  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    1/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    GROUP ELEMENT Nr. 1 SUBSTRUCTURE

    SUBSTRUCTURE (PROVISIONAL)

    D GROUNDWORK

    D20 EXCAVATING AND FILLING

    EXCAVATING IN NORMAL FIRM GROUND

    Site Pre aration

    A Clearing site vegetation, bushes, shrubs, undergrowth,

    hed es and trees

    m2 409 35 14,315.00

    Excavation

    B Excavating topsoil average 150mm deep m2 409 100 40,900.00

    Reduced level excavation

    C maximum de th; not exceedin 250mm dee m2 51 220 11,220.00

    Trench Excavation

    D Excavating trench width exceeding 0.30m maximum

    de th not exceedin 2.00m

    m3 184 650 119,600.00

    E Excavation in rock laterite and disposal of excavated

    materials as directed

    m3 20 1,150 23,000.00

    Pits for concrete foundation; (47 Nr.)

    F Excavating pits (47nr), maximum depth not exceeding

    2.00m

    m3 28 650 18,200.00

    Disposal

    G Excavated material; on site as directed; in spoil

    maximum distance not exceedin 50m

    m3 115 250 28,750.00

    Filling to excavations

    H Filling to excavations, average thickness exceeding

    0.25m; arising from the excavations; Compacted around

    foundations

    m3 117 190 22,230.00

    Granular materials

    J Filling to make up levels, average thickness exceeding

    250mm, laterite materials obtained off site.

    m2 82 750 61,500.00

    Carried to Collection 339,715.00

    0 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    2/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    SUBSTRUCTURE (Cont'd)

    Rock laterite hardcore

    A Boulder rock; hardcore exceeding 250mm thick;

    obtained offsite; depositing in layers 150mm maximum

    thickness; com acted and consolidated under beds

    m3 82 2,400 196,800.00

    Surface Treatment

    Pesticides: Dieldrex 20 anti-termite

    B Treating the bottom, sides and surface of excavation m2 1437 50 71,850.00

    E10: INSITU CONCRETE

    Plain Insitu Concrete

    Vibrated Grade 30.

    C Blinding beds, thickness not exceeding 50mm thick;

    oured on or a ainst earth

    m3 9 14,500 130,500.00

    Plain Insitu Concrete

    Vibrated Grade 30.

    D Foundations, 150 - 450mm thick m3 35 23,000 805,000.00

    Reinforced Insitu Concrete

    Vibrated Concrete Grade 30

    Column bases m3 24 25,000 600,000.00

    E Regular columns m3 3 25,000 75,000.00

    Beds; 150mm thick m3 44 25,000 1,100,000.00

    E20: FORMWORK FOR IN SITU CONCRETE

    Sawn formwork to:

    F Sides of column bases m2 72 1,100 79,200.00

    G Sides of Regular columns m2 80 1,100 88,000.00

    H Sides of floor bed m 121 165 19,965.00

    Carried to Collection 3,166,315.00

    1 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    3/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    E10: INSITU CONCRETE

    E30: REINFORCEMENT FOR IN SITU CONCRETE

    High tensile bars to BS 4449, striaght (provisional)

    A 20mm - 10mm Diametre bars t 2 180,000 360,000.00

    Mild steel bars to BS 4449, bent (provisional)

    B 10mm - 6mm Diametre bars t 1.72 180,000 309,600.00

    Fabric mesh A142 weighing 2.22kg/m2 laid as detailed

    in manufacturer's manual

    C Ground floor beds m2 287 650 186,550.00

    F10: BRICK/BLOCK WALLING

    BLOCKWORK; 225mm x 450mm Nominal; laid in

    stretcher bond; cement and sand mortar (1:3)

    D 230mm filled solid with concrete grade 15 in foundation m2 205 3,200 656,000.00

    E 150mm ditto m2 39 2,100 81,900.00

    F 0.13mm damp proof membrane laid with melted joint on

    and including 10mm layer of fine sand (Measured

    se aratel

    m2 287 235 67,445.00

    Carried to Collection 1,661,495.00

    Collection

    AYB/GA/3BF/1 339,715.00

    AYB/GA/3BF/2 3,166,315.00

    AYB/GA/3BF/3 1,661,495.00

    GROUP ELEMENT NR. 1: SUBSTRUCTURE

    CARRIED TO SUMMARY 5,167,525.00

    2 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    4/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    GROUP ELEMENT NR. 2: SUPERSTRUCTURE

    ELEMENT NR.2A FRAME

    E10: In situ Concrete

    Reinforced insitu concrete

    Vibrated concrete grade 25

    A Regular Columns m3 16 25,000 400,000.00

    B Beams m3 19 25,000 475,000.00

    E20: Formwork for in situ concrete

    Sawn formwork to:

    C Sides of regular Columns m2 275 1,100 302,500.00

    D Sides and soffits of Beams m2 231 1,100 254,100.00

    E30: Reinforcement for in situ concrete

    High tensile bars to BS 4449, straight (provisional)

    E 20 - 10mm Diametre bars t 2.44 180,000 439,200.00

    Mild steel bars to BS 4449, bent (Provisional)

    F 10-6mm Diametre bars t 2 180,000 360,000.00

    ELEMENT NR.2A FRAMES

    CARRIED TO SUMMARY 2,230,800.00

    3 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    5/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    ELEMENT NR.2B UPPER FLOORS

    E10: In situ Concrete

    Reinforced insitu concrete

    Vibrated concrete grade 25

    A Slabs thickness not exceeding 150mm, slope not

    exceeding 15

    m3 42 25,000 1,050,000.00

    E20: Formwork for in situ concrete

    Sawn formwork to:

    B Soffits of slabs, slab thickness not exceeding 200mm,

    slope not exceeding 15

    m2 280 1,100 308,000.00

    C Edges of suspended slabs, height not exceeding 250mm m 140 275 38,500.00

    E30: Reinforcement for in situ concrete

    High tensile bars to BS 4449, straight (provisional)

    D 20 - 10mm Diametre bars t 3.5 180,000 630,000.00

    Mild steel bars to BS 4449, bent (Provisional)

    E 10-6mm Diametre bars t 1.54 180,000 277,200.00

    ELEMENT NR.2B UPPER FLOORS

    CARRIED TO SUMMARY 2,303,700.00

    4 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    6/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    ELEMENT NR.2C ROOF

    E10: In situ Concrete

    Reinforced insitu concrete

    Vibrated concrete grade 25

    A Roof Beams/Cantilever m3 23 25,000 575,000.00

    E20: Formwork for in situ concrete

    Sawn formwork to:

    B Beams m2 442 1,100 486,200.00

    E30: Reinforcement for in situ concrete

    High tensile bars to BS 4449, straight (provisional)

    C 20 - 10mm Diametre bars t 2 180,000 360,000.00

    Mild steel bars to BS 4449, bent (Provisional)

    D 10-6mm Diametre bars t 1.22 180,000 219,600.00

    H: CLADDING/COVERING

    H72: Aluminium sheet coverings/flashing

    Stone coated step tiles or other approved industrial

    coloured Aluminium roofing sheets and accessories

    lapped and fixed to steel purlins (measured separetely)

    in accordance with manufacturer's details.

    E Roof Covering m2 961 4,250 4,084,250.00

    Carpentary/Timber framing/First fixing

    Wrot treated hardwood in:

    F 150x50mm tie beam m 443 350 155,050.00

    G 150x50mm rafter m 390 350 136,500.00

    H 150x50 kin ost m 161 350 56,350.00

    J 100x50mm struts m 402 250 100,500.00

    K 75x50mm purlin m 421 200 84,200.00

    L 50x50mm noggins m 435 120 52,200.00

    M 300 x 300mm; Concrete Fascia m 200 6,000 1,200,000.00

    ELEMENT NR. 2C ROOF

    CARRIED TO SUMMARY 7,509,850.00

    5 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    7/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    ELEMENT NR.2D STAIRS AND RAMPS

    E10: In situ Concrete

    Reinforced insitu concrete

    Vibrated concrete grade 25

    A Staircases m3 5 25,000 125,000.00

    E20: Formwork for in situ concrete

    Sawn formwork to:

    B Stairflights (3Nr); landing slab not exceeding 200mm

    thick; 1500mm wide

    m 52 1,100 57,200.00

    C Sloping soffits of stairs m2 10 1,100 11,000.00

    E30: Reinforcement for in situ concrete

    High tensile bars to BS 4449, straight (provisional)

    D 20 - 10mm Diametre bars t 0.52 180,000 93,600.00

    Mild steel bars to BS 4449, bent (Provisional)

    E 10-6mm Diametre bars t 0.11 180,000 19,800.00

    M20:Plastered/Rendered/Roughcast coatings

    15mm thick cement and sand (1:3) smooth rendering

    F Landings soffits, width exceeding 300mm m2 6 650 3,900.00

    G Sloping soffits of staircase width exceeding 300mm m2 13 650 8,450.00

    M: SURFACE FINISHES

    M10: Sand cement/ Concrete/Granolithic

    screeds/flooring

    42mm thick cement and sand (1:3) screeded bed

    H Stairflights (3Nr); landing slab not exceeding 200mm

    thick; 1500mm wide

    m2 6 1,450 8,700.00

    J Sloping soffits of stairs m2 13 1,450 18,850.00

    Carried to Collection 346,500.00

    6 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    8/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    STAIRCASES (Cont'd)

    M40:STONE/CONCRETE/QUARRY/CERAMIC

    TILING/MOSAIC/GRANITE/VITRIFIED TILING

    M41: TILING

    600x600x8mm thick tiles with including cement mortaron screeded bed (Measured separately)

    A Stairflights (3Nr); landing slab not exceeding 200mm

    thick; 1500mm wide

    m2 6 4,500 27,000.00

    B Sloping sides of stairs m 13 1,350 17,550.00

    M60: PAINTING/CLEAR FINISHING

    PREPARE AND APPLY PRIME COAT AND TWO

    FINISHING COATS OF EMULSION PAINTS ON

    RENDERED WALLS

    General surfaces

    C Stairflights (3Nr); landing slab not exceeding 200mm

    thick; 1500mm wide

    m2 6 800 4,800.00

    D Sloping sides of stairs m2 13 800 10,400.00

    L30: Stairs/Walkways/Balustrades

    METAL WORK

    MILD STEEL GRADE 43 BS 4360 IN STAIR

    BALUSTRADE SITE WELDED

    E 6 x 50mm flat core rail welded to balustrade m 25 1,200 30,000.00

    F Mitred and welded angle Nr 15 1,500 22,500.00

    G 50x50mm square hollow balusters 1000mm high, one end

    embedded in concrete 100mm deep and the other

    welded to core rail.

    Nr 20 1,350 27,000.00

    M60: PAINTING/CLEAR FINISHING

    KNOT, PRIME, STOP, PREPARE AND APPLY TWO

    FINISHING COATS OF GLOSS PAINT AS

    SPECIFIED

    General Surfaces

    H Metal work not exceeding 300mm girth m 60 800 48,000.00

    Carried To Collection 187,250.00

    Collection

    AYB/GA/3BF/7 346,500.00

    AYB/GA/3BF/8 187,250.00

    ELEMENT Nr. 2D STAIRS AND RAMPS

    CARRIED TO SUMMARY 533,750.00

    7 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    9/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    ELEMENT NR. 2E EXTERNAL WALLS

    F10 BRICK/BLOCK WALLING

    BLOCKWORK; 225 x 450mm Nominal; laid in

    stretcher bond; cement mortar (1:3)

    A 230mm thick hollow blocks m2 486 2,600 1,263,600.00

    ELEMENT NR. 2E EXTERNAL WALLS

    CARRIED TO SUMMARY 1,263,600.00

    8 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    10/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    ELEMENT NR. 2F WINDOWS AND EXTERNAL

    DOORS

    E10: In situ concrete

    Reinforced Insitu Concrete

    Vibrated grade 20

    A Isolated Lintels m3 14 25,000 350,000.00

    E20: FORMWORK FOR IN SITU CONCRETE

    Sawn formwork to:

    B Sides and Soffits of isolated lintels m2 177 1,100 194,700.00

    E30: Reinforcement for insitu concrete

    High tensile bars to BS 4449, straight (Provisional)

    C 12mm Diametre bars t 1.23 180,000 221,400.00

    Mild steel bars to BS 4449, bent (Provisional)

    D 10 - 6mm Diametre bars t 0.53 180,000 95,400.00

    L21: METAL DOORS/SHUTTERS/HATCHES

    Swing door complete with all accessories, Anodized

    aluminium green powder coated frame with 5mm thick

    top fixed glazing including Ironmongery designed to

    Arhcitect's details, built into blockwork and concrete

    surround, bedded and pointed in cement sand mortar

    E Steel panel entrance double leaf door, size 1500 x

    2100mm high and including frame

    Nr 4 100,000 400,000.00

    F Ditto 900 x 2100mm high Nr 4 30,000 120,000.00

    L11:METAL WINDOWS / ROOFLIGHTS /SCREENS

    /LOUVRES

    Projected windows in 5mm thick anodized glass framed

    in powder coated Aluminium blue profiles complete with

    flyscreen and purpose made 12mm rod in grid burglar-

    proofed grille to Architect's details, all built into

    blockwork and concrete surround bedded and pointed in

    G Projected windows size 1500 x 1200mm high overall Nr 8 72,000 576,000.00

    H Ditto size 1200 x 1200mm high Nr 16 57,600 921,600.00

    J Ditto size 900 x 600mm high overall Nr 8 21,600 172,800.00

    K Ditto size 600 x 600mm high Nr 16 14,400 230,400.00

    Element Nr. 2F WINDOWS AND EXTERNAL DOORS

    CARRIED TO SUMMARY 3,282,300.00

    9 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    11/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    ELEMENT NR: 2G INTERNAL WALLS AND

    PARTITIONS

    F10 BRICK/BLOCK WALLING

    BLOCKWORK; 225mm x 450mm nominal; laid in

    stretcher bond; cement mortar (1:3)

    A 150mm thick hollow blocks m2 569 2,100 1,194,900.00

    Element Nr. 2G INTERNAL WALLS

    CARRIED TO SUMMARY 1,194,900.00

    10 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    12/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    ELEMENT NR. 2H INTERNAL DOORS

    E10: In situ concrete

    Reinforced Insitu Concrete

    Vibrated grade 20

    A Isolated Lintels m3 3 25,000 75,000.00

    E20: FORMWORK FOR IN SITU CONCRETE

    Sawn formwork to:

    B Sides and Soffits of isolated lintels m2 38 1,100 41,800.00

    E30: Reinforcement for insitu concrete

    High tensile bars to BS 4449, straight (Provisional)

    C 12mm Diametre bars t 0.27 180,000 48,600.00

    Mild steel bars to BS 4449, bent (Provisional)

    D 10 - 6mm Diametre bars t 0.11 180,000 19,800.00

    L21: METAL DOORS/SHUTTERS/HATCHES

    KFCC or Wood kraft or other equal approved Masonia

    faced polished 44mm solid core finish doors to BS 459

    part 2 faced both sides with 5mm external quality

    masonia plywood and prefinished hardwood lipped all

    round and blocked out for ironmon er

    E Overall size 900 x 2100mm high Nr 16 23,000 368,000.00

    F Ditto 750 x 2100mm high Nr 20 23,000 460,000.00

    M60:PAINTING/CLEAR FINISHING

    KNOT, PRIME, STOP, PREPARE AND APPLY TWO

    FINISHING COATS OF GLOSS PAINT AS SPECIFIED

    General Surfaces

    G Metal door frames not exceeding 300mm girth m 88 600 52,800.00

    Element Nr. 2H INTERNAL DOORS

    CARRIED TO SUMMARY 1,066,000.00

    11 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    13/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    SUMMARY

    GROUP ELEMENT NR. 2 SUPERSTRUCTURE

    1 ELEMENT NR. 2A FRAMES 2,230,800.00

    2 ELEMENT NR. 2B UPPER FLOORS 2,303,700.00

    3 ELEMENT NR. 2C ROOF 7,509,850.00

    4 ELEMENT NR. 2D STAIRS AND RAMP 533,750.00

    5 ELEMENT NR. 2E EXTERNAL WALLS 1,263,600.00

    6 ELEMENT NR. 2F WINDOWS AND EXTERNAL DOORS 3,282,300.00

    7 ELEMENT NR. 2G INTERNAL WALLS & PARTITIONS 1,194,900.00

    8 ELEMENT NR. 2H INTERNAL DOORS 1,066,000.00

    GROUP ELEMENT NR. 2 SUPERSTRUCTURE

    CARRIED TO SUMMARY 19,384,900.00

    12 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    14/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    GROUP ELEMENT NR. 3 FINISHES

    ELEMENT NR. 3A WALL FINISHES

    M20 PLASTERED/RENDERED/ROUGHCAST

    COATINGS

    15mm thick cement and sand (1:5); Plain rendering;

    finishing trowelled smooth

    Walls

    A Surfaces over 300mm wide; internal m2 1238 500 619,000.00

    B Surfaces not exceeding 300mm wide; internal m 950 210 199,500.00

    15mm thick cement and sand (1:5); Plain rendering;

    finishing trowelled smooth

    Walls

    C Surfaces over 300mm wide; internal m2 988 500 494,000.00

    D Surfaces not exceeding 300mm wide; internal m 512 210 107,520.00

    M40: STONE/CONCRETE/ QUARRY/CERAMIC

    TILING/ MOSAIC/GRANITE/VITRIFIED TILING

    300X200X8mm thick glazed ceramic wall tiles of

    approved colour bedded and jointed in cement mortar onscreeded backing (measured separately) and grouted in

    white cement including all necessary round edge tile to:

    Walls

    E Over 300mm wide; internal at toilet m2 323 1,800 581,400.00

    F Ditto; surfaces not exceeding 300mm wide m 35 540 18,900.00

    12mm thick cement and sand (1:3) screeded backing

    G Walls; width exceeding 300mm wide m2 323 500 161,500.00

    H Walls; width not exceeding 300mm wide m 35 168 5,880.00

    Carried to Collection 2,187,700.00

    13 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    15/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    WALL FINISHES (Cont'd)

    M60: PAINTING/CLEAR FINISHING

    PREPARE AND APPLY PRIME COAT AND TWO

    FINISHING COATS OF EMULSION PAINTS ONRENDERED WALLS

    General Surfaces

    A Walls over 300mm girth; Internal m2 1238 450 557,100.00

    B Ditto surfaces not exceeding 300mm wide m 950 135 128,250.00

    PREPARE AND APPLY ONE PRIME COAT AND TWO

    FINISHING COATS OF TEXTURED PAINTS AS

    SPECIFIED

    General Surfaces

    C Walls over 300mm girth; External m2 988 500 494,000.00

    D Ditto surfaces not exceeding 300mm wide m 512 150 76,800.00

    E Screeding to walls over 300mm girth (Externally andInternally)

    m2 2226 500 1,113,000.00

    F Ditto surfaces not exceeding 300mm wide m 1,462 150.00 219,300.00

    Carried to Collection 2,588,450.00

    Collection

    AYB/GA/3BF/14 2,187,700.00

    AYB/GA/3BF/15 2,588,450.00

    Element Nr. 3A WALL FINISHES

    CARRIED TO SUMMARY 4,776,150.00

    14 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    16/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    ELEMENT NR. 3B FLOOR FINISHES

    M SURFACE FINISHES

    CEMENT - SAND (1:3) BEDS AND BACKINGS; TO

    RECEIVE SUBSEQUENT FINISH

    Floors; over 300mm wide

    A 42mm thick average; screeded bed; to falls only not

    exceeding 15 degrees from the horizontal to receive

    fully vitrified ceramic tiles

    m2 567 500 283,500.00

    B Ditto not exceeding 300mm wide m 210 180 37,800.00

    M40: STONE/CONCRETE/ QUARRY/CERAMIC

    TILING/ MOSAIC/GRANITE/VITRIFIED TILING

    600X300X8mm thick glazed ceramic wall tiles of

    approved colour bedded and jointed in cement mortar

    on screeded backing (measured separately) and

    grouted in white cement including all necessary round

    edge tile to:

    C Floors; level and to falls only not exceeding 15 degrees

    from horizontal; Internal

    m2 567 2,800 1,587,600.00

    D Ditto; not exceeding 300mm wide m 10 1,050 10,500.00

    E Skirtings; height 100mm including backing; Internal m 210 319 66,990.00

    ELEMENT NR. 3B FLOOR FINISHES

    CARRIED TO SUMMARY 1,986,390.00

    15 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    17/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    ELEMENT NR. 3C CEILING FINISHES

    M20 PLASTERED/RENDERED/ROUGHCAST

    COATINGS

    15mm thick cement and sand (1:5); Plain rendering;

    finishing trowelled smooth

    A Soffit of suspended slab exceeding 300mm wide;

    Internal

    m2 287 600 172,200.00

    M60: PAINTING/CLEAR FINISHING

    PREPARE AND APPLY PRIME COAT AND TWO

    FINISHING COATS OF EMULSION PAINTS ON

    RENDERED WALLS

    General Surfaces

    B Soffit of suspended slab exceeding 300mm wide;

    Internal

    m2 287 680 195,160.00

    K LINING/SHEETING/DRY PARTITION

    C Plaster of paris (POP) ceiling to Architect's design m2 287 3,000 861,000.00

    Element Nr. 3C CEILING FINISHES

    CARRIED TO SUMMARY 1,228,360.00

    16 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    18/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    SUMMARY

    1 GROUP ELEMENT NR. 3 FINISHES

    2 ELEMENT NR 3A WALL FINISHES 4,776,150.00

    3 ELEMENT NR 3B FLOOR FINISHES 1,986,390.00

    4 ELEMENT NR 3C CEILING FINISHES 1,228,360.00

    GROUP ELEMENT NR 3 FINISHES

    CARRIED TO GENERAL SUMMARY 7,990,900.00

    17 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    19/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    GROUP ELEMENT NR. 4 FITTINGS, FURNISHING

    AND EQUIPMENT

    ELEMENT NR. 4A GENERAL FITTINGS,

    FURNISHINGS AND EQUIPMENT

    N FURNITURE/EQUIPMENT

    N20: SPECIAL PURPOSE FIXTURES

    /FURNISHINGS/EQUIPMENT

    A Kitchen Cabinets Nr 4 150,000 600,000.00

    GROUP ELEMENT NR. 4 FITTINGS, FURNISHING

    AND EQUIPMENT

    CARRIED TO GENERAL SUMMARY 600,000.00

    18 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    20/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    GROUP ELEMENT NR. 5 SERVICES

    ELEMENT NR. 5A ELECTRICAL SERVICES

    V20: LV DISTRIBUTION

    Equipment; Metal clad Main distribution board

    surface/flush type as manufactured by FEDERAL

    ELECTRIC or MEM or BILLS including all MCB, back

    outlet connections to flush adaptable boxes, including

    earth bonding, labels and fixing in accordance with

    A Floor standing CUBICON switch board mv panel TP&N

    main MCB

    Nr 1 160,500 160,500.00

    B 100A 10-way TP & N MCB Distribution board comprising

    of 4nr 5A stablocks, 7nr 10A stablocks; 2nr. 20A

    stablocks, 2nr 30A stablocks and 3nr Spares consisting

    of 3nr 5A stablocks

    Nr 4 42,000 168,000.00

    Equipment; Metal clad isolating pattern switches or

    ELCB as manufactured by FEDERAL ELECTRIC, MEM or

    BILLS including all necessary fuse links with quick make

    and quick breaks contacts and fixing in accordance with

    manufacturers instructions

    C 100A TP&N ELCB Isolating fused switch Nr 4 25,000 100,000.00

    V21: GENERAL LIGHTING

    Lamps and Luminaires; as manufactured by PHILIPS,

    THORN, BEGA, TRILUX or other approved; rates to

    include for supply, installation and accessories necessary

    for com lete installation

    D 1 x 100W Gino chandellier wall bracket Nr 24 1,800 43,200.00

    E 3 x 100W Rise and fall dining lighting fitting Nr 4 6,500 26,000.00

    F 5 x 100W Rise and fall Gino chandellier fitting Nr 4 7,200 28,800.00

    G 1 x 100W Ceiling mounted light fitting Nr 48 2,850 136,800.00

    H 1 x 100W Screw neck fitting Nr 16 2,500 40,000.00

    J 1 x 100W Super club CD ceiling mounted fitting Nr 12 2,650 31,800.00

    K 1 x 100W Compact reccess ceiling mounted finish Nr 20 1,850 37,000.00

    L 1 x 18W Mirror shavers light Nr 16 2,100 33,600.00

    M 1 x 100W bulkhead water resistant fitting Nr 20 4,800 96,000.00

    Carried to Collection 901,700.00

    19 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    21/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    V21: GENERAL LIGHTING (Cont'd)

    A 1 x 100W bulkhead fitting (Roller) Nr 28 1,850 51,800.00

    B 1 x 100W adjustable retractable sport light Nr 20 1,850 37,000.00

    C 1 x 100W Bedhead reading lamp with self control switch Nr 12 1,850 22,200.00

    D 1 x 100W Ceiling rose for water heater Nr 16 1,850 29,600.00

    E 70W Newclime Ceiling fan Nr 16 7,800 124,800.00

    F 1 - gang, 1 - way 5A light switch Nr 16 655 10,480.00

    G 2 - gang, 2 - way 5A light switch Nr 48 950 45,600.00

    H 1 - gang, 2 - way 5A light switch Nr 10 690 6,900.00

    J 3 - gang, 1 - way 5A light switch Nr 10 1,100 11,000.00

    K 2 - gang, 1 - way 5A light switch Nr 12 750 9,000.00

    L 18A Dimmer switch type MK Nr 6 1,350 8,100.00

    M 13A Water heater switch with pilot lamp type MK Nr 16 750 12,000.00

    N 2 - gang, 1 - way 5A light switch Nr 4 750 3,000.00

    V22: GENERAL LV POWER

    Ancillaries; low voltage power socket outlets switches

    and contactors as manufactured by MK or ABB or MEM

    or approved equal complete with accessories for

    P 13A single socket outlet MK Nr 32 1,000 32,000.00

    Q 13A Twin socket outlet MK Nr 24 1,550 37,200.00

    R 15A socket outlet for Air conditioners MK Nr 20 1,200 24,000.00

    S 45A Cooker control unit type MK Nr 4 1,200 4,800.00

    Carried to Collection 469,480.00

    20 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    22/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    ELECTRICAL SERVICES (Cont'd)

    V21: GENERAL LIGHTING (Cont'd)

    Conduit: straight PVC pipe with flange joints in

    chases/floor screeds with and including conduit boxes,

    locknuts, brushes, couplers, bends, reducers, cuttingand other necessary accessories, rates to include

    makin ood surfaces disturbed

    A 20mm diametre m 1214 80 97,120.00

    B 25mm diametre m 147 85 12,495.00

    Y61: HV/LV CABLE AND WIRING

    Cables; PVC insulated cables as manufactured by

    NOCACO or other approved equal drawn into conduits or

    ducts or laid down into trunking or laid in trenchesincluding cable loops, terminations, glands and all other

    C 2 x 1.50mm single core PVC copper cable m 2258 125 282,250.00

    D 3 x 2.5mm single core PVC copper cable m 655 135 88,425.00

    E 3 x 4.0mm single core PVC copper cable m 429 239 102,638.25

    F 4 x 25mm2 PVC/PVC cable m 77 3,600 277,200.00

    G 4 x 35mm2 PVC/PVC cable m 65 4,550 295,750.00

    Y61: HV/LV CABLE AND WIRING

    W50: FIRE DETECTION AND ALARM

    H 4 x 120mm2 PVC/PVC cable m 80 25,000 2,000,000.00

    Equipment

    Supply and install fire detection/alarm system as

    manufactured by GENT or other approved, complete

    with all accessories to form a complete system

    Alarm equipment

    J Smoke detector Nr 22 4,500 99,000.00

    K Heat detector Nr 2 4,500 9,000.00

    Carried to Collection 3,263,878.25

    21 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    23/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    ELECTRICAL SERVICES (Cont'd)

    W50: FIRE DETECTION AND ALARM

    A 6 Zone Fire Alarm Panel Nr 1 40,000 40,000.00

    B Fire Alarm initiating break glass point Nr 4 4,000 16,000.00

    C Master Blast Siren Nr 2 8,500 17,000.00

    W51: EARTHING AND BONDING

    D Earthing of the whole installations at switch boards,

    distribution boards etc with 25 x 3 copper tape and 600

    x 600mm mat forming a basket and bonded to

    foundation reinforcement complete with salt and

    charcoal a lied as s ecified

    Item 75,000.00

    Builders Work

    E Allow a provisional sum of N 95,000.00 for builder's

    work in connection with all works

    Sum 95,000.00

    Carried to Collection 243,000.00

    ELECTRICAL SERVICES

    COLLECTION

    AYB/GA/3BF/20 901,700.00

    AYB/GA/3BF/21 469,480.00

    AYB/GA/3BF/22 3,263,878.25

    AYB/GA/3BF/23 243,000.00

    ELEMENT NR. 5A ELECTRICAL SERVICES

    CARRIED TO SUMMARY 4,878,058.25

    22 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    24/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    ELEMENT NR. 5B MECHANICAL SERVICES

    Y: MECHANICAL INSTALLATIONS

    N: FURNITURE /EQUIPMENT

    N13: SANITARY APPLIANCES/FITTINGS

    Sanitary appliances/fittings of approved make; including

    jointing to galvanised steel water supply and

    un lasticised PVC drain i e

    APPLIANCE/FITTING

    A Sweethome WC complete with Wash hand basin will all

    vanity pedestal or Armitage complete with foreign

    si hon P-tra

    Nr 16 45,900 734,400.00

    B Toilet roll holder Nr 16 500 8,000.00

    C 450 x 450mm mirror plugged into wall Nr 16 500 8,000.00

    D 38mm diametre bottle trap Nr 16 750 12,000.00

    E Soap dish Nr 16 1,250 20,000.00

    F 50litres capacity electric water heater Nr 12 21,000 252,000.00

    R DISPOSAL SYSTEMS

    Pipes; straight; UPVC; in ducts, wall, floor screeds:

    G 100mm dia M 230 270 62,100.00

    H 75mm dia M 225 225 50,625.00

    J 50mm dia M 288 135 38,880.00

    Pipework ancillaries

    K Floor drain, plastic drain coupled with dirt sleeve;

    mounted flush with floor finish; 50mm diametre

    Nr 16 155 2,480.00

    Carried to Collection 1,188,485.00

    23 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    25/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    R12: DRAINAGE BELOW GROUND

    Excavating Trenches

    P30: Trenches/Pipeways/Pits For Buried EngineeringServices

    A Excavating trenches for services 200mm nominal size;

    500mm average depth from 150mm below existing

    ground level; backfilling with selected excavated

    materials dis osal of sur lus excavated materials

    M 450 125 56,250.00

    Straight UPVC pipes in ducts/chases/trenches/floor

    screeds

    B 100mm diametre Nr 300 280 84,000.00

    Extra Over UPVC pipes; fittings

    Elbow

    C 100mm diametre Nr 45 387 17,415.00

    D 50mm diametre Nr 30 310 9,300.00

    Tee

    E 100mm diametre Nr 25 450 11,250.00

    F 75mm diametre Nr 20 390 7,800.00

    G 50mm diametre Nr 25 235 5,875.00

    Y11: Pipework ancillaries

    Pipework ancillaries

    H Floor drain, plastic drain coupled with dirt sleeve;

    mounted flush with floor finish; 50mm diametre

    Nr 16 250 4,000.00

    J Flexible pan connector; 100mm diametre Nr 16 560 8,960.00

    K Ditto 75mm diamtre Nr 16 300 4,800.00

    Carried to Collection 209,650.00

    24 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    26/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    R12: DRAINAGE BELOW GROUND (Cont'd)

    Inspection chambers; square on plan; in 150mm

    blockwork and concrete bed and cover slab;

    A Inspection chamber, 600 x 600 x 450mm deep

    internall

    Nr 10 4,000 40,000.00

    B Ditto Manhole Nr 6 4,000 24,000.00

    Septic tank; 2 nr. Attached to manholes 450 x 450

    x 450mm deep excavations, concrete, formwork,

    reinforcement, 230mm blockwork, rendering,

    pipework, filling etc..

    C 2270 x 1200 x 2000mm deep septic tank Nr 3 350,000 1,050,000.00

    Soakaways; comprising excavations, concrete work,

    formwork, reinforcement, 230mm blockwork,

    rendering, pipework, filling etc..

    D 2500 x 2500 x 2000mm deep soakaway pit Nr 3 200,000 600,000.00

    S PIPED SUPPLY SYSTEMS

    S10 COLD WATER

    P30: Trenches/Pipeways/Pits For Buried Engineering

    Services

    E Excavating trenches for services 200mm nominal size;

    500mm average depth from 150mm below existing

    ground level; backfilling with selected excavated

    materials dis osal of sur lus excavated materials

    m 250 125 31,250.00

    Pipes; Straight UPVC pipes in ducts/ chases/

    Trenches/floor screeds

    F 38mm diametre m 97 160 15,520.00

    G 25mm diametre m 112 155 17,360.00

    H 19mm diametre m 112 155 17 360.00

    Extra over pipework; galvanised mild steel

    J 25mm dia elbow Nr 22 210 4,620.00

    K 19mm dia elbow Nr 22 210 4,620.00

    L 25 x 25 x 19mm reducingTee Nr 19 335 6,365.00

    M 25 x 19mm reducing elbow Nr 12 290 3,480.00

    Carried to Collection 1,814,575.00

    25 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    27/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    R12: DRAINAGE BELOW GROUND (Cont'd)

    Extra over pipework; galvanised mild steel

    A 13mm dia Union Nr 20 430 8,600.00

    B Ditto Elbow Nr 14 170 2,380.00

    C Ditto Gate valve Nr 20 170 3,400.00

    D 13mm dia flexible connector Nr 20 125 2,500.00

    E Ditto equal tee 13 x 13 x 13mm Nr 14 250 3,500.00

    Pipes; Straight UPVC pipes in ducts/ chases/

    Trenches/floor screeds

    F 19mm diametre in chases Nr 15 100 1,500.00

    G 13mm diametre in chases Nr 23 70 1,610.00

    Extra over pipework; galvanised mild steel

    H 25mm diametre union Nr 6 335 2,010.00

    J 25mm diametre union 1 210 210.00

    K Ditto; unequal tee 25 x 25 x 19mm diametre Nr 2 340 680.00

    L 25mm diametre gate valve Nr 3 130 390.00

    M 19mm diametre gate valve Nr 5 130 650.00

    N 25mm diametre Elbow Nr 1 210 210.00

    P 19mm diametre Elbow Nr 6 210 1,260.00

    Q 19mm diametre plugs Nr 1 125 125.00

    R 19x 19x 19mm diametre Tee Nr 3 290 870.00

    Y59: SUNDRIES/COMMON MECHANICAL ITEMS

    S Marking position of holes, mortices and chases in the

    structure; for the i ed su l s stems installations

    Item 80,000.00

    Carried to Collection 109,895.00

    26 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    28/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    U VENTILATION/AIRCONDITIONING SYSTEMS

    U60 AIRCONDITIONING UNIT

    A National/Panasonic split unit cooling capacity 18,000

    BTU/hr (1.5 HP)

    Nr 20 75,000 1,500,000.00

    W50 FIRE DETECTION AND ALARM

    Equipment

    B 9kg Fire Extinguishers complete with wall bracket Nr 10 15,000 150,000.00

    Carried to Collection 1,650,000.00

    ELEMENT NR. 5B MECHANICAL INSTALLATIONS

    Collections

    AYB/GA/3BF/24 1,188,485.00

    AYB/GA/3BF/25 209,650.00

    AYB/GA/3BF/26 1,814,575.00

    AYB/GA/3BF/27 109,895.00

    AYB/GA/3BF/28 1,650,000.00

    ELEMENT NR.5B MECHANICAL INSTALLATIONS

    CARRIED TO SUMMARY N 4,972,605.00

    SUMMARY

    GROUP ELEMENT NR. 5 SERVICES

    ELEMENT NR. 5A ELECTRICAL SERVICES 4,878,058.25

    ELEMENT NR.5B MECHANICAL INSTALLATIONS 4,972,605.00

    GROUP ELEMENT NR. 5 SERVICES

    CARRIED TO SUMMARY N 9,850,663.25

    27 NOVEMBER 2015

  • 7/24/2019 Elemental Bill of Quantities for 3 Bedroom Apartment Block

    29/29

    CONSTRUCTION OF THREE BEDROOM FLAT

    ITEM DESCRIPTION UNIT QTY RATE AMOUNT

    GENERAL SUMMARY

    GROUP ELEMENT NR. 1 SUBSTRUCTURE 5,167,525.00

    GROUP ELEMENT NR.2 SUPERSTRUCTURE 19,384,900.00

    GROUP ELEMENT NR.3 FINISHES 7,990,900.00

    GROUP ELEMENT NR.4 FITTINGS, FURNISHING

    AND EQUIPMENT

    600,000.00

    GROUP ELEMENT NR. 5 SERVICES 9,850,663.25

    CARRIED TO GRAND GENERAL SUMMARY N 42,993,988.25