draft gagan power plant site investigation...
TRANSCRIPT
DRAFT
GAGAN POWER PLANT
SITE INVESTIGATION REPORT
U.S. ARMY KWAJALEIN ATOLL/REAGAN TEST SITE (USAKA/RTS)
REPUBLIC OF THE MARSHALL ISLANDS
Site ID CCKWAJ-009
NOVEMBER 2011
Contract No. DASG60-03-C-0081
Prepared for:
U. S. Army Space and Missile Defense Command
Von Braun Complex
Building 5220
Redstone Arsenal, Alabama 35898
Prepared by:
3150 C Street, Suite 250
Anchorage, Alaska 99503
DISTRIBUTION STATEMENT A. Approved for public release. Distribution is unlimited.
[THIS PAGE LEFT INTENTIONALLY BLANK]
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site i November 2011
TABLE OF CONTENTS
EXECUTIVE SUMMARY ...........................................................................................................1
1.0 INTRODUCTION.......................................................................................................... 1-1
1.1 Project Information .............................................................................................. 1-1 1.2 Site Information ................................................................................................... 1-1
1.2.1 Previous Site Investigation ............................................................................ 1-1
1.2.2 Conceptual Site Model ................................................................................... 1-5 1.2.3 Investigation Approach .................................................................................. 1-5
1.3 Purpose, Scope, and Objective............................................................................. 1-5
2.0 SITE BACKGROUND AND PHYSICAL SETTING ................................................ 2-1
2.1 Site Location and Description .............................................................................. 2-1
2.2 Physical and Environmental Setting .................................................................... 2-1
2.2.1 Environmental Setting ................................................................................... 2-1 2.2.2 Climate ........................................................................................................... 2-2
2.2.3 Regional Geology .......................................................................................... 2-4 2.2.4 Soil Characteristics ........................................................................................ 2-4 2.2.5 Hydrogeology ................................................................................................ 2-5
2.3 Operational History and Land Use ...................................................................... 2-5
3.0 FIELD ACTIVITIES ..................................................................................................... 3-1
3.1 Site Activities ....................................................................................................... 3-1 3.1.1 Field Documentation ...................................................................................... 3-2 3.1.2 Soil Gas Survey.............................................................................................. 3-2
3.1.3 Field Soil Screening ....................................................................................... 3-4 3.1.4 Soil Sampling ................................................................................................. 3-5
3.2 Deviations ............................................................................................................ 3-7 3.2.1 Soil Gas Survey.............................................................................................. 3-7
3.2.2 Soil Sampling ................................................................................................. 3-7 3.3 Conceptual Site Model Revision ......................................................................... 3-7
4.0 SAMPLE MANAGEMENT AND LABORATORY ACTIVITIES .......................... 4-1
4.1 Sample Management ............................................................................................ 4-1 4.2 Quality Control .................................................................................................... 4-1 4.3 Laboratory Analyses ............................................................................................ 4-2 4.4 Validation and Data Quality Objectives (DQOs) ................................................ 4-2
4.4.1 Accuracy/Bias ................................................................................................ 4-3
4.4.2 Precision ......................................................................................................... 4-3 4.4.3 Comparability ................................................................................................ 4-3 4.4.4 Completeness and Data Usability .................................................................. 4-4 4.4.5 Representativeness ......................................................................................... 4-4
4.4.6 Sensitivity ...................................................................................................... 4-4 4.4.7 Data Validation Results ................................................................................. 4-5
5.0 RESULTS ....................................................................................................................... 5-6
5.1 Field Screening Results........................................................................................ 5-6
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site ii November 2011
5.2 Analytical Results ................................................................................................ 5-7
5.3 Nature and Extent of Contamination ................................................................... 5-7 5.4 Data Evaluation .................................................................................................... 5-9
5.4.1 Applicable or Relevant and Appropriate Requirements (ARARs) ................ 5-9
5.4.2 Summary of Findings ..................................................................................... 5-9
6.0 SUMMARY AND CONCLUSIONS ............................................................................ 6-1
6.1 Summary .............................................................................................................. 6-1 6.2 Conclusions .......................................................................................................... 6-1 6.3 Future Work ......................................................................................................... 6-2
7.0 REFERENCES ............................................................................................................... 7-1
LIST OF TABLES
Table 1-1 Gagan Power Plant Fuel Spill Conceptual Site Model ............................................. 1-5
Table 3-1 Soil Gas Screening Summary ................................................................................... 3-2
Table 3-2 Field Soil Screening Summary ................................................................................. 3-4
Table 3-3 Soil Sampling Summary ........................................................................................... 3-5
Table 3-4 Revised Conceptual Site Model ................................................................................ 3-8
Table 4-1 Laboratory Analytical Methods for Soils ................................................................. 4-2
Table 5-1 Soil Gas Survey and Field Screening Results ........................................................... 5-6
Table 5-2 Results Summary for GRO, DRO and BTEX Compounds ...................................... 5-8
Table 5-3 Results Summary for PAH Compounds ................................................................... 5-5
Table 5-4 Frequency and Range of Detected Contaminants ..................................................... 5-7
LIST OF FIGURES
Figure 1-1 Gagan and Site Location ............................................................................................ 1-3
Figure 1-2 Gagan Power Plant Investigation Area ...................................................................... 1-4
Figure 2-1 Location of Kwajalein Atoll ...................................................................................... 2-3
Figure 3-1 Soil Gas Survey Locations ......................................................................................... 3-3
Figure 3-2 Gagan Power Plant Fuel Spill Soil Sample Locations ............................................... 3-6
APPENDICES
Appendix A Field Documents
Appendix B Analytical Data
Appendix C Data Validation Memorandum
Appendix D Field Photos
Appendix E Previous Studies
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site iii November 2011
LIST OF ACRONYMS AND ABBREVIATIONS
% percent
ARSTRAT U.S. Army Forces Strategic Command
ASTM American Society for Testing and Materials.
bgs below ground surface
BTEX benzene, toluene, ethylbenzene, xylenes
ºC degrees Celsius
COC contaminants of concern
COPC contaminant of potential concern
CSM conceptual site model
CY cubic yards
DL detection limit
DQO data quality objectives
DRO diesel range organics
EDB ethylene dibromide
EPA U.S. Environmental Protection Agency
EPH extractable petroleum hydrocarbon
ESL Guam EPA Environmental Screening Levels
ºF degrees Fahrenheit
FS Feasibility Study
FSP Field Sampling Plan
g/cc grams per cubic centimeter
GEPA Guam Environmental Protection Agency
GPS Global Positioning System
GRO gasoline range organics
ICBM intercontinental ballistic missile
KMR Kwajalein Missile Range
KRS Kwajalein Range Services
LOQ limit of quantitation
LCS laboratory control sample
LCSD laboratory control sample duplicate
mg/kg milligram per kilogram
mi2 square miles
mph miles per hour
MS/MSD matrix spike/matrix spike duplicate
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site iv November 2011
N No
Na not available
NC not calculated
ND not detected
NM not measured
PAH polycyclic aromatic hydrocarbon
PID photoionization detector
PMRF Pacific Missile Range Facility
POL petroleum, oil, and lubricant
ppm parts per million
PRT post-run tubing (system)
Q qualifier
QAPP Quality Assurance Project Plan
QC quality control
RAGS Risk Assessment Guidance for Superfund
RL reporting limit
RMI Republic of the Marshall Islands
RPD Relative Percent Difference
RSL Regional Screening Level
RTS Reagan Test Site
SB soil boring
SDG Sample Data Group
SI site investigation
Sivuniq Sivuniq, Inc.
SMDC U.S. Army Space and Missile Defense Command
TPH total petroleum hydrocarbon
TOC total organic carbon
UCL Upper Confidence Limit
UES U.S. Army Kwajalein Atoll Environmental Standards
USACE U.S. Army Corps of Engineers
USAEC U.S. Army Environmental Center
USAEHA U.S. Army Environmental Hygiene Agency
USAKA U.S. Army Kwajalein Atoll
VPH volatile petroleum hydrocarbon
WWII World War II
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site ES-1 November 2011
EXECUTIVE SUMMARY
In 2006, a pressure gauge ruptured at the generator building on Gagan Island (Facility 7510)
causing the release of approximately five thousand gallons of diesel fuel. Subsequent emergency
response actions removed and landfarm treated approximately 60 cubic yards (CY) of
contaminated soil. A 2007 after-action report by Kwajalein Range Services describes these
activities and indicates residual diesel range organic contaminants in the soils immediately
surrounding the building.
In November 2010, Sivuniq, Inc. (Sivuniq) performed a site investigation (SI) to evaluate
impacts near the generator building and landfarm. This investigation consisted of soil gas survey
and soil sampling. Soil sample analyses included gasoline- and diesel-range organic compounds.
The groundwater on the island is not potable; therefore, the investigation excluded this media.
Results confirmed localized amounts of petroleum residues immediately adjacent to the
generator building from the 2006 spill. The area surrounding the former landfarm also provided
detections of petroleum compounds. After comparing the maximum concentrations to screening
criteria, identified contaminants of potential concern (COPCs) included diesel range organics
(DRO), benzo(a)pyrene, benzo(a)anthracene, benzo(b)fluoranthene, and dibenzo(a,h)anthracene.
Data gaps in the soil data set prevented complete delineation of contamination extent and a
supplemental data collection event has been planned. Laboratory results suggest two isolated
areas of concern, of DRO near Building 7510 and polycyclic aromatic hydrocarbons (PAHs)
near the former landfarm area. Deeper soil samples are needed to define the vertical extent of
contamination and surface soil samples are neede to support evaluation of a future residential
exposure scenario. Groundwater is not considered developable and will only be sampled if
encountered during supplemental soil sampling.
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 1-1 November 2011
1.0 INTRODUCTION
1.1 PROJECT INFORMATION
The U.S. Army Space and Missile Defense Command/U.S. Army Forces Strategic Command
(SMDC/ARSTRAT) tasked Sivuniq, Incorporated with the evaluation of areas of potential or
known contamination sites located at the U.S. Army Kwajalein Atoll (USAKA) installation in
the Republic of the Marshall Islands (RMI). This work is issued under Contract DASG60-03-C-
0081, Task Assignment 10-001.
The scope of work for this task assignment includes, as required by the USAKA Environmental
Standards (UES), preliminary assessment (historic records and document review), site
investigation, data evaluation, treatment and feasibility studies, removal actions, and remedial
actions.
The Site Investigation phase summarized in this document follows UES Section 3-6.5.8(k) and
includes a presentation of soil and groundwater sampling data to evaluate contamination nature
and extent. Subsequent document submissions provide data evaluation/risk assessment,
feasibility studies, and remedial action plans.
1.2 SITE INFORMATION
The Gagan Power Plant is located on Gagan Island, in Kwajalein Atoll (Figure 1-1); the plant is
not permanently manned and telemetry equipment is remotely operated.
1.2.1 Previous Site Investigation
Following discovery of a 5,000-gallon fuel release at the generator building (Facility 7510)
caused by a ruptured pressure gauge on Gagan in 2006, Kwajalein Range Services (KRS)
launched spill response activities.
No immediate visible evidence of wildlife impact was observed at the site following discovery of
the spill. Damage to the environment has been assumed to be limited to the area surrounding the
release. The fuel released southeast of the building migrated vertically to approximately 5 feet
below ground surface (bgs); at this level, it is believed that the diesel fuel spread laterally. To the
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 1-2 November 2011
northwest of the building, soil impact extended approximately 7 inches bgs nearest the building,
decreasing in depth further from the release area. Appendix D contains field photographs
showing where fuel was leaked.
One month subsequent to the spill, impacted soil was excavated until a dense non-porous coral
layer was encountered at approximately 5 feet bgs. Approximately 60 cubic yards (CY) of
impacted soil was placed on plastic sheeting and bermed such that run-on waters had minimal
contact with the soils, which were stockpiled into two rows, to the northwest of the facility; the
approximate location of the landfarmed soils (estimated using text and figures from a KRS
report) is shown in Figure 1-3 (KRS, 2007). Each row of soil was estimated to be approximately
30 CY. The placement of the soils into rows acted to facilitate the natural biodegradation of the
petroleum products and enhanced the treatment by photo-oxidation. Soil samples were collected
by KRS from the stockpiled soils immediately following excavation activities, and again nine
months after the excavation. Laboratory analytical results from the second sampling event
indicated a significant decrease in levels of diesel range organics (DRO) in the contaminated
soils. The soils were ultimately spread on the surface of the site.
Laboratory samples were collected from the excavation prior to backfilling. Analytical results
indicated the presence of DRO in all sidewall samples. The KRS report confirms an
undetermined amount of DRO-impacted soils remained beneath the building after excavation
activities. The greatest concentrations (15,000 milligrams per kilogram [mg/kg]) are identified
beneath the doors where the diesel fuel exited the power plant facility (KRS, 2007).
A detailed summary of previous studies is included as Appendix E.
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 1-3 November 2011
Figure 1-1 Gagan and Site Location
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 1-4 November 2011
Figure 1-2 Gagan Power Plant Investigation Area
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 1-5 November 2011
1.2.2 Conceptual Site Model
Based on available information, primary contaminants of concern (COCs) include petroleum, oil
and lubricants (POL) compounds. Table 1-1 summarizes the preliminary conceptual site model
(CSM) for the Gagan Power Plant Fuel Spill Site.
Table 1-1 Gagan Power Plant Fuel Spill Conceptual Site Model
Model Element Input Rationale
Primary source Petroleum products (diesel fuel) Documented release
Primary Transport
Mechanism Direct product discharge
Release from power plant generator engine
pressure gauge
Secondary source Soil Contamination from direct discharge
Secondary Transport
Mechanisms
Product migration from the release
point(s) Reported soil contamination at various locations
Exposure Media Soil Reported contamination in soil
Exposure Pathways Incidental ingestion of soil
Dermal contact with soil Direct contact and use at site location
Current Receptors On-site operations personnel
On-site (construction) workers
USAKA and contractor personnel are potentially
exposed during work at site locations
Complete/Significant
Exposure Scenarios Incidental soil ingestion and dermal contact with contaminated soil by on-site operations
personnel and onsite construction workers
1.2.3 Investigation Approach
Fieldwork on Gagan focused on investigation, delineation, and documentation of soil
contamination to establish a feasible remediation strategy. Sampling methods included a soil gas
survey and soil sampling. Soil samples were field screened for petroleum hydrocarbons to
establish contaminant boundaries. Confirmation samples were submitted for laboratory analysis,
the results of which were used to characterize and determine extent of impact.
1.3 PURPOSE, SCOPE, AND OBJECTIVE
The core focus of the site investigation (SI) at the Gagan Power Plant Fuel Spill site includes
delineation of residual fuel contamination in soil at the point of release, and assessment of the
secondary impacts associated with the landfarm operations. Remedial actions will be
implemented as needed to mitigate human health impacts.
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 1-6 November 2011
[THIS PAGE LEFT INTENTIONALLY BLANK]
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 2-1 November 2011
2.0 SITE BACKGROUND AND PHYSICAL SETTING
2.1 SITE LOCATION AND DESCRIPTION
The Kwajalein Atoll is located in the “Ralik” (sunset or western) chain of the Marshall Islands in
the West Central Pacific Ocean. It is located 2,100 nautical miles southwest of Honolulu and
approximately 4,200 nautical miles southwest of San Francisco (just west of the international
dateline). Less than 700 miles north of the equator, Kwajalein is in the latitude of Panama and
the southern Philippines, and in the longitude of New Zealand, 2,300 miles south, and the
Kamchatka Peninsula of the former Soviet Union, 2,600 miles north (see Figure 2-1). The atoll’s
remoteness from centers of population and proximity to the sea has a major bearing on the
operation and maintenance of U.S. Army Kwajalein Atoll/Reagan Test Site (USAKA/RTS).
The U.S. Army utilizes 11 of the over 100 islands in the atoll, with active facilities on all or part
of eleven islands, one of which is Gagan. Two of the islands, Kwajalein and Roi-Namur, were
sites of extensive battles during World War II. Kwajalein, at the atoll’s southern tip, and Roi-
Namur, at its northern extremity, are the principal islands at USAKA/RTS and are 50 miles
apart; the other islands used by USAKA/RTS are situated between these two, on both sides of
the lagoon. Gagan is located on the east side of the atoll approximately 10 miles southwest of
Roi-Namur.
2.2 PHYSICAL AND ENVIRONMENTAL SETTING
2.2.1 Environmental Setting
Kwajalein Atoll is a coral reef formation in the shape of a crescent loop enclosing a lagoon. The
approximately 100 small islands share a total land area of only 5.6 square miles (mi2). The
largest islands are Kwajalein (1.2 mi2), Roi-Namur, and Ebadon at the extremities of the atoll;
together they account for nearly half the total land area. While the “typical” size of the remaining
islands may be about 450 by 2,100 feet, the smallest islands are no more than sand cays that
merely break the water's surface at high tide. The island of Gagan is approximately 6 acres.
The Kwajalein Atoll lagoon enclosed by the reef is the world’s largest, with a surface area of
1,100 mi2, and a depth that is generally between 120 to 180 feet. Coral atolls are seamounts that
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 2-2 November 2011
have been capped by calcareous marine growth constructed by lime-secreting organisms (coral
polyps and algae). The lower parts of atolls are composed of noncalcareous rocks, most often
volcanic materials. The overlying coral superstructures may be hundreds or even thousands of
feet in thickness. Emergent portions of the reef and islands tend to be composed of loose, poorly
consolidated calcareous materials derived from foraminifera, coral, shells, and marine algae, or
their debris resulting from destructive action of the elements. One notable characteristic of the
atolls is the steep slopes of the mounts seaward of the reef. Around Kwajalein Atoll, the depth
plunges to as much as 6,000 feet within two miles of the atoll, and to 13,200 feet within 10
miles.
All of the islands that comprise the atoll are relatively flat with few natural points exceeding 15
feet above mean sea level. This condition presents a major problem for underground construction
and allows spilled contaminants to easily reach the water table.
2.2.2 Climate
Kwajalein’s tropical marine climate exhibits little variation through the year. The atoll
experiences a relatively dry windy season from mid-December to mid-May, and a relatively wet
calm season from mid-May to mid-December. Normal annual rainfall is approximately 100
inches; approximately 72 percent (%) of the annual rainfall occurs during the wet season and
28% during the dry season. On average, the prevailing wind direction is from the east-northeast
during the entire year, although winds may become more variable during the wet season when
occasional southerly or even westerly winds occur. The average wind speed is approximately 17
miles per hour (mph) from December to April, and 12 mph from May to November.
The average daily maximum temperature is 86.5 degrees Fahrenheit (ºF); the average minimum
temperature is 77.6 ºF. The extreme temperatures recorded at the atoll are 97 ºF and 68 ºF.
Average relative humidity ranges from 83% at local noon to 78% at midnight.
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 2-3 November 2011
Figure 2-1 Location of Kwajalein Atoll
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 2-4 November 2011
Most of the rainfall at Kwajalein comes from rain showers; thunderstorm occurrences are
infrequent. On average, thunderstorms occur fewer than 12 days each year. The frequency of
thunderstorms ranges from 0.1 per month from January to March to two per month in September.
Since 1919, a fully developed typhoon has never struck Kwajalein Atoll; however, tropical
storms with sustained winds from 40 to 74 mph affect the atoll on average about once every four
to seven years. Rainfall varies significantly across the atoll with Roi-Namur receiving roughly 60
to 70% of the Kwajalein Island average of 100 inches per year.
2.2.3 Regional Geology
The detailed geology of Kwajalein Atoll is primarily based on shallow boring logs prepared by
the U.S. Army Corps of Engineers (USACE) and drilling logs prepared during the construction
of monitoring wells. However, from the limited geologic data available as well as from
inferences, which can be made from various hydrologic data, it appears as though many of the
features observed on Bikini and Enewetak are also common to Kwajalein. In particular, the
uppermost unconformity observed on Bikini and Enewetak at depths of 26 to 40 feet below sea
level also appears to exist on Kwajalein, and it exhibits many of the same general hydrogeologic
characteristics. The characteristics are typically marked by the occurrence of a hard coral ledge
and perhaps conglomerate horizons, above which the aquifers are characterized by moderate
permeabilities and generally fresh groundwater, and below which the aquifers appear to have
higher permeability and contain more saline groundwater. The salinity differences have been
confirmed by field data; however, the permeability differences are only inferred (Global, 1980).
2.2.4 Soil Characteristics
Soils on Kwajalein Atoll mainly consist of unconsolidated, reef-derived calcium carbonate sand
and gravel with minor consolidated layers of coral, sandstone, and conglomerate. A study was
conducted on Kwajalein and Roi-Namur Islands to determine background concentrations of
metals and other inorganic constituents in soils; composite samples were collected and analyzed
for total metals. The mean and maximum expected normal concentrations of each analyte are
presented in the 1991-1992 U.S. Army Environmental Hygiene Agency (USAEHA) Soil and
Contamination Study (USAEHA, 1991).
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 2-5 November 2011
2.2.5 Hydrogeology
The thick accumulation of limestone layers, unconformities caused by sea level changes over
time, and tidal activity play an important role in the fresh groundwater dynamics. Groundwater is
very shallow throughout the atoll; a thin freshwater lens lies atop the brackish groundwater on
the largest islands, including Kwajalein and Roi-Namur. Groundwater gradients radiate out from
groundwater mounds near the center of the islands. The shallow depth to groundwater and the
high permeability of the soils make the groundwater systems of the Kwajalein Atoll islands
highly vulnerable to contamination by chemicals (USAEHA, 1991). Groundwater has not been
encountered on Gagan Island.
2.3 OPERATIONAL HISTORY AND LAND USE
The Navy operated the facility from 1944 to 1964 after the U.S. liberation of the atoll from the
Japanese during World War II (WWII). The U.S. Army established control of Kwajalein Atoll in
1964 after being transferred from the U.S. Navy. The USAKA/Kwajalein Missile Range (KMR)
was renamed to USAKA/RTS on June 15, 2001.
The naming designations of the installation at Kwajalein Island throughout recent history are as
follows:
Navy Operating Base Kwajalein, Naval Air Station Kwajalein, Naval Station Kwajalein,
and Pacific Missile Range Facility (PMRF) Kwajalein at various times between 1945 and
1964.
Kwajalein Test Site from July 1, 1964, through April 14, 1968;
Kwajalein Missile Range from April 15, 1968, through November 13, 1986;
USAKA from November 14, 1986, through September 30, 1997.
The USAKA/RTS is a subordinate activity of the U.S. SMDC/ARSTRAT, headquartered in
Huntsville, Alabama.
The installation supports the RTS in support of theater missile defense, ballistic missile defense,
and intercontinental ballistic missile (ICBM) testing.
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 2-6 November 2011
[THIS PAGE LEFT INTENTIONALLY BLANK]
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 3-1 November 2011
3.0 FIELD ACTIVITIES
The SI at Gagan Island consisted of the following elements:
Establish site controls and perform a magnetometer survey to identify possible hazards
and utility conflicts within the investigation area.
Perform a soil gas survey within the investigation area to locate and assess the impacted
area.
Soil sample collection using a direct-push sampling system for direct assessment of soil
impacts.
Field screening analysis by a number of methods to provide daily data for dynamic
sampling adjustments in the field.
Confirmation sampling within the most impacted area allowed for characterization of the nature
of the contamination. Additional confirmation sampling at the contaminant horizon provided
accurate definition of the extent of contamination. Sampling points were surveyed to allow for
accurate delineation of impacts.
Although not specifically required as part of the dig permitting process, all intrusive activities on
Gagan Island were monitored by a qualified archeological specialist implementing the project-
specific Archeological Monitoring Plan (Kwaj-10-52). Major elements of this monitoring
included global positioning system (GPS) locating for all sample locations, inspection of coring
samples, and descriptive documentation of soil characteristics.
3.1 SITE ACTIVITIES
A summary of sampling activities is provided in the 2010 Site Investigation Work Plan (Sivuniq,
2010). Details related to the field/sampling techniques can be found in the Field Sampling Plan
and Standard Operating Procedures, both located in Annex A of the Work Plan.
The field crew surveyed sample locations with a handheld magnetometer prior to conducting
intrusive activities to identify possible conflicts and hazards.
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 3-2 November 2011
3.1.1 Field Documentation
A field report form, describing the summary of activities each day, was completed by the Field
Team Leader and provided to the Project Manager. In addition to the activities completed, a
description of the equipment used, the field analyses conducted, and any other pertinent
information was documented. The procedures for documenting field observation and data are
located in the Work Plan. Digital photographs were taken during fieldwork to document field
activities.
3.1.2 Soil Gas Survey
A soil-gas survey was conducted to provide rapid assessment of potential areas of contamination
with the following equipment and methods presented in Table 3-1. A total of 54 soil gas points
were installed at this site. Additional details of the soil gas sampling method are presented in the
Field Sampling Plan standard operating procedures.
Table 3-1 Soil Gas Screening Summary
Soil Gas
Sampling
Equipment
Direct-push rig (soil sampling) or slide hammer (soil screening), post-run tubing system
(PRT) soil gas probes, peristaltic pump, Tedlar® bags
Sampling
Locations
Coarse sampling: 50’ interval inside and adjacent to the power plant; probe inserted to depth
of 3’ bgs
Refined sampling: 25’ interval surrounding perimeter of coarse sampling locations
exhibiting soil-gas vapors; probe inserted to depth of 3’ bgs
Field Analyses Petroleum headspace vapor screening with Mini-RAE 2000 photoionization detector
Soil gas screening began to the east of the generator building (facility number 7510). Soil gas
monitoring was limited to days with no rainfall, as the soil moisture affects photoionization
detector (PID) readings. The field crew began by identifying the area of concern. A 10- or 25-
foot spacing soil-gas survey grid was typically applied to locations of suspected release, allowing
for delineation of the contaminant mass (Figure 3-1). Soil gas monitoring points north/northwest
of Facility Number 7510 were placed on a 25-foot grid due to the greater distance from the
known spill.
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 3-3 November 2011
Figure 3-1 Soil Gas Survey Locations
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 3-4 November 2011
Soil was penetrated with a 1-inch diameter post-run tubing system (PRT) soil gas probe installed
with a slide hammer. After the probes were installed to an average depth of 3 feet bgs, a PID
reading was recorded directly from the soil gas monitoring tip, without flexible tubing inserted
into the tip. The method of measurement collected directly from the soil gas monitoring tip was
found to be sufficiently accurate and more efficient than the other methods (described in Section
3.2.1), and was therefore used for the 52 of the 55 soil gas survey points. Soil gas survey results
are presented in Table 5-2.
3.1.3 Field Soil Screening
A field laboratory was set up to facilitate screening of soil samples to augment field screening
techniques, and to decrease the bulk of samples sent out for laboratory analysis. Detailed
descriptions of these methods are outlined in the approved Work Plan. Soil collection locations
and methods are presented in Section 3.1.4. Results of field screening are presented in Table 5-2.
Field screening of soil samples included a visual inspection of the soil, petroleum headspace
vapor screening with a PID, and direct product screening (sheen screen test). Additional
analyses were completed in the onsite field lab, including petroleum extraction/analysis with
RaPID Assay immunoassay kits, PetroFLAG®
turbidimetric analyzer, and InfraCal CVH infrared
spectrometer. Tests performed in the field laboratory for total petroleum hydrocarbons (TPH) in
soils include the methods presented in Table 3-2. Table 5-1 presents soil screening results.
Table 3-2 Field Soil Screening Summary
Field Analyses
Petroleum headspace vapor screening with Mini-RAE 2000 photoionization detector
Petroleum in soil by physical examination, texture, smell, sheen screen
Petroleum extraction/analysis with Wilks InfraCal CVH infrared spectrometer
Petroleum extraction/analysis with PetroFLAG turbidimetric analyzer
Petroleum extraction/analysis with RaPID Assay immunoassay kits
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 3-5 November 2011
3.1.4 Soil Sampling
Soil samples for field screening and analysis were collected using direct-push technology; soil
screening and confirmation sample locations are presented on Figure 3-2. A summary of the
methodology of intrusive soil investigation is presented in Table 3-3.
Table 3-3 Soil Sampling Summary
Sampling
Equipment Direct-push rig with macro-core samplers; stainless steel sampling spoons
Sampling
Locations
Nature of contamination: For the release point near Facility 7510, at least 3 locations along
building footer and near the center of contaminant mass, samples at 3’ bgs.
Extent of contamination: Perimeter locations radially distributed between the contaminant mass
and the horizon of detected contamination (as determined by soil field screening results),
samples at 3’ bgs and groundwater interface or 6’ bgs (whichever is deeper). At least 30% of
perimeter sampling locations placed outside of area of contamination to accurately define the
extent of contamination.
Soil sampling locations were chosen based on soil gas survey results; samples were collected in
locations where high PID readings were observed, as well as in clean locations in order to define
the boundaries of impact. Twenty-eight soil borings were installed with a Geoprobe MT540
direct push unit to 3 feet bgs, at points where soil gas had been monitored (Figure 3-2). The
direct push sampler used static force and a percussion hammer to advance the small-diameter
sampling tools. Soil samples were captured in clear polyethylene terphthalate liners, which were
inserted into the sampling tool prior to being pushed into the soil. To recover the soil, the
sampler was retrieved from the hole and the liner containing the soil sample was cut open with a
specialized cutting tool that safely sliced the entire length of the liner.
Confirmation sampling of soil within the product plume and at the contaminant horizon was
completed to provide accurate characterization of the nature and extent of contamination. The 0
to 3 foot interval was typically sampled for field screening analyses, including PID and sheen; a
portion of the sample was collected in a four ounce glass container for field screening.
Additionally, composite soil samples were collected at each location for laboratory analysis of
extractable petroleum hydrocarbons (EPH), volatile petroleum hydrocarbons (VPH) and
polycyclic aromatic hydrocarbons (PAHs).
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 3-6 November 2011
Figure 3-2 Gagan Power Plant Fuel Spill Soil Sample Locations
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 3-7 November 2011
3.2 DEVIATIONS
This investigation was conducted according to the Site Investigation Work Plan (Sivuniq, 2010);
however, deviations from the original plan were necessary in some instances. Deviations from
the plan are detailed in the following subsections.
3.2.1 Soil Gas Survey
Soil gas monitoring points were originally laid out as a 10 foot grid rather than the coarse (50-
foot interval) and refined (25-foot interval) sampling grid (Figure 3-1). The soils were penetrated
with a 1-inch diameter PRT soil gas probe installed with a slide hammer. After the probes were
installed to an average depth of 3 feet bgs, a soil gas monitoring tip was deployed into the
opening, flexible tubing was inserted, and a peristaltic pump used to purge the line for 15
seconds. Once the line was purged, the peristaltic pump was used to fill a tedlar bag, from which
a PID reading was recorded. A second reading was recorded directly from the soil gas
monitoring tip, without flexible tubing inserted into the tip. A third reading was recorded directly
from the flexible tubing, without the peristaltic pump to aid airflow.
The method of measurement collected directly from the soil gas monitoring tip (second method)
was found to be sufficiently accurate and more efficient than the other methods, and was
therefore used for the remainder of the soil gas survey. Soil gas monitoring was limited to days
with no rainfall, as the soil moisture affects PID readings. Soil gas monitoring points
north/northwest of Facility Number 7510 were placed on a 25-foot grid due to the greater
distance from the known contamination.
3.2.2 Soil Sampling
No deviations from the work plan are noted.
3.3 CONCEPTUAL SITE MODEL REVISION
Upon further consideration, the CSM has been revised to include future residents as a potential
receptor. The updated CSM is presented below:
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 3-8 November 2011
Table 3-4 Revised Conceptual Site Model
Model Element Input Rationale
Primary source Petroleum products (diesel fuel) Documented release
Primary Transport Mechanism Direct product discharge Release from power plant generator engine
pressure gauge
Secondary source Soil Contamination from direct discharge
Secondary Transport
Mechanisms
Product migration from the release
point(s) Reported soil contamination at various locations
Exposure Media Soil Reported contamination in soil
Exposure Pathways Incidental ingestion of soil
Dermal contact with soil Direct contact and use at site location
Current Receptors On-site operations personnel
On-site (construction) workers
USAKA and contractor personnel are potentially
exposed during work at site locations
Complete/Significant
Exposure Scenarios Incidental soil ingestion and dermal contact with contaminated soil by on-site operations
personnel, onsite construction workers and future residents
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 4-1 November 2011
4.0 SAMPLE MANAGEMENT AND LABORATORY ACTIVITIES
4.1 SAMPLE MANAGEMENT
Samples were managed according to the work plan. Once collected in the field, samples were
immediately placed in a cooler on ice. Upon returning from the field, samples were placed in a
refrigerator in order to maintain a temperature of 4 degrees Celsius (°C). A chain-of-custody
form for each sample set was completed to maintain a record of sample collection, transfer
between personnel, and receipt by the laboratory. When custody of samples was relinquished, the
chain-of-custody form was signed, and the date and time of transfer noted. Because the samples
were shipped by air to the Test America Laboratories in Honolulu, Hawaii, chain-of-custody
forms were completed and placed inside a 1-gallon Ziploc® bag and taped inside the top of the
cooler. One sample data group (SDG) is associated with the investigation conducted in Gagan
(SDG HTK0125).
4.2 QUALITY CONTROL
A series of quality control (QC) samples were collected in the field to confirm quality and
defensible analytical results. The QC samples collected and submitted for analysis included field
duplicates and matrix spike/matrix spike duplicates (MS/MSDs). The field duplicates were
collected at a rate of 10% (1 in 10 samples); MS/MSDs were collected at a rate of 5% (1 in 20
samples).
Three field duplicate samples were collected in conjunction with 25 primary soil samples.
Duplicate sample results are used to assess the precision of the sample collection process. The
field duplicate was collected at the same location as the primary sample either simultaneously or
in immediate succession using identical recovery techniques, and was treated in an identical
manner during storage and transportation. The primary and duplicate sample containers were
assigned unique identification numbers.
The MS/MSD is used to document the bias of a method due to the sample matrix. MS/MSDs are
aliquots of samples spiked by the laboratory with known concentrations of the analytes to be
analyzed, prior to sample preparation and analysis. The sample set did not include sufficient
sample volume for a specified MS/MSD sample, thus the laboratory split MS/MSD analyses
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 4-2 November 2011
between three different samples for gasoline range organics (GRO)/benzene, toluene,
ethylbenzene and xylenes (BTEX), DRO, and PAHs to apply this QC method.
A trip blank is typically submitted with each sample cooler containing samples to be analyzed
for VPH; however, no trip blank was included with SDG HTK0125. No adverse impacts to the
data are suspected since no systemic detections were present that would indicate trip blank
contamination issues.
4.3 LABORATORY ANALYSES
Results of confirmation sample analyses establish the horizontal and vertical extent of
contamination at the site. These results as well as physical data support the evaluation of
remedial alternatives. The specific analyses for soil are detailed below in Table 4-1. The
laboratory analytical results are presented in Appendix B.
Table 4-1 Laboratory Analytical Methods for Soils
Parameter Analytical Method
Volatile Petroleum Hydrocarbons (VPH) EPA Method 8260M
Extractable Petroleum Hydrocarbons (EPH) EPA Method 8015
Polycyclic Aromatic Hydrocarbons (PAHs) EPA Method 8270-SIM
Bulk Density ASTM D2937
Grain Size Distribution ASTM D422
Total Organic Carbon (TOC) EPA Method 9060
Notes: ASTM = American Society for Testing and Materials. TOC = total organic carbon. EPA = U.S. Environmental Protection
Agency.
4.4 VALIDATION AND DATA QUALITY OBJECTIVES (DQOS)
After completing fieldwork, the Data Manager organized analytical laboratory data for
evaluation, validation and presentation. Data validation involves a comprehensive review of the
laboratory data to verify conformance with quality controls; qualifiers flag any deficient data to
alert data users of possible quality concerns. Analytical results were validated using a set of
quality checks, which addressed different data quality objectives (DQOs) including accuracy,
precision, comparability, completeness, representativeness, and sensitivity.
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 4-3 November 2011
4.4.1 Accuracy/Bias
ACCURACY was a measurement of correctness and includes components of random error
(variability due to imprecision) and systemic error. Accuracy was quantified as the degree of
agreement between a measurement with a known reference. The accuracy was evaluated from
the percent recovery (%R), percent difference (%D), or percent drift (%Df) of the initial and
continuing calibration samples, internal standards, surrogate spikes, laboratory control samples,
and matrix spike samples.
Results of the method blank, calibration blank, and trip blank provide a measure of method bias
from the field and laboratory procedures.
4.4.2 Precision
Precision is defined as the degree of mutual agreement among independent measurements as the
result of repeated application of the same process under similar conditions. Analytical precision
is evaluated via the relative percent difference (RPD) values of laboratory control sample and
laboratory control sample duplicate (LCS/LCSD) and the MS/MSD analyses. The RPD values of
field duplicate analyses represent the combined precision of sample collection and analysis
procedures, as well as sample homogeneity.
The RPD values for MS/MSD and LCS/LCSD were all within the laboratory control limits for
all analytes. The RPD values for two field duplicate samples were within the laboratory control
limits except for the PAH analyses. The precision associated with the project analyses achieved
the DQOs in the Quality Assurance Project Plan (QAPP).
ComparabilityComparability describes the confidence with which one data set can be compared
to another data set. Comparability was achieved through the use of standardized operating
procedures analytic methods techniques, and equipment to collect and analyze representative
samples.
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 4-4 November 2011
Data generated during this sampling event maintained the comparability within this sampling
event.
4.4.3 Completeness and Data Usability
Completeness is a measure of the amount of valid data obtained for each analyte. The
completeness was measured as the total number of samples with valid results of target analytes
compared to the total number of collected samples’ target analytes, expressed as a percentage.
The data quality objective of a 95% completeness goal (valid data/ total possible data*100) was
expected.
The Gagan data set met completeness and data usability criteria for all analytical parameters.
4.4.4 Representativeness
Representativeness is a qualitative characteristic that measures the ability to collect a sample
reflecting the characteristics of the part of the environment being assessed. Representativeness
was achieved through use of the standard field, sampling, and analytical procedures.
Representativeness was also determined by appropriate program design, with consideration of
elements such as proper sample locations and sampling procedures. The evaluation of associated
method blanks also assists in identifying artifacts that may skew the representativeness of the
samples. To assure that the sample results were as representative as possible, the field sampling
procedures described in the work plan were diligently followed with all deviations noted.
No anomalies were identified in sample preservation, handling, preparation, and analysis that
affected data representativeness, except for the QC anomalies affecting the precision (Section
4.4.2) as discussed above. The uncertainty of the data quality potentially resulted from these
anomalies were conceivable, and were not significantly affecting the data representativeness.
4.4.5 Sensitivity
Sensitivity was the ability of an analytical method and instruments to detect a target component
in a sample matrix with a defined level of confidence. The sensitivity was evaluated from the
reporting limits (RL) compared to the goals set forth in the QAPP. The analytical laboratory was
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 4-5 November 2011
responsible for ensuring that sensitivity requirements of the data as described in the QAPP were
achieved and documented in the data package.
4.4.6 Data Validation Results
Data validation was performed on SDG HTK0125. Some of the data was qualified by the
laboratory, and additional qualification of data resulted from validation, as presented below:
Some GRO and BTEX data were qualified as not detected due to method blank
contamination;
Some PAH data were qualified as estimated due to field duplicate anomalies.
Other data are accepted without qualifiers; no data were rejected. The complete data validation
memoranda are presented in Appendix C.
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 5-6 November 2011
5.0 RESULTS
Field screening and analytical results have been evaluated to determine the nature and extent of
contamination in order to develop a feasible remediation strategy for the Gagan POL site.
5.1 FIELD SCREENING RESULTS
Table 5-1 Soil Gas Survey and Field Screening Results
Sample Name
1011KWAJ009-
Soil Gas
(ppm)
Soil PID
(ppm)
Soil
Sheen
RaPID Assay
(mg/kg)
InfraCal
(ppm)
PetroFLAG®
(ppm)
SB01003-10 12.1 2.1 N 235 825 62
SB02003-10 14.8 4.1 N 12 7 64
SB03003-10 NM 10.3 N 14 6 32
SB04003-10 NM 9.5 N 6 12 35
SB05003-10 0.9 1.5 N 21 9 28
SB06003-10 12.4 7.2 N 9 8 80
SB07003-10 0.1 7.5 N 18 14 41
SB08003-10 NM 3.7 N 12 12 52
SB09003-10 1.8 3.2 N 8 10 81
SB10003-10 0 3.8 N 16 18 102
SB11003-10 0.1 6.1 N 22 20 92
SB12003-10 0.2 4.2 N 17 22 90
SB13003-10 2.5 8 N 42 65 154
SB14003-10 3.2 2.2 N 88 126 174
SB15003-10 0 6.8 N 16 15 345
SB15003-11 0 6.8 N 12 14 81
SB16003-10 13.2 7.8 N 22 51 93
SB17003-10 36 6.3 N 8 10 31
SB17003-11 36 6.3 N 12 17 26
SB18003-10 5.1 4.2 N 9 7 24
SB19003-10 231 6.4 N 9 5 69
SB20003-10 NM 2.8 N 11 10 37
SB21003-10 174 4.3 N 9 6 114
SB22003-10 NM 5.3 N 17 9 40
SB23003-10 50.7 6.3 N 124 210 125
SB23003-11 50.7 6.3 N 141 201 137
SB24003-10 2.1 2 N 18 11 48
SB25003-10 5.2 9.8 N 14 15 26
SB26003-10 69.7 6.6 N 16 22 68
SB26003-11 69.7 6.6 N NM NM NM
SB27003-10 NM 3.1 N 8 3 42
SB28003-10 NM 10.4 N NM 6 47
Notes:
mg/kg: milligrams per kilogram; NM: not measured; N: no; ppm: parts per million
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 5-7 November 2011
Sample naming conventions are explained in the Field Sampling Plan (FSP), which is included
in the work plan (Sivuniq, 2010). The sample 1011KWAJ009-SB01003-10 represents a sample
taken in 2010 (10) in November (11); the sample location is Gagan Island (KWAJ009); the
sample was collected from the first soil boring (SB01), from a depth of 3 feet below ground
surface (003); the sample is a primary sample (rather than a dup) (-10).
5.2 ANALYTICAL RESULTS
Laboratory data indicates detections of petroleum constituents in the soil at the Gagan Power
Plant Fuel Spill site. Table 5-2 and Table 5-3 present a summary of results for all compounds.
The analytical laboratory report is presented in Appendix B.
Of the six field screening techniques utilized on 28 Gagan soil samples, the comparison of
analytical data to field screening data support the following techniques as useful (the most
accurate listed first): RaPID Assay (30% relative percent difference), InfraCal (42% relative
percent difference), and PetroFLAG (93% relative percent difference).
Physical characteristics data from four samples collected at the site confirm field observations.
Grain size analysis indicates that the area of contamination is predominantly medium grained
sand, with varying amounts of gravel, coarse and fine sand, silt, and clay. The average bulk
density is 1.44 grams per cubic centimeter (g/cc). The average organic carbon content of the soils
at the site is 120,000 mg/kg.
Appendix B contains complete results of the chemical and physical characteristics analyses.
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 5-8 November 2011
Table 5-2 Results Summary for GRO, DRO and BTEX Compounds
DRO GRO Benzene Toluene
Ethyl-
benzene m,p-Xylene o-Xylene
Sample ID Soil
Boring
Depth
(feet
bgs)
Analytical Results
1011KWAJ009
SB01003-10 SB01 0 - 3 407
0.61 U
ND
(0.0122)
ND
(0.0122)
ND
(0.0122)
ND
(0.0122)
ND
(0.0122)
1011KWAJ009
SB02003-10 SB02 0 - 3 4.09 J 0.591 U
ND
(0.0118) 0.0118 U
ND
(0.0118)
ND
(0.0118)
ND
(0.0118)
1011KWAJ009
SB03003-10 SB03 0 - 3 24.9
0.567 U
ND
(0.0113)
ND
(0.0113)
ND
(0.0113)
ND
(0.0113)
ND
(0.0113)
1011KWAJ009
SB04003-10 SB04 0 - 3 3.43 J 0.599 U
ND
(0.012)
ND
(0.012)
ND
(0.012)
ND
(0.012)
ND
(0.012)
1011KWAJ009
SB05003-10 SB05 0 - 3 10.2
0.645 U
ND
(0.0129)
ND
(0.0129)
ND
(0.0129)
ND
(0.0129)
ND
(0.0129)
1011KWAJ009
SB06003-10 SB06 0 - 3 46
0.636 U
ND
(0.0127)
ND
(0.0127)
ND
(0.0127)
ND
(0.0127)
ND
(0.0127)
1011KWAJ009
SB07003-10 SB07 0 - 3 2.28 J 0.604 U
ND
(0.0121)
ND
(0.0121)
ND
(0.0121)
ND
(0.0121)
ND
(0.0121)
1011KWAJ009
SB09003-10 SB09 0 - 3 25.2
0.664 U
ND
(0.0133)
ND
(0.0133)
ND
(0.0133)
ND
(0.0133)
ND
(0.0133)
1011KWAJ009
SB10003-10 SB10 0 - 3 8
0.621 U
ND
(0.0124)
ND
(0.0124)
ND
(0.0124)
ND
(0.0124)
ND
(0.0124)
1011KWAJ009
SB11003-10 SB11 0 - 3 7.11
0.653 U
ND
(0.0131)
ND
(0.0131)
ND
(0.0131)
ND
(0.0131)
ND
(0.0131)
1011KWAJ009
SB12003-10 SB12 0 - 3 26.1
0.605 U
ND
(0.0121)
ND
(0.0121)
ND
(0.0121)
ND
(0.0121)
ND
(0.0121)
1011KWAJ009
SB14003-10 SB14 0 - 3 135
0.628 U
ND
(0.0126)
ND
(0.0126)
ND
(0.0126)
ND
(0.0126)
ND
(0.0126)
1011KWAJ009
SB16003-10 SB16 0 - 3 16
0.619 U
ND
(0.0124)
ND
(0.0124)
ND
(0.0124)
ND
(0.0124)
ND
(0.0124)
1011KWAJ009
SB17003-10 SB17 0 - 3 16
0.632 U
ND
(0.0126)
ND
(0.0126)
ND
(0.0126)
ND
(0.0126)
ND
(0.0126)
1011KWAJ009
SB17003-11 SB17 0 - 3 12.2
0.686 U
ND
(0.0137)
ND
(0.0137)
ND
(0.0137)
ND
(0.0137)
ND
(0.0137)
1011KWAJ009
SB18003-10 SB18 0 - 3 12.5
0.661 U
ND
(0.0132)
ND
(0.0132)
ND
(0.0132)
ND
(0.0132)
ND
(0.0132)
1011KWAJ009
SB19003-10 SB19 0 - 3 2.84 J 0.673 U
ND
(0.0135)
ND
(0.0135)
ND
(0.0135)
ND
(0.0135)
ND
(0.0135)
1011KWAJ009
SB20003-10 SB20 0 - 3 8.97
0.652 U
ND
(0.013)
ND
(0.013)
ND
(0.013)
ND
(0.013)
ND
(0.013)
1011KWAJ009
SB21003-10 SB21 0 - 3 59.7
0.62 U
ND
(0.0124)
ND
(0.0124)
ND
(0.0124)
ND
(0.0124)
ND
(0.0124)
1011KWAJ009
SB22003-10 SB22 0 - 3 0.91 J 0.626 U
ND
(0.0125)
ND
(0.0125)
ND
(0.0125)
ND
(0.0125)
ND
(0.0125)
1011KWAJ009
SB23003-10 SB23 0 - 3 83
0.627 U
ND
(0.0125)
ND
(0.0125)
ND
(0.0125)
ND
(0.0125)
ND
(0.0125)
1011KWAJ009
SB23003-11 SB23 0 - 3 119
0.619 U
ND
(0.0124)
ND
(0.0124)
ND
(0.0124)
ND
(0.0124)
ND
(0.0124)
1011KWAJ009
SB24003-10 SB24 0 - 3 7.66
0.602 U
ND
(0.012) 0.012 U
ND
(0.012)
ND
(0.012)
ND
(0.012)
1011KWAJ009
SB25003-10 SB25 0 - 3 1.76 J 0.684 U
ND
(0.0137)
ND
(0.0137)
ND
(0.0137)
ND
(0.0137)
ND
(0.0137)
1011KWAJ009
SB26003-10 SB26 0 - 3 19.3 J 0.655 U
ND
(0.0131)
ND
(0.0131)
ND
(0.0131)
ND
(0.0131)
ND
(0.0131)
1011KWAJ009
SB26003-11 SB26 0 - 3 15.9 J 0.584 U
ND
(0.0117)
ND
(0.0117)
ND
(0.0117)
ND
(0.0117)
ND
(0.0117)
1011KWAJ009
SB27003-10 SB27 0 - 3 3.81 J 0.666 U
ND
(0.0133)
ND
(0.0133)
ND
(0.0133)
ND
(0.0133)
ND
(0.0133)
1011KWAJ009
SB28003-10 SB28 0 - 3 2.31 J 0.616 U
ND
(0.0123)
ND
(0.0123)
ND
(0.0123)
ND
(0.0123)
ND
(0.0123) Notes, Acronyms and Abbreviations:
Bolded values are positive detections
Non-detects are reported at the limit in the parenthesis
J Reported concentration is an estimated value
U Reported as a nondetection at the indicated limit due to qualification UJ Reported as a nondetection, and the indicated limit is an estimated value
Draft Gagan Power Plant Site Investigation Report Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 5-5 November 2011
Table 5-3 Results Summary for PAH Compounds
Analyte
2-Methyl-
naphthalene Acenaphthene Acenaphthylene Anthracene
Benzo (a)
anthracene
Benzo (a)
pyrene
Benzo (b)
fluoranthene
Benzo (g,h,i)
perylene
Benzo (k)
fluoranthene Chrysene
Dibenzo
(a,h)
anthracene
Fluoranthene Fluorene Indeno (1,2,3-
cd) pyrene Naphthalene Phenanthrene Pyrene
Sample ID SB
Depth
(feet
bgs)
Analytical Results
1011KWAJ009
SB01003-10 SB01 0 - 3 0.0028 J 0.00734 J 0.00105 J
0.020
3 J
0.0059
5 J 0.00315 J 0.00595 J
ND
(0.0176) 0.00245 J 0.00455 J
ND (0.00839
)
0.00804 J 0.0294 J ND
(0.00839
)
0.00105 J 0.0238 J 0.0
29
1011KWAJ009
SB02003-10 SB02 0 - 3
ND
(0.0085)
ND
(0.0085)
ND
(0.0085)
ND
(0.0085)
0.0031
9 J
ND
(0.0085) 0.0046 J
ND
(0.0178) 0.00212 J 0.00283 J
ND
(0.0085) 0.00496 J
ND
(0.0085)
ND
(0.0085)
ND
(0.0085) 0.0014
2 J
0.0
038
9
J
1011KWAJ009
SB03003-10 SB03 0 - 3
ND
(0.00813) 0.00102 J
ND
(0.00813)
0.001
69 J 0.0234
0.0363
0.0759
0.0166 J 0.0291
0.0441
ND
(0.00813)
0.0827
ND
(0.00813)
0.0152
ND
(0.00813)
0.0207
0.0
478
1011KWAJ009
SB04003-10 SB04 0 - 3
ND
(0.00884)
ND (0.00884
)
ND (0.00884
)
ND (0.008
84)
ND (0.0088
4)
ND (0.00884
)
ND (0.00884
)
ND
(0.0186)
ND (0.00884
)
ND (0.00884
)
ND (0.00884
)
ND (0.00884
)
ND (0.008
84)
ND (0.00884
)
ND (0.00884
)
ND (0.008
84)
ND
(0.0
0884)
1011KWAJ009
SB05003-10 SB05 0 - 3
ND
(0.00897)
ND
(0.00897)
ND
(0.00897)
ND
(0.00897)
0.0041
1 J 0.00336 J 0.00598 J
ND
(0.0188) 0.00224 J 0.00374 J
ND
(0.00897)
0.00561 J
ND
(0.00897)
ND
(0.00897)
ND
(0.00897)
ND
(0.00897)
0.0
044
9
J
1011KWAJ009SB06003-10
SB06 0 - 3 ND
(0.00835)
ND
(0.00835
)
ND
(0.00835
)
ND
(0.008
35)
ND
(0.0083
5)
ND
(0.00835
)
ND
(0.00835
)
ND (0.0175)
ND
(0.00835
)
0.00174 J
ND
(0.00835
)
0.00209 J
ND
(0.008
35)
ND
(0.00835
)
ND
(0.00835
)
ND
(0.008
35)
0.0
017
4
J
1011KWAJ009
SB07003-10 SB07 0 - 3
ND
(0.00914)
ND (0.00914
)
ND (0.00914
)
ND (0.009
14)
ND (0.0091
4)
ND (0.00914
)
ND (0.00914
)
ND
(0.0192)
ND (0.00914
)
ND (0.00914
)
ND (0.00914
)
ND (0.00914
)
ND (0.009
14)
ND (0.00914
)
ND (0.00914
)
ND (0.009
14)
ND
(0.0
0914)
1011KWAJ009SB09003-10
SB09 0 - 3 ND
(0.0087) 0.00145 J
ND (0.0087)
ND
(0.0087)
0.0065
3 J 0.00435 J 0.0102
ND
(0.0183) 0.00399 J 0.00725 J
ND (0.0087)
0.0102
ND
(0.0087)
ND
(0.0087) ND
(0.0087)
ND
(0.0087)
0.0
083
4
J
1011KWAJ009
SB10003-10 SB10 0 - 3
ND
(0.00884)
ND (0.00884
)
ND (0.00884
)
ND (0.008
84)
ND (0.0088
4)
ND (0.00884
)
ND (0.00884
)
ND
(0.0186)
ND (0.00884
)
ND (0.00884
)
ND (0.00884
)
ND (0.00884
)
ND (0.008
84)
ND (0.00884
)
ND (0.00884
)
ND (0.008
84)
ND
(0.0
0884)
1011KWAJ009SB11003-10
SB11 0 - 3 ND
(0.00965)
ND
(0.00965
)
ND
(0.00965
)
ND
(0.009
65)
ND
(0.0096
5)
ND
(0.00965
)
ND
(0.00965
)
ND (0.0203)
ND
(0.00965
)
ND
(0.00965
)
ND
(0.00965
)
ND
(0.00965
)
ND
(0.009
65)
ND
(0.00965
)
ND
(0.00965
)
ND
(0.009
65)
ND
(0.0096
5)
1011KWAJ009
SB12003-10 SB12 0 - 3
ND
(0.00888)
ND
(0.00888)
ND
(0.00888)
ND
(0.00888)
0.0096
2 0.0118
0.0189
0.00851 J 0.00703 J 0.0107
ND
(0.00888)
0.0196
ND
(0.00888)
0.00666 J
ND
(0.00888)
0.0051
8 J
0.0
159
1011KWAJ009SB14003-10
SB14 0 - 3 ND
(0.00921)
ND
(0.00921
)
ND
(0.00921
)
ND
(0.009
21)
ND
(0.0092
1)
ND
(0.00921
)
ND
(0.00921
)
ND (0.0193)
ND
(0.00921
)
ND
(0.00921
)
ND
(0.00921
)
ND
(0.00921
)
ND
(0.009
21)
ND
(0.00921
)
ND
(0.00921
)
ND
(0.009
21)
ND
(0.0092
1)
1011KWAJ009SB16003-10
SB16 0 - 3 ND
(0.00849)
ND
(0.00849
)
ND
(0.00849
)
ND
(0.008
49)
ND
(0.0084
9)
ND
(0.00849
)
ND
(0.00849
)
ND (0.0178)
ND
(0.00849
)
ND
(0.00849
)
ND
(0.00849
)
ND
(0.00849
)
ND
(0.008
49)
ND
(0.00849
)
ND
(0.00849
)
ND
(0.008
49)
ND
(0.0084
9)
1011KWAJ009
SB17003-10 SB17 0 - 3
ND
(0.00888)
ND (0.00888
)
ND (0.00888
)
ND (0.008
88)
0.024 J 0.0203 J 0.0285 J 0.0166 J 0.0122 J 0.02 J ND
(0.00888
)
0.0363 J ND
(0.008
88)
0.0137 J ND
(0.00888
)
0.0018
5 J
0.0
285 J
1011KWAJ009
SB17003-11 SB17 0 - 3
ND
(0.00923)
ND
(0.00923)
ND
(0.00923)
ND
(0.00923)
0.0019
6
U
J 0.00323
U
J 0.00392
U
J 0.00819
U
J 0.00158
U
J 0.00173
U
J
ND
(0.00923)
0.00162 UJ
ND
(0.00923)
0.00669
U
J
ND
(0.00923)
0.0015 UJ
0.0
0162
UJ
1011KWAJ009
SB18003-10 SB18 0 - 3
ND
(0.00896)
ND
(0.00896
)
ND
(0.00896
)
ND
(0.008
96)
ND
(0.0089
6)
ND
(0.00896
)
ND
(0.00896
)
ND
(0.0188)
ND
(0.00896
)
ND
(0.00896
)
ND
(0.00896
)
ND
(0.00896
)
ND
(0.008
96)
ND
(0.00896
)
ND
(0.00896
)
ND
(0.008
96)
ND
(0.0
089
6)
1011KWAJ009
SB19003-10 SB19 0 - 3
ND
(0.00906)
ND
(0.00906)
ND
(0.00906)
ND
(0.00906)
ND
(0.00906)
ND
(0.00906)
ND
(0.00906)
ND
(0.019)
ND
(0.00906)
ND
(0.00906)
ND
(0.00906)
ND
(0.00906)
ND
(0.00906)
ND
(0.00906)
ND
(0.00906)
ND
(0.00906)
ND (0.0
090
6)
1011KWAJ009
SB20003-10 SB20 0 - 3
ND
(0.0088) 0.00183 J
ND
(0.0088) 0.001
47 J
0.0080
7 J 0.0055 J 0.0099
ND
(0.0185) 0.00367 J 0.00843 J
ND
(0.0088) 0.0249
0.0018
3 J
ND
(0.0088) 0.0011 J 0.0282
0.0
165
1011KWAJ009SB21003-10
SB21 0 - 3 ND
(0.0092) 0.00115 J 0.00115 J
0.016
9 0.318
0.38
0.866
0.18
0.22
0.391
0.0445
0.529
0.0015
3 J 0.162
ND
(0.0092) 0.0778
0.4
02
Draft Gagan Power Plant Site Investigation Report Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 5-6 November 2011
Analyte
2-Methyl-
naphthalene Acenaphthene Acenaphthylene Anthracene
Benzo (a)
anthracene
Benzo (a)
pyrene
Benzo (b)
fluoranthene
Benzo (g,h,i)
perylene
Benzo (k)
fluoranthene Chrysene
Dibenzo
(a,h)
anthracene
Fluoranthene Fluorene Indeno (1,2,3-
cd) pyrene Naphthalene Phenanthrene Pyrene
Sample ID SB
Depth
(feet
bgs)
Analytical Results
1011KWAJ009
SB22003-10 SB22 0 - 3
ND
(0.00904)
ND (0.00904
)
ND (0.00904
)
ND (0.009
04)
ND (0.0090
4)
ND (0.00904
)
ND (0.00904
)
ND
(0.019) 0.00904 U
ND (0.00904
)
ND (0.00904
)
ND (0.00904
)
ND (0.009
04)
ND (0.00904
)
ND (0.00904
)
ND (0.009
04)
ND (0.0
0904)
1011KWAJ009SB23003-10
SB23 0 - 3 ND
(0.009) ND
(0.009) 0.00112 J
0.023
6 J 0.37 J 0.358 J 0.825 J 0.184 J 0.273 J 0.406 J 0.0495 J 0.686 J
ND (0.009)
0.171 J ND
(0.009) 0.128 J
0.5
47 J
1011KWAJ009
SB23003-11 SB23 0 - 3
ND
(0.00862)
ND (0.00862
)
0.000724 UJ 0.006
82 J 0.104 J 0.11 J 0.223 J 0.0585 J 0.0707 J 0.128 J 0.0154 J 0.29 J
ND (0.008
62)
0.0531 J ND
(0.00862
)
0.0442 J 0.1
82 J
1011KWAJ009
SB24003-10 SB24 0 - 3
ND
(0.00911)
ND (0.00911
)
ND (0.00911
)
ND (0.009
11)
0.0125
0.0106
0.0178
0.00873 J 0.00911 U 0.0106
ND (0.00911
)
0.0224
ND (0.009
11)
0.00873 J ND
(0.00911
)
0.0041
8 J
0.0
167
1011KWAJ009SB25003-10
SB25 0 - 3 ND
(0.00903)
ND
(0.00903
)
ND
(0.00903
)
ND
(0.009
03)
ND
(0.0090
3)
ND
(0.00903
)
ND
(0.00903
)
ND (0.019)
0.00903 U
ND
(0.00903
)
ND
(0.00903
)
ND
(0.00903
)
ND
(0.009
03)
ND
(0.00903
)
ND
(0.00903
)
ND
(0.009
03)
ND
(0.0090
3)
1011KWAJ009
SB26003-10 SB26 0 - 3
ND
(0.00854) 0.000985
U
J
ND (0.00854
)
0.016 J 0.268 J 0.248 J 0.524 J 0.122 J 0.144 J 0.313 J 0.0338 J 0.551 J 0.0010
7 J 0.115 J
ND (0.00854
)
0.0861
0.4
25 J
1011KWAJ009
SB26003-11 SB26 0 - 3
ND
(0.00902) 0.0015 J
ND (0.00902
)
0.008
27 J 0.111 J 0.12 J 0.188 J 0.0624 J 0.0703 J 0.136 J 0.0173 J 0.265 J
0.0011
3 J 0.0575 J
ND (0.00902
)
0.0538
0.1
96 J
1011KWAJ009SB27003-10
SB27 0 - 3 ND
(0.00895)
ND
(0.00895
)
ND
(0.00895
)
ND
(0.008
95)
ND
(0.0089
5)
ND
(0.00895
)
ND
(0.00895
)
ND (0.0188)
0.00895 U
ND
(0.00895
)
ND
(0.00895
)
ND
(0.00895
)
ND
(0.008
95)
ND
(0.00895
)
ND
(0.00895
)
ND
(0.008
95)
ND
(0.0089
5)
1011KWAJ009
SB28003-10 SB28 0 - 3
ND
(0.00895)
ND (0.00895
)
ND (0.00895
)
ND (0.008
95)
ND (0.0089
5)
ND (0.00895
)
ND (0.00895
)
ND
(0.0188)
ND (0.00895
)
ND (0.00895
)
ND (0.00895
)
0.00186 J ND
(0.008
95)
ND (0.00895
)
ND (0.00895
)
ND (0.008
95)
0.0
018
6
J
Notes, Acronyms and Abbreviations:
Bolded values are positive detections
Non-detects are reported at the limit in the parenthesis
J Reported concentration is an estimated value
U Reported as a nondetect at the indicated limit due to qualification
UJ Reported as a nondetect, and the indicated limit is an estimated value
Q qualifier
SB soil boring (i.e., “SB06” = soil boring 06)
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 5-7 November 2011
5.3 NATURE AND EXTENT OF CONTAMINATION
Table 5-4 presents the frequency and range of positive detections, average of positive results, the
95% upper confidence limit on the mean of all data (UCL95), and screening criteria for the
detected contaminants at the Gagan Power Plant Fuel Spill site. Figure 3-2 shows the locations
of the soil confirmation sample collected across the site.
Table 5-4 Frequency and Range of Detected Contaminants
Compound Frequency Range of positive
detections (mg/kg)
Average of
positive
detections
(mg/kg)
UCL95
(mg/kg)
Screening
Criteria
(mg/kg)
2-Methylnaphthalene 1 / 25 0.0028 0.003 NC 4,1001
Acenaphthene 6 / 25 0.00102 - 0.00734 0.002 0.004 3,7001
Acenaphthylene 3 / 25 0.00105 - 0.00115 0.0017 0.001 132
Anthracene 6 / 25 0.00147 - 0.0236 0.013 0.007 100,0001
Benzo (a) anthracene 12 / 25 0.00319 - 0.37 0.088 0.082 2.11
Benzo (a) pyrene 11 / 25 0.00315 - 0.38 0.098 0.084 0.211
Benzo (b) fluoranthene 12 / 25 0.0046 - 0.866 0.199 0.185 2.11
Benzo (g,h,i) perylene 7 / 25 0.00851 - 0.184 0.077 0.049 272
Benzo (k) fluoranthene 11 / 25 0.00212 - 0.273 0.064 0.055 211
Chrysene 13 / 25 0.00174 - 0.406 0.094 0.094 2101
Dibenzo (a,h) anthracene 3 / 25 0.0338 - 0.0495 0.043 0.036 0.211
Fluoranthene 14 / 25 0.00186 - 0.686 0.142 0.149 22,0001
Fluorene 4 / 25 0.00107 - 0.0294 0.008 0.005 26,0001
Indeno (1,2,3-cd) pyrene 7 / 25 0.00666 - 0.171 0.070 0.042 2.11
Naphthalene 2 / 25 0.00105 - 0.0011 0.001 0.001 1901
Phenanthrene 10 / 25 0.00142 - 0.128 0.038 0.028 113
Pyrene 14 / 25 0.00174 - 0.547 0.111 0.116 562
DRO 25 / 25 0.91 - 407 38.8 68.2 5002
Notes: 1 Screening levels obtained from EPA Regional Screening Levels Table (EPA, 2009)
2 Screening levels obtained from Guam EPA ESL Guidance, with nondrinking water source and shallow contamination (GEPA, 2009)
Bold analytes are contaminants of potential concern Compounds in shaded cells retained as chemicals of potential concern for future risk assessment and data evaluation
Diesel fuel was identified as the primary site contaminant from the 2006 release and was
detected at all sampling locations as diesel-range organics (DRO), but no results exceed the
residential and industrial screening thresholds established by the Guam EPA. The highest DRO
concentration was detected at soil borings SB-01 (immediately southeast of Facility Number
7510).
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 5-8 November 2011
PAH compounds were detected in approximately half of the soil sampling locations and have
general association with the DRO detections. GRO and BTEX constituents were not detected in
any samples.
Benzo(a)pyrene results from soil borings on the southwest side of the former landfarm treatment
area (SB21, SB23, and SB26) comprise the only detections that exceed the EPA Regional
Screening Levels. A relatively high DRO detection at SB-23 (on the southwest side of the
former landfarm) at a concentration of 119 mg/kg, but does not exceed screening levels. The
lateral extent of this contamination area is completely bounded by compliant borings within 25
feet of these locations on all sides. The vertical extent of this contamination is not defined, as
each of these samples only characterize the 3’ bgs soil horizon.
The DRO result for SB-01 (407 mg/kg) is highest diesel detection at this site, and happens to be
located on the edge of the 2006 spill excavation at Facility Number 7510. The remaining sample
locations in this immediate area lie generally to the southwest of SB01 and confirm the extent of
the surface release and demonstrate no screening level exceedence.
The nature of the detected contamination is primarily diesel, with trace amounts of associated
PAH compounds. The PAHs, though not uncommon constituents in diesel fuel, are more closely
associated with tars, asphalts, and higher molecular weight petroleum products. They are also
common combustion by-products, as soot emissions from large diesel engines like those
providing electricity generation at Facility Number 7510. The association of DRO detections
with PAH compounds at the spill site and landfarm areas suggests PAHs were deposited on the
ground around Facility Number 7510 as soot from the generator engines and contained within
the excavated soils during the 2006 response action.
Results sufficiently delineate horizontal extent of impacts on all sides, with the possible
exception of the area immediately northeast at SB-01. All soil samples come from the 3’ bgs soil
horizon and cannot verify the vertical extent of contamination for the selected contaminants of
potential concern.
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 5-9 November 2011
The vertical extent of contamination requires definition in the area of the PAH contamination
(SB21, SB23, and SB26). Additional confirmation of the vertical extent of contamination is
warranted.
5.4 DATA EVALUATION
5.4.1 Applicable or Relevant and Appropriate Requirements (ARARs)
The UES provides a regulatory framework for restoration activities at this site. Section 3-6.5.8 of
the UES classifies the SI as a Phase III activity and prescribes results screening against the US
EPA Regional Screening Levels (RSLs). The Guam EPA (GEPA) Environmental Screening
Levels (ESLs) for TPH fractions are used since no RSLs are published for petroleum products.
Results exceeding the screening criteria identify contaminants of potential concern in the site
soils. Since benzo(a)pyrene results exceed the screening threshold, it is identified as a
contaminant of potential concern and retained for additional data evaluation, including risk
assessment for receptors identified in the conceptual site model.
Other detected contaminants may act as secondary contributors to overall risk, so other
contaminants with maximum detections that exceed 10% of respective screening levels are also
identified as contaminants of potential concern in the Gagan Power Plant Spill Site soils.
5.4.2 Summary of Findings
Based on soil analytical results from 25 sample locations across the Gagan Power Plant Spill
Site, the following contaminants of potential concern are identified for further data evaluation
and risk assessment:
DRO
Benzo(a)pyrene
Benzo(a)anthracene
Benzo(b)fluoranthene
Dibenzo (a,h) anthracene
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 5-10 November 2011
[THIS PAGE LEFT INTENTIONALLY BLANK]
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 6-1 November 2011
6.0 SUMMARY AND CONCLUSIONS
6.1 SUMMARY
An estimated five thousand gallons of No. 2 diesel fuel was released directly from the generator
building (Facility Number 7510) to the ground, following rupture of pressure gauge piping.
Contaminated soil was visually identified and removed. A 2007 report prepared by KRS
describes these excavation activities, which supposedly removed the bulk of diesel-impacted soil
in the proximity of the generator building. The soil was placed in berms lined with plastic
sheeting to facilitate natural degradation of the petroleum products. Post-excavation sampling
revealed residual contaminants in the soils surrounding the building.
Sivuniq performed a SI to evaluate the nature and extent of contamination in the vicinity of the
generator building and the former landfarm. The investigation, which included a soil gas survey
and soil sampling, confirmed low levels of residual POL in the proximity of the generator
building. Although it is evident from soil sampling that residual POL remains in the soil,
contaminant levels generally fall below published screening criteria. Screening and confirmation
soil sampling in the investigation area effectively delineate the extent of impact. DRO, benzo (a)
pyrene, benzo(a)anthracene, benzo(b)fluoranthene, and dibenzo (a,h) anthracene were identified
as COPCs. Localized detections of benzo (a) pyrene exceeded screening criteria in three
samples.
The conceptual site model identified current transient site workers and future residents as a
potentially affected receptor groups.
6.2 CONCLUSIONS
Site investigation activities in the vicinity of the generator building on Gagan revealed residual
POL in soils. Exceedances for benzo(a)pyrene were identified to exceed screening levels in
multiple samples; but only one depth interval was sampled in soil and the vertical extent of
contamination has not been completely defined. Other low-level detections indicate that the
removal action and subsequent landfarming activity was generally successful, and that the
horizontal extent of contamination has been reasonably defined.
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 6-2 November 2011
6.3 FUTURE WORK
Data gaps were identified during the SI, which included deficiencies in determining the extent of
contamination in soil. Since 3-6.5.8(k) of the UES indicates that an SI may be performed in
phases, supplemental data will be collected to fill these data gaps.
Future work should include additional soil sampling, and potentially groundwater sampling, on
Gagan Island. Soil samples were collected at a maximum depth of 3 feet bgs at this site; field
screening indicated that samples were clean, however laboratory analysis showed detections of
DRO and a number of PAHs associated with diesel fuel.
Approximately 10 borings will be advanced in the known area of impact; confirmation samples
shall be collected to confirm maximum depth of impact. Soil borings shall be advanced to a
depth of 8 feet bgs, or refusal.
To delineate the extent of impacts to the southeast of FN7510 (generator building) additional soil
borings shall be advanced, and soil samples collected every foot, beginning at 3 feet bgs.
Samples will be field screened, and appropriate intervals shall be selected for laboratory analysis
for DRO and PAHs.
Additionally, a total of 10 surface soil samples will be collected and analyzed for DRO and
PAHs, to support evaluation of the residential exposure scenario. If groundwater is encountered
at borings inside the SB01 and/or SB21/SB23/SB26 areas of concern, piezometers will be
installed and sampled for DRO and PAHs to assess potential groundwater impacts for the
identified contaminants of potential concern.
After this supplemental data is collected, data evaluation and a risk assessment will be performed
in accordance with Risk Assessment Guidance for Superfund (and supplemental guidance) for
the identified complete/significant exposure scenarios outlined in the CSM. Results will be
delivered as a separate document from this SI pursuant to UES 3-6.5.8(l). The Data Evaluation
Report will include the data presented in this SI in addition to the supplemental data.
Decisions regarding potential removal and remedial actions will utilize current data to perform a
partial risk assessment, along with knowledge of the source of contamination and effected
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 6-3 November 2011
receptors based on the CSM. Once supplemental data is collected and analyzed in the formal
data evaluation and risk assessment, assumptions used as part of the decision-making process
will be refined to conform to the actual exposure scenarios and hazard analysis. A separate
Removal Action Memorandum/Feasibility Study will be developed as necessary to discuss and
evaluate these potential removal and remedial strategies upon completion of the data evaluation,
pursuant to 3-6.5.8(g) and (n).
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 6-4 November 2011
[THIS PAGE LEFT INTENTIONALLY BLANK]
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 7-1 November 2011
7.0 REFERENCES
Global Associates (Global, 1980). Groundwater Resources of Kwajalein Island, Marshall
Islands; Technical Report No. 126; University of Hawaii at Manoa. January 1980.
Guam Environmental Protection Agency (GEPA, 2008). Evaluation of Environmental Hazards
at Sites with Contaminated Soil and Groundwater. Title 22, Division 2 (Water Control),
Chapter 5. October 2008.
Kwajalein Range Services (KRS, 2007). Gagan Remediation Progress. 2007.
Sivuniq, Inc. (Sivuniq, 2010). Final 2010 Work Plan, Investigation of Nine Sites at the U.S.
Army Kwajalein Atoll/Reagan Test Site (USAKA/RTS), Republic of Marshall Islands.
October 2010.
U.S. Army Environmental Center (USAEC, 2002). Federal Remediation Technologies
Roundtable Remediation Technologies Screening Matrix and Reference Guide. Version
4.0. http://www.frtr.gov/matrix2/. January 2002.
U.S. Army Environmental Hygiene Agency (USAEHA, 1991). Soil and Groundwater
Contamination Study No. 38-26-K144-91 Kwajalein Atoll. October 1990 – August 1991.
U.S. Army Kwajalein Atoll (USAKA, 2009). Environmental Standards and Procedures for
United States Army Kwajalein Atoll (USAKA) Activities in the Republic of the Marshall
Islands. Eleventh Edition, September 2009.
U.S. EPA (U.S. EPA, 1997), Health Effects Assessment Summary Tables (HEAST). U.S.
Environmental Protection Agency, Washington, D.C., 1997.
U.S. EPA Regions 3, 6, and 9 (U.S. EPA, 2010). Regional Screening Levels for Chemical
Contaminants at Superfund Sites. http://www.epa.gov/reg3hwmd/risk/human/rb-
concentration_table/index.htm. May 23, 2011.
Draft Gagan Power Plant Site Investigation Sivuniq, Inc.
Kwajalein Atoll/Reagan Test Site 7-2 November 2011
[THIS PAGE LEFT INTENTIONALLY BLANK]