draft tender papers -...
TRANSCRIPT
- 1 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
For Authorised Use Only Tender No.B-1/
For 2013-2014
GODAVARI MARATHWADA IRRIGATION
DEVELOPMENT CORPORATION AURANGABAD.
WATER RESOURCES DEPARTMENT
CHIEF ENGINEER (WRD), NORTH MAHARASHTRA REGION, NASIK
COMMAND AREA DEVELOPMENT AUTHORITY, AHMEDNAGAR
MINOR IRRIGATION DIVISION, NASIK.
DRAFT TENDER PAPERS
NAME OF WORK :-- DETAILED SURVEY & INVESTIGATION FOR
LIFT DIVERSION SCHEME NO. 3 & 4 ON WEST
FLOWING RIVERS TO BE DIVERTED INTO
GODAVARI BASIN, DIST.NASHIK.
VOLUME – I & II
ESTIMATED COST :- RS. 7,68,97,449/-
- 2 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
MAIN BID-DOCUMENT APPROVAL
NAME OF WORK :-- Detailed Survey & Investigation for Lift
Diversion Scheme No. 3 & 4 on West
Flowing Rivers to be Diverted into Godavari
Basin, Dist.Nashik.
1. TENDER COST RS. 7,68,97,449/-
(G.M.SANGHANI)
Executive Engineer
Minor Irrigation Division
Nashik.
(N.L.SAVALE)
Superintending Engineer & Administrator,
Command Area Development Authority
Ahmednagar.
(B.C.Kunjir)
Chief Engineer (W.R.)
North Maharashtra Region
Nashik.
- 3 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
NAME OF WORK :-- Detailed Survey & Investigation for Lift
Diversion Scheme No. 3 & 4 on West
Flowing Rivers to be Diverted into Godavari
Basin, Dist.Nashik.
Class of Registration of Bidder :- Class 1 (C) & Above
Limit of Tendering :- RS. 7,68,97,449/-
Validity Period of Registration :- From …………….. To ………………
Issued to :- …………………………………………………………………
…………………………………………………………………
…………………………………………………………………
D.R.No.
Date :-
Sr.No.
Date :-
Divisional Accounts Officer (Gr.I)
Minor Irrigation Division
Nashik.
- 4 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
INDEX
Sr.
No.
Particular Page No.
From To
System E- Tender Notice, Press Notice, Tender Notice, 6 16
SECTION - I
DETAILED TENDER NOTICE, INFORMATION
AND INSTRUCTIONS FOR TENDERERS
1 Invitation 17 19
2 Eligibility 19 20
3 Details of Work 20 -
4 Issue of Blank Tender Forms 20 21
5 Pre-Tender Conference 21 22
6 Revision or Amendments of Tender Documents 22 -
7
Method of submission of Tender/Bid & its accompaniments 22 25
8 Opening of Tenders 25 26
9 Summery And Sequence Of Submission On Line 26 29
10 Instructions for Submission Commercial Envelope C-1 29 32
11 Tender Units 32 -
12 Corrections 32 -
13 Signing of Tender Documents 32 33
14 Acceptance of Tender 33 34
15 Validity for 90 days 34 -
16 Completion of Tender Documents 34 -
17 Language 34 -
18 License under Contract Labour 34 35
ANNEXE “A” 36
Description of Project, Status of Project Climatic Conditions
Scope of Work 36 37
1 Details of Work 38 -
2 Information for obtaining tender papers and its submission 38 39
3 Work and Site Conditions 39 40
4 Period of completion and programme works 40
5 Data for filling statements / Proforma 1(a), 1 (b), 1 (c)
6 Minimum Eligibility Criteria for Pre-Qualification
7 Certificate –A, Undertaking. 43 44
- 5 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Sr.
No.
Particular Page No.
From To
SECTION - II 45
1
Percentage Rate Tender and Contract for work (B-1 Tender
Form) 46 51
2
Schedule ―A‖ 52 53
3
Schedule ―B‖ 53 64
SECTION III 65
1
Forms
Appendix "A" Details of technical personnel with the contractor 66
Appendix "B" Details of plants and machinery immediately
available with the tenderer for use on this work 67
Appendix "C" Details of work of similar type and magnitude
carried out by the contractor 68
Appendix "D" Details of other works tendered for and in hand
on the date of submission of tender 69
Appendix "E" Details of plants and machinery proposed to be
used for the work but not immediately available 70 71
Appendix "F" Declaration of the contractor 72
Appendix "G" Bank Guarantee Bond 73 74
Appendix "H" Indenture for secured advance 75 79
Appendix "I" Professional Tax clearance certificate 80
Appendix "J" Agreement 81 82
Appendix ―K‖ Agreement 83
Appendix ―L‖ Agreement 84
SECTION IV 85
Conditions of Contract (B-1 Form) 86
SECTION V 111
Special Conditions of Contract 112 150
Guarantee Certificate of Work in Hand
Declaration Certificate (Marathi)
Under Taking in Marathi
General Specifications 151 170
- 6 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
SECTION – I
NOTICE
- 7 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
|ÉäºÉ xÉÉä]õÒºÉ
MÉÉänùÉ´É®úÒ ¨É®úÉ`ö´ÉÉb÷É {ÉÉ]õ¤ÉÆvÉÉ®äú Ê´ÉEòÉºÉ ¨É½þɨÉÆb÷³ý, +Éè®ÆúMÉɤÉÉnù
EòɪÉÇEòÉ®úÒ +ʦɪÉÆiÉÉ, ±ÉPÉÖ {ÉÉ]õ¤ÉÆvÉÉ®äú ʴɦÉÉMÉ, xÉÉʺÉEò
<Ç-ÊxÉÊ´ÉnùÉ ºÉÖSÉxÉÉ Gò¨ÉÉÆEò 1 ºÉxÉ 2013-14
MÉÉänùÉ´É®úÒ ¨É®úÉ`ö´ÉÉb÷É {ÉÉ]õ¤ÉÆvÉÉ®äú Ê´ÉEòÉºÉ ¨É½þɨÉÆb÷³ý, +Éè®ÆúMÉɤÉÉnù ªÉÉÆSÉäEòb÷Ò±É ´ÉMÉÇ-1 (Eò) ´É iªÉÉ´É®úÒ±É
ªÉÉäMªÉ iªÉÉ ´ÉMÉÉÇiÉÒ±É xÉÉånùhÉÒEÞòiÉ EÆòjÉÉ]õnùÉ®úÉEòbÚ÷xÉSÉ JÉɱÉÒ±É EòɨÉɺÉÉ`öÒ ¤É-1 ºÉÉ`öÒ +ÉìxɱÉÉ<ÇxÉ
<Ç-ÊxÉÊ´ÉnùÉ |ÉhÉɱÉÒxÉä näùEòÉ®ú ¨ÉÉMÉÊ´ÉhªÉÉÆiÉ ªÉäiÉ +ɽäþ.
+.Gò. EòɨÉÉSÉä xÉÉÆ´É +ÆnùÉÊVÉiÉ ËEò¨ÉiÉ EòÉ¨É {ÉÚhÉÇ
Eò®úhªÉÉSÉÉ
EòɱÉÉ´ÉvÉÒ
ÊxÉÊ´ÉnùÉ ºÉÆSÉ
ËEò¨ÉiÉ ¯û{ɪÉä
1. {ÉζSÉ¨É ´ÉÉʽþxÉÒ xÉtÉÆSÉä {ÉÉhÉÒ
MÉÉänùÉ´É®úÒ JÉÉä-ªÉÉiÉ
´É³ýÊ´ÉhªÉɺÉÉ`öÒ ={ɺÉÉ VÉÉäb÷
ªÉÉäVÉxÉÉ Gò. 3 ´É 4 SÉä
ºÉʴɺiÉ®ú ºÉ´ÉæIÉhÉ, +x´Éä¹ÉhÉ ´É
ºÉʴɺiÉ®ú |ÉEò±{É +½þ´ÉɱÉ
iɪÉÉ®ú Eò®úhÉä.
768.97 ±ÉIÉ 24 ¨ÉʽþxÉä
({ÉɴɺÉɲªÉɺɽþ)
¯û. 15,000/-
|ÉiªÉäEòÒ ºÉÆSÉ
1 <Ç-ÊxÉÊ´ÉnùÉ |ÉhÉɱÉÒ|ɨÉÉhÉä {ÉÚ´ÉÇ +½ÇþiÉÉ ºÉÆSÉÉSÉÒ
ËEò¨ÉiÉ ¯û.5,000/- (¯û.{ÉÉSÉ ½þVÉÉ®ú ¨ÉÉjÉ)
1 ¨ÉÖJªÉ ÊxÉÊ´ÉnùÉ ºÉÆSÉÉSÉÒ ËEò¨ÉiÉ ¯û.15,000/-
(¯û.{ÉÆvÉ®úÉ ½þVÉÉ®ú ¨ÉÉjÉ)
2 {ÉÚ´ÉÇ +½ÇþiÉÉ ºÉÆSÉ Ê´ÉGòÒ, Ênù. 13/09/2013
iÉä 19/09/2013 Ê`öEò : 17.00 ´ÉÉVÉä{ɪÉÈiÉ
2 <Ç-ÊxÉÊ´ÉnùÉ ºÉÆSÉÉSÉÒ Ê´ÉGòÒ EòɱÉÉ´ÉvÉÒ
Ênù. 29/11/2013 iÉä 6/12/2013,
Ê`öEò : 17.00 ´ÉÉVÉä{ɪÉÈiÉ
3 <Ç-ÊxÉÊ´ÉnùÉ {ÉÚ´ÉÇ +½ÇþiÉÉ ºÉÆSÉ ºÉÉnù®úÒEò®úhÉ,
Ênù. 25/09/2013, iÉä 27/09/2013
®úÉäVÉÒ nÖù.12.00 ´ÉÉVÉä{ɪÉÈiÉ, iªÉÉSÉ Ênù´É¶ÉÒ {ÉÚ´ÉÇ
+½ÇþiÉÉ ºÉÆSÉ Ê`öEò : 13.01 ´ÉÉVÉä{ÉɺÉÚxÉ
=PÉb÷hªÉÉiÉ ªÉäiÉÒ±É.
3 ÊxÉÊ´ÉnùÉ {ÉÚ´ÉÇ ¤Éè`öEò Ênù. 4/12/2013 ®úÉäVÉÒ
nÖù{ÉÉ®úÒ Ê`öEò : 12.00 ´ÉÉVÉiÉÉ ¨ÉÖJªÉ +ʦɪÉÆiÉÉ
(VÉ.ºÉÆ.), =kÉ®ú ¨É½þÉ®úɹ]Åõ |Énäù¶É, xÉÉʶÉEò ªÉÉÆSÉä
EòɪÉÉDZɪÉÉiÉ
4 +½ÇþiÉÉ |ÉÉ{iÉ Ê¤Éb÷ºÉÇSÉÒ ªÉÉnùÒ <Ç-ÊxÉÊ´ÉnùÉ
|ÉhÉɱÉÒ |ɨÉÉhÉä VÉÉʽþ®úÒEò®úhÉ
Ênù. 28/11/2013, ®úÉäVÉÒ ºÉɪÉÆEòɳýÒ Ê`öEò :
17.00 ´ÉÉVÉä{ɪÉÈiÉ
4 ¨ÉÖJªÉ ÊxÉÊ´ÉnùÉ ºÉÆSÉÉSÉä <Ç-ÊxÉÊ´ÉnùÉ |ÉhÉɱÉÒ|ɨÉÉhÉä
ºÉÉnù®úÒEò®úhÉ Ênù. 13/12/2013 iÉä
19/12/2013 Ê`öEò : 17.00 ´ÉÉVÉä{ɪÉÈiÉ
- 8 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Ê]õ{É :- ºÉnù®ú EòɨÉɤÉɤÉiÉ ÊxÉÊ´ÉnùÉ +]õÒ ´É ¶ÉiÉÔ <iªÉÉnùÒ ¤ÉɤÉiÉSÉÉ ºÉ´ÉÇ iÉ{ɶÉÒ±É ÊxÉÊ´ÉnùÉ ºÉÆSÉɨÉvªÉä xɨÉÚnù
Eäò±ÉÉ +ºÉÚxÉ {ÉÚ´ÉÇ +½ÇþiÉÉ ºÉÆSÉ ´É ÊxÉÊ´ÉnùÉ ºÉÆSÉ ½þÉ +ÉìxɱÉÉ<ÇxÉ
http://wrd.maharashtraetender.in through sub portal of
http:gmidc.maharashtra.etenders.in ªÉÉÆSÉä ½äþ±{ɱÉÉ<ÇxÉ´É®ú ={ɱɤvÉ +ɽäþ. <Ç-ÊxÉÊ´ÉnùÉ
|ÉhÉɱÉÒ|ɨÉÉhÉä/+ÉìxÉ ±ÉÉ<ÇxÉ ÊxÉÊ´ÉnùÉ ºÉÉnù®ú Eò®úhªÉÉEòÊ®úiÉÉ |ÉÉÊvÉEÞòiÉ EÆòjÉÉ]õnùÉ®úÉxÉä +ÊvÉEÞòiÉ EÆò{ÉxÉÒEòbÚ÷xÉ
ºÉÉnù®úÒEò®úhÉÉEò®úÒiÉÉ ]åõb÷®únùÉ®úÉÆxÉÒ +ÊvÉEÞòiÉ EÆò{ÉxÉÒEòbÚ÷xÉ Êb÷ÊVÉ]õ±É º´ÉÉIÉ®úÒ EòÒ (Digital Key) JÉ®äúnùÒ
Eò®úhÉä +ɴɶªÉEò +ɽäþ. +ÊvÉEÞòiÉ EÆò{ÉxÉÒSÉä xÉÉÆ´É 1.]õÒºÉÒBºÉºÉÒB, 2.BxÉ.EòÉäb÷ ºÉÉ䱪ÉÖ¶ÉxÉ ºÉÒB ªÉÉ
´ªÉÊiÉÊ®úCiÉ ªÉɺÉÉ`öÒSÉÒ +ÊvÉEò ¨ÉÉʽþiÉÒ VÉÉhÉÚxÉ PÉähªÉɺÉÉ`öÒ ´É®úÒ±É ½äþ±{ɱÉÉ<ÇxÉ´É®ú +ÊvÉEò ¨ÉÉʽþiÉÒ ={ɱɤvÉ
+ɽäþ. ºÉʴɺiÉ®ú ÊxÉÊ´ÉnùÉ ºÉÖSÉxÉÉ EòɪÉÇEòÉ®úÒ +ʦɪÉÆiÉÉ, ±ÉPÉÖ {ÉÉ]õ¤ÉÆvÉÉ®äú ʴɦÉÉMÉ, xÉÉʶÉEò ªÉÉÆSÉäEòbä÷ ±ÉäJÉÒ
+MÉ®ú ºÉ¨ÉIÉ ¨ÉÉMÉhÉÒ Eäò±ªÉÉºÉ ={ɱɤvÉ ½þÉä<Ç±É ´É xÉÉä]õÒºÉ ¤ÉÉäbÇ÷´É®ú näùJÉÒ±É ={ɱɤvÉ +ɽäþ. nÖù®úv´ÉxÉÒ
Gò¨ÉÉÆEò (0253-2315485)
EòɪÉÇEòÉ®úÒ +ʦɪÉÆiÉÉ
±ÉPÉÖ {ÉÉ]õ¤ÉÆvÉÉ®äú ʴɦÉÉMÉ
xÉÉʶÉEò.
- 9 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
PRESS NOTICE
Godavari Marathwada Irrigation Development Corporation
Aurangabad
EXECUTIVE ENGINEER, MINOR IRRIGATION DIVISION, NASIK.
E-Tender Notice No. 1 OF 2013-14
Godavari Marathwada Irrigation Development Corporation, Aurangabad is
inviting E-tender/Online tender from Authorized Contractors Registration
with Godavari Marathwada Irrigation Development Corporation, Aurangabad
in Class-I (C) Online for the B-1 Tender following work in Nasik District.
Sr.No. Name of Work Estimated
Cost Rs. In
lakhs
Work
Complete
Period
Main Tender
Booklet Cost
1. Detailed Survey &
Investigations for Lift
Diversion Scheme No. 3
& 4 on West Flowing
Rivers to be Diverted
into Godavari Basin,
Dist.Nashik.
768.97 24
Months
(Including
Mansoon
Period)
Rs.15,000/-
Each Copy
1 Cost of E-Tender system Pre-
Qualification Document Cost
Rs.5,000/- (Rs.Five Thousand Only)
1 Main Tender Commercial Booklets
cost Rs. 15,000/- (Rs.Fifteen
Thousand Only.
2 Pre-Qualification Documents will be
available for sale Period Date :-
13/09/2013 to 19/09/2013 @ : 17.00
hrs.
2 As per E-Tender system Main Tender
booklets will be available for sale
period on Dt. 29/11/2013 to
6/12/2013, upto : 17.00 hrs.
3 Date of submission of Pre-
Qualification Document through
E-Tender system on Dt. 25/09/2013,
to 27/09/2013 upto.12.00 hrs.
3 Pre Tender meeting will be held on
Dt.. 6/12/2013 at : 12.00 hrs. in the
Officer of the Chief Engineer (W.R.),
North Maharashtra Region, Sinchan
Bhavan, Nasik.
4 Pre-Qualification bidders only those
who are short listed on E-Tender
system declared Dt. 28/11/2013, at
17.00 hrs.
4 Submission of Main Tenders through
E-Tender system is 13/12/2013 to
19/12/2013 upto : 17.00 hrs.
- 10 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Note : Details of Tender condition etc. are in corporate in the E-Tender Pre-
Qualification documents and Tender document. Pre-Qualification Document set &
Main tender Document set is available online http://maharashtra.gov.in through sub
portal of http://gmide.maharashtra.etenders.in for submission of E-Tender/Online
tender bidder has to obtain Digital signature Key from authorized company/agency.
Name of authorized company/Agency is detail information available above website.
And details tender notice can be obtain from office of the Executive Engineer,
Minor Irrigation Division, Nasik. Phone No. (0253-2315485).
Executive Engineer
Minor Irrigation Division
Nashik.
- 11 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
E-TENDER NOTICE
E - TENDER NOTICE NO. 1 FOR 2013-14.
Sealed Online Tenders (e -tender) in B-1 form for the following work
are invited by the Executive Engineer, Minor Irrigation Division, Nashik
Pin Code-422 002, Tel. No. 2315485 Fax No. 2315485 on Government of
Maharashtra Electronic Tender Management System
http://maharashtra.etenders.in through Sub Portal of
http://gmidc.maharashtra.etenders.in from the contractors registered with
the Godawari Marathwada Irrigation Development Corporation, Aurangabad
in appropriate class mentioned. The blank tender forms shall be available on
the http://maharashtra.etenders.in through Sub Portal of
http://gmidc.maharashtra.etenders.in from 29/11/2013 to 6/12/2013 during
the period only qualified contractors in pre-qualification should submit duly
filled downloaded tender documents at the office of the Superintending
Engineer & Administrator, Command Area Development Authority,
Ahmednagar on or before dt. 19/12/2013 upto 17.00 hrs. & will be opened on
the dt. 27/12/2013 at 18.00 Hrs.
Sr.
No.
Name of work Estimated
Cost Rs.
In Lakhs
Time limit
for
completion
(Months)
Earnest
Money
Rs. In
Lakh
Cost of
blank
tender
form
(Rs.)
Class of
Registration
1 Detailed Survey
& Investigations
for Lift
Diversion
Scheme No. 3 &
4 on West
Flowing Rivers
to be Diverted
into Godavari
Basin,
Dist.Nashik.
768.97
24 Month
Calendar
(Including
mansoon)
7.69 15,000/-
Class-I (C) &
Above
(The bidder
should be a
Registered
contractor with
Public Works
Department
(Govt. of
Maharashtra)
and must be
registered with
Godawari
Marathwada
Irrigation
Development
corporation,
Aurangabad)
1. Detail tender notice can be seen on the notice board in the
Executive Engineers office. (Copy can be obtained free of cost
- 12 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
from Executive Engineer on request). Blank tender booklets are
available on the Government of Maharashtra website
http://maharashtra.etenders.in through Sub Portal of
http://gmidc.maharashtra.etenders.in. The competent authority reserves all
rights of rejecting tender without assigning any reason.
A) Pre-Qualification Stage :-
1) Pre-Qualification Documents will be available on Government of
Maharashtra website http://maharashtra.etenders.in through Sub Portal
of http://gmidc.maharashtra.etenders.in. from dt. 13/09/2013 to 19/09/2013
the Bidder has to submit the Bid capacity documents online as per key
dates mentioned below.
2) The cost of main tender document is Rs. 15,000/- only. It is necessary to
draw the Demand Draft of Rs 5,000/- in favour of "The Executive
Engineer, Minor Irrigation Division, Nasik for purchase of Pre-
Qualification Documents. Submit D.D. of Rs.5000/- to Executive
Engineer, Minor Irrigation Division, Nasik and take duplicate receipt from
Division office during sale period dt. 13/09/2013 to 19/09/2013, along with
registration copy there after immediate upload or login SCAN copy of
information of D.D. details & SCAN copy of Duplicate receipt No. & date
of Division on website http://maharashtra.etenders.in in order to download
Pre-Qualification, for further action of Bidders, within Key dates.
Bidders/contractor shall submit Registration certificate True Copy of
GMIDC on or before 19/09/2013, The Executive Engineer, Minor
Irrigation Division, Nasik, List of Eligible Bidders in Pre-Qualification
stage will be available on 28/11/2013 at 17.00 Hrs on web site
http://maharashtra.etenders.in.
B) Main Bid / Tender Stage :-
Only those contractors / Bidders, who are eligible and short listed in Pre-
Qualification stage, are allowed or eligible for participating in main tender.
The cost of main tender document is Rs. 15,000/- only. It is necessary to
- 13 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
draw the D.D. of Rs. 15,000/- in favour of Executive Engineer, Minor
Irrigation Division, Nasik and take Duplicate Receipt from Division office
during sale period 29/11/2013 to 6/12/2013. There after immediate upload or
log in information SCAN copy D.D. details and duplicate receipt and its
date of Division office on web site http://maharashtra.etenders.in in order
to download Main Tender Documents for further action of Bidders with
Key dates.
The EMD for tender should be in the form of D.D. & B.G. of any
Nationalized or Scheduled Bank in favour of the Executive Engineer,
Minor Irrigation Division, Nasik of Rs. 7.69 Lakhs. There after Bidders or
Contractors shall submit D.D. of Rs. 7.69 Lakhs. Irrevocable Bank
Guarantee to Office the Executive Engineer, Minor Irrigation Division,
Nasik on or before dt. 6/12/2013 in physical envelops. Bidders /
Contractors shall take submission receipt of D.D. of Rs. 7.69 Lakhs. Bank
Guarantee from Division Office for further action. Also Bidders /
Contractors shall submit Registration copy of GMIDC, in same envelop to
Division. There after upload receipt details, Registration copy details, on
website prior to date of final submission. The tender shall be summarily
rejected if it is not accompanied with EMD.
Main Bid Pre Tender Conference of contractors will be held on dt 4/12/2013 at
12 hours in the office of the Chief Engineer (W.R.), North Maharashtra
Region, Sinchan Bhavan, Nasik.
- 14 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
*KEY DATES* Please fill up the start date time and end date and time as per the schedule as
under.
Sr.
No.
GMIDC
Stage
Contractor Stage Start Date &
Time
Expiry Date
& Time
View
Forms Envelops
PRE – QUALIFICATION STAGE
1. Release
Tender
--
2. Pre-qual.
Document
Purchase and
Download
-- Pre Qualification
Bid
3. Pre-qual.
Document
Preparation and
online Bid
-- Pre Qualification
Bid
4. Close
Bidding
--
-- Pre-qual.
Bid
5. -- Pre Qualification
Bid submission
-- Pre-qual.
Bid
6. PQ Opening
document
opening &
short listing
--
-- Pre-
Qualification Bid
7. Main
Tender
Realease
--
-- Commercial
Envelope C1,
Tech.Enve.T1
8 Main
Tender
Purchase &
download
-- Commercial
Envelope C1,
Tech.Enve.T1
9 -- Main Tender
Document
Preparation
-- Tech.Enve.T1
10 -- Main Tender
Document &
online bid
-- Commercial
Envelope C1,
11 Close
bidding for
general
condition
--
-- Commercial
Envelope C1,
Tech.Enve.T1
12 Tender
submission
--
-- --
13 Tender
opening &
short listing
(technical)
--
-- Technical
Envelope T-1
14 Fina cial
Bid opening
--
-- Commercial
Envelope C-1
- 15 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
1. It is necessary to give the undertaking as follows ―Contractors are not
allowed to make any changes in tender documents downloaded from
website. If it so the tender of such contractors will be rejected and the
contractors who made such changes are liable for action as per Rules."
Tender documents published on Government website are considered as
an authentic and legal documents in case of any complaint about the
tender.
2. It is necessary to give undertaking as follows " I have seen detailed
drawings of works on website. It is part of tender documents. I have
filled tender by considering all these things. I am ready to sign on the
drawings before depositing security deposit and taking work order if my
tender will be accepted.
3. In order to participate in the tenders floated using the Electronic Tender
Management System (ETMS), all contractors/bidders are required to
get enrolled on the ETMS portal (http://maharashtra.etenders.in)
4. The bids submitted online should be signed electronically with a Digital
Certificate to establish the identity of the bidder bidding online. The
registered contractors has to obtain the Digital Certificate, the
information required to issuance of Digital Certificate he may contact
ETMS Help Desk,
5. For submitting the bids online, the contractors/bidders are required to
make online payment using the electronic payments gateway service
Bid Submission Fee Rs 1038/- The different modes of electronic
payments accepted on the ETMS is available and can be viewed online
on the ETMS Website (http://maharashtra.etenders.in).
6. The activities of Tender purchase/Download, Preparation of Bid
(Submit Bid Hash online), Submission of Bids, Submission of EMD
and other Documents will be governed by the time schedules given
under "Key Dates".
7. The Bidders has to submit (Upload Scan Copies/fill) his offer/credentials
- 16 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
online as required in the tender/prequalification in the online templates
in relevant envelopes The Scan copy of Earnest Money details to be
submitted online and original EMD need to be submitted in
Physical at office of the Executive Engineer, Minor Irrigation
Division, Nasik.
8. The Bidders may refer E-Tendering Tool Kit available online to perform
their online activities.
9. The contractor shall study the guidelines regarding E-Tendering to get
clarify E-Tendering Procedure.
- 17 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
DETAILED TENDER NOTICE
1. INVITATION :
1.1 E-Tenders in B-1 form are invited by the Corporation from the contractor
registration in appropriate class with the Godawari Marathwada Irrigation
Development Corporation, Aurangabad for the work as stated in Annex-A.
1.2 Definitions and interpretations : In this tender documents the following
terms shall have the meaning hereby assigned to them except where the
context otherwise requires.
a) ―Corporation‖ shall mean the Godawari Marathwada Irrigation
Development Corporation, Aurangabad acting through its Executive
Director, as defined in Maharashtra Act XVIII of 1998.
Godavari Marathwada Irrigation Development Corporation,
Aurangabad is a body corporate constituted under the Maharashtra Act
XVIII of 1997 and has been established by the notification published in
the Extra Ordinary Gazette dated 17/8/1998. The head quarters of the
Godawari Marathwada Irrigation Development Corporation, Aurangabad
(GMIDC, Aurangabad for short, and hereinafter referred to only as
Corporation) is Aurangabad. The office postal address for correspondence
is :
The office of the Executive Director,
Godawari Marathwada Irrigation Development Corporation,
Aurangabad Sinchan Bhavan, Jalna Road, Aurangabad-431 005.
Phone No. 334077.
General Information :-
The functions and powers of the Corporation have been listed in the
Maharashtra Act XVIII of 1998 in general, it has been entrusted with the
work of investigation, planning, designing of projects, maintenance of
completed projects, and construction of projects and irrigation
management of Major, Medium and Minor Projects in the Godawari
- 18 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Marathwada Irrigation. The projects comprise irrigation, hydroelectric
projects (except Bhandardara (Phase I & II) & Ghatghar Hydro electric
Power Projects) along with the command area development, and
multipurpose schemes. The Project are to be completed so as utilize water
in pertaining to Maharashtra State. During the project time slice, it is
expected to increase the performances efficiency of the completed projects
and to complete further ongoing and new works, so as to utilize the water
from Godavari basin.
b) ―Chief Engineer‖ shall mean Chief Engineer (W.R.), North
Maharashtra Region, Nashik.
c) ―Engineer/Engineer-in-charge‖ shall mean the Executive Engineer-in-
charge of the works and shall also include the superior Officers of the
Engineering Department of Corporation, i.e. the Superintending Engineer
of respective Circle/Chief Engineer.
d) ―Engineer‘s representative‖ shall mean the Sub-Divisional
Engineer/Assistant Executive Engineer/Sub-Divisional Officer/Assistant
Engineer Gr.I of the Corporation.
e) ―Contractor‖ shall mean the person, firm or company who enters into
contract, with the Corporation and shall include their executors,
administrators, successors and submitted assignees.
f) ―Tender‖ shall mean and include agreement having volume as below.
Volume- Tender Document, Specifications, Drawings.
g) ―Work‖ shall mean the work to be executed in accordance with contract.
h) ―Specifications‖ shall mean the specifications for material, works as
specified in Volume of the contract.
i) ―Drawing‖ shall mean prints of the maps, drawings, plans in Tender of the
contract and shall include any modifications of such drawing and any
further drawings as may be issued by the Engineer-in-charge from time to
time.
- 19 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
j) ―Site‖ shall mean the place where the survey, investigation of the works
are carried out any other lands or places provided by the Corporation.
k) ―Defect(s) liability period‖ shall mean period of 12 months from the date
of issue of completion certificate by the Engineer-in-charge.
Singular and Plural :
Works imparting the singular number shall also include the plural and
vice versa where the context requires.
Heading and marginal heading :
The headings and the marginal headings in the contract are solely for
the purpose of facilitating reference and shall not be deemed to be part
thereof or taken into consideration in the interpretation or construction
there or of the contract.
2. Eligibility :-
Blank tender papers will be issued to those contractors who would
satisfy the following criteria depending upon the cost of work.
1) For works costing less than Rs.50 Lakhs.
Contractor having an appropriate registration with Godawari
Marathwada Irrigation Development Corporation, Aurangabad.
2) For works costing between Rs. 100 Lakhs to 300 Lakhs.
Contractor on approved list in appropriate class with Corporation and
who have adequate bid capacity for work as certified by the competent
Corporation authority will only be eligible for purchase of blank tender forms.
3) For works costing more than Rs. 300 Lakhs.
Valid Register Contractor on approved list in appropriate class with
Corporation and who have been pre-qualified for the work by the competent
corporation authority will only be eligible for purchase of blank tender forms.
- 20 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Method of Online applying :
All the tender activities like tender download (tender seal) tender
preparation tender submission and opening of tender will be conducted
online only as per key dates mentioned in online time schedule.
Detailed tender notice can be seen on the notice board in the Executive
Engineer‘s Office (Copy can be obtained free of cost from Executive
Engineer on written request) Blank tender booklets are available on the
Government of Maharashtra website (http://maharashtra.etenders.in)
through sub portal of http://gmide.maharashtra.etenders.in the
competent authority reserves all rights of rejection any or all tenders
without assigning any reason.
3. DETAILS OF WORK :
The estimated cost, earnest money deposit, class of contractor, period
of completion of work and other information is given in Annex ―A‖ of
this section.
4. ISSUE OF BLANK TENDER FORMS :
Main Bid / Tender Stage :
Only those contractors/Bidders, who are eligible and short listed in
Pre-Qualification stage, are allowed or eligible for participating in
main tender. The cost of main tender document is Rs. 15,000/- only. It
is necessary to draw the D.D. of Rs. 15,000/- in favour of Executive
Engineer, Minor Irrigation Division, Nasik for purchase of main tender
documents. Submit D.D. of Rs. 15,000/- to the Executive Engineer,
Minor Irrigation Division, Nasik and take Duplicate receipt from
Division Office, during sale period 29/11/2013 to 6/12/2013. There
after immediate upload or log in information SCAN copy D.D. details
and duplicate receipt and its date, of Division Office on web site.
http://maharashtra.etenders.in In order to download Main Tender
documents for further action of Bidders, with Key dates.
- 21 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
The EMD for tender should be in the form of D.D. & B.G. of any
Nationalized or Scheduled Bank in favour of the Executive Engineer,
Minor Irrigation Division, Nasik and payable at Nasik, of Rs. 7.69
Lakhs. Irrevocable Bank Guarantee to Office the Executive Engineer,
Minor Irrigation Division, Nasik on or before dt. 6/12/2013, in
physical envelops Bidders / Contractors shall take submission receipt
of D.D. Rs. 7.69 Lakhs. Bank Guarantee from Division Office for
further action. Also Bidders / Contractors shall submit Registration
copy of GMIDC (Particular survey as a special work), in same envelop
to Division. There after receipt details, Registration copy details,
upload on website prior to date of final submission. The tender shall
summarily rejected if it is not accompanied with EMD.
Main Bid Pre Tender Conference of Contractor will be held on
dt. 4/12/2013 at 12 hours in the office of the Chief Engineer (W.R.),
North Maharashtra Region, Nasik.
5. PRE-TENDER CONFERENCE :
(Applicable for the work costing above Rs. 50 Lakhs)
1) Pre-tender conference open to pre-qualified tenderers will be held in
the office as stated in Annex ―A‖ of this section. Where in the
prospective tenderers will have an opportunity to obtain clarifications
regarding the work and the tender conditions.
2) The prospective tenderers are free to ask for any additional
clarification either in writing or orally and the reply to the same will be
given by the Chief Engineer, in writing and these clarifications referred
to as common set of conditions, shall form part of tender documents
and which will also be common and applicable to all tenderers.
3) The tender submitted by the tenderers shall be based on the
clarification, additional facility issued (if any) by the Corporation and
this tender shall be unconditional. Conditional tenders will be
summarily rejected as non-responsive.
- 22 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
4) All tenderers are cautioned that the tenders containing any deviation
from the contractual terms and conditions, specifications or other
requirements and conditional tenders will be rejected as non
responsive.
6. REVISION FOR AMENDMENT OF TENDER DOCUMENTS :
Right is reserved to revise or amend the tender documents prior to last
date notified for the issue of tenders and such revisions or amendments
or extensions shall be communicated to all concerned online E-
Tendering procedure on website http://maharashtra.etenders.in.
Tenderer shall be presumed to have carefully examined all documents
forms, statements special conditions, schedules, drawings, and
specifications of contract and to have fully acquainted himself with all
details of the site, his own quarries for rubble, sand, earthworks etc.
location of materials, river and the weather characteristics and labour
conditions in general and with all the necessary information and data
etc. pertaining to and needed for the work prior to tendering of the
work.
7. METHOD OF SUBMISSION OF TENDER AND ITS
ACCOMPANIMENTS :
Main Tender / Bid shall be submitted as per ―E‖ Tender
procedure on line The Tenders / Bidder shall submit the tender / bid
and documents as per following and comprising envelopes.
(a) E. M.D. stage
(b) C- 1 Commercial Envelope
(c) T-1 Technical Envelope
7.1 E.M.D. stage on (Part-1 stage) : Enclosures & contents
1 a) The Tenders / Bidder shall upload scan copy of duplicate Receipt taken
from Executive Engineer, Minor Irrigation Division, Nasik for purpose
of E.M.D. under physical submission. Details of E.M.D. & submission
- 23 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
are elaborated in detail tender notice, and Page No. 4 Tender / Bidder
shall upload the details E.M.D. Receipt & Duplicate Receipt.
1 b) Tenders‘ / Bidder shall upload for submission purpose as per E-tender
procedure on website, details of following documents, in this E.M.D.
Stage envelope.
2 a) Certificate in original or certified copy thereof as registered contractor
with the GMIDC, even though submitted earlier while issuing tender
form.
b) Copy of Income Tax Return for the year 2011-2012.
3. Deed of partnership or Article of Association and Memorandum of
Association for limited company.
4. The contractor shall have to attach any one of the valid the
documentary proof in respect of machines owned by him as below: -
i) RTO Registration
ii) Certificate of Taxation.
iii) Goods carriage permits in Form P-Gd Certificate (see Rule 72 (i)
iv) Certificate of fitness in form 38 (See Rule 62 (1) 7) in case of Non-
RTO Machinery, if the machinery is new the manufacturer‘s sale
certificate shall be produced. In case of second hand machinery, the
purchase document with proof of payment in Balance sheet certified by
the Chartered Accountant shall be produced. In lieu of the certificate of
the chartered accountant a certificate from a scheduled Bank of having
financed the machinery will be acceptable.
5. Power of Attorney (if essential).
6 Professional tax clearance (as shown and given on Page No. 11 to 12
of the tender form).
7. Statement showing yearly turnover in terms work during last three year
(in form No.6).
- 24 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
8. Statement showing the important items completed by the contractor
any one year please note down the year (in form No. 7).
9. Registration certificate of labour provident fund Act and Certificate of
competent authority for remittance of necessary amount in labour
provident fund account.
10. Tender‘s summary: original copies shall be kept ready at the time of
opening of tender.
a) The Tender rates are inclusive of all taxes, cesses and are also inclusive
of the liable tax in respect of sale by transfer of property in goods
involved in the execution of a work contract under the provision of
Rule 58 of Maharashtra Value Added Tax Act, 2005 for the purpose of
levy of Tax‖
7.2 C-1 Commercial Bid (Part II stage)
Commercial Bid shall contain, Volume No. 1 Commercial booklet,
Containing Section I to IV fully filled and digitally signed by
contractor document, in which, PERCENTAGE RATE TENDER
AND CONTRACT FOR WORKS B-1 TENDER FORM, UNDER
HEAD “TENDER FOR WORKS” is incorporated. Also the volume
No.1 booklet shall contain.
B) Envelope No. 2 : Tender:
Envelope No. 2 shall contain the main tender (Vol. I +II) including the
common set of condition / stipulations issued by the corporation after
then pretender conference and bank guarantee for additional Earnest
Money Deposit as required. A tender submitted without this would be
considered as invalid. The tenderer should quote his offer in the form
of percentage below or above of the estimated cost given in Schedule
―B‖ Part -1 (IA+IB) at appropriate place in B-1 form, He should not
- 25 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
quote his offer anywhere directly or indirectly in Envelope No.1 failing
which the Envelope No. 2 shall not be opened and his tender shall
stand rejected. The contractor shall quote for the work as per details
given in the main tender and also based on the common set of
condition issued / additional stipulations made by the corporation as
informed to him by a letter from the Superintending Engineer, of the
office as given in Annex-A of this Section, after pre-tender conference.
This tender shall be unconditional documents as required in Clause 7
(1 to 9) of this detailed Tender Notice, if applicable, shall also be
included.
8.0 OPENING TENDER: Tenderer / Bidder shall quote his ―OFFER IN
THE SYSTEM GENERATED FORMAT‖. For on Line evaluation
purpose, in opening stage of bid. Also Tenderer / Bidder shall quote his
offer in this ―PERCENTAGE RATE TENDER & CONTRACT B-1
FORM‖ under head Tender works, as integral part of this commercial
booklet volume No. I, Page No. 36 If the offers quoted in System
Generated Format and Percentage rate form in commercial Booklet are
different or in ambience. Tender will be summarily rejected.
―OFFER‖ in System Generated Format and percentage Rate B-1
tender form shall be same.
8.1 TECHNICAL ENVELOPE (T-1):
1. Technical Envelope shall contain ―Specification and Drawings‖
Upload T-1 envelope with ―Specification and Drawing‖.
The Tenderer / Bidder shall submit 1. E.M.D. Stage C-I Commercial
Envelope.
1. T-1 Technical Envelope as per detail instruction mentioned in
above procedure, on line as per ―E‖ tendering procedure and on
website (http://maharashtra.etenders.in) through sub portal of
(http://gmidc.maharashtra.etenders.in) if any of envelope is not
- 26 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
uploaded on website (http://maharashtra.etenders.in) through sub
portal of (http://gmide.maharashtra.etenders.in) in sequence for
submission or if any missing envelope, or uploading errors in
submission tender will be rejected. Please visit website
(http://maharashtra.etenders.in) through sub portal of manner of
submission. Also contact the Executive Engineer, Minor Irrigation
Division, Nashik, in person as on Phone No. 0253-2315485 for any
inquiry of submission.
9.0 SUMMARY AND SEQUENCE OF SUBMISSION ON LINE :
9.1 First Step : Upload E.M.D. Stage, as mentioned herein above, with all
details and enclosures.
9.2 Second Step : Upload and Fill, C-1 commercial booklet No.I, quoting
OFFER IN Percentage B-I Form and System generated ―OFFER
FORMAT‖ with all requisite details and enclosures.
9.3 Upload T-I Technical Envelope with all requisite details and
enclosures. If any omissions in above sequential procedure, errorless
submission, then tender / bid will be rejected.
i) a) EARNEST MONEY: All tenderers shall pay the entire EMD as
below: 1) Demand Draft of amount as stated in para 6.1 of Annexe ―A‖
as non interest bearing deposit with the corporation for a period of 90
days from the date of submission of tender for an amount as stated in
the para 6.1 of Annexe ―A‖. The D.D. shall be from any Nationalized
or Scheduled Banks Branches situated in the State of Maharashtra.
A Cheque or FDR will not be accepted.
b) ADDITIONAL EARNEST MONEY: In case contractor offer is less
than 90% of the updated estimated cost as stated at Sr.No. 5 of Annexe
―A-1 additional earnest money in the form of irrevocable Bank
Guarantee for a period of 90 days from the date of submission of the
tender and for an amount equal to the difference of contractor‗s offer
- 27 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
and 90% of updated estimated cost as stated above shall be enclosed in
Envelope No.2 non-submission of Bank Guarantee of required amount
shall make the offer invalid and shall stand rejected. The bank
Guarantee shall be from any Nationalized / Scheduled Bank‘s Branch
situated in the State of Maharashtra.
This earnest money amount shall not carry any interest whatsoever.
The earnest money will be refunded (Bank Guarantee, if any will be
released) in the case of tenderers whose tenders are not accepted, only
after completion of all formalities in respect of the accepted tender or
in case of expiry of validity of offer, when specially withdrawn by the
tendered. In the case of successful tenders, the earnest money will be
refunded after completion of contractor documents and payment of
security deposit as per provision made in para (ii) security deposit, or
converted into security deposit if required.
ii (a) SECURITY DEPOSIT : A sum as mentioned in printed B-1 Tender
form at para (e) (I) of Memorandum will have to be deposited in cash
in the form of D.D. Drawn in the name of Executive Engineer by the
contractor at the time of completing the contract documents, if his
tender is accepted by the corporation.
OR
The initial security deposit may be paid in cash Rs. 19.22 lakhs as per
D.D. Rs. 6.00 Lakhs & and Rs. 13.22 Lakhs in the form of irrevocable
bank Guarantee from any Nationalised or Scheduled Bank‘s Branch
situated in the State of Maharashtra for a period equal to the time limit
plus the period of defects liability (Sr. Clause - 20 of B-1 Tender form
Vol - 1)
OR
In lieu of security Deposit mentioned above corporation securities
corporation bonds, in the prescribed form as may be approved by
corporation from time to time, standing in the name of tenderer shall be
- 28 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
accepted if pledged as security deposit in the name of the Executive
Engineer, as stated at Sr. No. 2.1 of Annexe ‗A‘ of this Section.
OR
The Earnest money deposited by the contractor with his tender will be
retaining by the corporation as per of security deposit if Tenderer
requests in writing to that effect. The balance to make up his security
deposit may unless otherwise specified in the special conditions, be
deposited by the contractor in the form of irrevocable bank Guarantee
or cash or in the form of bonds / cash certificate of Corporation.
The security deposit will be retained by the corporation for the due and
faithful fulfillment of the contract by the contractor. In addition to the
sum as above sums as security deposit will be deducted from running
account bills at the rate shown at Memorandum Para (g) in B-1 Tender
form to total up to a sum mentioned at Memorandum Para (e) in B-1
Tender form. The sum of security deposit made from the running
accounts bill will remain in the form of cash or corporation securities
standing in the name of the Executive Engineer.
II B) ADDITIONAL SECURITY DEPOSIT : In case contractor‘s offer is
less than 90% of the updated estimated cost as stated at Sr. No. 5 of
Annex. ―A‖ Additional Security Deposit in the form of irrevocable
Bank Guarantee from any nationalized or scheduled Bank‘s branch
situated in the state of Maharashtra for a period of contract, and for an
amount equal to the difference of the contractor‘s offer and 90% of the
updated cost as completion of tender documents. Non-submission of
the above additional Security deposit will result into for feature of the
E.M.D. and Additional E.M.D. Security deposit will be refunded after
expiry of the defect (s) liability (maintenance) period as stipulated in
the contract.
- 29 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
iii) INCOME TAX CERTIFICATE : Income Tax is to be deducted from
the sums to be paid to the contractor for the works carried out at 2% of
the gross amount and surcharge on Income Tax as per prevailing
Government orders from time to time.
iv) VAT TAX : The tender rates are inclusive of all taxes, cess and are
also inclusive of the liable tax in respect of sale by transfer of property
in goods involved in the execution of a work contract under the
provision of Rules 58 of Maharashtra Value Added Tax Act, 2005, for
the purpose of levy of Tax.
v) PROFESSIONAL TAX: Certificate of registration with the
professional tax officer of the district in form IA. Certificate of
registration under section 5 (1) and 5 (2) of the Maharashtra Sales Tax
on Professions. Traders, calling and employment act 1975 Form is as
per Appendix I in the volume I.
It should be also made clear that the employees shall be all those who
receive the wages / salaries from the tenderer and shall include the
office and field staff and those operating the machinery / equipment. It
should also ensured that the machinery / equipment. It should also be
ensured that the machinery said to be deployed for the subject work is
really in the ownership of the tenderer.
10. INSTRUCTIONS FOR SUBMISSION OF COMMERCIAL BID
Documents to be submitted in C-1 commercial Bid shall confirm to the
instruction given below.
i) CONTRACTOR TO INFORM HIMSELF FULLY: The tenderer
shall be deemed to have fully acquainted him with the work and site
conditions and carefully examined the special conditions, the
specifications, schedules and drawings and shall be deemed to have
- 30 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
fully informed him regarding the local conditions. The tenderer shall
also be deemed to have fully acquainted with the various leads and lifts
involved in the works and materials of construction as well as shall be
deemed to have fully acquainted with his own various quarries for
construction materials, their availability and adequacy etc.
ii) CONDITIONAL TENDER: Conditional tenders will be summarily
rejected. The tenders which do not fulfill any of the conditions of the
notified requirements laid down in this detailed tender notice, the
general rules and directions for the guidance of the tenderers as
mentioned in the B-1 form or are incomplete in any respect are likely
to be rejected without assigning therefore.
iii) TENDERED RATE: The tenderer should quote his offer in the form
of percentage above or below the estimated cost, entered in Schedule
―B‖ Part – 1, at appropriate place in B-1 form both in figures as well as
in words in English. The percentage will not apply to schedule ―B‖
Part II. In case there is difference between the percentage quoted as
expressed in words and in figures, the percentages as expressed in
words will be taken as correct irrespective of whether it is lower or
higher than that expressed in figure. No. alternation in the form of
tender and in schedule of quantities will be permitted except schedule
―B1 Part II. The percentage mentioned in the tender shall be taken as
applying to all conditions of weather and will be inclusive of all taxes
if any The percentage should be written in one line only as far as
possible.
All the additional item (s) as many as foreseen by the tenderer with
quantity (i.e.), rate (s) amount (s) and the detailed description shall be
entered into by the tenderer in the space provided below schedule ―B‖
Part – II – Anticipated additional items as foreseen by the tenderer. The
tenderer is free to attach additional sheets, if required by him and sign
the sheets, which will form part of the tender.
- 31 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
The specifications for the additional item (s) as foreseen by the
tenderer shall be in conformity with the nearest comparable item
stipulated in the Hand Book of Standard Specifications (PWD) and the
applicability shall be decided before the acceptance of the tender.
The amount of all the items of Part- 1 of Schedule B with percentage
(+ or -) and the amount of Para – II of Schedule ―B‖ will be totaled and
this will be considered as the offer of the tenderer. The work in
additional items in Schedule ―B‖ Part – II shall be paid for only when
executed. The quantities of these items shall be fixed quantities
The provisions of Price Variation in para 33 of special conditions of
contract shall be applicable for the works executed under Additional
item of Schedule ‗B‖ of Part-II. The provisions of Clause 38 of
conditions of contract. Quantity Variation Clause will not be
applicable to the Additional anticipated items in Schedule ―B1 of Part
II‖
iv) If the percentage quoted by the tenderer is less than 90% of the updated
estimated cost as stated at Sr. No. 5 Annex ―A‖ then the tenderer shall
furnish his detailed item wise justification for all items costing Rs.
50,000/- (Rs. Fifty Thousand only) and above put to tender in
Envelope No. 2 in order to establish the reasonableness of the rates.
Tenderer shall also submit additional information in justification of his
offer wherever called for by the corporation, without which the offer
will not be considered.
V) QUANTITIES PUT TO TENDER : The schedule ―B‖ (Schedule of
Quantities and Bid rates) of the tender is made up of two parts as
below: -
1. Part- I – Items as put to tender by the corporation.
2 Part- II Anticipated Additional items as foreseen by the tenderer.
(Refer Note No.5 and 10 under schedule ―B‖)
- 32 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
The quantities given in schedule ―B‖ Part – I as put to tender by the
corporation for various items therein are approximate as some of the
items of works put to tender are likely to be executed departmentally
till the contract agency is fixed. Such quantities which would be
executed till the fixation of contract agency will stand deducted from
the quantities entered in the schedule B at the time of completing the
tender documents by the contractor. The contractor should take
cognizance of this fact ant no claims will be tenable on account of such
reduction in quantity.
The quantities of items on which the Department has carried out the
work, as measured on the date of work order shall stand deducted from
the quantities stipulated in Schedule B Pat I as put to tender by the
corporation for the purpose of application of the stipulation of clause
38 of conditions of contractor of the tender.
11) TENDER UNITS : The tender has been invited under the Metric
System of measurements. The tenderer should particularly note the
units mentioned in schedule B on which rates are to be based.
12) CORRECTIONS: No corrections should ordinarily be made in the
tender documents. Any corrections in the entries made by tenderer
should be by crossing the incorrect portion and writing the corrected
portion above and each sub correction shall bear the attestation of the
tenderer
13) SIGNING OF TENDER DOCUMENTS: The tender shall contain
the name residence and place of business of person or persons making
the tender and each page of tender document including drawings, shall
be signed by the tenderer with his full dated signature.
The tender by partnership firm shall furnish the full names of all the
partners in the forwarding letter. The letter shall be signed by the
partner or by an authorized representative followed by the name and
designation of the person signing.
- 33 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
An attested copy of the partnership deed shall be furnished. Tender by
company shall be signed with the legal name of company and signed
by the person authorized to sign in the matter.
Whenever whether in the submission of the tender or later, in other
matters the signatures are made by one person on behalf of the
company the tenderer shall supply an attested copy of the power of
attorney.
Witnesses shall be persons of status and probity and their names,
occupations and addresses shall be stated below their signatures. All
signatures shall be dated.
The tender is also liable to be rejected outright if while submitting
i) The tenderer proposes any alternation in the work specified in the
tender or in the time allowed for carrying out the work, in any other
conditions.
ii) Any of the pages of tender are removed and / or replaced.
iii) The percentages are not entered in ink, in figures and in works by the
tenderer in B-1 form
iv) Any erasures are made by the tenderer in the tender.
v) All corrections and additions or pasted slips are not signed by the
tenderer.
vi) Tender in the case of firm, each partner on the person holding the
power of attorney authoring him to do so thereof does not sign or the
signature is not attested by a witness in B-1 tender form at the space
provided for the purpose.
14) ACCEPTANCE OF TENDER : Acceptance of tender will rest with
the authority, as indicated in Annex. A1 of these sections, who reserves
the right to reject any or all tenders without assigning any reasons. The
acceptance tender may be intimated to the contractor by letter. Such
intimation shall be deemed to b an intimation of acceptance of tender.
The tenderer whose tender is accepted will have to complete the
- 34 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
contract form within 15 days of being notified to do so and shall abide
by all the rules and regulations are special conditions enumerated
therein or attached herewith. In the event of failure of the tenderer to
sign the agreement within the stipulated time, the earnest money
including additional earnest money if any, paid by him shall be liable
to be forfeited to corporation and the acceptance of the tender shall be
liable to be considered as withdrawn. In that event the work will be
awarded to next or any other contractor as corporation may decide.
15) VALIDITY FOR 120 DAYS : The offer shall remain valid for a
period of 120 (One Hundred Twenty) days from the date of the
opening of tender, and thereafter until it is withdrawn by notice in
writing by the tenderer, duly addressed to the authority as stated at
Sr.No. 2.10 of annex ―A‖ of the section, and sent by RPAD. If the
acceptance of tender is not communicated within 120 days and if the
offer is withdrawn by the contractor as aforesaid, earnest money paid
in cash shall be refund in full.
16) COMPLETION OF TENDER DOCUMENT : While completing
tender documents the contractor must invariably complete appendices
include in the tender documents giving correct information. However
this information shall have to be submitted the contractor in the
prescribed format separately in Envelope No.1 as per provision of
Paragraph 7 of the detailed tender notice.
17) LANGUAGE : The language of all correspondence regarding this
work shall be English only.
18) LICENSE UDNER CONTRACT LABOUR (REGULATION AND
ABOLITION) ACT 1970
18.1 The successful tenderer should produce to the satisfaction of the
competent authority acceptance the tender a valid and current license
issued in his favour under the provision of contract labour (Regulation
and Abolition) Act, 1970 and the Maharashtra Contract Labour (R &A)
- 35 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Rules 1971, before signing the contract. On failure to do so acceptance
of the tenderer will be withdrawn and also the Earnest money and
additional earnest money deposit, if any. Will be forfeited to
corporation. The contractor shall submit the certified copy of
registration certificate under ESIS and PF Act before payment of First
R.A. Bill is made.
- 36 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
ANNEX - A (SECTION - I)
DETAILED TENDER NOTICE INFORMATION AND INSTRUCTIONS
A) DESCRIPTION OF THE
PROJECT
:- To divert water from West Flowing
Rivers to Godavari basin. It is decided
to construct storage Dams in Tal-
Surgana, Peth, Dindori Dist-Nashik
for this work Survey, Investigations &
Preparation of detailed project report
are to be carried by the contractor
Agency. The scheme was sanctioned
respectively by (1) Govt. Resolution
AA 2012/552(205/2012)WRD
Mantralaya Mumbai dt.18/9/2012 &
(2) Govt. vide Resolution AA 2012
/551/ (204/2012)WRD Mantralaya
Mumbai dt.19/1/2013
B) STATUS OF PROJECT :- This scheme is initially Preliminary
surveyed. The planning and designing
are to be taken up by Detailed survey.
This includes Designing, Digital
mapping, Fixing capacity of dam,
Fixing Preliminary Alignment of
tunnels & open channels etc.
C) CLIMATIC CONDITIONS :- 1) RAINFALL :
The rain mainly confined in
the month of June to
September, Annual rainfall
near site is 2000 to 2500.mm.
2) TEMPERATURE :
The average temperature
varies from minimum 6 to 70C.
In December and maximum
420C in May.
- 37 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
D) SCOPE OF THE WORK :- This works consists of carrying out detail
survey, investigation & Preparation of
detailed project report Investigation required
for preparing a workable layout of the project
for diversion of water from West Flowing
Rivers into Godavari basin. The work under
this tender consists of carrying out detail
survey and investigation for Submergence
area Survey as a single work. Survey of
Tunnel Alignment and Design Taking Deep
Bores for Design of Tunnels, Survey and
Design of dams / diversion weirs. For
preparing contour Maps, showing survey
details on village maps etc. The most
important part of the job is preparation of
satellite imagery of the entire area having
65cm x 65 cm., resolution and preparing
Radio metrically and Geometrically corrected
stereo images.
The above said proposals can be used
for preparation of Details Project
Report (DPR) subsequently.
E) INFORMATION ABOUT WORK SITE :-
The information on following points is given is this Annex
1) Location of work :- 1) 70 km. from District place
2) 30 Km. from Taluka place.
2) Nearest Airport :- Mumbai (Maharashtra) 255 km.
3) Nearest Railway Station :- 85.00 Km. Nashik Road
4) Road :- Approachable by all the weather
road from Nashik to Dindori,
Peth, Surgana.
5) Telephone and Telegrame :- 1) Peth 2) Surgana 3) Dindori
6) Petrol and Diesel Pump :- 1) Peth 2) Surgana 3) Dindori
7) Land Acquisition :- Not required
- 38 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
1. Details of work :- Detailed Survey, Investigation&
Preparation of D.P.R. for Lift
Diversion Scheme No. 3 & 4 on
West Flowing Rivers to be Diverted
into Godavari Basin, Dist.Nashik.
1.1 Name of work :- Detailed Survey, Investigation &
Preparation of D.P.R. for Lift
Diversion Scheme No. 3 & 4 on
West Flowing Rivers to be Diverted
into Godavari Basin, Dist.Nashik.
1.2 Estimated Cost :- Rs. 7,68,97,449/-
1.3 Earnest Money (EMD) :- Rs. 3,00,000/- by D.D.
& irrevocable B.G. is Rs.
4,69,000/- of any Nationalised
Bank or Scheduled Bank.
1.4 Security Deposit Rs. 38,45,000/-
i) Initial 2.5 % :- Rs. 6,00,000/- by D.D. &
irrevocable B.G. is Rs.
13,22,500/- of any Nationalised
Bank or Scheduled Bank.
ii) Through R.A. Bills 2.5% :- Rs. 19,22,500/-
1.5 Class of Contractor :- Class-I (C) & Above (The bidder should
be a Registered contractor with Public
Works Department (Govt. of
Maharashtra) and must be registered
with Godawari Marathwada Irrigation
Development corporation, Aurangabad) 1.6 Period of Completion of work :- 24 Calender Months including
monsoon period.
2 Information for obtaining Tender Papers and its submission 2.1 Name and address of the :- Executive Engineer,
Executive Engineer-in-charge Minor Irrigation Division,
of work issuing tender papers Nashik
/ prequalification document
and in whose name Earnest
Money and Security Deposit
is to be pledged.
2.2 Period for Download :- 13/09/2013 to 19/09/2013
Forms for prequalification upto 17:30 hrs.
Documents.
- 39 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
2.3 Cost of application forms for :- Rs. 5,000/-
Prequalification document.
2.4 Time and date of submission of :- 27/09/2013 upto 12:00 hrs.
Prequalification document.
2.5 Name and address of the Officer :- Superintending Engineer &
Receiving pre-qualification Administrator, Command Area
document. Development Authority,
Ahmednagar
2.6 Period of issue of blank tender forms :- 29/11/2013 to 6/12/2013
upto 17:00 hrs.
2.7 Cost of Blank Tender Forms :- Rs. 15,000/-
2.8 Time and date of submission :- 13/12/2013– 17:46 hrs.
of Tender to 19/12/2013 upto 17:00 hrs.
2.9 Name and address of the :- Superintending Engineer & Administrator
Receiving and opening Command Area Development Authority,
the tender Documents. Ahmednagar.
2.10 Name and address of the officer:- Superintending Engineer & Administrator
opening the tender Documents Command Area Development Authority,
Ahmednagar.
2.11 Time and Date of opening of :- 19/12/2013 from 17:01 to
tender 27/12/2013 at 18:00 hrs. if possible
2.12 The name of the authority for :- Chief Engineer,
Accepting the tender. Water Resources Department,
North Maharashtra Region, Nashik.
3 WORK AND SITE CONDITIONS :
3.1 Location :- 1) 70 km. from District place.
2) 30 Km. from Taluka place.
3.2 Nearest Railway Station :- 85.00 Km. Nashik Road
3.3 Nearest Airport :- Mumbai (Maharashtra) 255 km.
3.4 Roads :- Approachable by all the weather road
from Nashik to Dindori, Peth,
Surgana.
- 40 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
3.5 Nearest Telephone and Telegraph :- 1) Peth 2) Surgana 3) Dindori
Facility.
3.6 Nearest Petrol and Diesel Pump. :- 1) Peth 2) Surgana 3) Dindori
3.7 Position of land acquisition :- Not required.
4. PERIOD OF COMPLETION AND CONSTRUCTION
PROGRAMME:
4.1 Period of Completion :- 24 Calendar months including
monsoon period.
4.2 Survey programme of major item to be surveyed :-
Description of Item - -
1)
2)
3)
Survey and investigation of dams
Survey and investigation of tunnels/ Canals
Taking deep bores
Design of Dam and weirs
19 nos
24km/19km
3135rmt
19 nos
Nos.
Km
Rmt
Nos.
Nos.
Km
Rmt
Nos.
Preparation of Water Availability Certificate
Preparation of DPR -
19 dams dams dams
Note : After Detailed and Final Survey and preparing DPR of LD
Scheme no 3 & 4 above mention quantities may change.
4.2(a) This is the work in tribal area. The work mainly required to completed
is Survey and Investigation for Lift Diversion Scheme No. 3 and 4
on west flowing rivers to be diverted into Godawari basin.
Progress on above item is the intermediate period shall be linear
proportionate per month.
B) FOR WORKS COSTING MORE THAN RS. 100 LAKHS.
THE CONSTRUCTION PROGRAMME IS ENCLOSED AT THE END OF
SCHEDULE 'B' OF TENDER DOCUMENT BASED ON WHICH THE
PHYSICAL PROGRAMME IS PREPARED IF THE TENDERER DOES NOT
AGREE WITH THIS PROGRAMME, HE SHALL SUBMIT HIS OWN
PROGRAMME WITHOUT CHANGING TOTAL PERIOD OF TENDER
ALONGWITH TENDER DOCUMENTS INCLUSIVE OF THE PHYSICAL
PROGRAMME, SUBJECT TO THE PROVISION THAT 50% OF THE WORK
SHALL BE COMPLETED IN 50% OF THE CONTRACT PERIOD.
- 41 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
5.0 Updated estimated cost of the
work based upon Schedule of
Rates for the year 2011-2012
when tenders were invited
(Clause 38 of Section IV (1)
conditions of Contract)
Rs. 7,68,97,449/-
6.0 Earnest Money / Security Deposit
(para 8 (i) and (ii) of Detailed Tender Notice)
6.1 E.M.D. : Rs. 3,00,000/- by D.D. &
irrevocable B.G. is Rs. 4,69,000/-
of any Nationalised Bank or
Scheduled Bank.
6.2 Security Deposit (5%) : Rs. 38,45,000/-
6.2.1 Initial (2.5%) : Rs. 19,22,500/-
i) Rs. 6,00,000/- by D.D.
ii) Irrevocable B.G.
Rs. 13,22,500/- by Nationalised
Bank or Scheduled Bank.
6.2.2 From R.A.Bill : Rs. 19,22,500/-
6.3 If EMD/Secutity Deposit is in the form
of Demand Draft, it should be drawn
on
: Any Scheduled/Nationalised Bank
Branch situated in State of
Maharashtra and payable at Nashik.
6.4 Name of Executive Engineer-in-charge
of the work in whose name Demand
Draft is to be drawn
: Executive Engineer,
Minor Irrigation Division,
Nashik.
Govt. of Maharashtra PWD No. CAT/06/04/148 Build-2 Mum.-2 date 16/5/05
Sr.
No.
Component Center/Place Percentage
1 Labour Component (K1) Nashik 64%
2 Material Component (K2) Nashik 29%
3 POL Component (K3) Nashik 7%
4 Bitumen component Actual --
5 HYSD & Mid Steel Component Actual --
6 Cement Component Actual --
7 C.I. & D.I. Pipe Component Actual --
Total … 100%
- 42 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
7.A Cost of Cement of Mix Variation
1) If the Cement is procured by the
contractor
(To be filled in by contractor for works
costing more than Rs. 100 Lakhs.)
Rs. /Bags
2) If the cement is supplied on Schedule 'A'
(To be filled in by Dept. for works costing
less than Rs. 100 Lakhs.)
Not
Applicable
- 43 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Godawari Marathwada Irrigation Development Corporation,
Aurangabad
CERTIFICATE – A (Note All the details must be filled in strike out the item which is not
applicable to the tender)
Place :
Date :
Certified that,
1. I / (we) have not been awarded any contract for the construction of
Earth work/lining/structure, on canals including Main, Branch, Distributory,
Minor, Sub-Minor/Distribution System – Disnet items under the
Superintending Engineer --------------------------------- as on ---------- (Date of
opening of the subject tender).
2. I / (we) have been awarded the following contract (s) for the work of
construction of Earth work/lining/structure, on canals including Main,
Branch, Distributory, Minor, Sub-Minor/Distribution System – Disnet items
under the Superintending Engineer --------------------------------- as on ----------
(Date of opening of the subject tender).
Name of work :
Estimated cost put to tender :
Contract No. and date of work order :
Amount of work executed to date :
Name of Division :
Name of Circle :
3. I / (we) have tendered for the following contract (s) for the work of
construction of Earth work/lining/structure, on canals including Main,
Branch, Distributory, Minor, Sub-Minor/Distribution System – Disnet items
under the Superintending Engineer --------------------------------- as on ----------
(Date of opening of the subject tender) and my offer is the lowest responsive
offer.
Name of work :
Estimated cost put to tender :
Contract No. and date of work order :
Amount of work executed to date :
Name of Division :
Name of Circle :
Signature of the Contractor
- 44 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Godawari Marathwada Irrigation Development Corporation,
Aurangabad
UNDERTAKING
I / We have allotted the work of ------------------------------------------------ vide
agreement bearing No. ----------------------------. The stipulated date of
completion of this work as per agreement was ---------------------------------
which was subsequently extended upto ----------------------------. However, the
work is still in an in complete stage.
I / We desire to complete this work for which I / We need extension of time
limit upto --------------------------------------------------.
I / We am/are aware of the present financial problems of the Corporation and
in knowledge of the fact that timely payment towards the work executed by
Me/Us are not possible I/We however desire to complete the above work by
mobilizing our own financial resources.
Not with standing anything contained in the tender documents of this work I /
We hereby undertake as follows.
i) I / We not claims for any compensation for delayed
payments of delay in execution of this work for any reason
whatsoever, executed by me/us in past as well as the work
that will be executed in future.
ii) It will be my/our responsibility to get information about
availability of funds with the corporation for the above work
allotted to me as and accordingly arrange for the labourers,
construction materials and finance.
iii) This undertaking will be part and parcel of the B-1
agreement bearing No.
Signature of the Contractor
(with stamp/seal in case of company)
- 45 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
SECTION – II
B-1 TENDER FORM
SCHEDULE „A‟
SCHEDULE „B‟
- 46 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
B – 1 TENDER FORM
PERCENTAGE RATE TENDER & CONTRACT FOR WORKS
REGION : North Maharashtra Region, Nasik
CIRCLE : Command Area Development Authority, Ahmednagar
DIVISION : Minor Irrigation Division, Nashik
General Rules and Directions for the Guidance of Contractors
1. All works proposed to be executed by contract shall be notified in a
form of invitation to tender pasted on a board hung up in the office
of the Executive Engineer and signed by the Executive Engineer.
form will state the work to be carried out as well as the data for
submitting and opening tenders and the time allowed for carrying
out the work, also the amount of the earnest money and additional
earnest money if required to be deposited with the tender, and the
amount of the security deposit and additional security deposit if
required to be deposited by the successful tenderer and the
percentage if any, to be deducted from bills. Copies of the
specification, designs and drawings estimated rates; scheduled rates
and any other documents required in connection with the work shall
be signed by the Executive Engineer for the purpose of
identification and shall also be open for inspection by contractors at
the office of the Executive Engineer during office hours. Where the
works are proposed to be executed according to the specifications
recommended by a contractor and approved by a competent
authority on behalf of the Corporation such specifications with
designs and drawing shall form part of the accepted tender.
2. In the event of the tender being submitted by a firm, it must be
signed by each partner thereof and in the event of the absence of
any partner, it shall be signed on his behalf by a person holding a
power of attorney authorizing him to do so.
i. The Contractor shall pay along with the tender the sum as stipulated
in Annex ‗A‘ of Section I as and by way of earnest money. The
contractor may pay the said amount by forwarding along with the
tender, Corporation cash receipt or demand draft drawn on bank in
favour of the Executive Engineer as indicated in Annex ‗A‘ of
Detailed Tender Notice.
ii. The contractor shall also enclosed irrevocable bank guarantee of
sum stipulated in Annex ‗A‘ Sr.No. 1.3.1 if his offer is less than
10% of updated estimated cost of stated at Sr.No. 5 Annex ‗A‘. The
- 47 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
said amount of earnest money shall not carry any interest
whatsoever.
iii. If, after submitting the tender, the contractor withdraws his offer, or
modifies the same or if after acceptance of his tender the contractor
fails or neglects to furnish the balance of security deposit without
prejudice to any other rights and powers of the Corporation here
under of in law, Corporation shall be entitled to forfeit the full
amount of the earnest money and the additional earnest money
deposited by him.
iv. In the event of his tender not being accepted, the amount of earnest
money deposited by the contractor shall, unless it is prior there to
forfeited under the provision of Sub-clause (iii) above, be refunded
to him on his passing receipt therefore.
v. In the event of the tender being submitted by a firm, it must be
signed by each partner thereof and in the event of the absence of
any partner, it shall be signed on his behalf by a person holding a
power of attorney authorizing him to do so.
3. Receipt for payment made on account of any work, when executed
by a firm, should also be signed by all the partners excepts where
the contractor are described in their tender as firm, in which case
the receipt shall be signed in the name of the firm by one of the
partners or by some other person having authority to give effectual
receipts of the firm.
4. Any person who submits a tender shall fill up usual printed form
stating at what percentage above or below the rates specified in
schedule B (Memorandum showing items of work to be carried out)
he is willing to undertake the work. The person who submits the
tender shall also fill up printed form of Schedule ―B‖ Part-II
anticipated Additional items as foreseen by the tenderer wherein the
tenderer shall mentioned item wise quantity, rates and amount as
assessed by him. However the percentage above or below the rates
specified in Schedule ―B‖ (Memorandum showing items of works
to be carried out) he is willing to undertake the work, shall
applicable only for the items rates and quantities stipulated in
Schedule ―B‖ Part-1. Only one percentage on all estimated rates
shall be named. Tenderer who propose any alternation except in
connection with Schedule ―B‖ Pat-II. Anticipated Additional items
as foreseen by the tenderer in the works specified in the said form
of invitation to the tender, or in the item allowed or carried out the
work or which contain any other conditions of any sort other than
those specified in this tender documents will be liable to rejection.
No printed forms of tender shall include a tender for more than one
work but if contractor who to tender two or more works they shall
- 48 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
submit a separate tender for each. Tenders shall have the name and
number of the work to which they refer, written outside the
envelops.
5. The Officer indicated in Annex ―A‖ to Section-I – Detailed Tender
Notice or his duly authorized assistant shall open tender in the
presence of contractors who have submitted tenders or their
representatives who may be present at the time and he will enter the
amounts of the several tenders in the comparative statement in a
suitable form. In the event of tender being accepted, the contractor
shall for the purpose of identification, sign copies of the
specifications and other documents mentioned in Rule 1. In event
of tender being rejected the competent officer shall refund the
amount of the earnest money deposited by the contractor, in his
giving a receipt for the return of money.
6. The Officer competent to dispose of the tenders shall have the right
of rejecting all or any of the tenders.
7. No receipt for any payment alleged to have been made by a
contractor in regard to any matter relating to this tender or the
contract shall be valid and binding on Corporation unless it is
signed by the Executive Engineer.
8. No materials of any type required for the work (costing more than
Rs.100 Lakhs) shall be supplied by the Corporation. All the work
shall be executed by the tenderer with contractors own material(s).
The memorandum of work to be tendered for shall be filled in and
completed by the office of the Executive Engineer before the tender
form is issued. If a form issued to an intending tenderer has not
been so filled in and completed he shall request the said office to
have this done before he completes and delivers his tender.
9. All work shall be measured net by standard measure and according
to the rules and customs of the Corporation and without reference
to any local custom.
10. Under no circumstances shall any contractor be entitled to claim
enhanced rates for items in this contract.
11. Every registered contractors should produce along with his tender
certificate of registration as approved contractor in the appropriate
class and renewal of such registration with the date of expiry.
12. All corrections, additions or pasted slips should be initialed.
13. The measurements of work shall be taken according to the usual
methods in use in the Corporation and no proposals to adopt
alternative methods will be accepted.
The Executive Engineer‘s decision as to what is the usual method
in use in the Corporation will be final.
14. The tendering contractor shall furnish a declaration along with the
tender showing all works for which he has already entered into
- 49 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
contract, and value of work that remains to be executed in each case
on the date of submitting the tender.
15. Every tenderer shall submit along with the tender information
regarding the Income Tax the reference to the number of the
assessment year and a valid Income Tax clearance certificate.
16. In view of the difficult position regarding the availability of foreign
exchange no foreign exchange would be released by the
Corporation for the purchase of plant and machinery required for
the execution of the work contracted for.
(GCB/PWD/CFM/1058/196/62517, Dated 26-9-1959)
17. The contractor will have to construct shed for storing controlled
and valuable materials at work site, having double looking
arrangement. The materials will be taken for used in the presence of
the Corporation person. No materials will be allowed to be removed
from the site of works, without prior permission of Engineer-in-
charge.
18. The contractor shall also give the list of machinery in their
possession which they propose to use on the work.
- 50 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
B – 1 TENDER FORM
PERCENTAGE RATE TENDER & CONTRACT FOR WORKS
Tender for works
1. I/We hereby tender for the execution, for the Godawari Marathwada
Irrigation Development Corporation (here-in-before and here-in-after
referred to as ―Corporation‖) of the work specified in memorandum as
enclosed within the time specified in such memorandum at *…………% (in
word …………… …….…………………………) percentage below/above
the estimated rates entered in Schedule ―B‖ Part-I and AT PAR with the
rates entered in Schedule ―B‖ Part-II (memorandum showing items of work
to be carried out) and in accordance in all respects with the specifications,
designs drawings and instructions in writing referred to in Rule 1 hereof.
2. I/We agree that the offer shall remain open for acceptance for a minimum
period of 120 days from the date fixed for opening the same & thereafter
until it is withdrawn by me/us by notice in writing duly addressed to the
authority opening the tenders and sent by registered post AD or otherwise
delivered at the office of such authority Demand Draft on …………. At
Scheduled Bank or Cash Challan of Corporation/Bank of Baroda in respect
to the sum of Rs. -------------/- in words Rupees ----------------------------------
------------------------------------------ Only representing the earnest money is
herewith forwarded. Additional earnest money in the form of Bank
Guarantee as required in view of offer being lower than 10% below the
updated estimated cost as stated at Sr.No. 5 of Annex ―A‖ is also enclosed.
The amount of earnest money shall not bear interest and shall be liable to the
forfeited to the Corporation should I/We fail to (i) abide by the stipulation to
keep the offer open for the period mentioned above or (2) sign and complete
the contract documents as required by the Engineer and furnish the security
deposit and additional security deposit if any as specified in item (e) and (f)
of the memorandum enclosed within the time limit laid down in clause (1) of
Condition of contract. The amount of earnest money may be adjusted
towards the security deposit or refunded to me/us if so desired by me/us in
writing, unless the same or any part thereof has been forfeited as foresaid.
3. Should this tender be accepted I/We hereby agree to abide by and fulfill all
the terms and provisions of the Conditions of Contract and Special
Conditions of Contract included in this booklet so far as applicable and in
default thereof to forfeit and pay to Corporation the sum of money
mentioned in the said conditions.
* in Figures as well as in words
* Amount to be specified in words and in figures
- 51 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
MEMORANDUM
a) General description Detailed Survey & Investigation for Lift
Diversion Scheme No. 3 & 4 on West
Flowing Rivers to be Diverted into
Godavari Basin, Dist.Nashik.
b) Estimated cost Rs. 7,68,97,449/-
c) Earnest money (EM) Rs. 7,69,000/- In the form of D.D.
d) Additional EMD (if required as
specified in para 9 (i)(b) in the
form of Bank Guarantee
i) Rs. 3,00,000/- by D.D.
ii) Rs. 4,69,000/- of any Nationalised
Bank or Scheduled Bank.
e) Security Deposit (S.D.) Rs. 38,45,000/-
i) Initial (2.5%) Rs. 19,22,500/-
ii) to be deducted from bills
(2.5%) @ rate of 5%
Rs. 19,22,500/-
Total Rs. 38,45,000/- 5% Percent.
f) Additional SD (if required as
specified in para 9(ii)(b) in the
form of Bank Guarantee
Rs. ---
Total Rs. ---
g) Percentage, if any, to be
deducted from bills so as to
make up the total amount
required as security deposit by
the time, half the work as
measured by the cost is done.
h) Time allowed for the work
from date of written order to
commence
24 (Twenty Four) Calendar months (including monsoon period)
Signature of Contractor Signature of witness
Address ----------------------------------
--------------------------------------------
--------------
Dated the --------------- day of --------
------
Address -------------------------------------------
-----------------------------------------------------
Occupation
The above tender is hereby accepted by me for and on behalf of the Corporation
Dated day of 2013 Signature of the officer by whom accepted
To be filled by tenderer.
- 52 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
SCHEDULE „A‟
- 53 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
SCHEDULE „A‟
APPLICABLE FOR WORKS COSTING LESS THAN 50 LAKHS
Name of work :- Detailed Survey & Investigation for Lift Diversion
Scheme No. 3 & 4 on West Flowing Rivers to be
Diverted into Godavari Basin, Dist.Nashik.
Schedule showing (approximately) the material to be supplied from the store
for the work contracted to be executed and the rates, which they are to be
charged for.
Sr.
No.
Particulars Qty. Rate at which the material
will be charged to the
contractor
Place of
delivery
Unit Rate
------------ NIL ----------
- 54 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
SCHEDULE „B‟
- 55 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
* SCHEDULE 'B' *
Detailed Survey & Investigation for Lift Diversion Scheme No. 3 & 4 on
West Flowing Rivers to be Diverted into Godavari Basin, Dist.Nashik.
Quantity
Particulars of Item
Estimate Rates
Unit
Amount In
Figures
In Words
Item No. 1 : Construction of
P.B.M.in C.C.1:2:4 of size
45x45 cm. and 75 cm. deep
fixing G.I.Pipe of 50 mm. dia at
centre as directed including
excavation, backfilling
trenches, curing etc. complete
with all leads & lifts as directed
by Engineer-in-charge.
Rs.One
Thousand Three
Hundred Sixty
Eight & Ps.
Forty Only.
40.00 1368.40 No. 54736.00
Item No. 2 : Carrying out
benchmark by double levelling
from GTS or any other bench
mark including submission of
field books, P.B.M. register etc.
as per direction of Engineer-in-
charge along with digitilised
data stored in compact disk.
Rs. Four
Thousand One
Hundred Thirty
Six & Ps. Sixty
Only.
46.29 4136.60 Km. 191484.00
Item No. 3 : Excavation for
Trial Pits/foundation including
removing the excavated
material with all leads & lifts.
beyond the working area &
stacking & spreading as
directed by Engineer-in-charge
with dewatering, preparing the
bed for the foundation &
necessary backfilling, ramming,
watering including shoring &
strutting etc. complete.
398.25 A) Soil & Soft Murum 108.90 Rs. One
Hundred Eight
& Ps. Ninety
Only.
Cum. 43369.43
Rs. One
Hundred
Twenty Four &
Ps. Thirty Only
238.95 B) Hard Murum 124.30 Cum. 29702.00
- 56 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Rs. Two
Hundred Forty
Eight & Ps.
Sixty Only
159.30 C) Soft Rock 248.60 Cum. 39601.98
Item No. 4 : Taking trial bores
for detailed investigation
75mm. boring including all
materials such as casing pipe &
accessories, grease & other
such materials as required
including conveying such
materials & machinery to the
site of work, Preserving the
loose samples in glass or plastic
jar/core samples serially
numbered at the site of work &
conveying the same to the head
quarter of the concerned office
as directed etc. complete as
directed by Engineer-in-charge.
A) In soil/soft murum/hard
murum/H.M. and
Overburden Dimond Drilling
machine
Rs. One
Thousand Five
Hundred Eighty
Four Only.
805.50 1584.00 Rmt 1275912.00
Rs.Two
Thousand Sixty
Eight Only.
1879.50 B) In soft rock Dimond Drilling
machine with Nx bit
2068.00 Rmt 3886806.00
2450.00 C) In hard rock Dimond
Drilling machine with Nx bit
Rs.Two
Thousand Nine
Hundred Four
Only.
2904.00 Rmt 7114800.00
Item No. 5 : Providing and
supplying jungle wood core box
including labour, shutter
fixtures locking arrangement of
100x45x10 cm. in size with 12
mm. (1/2‖) thick planks without
painting etc. complete with four
longitudinal compartments
with all leads & lifts as directed
by Engineer-in-charge.
505.00 1998.00 Rs. One
Thousand Nine
Hundred Ninety
Eight Only.
Per
No.
1008990.00
57.00 Item No. 6 : Providing Soil
sample of size 10 cm. dia. and
40.65cm. long, including
lowering, pressing the sample
with mechanical jack, erecting
275.00 Rs. Two
Hundred
Seventy Five
Only.
Per
No.
15675.00
- 57 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
platform, turning the sample,
sealing from the both ends,
lettering, painting etc. complete
with all leads & lifts as directed
by Engineer-in-charge.
Item No. 7 : Bringing the soil
samples from trial pits to the
Divisional laboratory including
loading, unloading, stacking &
including cost of empty cement
bags etc. complete as directed
by Engineer-in-charge.
1330.00 86.90 Rs. Eighty Six
& Ps. Ninety
Only.
Km 115577.00
Item No. 8 : Laboratory testing
of disturb/undisturbed samples
including payment of testing
fee by contractor including
attending laboratory, procuring
and submitting of soil testing
report to department in hard
copies as well as two sets of
CD in electronic form as
directed by Engineer-in-charge.
Rs. Thirty Three
Thousand Three
Hundred Fifty
Two Only.
57.00 Undisturbed Hearting 33352.00 Set of
Tests
1901064.00
Rs. Thirty Eight
Thousand Eight
Hundred Eight
Only.
57.00 Disturbed Hearting 38808.00 Set of
Tests
2212056.00
Rs. Forty Five
Thousand Nine
Hundred
Fourteen Only.
57.00 Disturbed Casing 45914.00 Set of
Tests
2617098.00
Item No. 9 : Preparing drawing
on Auto CAD with one proof
print for following size on
white paper with black &
coloured print providing tracing
with saving on disc of
following size per number as
directed by Engineer-in-charge.
Rs. One
Thousand Five
Hundred Eighty
Four Only.
105.00 A) Size A-0 1584.00 No 166320.00
- 58 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
210.00 B) Size A-1 1188.00 Rs. One
Thousand One
Hundred Eighty
Eight Only.
No 249480.00
Rs. Nine
Hundred Ninety
Only.
105.00 C) Size A-2 990.00 No 103950.00
Rs. Five
Hundred Ninety
Four Only.
105.00 D) Size A-3 594.00 No 62370.00
Rs. Three
Hundred
Seventy Four
Only.
175.00 E) Size A-4 374.00 No 65450.00
Item No. 10 : Printing of
drawing on Auto CAD in
following size on white paper
with tracing on reproducing
paper from available source per
number as directed by
Engineer-in-charge.
Rs. Four
Hundred
Twelve & Ps.
Fifty Only.
105.00 A) Size A-0 412.50 No 43312.50
Rs. Three
Hundred Thirty
Only.
210.00 B) Size A-1 330.00 No 69300.00
Rs. Two
Hundred Ninety
One & Ps. Fifty
Only.
105.00 C) Size A-2 291.50 No 30607.50
Rs. Two
Hundred Forty
Seven & Ps.
Fifty Only.
105.00 D) Size A-3 247.50 No 25987.50
175.00 E) Size A-4 165.00 Rs. One
Hundred Sixty
Five Only.
No 28875.00
Item No. 11 : Editing &
correction on drawing & giving
the prints on tracing paper with
tracing per number as directed
by Engineer-in-charge.
Rs. Three
Hundred Ninety
Six Only.
52.50 A) Size A-0 396.00 No 20790.00
- 59 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Rs. Three
Hundred Thirty
Only.
105.00 B) Size A-1 330.00 No 34650.00
Rs. Two
Hundred Ninety
Seven Only.
52.50 C) Size A-2 297.00 No 15593.00
Rs. Two
Hundred Fifty
Eight & Ps.
Fifty Only.
52.50 D) Size A-3 258.50 No 13572.00
Rs. One
Hundred Eighty
Seven Only.
87.50 E) Size A-4 187.00 No 16362.50
3790.82 Item No. 12 : Carrying out grid
survey at 15m. x 15m. for
submergence of Dam, Tunnel
alignment, rising mains, river
survey, dam alignment etc.
including ranging, chaining,
pegging, taking bearing,
distance and levels for
preparing contour plan at 0.20
m. interval and submission of
original field books to
Department etc. complete along
with digitised data stored in
compact disk including
marking of electrical poles,
structure, village & forest
boundaries, roads, huts in the
submergence area with advance
survey instrument including
clearing site etc. complete as
directed by Engineer-in-charge.
5243.00 Rs.Five
Thousand Two
Hundred Forty
Three Only.
Hect 19875270.00
Cost of work portion
Dam
900625600.00
Item No. 13 : Fixing the
capacity of dam with analysis
of drain area including
consideration of existing and
proposed dams in catchments
area, rainfall pattern, working
out runoff at site. Fixing of
various controlling levels &
calculating draw down levels &
finding of approximate cross
section of earthen dam,
1.00% One Percentage
Amount of Cost
of Dams (Work
Portion Only)
9006256.00
- 60 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
overflow & non-overflow
sections of dam including sub
drainage system, rock toe
details, calculations of stability
of masonry dam etc. complete
as directed by Engineer-in-
charge.
Cost of Tunnel/canal
work portion
1876150000.00
Item No. 14 : Fixing
preliminary alignment of
tunnels/Canal as per the contour
mapping in the GIS
environment so as to
accomplish the flow of water
through the Tunnel/canal by
gravity flow only. The
alignment shall be marked on
the GIS base map of the project
including preliminary design of
section of tunnel including
alternative alignments etc.as
directed by Engineer-in-charge.
1.00% One Percentage
Amount of Cost
of Tunnel/canal
work (On Work
Portion Only)
18761500.00
259123000.00 Item No. 15 : Design and
estimation of lift diversion
scheme, preparation of broad
conceptual report, general
layout of pump house, rising
main, delivery chamber, design
and analysis of frame of pump
house, design of pumping
machinery, control room,
service bay etc. Design of
delivery chamber details of
rising main, thrust block,
anchor block, expansion joint,
manifold details etc. complete
as directed by Engineer-in-
charge.
1.00% One Percentage
Amount of Cost
of Dams (On
Work Portion
Only)
2591230.00
2.00
Item No. 16 : Preparation of
work of detailed project report
for getting administrative
approval comprising of the
layout, design and estimation of
dam and water conducting
systems such as Tunnels
Canals, rising mains and
presenting the details of the Lift
2604870 Rs. Twenty Six
Lakh Four
Thousand Eight
Hundred
Seventy Only.
No. 5209740.00
- 61 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Note :
(1) Service Tax :- Service tax will be paid to the contractor prevailing at
the time of payment of each R.A. Bill after submission of complete
proof of payment of service tax by the contractor. The present rate of
service tax is 12.36% of the Gross Amount of the R.A.Bill.
(2) Labour Cess paid by the contractor will be reimbursed to the contractor
after production of proof of payment to the concerned department.
Diversion Scheme on the basis
of the study of available
toposheets and according to
surveyed data etc. complete as
directed by Engineer-in-charge.
Total Rs. 76897449.00
- 62 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Schedule “B”
Applicable Specifications
Sr.No. Description of Item Ref. of Specifications
1 Construction of P.B.M.in C.C.1:2:4 of size 45x45 cm. and
75 cm. deep fixing G.I.Pipe of 50 mm. dia at centre as
directed including excavation, backfilling trenches, curing
etc. complete with all leads & lifts as directed by
Engineer-in-charge.
This Volume Page
2 Carrying out benchmark by double levelling from GTS or
any other bench mark including submission of field books,
P.B.M. register etc. as per direction of Engineer-in-charge
along with digitilised data stored in compact disk.
This Volume Page
3 Excavation for foundation including removing the
excavated material with all leads & lifts. beyond the
working area & stacking & spreading as directed by
Engineer-in-charge with dewatering, preparing the bed for
the foundation & necessary backfilling, ramming, watering
including shoring & strutting etc. complete.
This Volume Page
A) Soil & Soft Murum
B) Hard Murum
C) Soft Rock
4 Taking trial bores for detailed investigation 75mm. boring
including all materials such as casing pipe & accessories,
grease & other such materials as required including
conveying such materials & machinery to the site of work,
preventing the loose samples in glass or plastic jar/core
samples serially numbered at the site of work & conveying
the same to the head quarter of the concerned office as
directed etc. complete as directed by Engineer-in-charge.
This Volume Page
A) In soil/soft murum/hard murum/H.M. and
B) overburden Dimond Drilling machine
B) In soft rock Dimond Drilling machine with Nx bit
B) In hard rock Dimond Drilling machine with Nx bit
5 Providing and supplying jungle wood core box including
labour, shutter fixtures locking arrangement of 100x45x10
cm. in size with 12 mm. (1/2‖) thick planks without
painting etc. complete with four longitudinal
compartments with all leads & lifts as directed by
Engineer-in-charge.
This Volume Page
6 Providing Soil sample of size 10 cm. dia. and 40.65cm.
long, including lowering, pressing the sample with
mechanical jack, erecting platform, turning the sample,
sealing from the both ends, lettering, painting etc.
complete with all leads & lifts as directed by Engineer-in-
charge.
This Volume Page
- 63 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
7 Bringing the soil samples from trial pits to the Divisional
laboratory including loading, unloading, stacking &
including cost of empty cement bags etc. complete as
directed by Engineer-in-charge.
This Volume Page
8 Laboratory testing of disturb/undisturbed samples
including payment of testing fee by contractor including
attending laboratory, procuring and submitting of soil
testing report to department in hard copies as well as two
sets of CD in electronic form as directed by Engineer-in-
charge.
This Volume Page
Undisturbed Hearting
Disturbed Hearting
Disturbed Casing
9 Preparing drawing on Auto CAD with one proof print for
following size on white paper with black & coloured print
providing tracing with saving on disc of following size per
number as directed by Engineer-in-charge.
This Volume Page
A) Size A-0
B) Size A-1
C) Size A-2
D) Size A-3
E) Size A-4
10 Printing of drawing on Auto CAD in following size on
white paper with tracing on reproducing paper from
available source per number as directed by Engineer-in-
charge.
This Volume Page
A) Size A-0
B) Size A-1
C) Size A-2
D) Size A-3
E) Size A-4
11 Editing & correction on drawing & giving the prints on
tracing paper with tracing per number as directed by
Engineer-in-charge.
This Volume Page
A) Size A-0
B) Size A-1
C) Size A-2
D) Size A-3
E) Size A-4
- 64 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
12 Carrying out grid survey at 15m. x 15m. for submergence
of Dam, Tunnel alignment, rising mains, river survey, dam
alignment etc. including ranging, chaining, pegging, taking
bearing, distance and levels for preparing contour plan at
0.20 m. interval and submission of original field books to
Department etc. complete along with digited data stored in
compact disk including marking of electrical poles,
structure, village & forest boundaries, roads, huts in the
submergence area with advance survey instrument
including clearing site etc. complete as directed by
Engineer-in-charge.
This Volume Page
13 Fixing the capacity of dam with analysis of drain area
including consideration of existing and proposed dams in
catchments area, rainfall pattern, working out runoff at
site. Fixing of various controlling levels & calculating
draw down levels & finding of approximate cross section
of earthen dam, overflow & non-overflow sections of dam
including sub drainage system, rock toe details,
calculations of stability of masonry dam etc. complete as
directed by Engineer-in-charge.
This Volume Page
14 Fixing preliminary alignment of tunnels/Canal as per the
contour mapping in the GIS environment so as to
accomplish the flow of water through the Tunnel/canal by
gravity flow only. The alignment shall be marked on the
GIS base map of the project including preliminary design
of section of tunnel including alternative alignments etc.as
directed by Engineer-in-charge.
This Volume Page
15 Design and estimation of lift diversion scheme, preparation
of broad conceptual report, general layout of pump house,
rising main, delivery chamber, design and analysis of
frame of pump house, design of pumping machinery,
control room, service bay etc. Design of delivery chamber
details of rising main, thrust block, anchor block,
expansion joint, manifold details etc. complete as directed
by Engineer-in-charge.
This Volume Page
16 Preparation of work of detailed project report for getting
administrative approval comprising of the layout, design
and estimation of dam and water conducting systems such
as Tunnels Canals, rising mains and presenting the details
of the Lift Diversion Scheme on the basis of the study of
available toposheets and according to surveyed data etc.
complete as directed by Engineer-in-charge.
This Volume Page
- 65 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
SECTION III
FORMS
(APPENDICES)
- 66 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
APPENDIX "A"
DETAILS OF TECHNICAL PERSONNEL WITH THE CONTRACTOR
Vide para 7 (V) of Detailed Tender Notice
Sr.
No.
Description Name Length of
service in
the firm
Qualification Professional
experience
and details
of work
carried out
Remarks.
1 2 3 4 5 6 7
1 Project
Manager
2 Works
Manager
(Civil Senior
Engineer)
3 Engineer
(Civil)
4 Supervisors
Note :- If there is no technical personnel with your firm please give details how can
your firm manage the same in remark column.
- 67 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
APPENDIX "B"
DETAILS OF PLANTS & MACHINERY IMMEDIATELY
AVAILABLE WITH THE TENDERER FOR USE ON THIS WORK
Vide para 7 (vi) of Detailed Tender Notice
Sr.
No.
Name of
equipment
No.of
units
Kind
of
Make
Capacity Age and
condition
Present
Location
Remarks.
1 2 3 4 5 6 7 8
- 68 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
APPENDIX "C"
DETAILS OF WORK OF SIMILAR TYPE AND MAGNITUDE CARRIED
OUT BY THE TENDER
Vide para 7 (vi) of Detailed Tender Notice
Sr. No. Name of work Place Tendered
Cost
Rs. In
lakhs
Time in
month
which
completed
Date of
completion
Principal
features
1 2 3 4 5 6 7
- 69 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
APPENDIX "D"
DETAILS OF WORKS TENDERER FOR AND IN HAND AS ON THE DATE OF
SUBMISSION OF TENDER
Vide para 7 (vi) of Detailed Tender Notice
Sr.
No.
Name of
Work
Place Work in Hand Works tendered for Remarks.
Tendered
cost
Rs.In
lakh
Cost of
remaining
work
Rs.In lakh
Anticipated
date of
completion
Estimated
cost
Rs.In lakh
Date by
which
decision
expected
Stipula
ted
date or
period
of
comple
tion
1 2 3 4 5 6 7 8 9 10
- 70 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
APPENDIX "E"
DETAILS OF PLANTS & MACHINERY PROPOSED TO BE USED FOR
WORK NOT IMMEDIATELY AVAILABLE
Vide para 7 (vi) of Detailed Tender Notice
Sr.
No.
Name of
equipment
No. of
units
Kind
and
make
Capacity If already owned If to be
purchased
When?
Month
and year
Remarks.
Age and
condition
Location Probable
date of
availability
1 2 3 4 5 6 7 8 9 10
- 71 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
APPENDIX "I"
STATEMENT SHOWING THE YEARLY TURNOVER IN TERMS WORK
DONE DURING LAST THREE YEARS.
Sr.No. Name of
Work
Value of Civil Engineering works
done during the year (excluding
advances if any) Rs. In Lakhs.
Total
Year
2010-11
Year
2011-12
Year
2012-2013
Note : Necessary Certificate in respect each work duly certified by Executive
Engineer are attached herewith.
- 72 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
APPENDIX „F‟
(Vide para 36 of Special Condition of Contract)
DECLARATION OF THE CONTRACTOR
1. I/We -------------------------------------------------- Contractor(s)
hereby undertake that I/We shall pay the labourer‘s engaged on the
work as indicated in Annexure ‗A‘ to Section I – Detailed Tender
Notice, wages as per minimum wages Act, 1984 and amendments
thereto applicable to the zone in which work lies and act
accordingly. I/We also undertake to abide by the various laws in
force and extend necessary facilities and amenities to the staff and
workers employed by me/us.
2. I/We hereby declare that I/We has made myself/ourselves
thoroughly conversant with the local conditions regarding all
materials and labour on which I/We have bided my/our rates for
this work. The specifications of this work have been carefully
studied and understood by me/us before submitting this tender.
- 73 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
APPENDIX „G‟
(Vide para 9 of Detailed Tender Notice)
MODEL FORM OF BANK GUARANTEE BOND
1. This deed of Guarantee is made on the --------------------------------------
by ------------------------ having his head office at -----------------
(hereinafter called the said Contractor(s) from the demand under the
terms and conditions of Agreement dated ----------------- made
between --------------------- and ------------------------ for ------------------
(hereinafter called the Agreement) of additional security deposit for
the due fulfillment by the said contractors of the terms and conditions
contained in the said Agreement on production of the Bank Guarantee
for Rs. ----------------- (Rs. ----------------------------------------------------
only). We -------------------------------------------- (hereinafter referred to
as ―the Bank‖) at the request of -------------------- (contractor) do
hereby undertake to pay to the Godawari Marathwada Irrigation
Development Corporation, hereinafter referred to as Corporation, an
amount not exceeding Rs. ---------------- against any loss or damage
caused to or suffered by the Corporation by reason of any breach by
the said contractor of any of the terms or conditions contained in the
said Agreement.
2. We ----------------------------- (indicate the name of bank) do hereby
undertake to pay the amount due and payable under this guarantee
without any demur, merely on a demand from the Corporation stating
that the amount claimed is due by way of loss or damage caused to or
would be caused to or suffered by the Corporation by reason of breach
by the said Contractor(s) of any of the terms of conditions contained in
the said Agreement or any reason of the contractor(s) failure to
perform the said agreement. Any such demand made on the bank shall
be conclusive as regards the amount due and payable under this
guarantee shall be restricted to an amount not exceeding Rs. ------------
3. We undertake to pay to the corporation any money so demanded not
withstanding any dispute or dispute raised by the Contractor(s) /
Supplier (s) in any suit or proceeding pending before any court or
tribunal relating thereto, our liability under this present being absolute
and unequivocal. The payment so made by us under this bond shall be
valid discharge of our liability for payment there under and the
- 74 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Contractor(s)/ Supplier (s) shall have no claim against us for making
such payment.
4. We ----------------------------------- (indicate the name of Bank) further
agree that the guarantee herein contained shall remain in full force and
effect during the period that would be taken for the performance of the
said Agreement and that it shall continue to be force able till all the
dues of the Corporation under or by virtue of the said Agreement have
been fully paid and its claims satisfied or discharged or till ------------
(office/Corporation) of ---------------------------------- (indicate the
name of Administrative Officer) certifies that terms and conditions of
the said Agreement have been fully and properly carried out by the
said Contractor(s) and accordingly discharges this guarantee. Unless a
demand of claim under this guarantee is made on us in writing on or
before the ---------------- we shall be discharged from all liability under
this guarantee thereafter.
5. We --------------------------------------- (indicate the name of Bank)
further agree with the corporation that the Corporation shall have the
fullest liberty without our consent and without affecting in any manner
our obligations hereunder to vary any of the terms and conditions of
the said Agreement or to extend time of performance by the said
Contractor from time to time or postpone for any time or from time to
time any of the powers exercisable by the corporation against the said
Contractor(s), and to for the of enforce any of the terms and conditions
relating to the said Agreement, and we shall not to be relieved from
our liability by reason of any such variation, or extension being
granted to the said Contractor(s) or for any forbearance, act or
commission on the part of the Corporation or any indulgence by the
Corporation to the said contractor or by any such matter of thing
whatsoever which under the law relating to surety would, but this
provision, have effect of so relieving us.
6. This guarantee will not be discharged due to the change in the
constitution of the Bank or the change in the constitution of the
Contractors/suppliers.
7. We ------------------------------------------- (indicate the name of Bank)
lastly under take not to revoke this guarantee during its currency
expect with the previous consent of the Corporation in writing.
Dated the --------------------------- day of --------------------------- 20
For ----------------------------
(indicate the name of Bank)
- 75 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
APPENDIX „H‟
(Vide para 1.14 of General Specification Section 1)
INDENTURE FOR SECURED ADVANCES
(For use in cases in which the contract is for finished work and the Contractor
has entered into an Agreement for the execution of certain specified quantity
of work in a given time)
THIS INDENTURE made the -------------- day of -------------------------
between-------------------------------------------------------- (hereinafter called
―the contractor‖ which expression shall where the context so admits or
implies be deemed to include his executors, administrators and assigns) of the
one part and The Godawari Marathwada Irrigation Development Corporation
(hereinafter called as the Corporation which expression shall where the
context so admits or implies be deemed to include his successors in office and
assigns) of the other part.
WHEREAS by an agreement dated ----------------- (hereinafter called
the said Agreement the Contractor has agreed.
AND WHEREAS the Contractor has applied to the Corporation that he
be allowed advances on the security of materials absolutely belonging to him
and brought by him to the site of the works, the subject of the said Agreement
for use in the construction of such of the works as he has undertaken to
execute at rates for the finished work (inclusive of the cost of material and
labour and other charges)
AND WHEREAS the Corporation has agreed to advance to the
Contractor the sum of Rupees ----------------------- (in words, Rupees -----------
----------------------) on the aforesaid security and has reserved to himself the
option of making any further advance or advances on security of aforesaid
nature, the quantities and other particulars of the materials on the security of
which the advance or advances are made being detailed in Part – II of the
running account bill for the said works, signed at the time being by the
Contractor on.
NOW THIS INDENTURE WITHNESS that in pursuance of the said
Agreement and in consideration of the sum of Rs. ------------------- on or
before the execution of these presents paid to the Contractor by the
Corporation (the receipt whereof the Contractor both hereby acknowledge)
and of such further advances (if any) as may be made to him as aforesaid, the
- 76 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
contractor does hereby convenient and agree with the Corporation and declare
as follows
1) That the said sum of Rs. ----------------- so advanced by the Corporation
to the Contractor as aforesaid shall be employed by the Contractor in
or towards expediting the execution of the said works and for non other
purpose whatsoever.
2) That the materials detailed in the said running account bill which have
been offered to and accepted by the Corporation as security are
absolutely the Contractor‘s own property and free from encumbrances
of any kind and the Contractor will not make any application for or
receive a further advance on the security of materials which are not
absolutely his own property, and free from encumbrances of any kind
and the Contractor indemnifies the Corporation against all claims to
any materials in respect of which an advance has been made to him as
aforesaid.
3) That the materials detailed in the said running account bill and all other
materials on the security of which any further advance or advances
may hereafter be made as aforesaid (hereinafter called ―the said
materials‖) shall be used by the Contractor solely in the execution of
the said works in accordance with the directions of the Divisional
Officer, Division (hereafter called ―The Divisional Officer‖) and in the
terms of the said Agreement.
4) That the Contractor shall make at his own cost all necessary and
adequate arrangement for the proper watch, safe custody and
protection against all risks of the said materials and that until used in
construction as aforesaid, the said materials shall remain at the site of
the said works in the Contractor custody and on his own responsibility
and shall at all times be open to inspection by the Divisional Officer or
any officer authorized by him. In the event of the said materials or any
part thereof being stolen, destroyed or damaged, the contractor will
forthwith replace the same with other materials of like quality or repair
and make good the same as required by the Divisional Officer.
- 77 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
5) That the said materials shall not on any account be removed from the
site of the said works except with the written permission of the
Divisional Officer or an officer authorized by him in that behalf.
6) That the advances shall be repayable in full when or before the
Contractor receives payment from the Corporation of the price payable
to him for the said works under the terms and provisions of the said
agreement, provided that if any intermediate payments are made to the
contractor on account of work done, then on occasion of each such
payment, the Corporation will be at liberty to make a recovery from the
Contractor‘s bill for such payment by deducting there from the value of
the said materials than actually used in the construction and in respect
of which recovery has not been made previously the value for this
purpose being determined in respect of each description of materials, at
the rates at which the amount of advances made under these presents
were calculated.
7) That if the Contractor shall at any time make any defaults in the
performance or observance of any of the terms and provisions of the
said agreement or of these presents, the total amounts of the advance or
advances that may still be owing to the Corporation Maharashtra shall
immediately on the happenings of such defaults be repayable by the
Contractor to the Corporation, together with interest thereon at twelve
percent per annum from the date of respective dates of such advance of
advances to the date of repayment and with all costs, charges, damages
and expenses incurred by the Corporation I or for the recovery thereof
or the enforcement of this security covenant‘s and agrees with
Corporation to repay and pay the same respectively to him according.
8) That the Contractor hereby charges all the said materials with the
repayment to the Corporation of the said sum of Rs. ----------------------
- and any further sum of sums advanced as aforesaid and all costs,
charges, damages and expenses payable under these presents
PROVIDED ALWAYS and it is hereby agreed and declared that
notwithstanding anything in the said Agreement and without prejudice
to the powers contained therein, if and whenever the covenant for
payment and Repayment hereinbefore contained shall become
enforceable and the money owing shall not be paid in accordance there
- 78 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
with, the Corporation may at any time thereafter adopt all or any of the
following courses, as he may deem best.
a) Seize and utilize the said materials or any part thereof in the
completion of the said works on behalf of the Contractor in
accordance with the provisions in that behalf contained in the said
agreement, debiting the Contractor with the actual cost of effecting
such completion and the amount due in respect of advances under
these present and crediting the contractor with the value of work
done, as if he had carried it out in accordance with the said agreement
and at the rates thereby provided. If the balance is against the
Contractor, he is to pay the same to the Corporation on demand.
b) Remove and self by public action the seized materials or any
part thereof and out of the money arising from the sale, retain all the
sums aforesaid repayable to the Corporation under these present and
pay over the Surplus if any to the Contractor.
c) Deduct all or any part of the money owing out of the security
deposits or any sum due to the Contractor under the said Agreement.
9) That except in the event of such default on the part of the Contractor as
aforesaid, interest on the said advance shall not be payable.
10) That in the event of any conflict between the provisions of these
present and the said Agreement, the provisions of these presents shall
prevail and in the event of any dispute or difference arising over the
construction or effect of these presents, the settlement of which has not
been hereinbefore expressly provided for the same shall be referred to
the Superintending Engineer, --------------------------------------------------
-------- Circle, whose decision shall be final.
- 79 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
IN WITNESS WHEREOF the said ---------------------- and ---------------
------------ by the order and under the direction of the Corporation set
their respective hands the day and year first above written.
Signed, sealed and delivered by the said Contractor in the presence.
Witness
Signature
Name
Address
Signed by ----------------------------
By the order and director of the Godawari Marathwada Irrigation
Development in presence of
Witness
Signature
Name
Address
- 80 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
APPENDIX „I‟
PROFESSIONAL TAX CLERANCE CERTIFICATE
This is to certify that M/s. --------------------------------------------------------------
--------------- of (address) is a registered dealer under the Maharashtra State
Tax on Professions, Traders, Callings and Employments Act No. XVI of
1975, holding registration Certificate No. -------------------------- w.e.f. ---------
--------------------
The said dealer has paid all tax dues upto 31st March ---------------------
(previous year) under the act. The dealer has paid the Professional Tax dues
for the employees mentioned below.
Sr.No. Name of the Employee Designation
There is no Professional Tax dues outstanding against the dealer under the
act.
This certificate is valid for ONE year from the date of issue.
Place :-
Date :-
Signature -----------------
Professional Tax Officer.
- 81 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
APPENDIX „J‟
AGREEMENT
Articles of agreement executed on this the ----------------- of -------------
Two Thousand and ---------------------------- between Executive Engineer,
GMIDC (hereinafter referred to as GMIDC of the one part) and Shri. ----------
----------------------------------------------- (name and address of the tenderer)
(hereinafter referred to as ―the bounden‖) of the other part.
Whereas in response to the notification No. -------------- dated -----------
the bounden has submitted to the GMIDC a tender for the work -----------------
------------- specified therein subject to the terms and conditions contained in
the said tender.
Whereas the bounden has also deposited with GMIDC a sum of Rs. ----
------ as earnest money for execution of an agreement undertaking the due
fulfillment of the contract in case his tender is accepted by the GMIDC.
Now these present witness and it is mutually agreed as follows.
1. In case the tender submitted by the bounden is accepted by the GMIDC
and the contract for -------------------------------------------- is awarded to
the bounden, the bounden shall within ------------------- days of
acceptance of his tender execute an agreement with the GMIDC
incorporating all the terms and conditions under which the GMIDC
accepts his tender.
2. In case the bounden fails to execute the agreement as aforesaid
incorporating terms and conditions governing the contract, the GMIDC
shall have power and authority to recover from the bounden and loss or
any damage caused to the GMIDC by such breach, as may be
determined by the GMIDC by appropriating the earnest money
deposited by the bounden and if the earnest money is found to be
inadequate the deficit amount may be recovered from the bounden and
- 82 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
his properties, movable and immovable, in the manner hereafter
contained.
3. All sums found due to the GMIDC under or by the virtue of this
agreement shall be recoverable from the bounden and his properties,
movable and immovable, under the provisions of the Maharashtra
Land Revenue Code for the time being in force as though such sums
are areas of land revenue and in such other manner as the GMIDC may
deem fit.
In witness whereof Shri. ------------------------------------ (Name and
designation) for and on behalf on the GMIDC and Shri. ------------------
----------------------- the bounden have hereunto set their hand the days
and year shown against their respective signature.
Signed by Shri. --------------------------------------------- date ---------------
in the presence of witness.
2. ---------------------------------------------------
3. ---------------------------------------------------
Signed by Shri. ------------------------------------------- in the presence of
witness.
1. ---------------------------------------------------
2. ---------------------------------------------------
- 83 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
APPENDIX – „K‟
UNDERTAKING
I/We have been allotted the work of ------------------------------------------
----------------------------------------------------------------------------------------------
--------------------vide agreement No. -------------------- Year 20 - 20 . The
stipulated date of completion this work as per agreement is / /20 .
I/We desire to complete this work in time.
I/We am/are of the present financial problems of the Corporation and
in knowledge of the fact that timely payment towards the work executed by
me/us are not possible. I/We however desire to complete the above work by
mobilizing our own financial resources.
Notwithstanding, anything contained in the tender documents of this work.
I we hereby undertake as follows.
i) I/We will not claim for any compensation for delayed payments
or delay in execution of this work for any reason whatsoever,
executed by me/us in past as well as the work that will be
executed in future.
ii) It will be my/our responsibility to get the information about
availability of funds with the Corporation for the above work
allotted to me/us and accordingly to arrange for the labourers,
construction materials and finance.
iii) This undertaking will be part and Parcel of the B-1 agreement
bearing No. ----------------- of Year 20 - 20 .
Signature of the Contractor.
(With Stamp/Seal in case of
Company)
- 84 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
APPENDIX – „L‟
UNDERTAKING
I/We have allotted the work of --------------------------------------------------------
----------------------------------------------------------------------------------------------
-----------------vide agreement bearing No. B-1/ ------ Year 20 - 20 . The
stipulated date of completion of this work is / /20 .
Notwithstanding, anything contained in the tender documents of this work. I
we hereby undertake as follows.
i) I/We will not claim any demand for extra lead and lift charges
as I/We aware fully that the charges for lead and lifts are
included in the Schedule-B. Rates for the item concerned and I
have to find out the suitable quarry for material required for the
concerned construction of work.
ii) It will not claim any quarry fees, Royalties, Octroi charges and
ground rent for stacking the material as paid by me as per
Clause No.36 of the concerned authorities as I am fully aware
that the charges are included in the tender rate and I will submit
the paid voucher of Royalty to Revenue or Component authority
before submission of R.A.Bills.
iii) This undertaking will be part of the B-1 agreement bearing No.
B-1/ ----for 20 - 20 .
Place :
Date :
Signature of the Contractor.
(With Stamp/Seal in case of
Company)
- 85 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
SECTION IV
CONDITION
OF CONTRACT
- 86 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
CONDITIONS OF CONTRACT
Clause 1 – The person/persons whose tender may be accepted (hereinafter
called the contractor, which expression shall unless excluded by or
repugnant to the context includes his heirs, executors, administrators, and
assigns) shall (A) within 10 days (which may be extended by the
Superintending Engineer concerned up to 15 days if the superintending
Engineer thinks fit to do so) of the receipt by him of the notification of the
acceptance of his tender deposit with the Executive Engineer in cash or
Corporation securities endorsed to the Executive Engineer (if deposited for
more than 12 months) of sum sufficient which will make up the initial
security deposit specified in the tender form at para (i) of memorandum
provided always that in the event of the contractor depositing a lump sum
by way of security deposit as contemplated at (a) above then and in such
case, if the sum so deposited shall not amount specified in memorandum it
shall be lawful for Corporation at the time of making any payment to the
contractor for work done under the contract to make up the full amount of
security deposit as specified in memorandum at para (a) deducting a
sufficient sum at the rate specified at (g) of memorandum from every such
payment as last aforesaid until the full amount of the security deposit is
made up. All compensation or other sums of money payable by the
contractor to Corporation under the terms of his contract may be deducted
from or paid by the sale of sufficient part of his security deposit or from the
interest arising there from, or from any sums which may be due or may
become due by Corporation to the contractor under any other contract or
transaction of any nature on any account whatsoever and in the event of his
security deposit being reduced by reason of any such deduction/ sale as
aforesaid, the contractor shall, within 10 days thereafter, make good in cash
or Corporation securities endorsed as aforesaid any sum or sums which may
have been deducted from or raised by sale of his security deposit or any part
thereof. The security deposit referred to, when paid in cash may, at the cost
of the depositor, be converted into interest bearing Corporation securities
provided that the depositor has expressly desired this in writing. In case
contractors offer is less than 10% of the updated estimated cost as stated at
Sr. No. 5 of Annex ―A‖ additional Security Deposit in the form of
irrevocable Bank Guarantee for a period equal to period of contract, ad for
an amount equal to the difference of the contractor‘s offer and 90% of the
updated estimated cost as stated above shall be submitted to the Engineer-
in-charge at the time of completing tender documents.
Non submission of the above additional Security Deposit result into
forfeiture of the E.M.D. and additional E.M.D. If the amount of the security
deposit to be paid in a lump sum and additional Security Deposit in form of
irrevocable Bank Guarantee is not paid within the period specified at (A)
above the tender/contract already accepted shall be considered as cancelled
and legal steps taken against the contractor for recovery of the amounts. The
amount of the Security Deposit lodged by the contractor shall be refunded
along with the payment of the final bill, if the date upto which the contractor
has agreed to maintain the work in good order is over. If such date is not
over, only 50% amount of Security Deposit shall be refunded along with the
payment of the final bill. The amount of Security Deposit retained by the
Corporation shall be released after expiry of period upto which the
contractor has agreed to maintain the work in good order is over. In the
(A) Security
deposit
- 87 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
event of the contractor failing or neglecting the complete
rectification work within the period upto which the contractor has
agreed to maintain the work in good order, then subject to provisions
of clauses 17 and 20 hereof the amount of Security Deposit retained
by Corporation shall be adjusted towards the excess cost incurred by
the Corporation on rectification work.
The Additional Security Deposit shall be refunded to the
Contractor on issuing of the completion certificate by the Engineer-
in-charge as stipulated in the Clause No. 7 of the contract, provided
that the Engineer-in-charge, if demanded in writing by the contractor
shall, from time to time, release the Additional Security Deposit in
parts which are in proportion to the amount of the completed work.
Clause 2- The time allowed for carrying out the work as entered in
the tender shall be strictly observed by the contractor and shall be
reckoned from the date on which the order to commence work is
given to the contractor. The work shall through the stipulated period
of the contract be proceeded with, all due diligence (time being
deemed to be the essence of the contract on the part of the contractor)
and the contractor shall pay as compensation an amount equal to one
percent or such smaller amount as the Superintending Engineer
(Whose decision in writing shall be final) may decide, of the amount
of the estimated cost of the whole work as shown in the tenderer for
every day that the work remains uncommenced, or unfinished after
the proper dates, And further to ensure good progress during
execution of the work, the contractor shall be bound. In all cases in
which the time allowed for any work exceeds one month to complete
the part work works in specified time slice as per the programme
given in Annex A to Section-I Detailed Tender Notice/enclosed at the
end of Schedule ―B‖.
If the contractor has not achieved the target as per physical
programme of all items with respect to time as given Annex ―A‖ to
Section-I Detailed Tender Notice/ enclosed at the end of Schedule
―B‖ then the compensation will be recovered with prior notice to the
contractor till the achievement of particular target as decided by the
Engineer-in-charge.
In the event of the contractor failing to comply with this condition he
shall be liable to pay as compensation an amount equal to one percent
or such smaller amount as the Superintending Engineer (Whose
decision in writing shall be final) may decide of the said estimated
cost of the whole work for every day that the due quantity of work
remains incomplete. Provided always that the total amount of
compensation to be paid under the provisions of this clause shall not
exceed 10 percent of the estimated cost of the work as shown in the
tender. Superintending Engineer, should be the final authority in this
respect.
Compensation
for delay.
- 88 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Clause 3 – In any case in which under any clause of this contract
the contractor shall have rendered himself liable to pay
compensation amounting to the whole of this security deposit as
specified at para (e) of the memorandum or in the case of
abandonment of the work owing to serious illness or death of the
contractor or any other cause the Executive Engineer, on behalf of
the Corporation, shall have power to adopt following courses,
(a) To rescind the contract (for which rescission notice in
writing to the contractor under the hand of Executive Engineer shall
be conclusive evidence) and in that case the security deposit and
additional security deposit of the contractor shall stand forfeited and
be absolutely at the disposal of Corporation.
(b) In case of contract shall be rescinded under clause above the
contractor shall not entitled to recover or be paid, any sum for any
work therefore actually performed by him under this contract unless
and until the Executive Engineer shall have certified in writing the
performance of the such work and the amount payable to him in
respect thereof and he shall only be entitled to be paid the amount
so certified.
(c) The contractor shall have no claim to compensation for any loss
sustained by him by reason of his having purchased or procured any
materials or entered in to any engagements or made any advance on
account of or with a view to the execution of the work or the
performance of the contract. The contractor shall also be not eligible
to tender for the work remaining unexecuted under this contract.
Clause 4 – If the progress of any particular portion of the work is
unsatisfactory the Executive Engineer shall not withstanding that
the general progress of the work is in accordance with the
conditions mentioned in clause 2, be entitled to take action as under
after giving the contractor 10 day‘s notice in writing.
The Corporation will have to order that the work of the contractor
be measured up and to take such part thereof as shall be unexecuted
out of his hands, and to give it to another contractor to complete in
which case. All expenses incurred to advertisements for fixing a
new contracting agency, additional supervisory staff including the
cost of work charged establishment and the cost of the work
executed by the new contract agency will be debited to the
contractor and the value of the work done or executed through the
new contractor (including escalation due) shall be credited to the
contractor in all respects and in the same manner and at the same
rates as if it has been carried out by the contractor under the terms
of his contract.
The certificate of the Executive Engineer as to all the cost of the
work and other expenses incurred as aforesaid for or in getting the
unexecuted work done by the new contractor and as to the value of
the work so done shall be final and conclusive against the
contractor.
Action when whole of
security deposit is
forfeited.
Action when the
progress of any
particular portion of
the work is
unsatisfactory.
- 89 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
In case the cost of the work executed through a new contractor and
other allied expenses exceeding the value of such work credited to the
contractors, the amount of excess shall be deducted from any money
due to the contractor by Government or Corporation under the
contract or otherwise howsoever or from his security deposit and
additional security deposit or the sale proceeds thereof provided,
however that the contractor shall have no claim against Corporation
even if the certified value of the work done through a new contractor
exceeds the certified cost of such work and allied expenses. The
contractor shall have no claims to compensation for any loss sustained
by him reason of his having purchased or procured any materials or
entered into any engagements, or made any advances on account of or
with a view to the execution of the work or the performance of the
contract.
The contractor of the whole work shall not be considered eligible to
tender for the execution of work so withdrawn from this contract.
The contractor will have no claim for compensation, for any loss
sustained by him owing to such action.
Clause 5 – In any case in which any of the power conferred upon the
Executive Engineer by clause 3 and 4 hereof shall have become
exercisable and the same shall not have been exercised the non-
exercise thereof shall not constitute a waiving of any of the
conditions hereof and such powers shall notwithstanding be
exercisable in the event of any future case of default by the
contractor for which under any clause hereof he is declared liable to
pay compensation amounting to the whole of his security deposit and
additional security deposit and the liability of the contractor for past
and future compensation shall remain unaffected.
In the event of the Executive Engineer taking action under clause 3,
he may, if he so desires, take possession of all/ any tools and plant,
materials and stores in or upon the work of the site thereof or
belonging to the contractor, or procured by him and intended to be
used for the execution of the work or any part thereof paying or
allowing for the same in account at the contract rates, or in the case
of contract rates not being applicable at current market rates to be
certified by the Executive Engineer whose certificate thereof shall be
final. In the alternative the Executive Engineer may, after giving
notice in writing to the contractor or his clerk of the work, foreman
or other authorised agent require him to remove such tools and plant,
materials, or stores from the premises within a time to be specified in
such notice, and in the event of the contractor failing to comply with
any such requisition, the Executive Engineer may remove them at the
contractor‘s expense or sale them by auction or private sale on
account of the contractor and at his risk in all respects and the
certificate of the Executive Engineer as to the expense of any such
removal and the amount of the proceeds and expense of any such
sale shall be final and conclusive against the contract.
Contractor remains
liable to pay
compensation if action
not taken under
clauses 3 and 4
Power to take
possession of or
require removal of or
sell contractor‘s
plant.
- 90 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Clause 6 – If the contractor shall desire an extension of the time for
completion of work on the ground of his having been unavoidably
hindered in its execution or on any other ground he shall apply in
writing to the Executive Engineer before the expiration of the
period stipulated in the tender or before the expiration of 30 days
from the date on which he was hindered as aforesaid or on which
the cause for asking for extension occurred, whichever is earlier and
the Executive Engineer, or in the opinion of Superintending
Engineer, or Chief Engineer as the case may be if in his opinion,
there were reasonable grounds for granting an extension, grant such
extension as he thinks necessary or proper. The decision of the
Executive Engineer/Superintending Engineer/Chief Engineer in this
matter shall be final. Only on extension shall be granted to the
contractor on the grounds of unavoidable hindrance in its execution
or on any other reasonable grounds. Any further extension will not
be granted on any reason and the contract will be terminated at the
stage, and the security deposit and additional security deposit. If
any, shall stand forfeited to the Corporation.
The contractor of this work shall not be considered eligible to
tender for the execution of the works so terminated.
Clause 7 – On the completion of the work the contractor shall be
furnished with a certificate by the Executive Engineer(hereinafter
called the Engineer-in-charge) of such completion; but no such
certificate shall be given or shall the
work be considered to be complete until the contractor shall have
removed from the premises on which the work shall have been
executed, all scaffolding, surplus materials and rubbish, and shall
have cleaned off, the dirt from all wood work, doors, windows, wall
floor or other parts of any building in or upon which the work has
been executed or of which he may have had possession for the
purpose of executing the work, nor until the work shall have been
measured by the Engineer-in-charge or where the measurements
have been taken by his subordinate until they have received
approval of the Engineer-in-charge, the said measurements being
binding and conclusive against contractor. If the contractor shall fall
to comply with the requirements of this clause as to the removal of
scaffolding surplus materials and rubbish and cleaning of dirt on or
before the date fixed for the completion of the work the Engineer-
in-charge may at the expense of the contractor, remove such
scaffolding surplus materials and rubbish, and dispose off the same
as he thinks fit and clean off such dirt as aforesaid and the
contractor shall forthwith pay the amount of all expenses so
incurred, but shall have no claim in respect of any such scaffolding
or surplus materials as aforesaid except for any sum actually
realized by the sale thereof.
Clause 8 – No payments shall be made for any work estimated to
cost less than rupees one thousand till after the whole of work shall
have been completed and a certificate of completion given. But in
the case of works estimated to cost more than rupees one thousand
the contractor shall on submitting a monthly bill therefore a entitled
Extension of time.
Final certificate
- 91 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
to received payment proportionate to the part of the work then
approved and passed by the Engineer-in-charge, whose certificate
of such approval and passing the sum so payable shall be final and
conclusive against the contractor. All such intermediate payments
shall be regarded as payments by way of advance against the final
payments only and not as payments for work actually done and
completed and shall not preclude the Engineer-in-charge from
requiring any bad, unsound imperfect or unskillful work to be
removed or taken away and reconstructed or re-erected nor shall
any such payment be considered as an admission of the due
performance of the contract or any part thereof in any respect or he
occurring of any claim nor shall ir conclude, determine or effect in
any other way the powers of the Engineer-in-charge as to the final
settlement and adjustment of the accounts or otherwise, or in any
other way vary or within one month of the date fixed for the
completion of the work, otherwise the Engineer-in-charge‘s
certificate of the measurements and of the total amount payable for
the work shall be final and binding on all parties.
Clause 9 – The rates for several items of work estimated to cost
more than Rs. 1000 agreed to within, shall be valid only when the
item concerned is accepted as having been completed fully in
accordant with the sanctioned specifications. In cases where the
items of work are not accepted as so completed by the Engineer-in-
charge may make a payment on account of such items at such
reduced rates as he may consider reasonable in the preparation of
final or on account bills.
Clause 10 – A bill shall be submitted by the contractor in each
month or before the date fixed by the Engineer-in-charge for all
work executed in the previous month, and the Engineer-in-charge
shall check the measurement for the purpose of having the same
verified.
The measurements for payments of running account bills shall be
taken by the contractor‘s authorized Engineer in the presence of
Engineer-in-charge or his representatives. Based on the above
measurements, the contractor shall have to submit his R.A.bills in
quadruplicate along with details of measurements and calculations
of quantities in proforma approved by the Engineer-in-charge duly
authorized by the Executive Engineer. The measurements shall be
recorded in the M.B. issued by the Corporation.
The initial levels before starting the work/foundation levels/ final
measurements/final levels shall be taken by the Authorised
Engineer of the contractor in the presence of Engineer-in-charge of
his authorized representative and the same shall be got attested
from the Engineer-in-charge or his authorized representative in
token of acceptance.
The payment of final bill will be made only after.
i) Detailed scrutiny of the measurements and the acceptance of the
bill thereafter and
Payment at reduced
rates on account of
items of work not
accepted as
completed to be at
the discretion of the
Engineer-in-charge
Bill in
quadruplicate to be
submitted monthly.
- 92 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
ii) The contractor produces the challan of having made the
payment into District Treasury in respected of all dues of Sales Tax
under the Maharashtra Sales Tax on Transfer of Goods‖ involved in
the execution of works contract (Re-enacted) Act 1989.
Clause 11 – The contractor shall submit all bills on the printed forms
to be had on application at the office of the Engineer-in-charge. The
charges to be made in the bill shall always be entered at the rates
specified in the tender or in the case of any extra work ordered in
pursuance of these conditions and not mentioned or provided for in
the tender at the rates here-in-after provided for such work.
Clause 12 – If the specification or estimate of the work provides for
the use of any special description of material to be supplied from the
store of the Corporation or if it is required that the contractor shall use
certain stores to be provided by the Engineer-in-charge (such material
and stores and the process to have charged therefore as hereinafter
mentioned being so far as practicable for the convenience of the
contractor but not so as in any way to control the meaning or effect of
this contract specified in the schedule or memorandum hereto
annexed.) the contractor shall be supplied with such materials and
stores as may be required from time to time to be used by him for the
purpose of the contract only. And value of the full quantity of the
materials and stores so supplied shall be set off or deducted from any
sums then due, or thereafter to become due to the contractor under the
contract, or otherwise, or from the security deposit or the proceeds of
sale thereof if the security deposit is held in Corporation securities,
the same or a sufficient portion thereof shall in that case be sold for
the purpose. All materials supplied to the contractor shall remain the
absolute property of Corporation and shall on no account be removed
from the site of the work, and shall at all times be open for inspection
be the Engineer-in-charge. Any such materials unused and in perfectly
good condition at the time of completion or termination of the
contract shall be returned to the Corporation store if the Engineer-in-
charge so requires by a notice in writhing given under his hand but the
contractor shall not be entitled to refinery such materials except with
consent of the Engineer-in-charge and he shall have no claim for
compensation on account of any such material supplied to him as
aforesaid but remaining unused by him or for any wastage in or
damage to any such materials.
Clause 12 (A) – If all stores of controlled materials such as cements,
steel etc. supplied to the contractor by Corporation should be kept by
the contractor under lock and key and will be accessible for inspection
by the Engineer-in-charge or his agent at all the times.
Bills to be on
printed forms
Works to be executed in
accordance with
specifications,
drawings, orders, etc.
Stores supplied by
Corporation
- 93 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Clause 13 – The contractor shall execute the whole and every part
of the work in the most substantial and workmanlike manner, and
both as regards materials and every other respect in strict
accordance with specifications. The contractor shall also conform
exactly, fully and faithfully to the designs, drawings and
instructions in writing relating to the work signed by the Engineer-
in-charge and lodged in his office and to which the contractor shall
be entitled to have access for the
purpose of inspection at such office, or on the site of the work
during office hours. The contractor will be entitled to receive three
sets of contract drawings as well as one certified copy of the
accepted tender along with the work order free of cost. Further
copies of the contract drawings & working drawings if required by
him, shall be supplied at the rate of Rs.500/- per set of contract
Drawings & Rs.100/- per working drawing except where otherwise
specified.
Clause 14 – The Engineer-in-charge shall have power to make any
alteration in or additions to the original specifications, drawings,
designs and instructions that may appear to him to be necessary or
advisable during the progress of the work and the contractor shall
be bound to carry out the work in accordance with any instructions
in this connection which may be given to him in writing signed by
the Engineer-in-charge and such alteration shall not invalidate the
contractor, and any additional work which the contractor may be
directed to do in the manner above specified as part of the work
shall be carried out by the contractor on the same conditions in all
respects on which he agreed to do the main work, and at the same
rates as are specified in the tender for the main work, and if he
additional and altered work includes any class of work shall be
carried out at the rates entered in the Schedule of Rates of the
Division or at the rates mutually agreed upon between the
Engineer-in-charge and the contractor, whichever are lower.
If the additional or altered work for which no rate is entered in the
schedule of Rates of he Division is ordered to be carried out before
the rates are agreed upon, then the contractor shall within
seven days of the date of receipt by him of the order to carry out
the work, inform the Engineer-in-charge of the rate which it is his
intention to charge for such class of work. And if the Engineer-in-
charge does not agree to this rate he shall by notice in writing be at
liberty to cancel his order to carry out such class of work and
arrange to carry out in such manner as he may consider advisable
provided always that if the contractor shall commence work or
incur any expenditure in regard thereto before the rates shall have
been determined as lastly hereinbefore mentioned, then in such
case he shall only be entitled to be paid in respect of the work
carried out or expenditure incurred by him prior to the date of the
determination or the rate as aforesaid according to such rate or
rates as shall be fixed by the Engineer-in-charge. In the event of a
dispute the decision of Superintending Engineer of the Circle will
be final.
Alterations in
specifications and
designs not to
invalidate contracts.
Rate for works not
entered in estimate
or schedule of rates
of Dist.
- 94 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Where, however, the work is to be executed according to the
designs, drawings and specifications, recommended by the
contractors and accepted by the competent authority the
alterations above referred to shall be within the scope of such
designs, drawings and specifications appended to the tender.
The time limit for the completion of the work shall be
extended in the proportion that increase in its cost occasioned
by alterations or additions bears to the cost of the original
contract work, and the certificate of the Engineer-in-charge as
to such proportion shall conclusive. However such an by
extension will be governed provisions of clause 6.
Clause 15 (1) – If at any time after the execution of the
contract documents the Engineer shall for any reason
whatsoever (other than default on the part of the contractor for
which the Corporation is entitled to rescind the contract)
desires that the whole or any part of the work specified in the
tender should be suspended for any period or that the whole or
part of the work should not be carried out at all, he shall give to
the contractor a notice in writing of such desire and upon the
receipt of such notice the contractor shall forthwith suspend or
stop the work wholly or in part as required, after having due
regard to the appropriate stage at which the work should be
stopped or suspended so as not to causes any damage or injury
to the work already done or endanger the safety thereof
provided that the decision of he Engineer as to the stage at
which the work or any part of it could have been safely stopped
or suspended shall be final and conclusive against the
contractor. The contractor shall have no claim to any payment
or compensation whatsoever by reason of or in pursuance of
any notice as aforesaid. On account of any suspension,
stoppage or curtailment except to the extent specified
hereinafter.
(2) Where the total suspension of work ordered as aforesaid
continued for a continuous period exceeding 90 days the
contractor shall be at liberty to withdraw from the contractual
obligations under the contract so far as it pertains to the
unexecuted part of the work be giving a 10 days prior notice in
writing to the Engineer, within 30 days of the expiry of the said
period of 90 days, of such intention and requiring the Engineer
to record the final measurement of the work already done and
to pay final gill. Upon giving such notice the contractor shall
be remaining unexcited work under his contract. On receipt of
such notice the Engineer shall proceed to complete the
measurements and make such payment as may be finally due to
the contractor within a period of 90 days from the receipt of
such notice in respect of the work already done by the
contractor. Such payment shall not in any manner prejudice the
right of the contractor to any further compensation under the
remaining provisions of this clause.
(3) Where the Engineer required the contractor to suspend the
work for a period in excess of 30 days at anytime or 60 days in
No claim to any
payment or
compensation for
alteration in or
restriction of
work
- 95 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
the aggregate, the contractor shall be entitled to apply to the
Engineer within 30 days of the resumption of work after such
suspension for payment of compensation to the extent of
pecuniary loss suffered by him in respect of working
machinery remained idle on the site or on the account of his
having and to pay the salary or wages of labour engaged by
him during the said period of suspension provided always that
the contractor shall not be entitled to any claim in respect of
any such working machinery, salary or wages for the first 30
days whether consecutive or in the aggregate or such
suspension or in respect of any suspension whatsoever
occasioned by unsatisfactory work or any other default on his
part. The decision of the Engineer in this regard shall be final
and conclusive against the contractor.
(4) In the event of
(i) any total stoppage of work on notice from Engineer under Sub
clause (1) in that behalf
(ii) Withdrawal by the contractor from the contractual obligations to
complete the remaining unexecuted work under sub-clause (2) on
account of continued suspension of work for a period exceeding 90
days.
Or
(iii) Curtailment in the quantity of item or items originally
tendered on account of any alteration, omissions on substitution in
the specifications, drawings, designs or instructions under clause
14 (1) where such curtailment exceeds 25% in quantity and the
value of the quantity curtailed beyond 25 percent at the rates for
the item specified in the tender is more than Rs. 5000/-
It Shall be open to the contractor, within 90 days from the service
of (I) the notice of stoppage of work or (ii) the notice of
withdrawal from the contractual obligations under the contract on
account of the continued suspension of work or (iii) notice under
clause 14(1) resulting in such curtailment to produce to the
Engineer satisfactory documentary evidence that he had
purchased or agreed to purchase material for use in the contracted
work, before receipt by him of the notice of stoppage, suspension
or curtailment and require the Government to take over on
payment such material at the rates determined by the Engineer,
provided, however, such rates shall in no case exceed the rates at
which the same was acquired by the contractor. The Corporation
shall thereafter take over the material so offered, provided the
quantities offered, are not in excess of the requirement of the
unexecuted work as specified in the accepted tender and are of
quality and specifications approved by the Engineer.
Clause 15 A – The contractor shall not be entitled to claim any
compensation from Corporation for the loss suffered by him on
account of delay by Government in the supply of materials entered
in Schedule A where such delay is caused by –
- 96 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
(i) Difficulties relating to the supply of railway wagons.
(ii) Force majored.
(iii) Act of God.
(iv) Act of enemies of the State or any other reasonable cause
beyond the control of Corporation.
In the case of such delay in the supply of materials, Corporation
shall grant such extension of time of the completion of the work as
shall appear to the Executive Engineer to be reasonable in
accordance with the circumstances of the case. The decision of the
Executive Engineer as to the extension of time shall be accepted as
final by the contractor and will be governed by the provision of
Clause 6.
Clause 16 – Under no circumstance whatever shall the contractor
be entitled to any compensation from Corporation on any account
unless the contractor shall have submitted a claim in writing to the
Engineer-in-charge within one month of the case of such claim
occurring.
Clause 17 – If any time before the security deposit or any part
thereof is refunded to the contractor it shall appear to the Engineer-
in-charge or his subordinate in charge of the work, that any work
has been executed with unsound, imperfect or unskillful
workmanship or with materials of inferior quality, or that any
materials or articles provided by him for the execution of the work
are unsound, or of a quality inferior to that contracted for or are
otherwise not in accordance with the contract, it shall be lawful for
he Engineer-in-charge to intimate this fact in writing to the
contractor and then notwithstanding the fact that the work,
materials or articles complained of may have been inadvertently
passed, certified and paid for the contractor shall be bound
forthwith to rectify, or remove and reconstruct the work so
specified in whole or in part, as the case may require or if so
required, shall remove the materials or articles so specified and
provide other proper and suitable materials or articles at his own
charge and cost proper and suitable materials or articles at his own
charge and sot and in the event of his failing to do so within a
period to be specified by the Engineer-in-charge in the written
intimation aforesaid, the contractor shall be liable to pay
compensation at the rate of one percent on the amount of he
estimate for every day not exceeding 10 days, during which the
failure so contains and in the case of any such failure the Engineer-
in-charge may rectify or remove and re-execute the work or
remove, and replace the materials or articles complained of as the
case may be at the risk and expense in all respects of the contractor.
Should the Engineer-in-charge consider that any such inferior work
or materials as described above may be accepted or made use of it
shall be within his discretion to accept the same at such reduced
rates as he may fix therefore.
No claim to
compensation
on account of
loss due to
delay in supply
of material by
Govt.
Time limit for
unforeseen
claims
Action and
compensation
payable in case of
bad work
PWD
Resolution No.
CAT 1087 / CR
94/ Bldg 2, dt.
14/6/89
- 97 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Clause 18 – All works under or in course of execution or executed
in pursuance of the contract shall at all times be open to the
inspection and supervision of the Engineer-in-charge and his
subordinates and the contractor shall at all times during the usual
working hours and at all times at which reasonable notice of the
intention of the Engineer-in-charge and his subordinate to visit the
work shall have been given to the contractor, either himself be
present to receive orders and instructions or have responsible agent
duly accredited in writing present for that purpose. Orders given to
the contractor‘s duly authorised agent shall be considered to have
the same force and effect as if they had been given to the contractor
himself.
Clause 19 – The contractor shall give not less than five days notice
in writing to the Engineer-in-charge or his subordinate in charge of
the work before covering up or otherwise placing beyond the reach
of measurement any work in order that the same may be measured
and correct dimensions thereof taken before the same is so covered
up or place beyond the reach of measurement any work without the
consent in writing of the Engineer-in-charge or this subordinate in
charge of the work, and if any work shall be covered up or placed
beyond the reach of measurement, without such notice having been
given or consent obtained the same shall be uncovered at the
contractor‘s expenses, and in default thereof no payment or
allowance shall be made for such work or for the materials with
which the same was executed.
Clause 20 – If during the period of 06 months from the date of
completion as certified by the Engineer-in-charge pursuant to
Clause 7 of the contract or 06 months after commissioning the
work, whichever is earlier in the opinion of the Executive Engineer,
the said work is defective in any manner whatsoever, the contractor
shall forthwith on receipt of notice in that behalf from the
Executive Engineer, duly commence execution and completely
carry out at his cost in every respect all the work that may be
necessary for rectifying and setting right the defects specified
therein including dismantling and reconstruction of unsafe portion
strictly accordance with and in the manner prescribed and under the
supervision of the Executive Engineer. In the event of the
contractor failing or neglecting to commence execution of the said
rectification work within the period therefore in the said
rectification work within the period prescribed therefore in the said
notice and/or to complete the same as aforesaid as required by the
said notice, the Executive Engineer may get the same executed and
carried out departmentally or by any other agency at the risk on
account and at the cost of the contractor. The contractor shall
forthwith on demand pay to the Corporation the amount of such
cost of the contractor. The contractor shall forthwith on demand
pay to the Govt. the amount of such costs charges and expenses
sustained or incurred the Corporation of which the certificate of the
Executive Engineer shall be final and binding on the contractor.
Work to be open
to inspection.
Contractor or
responsible agent
to be present.
Notice to be
given before
work is covered
up.
Contractor liable
for damage done
and for
imperfection for
three months after
certificate.
PWD
Resolution No.
CAT 1087 / CR
94/ Bldg 2, Dt.
14.6.89
- 98 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Such costs, charges and expenses shall be deemed to be arrears of
land revenue and on the event of the contractor failing or
neglecting to pay the same on demand as aforesaid without
prejudice to any other rights and remedies of the Corporation the
same may be recovered from the contractor as arrears of land
revenue. The Corporation shall also be entitled to deduct the same
from any amount which may then be payable or which may
thereafter become payable by the Corporation to the contractor
either in respect of the said work or any other work whatsoever or
from the amount of security deposit retained by Corporation.
Clause 21 – The contractor shall supply at his own cost all material
(except such special materials if any as may in accordance with the
contract, be supplied from the Corporation stores ) plant, tools,
appliances, implements, ladders, cordage, tackle, scaffolding and
temporary works requisite or proper for the proper execution of the
work, whether, in the original, altered or substituted forming part of
the contract or referred to in these conditions or not and which may
be necessary for the purpose of satisfying or complying with the
requirements of the Engineer-in-charge as to any matter as to which
under these conditions he is entitled to be satisfied of which he is
entitled to required together with the carriage therefore to and from
the work. The contractor shall also supply without charge the
requisite number of persons with the means and materials
necessary for the purpose of setting out works and counting ,
weighing and assisting in the measurement or examination at any
time and from time to time of the work or the materials, failing
which the same may be provided by the Engineer-in-charge at the
expense of the contractor and the expenses may be deducted from
any money due to the contractor under the contract or from his
security deposit or the proceeds of sale thereof, or of a sufficient
portion thereof. The contractor shall provide all necessary fencing
and lights required to protect the public from accident and shall
also be bounds to bear the expenses of defense of every suit, action
or other legal proceeding, that may be brought by any person for
injury sustained owing to neglect of the above precautions, and to
pay any damages and cost which may be awarded in any such suit,
action or proceedings to any such person or which may with
consent of the contractor be paid for compromising any claim by
any such person.
Clause 21 A – The contractor shall provide suitable scaffolds and
working platforms, gangways and stairways and shall comply with
the following regulations in connections therewith.
(a) Suitable scaffolds shall be provided for workmen for all works
that cannot safely done from ladder or by other means.
(b) A scaffold shall not be constructed, taken down or substantially
altered except.
Contractor to
supply plant,
ladder,
scaffolding etc.
And is liable for
damages arising
from non
provisions of
light fencing
etc.
- 99 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
(i) Under the supervision of a competent and responsible person
and
(ii) As far as possible by competent workers possessing adequate
experience in this kind of work.
(c) All scaffolds and appliances connected therewith and ladders
shall
(i) be of sound material
(ii) be of adequate strength having regard to the loads and
strains to which they will be subjects, and
(iii) be maintained in proper conditions.
(d) Scaffolds shall be so constructed that no part thereof can be
displaced in consequence of normal use.
(e) Scaffolds shall not overloaded and so far as practicable the load
shall be evenly distributed.
(f) Before installing lifting gear on scaffolds special precautions
shall be taken to ensure the strength and stability of the scaffold.
(g) Scaffold shall be periodically inspected by the competent
person.
(h) Before allowing a scaffold to be used by his workmen the
contractor shall verify whether the scaffold has been erected by
his workmen or not take steps to ensure that it complies fully
with the regulations herein specified.
(i) Working platform, gangways, stairways shall,
(i) be so constructed that no part thereof can sag unduly or
unequally.
(ii) be so constructed and maintained having regard to the
prevailing conditions as to reduce as far as practicable risks
of persons tripping or slipping, and
(iii) be kept free from any unnecessary obstruction.
(j) In the case of working platform, gangways, working places and
stairways at the height exceeding 3 meters.
(i) Every working platform and every gangway shall be closely
boarded unless other adequate measures are taken to ensure safety.
(ii) Every working platform and gangway shall have adequate width
&
(iii) Every working platform, gangways, working place and stairway
shall be suitably fenced.
(k) Every opening in the floor of a building or in a working platform
shall except for the time and to the extent required to allow the
access of persons or the transport or shifting of materials be
provided with suitable means to prevent the fall of persons or
materials.
- 100 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
(l) When peons are employed on rood where there is a danger of
falling from a height exceeding 3 meters suitable precautions
shall be taken to prevent the fall of persons or materials.
(m) Suitable precautions shall be taken to prevent persons being
struck by articles which might fall from scaffold or other
working places.
(n) Sate means of access shall be provided to all working platforms
and other working places.
(o) The contractor(s) will have to make payment to the laborers as
per Minimum Wages Act.
Clause 21 B – The contractor shall comply with the following
regulation as regard the Hoisting Appliances to be used by him:
(a) Hoisting machine and tackle, including heir attachments,
anchorage and support shall –
(i) Be of good mechanical construction, sound material and
adequate strength and free from patent and,
(ii) Be kept in good repair and in good working order.
(b) Every rope used in hoisting or lowering materials or as a means
of suspensions shall be of suitable quality and adequate
strength and free from patent defect.
(c) Hoisting Machine and tackle shall be examined and adequately
tested after erection on the site and before use and be re-
examined in position at intervals to be prescribed by the
Corporation.
(d) Every Chain, ring, hook, shackle, swivel and pulley block used
in hoisting or lowering materials or as a means of suspension
shall be periodically examined.
(e) Every crane driver of hoisting appliance operator shall be
properly qualified.
(f) No person who is below the age of 18 years shall be n control of any hoisting machine,
including any scaffold winch, or give signals to the operator.
(g) In the case of every hoisting machine and of every chain, ring, hook, shackle, swivel,
pulley block used in hosting or lowering or as means of suspension, the safe working
load shall be ascertained by adequate means.
(h) Every Hoisting machine and all gear referred to in preceding regulation shall be plainly
marked with the safe working load.
(i) In the case of hoisting machine having a variable safe working load, each safe working
load & the conditions under which it is applicable shall be clearly indicated.
- 101 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
(j) No part of any hoisting machine or of any gear referred to in
regulation (g) above shall be loaded beyond safe working load
except for the purpose of testing.
(k) Motors, gearing transmissions, electric wiring and other
dangerous part of hoisting appliances shall be provided with
efficient safeguards.
(l) Hosting appliances shall be provided with such means as will
reduce to minimum the risk of the accidental descent of the
load.
(m) Adequate precaution shall be taken to reduce to a minimum
the risk of any part of a suspended load becoming accidentally
displaced.
Clause 22 – The contractor shall not set fire to any standing jungle,
trees, brushwood or grass without a written permit from the
Executive Engineer.
When such permit is given, and also in all cases when destroying
cut or dug up trees brushwood, grass etc. by fire, the contractor
shall take the necessary measure to prevent such fire spreading to
or otherwise damaging surrounding property.
The contractor shall make his own arrangements for drinking water
for the labour employed by him.
Clause 23 – Compensation for all damages done intentionally or
unintentionally by contractor‘s labour whether in or beyond the
limits of Corporation property including any damage caused by the
spreading of fire mentioned in clause 22 shall be estimated by the
Engineer-in-charge or such other officer as he may appoint and the
estimate of the Engineer-in-charge subject to the decision of the
Superintending Engineer on appeal shall be final and the contractor
shall be bound to pay the amount of the assessed compensation on
demand, failing which, the same will be recovered from the
contractor as damages in the manner prescribed in clause 1 or
deducted by the Engineer-in-charge from any sums that may be due
or become due from Corporation to contractor under this contract
or otherwise.
The contractor shall bear the expenses of defending any action or
other legal proceeding that may be brought by any persons for
injury sustained by him owing to neglect of precautions to prevent
the spread of fire and he shall pay any damages and cost that may
be awarded by the court in consequence.
Clause 24 – DELETED
Employment of
female labour.
Liability of
contractor for any
damage done in or
outside work area.
Measure for
prevention of
fire.
- 102 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Clause 25 – No work shall be done on weekly local holiday
without the sanction in writing of the Engineer-in-charge.
Clause 26 – The contract shall not be assigned or sublet without
the written approval of the Engineer-in-charge. And if the
contractor shall assign or sublet his contract, or attempt so to do, or
become insolvent or commence any proceeding to get himself
adjudicated and insolvent or make any composition with his
creditors, or attempt so to do or if bribe, gratuity, gift, loan,
perquisite, regard or advantage, pecuniary or otherwise, shall either
directly or indirectly be given, promised or offered by the
contractor or any of his servants or agents to any public officer or
person in the employ of Corporation in any way relating to his
office or employment, or if any such officer or person shall become
in any way directly or indirectly interested in the contract, the
Engineer-in-charge may thereupon by notice in writing rescind the
contract, and the security deposit of the contractor shall thereupon
stand forfeited and be absolutely at the disposal of Corporation and
the same consequences shall ensure as if the contract had been
rescinded under Clause 3 hereof and in addition the contractor shall
not be entitled to recover or be paid for any work therefore actually
performed under the contract.
Clause 27 – All sums payable by a contractor by way of
compensation under any of these conditions shall be considered as
reasonable compensation to be applied to the use of Corporation
without reference to the actual loss or damage sustained, and
whether any damage has or has not been sustained.
Clause 28 – In the case of tender by partners, any change in the
constitution of a firm shall be forthwith notified by the contractor
to the Engineer-in-charge for his information.
Clause 29 – All works to be executed under the contract shall be
executed under the direction and subject to the approval in all
respects of the Superintending Engineer of the Circle, for the time
being, who shall be entitled to direct at what point or points and in
what manner they are to be commenced, and from time to time
carried on.
Clause 30 (1) – Except where otherwise specified in the contract
and subject to the powers delegated to him by Corporation under
the Code, rules then in force, the decision of the Superintending
Engineer of the circle for the time being shall be final, conclusive
and binding on all parties to the contract upon all questions relating
to the meaning of the specifications, designs, drawings and
instructions hereinbefore mentioned and as to the quality or
Contractor may be
rescinded any
security deposit
forfeited for
subletting it
without approval or
for bribing a
Corporation officer
or if contractor
becomes insolvent.
Work not to sublet
Work on weekly
holidays
Sum payable be way
of compensation to
be considered as
reasonable
compensation wit out
reference to actual
loss Changes in the
constitution of firm
to be notified .
Direction and control
of the Superintending
Engineer
Decision of the
Superintending
Engineer be final.
- 103 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
workmanship or materials used on the work or as to any other
question, claim, right, matter, or thing whatsoever, if any way
arising out of, or relating to the contract designs, drawings,
specifications, estimates, instructions, orders, or these conditions,
or otherwise concerning the works, or the execution or failure to
execute the same whether arising during the progress of the work,
or after the completion or abandonment thereof.
Clause 30 (2) –The contractor may within thirty days of receipt by
him of any order passed by the Superintending Engineer of the
Circle as aforesaid appeal against it to the Chief Engineer
concerned with the contract, Work or Project provided that – (a)
The accepted Value of the Contract exceeds Rs. 10 Lakhs (Rs. Ten
Lakhs). (b) Amount of claim is not less than Rs. 1.00 Lakh (Rupees
one Lakh)
Clause 30 (3) –If the contractor is not satisfied with the order
passed by the Chief Engineer as aforesaid, the contractor may,
within thirty days of receipt by him of any such order, appeal
against it to the Executive Director, Godawari Marathwada
Irrigation Corporation, Aurangabad, who if convinced that
prima facie the contractor‘s claim rejected by Superintending
Engineer/ Chief Engineer is not frivolous and that there is some
substance in the claim of the contractor as would merit a detailed
examination and decision by the Executive Committee/Standing
Committee, shall put up to the Executive Committee/Standing
Committee at Corporation level for suitable decision.
Clause 31 – The contractor shall obtain from the Corporation
stores, all stores and articles of European or American manufacture
which may be required for the work, or any part thereof or in
making up any articles required therefore or in connection
therewith unless he has obtained permission in writing from the
Engineer-in-charge to obtain such stores and articles elsewhere.
The value of such stores and articles as may be supplied to the
contractor by the Engineer-in-charge will be debited to the
contractor in his account at the rates shown in the schedule, in
Form A attached to the contract and ir they are not entered in the
said schedule, they shall be debited to him at cost price which for
the purpose of this contract shall include the cost of carriage and
other expenses whatsoever which shall have been incurred in
obtaining delivery of the same at the stores aforesaid.
Clause 32 – When the estimate on which a tender is made includes
lump sums in respect of parts of the work the contractor shall be
entitled to payment in respect of the items of work involved or the
part of the work in question at the same rates, as are payable under
Stores of European
or American
manufacture to be
obtained from the
Corporation
Lump sums in
estimates
- 104 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
this contract for each items, or if the part of work in question is not
in the opinion of the Engineer-in-charge capable of measurement,
the Engineer-in-charge may at his discretion pay the lump sum
amount entered in the estimate and the certificate in writing of the
Engineer-in-charge shall be final and conclusive against the
contractor with regard to any sum or sums payable to him under the
provision of this clause.
Clause 33 – In the case of any class of work for which there is no
such specification as is mentioned in rule 1 such work shall be
carried out in accordance with the Divisional specifications, and in
the event of there being no Divisional specification, then in such
case work shall be carried out in all respects in accordance with all
instructions and requirements of the Engineer-in-charge.
Clause 34 – The expression ―work‖ or ―works‖ where used in
these conditions shall unless there be something in the subject or
context repugnant to such construction, be construed to mean the
work or works contracted to be executed under or in virtue of the
contract, whether temporary or permanent and whether original,
altered, substituted or additional.
Clause 35 – The percentage referred to in the tender shall be
deducted from / added to the gross amount of the bill before
deducting the value of any stock issued.
Clause 36 – All quarry fees, royalties, octroi dues and ground rent
for stacking materials, if any, should be paid by the contractor and
take all steps necessary as are essential in terms of Maharashtra
Mineral Extraction Rules.
Clause 37 – The contractor shall be responsible for and shall pay
any compensation to his workmen payable under the Workmen‘s
Compensation Act 1923 (VIII of 1923) (here-in-after called the
said Act) for injuries caused to the workmen. If such compensation
payable is paid by Corporation as principal under Sub-section (1)
of section 12 of the said Act on behalf of the contractor, it shall be
recoverable by Corporation from the contractor under sub-section
(2) of the said section. Such Compensation shall be recovered in
the manner laid down in Clause 1 above.
Clause 37 A – The contractor shall be responsible for and shall pay
the expenses of providing medical aid to any workman who may
suffer a bodily injury as a result of an accident. If such expenses are
incurred by Corporation the same shall be recoverable from the
contractor forthwith and be deducted without prejudice to any other
remedy of Corporation from any amount due or that may become
due to the contractor.
Clause 37 B – The contractor shall provide all necessary personal
safety equipment and first aid apparatus available for the use of the
persons employed on the site and shall maintain the same in
condition suitable for immediate use at any time and shall comply
with the following regulations in connection therewith.
Actions where no
specifications.
Definition of
work
Contractor‘s percentage
whether applied to net or
gross amount of bill
Refund of quarry fees
and royalties.
Compensation under
Workmen‘s
Compensation Act.
- 105 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
(a) The workers shall be required to use the equipment so provided by the
contractor and the contractor shall take adequate steps to ensure proper use of
the equipment by those concerned.
(b) When work is carried on in proximity to any place where there is a risk of
drowning all necessary equipment shall be provided and kept ready for use and
all necessary step shall be taken for the prompt rescue of any person in danger.
(c) Adequate provision shall be made for prompt first aid treatment of all
injuries likely to be sustained during the course of the work.
Clause 37 C – The contractor shall duly comply with the provisions of ―the
Apprentices Act, 1961‖ (III of 1961) the Rules made there under and the orders
that may be issued from time to time under the Act and the said Rules and on
his failure or neglect to do so, he shall be subject to all the liabilities and
penalties provided by the said Act and said Rules.
Clause 38 – (1) Quantities shown in the tender are approximate and no claim
shall be entertained for quantities of work executed being either more or less
than those entered in the tender or estimate.
(2) Quantities in respect of the several items shown in the schedule B Part-I of
the tender are approximate and no revision in the tendered rate shall be
permitted in respect of any of the items so long as, subject to any special
provision contained in the specifications prescribing a different percentage of
permissible variation the quantity of the item does not exceed the tender
quantity by more than 25% and so long as the value of the excess quantity
beyond this limit at the rate of the item specified in the tender is not more than
Rs. 5000.
(3) The contractor shall if ordered in writing by the Engineer so to do, also
carry out any quantities in excess of the limit mentioned in sub clause (2)
hereof on the same conditions as and in accordance with the specifications in
the current schedule of rates and in the absence of such rates (ii) at the rate
prevailing in the market. The price variation clause shall be applicable with the
initial basic index existing on the date when quantity exceeds/decreases more
than 25% in schedule ―B‖ Part-1. The rates once decided as above shall not be
revised till completion of the quantity under that item.
(4) In case the quantity of any item reduced than 25% the rates of such item
shall be revised as per provisions of sub clause 3 of clause 38, However, the
total payment of such item shall be limited to seventy fiver percent of estimated
cost of that item put to tender.
(5) The provision of this clause will not be applicable the additional anticipated
items in schedule ―B‖ Part-II.
Clause 39 – The contractor shall employ any famine, convict or other labour of
particular kind or class if ordered in writing to do so by the Engineer-in-charge.
Clause 40 – No compensation shall be allowed for any delay caused in the
starting of the work on account of acquisition of land or in the case of clearance
works, on account of any delay in according to sanction of estimates.
Claim for
quantities
entered in the
tender or
estimates.
Employment of.
famine labour etc.
Claim for
compensation for
delay in starting the
work.
- 106 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Clause 41 – No compensation shall be allowed for any delays in
the execution of the work on account of water, standing in borrow
pits or compartments. The rates are inclusive for hard or cracked
soil. Excavation in mud, soil, water standing in borrow pits & no
claim for an extra rates shall be entertained, unless otherwise
expressly specified.
Clause 42 – The contractor shall not enter upon or commence any
portion of work except with the written authority and instruction of
the Engineer-in-charge or of his subordinate in charge of the work.
Failing such authority the contractor shall have no claim to ask for
measurements of or payment for work.
Clause 43 – (i) No contractor shall employ any person who is
under the age of 14 years.
(ii) No contractor shall employ donkeys or other animals with
breeching of string or thin rope. The breeching must be at least
three inches wide and should be of tape (Nawar)
(iii) The Engineer-in-charge or his Agent is authorised to remove
from the work any person or animal found working which does not
satisfy these conditions and no responsibility shall be accepted by
Corporation for any delay caused in the completion of the work by
such removal.
(iv) The contractor shall pay fair and reasonable wages to the
workmen employed by him, in the contract undertaken by him, in
the event of any dispute arising between the contractor and his
workmen on the grounds that the wages paid are not fair and
reasonable, the dispute shall be referred without delay to the
Executive Engineer who shall be decide the same. The decision of
the Executive Engineer shall be decide the same. The decision of
the Executive Engineer shall be conclusive and binding on the
contractor but such decision shall not in any way effect the
conditions in the contract regarding the payment to be made by
Corporation at the sanctioned tender rates.
(v) Contractor shall provide drinking water facilities to the workers.
Similar amenities shall be provided to the workers engaged on large
work in urban areas.
(vi) The contractor should take precautions against accidents which
take place on account of labour using loose garments while working
near machinery.
Clause 44 – Payment to contractors shall be made by cheque drawn
on any treasury within the division convenient to them provided the
amount exceeds Rs. 10/- amounts not exceeds Rs. 10/- will be paid
in cash.
Clause 45 – Any contractor who does not accept these conditions
shall not be allowed to tender for works.
Clause 46 – If Government declares a state of scarcity or famine to
exist in any village situated within 10 miles of the work, the
contractor shall employ upon such parts of the works, as are suitable
for unskilled labour, any person certified to him by the Executive
Claim, for
compensation for
delay in execution
of work
Entering upon or
commencing any
portion of work
Minimum age of
persons employed
the employment of
donkeys and or
other animals.
Method of
payment
Acceptance of conditions compulsory
before tendering the work.
Employment of
scarcity labour.
- 107 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Engineer, or be any person to whom the Executive Engineer
may have delegated this duty in writing to be in need of relief
and shall be bound to pay to such person wages not below the
minimum which Government may have fixed in this behalf.
Any disputes which may arise in connection with the
implementation of this clause shall be decided by the
Executive Engineer whose decision shall be final and binding
on the contractor.
Clause 47 – The price quoted by the contractors shall not in
any case exceed the control price, if any, fixed by Govt. or
reasonable price which it is permissible for him to charge a
private purchaser for the same class and description, the
controlled price or price permissible under Hoarding and
Profiteering Ordinances, 1948 as amended from time to time, if
the price quoted exceeds the controlled price or the price
permissible under Hoarding and Profiteering Prevention
Ordinance, the contractor will specifically mention this fact in
his tender along with the reasons for quoting such higher
prices. The purchaser at his discretion will in such case
exercise the right of revising the price at any stage so as to
conform with the controlled price on the permissible under the
Hoarding and Profiteering Prevention Ordinance. This
discretion will be exercised without prejudice to any other
action that may be taken against the contractor.
Clause 48 –The rates to be quoted by the contractor must be
inclusive of sales tax No extra payment on this account will be
made to the contractor.
The tender rates shall be inclusive of all taxes, rates and cesses
and are also be inclusive of the leviable tax in respect of sale by
transfer of property in goods involved in the execution of a
work contract under the provision of Rule 58 of Maharashtra
Value Added Tax Act, 2005 for the purpose of levy of Tax.
2% VAT will be deducted from R.A.bills on producing
certificate of registration under MVAT Act, 2005, otherwise
the VAT will be deducted about 4% under MVAT ACT 2005.
Clause 49 – In case of materials that may remain surplus with
the contractor from hose issued for the work contracted for the
date ascertainment of the materials being surplus will be taken
as the date of sale for the purpose of sales tax and the sales tax
will be recovered on such sale.
Clause 49 (a) – Contractor should note that recovery at penal
rate of twice the issue rate will be affected if the contractors do
not return the surplus materials and the sales tax and income
tax will also recovered from them.
Clause 50 – The contractor shall employ he unskilled labour to
be employed by him on the said work only from locally
available labours and shall give preference to those persons
enrolled under Maharashtra Government Employment and Self
Employment Department‘s Scheme.
- 108 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Provided, however, that if the required unskilled labours are not
available locally, the contractor shall be in the first instruct
employ such number of persons as is available and thereafter
may with previous permission, in writing of Executive
Engineer-in-charge of the said work, obtain the rest of
requirement of unskilled labour for outside the above scheme.
Clause 51 – Wages to be paid to the skilled and unskilled
labourers engaged by the contractor.
The contractor shall pay the labourers skilled according to the
wages prescribed by the Minimum Wages Act of 1948
applicable to the area in which the work of the contractor is
located.
Clause 52 – All amount whatsoever which the contractor is
liable to pay to the Corporation in connection with the
execution of the work including the amount payable in respect
of (i) materials and / or stores supplied/ issued hereunder by the
Corporation to the contractor (ii) hire charges in respect of
heavy plant, machinery and equipment given on hire by the
Corporation to the contractor for execution by him of the work
and / or on which advances have been given by the Corporation
to the contractor shall be deemed to be arrears of the Land
Revenue and the Corporation may without prejudice to any
other rights and remedies of the Corporation recover the same
form the contractor as arrears of revenue.
Clause 53 – The contractor shall duly comply with all the
provisions of the Contract Labour (Regulation & Abolition)
Act, 1970 (37 of 1970) and the Maharashtra Contract labour
(Regulation and Abolition ) Rules, 1971 as amended from time
to time and all other relevant statutes and statutory provision
concerning payment of wages particularly to workmen
employed by the Contractor and working on the site of the
work, In particular the contractor shall pay wages to each
worker employed by him on the site of the worker at the rates
prescribed under the Maharashtra Contract Labour (Regulation
and Abolition ) Rules 1971. It the contractor fails or neglects to
pay wages at the said rates or makes short payment and the
Corporation makes such payment of wages in full or part
thereof less paid by the contractor as the case may be, the
amount so paid by the Corporation to such workers shall be
deemed to be arrears of Land Revenue and the Corporation
shall be entitled to recover the same as such from the contractor
or deduct same for, the amount payable by the Corporation to
the contractor hereunder or from any other amount payable to
him by the Corporation.
Clause 54 - The contractor shall duly comply with all the
provision of the Maharashtra Sales Tax on Professions and
traders callings and employment Act 1975 (See rule 3 (2)). The
contractor shall obtain certificate of registration under this act
P.W.Dept. No. CAT
1284 (120) /Building
2, dated 14/8/85
- 109 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
and shall produce to Corporation clearance certificate as and
when demanded.
Clause 55 – RELATION WITH PUBLIC AUTHORITIES :-
The Contractor shall make sufficient arrangement for draining
away the suffrage water as well as water coming from the
bathing & washing places and shall dispose of this water in
such way as not to cause nuisance. He shall also deep the
premises clean by employing sufficient number of sweepers.
The Contractor shall comply with all rules, regulations, bye
laws and directions given from time to time by any local or
public authority in connection with this work and shall pay
fees or charges which are livable to him without any Extra cost
to Corporation.
Clause 56 :- Where the workers are required to work near
machines and area liable to accident they should not be
allowed to wear loose cloth like Dhoti Jhabba etc.
Clause 57 :- Deduction of income tax 2% plus surcharge will
be made from contractor‘s bill. (if applicable)
Clause 58 :- The contractor is free to utilize suitable material
out of the excavated available material on site. However, he
could not claim on account of non-suitability or non-
availability of sufficient excavated material not entertains.
Clause 59 :- Condition relation to insurance of contract work.
The contractor shall take necessary insurance Policy/Policies
so as to work for total contract value and complete contract
period from the ―Director of Insurance for correspondence
Address is 264, MHADA, First floor Opposite Kalanagar,
Bandra (East), Mumbai (Telephone Nos. 022-
26438690/26438746 and Fax No. 022-26438461) Similarly all
workmen‘s appointed to complete the contract work are
required to insure under workmen‘s compensation Insurance
Policy. Insurance Policy/Policies taken out from any other
company will not be accepted and the amount of premium
calculated by the Directorate of Insurance will be recovered
directly from the amount payable to the contractor for the
executed contract work. One percent amount of the bill will be
recovered if documents for insurance policy are not submitted
by the contractor.
- 110 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Clause 60 :- ¶ÉɺÉxÉÉSªÉÉ +ÆMÉÒEÞòiÉ ={ÉGò¨ÉÉSªÉÉ ºÉƤÉÆvÉÒiÉ±É EÆòjÉÉ]õÉÆSªÉÉ
ºÉÆnù¦ÉÉÇiÉ EòɨÉMÉÉ®ú ¦ÉʴɹªÉ ÊxÉ´ÉÉǽþ ÊxÉvÉÒ +ÊvÉÊxɪɨÉÉiÉÒ±É iÉ®úiÉÚnùÒxÉÖºÉÉ®ú
EÆòjÉÉ]õnùÉ®úɱÉÉ xÉÉånùhÉÒEÞòiÉ +ºÉhÉä Vɯû®úÒSÉä +ɽäþ. iɺÉäSÉ EòɨÉMÉÉ®ú ¦ÉʴɹªÉ
ÊxÉ´ÉÉǽþ ÊxÉvÉÒ +ÊvÉÊxɪɨÉÉxÉÖºÉÉ®ú iªÉÉÆxÉÒ ¦ÉʴɹªÉ ÊxÉ´ÉÉǽþ ÊxÉζSÉiÉ +ɴɶªÉEò
iÉÉä ¦É®úhÉÉ Eäò±ÉÉ +ɽäþ ËEò´ÉÉ EòºÉä ªÉÉ ¤ÉɤÉiÉ EÆòjÉÉ]õnùÉ®úÉxÉä ºÉIÉ¨É +ÊvÉEòÉ-
ªÉÉSÉä +ɴɶªÉEò iÉä |ɨÉÉhÉ{ÉjÉ ºÉÉnù®ú Eò®úhÉä Vɯû®úÒSÉä +ɽäþ.
Clause 61 :- Building and other construction Labour
Welfare cess Recovery (<¨ÉÉ®úiÉ ´É <iÉ®ú ¤ÉÉÆvÉEòÉ¨É EòɨÉMÉÉ®ú
Eò±ªÉÉhÉEòÉ®úÒ ={ÉEò®ú +ÊvÉÊxÉªÉ¨É 1996 +ÆiÉMÉÇiÉ ={ÉEò®ú ´ÉºÉÚ±ÉÒ) (¶ÉɺÉxÉ
ÊxÉhÉÇªÉ Gò. ¤ÉÒºÉÒB 2009/|É.Gò.108/EòɨÉMÉÉ®ú, 7 + ÊnùxÉÉÆEò
17/6/2010 ¨ÉvªÉä Ênù±É䱪ÉÉ ºÉÚSÉxÉäxÉÖºÉÉ®ú <¨ÉÉ®úiÉ ´É <iÉ®ú ¤ÉÉÆvÉEòɨÉ
EòɨÉMÉÉ®ú Eò±ªÉÉhÉEòÉ®úÒ ={ÉEò®ú +ÊvÉÊxÉªÉ¨É 1996 +ÆiÉMÉÇiÉ ¤ÉÉÆvÉEòɨÉÉSªÉÉ
BEÚòhÉ ¨ÉÖ±ªÉÉxÉÖºÉÉ®ú 1 % ={ÉEò®ú ´ÉºÉÚ±É Eò®úhªÉÉÆiÉ ªÉä<DZÉ.
Clause 62 :- ROYALTIES :- All quarry fees., royalties,
Octroi dues and ground rent for stacking materials, if any, shall
be paid by the contractor (As per PWD G.R.No. ¨É½þÉ®úɹ]Åõ ¶ÉɺÉxÉ,
¨É½þºÉÚ±É ´É ´ÉxÉʴɦÉÉMÉ, ¨ÉÆjÉɱɪÉ, ¨ÉÖƤÉ<Ç-32 Gò. MÉÉèhÉJÉÊxÉVÉ 10/2009
|É.Gò. 309/JÉ, ÊnùxÉÉÆEò 11 ¡äò¥ÉÖ´ÉÉ®úÒ 2010.
- 111 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
SECTION V
SPECIAL CONDITION
OF CONTRACT
- 112 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
SPECIAL CONDITIONS OF CONTRACT
1. CONTRACTOR TO INFORM HIMSELF FULLY :-
The contractor shall be deemed to have carefully examined the
work and site condition, the special conditions, the specifications,
schedules and drawings and, shall be deemed to have visited the work
site, his own quarries for rubble and sand and to have fully informed
himself regarding the availability of construction material, local
conditions, ancillary works required to be done etc. before quoting the
offer.
If he shall have any doubts as to the meaning of any portion of
the special conditions or the scope of work or the specifications or any
other matter concerning the contract, he shall in good time set forth the
particulars thereof and submit them to the Engineer-in-charge. The
Engineer-in-charge generally means the Executive Engineer directly in
charge of the work, but also means the Superintending Engineer. Chief
Engineer of Government for exercising powers under this contract.
Once a tender submitted the matter will be decided according to tender
conditions in the absence of such authentic pre-clarification.
2. CONTRACT DRAWINGS AND SPECIFICATION:-
2.1 On acceptance of the tender sets of contract drawings, and working
drawings as well as one certified copy of the accepted tender will be
supplied to the contractor free of charge within one week. On request
by the contractor and at the discretion of Engineer-in-charge, the
contractor may be supplied additional copies of contract documents to
the charged at the rate of Rs. 2500/- (Rs. Two Thousand Five Hundred
Only per set)
2.2 The drawings, which form, part of the contract show the works to be
done in such details as possible to do for the present. They will be
supplemented or superseded by such additional detailed drawing as
may be necessary as the work progresses. The contractor shall carry out
the work in accordance with these additional and / or revised drawings
as the case may be at the applicable rates as per the contract. The
contractor shall be supplied a maximum number of three copies of each
of the working drawing free of charge. Should the contractor require
any additional copy for his use the same may be supplied at the
discretion of Engineer-in-charge and the contractor will be charged Rs.
500/- per set of contract drawing and Rs. 100/- for each of such
additional copy of each drawings.
2.3 The contractor shall check all drawing carefully and intimate the
Engineer-in-charge immediately any errors or omissions discovered.
The contractor shall not take advantage of any kind of errors or
omissions in the drawings supplied.
- 113 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
3. DATA AND DRAWINGS TO BE FURNISHED BY THE
CONTRACTOR :-
a) Prior to the commencement of the work, the contractor shall submit
to the Engineer-in-charge for approval, drawings or prints on white
ammonia paper of size 1020 mm x 690 mm or 510 mm x 345 mm as
may be suitable in triplicate showing the location of major plant
workshop, if any, roadways, temporary bridges, unloading facilities
and storage yards, et. Which he proposes to put up at the site.
b) Then contractor shall submit to the Engineer-in-charge for approval
within one month from the date of his receiving notice to start work,
a layout plan of construction plant and equipment for the execution of
the work, which the contractor proposes to adopt at site.
c) Any changes in the approved layout will be subject to further
approval.
d) The approval of the drawings, however, will not relieve the
contractor of his responsibility.
e) The contractor shall have to the get approval to the design of main
Dam, Waste weir EDA & Head Regulator from C.D.O. Nasik at his
own cost, the necessary information & data required for design will
be availed by the Corporation.
4. ERRORS, OMISSIONS, DISCREPANCIES :-
a) In all cases of errors, omissions and / or disagreement between
written and scaled dimensions on the drawings or between the
drawings and specifications, the following orders to preference
shall apply.
Between actual scaled and written dimensions or description on
drawing and corresponding one in the specification, the latter shall
be adopted.
Between the written description of the item in the schedule of
quantities and the detailed specifications of the same item, the latter
shall be adopted.
b) The information in connection with the works and work site as well
as specifications are contained in this book of contract in general
and in particular in two parts, vis. Special conditions and
specifications for item of work. In case of any discrepancy or
repugnancy in the clauses in these sections, the specifications will
prevail over special conditions.
c) The special conditions of contract and the specifications shall
prevail over or description of any item, a reference shall be made to
- 114 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
the Engineer-in-charge whose elucidation, elaboration or decision
shall be considered as authentic and final subject of the Clause 30
of B-1 form. The contractor shall be held responsible for any errors
that may occur in the work through lack of such reference and
precaution.
5. USE OF SITE :-
a) All land required shall be arranged by the contractor from private
landowner / Revenue department at his owns cost and no claim on
this account shall be entertained.
b) All area of operation, including those for his staff and labour
colonies, in case handed over to the contractor shall be cleared
and handed over back in good condition to the Engineer-in-
charge, except areas under works constructed from the Engineer-
in-charge. The contractor shall make good, to the satisfaction of
the Engineer-in-charge, any damage or alteration made to areas,
which he has to hand over bank or to other property or land
handed over to him for the purpose of this work.
c) The land shall as here in before mentioned, be handed over back
to the Engineer-in-charge within three month after the completion
of the work under this contract or the termination of the contract
whichever is earlier. Also no land shall be held by the contractor
longer than the Engineer-in-charge, shall deem necessary and the
contractor shall on the due notice by the Engineer-in-charge,
vacate and return the land which the Engineer-in-charge may
certify as no longer required by the contractor for the purpose of
the works. In case the land are not handed over bank to the
Government within the time limit, specified above, penal rent a
may be decided by the Engineer-in-charge will be recoverable.
d) The vegetation and forest is noticeable in project area. The
contractor should take utmost care for the preservation of this
vegetation and forest. Any damage in this vegetation and forest
will have to be compensated by the contractor and decision from
Engineer-in-charge will be final and binding on contractor.
6. CONTRACTOR NOT TO DISPOSE OFF SOIL ETC. :-
The contractor shall not sell or otherwise dispose off or remove
except for the purpose of this contract, sand, stone, clay, ballast,
earth rock or other substance or materials which may be obtained
from the excavation made 01 the purpose of this contract or any
produce from the site. All such substance, materials and produces
- 115 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
shall be the property of Government and shall be disposed off in a
manner and at a place shown in the drawings or as and where the
Engineer-in-charge may direct.
7. GOLD / SILVER, MINERALS, OILS, RELICS, ETC. FOUND
ON THE SITE. :-
All gold, silver, oil or other mineral of any description and all
precious stones, coins treasure, relics, antiquities and other similar
things which shall be found in or upon the site, shall be properly of
Government and the Contractor shall duly preserve the same to the
satisfaction of the Engineer-in-charge and shall from time to time,
deliver the same to such person or person as the Engineer-in-charge
may appoint.
8. ACCESS TO SITE AND WORK AND CO-OPERATION
WITH OTHER CONTRACTOR :-
The Engineer-in-charge may, if no consider fit, from time to time,
ender on any lands which may be in the possession of the
Contractor under the contract for the purpose of executive any
works not included in the contract and may execute such works not
included in this contract by agents or by other contractor at his
option and the contractor shall in accordance with the requirements
of Engineer-in-charge afford all reasonable facilities for execution
of the works, including occupation of lands by structures or
otherwise to any other contractor employed by the Government and
his workmen or for the workmen of the Government who may be
employed in the execution on or near the site of work not included
in the contract, or of any contract in connection with or specially to
the works and in default, the contractor shall be liable to the
Government for any delay or expenses incurred by reason of such
default. The contractor shall not however, on account of any such
modified, new of extra work executed by or for the sake of the
Government be entitled to claim relief from the obligation to
execute the works. The contractor shall also co operate with other
contractor with nil fairness and mutual understanding arid use the
common facilities like access roads to quarries, water supply
arrangements etc.
The contractor shall also not cause advertently or
inadvertently any obstruction or impediments in the progress of the
other works being executed by Government or through other
agencies. In the event of dispute regarding the claim, the
responsibility, liabilities etc. in respect of such facilities,
- 116 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
disturbance to existing canal flows etc. the decision of the
Engineer-in-charge shall be final.
9. CLEANING UP. :-
a) The contractor shall at all times keep the construction areas and
his colony and storage free from accumulation of waste or
rejected materials.
b) Prior to be completion of (he work, the contractor shall remove
all rubbish from and around the premises and all tools,
scaffolding equipment and materials which are not part of
permanent structures except otherwise asked for or as provided
under any other clauses of this contract, the premises will be left
in a manner fully satisfactory to the Engineer-in-charge.
10. LAYOUT OF CONSTRUCTION ROADS. :-
The contractor shall have to submit detailed plan to the Engineer-
in-charge showing the layout of the work site, roads and approach
roads proposed by him, before he starts the actual work. Such a
road layout plan will be scrutinized by the Engineer-in-charge and
any modifications suggested by him will be binding on the
contractor. If it is decided by the Engineer-in-charge to have some
of the roads proposed by the contractor as common charge to have
some of the roads proposed by the contractor as common roads
for common use of Government and other contractor or
convenient and for compact and planned layout of work site, the
contractor will be bound to construct them and allow them to be
used simultaneously by other contractor and departments. In case
of existing canal service road should be used for material or heavy
machinery transportation in case of disputes, the decision of the
Engineer-in-charge shall be final and binding on the contractor.
11. PERIOD AND HOURS OF WORK. :-
The work shall be done usually during the day time. In the interest
of progress if it is felt necessary to work during night, the
contractor shall obtain specific permission of the Engineer-in-
charge. If the work is to be done at night, prior permission of
Engineer-in-charge should be obtained and adequate lighting
arrangement shall be made as directed by the Engineer-in-charge.
Contractor has to carryout work @ night as per necessity of work
and if Engineer-in-charge instructs to do so taking all necessary
precautions.
- 117 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
12. SIGNING FIELDS BOOKS, LONGITUDINAL SECTIONS,
CROSS SECTIONS AND MEASUREMENT BOOKS. :-
12.1 Before starting the work, and at the end before the work is covered,
levels for plotting the longitudinal section (along the axis as decided
by the Engineer-in-charge or his authorized representative) and
cross sections of the portion of the work shall be taken by the
authorized Engineer of the contractor in the presence of Engineer-
in-charge or his duly authorized representative and the same shal
have to be got attested from the Engineer-in-charge or his
authorized representative in token of acceptance. If the contractor
fails to take measurements and sign them, the measurements
recorded by the Engineer-in-charge of his representative in the
authorized books shall be fixed by the Engineer-in-charge and
intimated to the contractor at least three days in advance.
If the contractor or his duly authorized agent fails to attend on the
appointed date or dales, the levels shall be taken in his absence
and such levels and longitudinal sections and cross sections based
thereon shall be final and binding on the contractor. The levels
will be taken on such alignment and cross sections as will be
useful for reference permanently and described under
specifications for Excavation. The points of locations for the level
will depend upon the roughness, of the area and will also be at
least in conformity with the requirements of specifications for
‗Excavation‘ as for as possible.
13. PROGRAMME OF CONSTRUCTION :-
Work and Progress Schedules
The construction programme is given in Annex ―A‖ to Section-I
Detailed Tender Notice / enclosed at the end of Schedule ―B‖ of
tender document based on which the physical programme is
prepared.
a) Methodology of constructions and construction equipments.
Contractor shall furnish at least 15 days in advance his programme
of commencement of item of work, the details, actual methods that
would be adopted by the contractor for the execution of various
items of work included in the Tender.
The Engineer-in-charge reserves the right to suggest modifications
of make complete change in the method proposed by contractor
whether accepted previously or not any stage of work, to obtained
the designed accuracy, quantity and progress of the work which
- 118 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
shall binding on the contractor and no claim an account of such
change of execution will be entertained by Government so long as
specifications of the items remain unaltered.
The sole responsibility for the safety and adequacy of the methods
adopted by the contractor will however, rest on the contractor,
irrespective of any given by the Engineer.
In case of slippage from the approved work programme at any
stage, the contractor shall furnish revised programme to make up
the slippage within the stipulated time schedule and obtain the
approval of the Engineer to the revised programme in case of
disturbance to canal water supply schedule at any stage due to
improper progress or lack if management by the contractor being a
perennial canal it will course heavy national less so contractor will
be heavily panelized as deviled by Engineer-in-charge or competent
authority of Government.
b) Construction equipment :-
The contractor shall be required to give a trial run of the
equipments for establishing their capability to achieve the laid
down specifications and tolerance to the satisfaction of the Engineer
before commencement of the work. All equipments provided shall
be of proven efficiency and shall be operated and maintain at all
times. In a manner acceptable to the Engineer and no equipment or
personnel will be removed from site without permission of the
Engineer.
13.1 Progress schedule :-
The contractor shall furnish with in the prior stipulated in writing
by Engineer-in-charge a detailed programme schedule using
CPM/PERT technique in quadruplicate indicating the date of actual
start, the monthly progress expected to be achieved and the
anticipated completion date of procurement and setting up of
materials, plant and machinery. The schedule is to be such as is
practicable of achievement towards the completion of work in the
time limit, and of the particular items, if any, on the due dates
specified in the contract and shall have the approval of the
Engineer-in-charge. No revision is further empowered to ask for
more detailed schedule or schedules say, weekly for any item or
items, in any case of urgency of work as will be directed by him
and the contractor shall supply the same as and when asked for.
The contractor shall furnish sufficient plant, equipment, and
Labour as may be necessary to maintain the progress as schedule.
The working and shift hours restricted to one shift a day for
- 119 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
operations to be done under the Government supervision shall be
such as may be approved by the Engineer-in-charge. They shall not
be varied without the prior approval of the Engineer. Night work
which required supervision shall not be permitted except when
specifically allowed by Engineer each time if required by the
contractor. The contractor shall provide necessary lighting
arrangement etc. for night work as directed by Engineer without
extra cost. Further the contractor shall submit the progress report of
work in prescribed forms and charts etc. at periodical intervals, as
may be specified by the Engineer-in-charge schedule shall be in the
form of progress charts forms progress statement and / or reports as
may be approved by the Engineer. The contractor shall maintain
proformas charts, details regarding machinery, equipment, Labour
materials, personnel etc. as may be specified by the Engineer and
submit periodic returns there of as may be specified by the
Engineer-in-charge.
14. MATERIALS :-
a) Cement :-
The cement shall conform to I.S. 269-1967 and subsequent
revisions for Portland Cement and I.S. 1489-1976 and subsequent
revisions for Pozollana cement.
All cement required for the work under this contract shall be
procured well in advance by the contractor in polythene bags of
twenty to a metric tones received from the cement factories. The
cement bags shall be branded by words ―GOVERNMENT OF
MAHARASHTRA‖ with 80-mm high and 15-mm thin letters on
one side of bag. The contractor shall by written application collect
the authorization letter indicating contract number, quantity of
cement, from the Engineer-in-charge to the Government approved
cement factory, from where the contractor intends to purchase the
cement to brand the cement bags as stipulated above.
Following cement factories have been approved by the
(1) ACC Ltd, (2) Manikagadh, (3) L & T, (5) Rajashree,(6)
Narmada.
The contractor shall produce proof of purchase of cement from the
cement factories. The purchase bill supported by Delivery Challan
and Excise Gate Pass shall constitutes adequate proof of purchase.
Cement shall be stored in such a way as to allow the removal and
use of cement in chronological order of receipt i.e. first received
being first used.
- 120 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Cement shall be kept in store under double locking arrangement
(one lock to be operated by contractor and second lock to be
operated by the authorized person of) so that it can be taken out or
fresh stock admitted with the knowledge of supervising staff of the
watch and ward of the cement stores shall be the responsibility of
the contractor.
In the event of cement in branded bags remaining surplus due to
authorized reduction in quantity of work certified by the Engineer-
in-charge and as noticed after the issue of completion certificate,
the contractor may choose either of the following three alternatives:
- To transfer the cement in branded bags, with prior written
permission from the Engineer-in-charge, to any of the contract work
with the Government and account for the same therein.
- To sell the cement in branded bags with prior written permission
from the Engineer-in-charge, to any of the contractors carrying out
the works on contract with the Government at a price to negotiated
by both the contractor and account for the same.
- To sell the cement in branded bags with prior written permission
from the Engineer-in-charge, to the Government at the Ex-factory
price + Sales Tax + Octroi, if any + delivery at Government
godown as directed by the Government. The Government will
accept the cement in branded bags only if the same is as per the
specifications and of acceptable quality.
- For works costing loss than Rs. 50 lakhs, cement shall be
supplied by Government at the rates and places of delivery as
specified in schedules.
15. LABORATORY FOR TESTING WORK :-
Whenever the testing of materials, concrete mixes, mortar and also
of foundations of completed works are required as per the detailed
specifications or otherwise required by the Engineer-in-charge, the
same shall be carried out at the laboratory, selected by the
Engineer-in-charge at Government‘s cost and the results given by
the laboratory shall be considered correct and authentic by
contractor.
The material, mixes and any other arrangements, including laborers,
shall be supplied by the contractor to the Government free of cost.
The samples for testing shall be taken in the presence of Engineer-
in-charge or his representative present on site.
- 121 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
The contractor or his authorized representative shall have free
access in these laboratories, to get himself satisfied about procedure
of testing etc. Even if the contractor or his representative fails to
remain present while collecting samples or testing the results will
be considered as authentic and binding on the contractor.
Quality of Supply & Testing :
1. All materials supplied shall be strictly as per specifications laid
down and in strict accordance with and as per I.S.I. standard and the
test shall give result on parameters and recommendation as below
(ANNEXURE-I)
2. The contractor should submit the test Certificates/reports (as
detailed above from the manufacture‘s /from whom the supply is
effected for respective quantity of material i.e. conversion
Agent/I.S.I. approved rolling mills.
3. The material should be tests to I.S.I. specification. The third party
inspection and testing and steel bars got done through one of the
following agencies.
1. Lioyd‘s Register Industrial Services (I) Ltd, Mumbai.
2. Certification Engineers International Ltd, Mumbai.
3. Bureau Veritals Industrial Services (India) Pvt. Ltd, Mumbai.
4. S.G.S. India Ltd, Mumbai.
5. ITENG Engineers Pvt. Ltd, Mumbai.
6. Tata Consultancy Services.
7. Maharashtra Engineering Research Institute, Nasik. (MERI,
Nasik).
All the tests viz. for parameters (listed in Annexure-I) as specified in
the relevant Indian Standard shall be carried out by third party
Inspection and reports should be produced. For M.S.Round (I.S.
2062 Grade ―A‖) and Tor steel/CTD bars (S:1786) the physical and
chemical testing should be witnessed by the inspector or third party
inspecting agency and approval note should be given truck / trailer
wise by the third party inspecting agency. All the charges for the
same shall be borne by the Contractor.
16. HIRE OF CONSTRUCTION EQUIPMENTS :-
Construction equipment owned by the Government if available and
can be given on hire conveniently, will be made available on
specific request, to the contractor at rates that will be prescribed by
Government from time to time. Supervision charges will also be
levied as prescribed by the Government from time to time. The
contractor shall executive the agreement bond as prescribed by the
Government, and shall agree to the specific rates of hire and
supervision charges in force on the day of transaction of writing
before machinery is taken out of the Government‘s yard by him.
- 122 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
The contractor shall pay irrevocable bank guarantee for a value
equal to 25% of the cost of the similar new machinery; for a period
equal to period of hire plus three months. Some such items of
equipment are indicated below.
Rated Equipment
i) Tankers
ii) Diesel road rollers
iii) Tippers
iv) Dozers
v) Loader
vi) Seismopactor
The machinery shall be entirely in the custody of the Government.
It shall be issued to the contractor at the yard where they are
stationed. The machinery will not be allowed to leave the work area
on any account. All machinery so hired will be entirely operated
and maintained by the Government in consideration of the hire
charges to be paid by the contractor.
If any equipment is to be used in excess of 8 (eight) hours per day,
permission of the Engineer-in-charge shall be obtained in advance.
Reckoning of working hours will start from the time the machinery
leaves Government yard, where it has to return to it daily, and in
other cases, when the machinery actually starts working. Closing
time of working will be when it returns to the Government yard or
actually ceases working for the day, respectively.
Log books shall be maintained by the Engineer or his authorised
representative for each place of equipment in the form laid down by
the Engineer. The contractor or his duly authorised agent shall
verify and sign in the log book or on the machinery duty slip in lieu
thereof, daily. If the contractor‘s representative fails to sign the log
book, the entries made by the Government representative, shall be
binding on the contractor. Arty complaint or representation
regarding the recorded working hours must be submitted in writing
within 24 (twenty four) hours of the close of the shift. The
Engineer‘s decision regarding such disputes pertaining to working
hours shall be final and binding on the contractor. Complaints or
representations made after lapse of 24 (twenty four) hours limit
shall not be considered. The logbooks shall form the basis for
raising debits against the contractor.
- 123 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
All expenses in respect of oil, fuel, grease, cotton waste etc. shall be
borne by Government of Maharashtra. Crew operating the
equipment shall be provided by the Government of Maharashtra.
All minor and major repairs shall be carried out by the Government,
to keep the equipment in working condition. However, in case of
any breaking, damages, slips etc. which may occur due to the
negligence of contractor‘s labour equipment or staff or by reason,
for which Government personal are not responsible, the cost of such
damages shall be recovered from the contractor from the contractor.
The decision regarding fixing or responsibility for any damages
shall rest with the Engineer-in-charge and decision given by him
shall be binding on the contractor.
Equipment shall be given on hire only when these can be spared.
No claim on account of sickness or non-availability of machinery
shall be entertained.
In case of damages to the equipment during haulage to site of work
from Government stores or servicing yard, full cost of repairs shall
be recovered from the contractor when damages is due to rough
handling. That damage to trucks / tipper due to bad haulage roads
will also be recovered from the contractor. Decision of the
engineer-in-charge regarding of repairs and cause of damage shall
be final and binding on the contractor.
A truck, tipper, tanker and any other equipment may be hired for a
single day at a time and the minimum charges to be levied will be 8
(eight) hours plus mileage or for 8 (eight) hours when mileage is
not applicable.
Compressor and concrete mixers shall not be hired for less than a
day time and minimum charge for hire will be that for four hours
per day. Crusher shall not be hired for a period less than a month, at
a time. The minimum charges for hire will be those for 25 (twenty
five) day and 8 (eight) hours per day.
17. BILLS AND PAYMENTS :-
1) The contractor shall carry out the work his own funds and shall
deploy all necessary resources such as labour, material
machinery etc. On the work and shall carry out the contract
work as per construction programme, so as to complete the work
within the contract period. The contractor shall not claim
any amount in the view of above condition. Completion of work
payment for the executed shall be made to the contractor as per
availability of funds with the department. This payment is also
- 124 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
likely to be delayed due to shortage of funds of this work. The
contractor shall be will aware of this financial status of
department. Any claim on delayed payment such as interest etc.
shall not be entertained by the department. This condition shall
be noted by the contractor in advance while tendering the work.
2) Measurement shall be recorded in same month when works are
carried out, contractor shall not claim any price escalation on the
basis of date of payments of bill and price index thereof. Price
index on the actual period of work done shall only be applicable
irrespective of date of payment.
3) In case of financial crisis or any other reason department. Pune
or its successor reserve the right to withdraw the work under
contract clause no. 15. The initial levels before starting the work
/ foundation level/ final measurement / final levels shall be taken
by the authorised Engineer of the department. In the presence of
contractor or his authorised representative and the same shall be
got attested from the Engineer-in-charge or his authorised
representative in token of acceptance.
4) The format of running bill on which the bills are to be submitted
by the contractor will be supplied to the contractor by the
Corporation. Printed copies of the bill forms as per this format
shall be arranged by the contractor at his cost. The bills in five
copies shall be submitted to the concerned. Asst. Engineer /
Sub-Divisional Engineer / Sub-Divisional Officer, in the
standard pro-forma only.
5) The final bill shall be submitted within one month of the date of
issue of completion certificate.
18. SECURITY DEPOSIT :-
The security deposit accumulated from deductions from the running
account bills may from time to time and at any time, on application
by and at the cost of the contractor, be converted into interest
bearing Government securities, approved by and in the name of the
Government. Should the market value of the securities fall, for any
reason whatsoever below that specified, the contractor shall make
good the same in cash or as may otherwise by acceptable whenever
called upon to do so or to replace the security by other acceptable to
the Engineer-in-charge.
The contractor shall bear all charges for commission and brokerage
incidental to the purchase, safe custody, withdrawal and collection
of interest on these securities.
- 125 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
19. NO INTEREST ON MONEY DUE TO THE
CONTRACTOR :-
No omission by the Engineer to pay the amount due upon
measurements or otherwise shall vitiate or make vold the contract
nor shall be contractor be entitled to interest on any guarantee bond
or payment in arrears nor on any balance which may on the final
settlement of his account be found due to him.
20. OTHER CONTRACTOR FOR THE WORK :-
Government has the right to split-up the project work detailed
in the work and site condition, into district items and this
contract shall apply only to those items which shall have been
specified in this contract.
Should Government enter into other contractors for specified items
of the project work each contractor shall co-operate with others to
the fullest extent and shall allow others every facility and co-
operation for execution of their works simultaneously and
satisfactorily, as intended in the designs, specifications and
drawings.
Should there be a dispute or disagreement between the contractors
for any cause whatsoever, the same shall be referred to the
Engineer-in-charge whose decision regarding the co-ordination, co-
operation and facilities to be provided by any of the contractors to
others shall be final and binding on all parties and such a decision
shall not vitiate any contract nor absolve the contractor of his
responsibilities under the contract nor form the grounds for any
claim of compensation.
21. CONTRACT DOCUMENTS AND MATTERS TO BE
TREATED AS CONFIDENTIAL :-
All documents correspondence, decisions and other matters
concerning the contract shall be considered as of confidential and
restricted nature by the contractor and he shall not divulge or
allow access thereof to any unauthorised person.
22. ACCESS TO THE CONTRACTOR‟S BOOKS :-
Whenever it is considered necessary by the Engineer-in-charge to
ascertain the actual cost of execution of any particular item of
worm or supply of plant or material he shall direct the contractor
to produce the relevant documents, such as payrolls, records of
personal, invoices of materials and any and all other data and
documents relevant to the item or necessary to determine its cost
- 126 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
etc. and the contractor shall when so requirement furnish
information, pertaining to the aforesaid items in the mode and
manner that may be specified.
23. BREACH ON PART OF GOVERNMENT NOT TO ANNUAL
CONTRACT :-
No breach or non-observance on the part of Government of may
of the conditions contained herein shall annual this contract or
discharge the contractor from the observance and performance
thereof, but on application to the Engineer-in-charge, an extension
of time may be given to the contractor in respect of such breach or
non-observance by the Government, which shall be governed by
Clause 6 of B-1 form.
The contractor shall not however, be entitled to consideration or
any extension of time for any item of the work unless the
contractor shall have made an application in writing to the
Engineer-in-charge within one month of the arising of the cause
needing such extension, but the Engineer-in-charge may at his
discretion, which shall be conclusive, waive the condition
regarding this period of one month.
24. LOCAL LAWS :-
All local laws in force at the time entering into the contract and
those enacted thereafter shall be binding on the contractor and he
shall abide by the same.
All import and excise duties, sales tax, local panchayat tax and
other taxes shall be home by the contractor and they shall be
doomed to have been covered by his quoted tender rates, except
that the contractor shall not be liable to any land tax for the land
handed over to him for the operation in connection with this
contract or for his colony or appurtenant works constructed by
him for the purpose of this contract.
The contractor shall also be liable to all relevant provisions of the
Indian Income Tax Act, which may be applicable to him from
time to time.
The contractor shall protect and indemnify Government against
all claims or liabilities arising from or based on the violation of
such laws, ordinances regulation, bylaws by him or his employee.
25. PERSONNEL OF THE CONTRACTOR :-
The contractor shall at all times, maintain on the work, a staff of
duly qualified engineers and supervisors of sufficient experience
- 127 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
of similar other jobs, to assure that the quality of work turned out
shall be as intended in the specifications. The contractor shall also
maintain at the work, a works Manager of sufficient status,
experience and officer, and duly authorize him to deal with all
aspects of the day to day work. All communications to and
commitments by this works Manager shall be absolutely binding
on the contractor. Also he should have decision pareses to carry
out the work as per instructions of Engineer-in-charge.
The contractor shall supply to the Engineer-in-charge details of
names, qualifications and experience in regards of all supervisory
staff employed by the contractor and notify changes when made,
and satisfy the Engineer-in-charge regarding the qualify and
sufficiency of staff thus employed.
The Engineer-in-charge will have the unquestionable right to ask
for changes in the quality and number of contractor‘s staff. The
contractor shall on the written directives of the Engineer-in-
charge, remove from the works any person employed thereon,
who may in the opinion of the Engineer-in-charge be incompetent
or has misconduct himself. Such person shall not be employed
again, on the work, without the written permission of the
Engineer-in-charge. The contractor shall have to submit
information regarding proof of payment of Professional Tax and
the clearance certificate in format vide Appendix ―I‖.
26. DEATH, BANKRUPTCY ETC. :-
If the contractor shall die or commit any act of bankruptcy or
being Government of Maharashtra commences winding up except
for reconstruction purpose of carry on its business under a
receiver, the executors, successors or other representative in Law
of the estate of the contractor or any such receiver, liquidator any
person in whom the contract may become vested, shall forthwith
give notice thereof in writing to Government and shall for one
month during which lie shall take all reasonable steps to prevent a
stoppage of work, have the option of carrying out his contract
subjected to his or their providing such guarantee as may required
by Government but not exceeding value of work for the time
being remaining unexecuted. In the event of stoppage of work, the
period of option under this clause shall be fourteen days only
should the above option be not exercised, the contractor may be
terminated by Government by notice in writing to the contractor.
The power and provisions reserved to Government in this contract
of taking of the work out of contractor‘s hand shall immediately
- 128 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
become operative. Copy of such notice shall be pasted on work
site and advertised in newspaper.
27. NOTICES, HOW TO BE GIVEN. :-
Where any legal or other notice or any other document or any
other direction is to be given to or served upon the contractor, it
shall be deemed to be duly given or served, if it shall have been
either delivered to him personally or to his recognized agent or
Works Manager (including in the case of company, the Secretary
of such Company) or delivered at or sent through the post,
addressed to the last known place of business, or abode of the
contractor, a notice or other documents which shall he so given to
or so served on any one of the partners in such firms, shall be
deemed to have been given or served on all them.
Work order Book :-
The contractor shall maintain bound work order book at work
sites as the Engineer-in-charge may direct. The work order books
should have pages in triplicate. The contractor shall make them
available to the Engineer-in-charge or his representative,
whenever called for.
Executive Engineer or his representative may record order about
works in this book, leaving the original copy in the book and
remove the second and third copy with him. The contractor or his
authorised representative shall also sing this work order, in token
of its acceptances.
All orders recorded in this work order book shall be deemed to
have been served on the contractor. On completion of the work all
the work order booked may be handed to the Executive Engineer.
In the event of refusal of the Contractor‘s representative on the
spot to sign the work order book, Engineer-in-charge shall take
the necessary further steps in respect of further communication
and control, modification or stoppage or work as deemed fir at the
entire responsibility of the contractor.
PASSING OF FOUNDATION ETC. :-
After the completion of work of execution, the same will be
checked and passed by the Executive Engineer. No masonry or
concrete or back filling shall be laid unless the foundation is
passed. No concreting shall commence unless the centering and
the reinforcement is checked and passed by the Engineer-in-
charge.
- 129 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
28. REFERENCE TO STANDARD SPECIFICATIONS. :-
The specifications of the work as enclosed with this contract are
drawn with a specific reference to site conditions and do not every
where include the details of standard tests and procedures, which
are already laid down and available in the current Indian Standard
Specifications. Whenever such details are not specified in this
contract, provisions under the current Indian Standard
Specifications and or the Standard Specification (1970) of Govt.
of Maharashtra shall be deemed to be applicable.
29. COMMUNICATIONS AND NOTICES BY CONTRACTORS.
:-
All communications and / or notices pertaining to works and
concerning matters. Such as passing and approving of foundation,
reinforcement and form work measurements, mark outs, etc. shall
not be addressed by the contractor to an officer below the rank of
Sub-Divisional Officer. All such notices communications, etc.
shall be addressed in good time so as not to hold up the work.
30. NON-COMPLIANCE OF CONTRACT CONDITIONS. :-
It the contractor shall neglect of fail to proceed with the works,
with due diligence or he violates any of the provisions of the
contract, the Engineer-in-charge may give notice to the contractor,
identifying deficiencies in performance and demanding corrective
action. The Engineer-in-charge shall also clearly state in the
notice the nature of action, that shall be taken, if contractor fails to
fulfill by necessary corrective action.
Depending on nature of default the Engineer-in-charge at his
discretion shall have two options, regarding action to be taken in
case of default by contractor. He shall withhold any of the
payment due to the contractor or shall terminate the contract in
whole or in part. But Engineer-in-charge shall clearly mention in
his notice, the action that shall be taken if the contractor fails to
take the corrective action. The period of 14 days shall be given to
the contractor to take such corrective action after the issue of such
notice.
No claims, for compensation of any sort, from contractor will be
entertained for withholding the bills indefinitely till specified
requirements are complied with by the contractor.
After the issue of the notice about default by the contractor, the
contractor shall not remove, from the site any plant, equipment
and materials. The Government shall have a lien on all such plant,
- 130 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
equipment‘s materials, from the date of such notice, till
deficiencies have been corrected.
31. EXTRA ITEMS. :-
Extra item of work shall not vitiate the contract. The contractor
shall be bound to execute extra items of works as directed by the
Engineer-in-charge. The rates for extra items will be governed by
the provisions of Clause 14 and 13 of conditions of contract.
[Reference- As per Govt. Resolution Public Works Department No.
CAT06/04/148/Buildings-2, Dated 16/5/2005]
32. PRICE VARIATION CLAUSE. :-
ACCOMPANIMENT TO THE GOVERNMENT RESOLUTION PUBLIC
WORKS DEPARTMENT NO. CAT/06/04/148, DATE :- 16/5/2005
PRICE VARIATION CLAUSE
If during the operative period of the contract as defined in condition
(i) below, there shall be any variation, in the Consumer Price Index (New
Series) for Industrial Workers for Nashik centre as per the Labour Gazette
published by the Commissioner of Labour, Government of Maharashtra and/or
in the whole-sale Price Index for all commodities prepared by the Office of the
Economic Advisor, Ministry of Industry, Government of India, or in the price
of petrol /oil and lubricants and major construction materials like bitumen,
cement, steel, various types of metal pipes, etc. then subject to the other
conditions mentioned below, price adjustment on account of
(1) Labour component
(2) Material component
(3) Petrol, Oil and Lubricants component
(4) Bitumen component
(5) HYSD & Mild steel component
(6) Cement component
(7) C.I. and D.I. Pipes component
- 131 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Calculated as per the formula hereinafter appearing, shall be made. Apart
from these, no other adjustments shall be made to the contract price for any
reasons, whatsoever. Components percentage as given below are as of the total
cost of work put to tender. Total of labour, material & POL, components shall
be 100 and other components shall be as per actual.
1. Labour component - K1 ( 64 %)
2. Material component – K2 ( 29 %)
3. Petrol, Oil and Lubricants component – K3 ( 07 %)
TOTAL --- 100%
4. HYSD & Mid Steel components
5. Cement components
Note :- If cement, steel, bitumen, C.I. and D.I. Pipes are supplied on Schedule
‗A‘ then respective components shall not be considered. Also if particular
components is not relevant same shall be deleted.
1. Formula for Labour Component :
V1= 0.85 x P x [ (K1/100) x ( L1-L0)/L0]
Where,
V1 = Amount of price variation in Rupees to be allowed for Labour component.
P = Cost of work done during the quarter under Consideration the cot of cement
MINUS HYSD and Mild Steel, bitumen, C.I. & D.I. Pipes calculated at the
basic star rates as applicable for the tender, consumed during the quarter under
consideration. (These star rates shall be specified here)
K1 = Percentage of labour component as indicated above.
Lo = Basic consumer price index for Nashik centre shall be average consumer price
index for the month preceding the month in which the last date prescribed for
the receipt of tender, falls.
- 132 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
L1 = Average consumer price index for Nashik centre for the quarter under
consideration.
2. Formula for Materials Component :
V2= 0.85 x P x [ (K2/100) x (M1-M0)/M0]
Where,
V2 = Amount of price variation in Rupees to be allowed for Materials component.
P = Same as worked out for labour component.
K2 = Percentage of material component as indicated above.
Mo = Basic wholesale price index shall be average wholesale price index for the
month preceding the month in which the last date prescribed for the receipt of
tender, falls.
M1 = Average wholesale price index during the quarter under consideration.!
3. Formula for Petrol, Oil and Lubricant Component :
V3 = 0.85 x P x [K3 /100 x (P1-P0)/P0]
Where,
V3 = Amount of price variation in Rupees to be allowed for POL component.
P = Same as worked out for labour component.
K3 = Percentage of Petrol, Oil & Lubricant Component.
P0 = Average price of HSD at Mumbai during the month preceding the month in
which the last date prescribed for the receipt of tender, falls.
P1 = Average price of HSD at Mumbai during the quarter under consideration.
4. Formula for Bitumen component :
V4 = QB (B1 - B0)
Where,
- 133 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
V4 = Amount of price variation In Rupees to be allowed for Bitumen component.
QB = Quantity of Bitumen (Grade …..) in metric tone used in the permanent works
and approved enabling works during the quarter under consideration.
B1 = Current, average ex-refinery price per metric ton of Bitumen (Grade ---) under
consideration including taxes (octroi, excide duty etc.)
B0 = Basic rate of Bitumen in rupees per metric tone as considered for working out
value of P or average ex-refinery price in rupees per metric ton including taxes
(octroi, excise, sales tax) of bitumen for the grade of bitumen under
consideration prevailing quarter preceding the month in which the last date
prescribed for receipt of tender, falls, whichever is higher, whichever is higher.
5. Formula for HYSD and Mild Steel component :
V5 = So (SI1 - SI0)
. -------------------------- X T
SI0
Where,
V5 = Amount of price variation In Rupees to be allowed for HYSD/ Mild Steel
component.
S0 = Basic rate of HYSD/Mild Steel, in rupees per metric tonne as considered for
working out value of P.
SI1 = Average Steel Index as per RBI Bulletin during the quarter under
consideration.
SI0 = Average of Steel Index as per RBI Bulletin for the month preceding the month
in the last date prescribed for the receipt of tender, falls
T = Tonnage of steel used in the permanent works for the quarter under
consideration.
- 134 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
6. Formula for Cement component :
V6 = Co (CI1 - CI0)
. ------------------------ X T
CI0
Where,
V6 = Amount of price escalation in Rupees to be allowed for cement component.
C0 = Basic rate of cement in Rupees per metric ton as considered for working out
value of P.
CI1= Average cement Index published in the RBI bulletin for the quarter under
consideration.
CI0 = Average of cement. Index published in the RBI bulletin for the month
preceding the month in which the last date prescribed for the receipt of tender,
falls
T = Tonnage of cement used in the permanent works for the quarter under
consideration.
7. Formula for C.I./D.I.pipe component :
V7 = Qd (D1 - D0)
Where,
V7 = Amount of price escalation in Rupees to be allowed for C.I./D.I.pipe
component.
Qd = Tonnage or C.I./D.I. pipes used in the works during the quarter under
consideration.
D0= Pig Iron basic price in rupees per toe considered for working out value of P.
D1 = Average pig lion price in rupees per tone during the quarter under
consideration (published by IISCO)
The following conditions shall prevail,
- 135 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
i) The operative period of the Contract shall mean the period commencing from
the date of work order issued to the Contractor and ending on the date on
which the time allowed for the completion of the works specified in the
Contract for work expires, taking into consideration the extension of time, if
any, for completion of the work granted by the Engineer under the relevant
clause of the Conditions of Contract in cases other than those where such
extension is necessitated on account of default of the Contractor. The decision
of the Engineer as regards the operative period of the Contract shall be final
and binding on the Contractor. Where any compensation for liquidated
damages is levied on the Contractor on account of delay in completion or
inadequate progress under the relevant Contract provisions, the price adjust-
ment amount for the balance of work from the date of levy of such
compensation shall be worked out by pegging the indices, L1, M1, C1, P1, B1,
SI1, and CI1 to the levels corresponding to the date from which such
compensation is levied.
ii) This price variation clause shall be applicable to all contracts in B1 / B2 & C
form but shall not apply to piece works. The price variation shall be
determined during each quarter as per formula given above in this clause.
iii) The price variation under this Clause shall not be payable for the extra items
required to be executed during the completion of the work and also on the
excess quantities of items payable under the provisions of Clause 38 of the
contract from B-1 contract as per current DSR with no revision in rate once
decided. The price variation clause shall be applicable with initial basic index
existing on the date when quantity exceeds/decreases more than 25% in
Schedule (part I) and in case of extra item the basic index on the date of
cropping up of extra items shall be applicable.
iv) This clause is operative both ways, i.e. if the price variation as calculated
above is on the plus side, payment on account of the price variation shall be
allowed to the contractor and if it is on the negative side, the Government shall
be entitled to recover the same from the Contractor and the amount shall be
deductible from any amounts due and payable under the contract.
- 136 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
v) To the extent that full compensation for any rise or fall in costs to the
Contractor is not entirely covered by the provision of this or other clauses in
the contract, the unit rate and prices included in the contract shall be deemed to
include amount to cover the contingency of such other actual rise or fall in
costs.
33. CO-ORDINATION WITH OTHER CONTRACTORS :-
The contractor should note that there will be other agencies
including the Department working on in the same for works other
than that included in this contract. The contractor shall co-operative
with these agencies of full extent and shall allow them reasonable
facilities and co-ordination for execution of work simultaneously
satisfactorily as intended in the contract conditions, specifications
and drawings.
Should there be a dispute or disagreement between the contractor
and the other agencies for any cause whatsoever, the same shall be
referred to the Engineer-in-charge whose decision regarding the co-
ordination and facilities to be provided by all contracting agencies
to the other shall be final and binding on all parties and such a
decisions shall not vitiated any contract not absolve the contractor
of his responsibilities under the contract, and shall not form the
ground for any claim or compensation.
34. UNDERTAKING UNDER CONTRACT LABOUR ACT. :-
The contractor shall furnish the undertaking towards
implementation of contract Labour Act as given in Appendix – F.
35. PHOTOGRAPHS OF THE WORKS. :-
The contractor will not be allowed to lake photographs showing
fieldwork or the general location of the work. The Engineer, may
however, at his discretion allow a few construction photographs to
be taken for the purpose of the contractor‘s record Prior approval of
the Engineer-in-charge should be obtained in such cases and also in
case such photographs are to be exhibited in public literature and
calendars etc. in all such cases, negatives of the photos shall be
submitted to the Engineer, after taking approved number of copies
and the negative will become the absolute property of the
Government.
- 137 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
36. DATA, DRAWINGS TO BE FURNISHED BY THE
CONTRACTOR. :-
a) Prior to the commencement of the work the contractor shall
submit to the Engineer-in-charge for approval, drawings or prints in
while ammonia paper of size 1020 mm x 690 mm or 510 mm x 345
mm as may be suitable, in triplicate, showing the location of major
plant, workshop, if any roadways, temporary bridges, unloading
facilities and storage yards etc. which he proposes to put at the site
and the contractor is supposed to plan with respect to the land
provided and it shall not be responsibility of the Government to
make available the land suitable to the plan submitted by the
contractor.
b) The contractor shall submit to the Engineer-in-charge for
approval within one month from the date of his receiving notice to
start work.
i) A layout plan of construction plants and equipment‘s for the
execution of the work which the contractor proposes to adopt at site
and
c) Any changes in the approved layout will be subject to further
approval from the Engineer-in-charge.
d) The approval of the drawings, however, will not relieve the
contractor of his responsibility from any errors or omissions.
37. FENCING, LIGHTING AND VENTILATION. :-
a) The contractor shall be responsible for the proper lighting,
fencing, guarding and necessary health and safety measures while
executing all works under this contract and for proper provision of
temporary roadways, guards, footways, fences, caution notices, etc.
as far as the same may be rendered necessary by reasons of the
work, for the accommodation of workmen, foot passengers or other
traffic and the owners and occupiers of adjacent property and of the
public and shall remain responsible for any accidents that my occur
on account of his failure to take proper and timely precaution.
b) Maintenance of Services :-
After all the work under this contract is completed and accepted as
such, in case the Engineer-in-charge so directs, the contractor shall
maintain the lighting, ventilation, communication facilities etc. up
to a date determined by the Engineer-in-charge, but not longer than
for a period of twelve months. All reasonable charges for such
maintenance otherwise not required by the contractor for his
- 138 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
purposes under the contract will be borne by Government. As
regards the reasonableness of such charges, the decision of the
Engineer-in-charge shall be final and binding on the contractor.
38. LIABILITY FOR ACCIDENTS TO PERSONS. :-
It shall be contractor‘s responsibility to protect against accidents on
the work site. He shall indemnify the Government against any
claims for damage to the property, injury to workers or any other
persons, death etc.
On the occurrence of an accidents resulting in death or which is so
serious as to be likely to result in death, the contractor shall within
24 hours, report in writing to the Engineer-in-charge, the facts
stating clearly about the circumstances in which accident has
occurred and the subsequent action taken. Other minor accidents
causing minor injuries and loss to property should be communicate
in writing, promptly to the Engineer-in-charge. In all cases the
contractor shall indemnify the Government against all losses for
damages resulting directly or indirectly from the contractor‘s failure
to report in the manner aforesaid. This includes penalty or fines if
any, payable by the Government as a consequence of failure to give
notice under the workmen‘s compensation Act of failure to conform
to the provisions of the said Act in regard to such accidents.
In the event of accident in respect of which compensation may
become payable under the Workmen‘s Compensation Act VIII, of
1923 including all subsequent modifications thereof, Engineer-in-
charge may retain the sums of money as may in the opinion of the
Engineer-in-charge be sufficient to meet such liability out of the
amounts payable to the contractor. These sums shall be recovered
from the immediate payment due to the contractor in one
installment or in more than one installment. The decision of the
Engineer-in-charge regarding this shall be final and binding on the
contractor. On receipt of award from the Labour Commissioner, the
balance amount shall be reimbursed to or recovered from the
contractor.
It should be noted that the Government is a Principal employer the
complete responsibility of compensation shall be on the contractor.
39. THE CONTRACTOR TO SUPPLY AND BE RESPONSIBLE
FOR THE SUFFICIENCY OF THE MEANS EMPLOYED. :-
The contractor shall supply and take upon himself the entire
responsibility of the sufficiency of the scaffolding, timbering,
machinery, tools, implements and generally of all the means
- 139 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
irrespective of whether such means may or may not have been
approved of or recommended by the Engineer-in-charge and the
contractor mush accept all risks of accidents or damages from
whatsoever cause they may arise, until the completion of this
contract.
40. COVERING OF WORK. :-
The contractor shall give not less than seven days notice in writing
to the Engineer-in-charge of the work which is proposed to be
covered up or placed beyond the reach of measurement so that the
measurement may be taken before the work is covered up or placed
beyond the reach of measurements. No work shall be covered up or
placed beyond the reach of measurements, before ensured that the
measurements of work to be covered up are recorded. Any work
covered up or placed beyond the reach of measurements without
such notice having been given or consent obtained, the same shall
be uncovered at the contractor‘s expenses and in default thereof no
payment or allowance shall be made for such work or for materials
with which the same was executed.
41. QUANTITIES OF WORK. :-
The quantities of work under the various items have been provided
as could be reasonably anticipated and estimated should be taken as
indicative only. The amount of work will depend upon the actual
conditions that will be encountered in the construction and the
results of detailed designs which will continue to be refined as more
field data and information comes to hand. If the work is started by
the Government, the quantities put to tender shall be reduced to the
extent, the work is done by the Government up to the date of
starting the work by the contractor, No claims due to reduction in
quantity on this account will be entertained.
42. ACCURACY OF LINES, LEVELS AND GRADES. :-
Setting Out :-
a) The contractor shall be responsible for the true and proper
setting out of the work and for the correctness of the position,
levels, dimension, and alignment of all parts of the work and for the
provisions of all necessary instruments, appliances and labour in
connection with this.
b) For the purpose 0 setting out, one permanent bench mark
shall be established by the Government near the site, the value of
which shall be given to the contractor, by the Engineer-in-charge on
demand by the contractor. Similarly the reference line in the form
- 140 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
of center line of junction wall and of some other components, if
found by the Engineer-in-charge for complete getting out of the
structure shall be given. All the setting out shall be with reference
to this bench mark and reference line.
c) If at any time during the progress of works the error shall
appear or arise in the position, level, dimension or alignment of any
part of the work, the contractor shall rectify such error to the
satisfaction of the Engineer-in-charge without any extra cost to the
Government.
d) The periodical checking of these by Government staff
shall not absolve the contractor of his responsibility regarding
accuracy. In case of deviation/the contractor shall make good to the
discrepancy at his own cost and without any compensation for the
additional work involved. Wherever such discrepancies, if any are
found to arise between the works of different contractors at the
junction of their works, the relative liability to set right their
respective discrepancies shall be fixed by the Engineer-in-charge,
whose decision shall be final and binding on the contractors
concerned. The Engineer-in-charge shall further have the
unquestioned right to rectify the discrepancies and recover the costs
from the contractor or contractors according to proportions as he
may consider reasonable.
e) It is responsibility of contractor to preserve the benchmark
and the reference points established for setting out.
43. EXCAVATED MATERIAL. :-
All the material available from excavation will be the property of
Government and shall be disposed off only as directly by the
Engineer-in-charge. The materials of approved quality available
from the excavation including that carried out by the Government
may be used by the contractor in the items of works included in
Schedule ―B‖ or for ancillary or preparatory work, free of cost Prior
approval of the Engineer-in-charge for such use shall, however, be
taken. The contractor shall make proper arrangements for soiling
out and stacking material of approved quality that ht proposes to
use as aforesaid. Government will be free to make use other
materials not required or not likely to be required for use by the
contractor as will be determined by the Engineer-in-charge.
The excavated material not to be used by the contractor as above or
stacked for his use, but remaining unused at site after completion of
works, shall be disposed off by the contractor at his own cost in a
- 141 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
manner and at place shown in the drawings or as and where the
Engineer-in-charge may direct.
The contractor should utilize material available from excavated
stuff for back filling
44. SAFETY MEASURES. :-
The contractor shall arrange for the safety in his operations as
required including the provisions in the safety manual published by
the Central Water and Power Commission, New Delhi (Jan. 1962
Ed.). In case the contractor fails to make such arrangements the
Engineer-in-charge shall be entitled to cause them to be provided
and to recover the cost thereof from the contractor. The following
are some of the measures listed, but the same are not exhaustive and
the contractor shall add to and suggest these precautions on his own
where necessary and should comply with the directions issued by
the Engineer-in-charge in this behalf from time to time and at all
times.
Providing protective head guard to workers in the works like deep
excavation to protect them against fall of overburden materials.
Getting the workers in such jobs periodically examined for chest
trouble due to too much breathing in fine dust.
Taking such normal precaution like fencing and lighting to
excavations or trenches, not allowing, nails or metal arts or useless
timber spread around, marking danger area for blasting whistles etc.
Providing sufficient suitable and safe accesses to all work spots
including ladders gangways, platforms, etc. avoiding naked wires,
etc. such would electrocute the workers.
Taking necessary steps towards training the workers concerned on
the use of machinery before they are allowed to handle thorn
independently and taking all necessary precautions in and around
areas where machines hoists and similar units are working.
45. MAINTENANCE. :-
After the works are completed in all respects in accordance with the
contract condition, a completion certificate will be issued by the
Engineer-in-charge.
From the date of issue of the completion certificates, till the expiry
of 12 calendar months, the contractor shall be liable for the
replacement of any part of plant or work found to be defective from
the causes arising from faulty materials or workmanship or other
- 142 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
causes, for which in the judgment of the Engineer-in-charge, the
contractor is responsible and for making good any damage arising
there from. Contractor has to maintain his staff / machinery @ site
of work during construction and also Adequate number of rotations
of water releases through canal after completion of work to
maintain designed canal discharge @ site of work to the disposal of
Engineer-in-charge.
If any problem arises during water releases at the said work
necessary work should be carried out @ contractors cost to
maintain designed discharge as per instructions of Engineer-in-
charge.
46. SUNDAY AND HOLIDAYS. :-
No work shall be done on weekly local holidays or on other
Government holidays duly Gazetted or on holidays observed by
local usage without the prior sanction of the Engineer-in-charge.
Withholding of such sanction shall not form any grounds for
compensation or extension of time limit.
If on the other hand, the Engineer-in-charge directs that the work
shall be proceeded with on days and during hours otherwise not
permissible under this contract the contractor shall proceed with the
works as directed, without in any way violating this contract or
forming any grounds for compensation or claim.
The contractor shall, in his dealing with labour at all times during
the period of this contract, have due regard to local festivals,
religious and other customs.
47. BANK GUARANTEE. :-
Bank guarantee shall be given shall be given on the stamp paper of
Rs. 50/- in the form prescribed by the Government. The bank
guarantee shall be valid for the entire period of contract till the date
of issue of completion certificate as prescribed under para No. 7 of
conditions of contract. It will be the responsibility of the contractor
to get validity of Bank Guarantee extended on the stamp paper of
Rs. 50/- at least one month prior to expiry date from time to time,
failing which the Bank Guarantee shall be en-cashed by the
Government well before expiry date or Bank Guarantee and cash
accrued will be at the disposal of the Government.
48. HANDING OVER OF WORK. :-
All the work and materials, before being finally taken over by
Government will be the entire liability of the contractor for
- 143 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
guarding, maintaining and making good any damages of any
magnitude. Interim payments made for such work will not alter this
position.
The handling over by the contractor and taking over by the
Executive Engineer or his authorised representative will be always
in writing of which copies will go to the Executive Engineer or his
authorised representative and the contractor. It is however,
understood that before taking over such work, Government will not
put it into regular use as distinct from casual or incidental one,
except as specifically mentioned elsewhere or as mutually agreed
to.
49. INSTRUMENTATION. :-
In case, it is proposed to have any instrumentation, in work, the
instruments and their accessories will be procured and installed by
the Government as per programme framed by the Engineer-in-
charge. Care should be taken by the contractor to protect these
instruments as well as their connections during various construction
operations. The contractor shall also extend all facilities for
installation and observation of these instruments. All the operation
required for facilitating the installation of the instruments shall
stand included in the relevant items of tender. No claim, however
shall be entertained due to any delay or obstruction that might be
created due to installation or observation.
50. INSPECTION OF WORKS. :-
The engineer or his duly authorised representative shall have at all
times full power to inspect the work, whenever in progress either on
the site, in the contractor‘s premises or the work site. Further,
contractor shall not without written authorization, permit entry on
site of work of any person except authorised representative of the
Government or the Engineer or the contractor‘s staff and labour
directly engaged on and in connection with the work.
The contractor shall at his cost, provide all necessary facilities for
proper inspection and supervision of the work gangways, platforms,
scaffolding and ladders, etc. of suitable dimensions and sufficiently
strong at appropriate location and all accesses to passages etc. shall
be well lighted and maintained in good order. The Engineer‘s
decision about the sufficiency and adequacy thereof shall be final.
The contractor shall, during working hours, maintain, supervisor of
sufficient training and experience to supervise various items and
operations of the work and the said supervisors shall remain present
- 144 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
during inspections of the Engineer. All orders and directions given
to such supervisors or other staff of the contractor shall be deemed
to have been given to the contractor directly. Further the Engineer
may, by due notice to the contractor, to be present on any specified
inspection and the contractor shall comply with such directions.
51. OPENING OUT WORKS. :-
Should the Engineer consider, if necessary, in order to satisfy
himself as to the quality of work the contractor shall at any time
during the continuance of the contract pull down or cut into any part
of the work, and make such openings into and to such an extent
through the same as the Engineer may direct and the contractor
shall make good the same at his cost and to the satisfaction of the
Engineer.
52. REMOVAL OF IMPERFECT WORK. :-
If it shall appear, that the work has been executed with unsound,
imperfect or of an inferior quality or otherwise not in accordance
with the contract documents, the contractor shall at his own cost
rectify, remove or reconstruct the same, wherein whole or in part as
may be, directed by the Engineer, whether or not, the value of nay
such work of material shall have been included in any payment
made to the contractor. The decision of the Engineer-in-charge shall
be final and binding on the contractor. The Executive Engineer
may, if he thinks fit, allow such work to be paid at reduced rates
and his decision will be final and binding, provided further that the
rates and his decision will be final and binding, provided further
that the rates fixed by the Engineer, be not acceptable to the
contractor, he shall have the option to replace the defective work or
materials with ones in accordance with the specified standards.
53. JURISDICTION OF COURT FOR DISPUTE. :-
Disputes, if any, arising out of his contract shall be subject to the
jurisdiction of the High Court of Mumbai, Bench at Aurangabad.
54. MODE OF PAYMENT OF THE QUANTITIES OF
EXCAVATION, MASONRY AND CONCRETE ITEMS
EXECUTED IN EXCESS OF 125%. :-
54.1 Clause No. 38 of B-1 Tender Form pertains to payment of
quantities of different items of Schedule ‗B‘ in excess of 125% of
the tendered quantities. It is to be clarified that in the case of items
of excavation in soft strata and hard strata. In the present tender,
this clause will become applicable only if the total quantity
excavation (i.e. quantity given in Schedule ‗B‘ Part-I, Excavation in
- 145 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
soft strata, quantity given for Excavation in hard strata) exceeds by
125% during execution. For payment of quantity executed in excess
of 125% of total quantity of execution following procedure will
apply.
Case 1 : Where quantity of excavation executed, exceeds 125% of total of
tendered quantity of items of excavation in soft strata and in hard
strata, but quantity executed of any one of the individual items is
less than or equal to the tendered quantity for the item. All the
excess quantity beyond 125% of total tendered quantity in items of
execution in soft strata, will be paid by revising the rate of only that
item where excess has occurred.
Case 2 : Where total quantity of excavation executed for both items
(excavation in soft strata and hard strata) exceeds 125% of the total
tendered quantity of items of excavation, quantity in excess of
125% of total tendered quantity will be distributed in the ratio of
Executed quantity of individual items of excavation
Total executed quantity of items of excavation in soft strata and
hard strata.
And will be paid by revising the rate of individual item as per
clause 38 (2), subject to the provision that the revision of rate will
be applicable only for the quantity of individual item executed
beyond the tendered quantity.
In case of executed quantity is less than 75% of the total quantity of
excavation in soft strata and hard strata, these will be treated on
similar lines as in case (1) and (2) above.
Case 3 : Where total quantity of all masonry items taken together exceeds
125% of the total tendered quantities of all masonry items, quantity
in excess of 125% of total tendered quantity will be distributed in
the Ratio of
Executed quantity of individual items of masonry
Total executed quantity of all masonry items taken together
And will be paid by revising the rate of individual item as per
clause 38 (2), subject to the provision that the revision of rate will
be applicable only for the quantity of ….
Individual item executed beyond the tendered quantity.
In case of executed quantity is less than 75% of the total quantity of
all masonry item taken together, these will be treated on similar
lines as in case (1) and (2) above.
- 146 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Case 4 : Where Total quantity of all concrete items taken together exceeds
125% of the total tendered quantities of all concrete items, quantity
in excess of 125% of total tendered quantity will be distributed to
the Ratio of
Executed quantity of individual items of concrete
Total executed quantity of all masonry items taken together
And will be paid by revising the rate of individual item as per
clause 38 (2), subject to the provision that the revision of rate will
be applicable only for the quantity of ….
Individual item executed beyond the tendered quantity.
In case of executed quantity is less than 75% of the total quantity of
all concrete item taken together, these will be treated on similar
lines as in case (1) and (2) above.
For payment of quantities in excess of 125% of tendered quantity
for items other than excavation, masonry and concrete item,
provision of clause 38 (2) of B-1 Tender Form will be applicable.
55. Mode of payment of excavation quantities in running bill and
final bill :
55.1 Payment of work done under items of excavation in soft strata and
hard strata will be made at 90% of the contract rate in R.A. bills for
all excavated quantities till the final designed cross section of
component as decided by the Engineer-in-charge is reached. The
component cross section as per design shall be deemed to have been
reached only if no work remains to be executed between the two
adjacent cross sections. 100% of payment of contract rate in
R.A.bills may be released only after the work of excavation is
completed between two adjacent cross section and in conditions
lengths from head reach to tail reach of canal. No intermediate
lengths will be considered.
Government reserve the right to change the location of different
components of works amend the layout due to any reason,
whatsoever, No claim of any nature due to above change shall be
entertained.
The information in connection with the works and worksite as well
as specifications are contained in this book of contract in general
and in three parts. viz. work and site conditions special conditions
and specifications for items of work in case of any discrepancy or
- 147 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
repugnance in the clauses in those sections following, priorities /
Interpretation will hold good.
a. Special conditions of contracts will prevail over work and site
conditions.
b. The specifications will prevail over special condition.
c. The works and site conditions, the special conditions of the
contract of the contract and specifications shall prevail over the
various clauses of B-1 tender form.
56. PROPOSED CONDITION RELATING TO INSURANCE :
Contractors shall take out necessary Insurance Policy / Policies
so as to provide adequate insurance cover for execution of the
awarded contract work from the ―Director of Insurance,
Maharashtra State, Mumbai 400 051.‖ Only it‘s postal address for
correspondence is ―264, MHADA, Opp. Kalanagar, Bandra (E),
(Tel. No. 6438403) (Fax) 6438461/6438690. Insurance Policy /
Policies taken out from any other company will not be accepted.
However, if the contractors desire to effect insurance with the
local office of the insurance company, the same should be under the
co-insurance cu servicing arrangements approved by the Director of
Insurance Company if the policy taken out by the contractor‘s is on
co-insurance basis. (G.I.F.60% and Insurance Company 40%) the
same will notes be accepted and the amount of premium calculated
by the Director of Insurance will be recovered directly from the
amount payable to the contractors for the executed contract work
which may be noted.
57. LABOUR CESS :-
Cess payable on building and other works for Labour welfare as
per =tÉäMÉ, =VÉÉÇ ´É EòɨÉMÉÉ®ú ʴɦÉÉMÉ, ¨ÉÆjÉɱɪÉ, ¨ÉÖƤÉ<Ç ªÉÉÆSÉä ¶ÉɺÉxÉ ÊxÉhÉÇªÉ Gò.
¤ÉÒºÉÒB-2009/ |É.Gò.108/EòɨÉMÉÉ®ú 7-+, ÊnùxÉÉÆEò 17 VÉÖxÉ-2010 an amount
equal to one percent an contract amount shall be deducted from the
payment of the contractor.
58. LIABILITY OF CONTRACT OF PAY THE ROYALTY :-
1) The contractor should pay royalty charges of construction
materials required for the and produce necessary paid vouchers,
then only as per produced vouchers the amount of Royalty charges
will be released as per item of Schedule ―B‖.
2) The rates of items mentioned in schedule ―B‖ are excluding royalty
charges. The items of royalty charges is taken separately. The
- 148 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
percentage quoted above or below will not be applicable to the of
royalty charges. The amount of royalty charges for this works is
Rs. 70.68/Cum. Contractor shall take this fact in consideration
while quoting this offer.
3) If rate royalty is increased by revenue department extra amount
due to increase in rate of royalty will be paid by contractor.
58.1 SPECIAL CONDITION OF THE CONTRACT @ SOIL
SAMPLES ETC :
i. Samples of the material (Soil, Murum, Rock, Rubble etc.)
required for testing from laboratory should be collected from
borrow area of quarried proposed or site of work by the contractor
in presence of concerned field officer not below the rank of Sub
Divisional Officer / Asstt. Engineer Gr.I of the work.
ii. Samples collected should be in sufficient quantity & manner
required as per norms of MERI.. Material like empty polythene
bags etc. & Labour required for collection of samples should be
provided by the contractor.
iii. All the samples collected by the contractor should be handed over
by the contractor in the laboratory in presence of concerned Sub
Divisional Officer / Asstt. Engineer Gr.I of the work.
iv. Arrangement of transportation of the samples collected for testing
from site of works to the laboratory should be made by the
contractor.
v. After submission of samples to the laboratory concerned Sub
Divisional Officer / Asstt. Engineer Gr.I of the work, should
personally inspect the work of testing of samples in the laboratory
for this purpose concerned Sub Divisional Officer / Asstt.
Engineer Gr.I should attend the laboratory frequently & observe
that the testing has been done satisfactorily.
vi. Above test result will be submitted by the laboratory to this office
by the Post.
59. Additional conditions regarding payment of royalty charges as per
Revenue & Forest Department notification dated 11.02.2010 & B & C
Department circular vide letter no. 1130, dated 15.02.2010..
1. The royalty charges i.e. Rs. 70.67 / Cum. are to be paid by the
Contractor to the Revenue authorities is the prime responsibility of
Contractor.
2. The Royalty charges recovered as per Clause 36 of B-1 Tender
Form stall be released to the contractor subject to the following
conditions.
a) Contractor shall submit proof of the payment of the royalty charges
to the concerned Revenue Authorities acceptable to the Engineer-
in-charge.
- 149 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
b) The total amount that can be released shall be limited to the actual
payment made as mentioned in the condition (a)
c) If the actual royalty charges are less than the amount withheld,
remaining amount shall be retained by the Government.
d) If the actual royalty charges are more than the amount withheld the
contractor shall pay the excess amount to the concerned Revenue
Authority without any burden on the Government.
e) The contractor shall indemnify Government towards payment of
the royalty charges.
60. VALUE ADDED TAX :
―The tender rates are inclusive of all taxes, rates and case and are
also inclusive of the leviable tax in respect of sale by transfer of
properly in goods involved in the execution of a work contract
under the provision of Rule 8 & 9 of Maharashtra Value Added Tax
(MVAT) Act 2005, for the purpose of levy of Tax‘.
a) Anti malarial and other health measures shall be as directed by the
Joint Director of Health Services. Punt.
b) Contractor shall see that the mosquitogenic conditions are not
created so as to keep vector population to minimum level.
c) Contractor shall carry out anti malarial measures in the area as per
guidelines prescribed under National Malaria Eradication
Programme and as directed by the Joint Director (M & F of Health
Services, Pune.)
d) In the case of default in carrying out prescribed anti-Malarial
measures resulting in increase in material incidence, contractor
shall be liable to pay Corporation, the amount spent by Government
on an anti-Malarial measure to control the situation in addition in
fine.
e) The contractor shall make sufficient arrangement of draining away
the sullage water as well as water coming from the bathing and
washing places and shall dispose of Hot-water in such a way as not
to cause any nuisance He shall also keep the premises. Clean by
employing sufficient number of sweepers.
The contractor shall comply with all rules, regulations, byelaws and
directions given from time to time by any local or public authority in
connection with this work and skill fees or charges which are leviable
on him without any extra cost of Corporation.
61. Water Availability Certificate :
Contractor shall obtain the water availability certificate for individual
dams included in lift diversion scheme No. 3 & 4, from Planning &
Hydrology, Nasik and submit the Water Availability Certificate to the
Executive Engineer, Minor Irrigation Division, Nasik before starting
the work of D.P.R.
- 150 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
62.1 The office building of Minor Irrigation Investigation (Tribal) Sub
Division, Nashik is old one and needs renovation so as to facilitate the
speedy work of this and other ongoing projects. The successful contractor
should execute at his cost, the renovation work of office building which
is originally a godown worth Rs. 3.00 Lakhs as per specifications and
instruction of Engineer-in-charge.
62.2 The successful contractor shall arrange to provide following special make
instruments, vehical as per latest specifications and latest
configuration/versions.
A) Computers with laser printers - 2 No.
B) Planimeter - 2 No.
C) Prismatic Compass - 2 No.
D) Tata Sumo Jeep with latest Version- 1 No.
The Contractor shall install / provide the above instruments in the office of
the Minor Irrigation Investigation (Tribal) Sub Division, Nashik working
under Minor Irrigation Division, Nashik within a period of two months
from the date of work order by the Executive Engineer. If contractor fails
to provide above mentioned in 62.1 & 62.2 within two months, the amount
of Rs. 12 Lakhs will b recovered from 1st R.A. Bill of Contractor. The
procurement of instruments/vehicle & renovation work of office building
will be done from the amount recovered. The above instruments supplied
by the contractor will be the property of GMIDC and will not be returned
to the contractor.
63. Taking prior permission for detail survey & Investigation in forest area
is a sole responsibility of the contractor.
64. Payment for the item no. 13, 14, & 15 is on the cess of work for ‗C‘ work,
‗D‘ Regulator, ‗E‘ Falls, ‗F‘ RHT works, ‗G‘ Bridge & ‗L‘ Earthwork
only.
65. (1) Service Tax :- Service tax will be paid to the contractor prevailing at
the time of payment of each R.A. Bill after submission of complete proof
of payment of service tax by the contractor. The present rate of service tax
is 12.36% of the Gross Amount of the R.A.Bill.
(2) Labour Cess paid by the contractor will be reimbursed to the contractor
after production of proof of payment to the concerned department.
- 151 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
VOLUME - II
GENERAL
CONDITIONS &
SPECIFICATIONS
- 152 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
GENERAL CONDITIONS
1) Income Tax or any other tax payable to Govt. shall be borne the contract.
2) There are other contractor‘s also doing the work in the area. Good relations
with other agencies is essential and in case of any dispute hampering the speed
and quality of work. The Executive Engineer decision is final and binding on
both or more contractors involved in the dispute.
3) The contractor shall execute the items in sequence of priority fixed by the
Engineer-in-charge or his authorised representative on site. The payment of
any other item executed by the contractor, other than sequence of priority shall
be with held till the items of priority is sequence are fully attended to by the
contractor.
4) All items in the contractor shall be paid at 90% of the tendered rate. The full
rate will not only be released in the final bill after successful completion of all
the works in the tender. Due to or other reason, if the contractor fails to
complete the work, the tender will be finalised @ 90% of the approved rate.
5) If the contractor fail to complete the work, his security deposit will be
confiscated.
6) Generally no extension will be granted to the work. However in extra ordinary
cases only one extension for one month will be granted.
7) After giving extension period too, if the contractor fails to complete the work
in the stipulated extension period, the tender work will be finalised as it is at
90% of the tendered approved rate with no claim on Govt.
8) The quantity shown in schedule ―B‖ may be less due to change in
departmental planning. If it is happened no compensation or claim will be
entertained for less quantity.
9) The contractor should visit the site and gate himself acquainted with the work
to be done. Condition of the area before quoting the tender.
10) Contractor will not have liberty to start the work anywhere he wants. The
Engineer-in-charge or his authorised representative will give him a programme
fixing the priority of work to be done. The contractor should followed the
instructions strictly. Due to one or other reason if contractor executes the
works of his own choose first, payment shall not be made unless he complete
the priority work shown by the Department.
11) The work is remained to be completed within the stipulated time only. Any
claim or liabilities on account of his work will not be entertained and
considered for payments.
- 153 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
SPECIFICATIONS
At the outset the consultant should frame a general layout of the entire
project by doing Toposheet study and after doing on the field
Reconnaissance. Various components of the project showing locations of
important structures like dams, canals, tunnels, power houses etc. should be
tentatively proposed. The possible alignment of canals, tunnels etc. should
also be proposed on the basis of the contours available on the Toposheets.
The static head available at the locations of different power houses should be
assessed on the basis of the levels available on the Toposheets and Rough
assignment of the possible capacity of Power Generation should be made.
On the basis of the contours available on the Toposheets an
assessment of the Command Area available for irrigation should be made.
After finalizing the tentative proposals as mentioned above the (as per
C.S.R.) rough cost of the projects construction should be assessed and the
Detailed Project Report on the basis of the tentative proposals should be
submitted to the Executive Engineer.
The item wise specifications are given hereafter. Mode of payment of
each item is also mentioned in the item wise specifications.
Measurement :- The unit for the measurement of the Quantity of majority of
items will be in No. The Quantity entered in Schedule ―B‖ is approximate.
The Quantity for payment will be the Quantity arrived in D.P.R. approved by
the Chief Engineer, North Maharashtra Region, Nasik.
- 154 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
GENERAL SPECIFICATION
ITEM NO. 1 :
Construction of P.B.M. in C.C. 1:2:4 of size 45 x 45 cm. and 75 cm. deep fixing G.I.
pipe of 50 mm. Dia at centre as directed, including excavation back filling trenches,
curing etc. complete with all leads and lifts as directed by Engineer-in-charge.
Construction of PBMs :
The PBMs shall be constructed by digging a Pit of the dimension 450 mm x
450 mm x 750 mm. at a location which is not likely to be disturbed.
The PBM should be located at one corner of the field, which will not hamper
obstruct the agricultural operations.
The Pit shall be refilled by concrete 1:2:4 and the concrete top shall be 75 mm.
above the ground level.
G.I. Pipe of 50 mm. dia about 200 mm. in length shall be embedded in the concrete,
and the top of the concrete shall be level with the top of the pipe. The ring of the
pipe which will be visible at the top indicates the position of levelling staff.
Adequate care shall be taken by the Consultant for curing of the concrete laid for the
PBM. The PBM shall be numbered in oil paint for its identification.
Mode of Measurements :-
The Unit for the measurement of the quantity of this item will be in No. The
quantity entered in Schedule ‗B‘ is approximate. The quantity for final payment will
be as per actual Final measurements.
Mode of Payment :-
(1) After Construction of P.B.M. backfilling etc. complete – 80%
(2) After submission of DPR to the Chief Engineer (W.R.), North
Maharashtra Region, Nashik - 15%
(3) After the Chief Engineer (W.R.), North
Maharashtra Region, Nashik, – 05%
- 155 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
ITEM NO. 2 :
Carrying out Benchmark by double leveling from GTS or any other benchmark
including submission of field books, PBM Register etc. as per directions of
Engineer-in-Charge along with digitized data stored in Compact Disk.
This quantity is tentative. The final quantity will be as per actual survey.
The Consultant shall have to establish the values of the PBMs constructed by him
from the bench mark value of the G.T.S. Bench mark. The values shall be
established by the Consultant. Separate field books shall be maintained by the
consultant for the survey of the PBMs. The permissible error shall not exceed the
least count of the standard levelling staves. The work of establishing the values of
the PBMs shall be carried out in advance of the field work. A representative of the
Department of the cadre of Junior Engineer will be present with the Consultant
while the PBMs are established. The B.M. will be checked by Department
simultaneously as far as possible.
A proper system shall be evolved for numbering the PBMs. A Plan (to a scale of
1:8000) including location and levels of all PBMs shall be prepared and submitted to
the Department for approval.
Mode of Measurements :-
The Unit for the measurement of the quantity of item will be in Km. The quantity
entered in Schedule ‗B‘ is approximate. The quantity for final payment will be as per
the actual measurements.
Mode of Payments :-
(1) After carrying out GTS Benchmark and submission of Field book to Sub
Division – 60%
(2) After submission of digitized data stored in Compact Disk - 20%
(3) After submission of DPR to the Chief Engineer (W.R.), North Maharashtra
Region, Nashik –10%
(4) After the Chief Engineer (W.R.), North Maharashtra
Region, Nashik, – 10%
- 156 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
ITEM NO. 3 :-
Excavation for trial pits in earth and soil of all types sand, gravel, soft murum, Hard
murum & Soft Rock including removing the excavated material up to a distance of
50m. beyond the trial pit & stacking & as directed, dewatering &
necessary backfilling, ramming and watering including shoring & strutting etc.
complete.
The Trial pit excavation is of 1.50m x 1.50m. size & up to 2.50m. depth or upto hard
strata, if hard strata is met within the 2.5 m. depth as per Classification and refilling,
the Trial Pit, as per directions of the Engineer-in-charge.
Mode of Measurements :-
The Unit for the measurement of the quantity of this item will be in Cum.. The
quantity entered in Schedule ‗B‘ is approximate. The quantity for payment will be as
per actual measurements.
Mode of Payment :-
(1) After Trial pit Excavation – 60%.
(2) Strata verification by Dept. & refilling the Trial pits - 20%.
(3) After submission of DPR to the Chief Engineer (W.R.), North Maharashtra
Region, Nashik –15%.
(4) After the Chief Engineer (W.R.), North Maharashtra
Region, Nashik, – 05%
- 157 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
ITEM NO. 4 :-
Taking trial bores for detailed investigation, 75mm boring, including all materials
such as casing pipe & accessories, grease & other such materials as required
including conveying such materials & machinery to the site of work, preserving the
loose samples in glass or plastic jar/core samples serially numbered at the site of
work & conveying the same to the head quarter of the concerned office as directed
etc. complete as directed by Engineer-in-charge.
General :- Trial bores of the specified diameter shall be taken to the required depth
to ascertain the strata below ground level. The diameter of the bore refers to the
diameter of the core.
Boring rig and operation :- boring Rig of standard make Hydraulically operated
capable of taking out cores up to 50 M. depth should be used. It shall be such as to
give core samples of the required diameter. Only experienced operators who know
proper handling of the machine, careful collection of the cores and samples, and
correct logging of the operation shall be employed. The equipment shall be set up at
predetermined location as directed by the Engineer. Boring shall be done from the
found action level to the required depth in the strata met with as directed by the
Engineer-in-charge.
Any water that will be met with shall be removed when ever necessary either by
pumping or by any other method. Suitable casing pipes shall be provided wherever
necessary to prevent collapse of the sides. The permanent mark shall be left to
indicate the location of the borehole.
The equipment shall be dismantled and removed from the site after boring is
complete.
Classification: - boulders, soft rock, hard rock and laterite as indicated by the core
recovered shall be considered as rock and all other strata including no recovery
portions shall be considered as strata other than rock, for the purpose of this item.
- 158 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
Item to include :-
(1) Carrying out core drilling.
(2) Dewatering, if any and necessary during the operation.
(3) Conveying, erecting the boring machinery, dismantling and removing
the same after completion.
(4) All labour, materials and use of equipment necessary to carry out the
item satisfactorily.
Mode of Measurements :-
The Unit for the measurement of the quantity of item will be in Rmt.. The quantity
entered in Schedule ‗B‘ is approximate. The quantity for payment will be as per
actual measurements.
(1) The contract rate shall be per running meter of the trial bore taken (1) in
rock and (2) strata other than rock separately. The diameter of the trial bore shall be
as mentioned in the wording of the item. The depth shall be measured correct up to
two places of decimals of a meter.
Mode of Payment :-
(1) After core logging – 60%.
(2) After Supplying core samples to Division office - 20%.
(3) After submission of DPR to the Chief Engineer (W.R.), North Maharashtra
Region, Nashik – 15%.
(4) After the Chief Engineer (W.R.), North Maharashtra Region, Nashik, – 05%
- 159 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
ITEM NO. 5 :-
Providing and supplying jungle wood core boxes, including labour, shutter fixtures,
locking arrangements of 100X45X10 cm in size with 12mm (1/2 ") thick planks,
without painting etc. complete with four longitudinal compartments, with all leads as
directed by Engineer-in-charge.
The core Boxes should be prepared from Good Quality Hard wood. The size of the
Core Box should be . x 45 cm. x 10 cm. made from 12 mm. thick planks.
There should be four longitudinal Compartments inside the Core Box. The Box
should have a shutter with necessary fixtures and locking arrangement.
Mode of Measurements :-
The Unit for the measurement of the quantity of item will be in Per No.. The
quantity entered in Schedule ‗B‘ is approximate. The quantity for payment will be as
per actual measurements.
Mode of Payment :-
(1) After supplying of the Box to Sub Division — 80%.
(2) After submission of DPR to the Chief Engineer (W.R.), North Maharashtra
Region, Nashik – 15%.
(3) After the Chief Engineer (W.R.), North Maharashtra Region, Nashik, – 05%
- 160 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
ITEM NO. 6:-
Providing Soil sample of size 10 cm. dia. and 40.65cm. Long, including lowering,
pressing the sample with mechanical jack, erecting platform, turning the sample,
sealing from the both ends, lettering, painting etc. complete with all leads and lifts
as directed by Engineer-in-charge.
Cores of undisturbed Soil samples of size 10cm dia shall be obtained in as long
lengths (40.65cm) as possible, and shall be preserved in Jungle wood boxes,
and disturbed samples in closed glass / plastic jars of suitable dimensions.
They shall be handed over to the Engineer. They shall always be accompanied by a
bore log showing.
a) Number and location of bore,
b) Date started
c) Date completed
d) Total Depth.
e) Depths at which various strata were encountered and description of the same
including boring time required to penetrate each kind of stratum.
f) Depth at which water was met with and
g) Standing level of water.
Mode of Measurements :-
The Unit for the measurement of the quantity of item will be in Per No. of sample.
The quantity entered in Schedule ‗B‘ is approximate. The quantity for payment will
be as per actual measurements.
Mode of Payment :-
(1) After submission of core samples to the Division Office- 60%.
(2) After submission of DPR to the Chief Engineer (W.R.), North Maharashtra
Region, Nashik – 30%.
(3) After the Chief Engineer (W.R.), North Maharashtra Region, Nashik, – 10%.
- 161 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
ITEM NO. 7 :
Bringing the soil samples from trial pits, to the Divisional laboratory including
loading, unloading, stacking & including cost of empty cement bags etc. complete as
directed by Engineer-in-charge
After The Strata wise Classification the soil samples should be collected in empty
cement bags and transported From Site to the Laboratory including loading &
Unloading, stacking in the laboratory as directed by Engineer-in-charge.
Mode of Measurements :-
The Unit for the measurement of the quantity of item will be in Km. of
transportation of samples from site to the Laboratory. The quantity entered in
Schedule ‗B‘ is approximate. The quantity for payment will be as per actual
Measurements.
Mode of Payment :-
(1) After the sample is collected and brought to laboratory - 80 %.
(2) After submission of DPR to the Chief Engineer (W.R.), North Maharashtra
Region, Nashik – 15%.
(3) After the Chief Engineer (W.R.), North Maharashtra Region, Nashik, – 05%
- 162 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
ITEM NO. 8 :
Laboratory Testing of disturbed / undisturbed samples including payment of testing
fee by contractor including attending laboratory, procuring and submitting of-:Soil
testing report to department in hard copies as well as two sets of CD in electronic
form as directed by Engineer-in-charge.
All Payment of testing fees and procuring and submitting the Soil Testing report to
the department and 2 set of scanned report copy in CD Format, should be borne by
the Contractor.
Mode of Measurements :-
The Unit for the measurement of the quantity of item will be in Set of Tests as per
Bills of the Laboratory. The quantity entered in Schedule ‗B‘ is approximate. The
quantity for payment will be as per actual Measurements.
Mode of Payment :-
After submitted the Testing report to Division Office. - 80 %.
After submission of DPR to the Chief Engineer (W.R.), North Maharashtra
Region, Nashik – 15%.
After the Chief Engineer (W.R.), North Maharashtra Region, Nashik, – 05%
- 163 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
ITEM NO. 9 :
Preparing drawing on Auto CAD with one proof print for following size on white
paper with black & coloured print providing tracing with saving on disc of following
size per number as directed by Engineer-in-charge as per following sizes.
Sizes A-0, A-1, A-2, A-3 and A-4.
Drawings should be prepared on AutoCAD Software as per the direction of
Engineer on Diff. scale and sizes as per requirement after preparation of CAD work,
taking one proof print on white paper for checking purpose. After finalization &
necessary correction, the Tracing copy & Soft copy in CD should be submitted.
Mode of Measurements :-
The Unit for the measurement of the quantity of item will be in No. of Drawings.
The quantity entered in Schedule ‗B‘ is approximate. The quantity for payment will
be as per actual Measurements.
Mode of Payment :-
(I) After submission of one proof Print to Division Office. - 50 %.
(2) After submitting the final Tracing copy along with CD. — 30 %.
(3) After submission of DPR to the Chief Engineer (W.R.), North
Maharashtra Region, Nashik – 15%.
After the Chief Engineer (W.R.), North Maharashtra Region, Nashik, – 05%
- 164 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
ITEM NO. 10 :
Printing of drawing on Auto CAD in following size on white paper with reproducing
papers from available source per number as directed by Engineer-in-charge as per
following sizes..
Sizes A-0, A-1, A-2, A-3 and A-4.
Printing Drawings on plane white paper on Diff. scale and sizes as per requirement
with submission of tracing on high quality reproducing paper.
Mode of :-
The Unit for the measurement of the quantity of item will be in No. of Drawings.
The quantity entered in Schedule ‗B‘ is approximate. The quantity for payment will
be as per actual Measurements.
Mode of Payment :-
After submission to the Division Office - 80 %.
(2) After submission of DPR to the Chief Engineer (W.R.), North Maharashtra
Region, Nashik – 15%.
(3) After the Chief Engineer (W.R.), North Maharashtra Region, Nashik, – 05%
- 165 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
ITEM NO. 11 :
Editing & correction on drawing & giving the prints on tracing paper with tracing
per number as directed by Engineer-in-charge, as per following sizes :-
Sizes A-0, A-1, A-2, A-3 and A-4.
Final Editing & Correction on Drawing in Autocad And Giving The Print On tracing
Paper
Mode of Measurement :-
The Unit for the measurement of the quantity of item will be in No. of Drawings.
The quantity entered in Schedule ‗B‘ is approximate. The quantity for payment will
be as per actual Measurements.
Mode of Payment :-
(1) After submission of the Prints to Division Office. - 80 %
(2) After submission of DPR to the Chief Engineer (W.R.), North Maharashtra
Region, Nashik – 15%
(3) After the Chief Engineer (W.R.), North Maharashtra Region, Nashik, – 05%
- 166 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
ITEM NO. 12 :
Dam, Tunnel
alignment, rising mains, river survey, dam alignment etc. including ranging,
chaining, pegging, taking bearing, distance and levels for preparing contour plan at
0.20 m. interval and submission of original field books to Department etc. complete
alongwith digitized data stored in compact disk including marking of electrical
poles, structure, village and forest boundaries, roads, huts etc., in the submergence
area by using with advance survey instruments, including clearing site etc. complete
as directed by Engineer-in-charge.
level
along with pegging of the levels required for forest proposal approximate
quantity of this Area is 1566.21 Ha.
2. Size of the grid shall be 15m. X 15m.
3. Survey shall be conducted with reference to permanent G.T.S. bench mark
which have already been carried by the Consultant and have been established
in the Submergence Area.
Mode of Measurements :-
The Unit for the measurements of the quantity of item will be in Hact . The quantity
entered in Schedule ‗B‘ is approximate. The quantity for payment will be as per
actual Measurements.
Mode of Payment :-
(1) After completion of Grid Survey, submission of Field Books with plotting on
drawing sheet, with one copy of 1:4000 map with contour Plotting — 70%
(2) After checking by Department (Executive Engineer), submission in C.D.
etc.-10%.
(3) After submission of DPR to the Chief Engineer (W.R.), North Maharashtra
Region, Nashik – 15%
(4) After the Chief Engineer (W.R.), North Maharashtra Region, Nashik, – 05%
- 167 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
ITEM NO. 13 :-
Fixing the capacity of dam with analysis of drain area including consideration of
existing and proposed Dams in catchment area, rainfall pattern, working out runoff
at site, fixing of various controlling levels & calculating drawdown levels, & finding
of approximate cross section of earthen dam, overflow & non-overflow sections of
dam including sub drainage system, rock toe details, calculations of stability of
masonry dam etc. complete as directed by Engineer-in-charge.
The storage capacity of the Reservoir should be worked out from the
Contour Map of the Submergence Area. Water Utilisation Planning should be made
by taking into account the existing dams, Rain fall, Run Off etc. and Water
Availability Certificate should be obtained by the contractor from the Planning &
Hydrology, Nasik. All controlling levels should be finalized after above exercise.
Mode of Measurements :-
The Unit for the measurement of the quantity of item will be in 1% Amount of cost
of Dams (Work portion only). The quantity (cost of Dam) entered in Schedule ‗B‘
is approximate. The quantity for payment will be as per the Final total Cost of Dam
arrived in DPR.
Mode of Payment :-
(1) After completing detailed survey of Dam line, fixing of various controlling
levels calculation of draw down levels, flood heights etc. - 60%
(2) After detailed design, of section, stability calculations etc. — 20%.
(3) After submission of DPR to the Chief Engineer (W.R.), North Maharashtra
Region, Nashik – 15%.
(4) After the Chief Engineer (W.R.), North Maharashtra Region, Nashik, – 05%
- 168 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
ITEM NO. 14 :-
Fixing preliminary alignment of tunnels as per the contour mapping in the GIS
environment so as to accomplish the flow of water through the tunnel/canal by
Gravity flow only. The alignment shall be marked on the GIS base map of the
Project including preliminary design of section of tunnel including alternative
alignments etc. complete as directed by Engineer-in-charge.
For diversion of water from one valley to another valley the intervening Ridge is
required to be crossed. Provision of Tunnel becomes necessary, when the open cut
becomes costly. Tunnels should be proposed in a straight line to ensure proper flow
of water by gravity. The length of Tunnel should be kept minimum provided
commensurate with economic cost, compared with the cost of the open cut.
Mode of Measurements :-
The Unit for the measurement of the quantity of this item will be in 1% Amount of
cost of Tunnel / Canal (Work portion only). The quantity
entered in Schedule ‗B‘ is approximate. The quantity for payment will be as per the
Final Cost of the Tunnel / Canal arrived in DPR.
Mode of Payment :-
After submission of preliminary alignment with alternatives if any, marking it
on GIS base map. - 50 %.
After design of section of finally approved alignment — 30%.
(3) After submission of DPR to the Chief Engineer (W.R.), North Maharashtra
Region, Nashik – 15%
(4) After the Chief Engineer (W.R.), North Maharashtra Region, Nashik, – 05%
- 169 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
ITEM NO. 15 :
Design and estimation of Lift diversion Scheme, Preparation of broad conceptual
report, general layout of pump house, rising main, delivery chamber, design and
analysis of frame of pump house, control room, service bay etc. Design
of delivery chamber, details of rising main, thrust block, anchor block, expansion
joint, manifold details etc. complete as directed by Engineer-in-charge.
The work includes Detail Design of diversion Scheme including the following
items.
1. Preparation of Broad Conceptual Layout.
2. General Layout of Pump house.
3. Design of Rising Main including Thrust Block & Anchor block design.
4. Design of Delivery Chamber.
5. Design of pump House alongwith Arrangement of Service Bay, and
control Room.
6. Design of manifold.
Mode of Measurements :-
The Unit for the measurement of the quantity of item will be as 1% Amount of cost
of The quantity entered in Schedule ‗B‘ is
approximate. The quantity for payment will be as per the Final Cost of the LIS
arrived in DPR.
Mode of Payment :-
After Submitting the Broad Conceptual and general Layout - 40 %
After Submitting The Design Report of Pump House, rising main, delivery
Chamber & Manifold Design - 40%.
After submission of DPR to the Chief Engineer (W.R.), North Maharashtra
Region, Nashik – 15%
After the Chief Engineer (W.R.), North
Maharashtra Region, Nashik, – 05%
- 170 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
ITEM NO. 16 :
Preparation of work of Detailed Project Report for getting Administrative Approval.
The work comprising of the layout, design and estimation of Dam and water
conducting systems such as Tunnels, Canals, Rising mains and presenting the details
of the Lift diversion scheme on the basis of the study of available Toposheets and
according to surveyed data etc complete as directed by Engineer- in-charge.
The work includes preparation of Detail Project report of diversion Scheme
including the following Items.
Layout , Design & Estimation of Dam.
Design & Estimation of Tunnel .
Design & Estimation of Rising Main , Delivery Chamber etc.
Preparation of Detail Project Report and compliance of remarks of the Chief
Engineer and the Managing Director, G.M.I.D.C. Aurangabad.
Mode of Measurements :-
The Unit for the measurement of the quantity of item will be in No. The
quantity entered in Schedule ‗B‘ is approximate. The quantity for payment
will be as per actual requirements.
Mode of Payment :-
1) After submitting the Detail Project Report to EE — 80%
2) After submission of DPR to the Chief Engineer (W.R.), North Maharashtra
Region, Nashik – 15%
3) After the Chief Engineer (W.R.), North Maharashtra Region, Nashik, – 05%
- 171 - ------------------------------------------------------------------------------------------------------
Godawari Marathwada Irrigation Development Corporation, Aurangabad
------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------
Contractor No.of Corrections Executive Engineer
DRAWINGS