electricity markets in latin america: costs, prices and
TRANSCRIPT
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
1
Hugh RudnickIEEE PES Distinguished Lecturer
IEE- IEEELondon, UK, April 5, 2000
ELECTRICITY MARKETS INLATIN AMERICA:
COSTS, PRICES ANDQUALITY OF SERVICE
Pontificia Universidad Católica de ChileSchool of Engineering
500 km.1700 km
Chile (main system)
England & Wales
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
2
Structure of the presentation
Latinamerican power sectorPower market reformMarket design - generation, transmission, distributionSuccessesProblems and challenges
LATINAMERICALATINAMERICA a region in transition and growth a region in transition and growth
* Open economies and democratic governments
* End of the debt crisis
* Economic reforms with market economies encouraging economic growth
* Geopolitics reasons increase worldwide interest in the region - the place for investment
* Increasing regional commercial exchanges are creating new conditions for economic development
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
3
The AmericanElectricit y Market
CANADA & UNITED STATES
• Market of 765000 MW• 1-2% annual growth = 7650 - 15300 MW a year
LATINAMERICA
• Market of 190000 MW• 5% annual growth = 9500 MW a year
Growth in GDP
Growth in electricity demand
Argentina
Bolivia
Brazil
Chile
Peru
2%
4%
6%
8%
10%
12%
14%
0% 1% 2% 3% 4% 5% 6% 7% 8%
1990-97
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
4
GDP vs. electricity demandGDP vs. electricity demand
United States
FranceGermany
JapanAustralia
Singapore
ItalyUnited KingdomHong Kong
SpainTaiwan
GreecePortugal
S. Korea
Venezuela
PeruMexico
BrazilArgentina
Chile0
2.000
4.000
6.000
8.000
10.000
12.000
14.000
16.000
0 5.000 10.000 15.000 20.000 25.000
GDP per capita (US$)
KWh per capita
Source: CNE Chile 1997
90% and above
70-90%
50-70%
below 50%
Latinamerican electrification, 1997
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
5
Hydro71.8%
Nuclear1.2% Thermal
23.2%
Others3.8%
Southamerica: installed capacity pertechnology (1997)
Total Capacity: 141.451 MWSource: Cier 1998
30% 35% 40% 45% 50% 55% 60% 65% 70%Load factor
Brazil
Mexico
ArgentinaColombia
ChilePeru
0
50
100
150
200
250
300
350
Gen
erat
ion
(TW
h)
Hydro
Other
Thermal
Electricity generation by type, 1997
MarketLine, 1998
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
6
Western Europe
Eastern Europe
North America
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Asia
Latin America
No interest
Low importance
Important
Very importantAreas of interest for future power investment
(MarketLine, 1998)
Structure of the presentation
Latinamerican power sectorPower market reformMarket design - generation, transmission., distributionSuccessesProblems and challenges
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
7
ELECTRICAL SECTOR- historicaldevelopment in Latinamerica
Initial private developments
Government action - vertically integrated utilities(Endesa, Electroperú, Ende, Eletrobras, ISA,Edelca, CFE)
Limited private participation
ELECTRICAL SECTOR main problems in Latinamerica
Financial & economic crisisTariffs problems and cross subsidies
Management problemsInfrastructure deteriorationHigh levels of losses
Overstaffing
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
8
Drivers of deregulation and privatization
- sustain investment with high demand growth- price reductions (not necessarily)
- political reasons - open market ideology- fiscal deficit- need to sell State assets
International “trend”-World Bank initiatives
-not technological changes-minimum quality levels
COLOMBIA1994
PERU1993
BOLIVIA
1994
CHILE1982
ARGENTINA
1992
BRAZIL
1998
Pioneering regulatory changes in the electrical sector
MEXICO
1999
CENTRAL AMERICA & PANAMA1997-9
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
9
Structure of the presentation
Latinamerican power sectorPower market reformMarket design - generation, transmission, distributionSuccessesProblems and challenges
ELECTRICITY MARKET REFORMS
*wholesale market deregulation (unregulated prices for large consumers)
*competition at generation level with centralized generation dispatch
*short term marginal cost based schemes
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
10
ELECTRICITY MARKET REFORMS
*regulation in transmission and distribution
*transmission open access regulation, base for competition, global allocation of network costs
*incentive based regulation in distribution (yard stick competition, price cap)
Change of paradigma
Vertically integratedcompany
-public service company
-obligation to serve
-protection and rates
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
11
Change of paradigma
Generation
-competition
-no public service
-no obligation to serve
-no protection
Change of paradigma
Distribution
-franchised monopoly
-obligation to serve
Transmission
-open access obligation
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
12
Structure of the presentation
Latinamerican power sectorPower market reformMarket design - generation, transmission, distributionSuccessesProblems and challenges
Investment in the Chilean Central System
0
1.000
2.000
3.000
4.000
5.000
6.000
7.000
8.000
9.000
1.997 1.998 1.999 2.000 2.001 2.002 2.003 2.004 2.005 2.006
YEAR
DE
MA
ND
(M
W)
DEMAND SUPPLY
PANGUE
LOMA ALTASES
PETROPOWERNEHUENCO
PEUCHENMAMPIL
SAN ISIDRORUCUE
CORTADERAL
RALCOTHERM. 332,4
THERM. 332,42 X THERM.
332,4
Source: CNE Chile
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
13
PERU- ELECTRICITY COVERAGE
Ene-
94
Jun-
94
Ene-
95
Jun-
95
Dic-9
5
Jun-
96
Dic-9
6
Dic-9
7
83% 83% 86% 87% 90% 90%
91%100%
0%
20%
40%
60%
80%
100%
39% 42% 46% 50% 54%
0%
20%
40%
60%19
87
1992
1993
1994
1995
National Edelnor- Lima
WHOLESALE ARGENTINE MARKETAVERAGE MONTHLY PRICE
0
10
20
30
40
50
60
70
80
jan-
92
apr-
92
Jul-9
2
Oct
-92
jan-
93
apr-
93
Jul-9
3
Oct
-93
jan-
94
apr-
94
Jul-9
4
Oct
-94
jan-
95
apr-
95
Jul-9
5
Oct
-95
jan-
96
$/M
Wh
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
14
Energy prices SIC - SING(Oct.1999 values)
0.00
10.0020.00
30.0040.00
50.0060.00
70.0080.00
90.00
AB
RIL 1983
AB
RIL 1984
AB
RIL 1985
AB
RIL 1986
AB
RIL 1987
AB
RIL 1988
AB
RIL 1989
AB
RIL 1990
AB
RIL 1991
AB
RIL 1992
AB
RIL 1993
AB
RIL 1994
AB
RIL 1995
AB
RIL 1996
AB
RIL 1997
AB
RIL 1998
AB
RIL 1999
$/kW
h
SIC (Alto Jahuel) SING(Antofagasta)
0,4
0,6
0,8
1,0
1,2
1,4
1,6
1,8
1992 1996
FIRM
REGULATOR
RESULT
VALUE ADDED COST - high voltage distribution
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
15
Energy losses in distribution systems in Perú(1990-1999)
11.8%12.4%
14.6%17.1%
19.7%20.6%21.8%
13.9% 15.4%18.2%
0%
5%
10%
15%
20%
25%
90 91 92 93 94 95 96 97 98 99
E. Zolezzi, CTE, Oct. 99
6,6496,609
8,52110,022
10,62711,277 11,783
12,898
2,980 2,833 2,445 2,347 2,088 1,970 1,998 1,692
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
89 90 91 92 93 94 95 96
N° Employees
Production (GWh)
ENDESA productivity increase:production (GWh) versus number of employees in Chile
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
16
Clients per Worker
509582
795
1036
1.994 1.995 1.996 1.997 GWh per Worker
2.3 2.5
3.2
4.2
1.994 1.995 1.996 1.997
PRODUCTIVITY INCREASES AT DISTRIBUTION COMPANY EDELNOR- PERU
0.0
1.0
2.0
3.0
4.0
5.0
6.0
1988 1989 1990 1991 1992 1993 1994
Average time for emergency service
Hrs.
CHILE- PRODUCTIVITY INCREASES AT DISTRIBUTION COMPANY CHILECTRA
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
17
M. Pereira, 1999
Growingelectricinterconections
Colombia
Ecuador
Perú-SICN
Perú-SISUR
Bolivia
Chile-SING
Chile-SIC
ArgentinaMercado
ArgentinaComahue
Paraguay
Uruguay
Brasil-N
Brasil-NE
Brasil-SE
Brasil-Sur
Venezuela
Growinggasinterconections
CIER, 1996
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
18
Non served energy January 88 - Dec 95 (GWh) - Argentina
Structure of the presentation
Latinamerican power sectorPower market reformMarket design - generation, transmission, distributionSuccessesProblems and challenges
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
19
PROBLEMS AND CHALLENGES INMARKET DESIGN
-independent operator(Chile)
-transmission open access(Argentina, Bolivia, Colombia,Chile, Perú)
-distribution pricing (Bolivia,Chile, Perú)
-blackout crisis (Argentina, Chile)
-regional energy market
GOVERNANCE OF THE POOL
Generation
-problems with pool governance-spot price calculations-capacity payments-reliability control
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
20
Assumptions
-a central dispatch is needed for competing generators-governance better achieved by agreement among allparticipants-with perfect competition, prices will be marginal costs
-central dispatch needed to clear the wholesale market(Adam Smith role)
GOVERNANCE OF THE POOL
Market design-central dispatch as a single system irrespective ofownership-marginal cost based dispatch (traditional pool)-large generators form a club that acts as an independentoperator-agreements to be achieved unanimously, otherwiseregulator intervenes
Market reality-competition on cost of supply (efficiencies increased, newtechnologies introduced- CCGT) and on commercialactions (contract portfolios)-club scheme operates well for over 10 years (outsidecriticism by parties that are not able to participate)
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
21
-as competition increases and prices decrease, unanimousagreements become the exception (disagreements ondetermination of spot price, dispatch models, transmissionmodeling, operation security strategies)-governing difficulties-regulator essentially directing the actions of the pool, withno interest to do so-reliability endangered by disagreements
Divergences within the pool(CDEC-SIC)
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
0
2
4
6
8
10
12
14
16
Num
ber
of
dive
rgen
ces
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
Year
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
22
TRANSMISSION PRICING
Transmission
-problems with open access tariffs-lack of expansion signals-congestion
Assumptions- agents that cause transmission expansion must pay for use- generators and consumers- differences among countries
Market design-transmission payments based on natural economic use oflines, no relation with commercial use and contracts-natural use measured as incremental use under economicdispatch-peak capacity use or energy use
TRANSMISSION PRICING
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
23
Market reality
-weak definition of natural use-disputes on how to measure natural use-incremental measure dependent on marginal bus location
-no clear definition on handling of network restrictions andeconomic decoupling of areas of the system
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Peak block Single bus Block single bus Block variable bus
Method
Pay
men
ts [%
]
A PC/PD
A A
A G
G G
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Peak block Single bus Block single bus Block variable bus
Method
Pay
men
ts [%
]
A PC/PD
A A
A G
G G
Generators
Consumers
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
24
DISTRIBUTION PRICING
Distribution
-conflicts in tariff calculations
-quality of service
Assumptions
-economies of scope give place to monopolistic activity-geographic franchised activity subject to regulation-strategic objective for pricing is to avoid welfare lossesfrom monopoly pricing, provide signal for economicefficiency (investment and operation), with symmetry ofrisk and opportunities for regulated firm
-obligation to serve (only one in electricity chain)-competition by comparison (benchmarking) reducesasymmetry of information about the firm´s costs
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
25
Market design
-prices based on cost comparison against an efficient modelfirm-value added cost of distribution based on hypotethicalmodel distribution firms-standardized costs, optimally sized firms and optimalbusiness management-typical standardized distribution areas-independent studies by consultant requested by regulatorand firms-preliminary prices determined and coherency check forrevenue of the whole distribution industry
0
200
400
600
800
1000
1200
1400
1600
1800
0 50 100 150 200
Maximum demand (MW)
Tot
al c
ost
(MU
S$/
Mon
th)
Total monthly cost for area 2 (Chile, 1988)
Average value 10,2 US$/kW/month
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
26
Market reality (Chile, 1996)
-complete study bases issued by regulator for 39 distributioncompanies, 5 typical distribution areas-differences in criteria between regulator and firms-unclear definition on treatment of unregulated consumers,economies of scope, stand-alone firm or shared-costs firm,criteria for optimal installation expansion, technologicalupdating, useful life for installations-extended legal battles
1988
1992
1996
Differences among value added costs asdetermined by regulator and companiesDifferences among value added costs asdetermined by regulator and companies
High voltage distribution Low voltage distribution
64
21 23
118123
60
44
73
-17-20
0
20
40
60
80
100
120
140
High Average
Distribution density
% d
e va
riaci
ón
Low
53
37
49
97
137
62
40
64
10
0
20
40
60
80
100
120
140
Distribution density
% d
e va
riaci
ón
High Average Low
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
27
BLACKOUT CRISIS
Generation
-unsupplied energy
Regulator intervention for adequacy
*capacity payments
*regulated tariffs for small consumers
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
28
System operator and security
*freedom to compete?
*mandatory poolco approach
Penalties
Chile
*drought 1998-99
*combined cycle failure
*rotating blackouts
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
29
RESERVOIR STORED ENERGY
0.0
1,000.0
2,000.0
3,000.0
4,000.0
5,000.0
6,000.0
7,000.0
1/01
/94
1/04
/94
1/07
/94
1/10
/94
1/01
/95
1/04
/95
1/07
/95
1/10
/95
1/01
/96
1/04
/96
1/07
/96
1/10
/96
1/01
/97
1/04
/97
1/07
/97
1/10
/97
1/01
/98
1/04
/98
1/07
/98
1/10
/98
1/01
/99
1/04
/99
1/07
/99
1/10
/99
1/01
/00
GIG
AW
AT
TS
HO
UR
(GW
h)
RAPEL INVERNADA COLBUN CHAPO LAJA
Chile
*no lack of investment
*decoupled price signals
*contracts do not obligegenerators to serve*weak coordination pool
*low “unsupplied” energy cost
*law changed to impose obligation to serve
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
30
Argentina
*substation failure
*extended blackout
Argentina
*no lack of investment
*lack of coordination
*low “unsupplied” energy cost
*penalties imposed
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
31
REGIONAL ENERGY MARKET DEVELOPMEN T
Commercial/market agreements
Gas interconnections
Electricity interconnections
Geographic distribution of consumer loads and energy resources
Important load
Natural gas resources
Hydroelectric resources
BRASIL
URUGUAY
PARAGUAY
BOLIVIAPERU
Asunción•
Lima
Santa Cruz
Sao PauloRio de Janeiro
•
••
•
Concepción
Buenos Aires
•
•
Santiago
Mejillones •
•
NOA
ARGENTINA
ExcedentesHidráulicos
Neuquén
CHILE
Figura 2
Endesa 1999
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
32
BRASIL
URUGUAY
PARAGUAY
BOLIVIAPERU
Asunción•
Lima
Santa Cruz
Sao PauloRio de Janeiro
•
••
•
Concepción
Buenos Aires
•
•
Santiago
Mejillones •
NOA
Excedentes
Hidráulicos
Neuquén
Asunción
•
Asunción
• Interconexión
Argentina Brasil
Electroducto
Argentina Chile
Gasoducto
Atacama
Interconexión
SING-SIC
Generación Hidro
Sur Austral
Gasoducto del Pacífico
Electroductos
Tucumán - Carrera Pinto
Mendoza - San Isidro
Asunción
•
Electroducto
Alicurá - Osorno
Gasoducto
Gasandes
Carrera Pinto
San Isidro
•
Interconnections and market integration
Endesa 1999
Integration among markets
-price equilibrium among markets
-natural gas grows in importance - large gascompanies join the electricity market
-minimum size of companies changes - expansion toother markets and new economies of scale
-decisions of gas and electricity expansion projectsare linked
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
33
Technology impact: combined cycle plants
-new plants replacing coal plants
-combined cycle defining long run marginal cost(substantially lower that the historic one)
-combined cycle competing with transmission andchanging investment patterns
Restructuring of the world electricity market
-arrival to Latinamerica of main world energy (gas andelectricity) players looking for regional portfolios
-increase of competition versus increase of verticaland horizontal integration
-prices initially on a downward trend
-regional expansion of transmission
-need for regional common regulatory arrangements
Hugh Rudnick, IEE-IEEE Lecture, London, April 5, 2000
34
Hugh RudnickProfessor
Department of Electrical EngineeringPontificia Universidad Católica de Chile
Santiago, Chile
Email [email protected]://www.ing.puc.cl/power/