits as a result of access road construction
The project will regularly repair and maintain the main road leading to the project area and also
the project service roads such that the local people will have uninterrupted service of the roads
for their mobility. Improved road conditions will benefit the community in various ways such
as faster accessibility to hospitals, year-round accessibility to bigger markets such as Salleri to
sell their farm as well as livestock products, easy access to education etc.
v. Public Shares
The project will provide 10% of the public shares to the locals in the project area.
vi. Rural Electrification
The proposed Project may open the door for the expansion of distribution network for rural
electrification in the vicinity of the project areas where there is no access to electricity.
However, the proposed Project will not carry out the rural electrification program itself. 7.2 Community Support Program (CSP)
As per the Concept Paper and Work Plan for National Energy Crisis Alleviation and Electricity
Development Decade, 2015 (/fli6o phf{ ;+s6 lgjf/0f tyf ljB't ljsf;sf nflu cjwf/0ff kq tyf
sfo{of]hgf, @)&@), 0.50% (NRs. 101,022,050.00) of the total project cost has been allocated for
Community Support Program (CSP). The project has suggested the following sectors for the
uptimum utilization of CSP cost for overall community development of the project area:
7.2.1 Education Support
The project suggests providing financial support to local education sector. Support shall be
provided to those schools which are located near to the project construction sites. Support shall
be provided for the establishment of library, widening of playground, educational materials
including sports, and other physical facilities.
7.2.2 Health Sector Support
Physical facility of existing health posts located in the project affected wards are poor in terms
of infrastructure and service delivery. There is a need of strengthening existing physical
facilities. Hence, the project suggests to provide financial support for strengthening the existing
health posts of the project affected wards.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
137| P a g e Department of Electricity Development
7.2.3 Drinking water support
The project suggests to provide financial support for strengthening the community-level water
supply facilities in each project affected Wards which already exist in the settlements of the
project affectedarea.
7.2.4 Irrigation System Support
The project suggests to provide support for strengthening the community-level irrigation
facilities in project affected area.
7.2.5 Support to Cultural Heritage:
The project suggests to support in the preservation, improvement and renovation of the cultural
heritage sites lying nearby the project affected area.
7.2.6 Conservation of Local Forest and Biodiversity
The project suggests to provide financial support to local Forest User’s Groupin coordination
with Division Forest Office (DFO) to pursue afforestation in degraded land and conservation
of biodiversity in the project area.
7.3 Environmental Mitigation Measures
7.3.1 Physical Environment
(iii) Construction Phase
i. Change in land use
• Due consideration will be given to avoid use of good forest, fertile land, settlement
areas for the establishment of labour camp, quarry sites, construction material
stockpiling area including other permanent project features;
• Appropriate compensation will be provided for families who will loose their land.
Detail is presented under socio-economic and cultural impact part.
• Temporarily acquired land will be leased for construction period and it will be
rehabilitated and brought to its original status, after the completion of construction
work, to the extent possible.
• Losses of forest area will be compensated as per the prevailing law. As per the Work
Procedure Regarding Use of National Forest Area for Projects of National Priority,
2074, the project will develop a plantation site.
• All the muck will be disposed in designated areas only.
ii. Possible Glacier Lake Outburst Flood (GLOF) and associated impacts
GLOF impacts on the project area will be caused by natural events without relationship to
project activities or facilities. But due to the establishment of the project, mitigation measures
against natural GLOFs will be introduced and should in principle be classified as enhancement
rather than mitigation measures. From an environmental perspective the most important actions
are:
• Establishment of an initial and temporary GLOF warning system tailored to the fact
that large numbers of workers are exposed in construction sites near the river and inside
tunnels that cannot be closed for protection.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
138| P a g e Department of Electricity Development
• Preparation of emergency plans in respect of GLOF warnings and establishment of
evacuation paths for escape to higher ground (up to 15 m above river level at the intake
site) at critical sites.
A budget of NRs. 1 million has been allocated to provide early warning system of Flood due
to GLOF.
iii. Landslides and soil erosion
Following mitigation measures for the soil erosion and landslides impacts are prescribed;
• Land clearance will be minimized as far as possible
• Dumping of excavated spoils in the hill slope will be avoided
• Surface excavations works in headwork, access roads and powerhouse areas will be
controlled as to the geotechnical requirements of land stability and erosion
• After excavation works, the excavated slopes in all areas will be stabilized by the
application of civil and bioengineering works as required by the local geotechnical
conditions.
• The spoil will be deposited to levels and heights taking into consideration of the
geotechnical stability of deposited materials
• All excavated materials will be deposited in the safe spoil disposal sites as designated
in the proposal
• Disposal of excavated loose materials along the water pathways will be prohibited
• Protection walls for major active landslides shall be constructed
iv. Possible impacts on spring sources above and below along the tunnel alignment
Prior to the start of the construction work, the water spring within 200m strip above the tunnel
alignment will be surveyed in the peak dry season and the available spring discharge is
measured and documented. The survey will be done in the presence of the village elites and
wards’ representatives. Estimated cost for the survey of spring location and discharge
measurement is NRs. 2,00,000. Alternative arrangement for the water supply wil be made if
the existing water springs sources are affected by the tunnel construction.
v. Impact on river morphology
The extraction of river bed materials will be planned properly in such a way that river
morphology does not change after the removal of the materials. Further, during the extraction
of materials, due consideration will be given to minimize bank erosion. Similarly, the
construction of the weir will be planned in a way so that concentrated flow or the diverted flow
does not make bank erosion as such. As the mitigation measure is related to planning, no budget
will be required for mitigating this impact.
vi. Generation of spoils and spoil disposal related issues
Following mitigating measures need to be adopted:
• Top soil (up to 15cm depth from the surface) from the affected area will be scrapped
and stored for later reuse in land development at disposal sites and other degraded land
in the project area.
• The excavation materials will be used for backfilling purposes wherever required
• All excavated materials will be deposited in the safe spoil disposal sites as provided by
the project design.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
139| P a g e Department of Electricity Development
• Deposition of the spoils on the hill slopes, drainage structures, private agricultural land,
natural waterways etc will be strictly prohibited.
• The excavated areas including the slopes will be revegetated so that the erosion prone
area could be protected. The revegetation works will be carried out with the local
species of grass, herbs, shrubs or trees.
• Prior to the start of muck disposal, the contractor will make a plan for muck disposal
and get approval from the project environmental officer. The plan besides other will
have a plan for toe and slope protection of the muck areas from the monsoon washout.
• The muck deposited will be properly compacted and will be facilitated by surface runoff
drainage facilities to avoid air pollution and run off erosion.
• The muck disposal site will be rehabilitated by covering the muck surface by the top
soil saved from the access roads, headworks and power house site preparation.
vii. Water quality management and waste water disposal issues
Control of oil, chemicals and other substance spillage
• The storage areas for the chemicals, oils and other substances will be located far from
the water sources to avoid the contamination by spillage.
• Service vehicles will be used to refuel heavy machineries to minimize the risks of
spillage.
• Workshop facilities will be located at least 100m away from the water sources. Spilled
oil and grease trapping systems will be built in the workshop. Such trapping systems
will be maintained periodically to avoid contaminated runoff into the water courses.
• Periodic maintenance of vehicles and other equipments will be done in order to ensure
no leakages in the fuel tanks.
Wastewater Management
• All kinds of waste shall be kept away from water sources to avoid contamination
through seepage or direct runoff.
• Toilets shall be provided at all construction sites and camp site with appropriate septic
system. Toilets will be located away from water courses. At construction site one toilet
shall be provided for no more than 20 workers. The provided toilet facilities should
accommodate the loads over the full construction period. The facilities shall be
maintained periodically and maintenance programme shall be mentioned in the
contractor's plan to be approved by the concerned project authority.
• Open urination and defecation shall be prohibited.
• Camp effluents shall not be discharged directly into the water sources. An adequate size
effluent treatment system will be constructed to treat the camp effluent.
• Any discharge in inland surface water will be practiced as per the tolerance limit set by
the MoFE.
Water quality monitoring
• Water quality of the sources in and around the construction sites, camp sites and major
settlements shall be monitored quarterly (dry season and wet season monitoring). The
drinking water used in the camps and housings shall also be monitored.
viii. Loss of fertile top soil
While preparing the site for construction for the access road, powerhouse and headworks, the
top soil will be managed separately and saved in a separate area for later rehabilitation works.
The top soil (0-25 cm) from the productive land (borrow areas, access road construction areas,
etc.) shall be preserved and reused for plantation and restoration purposes. A 15 cm top soil
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
140| P a g e Department of Electricity Development
will be stripped off from the borrow pit and this will be stored in stockpiles in a designated area
for height not exceeding 2m and side slopes not steeper than 1:2 (Vertical: Horizontal).
ix. Clogging of natural drainages
Following are the mitigating measures to reduce the impact:
• During excavation natural drainage channels will be protected as far as possible
• Runoff drainages will be constructed in project construction sites (headworks and
powerhouse), and project facility sites (camps, storage facilities, muck disposal sites
etc.) will be facilitated during the construction period and later remodified to suit to the
local conditions in the operation period as permanent network. The runoff water
collected will be safely discharged to the natural water bodies. After the completion of
the muck disposal, the muck disposal sites will be facilitated by permanent drainage
networks to collect and discharge the runoff water safely to the water bodies
• Permanent side drains and cross drainage structures will be constructed along the access
roads to collect water from the slope area. The collected water of the side drains will be
discharged to suitable natural waterways to avoid upstream and downstream erosion.
• In the agricultural fields, provisions will be made to drain the slope water to the down
slope agricultural land such that the water required for irrigation is not blocked with
prior consultation and agreement with farmers.
• Regular clearing of the drainage structure will be practiced (two times during monsoon
and one time each before and after monsoon) to remove the blockages by the sediments.
x. Noise and vibration related impacts
Control of blast related noise and vibration
• As far as possible blasting operation will be avoided during nights.
• Blasting will be controlled using limited detonators (charge weights) in small lot.
• Charge weight for each blast will be allocated considering relative distance to the
sensitive locations.
• The damage occurred due to blasting in surrounding private structures will be
compensated.
• The vulnerable population to vibration and noise will be temporarily shifted to safe
locations during blasting period.
• Confining blasting operations during the day time only. Prior information should be
given by blowing siren 10 minutes before blasting operation and 10 minutes after
blasting operation to indicate the commencement and conclusion of the operation;
• Regular maintenance of the vehicles to reduce the mechanical and body noise while
driving;
• Prohibition on the blowing of horns in critical stretches close to villages and near the
school area along the road; and
• Installing noise reducing equipment in the ventilators, compressors and diesel generator
set
• Construction equipment and engines will be maintained regularly as per manufacturer's
specification.
• Pressure horns in the vehicles will be prohibited. Blowing of horns will be allowed only
for safety reasons.
• The noise generating machineries and equipments such as generators, crushers,
concrete mixers will be placed far from the residential areas
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
141| P a g e Department of Electricity Development
Monitoring
Noise intensity level will be monitored regularly in the major construction sites such as
headworks, powerhouse, settlements along the roads etc.
xi. Issues relating haphazard stockpiling of construction material
The impacts will be mitigated by the following mitigation measures:
• Proper disposal mechanisms will be established for the management of what remains
of construction materials;
• Stockpiling and storage of the construction materials in designated sites only.
• The construction materials such as brick, sand and gravel will be methodically stored
at proper locations separately; and
• The residual of construction materials will be re-utilized for other construction purposes
like construction of resting places wherever possible.
xii. Issues relating to generation of solid waste and their management
Waste disposal
• Dumping facilities will be provided at each construction site to avoid proliferation of
the litters and construction trash materials.
• The construction wastes will be managed within the work areas. Tins and other metals
are kept in a closed scrap yard within the construction premise.
• Solid waste from the camp and work areas will be collected regularly.
• Separate waste collection bins will be provided in the camps to segregate wastes of
different nature. Appropriate methods will be adopted for disposal of the waste of
different nature. Appropriate location will be identified for the disposal of wastes. The
waste disposal area will be developed in such a way to ensure that the pollution of
surface water by run-off and underground water through leachate will be avoided.
• If the wastes are to burn, then the burning area will be located far from the settlements,
camps/housing area and working sites.
• Vector control measures (for examples use of insecticides) will be adopted in order to
check growth of disease carrying vectors.
xiii. Air pollution related issues
Dust control measures
• Excavation will be minimized as far as possible.
• The aggregate crushing plants, and concrete mixing plants will be located far from the
settlements and camp areas.
• The access roads and excavation areas will be regularly sprayed with water during dry
days, at least two times a day during peak construction period.
• The borrow vehicles will be covered during the transportation of dusty materials in the
construction sites. The spoils disposed in the spoil tip areas will be compacted in order
to stabilize them and avoid dust blowing by the wind; after the completion of the
construction plantation will be carried out in the spoil tip areas.
• Excavated areas will be revegetated to minimize the bare surface.
Emission Control Measures
• The stationery engines will be placed away from the settlement and camp areas.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
142| P a g e Department of Electricity Development
• Fume/smoke stacks will be provided in diesel and petrol operated machines and plants
such as diesel generators, stone and aggregate crushers etc.
• Vehicles and stationary combustion engines will be maintained regularly as per
manufacturer's specification.
• The emission impact will also be mitigated by installation of filters and air pollution
control equipment.
Monitoring
• Monitoring of emission of the vehicles used for construction and stationery
engines/construction machines for compliance with GoN's emission standards
• Monitoring of air quality will be done in construction sites will be done during whole
construction period. The air quality monitoring will be done in major construction sites
such as headworks, powerhouse, and settlements along access roads. Compliance with
National Ambient Air Quality Standard of GoN will be checked.
7.3.2 Operation Phase
i. GLOF and associated impacts
Following are the mitigating measures to reduce the impact
• Provide permanent warning system along the riverbank of Dudh Koshi and educate the
local residents about the system and characteristics of lake outbursts.
• It is recommended to develop emergency response procedures in case of glacial
outbursts.
ii. Impacts on river flow regime downstream of diversion weir (dewatered stretch of
Dudh Koshi River) and possible microclimatic changes
Changes in microclimate will be expected during dry season in the downstream area. As a
mitigation measure, the project will maintain a minimum flow of 10% of the mean monthly
flow. The extraction of river bed materials will be planned properly in such a way that river
morphology does not change after the removal of the materials. Further, during the extraction
of materials, due consideration will be given to minimize bank erosion. The project is
committed for the release of a minimum 1.48m3/s from the weir.
iii. Possible impacts on spring sources above and below along the tunnel alignment
Alternative arrangement for the water supply will be made if the existing water springs sources
are affected by the tunnel construction.
iv. Land submergence created by 18.1m high diversion weir and associated impacts
The river bank erosion due to bed level rise and damage to the agricultural fields will be
minimized by the river bank protection measures in the critical areas successively as the erosion
potentials are noted or reported by the farmers.
v. Management/final disposal of solid waste and wastewater (both black water and
grey water)
Following are the mitigating measures to reduce the impact
• Solid waste and wastewater from project permanent camp and project office will be
managed properly.
• Haphazard disposal of wastes will be strictly prohibited.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
143| P a g e Department of Electricity Development
vi. Noise and vibration
Since, the operation phase impacts on air quality, water quality, noise pollution and
solidwaste generation is too minimal, the mitigation actions required are also few.
vii. Air Quality
• The machines such as generators will be repaired and serviced regularly
• The project vehicles will be maintained and repaired regularly.
• Monitoring of air quality of the powerhouse and settlements along the project road
(periodically for one year after project construction)
viii. Water Quality
• The effluent discharges from project office and project camp to nearby water sources
will be prohibited.
• The spillage of chemicals such as oils and paints which can occur during repairing and
maintenance of powerhouse equipment and machines will be controlled.
• Haphazard disposal of spent oils and lubricants from the powerhouse and the
switchyard will be prohibited. All the spent oils, lubricants, from the powerhouse and
switch yards and transformers will be collected and kept in a separate designated area.
These spent oils and lubricants will be handed over to the authorized private waste oil
and lubricant dealers for treatment reuse
• Drinking water quality of the camp and water quality of the water sources around
powerhouse will be monitored periodically (for one year after the construction)
ix. Noise pollution
• The powerhouse workers will be provided with the ear muffs to reduce the exposure to
continuous noise of turbine operation
• Pressure horns blowing will be prohibited in the settlements along the roads in the
project area.
• Noise the camp and water quality of the water sources around powerhouse will be
monitored periodically (for one year after the construction)
7.3.3 Biological Environment
(i) Construction Phase
i. Impacts on forest area and forest vegetation and overall forest biodiversity
Following are the mitigating measures to reduce the impact
• Forest and vegetation will be cleared only to the required by pegging the area and
numbering the trees;
• Compensatory afforestation for the felled local tree species as per department of Forest
guideline will be carried out in consultation with the Division Forest Office on the
project costs. The plantation will be carried out with the species those are required to
cut down for the project construction in order to compensate for the lost species.
Moreover, emphasis will be given to the species with high value for timber and
fuelwood.
• As per rule of 1:25, a total of 87,850 tree saplings will be planted. The cost of plantation
has been estimated to be NRs. 21,634,818.91 (Annex 8). The total cost including
caretakers has been estimated to be NRs. 25,234,818.91.
ii. Impact on aquatic life including fishery resources of the Dudh Koshi River
Following are the mitigating measures to reduce the impact
• Unless required by the project structural placement, the riverbed will not be disturbed
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
144| P a g e Department of Electricity Development
• Spoil disposal in the river flood plain will be prohibited
• Fishing will be restricted for the project staff and outside project workforce
iii. Possible impacts on protected species of flora and fauna
Following are the mitigating measures to reduce the impact
• As far as possible, the felling of rare, endangered, endemic species will be avoided
• In case the felling is required by the project layout, such species will be planted in
afforestation areas as a part of compensatory afforestation as per department of Forest
guideline
iv. Impact on wildlife and avian population
Following are the mitigating measures to reduce the impact
• Forest and vegetation will be felled only to the required by pegging the area and
numbering the trees
• The project will organize programs to raise awareness on conservation of wildlife
habitats and wildlife species for local people, school children and project workers
• Night time construction activities using heavy machineries and blasting operations
between 18 hours to 5 hours will be avoided as far as possible
v. Impact on Non-Timber Forest Products/MAPs
Following are the mitigating measures to reduce the impact
• The project will develop programs to support NTFP promotion.
• While carrying out afforestation, the plantation of NTFP species will also be carried
out.
vi. Possible Risk of forest fire
Following are the mitigating measures to reduce the impact
• The project staff and workforce will be instructed not to visit the forested areas
• Awareness relating to importance of forest and biodiversity and consequences of forest
fires will be provided to the local people and the project staffs.
vii. Loss of aquatic habitat and consequent impacts on aquatic lives
Mitigation: Following are the mitigating measures to reduce the impact
• Unless required by the project structural placement, the riverbed will not be disturbed
• Spoil disposal in the river flood plain will be prohibited
• Fishing will be restricted for the project staff and outside project workforce
(ii) Operation Phase
i. Impacts on fish and aquatic fauna and their habitat
Mitigation: Following are the mitigating measures to reduce the impact
• Hatchery backed open water fish stocking of fish species will be carried out annually
in the upstream section of the Dudh Koshi River from the weir by obtaining fingerlings
from private hatchery
• Steel wiremesh will be placed at the mouth of intake structure to prevent fish passage
to the waterways
• Residual environmental flow (1.48 m3/s) will be released round the year from the weir
as per Hydropower Policy to sustain the aquatic life of the dewatered section between
weir and tailrace.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
145| P a g e Department of Electricity Development
• Release of 500,000 fingerlings @ 100,000 fingerlings per year is proposed for 5 years
in upstream of Dudhkoshi River weir (NRs. 5,000,000.00)
ii. Change in composition of fish fauna in upstream section of diversion weir
• Hatchery backed open water fish stocking of fish species will be carried out annually
in the upstream section of the Dudh Koshi River from the weir by obtaining fingerlings
from private hatchery
• Steel wiremesh will be placed at the mouth of intake structure to prevent fish passage
to the waterways
• The creation of numerous small shallow pools from 10m² to 25m², and 0.15m to 0.3m
deep) within the same reservoir bank area. These pools should be appropriately spaced
on both banks, and would re-create breeding sites for the majority of the amphibian
fauna of the locality.
• Vegetation should not be cleared around or in these pools.
iii. Possible disturbance to the wildlife activities
Following are the mitigating measures to reduce the impact
(i) No poaching and hunting activities will be allowed.
(ii) Minimum disturbance will be maintained
Following are the mitigating measures to reduce the impact
• The project staff and workforce will be instructed not to visit the forested areas
• Awareness relating to importance of forest and biodiversity and consequences of forest
fires will be provided to the local people and the project staff.
7.3.4 Socioeconomic and Cultural Environment
(i) Construction Phase
i. Land acquisition and Land compensation related issues
Following are the mitigating measures to reduce the impact
• The private lands which will be acquired by the project will be compensated. The
compensation value of land will be determined through a compensation determination
committee including representatives from district administrative officials (CDO,
District Land Revenue Officer and DCC Chairman), representatives from affected
landowners and project authorities.
• The standing crop at the time of acquisition will be allowed to harvest by the respective
landowners. If the project
• Developer chooses to enter into the area before the harvesting of standing crop, the
standing crop will be compensated as per the production potential at market price.
• The trees in the private forests and other agricultural lands that need to be cut down for
the project will be duly compensated by the project.
• Employment priorities will be given to the population in the household whose land and
property are lost due to project.
ii. Issues relating to loss of private/farm trees (timber, fruits, fodder) as well as
standing crops and their compensation
Following are the mitigating measures to reduce the impact
• The project will develop training packages for the development and enhancement of
skills of the people in the households whose land is affected. Such trainings would be
developed in consultation with the affected households. Masonry, carpentry, driving,
electrician, welding, computer educations are fields which the people in the project area
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
146| P a g e Department of Electricity Development
have shown interest towards, during field survey. Such trained human resource can be
employed by the project to fulfill project human resource requirement. The trainings
such provided will be useful in terms of earning livelihood for the affected households
after the project construction also.
• The project will develop training programs to the project area farmers to enhance their
knowledge and skills in improved farming techniques and livestock rearing in
collaboration with the DADO and DLSO.
• The project will also develop and implement income generating programs to the project
affected households. Such programs will be developed in consultation with the affected
households. Implementation of such IGPs will be carried out with assistance from the
local CBOs and NGOs.
iii. Loss of community forest resources and compensation related issues
This has been dealt in section 7.3.3.1 (i).
iv. Loss of agricultural land and crop production
The project will provide adequate compensation for the loss of agriculture land and crop
production. Trainings on scientific agriculture technologies and an improved seed program
will increase the agricultural production in the project area. Moreover, people on the project
area/s will be motivated for cash crop plantation. Such trainings will somehow compensate
for the loss in agriculture production and will help boost economic conditions of the locals.
v. Issues relating to damage to or loss of community as well as private properties and
their compensation
Following are the mitigating measures to reduce the impact
• The project will compensate for the community land on a lease basis for temporary
acquisition
• The project will negotiate with the affected households to provide compensation for the
loss of tree from the private land on mutual basis. Compensation will be paid as per the
numbers of plant rather than wood volume. Owner will have the right to use the
uprooted trees without deducting amount.
• Will compensate the aggregate volume excavated as per DCC guideline in case of
boulder, aggregate and sand extraction
vi. Pressure on existing facilities, services and resources of the project area
Following are the mitigating measures to reduce the impact
• The project will support the existing educational institution in the project area to
provide education to the project workers and staffs
• The project will support existing health institution in the project area to upgrade its
capacity
• The project will establish Project Health Unit (PHU) within the premise of the project
for its staff and construction worker. Such a unit will also provide free of cost service
to the local area people. The project will employ a health assistant and an ANM in the
PHU for the treatment.
• The project will establish a self standing water supply system for the project camp
facilities without impinging upon the community supply system
• The project will establish self standing communication facilities for the project staff
and workers in project camp
• The project will request CDO of the Solukhumbu district to establish a Police Post to
ensure law and order in the local area and financially support to such posts
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
147| P a g e Department of Electricity Development
vii. Possible interference with village trails
Following are the mitigating measures to reduce the impact
• As far as possible the waterway structures will be aligned so as to avoid the existing
foot trails.
• The project will construct alternative foot trails in replacement of the foot trails which
will be interfered by the waterway structure.
• Wherever possible, as allowed by the topography, the headrace as well as penstock pipe
will be buried underground so that the impact on interference with the foot trails could
be minimized.
viii. Occupational health and safety related issues
Following are the mitigating measures to reduce the impact
• The project will establish a Project Health Unit (PHU) within the premise of the project
for its staff and construction worker. Such a unit will also provide free of cost service
to the local area people. The project will employ a health assistant and an ANM in PHU
for the treatment of ills. There will be provision of medical stocks and other support
facilities in the PHU of the camp to stabilize the conditions of injured prior to shifting
to the nearby hospital outside (Damku/Salleri/Kathmandu) the project area. An
ambulance will be provisioned standby at the PHU for the service of injured and ills.
• The project will make the Contractor to prepare health and safety plan for the project
workers approve it and monitor its implementation by the Contractor.
• First aid facility in each of the construction sites will be provisioned with instructions
of use.
• Emergency fire fighting systems will be provisioned in the camps and the construction
areas.
• Personnel protective equipments such as helmets, gloves, boots, mask, ear plugs, safety
belts etc. as to the requirement of the construction work nature to each of the
construction workers and supervisors will be provided. Workers without required PPEs
will not be allowed to enter in to the construction site.
• The project will make the Contractor to organize regular safety instruction and safety
drills prior to, during and after the working hours in a routinely manner
ix. Issues relating to public health and sanitation and as well as public safety
Following are the mitigating measures to reduce the impact
• The Contractor will make provisions for checking health status of the worker he wants
to employ. Workers with contagious diseases will be discarded from employment.
• The project will launch community awareness program on sexually transmitted disease
and ways to prevent such disease apart from medication from the camp hospital.
• The project will distribute condoms at nominal price to the workers and locals through
the health serve facilities of the camps
• The project will launch community awareness program on communicable disease and
ways to prevent such disease
• Health status of project workers and community people residing nearby the project
construction and facilities sites will be monitored periodically. Health camps will be
organized once in every six months in the project area.
• Hoarding boards, and traffic signs in the critical points in road corridor will be placed
and awareness campaigns will be conducted in the project area
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
148| P a g e Department of Electricity Development
• Signboards with signs on different construction related activities will be placed in the
entrance of the construction sites. Danger boards will be placed in critical danger areas
in the construction sites
• All the construction sites will be fenced and unauthorized persons will not be allowed
in the construction sites.
• Sirens will be blown 10 minutes before and 5 minutes after surface blasting for public
safety. All foot trails will be blocked for public movement at the time of blasting
operations
• All visitors in the construction site will be instructed to wear protective gears
x. Socio cultural issues such as community conflict with the outside work force
Following are the mitigating measures to reduce the impact
• The project will organize regular ethical behavioral programs to outside workers before
work session to respect local people, their culture and traditions
• The project will discourage alcohol consumption in the public places outside the camp
areas by putting penalty to the project workers
• Gambling in the project area premises will be strictly prohibited.
xi. Issues relating to increased gambling, alcoholism and prostitution
Following are the mitigating measures to reduce the impact
• The project will organize regular ethical behavioral programs to outside workers before
work session to respect local people, their culture and traditions
• The project will discourage alcohol consumption in the public places outside the camp
areas by putting penalty to the project workers
• Gambling in the project area premises will be strictly prohibited.
(ii) Operation Phase
i. Occupational health and safety related issues of the power station workers
Following are the mitigating measures to reduce the impact
• Occupational health and safety plan (OHSP) specific to operation and maintenance
phase of the project will be developed incorporating plans to deal with safety in
powerhouse as well as maintenance activities shall be developed and implemented.
Compliance of the implementation of the measures recommended in the plan will be
monitored periodically.
• Safety signs, warning symbol boards will be placed in powerhouse complex. Road
safety symbols will be maintained at key points.
• Powerhouse workers will be equipped with all necessary safety equipments.
• Emergency fire fighting system will be provisioned in the camps and the powerhouse
complex
• Powerhouse workers will be made aware of the safety issues inside the powerhouse.
ii. PublicSafety Related Issues/Movement of people in dangerous places
Following are the mitigating measures to reduce the impact
• All dangerous sites such as switch yard will be fenced as a precautionary measure to
restrict people's movement in the area;
• Safety signs and posts will be erected at critical areas; and
• Local people will be made aware of dangerous project areas.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
149| P a g e Department of Electricity Development
iii. Issues relating to upstream and downstream (dewatered stretch of the Dudh Koshi
River) water uses and conflicts
• The project will arrange an alternative cremation ground upstream from the proposed
weir site with facilities such as cremation platform, steel truss hut etc.
• Similarly, implementation of the proposed Dudh Koshi hydropower will affect
downstream purpose Dudh Koshi-4, hydropower headworks at ward-4. The proposed
Dudh Koshi -4 hydropower activities will be carried out at about 200m-500m
downstream from the proposed power house and switchyard of Dudh Koshi 5 HPP. The
project has a plan to coordinate with Dudh Koshi -4 HPP.
iv. Issues relating to sudden release of water to downstream
During the operation phase, the sudden release of water downstream of the headworks may
cause accidents. Thus, as a mitigation measure, a siren system will be established to make
the downstream people aware about the timings of the release of water. Similarly, local
people will be made aware about the siren system.
v. “Boom Town” effect and its impact on local economy
Upon the completion of the project, most of the skilled labour will lose jobs. They will not
be able to utilize their skills locally. In order to maintain their economy through the utilization
of their skills, they will have two options: either, they have to leave the area and go elsewhere
in search of jobs that match their skills or they have to remain in the local area and find jobs
which are locally available.
In order to mitigate such kind of trauma of job loss after the project, the following measures
will be adopted by the project:
• The project will try to appoint maximum number of local people as far as possible
during the operation period;
• Training sessions will be conducted at least 3 months prior to the project completion,
so that the labour force will be able to start their own businesses immediately upon the
termination of their jobs in the project;
• Training programs will be organized particularly targeting the skilled labour force
willing to establish their own entrepreneurship, where they can utilize their skills and
make a living; and
• Possible efforts will be made by the project to help the trained and interested local
human resource obtain employment in new hydroelectric projects.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
150| P a g e Department of Electricity Development
8. ENVIRONMENTAL MANAGEMENT PLAN
8.1 Introduction
The Environmental Management Plan (EMP) has been prepared as an integral part of
Dudhkoshi-5 Hydropower Project to set out the procedural framework to ensure the
implementation of mitigation measures, monitoring and auditing requirements. The plan
specifies the environmental responsibilities of all parties involved in the project, and detail
environmental management requirements for the project during the pre-construction,
construction and operation phases. The plan also specifies the coordination mechanism with
various line agencies, non-project participants and schedule. The monitoring component
likewise defines the monitoring mechanism, reporting etc. Similarly impact audit define the
auditing parameters and responsibility. The project proponent will be responsible for the
implementation of the EMP. The plan will apply adaptive management to accommodate
changes in project design during the time. The EMP will follow Plan – Do – Check Act Cycle
(PDCA) approach. The EMP will be updated during the detail design to cover the likely
changes in project design, likely changes in policy and regulatory mechanism and stakeholder
concerns.
8.2 Planning
8.2.1 Stages for the Implementation of Environment Protection Measures
The environmental protection measures (EPMs) will be implemented during the pre-
construction, construction and operational and maintenance stages of the project. The
implementation of EPMs will be the responsibility of the proponent. All preparatory activities
related to site clearance including the necessary permission from the relevant government
organization(s) as well as land and property acquisition will be completed during the pre-
construction stage. In this stage, the project will delineate the actual area to be acquired for the
project activities, negotiate with the land and property owner(s), and compensate for the lost
resources. In case of government land, the project will request the government for leasing out
required land. The project will negotiate with the community forest user groups for the
temporary use of their land following the government procedure. As these are basically related
to the pre-construction stage, the project will not be implemented without completing these
pre-requisites. Similarly, the design will be undertaken by adopting the basic civil engineering
design principle for the environmental protection (for example design of the access road in
balance depth, connecting outlet of the drain to the natural drain, providing bio-engineering
measures for covering the exposed area due to excavation etc.). To be specific the detailed
design will consider all the proposed mitigation measures in this EIA report. A detail
Environmental, Social and CSP Action Plans of the Project is presented in Table 8-1 to Table
8-11.
Table 8-1: Awareness, Orientation and Training Plan
SN Actions Target Groups Schedule Responsibility
1
Leaflet/flyers/brochures be
prepared in different
languages to make aware of
project and its surrounding –
environmental affairs (e.g.
Construction
crew and other
stakeholders
Construction
phase Employer
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
151| P a g e Department of Electricity Development
SN Actions Target Groups Schedule Responsibility
dos & don’ts for labors on
terrestrial and aquatic
environment viz. forests fires)
2 Orientation and Environment
Training
Project decision,
Project
Management and
Contractor team
Pre-construction
Employer in co-
ordination with
Experts as needed
3
Orientation and Environment
Trainers Training with focus
on mitigation and monitoring
actions (EMP
Implementation) including
satefy requirements
Section staff of
Environment
Management
Unit of Employer
and Contractor
Pre-construction
Employer in co-
ordination with
Experts as needed
4
Orientation and environmnt
training to the project
operators on oil handling,
storage, and recycling, safety
and emergency prepardness
Project operation
team
At the begining of
the operation
phase
Employer in co-
ordination with
Experts as needed
5
Importance of inclusion of
EA prescription in the tender
document
Employer, its
representative
and Contractor
Approval of the
project
implementation
Employer, its
representative and
Contractor
Table 8-2: Permit and Approval Plan
SN Requirements Authority Implementation
Time
Responsibility
1 EIA approval MoFE Feasibility Stage DoED
2 Tree clearing from community
forest
DFO and MoFE Pre-construction DK-5
HPP/EMU/GRU
3 Permanent land acquisition Land
owners/CDO
Pre-construction DK-5
HPP/EMU/GRU
4 Land lease agreement for
temporary facilities
Land
owners/CDO
Pre-construction DK-5
HPP/EM/GRU
5 Entry to private land and
property, if required
Land owners Pre-construction Contractor
Note: CDO = Chief District Officer, DFO = Division Forest Office, EM and GRU:
Environment Management Unit and Grievance Redress Unit
Table 8-3: Resettlement and Rehabilitiation Plan
S.N. Action Timing of Action Responsibility
1 Re verification of the owners of the land to be
acquired permanently including their affected
land areas, land plot numbers and
landownership
DK5 HPP
Project
Management
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
152| P a g e Department of Electricity Development
S.N. Action Timing of Action Responsibility
Identification of the household or parties
traditionally using land without land
certificates in case of acquisition /lease of such
land
Pre-construction (6
months before
construction)
2 Negotiation with concerned land owners
regarding the amount to be paid
3 Handling of grievances of the affected parties
and individuals (formalities of Grievance
Redress Mechanism)
Pre-construction and
construction
Dk 5 HPP
Project
Management /
EM and GRU/
LC
4 Monitoring of the implementation of R&R Pre-construction and
construction
EMU/ Joint
Monitoring
Committee/
Panel of Expert
Notes: LCF: Local Consultancy Forum EMU: Environmental Management Unit
Table 8-4: Construction Camps and Traffic Management Plan
S. N. Activities Timing of
actions
Responsibilities
1 Pre-information to the local area people on
the start date of project preparation works
and the range of activities to be undertaken
Pre-construction Dk 5 HPP PMO/ EM and
GRU
2 Preparation of environmental management
plan for the construction camps (issue based
and site based)
Pre-construction Contractor
3 Site clearance and construction plan for
construction camps (engineer, contractor,
labor force, mechanical yards, long term
storage facilities etc) with plans to save top
soil for later use
Pre-construction Supervising engineer/
EMU/ Contractor
4 Preparation of a Guideline for construction
vehicle operation (speed, use of horn,
parking on the road and off the road etc.)
and meet pollution criteria green stickers
Pre-construction Supervising engineer/
EMU/ Contractor
5 Preparation of sites for parking of the
project vehicles, material storage and
staying facilities for the early construction
workers/contractors with adequate facilities
of water supply, drainage, cooking, dining,
toilets, solid waste collection and storage
etc.
Construction Contractor
6 Construction of camps and facilities Construction Contractor
7 Monitoring of related activities pre-construction and
construction
Supervising engineer/ EMU
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
153| P a g e Department of Electricity Development
Table 8-5: Pollution Abatement Plan
S. N. Activities Timing of actions Location Responsibilities
1
The earthen and graveled road corridors will be sprinkled
regularly to minimize the fugitive dusts from the plying of
the construction related vehicles particularly in the winter
and Sumer dry season.
Pre-construction Headworks area, powerhouse
area and adit area to spoil
disposal site.
Contractor
2
The aggregate crushing sites and active construction sites
will also be sprinkled regularly by water as to the
requirement on the advice of supervising engineers/
Environmental Monitor
Construction Aggregate crushing site, and
active construction sit
Contractor
3
The occupational workers at the construction sites, engineers
and supervisors will be provided with PPE (air masks,
helmets and safety goggles as per the standard guideline)
Pre-construction,
Construction period
All construction sites
Contractor
4 Ventilators of adequate capacity for ventilating the tunnel
area during blasting and mucking period
Construction period
Adit portals to tunnel Contractor
5
The sites for surface structure and all project facility sites
(camps, mechanical yards, storage facilities, muck disposal
sites etc.) will be facilitated with temporary drainage
facilities to collect and discharge the runoff water after
required treatment (sedimentation and oil and grease
removal) safely to the natural water bodies.
Pre-construction,
Construction period
All camp and facility sites Contractor
6 Discharge of construction waste such as cement, and
concrete slurry will not be discharged to the river water.
Construction period Headwork, powerhouse Contractor
7
The water discharged from aggregate washing plant will be
collected in settling tanks/ponds at suitable location for
sedimentation and treatment
Construction period Aggregate waste water discharge
point
Contractor
8
All spent grease and mobil and unused or date expired toxic
chemicals will be collected separately in plastic drums and
stored in a safe place under the shade
Pre-construction,
Construction/ operation
All construction sites, camps and
other facility sites/operation
Contractor/ Operation
manager
9
The unused chemicals, spent mobil, grease etc. will
discharged only with the approval of the chief of the
Environmental Monitoring Unit
Pre-construction,
Construction period
All construction sites, camps and
other facility sites
Contractor
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
154| P a g e Department of Electricity Development
10
The petroleum bunkers will be placed in a separate area in a
concrete bounded area with the facility of oil and grease
separator
Pre-construction,
Construction period
Storage yards Contractor
11
The waste water from the mechanical yards will be collected
in a separate area. The water will be treated for the oil and
grease and then released to the water bodies.
Construction period Mechanical yard waste water
discharge point
Contractor
12
Provisioning of adequate toilet facilities will be made in the
camps and active construction sites. The toilet waste of the
camps will be drained to a single treatment facility in each
camp. The treated water will only be released to the nearby
area.
Pre-construction,
Construction period
All camps and active
construction site
Contractor
13
Open defecation will be prohibited in and around the
construction sites, camp sites and in the river bank area.
Hoarding sign boards will be placed in the construction
camps, and active construction sites.
Pre-construction,
Construction period
In areas surrounding the
construction sites
Contractor
14
A solid waste collection and storage system will be
established in all the construction related camps and
construction sites. The collected waste will be segregated as
to the property of the waste as degradable, glass, metals,
plastics, cloths and leather etc and will be stored in separate
bounded areas. These materials will be disposed as to the
recommendations and approval of the project environmental
officer
Pre-construction,
Construction /operation
All camps and active
construction sites/Operation
camps
Contractor/ Operation
Manager
15
Garbage containers of adequate size will be placed at critical
places in the construction related camps and construction
sites. The collected garbage will be collected daily for
segregation and storage as outlined above
Pre-construction,
Construction/ operation
All camps and active
construction sites/Operation
camp
Contractor/ Operation
Manager
16
Stockpiling and storage of the construction materials in
designated sites only away from the water paths. Prohibition
on the stockpiling of construction materials in other areas
Pre-construction,
Construction period
All camps and active
construction sites
Contractor
17
Muck disposal will be carried out in the designated sites
only. Prohibition of muck disposal in other non-designated
area
Construction period All camps and active
construction sites
Contractor
18 Operation of noise generating construction activities in the
day time zone as far as possible
Pre-construction,
Construction period
All camps and active
construction sites
Contractor
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
155| P a g e Department of Electricity Development
19
Prohibition on surface blasting operations in the day time
zone only. Prior information will be given through siren
blow 10minutes before the blasting operation and 10
minutes after the blasting operation
Construction period
Tunnel, headwork, and
powerhouse
Contractor
20
Regular maintenance of the vehicles to reduce the
mechanical and body noise while plying
Pre-construction,
Construction period
All vehicle and machinery Contractor/
Supervising engineers/
Proponent
21
Prohibition in the blowing of horns in critical stretches close
to villages and near the school area along the road
Pre-construction,
Construction period
Villages and school areas
Contractor/
supervising engineers/
Proponent
22
Fitting of noise reducing equipments in the ventilators
compressors and diesel generator sets
Pre-construction,
Construction period
Ventilator compressors and
diesel generator sets
Contractor
23 Fitting of noise reducing equipments in the ventilators
compressors and diesel generator sets
Pre-construction,
Construction period
Ventilator compressors and
diesel generator sets
Contractor
24
Compliance monitoring of A, B and C Construction/ Operation All above sites EMU/ Supervising
engineers/ Operation
Manager
25
Impact Monitoring related to A, B, and C
Construction/ Operation All above sites EMU/ Supervising
engineers/ Operation
Manager
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
156| P a g e Department of Electricity Development
Table 8-6: Terrestrial Ecology (Forest Loss Management) Management Plan
S. N. Activities Timing of Action Location Responsibilities
1 /fli6«o k|fyldstf k|fKt cfof]hgfsf] nflu /fli6«o jg If]q k|of]u ug{
lbg] ;DalGw sfo{ljlw, @)&$
• Consultation with the DFO, local community and forest
user groups to identify the required area for
compensatory afforestation
• Seedling preparation or procurement
• Plantation of at least 87850 seedling in the afforestation
area as per forest norms
• Taking care of the plantation area for 5 years to ensure
that the planted trees or deposit the required amountto the
division forest office to grow to sufficient height
• Handover the afforested area to thedistrict forest office
after 5 years
Construction and
Operation
Area as designated
by committee
DK5HPP/EMU
2 Preference to the local for project employment as
mentioned in mitigation section
Preconstruction,
construction
All project works
Dk 5 HPP Project
Management/ contractor/
Supervising engineers/
Operation Manager
3 Provision of LPG or kerosene to the outside workforce for
cooking/heating
Preconstruction,
construction
Construction workers of
all project sites
Contractor
4 Provision for camp lodging to the outside workforce with a
common cooking facility
Preconstruction,
construction
All outside construction
workers
Contractor
5 Prohibition on the sale and purchase of the local NTFP and
fishes in the camps
Preconstruction,
construction and
operation
All project locations Contractor/ Supervising
engineers/ Operation
Manager
6 Prohibition in roaming in the local forest area by the
outside workforce
Preconstruction,
construction and
operation
Surrounding areas of
project site
Contractor/ Supervising
engineers/ Operation
Manager
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
157| P a g e Department of Electricity Development
S. N. Activities Timing of Action Location Responsibilities
7 Lease Compensation to the Forest Land Area Construction,
operation
All permanently
occupied forest areas
DK-5 HPP Project
Management
8 Clearing of the forest vegetation and stockpiling the
vegetation products before handover:
construction All permanently
occupied forest areas
Environmental Monitoring
Unit/ DK 5 HPP project
management
9 Implementation of training, NTFP and other forest related
programs
construction Project affected
community forest
EM and ERU
10 Project will inform in time to the local authorities,
Ward/Rural Municipality representative, Community forest
user groups and the forest range post office, if it finds the
forest area is encroached close to the construction site
construction Surrounding forests of
the project site
EMU/DK-5 HPP project
management
11 Hoarding boards will be placed at critical location of the
district road , project component road and other public
places on the preventive actions to control the forest fire
Construction
Surrounding areas of the
project site
EM and ERU/ DK-5 HPP
project management
12 Public awareness programs will be launched to prevent the
forest fires in the local area
Construction Surrounding areas of the
project site
EM and ERU
13 Project workers will be regularly informed not to throw
lighted cigarette tips in the forest areas and not to use forest
area as picnic spots
Construction Surrounding areas of the
project site
EM and ERU/ Environmental
Monitoring Unit
14 Compliance and impact monitoring of the related activities Construction/
operation
All sites as designated Environmental Monitoring Unit
Table 8-7: Aquatic Ecology Management Plan
S.N. Activities Timing of Action Location Responsibilities
1 Restriction on fishing activities by the construction
workforce on the Dudh Koshi River Preconstruction and
construction
Dudh Koshi River
headworks to Powerhouse
Environmental
Monitoring Unit
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
158| P a g e Department of Electricity Development
S.N. Activities Timing of Action Location Responsibilities
2 Water and land pollution abatement Pre - construction,
Construction and
operation
All project sites as
designated
Environmental
Monitoring Unit/
Contractor
3 Restriction on the use of pesticides, electrical gears and
explosive for fish capture in Dudh Koshi River Pre - construction,
Construction and
operation
Reservoir to powerhouse
tailrace
Project RMC
authorities,
District
Agriculture
Office and Local
NGOs
4 Complete prohibition on the discharge of muck/spoil into
the river Construction All construction sites Contractor
5 Design the provision of releasing 10% of the minimum
monthly flow as a inbuilt structure of the weir and ensure
that the structure is constructed
Design weir Design Engineer/
Supervising
engineers/
6 Monitoring of relative activities Pre-
construction/construction
and operation
All project site Environmental
Management unit
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
159| P a g e Department of Electricity Development
Table 8-8: Erosion Abatement and Muck/Spoil Management Plan
S. N. Activities Timing of Action Location Responsibilities
1 While preparing the site for construction of project
component roads, camp, etc, the top soil will be managed
separately and saved in a separately for later rehabilitation
works
Pre-construction/ Construction
All project sites Contractor
2 All surface excavation above 3m vertical height will be
excavated through benching.
Construction
All project sites
Supervising
Engineer/Contractor
3 Potential landslide and soil erosion will be controlled
through:
• Pegging and flagging on the boundaryof the landslide
area
• Maintenance of slope less than theangle of response
• Provision of proper drains
• Bio-engineering measures on landslide
• Grass turfing on gentle slope andconcreting on the steep
slope withbenching height >3m & proper drainage
Preconstruction
andconstruction
Projectarea
Contractor
4 The excavated surface will be protected againstthe water
erosion by adequate vertical andhorizontal drainages and
the water collectedfrom the excavation area will be
discharged into safe area.
Construction All project sites Supervising Engineer/
Contractor
5 All excavated areas and spoil deposited areas will be
stabilized by civil and bio-engineering works.
Construction All project sites Contractor/DK5HPP
6 Stockpiling and storage of the constructionmaterials will be
done in designated sites only.
Prohibition on the stockpiling of constructionmaterials in
other areas.
Construction Allprojectsites Contractor
7 Muck disposal sites will be carried out in the designated
sites only.
Prohibition of muck disposal in other non-designated areas.
Construction
All project sites
Contractor
8 Prior to the start of spoil disposal, thecontractor will make a
plan for spoil disposaland get approval from the
Construction Designated spoil disposalarea EMU/Contractor
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
160| P a g e Department of Electricity Development
S. N. Activities Timing of Action Location Responsibilities
projectenvironmental officer. The plan, among others, will
have measures for toe protection from the monsoon
washout.
9 The muck deposited will be properly compacted and will
be facilitated by surface runoff drainage facilities to avoid
air pollution and run off erosion.
Construction Spoil disposal area Contractor/
DK5HPP
10 The excavated surface will be protected against the water
erosion by adequate vertical and horizontal drainages and
the water collected from the excavation area will be
discharged into safe area.
Construction Spoil disposal area Contractor/
Supervising Engineer
11 All project facility sites (camps, mechanical yards,
storage facilities muck disposal sites etc.) will have
drainage facilities to collect and discharge the runoff
water safely to the natural water bodies
Construction All project sites Contractor/
Supervising Engineer/ EMU
12 The access roads will have permanent side drain structures
to collect water from the upslope area. The collected water
of the side drains will be discharged to suitable natural
waterways to avoid upstream and downstream erosion.
Construction Access roads Contractor
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
161| P a g e Department of Electricity Development
Table 8-9: Public Health and Occupational Safety Management Plan
Activities Timing of
Action
Location Responsibilities
Implement Pollution
Abatement Plan
During
construction
All project sites Contractor
Preparation of occupational
health andsafety plan and
submission to EMU of
DK5HPP for approval
Pre-
construction
All project sites
and all workforce
Contractor
Provision of First aid
facilities
Construction
phase
All active construction
sites and yards
Contractor
Medical checkup of the
workforce before
employment
Construction
phase
Allconstruction
workers
Contractor
Regular medical checkup of
the
construction workers every
6 months
Construction
phase
Allconstructionworkers Contractor
Sopport to Health facilities
(intermittenthealth camps,
strengthening health
postnearby the project) to
local public as per the CSP
Construction
phase
People ofproject area
Contractor/
DK5HPP
Potable water supply facility Construction All project camp Contractor
Establishment
ofconstruction waste
collection system and
management
Construction All activeconstruction
sites
Contractor
Fencing of all construction
sites and restriction on entry
to the outsiders
others than authorized
person
Construction All activeconstruction
sites
Contractor
Appropriate danger signs in
all active construction sites
work areas as to the degree
of risk in the site
Construction All activeconstruction
sites
Contractor
Provision of Personal
Protective
Equipment (such as boots,
gloves, masks, ear plugs,
helmets, safety goggles etc.)
tothe construction workers
as appropriateto the
Construction All activeconstruction
sites
Contractor
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
162| P a g e Department of Electricity Development
requirement and risk of
theworking area and
implement the
useeffectively
Regular training as required
to the
construction workers and
health and safety issues of
the construction work
Before and
during
construction
Allconstructionworkers Contractor
Regular training to
operation staff asrequired on
occupation health and safety
issues
Operation Allconstructionworkers
Contractor
Insurance of workers Pre-
construction
All workers Contractor
Table 8-10: Rehabilitation Management Plan
Activities Schedule Location Responsibilities
Rehabilitate the excavated slopes
of the
construction areas using
appropriate bioengineering,
plantation/vegetation
Postconstruction
Access roads,
headworks, adit
and penstock
area,
powerhouse,
tailrace
Contractor
Rehabilitation the drainage
networks as
to the requirement (some area
might need
strengthening while in some it
might
have to demolish completely to
give the
land and drainage the natural
condition)
Postconstruction Access roads,
headworks,
camps, storage
area,
powerhouse,
spoil disposal
sites etc.
Contractor
Demolition of all unnecessary
structures, their foundations,
clean up and reclaim
the sites to pre-construction
phase
Post-
construction
Temporary
residential
camps, storage
yards,
mechanical
yards, batching
plant, aggregate
crushers,
aggregate
Contractor
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
163| P a g e Department of Electricity Development
washing plants,
etc.
Rehabilitation the muck disposal
site withproper drainage facility as
per approvedplan. Use the saved
top soil on the top of the spoil
sites to develop the land in an
usable land for afforestation or
other purpose as per the
recommendation of the EMU
Postconstruction Spoil
disposalsite
Contractor
Rehabilitation of the quarry area
in such that puddles and
depressions are not left out
Postconstruction
Quarry area Contractor
Rehabilitate the temporarily
acquiredcultivable land by tilling
and spreading the top soil saved.
Postconstruction Temporarycamp
and storage area
Contractor
Handover the temporary land
acquired sites to the respective
owners and get a certificate of
handover
Postconstruction Labour camps Contractor
Table 8-11: Emergency Management Plan
Activities Schedule Location Responsibilities
Provision of helipad for
emergency
evacuation of injured or other
people
Preconstruction Construction sites Contractor/
DK5HPP
Provision of standby
ambulance to
evacuate the injured at the
earliest to the nearest hospital
Construction
Powerhouse
&Headworks area
Contractor/
DK5HPP
Provision of medical stock
particularly for water borne
disease to tackle theepidemic
in the camp or in the villages
surrounding the project site
Construction
Health care
facility at project site
Contractor
Provision of firefighting
equipment and regular fire
fighting training as needed
Construction Construction
sites
Contractor
Provision of sirens to inform
people of
the emergencies (fire
hazards, blastingoperations,
chemical hazard,
trafficaccidents, earthquake
etc.) and drill operations at
least once in 6 months
Construction
Powerhouse,
camp sites,
headwork, adit
portals
Contractor
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
164| P a g e Department of Electricity Development
Emergency preparedness
training and on drill
operation (GLOF, floods,
release of waterfrom weir,
epidemic outbreak,
earthquakeetc.) at least every
6 months
Operation All
projectsite/powerhouse
and headworkand
dewatered stretch
Operation
Manager
8.2.2 Implementation Approach and Mechanism
(i) Project Stakeholders for Environmental Management
Key stakeholders including DK 5 HPP, to be involved for project environmental management
in hierarchy orders are:
• Ministry of Forests and Environment (MoFE);
• Ministry of Energy, Water Resources and Irrigation (MoEWRI);
• Department of Forest;
• Department of Environment
• Construction Management/Supervision Consultant;
• Project proponent
• Environment Monitoring Unit
• Environment Management and Grievances Redress Unit
• Local Consultative ForumContractor;
• Local level Government and non- government organizations such as District
Coordination Committee, (DCC),
• Division Forest Office (DFO),
• Mapya Dudhkoshi Rural Municipality (RM),
• NGOs and Community based Organizations (CBOs).
(ii) Institutional Arrangement and Responsibility
a) Project Manager Office
The DK 5 HPP Project Manager Office will be established under the organizational setup of
the Project. The Project Manager will have overall responsibility regarding the implementation
of EMP including others. He will be also responsible for acquiring necessary permits for forest
clearance from Ministry of Forest and Environment, land acquisition and compensation etc.
The Project Manager will be responsible to make sure the incorporation of EIA
recommendations in tender document and contract agreement and allocation of necessary
budget for the implementation of EMP.
b) Dudh Koshi-5 Environment Managementand Social Development Unit (DK 5
HPP-EMSDU)
Local consulting firm will be assigned for environment monitoring of the project. The
consulting firm will establish Dudh Koshi-5 Environment Monitoring Unit for day to day
environmental monitoring of the project, implementation of monitoring plan and coordination
of work with concerned stakeholders. The unit will work for Project Manager Office and the
cost required for the establishment and operation of the unit will be provided by the PMO.
The following human resources will be deployed in DK 5 HPP -EMSDU.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
165| P a g e Department of Electricity Development
• Environmental Expert/Unit Chief
• Ecologist/ Forest Expert
• Wildlife expert
• Socio-economist
• Field Technician/Supervisors-2
• Support staff – 1
c) Environment Management and Grievances Redress Unit (EM & GRU)
Environment Management and Grievances Redress Unit will be established under the Project
Organizational setup. This office will be under direct supervision of PMO. This unit will have
three sections namely Land Acquisition and Rehabilitation Section (LARS), Project
Information Center (PIC) and Mitigation Implementation Section (MIS). All three sections
have unique responsibility regarding the implementation of different action. LARS will be
responsible for the implementation of land acquisition and rehabilitation program whereas
public disclosure work will be conducted through PIC. The MIS will implement mitigation
measures proposed in Chapter 7 especially the program proposed in biological and
socioeconomic environment. The MIS will coordinate the work district level line agencies such
as Division Forest Office, District Coordination Committee, District Land Revenue etc.
d) Construction Contractor
The construction contractor will be responsible for implementation of mitigation measures
specified in the part of contractor and compliance with the tender clauses. The contractor will
be responsible for the implementation of spoil disposal, waste management, occupational
safety, structural bioengineering measures, air, noise and water quality protection measures,
etc.
e) Construction Management/Supervision Consultant
The coordination of the compliance monitoring and mitigation program allocated under the
contractor will be the responsibility of Consultant. Environment Monitoring Unit of the project
will work for the monitoring of compliance issues and report to the Project Manager. The
project manager delivers the written message to the Consultant for prompt action. He will have
authority to stop work fully or partially; delay in payment or otherwise penalize contractors for
of non-performance of environmental tender clauses. The Consultant will also be responsible
for the supervision and quality control of the works conducted by the DK 5 HPP-EMU and
Contractor. The Consultant will also have responsibility for the approval of Environment
Protection Plan, Health Safety Plan, Waste Management Plan and Muck Disposal Plan
prepared by the Contractor on recommendation of DK 5 HPP EMU chairman of project
affected RMC, representative of principle of local high school, NGOs, DK 5 HPP-EMU, EM
and GRU and PAFs will be the member of committee. Committee will promptly act to resolve
the social and environmental issues related to project.
f) Local Consultative Forum
A Local Consultative Forum (LCF) will be established to address the grievances regarding
compensation and other social and environmental issues. This committee will work as an
independent body and will have separate office within the project area. The logistic support
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
166| P a g e Department of Electricity Development
required for the operation of this office will be provided by the Project Manager Office. The
committee will be headed by social worker respected in the community, RM chairman of
project affected RM, representative of principle of local high school, NGOs, DK5 HPP-EMU,
EM and GRU and PAFs will be the member of committee. Committee will promptly act to
resolve the social and environmental issues related to project.
g) Joint Monitoring Committee
To ensure the proper implementation of mitigation measures and monitoring work a joint
monitoring team will be formed which will monitor the activities of the DK5 HPP-EMU, EM
& GRU and Contractor on periodic basis. This monitoring team will be coordinated by the
project central office Kathmandu. Coordination with line ministries (MoFE and MoEWRI) is
required during monitoring works. The committee will include the representative of district
level line agencies (DCC, DFO, Agriculture Development Officer, District Administration
Officer, Education and Health Officer), representative of local club and mother group.
8.2.3 Reporting
DK5 HPP-EMU will be responsible for the preparation of Environmental Management Reports
whereas EM & GRU will prepare quarterly progress report regarding the implementation of
mitigation and enhancement program. The Project Manager Office (PMO) will be responsible
for the distribution of report to the concerned agencies. The DK 5 HPP-EMU will prepare the
following reports: -
(i) Pre-construction Environmental Report
This report will be prepared prior to start (just before start) of construction work. The report
includes the changes in baseline situation and site condition prior to start of actual construction
work. The Environment Management Plan will be updated during this period.
(ii) Construction Phase Environmental Report
The construction phase environmental report will be prepared on quarterly basis and annual
environmental report will be prepared at the end of each calendar year. A final environmental
report will be prepared after the completion of the construction work. DK 5 HPP-EMU will be
responsible for the preparation of report. The report will be distributed to Ministry of Forest
and Environment, Ministry of Energy, Water Resources and Irrigation, Department of
Electricity Development and district level line agencies.
(iii) Operation and Maintenance Phase Environmental Report
Operation and maintenance phase environmental report will be prepared for the two years
following the construction. DK 5 HPP-EMU will prepare this report for project. The report will
describe mitigation measures, problems and recommended solution. The report shall clearly
identify where operational mitigation measures are not being met or where mitigation efforts
are inadequate to protect natural and socioeconomic resources. Unanticipated deleterious
impacts of the projects will be clearly identified. Measures to solve problem will be proposed
and be funded under the project annual operating budget. The environmental audit report will
be prepared by MoFE as per EPR 97.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
167| P a g e Department of Electricity Development
Figure 8-1: Organogram of the Environmental Management Unit for Dudhkoshi-5
Hydropower Project
8.2.4 Monitoring Implementation and costs
The environmental monitoring works will be implemented by the Dudh Koshi-5 HPP
Environmental Management Unit (DK-5 HPP EMU) (Refer Section 10.3 and 10.4 of Chapter
10). The cost for baseline monitoring is estimated in below table. The compliance monitoring
will be conducted by the DK-5 HPP EMU team, the cost of which will be included in operation
cost of DK-5 HPP EMU (remuneration of DK-5 HPP EMU staff). Similarly, apart from DK-5
HPP EMU team of staffs, impact monitoring requires expertise from various fields which will
be hired as and when required. Such expert human resource may be required in the field of GIS
mapping, fisheries, and environmental pollution etc. Costs required for environmental
monitoring is provided in Table 8.12.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
168| P a g e Department of Electricity Development
Table 8-12: Implementation Cost for Social and Environment Protection Measures
S.
N.
Mitigation Action Estimated
Cost (NRs)
Remarks
A Physical and Biological
Environment
A1 Construction Phase
Reclaiming of the muck disposal area and
quarry site area 1,000,000.00
The amount is included in the
Project Cost
Prior survey of house structures along the
tunnel alignment
300,000.00
Survey of spring location and discharge
measurement
200,000.00
Temporary water supply arrangements in
the event of the effect on used springs 500,000.00
Bio-engineering works for slope
stabilization
500,000.00 The amount is included in the
Project Cost
Compensatory plantation of 87850
seedlings as per the Work Procedure
Regarding Use of National ForestArea for
Projects of National Priority, 2074,
calculations as per forest norms
25,234,818.00
Compensation to the lost forest area as per
the Forest Act The amount is included in the
Project Cost
Clearance and stockpiling of the felled
forest products
200,000.00
Combined supervision with the official of
DFO/CFUGs to mark trees and poles for
felling
400,000.00
Technical and financial assistance (forest
conservation programs, awareness
campaigns, etc.) to the affected forest user
group
1,000,000.00
Hoarding boards costs at critical locations
and near the project facilities on the
preventive actions
100,000.00
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
169| P a g e Department of Electricity Development
S.
N.
Mitigation Action Estimated
Cost (NRs)
Remarks
Public awareness programs on
conservation and forest resource
management in the local area
250,000.00
Public awareness programs with
firefighting training to prevent the forest
fires in the local area
200,000.00
Sub-Total (A1) 29,884,818.00
A2 Operation Phase
Bio-engineering works for slope
stabilization
500,000.00 The amount is included in the
Project Cost
Hoarding boards at critical locations and
their maintenance to generate awareness to
the visitors on the significance of forests
and wildlife of the area
100,000.00
Release of 500,000 fingerlings @ 100,000
fingerlings per year is proposed for 5 years
in upstream of Dudhkoshi River weir
5,000,000.00
Sub-Total (A2) 5,600,000.00
B Socio-economic and Cultural Impacts Mitigation
B1 Construction Phase
Compensation for loss of private land
(4.133 ha)
123,563,672.00 The amount is included in the
Project Cost
Temporary lease of land during
construction period
Contractor will be made
responsible for this
Compensation for loss of crop production
(one-time compensation during permanent
acquisition of land)
373,270.00
Compensation for loss of trees from
private land
500,000.00
Hiring security guards for securing project
facilities
Contractor’s Overhead
Rehabilitation of religious and cultural
resources (Cremation sites)
800,000.00
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
170| P a g e Department of Electricity Development
S.
N.
Mitigation Action Estimated
Cost (NRs)
Remarks
Implementation of Livelihood
improvement plan for PAFs
200,000.00
Sub-Total (B1) 125,436,942.00
B2 Operation Phase
Installation of early warning system (siren
system)
1,000,000.00
Awareness program on the use of early
warning system
200,000.00
Support downstream fishing communities
through skill training and capacity
development trainings
200,000.00
Sub-Total (B2) 1,400,000.00
C Beneficial impacts enhancement
measures
Income generation training 20,85,000.00
Skill enhancement training 50,15,480.00
Local employment facilitation measures
for PAFs
200,000.00
Equipment operation related trainings 100,000.00
Maintenance of existing infrastructure like
health posts, schools and water supply
systems
1,000,000.00
Co-ordination with the DFO management
and CFUGs
200,000.00
Sub-Total (C) 8,600,480.00
D Community Support Program (CSP)
Community Support Program (CSP)
(0.50% of total project cost)
101,022,050.00
Sub-Total (D) 101,022,050.00
Grand Total 271,944,290.00 Excluding project cost items
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
171| P a g e Department of Electricity Development
8.2.5 Costs for Environmental Monitoring
The costs included in this section present only the costs where DK5HPP management is
responsible for the compliance and impact monitoring through instrumental monitoring. The
costs of the other monitoring activities through technical support staff at site are included in
the environmental management costs of the project. The costs where contractor is responsible
are the part of the project civil cost and not included here.
Table 8-13: Estimated Cost for Environmental Monitoring
S.
No. Items
Person-
month
Rate/Month
(NRs.)
Amount
(NRs.)
1 Pre-construction Phase
1.1 Human Resources
1.1.1 Environmental Expert/ Team Leader 1 100,000.00 1,00,000/-
1.1.2 Environmental Engineer 1 75,000.00 75,000/-
1.1.3 Forestry Expert/ Ecologist 1 75,000/- 75,000/-
1.1.4 Socio-economist 1 75,000/- 75,000/-
1.1.5 Support Staff 1 20,000/- 20,000/-
Sub total 3,45,000/-
1.2 Out of Pocket Expenses
1.2.1 Field Assistant LS 50,000/-
1.2.2 Transportation LS 3,00,000/-
1.2.3 Report Production LS 50,000/-
1.2.4 Sampling/ Laboratory Analysis LS 75,000/-
1.2.5 Miscellaneous LS 50,000/-
Subtotal 5,25,000/-
Total (1) 8,70,000.00
2 Construction Phase
2.1 Human Resources
2.1.1 Senior Environmental Advisor 2 100,000.00 200,000.00
2.1.2 Unit Chief/ Environmental Expert 48 75,000.00 3,600,000.00
2.1.3 Environmental Engineer 2 75,000.00 1,50,000.00
2.1.4 Forestry Expert/ Ecologist 2 75,000.00 1,50,000.00
2.1.5 Monitors 48 25,000.00 1,200,000.00
2.1.6 Support Staff 48 15,000.00 720,000.00
Sub -total 60,20,000.00
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
172| P a g e Department of Electricity Development
S.
No. Items
Person-
month
Rate/Month
(NRs.)
Amount
(NRs.)
2.2 Out of Pocket Expenses
2.2.1 Field & Office Equipment LS 2,50,000.00
2.2.2 Office Establishment LS 2,50,000.00
2.2.3 Office Supplies/ Report Preparation LS 2,50,000.00
2.2.4 Sampling/ Lab Analysis LS 2,50,000.00
2.2.5 Transportation (Vehicles/ fuels/
maintenance etc.)
LS 10,00,000.00
2.2.6 Miscellaneous LS 2,50,000.00
Sub-total 22,50,000.00
Total (2) 82,70,000.00
3 Operation and Maintenance Phase (24 months)
3.1 Human Resources
3.1.1 Environmental Expert/ Team Leader 1 1,00,000.00 1,00,000.00
3.1.2 Forestry Expert/ Ecologist 1 75,000.00 75,000.00
3.1.3 Socio-economist 1 75,000.00 75,000.00
3.1.4 Support Staff 1 20,000.00 20,000.00
Sub-total 2,70,000.00
3.2 Out of Pocket Expenses
3.2.1 Field Assistant LS 1,00,000.00
3.2.2 Transportation LS 1,00,000.00
3.2.3 Field sampling/ lab analysis LS 2,00,000.00
3.2.4 Report Production LS 1,00,000.00
3.2.5 Miscellaneous LS 50,000.00
Sub-total 5,50,000.00
Total (3) 8,20,000.00
Grand Total (1+2+3) 9,960,000.00
8.2.6 Environmental Management Cost
The environmental management cost for staff and consultants of the Environmental Support
Unit ofthe Project Management Office is already included in the civil management cost of the
project costs.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
173| P a g e Department of Electricity Development
8.2.7 Environmental Audit Cost
Environmental audit is to be carried out by the MoFE as per the EPR, 1997. Hence, the
environmental audit cost has been allocated by the project.
8.3 Summary of Environmental Mitigation, Monitoring andManagement Cost
Table 8.14 presents the summary of the project environmental costs excluding the cost included
in project cost.
Table 8-14: Summary of the Project Environmental Costs
S. N. Particulars Estimated Cost (NRs)
1 Environmental Mitigation (Construction Phase) 155,321,760.00
2 Environmental Mitigation (Operation Phase) 7,000,000.00
3 Environmental Enhancement Measures 8,600,480.00
4 Community Support Program (CSP) 101,022,050.00
5 Environmental Monitoring (Pre-Construction Phase) 870,000.00
6 Environmental Monitoring (Construction Phase) 82,70,000.00
7 Environmental Monitoring (Operation Phase) 820,000.00
8 Environmental Auditing 21,00,000.00
Total Environmental Cost
(excluding the cost included in project cost)
284,004,290.00
Total environmental cost for the project accounts to the sum of environmental mitigation cost,
environmental enhancement cost which is NRs. 271,944,290, Community Support Program
(CSP) cost is NRs. 101,022,050.00, cost for environmental monitoring is NRs. 9,960,000.00
and cost for environmental auditing is NRs.2,100,000.00. The total environmental cost for the
proposed Dudh Koshi 5 HPP is NRs. 284,004,290.00 which is about 1.40% of the total project
cost (NRs. 20,204,409,910.00).
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
174| P a g e Department of Electricity Development
9. REVIEW OF PLANS, POLICIES, ACTS, REGULATIONS,
GUIDELINES, STANDARDS, CONVENTIONS
This Chapter reviews the Policies, Procedures, Guidelines and Legislative provisions of the
Government of Nepal that have a direct relevance with the proposed project development and
operation. Some of the related international conventions and guidelines pertinent to the present
study were also reviewed.
9.1 The Constitution
9.1.1 Constitution of Nepal
The proponent shall only exercise the rights provided by the Constitution and shall abide by
the Constitutional requirements stipulated in its Clauses in course of implementation of the
proposed DK-5HPP. Some of the relevant Constitutional provisions are;
i. The Constitution of Nepal, 2015 in its Article 30 (1) recognizes the right of every citizen
to live in a clean and healthy environment.
ii. Article 30 (2) makes polluter of the environmental pollution and degradation liable to
compensate the victim of the consequences arising out of such pollution and degradation
as provided by the law. However, Article 30 (3) also states that “this Article shall not be
deemed to obstruct the making of required legal provisions to strike a balance between
environment and development for the use of national development works”.
iii. Article 15 of the Constitution of Nepal recognizes Right to Property of every citizen of
Nepal.
iv. Article 51 (f) “Development Policy” of the Constitution of Nepal, 2015 emphasizes on
prioritization of under-developed regions while going for balanced, environment-
friendly, qualitative and sustainable physical infrastructure development. The same
Article 51 (f) (3) also identifies need of increasing the participation of local people in
development process. Similarly, Article 51 (f) (7) states that “the State shall pursue a
policy of adopting appropriate ways of minimizing or stopping negative impacts on
environment if it is there or if there is a possibility of such an impact on nature,
environment, or biodiversity”.
9.2 Plans and Polices
9.2.1 National Five-Year Plans (1st to 10th)
Nepal started its planned process of development in 1956, when the First Five Year Plan (1956-
1961) was launched. The Sixth Five Year Plan (1980-1985) was the first to emphasize the need
for EIA for major infrastructure projects and committed to adopt a policy for the integration of
environmental aspects during the construction of large-scale projects. After that, the Seventh
Five Year Plan (1985-1990), was the first to consider the environment as a distinct component
in the planning process. Unfortunately, implementation of environmental programmes, such as
the EIA policy stated in the Seventh Five Year Plan, were not realized to the extent previewed,
largely due to the lack of coordination among sectoral programmes, insufficient skilled human
resource, a lack of appropriate legislation and funds and, above all, a lack of appropriate
institutional arrangement. Later the realization for the importance of Environmental
Assessments was mooted in the water resources sector upon the publication of a report on
"WECS and the Environment "in 2047 by the Water and Energy Commission Secretariat, GON
enunciated separate Hydropower Development Policy in 2049. One of the objectives of this
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
175| P a g e Department of Electricity Development
policy is to "render assistance in the conservation of environment by supplying clean energy
through the development of hydroelectricity power". This policy objective calls for expanding
the use of electricity to minimize fuel wood consumption and provide the guidance for the
construction and operation of hydroelectricity project ensuring minimization of adverse effects
on the environment (MOWR, 2049). For the first time a national level policy on environment
management was incorporated. Policy commitments were made in this Plan to carry out EIA
for all major development projects related to the sectors of tourism, water resources,
transportation, urbanization, agriculture, forestry and industry. The plans and programmes
formulated in the Seventh year Plan were of great significance to environmental protection in
Nepal.
The Eighth Five Year Plan (1991-1995) and the Nepal Environmental Policy and Action Plan
(1993) re-emphasized the need for an EIA system to integrate environmental concerns into the
development process. The Eight Five Year Plan anticipated the establishment of a national
system for EIA and stipulated that EIAs be conducted at the stage of feasibility study. It further
emphasized in the commercial development of hydropower with an objective of integrating
energy generation in the national productive sector.
The Ninth Five Year Plan (2055-2059) has encouraged the private sector and joint venture
investments on hydroelectricity development (NPC, 2055). The Plan has emphasized the need
for developing hydroelectricity with special attention of mitigating of adverse environmental
impacts through the integration of watershed management in the projects of water resource
development. Integration of EIA has been given a priority in implementation of the mitigation
of adverse effects and the enhancement of beneficial impacts
Tenth Five Year Plan (2002– 2007) aims to extend the electrification within country and export
to India for mutual benefit.
9.2.2 The Fourteenth Three Year Plan (2073/74-2075/76 B.S.)
The Fourteenth Three Year Plan (2073/74-2075/76 B.S.) has recognized the wise use of water
resources as an opportunity for prosperity of Nation.The plan has emphasized on the need to
prioritize and implement Micro, Medium and Large hydropower projects to make our country
self- relient in the energy sector. The main goal of this plan is to ensure that hydroelectricity is
available to all households in all region of Nation.
The fourteenth plan policy encourages the private sector to invest in hydropower sector,
similarly the plan has also emphasized to create an opportunity for the local communities to
acquire shares in Medium and large hydropower projects.
The objective of fourteenth plan also includes;
• To increase the natonal hydropower generation to 2,301 MW by 2075/76 BS
• To make power available to at least 87% of the country’s population by 2075/76 BS
9.2.3 National Water Plan 2059-2064 BS (2002-2007 A.D.)
The National Water Plan 2002-2007 (NWP) was prepared to implement the Water Sector
Strategy of Nepal. The Plan targets an increase in Nepal's hydropower generation from 600
MW in 2007 to 4,000 MW by 2027. The NWP emphasizes the need for Strategic
Environmental Assessment. Section 7 of the NWP highlights the Environment Management
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
176| P a g e Department of Electricity Development
Plan (EMP) as a strategic document for the implementation, monitoring and auditing of
environmental protection programs.
9.2.4 Nepal Environmental Policy and Action Plan, 2050 B.S. (1993 A.D.)
The Nepal Environmental Policy and Action Plan (NEPAP), endorsed in 1993 recognize that
a growing number of people are exposed to pollution from industrial enterprises. NEPAP
identifies the following factors as contributing to this process.
(iii) Industrial plants inappropriately sited close to pollution centre
(iv) Insufficient emphasis on fuel efficiency
(v) Little if any pollution abatement equipment used for reducing emission and
(vi) A total lack of industry pollution standards.
The Action Plan for infrastructure development within NEPAP recommends the finalization of
draft EIA guidelines for water resources, the development of EIA guidelines for road
construction and the use of EIA when designing hydroelectric projects.
9.2.5 Climate Change Policy, 2068 BS (2011)
The Climate Change Policy, 2011 envisions making the Country free from the adverse impacts
of climate change, by considering climate justice, through the pursuit of environmental
conservation, human development, and sustainable development--all contributing toward a
prosperous society. This way the policy relates to the Project Developer’s responsibility in
implementing the Project so that it can have minimal impacts on environment contributing to
minimization of climate change impacts. One of the policies of the Climate Change Policy,
2011 is to implement existing air quality standards and developing and implementing new
standards to support low carbon and climate-resilient development which is relevant in context
of the development of the proposed DK5HPP.
9.2.6 Hydropower Development Policy, 2058 BS (2001 AD)
The main objective of Hydropower Development is to generate/produce electric power at low
cost by utilizing water resources available within the country. And to supply/extend reliable
electricity service nationwide at reasonable price. Other objectives are to develop hydropower
as export orientated commodity and also relate electrification with the economic activities of
the country.
Some of the highlights of Hydropower Development Policy 2001 are as follows:
i. Develop small, medium, large and reservoir type projects considering maximum and
optimum benefit to the country with minimum environmental consequences.
ii. Encourage local bodies, co-operatives and private sectors participation with clear,
simple and transparent rules and regulation.
iii. Develop hydropower as an alternative to Bio and Thermal energy with an aim to
contribute in the environmental protection.
iv. Encourage people’s participation in hydropower development with a view to
dissemination of benefit at local level also.
v. Render priority to Nepalese labour, skill and resources in implementation of hydropower
projects.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
177| P a g e Department of Electricity Development
vi. Control in the leakage of electricity.
9.2.7 Forest Policy, 2071 BS (2014 AD)
The forest policy 2071 aims to strengthen the forest resources of Nepal. The policy aims:
(vii) To manage forest resource sustainably, increase productivity of forest area/sector
and increase overall production from forest.
(viii) To conserve biodiversity, conservation of sources, and equal sharing and
distribution of environmental services gained from conservation.
(ix) The policy also aims to conservation of water, soil on basin level studying and
planning based on catchment level. The Hydropower sector while promoting
conservation at local level shall think and act on the watershed conservation basis.
(x) To encourage private sector for the development and conservation of forest sector.
Also aims to promote the forest-based entrepreneurships, diversification, value
addition through marketing and creation and promotion of green employment
(xi) To reduce and mitigate the adverse impacts of climate related hazards and
enhance climate change adaptation measures and resilience in Nepal.
(xii) Good governance, inclusion and social justice for the conservation of forest
resources.
(xiii) To enhance the conservation the policy aims to encourage forest conservation
groups to manage forest in scientific way to strengthening ecosystem and other
environmental services.
9.2.8 Land Acquisition, Resettlement and Rehabilitation Policy, 2071 BS (2015 AD)
With an aim to improve social and economic status of project affected families by providing
fair and adequate compensation, appropriate resettlement and rehabilitation assistances/
allowances, the GoN has released Land Acquisition, Rehabilitation and Resettlement Policy in
2015. The Policy mission is to facilitate timely execution (completion) of development projects
by minimizing adverse impacts on economic, social and cultural aspects of affected
families/people and the project area. The Policy has following specific objectives;
i. Avoid displacement wherever possible and if not, minimize as far as possible
ii. If population displacement is unavoidable, mitigate adverse impact by providing
adequate compensation and rehabilitation assistance to affected person, family and
community
iii. Create conducive environment for timely completion of the project by simplifying land
acquisition, valuation, compensation, resettlement and rehabilitation process.
The Policy classifies projects on the basis of numbers of families to be displaced such as;
iv. High risk project: Project that displaces (both physical and economic) 50 or more
families in the mountain region, 75 or more families in the hills and 100 or more
families in the Terai plains
v. Medium risk project: Project that displaces (both physical and economic) less than 50
families in the mountain region, less than 75 families in the hills and less than 100
families in the Terai plains.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
178| P a g e Department of Electricity Development
vi. Low risk project: Projects with no physical displacement Project with only economic
displacement and None of Affected person loose more than 10% of their productive
asset
Four approaches for land acquisition has to be adopted namely, voluntary donation, direct
negotiation, land development program and expropriation (Use of eminent domain). The
proposed DK5HPP falls under low risk project as per the categorization of the Policy.
9.3 Strategies
9.3.1 Nepal Biodiversity strategy and Action Plan (2014-2020 A.D.)
Nepal is committed to conservation and utilization of the country’s unique biodiversity and
biological resources on a sustainable basis for the benefit of present and future generations.
Moreover, as a Party to the CBD, Nepal has an obligation of developing a national strategy for
conservation and sustainable use of her biodiversity and integrating conservation into relevant
sectoral and cross-sectoral plans and policies.
Accordingly, the first national biodiversity strategy and its implementation plan were prepared
by the Ministry of Forests and Soil Conservation (MoFSC; CBD Focal Agency) in 2002 and
2006, respectively (MoFSC, 2002; MoFSC, 2006a). This National Biodiversity Strategy and
Action Plan (NBSAP) is a revised and updated version of theNepal Biodiversity Strategy
(NBS). It builds on the achievements and lessons learned from implementation of the NBS. It
is prepared by taking into considerations of the national needs in terms of conservation of
biodiversity, sustainable use of its components and equitable sharing of benefits accrued from
conservation and utilization of genetic resources. Relevant decisions and guidelines of the CBD
Conference of Parties (COP), particularly the COP 10 Decision X/2 on Strategic Plan for
Biodiversity 2011–2020 adopted by the Parties in October 2010, and the Aichi Biodiversity
Targets provided theoretical framework and technical guidance for developing the NBSAP.
The NBSAP has been prepared by the Ministry of Forests and Soil Conservation with funding
support of the Global Environment Facility through the United Nations Environment Program.
The overall goal is to significantly enhance the integrity of Nepal’s ecological systems by 2020,
thereby contributing to human well-being and sustainable development of the country. This is
to be achieved through implementation of a number of sectorspecific and cross-sectoral
strategies and priority actions. Eight principles underpin the strategy and 13 broad strategic
approaches have been prescribed to facilitate itsimplementation. The experience gained and
lessons learned from implementation of the Nepal Biodiversity Strategy (2002) and Nepal
Biodiversity Strategy Implementation Plan (2006) provided the necessary context for
formulating the strategy. The specific strategies and associated actions are grouped into the six
biodiversity themes and 15 cross-cutting subjects. The strategies for managing protected area
and forest biodiversity aim at reducing or managing human pressures on natural resources,
reducing human-wildlife conflict, controlling invasive alien species, mitigating climatic threats
to ecosystems, species and their habitats, and addressing economic and social concerns of local
and indigenous communities through targeted programmes, enabling policy and legislative
environment. Reducing the rate of loss and degradation of forest habitats, improving biological
connectivity, enhancing knowledge and understanding about forests, promoting conservation
of species and genetic diversities, enhancement of forest-based livelihoods is some of the
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
179| P a g e Department of Electricity Development
focused areas. The mainstrategy of the Nepal National Biodiversity strategy and Action Plan
are;
• Management of rangeland biodiversity emphasize on improving knowledge and
understanding of rangeland ecology and biodiversity, and development and
implementation of integrated rangeland management plans and programmes for the
conservation of rangeland and enhancing the herders’ livelihood.
• Improving and expanding the existing community-based management of agricultural
genetic resources; strengthening the national ex-situ conservation programme;
enhancing communication, education and public awareness; and promoting indigenous
traditional knowledge, skills and practices are some of the strategies for management
of agro biodiversity.
• Managing mountain biodiversity include: improving understanding of mountain
biodiversity and ecosystem services; promoting environment-friendly economic
development and alternative livelihood opportunities through development of local
forest and agriculture-based enterprises; designing and implementation of ecosystem-
based adaptation programmes; and promoting public–private partnerships and regional cooperation.
9.3.2 National Water Resource Strategy, 2058 BS (2002 AD)
Realizing the fact that the development and management of water resources should be under
taken in a holistic and systematic manner aimed at the sustainable use of resources ensuring
conservation and protection of the environment. Nepal has adopted National Water Resource
Strategy (NWRS). This strategy underscores the interdependencies between water resource
development and environment conservation, and has adopted environment principles related,
inter alia, to the integration of ecological aspects at every level of hydropower development
process, conserve biodiversity, watersheds and adopt ecosystem approach. The activities are
also related to ensure compliance with environmental regulations, promotecommunity
participation for the sustainable management of watersheds and aquatic ecosystems (WECS,
2002). The WRS has a target of developing 820 MW of hydropower by 2063/064 to meet the
domestic demand at base case scenario including export to the tune of 150 MW and achieve
per capita electricity consumption of 100KWh.
9.3.3 National Conservation Strategy, 2050 BS (1993 AD)
The National Conservation Strategy for Nepal (NCS), endorsed by the government in 1988,
recognizes the interdependence of conservation and development. The environmental policy
of the NCS emphasizes a need for socioeconomic and environmental impact assessment of
infrastructure and other developmental projects, and adequate measures to minimize the
adverse impact to a significant level.
9.3.4 Water Resources Strategy, 2058 BS (2001 AD)
Integrated Water resource management has been adopted as one of the principle themes of the
National Water Strategy. It professes that water must be viewed from a holistic perspective,
both in its natural state and in balancing the competing demands on it, e.g. domestic,
agriculture, hydropower, industrial, cultural and environmental. The National Water Strategy
has set forth 10 strategic outputs for short, mid and long term for the overall development of
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
180| P a g e Department of Electricity Development
water resources. The Nepal Water Plan is built around these strategic outputs of the National
Water Resources Strategy.
9.4 Act and Rules
9.4.1 Environment Protection Act, 2053 BS (1997 AD) and Environment Protection
Rules (latest amendment 2010), 2054 BS (1997 AD)
The Environment Protection Act (EPA) of 1997 can be considered as the first act dealing with
environment in totally. It considers that sustainable development is possible through proper
consideration of interdependency of economic development and environmental protection. The
Act has taken the term “Environment” as aphysical, biological and social-economic and
cultural aspects and their interaction and inter relation. The projects and program are to be
developed and implemented to minimize adverse impact on physical, biological and social-
economic and cultural environment. The salient features of the Act are consideration of proper
use and management of natural resources, incorporation of environmental concerns in the
development process, participatory role of communities and stakeholders to mention the few.
The procedure and framework as outlined in the Act are as follows;
• Project planning and project approval
• Project implementation and pollution control mechanism
• Punishment and penalties for non-compliance
The EPA, 2053 has made public consultation a pre-requisite to all the prescribed development
projects and programs. The legal provision has provided the local people an opportunity to
voice their concerns and issues right from the scoping stage to approval of the EIA report. The
section 3 of the EPA, 2053 calls for carrying out IEE orEIA for the prescribed proposals.
Section 4 of the said Act prohibits the proponents not to execute the projects without approving
IEE/EIA reports. Section 6 empowers the concerned Ministry and the Ministry of Forests and
Environment to approve IEE andEIA reports respectively.
The proposal requiring IEE/EIA studies are broadly listed in Schedule 1 and Schedule 2 under
rules 3 of EPR, 2054 enforced under the provisions of EPA. As per rule 4, proposal requiring
EIA will have to prepare a scoping document incorporating the public concerns and apply to
Ministry of Forests and Environment through concerned agencies. In this process a 15 days
public notice in the national newspaper requesting suggestions and comments on
environmental issues arising due to the proposal implementation has to be published. The
Ministry of Forests and Environment is empowered to review the document and give approval
with or without needed amendments.
As per rule 5, proponent of both IEE/and EIA proposals has to prepare Terms of Reference
(ToR) of the proposal for approval. In the case of IEE, ToR is approved by the concerned
agency whereas Ministry of Forests and Environment will give ToR approval requiring EIA, it
will have to comply with all provisions of EIA. Rule 7 of EPR provides that the IEE proposal
proponent to publish fifteen day’s public notifications in the national daily newspaper and
present the notification to the public institution of the affected areas for comments and
suggestion on IEE proposals during the study phase. Whereas proponents of the EIA proposal
have to organize a public hearing in the project affected area to collect public concerns and
suggestions.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
181| P a g e Department of Electricity Development
Rule 10 of EPR stipulates that all the proposals submitted for approval will have to take letter
of recommendations from the concerned affected rural municipalities and municipalities on the
proposals. However, the rule is silent on the status of the IEE/EIA if it is approved contrary to
public and the affected rural municipality and municipality opinion. However, the Ministry can
only grant its approval to implement the proposals if it does not cause significant adverse effect
on the environment under rule 11.
Rule 12 of EPR stipulates that the proponent is obliged to follow the terms of conditions set by
concerned agencies or Ministry of Forests and Environment in the approval letter during project
implementation and operation. Rule 13 provides that the concerned agency to be responsible
for the project monitoring.
Rule 14 provides that the Ministry of Forests and Environment to be responsible
forenvironmental audit after 2 years of project implementation.
9.4.2 Solid Waste Management Act, 2068 BS (2011 AD) and Solid Waste Management
Rules, 2070 BS (2013 AD)
The Act clearly envisages about management of solid waste and provision of licensing for
management. In such case, the article (7) on discharge of solid waste entails about the person,
organization that produces hazardous waste or chemical waste shall have to manage such waste
as prescribed (sub article 2). It is restricted that nobody shall do or cause to do the work relating
to the solid waste management without obtaining license from the Local Body as prescribed by
article 13 of chapter, miscellaneous sub article 1.
Solid waste management rules 2070 BS have been issued by the government of Nepal by power
conferred by section 50 of the solid waste management Act 2068. Rule 3 of this Rules enforced
the segregation and management of the solid waste. Sub rule 1 of this rule stipulates the
segregation of solid waste at least organic and inorganic solidwaste at its source under section
6 have to management and segregation of harmful and chemical waste separately. The
responsibility of managing of the chemical and harmful solid waste under sub rule1 shall be a
concern generator. Rule 4 of this rules endorsed the discharge the solid waste as comfortable
manner for transportation, processing and final discharge by take in to account the possible
adverse effect on the public health and environment and the ways of reduction of such effect.
9.4.3 Plant Protection Act, 2064 BS (2007 AD) and Plant Protection Rules, 2067 BS
(2010 AD)
Plant Protection Act, 2007 {vide its Section 6 (2) (e)} and its succeeding Plant Protection Rules,
2010 prescribes terms and restrictions relating to the trafficking and use of plants and plant
products, biological control agents and beneficial organisms.
9.4.4 Child labor (Prohibition and regularization) Act, 2056 BS (2000 AD) and Child
Labor (Prohibition and Regulation) Rules, 2063 BS (2006 AD)
Child Labour (Prohibition and Regulation) Act, 2000 (2056) has been enacted and enforced
with a view to adopting ILO Convention concerning Elimination of Worst Forms of Child
Labour (C182) and Minimum Age Convention (C138). This Child Labour (Prohibition and
Regulation) Act, 2000 was enacted as legislative measure for preparative works. This is the
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
182| P a g e Department of Electricity Development
main Act which deals with issues of child labour. Although the Act was promulgated in 2000,
it came into force only on 16th November, 2004.
9.4.5 Local Government Operation Act, 2014 AD (2071 BS) and Local Self
Governance Regulations, 2056 BS (1999 AD)
This newly formed act describes about the criteria to divide a state into municipalities or rural
municipalities and respective rights, duties and responsibilities in different development and
conservation sector. It clarifies the rights of municipalities/rural municipalities to form local
laws, regulations and criteria for conservation of environment protected areas and species; for
environmental pollution and hazard control; solid waste management etc.
9.4.6 Forest Act, 2049 BS (1993 AD) and Forest Rules, 2051 BS (1995 AD)
The Forest Act, 1993 recognizes the importance of forests in maintaining a healthy
environment. The Act requires the decision makers to consider all forest values melding
biodiversity, not just production of timber and other commodities. Act 68 (1) of the Act states
“Not withstanding anything contained in this Act, in case there is no alternative except to use
the Forest Area for the implementation of the plan having national priority and if there shall be
no significant adverse effect in the environment while conducting such plan, GoN may give
assent to use any part of the Government Managed Forest, Community Forest, Lease hold
Forest or Religious Forest for the implementation of such plan”.
The Forest Regulation, 1995 makes any project proponent liable of compensating for the losses
or harms caused by the execution of such project in any forest area. Article 65 (1) of the
regulation states, “In case the execution of any project having national priority any causes any
loss or harm to any local individual or community, the operators of the concerned project itself
shall bear the amount of compensation to be paid in consideration thereof”. Article 65 (2) states
“The entire expenses required for the cutting, making in to pieces and transporting the Forest
Products in a Forest Area to be used by the approved project shall be borne by the operators of
the project”.
9.4.7 Water Resources Act, 2049 BS (1992 AD) and Water Resources Regulations,
2050 BS (1993 AD)
Water Resource Act, 1992 is the umbrella Act governing water resource management, which
declares the order of priority of water use, vests ownership of water in the State, provides for
the formation of water user associations, establishes a system of licensing and prohibits water
pollution. Article 19 (1) of the act mentions that the government through notification in the
Nepal Gazette prescribe pollution tolerance limits for the water resources. Similarly, article 19
(2) requires any person to abide by the act not to pollute water resources beyond specified limit.
Article 20 states that while utilizing water resources, there should not be significant adverse
impact on the environment with regard to soil erosion, flood, landslide and other similar cases.
Articles 16, 19, 20 of the Act are also related to land acquisition. According to article 16 (3),
the government shall, according to existing laws, acquire land for the licensed person or
institution and any compensation in this regard shall be paid by the licensed person.
Water Resource Regulation, 1993 is the umbrella Regulation governing water resource
management. The regulation particularly sets out the procedure to register a Water User
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
183| P a g e Department of Electricity Development
Association and to obtain a license, establishes the District Water Resource Committee, sets
out the rights and obligations of Water User Associations and license holders and deals with
the acquisition of house land and compensation.
9.4.8 Electricity Act, 2049 BS (1992 AD) and Electricity Rules, 2050 BS (1993)
Electricity Act governs the use of water for hydropower generation, establishes a system of
licensing, sets out the power functions and duties of a license holder provides certain financial
incentives for the license holder and sets out the powers to the government. It requires any
person or corporate bodies to obtain license prior to survey, generation, transmission or
distribution of electricity of more than 1000 KW. In article 24 of the Act, it states that “While
carrying out electricity generation, transmission or distribution, it shall be carried out in such
manner that no substantial adverse effect be made on environment by way of soil erosion, flood,
landslide, air pollution etc.” Article 33 deals with land acquisition. Licensed individuals can
apply the government to acquire land for the purpose of electricity generation, transmission
and distribution. The government shall acquire the land for the stated objectives under existing
regulations the compensation incurred to acquire land and other property shall be paid by the
applicant.
Rule 12 (f) of the Electricity Rules, 1993 have made provision of application for production
license. It states “Analysis of environmental effect (measures to be taken to minimize adverse
effects due to the project on environment, social and economic effect on said area, utilization
of local labor, source and material, benefits to be taken by local people after the completion of
the project, training to be provided to the local people in relation to the construction,
maintenance, operation; facilities to be required for the construction site, safety arrangements
and effect on local landowners due to the operation of the project, details of people to be
evacuated (relocated) and necessary plan for their rehabilitation should also be shown”.
9.4.9 Labor Act, 2074 BS (2017 AD) and Labor Rules, 2075 BS (2018 AD)
The Labor Act, 2017 have made provisions for recruitments, minimum wages and
remunerations, minimum standard for working places like arrangement of residence of the
workers at site etc. The Act also provides requirements for health and safety of the employees
as well as a healthy, safe and secured environment for workers. The Act regulates all labor
issues pertaining to an enterprise i.e. all labor issues of industrial, commercial, transport and
construction labor. The Act by its Section 5 prohibits employment of children in any work
against law. Section 6 and Section 7 prohibits discrimination in employment of anyone based
on religion, race, gender, ethnicity, caste, origin, language and political inclination or any other
forms and also prohibits discrimination on remuneration wage to the employee. Paragraph 7 of
the Act includes provisions for working hours and management of transportation for the
employee. Paragraph 8 includes provisions relating to renumerations. Section 53 and 54
include provisions for health and accident insurances. Paragraph 8 stipulates provisions relating
to occupational health and safety at the workplace.
The Government of Nepal (“GoN”) has framed the Labor Rules, 2075 (2018) ("Labor Rules")
by exercising the power conferred to it under Section 184 of the Labor Act,
2074 (2017) (“Labor Act”) which was passed by the Council of Ministers on May 28,2018
(Jestha 14, 2075). The Labor Rule has been published in Nepal Gazette on June 22, 2018 (Asar
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
184| P a g e Department of Electricity Development
08, 2018) with immediate effect and has repealed the then Labor Rules,1994 (2050) (“Previous
Labor Rules”).
Rule 16 of the Labor Rules provides flexibility to the Employer to determine the work hours.
The Employer can determine the work hours on the basis of the nature of the work of the entity.
The notice of the work hours however, should be given to all the Employees.
The Labor Rules also provides that the Employer may put the Employee to work on rotation
based on nature of its work. It seems that the Labor Rules envisages putting the Employee in
different shifts.
The Labor Rules requires the Employer to provide additional rest period for certain female
Employees. The Employer should provide half an hour additional time for female Employees
(a) who has baby below 3 years for breast feeding, and (b) who is pregnant.
The Labor Rules specifically require the Employer to pay the salary to the Employee for weekly
off. The Labor Act also authorizes the Ministry of Labor to specify the Employer who should
pay the salary to the Employee through banking channel.
Similarly, Labor rule also states about Occupational Safety and Health policy “Employers are
required to maintain an occupational health and safety policy. The policy should cover different
measures in accordance with the entity’s nature of business. The policy should be drafted in a
way which includes provisions related to arrangements Employee’s safety and security,
Employee’s health, probable accident in workplace, precautions to be taken while operating
devices and machines in workplace and precautions to be taken while using chemical
substances.
9.4.10 Industrial Enterprise Act, 2049 BS (1992 AD)
Industrial Enterprises Act requires permission for the extension and diversification of
environmentally sensitive industries and provides financial incentives for industrial enterprises
that minimize harmful effects on the environment.
9.4.11 Soil and Watershed Conservation Act, 2039 BS (1982 AD) and Soil and
Watershed Conservation Rules, 2042 BS (1985 AD)
The Act prohibits any person from doing anything that may result in soil erosion or washout
on lands on protected watershed or in adjoining areas. The Act also makes provisions for
acquisition and compensation for the lands comprising the private property of anyone Article
10 of the Act states “Not withstanding anything contained in current law, no person shall be
allowed to take any of the actions without the permission of the Watershed Conservation
Officer on lands located within any protected watershed area prescribed as those on which
floods, landslides, washouts, or erosion occur or may occur:”
The Soil and Watershed Conservation Regulation in its Rule 11 requires any proponent to
undergo through application procedures to use the protected watershed area or land prone to
natural calamity.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
185| P a g e Department of Electricity Development
9.4.12 Land Revenue Act, 2034 BS (1977 AD)
The Act is also applicable, as the land acquisition involves change of ownership of land. Article
8 of the Act states that registration, change in ownership, termination of ownership right and
maintenance of land records are done by Land Revenue Office.Similarly, article16 states, if
land revenue is not paid by the concerned owner forlong period of time, the revenue can be
collected through auction of the parcel ofthe land for which revenue has been due.
9.4.13 Land Acquisition Act, 2034 BS (1977 AD)
The Act aims at amending and consolidating current legislation relevant to the acquisition of
land. The Government may acquire any land at any place for any public purpose, if it so deems
necessary, according to the procedure set out by this Act. To this end it regulates the nomination
of an officer responsible for preliminary action in charge of the determination of the land area
to be acquired (through a survey, collection of samples of soil, demarcation of land, installation
of equipment), the determination of the compensation and the submission of a report to the
local officer regarding the findings of preliminary action. After having received the report, the
local officer shall issue a notification containing all the particulars required (e.g. purpose of
acquisition, location of the land, terms of acquisition, plot number or boundaries of the land,
land area). Further provisions concern the publication of said notice, the decision by the Zonal
Commissioner of complaints filed by the landowner, the occupation of the land by the local
officer, the criteria for the determination of the compensation which shall be paid either in cash
or by allotment of other lands in exchange, if so, required by the landowner.
9.4.14 National Parks and Wildlife Conservation Act, 2029 BS (1973 AD) and National
Parks and Wildlife Conservation Rules, 2030 BS (1974 AD)
Schedule 1 relating to section 10 of this act provides the list of protected wildlife. According
to section 10, wildlife mentioned in schedule 1, are prohibited for hunting. According to section
11, no person shall be permitted to hunt wildlife without obtaining license. There will be
punishment in terms of fine or imprisonment or both if any person illegally kills or injures
wildlife within protected areas. Rule 5 of the NPWC Rules imposes restriction in hunting (in
special circumstances even when one has the license to hunt).
9.4.15 Land Reform Act, 2021 BS (1964 AD)
The act was enforced to implement the land reform program of government. The actcame in to
effect with the objectives such as rapid economic development through the proper utilization
of the land resources, improvement of livelihood of the land peasants through the equal
distribution of agricultural land and providing them withthe easy access of essential knowledge
and required tools for the encouragement of farming and high productivity.
9.4.16 Explosive Act, 2018 BS (1961 AD) (latest amendment 1991)
It is expected that explosives will be used during the construction of the Project. Hence, the
provision of the Explosive Act, 2018 also needs to be taken into consideration. Section, 3 of
the Act states that GoN by a notification in the Nepal Gazette may declare any substance as
explosives. Section 4 forbids producing, storing, using, carrying and importing explosives
without a license. The Section also provides the person to apply for the license to the Chief
District Officer with prescribed descriptions.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
186| P a g e Department of Electricity Development
9.4.17 Aquatic Animal Protection Act, 2017 BS (1960 AD)
This act mainly focuses on the protection and management of aquatic ecology, aquatic fauna
including fish and wetlands. This act prohibits use of poison or harmful chemicals or materials
in the water bodies or explosives to dismantle any embankment with a view to catching or
killing aquatic animals including fish. However, there is no specific law for fishing and
fisheries management.
9.4.18 CITES Act, 2016, ;Í6fkGg jGohGt' tyf ag:kltsf] cGt/fli6«o Aofkf/nfO{ lgodg tyf
lgoGq0f ug{ ag]sf] P]g, @)&#
This Act was enforced for the enactment of Convention on International trade in endangered
species of wild flora and fauna (CITES, 1973) and Nepal also has signed the Convention. This
acts states about the regulation and control of international trade of such endangered flora and
fauna species.
The species are protected by CITES against over exploitation and they are listed in three CITES
Appendices I, II, and III for different levels or types of protection. Appendix I lists species that
are the most endangered among the CITES listed animals and plants. These are threatened with
extinction and CITES prohibits commercial international trade except for scientific research.
Appendix II lists species that are not threatened with extinction at present but may become so
unless trade is closely controlled. Appendix III lists species that are included at the request of
a Party that regulates trade and that needs cooperation of other countries to prevent
unsustainable or illegal exploitation.
9.4.19 Contribution Based Social Security Act, 2074 BS (2017 AD)
This act was passed by the Parliament on July 24, 2017 (Shrawan 09, 2074) and accorded the
assent by the President on 13 August, 2017 (2074-04-29). The Social Security Act is effective
from November 11, 2017 (Kartik 25, 2074) by virtue of Section 1(2) of the Act. Section 1 (2)
of the Social Security Act provides that it will be effective from 91 (Ninety-One days) from
the date of assent by President.
Clause 2.1.1 of the act states that the government specifies the timeline within which the
employer is required to be listed in the Social Security Fund ("Fund"). The time is specified in
the Gazette notice that prescribes the sectors, business, industry or service that the Social
Security Act applies.
Clause 2.2.1 states that the employer to enlist the employees in the Fund. The timeline for
enlisting the employees depends on applicability of the said Act to the employer. For example,
the employers to whom the Social Security Act is applicable at its effective date i.e. Nov.11,
2017 should enlist its employees within six (6) months from the effective date. The other
employers should enlist the employees in the Fund within 3 months from the date of appointing
or establishing the employment relation with such employee.
9.4.20 Muluki Civil Act (Code), 2074 BS (2017 AD)
This Act came into action from 1st Bhadra, 2075. Clause 617 states that the tenure of lease
contract lasts for fourty years for the construction, development and operation of infrastructure
like electricity generation.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
187| P a g e Department of Electricity Development
Clause 640 states about the age of person engaging in the manual works. It states that a person
under 16 years should not be forced to engage in physically challenging works.
Clause 641 states that workers should not be liable to work more than 8 hours a day and 48
hours a week witbout extra time payments.
9.5 Guidelines and Manuals
9.5.1 MoEST- A Guide to Environmental Management Plan of Hydropower Projects
(2006 AD)
The guide sets out the guideline for the formulation of the environmental management plan of
hydropower development projects relating to project management structure, roles and
responsibilities of the stakeholders and the project proponent. It provides the framework for
monitoring and auditing principles and planning.
9.5.2 DOED Manuals for Preparing EIA Documents for Hydroelectric Projects
The Department of Electricity Development, Government of Nepal, in collaboration with the
United States Agency for International Development and International Resource Group has
developed a series of manuals for the conduction and preparation of EIA and IEE documents
in the power and transmission line development sector. Important manuals developed are:
• Manual to establish baseline information, impact analysis and mitigation measures for
hydropower project, December (2006)
• Manual for Addressing Gender Issues in Environmental Impact Assessment/Initial
Environmental Examination for Hydropower Projects (2005)
• Manual for Conducting Public Hearings in the Environmental Impact Assessment
Process for Hydropower Projects, (2004)
• Manual for Developing and Reviewing Water Quality Monitoring Plans and Results for
Hydropower Projects (2002)
• Manual for Preparing Environmental Management Plan (EMP) for Hydropower
Projects, (2002)
• Manual for Developing and Reviewing Water Quality Monitoring Plans and Results for
Hydropower Projects, (2002)
• Manual for Preparing Environmental Management Plan (EMP) for Hydropower
Projects (2002)
• Manual for Preparing Terms of References (TOR) for Environmental Impact
Assessment (EIA) of Hydropower Projects, with Notes on EIA Report Preparation,
(2001)
The manuals set forth by DoED provide systematic details of methods and tools for the
conduction of IEE/EIA public hearing, IEE/EIA level assessment of gender related issues,
preparation of IEE/EIA level environmental management plans, review of IEE/EIA level water
quality assessment, and preparation of IEE/EIA terms of reference.
The EIA study team has thoroughly reviewed available manual and followed those as guiding
documents while carrying out the EIA study of the proposed DK5HPP.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
188| P a g e Department of Electricity Development
9.5.3 Hydropower Environmental Impact Assessment Manual, 2074 BS (2018 AD)
Ministry of Forests & Environment has prepared this Hydropower Environmental Impact
Assessment Manual, in line with the National Environmental Impact Assessment Guideline. It
has undergone extensive gap analysis of existing Nepali EIA related documents and legislation
followed by a series of multi-stakeholder participatory processes in order to assist hydropower
companies conduct better EIAs that meet international standards and aid the Government with
the review and approval process.
This Manual has been designed in a format that is user-friendly and aims to guide practitioners,
regulators and developers in the industry understand in detail the importance of several existing
gaps like meaningful engagement of stakeholders, adequate definition of areas of influence and
study areas, sufficient identification of baseline studies, knowledge on identifying and
quantifying impacts, need of precision on impact predictions, and suitable alternatives analysis.
9.5.4 Nepal Environmental Impact Assessment Guidelines, 2050 BS (1993 AD)
To address environmental impact assessment as envisaged by NCS 1987, National
Environmental Assessment (EIA) Guidelines were endorsed by Government of Nepal on 27
September 1992 and gazetted on 19 July, Volume 1993, Number 5. The guideline provides
criteria for project screening and initial environmental examination (IEE). This includes
scoping, preparation of terms of reference for EIA, methods for EIA report, impact
identification and prediction, impact mitigation measures, review of the draft EIA report,
impact monitoring, evaluation of impact studies, impact auditing, community participation and
schedules and annexes to IEE and EIA.
Many of the guideline provisions are now included in the Environment Protection Act 1977
and Environment Protection Regulation 1997. EIA in Nepal has now become legally
mandatory. However, as the national Environmental Guidelines, 1993 have not been issued
under the environmental Protection Act (1997), they do not have any legal force. It is a policy
guideline issued by the Government that is still followed in the matters which are not covered
by the Environment Protection Act (1997) and Environment Protection Regulations (1997).
9.5.5 EIA Guidelines for Forestry Sector, 2052 BS (1995 AD)
Within the broad framework of the National EIA guidelines, two separate EIA guidelines of
Forestry and Industry Sector were prepared and the government endorsed them in 1995. These
two guidelines primarily differ on schedules, which include projects and program requiring
levels of environmental assessment.
It has given focus on to make proposals socio-culturally acceptable, economically feasible, and
environmentally sustainable, thereby to conserve genetic resources and biodiversity, and
minimize environmental damage in forest areas and facilitate in identification of positive and
adverse impacts of proposal implementation.
9.5.6 Department of Forest Guidelines
The Department of Forest has made public various guidelines with relevance to environmental
assessment of the development projects as under:
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
189| P a g e Department of Electricity Development
i. Forest Produces Collection, Sale and Distribution Guidelines, 2057 BS (1998 AD)
The guidelines, clauses 3 to 4 have specified various procedures and formats for getting
approval for vegetation clearance, evaluation of the wood volume etc. and government offices
and officials responsible for the approval. These provisions have a direct relevance to the
development of the project and need compliance to these provisions.
ii. Community Forest Development Program Guidelines, B.S. 2071 (2014 AD)
The community forest development guideline, 2014 is prepared with the amendment in
community forest guideline, 2000. The guideline is prepared for users’ groups, field workers
in government and nongovernmental organization, forester and facilitators involving in the
field of forest development. The guideline shall be followed by users' group, partner
organization for users' group formation and forest action plan preparation, implementation,
monitoring and evaluation.
iii. Community Forest Inventory Guidelines, 2061 BS (2005 AD)
The guideline for inventory of community forests advice to classify the forest into timber trees,
pole size trees and regeneration on the basis of diameter. It has recommended using 25 m x 20
m size of quadrat for timber trees, 10 m x10 m for shrub and 5 m x 5 m for sapling and 2 m x
5 m for seedling plots in the community forest. Plants having DBH (Diameter at Breast Height,
i.e. 1.3 m above ground) greater than 30 cm is considered as trees. Trees having DBH between
10 to 29.9 cm are categorized as poles and plants having less than 10 cm DBH and more than
one-meter height belongs to sapling and plants having height of less than one meter categorized
as seedlings. The guidelines provided the methods of calculating volume of timber and fuel
wood. The guideline also advises to stratify the large areas in the hills and mountains to
eliminate variations in slope aspects etc. After stratification, area of each stratum could be
calculated.
9.6 Working Procedures/Work Plans
9.6.1 Working Procedure for the Use of National Forest Area for National Priority
Project, 2074 BS (2017 AD)
Realizing the need to manage the provision in relation with giving approval to use forest area
for operation of national priority projects, Government of Nepal has endorsed this “Working
Procedures relating to use of National Forest Area for Projects of National Priority, 2017”
under provisions stipulated in Clause 68 (1) of the Forest Act, 1992. This working procedure
supersedes the previous “Working Procedures relating to use of National Forest Area for other
purposes, 2006”.
Section 3 (1) of this procedure requires Ministry (concerning to specific national priority
project) to carry out feasibility study and alternatives of the project avoiding the national forest
to the extent possible. However, as per the provision of Section 3 (2), if such study carried out
in accordance with Section 3 (1) requires use of forest area, then the alternative requiring
minimum forest area or clearance of minimum number of trees and vegetation shall be selected.
Section 4 (1) of the Procedures provisions need of preparation of an Initial Environmental
Examination or an Environmental Impact Assessment Report relating to environmental
impacts of such project which requires forest area for its implementation in accordance with
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
190| P a g e Department of Electricity Development
the prevalent Environment Protection Act and Environment Protection Regulation. If the
investigation carried out in accordance with Section 4 (2) reveals implementation of the project
causes impacts on the environment, then the concerned Ministry shall prepare a report
incorporating mitigation measures to minimize such impacts along with environmental
management plans for the project. Section 4 (4) requires concerned Ministry to take approval
from the Ministry of Forests and Environment prior approval of the IEE or EIA reports in
accordance with prevalent law for the projects requiring national forest area.
Section 5 (1) describes the procedures to submit application for the use of national forest areas
attaching necessary documents such as evidential reasons and rationality of requirement of
national forest area, copy of relevant license, DPR and other technical documents, feasibility
and alternative study report carried out as per Section 3 of the procedure and the reports
prepared in accordance with Section 4 (1) or Section 4 (3) of the Procedure. Documents proving
the project for which the national forest area is required is a national priority project as well as
national forest area is required for such project must be attached along with the application.
Section 8 describes provisions relating to availing land area as a replacement for the land area
to be used for the implementation of the project in accordance with the procedures and Section
9 describes provisions on possibility of availing monetary compensation (as per the rate
determined by the Ministry of Forests and Environment) of the national forest area to be used
if the project could not avail replacement land area.
Section 10 explains provisions relating to compensatory plantation and requires 25 saplings to
be planted for loss of a tree. The proponent of project shall bear cost of land area equivalent to
land area occupied by the physical infrastructures of the project and also cost of afforestation
in the area designated by the concerned District Forest Office as well as the cost of maintaining
and protection of such afforestation areas for five years; after which such forest shall be handed
over to the concerned DFO. If the project is unable to carry out afforestation by itself, then the
project shall avail cost of afforestation and cost for maintaining and protection of afforested
area to the concerned District Forest Office which shall carry out the afforestation and
subsequent maintenance and protection of the afforested area.
As per Section 11, the project shall pay annual lease amount for temporary occupancy of
national forest at the rate fixed for leasehold forests as per Schedule 20 of Forest Regulations,
1993 which shall be deposited in federal saving account.
Section 12 of the Procedure mandates the project to implement mitigation measures mentioned
in IEE or EIA report of the project and the cost for such measures shall be borne by the project
itself.
9.6.2 Working Procedures relating to Initial Environmental Examination (IEE) and
Environmental Impact Assessment (EIA) of Hydropower and Transmission Line
Project, 2073 BS (2016 BS)
This Working Procedures has been formulated in accordance with Rule 94 (1) of the Electricity
Regulation, 1992 in order to simplify procedures relating to IEE and EIA as mentioned in
Clause 76 of the Concept Paper and Work Plan for National Energy Crisis Alleviation and
Electricity Development Decade, 2015. As per the Procedures, the IEE report registered in
Registration Section of the Department of Electricity Development shall be forwarded directly
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
191| P a g e Department of Electricity Development
to the Planning Section. The concerned officer shall examine the IEE reports and will request
(taking consent from Environment Section Chief) for additional information, if any within two
working days. After receiving all necessary documents, required number of copies (both hard
copy and electronic copy) of the report shall be requested for Review Committee. The project
proponent shall be informed to carry out presentation of the IEE report within seven working
days. The review committee members shall be availed timely availed with the reports. The
review committee member shall study the report beforehand and avail their comments and
suggestions on the report after the presentation. The comments and suggestions of the review
committee members shall be compiled and given to the project proponent asking to revise and
submit the report within two working days. The revised IEE report shall be examined for if the
comments/suggestions are incorporated or on by the concerned officer and if all is found
satisfactory, the report shall be forwarded to Ministry of Energy, Water Resources and
Irrigation for approval along with the template. The Ministry of Energy, Water Resources and
Irrigation shall approve the report within 5 working days from the date of receipt of the report.
9.6.3 Concept Paper and Work Plan for National Energy Crisis Alleviation and
Electricity Development Decade, 2072 BS (2015 AD)
The Concept Paper was issued with an objective to substantially end the power outage within
one year, completely end power outage (even in the dry season) within two years and to ensure
energy security within the next decade. Realizing land acquisition remaining to be a major
hurdle in development of power projects, the concept paper has proposed a number of reforms
to simplify the process of land acquisition which include;
- Inapplicability of land ceiling to hydropower projects provided that such area of land
has been approved in the course of obtaining necessary environmental clearances, and
- Formation of special committees at the district level to review consideration for
acquisition of land.
Also, the concept paper attempts to ease and clarify the process for obtaining environmental
and social clearances by prescribing timelines for environmental and other agencies to process
applications and review/approve relevant documents and provide necessary clearances.
9.6.4 zf;sLo tyf cfly{s ;'wf/sf nflu tTsflng sfo{of]hgf, @)^( (2012)
Government of Nepal has placed energy section under high priority and special provision for
the transmission line construction has been made:
• %))) d]ufjf6 ljB't pTkfbg geP;Dd sf6]sf] ?vsf] ;+Vofsf] b'O{ u'0ffdf ?v jg tyf
jftfj/0f dGqfnon] pknAw u/fPsf] :yfgdf /f]Kg} kg]{ Joj:yfug]{ .
• hnljB't pTkfbgsf] nflu ?v sf6\g cg'dltdfu]sf] tL; lbgleq cg'dlt glbPdf :jtM cg'dlt
ePsf] dfgL sf/jfxL cuf8L a9fpg] .
9.6.5 Order relating to exemption of land ceilings, 2017
Government of Nepal has passed an order to exempt existing ceilings on land for selected
developmental entities including hydropower projects. Section 3 of the Order requires
application to filed to purchase land area more than ceiling prescribed by the Land Act, 1957.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
192| P a g e Department of Electricity Development
As per the Schedule 2 of the Order, hydropower projects can purchase land area in quantity
mentioned in the detailed project report of the concerned project.
9.7 Standards
9.7.1 Nepal Vehicular Mass Emission Standards, 2069 BS (2012 AD)
Nepal Vehicular Emission Standard, 2012 enforced for the vehicles operating on petrol, gas,
and diesel. The emission standards are very specific for two, three and four-wheeler vehicles.
The vehicles used by the project should comply with the vehicular emission standards during
the construction and operation phase.
9.7.2 National Ambient Air Quality Standard, 2069 BS (2012 AD)
National Ambient Air Quality Standard is established for various parameters such as TSP,
PM10, Sulphur Dioxide, Nitrogen Dioxide, Carbon Monoxide, Lead, Benzene, PM2.5 and
Ozone. The standard states that the maximum concentration stated for averaging time of 24
hours for TSP, PM10, Sulphur Dioxide, Nitrogen Dioxide, and PM2.5 and the maximum
concentration stated for averaging time of 8 hours for Carbon Monoxide and Ozone should be
under standard limit for at least 95% duration for one fiscal year and should not exceed
maximum concentration for 18 days in 365 days. No any parameters shall exceed its maximum
concentration limit for two consecutive days within one year.
9.7.3 National Noise Quality Standard, 2069 BS (2012 AD)
National Standard for Sound Quality is established as per Rule 15 of Environment Protection
Rules, 2054. The maximum limit of sound for city and residential area is 55 decibels for
daytime and 50 decibels for night hours. Whereas for the industrial area, the maximum limit of
sound is 75 decibels for daytime and 70 decibels for night hours. Further, for the peace zone,
the maximum limit of sound is 50 decibels for daytime and 40 decibels for night hours.
9.7.4 Standards for Emission from in-use and Imported Diesel Generators, 2069 BS
(2012 AD)
The MoSTE (now MoFE) introduced in October 2012 the National Diesel Generator Emission
Standard (NDGES) for new and in-use diesel generators with a capacity of 8 kW-560 kW
(under the 1997 Environment Protection Act). In doing so they followed the Indian standards
for construction equipment rather than for diesel gensets. Hence, the Nepal emission standards
for new and in-use diesel gensets are less stringent than in India. The emissions standards set
for new diesel generator imports is equivalent to Bharat Stage III standards and, for in-use
diesel generators, is equivalent to Bharat Stage II. The emissions limits are set for four major
pollutants: CO, HC, NOx, and PM. The emissions limit for PM for new DG sets less than 19
kW is 0.80 g/kWh; for 19 to <37 kW, the emissions limit is 0.60 g/kWh; for 37 to <75, it is
0.40 g/kWh; for 75 to <130 kW, it is 0.30 g/kWh; and for 130 to <560 kW, it is 0.20 g/kWh.
MoSTE has not yet been able to monitor the compliance of emissions standards for new and
in-use DG sets.
9.7.5 National Indoor Air Quality Standards, 2067 BS (2009 AD)
Government of Nepal has formulated noise level standard for different area for day and night
time. Department of Environment has been established under the Ministry of Population and
Environment for monitoring the environmental condition. The National Noise Quality
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
193| P a g e Department of Electricity Development
Standards, 2012 enforced by GoN has set quality standards for the maintenance of the ambient
noise quality. The project during its construction and operation will have to comply the set
standards for the ambient noise quality.
9.7.6 Nepal Drinking Water Quality Standards, 2062 BS (2005 AD)
Provides details of the water quality standards to be applied to all water supply Subprojects.
These set out the water quality parameters, which the water suppliers should adhere to. The
directives also ensure that the water sampling, testing and analysis procedures used to certify
that the drinking water supplied or to be supplied conforms to the NDWQS and also sets the
monitoring and surveillance procedures to certify that the quality of supplied water conforms
to the standards.
9.7.7 Tolerance Limits for Industrial Effluents to be Discharged into Inland Surface
Waters, 2003
The Ministry of Environment has set tolerance limits for the industrial effluents to be
discharged into the inland surface water. Since the project is considered as an industry it will
have to comply with the tolerance limits set in the standard prior to the discharge of the
effluents into the inland surface water during the construction and operation period.
9.8 International Instruments
9.8.1 The World Charter for Nature (1992)
The World Charter for Nature, 1992 seeks commitment from the States along with other public
authorities, groups and corporation to control the activities which might have an impact on
nature (particularly irreversible damage to the nature) and the best available technologies that
minimizes significant risks to nature or other adverse effects shall be used. Charter presents
special concerns over the pollutants and in its Clause 12 states "discharge of pollutants into
natural systems shall be avoided with special precautions for prevention of radioactive and
toxic wastes".
9.8.2 Convention on Biological Diversity (CBD) (1992)
Nepal signed the Convention on Biological Diversity (CBD) during the Earth Summit in June
1992; ratified it in the fall of 1993; and it has entered into force since 21 February 1994. Nepal
is committed to implementation of the convention. The Forest Act, 1993, Forest Rules, 1995,
EPA, 1997 and EPR 1997 are enforced by GoN in response to CBD. As the state is fully
committed to conserve its biodiversity, the proposed project being an entity of state itself is
also full-heartedly committed to conserve biodiversity in and around project area.
9.8.3 United Nations Framework Convention on Climate Change (1992)
The ultimate objective of this Convention and any related legal instruments that the Conference
of the Parties may adopt is to achieve, in accordance with the relevant provisions of the
Convention, stabilization of greenhouse gas concentrations in the atmosphere at a level that
would prevent dangerous anthropogenic interference with the climate system. Such a level
should be achieved within a time-frame sufficient to allow ecosystems to adapt naturally to
climate change, to ensure that food production is not threatened and to enable economic
development to proceed in a sustainable manner.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
194| P a g e Department of Electricity Development
9.8.4 ILO Convention C-169 (1989)
Article 7 of the convention provides the right to the indigenous and tribal people to decide their
own priorities for the process of development. However, for the national development plans
and programs, it mandates consultation with them in the formulation of the plans and programs.
Article 12, 13, 14 and 15 safeguards rights of the indigenous people in the land and natural
resources in territories traditionally occupied by them. In the event that the state retains the
right of the natural resources in their territories, it mandates formulation of special provisions
under the state legislation for participation in the decision-making process and resettlement
process with full compensation of the resulting loss or injury (Article 16). As Nepal is signatory
of the convention will have to comply the provisions stipulated in the conventions, if the project
is to impact the safeguard rights of the indigenous people.
9.8.5 The Basel Convention (1989)
The Basel Convention of 1989 was in response to a series of incidents involving dumping of
hazardous wastes in developing countries in Africa and Asia. Spirit of the Basel convention
will be followed ensuring hazardous waste generation at source that hazardous wastes and
treating/disposing such waste as close as possible to their source of generation.
9.8.6 Convention on International Trade in Endangered Species of Wild Flora and
Fauna (1973)
The convention classifies species according to criteria where access or control is important
(e.g. I-species threatened with extinction, II-species which could become endangered; III-
species that are protected; E- Endangered; V- Vulnerable, R-Rare (CITES 1983)). The project
will have to minimize impacts to the CITES species as far as possible.
The Project shall comply with the provisions of above listed policies, laws, guidelines,
manuals, standards and international conventions and treaties. Besides above-mentioned
legislations, the Project shall also comply with the provisions of any other legislation attracted
due to various activities that will be undertaken during project implementation.
9.9 Relevant Institutions
During the construction and operation of this project, some organisations will be directly
involved. They are grouped under local and national level institutions. The local institutions
include both village and district level organisations.
9.9.1 Local Institutions
Local Bodies
All the project components will be located in the Dudhkosi Gaupalika. Hence, this affected
Gaupalika can facilitate the project in land and property acquisition and compensation issues,
and educate the local people in assisting project construction in time. Based on the Local
Government Operation Act, the Gaunpalika can plan and implement the environmental
conservation programmes and the project can assist in such activities of the Gaunpalika.
District Administration Office (DAO)
The District Administration Office (DAO), Solukhumbu could assist the project on land and
property acquisition and compensation issues, and avoiding and/or resolving any conflicts
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
195| P a g e Department of Electricity Development
during the project implementation. Similarly, the Chief District Officer (CDO) might facilitate
the implementation of the project by issuing the license regarding the use of necessary
explosives.
District Coordination Committee (DCC)
The Solukhumbu DCC could play a pivotal role for timely completion of the project by
educating local people on its importance and also helping the Project for coordinating with
project affected local bodies in land acquisition process. As the DCC will receive part of the
royalty from this project during its operational stage, it might have additional interest to
complete the project to the earliest possible.
MapyaDudhkoshi Gaupalika
The entire project infrastructure is located within the MapyaDudhkoshi Gaupalika. The
proponent will have to work in close coordination with this local body. As the local bodies will
receive part of the royalty from this project during its operational stage, it might have additional
interest to complete the project to the earliest possible.
Other District Organisations
The District Forest Office and Land Revenue Office might provide technical assistance for the
conservation and management of forests and re-greening the project area, transfer the land
ownership in the name of the proponent once the private lands and properties are compensated.
Furthermore, the District Water Resources Committee might contribute to resolve any conflict
on water use(s) raised at different stages of the project, and facilitate its timely implementation.
Local level Project Coordination Committee
A local level Coordination Committee will be formed having representation from all declared
affected Gaupalikas in the project. This committee will facilitate in the implementation of the
project at the local level. The proposed development fund will be channelled through this
committee. This committee will also address the grievance of the local people if any from the
project activities.
9.9.2 National Institutions
Department of Electricity Development (DoED)
As the proponent of this project, DOED has also intention for timely approval of this EIA report
and the implementation of the project. Furthermore, the Dudhkoshi Gaunpalika can participate
in environmental monitoring works on behalf of the Ministry of Energy, Water Resources and
Irrigation.
Ministry of Energy, Water Resources and Irrigation
In this project, the Ministry of Energy, Water Resources and Irrigation can facilitate the EIA
report approval process by timely sending it, with its comments and suggestions, if any, to the
Ministry of Forest and Environment. It can also make necessary arrangements for land and
property acquisition for the smooth implementation of the project. As per the EPR (1997), the
ministry should be involved in environmental monitoring and it should also issue necessary
directives to the proponent to adopt measures to reduce or avoid adverse environmental
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
196| P a g e Department of Electricity Development
impacts. The ministry has also the responsibility to inform Ministry of Forest and Environment
about the directives issued to the proponent.
Ministry of Forests and Environment (MoFE)
The Ministry of Forests and Soil Conservation (MFSC) and Ministry of Populattion and
Environment has been merged and Ministry of Forests and Environment has been formed. The
ministry might promptly issue permission to use barren land and the Division Forest Office
(DFO) of Solukhumbu might issue permit for cutting and transportation of the trees even not
registered as the private forest based on the provisions of the Forest Rules (1995). The DFO
might also be involved in providing technical inputs on forestry matters to the project, and in
environmental monitoring of the forestry sector.
As per the EPR, the Ministry of Forests and Environment approves the EIA report. The MoFE,
however, would be involved in preparing the environmental auditing report after two years of
operation of the project.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
197| P a g e Department of Electricity Development
10. ENVIRONMENTAL MONITORING
10.1 Environmental Monitoring Plan
Monitoring is an important element of the environmental management as there is always some
uncertainty to the extent of the project impacts on the natural, socio-economic and cultural
environments. Similarly, there is uncertainty about the effectiveness of the proposed mitigation
measures. The objective of monitoring is to provide information that the predicted impacts of
a project are within the acceptable limits and to provide early warning about unacceptable
environmental conditions. Environmental monitoring programmes are also required to ensure
project compliance with recommended environmental studies conducted for the project as well
to ensure compliance with environmental laws and in ameliorating and eliminating adverse
impacts caused by the project. Therefore, a monitoring programme is required to evaluate
application and effectiveness of the mitigation measure, compliance with environmental
standards and designing of alternative mitigation measures for negative impacts that were
perceived significant during the study phase.
The National EIA Guidelines of 1993 propose three types of monitoring. They are baseline
monitoring, compliance monitoring and impact monitoring; the plans for which are presented
in this chapter.
10.2 Baseline Monitoring
Baseline monitoring is required to compile and maintain the database on environmental
conditions prior to the implementation of the project. The primary concern during this phase
will be to implement field data collection programs to obtain the baseline conditions, such as
scientific and sociological information needed to finalize the design and cost of the mitigation
measures. This is especially important if the project is delayed due to unforeseen
circumstances. Such data recorded before project implementation will facilitate the comparison
of information obtained in monitoring activities conducted during project implementation.
Changes in the baseline conditions will imply the impact of the project implementation on
environment. Hence, baseline monitoring serves as an important basis for monitoring of the
project impacts on the environment i.e. the impact monitoring. A plan for the baseline
monitoring for the proposed Dudh Koshi-5HPP is presented in Table 10.1.
Table 10-1: Plan for Baseline Monitoring
SN Parameter Indicators Method Location
A. Physical Environment
1 Topography Degrees of slopes Site observation Construction area
2 Land use Area of land under different land
use such as forest, shrubs, barren
land, cultivated lands etc.
Site observation, GIS
Mapping
Project Area
3 Hydrology Discharge and flood level Direct discharge
measurements, gauge
readings
Dudh Koshi
River
4 Geology Stability of slopes, Occurrence of
land slides
Field observation Project Area
5 Air Quality Dust pollution (TSP, PM10);
Industrial Pollution
Observation and air
quality measurement
Headworks,
Powerhouse and
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
198| P a g e Department of Electricity Development
SN Parameter Indicators Method Location
using a high-volume
sampler
Settlements along
the project road
6 Water Quality Temperature, pH, Turbidity,
Electrical conductivity, TSS, TDS,
Iron, Sulphate, BOD, COD, DO,
Alkalinity, Total Hardness, Total
Coliform and Fecal Coliform
Field measurements,
Water sampling and
lab testing
Dudh Koshi
River at
headworks and
powerhouse site,
7 Noise Loudness and intensity of noise Field measurement
using a dB meter
Headworks,
Powerhouse and
Settlements along
the project road
8 Solid waste Quantity and composition of waste Observation and
questionnaire survey
Project Area
B. Biological Environment
9 Forest and
vegetation
Forest area, type, species
composition, frequency, density,
BA, crown cover, standing stock,
biomass, Timber, fodder and
fuelwood
NTFPs, forest management, forest
use, Energy use
Observation, GIS
mapping, Forest
measurements
(Quadrate sampling),
household surveys,
FGD
Project Area
10 Wildlife
(including
mammals,
avian fauna
and
herpetofauna)
Wildlife habitat, wildlife species,
hunting and poaching activities,
crop and animal depredation,
human wildlife conflicts
Observation, Transect
survey, Questionnaire
surveys, FGD, KII
Project Area
12 Fishes Fish species, abundance, spawning,
rearing and breeding habitats,
fishing practices, fishing
households, fish market
Observation, fish
sampling,
Questionnaire surveys,
FGD, KII
Dudh Koshi
River
C. Socioeconomic and Cultural Environment
13 Demographic
characteristics
Household numbers, population,
ethnicity, religion, language
spoken, migration, education and
literacy, occupation and skills
Secondary sources,
Household survey,
FGD
Project Area
14 Agriculture
and livestock
Land ownership, land holding,
cultivated area, cropping practices,
crop production, crop yield, agro-
biodiversity
Livestock ownership and holding,
livestock products
Crop and livestock product market
Secondary sources,
Household survey,
FGD
Project area
15 Economy Occupation and skills, markets,
annual income and expenditures,
food sufficiency
Household survey,
FGD
Project area
15 Sanitation and
health
Drinking water source, treatment
practices, toilet availability and
types, cooking practices, waste
management practices
Diseases, treatment practices,
disability, natality and mortality
Secondary sources,
Household survey,
FGD
Project Area
16 Culture Religious shrines, festivals Discussions with the
local people, Rural
Project area
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
199| P a g e Department of Electricity Development
SN Parameter Indicators Method Location
Municipality wards
and observation,
Questionnaire surveys
17 History and
archaeology
Sites of archaeological and historic
significance
Secondary Sources,
FGD
Project area
18 Gender Property ownership in women,
participation of women in
community groups, decision
making by women
Household survey,
FGD
Project area
19 Vulnerable
communities
Participation of vulnerable
communities in community groups
Secondary Sources,
FGD
Project area
20 Infrastructures Road, Bridge, School, health
facilities, irrigation system,
drinking water system, community
building, watermills, Temples and
shrines, Cremation sites etc.
Secondary Sources,
FGD, Rural
Municipality surveys
Project area
Baseline monitoring will be carried out before the project construction commencement. For
DK-5 HPP, if the project comes under construction within 2 years from the data collection for
this EIA study, the baseline data and information presented in this EIA report will serve as
baseline and hence baseline monitoring will not be required. However, under any unforeseen
circumstances, if the propose DK-5 HPP gets delayed for more than two years (from the data
collection for the present EIA), the project requires to carry out a baseline monitoring prior
project construction. Any difference in baseline conditions in any of the physical, biological
and socioeconomic & cultural parameters observed and assessed during baseline monitoring
from those established during present EIA study will provide a reference to understand the
changes occurring in project area environment without project implementation scenario.
The responsibility for the baseline monitoring including the cost for monitoring lies within the
project proponent. Cos have been allocated for baseline monitoring of the proposed DK-5 HPP.
10.3 Compliance Monitoring
Compliance Monitoring employs a continuous recording of specific environmental quality
indicators in order to ensure project compliance with recommended environmental protection
standards. The main objective of the compliance monitoring is to ensure that all conditions set
forth and commitments made in the approved EIA report and other applicable regulatory
requirements and standards, the project documents including project contracts and
specifications etc. An early compliance assessment is also required to check if the
environmental mitigation activities prescribed in the approved EIA report are well integrated
in subsequent project documents such as detailed engineering design and tender documents.
Table 10.2 gives the compliance monitoring plan, which includes compliance parameters,
indicators for measuring compliance, methods to be followed and guiding document to be
referred, responsible parties for compliance monitoring and the schedule for compliance check.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
200| P a g e Department of Electricity Development
Table 10-2: Plan for compliance monitoring
S. N. Parameter Indicators Method/ Guiding Document Responsible
Agency Schedule
1
EIA mitigations
Incorporation of EIA mitigation measures
recommendations into contractual documents
Review of detailed design, project
specification and tender documents/
Approved EIA
Consulting
engineers
Following
completion
of tender
documents
2 Environmental
Considerations
The presence of each of the environmental
considerations from the tender documents in the
work plan
Review of proposed work plans/
Approved EIA
Consulting
engineers
During
contract
negotiations
3
Contractor’s
compliance in carrying
out environmental
mitigation activities
prescribed in EIA,
project contract
documents and project
specification
documents
Forest clearance Excavation of lands for project
construction, , spoils management, work area
hygiene, application of slope stability measures,
air quality protection, water quality protection,
noise minimization, solid waste management, over
extraction of aggregates, felling of trees, intrusion
in the surrounding forest, blasting practices, pre-
employment screening of project workers, safety
equipment for workers and safety assurance
practices in area, public safety assurance practices,
project camp management (drinking water, toilets,
cooking fuel), control of social disorder
(alcoholism, gambling, prostitution) and all others
mentioned in Chapter 9 of this report
Site observation and discussion with project
management, project staffs and local people
using a checklist/
Approved EIA, Project Contract and
Specification document, Regulatory
documents of GON
Consulting
engineers/
DK-5 HPP
EMU
Continuous
during the
construction
period
4
Contractor’s
compliance to GON’s
regulatory
requirements (Acts,
Regulations,
Guidelines, Standards)
Water quality, air quality, noise, forest clearance,
employment, occupational health and safety
Review of the regulatory documents, enlisting
of the relevant clauses, site inspection and
observation/
Constitution of Nepal (2015), Environment
Protection Act (1996) and Environment
Protection Regulation (1997), Aquatic
Animals Protection Act (1961), Labor Act
(1992), Water Resources Act (1992), Water
DK-5 HPP
EMU
Continuous
during the
construction
period
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
201| P a g e Department of Electricity Development
S. N. Parameter Indicators Method/ Guiding Document Responsible
Agency Schedule
Resources Regulation (1993), Forest Act
(1992), Forest Regulation (1993), Local
Government Operation Act (2017); Local Self
Governance Regulation (1999), Soil and
Watershed Conservation Act (1982), Soil and
Watershed Conservation Regulation (1982),
Explosives Act (1961), Nepal Ambient Air
Quality Standards (2003), Nepal Vehicular
Mass Emission Standard (2000), Nepal
Drinking Water Quality Standards
(2005),Tolerance Limits for Industrial
Effluents to be Discharged into Inland Surface
Waters (2003)
5 Project Proponent’s
compliance in carrying
out activities
prescribed in
environmental
mitigation and
environmental
enhancement activities
Compensation, soil erosion and landslide control,
compensatory plantation, staff employment,
implementation of trainings, income generating
programmes, awareness programs, support to
social institutions and all others mentioned in
Chapter 9 of this EIA report
Review of project correspondence letters,
evidence documents, observations, interviews
with the concerned project authority,
interviews with the project affected
households/ Approved EIA
Concerned
Ministry and
Departments
of GON
Continuous
during the
construction
period
6
Project Proponent’s
compliance GON’s
regulatory
requirements
Land acquisition and compensation, project staff
employment, environmental protection
Review of the regulatory documents, enlisting
of the relevant clauses, site inspection and
observation/
All the regulatory documents mentioned in
point 4 above (of this table) including Land
Acquisition Act (1977), Industrial Enterprise
Act (1992)
Concerned
Ministry and
Departments
of GON
Continuous
during the
construction
period
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
202| P a g e
Department of Electricity Development
10.4 Impact Monitoring
Impact Monitoring measures the physical, biological, socio-economic and cultural parameters
within the project area during the construction and operation phases in order to detect
environmental changes that occur as a result of project implementation. The main objectives
of impact monitoring are to ensure that the actual impacts measured in the field are really within
the manageable limit of the designed mitigation measures and also to detect any unexpected
damages and thereby providing early warning to the responsible agencies for undertaking
corrective and additional measures to avert, if possible or minimize the risks of such
unanticipated impacts. It involves actual measurement of the impacts of construction activities
on the environment, such as water quality samples being taken at regular intervals to assess
pollution concentrations in the river from construction work camps, after mitigation steps are
taken.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
203| P a g e Department of Electricity Development
Table 10-3: Plan for impact monitoring
S. N. Parameter Indicator Location Methods Schedule Responsible
agencies
A. Physical Environment
1 Land use Change in area under
different land use Project Area
Observation,
GIS Mapping
One time after
completion of project
construction
DK-5 HPP EMU
2
Soil Erosion
and land
stability
Development of rill
and gullies,
occurrence of
landslides, drainage
failures, river bank
cutting
Construction area,
spoil disposal areas,
project roads, Dudh
Koshi River bank
Observation
Continuous
throughout project
construction
DK-5 HPP EMU
3 Air quality TSP, PM10, SOx,
NOx, CO
Headworks,
Powerhouse and
settlements along
project road
Sampling using
high volume
sampler
Twice a year during
construction phase in
dry and wet season;
one time after a year of
powerhouse operation
in Powerhouse
complex
DK-5 HPP EMU
2 Water Quality
Temperature, pH,
Turbidity, TDS, TSS,
Conductivity,
alkalinity, hardness,
iron, BOD, COD,
SO4, DO, Total
Coliform, Fecal
Coliform
Dudh Koshi River
downstream of weir,
upstream and
downstream of
powerhouse, drinking
water of project camp
Water
sampling and
laboratory test
Twice a year during
construction phase in
dry and wet season;
two-time monitoring
of project permanent
camp drinking water
and Dudh Koshi River
near powerhouse
DK-5 HPP EMU
3 Noise Noise intensity level
Major construction
areas, settlements
along project road
Measurement
of noise using
dB meter
During peak
construction period
DK-5 HPP EMU
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
204| P a g e Department of Electricity Development
S. N. Parameter Indicator Location Methods Schedule Responsible
agencies
4 Solid waste Proliferation of waste Project area Observation
Continuous
throughout project
construction and one
year of project
operation
DK-5 HPP EMU
B. Biological Environment
5 Forest Change in forest area
(area)
Headworks,
Powerhouse, Water
way alignment, project
road alignment, forests
in the project area
Observation,
GIS mapping
One time monitoring
after completion of
project construction
DK-5 HPP EMU
/CFUG
6 Vegetation No of trees and
shrubs cleared
Headworks,
Powerhouse, Water
way alignment, project
road alignment
Records of
clearance of
species
During clearance in
each area
DK-5 HPP EMU
7 Protected
species
No of protected
species cleared
Headworks,
Powerhouse, Water
way alignment, project
road alignment
Records of
clearance of
species
During clearance in
each area
8
Compensatory
Plantation
Status of plantation
and survival rate Plantation area
Records of
plantation and
counting of
survived
saplings
Every three months
after plantation DK-5 HPP EMU
9 Wildlife
Poaching events, crop
depredation
frequency
Project area Interviews with
local people
Continuous
throughout project
construction
DK-5 HPP EMU
10 Fish Fish diversity and
abundance
Dudh Koshi River
between downstream
of weir and upstream of
powerhouse
Fish sampling
Every four months
during construction
and every four months
for one year during
operation
DK-5 HPP EMU
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
205| P a g e Department of Electricity Development
S. N. Parameter Indicator Location Methods Schedule Responsible
agencies
C. Socioeconomic and Cultural Environment
11 Affected
households
Livelihood
conditions of the
affected households
by land and property
acquisition
Affected households
Household
survey using
structured
questionnaires
End of every year
during construction
period; at the end of
the first year of
operation
DK-5 HPP EMU
12 Affected
community
Quality of
community life in
project area
Affected Rural
Municipality
Observation,
Interviews,
FGD
End of every year
during construction
period; at the end of
the first year of
operation
DK-5 HPP EMU
13 Employment
No of local as well as
migrant employees
working for the
Contractor and the
project proponent
Project Work Records of
employees
Every month during
construction phase;
one time monitoring in
the beginning of
operation
DK-5 HPP EMU
14 Community
services
Pressures in existing
service institutions
and facilities such as
schools, health posts,
drinking water etc.
Service institutions in
the project area
Records of
particular
service
institution such
as health posts
and school,
interviews with
schools,
teachers, health
personnel,
water user
groups
Every four months
during construction,
one-time monitoring
at the end of first year
of operation
DK-5 HPP EMU
15
Community
health and
safety
Incidence of
communicable
diseases, STDs,
accidents
Project area
Interviews,
structured
questionnaire
surveys,
Every three months
during construction,
one time monitoring at
DK-5 HPP EMU,
PHU
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
206| P a g e Department of Electricity Development
S. N. Parameter Indicator Location Methods Schedule Responsible
agencies
reports from
health
institutions
the end of first year of
operation
16
Occupational
health and
safety
Injuries, deaths,
accidents of
construction
workforce
Construction areas
Project reports,
interviews with
construction
workers
Every month during
construction, one time
monitoring at the end
of first year of
operation
DK-5 HPP EMU,
PHU, Contractor
17 Conflicts
Conflicts between
locals and outside
workforce
Project area Interviews,
record keeping
Every months during
construction
DK-5 HPP EMU,
Rural Municipality
18 Law and order Events of burglary,
fights Project area
Interviews,
record keeping
Every month during
construction
DK-5 HPP EMU,
Rural Municipality,
Police post
19 Commodity Prices of the
commodity Project area
Records of
commodity
prices in local
markets
Every month during
construction, one time
at the end of first year
of operation
DK-5 HPP EMU
20
Environmental
Enhancement
Programs
People perception of
environmental
enhancement
programs
Project area
Discussions
with the
beneficiary of
enhancement
programs
Every six-month
during project
construction, one time
at the end of first year
of operation
DK-5 HPP EMU
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
207| P a g e
Department of Electricity Development
11. ENVIRONMENTAL AUDITING
11.1 Introduction
An environmental auditing will compare monitoring results with information generated during
the preproject period. Comparisons can be made with similar projects or against standard
norms. It helps to evaluate the accuracy and adequacy of EIA predictions by relating actual
impacts with predicted impacts.
Impact monitoring provides raw data, which can be used to undertake an EIA audit. Such audit
can be effective tools by providing control authorities with an overall picture of the main
impacts of the project and identifying issues of concern, where actual impacts have exceeded
norms. However, MoFE will carry out post-construction environmental audit study after two
years of commencement of project operation as per provision of EPR, 2054. It helps to examine
the actual environmental impacts, accuracy of predictions, effectiveness of environmental
impact mitigation and enhancement measures and functioning of monitoring mechanisms.
The environmental audit for physical, biological and socio-economic and cultural environment
is described in sub sections 11.2, 11.3 and 11.4 respectively. The environmental audit shall
include, but not be limited to, the following tasks.
11.2 Physcical Environment
Following aspects shall be covered under the physical environment:
• Changes in baseline condition in the physical environment of the project area after the
project construction such as topography, land use, landslide, hydrology;
• Accuracy of the predicted impacts;
• Magnitude of the predicted impacts;
• Effectiveness of the implemented mitigation measures;
• Compliance with the EIA report;
• Compliance with environmental clauses of tender document;
• Identification of numbers and area of non-compliances; and
• Effectiveness of compliance monitoring system.
11.3 Biological Environment
Following aspects shall be covered under the biological environment:
• Changes in baseline condition in the biological environment of the project area after the
project construction;
• Accuracy of the predicted impacts;
• Magnitude of the predicted impacts;
• Effectiveness of the implemented mitigation measures;
• Compliance with the EIA report;
• Compliance with environmental clauses of tender document;
• Identification of numbers and area of non-compliances; and
• Effectiveness of compliance monitoring system
11.4 Socio-economic and Cultural Environment
Following aspects shall be covered under the socio-economic and the cultural environment:
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
208| P a g e
Department of Electricity Development
• Changes in baseline condition in the socio-economic and cultural environment of the
project area after the project construction;
• Accuracy of the predicted impacts;
• Magnitude of the predicted impacts;
• Effectiveness of the implemented mitigation measures;
• Positive and negative impacts of the project on local community;
• Compliance with the EIA report;
• Compliance with environmental clauses of tender document;
• Identification of number and area of non-compliances;
• Effectiveness of compliance monitoring system; and
• Impact of the project on the regional and national economy
11.5 Approach and Methodology
Environmental audit will follow the same methodology and survey sites covered in
EnvironmentalImpact Assessment Study and monitoring report. Review of monitoring report,
field visit, data collection, sampling, lab test and use of checklist, meeting and discussion with
local community, Rural Municipality, DCC and the line agencies shall be the main
methodologies to be adopted for the environmental impactaudit.
11.6 Schedule
Environmental audit of the proposed project shall be conducted after two years of the
completion of the project, as per EPR, 2054. The estimated time for the audit is proposed for 6
months from the date of commencement.
11.7 Required Human Resources
Environmental audit requires a team of multidisciplinary experts with relevant experiences
inhydropower project. Following team is proposed for environmental audit of the proposed
Project.
• Team Leader/ Environmental Expert;
• Hydropower Engineer/ Civil Engineer;
• Environmental Engineer;
• Forestry Expert/ Ecologist;
• Socio-economist; and • Support staff
11.8 Estimated Cost
The estimated cost to carry out the environmental impact audit is estimated as NRs.
21,00,000.00 including the experts, datacollection, sampling, lab test, transportation and report
production. The detail of the environmental auditcost is presented in the Table-11.1 below:
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
209| P a g e
Department of Electricity Development
Table 11-1: Environmental Audit Cost for DK5HPP
S. N. Particulars of Item Unit Quantity Rate (NRs.) Amount
(NRs.)
1. Personal Cost
Team Leader/Environment
Specialist
month 4 150,000.00 600,000.00
Environmental Engineer month 3 100,000.00 300,000.00
Ecologist/Forester month 3 100,000.00 300,000.00
Social Safeguard Specialist month 3 100,000.00 300,000.00
Support Staff month 4 50,000.00 200,000.00
2. Field per diem LS 150,000.00
3. Vehicles & Logistics LS 100,000.00
4. Office supplies & consumables LS 100,000.00
5. Report Preparation LS 50,000.00
Grand Total (NRs.) 2,100,000.00
11.9 Organizational Responsibility
The project proponent will be responsible for the auditing activities after the completion of the
project as per the Environment Protection Regulation of the Government of Nepal. However,
agencies like the Ministry of Forests and Environment, Ministry of Energy, Water Resources
and Irrigation and other relevant organizations will be consulted during the auditing. Local
NGOs and National NGOs may also be entrusted to carry out the task, if they are engaged to
do so by the government.
MoFE is supposed to undertake the post-construction environmental audit work of the
Dudhkoshi-5 Hydropower Project as per the provision made in Environment Protection Rules,
2054 (1997).
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
210| P a g e
Department of Electricity Development
12. CONCLUSIONS
The proposed Dudh koshi-5 Hydropower Project will generate 618.80 GWH of annual average
energy, out of which 100.39 GWh would be dry season (Paush to Chaitra) and wet season
energy would be 518.41 GWh.
Apart from the generation of the hydroelectric power, the project will provide a number of
benefits both during the construction and the operational stages. During the construction stage,
some of the beneficial impacts include the employment generation, increase in local economy
and enhancement of technical skills and know-how. It will have long-term impact for the
development of the local area.
The project will also result in some adverse impacts of different magnitudes, in different
locations and even for the long-term duration. The major adverse impacts include land
acquisition. The project intends to acquire about 4.133 ha of private land and about 20.191 ha
of the government land. This project will also have significant impact in the forest area about
15.104 ha.
During the operation phase, water diversion will have impact on the river stretch (from
headworks to powerhouse site) due to reduced flow for an extended length about 7.9 km.
However, the rivulets between headworks and powerhouse contribute substantial amount of
water to maintain ecological flow. This EIA report includes mitigation measures for each of
the significant adverse impacts. The proposed project could be implemented by ensuring the
implementation of the proposed EPMs (Environmental Protection Measures). The project will
also commit to compensate/mitigate any other impact encountered during the construction and
operation of the Project. No further environmental study will be required for project clearance.
Environmental Impact Assessment (EIA) Report of Dudhkoshi 5 Hydropower Project (110 MW)
211| P a g e
Department of Electricity Development
13. REFERENCES
• CBS (2014). National Population and Housing Census 2011 (National Report). Volume 01,
NPHC 2011.Central Bureau of Statistics, Government of Nepal, Thapathali, Kathmandu.
• DDC (2009). District Development Profile of Solukhumbu, Salleri.
• DOED (2001). Manual for Preparing Scoping Document for Environmental Impact
Assessment (EIA) of Hydropower Projects. Department of Electricity Development,
Kathmandu.
• DOED (2001). Manual for Preparing Terms of Reference (TOR) for Environmental Impact
Assessment (EIA) of Hydropower Projects with Notes on EIA Report Preparation. Department
of Electricity Development, Ministry of Water Resources, Kathmandu.
• EPR (1997). Environment Protection Rule of Nepal.
• EPA (1997). Environmental Protection Act of Nepal.
• ERM (2009). Baynes Hydropower ESHIA: Final Scoping Report. ERM Southern Africa in
association with Environment Dynamics, Urban Dynamics, IRDNC, Holisticos and Angola
Research Institute, October, 2009.
• SchEMS (2008). Baseline Study of Tamakoshi III Hydropower Project. Volume I Main Draft
Report.
• Draft Feasibility Study Report of Dudh Koshi-5 Hydropower Project, unpublished
• Field Investigation Reports of Dudh Koshi-5 Hydropower Project
• Draft Feasibility Study Report of Dudh Koshi-4Hydropower Project, unpublished
• Draft IEE Report of Dudh Koshi-4Hydropower Project, unpublished
• Village Development Profile of Basa VDC and BakuVDC. (2009)
ANNEXES