elemental bill of quantities for 3 bedroom apartment block
TRANSCRIPT
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
1/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
GROUP ELEMENT Nr. 1 SUBSTRUCTURE
SUBSTRUCTURE (PROVISIONAL)
D GROUNDWORK
D20 EXCAVATING AND FILLING
EXCAVATING IN NORMAL FIRM GROUND
Site Pre aration
A Clearing site vegetation, bushes, shrubs, undergrowth,
hed es and trees
m2 409 35 14,315.00
Excavation
B Excavating topsoil average 150mm deep m2 409 100 40,900.00
Reduced level excavation
C maximum de th; not exceedin 250mm dee m2 51 220 11,220.00
Trench Excavation
D Excavating trench width exceeding 0.30m maximum
de th not exceedin 2.00m
m3 184 650 119,600.00
E Excavation in rock laterite and disposal of excavated
materials as directed
m3 20 1,150 23,000.00
Pits for concrete foundation; (47 Nr.)
F Excavating pits (47nr), maximum depth not exceeding
2.00m
m3 28 650 18,200.00
Disposal
G Excavated material; on site as directed; in spoil
maximum distance not exceedin 50m
m3 115 250 28,750.00
Filling to excavations
H Filling to excavations, average thickness exceeding
0.25m; arising from the excavations; Compacted around
foundations
m3 117 190 22,230.00
Granular materials
J Filling to make up levels, average thickness exceeding
250mm, laterite materials obtained off site.
m2 82 750 61,500.00
Carried to Collection 339,715.00
0 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
2/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
SUBSTRUCTURE (Cont'd)
Rock laterite hardcore
A Boulder rock; hardcore exceeding 250mm thick;
obtained offsite; depositing in layers 150mm maximum
thickness; com acted and consolidated under beds
m3 82 2,400 196,800.00
Surface Treatment
Pesticides: Dieldrex 20 anti-termite
B Treating the bottom, sides and surface of excavation m2 1437 50 71,850.00
E10: INSITU CONCRETE
Plain Insitu Concrete
Vibrated Grade 30.
C Blinding beds, thickness not exceeding 50mm thick;
oured on or a ainst earth
m3 9 14,500 130,500.00
Plain Insitu Concrete
Vibrated Grade 30.
D Foundations, 150 - 450mm thick m3 35 23,000 805,000.00
Reinforced Insitu Concrete
Vibrated Concrete Grade 30
Column bases m3 24 25,000 600,000.00
E Regular columns m3 3 25,000 75,000.00
Beds; 150mm thick m3 44 25,000 1,100,000.00
E20: FORMWORK FOR IN SITU CONCRETE
Sawn formwork to:
F Sides of column bases m2 72 1,100 79,200.00
G Sides of Regular columns m2 80 1,100 88,000.00
H Sides of floor bed m 121 165 19,965.00
Carried to Collection 3,166,315.00
1 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
3/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
E10: INSITU CONCRETE
E30: REINFORCEMENT FOR IN SITU CONCRETE
High tensile bars to BS 4449, striaght (provisional)
A 20mm - 10mm Diametre bars t 2 180,000 360,000.00
Mild steel bars to BS 4449, bent (provisional)
B 10mm - 6mm Diametre bars t 1.72 180,000 309,600.00
Fabric mesh A142 weighing 2.22kg/m2 laid as detailed
in manufacturer's manual
C Ground floor beds m2 287 650 186,550.00
F10: BRICK/BLOCK WALLING
BLOCKWORK; 225mm x 450mm Nominal; laid in
stretcher bond; cement and sand mortar (1:3)
D 230mm filled solid with concrete grade 15 in foundation m2 205 3,200 656,000.00
E 150mm ditto m2 39 2,100 81,900.00
F 0.13mm damp proof membrane laid with melted joint on
and including 10mm layer of fine sand (Measured
se aratel
m2 287 235 67,445.00
Carried to Collection 1,661,495.00
Collection
AYB/GA/3BF/1 339,715.00
AYB/GA/3BF/2 3,166,315.00
AYB/GA/3BF/3 1,661,495.00
GROUP ELEMENT NR. 1: SUBSTRUCTURE
CARRIED TO SUMMARY 5,167,525.00
2 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
4/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
GROUP ELEMENT NR. 2: SUPERSTRUCTURE
ELEMENT NR.2A FRAME
E10: In situ Concrete
Reinforced insitu concrete
Vibrated concrete grade 25
A Regular Columns m3 16 25,000 400,000.00
B Beams m3 19 25,000 475,000.00
E20: Formwork for in situ concrete
Sawn formwork to:
C Sides of regular Columns m2 275 1,100 302,500.00
D Sides and soffits of Beams m2 231 1,100 254,100.00
E30: Reinforcement for in situ concrete
High tensile bars to BS 4449, straight (provisional)
E 20 - 10mm Diametre bars t 2.44 180,000 439,200.00
Mild steel bars to BS 4449, bent (Provisional)
F 10-6mm Diametre bars t 2 180,000 360,000.00
ELEMENT NR.2A FRAMES
CARRIED TO SUMMARY 2,230,800.00
3 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
5/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT NR.2B UPPER FLOORS
E10: In situ Concrete
Reinforced insitu concrete
Vibrated concrete grade 25
A Slabs thickness not exceeding 150mm, slope not
exceeding 15
m3 42 25,000 1,050,000.00
E20: Formwork for in situ concrete
Sawn formwork to:
B Soffits of slabs, slab thickness not exceeding 200mm,
slope not exceeding 15
m2 280 1,100 308,000.00
C Edges of suspended slabs, height not exceeding 250mm m 140 275 38,500.00
E30: Reinforcement for in situ concrete
High tensile bars to BS 4449, straight (provisional)
D 20 - 10mm Diametre bars t 3.5 180,000 630,000.00
Mild steel bars to BS 4449, bent (Provisional)
E 10-6mm Diametre bars t 1.54 180,000 277,200.00
ELEMENT NR.2B UPPER FLOORS
CARRIED TO SUMMARY 2,303,700.00
4 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
6/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT NR.2C ROOF
E10: In situ Concrete
Reinforced insitu concrete
Vibrated concrete grade 25
A Roof Beams/Cantilever m3 23 25,000 575,000.00
E20: Formwork for in situ concrete
Sawn formwork to:
B Beams m2 442 1,100 486,200.00
E30: Reinforcement for in situ concrete
High tensile bars to BS 4449, straight (provisional)
C 20 - 10mm Diametre bars t 2 180,000 360,000.00
Mild steel bars to BS 4449, bent (Provisional)
D 10-6mm Diametre bars t 1.22 180,000 219,600.00
H: CLADDING/COVERING
H72: Aluminium sheet coverings/flashing
Stone coated step tiles or other approved industrial
coloured Aluminium roofing sheets and accessories
lapped and fixed to steel purlins (measured separetely)
in accordance with manufacturer's details.
E Roof Covering m2 961 4,250 4,084,250.00
Carpentary/Timber framing/First fixing
Wrot treated hardwood in:
F 150x50mm tie beam m 443 350 155,050.00
G 150x50mm rafter m 390 350 136,500.00
H 150x50 kin ost m 161 350 56,350.00
J 100x50mm struts m 402 250 100,500.00
K 75x50mm purlin m 421 200 84,200.00
L 50x50mm noggins m 435 120 52,200.00
M 300 x 300mm; Concrete Fascia m 200 6,000 1,200,000.00
ELEMENT NR. 2C ROOF
CARRIED TO SUMMARY 7,509,850.00
5 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
7/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT NR.2D STAIRS AND RAMPS
E10: In situ Concrete
Reinforced insitu concrete
Vibrated concrete grade 25
A Staircases m3 5 25,000 125,000.00
E20: Formwork for in situ concrete
Sawn formwork to:
B Stairflights (3Nr); landing slab not exceeding 200mm
thick; 1500mm wide
m 52 1,100 57,200.00
C Sloping soffits of stairs m2 10 1,100 11,000.00
E30: Reinforcement for in situ concrete
High tensile bars to BS 4449, straight (provisional)
D 20 - 10mm Diametre bars t 0.52 180,000 93,600.00
Mild steel bars to BS 4449, bent (Provisional)
E 10-6mm Diametre bars t 0.11 180,000 19,800.00
M20:Plastered/Rendered/Roughcast coatings
15mm thick cement and sand (1:3) smooth rendering
F Landings soffits, width exceeding 300mm m2 6 650 3,900.00
G Sloping soffits of staircase width exceeding 300mm m2 13 650 8,450.00
M: SURFACE FINISHES
M10: Sand cement/ Concrete/Granolithic
screeds/flooring
42mm thick cement and sand (1:3) screeded bed
H Stairflights (3Nr); landing slab not exceeding 200mm
thick; 1500mm wide
m2 6 1,450 8,700.00
J Sloping soffits of stairs m2 13 1,450 18,850.00
Carried to Collection 346,500.00
6 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
8/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
STAIRCASES (Cont'd)
M40:STONE/CONCRETE/QUARRY/CERAMIC
TILING/MOSAIC/GRANITE/VITRIFIED TILING
M41: TILING
600x600x8mm thick tiles with including cement mortaron screeded bed (Measured separately)
A Stairflights (3Nr); landing slab not exceeding 200mm
thick; 1500mm wide
m2 6 4,500 27,000.00
B Sloping sides of stairs m 13 1,350 17,550.00
M60: PAINTING/CLEAR FINISHING
PREPARE AND APPLY PRIME COAT AND TWO
FINISHING COATS OF EMULSION PAINTS ON
RENDERED WALLS
General surfaces
C Stairflights (3Nr); landing slab not exceeding 200mm
thick; 1500mm wide
m2 6 800 4,800.00
D Sloping sides of stairs m2 13 800 10,400.00
L30: Stairs/Walkways/Balustrades
METAL WORK
MILD STEEL GRADE 43 BS 4360 IN STAIR
BALUSTRADE SITE WELDED
E 6 x 50mm flat core rail welded to balustrade m 25 1,200 30,000.00
F Mitred and welded angle Nr 15 1,500 22,500.00
G 50x50mm square hollow balusters 1000mm high, one end
embedded in concrete 100mm deep and the other
welded to core rail.
Nr 20 1,350 27,000.00
M60: PAINTING/CLEAR FINISHING
KNOT, PRIME, STOP, PREPARE AND APPLY TWO
FINISHING COATS OF GLOSS PAINT AS
SPECIFIED
General Surfaces
H Metal work not exceeding 300mm girth m 60 800 48,000.00
Carried To Collection 187,250.00
Collection
AYB/GA/3BF/7 346,500.00
AYB/GA/3BF/8 187,250.00
ELEMENT Nr. 2D STAIRS AND RAMPS
CARRIED TO SUMMARY 533,750.00
7 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
9/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT NR. 2E EXTERNAL WALLS
F10 BRICK/BLOCK WALLING
BLOCKWORK; 225 x 450mm Nominal; laid in
stretcher bond; cement mortar (1:3)
A 230mm thick hollow blocks m2 486 2,600 1,263,600.00
ELEMENT NR. 2E EXTERNAL WALLS
CARRIED TO SUMMARY 1,263,600.00
8 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
10/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT NR. 2F WINDOWS AND EXTERNAL
DOORS
E10: In situ concrete
Reinforced Insitu Concrete
Vibrated grade 20
A Isolated Lintels m3 14 25,000 350,000.00
E20: FORMWORK FOR IN SITU CONCRETE
Sawn formwork to:
B Sides and Soffits of isolated lintels m2 177 1,100 194,700.00
E30: Reinforcement for insitu concrete
High tensile bars to BS 4449, straight (Provisional)
C 12mm Diametre bars t 1.23 180,000 221,400.00
Mild steel bars to BS 4449, bent (Provisional)
D 10 - 6mm Diametre bars t 0.53 180,000 95,400.00
L21: METAL DOORS/SHUTTERS/HATCHES
Swing door complete with all accessories, Anodized
aluminium green powder coated frame with 5mm thick
top fixed glazing including Ironmongery designed to
Arhcitect's details, built into blockwork and concrete
surround, bedded and pointed in cement sand mortar
E Steel panel entrance double leaf door, size 1500 x
2100mm high and including frame
Nr 4 100,000 400,000.00
F Ditto 900 x 2100mm high Nr 4 30,000 120,000.00
L11:METAL WINDOWS / ROOFLIGHTS /SCREENS
/LOUVRES
Projected windows in 5mm thick anodized glass framed
in powder coated Aluminium blue profiles complete with
flyscreen and purpose made 12mm rod in grid burglar-
proofed grille to Architect's details, all built into
blockwork and concrete surround bedded and pointed in
G Projected windows size 1500 x 1200mm high overall Nr 8 72,000 576,000.00
H Ditto size 1200 x 1200mm high Nr 16 57,600 921,600.00
J Ditto size 900 x 600mm high overall Nr 8 21,600 172,800.00
K Ditto size 600 x 600mm high Nr 16 14,400 230,400.00
Element Nr. 2F WINDOWS AND EXTERNAL DOORS
CARRIED TO SUMMARY 3,282,300.00
9 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
11/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT NR: 2G INTERNAL WALLS AND
PARTITIONS
F10 BRICK/BLOCK WALLING
BLOCKWORK; 225mm x 450mm nominal; laid in
stretcher bond; cement mortar (1:3)
A 150mm thick hollow blocks m2 569 2,100 1,194,900.00
Element Nr. 2G INTERNAL WALLS
CARRIED TO SUMMARY 1,194,900.00
10 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
12/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT NR. 2H INTERNAL DOORS
E10: In situ concrete
Reinforced Insitu Concrete
Vibrated grade 20
A Isolated Lintels m3 3 25,000 75,000.00
E20: FORMWORK FOR IN SITU CONCRETE
Sawn formwork to:
B Sides and Soffits of isolated lintels m2 38 1,100 41,800.00
E30: Reinforcement for insitu concrete
High tensile bars to BS 4449, straight (Provisional)
C 12mm Diametre bars t 0.27 180,000 48,600.00
Mild steel bars to BS 4449, bent (Provisional)
D 10 - 6mm Diametre bars t 0.11 180,000 19,800.00
L21: METAL DOORS/SHUTTERS/HATCHES
KFCC or Wood kraft or other equal approved Masonia
faced polished 44mm solid core finish doors to BS 459
part 2 faced both sides with 5mm external quality
masonia plywood and prefinished hardwood lipped all
round and blocked out for ironmon er
E Overall size 900 x 2100mm high Nr 16 23,000 368,000.00
F Ditto 750 x 2100mm high Nr 20 23,000 460,000.00
M60:PAINTING/CLEAR FINISHING
KNOT, PRIME, STOP, PREPARE AND APPLY TWO
FINISHING COATS OF GLOSS PAINT AS SPECIFIED
General Surfaces
G Metal door frames not exceeding 300mm girth m 88 600 52,800.00
Element Nr. 2H INTERNAL DOORS
CARRIED TO SUMMARY 1,066,000.00
11 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
13/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
SUMMARY
GROUP ELEMENT NR. 2 SUPERSTRUCTURE
1 ELEMENT NR. 2A FRAMES 2,230,800.00
2 ELEMENT NR. 2B UPPER FLOORS 2,303,700.00
3 ELEMENT NR. 2C ROOF 7,509,850.00
4 ELEMENT NR. 2D STAIRS AND RAMP 533,750.00
5 ELEMENT NR. 2E EXTERNAL WALLS 1,263,600.00
6 ELEMENT NR. 2F WINDOWS AND EXTERNAL DOORS 3,282,300.00
7 ELEMENT NR. 2G INTERNAL WALLS & PARTITIONS 1,194,900.00
8 ELEMENT NR. 2H INTERNAL DOORS 1,066,000.00
GROUP ELEMENT NR. 2 SUPERSTRUCTURE
CARRIED TO SUMMARY 19,384,900.00
12 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
14/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
GROUP ELEMENT NR. 3 FINISHES
ELEMENT NR. 3A WALL FINISHES
M20 PLASTERED/RENDERED/ROUGHCAST
COATINGS
15mm thick cement and sand (1:5); Plain rendering;
finishing trowelled smooth
Walls
A Surfaces over 300mm wide; internal m2 1238 500 619,000.00
B Surfaces not exceeding 300mm wide; internal m 950 210 199,500.00
15mm thick cement and sand (1:5); Plain rendering;
finishing trowelled smooth
Walls
C Surfaces over 300mm wide; internal m2 988 500 494,000.00
D Surfaces not exceeding 300mm wide; internal m 512 210 107,520.00
M40: STONE/CONCRETE/ QUARRY/CERAMIC
TILING/ MOSAIC/GRANITE/VITRIFIED TILING
300X200X8mm thick glazed ceramic wall tiles of
approved colour bedded and jointed in cement mortar onscreeded backing (measured separately) and grouted in
white cement including all necessary round edge tile to:
Walls
E Over 300mm wide; internal at toilet m2 323 1,800 581,400.00
F Ditto; surfaces not exceeding 300mm wide m 35 540 18,900.00
12mm thick cement and sand (1:3) screeded backing
G Walls; width exceeding 300mm wide m2 323 500 161,500.00
H Walls; width not exceeding 300mm wide m 35 168 5,880.00
Carried to Collection 2,187,700.00
13 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
15/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
WALL FINISHES (Cont'd)
M60: PAINTING/CLEAR FINISHING
PREPARE AND APPLY PRIME COAT AND TWO
FINISHING COATS OF EMULSION PAINTS ONRENDERED WALLS
General Surfaces
A Walls over 300mm girth; Internal m2 1238 450 557,100.00
B Ditto surfaces not exceeding 300mm wide m 950 135 128,250.00
PREPARE AND APPLY ONE PRIME COAT AND TWO
FINISHING COATS OF TEXTURED PAINTS AS
SPECIFIED
General Surfaces
C Walls over 300mm girth; External m2 988 500 494,000.00
D Ditto surfaces not exceeding 300mm wide m 512 150 76,800.00
E Screeding to walls over 300mm girth (Externally andInternally)
m2 2226 500 1,113,000.00
F Ditto surfaces not exceeding 300mm wide m 1,462 150.00 219,300.00
Carried to Collection 2,588,450.00
Collection
AYB/GA/3BF/14 2,187,700.00
AYB/GA/3BF/15 2,588,450.00
Element Nr. 3A WALL FINISHES
CARRIED TO SUMMARY 4,776,150.00
14 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
16/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT NR. 3B FLOOR FINISHES
M SURFACE FINISHES
CEMENT - SAND (1:3) BEDS AND BACKINGS; TO
RECEIVE SUBSEQUENT FINISH
Floors; over 300mm wide
A 42mm thick average; screeded bed; to falls only not
exceeding 15 degrees from the horizontal to receive
fully vitrified ceramic tiles
m2 567 500 283,500.00
B Ditto not exceeding 300mm wide m 210 180 37,800.00
M40: STONE/CONCRETE/ QUARRY/CERAMIC
TILING/ MOSAIC/GRANITE/VITRIFIED TILING
600X300X8mm thick glazed ceramic wall tiles of
approved colour bedded and jointed in cement mortar
on screeded backing (measured separately) and
grouted in white cement including all necessary round
edge tile to:
C Floors; level and to falls only not exceeding 15 degrees
from horizontal; Internal
m2 567 2,800 1,587,600.00
D Ditto; not exceeding 300mm wide m 10 1,050 10,500.00
E Skirtings; height 100mm including backing; Internal m 210 319 66,990.00
ELEMENT NR. 3B FLOOR FINISHES
CARRIED TO SUMMARY 1,986,390.00
15 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
17/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT NR. 3C CEILING FINISHES
M20 PLASTERED/RENDERED/ROUGHCAST
COATINGS
15mm thick cement and sand (1:5); Plain rendering;
finishing trowelled smooth
A Soffit of suspended slab exceeding 300mm wide;
Internal
m2 287 600 172,200.00
M60: PAINTING/CLEAR FINISHING
PREPARE AND APPLY PRIME COAT AND TWO
FINISHING COATS OF EMULSION PAINTS ON
RENDERED WALLS
General Surfaces
B Soffit of suspended slab exceeding 300mm wide;
Internal
m2 287 680 195,160.00
K LINING/SHEETING/DRY PARTITION
C Plaster of paris (POP) ceiling to Architect's design m2 287 3,000 861,000.00
Element Nr. 3C CEILING FINISHES
CARRIED TO SUMMARY 1,228,360.00
16 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
18/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
SUMMARY
1 GROUP ELEMENT NR. 3 FINISHES
2 ELEMENT NR 3A WALL FINISHES 4,776,150.00
3 ELEMENT NR 3B FLOOR FINISHES 1,986,390.00
4 ELEMENT NR 3C CEILING FINISHES 1,228,360.00
GROUP ELEMENT NR 3 FINISHES
CARRIED TO GENERAL SUMMARY 7,990,900.00
17 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
19/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
GROUP ELEMENT NR. 4 FITTINGS, FURNISHING
AND EQUIPMENT
ELEMENT NR. 4A GENERAL FITTINGS,
FURNISHINGS AND EQUIPMENT
N FURNITURE/EQUIPMENT
N20: SPECIAL PURPOSE FIXTURES
/FURNISHINGS/EQUIPMENT
A Kitchen Cabinets Nr 4 150,000 600,000.00
GROUP ELEMENT NR. 4 FITTINGS, FURNISHING
AND EQUIPMENT
CARRIED TO GENERAL SUMMARY 600,000.00
18 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
20/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
GROUP ELEMENT NR. 5 SERVICES
ELEMENT NR. 5A ELECTRICAL SERVICES
V20: LV DISTRIBUTION
Equipment; Metal clad Main distribution board
surface/flush type as manufactured by FEDERAL
ELECTRIC or MEM or BILLS including all MCB, back
outlet connections to flush adaptable boxes, including
earth bonding, labels and fixing in accordance with
A Floor standing CUBICON switch board mv panel TP&N
main MCB
Nr 1 160,500 160,500.00
B 100A 10-way TP & N MCB Distribution board comprising
of 4nr 5A stablocks, 7nr 10A stablocks; 2nr. 20A
stablocks, 2nr 30A stablocks and 3nr Spares consisting
of 3nr 5A stablocks
Nr 4 42,000 168,000.00
Equipment; Metal clad isolating pattern switches or
ELCB as manufactured by FEDERAL ELECTRIC, MEM or
BILLS including all necessary fuse links with quick make
and quick breaks contacts and fixing in accordance with
manufacturers instructions
C 100A TP&N ELCB Isolating fused switch Nr 4 25,000 100,000.00
V21: GENERAL LIGHTING
Lamps and Luminaires; as manufactured by PHILIPS,
THORN, BEGA, TRILUX or other approved; rates to
include for supply, installation and accessories necessary
for com lete installation
D 1 x 100W Gino chandellier wall bracket Nr 24 1,800 43,200.00
E 3 x 100W Rise and fall dining lighting fitting Nr 4 6,500 26,000.00
F 5 x 100W Rise and fall Gino chandellier fitting Nr 4 7,200 28,800.00
G 1 x 100W Ceiling mounted light fitting Nr 48 2,850 136,800.00
H 1 x 100W Screw neck fitting Nr 16 2,500 40,000.00
J 1 x 100W Super club CD ceiling mounted fitting Nr 12 2,650 31,800.00
K 1 x 100W Compact reccess ceiling mounted finish Nr 20 1,850 37,000.00
L 1 x 18W Mirror shavers light Nr 16 2,100 33,600.00
M 1 x 100W bulkhead water resistant fitting Nr 20 4,800 96,000.00
Carried to Collection 901,700.00
19 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
21/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
V21: GENERAL LIGHTING (Cont'd)
A 1 x 100W bulkhead fitting (Roller) Nr 28 1,850 51,800.00
B 1 x 100W adjustable retractable sport light Nr 20 1,850 37,000.00
C 1 x 100W Bedhead reading lamp with self control switch Nr 12 1,850 22,200.00
D 1 x 100W Ceiling rose for water heater Nr 16 1,850 29,600.00
E 70W Newclime Ceiling fan Nr 16 7,800 124,800.00
F 1 - gang, 1 - way 5A light switch Nr 16 655 10,480.00
G 2 - gang, 2 - way 5A light switch Nr 48 950 45,600.00
H 1 - gang, 2 - way 5A light switch Nr 10 690 6,900.00
J 3 - gang, 1 - way 5A light switch Nr 10 1,100 11,000.00
K 2 - gang, 1 - way 5A light switch Nr 12 750 9,000.00
L 18A Dimmer switch type MK Nr 6 1,350 8,100.00
M 13A Water heater switch with pilot lamp type MK Nr 16 750 12,000.00
N 2 - gang, 1 - way 5A light switch Nr 4 750 3,000.00
V22: GENERAL LV POWER
Ancillaries; low voltage power socket outlets switches
and contactors as manufactured by MK or ABB or MEM
or approved equal complete with accessories for
P 13A single socket outlet MK Nr 32 1,000 32,000.00
Q 13A Twin socket outlet MK Nr 24 1,550 37,200.00
R 15A socket outlet for Air conditioners MK Nr 20 1,200 24,000.00
S 45A Cooker control unit type MK Nr 4 1,200 4,800.00
Carried to Collection 469,480.00
20 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
22/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
ELECTRICAL SERVICES (Cont'd)
V21: GENERAL LIGHTING (Cont'd)
Conduit: straight PVC pipe with flange joints in
chases/floor screeds with and including conduit boxes,
locknuts, brushes, couplers, bends, reducers, cuttingand other necessary accessories, rates to include
makin ood surfaces disturbed
A 20mm diametre m 1214 80 97,120.00
B 25mm diametre m 147 85 12,495.00
Y61: HV/LV CABLE AND WIRING
Cables; PVC insulated cables as manufactured by
NOCACO or other approved equal drawn into conduits or
ducts or laid down into trunking or laid in trenchesincluding cable loops, terminations, glands and all other
C 2 x 1.50mm single core PVC copper cable m 2258 125 282,250.00
D 3 x 2.5mm single core PVC copper cable m 655 135 88,425.00
E 3 x 4.0mm single core PVC copper cable m 429 239 102,638.25
F 4 x 25mm2 PVC/PVC cable m 77 3,600 277,200.00
G 4 x 35mm2 PVC/PVC cable m 65 4,550 295,750.00
Y61: HV/LV CABLE AND WIRING
W50: FIRE DETECTION AND ALARM
H 4 x 120mm2 PVC/PVC cable m 80 25,000 2,000,000.00
Equipment
Supply and install fire detection/alarm system as
manufactured by GENT or other approved, complete
with all accessories to form a complete system
Alarm equipment
J Smoke detector Nr 22 4,500 99,000.00
K Heat detector Nr 2 4,500 9,000.00
Carried to Collection 3,263,878.25
21 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
23/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
ELECTRICAL SERVICES (Cont'd)
W50: FIRE DETECTION AND ALARM
A 6 Zone Fire Alarm Panel Nr 1 40,000 40,000.00
B Fire Alarm initiating break glass point Nr 4 4,000 16,000.00
C Master Blast Siren Nr 2 8,500 17,000.00
W51: EARTHING AND BONDING
D Earthing of the whole installations at switch boards,
distribution boards etc with 25 x 3 copper tape and 600
x 600mm mat forming a basket and bonded to
foundation reinforcement complete with salt and
charcoal a lied as s ecified
Item 75,000.00
Builders Work
E Allow a provisional sum of N 95,000.00 for builder's
work in connection with all works
Sum 95,000.00
Carried to Collection 243,000.00
ELECTRICAL SERVICES
COLLECTION
AYB/GA/3BF/20 901,700.00
AYB/GA/3BF/21 469,480.00
AYB/GA/3BF/22 3,263,878.25
AYB/GA/3BF/23 243,000.00
ELEMENT NR. 5A ELECTRICAL SERVICES
CARRIED TO SUMMARY 4,878,058.25
22 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
24/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT NR. 5B MECHANICAL SERVICES
Y: MECHANICAL INSTALLATIONS
N: FURNITURE /EQUIPMENT
N13: SANITARY APPLIANCES/FITTINGS
Sanitary appliances/fittings of approved make; including
jointing to galvanised steel water supply and
un lasticised PVC drain i e
APPLIANCE/FITTING
A Sweethome WC complete with Wash hand basin will all
vanity pedestal or Armitage complete with foreign
si hon P-tra
Nr 16 45,900 734,400.00
B Toilet roll holder Nr 16 500 8,000.00
C 450 x 450mm mirror plugged into wall Nr 16 500 8,000.00
D 38mm diametre bottle trap Nr 16 750 12,000.00
E Soap dish Nr 16 1,250 20,000.00
F 50litres capacity electric water heater Nr 12 21,000 252,000.00
R DISPOSAL SYSTEMS
Pipes; straight; UPVC; in ducts, wall, floor screeds:
G 100mm dia M 230 270 62,100.00
H 75mm dia M 225 225 50,625.00
J 50mm dia M 288 135 38,880.00
Pipework ancillaries
K Floor drain, plastic drain coupled with dirt sleeve;
mounted flush with floor finish; 50mm diametre
Nr 16 155 2,480.00
Carried to Collection 1,188,485.00
23 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
25/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
R12: DRAINAGE BELOW GROUND
Excavating Trenches
P30: Trenches/Pipeways/Pits For Buried EngineeringServices
A Excavating trenches for services 200mm nominal size;
500mm average depth from 150mm below existing
ground level; backfilling with selected excavated
materials dis osal of sur lus excavated materials
M 450 125 56,250.00
Straight UPVC pipes in ducts/chases/trenches/floor
screeds
B 100mm diametre Nr 300 280 84,000.00
Extra Over UPVC pipes; fittings
Elbow
C 100mm diametre Nr 45 387 17,415.00
D 50mm diametre Nr 30 310 9,300.00
Tee
E 100mm diametre Nr 25 450 11,250.00
F 75mm diametre Nr 20 390 7,800.00
G 50mm diametre Nr 25 235 5,875.00
Y11: Pipework ancillaries
Pipework ancillaries
H Floor drain, plastic drain coupled with dirt sleeve;
mounted flush with floor finish; 50mm diametre
Nr 16 250 4,000.00
J Flexible pan connector; 100mm diametre Nr 16 560 8,960.00
K Ditto 75mm diamtre Nr 16 300 4,800.00
Carried to Collection 209,650.00
24 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
26/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
R12: DRAINAGE BELOW GROUND (Cont'd)
Inspection chambers; square on plan; in 150mm
blockwork and concrete bed and cover slab;
A Inspection chamber, 600 x 600 x 450mm deep
internall
Nr 10 4,000 40,000.00
B Ditto Manhole Nr 6 4,000 24,000.00
Septic tank; 2 nr. Attached to manholes 450 x 450
x 450mm deep excavations, concrete, formwork,
reinforcement, 230mm blockwork, rendering,
pipework, filling etc..
C 2270 x 1200 x 2000mm deep septic tank Nr 3 350,000 1,050,000.00
Soakaways; comprising excavations, concrete work,
formwork, reinforcement, 230mm blockwork,
rendering, pipework, filling etc..
D 2500 x 2500 x 2000mm deep soakaway pit Nr 3 200,000 600,000.00
S PIPED SUPPLY SYSTEMS
S10 COLD WATER
P30: Trenches/Pipeways/Pits For Buried Engineering
Services
E Excavating trenches for services 200mm nominal size;
500mm average depth from 150mm below existing
ground level; backfilling with selected excavated
materials dis osal of sur lus excavated materials
m 250 125 31,250.00
Pipes; Straight UPVC pipes in ducts/ chases/
Trenches/floor screeds
F 38mm diametre m 97 160 15,520.00
G 25mm diametre m 112 155 17,360.00
H 19mm diametre m 112 155 17 360.00
Extra over pipework; galvanised mild steel
J 25mm dia elbow Nr 22 210 4,620.00
K 19mm dia elbow Nr 22 210 4,620.00
L 25 x 25 x 19mm reducingTee Nr 19 335 6,365.00
M 25 x 19mm reducing elbow Nr 12 290 3,480.00
Carried to Collection 1,814,575.00
25 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
27/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
R12: DRAINAGE BELOW GROUND (Cont'd)
Extra over pipework; galvanised mild steel
A 13mm dia Union Nr 20 430 8,600.00
B Ditto Elbow Nr 14 170 2,380.00
C Ditto Gate valve Nr 20 170 3,400.00
D 13mm dia flexible connector Nr 20 125 2,500.00
E Ditto equal tee 13 x 13 x 13mm Nr 14 250 3,500.00
Pipes; Straight UPVC pipes in ducts/ chases/
Trenches/floor screeds
F 19mm diametre in chases Nr 15 100 1,500.00
G 13mm diametre in chases Nr 23 70 1,610.00
Extra over pipework; galvanised mild steel
H 25mm diametre union Nr 6 335 2,010.00
J 25mm diametre union 1 210 210.00
K Ditto; unequal tee 25 x 25 x 19mm diametre Nr 2 340 680.00
L 25mm diametre gate valve Nr 3 130 390.00
M 19mm diametre gate valve Nr 5 130 650.00
N 25mm diametre Elbow Nr 1 210 210.00
P 19mm diametre Elbow Nr 6 210 1,260.00
Q 19mm diametre plugs Nr 1 125 125.00
R 19x 19x 19mm diametre Tee Nr 3 290 870.00
Y59: SUNDRIES/COMMON MECHANICAL ITEMS
S Marking position of holes, mortices and chases in the
structure; for the i ed su l s stems installations
Item 80,000.00
Carried to Collection 109,895.00
26 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
28/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
U VENTILATION/AIRCONDITIONING SYSTEMS
U60 AIRCONDITIONING UNIT
A National/Panasonic split unit cooling capacity 18,000
BTU/hr (1.5 HP)
Nr 20 75,000 1,500,000.00
W50 FIRE DETECTION AND ALARM
Equipment
B 9kg Fire Extinguishers complete with wall bracket Nr 10 15,000 150,000.00
Carried to Collection 1,650,000.00
ELEMENT NR. 5B MECHANICAL INSTALLATIONS
Collections
AYB/GA/3BF/24 1,188,485.00
AYB/GA/3BF/25 209,650.00
AYB/GA/3BF/26 1,814,575.00
AYB/GA/3BF/27 109,895.00
AYB/GA/3BF/28 1,650,000.00
ELEMENT NR.5B MECHANICAL INSTALLATIONS
CARRIED TO SUMMARY N 4,972,605.00
SUMMARY
GROUP ELEMENT NR. 5 SERVICES
ELEMENT NR. 5A ELECTRICAL SERVICES 4,878,058.25
ELEMENT NR.5B MECHANICAL INSTALLATIONS 4,972,605.00
GROUP ELEMENT NR. 5 SERVICES
CARRIED TO SUMMARY N 9,850,663.25
27 NOVEMBER 2015
-
7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block
29/29
CONSTRUCTION OF THREE BEDROOM FLAT
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
GENERAL SUMMARY
GROUP ELEMENT NR. 1 SUBSTRUCTURE 5,167,525.00
GROUP ELEMENT NR.2 SUPERSTRUCTURE 19,384,900.00
GROUP ELEMENT NR.3 FINISHES 7,990,900.00
GROUP ELEMENT NR.4 FITTINGS, FURNISHING
AND EQUIPMENT
600,000.00
GROUP ELEMENT NR. 5 SERVICES 9,850,663.25
CARRIED TO GRAND GENERAL SUMMARY N 42,993,988.25